location - qcfihyderabad.comqcfihyderabad.com/cc2016/tech-presentations/energy/energy best... ·...
TRANSCRIPT
Location Max Temperature:47oC
Min Temperature:14oC
Annual Rainfall:600 -700 mm
1985 – M/s TEXMACO LTD Capacity – 1500TPD Cement Plant 1993 – Enhanced production capacity from -1500 TPD to 1800TPD 1995 – Management Change to ZUARI INDUSTRIES LIMITED 1998-99 – Plant capacity has enhanced to 5000 TPD (1.8MTPA- Clinker) 2000 – 50:50 Joint venture with Italcementi Group 2006 – Become 100 % share holder in ZCL. 2009 – Clinker production cap. increased to 1.8 to 2.0MTPA 2010 – New Clinker Line(2.3 MTPA)Commissioned.2016 - Management Changed to HEIDELBERG CEMENT
Plant history & Details
1985:TEXMACO LTD
1993:Enhanced Production
1500 to 1800TPD
1995:ManagementTook over by
ZCL
1998-99 :Enhanced
Clinker Prod1.6 to
1.8MTPA
2000:50:50 Joint
venture with
ItalcementiGroup
2006:Italcementi
become 100 % share holder in ZCL
2009:Enhanced
Clinker Product1.8 to
2.0 MTPA
2010 :New
Clinker Line(2.3 MTPA)
Commissioned
2016 :Management Took over by HEIDELBERG
CEMENT
Installed Capacity (Clinker) - 4.3 mMTPA
Installed Capacity (Cement) - 5.4 mMTPA
Wind Power Installed Capacity - 6 MW
Solar Power Installed Capacity - 550 Kwp
Product Range - OPC , PPC , PSC and MC
ZCL – Yerraguntla Plant
Arrested compressed air leakages
Installed VFD
Reduced Loading unloading set points
Separated packing plant silo aeration and installed 30 kw
compressor
Installed 55 Kw compressor and stopping bigger compressor
when equipment stop condition
Reduction of Compressor power consumption
Innovative project- 1
Pipe line modification for reducing pressure drop
Installed small receiver tanks for critical locations
Reduction of Compressor power consumption
Innovative project- 1
Installed solenoid valves for auto
cut off the valve with equipment
running
Introducing SMS Alert system
Reduction of Compressor power consumption
Innovative project- 1
Compressor speed increases sms will send to concerned and
solinoids intraduced is Known Concept, but applied for differently
and also it is beyond the scope of OEM and having high Replication
Potential in the sector
819 Kwh / day
19.39 Lakhs per Annum
6 Lakhs
4 months
100 % Replication is possible in All industries
Cemen
t silo
Modification
Innovative project-2
Direct feeding system to EEL-2 Vibrating screen by avoiding CB-2 :
Avoided Extra circuit running
by connecting directly to the
vibrating screen with
installation of one air slide
and diverting gate .
CB-2 Circuit is not required
when we are running one
product in one packer
Innovative project-2
Direct feeding system to EEL-2 Vibrating screen by avoiding CB-2 :
Packer is recently installed (2010 ) and modification in the packer
circuit is beyond the scope of OEM and having high Replication
Potential where ever EEL supplied same cicuit
80 Kw
41.1 Lakhs per Annum
6 Lakhs
2 months
Innovative project-3
Idler design for Increasing low bulk density Alternate fuel
Low bulk density alternate fuel like RDF is not flowing
through feeding hopper and belt is running with out material due to arch
forming and disturbing the pc outlet temperature ZCL designed a spike roller
for disturbing the material and leads to improved flowability
ZCL designed a spike roller for improving flow ability, it is beyond the scope of OEM and having high Replication Potential in the sector
Innovative project-3
Idler design for Increasing low bulk density Alternate fuel
1.43 Kcal / kg clink
18.1 Lakhs per Annum
1 Lakhs
1 months
Installed VFD
Installed floating valves for the storage tanks
Reduced Pump RPM
Further reducing Pump RPM with Ok mill or Kiln
running status
SMS Alert system
Daily monitoring and reporting power
consumption through mail
Reduction of Process Water Pumps Power Consumption
2462 Kwh / day
3278 Kwh / day
816 Kwh / day
Innovative project- 4
ATOX-55 is the first mill in Asia order by Zuari cement ltd with design capacity 430 TPH
Mill Feed gain size : 120 mm
VRM- 2 ( ATOX – 55) Optimization with Reject B.E
Need for the projects
• To improve reliability of mill
• Higher power consumption
• Production enhance to
match
kiln production
Raw Mill-3 (ATOX-55) reject B.E
Reject B.E design (Original)Capacity : 225 TPH Grain size : 60 mmMill feed grain size : 120 mm
Reject B.E design (Modified)Capacity : 400 TPH Grain size : 150 mmMill feed grain size : 120 mm
OEM not accepted to change the B.E
Route cause• Under capacity reject B.E design• To control reject , fan speed keep higher side resulting fan power consumption is high to control rejects
VRM- 2 ( ATOX – 55) Optimization with Reject B.E
Raw mill-3 (ATOX-55) Operating
Parameters Before B.E
Modification
Raw mill-3 (ATOX-55) Operating
Parameters After B.E
Modification
VRM- 2 ( ATOX – 55) Optimization with Reject B.E
Advantages After Modification of Reject B.E
• After changing the B.E the mill stoppage during start up is reduced.
• With old B.E number of stoppages in 2013 was 168 .
• With Modified B.E number of stoppages in 2015 is zero .
• The mill fan speed reduced from 95 % to 92 % - Optimized .
Results achieved
• The Average mill production increased from 420 TPH to 437 TPH.
• Reliability of raw mill increased from 89 to 93 % .
•The specific power reduced by 1.2 kWh/ T of raw meal.
• Total Savings achieved in a year : 124.7 lakh /Year.
VRM- 2 ( ATOX – 55) Optimization with Reject B.E
line-2 calciner fine coal transport blower speed reduced by 10 %.
PA fan VFD installed in line-2 kiln
Total Power saving : 800 kWh/day
line-1 calciner Fine coal transport blower speed reduced by 10 %.
Total Power saving : 600 kWh/day
Electrical Energy Saving projects
Energy Conservation Projects
Replaced entire Start up diesel with liquid Alternative fuel
Mixing Of Red mud in lime stone pile To Use High Sulfur
Pet coke
Need for the projects
Stared using high sulfur pet coke.
Facing problem of coating in smoke chamber & raiser ducts.
To neutralize the sulfur content in pet coke need red mud (rich in alkali)
Kiln not in stable operation .
Silica content in lime stone is higher
Challenges
Handling red mud with 25 % moisture
Mixed the red mud with lime stone & feed to additive hoppers (Two) having
capacity 400 MT each.
Hopper getting jam frequently and raw mix quality not matching with the pet
coke fuel.
Advantages of using Red mud in raw mix
* High sulfur pet coke consumption
* Low grade limestone utilization
* Kiln stable Operation with increase in
production.
* Reduced Raw mix and fuel cost.
* With mixing in lime stone pile , there is no
jamming in chutes/ Hopper.
* Quality of raw mix & clinker is consistence
Red mud spreading on stock pile
Mixing Of Red mud in lime stone pile To Use High Sulfur
Pet coke
Results:Use of red mud in line-2 kiln is successful with enhanced kiln stable operations with high sulfur Pet Coke & consistent quality .
DescriptionKiln feed
Clinker
Production
Clinker
Production
TPH TPH TPD
Without red mud and 100 % pet coke 390 244 5844
With red mud and 100 % pet coke
with stable condition413 258 6194
Savings achieved :•With the optimized output we saved the specific power consumption by 0.65 kWh/ Tof clinker and Specific fuel 3 Kcal/Kg clinker.•By the use of red mud along with the fuel mix savings against increased clinkerproduction works 120 lakh /year• Saving due to reduction in energy consumption Rs : 123 lakh/year•Total saving per year Rs: 243 lakh/year
Mixing Of Red mud in lime stone pile To Use High Sulfur
Pet coke
Brixmate Cement Quality Parameters
DESCRIPTION UnitTest
Results
Specification
IS:3466
PHYSICAL TESTS:
Residue on 45
Micron% 11.60 Max 15.0
Setting Time
- Initial Minutes 170 Min 90.0
- Final Minutes 310 Max 1440
Air Content % 7.40 Min 6.0
Water Retention % 74.00 Min 60.0
Compressive
Strength
7-Days MPa 12.00 Min 2.5
28-Days MPa 18.00 Min 5.0
Soundness -
Autoclave% 0.05 Max 1.0
Soundness - Le-
Chatliermm 1.25 Max 10.0
Advantages• Less shrinkages & cracks• Longer initial setting time• Greater Durability• Brick work with super finish• Lesser clinker consumption• Skilled man power not required for application
Results:• Carbon emission reduced to 50% compared to ordinary cements. • Eco friendly.
Manufacturing Brixmate Cement
Energy Saving Projects implemented during last 3
years with No Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment Payback
(Months)Million Units
Million Rs
Tones fuel
Million Rs
Million Rs
Million Rs
Reducing the line-2 water pump speed during kiln shut down
0.02 0.13 0.0 0.0 0.13 0.0 0.0
Replacement of diesel with pyrolysis oil
0.00 0.0 436 7.20 7.20 0.0 0.0
Reduction of surface in 43 grade cement
0.25 1.62 0.0 0.0 1.62 0.0 0.0
Coal Crusher bypass during fine (imported) coal unloading.
0.15 0.97 0.0 0.0 0.97 0.0 0.0
Increased OK mill PPC grinding 0.23 1.49 0.0 0.0 1.49 0.0 0.0
Maximizing unloading fly ash in bin instead of unloading in silo
0.06 0.39 0.0 0.0 0.39 0.0 0.0
Reduce the Damper loss in line-2 cooler vent fan
0.16 0.95 0.0 0.0 0.95 0.0 0.0
Energy Saving Projects implemented during last 3
years with No Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment Paybac
k (Month
s)Million Units
Million Rs
Tones fuel
Million Rs
Million Rs
Million Rs
Optimization of quarry water pumps 0.18 1.05 0.00 0.00 1.05 0.00 0.00
Optimized use of petcoke with Redmud & increase clinker Production
1.50 9.00 650 3.25 12.25 0.00 0.00
Optimisation of rawmill grinding media
0.27 1.62 0.00 0.00 1.62 0.00 0.00
Optimisation of CM-3 Grinding media 0.29 1.73 0.00 0.00 1.73 0.00 0.00
Optimisation of Idle running power by logic modification
0.40 2.41 0.00 0.00 2.41 0.00 0.00
Punch plate removal in Rawmill-3 0.69 4.16 0.00 0.00 4.16 0.00 0.00
Energy Saving Projects implemented during last 3
years with No Investments
Description of Energy Saving Projects implemented
Annual Electrical Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback
(Months)Million
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
Optimization of K line bag house fan
0.10 0.60 0.00 0.00 0.60 0.00 0
Optimize the loading of DG Transformer
0.00 0.02 0.00 0.00 0.02 0.00 0
Optimizing the fly ash unloading system
0.05 1.81 0.00 0.00 1.81 0.00 0
Optimising the Air volume in line-2 Rawmill
0.75 4.50 0.00 0.00 4.50 0.00 0
Reduction of damper loss in CM-1 Bag house fan
0.03 2.38 0.00 0.00 2.38 0.00 0
Total Saving without investment : 4.53 Cr
Energy Saving Projects implemented during last 3
years with Investments
Description of Energy Saving Projects implemented
Annual Electrical Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback
(Months)Million
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
Optimisation of Line-2 water pump by Instaltion of VFD
0.49 3.16 0 0 3.16 0.80 3.0
Damper and LRS losses reduced by installation of VFD for CM-2 sepax fan
0.32 2.06 0 0 2.06 1.60 9.3
Damper and LRS losses reduced by installation of VFD for CM-3 sepax fan
0.36 2.31 0 0 2.31 1.60 8.3
Optimized EEL packer Bag filter by Instaltion of VFD
0.16 1.03 0 0 1.03 0.45 5.3
Line-2 PA Fan optimized by Instaltion of VFD
0.16 1.03 0 0 1.03 0.95 11.1
Direct feeding of cement to EEL packer-2 vibrating screen bypassing CB-2 circuit
0.63 4.11 0 0 4.11 0.60 1.8
OK mill separator Felt seal arrangement
0.15 0.98 0 0 0.98 0.10 1.2
Energy Saving Projects implemented during last 3
years with Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback (Month
s)Million Units
Million Rs
Tones fuel
Million Rs
Million Rs
Million Rs
Line-1 Calciner coal firing blower speed reduced by 10%
0.20 1.28 0.0 0.0 1.28 0.05 0.5
CM-2 Grinding media optimization 0.52 3.39 0.0 0.0 3.39 2.28 8.1
Cooler vent fan HT motor replaced with LT Motor and installed VFD
0.63 4.11 0.0 0.0 4.11 1.60 4.7
Installation of VFD for Line-1 Post Clinker Water Pupms
0.16 1.02 0.0 0.0 1.02 0.45 5.3
Replacement of 250w HPSV street lights with 60 W LED lights
0.05 0.31 0.0 0.0 0.31 0.53 20.0
Coal firing blower optimised with reducing blower speed by changing pully
0.20 1.31 0.0 0.0 1.31 0.05 0.5
Installation of high efficiency bag house fan in cement mill -2
0.03 0.21 0.0 0.0 0.21 0.80 46.7
Energy Saving Projects implemented during last 3
years with Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback (Month
s)Million Units
Million Rs
Tones fuel
Million Rs
Million Rs
Million Rs
Installation of high efficiency bag house fan in cement mill -3
0.03 0.21 0.00 0.00 0.21 0.80 46.7
Installation of Solenoid Valve system In packing Plant for optimization of compressed air
0.30 1.94 0.00 0.00 1.94 0.60 3.7
Optimisation of line-2 Raw mill Circuit Air flow Volume After Reject B.E Installation
2.08 12.47 0.00 0.00 12.47 9.00 8.66
Reduction of Pressure drop Across Venturi in line-1 VRM
0.73 4.36 0.00 0.00 4.36 3.00 8.26
Optimization of Coal transport blowers in Line-2
0.36 2.18 0.00 0.00 2.18 0.05 0.28
Line-2 Pyro section Compressor Optimization
1.82 10.89 0.00 0.00 10.89 1.00 1.10
Line-2 cement mill section Compressor Optimization
1.49 8.91 0.00 0.00 8.91 1.00 1.35
Energy Saving Projects implemented during last 3
years with Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment Payback
(Months)Million
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
Line-1 Pyro section Compressor Optimization
0.36 2.16 0.00 0.00 2.16 1.20 6.67
Optimization of line-1 pyro cooling water circuit
0.36 2.18 0.00 0.00 2.18 1.00 5.51
Optimization of line-1 cement cooling water circuit
0.33 1.98 0.00 0.00 1.98 1.00 6.06
Reduction of Pressure drop between bag house outlet to fan inlet in CM-4
0.33 1.98 0.00 0.00 1.98 0.15 0.91
Street lights optimization 0.06 0.37 0.00 0.00 0.37 0.49 15.69
Cement mill - 2 Bag house fan changed with High efficiency fan
0.07 0.44 0.00 0.00 0.44 3.00 82.64
Optimization of line-1 lighting voltage 0.01 0.07 0.00 0.00 0.07 0.20 34.3
Energy Saving Projects implemented during last 3
years with Investments
Description of Energy Saving Projects implemented
Annual Electrical
Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback (Month
s)Million Units
Million Rs
Tones fuel
Million Rs
Million Rs
Million Rs
Reduction of damper losses in line-1 VCLM booster fan with installation of VFD
0.30 0.02 0.00 0.00 0.02 1.00 600
Reduction of line-1 pyro compressors pressure from 7.2 to 6 BAR
0.40 4.46 0.00 0.00 4.46 0.15 0.4
Reduction of pressure drop between Cm-4 bag house outlet to fan inlet
0.33 0.15 0.00 0.00 0.15 0.10 8
Reduction of pressure drop across venturi in line-1 VRM coal mill
0.40 1.98 0.00 0.00 1.98 0.10 0.61
Replacement of MV Lamps with metal halide lamps in workshop
0.02 2.97 0.00 0.00 2.97 0.20 0.81
Installation of energy efficient fluorescent lamps in line-1
0.06 0.37 0.00 0.00 0.37 0.49 15.58
Cement mill - 3 Bag house fan changed with High efficiency fan
0.07 0.44 0.00 0.00 0.44 3.00 82.6
Energy Saving Projects implemented during last 3
years with Investments
S. No
Year of implementa
tion
No. of Energy Saving
Projects implemented
Annual Electrical Savings
Annual Thermal Savings
Total Annual Savings
Investment Pay
back in MonthsMillion
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
1 2013-2014 13 2.5 19.76 0 0 19.76 5.24 3.2
2 2014-2015 19 11.5 69.3 650 3.3 72.5 20.9 3.5
3 2015-2016 22 5.1 33.04 436 7.20 40.2 13.3 4.0
Grand Total 19.2 122.1 1086 10.5 132.5 39.4 3.6
710
711
712
713
714
715
716
717
718
719
720
2013 -14 2014 -15 2015 -16
720
718
717
Specific Thermal Energy Consumption
3 Kcal / kg clink (0.4%)
Reduced
56.0
57.0
58.0
59.0
60.0
61.0
62.0
63.0
64.0
65.0
66.0
67.0
2013 -14 2014 -15 2015 -16
66.5
63.6
59.9
76.0
78.0
80.0
82.0
84.0
86.0
88.0
90.0
92.0
2013 -14 2014 -15 2015 -16
91.5
85.5
82.1
Specific Electrical Energy Consumption
10 % Reduced
10 % Reduced
Base Line Specific energy Consumption : 0.082385 Toe / Ton
Target For PAT Cycle-1 : 0.078583 Toe / Ton
Achieved Specific Energy Consumption : 0.0735429 Toe / Ton
Energy saving certificates : 11824
PAT CYCLE-1
Energy management cell formed with cross function team members. The coordinator for the Energy management cell is Energy Manager.We launched ‘’i.max for manufacturing excellence ‘’ program as plat form for key performance improvement Ideas generation from the all the employees and tracking the work process based on the priority. The daily review of energy monitoring by each section .Weekly review by plant head. Awards for the best idea & Energy savings implementedSMS alert system for stoppages to control the down time.
Strategy adapted to Reduce Energy Consumption
Head production
DGM-process
Maintenance head
GM-Mech
Quality headG.M -QC
Head E& I DGM-E&I
Team 2:
Kiln & Coal mill section head &
engineers
Team 3:
Crushers & raw mill section engineers
Team 5:
Cement grinding
incharge & engineers
Team 4:
Packing & dispatch section
engineers
Plant Head S.V.P-Works
Energy Manager
Head MinesGM-Mines
Team 1:
Mines section head &
engineers
Energy Management Committee
64.8%
35.2%
Idea contribution
Management Workers
Employees involvement & Suggestions status
0
50
100
150
200
Total Ideas New Ideas With outCapex
With smallCapex
With Capex Ideasimplementted
Ideas underProgress
172
8
6851 45 52
22
Energy ManagementCommittee includes OneEnergy Auditor & Two EnergyManagers :
Mr. Jignesh Kumar Duva –DGM (Production) - EA
Mr. P. Raghuram – DGM(Electrical & Instrumentation) -EM
Mr. G.SaiSunil Bharathbabu– Dy. Manager (Electrical) - EM
Strategy adapted to Reduce Energy Consumption
SL APPRISAL FACTORS
RATINGS (R)
REMARKS1-POINT 2-POINTS 3- POINTS 4-POINTS 5-POINTS
POINTS
AWARDE
D
01Equipment reliability
(Kilns)> 97% >97.5% >98% >98.5% >99% 5
02
SD Targets & Safety
Targets as per Group
Standards.
<92% 94% 96% 98% 100% 5
03 MTBF – Kilns ( Hours) <110 160 180 200 250 5
04Maintaining Power
Factor>0.97 >0.975 >0.98 >0.98.5 >0.99 5
05i.Max (Power)
KWH/T<84 <83 <81.5 <79.1 <78.2 5
06 Energy Saving Ideas 1 2 3 4 5 5
(PART -3 ASSESSMENT BY THE INITIATING OFFICER / IMMEDIATE SUPERIOR)
Energy Score Card
Displayed Energy Conservation & Wastage
consequences Awareness Posters at various locations in
the plant
Best Suggestion
Best Energy Conservation Team Best Energy Contribution Awards
Rcognisation Program for Encon Efforts
Best Suggestion Ideas Contribution
Operational Excellence Awards Energy Saving Measures
Rcognisation Program for Encon Efforts
Training Programs to Employees & Contract Workers
Energy conservation projects planned 2016-2018
Description of Energy Saving Projects Year
Annual Electrical Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback
(Months)Million
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
Reduction of Pressure drop in C - line bag house out let to fan inlet duct
2016-17 0.37 2.2 0.0 0.0 2.2 1.2 6
Installation of mill scan for cement mill-2 2016-17 0.44 2.6 0.0 0.0 2.6 1.2 6
Installation of mill scan for cement mill-3 2016-17 0.44 2.6 0.0 0.0 2.6 1.2 6
Rawmix optimization after installation of crosbelt analyser
2016-17 0.00 0.0 458 1.83 1.8 18.0 118
Avoiding pnumatic conveying by Installation of new steel silo for export and slag cement.
2016-17 0.60 3.6 0.0 0.0 3.6 50.0 167
Installation of Fly ash feeding to mill discharge arrangement
2016-17 0.09 0.5 0.0 0.0 0.5 1.1 24
Replacement of 250w HPSV street lights with 60 W LED lights
2016-17 0.05 0.3 0.0 0.0 0.3 0.5 22
Energy conservation projects planned 2016-2018
Description of Energy Saving Projects Year
Annual Electrical Saving
Annual Thermal Saving
Total Annual Savings
Investment
Payback
(Months)Million
UnitsMillion
RsTones fuel
Million Rs
Million Rs
Million Rs
Replacement of line-1 VCLM CA Fan HT motor with high efficiency motor along with VFD
2016-17 0.63 3.8 0.0 0.0 3.8 2.0 6
Installation of line-1 fine coal dosing system
2016-17 0.00 0.0 1832 7.30 7.3 30.0 49
Installation of Pyrojet burner for line-2 2016-17 0.00 0.0 916 3.65 3.7 15.0 49
Optimisation of RVRM-3 2016-17 2.35 14.1 0.0 0.0 14.1 2.0 2
Line-2 Calciner Coal firing points connecting to feed box
2016-17 0.00 0.0 664 2.65 2.6 0.3 1
Line-1 Calciner Coal firing points connecting to feed box
2016-17 0.00 0.0 180 0.72 0.7 0.3 5
Optimised EEL packer Bag filter by Installation of VFD
2016-17 0.16 1.0 0.0 0.0 1.0 0.5 6
Line-1 Old Pre heater Fan replacing with high efficiency fan.
2017-18 1.87 11.2 0.0 0.0 11.2 6.0 6
550 Kwp Solar Power Plant In The Plant Solar Street Lights In Colony Road &
Mines Operation
Utilization of Renewable Energy Resources
Utilization of Renewable Energy Resources
6 MW Wind Power Plant In Anathapur
Utilizing Bio mass as a Alternate fuel
Replacement of Electrical Energy with Renewable Energy
DescriptionInstalled Capacity
(kW)
2013-14 (million kWh)
% Share2014-15
(million kWh)%
Share2015-16
(million kWh)%
Share
Wind Energy 6000 0.00 0.00 3.08 1.19 14.81 6.68Solar Energy 550 0.50 0.18 0.70 0.27 0.75 0.34
Total 0.50 0.18 3.79 1.46 15.57 7.02
Utilization of Renewable energy ( % of Total Energy)
Replacement of Thermal Energy with Renewable Energy
DescriptionFuel Savings in
2013-14 (million kcal/year)
% Share
Fuel Savings in 2014-15 (million
kcal/year)
% Share
Fuel Savings in 2015-16 (million
kcal/year)
% Share
Biomass 65183.1 3.45 91323.5 4.80 83067.4 4.84
6. Awards
“Best Management Award” in 2016
Environment award “Greenco Gold rating Award” in 2016
6. Awards
Excellent Energy Efficient Plant in Cement Sector in INDIA (2015) by CII
Excellent Energy Efficient Plant in Cement Sector in INDIA (2016) by CII
Greenpro - Green product certification for Zuari Superlite AAC
Awards & Appreciation
……..aiming to conserve natural resources
54
When we heal the earth, we heal ourselves ~ David Orr
Great things are not done by impulse, but by a series of small things
brought together