logistics conceptual design
TRANSCRIPT
-
8/19/2019 Logistics Conceptual Design
1/57
Logistics & Transport International
TITLE:801-AA10.01-CONTENS:PROJECT REQUIREMENTS ANALYSIS-PROJECT MANAGER:MANOLAS I.-23/1/2013
CLIENT:
"INTERNATIONAL LOGISTICS CENTER"PROJECT:
DELIVERABLES
PROJECT REQUIREMENTS ANALYSIS
MANOLAS I.
23/1/2013
TITLE:
PROJECT MANAGER:
DATE:
801-AA10.01DOCUMENT CODE:
CONTENTS DATELEAD DESIGNER
01.
02.
PROJECT SCOPE
PROCESS FLOW CHART (PFC) SERVICE STOCKS 3PL
MANOLAS I.
MANOLAS I.
23/1/2013
23/1/2013
03.
04.
05.
06. INSTALLATION SPECIFICATIONS
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013
PROCESS FLOW CHART (PFC) SERVICE STOCKS TRANSPORT INTERN.
ORGANIZATION CHARTGENERAL SPECIFICATIONS OF CUSTOMER
MANOLAS I.
MANOLAS I.
23/1/2013
23/1/2013
.
07.
08.
09.
.
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013
SITE PRESENTATION & LEGAL FRAMEWORK
STORAGE SYSTEM: BACK TO BACK
MANOLAS I. 23/1/2013STORAGE SYSTEM: B2B & VNA
10.
11.
12. STOCK DATA - TRANSPORT INTERNATIONAL (RECEIPT VOLUMES)
STORAGE SYSTEM: DRIVE IN
MANOLAS I. 23/1/2013MANOLAS I. 23/1/2013
STORAGE SYSTEM: LIVE STORAGE & BACK TO BACK
MANOLAS I. 23/1/2013
13. CALCULATION OF REQUIRED SPACE (RL / UNLOADING)
14. STOCK DATA - TRANSPORT INTERNATIONAL (DISPATCH VOLUMES)
15. CALCULATION OF REQUIRED SPACE (RL / LOADING)
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013
.
17. CALCULATION OF REQUIRED SPACE - CRITICAL ZONE (FRIDAY)
18. EVALUATION DATA STORAGE
19. DRAFT
.
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013
MANOLAS I. 23/1/2013. .
-
8/19/2019 Logistics Conceptual Design
2/57
TITLE:801-AA10.01/01./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:PROJECT SCOPE/LEAD DESIGNER:MANOLAS I.
/DATE:23/1/2013
1. PROJECT SCOPE1.1.INTRODUCTION
The Project "Preliminary Design for Warehouse and Offices Coplex" intends to document the ongoing procedures of COMPANY at
the present facilities, in order to track critical points for the stock management, the ergonomics of the building facilities, in order to
achieve a "Complete Operational Planning" of the new facilities.
What the whole effort intends to do is the development of specifications for the design of new facilities on the site proposed by theclient. The design should intend to develop a complete building up to 13.000 m2 of surface, which will be constructed in two
phases. Phase A concerns the construction of warehouse and administration areas of about 8.000 m2 and maximum budget
4.000.000 €.
For this purpose we have considered:
a) the main operational planning of the client
b) the proposed site by the client
c) the ongoing procedures for the stock management
d) the stock featurese) the uses of the outdoor area
" "
1. The main goal of the investment is to construct and operate modern logistics center facilities
(International Transport & 3PL) involving road & rail access. The first phase of construction includes
While considering the present situation we identified the following "Critical Points" (CP analysis)
a) Operational Planning
2.
o ce ac es . m , n erna ona ranspor ware ouse . m an ware ouse .
m2).
The facilities should have high interoperability (international transport, 3PL, ADR stock, customs & taxcontrol).
3.
b) The proposed site by the client
The site proposed complies with the investment intention. The site evaluation is to follow.
Maximum stock capacity and low operational cost
1. It is of great importance to consider the approach by rail and the respective unloading and stocking of
containers.
c) The ongoing procedures for the stock management
2.
3.
4.
The distinct development of the activities is not possible because the operational area is limited.
The informatics support of the stock appears with serious deficits.
The concentration of 60% of stock loading and unloading on Fridays defines the ergonomic and
operational limits of the warehouse areas.
-
8/19/2019 Logistics Conceptual Design
3/57
TITLE:801-AA10.01/02./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:PROCESS FLOW CHART (PFC) SERVICE STOCKS 3PL/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
2.PROCESS FLOW CHART (PFC)2.1.SERVICE STOCKS 3PL
Χ.0 Transportation trucks
Expected stock01
.Trucks of company's clients, national, internationaltransportation, returns(3PL stock)
Χ.1 Receiving - Loading [RL]
Unloading & Receiving stock.1 Α.
Χ0) Trucks
, ,.. , .Stock handling units are used.The stock consists of One code pallets(75%), Mixed codepallets(15%) & Boxes(10%).
.Stock identification-Quality&Quantity control.2 Α.The quality - quantity control takes place during the unloadingat the receiving area where the pallets are identified (both One
One code / Mixed code Pallets02
UNLOADINGΑct.1
code pallets and Mixed code pallets). In case full control is
required (of part of the stock, of ruined stock) this proceduretakes place in a specified area. Stock identification follows(labeling reffering to One code pallets)
Unloading for sorting2Χ.
Χ1) Receiving - Loading Area
IDENTIFICATIONQUALITY& QUANTITY CONTROL
Αct.2
Internal transportation1.3 Α.Transportation by means of handling equipment to the storagearea (for the stock which should be received in detail,processed, relieved of inappropriate stock). Only partof the stock passes through the storage area.
.Quality&Quantity control, stock identification4 Α.
INTERNAL TRANS. (RELOADING)Α.3.2INTERNAL TRANS.
[Cross Docking]Α.3.3
INTERNAL TRANSPORTATIONΑ.3.1
ua y uan y con ro a es p ace o owe y s oc
Χ3.1 Storage Area (Loc. Stock, Loc. Picking)
Χ3.2 Inappropriate stock storage area
Χ5) Loading and final control area
One code pallets08One code pallets06
Mixed code pallets07
One code pallets04
Mixed code pallets05
.
Α.5.1 Internal transportationTransportation by means of handling equipment to the storageareas (Rack areas), the storage can be made in stock locationsor in picking locations
Α.5.2 Internal transportation
Χ4) Order composing area
Χ2) Unloading area to be placed
DENTIFICATION QUALITY &QUANTITY CONTROL
Α.4.0
Transportation by means of handling equipment to theInappropriate stock storage area
Α.5.3 Internal transportation
Transportation by means of handling equipment to the Specialstorage areas
INTERNAL TRANS.Α.5.2 INTERNAL TRANS.Α.5.1 INTERNAL TRANS.Α.5.3
Α.6.1 2 RefeedingStock regrouping (between stock places) refeeding of pickingspots. The procedures are performed by means of handlingequipment
Χ4) Order composition area
Χ3.2) Inappropriate stock storage area
One code pallets9.2
Χ3.1) Storage area(Loc. Stock, Loc. Picking)
One code pallets9.1
Χ3.3) Special storage area
One code pallets9.3
s poss e o per orm processng ac v es ns ethe order composition area]
Α.3.3. Internal stock transportation Cross DockingTransportation of stock which has arrived to the order
composition area (both One coded pallets & Mixed coded
One code pallets10.1
REFEEDING RESTORAGINGΑ.6.1
REFEEDING RESTORAGINGΑ.6.2
One code pallets10.2
oncernng e or er compos on po cy.In case the order composition takes place at the racks (listbased - paper or RF) and the order is collected, identified andcontrolled in one step, then it is possible to match the ordercomposition area and the loading ramp coincide. If the order iscomposed in two steps (prepicking - picking) or the idenificationand the control require more space then we define area X4 for
Χ3.1) Storage area(Loc. Stock, Loc. Picking)
Χ3.3) Special storage area
.
Χ5) Loading & final control area
.
COLLECTIONΑ.7Α.10 QUALITY&QUANTITY
CONTROL
-
8/19/2019 Logistics Conceptual Design
4/57
TITLE:801-AA10.01/02./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:PROCESS FLOW CHART (PFC) SERVICE STOCKS 3PL/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
2.PROCESS FLOW CHART (PFC)2.2.CP Analysis
Cp
1
Category description
Unloadin boxes and lue,unloadin dela , ual it - uanti t cont ro l, a llet iz in dela
2.3.Necessary equipment
Problem caused by the handling of inappropriate stock and stock which needs detailed receipt3
2
Problem caused by the simultaneous handling of transportation goods & 3PL
1
2
3
4
5
Loading - Unloading
Identification, order composing, internal moving Α2, Α3, Α4, Α5, Α6, Α7, Α8, Α9, Α10,
Α1, Α3, Α5, Α7, Α8, Α11
Α5, Α6, Α7,
Α10
Internal moving, Picking
Internal moving, regrooping
Electric trucks (+RF)
Forklifts (RT, VNA) (+RF)
Pallet wrapping Prior to the loading (between Α10 - Α11)
Manually handled trucks
RF - Terminals
Α1, Α11
-
8/19/2019 Logistics Conceptual Design
5/57
TITLE:801-AA10.01/03./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:PROCESS FLOW CHART (PFC) SERVICE STOCKS TRANSPORT INTERN./LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
3.PROCESS FLOW CHART (PFC)3.1.TRANSPORT INTERNATIONAL
Expected stock01
Χ.0 TrucksExpected stock.1
Trucks of company's clients, national, internationaltransportation, returns(3PL stock)
Χ0) Trucks
Χ.1 Receiving - Loading [RL]Unloading & Receiving stock.1 Α.
There will be unloading ramps (TIR, ,..), Dry Cargo stock.Stock handling units are used.The stock consists of One code pallets, Mixed code pallets,individually packaged goods in bulk, & irregular cargo
One code / Mixed code Pallets02
UNLOADINGΑct.1IDENTIFICATION QUALITY &
QUANTITY CONTROLΑ.2.2
"On Car Truck"Immediate Delivery
(voluminous items).
.Stock identification-Quality&Quantity control.1.2 Α.The quality - quantity control takes place during the unloading atthe receiving area where the pallets as well as the individuallypackaged goods are identified (both One code pallets andMixed code pallets). In case full control is required (of part of the
Χ1) Receiving - Loading Area
Boxes03
IDENTIFICATIONQUALITY& QUANTITYCONTROL
Αct.2
-RL
,
specified area. Stock identification follows (labeling reffering toOne code pallets, individually packaged goods or individualclients).
For (Stock identification-Quality&Quantity control.2.2 Α.).immediate Delivery
Thisconcerns oods to bedelivered immediatel to the client
INTERNAL TRANS. (RELOADING)Α.3.2INTERNAL TRANS.
[Cross Docking]Α.3.3
INTERNAL TRANSPORTATIONΑ.3.1
RL
(for reasons related to the delivery time or cost). In this case thecargo is checked before delivery and complemented as needmay be (in case another delivery, from a different country orvehicle, is due for the same client).
Unloading for sorting2Χ.]detailed receipt process Area for stock which requires a[
Χ5) Loading and final control area
One code pallets08One code pallets06
Mixed code pallets07
One code pallets04
Mixed code pallets05
Internal transportation1.3 Α.Transportation by means of handling equipment to the storage
area (for the stock which should be received in detail,processed, relieved of inappropriate stock). Only partof the stock passes through the storage area.
.Quality&Quantity control, stock identification4 Α.
Χ4) Order composing area
Χ2) Unloading area to be placed
IDENTIFICATION QUALITY &QUANTITY CONTROL
Α.4.0
Quality&Quantity control takes place followed by stockidentification (labeling reffering to One code pallets, individuallypackaged goods or individual clients)
Temporary Storage Area1.3ΧInappropriate stock storage area2.3Χ
PL3-Loc. Stock, Loc. Picking)(AreaStorage3.3Χ Α 5 1 Internaltrans ortation
INTERNAL TRANS.Α.5.2 INTERNAL TRANS.Α.5.1 INTERNAL TRANS.Α.5.3
. .Transportation by means of handling equipment to the storageareas (Rack areas). This concerns identified cargo intended forimmediate delivery to clients. Storage Location depends on thetime the stock remains in the warehouse before delivery
Α.5.2 Internal transportationTransportation by means of handling equipment to the storage
Χ3.2) Inappropriate stock storage area
One code pallets9.2
Χ3.1) Storage area(Loc. Stock, Loc. Picking)
One code pallets9.1
Χ3.3) Special storage area
One code pallets9.3 areas with a special status (possible change of status for thestock from interchange to storage).
Α.5.3 Internal transportationTransportation by means of handling equipment to 3PL stockmanagement areas. This results in a change of status for the
from interchange to storage.stock
One code pallets10.1
REFEEDING RESTORAGINGΑ.6.1 REFEEDING RESTORAGINGΑ.6.2
One code pallets10.2
Α.6 RefeedingRegrouping of stock (between stock areas), Resupply of Pickingareas. The process is carried out with handling equipment.
Χ4) Order composition area
[It is possible to perform processing activities inside the
Χ3.1) Storage area(Loc. Stock, Loc. Picking) Χ3.3) Special storage area
Α.3.3. Internal stock transportation Cross DockingTransportation of stock which has arrived to the ordercomposition area (both One coded pallets & Mixed codedpallets, individually packaged goods)
,Collection of pallets,Internal transportation7 Α.Collection with the help of material handling equipment fromem orar stora e areas intheorder com osition areaor the
.
COLLECTIONΑ.7Α.10 QUALITY&QUANTITY
CONTROL
loading and final control area.Collection of individually packaged goods8 Α.
-
8/19/2019 Logistics Conceptual Design
6/57
TITLE:801-AA10.01/03./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:PROCESS FLOW CHART (PFC) SERVICE STOCKS TRANSPORT INTERN./LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
3.PROCESS FLOW CHART (PFC)2.2.CP Analysis
Cp
1
Category description
Unloadin ofboxesandindividual l acka ed oods, Dela s inunloadin , Q-Q control , allet bui ldin
2.3.Necessary equipment
2 Problems due to the handling of interchange & 3PL products in a single fashion
Problems in the management of damaged goods and cargo which requires a detailed process of receipt
3
1
2
3
4 Forklifts (RT, VNA) (+RF) Internal transfer, Resorting Α5, Α6, Α7,
RF - Τerminals Identification, Order Composition, Internal transfers Α2, Α3, Α4, Α5, Α6, Α7, Α8, Α9, Α10,
Powered pallet jacks (+RF) Internal transfers, Picking Α1, Α3, Α5, Α7, Α8, Α11
Manual pallet jacks Loading/Unloading Α1, Α11
-
8/19/2019 Logistics Conceptual Design
7/57
TITLE:801-AA10.01/04./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:ORGANIZATION CHART/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
4.ORGANIZATION CHART4.1. MANAGEMENT
1 Manager Α
Secretary 1 3
2Assistant ManagerB
Secretary 2 3
3International TransportC1 National and Balcans D1 Finance & Administr.E1 Logistics ManagerF1
[Respectively to the hierarchy position]
[Number of workstations / office]
[Number of offices]
Status 1 2 3
Workstations 1 1 1
Number of offices 1 2 3
1
Office code
Ranking
[Total]
4.2.INTERNATIONAL TRANSPORT
Total 1 2 3 C3,4 1
Workstations
International
Transport C1 2
SALESC2 ROAD TRANS.SECTION IMPORT
C3 ROAD TRANS.
SECTION EXPORTC4
AIR, SEA & RAILTRANS. SECTION
C5 ITC6 EXTERNALACTIVITIES SEC.
C7
C1.1 1 4
3
C2.1 1
C2.2 1
C3.1 1
C3.2 2
C4.1 1
C4.2 2
C5.1 1
C5.2 2
C6.1 1
C6.2 1
C7.1 1
C7.2 3
4 5 4 5 4 5 4 5 4 5 4 5
.
C2.4 3
C3.3 1
C3.4 2
C3.5 1
C4.3 1
C4.4 2
C4.5 1
C5.3 1
C5.4 2
C6.3 1
C5.5 1
C3.6 2
C3.7 1
C3.8 2
C4.6 2 C5.6 2
.
C3 10 2
-
8/19/2019 Logistics Conceptual Design
8/57
TITLE:801-AA10.01/04./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:ORGANIZATION CHART/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
4.ORGANIZATION CHART4.3. NATIONAL TRANSPORT
National
and
Balcans
Transport
D1 2
SALESD2 INTERNAL ROAD
TRANS. SECTIOND3
BALKANS ROAD TRANS.SECTION
D4 NATIONAL RAIL
TRANS. SECTIOND5 D6 3
4 5 4 5 4 5 4 5 4 5
.
D3.2 2
D3.3 1
D3.4 2
.
D4.2 2
D4.3 1
D4.4 2
.
D5.2 2
.
D6.2 2
.
D2.2 2
D3.5 1
D3.6 2
Status1 2 3 4 5
Workstations 1 1 1 1 2 3
8 0
Total 0 1 5 24
Number of offices 1 5 8 0C3,4 1
Office code
Workstations
D.2.1 Sales office D.3.1/3/5 D.4..1/3 D.5. Line Manager D.6. Line Manager
D.2.2 Sales secretary Line Manager Line Manager D.5. Operation D.6. Operation
D.3.2/4/6 C.4.2/4
Operation Operation
4.4. FINANCIAL MANAGEMENT
Finance & Administr E1 2
C3,4 1
Office code
Workstations
.
Ε.1.1 1
4 5
Ε.1.1/3 Administration manager
Ε.1.2/4 Operation
Status 1 2 3 4 5
2 3
Number of offices 1 0 2 0 0 2
Workstations 1 1 1 1
Total 0 1 0 8
Ε.1.2 3
Ε.1.3 1
Ε.1.4 3
4.5. LOGISTICS - 3PL
Logistics Manager3PL
F1 2
-
8/19/2019 Logistics Conceptual Design
9/57
TITLE:801-AA10.01/04./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:ORGANIZATION CHART/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
4.ORGANIZATION CHART4.6. Client Area
3PLTR. INT.
CLIENT & ASSOCIATES
AREAΕ1 2
Status 1 2 1 2Workstations 1 2 1
Number of offices 3 3 4
Surface (m2) 12 50 12
INTER. TRANS.Ε2 LOGISTICS - 3PLΕ3
4 5 4
3
Total (m2) 36 150 48
Office code
F.3.1 1
F.3.2 1
F.2.1 1
F.2.2 2
C3,4 1
Surface code
. .
F.2.4 2
F.2.5 1
F.3.3 1
Ε.2.1/3/5 Ε.3.1/2/3/4
Representative Client manager
. . . .
Ε.2.2/4/6
Quality control area
. - Α Β C D Α Β C D
Status 1 2 3 4 5 3 4 5 5 5 55 5 5 Status 1 2
2 3 82 3 8 Workstations 0 1Number of offices 1 5 14 29 1
1 1 1Workstations 1 1 1 1 15 5 1 1 1 120 4 0 Number of offices 1
0 1 5 19Total staff /Status 1 5 14 82 Total staff /Status
General staff total 102 General staff total 25
-
8/19/2019 Logistics Conceptual Design
10/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.1.GENERAL REQUIREMENTS
nves men n y LI
Phase A Time schedule 25/3/2012 - 25/2/2013
TRANSP.
INTERN.3PL
m2
m
m2
Demand for warehouse area 3,000Demand for height of warehouse areas (net height) 6 12
In case a refrigeration area is requested0 0
5,000
m 12The logistics center is designed to serve: 6
Transport trucks (National & International transportation) [Loading &
Unloading]
Nb / Da
80 30
Container (National & International transport) [Loading & Unloading]15 15
The curve radius of the rail line should be at least 125m (R – 125m).
Rail wagons - Container [Approaching]15
The inclination of the rail line should be between 8%ο - 12%ο.
5.2.GENERAL STOCK SPECIFICATIONS
5.2.1.Stock description
TRANSP.
INTERN. 3PL
Industrial Equipment 60 1,000
Household devices 60 1,000
Cosmetics 60 1,000
Textile 60 1,000
Car parts 60 1,000
-
8/19/2019 Logistics Conceptual Design
11/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.2.2.Requested services
TRANSP.3PL
.
Storage YES YES
Per package YES YES
PickingYES YES
Processing YES YES
Distribution
5.2.3.Type of used pallets
Europallet 0,8 X 1,2 1 YES
Industrial (1,0 X 1,2) YES YES
5.2.4.Height of pallets
1,20m - 1,25m 25% 25%
, m - , m 10% 10%
2,00m - 2,10m 60% 60%
2,10m - 2,30m 5% 5%
5.2.5.Weight of pallets
- . 80% 5%
From 1.000 - to 1.200Kgr 10% 35%
From 1.200 - to 1.500Kgr 10% 60%
5.2.6.Picking (level)
B
-
8/19/2019 Logistics Conceptual Design
12/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.2.8.Average time of stock storage (days)
.
INTERN.3PL
From 1 - to 6 Day 2% 60%
From 7 - to 15 Da
From 16 - to 30 Day 60% 15%
From 31 - to 60 Day 20% 10%
5.2.9.Access / Pallet
Back to Back
Drive in / Live Storage / Block Stacking30% 40%
-
8/19/2019 Logistics Conceptual Design
13/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.3.ERGONOMIC LIMITS OF WAREHOUSE5.3.1.Operation Model of Logistics Center
hours
TRANSP.
INTERN.3PL
Total working time / day 16 8
shifts
Days
Shifts / day 2 1
Days / period 6 5
hoursTotal time for unloading stock / day 8 8
5.3.2.Unloading
PltsMaximum stock unloading / day 640 480
TIR
5.3.3.Loading
ax mum num er o arr va s ay 20 15
Plts
TIR
Maximum stock loading / day 650 650
Maximum number of arrivals / Day (14 Plts load, 60% full, 6 deliveries) 30
PltsMaximum number of arrivals / Day (32 Plts load, 90% full, 2 deliveries)
25
. . .
PltsMaximum estimated necessary surface 500 1,500
5.3.5.Dock Levellers
PltsMaximum estimated necessary number of electrohydraulic ramp
7 10
TIRMaximum estimated necessary number of external type ramps
2
-
8/19/2019 Logistics Conceptual Design
14/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.4.REQUIREMENTS FOR STORAGE AND AUXILLIARY AREAS5.4.1.Warehouse Ambient & Chilled
Warehouse Ambient
chapter 6, ELEMENTS OF COMMERCIAL STORAGE BUILDING AND FIEL
Warehouse Chilled
chapter 6, ELEMENTS OF COMMERCIAL STORAGE BUILDING AND FIEL
5.4.2.Warehouse for Small Items & Expendables
Re uired surface 100 m2
Warehouse
Connected with the dry cargo warehouse area
5.4.3.Flamables Warehouse - ADR
Suitable industrial floor
Warehouse
Dr car o tem erature YES
Distinct area from the rest of the warehouse
(in direct contact with it)YES
Required volume 1,500
5.4.4.Tax Controlled Warehouse
Suitable industrial floor YES
Warehouse
Dr car o tem erature YES
Distinct area from the rest of the warehouse
(in direct contact with it)YES
Required volume 1,000
5.4.5.Customs Controlled Warehouse
Suitable industrial floor YES
Warehouse
Dr car o tem erature YES
Distinct area from the rest of the warehouse (in direct contact with it)YES
Required volume 500
Suitable industrial floor YES
-
8/19/2019 Logistics Conceptual Design
15/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.5.SPECIFICATIONS FOR ADMINISTRATION AND PERSONNEL AREAS5.5.1.ADMINISTRATION AREA - OFFICES
General Requirements TRANSP.INTERN.
3PL
Distinct from the main facility and in contact with it YES
Concrete construction reinforced concrete
Desired office floors2 1
Indication of needed m2 1,500 500
Metal structure YES
Number of employees 100 25
High commercial value areas YES
National & International ΜεταφοράNb of offices
Factor
(m2/off.)Surface m2
Management C (3) 3 12 36Staff workstations: 1 0 12 0
Management Α (1) 1 35 35
Management Β (2) 2 20 40
Staff (workstations: 3) 0 21 0
Staff (workstations: 8) 5 56 280
19 503
Staff (workstations: 2) 8 14 112
Θέσεις
Εργασίας
Α∆ (m2 /
ΘΕ)
Επιφ. m2
Meeting room 5 3 15
Archives 0 0 30
Meeting room 40 3 120
Meeting room 10 3 30
Restaurant 60 2 75 165
Dining room 50 2.75 138
-
8/19/2019 Logistics Conceptual Design
16/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMERLogistics - 3PL
Πλ. Γραφείων Α∆ (m2/Γρ.) Surface m2
Management C (3) 5 12 60
Staff workstations: 1 1 12 12
Management Α (1) 0 35 0
Management Β (2) 1 20 20
Staff (workstations: 3) 1 21 21
Staff (workstations: 8) 1 56 56
10 183
Staff (workstations: 2) 1 14 14
WorkstationsFactor
(m2/W.st.)Surface m2
WC 10 2.75 28
Infirmary 3 5 15
Locker Room 20 4 80
Dining room 20 2.75 55
198
Special areas for associates & clientsWorkstations
FactorSurface m2
Workshop 2 10.00 20
(m2/W.st.)
Area Surface 48
Total 3PL m2 429
-
8/19/2019 Logistics Conceptual Design
17/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.6.SPECIFICATIONS FOR OUTDOOR AREA FACILITIES5.6.1.Main Entrance Gate
5.6.2.Gate Security Station
In accordance with standards and regulations
Constructed in reinforced concrete
Air conditioned area
At the complex gate
5.6.3.Truck Scale
n erna commun ca on w a m n s ra ve an opera ona areas
Constructed in reinforced concrete
In proximity to the gate security stationElectronic survey of the measurements
5.6.4.Parking ShedsSurrounding Area's
Staff private vehicles 10
5.6.5.Open Parking
15
'
Staff private vehicles 30
Distribution vehicles 25
Large trucks 15
Pillars 5
5.6.6.Forklift Sheds
75
Surroundin Area's
Outdoor area forklifts 2
Diesel forklifts 2
4
5.6.7.Container Area
-
8/19/2019 Logistics Conceptual Design
18/57
TITLE:08603-EC10.01/01./REPORTING OFFICER DEVELOPMENT PROJECT ANALYSIS & BUSINESS
AFFAIRS/CONTENTS:STANDARD WORKSHEET - P01 (A4 Portrait)/LEAD DESIGNER:MANOLAS I. /DATE:18/7/2012
5. GENERAL SPECIFICATIONS OF CUSTOMER5.6.9.Other Outdoor Area Data
Surrounding Area's
Asphalt area required YES
Reinforced concrete at the ramp area YES
Fencing required YES
Commercial value of the outdoor area HIGH
Required sidewalks YES
-
8/19/2019 Logistics Conceptual Design
19/57
TITLE:801-AA10.01/06./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
6.INSTALLATION SPECIFICATIONS6.1.ELEMENTS OF COMMERCIAL STORAGE BUILDING AND OUTDOOR AREA6.1.1.BUILDING SPACES CATEGORIES
Space of report - Area - m2
2,140 100%
Warehouse Stock Loading Dock Sum (m2) %
Warehouse Storage - Cross Docking
A12,140 0 0%
1,670 1,390 83% 280 17%
Warehouse Storage A2
A3
A4
280 17%
1,670 1,390 83% 280 17%
17%1,670 1,390 83% 280
1,670 1,390 83%
A5
0 0 0 20%Warehouse Cold Storage (Frozen)
0 080%
020%
Warehouse Refrigeration Storage (Chilled)
75%
8,820 5,560 63% 3,260 37%
8,820
Total
Total Warehouse Storage Area
Space of report - Area - m2 Warehouse Stock Loading Dock Sum (m2) %
670
1,345
Ground floor Administrative Spaces
1st Floor Administrative Spaces
2,015
674 76%Pump House (ESFR - In Rack)
Administrative Spaces
Mechanical Room (Heating - Freezing)
17%
124 14%
0 0%
65 7%
Electrical Room (Transformer)
Battery Charging Room
Auxilary Facilities
Facilities Operations Support
20 2%
883
11,718Total Building's Area 51%
Guard House
Technical Spaces 8%
6.1.2.OUTDOOR AREAS CATEGORIES
Area - m2Roadways
,
0 0%
Firetrucks
-
8/19/2019 Logistics Conceptual Design
20/57
TITLE:801-AA10.01/06./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
6.INSTALLATION SPECIFICATIONS6.2.SURROUNDING AREA6.2.1.ROADWAYS & UTILITIES
1. Warehouse Floor
Concrete AsphaltCirculation
AsphaltBase
Subbase -
Gravel
25 (cm)
70 (cm) 20 (cm) 20 (cm) 30 (cm)
60 (cm) 20 (cm) 15 (cm)
2. Front of Ramp-Doors
cm
50 (cm) 5 (cm) 5 (cm) 15 (cm) 25 (cm)
cm cm cm cm
25 (cm)
55 (cm) 5 (cm) 5 (cm) 15 (cm) 30 (cm)
45 (cm) 5 (cm) 5 (cm) 10 (cm)
. a n oa s
4.Secondary Roads5. Car Parking Space
6.Truck Parking Space
30 (cm)
0 (cm)
63 (cm) 18 (cm) 15 (cm)
0 (cm)
0 (cm)
8.Container Handling Area
9.Railroad
10.Planted Areas
7.Tractor Parking
25 (cm)60 (cm) 20 (cm) 15 (cm)11.Offices' Floor
6.3.1.GEOTECHNICAL WORK
25 - 30cmSite clearing fron natural ground
Subbase Layers of 25cm using vibrating road roller 10tn, 4 passes at every
6.3.2.FLOOR LOADING
Design Load for Warehouse -60 KN/m2 6 tn/m2
.
-
Forklift Load
Load per wheel -
Pressure of contact -
25 KN 3 tn
6,000 KN/m2 612 tn/m2
pee
Number of transits
Design Load for Offices
m
200 per day
Ground Floor -
1st Floor -
Designing Load for Charging Room -
5 KN/m2 1 tn/m2
3 KN/m2 0 tn/m2
60 KN/m2 6 tn/m2
6 3 3 ROAD NETWORK
-
8/19/2019 Logistics Conceptual Design
21/57
TITLE:801-AA10.01/06./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
6.INSTALLATION SPECIFICATIONS6.3.4.UTILITIES
Stormwater Utility According to the design requirements, can be at stormwater Sewer, or to
Water Connection
Drinkable Water Connection According to the design requirements, office requirements.
. According to the design requirements, office requirements, warehouse
requirements and the water tank for fire suppression.
Low Currents Network
According to the design requirements, office requirements, warehouserequirements.
. . .
Fencing
Sliding Gate
2.00 m high Chain Link Fencing with Barb-Wire; Posts set in concrete
Electrical 10,00Χ2,00m
Manual 6,00Χ2,00m
Outdoor Area Lighting Photocell operated, 150Lux at loading area, 15Lux at roads and parking space.
Perimetrical Building Separation
8m high light poles at trucks parking
Planted Area
6.4.WAREHOUSES
3,2m high light poles at car parking
According to the design requirements
6.4.1.BASIC INFRASTRUCTURES
Warehouse's Perimetric Concrete Panels 15cm Thick, 2,10m High, made from precast concrete panels or cast onsite
concrete walls.
Firecell
are ouse s er me r c oncre e ane s
at the cross dock
cm c , , m g , ma e rom precas concre e pane s or cas ons e
concrete walls.
60min fire walls
60min with concrete wall
Fire Exit Stairs at Loading Docks
90min fire walls
90min with concrete wall
Made of reinforced concrete
Steel constructionBattery Charging Room
Infrastructures outside of the warehouses
Specified as hazardous area ( 60min firecell), with perimetric reinforcedconcrete wall of 15cm width and 0,6m minimum height.
Footing for the Firefighting reservoirs
Footing for the main vehicle entrance
Access Ramp made of reinforced concrete per 10.000m² of Warehouse
-
8/19/2019 Logistics Conceptual Design
22/57
TITLE:801-AA10.01/06./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
6.INSTALLATION SPECIFICATIONSReinforced Concrete Loads kΝ / m2
Roof Dead Load
kg / m2
1 100
Brick Weight
Soil 18 1,800
4 360
e sm c oa s
Seismic Hazard ZoneII a = 0.24 g
Foundation oil kΝ m2
Foundation Depth 1,5 m (according to the level of the surrounding area)
Soil Stress 200 (CAT. Β)
6.4.3.BEARING STRUCTURE ELEMENTSFoundation Type
Beams on Elastic foundation
Frame Type
Steel Structure for Coating Panels
Reinforced Concrete Columns - Steel Roof
Frame
Column Axis m
WidthLen th
22.806.00
Roof Elements m
Bent 3,1% (TPO)
6.4.4.COATING ELEMENTSRoof Coating
Translucent areas
Roof openings for the smoke removal
- -
TPO Film / POLYURETHANE3% percent of the covered surface
1% percent of the covered surface
-
8/19/2019 Logistics Conceptual Design
23/57
TITLE:801-AA10.01/06./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
6.INSTALLATION SPECIFICATIONS
Interior Lighting
Technical Support Spaces 250 Lux
Special Systems Requirements Administrative Spaces Data & Voice
. . .
Sprinkler System ESFRPump Rooms Per BuildingFirefighting Reservoirs Outside each Building
6.5.WAREHOUSE OFFICES6.5.1.BASIC INFRASTRUCTURE
Placed Inside the buildingLevels Ground floor and mezzanine
HVAC Installation To be designed Active Fire Protection System Sprinklers
Water Supply WCSanitary Installation WC
Ventilation See HVAC InstallationSupply of Electric Power Low and Extra Low voltage
-
8/19/2019 Logistics Conceptual Design
24/57
- . .
: . :
.. .
rea
-
x ens on ou s e o e ro er an o
are ouse es
n us r o
. . .
are ouse es
ommerc a ora e en er o
. .. . .
enera c arac er za on o e an use u s e e c an
ores s o oun
-
8/19/2019 Logistics Conceptual Design
25/57
- . .
: . :
.. . .
-
8/19/2019 Logistics Conceptual Design
26/57
- . .
: . :
.
-
8/19/2019 Logistics Conceptual Design
27/57
- . .
: . :
.
. . . -
u n e u a on
- - - -
- - - -
- - - - -- - - -
enera ons ruc on e u a on
-. ,
- - - -
- , - - κ- - -
- - - - - - -
. . .
u n cate or : n ustr a are ouse
,
n s ances rom e u n ne: m
,
.
. ,
. ,
e
-
8/19/2019 Logistics Conceptual Design
28/57
- . .
: . :
.. .. . .
"as c aws or nv ronmen
rotect on .
.
.
ommon n s era ecs on nrommon n ster a ec s on nr - -
. . .
o o ra c a ram
overa e a ram –
ron ews
ect on ews
ruc ura es n nec a oun at on
c ve re- ro ec on u
as ue u
. . .
-
8/19/2019 Logistics Conceptual Design
29/57
- . .
: . :
.. .. . .
ro uc a e or
asse
-
,
,
,
-
8/19/2019 Logistics Conceptual Design
30/57
TITLE:801-AA10.01/08./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK MOVEMENT DB 2009 - "MANDRA"/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
8.STORAGE SYSTEM - BACK TO BACK - REACH TRUCK
BackBack to
Zr Zp
Ast(n)
Zr Zp
x y
Ast
Ast(n)
DETAILS SHELVES - [X AXIS] DETAILS SHELVES - [Z AXIS]Margin
BACK TO BACK - Reach Truck
zh Drive
in (4%) zh Plts
Thickness
of Beam
Need
Height
Level of
Pallet
BACK TO BACK - Reach Truck
Width Palette [Xp] mm 1,200 EUROPALLETE mm
Overflow pallet [x] mm 0 0 11,600 mm
[z5h] levels 5 1,800 3 00 100 2,200 9,400 mm
Module Block [mx] m 1.2 [z4h] levels 4 1,800 2 00 150 2,150 7,250 mm
[z3h] levels 3 2,000 2 00 150 2,350 4,900 mm
DETAILS SHELVES - [Y AXIS] [z2h] levels 2 2,100 2 00 150 2,450 2,450 mm
Euro-Ind [z1h] levels 1 2,100 200 150 2,450 0 mm
Length Palette [Yp] mm 800 Levels stacking pallets [z] PLTS 5
Distance between pallets [d] mm 100
Height Shelves [Zr] mm 11,600
Module Block m m 2.800 Hei ht of last Pallet Z mml l . i l ll ,
SHELVES MODULE
Depth of a Block [x] Plts 6 2 2 2 2 4 4 4 4 6 6 6 6 8 8 8 8
Bays - Block [y] bay 10 8 9 10 11 8 9 10 11 8 9 10 11 8 9 10 11
Width Shelves [Xr] m 7 2 2 2 2 5 5 5 5 7 7 7 7 10 10 10 10 O B
A C K
Length Shelves [Yr] m 28 22 25 28 31 22 25 28 31 22 25 28 31 22 25 28 31
Repeatability of Module 2
Plts / Bay 3
ACCESS TO AISLE
Front Access 6 0 1
B A C K
T
Dimension [Χδ1] m 2.80 Aisle Reach Truck
Dimension [Χδ2] m 0.000
Dimension [Y2] m 3.400
MARGINS FROM THE WALLS 3 2
[Χc] m 0.200
[ Υc] m 0.300
CHARACTERISTICS DATA MODULE
-
8/19/2019 Logistics Conceptual Design
31/57
TITLE:801-AA10.01/09./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
9.STORAGE SYSTEM - BACK TO BACK - VNA
BackBack to
Zr Zp
Ast(n)
Zr Zp
x y
Ast
Ast(n)
DETAILS SHELVES - [X AXIS] DETAILS SHELVES - [Z AXIS]BACK TO BACK - Reach Truck
zh Drive
in (4%) zh Plts
Thickness
of Beam
Need
Height
Level of
Pallet
BACK TO BACK - VNA
Margin
Width Palette [Xp] mm 1,200 EUROPALLETE mm
Overflow pallet [x] mm 0 0 11,600 mm
[z5h] l eve ls 5 1,800 3 00 100 2,200 9,400 mm
Module Block [mx] m 1.2 [z4h] l eve ls 4 1,800 2 00 150 2,150 7,250 mm
[z3h] l eve ls 3 2,000 2 00 150 2,350 4,900 mm
DETAILS SHELVES - [Y AXIS] [z2h] l eve ls 2 2,100 2 00 150 2,450 2,450 mm
Euro-Ind [z1h] l eve ls 1 2,100 200 150 2,450 0 mm
Length Palette [Yp] mm 800 Levels stacking pallets [z] PLTS 5
Distance between pallets [d] mm 100
Height Shelves [Zr] mm 11,600
Module Block [my] m 2.800 Height of last Pallet [Zp] mm 9 500l l i l ll ,
SHELVES MODULE
Depth of a Block [x] Plts 8 2 2 2 2 4 4 4 4 6 6 6 6 8 8 8 8
Bays - Block [y] bay 9 8 9 10 11 8 9 10 11 8 9 10 11 8 9 10 11
Width Shelves [Xr] m 10 2 2 2 2 5 5 5 5 7 7 7 7 10 10 10 10
l O B
A C K
Length Shelves [Yr] m 25 22 25 28 31 22 25 28 31 22 25 28 31 22 25 28 31
Repeatability of Module 2
Plts / Bay 3
ACCESS TO AISLE
Front Access 8 0 1
B A C K
Dimension [Χδ1] m 1.80 Aisle Reach Truck
Dimension [Χδ2] m 0.000
Dimension [Y2] m 3.400
MARGINS FROM THE WALLS 3 2
[Χc] m 0.200
c m .
CHARACTERISTICS DATA MODULE
TITLE 801 AA1001/10 /PROJECTREQUIREMENTSANALYSIS/CONTENTS /LEAD DESIGNER MANOLAS I /DATE 23/1/2013
-
8/19/2019 Logistics Conceptual Design
32/57
TITLE:801-AA10.01/10./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
10.STORAGE SYSTEM - DRIVE INΧθ
ΧcΧr
Yc1
Χδ
a d i n g
a d i n g
Yr Υθ
r C o l l e c t i o n
& L
o a d i n
r C o l l e c t i o n
& L
o a d i n
C o r r i d o r C o l
C o r r i d o r C o l
Yc2
ΥδΒδ
- -
y
x
Υδ
Χε
DETAILS SHELVES - [X AXIS] DETAILS SHELVES - [Z AXIS]
Width Palette [Xp] mm 800 EUROPALLETE
Overflow pallet [x] mm 40
[z5h] levels 5 2,100 3 00 100 2,500 9,800 mm
-
zh Drive
in (4%) zh Plts
Thickness
of Beam
Need
Height
Level of
Pallet
-
Margin
, ,
Module Block [mx] m 0.84 [z4h] levels 4 2,100 2 00 150 2,450 7,350 mm
[z3h] levels 3 2,100 2 00 150 2,450 4,900 mm
DETAILS SHELVES - [Y AXIS] [z2h] levels 2 2,100 2 00 150 2,450 2,450 mm
Euro-Ind [z1h] levels 1 2,100 200 150 2,450 0 mm
Width Palette [Yp] mm 1,200 Levels stacking pallets [z] PLTS 5
i mmi
Overflow pallet [YD2] mm 75 Height Shelves [Zr] mm 12,300
Module Block [my] m 1.510 Height of last Pallet [Zp] mm 11,900
SHELVES MODULE
Bays - Block [y] Plts 24 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
l lDepth of a Block [x] Plts 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Length Shelves [Yr] m 36.24 15 17 18 20 21 23 24 26 27 29 30 32 33 35 36 38
Width Shelves [Xr] m 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
Repeatability of Module 2
Plts / Bay 1
B A C K
T O B
A C K
ACCESS TO AISLE
Front Access 2 1 0
Dimension [Χδ] m 3.400 Aisle Reach Truck
Dimension [Yδ] m 3.400
4 2 [Χc] m 0.200
[Υc] m 0 300
TITLE:801-AA10 01/11 /PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I /DATE:23/1/2013
-
8/19/2019 Logistics Conceptual Design
33/57
TITLE:801 AA10.01/11./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:/LEAD DESIGNER:MANOLAS I. /DATE:23/1/2013
11.STORAGE SYSTEM LIVE STORAGE & BACK TO BACK
xc xb xδ1 xr1 xδ2 xr2 xδ1 xb xc
yc1
xθ
to BackBack
d
C o r r i d o
C o l l e c t i o n
yr yθ
C o l l e c t i o n
xy
AstAst(n)
d2 d3d1
L o
C o r
r i d o r
C o r
r i d o r
LIVE STORAGE
Ζ4
Ζ5Α
ΖpΖr Ζ3
Ζ2
y
x
y2
yc2Ast
Ast(n)
dd2 d3d1
yΑ
x
Ζ1
DETAILS SHELVES - [X AXIS] DETAILS SHELVES - [Z AXIS]
LIVE STORAGE - Reach Truck LIVE STORAGE - Reach Truck
Level of
Pallet
zh Drive
in (4%)zh Plt s Margin
Thickness
of Beam
Need
Height
Width Palette [Xp] mm 1,200 EUROPALLETE
Overflow pallet [x] mm 53
[z5h] levels 5 2,100 200 0 2,300 10,339 mm
Module Block [mx] m 1.25 [z4h] levels 4 2,100 2 00 150 2,450 7,889 mm
[z3h] levels 3 2,100 2 00 150 2,450 5,439 mm
DETAILS SHELVES - [Y AXIS] [z2h] levels 2 2,100 2 00 150 2,450 2,989 mm
[z1h] levels 1 539 2,100 200 150 2,989 0 mm
Length Palette [Yp] mm 800 EUROPALLETE Levels stacking pallets [z] PLTS 5
Distance between pallets [d] mm 100
Height Shelves [Zr] mm 12,639
Module Block [my] m 2.000 Height of last Pallet [Zp] mm 12,439
DETAILS SHELVES - [X AXIS] DETAILS SHELVES - [Z AXIS]
Width Palette [Xp] mm 1,200
EUROPALLETE
BACK TO BACK - Reach Truck
zh Drive
in (4%)
BACK TO BACK - Reach Truck
zh Plt s MarginThickness
of Beam
Need
Height
Level of
Pallet
[z5h] levels 5 1,700 0 100 1,800 8,200 mm
Module Block [mx] m 1 [z4h] levels 4 1,700 2 00 150 2,050 6,150 mm
[z3h] levels 3 1,700 2 00 150 2,050 4,100 mm
DETAILS SHELVES - [Y AXIS] [z2h] levels 2 1,700 2 00 150 2,050 2,050 mm
Euro-Ind [z1h] levels 1 1,700 200 150 2,050 0 mm
Length Palette [Yp] mm 800 Levels stacking pallets [z] plts 5
Distance between pallets [d] mm 100
Height Shelves [Zr] mm 10,000
-
8/19/2019 Logistics Conceptual Design
34/57
-
8/19/2019 Logistics Conceptual Design
35/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
12.STOCK DATA - TRANSPORT INTERNATIONAL12.1.RECEIPT VOLUMES
Qdty Vol. Weight
TYPE Quantity 1 Quantity 2 Quantity 3 Volume Gross
Weight
Total
Packaging
14% 5% 4%
7% 2% 2%
7% 38% 42%24,064 770 11 45,006 10,466,250 24,845
2 2,372 501,201 24,328
,
44,557 467 2 6,403 45,026
PLTS
BOX 977,709
ROL
, , , ,
24,249 77
1% 0% 0%
0% 0% 0%
0% 0% 0%270 1 0 358 101,632 271
304 1 0 123 58,161 305
1,636 108 18 347 84,381 1,762
, , ,
BUNDLE
BARREL
ITEM
0% 1% 1%
0% 0% 0%
0% 0% 0%
0% 0% 0%3 10 0 1 200 13
6 1 0 306 53,510 7
12 0 0 1 316 12
40 0 0 1,640 276,210 40
, ,
BOX 2
POT
BULK
BAG
0% 0% 0%
0% 0% 0%
0% 0% 0%
100% 100% 100%332,86724,816,007119,810330,616 2,091 160
1 0 0 0 13 1
1 0 0 0 100 1
3 0 0 2 328 3
PARCEL 2
TOTAL
BOX OF WOOD
PARCEL
max PICK FACES
.
BULK 93% 62% 58%
PLTS 7% 38% 42%
Medium Weight Palette (Kg/ Plts)
Number of Pallet (Plts/ Yard)
421
24,845
Ratios Pallet
Average Pallet Height (m)
Pallet Average Volume (m3 / Plts)
1.81
1.74
-
8/19/2019 Logistics Conceptual Design
36/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
12.STOCK DATA - TRANSPORT INTERNATIONALTransformation Packages
Qdty Vol. Weight
69% 50% 46%
14% 5% 4%
2% 0% 0%CARTON 6 745 30 65 576 87 926 6 840
45,026BOX 44,557 467 2 6,403 977,709
Packaging
COLA 228,669 625 62 60,394 11,490,425 229,356
TYPE Quantity 1 Quantity 2 Quantity 3 Volume
Weight
1% 0% 0%
0% 0% 0%
0% 2% 3%
0% 1% 1%40BOX 2 40 0 0 1,640 276,210
271
CONTAINER 56 1 0 2,280 717,645 57
BUNDLE 270 1 0 358 101,632
1,762ITEM 1,636 108 18 347 84,381
, , ,
0% 0% 0%
0% 0% 0%
0% 0% 0%
0% 0% 0%3BOX OF WOOD 3 0 0 2 328
7
BAG 3 10 0 1 200 13
BULK 6 1 0 306 53,510
POT 12 0 0 1 316 12
0% 0% 0%
0% 0% 0%
85% 60% 56%
1
TOTAL 281,999 1,243 147 72,308 13,790,395 283,389
PARCEL 2 1 0 0 0 13
PARCEL 1 0 0 0 100 1
Avg Box / Plts
Avg in Plts
6
47,232
Avg Weight / Plts
Average Pallet Height (m)
Pallet Average Volume (m3 / Plts)
292
1.53
1.47
-
8/19/2019 Logistics Conceptual Design
37/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
13.CALCULATION OF REQUIRED SPACE13.1.RECEIVING - LODGING (RL) & DOCK LEVELLERS (DL)13.1.1.INVENTORY & ACTIVITY RATIOS
EUROPALLET 1,20 X 0,80
UNLOADING PLTS - TR.INTERNATIONAL UNLOADING BULK - TR.INTERNATIONAL
PALLETS
handling (number of workers) 3 3Number of Plts 32 28
Unloading Avg 32 Plts 15 60min
MHE : Pallet Trucks Hand pallet trucks & Pallet Trucks
Unloading Area / Plts 2,0 2,5m2 / Plts
Stockholding in location RL 30 30Stock transfer time in location STOCK 30,0 30,0
minmin
2,34 4,29 Tt - Type 2min/PLTSUnloading - Receiving - Put Away in Stock
Location (Tt - Type 1)
Total working time / day 8 8
Shifts / day 1 1
Days / Week 6 6
Unloading Time / Day 8 8Hours
Shifts
Days
Hours
13.1.2.INVENTORY UNLOADING DATA
Day Plts RL -m2 RL - h
Effective
use of
space
(m2/h)
DateNb of
Trucks IN
Nb of
distribution
truck
Nb of Docks Total PltsPlts - Bulk
Thu 0
Fri 22
Sat 18
4 44
7 54 2 25
0 0
0
0
-
2-Jan 4 16 12
3-Jan 1 5 7
22 99
0 0 0 01-Jan 00
Mon 5 3 18 1 85-Jan 1 5 0 2
-
8/19/2019 Logistics Conceptual Design
38/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
13.CALCULATION OF REQUIRED SPACE
50
Chart: number of vehicles unloading / Day
40
20
30
0
10
1 / 1
1 5 / 1
2 9 / 1
1 2 /
2 6 /
1 1 /
2 5 /
8 /
2 2 /
6 /
2 0 /
3 /
1 7 /
1 /
1 5 /
2 9 /
1 2 /
2 6 /
9 /
2 3 /
7 / 1
2 1 / 1
4 / 1 1
1 8 / 1 1
2 / 1
1 6 / 1
3 0 / 1
Chart: Plts Unloading / Day
400
500
200
300
100
0
1 / 1
1 5 / 1
2 9 / 1
1 2 / 2
2 6 / 2
1 1 / 3
2 5 / 3
8 / 4
2 2 / 4
6 / 5
2 0 / 5
3 / 6
1 7 / 6
1 / 7
1 5 / 7
2 9 / 7
1 2 / 8
2 6 / 8
9 / 9
2 3 / 9
7 / 1 0
2 1 / 1 0
4 / 1 1
1 8 / 1 1
2 / 1 2
1 6 / 1 2
3 0 / 1 2
800
1.000Chart: Plts "Bulk" Unloading / Day
-
8/19/2019 Logistics Conceptual Design
39/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
13.CALCULATION OF REQUIRED SPACE
1.200Chart: Total Plts Unloading / Day
800
1.000
600
200
1 / 1
1 5 / 1
2 9 / 1
1 2 / 2
2 6 / 2
1 1 / 3
2 5 / 3
8 / 4
2 2 / 4
6 / 5
2 0 / 5
3 / 6
1 7 / 6
1 / 7
1 5 / 7
2 9 / 7
1 2 / 8
2 6 / 8
9 / 9
2 3 / 9
7 / 1 0
2 1 / 1 0
4 / 1 1
1 8 / 1 1
2 / 1 2
1 6 / 1 2
3 0 / 1 2
4%
Day
Mon
Nb of
Trucks INPlts Plts - Bulk
141 784 1.458
Nb of
Trucks IN
5%
Total Plts
2.242
6%
8%
12%
62%
3.608
1.720 3.219 4.939
3.110 4.630 7.740
13.353 25.615 38.968
8%
9%
14%
60%
Tue
Wed
Thu
Fri
236
271
429
1.785
1.399 2.209
8%825 4.104 4.929
Total 2.990 21.191 41.235 62.426
4% Sat 128
1.500
2.000ar : o ruc s ay
500
1.000
0
-
8/19/2019 Logistics Conceptual Design
40/57
TITLE:801-AA10.01/12./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL ANALYSIS / PERIOD /LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
13.CALCULATION OF REQUIRED SPACE15
Chart: Nb of Dock Unlloading / Day
9
12
6
0
3
1 / 1
8 / 1
5 / 1
2 / 1
9 / 1
5 / 2
2 / 2
9 / 2
6 / 2
4 / 3
1 / 3
8 / 3
5 / 3
1 / 4
8 / 4
5 / 4
2 / 4
9 / 4
6 / 5
3 / 5
0 / 5
7 / 5
3 / 6
0 / 6
7 / 6
4 / 6
1 / 7
8 / 7
5 / 7
2 / 7
9 / 7
5 / 8
2 / 8
9 / 8
6 / 8
2 / 9
9 / 9
6 / 9
3 / 9
0 / 9
/ 1 0
/ 1 0
/ 1 0
/ 1 0
/ 1 1
/ 1 1
/ 1 1
/ 1 1
/ 1 2
/ 1 2
/ 1 2
/ 1 2
/ 1 2
1 2 2 1 1 2 1 1 2 1 2 2 1 2 2 1 1 2 1 2 2 1 1 2 1 2 3 7 1 4
2 1
2 8 4
1 1
1 8
2 5 2 9
1 6
2 3
3 0
500Effective use of space (m2/h) / Day
400
200
300
0
100
1 / 1
1 5 / 1
2 9 / 1
1 2 / 2
2 6 / 2
1 1 / 3
2 5 / 3
8 /
2 2 /
6 / 5
2 0 / 5
3 / 6
1 7 / 6
1 / 7
1 5 / 7
2 9 / 7
1 2 / 8
2 6 / 8
9 / 9
2 3 / 9
7 / 1 0
2 1 / 1 0
4 / 1 1
1 8 / 1 1
2 / 1 2
1 6 / 1 2
3 0 / 1 2
-
8/19/2019 Logistics Conceptual Design
41/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
14.STOCK DATA - TRANSPORT INTERNATIONAL14.1.DISPATCH VOLUMES
Qdty Vol. Weight
TYPE Quantity 1 Quantity 2 Quantity 3 Volume Gross
Weight
Total
Packaging
14% 28% 20%
4% 1% 1%
2% 33% 42%
ITEM
COLA
PLTS
33.161
16.765 0 0 40.166 7.886.989 16.765
33.161 0 0 1.045 142.463
.
131.951 0 0 33.711 3.733.578 131.951
. . . .
0% 0% 1%
0% 0% 0%
0% 0% 0%BARREL 2
BUNDLE
BOX
1.949
304 0 0 127 10.665 304
1.949 0 0 127 14.902
.
3.806 0 0 601 102.995 3.806
. . .
0% 0% 0%
0% 0% 0%
0% 1% 1%
0% 0% 0%BULK
PARCEL
CONTAINER
20
1 0 0 75 5.925 1
20 0 0 617 247.964
24 0 0 6 1.091 24
BARREL 1 61 0 0 45 12.852 61
.
100% 100% 100%927.419
max PICK FACES
TOTAL 927.419 0 0 122.582 18.706.731
Qdty Vol. Weight
BULK 98% 67% 58%
PLTS 2% 33% 42%
Medium Weight Palette (Kg/ Plts)
Number of Pallet (Plts/ Yard)
Ratios Pallet470
16.765
Average Pallet Height (m)
Pallet Average Volume (m3 / Plts) 2,40
2,50
Qdty Vol. WeightGross
Weight
Total
PackagingTYPE Quantity 1 Quantity 2 Quantity 3 Volume
Transformation Packages
1% 1% 2%61BARREL 1 61 0 0 45 12 852
. . . .
-
8/19/2019 Logistics Conceptual Design
42/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
14.STOCK DATA - TRANSPORT INTERNATIONAL
Qdty Vol. WeightTYPE Quantity 1 Quantity 2 Quantity 3 Volume Gross
Wei ht
Total
Packa in
81% 53% 57%
15% 43% 37%
4% 1% 1%
0% 1% 1%BOX 3.806 0 0 601 102.995 3.806
33.161ITEM 33.161 0 0 1.045 142.463
729.432
COLA 131.951 0 0 33.711 3.733.578 131.951
CARTON 729.432 0 0 41.846 5.798.845
0% 0% 0%
0% 0% 0%0% 0% 1%
0% 0% 0%24CONTAINER 24 0 0 6 1.091
141BOX OF WOOD 141 0 0 244 63.531
1.949
BARREL 2 304 0 0 127 10.665 304
BUNDLE 1.949 0 0 127 14.902
0% 1% 2%
0% 0% 0%
100% 100% 100%
1
TOTAL 900.789 0 0 78.398 10.121.960 900.789
BULK 1 0 0 75 5.925
PARCEL 20 0 0 617 247.964 20
Avg Box / Plts
Avg out Plts
26
34.646
Avg Weight / Plts
Average Pallet Height (m)
Pallet Average Volume (m3 / Plts)
292
2,36
2,26
-
8/19/2019 Logistics Conceptual Design
43/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
15.CALCULATION OF REQUIRED SPACE15.1.RECEIVING - LODGING (RL) & DOCK LEVELLERS (DL)15.1.1.INVENTORY & ACTIVITY RATIOS
EUROPALLET 1,20 X 0,80PALLETS
LOADING PLTS - TR.INTERNATIONAL LOADING BULK - TR.INTERNATIONAL
handling (number of workers) 3 3Number of Plts 32 28
Unloading Avg 32 Plts 15 60min
MHE : Pallet Trucks Hand pallet trucks & Pallet Trucks
Unloading Area / Plts 2,0 2,5m2 / Plts
Stockholding in location RL 30 30Stock transfer time in location STOCK 30,0 30,0
minmin
2,34 4,29 Tt - Type 2Unloading - Receiving - Put Away in Stock
Location (Tt - Type 1)min/PLTS
Total working time / day 8 8
Shifts / day 1 1
Days / Week 6 6
Unloading Time / Day 4 4
Hours
Shifts
Days
Hours
13.1.2.INVENTORY UNLOADING DATA
Day Plts Nb of Docks
Effective
use of
space
(m2/h)
Total PltsDateNb of
Trucks OUT
Nb of
distribution
truck
Plts - Bulk RL -m2 RL - h
Thu
Fri 1
Sat
-
121
3-Jan 0 0 0 0 0
0 0
2-Jan 10 28 120 302 12 3 76
1-Jan 0 0 0
Mon 21 345-Jan 1 1 34 85 3 1
-
8/19/2019 Logistics Conceptual Design
44/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
15.CALCULATION OF REQUIRED SPACE
60
Chart: number of vehicles Loading / Day
40
50
20
30
0
10
1 1 1 1 1 1 1 1 1
1 /
8 /
1 5 /
2 2 /
2 9 /
5 /
1 2 /
1 9 /
2 6 /
4 /
1 1 /
1 8 /
2 5 /
1 /
8 /
1 5 /
2 2 /
2 9 /
6 /
1 3 /
2 0 /
2 7 /
3 /
1 0 /
1 7 /
2 4 /
1 /
8 /
1 5 /
2 2 /
2 9 /
5 /
1 2 /
1 9 /
2 6 /
2 /
9 /
1 6 /
2 3 /
3 0 /
7 / 1
1 4 / 1
2 1 / 1
2 8 / 1
4 / 1
1 1 / 1
1 8 / 1
2 5 / 1
2 / 1
9 / 1
1 6 / 1
2 3 / 1
3 0 / 1
Chart: Plts Loading / Day
400
500
200
300
100
0
1 / 1
8 / 1
1 5 / 1
2 2 / 1
2 9 / 1
5 / 2
1 2 / 2
1 9 / 2
2 6 / 2
4 / 3
1 1 / 3
1 8 / 3
2 5 / 3
1 / 4
8 / 4
1 5 / 4
2 2 / 4
2 9 / 4
6 / 5
1 3 / 5
2 0 / 5
2 7 / 5
3 / 6
1 0 / 6
1 7 / 6
2 4 / 6
1 / 7
8 / 7
1 5 / 7
2 2 / 7
2 9 / 7
5 / 8
1 2 / 8
1 9 / 8
2 6 / 8
2 / 9
9 / 9
1 6 / 9
2 3 / 9
3 0 / 9
7 / 1 0
1 4 / 1 0
2 1 / 1 0
2 8 / 1 0
4 / 1 1
1 1 / 1 1
1 8 / 1 1
2 5 / 1 1
2 / 1 2
9 / 1 2
1 6 / 1 2
2 3 / 1 2
3 0 / 1 2
" "
800
1.000
600
-
8/19/2019 Logistics Conceptual Design
45/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
15.CALCULATION OF REQUIRED SPACE
1.200
Chart: Total Plts Loading / Day
800
1.000
400
600
0
200
1 1 1 2 2 3 3 4 5 5 6 6 7 7 7 8 8 9 9 0 0 1 1 2 2 2
1 /
1 5 /
2 9 /
1 2 /
2 6 /
1 1 /
2 5 /
8 /
2 2 /
6 /
2 0 /
3 /
1 7 /
1 /
1 5 /
2 9 /
1 2 /
2 6 /
9 /
2 3 /
7 / 1
2 1 / 1
4 / 1
1 8 / 1
2 / 1
1 6 / 1
3 0 / 1
4%4% Mon 128 1.011 1.507 2.518
Nb of
Trucks INDay Nb of Trucks IN Plts Plts - Bulk Total Plts
8%
14%
11%
57%58% Fri 2.046 10.082 23.609 33.691
9% Thu 326 2.864 3.794 6.658
13% Wed 458 2.059 5.978 8.037
9% Tue 304 1.830 2.771 4.601
6%
1%353
Total 3.528 19.354 39.875 59.229
2% Sun 55 11 342
6% Sat 211 1.497 1.874 3.371
2.000
Chart: Nb of Trucks OUT / Day
1.000
1.500
500
-
8/19/2019 Logistics Conceptual Design
46/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
15.CALCULATION OF REQUIRED SPACE
25
Chart: Nb of Dock Loading / Day
20
10
15
0
5
1 / 1
8 / 1
1 5 / 1
2 2 / 1
2 9 / 1
5 / 2
1 2 / 2
1 9 / 2
2 6 / 2
4 / 3
1 1 / 3
1 8 / 3
2 5 / 3
1 /
8 /
1 5 /
2 2 /
2 9 /
6 / 5
1 3 / 5
2 0 / 5
2 7 / 5
3 / 6
1 0 / 6
1 7 / 6
2 4 / 6
1 / 7
8 / 7
1 5 / 7
2 2 / 7
2 9 / 7
5 / 8
1 2 / 8
1 9 / 8
2 6 / 8
2 / 9
9 / 9
1 6 / 9
2 3 / 9
3 0 / 9
7 / 1 0
1 4 / 1 0
2 1 / 1 0
2 8 / 1 0
4 / 1 1
1 1 / 1 1
1 8 / 1 1
2 5 / 1 1
2 / 1 2
9 / 1 2
1 6 / 1 2
2 3 / 1 2
3 0 / 1 2
600
Effective use of space (m2/h) / Day
400
500
200
300
0
100
1 / 1
8 / 1
1 5 / 1
2 2 / 1
2 9 / 1
5 /
1 2 /
1 9 /
2 6 /
4 /
1 1 /
1 8 /
2 5 /
1 /
8 /
1 5 /
2 2 /
2 9 /
6 /
1 3 /
2 0 /
2 7 /
3 /
1 0 /
1 7 /
2 4 /
1 /
8 /
1 5 /
2 2 /
2 9 /
5 /
1 2 /
1 9 /
2 6 /
2 /
9 /
1 6 /
2 3 /
3 0 /
7 / 1
1 4 / 1
2 1 / 1
2 8 / 1
4 / 1 1
1 1 / 1 1
1 8 / 1 1
2 5 / 1 1
2 / 1
9 / 1
1 6 / 1
2 3 / 1
3 0 / 1
-
8/19/2019 Logistics Conceptual Design
47/57
TITLE:801-AA10.01/14./PROJECT REQUIREMENTS ANALYSIS/CONTENTS:STOCK LEVEL 1/1/2010 - "MANDRA"/LEAD
DESIGNER:MANOLAS I. /DATE:23/1/2013
16.CALCULATION OF REQUIRED SPACE16.1.RECEIVING - LODGING (RL) & DOCK LEVELLERS (DL)16.1.1.INVENTORY & ACTIVITY RATIOS
EUROPALLET 1,20 X 0,80PALLETS
UNLOADING & LOADING PLTS - UNLOADING & LOADING BULK -
handling (number of workers) 3 3
Number of Plts 32 32
. .
Unloading Avg 32 Plts 15 60
MHE : Pallet Trucks Hand pallet trucks & Pallet Trucks
min
Unloading Area / Plts 2,0 2,5
Stockholding in location RL 30 30
m2 / Plts
min
Stock transfer time in location STOCK 30,0 30,0
2,34 3,75 Tt - Type 2
min
Unloading - Receiving - Put Away in Stock
Location (Tt - Type 1)min/PLTS
Total working time / day 8 8
Shifts / day 1 1
Days / Week 6 6
Hours
Shifts
DaysUnloading Time / Day 8 8
16.1.2.INVENTORY UNLOADING & LOADING DATA
Hours
Day Plts Nb of Docks
Effective
use of
s aceTotal PltsDate
Nb of
Trucks OUT
Nb of
distribution Plts - Bulk RL -m2 RL - h
Thu
Fri 23
(m2/h)
1-Jan
ruc
212
-
0 0
2-Jan 14 44 189 519 20 3 65
Sun 0 04-Jan
-
8/19/2019 Logistics Conceptual Design
48/57
TITLE:801-AA10.01/14./PROJECT REQUIREMEN