Page 1: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

Level 1 - Implementation Overview

Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN

EUROCONTROL

Page 2: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 3: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 4: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 5: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan Released Issue

 

 

 

 

Document Title  LSSIP Year 2017 for Azerbaijan 

Infocentre Reference  18/02/26/07 

Date of Edition  05/09/18 

LSSIP Focal Point   Agabek Balabekov – [email protected]  

LSSIP Contact Person  Predrag Vranjkovic ‐ [email protected]  

Status  Released Issue 

Intended for  Agency Stakeholders 

Available in  http://www.eurocontrol.int/articles/lssip  

 

 

 

Reference Documents   

LSSIP Documents  http://www.eurocontrol.int/articles/lssip 

LSSIP Guidance Material  http://www.eurocontrol.int/articles/lssip 

Master Plan Level 3 – Plan Edition 2017 

http://www.eurocontrol.int/articles/european‐atm‐master‐plan‐level‐3‐implementation‐plan  

Master Plan Level 3 – Report Year 2016 

http://www.eurocontrol.int/articles/european‐atm‐master‐plan‐level‐3‐implementation‐report  

European ATM Portal  https://www.eatmportal.eu and http://www.atmmasterplan.eu/  

STATFOR Forecasts  http://www.eurocontrol.int/statfor 

Acronyms and abbreviations  http://www.eurocontrol.int/articles/glossaries 

 

 

 

 

   

Page 6: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 7: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan Released Issue

 

APPROVAL SHEET  

 

The following authorities have approved all parts of the LSSIP Year 2017 document and their signature confirms the correctness of the reported information and reflects their commitment to implement the actions laid down in the European ATM Master Plan  Level 3 Implementation Plan – Edition 2017 (also known as the ESSIP Plan). 

 

 

 

Page 8: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 9: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan Released Issue

 

CONTENTS  

 

 

 

1.  National ATM Environment ............................................................. 6   Geographical Scope .............................................................................................6 1.1.  National Stakeholders .........................................................................................8 1.2.

2.  Traffic and Capacity ....................................................................... 17   Evolution of traffic in Azerbaijan ...................................................................... 17 2.1.  ACC BAKU ......................................................................................................... 18 2.2.

3.  Master Plan Level 3 Implementation Report conclusions ............. 20 

4.  Implementation Projects ............................................................... 21   National projects .............................................................................................. 21 4.1.  Regional projects .............................................................................................. 23 4.2.

5.  Cooperation activities .................................................................... 24   FAB Co‐ordination ............................................................................................ 24 5.1.  Regional cooperation ....................................................................................... 24 5.2.

6.  Implementation Objectives Progress ............................................. 25   State View......................................................................................................... 25 6.1.  Detailed Objectives Implementation progress ................................................ 30 6.2.

 

Annexes 

 

Page 10: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 11: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 1 Released Issue

Executive Summary  

 

 

 

National ATM Context   

Azerbaijan is the farthest ECAC Member State to the east of Europe bordering with Kazakhstan, Turkmenistan and Russia to the North and East, Islamic Republic of Iran to the South and Georgia, Armenia and Turkey to the West. 

Azerbaijan is among the former USSR countries with the highest economic development characteristics in the area.  Azerbaijan’s economy is dynamically evolving and supporting a liberalised political, economic and social system. Oil and gas production, the chemical industry, agriculture and tourism have become the backbone for this swift advance.  

 

Since November 17, 2011, all countries of the former USSR bordering Azerbaijan have switched to a reduced minimum of vertical separation (RVSM), which has significantly increased the capacity of the air routes through the region and reduced the risks of errors. The transition has eliminated the need for switching between feet system of separation to metric system and back. The airways over the Azerbaijan allowed significantly reduced the way from Europe to the countries of South – East Asia, as well as from the Middle East to Europe and the USA.  

In August 2017, within the State Civil Aviation Administration, was created a State Inspection for the Safety all of the aviation activities in Azerbaijan.  The main function of State Safety Inspection is the put into practice of safety oversight.  

The following legislation documents were developed and implemented by SCAA in 2017 “AAR – ATC PEL’ and will be implemented in 2018 “AAR – aeronautical charts”; “AAR – AIS”. 

Azerbaijan  is playing a proactive  role  in  the  regional and  international  co‐operation  in ATM.    In addition  to ICAO and ECAC membership, Azerbaijan has joined CANSO. 

 

Traffic and Capacity 

Traffic in Azerbaijan increased by 4.6% during Summer 2017 (May to October), when compared to the same period during 2016. 

   

Page 12: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 2 Released Issue

8; 29%

7; 25%5; 18%

4; 14%

4; 14%

Completed

Ongoing

Planned

Late

No Plan

Not Applicable

Missing Data

Undefined

 

Implementation Objectives Overview 

The figure on the left shows the progress made so far in the implementation  of  the  pre‐SESAR  and  PCP  elements.  The percentage  is  calculated  as  an  average  of  the  relevant objectives  as  shown  in  Chapter  6.1.2  ‐  PCP  objectives  are marked as such, the rest except AOP14, ATC02.9, ATC18 and NAV12 are considered pre‐SESAR. The four aforementioned objectives are neither pre‐SESAR nor PCP and will be part of an overall future indicator covering the SESAR 1 phase. 

Note  that  two  objectives  –  AOM19.1  and  FCM05  –  are considered as both part of the pre‐SESAR and PCP so their progress contributes to the percentage of both phases.  

The objectives declared ‘Achieved’ in previous editions (up to, and including, ESSIP Edition 2011‐2015) are also taken into account for as long as they were linked to the Level 2 of the ATM Master Plan and implemented by the State. 

 

Progress distribution for applicable Implementation Objectives 

 

The  overall  progress  of  implementation  in  Azerbaijan  is  very  good. Only  4  implementation  objectives  are currently delayed in implementation. The rest are progressing on time towards the planned deadlines. 

 

Progress per SESAR Phase 

The figure below shows the progress made so far in the implementation of the pre‐SESAR and PCP elements. The percentage is calculated as an average of the relevant objectives as shown in Chapter 6.1.2 ‐ PCP objectives are marked as such, the rest except AOP14, ATC02.9, ATC18 and NAV12 are considered pre‐SESAR. The four aforementioned objectives are neither pre‐SESAR nor PCP and will be part of an overall future indicator covering the SESAR 1 phase. 

Note that two objectives – AOM19.1 and FCM05 – are considered as both part of the pre‐SESAR and PCP so their progress contributes to the percentage of both phases.  

The objectives declared ‘Achieved’ in previous editions (up to, and including, ESSIP Edition 2011‐2015) are also taken into account for as long as they were linked to the Level 2 of the ATM Master Plan and implemented by the State. 

 

Pre‐SESAR Implementation 

2010  2019

70%    

PCP Implementation 

2015  2023 

11%    

  

Page 13: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 3 Released Issue

Progress per SESAR Key Feature and Phase 

The figure below shows the progress made so far, per SESAR Key Feature, in the implementation of the pre‐SESAR and the PCP elements. The percentages are calculated as an average, per Key Feature, of the same objectives as in the previous paragraph. 

 

ICAO ASBUs Progress Implementation 

The figure below shows the progress made so far in the implementation of the ICAO ASBUs both for Block 0 and Block 1. The percentage is calculated as an average of the relevant Objectives contributing to each of the relevant ASBUs; this is explained in Chapter 6.1.3.  

 

Block 0 2010  2018

67%    

Block 1 2015  2022

13%    

 

   

n/a 5% 30%  1% 

Pre‐SESAR 

75% 

100% 

 

90% 

19% 

Pre‐SESAR 

Pre‐SESAR 

Pre‐SESAR

PCP 

PCP 

PCP

PCP

Optimised ATM Network Services 

Advanced Air Traffic Services  High Performing 

Airport Operations 

Enabling Aviation Infrastructure 

  

 

Page 14: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 4 Released Issue

 

ATM Deployment Outlook 

●  State objec ves 

Deployed in 2016‐2017: ‐ MTCD & CORA [ATC12.1] 100% progress ‐ Collaborative Flight Planning [FCM03] 100% progress  

 

 

‐ Coordination and transfer [ATC17] 92% progress ‐ RNAV 1 for TMA Operations [NAV03.1] 88% progress ‐ Voice over IP [COM11] 75% progress ‐ Ground‐Based Safety Nets [ATC02.8] 75% progress ‐ APV Procedures [NAV10] 72% progress ‐ eTOD [INF07] 48% progress ‐ OAT and GAT handling [AOM13.1] 43% progress ‐ Direct Routing [AOM21.1] 10% progress ‐ Interactive Rolling NOP [FCM05] 5% progress ‐ ASM Tools  [AOM19.1] 0% progress ‐ ETFMS [FCM01] 0% progress ‐ Low‐Level IFR Routes for Rotorcraft [NAV12] % progress  

  ‐ Enhanced STCA for TMAs [ATC02.9] 0% progress  

‐ Extended Flight Plan [FCM08] 0% progress  

 

●  Airport objec ves ‐ UBBB ‐ Baku ‐ Heydar Aliyev International Airport 

Deployed in 2016‐2017:  

 

 

‐ CCOs [ENV03] 50% progress ‐ Remote Tower  [AOP14] 0% progress  

     

 

   

By 12/2018 By 12/2019 By 12/2020 2021+

By 12/2018 By 12/2019 By 12/2020 2021+

Page 15: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 5 Released Issue

 

Introduction  

 

The  Local  Single  Sky  ImPlementation  (LSSIP) documents,  as  an  integral part of  the Master  Plan  (MP)  Level 3 (L3)  / LSSIP  mechanism,  constitute  a  short/medium  term  implementation  plan  containing  ECAC  States’ actions  to  achieve  the  Implementation  Objectives  as  set  out  by  the  MP  Level  3  and  to  improve  the performance of  their national ATM System.   This LSSIP document describes  the situation  in  the State at  the end of December 2017, together with plans for the next years. 

 

Chapter 1 provides an overview of the ATM  institutional arrangements within the State, the membership of the State in various international organisations, the organisational structure of the main ATM players ‐ civil and military  ‐  and  their  responsibilities  under  the  national  legislation.  In  addition,  an  overview  of  the Airspace Organisation and Classification, the ATC Units, the ATM systems operated by the main ANSP are also provided; 

Chapter 2 provides a comprehensive picture of the situation of Air Traffic, Capacity and ATFM Delay per each ACC in the State. It shows the evolution of Air Traffic and Delay in the last five years and the forecast for the next five years. It gives also the achieved performance in terms of delay during the summer season period and the planned projects assumed to offer the required capacity which will match the foreseen traffic increase and keep the delay at the agreed performance level; 

Chapter 3 provides  a  set of  conclusions extracted  from  the MP  L3  Implementation Report 2016 which  are relevant to the State/stakeholders concerned. The State reports how they have handled those conclusions and the actions taken during the year to address the concerns expressed by those conclusions; 

Chapter 4 provides  the main  Implementation Projects  (at national, FAB and regional  level) which contribute directly  to  the  implementation of  the MP Operational  Improvements  and/or  Enablers  and  Implementation Objectives. Level 1 document covers high level list of the projects showing the applicable links. All other details like  description,  timescale,  progress made  and  expected  contribution  to  the  ATM  Key  Performance  Areas provided by the State per each project are available in Level 2 document; 

Chapter 5 deals with other cooperation activities beyond Implementation Projects. It provides an overview of the FAB cooperation and also all other regional initiatives which are out of the FAB scope. The content of this chapter generally is developed and agreed in close cooperation between the States concerned; 

Chapter  6  contains  aggregated  information  at  State  level  covering  the  overall  level  of  implementation, implementation  per  SESAR  Key  Feature  and  implementation  of  ICAO  ASBUs.  In  addition  the  high‐level information on progress and plans of each  Implementation Objective  is presented. The  information for each Implementation Objective is presented in boxes giving a summary of the progress and plans of implementation for each Stakeholder. The conventions used are presented at the beginning of the section. 

Level 1 document is completed with a separate document called LSSIP Level 2. This document consists of a set of  tables  organised  in  line with  the  list  of  Implementation  Objectives.  Each  table  contains  all  the  actions planned by  the  four national  stakeholders  to achieve  their  respective Stakeholder  Lines of Action  (SLoAs) as established  in  the  European  ATM Master  Plan  L3  Implementation  Plan  Edition  2016.In  addition  it  covers detailed description of the Implementation Projects for the State as extracted from the LSSIP Data Base.  

The  information contained  in Chapter 6  is deemed sufficient  to satisfy State  reporting  requirements  towards ICAO in relation to ASBU (Aviation System Block Upgrades) monitoring. 

   

Page 16: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 17: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 6 Released Issue

1. National ATM Environment  

 

 

Geographical Scope 1.1.

International Membership  

Azerbaijan is a Member of the following international organisations in the field of ATM: 

 

Organisation    Since 

ECAC    2002 

EUROCONTROL    - 

European Union    ‐ 

EASA    ‐ 

ICAO    1992 

NATO    ATM/CNS Committee 

ITU    1992 

JAA     

 

Geographical description of the FIR(s)  

The geographical scope of this document addresses the single Baku FIR. The FIR boundaries approximate the 

state border of Azerbaijan Republic. The region  is strategically  located at the conjunction of Europe, Central 

Asia, and the Middle East. This area has served as a crossroads for centuries, a critical junction in the Silk Road 

connecting Europe and Asia. 

The  following map  shows  the  geographical  location of Azerbaijan Republic  (indicating  the  location of main 

Airports): 

Page 18: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 7 Released Issue

 

 

 

 

Baku FIR borders the following FIRs/UIRs: 

ECAC/EUROCONTROL States: 

‐ West: Yerevan FIR/UIR (Armenia). 

‐ North‐West: Tbilisi FIR/UIR (Georgia). 

 

Non‐ECAC States: 

‐ North: Rostov FIR/UIR (Russia); 

‐ North‐East: Aktau FIR/UIR (Kazakhstan); 

‐ East: Turkmenbashi FIR/UIR (Turkmenistan); 

‐ South: Tehran FIR/UIR (Iran). 

Page 19: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 8 Released Issue

Airspace Classification and Organisation  

All airspace  is divided  into Upper Airspace and Lower Airspace.   The boundary between  them  is FL285. The graphical presentation is below.  

The re‐organisation of the Baku FIR airspace to ensure a uniform and simplified application of ICAO Air Traffic Service classes Flight Level 285 and below within ECAC airspace has been achieved. 

 

 

 

 

 

National Stakeholders 1.2. 

The main National Stakeholders involved in ATM in Azerbaijan are the following: 

‐  Government (Cabinet of the Ministry); 

‐  State Civil Aviation Administration (SCAA); 

‐  “Azerbaijan Hava Yollari” Closed Joint Stock Company; 

‐  AZANS – Azerbaijan Air Navigation Services. 

Their  activities  are  detailed  in  the  following  subchapters  and  their  relationships  are  shown  in  the  diagram below. Also there is a figure of preliminary structure State Safety Inspection (source CAA,2017) 

 

Page 20: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 9 Released Issue

GovernmentThe cabinet

CAA Ministry of Defense

“Azerbaijan Hava Yollari”CJSC

Commander of Air ForceAnd Air Defense

Air DefenseAir Force

Aviation SafetyInspection and

Certification Office

Air NavigationServices

Airports National Airlines

 

Civil Aviation Authority  is the responsible body for all civil aviation regulatory matters and reports directly to the government. State inspectorate for civil aviation flight safety is be responsible for oversights (all functions and accountabilities finally are not defined yet). 

Issues related to military aviation matters are dealt with through the Ministry of Defence.  

Azerbaijan became a member of  the  International Civil Aviation Organisation  (ICAO),  the  Interstate Aviation Committee (IAC)  in 1992 and a member of ECAC since 2002.   All Azerbaijan Airlines flights are  in compliance with international laws and regulations. 

The CAA  is directed  in  its operation by Air Codex, by decrees and orders of  the President of Azerbaijan, by decrees and orders of the Government of Azerbaijan, by the SARPs adopted by ICAO, and by other legislative acts.   The authority and responsibilities of the CAA are assigned  in  its Order, affirmed by the Government of Azerbaijan.    Acting within  its  authority,  the  CAA  produces  legal  documents  and  oversees  other ministries, departments,  enterprises,  organisations  and  personnel  which  regulate  the  operation  of  civil  aviation  in Azerbaijan. The Director of the CAA and his deputies are assigned by decree of the President of Azerbaijan. 

Air navigation services, airports authorities, aviation security and national airline are managed by “Azerbaijan Hava Yollari” which is a Closed Joint Stock Company. 

Contained  within  “Azerbaijan  Hava  Yollari”  is  “Azeraeronavigation”  (AZANS)  which  is  responsible  for  the provision of air traffic services.  AZANS is also responsible for provision of the meteorological and Aeronautical Information Service. 

 

Civil Regulator(s)  

General Information  

Civil Aviation  in Azerbaijan  is the responsibility of the Civil Aviation Authority.   The different national entities having regulatory responsibilities in ATM are summarised in the table below. 

 

 

Page 21: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 10 Released Issue

Activity in ATM:  Organisation responsible  Legal Basis 

Rule‐making  CAA / AHY CJSC  Aviation Law 

Safety Oversight  CAA  State Safety Programme 

Enforcement actions in case of non‐compliance with safety regulatory requirements 

Formal procedures for enforcement have yet to be established 

Will be established in new edition of State Safety Programme 

Airspace  CAA  Aviation Law 

Economic  Azerbaijan Hava Yollari CJSC 

Aviation Law 

Environment  CAA  Aviation Law  

Security  CAA/ Azerbaijan Hava Yollari CJSC 

Aviation Law 

Accident investigation  CAA   Aviation Law 

 

The  creation of  a National  Supervisory Authority  as per  the  SES  Service Provision Regulation has not been implemented in Azerbaijan.  The CAA fulfils the role of the NSA. 

 

CAA 

The Civil Aviation Authority is responsible for: 

‐  Supervision of utilisation of the airspace of Azerbaijan Republic; 

‐  Certification of airports, aircraft and equipment; 

‐  Supervision of the aviation safety; 

‐  Licensing; 

‐  Investigation of incidents. 

The organisational chart of the CAA is shown in the Annex B of this document. 

Annual Report published:  N  CAA is not yet producing the Annual Report. 

 

Web: www.caa.gov.az  

 

 

 

 

 

 

 

 

 

 

 

Page 22: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 11 Released Issue

AZANS (Azerbaijan Air Navigation Services)  

Azeraeronavigation (AZANS) is the only ANS provider within Azerbaijan Republic. 

AZANS has one FIR for the whole upper airspace of Azerbaijan Republic, six TMA’s at Baku, Ganja, Nakhchivan, Lankaran,  Zagatala,  Gabala  ,  Yevlakh  aerodromes  and  a  CTR  at  Zabrat  heliport.    There  are  also  other aerodromes which are not permanently manned by AZANS staff due to lack of traffic. 

AZANS is responsible for: 

‐  provision of air traffic services; 

‐  development of air traffic management system; 

‐  maintenance of ATC technical facilities; 

‐  modernisation of ATC technical facilities; 

‐  provision of aeronautical information service; 

‐  provision of meteorological service. 

Service provided  

Governance:  Subdivision of CJSC    Ownership:  CJSC “Azerbaijan Hava Yollari” 

Services provided  Y/N  Comment 

ATC en‐route  Y  Baku ACC (East and West)  Nakhichevan  ACC (South) 

ATC approach  Y  Baku APP, Nakhichevan  APP/TWR, Ganja APP/TWR, Lankaran APP/TWR , Gabala APP/TWR  , Yevlakh APP/TWR 

ATC Aerodrome(s)  Y  Baku TWR , Nakhichevan  APP/TWR, Ganja APP/TWR, Lankaran APP/TWR, Zabrat  TWR, Zagatala TWR, Gabala TWR, Yevlakh APP/TWR 

AIS  Y  AIP, NOTAMs, AIC, PIB 

CNS  Y  All type of services for all International airports  in Azerbaijan 

MET  Y  All type of services for all International airports  in Azerbaijan 

ATCO training  Y  National Aviation Academy/AZANS/Outsourcing 

Others     

Additional information:   

Provision of services in other State(s): 

N   

Annual Report published:  N  AZANS is still not yet producing Annual Report. 

 

Remark: APP/TWR means combined unit. 

Number of air traffic controllers  171 

Supervisors  25 

ACC  38 

APP  32 

TWR  95 (including 29 ATCO of heliport) 

 

The organisational chart of AZANS is shown in the Annex B of this document. 

   

Page 23: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 12 Released Issue

ATC systems in use  

 

Main ANSP part of any technology alliance1  No   

 

FDPS 

Specify the manufacturer of the ATC system currently in use:  Air Traffic Automation Control System: Indra AIRCON 2100 

Upgrade of the ATC system is performed or planned?  2014 

Replacement of the ATC system by the new one is planned?   No plans yet 

ATC Unit  Baku ACC, Baku APP 

 

Specify the manufacturer of the ATC system currently in use:  THALES Eurocat C 

Upgrade2 of the ATC system is performed or planned?  2016 

Replacement of the ATC system by the new one is planned?   No plans yet 

ATC Unit  Nakhichevan ACC, Nakhichevan APP 

 

SDPS 

Specify the manufacturer of the ATC system currently in use:  Air Traffic Automation Control System : Indra AIRCON 2100  

Upgrade of the ATC system is performed or planned?  2014 

Replacement of the ATC system by the new one is planned?   No plans yet 

ATC Unit  Baku ACC, Baku APP 

 

Specify the manufacturer of the ATC system currently in use:  Thales MSSR/PSR and SMR  

Upgrade of the ATC system is performed or planned?  2014 

Replacement of the ATC system by the new one is planned?   No plans yet 

ATC Unit  Baku ACC, Baku APP 

 

   

                                                            1Technology alliance  is an alliance with another  service provider  for  joint procurement of  technology  from a particular supplier (e.g. COOPANS alliance) 2  Upgrade  is  defined  as  any modification  that  changes  the  operational  characteristics  of  the  system  (SES  Framework Regulation 549/2004, Article 2 (40))

Page 24: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 13 Released Issue

ATC Units  

The ATC units in the Azerbaijan’s airspace, which are of concern to this LSSIP are the following: 

 

ATC Unit  Number of sectors  Associated FIR(s)  Remarks 

En‐route  TMA 

Baku  2  1  Azerbaijan  ACC Baku (West, East) 

Ganja    1  Azerbaijan   

Nakhichevan  1  1  Azerbaijan  ACC Nakhichevan (South) 

Zagatala    1  Azerbaijan   

Lenkoran    1  Azerbaijan   

Gabala    1  Azerbaijan   

Yevlakh    1  Azerbaijan   

 

Buffer  zones with  Russia,  Kazakhstan  and  Turkmenistan were  eliminated  due  to  RVSM  transition  in  these 

countries. 

Airports 

General information  

Azerbaijan  Hava  Yollari”  CJSC  regulates  operation  of:  Heydar  Aliyev  (Baku),  Ganja,  Nakhchivan,  Zagatala, Naftalan, Gabala,  Lankaran, Yevlakh, Sheki airports and Zabrat heliport. This  is  shown  in  the picture below. Naftalan, Sheki are not operational due to lack of traffic.  Heydar Aliyev (Baku), Ganja, Nakhchivan, Lenkaran, Gabala and Zagatala airports are International. 

 

Page 25: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 14 Released Issue

Airport(s) covered by the LSSIP  

Referring to the List of Airports in the European ATM Master Plan Level 3 Implementation Plan Edition 2017 – Annex 2, it is up to the individual State to decide which additional airports will be reported through LSSIP for those Objectives. 

This edition of the LSSIP contains information regarding the main national airport, Baku Heydar Aliyev.  The EUROCONTROL Public Airport Corner also provides information for the following airport(s):   https://ext.eurocontrol.int/airport_corner_public/UBBB  

 

Military Authorities  

The Military Authorities in Azerbaijan are comprised of: 

‐  Ministry of Defence; 

‐  Commander of Air Forces and Air Defence; 

They report to the Cabinet. 

The Commander of Air  Forces  and Air Defence  is  the  responsible body  for military  aviation matters  in  the Azerbaijan Republic.   Military  authorities provide  air  traffic  services  at military  aerodromes  and designated zones for military training flights and exercises. 

There  is  a military  co‐ordination unit established  in OPS  room of Baku ACC  responsible  for operational  co‐ordination.  Although Flexible Use of Airspace (FUA) is not formally defined most of the principles of FUA are in place and the co‐ordination procedures are at very good level. 

 

 

 

Regulatory role  

Regulatory framework and rule‐making 

OAT  GAT 

OAT and provision of service for OAT governed by national legal provisions? 

Y  Provision of service for GAT by the Military governed by national legal provisions? 

Level of such legal provision: Ministry of Defence – Air Law for Air Defence 

Level of such legal provision: ‐ 

Authority signing such legal provision: Minister of Defence 

Authority signing such legal provision:  

Cabinet of the Ministry 

These provisions cover:  These provisions cover: 

Rules of the Air for OAT  Y     

Page 26: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 15 Released Issue

 

Oversight  

 

Service Provision role  

 

Military ANSP providing GAT services SES certified? 

N  If YES, since:    Duration of the Certificate: 

 

Certificate issued by:   N  If NO, is this fact reported to the EC in accordance with SES regulations? 

 

 

 

Organisation of military ATS for OAT  Y  Organisation of military ATS for GAT  N 

OAT/GAT Co‐ordination  Y  OAT/GAT Co‐ordination  Y 

ATCO Training  N  ATCO Training  N 

ATCO Licensing  N  ATCO Licensing  N 

ANSP Certification  N  ANSP Certification  N 

ANSP Supervision  N  ANSP Supervision  N 

Aircrew Training  N  ESARR applicability  N 

Aircrew Licensing  N     

Additional Information:  Additional Information: 

Means used to inform airspace users (other than military) about these provisions: 

Means used to inform airspace users (other than military) about these provisions: 

National AIP  N  National AIP  Y 

National Military AIP  N  National Military AIP  N 

EUROCONTROL eAIP  N  EUROCONTROL eAIP  N 

Other:  National VFR Manual  ‐  Other: National Regulatory Documents  Y 

OAT  GAT 

National oversight body for OAT: Ministry of Defence 

No military oversight role 

Additional information:   

OAT  GAT 

Services Provided: MIL  Services Provided: None 

En‐Route  N    En‐Route  N 

Approach/TMA  N    Approach/TMA  N 

Airfield/TWR/GND  Y    Airfield/TWR/GND  Y 

AIS  N    AIS  N 

MET  N    MET  N 

SAR  N    SAR  N 

TSA/TRA monitoring  N    FIS  N 

Other:     Other:    

Additional Information:  Additional Information: 

Page 27: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 16 Released Issue

 

User role  

 

 

 

Flexible Use of Airspace (FUA)  

 

 

   

IFR inside controlled airspace, Military aircraft can fly?  

OAT only    GAT only  X  Both OAT and GAT   

If Military fly OAT‐IFR inside controlled airspace, specify the available options: 

Free Routing  Y  Within specific corridors only  X 

Within the regular (GAT) national route network  Y  Under radar control  Y 

Within a special OAT route system  Y  Under radar advisory service  N 

If Military fly GAT‐IFR inside controlled airspace, specify existing special arrangements:   

No special arrangements  N  Exemption from Route Charges  X 

Exemption from flow and capacity (ATFCM) measures  N  Provision of ATC in UHF  N 

CNS exemptions:  RVSM  N  8.33  N  Mode S  N  ACAS  N 

Others:  * If there is request from the military, and radar control is not possible, ATC close the route until the military aircraft has passed through it. 

Military in AZ applies FUA requirements as specified in the Regulation No 2150/2005:     N 

FUA Level 1 implemented: : N 

FUA Level 2 implemented:  N 

FUA Level 3 implemented:  N 

Page 28: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 17 Released Issue

2. Traffic and Capacity  

Evolution of traffic in Azerbaijan 2.1.

 

 

 

 

 

2017 Traffic  in Azerbaijan increased by 4.6% during Summer 2017 (May to October), when compared to the same period during 2016. 

2018‐2022 

The EUROCONTROL Seven‐Year forecast predicts an average annual traffic growth between 2.8% and 6.4%, with an average baseline growth of 4.5% throughout the planning cycle.     

 

   

0

50,000

100,000

150,000

200,000

250,000

2013 A 2014 A 2015 A 2016 A 2017 F 2018 F 2019 F 2020 F 2021 F 2022 F 2023 F

IFR

flig

hts

Azerbaijan - Annual IFR Movements

IFR movements - Actuals

IFR movements - Baseline forecast

IFR movements - High forecast

IFR movements - Low forecast A = ActualF = Forecast

2014 A 2015 A 2016 A 2017 F 2018 F 2019 F 2020 F 2021 F 2022 F 2023 F

H 5.5% 8.3% 6.0% 6.4% 5.5% 5.8% 5.7%

B -1.2% 1.4% 5.1% 4.9% 6.5% 4.0% 4.2% 3.8% 4.0% 4.1%

L 4.4% 4.7% 2.0% 2.8% 2.2% 2.5% 2.5%

ECAC B 1.7% 1.6% 2.8% 4.5% 2.8% 2.1% 1.9% 1.5% 1.7% 1.7%

EUROCONTROL Seven-Year Forecast (September 2017)IFR flights yearly growth

Azerbaijan

Page 29: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 18 Released Issue

ACC BAKU 2.2.

 

Summer 2017 performance 

Traffic Evolution 2017 Capacity Baseline En-route Delay (min/flight) - Summer Capacity

gap Ref value Actual

+4.6% 65 (0%) 0.01 0.0 No

The average en-route delay per flight remained at zero in Summer 2017.

Capacity Plan: Sufficient Capacity to meet demand Achieved Comments

ATS route network optimisation - an on-going process in co-operation with neighboring States

Yes

Maximum configuration: 5 + 3APP Yes

Summer 2017 performance assessment

The ACC capacity baseline was estimated at 65. During the measured period, the average peak 1 hour demand was 33 and the average peak 3 hour demand was 24.

Planning Period 2017‐2021 ‐ Summer 

The planning focuses on the Summer season to reflect the most demanding period of the year from a capacity perspective. This approach ensures consistency with the previous planning cycles. 

Summer Capacity Plan

2017 2018 2019 2020 2021

Free Route Airspace

Airspace Management Advanced FUA

Airport & TMA Network Integration

Cooperative Traffic Management

Airspace ATS route network optimisation - an on-going process in co-operation with neighboring States Procedures

Staffing

Technical

Capacity

Significant Events

Max sectors 5 + 3APP 5 + 3APP 5 + 3APP 5 + 3APP 5 + 3APP

Planned Annual Capacity Increase Sufficient capacity to meet expected demand

Reference profile Annual % Increase 0% 0% 0% N/A N/A

Difference Capacity Plan v. Reference Profile

Sufficient capacity to meet expected demand

Annual Reference Value (min) 0.01 0.01 0.01 N/A N/A

Summer reference value (min) 0.01 0.01 0.01 N/A N/A

Additional information

H 65 0% 65 0% 65 0%

Ref. 65 0% 65 0% 65 0%

L 65 0% 65 0% 65 0%

Open 65 0% 65 0% 65 0%

C/R 65 0% 65 0% 65 0%

2018 2019

UBBA 65

ACC2016

baseline 2017

Capacity ProfilesProfiles (hourly movements and % increase over previous year)

Page 30: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 19 Released Issue

 

Up to 5 ACC and 3 APP sectors could be open. However, with the current  levels of traffic, 3 ACC + 3 APP are sufficient.  

 

 

   

0

1

2

3

4

5

6

7

8

00:00

02:00

04:00

06:00

08:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

Sectors available ‐ Summer 2018 ‐WD

0

1

2

3

4

5

6

7

8

00:00

02:00

04:00

06:00

08:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

Sectors available ‐ Summer 2018 ‐WE

2015 2016 2017 2018 2019 2020 2021

2017‐2019 Reference Capacity Profile 65 65 65

Capacity Profile ‐ Shortest Routes (Open) 65 65 65

Capacity Profile ‐ Current Routes 65 65 65

Capacity Profile ‐ High 65 65 65

Capacity Profile ‐ Low 65 65 65

Capacity Baseline 65 65

2017 ‐ 2021 Plan 65 65 65 65 65

0

10

20

30

40

50

60

70

Cap

acity profile (movements per hour)

UBBACTA - Reference capacity profile and alternative scenarios

2018‐2022 Planning Period Outlook 

No problems are foreseen for Azerbaijan during the current planning cycle.  

Page 31: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 20 Released Issue

3. Master Plan Level 3 Implementation Report conclusions 

 

 

 

 

Conclusions  issued  from  the European ATM Master Plan  Level 3  Implementation Report 2016 applicable  to Azerbaijan for all items that require corrective actions and improvements.  

 

Conclusion  Applicable to VERY GOOD PROGRESS IN IMPLEMENTATION OF BOTH FREE ROUTE AND DIRECT 

ROUTING. 

THIS MOMENTUM SHOULD BE KEPT AND SUPPORTED BY ALL INVOLVED STAKEHOLDERS. 

(page 14 of the Report) 

All State that are 

implementing 

AOM21.1 and 

AOM21.2 State’s action planned for this conclusion: YES  

Description of the planned action: Azerbaijan is implementing direct routing on its territory. Implementation 

of the FRA concept is not being implemented at this stage due to complexity of the airspace and issue of 

restricted flight zone at its territory.  

 

Conclusion  Applicable to ADQ IMPLEMENTATION ISSUES HAVE TO BE ADDRESSED AS SOON AS POSSIBLE AS THEY 

CAN IMPACT ON SWIM IMPLEMENTATION. (page 25 of the Report)  All States + EC 

State’s action planned for this conclusion: YES  

Description of the planned action: ADQ regulation is not applicable in AZ. However, AZ is following all trends in this area and much functionality related to ADQ is already available. Moreover, roadmap in AIM area is 

established to implement these functionalities.  

 

Page 32: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 21 Released Issue

4. Implementation Projects  

National projects 4.1. 

Name of project:  Organisation(s):  Schedule:  Status:  ATM MP Links: 

Implement full back‐up ATC system at Baku ACC (BCUP‐ACC) 

AZANS (AZ)  2018  Ongoing  ‐ 

Implementation of Airspace Efficiency, Strategy and Development Center (ASEC) (FLOW) 

AZANS (AZ)  2018  Ongoing  L3: FCM05, FCM06, FCM08 

Implementation of VSAT Communication System (VSAT) 

AZANS (AZ)  2018  Ongoing  L2: CNS‐0001‐A 

Implementation of complete AIS to AIM system (AIS‐AIM) 

AZANS (AZ)  2018  Ongoing  L3: INF07, ITY‐ADQ 

Implementation of the Virtual Tower with remote control on Chilov Island (RTWR_Chilov) 

AZANS (AZ)  February 2018 ‐ December 2018  

Planned  L3: AOP14 

Installation of METEO radars (METEO AZ) 

AZANS (AZ), Ganja Airport (AZ), Nakhchivan Airport (AZ) 

2018  Ongoing  L3: ITY‐ADQ 

Installlation of new satelite connection system with adjecent ATS centres (SAT_AZ) 

AZANS (AZ)  2018  Ongoing  ‐ 

MSSR Radar instalation at Yevlakh Airport (MSSR‐UBEE) 

Yevlakh Airport (AZ)  2018  Ongoing  L3: ITY‐ACID, ITY‐SPI 

Modernisation of ILS at Baku Airport (ILS‐Baku) 

AZANS (AZ), BAKU ‐ Heydar Aliyev International Airport (AZ) 

2019  Planned  L2: CNS‐0001‐A 

Page 33: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 22 Released Issue

Name of project:  Organisation(s):  Schedule:  Status:  ATM MP Links: 

Runway extension and ATC system renewal at Zaqatala International Airport (RWY‐UBBY) 

AZANS (AZ)  2018  Ongoing  ‐ 

The second phase of installation of ADS‐B and WAM system (Phase II ADS‐B) 

AZANS (AZ)  2018  Ongoing  L3: ITY‐ACID, ITY‐SPI 

Upgrade of the Nakhchivan Airport runway and navigation AIDS (ATM‐UBBN) 

Nakhchivan Airport (AZ) 

2018  Ongoing  ‐ 

Implementation of the ATC Contingency System  in Baku ASEC building  

AZANS (AZ)  2018  Ongoing   

Implementation of MoC AZANS‐IATA  

AZANS (AZ)  2018  Ongoing   

 

 

   

Page 34: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 23 Released Issue

 

Regional projects 4.2. 

OLDI system implementation. (OLDI) 

Organisation(s):  AZANS (AZ)  Type of project: Regional 

Schedule:  2018 

Status:  Ongoing 

Description:  Implementation of OLDI system at Baku ACC center. 

Link and references 

ATM MP links:   L3: ATC17 

Other links:   ‐ 

Project included in RP2 Performance Plan: 

‐  Name/Code in RP2 Performance Plan: 

‐ 

Project included in DP2016: 

‐  Name/Code in DP2016:  ‐ 

Performance contribution 

Safety:  +++  Enhancing safety of operations through more efficient COMs. 

Environment:    ‐ 

Capacity:  +++  Creating new capacity in Baku ACC. 

Cost‐efficiency:    ‐ 

Operational efficiency:  +++  Better  operational  efficiency  through  more  efficient  transfer  of 

responsibility. 

Cooperation Activities:  Testing activities with Rostov ongoing. Tbilisi is scheduled after. 

 

 

 

 

   

Page 35: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 24 Released Issue

5. Cooperation activities  

 

FAB Co‐ordination 5.1. 

Not applicable. 

 

Regional cooperation 5.2.

Regional cooperation initiatives  

There are no Regional Cooperation Initiatives to which Azerbaijan has joined. 

 

 

 

Page 36: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 25 Released Issue

6. Implementation Objectives Progress  

 

State View 6.1. 

Objective Progress per SESAR Key Feature  

Note: The detailed table of links between Implementation Objectives and SESAR Key Features is available in Annex C. 

 

Legend: 

 ## %  = Expected completion / % Progress    = Implementation Objective timeline (different colour per KF)  

 100% = Objective completed    = Completion beyond Implementation Objective timeline  

 

 Optimised ATM Network Services 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOM13.1 Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling  

      43% 

 

AOM19.1 (PCP)  ASM Support Tools to Support AFUA      0% 

 

AOM19.2 (PCP)  ASM Management of Real‐Time Airspace Data      0% 

‐  

AOM19.3 (PCP) Full rolling ASM/ATFCM Process and ASM Information Sharing 

     0% 

‐  

FCM01  Enhanced Tactical Flow Management Services       0% 

 

FCM03  Collaborative Flight Planning      100% 

 

FCM04.1  STAM Phase 1       

 n/a  

FCM04.2 (PCP)  STAM Phase 2       

n/a  

FCM05 (PCP)  Interactive Rolling NOP      5% 

 

FCM06 (PCP)  Traffic Complexity Assessment      0% 

 

 

   

Page 37: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 26 Released Issue

 

Advanced Air Traffic Services 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOM21.1 (PCP)  Direct Routing       10% 

 

AOM21.2 (PCP)  Free Route Airspace       

n/a  

AOP14  Remote Tower Services  Local objective    

 

  UBBB ‐ Baku ‐ Heydar Aliyev International Airport  0% 

ATC02.2  STCA En‐Route      100% 

 

ATC02.8  Ground‐Based Safety Nets       75% 

 

ATC02.9  Enhanced STCA for TMAs      0% 

 

ATC07.1  AMAN Tools and Procedures        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

ATC12.1 Automated Support for Conflict Detection, Resolution Support Information and Conformance Monitoring 

     100% 

 

ATC15.1 Information Exchange with En‐route in Support of AMAN 

      

n/a  

ATC15.2 (PCP) Arrival Management Extended to En‐route Airspace 

       

n/a  

ATC16  ACAS II Compliant with TCAS II Change 7.1      100% 

 

ATC17 Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer 

     92% 

 

ATC18  Multi Sector Planning En‐route ‐ 1P2T  Local objective    0% 

‐  

ENV01  Continuous Descent Operations        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

100% 

ENV03  Continuous Climb Operations   Local objective     

  UBBB ‐ Baku ‐ Heydar Aliyev International Airport  50% 

ITY‐COTR Ground‐Ground Automated Co‐ordination Processes 

     68% 

 

NAV03.1  RNAV 1 in TMA Operations       88% 

 

NAV03.2 (PCP)  RNP 1 in TMA Operations       0% 

‐  

NAV10  APV procedures       72% 

 

NAV12 Optimised Low‐Level IFR Routes in TMA for Rotorcraft 

 Local objective    0% 

 

 

   

Page 38: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 27 Released Issue

 

 

  High Performing Airport Operations 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOP04.1  A‐SMGCS Level 1        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

100% 

AOP04.2  A‐SMGCS Level 2         

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

100% 

AOP05  Airport CDM        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

AOP10 (PCP)  Time‐Based Separation         

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

AOP11 (PCP)  Initial Airport Operations Plan        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

AOP12 (PCP) Improve Runway and Airfield Safety with ATC Clearances Monitoring 

       

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

AOP13 (PCP) Automated Assistance to Controller for Surface Movement Planning and Routing 

       

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

ENV02  Collaborative Environmental Management        

 UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

n/a    

SAF11 Improve Runway Safety by Preventing Runway Excursions 

     100% 

   

 

   

Page 39: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 28 Released Issue

 

 Enabling Aviation Infrastructure  

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

COM10  Migrate from AFTN to AMHS      100% 

   

COM11  Voice over Internet Protocol (VoIP)      75% 

   

COM12 (PCP)  NewPENS        

 n/a  

FCM08 (PCP)  Extended Flight Plan      0% 

   

INF04  Integrated Briefing      100% 

  

INF07  Electronic Terrain and Obstacle Data (eTOD)       48% 

   

ITY‐ACID  Aircraft Identification      100% 

   

ITY‐ADQ Ensure Quality of Aeronautical Data and Aeronautical Information 

      83% 

   

ITY‐AGDL  Initial ATC Air‐Ground Data Link Services      10% 

   

ITY‐AGVCS2 8,33 kHz Air‐Ground Voice Channel Spacing below FL195 

     

 n/a  

ITY‐FMTP  Common Flight Message Transfer Protocol       100% 

   

ITY‐SPI  Surveillance Performance and Interoperability      100% 

   

   

Page 40: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 29 Released Issue

ICAO ASBU Implementation  

The following table shows, for each of the ASBU Block 0 modules, the overall status, the final date foreseen for completion and the percentage of progress achieved in the current cycle.    

These  results were  determined  using  the  LSSIP  Year  2017  declared  statuses  and  progress  of  the  relevant Implementation objectives  in accordance with the mapping approved by  ICAO EUR EANPG/59 (European Air Navigation Planning Group).     

 

Legend: 

   = Completed (during 2017 or before)  

  = Missing planning date  

 = Progress achieved in 2017    = Not applicable  

 

    <16     16  17  18  19  20  21  22  23  24   ≥25  

B0‐APTA  Optimization of Approach Procedures including vertical guidance 

       100% 

  80%  

B0‐SURF  Safety and Efficiency of Surface Operations (A‐SMGCS Level 1‐2) 

       100% 

  

B0‐FICE  Increased Interoperability, Efficiency and Capacity through Ground‐Ground Integration 

       100% 

  87%  

B0‐DATM  Service Improvement through Digital Aeronautical Information Management 

       100% 

  92%  

B0‐ACAS  ACAS Improvements        100% 

 

B0‐SNET  Increased Effectiveness of Ground‐Based Safety Nets 

       100% 

  38%  

B0‐ACDM  Improved Airport Operations through    

  

B0‐RSEQ  Improved Traffic flow through Runway sequencing (AMAN/DMAN)  

   

  

B0‐FRTO  Improved Operations through Enhanced En‐Route Trajectories 

       100% 

  37%  

B0‐NOPS  Improved Flow Performance through Planning based on a Network‐Wide view 

       100% 

  50%  

B0‐ASUR  Initial capability for ground surveillance         100% 

  

B0‐CDO  Improved Flexibility and Efficiency in Descent Profiles (CDO) 

       100% 

  

B0‐TBO  Improved Safety and Efficiency through the initial application of Data Link En‐Route 

       100% 

  10%  

 

 

   

Page 41: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 30 Released Issue

Detailed Objectives Implementation progress 6.2. 

Note: The detailed table of applicability area for the Implementation Objectives is available in Annex C. 

 

Objective/Stakeholder Progress Code: 

Completed    No Plan   

Ongoing    Not Applicable   

Planned    Missing Data   

Late       

 

Main Objectives   

AOM13.1 

Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) Handling Timescales: Initial operational capability: 01/01/2012 Full operational capability: 31/12/2018 

43%  Ongoing 

 ‐  

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules were developed in accordance with ICAO and EUROCONTROL requirements. New plans are being considered for further cooperation between CIV and MIL. 

31/12/2018 

REG (By:12/2018) 

State Civil Aviation Administration 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry.  Rules developed in accordance with ICAO and EUROCONTROL requirements.New plans are being considered for further cooperation between CIV and MIL. 

‐  40% 

Ongoing 

31/12/2018 

ASP (By:12/2018) 

AZANS 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules developed in accordance with ICAO and EUROCONTROL requirements. New plans are being considered for further cooperation between CIV and MIL. 

‐  63% 

Ongoing 

31/12/2018 

MIL (By:12/2018) 

Mil. Authority 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules developed in accordance with ICAO and EUROCONTROL requirements. New plans are being considered for further cooperation between CIV and MIL. 

‐  32% 

Ongoing 

31/12/2018 

   

AOM19.1 

ASM Support Tools to Support Advanced FUA (AFUA) Timescales: Initial operational capability: 01/01/2011 Full operational capability: 31/12/2018 

0%  Planned 

 ‐  

Azerbaijan is currently building a new center that will include these functions.   01/07/2018 

ASP (By:12/2018) 

AZANS Azerbaijan is currently building a new center that will include these functions.  

‐  0% Planned 

01/07/2018 

Page 42: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 31 Released Issue

   

AOM19.2 

ASM Management of Real‐Time Airspace Data Timescales: Initial operational capability: 01/01/2017 Full operational capability: 31/12/2021 

0%  No Plan 

 ‐  

Azerbaijan is currently not in a position to establish ASM management of real‐time airspace data at the European Network level. The objective will be reviewed in the future when circumstances change.  

‐ 

ASP (By:12/2021) 

AZANS 

Azerbaijan is currently not in a position to establish ASM management of real‐time airspace data at the European Network level. The objective will be reviewed in the future when circumstances change.  

‐  0% 

No Plan 

‐ 

   

AOM19.3 

Full Rolling ASM/ATFCM Process and ASM Information Sharing Timescales: Initial operational capability: 01/01/2014 Full operational capability: 31/12/2021 

0%  No Plan 

 ‐  

Azerbaijan is currently not in a position to establish rolling ASM/ATFCM process at the European Network level. The objective will be reviewed in the future when circumstances change.  

‐ 

ASP (By:12/2021) 

AZANS 

Azerbaijan is currently not in a position to establish rolling ASM/ATFCM process at the European Network level. The objective will be reviewed in the future when circumstances change.  

‐  0% 

No Plan 

‐ 

   

AOM21.1 

Direct Routing Timescales: Initial Operational Capability: 01/01/2015 Full Operational Capability: 31/12/2017 

10%  Late 

 ‐  

Azerbaijan is in the process of implementation of this objective. One direct route is already defined for testing. This is not reflected in ERNIP, it is AZANS project solely. In future, AZANS is looking for more cooperation with EUROCONTROL in this area. New Center of Airspace Efficiency, Strategy and Development  should help in the promotion in this area. 

31/12/2018 

ASP (By:12/2017) 

AZANS Azerbaijan is in the process of implementation of this objective. One direct route is already defined for testing. 

‐  10% Late 

31/12/2018 

     

Page 43: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 32 Released Issue

 

AOM21.2 

Free Route Airspace    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

At this stage, Azerbaijan is unable to implement this objective due to complexity of the airspace and issue of restricted flight zone at its territory.  

‐ 

ASP (By:12/2021) 

AZANS At this stage, Azerbaijan is unable to implement this objective due to complexity of the airspace and issue of restricted flight zone at its territory.  

‐  % Not Applicable 

‐ 

   

AOP04.1 

Advanced Surface Movement Guidance and Control System A‐SMGCS Surveillance (former Level 1) Timescales: ‐ not applicable ‐ 

100%  Completed 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan has completed the implementation of this objective and A‐SMGCS Level 1 is operational at Baku Airport. 

31/12/2014 

REG (By:12/2010) 

State Civil Aviation Administration 

Azerbaijan has completed the implementation of this objective and A‐SMGCS Level 1 is operational at Baku Airport. 

‐  100% 

Completed 

31/12/2014 

ASP (By:12/2011) 

AZANS Azerbaijan has completed the implementation of this objective and A‐SMGCS Level 1 is operational at Baku Airport. 

‐  100% Completed 

31/12/2014 

APO (By:12/2010) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan has completed the implementation of this objective and A‐SMGCS Level 1 is operational at Baku Airport. 

A‐SMGCS Level I and II 

100% 

Completed 

31/12/2014 

   

AOP04.2 

Advanced Surface Movement Guidance and Control System (A‐SMGCS) Runway Monitoring and Conflict Alerting (RMCA) (former Level 2) Timescales: ‐ not applicable ‐ 

100%  Completed 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

A‐SMGCS Level 2 is implemented and operational at Baku Airport. Control function equipment installed. HITT system used. 

31/12/2015 

ASP (By:12/2017) 

AZANS Azerbaijan has completed the implementation of this objective. 

‐  100% Completed 

31/12/2015 

APO (By:12/2017) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan has completed the implementation of this objective. 

A‐SMGCS Level I and II 

100% 

Completed 

31/12/2015 

Page 44: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 33 Released Issue

   

AOP05 Airport Collaborative Decision Making (A‐CDM) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not within the area of applicability of this airport related objective.   ‐ 

ASP (By:12/2016) 

AZANS Azerbaijan is not within the area of applicability of this multi‐national objective.  

‐  % Not Applicable 

‐ 

APO (By:12/2016) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

‐  % 

Not Applicable 

‐ 

   

AOP10 Time‐Based Separation Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not within the area of applicability of this objective.    ‐ 

REG (By:12/2023) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

ASP (By:12/2023) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

   

AOP11 Initial Airport Operations Plan Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not in the applicability area of the PCP regulation.  ‐ 

ASP (By:12/2021) 

AZANS Azerbaijan is not in the applicability area of the PCP regulation. 

‐  % Not Applicable 

‐ 

APO (By:12/2021) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan is not in the applicability area of the PCP regulation. 

‐  % 

Not Applicable 

‐ 

     

Page 45: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 34 Released Issue

 

AOP12 

Improve Runway and Airfield Safety with Conflicting ATC Clearances (CATC) Detection and Conformance Monitoring Alerts for Controllers (CMAC) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not in the applicability area of the PCP regulation.  ‐ 

ASP (By:12/2020) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

APO (By:12/2020) 

BAKU ‐ Heydar Aliyev International Airport 

‐  ‐  % 

Not Applicable 

‐ 

   

AOP13 

Automated Assistance to Controller for Surface Movement Planning and Routing Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Baku Airport is not in applicability area of this objective.  ‐ 

REG (By:12/2023) 

State Civil Aviation Administration 

‐  ‐  % 

Not Applicable 

‐ 

ASP (By:12/2023) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

   

ATC02.8 

Ground‐Based Safety Nets Timescales: Initial operational capability: 01/01/2009 Full operational capability: 31/12/2016 

75%  Late 

 ‐  

MSAW and APW functions are fully implemented in AZANS. APM implementation is currently ongoing. 

31/12/2018 

ASP (By:12/2016) 

AZANS MSAW and APW functions are fully implemented in AZANS. APM implementation is currently ongoing. 

‐  75% Late 

31/12/2018 

     

Page 46: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 35 Released Issue

 

ATC02.9 

Enhanced Short Term Conflict Alert (STCA) for TMAs Timescales: Initial operational capability: 01/01/2018 Full operational capability: 31/12/2020 

0%  Planned 

 ‐  

‐  31/12/2020 

ASP (By:12/2020) 

AZANS  ‐  ‐  0% Planned 

31/12/2020 

   

ATC07.1 AMAN Tools and Procedures Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  Moreover, there is no OPS need. However implementation of AMAN system is discussed in the frame of existing modernization programme. 

‐ 

ASP (By:12/2019) 

AZANS  No OPS needs, the investment can not be justified Installation of new ATC system 

% Not Applicable 

‐ 

   

ATC12.1 

Automated Support for Conflict Detection, Resolution Support Information and Conformance Monitoring Timescales: Initial operational capability: 01/01/2015 Full operational capability: 31/12/2021 

100%  Completed 

 ‐  

MTCD support function exists in the system. CORA function implemented. Procedures are defined. Functionality is operational. 

31/12/2017 

ASP (By:12/2021) 

AZANS MTCD support function exists in the system. Procedures are defined. Functionality is operational. 

‐  100% Completed 

31/12/2017 

   

ATC15.1 

Information Exchange with En‐route in Support of AMAN    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

There is no operational need for this tool in Azerbaijan.  ‐ 

ASP (By:12/2017) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

     

Page 47: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 36 Released Issue

  

ATC15.2 

Arrival Management Extended to En‐route Airspace    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

Not applicable for AZ.  ‐ 

ASP (By:12/2023) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

   

ATC17 

Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer Timescales: Initial operational capability: 01/01/2013 Full operational capability: 31/12/2018 

92%  Ongoing 

 ‐  

New ATM system is capable to exchange some OLDI messages. AZANS is in negotiations with adjacent countries. Testing is ongoing with Rostov FIR. 

31/12/2018 

ASP (By:12/2018) 

AZANS New ATM system is capable to exchange basic OLDI messages. AZANS is in negotiations with adjacent countries. Testing is ongoing with Rostov FIR. 

OLDI system implementati

on. 

92% Ongoing 

31/12/2018 

   

COM10 

Migrate from AFTN  to AMHS  Timescales: Initial operational capability: 01/12/2011 Full operational capability: 31/12/2018 

100%  Completed 

 ‐  

Azerbaijan completed the transition to AMHS.  System capabilities implemented into the new ACC. However, due to inability of adjacent Rostov FIR system is still working as AFTN. 

31/12/2014 

ASP (By:12/2018) 

AZANS 

Azerbaijan completed the transition to AMHS.  System capabilities implemented into the new ACC. However, due to inability of adjacent Rostov FIR system is still working as AFTN. 

Installation of new ATC system 

100% 

Completed 

31/12/2014 

   

COM11 

Voice over Internet Protocol (VoIP) Timescales: Initial operational capability: 01/01/2013 Full operational capability: 31/12/2020 

75%  Ongoing 

 ‐  

AZANS has partly implemented this objective. In some areas the concept is already operational.  31/12/2018 

ASP (By:12/2020) 

AZANS AZANS has partly implemented this objective. In some areas the concept is already operational. 

Installation of new ATC system 

75% Ongoing 

31/12/2018 

   

Page 48: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 37 Released Issue

COM12 

New Pan‐European Network Service (NewPENS)    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

‐  ‐ 

ASP (By:12/2024) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

APO (By:12/2024) 

   

ENV01 Continuous Descent Operations (CDO) Timescales: ‐ not applicable ‐ 

100%  Completed 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Procedures developed to decrease C02 emissions at Baku Airport and published. Objective is completed. 

31/03/2015 

ASP (By:12/2013) 

AZANS Procedures developed to decrease C02 emissions at Baku Airport and published. Objective is completed. 

‐  100% Completed 

31/03/2015 

APO (By:12/2013) 

BAKU ‐ Heydar Aliyev International Airport 

Procedures developed to decrease C02 emissions at Baku Airport and published. Objective is completed. 

‐  100% 

Completed 

31/03/2015 

   

ENV02 Airport Collaborative Environmental Management Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport  (Outside Applicability Area) 

Azerbaijan is not within the area of applicability of this airport related objective.   ‐ 

ASP (By:12/2016) 

AZANS Azerbaijan is not within the area of applicability of this multi‐national objective.  

‐  % Not Applicable 

‐ 

APO (By:12/2016) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

‐  % 

Not Applicable 

‐ 

     

Page 49: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 38 Released Issue

 

FCM03 

Collaborative Flight Planning Timescales: Initial operational capability: 01/01/2000 Full operational capability: 31/12/2017 

100%  Completed 

 ‐  

Since early January 2016, associations with IFPS is completed and operational. AIC distributed . All messages exchanged through the system to the extent necessary for AZ being a non EUROCONTROL State. 

31/12/2017 

ASP (By:12/2017) 

AZANS Since early January 2016, associations with IFPS is completed and operational. AIC distributed . All messages exchanged through the system. 

Implementation of IFPLS 

100% Completed 

31/12/2017 

   

FCM04.1 

Short Term ATFCM Measures (STAM) ‐ Phase 1    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

Azerbaijan is not in the applicability area of this objective.  ‐ 

ASP (By:10/2017) 

AZANS  Azerbaijan is not in the applicability area of this objective.  ‐  % Not Applicable 

‐ 

   

FCM04.2 

Short Term ATFCM Measures (STAM) ‐ Phase 2    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

Not applicable for AZ. Not in the applicability area.  ‐ 

ASP (By:12/2021) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

     

Page 50: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 39 Released Issue

  

FCM05 

Interactive Rolling NOP Timescales: Initial operational capability: 01/09/2013 Full operational capability: 31/12/2021 

5%  Ongoing 

 ‐  

Objective is planned to be implemented in future with new ATFCM center in Baku. Activity is started already with provision of airport slot info to DDR. 

31/12/2018 

ASP (By:12/2021) 

AZANS Objective is planned to be implemented in future with new ATFCM center in Baku. 

Implementation of 

Airspace Efficiency, Strategy and Development Center (ASEC) 

0% 

Planned 

31/12/2018 

APO (By:12/2021) 

BAKU ‐ Heydar Aliyev International Airport 

Objective implementation started. To be implemented in relations to new ATFCM center in Baku. 

‐  10% 

Ongoing 

31/12/2018 

   

FCM06 

Traffic Complexity Assessment    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

0%  Planned 

 ‐  

The objective is being considered for implementation in new flow and capacity management center in Baku.  

31/12/2021 

ASP (By:12/2021) 

AZANS The objective is being considered for implementation in new flow and capacity management center in Baku.  

Implementation of 

Airspace Efficiency, Strategy and Development Center (ASEC) 

0% 

Planned 

31/12/2021 

   

FCM08 

Extended Flight Plan Timescales: Initial operational capability: 01/01/2016 Full operational capability: 31/12/2021 

0%  Planned 

 ‐  

The objective will be implemented in new flow and capacity management center in Baku.  31/12/2021 

ASP (By:12/2021) 

AZANS The objective will be implemented in new flow and capacity management center in Baku. 

Implementation of 

Airspace Efficiency, Strategy and Development Center (ASEC) 

0% 

Planned 

31/12/2021 

Page 51: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 40 Released Issue

   

INF07 

Electronic Terrain and Obstacle Data (eTOD) Timescales: Initial operational capability: 01/11/2014 Full operational capability: 31/05/2018 

48%  Late 

 ‐  

Implementation of e‐TOD was approved by State Civil Aviation Administration. Implementation is considered as part of implementation of ADQ requirements. 

31/12/2018 

REG (By:05/2018) 

State Civil Aviation Administration 

Implementation of e‐TOD was approved by State Civil Aviation Administration. Implementation is considered as part of implementation of ADQ requirements. 

‐  55% 

Late 

31/12/2018 

ASP (By:05/2018) 

AZANS Implementation of e‐TOD was approved by State Civil Aviation Administration. Implementation is considered as part of implementation of ADQ requirements. 

Implementation of 

complete AIS to AIM system 

40% 

Late 

31/12/2018 

APO (By:05/2018) 

BAKU ‐ Heydar Aliyev International Airport 

Implementation of e‐TOD was approved by State Civil Aviation Administration. Implementation is considered as part of implementation of ADQ requirements. 

‐  40% 

Late 

31/12/2018 

   

ITY‐ACID 

Aircraft Identification    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

100%  Completed 

 ‐  

Azerbaijan ATM system support this functionality. Mode S is implemented, it functions. No declaration of Mode S is provided to NM, as AZ is not EUROCONTROL State. 

31/12/2014 

ASP (By:01/2020) 

AZANS  Azerbaijan ATM system support this functionality. 

Mode S implementati

on / The second phase of installation of ADS‐B and WAM system 

100% 

Completed 

31/12/2014 

     

Page 52: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 41 Released Issue

 

ITY‐ADQ 

Ensure Quality of Aeronautical Data and Aeronautical Information    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

83%  Ongoing 

 ‐  

Although not applicable to AZ, there are plans and activities towards the  implementation of ADQ in AZ. AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done. Roadmap for implementation is established. 

31/12/2018 

REG (By:06/2017) 

State Civil Aviation Administration 

AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done.  

‐  100% 

Completed 

31/12/2015 

ASP (By:06/2017) 

AZANS 

Although not applicable to AZ, there are plans and activities towards the  implementation of ADQ in AZ. AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done. Roadmap for implementation is established. 

Implementation of 

complete AIS to AIM system / 

Installation of METEO radars 

75% 

Ongoing 

31/12/2018 

APO (By:06/2017) 

BAKU ‐ Heydar Aliyev International Airport 

Airport AIS handled by AZANS.   ‐  % 

Not Applicable 

‐ 

   

ITY‐AGDL 

Initial ATC Air‐Ground Data Link Services    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

10%  Ongoing 

 ‐  

Azerbaijan is not within the area of applicability of this EU+ objective. New ATC Centre includes CPDLC functionality. Connection to SITA to be performed in the future. 

31/12/2018 

REG (By:02/2018) 

State Civil Aviation Administration 

Azerbaijan is not within the area of applicability of this EU+ objective. New ATC Centre includes CPDLC functionality. Connection to SITA to be performed in the future. 

‐  0% 

Planned 

01/02/2018 

ASP (By:02/2018) 

AZANS 

Azerbaijan is not within the area of applicability of this EU+ objective. New ATC Centre includes CPDLC functionality. Connection to SITA to be performed in the future. 

‐  13% 

Ongoing 

31/12/2018 

MIL (By:01/2019) 

Mil. Authority  ‐  ‐  % Not Applicable 

‐ 

   

Page 53: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 42 Released Issue

ITY‐AGVCS2 

8,33 kHz Air‐Ground Voice Channel Spacing below FL195    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

 ‐  

Azerbaijan is not in the applicability area of this objective.  ‐ 

REG (By:12/2018) 

State Civil Aviation Administration 

‐  ‐  % 

Not Applicable 

‐ 

ASP (By:12/2018) 

AZANS  ‐  ‐  % Not Applicable 

‐ 

MIL (By:12/2020) 

Mil. Authority  ‐  ‐  % Not Applicable 

‐ 

APO (By:12/2018) 

BAKU ‐ Heydar Aliyev International Airport 

‐  ‐  % 

Not Applicable 

‐ 

   

ITY‐FMTP 

Common Flight Message Transfer Protocol (FMTP) Timescales: Entry into force of regulation: 28/06/2007 All EATMN systems put into service after 01/01/09: 01/01/2009 All EATMN systems in operation by 20/04/11: 20/04/2011 Transitional arrangements: 31/12/2012 Transitional arrangements when bilaterally agreed between ANSPs: 31/12/2014 

100%  Completed 

 ‐  

Functionality completed. FMTP is based on the TCP/IP protocol, IPv4.  31/12/2015 

ASP (By:12/2014) 

AZANS Functionality completed. FMTP is based on the TCP/IP protocol, IPv4. 

‐  100% Completed 

31/12/2015 

MIL (By:12/2014) 

Mil. Authority Mil systems are not interconnected with Civil ATC. One position of Baku ATC system is dedicated for  Mil sector at Baku ACC.  

‐  % Not Applicable 

‐ 

     

Page 54: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 43 Released Issue

 

ITY‐SPI 

Surveillance Performance and Interoperability    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

100%  Completed 

 ‐  

ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE requirements.  Airborn equipment or modification is subject to EASA certification.  Surveillance data exchanged in ASTERIX format. All actions completed. AZ is not in the applicability area ‐ voluntary implementation. 

31/12/2015 

REG (By:02/2015) 

State Civil Aviation Administration 

ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE. Airborn equipment or modification is subject to EASA certification. REG action completed. 

‐  100% 

Completed 

31/12/2015 

ASP (By:02/2015) 

AZANS 

ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE. All data processing is in ICAO standarts. UTC time coordination is obtained by GPS time systems. ASTERIX formats used (ASTERIX 62, 19, 20, etc.) 

MSSR Radar installation at 

Yevlakh Airport / Mode S 

implementation / The 

second phase of installation of ADS‐B and WAM system 

100% 

Completed 

31/12/2015 

MIL (By:06/2020) 

Mil. Authority  ‐  ‐  % Not Applicable 

‐ 

   

NAV03.1 

RNAV 1 in TMA Operations Timescales: Initial operational capability: 01/01/2001 Full operational capability: 31/12/2023 

88%  Ongoing 

 ‐  

RNAV procedures were approved by SCAA.   RNAV arrival and departure procedures are used only in Baku for RNAV approved aircraft. RNAV procedures for other international airports in AZ are ongoing to develop. 

31/12/2018 

ASP (By:12/2023) 

AZANS  The P‐RNAV procedures were tested in a Baku terminal area. New P‐RNAV procedures now are used for arrival and departure for all RWY.  

‐  88% Ongoing 

31/12/2018 

     

Page 55: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 44 Released Issue

 

NAV03.2 

RNP 1 in TMA Operations Timescales: Initial operational capability: 01/01/2018 Full operational capability: 31/12/2023 

0%  No Plan 

 ‐  

‐  ‐ 

ASP (By:12/2023) 

AZANS  ‐  ‐  0% No Plan 

‐ 

   

NAV10 

APV Procedures Timescales: Initial operational capability: 01/06/2011 Full operational capability: 31/12/2016 

72%  Late 

 ‐  

RNP BARO procedure implemented for one runway end at Baku Airport. It is planned to develop procedures for all runway ends by the end of the year. 

31/12/2018 

REG (By:04/2016) 

State Civil Aviation Administration 

AZ is out of EASA remit. However, many standards have been applied. 

‐  % 

Not Applicable 

‐ 

ASP (By:12/2016) 

AZANS RNP BARO procedure implemented for one runway end at Baku Airport. It is planned to develop procedures for all runway ends by the end of 2017. 

‐  72% Late 

31/12/2018 

     

Page 56: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 45 Released Issue

 

SAF11 

Improve Runway Safety by Preventing Runway Excursions Timescales: Initial operational capability: 01/09/2013 Full operational capability: 31/01/2018 

100%  Completed 

 ‐  

Azerbaijan has implemented technical measures to prevent runway excursions. The aerodrome service unit is responsible for runway safety issues. The activities of this unit are closely coordinated with other services. A Special team is organised for runway incursion and all objectives have been met. 

31/12/2015 

REG (By:01/2018) 

State Civil Aviation Administration 

Azerbaijan has implemented technical measures to prevent runway excursions. The aerodrome service unit is responsible for runway safety issues. The activities of this unit are closely coordinated with other services. A Special team is organised for runway incursion and all objectives have been met. 

‐  100% 

Completed 

31/12/2015 

ASP (By:12/2014) 

AZANS 

Azerbaijan has implemented technical measures to prevent runway excursions. The aerodrome service unit is responsible for runway safety issues. The activities of this unit are closely coordinated with other services. A Special team is organised for runway incursion and all objectives have been met. 

‐  100% 

Completed 

31/12/2015 

APO (By:12/2014) 

BAKU ‐ Heydar Aliyev International Airport 

Azerbaijan has implemented technical measures to prevent runway excursions. The aerodrome service unit is responsible for runway safety issues. The activities of this unit are closely coordinated with other services. A Special team is organised for runway incursion and all objectives have been met. 

‐  100% 

Completed 

31/12/2015 

   

 

 

   

Page 57: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 46 Released Issue

Additional Objectives for ICAO ASBU Monitoring  

ATC02.2 

Implement ground based safety nets ‐ Short Term Conflict Alert (STCA) ‐ level 2 for en‐route operations Timescales: Initial operational capability: 01/01/2008 Full operational capability: 31/01/2013 

100%  Completed 

 ‐  

STCA functions exist and are optimised to the local environment.  Existing system has STCA functions. Review of  new EUROCONTROL specifications was done during 2010.  NEW ATC Centre and ATC Tower has been  built and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. Nowadays New system  is working. ATS personnel use new SIDs and STARs. 

30/11/2014 

ASP (By:01/2013) 

AZANS 

STCA functions exist and are optimised to the local environment.  Existing system has STCA functions. Review of  new EUROCONTROL specifications was done during 2010. NEW ATC Centre and ATC Tower has been  built and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. Nowadays New system  is working. ATS personnel use new SIDs and STARs 

‐  100% 

Completed 

30/11/2014 

   

ATC16 

Implement ACAS II compliant with TCAS II change 7.1   Timescales: Initial operational capability: 01/03/2012 Full operational capability: 31/12/2015 

100%  Completed 

 ‐  

All aircraft, in accordance with the plan were equipped with TCAS Version 7.1. AZANS system is capable of ACAS II performance monitoring. 

31/12/2015 

REG (By:12/2015) 

State Civil Aviation Administration 

All aircraft, in accordance with the plan were equipped with TCAS Version 7.1 

‐  100% 

Completed 

31/12/2015 

ASP (By:03/2012) 

AZANS 

AZANS systen is capable to perform ACAS II performance monitoring. Acquisition information about TCAS II version 7.1and develop training plan to train ATCO in ACAS II (TCAS II version 7.1) has been completed. 

‐  100% 

Completed 

31/12/2015 

MIL (By:12/2015) 

Mil. Authority 

MIL has no ATS role.  ‐  % Not 

Applicable 

‐ 

     

Page 58: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 47 Released Issue

  

FCM01 

Implement enhanced tactical flow management services Timescales: Initial operational capability: 01/08/2001 Full operational capability: 31/12/2006 

0%  Planned 

 ‐  

Azerbaijan is planning to build new airspace flow efficiency center which will implement tools to enhance tactical flow management. Bilateral agreement with EUROCONTROL addressing ATFCM issues signed in 2015. Status is planned (not LATE) as Azerbaijan was unable to implement this objective earlier as there was no basis to be in the scope of CFMU. 

31/12/2018 

ASP (By:07/2014) 

AZANS 

Azerbaijan has built new airspace flow efficiency center which will implement tools to enhance tactical flow management. Bilateral agreement with EUROCONTROL addressing ATFCM issues signed in 2015. Status is planned as Azerbaijan was unable to implement this objective earlier as there was no basis to be in the scope of CFMU. 

‐  0% 

Planned 

31/12/2018 

   

INF04 

Implement integrated briefing Timescales: Initial operational capability: 01/07/2002 Full operational capability: 31/12/2012 

100%  Completed 

 ‐  

Integrated briefing is implemented and operational at Baku Heydar Aliyev Airport. AZANS currently implementing self briefing automated system at Baku Heydar Aliyev Airport.  

31/01/2012 

ASP (By:12/2012) 

AZANS 

Integrated briefing is implemented and operational at Baku Heydar Aliyev airport. AZANS currently implementing self briefing automated system at Baku Heydar Aliyev airport.  

‐  100% 

Completed 

31/01/2012 

   

ITY‐COTR 

Implementation of ground‐ground automated co‐ordination processes    (Outside Applicability Area) Timescales: ‐ not applicable ‐ 

68%  Ongoing 

 ‐  

OLDI is installed in AIRCON system. The Installation of OLDI system continue in the adjacent Centers. Communication through the OLDI system between Baku and Rostov is in test mode.  

31/12/2018 

ASP (By:12/2012) 

AZANS 

OLDI is installed in AIRCON system. The Installation of OLDI system continue in the adjacent Centers. Communication through the OLDI system between Baku and Rostov is in test mode.  

‐  68% 

Ongoing 

31/12/2018 

MIL (By:12/2012) 

Mil. Authority 

Azerbaijan is outside of the applicability of this objective.  

‐  % Not 

Applicable 

‐ 

   

Page 59: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 48 Released Issue

Local Objectives  

AOP14 Remote Tower Services Applicability and timescale: Local 

0%  Planned 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport 

It is planned to create a virtual tower on the island of Chilov in the Caspian Sea for helicopter operations. Note that this Objective refers to Chilov heliport and not Baku airport, which was selected because Chilov was not in our database.  

31/12/2018 

 

ATC18 Multi‐Sector Planning En‐route ‐ 1P2T   Applicability and timescale: Local 

%  No Plan 

 ‐  

‐  ‐  

ENV03 Continuous Climb Operations (CCO) Applicability and timescale: Local 

50%  Ongoing 

UBBB ‐ Baku ‐ Heydar Aliyev International Airport 

SIDs PBN has been developed and implemented in the practical at the airport Heydar Aliyev. RNAV arrival and departure procedures are used for P‐RNAV approved aircraft and for all RWY. Training programs are being developed and will be implemented after approved by SCAA.  

31/12/2018 

 

NAV12 Optimised Low‐Level IFR Routes in TMA for Rotorcraft   Applicability and timescale: Local 

%  Ongoing 

 ‐  

Low‐Level IFR Routes in TMA are developed and will be published in the local AIP  31/12/2018  

 

 

Page 60: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation
Page 61: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 49 Released Issue

 

ANNEXES 

 

ANNEX A ‐ Specialists involved in the LSSIP Process  

 

LSSIP Co‐ordination  

 

LSSIP Focal Points  Organisation  Name 

LSSIP Focal Point for Azerbaijan  AZANS  Alexander TELEGIN 

LSSIP Focal Point for ANSP  AZANS  Agabek BALABEKOV  

 

EUROCONTROL LSSIP Support 

 

Function  Directorate  Name 

LSSIP Contact Person for Azerbaijan  DECMA/PRM  Predrag VRANJKOVIC 

    

Page 62: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 50 Released Issue

Implementation Objectives 

 

Implementation Objective 

EUROCONTROL PEPR Objective Coordinator 

EUROCONTROL Objective Owners 

National Stakeholder Specialist  

AOM13.1  A. DYBOWSKA  O. MROWICKI/ C. LUCCIOLI  Vahid GADIROV 

AOM19.1  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

 

AOM19.2  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

 

AOM19.3  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

 

AOM21.1  A. DYBOWSKA  C. BRAIN  Vahid GADIROV 

AOM21.2  A. DYBOWSKA  C. BRAIN  Vahid GADIROV 

AOP04.1  P. VRANJKOVIC  R. GRAHAM  Safa MAMMADOV 

AOP04.2  P. VRANJKOVIC  R. GRAHAM  Safa MAMMADOV 

AOP05  F. ROOSELEER  M. BIRENHEIDE   

AOP10  F. ROOSELEER  R. GRAHAM   

AOP11  F. ROOSELEER  M. BIRENHEIDE   

AOP12  P. VRANJKOVIC  R. GRAHAM   

AOP13  P. VRANJKOVIC  R. GRAHAM   

AOP14  A. DYBOWSKA  R. GRAHAM / G. ASSIRE   

ATC02.8  F. ROOSELEER  S. DROZDOWSKI   

ATC02.9  F. ROOSELEER  S. DROZDOWSKI   

ATC07.1  L. DELL’ORTO  pending   

ATC12.1  L. DELL’ORTO  pending   

ATC15.1  L. DELL’ORTO  pending   

ATC15.2  L. DELL’ORTO  P. HOP   

ATC17  L. DELL’ORTO  S. MORTON   

ATC18  L. DELL’ORTO  I. PENDACHANSKI   

COM10  J. PINTO  Y. EYUBOGLU  Safa MAMMADOV 

COM11  J. PINTO  L. POPESCU  Safa MAMMADOV 

COM12  J. PINTO  W. JANSSENS   

ENV01  B. HILL  D. BRAIN  Aleksandr ESTROV 

ENV02  B. HILL  S. MAHONY   

ENV03  A‐P. FRANGOLHO  D. BRAIN   

FCM03  O. CIOARA C. BOUMAN/I. PENDACHANSKI 

Farhan GULIYEV 

FCM04.1  I. MARCETIC P. HOP/I. PENDACHANSKI   

FCM04.2  I. MARCETIC  P. HOP/I. PENDACHANSKI   

FCM05  O. CIOARA I. MENDES VIDEIRA/I. PENDACHANSKI 

Farhan GULIYEV 

FCM06  F. ROOSELEER  P. HOP/I. PENDACHANSKI  Farhan GULIYEV 

FCM08  O. CIOARA  K. BREIVIK/I. PENDACHANSKI  Farhan GULIYEV 

Page 63: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 51 Released Issue

INF07  A‐P. FRANGOLHO  A. PETROVSKY  Aleksandr ESTROV 

ITY‐ACID  O. CIOARA pending Safa MAMMADOV

ITY‐ADQ  A‐P. FRANGOLHO M. UNTERREINER Julia DRONOVA

ITY‐AGDL  B. HILL D. ISAAC Safa MAMMADOV

ATY‐AGVCS2  B. HILL J. POUZET Safa MAMMADOV

ITY‐FMTP  O. ALFARO L. POPESCU Safa MAMMADOV

ITY‐SPI  O. CIOARA  M. BORELY  Safa MAMMADOV 

NAV03.1  I. MARCETIC  F. PAVLICEVIC 

NAV03.2  I. MARCETIC  F. PAVLICEVIC 

NAV10  I. MARCETIC  R. FARNWORTH  Aleksandr ESTROV 

NAV12  I. MARCETIC  B. RABILLER / F. RIQUET   

SAF11  F. ROOSELEER  pending  Alexander TELEGIN 

 

 

   

Page 64: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 52 Released Issue

ANNEX B ‐ National Stakeholders Organisation charts  

 

 

 

   

Page 65: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 53 Released Issue

AZANS Organisation Chart 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 66: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 54 Released Issue

Azerbaijan state inspectorate on Civil Aviation Flight Safety

Page 67: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 55 Released Issue

ANNEX C – Implementation Objectives’ Applicability  

Objective SESAR 

Key Feature 

ICAO ASBU 

B0 European ATM Masterplan Level 3 Applicability area 

AOM13.1  

‐ All ECAC States except Albania, Latvia, Luxembourg, Maastricht UAC and 

Moldova. 

AOM19.1  

B0‐FRTO All ECAC States except Armenia, FYROM, Malta, Luxembourg, and 

Moldova 

AOM19.2  

‐  All ECAC States except Armenia, Luxembourg and Moldova 

AOM19.3  

‐  All ECAC States except Armenia, Luxembourg and Moldova 

AOM21.1  

B0‐FRTO  25 ECAC States 

AOM21.2  

‐ All ECAC States except Azerbaijan, Belgium, Luxembourg and the 

Netherlands 

AOP04.1  

B0‐SURF  25 PCP airports, 22 non‐PCP airports 

AOP04.2  

B0‐SURF  25 PCP airports, 22 non‐PCP airports 

AOP05  

B0‐ACDM  25 PCP airports, 21 non‐PCP airports 

AOP10  

‐  16 PCP Airports 

AOP11  

‐  24 PCP airports, 15 non‐PCP airports 

AOP12  

‐  25 PCP airports 

AOP13  

‐  25 PCP airports 

AOP14  

‐  Local: Low to medium complexity aerodromes, subject to local needs 

ATC02.2    B0‐SNET Additional for ICAO ASBU monitoring: applicable all ECAC States that did 

not yet implement it 

ATC02.8  

B0‐SNET  All ECAC States except the Netherlands 

ATC02.9  

B0‐SNET  TMAs, according to local business needs 

ATC07.1  

B0‐RSEQ  23 PCP Airports, 8 non‐PCP airports 

ATC12.1  

‐  All ECAC States except Luxembourg 

ATC15.1 

 

 B0‐RSEQ 

EU States except Cyprus, Greece, Lithuania, Luxembourg, Malta, Slovak 

Republic, Slovenia. Plus: Bosnia and Herzegovina, Maastricht UAC, 

Norway, Switzerland, Turkey 

ATC15.2  

‐ ACCs within the extended AMAN horizon, including those adjacent to 

TMAs serving/associated to PCP airports 

ATC16    B0‐ACAS Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

ATC17  

B0‐FICE  All ECAC States except Ireland, Slovak Republic and Ukraine 

ATC18  

‐  Local: Subject to local needs and complexity 

COM10  

‐   All ECAC States 

COM11  

‐  All ECAC States 

Page 68: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 56 Released Issue

COM12 

 

 ‐ 

‐ Area 1 (ANSPs signatories of the NewPENS Common Procurement 

Agreement): 33 ANSPs 

‐ Area 2 (Other stakeholders): Stakeholders from all ECAC States not part 

of Area 1 

ENV01  

B0‐CDO  59 Airports 

ENV02  

‐  47 Airports 

ENV03  

B0‐CCO  Local: Aerodromes subject to local needs and complexity 

FCM01    B0‐NOPS Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

FCM03  

B0‐NOPS  All ECAC States 

FCM04.1  

B0‐NOPS Austria, Belgium, Croatia, Czech Republic, France, Germany, Italy, Poland, 

Spain, Switzerland 

FCM04.2  

B0‐NOPS  All EU+ States 

FCM05  

B0‐NOPS All ECAC States except Armenia, FYROM, Luxembourg, Maastricht UAC 

and Moldova 

FCM06  

B0‐NOPS  All EU+ States 

FCM07  

‐  All EU+ States 

FCM08  

‐  All ECAC States 

FCM09  

‐  All ECAC States 

INF04    B0‐DATM Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

INF07  

‐  All ECAC States except Maastricht UAC 

INF08.1  

‐  All EU+ States 

INF08.2  

‐  All EU+ States 

ITY‐ACID  

‐  All EU+ States 

ITY‐ADQ  

B0‐DATM  All EU+ States except FYROM, Georgia and Maastricht UAC 

ITY‐AGDL  

B0‐TBO  All EU+ States except Georgia, Luxembourg and Netherlands 

ITY‐AGVCS2  

‐  All EU+ States except Georgia and Moldova 

ITY‐COTR    B0‐FICE Additional for ICAO ASBU monitoring: applicable all EU+ States that did 

not yet implement it 

ITY‐FMTP  

B0‐FICE  All ECAC States 

ITY‐SPI  

B0‐ASUR  All EU+ States 

NAV03.1  

B0‐CDO,  

B0‐CCO All ECAC States except Luxembourg, Maastricht UAC and Slovak Republic 

NAV03.2  

‐ Mandatory for TMAs listed in section 1.2.1 of the Annex of the PCP 

Regulation. For all other ECAC TMAs, according to local business needs 

NAV10  

B0‐APTA  All ECAC States except Maastricht UAC 

NAV12  

‐  Local: TMAs subject to local needs and complexity 

SAF11  

‐  All ECAC States except Malta 

Page 69: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 57 Released Issue

 

Legend:  

 

Objective’s link to SESAR Key Feature: 

 

Optimised ATM Network Services  

High Performing Airport Operations 

 

Advanced Air Traffic Services  

Enabling Aviation Infrastructure 

 

   

Page 70: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 58 Released Issue

ANNEX D ‐ Glossary of Abbreviations  

This Annex mostly shows only the Abbreviations that are specific to the LSSIP Azerbaijan. 

Other  general  abbreviations  are  in  the  Acronyms  and  Abbreviations  document  in http://www.eurocontrol.int/articles/glossaries 

 

Term  Description 

ACAS  Airborne Collision Avoidance System 

ACC  Area Control Centre 

AIS  Aeronautical Information Services 

AMC  Acceptable means of Compliance  

ANS  Air Navigation Services 

ANSP  ANS Provider 

AOP  Airports Operations (Domain) 

APV  Approach with Vertical Guidance 

ARN  ATS Route Network 

ATS  Air Traffic Services 

CAD  Civil Aviation Department 

CDM  Collaborative Decision Making 

CNS  Communications, Navigation and Surveillance 

COM  Communications 

CTR  Control Zone 

DFL  Division Flight Level 

EAD  European AIS Database 

eAIP  European Aeronautical Information Publication 

EATM  European Air Traffic Management 

ECAC  European Civil Aviation Conference 

ESARR  EUROCONTROL Safety Regulation Requirement 

ESP  European Safety Programme 

FDP  Flight Data Processing 

FIR  Flight Information Region 

FL  Flight Level 

FSQA  Flight Safety and Quality Assurance  

FUA  Flexible Use of Airspace 

GBAS  Ground Based Augmentation System 

GNSS  Global Navigation Satellite System 

HRS  Human Resources 

HUM  Human (Domain) 

IFPS  Initial Flight‐plan Processing System 

Page 71: Local Single Sky ImPlementation LSSIP 2017 - AZERBAIJAN€¦ · Document Title LSSIP Year 2017 for Azerbaijan ... Master Plan Level 3 – Report Year ... The following legislation

LSSIP Year 2017 Azerbaijan 59 Released Issue

IFR  Instrument Flight Rules 

ISO  International Standards Organisation 

JAA  Joint Aviation Authorities 

kHz  Kilohertz 

LoA  Letters of Agreement 

MIL  Military 

NAV  Navigation 

NM  Nautical Mile 

NOTAM  Notice To Airmen 

OLDI  On Line Data Interchange 

OPS  Operations 

PSR  Primary Surveillance Radar 

QMS  Quality Management System 

REG  Regulatory Authorities 

RNP  Required Navigation Performance 

RVSM  Reduced Vertical Separation Minimum 

SAN  Sakaeronavigatsia Ltd (ATM of Georgia) 

SBAS  Satellite‐Based augmentation systems (SBAS) 

SLOA  Stakeholder Line of Action 

SMQS  Safety Management and Quality System 

SMS  Safety Management System 

SRC  Safety Regulation Commission  

SSR  Secondary Surveillance Radar 

STCA  Short Term Conflict Alert 

SUR  Surveillance (Domain) 

TMA  Terminal Manoeuvring Area; Terminal Control Area