Visit PortTalk.ca 1 September 2012 Small Group Meetings Low Level Road Project Community Consultation

Upload: dinhque

Post on 20-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Visit PortTalk.ca 1

September 2012

Small Group Meetings

Low Level Road Project

Community Consultation

Visit PortTalk.ca 2

Meeting Agenda

Task Timing

Welcome

•  Agenda Review

•  Introductions

10 minutes

Presentation and Discussion Guide

Review

30 minutes

Questions & Answers 50 minutes

Feedback Form 20 minutes

Closing Remarks 10 minutes

Workshop Ends 8 p.m.

Visit PortTalk.ca 3

A Staged Approach to Consultation and Design

Visit PortTalk.ca 4

Current Project Design

Visit PortTalk.ca 5

Consultation & Information Topics

Landscaping

Viewpoints

Noise Walls

Public Art

Spirit Trail

Traffic Management

Retaining Walls

Lighting

Visit PortTalk.ca 6

Section: St. Georges to St. Patricks

Please refer to pages 9 – 12 of your Discussion Guide

Visit PortTalk.ca 7

Section: St. Patricks to St. Davids

Please refer to pages 13 – 16 of your Discussion Guide

Visit PortTalk.ca 8

Section: St. Davids to Moody Avenue

Please refer to pages 17 – 20 of your Discussion Guide

Visit PortTalk.ca 9

Section: Moodyville Park

Please refer to pages 21 - 24 of your Discussion Guide

Visit PortTalk.ca 10

Section: Heywood Street Area

Please refer to pages 25 - 28 of your Discussion Guide

Visit PortTalk.ca 11

Building the Low Level Road

Visit PortTalk.ca 12

Traffic Management Objectives

  Minimize Low Level Road and East 3rd Street closures

  Maintain emergency services access during construction

  Maintain cycling access on Low Level Road throughout construction

  Maintain driveway access (or alternate) at all times for commercial deliveries.

  Keep lane closures/temporary detours as short as possible.

  Minimize duration of closure of lane behind 500-600 Block of East 1st Street

  Keep the construction site, access points and construction vehicles clean

  Communicate early and often, while avoiding over communicating

  Maintain access to port during construction

Visit PortTalk.ca 13

Communications Tools

  Dedicated website for notification of overall construction

activities, with up-to-date information and optimized for mobile use

  Information provided in newspapers, household/business delivery, email and Twitter

  On-road information signs (and Spirit Trail) indicating notice of closure and detours. Include “businesses open during

construction” signs near eastern and western business areas

  Use of on-road electronic message boards at major access points to advise of significant lane closures as well as full

closures

  Traffic reporter advisories

Visit PortTalk.ca 14

Next Steps

•  Open house – Saturday, September 22

•  Consultation Summary Report

•  Input Consideration Memo

•  Contractor Selection

•  Notice of Construction

•  Commence Construction

Ques%ons  &  Answers  

Visit PortTalk.ca 16

Thank  You  

Please remember to:  Complete your Feedback Form

 Attend the Open House  Register on PortTalk.ca

Visit PortTalk.ca 17

St.  Georges  Avenue  –  Cross  Sec%on  

Visit PortTalk.ca 18

St.  Andrews  Avenue  –  Cross  Sec%on  

Visit PortTalk.ca 19

St.  Patricks  Avenue  –  Cross  Sec%on  

Visit PortTalk.ca 20

St.  Davids  Avenue  –  Cross  Sec%on  

Visit PortTalk.ca 21

Moodyville  Park  –  Cross  Sec%on  

Visit PortTalk.ca 22

Neptune/Cargill  Overpass  –  Cross  Sec%on  

Visit PortTalk.ca 23

Heywood/East  3rd  St.  –  Cross  Sec%on