7/26/2019 Long Lead ItemS List http://slidepdf.com/reader/full/long-lead-items-list 1/20  KING ABDULAZIZ INTERNATIONAL AIRPORT D EVELOPMENT P ROJECT  (KAIA) CONTRACT: J-10-421-PF-00 To the Construction Manager: DAR AL HANDASAH (DAR) Document Type DOCUMENT SUBMITTAL Document No. 421-DCS-SPC-32002-R0 Document Title: EFPS-AMAN/DMAN System Long Lead Item List Date: 31 st  January 2013

Upload: arjunchandroth

Post on 02-Mar-2018

227 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 1/20

 

KING ABDULAZIZ INTERNATIONAL AIRPORT 

DEVELOPMENT PROJECT (KAIA)

CONTRACT:

J-10-421-PF-00 

To the Construction Manager:

DAR AL HANDASAH (DAR)

Document Type

DOCUMENT SUBMITTAL 

Document No.

421-DCS-SPC-32002-R0

Document Title:

EFPS-AMAN/DMAN System Long Lead Item List

Date: 31st

 January 2013

Page 2: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 2/20

 

AviBit GmbH 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  2/20

 AviBit Document Control

Edition No. 0.1 Draft 

Edition Issue Date 31.01.2013 

Author G. Reiter  

AviBit Reference ICAD-ATM/CDRL-040/LLIL-D0.1 

Copy No.  Stamp here 

Copyright Notice

 © 2012, 2013 AviBit data processing GmbH, Austria

All rights reserved.

No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form orby any means, electronic, mechanical, photocopying, recording or otherwise, without the prior writtenpermission of AviBit.

Page 3: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 3/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 3/20

 Approval Table

AviBit Date Signature ICAD Date Signature

ProjectManager

P. Venton

31.01.2013

QualityManager

T. Leitner

31.01.2013

Document Identification

Full Title: EFPS-AMAN/DMAN System Long Lead Item List

Total Number of Pages: 20

Distribution

COPY No. Role Organisation

1 Primary Contractor ICAD

Edition History

Edition No. Issue Date Author Reason

0.1 31.01.2013 G. Reiter Initial draft

Page 4: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 4/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 4/20

Review Table

Edition No. Review type, scope,depth & focus

Reviewers Date Conclusion

0.1 Complete Document P. Venton 31 Jan 2013 OK

System Release

System Release: Edition No.:

TBP

Page 5: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 5/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 5/20

Table of Contents

1.  Scope ....................................................................................................................... 7 

1.1.  Identification ................................................................................................................... 7 

1.2.  Purpose of this Document ............................................................................................. 7 

2.  Introduction ............................................................................................................. 8 

3.  Long Lead Item List ................................................................................................ 9 

4.  S YSTEM DESCRIPTION ............................................................................................... 10 

5.  COMPLIANCE STATEMENTS........................................................................................ 11 

6.  MATERIAL LIST  ......................................................................................................... 13 

7.  DATA SHEETS........................................................................................................... 15 

8.  TEST CERTIFICATES  .................................................................................................. 16 

9.  SPARE PARTS  .......................................................................................................... 17 

10.  Appendix A: ACRONYMS ................................................................................... 19 

Page 6: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 6/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 6/20

List of Tables

Table 1  – Aerodrome System Deployment ............................................................................................... 7 

Page 7: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 7/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 7/20

1. SCOPE

1.1. IDENTIFICATIONThis document describes the Long Lead Item List used for the ICAD New Jeddah Tower Project.

King Abdulaziz International Airport (KAIA) is expanding its runway and passenger capability. To facilitatethis expansion, a new Air Traffic Control Tower (ATCT), a new West Support Tower, a new passengerterminal, transport facilities and support buildings will be constructed.

The new airport will initially support up to 30 million passengers per year, growing to 45 million in the firstfew years to an eventual capacity of 80 million passengers per year.

The expansion creates a need to extend and add to the Air Traffic Management Systems in order toprovide safe and efficient air traffic control services as the volume of air traffic increases.

These systems will be fully integrated giving users access to timely, accurate and consistent information

as and when needed as well as the control functions necessary for reliable and effective management ofair operations.

This project foresees deployment for the AviBit systems shown in the following table at KAIA in Jeddah:

Aerodrome System to be delivered

KAIA JeddahDIFLIS®;

 AMAN/DMAN;

Table 1 – Aerodrome System Deployment

1.2. PURPOSE OF THIS DOCUMENT

This document identifies those items that should be ordered before the provisioning conference and thesubsequent spares order, because of the extensive production lead time.

Page 8: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 8/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 8/20

2. INTRODUCTION

The Long Lead Item List (LLIL) is provided to identify those recommended spare items that, because ofextensive production lead time, should be ordered before the provisioning conference and thesubsequent selected spares order. An item qualifies as "long lead" if its production lead time is more thanone year.

Page 9: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 9/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 9/20

3. LONG LEAD ITEM LIST

None of the system parts used by AviBit are considered long lead items. All production lead times areless than one year.

Page 10: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 10/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 10/20

4. SYSTEM DESCRIPTIONNOT APPLICABLE FOR THIS DOCUMENT

Page 11: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 11/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List 11/20

5. COMPLIANCESTATEMENTS

NOT APPLICABLE FOR THIS DOCUMENT

Page 12: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 12/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  12/20 

Material Compliance with Project Specifications

Submittal Title: Rev. No. Facility Code:

Sub-Contractor: Area of Application:

Project Specifications Material SpecificationsCompliance

RemarksSpecifications

SpecificationsStandard

ReferenceSpecifications

Standard

ReferenceNo. Clause Supplier Contractor

Page 13: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 13/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  13/20 

6. MATERIAL LISTNOT APPLICABLE FOR THIS DOCUMENT

Page 14: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 14/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  14/20 

Sr.# Product Number Product Description

Sub-Header

Sub-Header

Page 15: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 15/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  15/20 

7. DATA SHEETSNOT APPLICABLE FOR THIS DOCUMENT

Page 16: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 16/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  16/20 

8. TEST CERTIFICATESNOT APPLICABLE FOR THIS DOCUMENT

Page 17: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 17/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  17/20 

9. SPARE PARTSNOT APPLICABLE FOR THIS DOCUMENT

Page 18: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 18/20

The Construction Manager: King Abdulaziz

International Airport

Development Project

(Phase I) Jeddah, KSA 

The Contractor:

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  18/20 

Sr.# Product Number Product Description Qty

Sub-Header

Sub-Header

Page 19: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 19/20

 

421-DCS-SPC-32002-R0

EFPS-AMAN/DMAN System Long Lead Item List  19/20 

10. APPENDIX A: ACRONYMS

Acronym Description

A

 AMAN Arrival Manager

 ATCT Air Traffic Control Tower

 ATM Air Traffic Management

C

CDRL Contract Deliverables Requirements List

D

DAR Dar Al Handasah

DIFLIS Departure Information Flight List System

DMAN Departure Manager

I

ICAD Innovative Contractors for Advanced Dimensions

K

KAIA King Abdul Aziz International Airport

KSA Kingdom of Saudi Arabia

L

LLIL Long Lead Item List

T

TBP To Be Provided

W

Page 20: Long Lead ItemS List

7/26/2019 Long Lead ItemS List

http://slidepdf.com/reader/full/long-lead-items-list 20/20

 

DOCUMENT FINAL PAGE