Lost Creek Drive Road Rebuild
Project
Fall 2018
Public Works – Street Division
Public Works – Street Division
Overview
● Why Road Work is Needed
● Reclamation Method
● Project Schedule
● Lane Closures & Delays
● Things to Consider
● Resources Available to You
Public Works – Street Division
Why Road Work is Needed
● Road is in need of repairs due to major base failures
● Normal method is pothole repair
● Soil under Lost Creek Drive is currently not stable
enough for long term pothole patching or standard
overlay
Public Works – Street Division
Method for Reclamation
Public Works – Street Division
Method for Reclamation
● Full depth reclamation with cement
○ Recycle existing roadway
○ Added cement stabilizes road base
● Steps in process
○ Pulverize existing base
○ Mix in-place with water & cement
○ Grade & Compact Base
○ Wet Cure – Strength & Dust
○ Pave
Public Works – Street Division
Project Schedule
● Bid Contract – Complete
○ – Awarded to Armstrong Contractors, LLC
● Construction Schedule
○ – Construction Phases
● Will Take Approximately 15 weeks
● Milling Phase
● Cement (CMRB) Phase
● Paving Phase
Public Works – Street Division
Milling Phase
Public Works – Street Division
Cement Phases
Public Works – Street Division
Paving Phases
Public Works – Street Division
Traffic by Hour in Chestnut Hill
Public Works – Street Division
Lane Closures & Delays
○ The Contractor will enforce traffic control
○ Access to entrances
○ Efforts to control dust
○ Cure period of CMRB “Reclaimed” roadway (Wet Cure)
○ Construction will take place between the hours of 7:30 a.m.-5:30 p.m.,
Monday morning to Friday evening
Public Works – Street Division
Stationary Construction Signs 500’ from Intersections
Flagger and Pilot Cars
● Flaggers and possibly a pilot car will be used during
construction operations to assist with guiding residents
through the construction zone
● Please forgive the delays for these measures/procedures
are in place to provide continuous safe travel to
Chestnut Hill residents within the construction zone
Public Works – Street Division
Public Works – Street Division
Is It Ok To Pave In The Rain?
Considerations
● Weather Restrictions
● Rain
● If Temperature < 55 °F – cannot pave
● Utilities
○ Although utilities are supposed to be marked there is a high probability that
something is underground that is unknown.
○ Not uncommon to have depths above expected levels
● Other Considerations
○ Murphy’s Law
Public Works – Street Division
Social Media
● Posts Will be each Friday at 7:30 p.m.● Facebook
○ Construction status reports weekly
○ Updates on lane shifts and progress
● www.facebook.com/COCPublicWorks● Twitter
○ Construction status reports weekly
○ Updates on lane shifts and progress
● www.twitter.com/COCPublicWorks
Public Works – Street Division
#LostCreekPaving
WWW.Columbia.SC.Gov/Engineering
Questions
Public Works – Street Division
Fall 2018