long term planning
DESCRIPTION
Long Term PlanningTRANSCRIPT
Long term Planning
Long Term Planning is being used for simulation purposed of the planning scenario.
Path:�Logistics�Production�Production Planing�Long Term Planing�
Create Planning Secenario, Used the transaction codes MS31
Filled the time duration for which you want to do the planning.
Filled up the BOM selection ID, this is being used for LTP for individuals long Term BOm Planing
Click on the plant
Add the plant for which the simulation planning is to be done
Save it , now click on the Planned Independent requirement Tab.
Add the required version for which you want to do the planning.
Now releases the planning scenario
Click on “ ”
When you save and released it sysyetm will create the planning file enteries
In long term planning we have to create own version of planning, which are being only used for
These planning Secenario could be deleted also by using the reansaction
For LTP there is being separate planning file enteries
The long term planning file contains all the material which are being present in the operative
planning.
Used the transaction MS64 to copy the requirement.Used the transaction MS65 for viewing the
Requirement for the Secenario
Now used the Transaction MS01, for Simulative MRP running for plant wise.
Used the transaction MS04 for LTP results
In system you could also get simulative planned order. Used the transaction code MS11
Ued the Transaction MS23 to delete the plaining Secenario.MSAb used as Background for
deleting the Planing Secenario.For checking the planning secenario used the transaction
MS32,and MS22 for viewing it
simulative pruposed.For each version of the demand programme , the system calculated
capacity and requirement
During long term planning no activities is being done in operative planning.
Create Planned Independent requirement Version
Various version of the independent requirement is being created .The system used various
version to compare the result
The aim of the long term planning is to check and adjust the planning result created by using
the simulative version of the demand programme. Once you checked the result, the simulative
version may be changed to operative version. It means that version planned in simulative
version is either component operative version or they can entirely replace them within the
specified period.
Customization: in Demand management various inactive version no has to be created. We can
either create a new version of the planned independent requirement or can copy the existing
the planned independent requirement (From operative planning to a simulative version no)