Los Gatos Creek Bridge Replacement Project
Oct 18. 2017
![Page 2: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/2.jpg)
Agenda
I. Project Description
II. Project Benefits
III. Challenges
IV. Construction Update
![Page 3: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/3.jpg)
Project Location Located along Caltrain line
• In the City of San Jose
• Bounded by Park Avenue to the north and Interstate 280 to the south
![Page 4: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/4.jpg)
Los Gatos Creek Bridge • Owned by the Peninsula Corridor Joint Powers Board
• MT1 owned by UPRR Built in 1935 Does not meet existing current seismic safety standards Has structural deficiencies Southern timber span was
damaged by fire Recent Flooding has
caused significant scour
![Page 5: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/5.jpg)
Project Elements • Demolish existing two-track bridge
• Replace existing bridge with three new single track bridges
Meet current safety and seismic codes Include a tail track to maintain rail operations throughout
construction
• Build a Retaining Wall Widen Creek Channel Facilitate City of San Jose future bike trail
![Page 6: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/6.jpg)
Project Benefits
![Page 7: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/7.jpg)
Project Benefits
• Safe rail operations
• Improves operations at the San Jose Diridon Station
• Addition of Tail Track
![Page 8: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/8.jpg)
Construction Challenges
![Page 9: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/9.jpg)
• Phase I • Pre June 1 Work
• Staging, fencing, temporary access roads, signal work, tail track abutment work, and retaining wall work
• Phase II – Dry Season Window • June 2017 – Aug. 2017 – Single Tracking on MT1
• Tail track bridge construction, includes bridge foundation and abutment work, pre-cast superstructure crane-in
• Aug. 2017 – Oct. 2017 – Single Tracking on Tail Track • Existing bridge demolition, new Main Track 1 & 2 bridge
construction and in-creek site mitigation • Phase II -- Post Oct 2017
• Main Track 1 & 2 track and signal work, out-of-creek site mitigation, and site clean-up.
Construction Phases
![Page 10: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/10.jpg)
Construction Staging -- In Creek
![Page 11: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/11.jpg)
Unforeseen Conditions
![Page 12: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/12.jpg)
Water Diversion Creek Water Diversion & Fish Relocation
![Page 13: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/13.jpg)
Limited Access
![Page 14: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/14.jpg)
Construction Status
![Page 15: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/15.jpg)
Progress in Field – Shoofly
![Page 16: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/16.jpg)
Progress in Field – MT 1 and MT2
![Page 17: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/17.jpg)
MT1 Bridge Construction
![Page 18: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/18.jpg)
Building Bents
![Page 19: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/19.jpg)
MT1 and MT2 Bridges
![Page 20: Los Gatos Creek Bridge Replacement Projectand+Minutes/JPB/... · 18/10/2017 · Challenges IV. Construction Update. Project Location Located along Caltrain line • In the City of](https://reader033.vdocument.in/reader033/viewer/2022042114/5e91319c2b59e2517c0d52ff/html5/thumbnails/20.jpg)
Questions