low voltage ride-through capability improvement of wind power

Upload: haill

Post on 13-Oct-2015

12 views

Category:

Documents


0 download

DESCRIPTION

Low Voltage Ride-Through Capability Improvement of Wind Power.pdf

TRANSCRIPT

  • Low Voltage Ride-Through Capability Improvement of Wind Power

    Generation Using Dynamic Voltage Restorer

    NAOHIRO HASEGAWA, TERUHISA KUMANO

    Department of Electronics and Bioinformatics, School of Science & Technology

    Meiji University

    1-1-1 Higashi-mita, Tama-ku, Kawasaki-shi, Kanagawa 214-8571

    JAPAN

    [email protected], [email protected]

    Abstract: - Recently, the total amount of generation from wind power plants has been increased all over the world.

    In this situation, a large amount of disconnection of wind generation may give a serious influence in the power

    system. Consequently, Low Voltage Ride-Through (LVRT) is now required for wind power plants in many

    countries. This paper studies LVRT capability enhancement using Dynamic Voltage Restorer (DVR), especially it

    purposes to reduce DVR capacity. It shows that limit of DVR output and only reactive power output achieves to

    reduce device MVA rating capacity and energy storage capacity.

    Key-Words: - Wind power generation, Fixed-speed induction generator, Fault Ride-Through, Low Voltage Ride-

    Through, Voltage sag, Dynamic Voltage Restorer, Energy storage

    1 Introduction

    In recent years, the total capacity of wind generation

    connected to the power system has been increased

    significantly due to its low environmental cost and low

    installation cost compared with other renewable

    energy. In this situation, the sudden disconnection of

    wind power generation due to the power system

    disturbance may collapse power balance between the

    power supply and the power demand. In response to

    this problem, transmission system operators have

    revised grid codes in many countries, and they require

    Fault Ride-Through (FRT) capability [1]. FRT is to

    keep connection of the wind power generator to the

    power system when power system disturbance (e.g.

    voltage sag and swell, over and under frequency etc.)

    occurs. In FRT, the case of voltage sag is called Low

    Voltage Ride-Through (LVRT). However, sudden

    voltage sag may cause unstable generator speeding

    because of an unbalance between input power

    (mechanical) and output power (electrical). In order to

    meet the LVRT, the stabilization of the generator and

    voltage recovery are needed. But it is very challenging

    for wind power generation, especially Fixed-Speed

    Induction Generator (FSIG) type wind power plants

    because it can not control its active and reactive power

    outputs.

    There are two methods to enhance LVRT capability

    of FSIG. One is to reduce mechanical input of wind

    turbine and the other is to increase electrical output of

    wind generator during fault and after fault clearance.

    The method to reduce mechanical input is represented

    by pitch angle controlling [2]. The methods to increase

    electrical output are represented by using

    mechanically switched capacitor [3], Static Var

    Compensator (SVC) [4], STATic synchronous

    COMpensator (STATCOM) [5]-[7], Unified Power

    Quality Conditioner (UPQC) [6],[7], Dynamic

    Voltage Restorer (DVR) [8], and Series braking

    resistor [9] etc.

    Pitch angle controlling can enhance LVRT

    capability and has advantage in the cost. But, the

    response of change in the pitch angle is slow in general,

    so that this technique has a possibility not enough to

    enhance LVRT capability. Using mechanically

    switched capacitor has also cost-effective. However,

    the ability to supply reactive power declines in

    proportion to the square of the voltage, thus it may

    degrade the contribution of the capacitor to enhance

    LVRT capability. The same thing can be said to the

    capacitor-based SVC. Reactive power output from

    STATCOM during low voltage is larger than SVC or

    capacitor, but STATCOM can not output during

    voltage sag in order to avoid injection of additional

    fault current into the power system. Therefore,

    STATCOM has to be operated after fault clearance.

    UPQC and DVR have good performance of LVRT

    enhancement. However, both techniques often require

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 166 ISBN: 978-960-474-159-5

  • high capital cost because UPQC and DVR need twin

    inverter and energy storage device respectively. Series

    braking resister is cost-effective but it does not work

    effectively after the generator accelerates greatly.

    This paper studies LVRT capability enhancement of

    FSIG using DVR device, and proposes the method for

    decreasing the energy storage and inverter capacity of

    DVR. Section 2 describes how to use DVR to FSIG in

    order to enhance LVRT capability. Section 3 explains

    the simulation model. Section 4 shows numerical

    simulation results using EMTP-ATP, where two

    simulation cases are described. The first simulation

    examines the stabilization effects of the wind

    generator when Automatic Voltage Regulator (AVR)

    of DVR is operated with its output limitation. The

    second simulation shows the case that DVR is

    operated after fault clearance. Section 5 is conclusions

    in this work.

    2 Application of DVR to Wind Power

    System

    There are two influences that the short circuit in the

    power system exerts on FSIG type wind generator.

    Firstly, the generator accelerates during voltage sag

    caused by short circuit, so that it will be disconnected

    by the over-speed relay if it exceeds the maximum

    tolerable speed. This phenomenon results from the

    fact that the active power output from IG declines by

    the square of the terminal voltage, while the

    mechanical input from the wind turbine is almost

    constant. The maximum speed of generator depends

    on the residual voltage, the inertia of generator and

    turbine, input wind (mechanical) power and the

    duration of the fault. Secondly, huge amount of

    absorption of reactive power by IG after fault

    clearance may disturb terminal voltage recovery. As a

    result, the generator is further accelerated, and it will

    be tripped by over-speed or under-voltage relays. For

    these two reasons, voltage compensation is a good

    solution in order to avoid disconnection of wind

    generator (i.e. improvement of LVRT capability).

    Therefore, the authors use DVR as voltage sag

    compensator.

    DVR is a series solid state device that connects

    power system in order to regulate the load side voltage.

    It has been introduced for the purpose of protecting

    sensitive load such as semiconductor fabrication plant

    from power system disturbance (e.g. voltage sag,

    swell, harmonics, fault current etc.). It can compensate

    for voltage sag by low device capacity compared with

    UPS used for outage compensation or STATCOM.

    This conventional role is modified to a wind generator

    protection in this work. General configuration of DVR

    consists of the series transformer, the harmonic filter,

    the voltage source converter and the energy storage

    device.

    One-line diagram of the FSIG type wind farm and

    the power system with DVR is shown in Fig.1. In this

    figure, DVR boosts up the generator side voltage Vr

    regulated by the DVR output voltage VDVR in the event

    of supply side voltage Vs sags. By this voltage

    insertion, DVR can absorb the excess power that

    cannot be exported into the power system from the

    generator, and inject necessary reactive power.

    Block diagram of DVR controller in this work is

    presented in Fig. 2. DVR has the function of AVR

    because it aims to keep constant voltage usually.

    Although there are some methods of voltage insertion,

    In-Phase Compensation (IPC) is adopted in AVR

    considering that wind power system is robust against

    phase jump. IPC is the method that the injected DVR

    voltage is in phase with the supply side voltage

    regardless of current and the pre-fault voltage.

    DVR

    FSIG

    FSIG

    TR1

    TR2

    TR2

    TR_DVR

    Vs Vr

    VDVR

    VPCC

    Infinite bus

    Fig.1 Fixed-speed wind farm with DVR

    Eq. 1: Vd=amp*cos, Vq=amp*sin [IPC]

    Eq. 2: Vd=amp*cos(++), Vq=amp*sin(++)

    Fig.2 DVR control model

    Vs

    abc

    dq

    +

    Vr_ref

    Vr_d

    Vr

    Vr_q

    +

    0

    VDVR_d

    VDVR_q

    dq

    abc

    VDVR

    abc

    dq tan-1(Iq/Id)

    (AVR)

    Vr_d Vr_q

    I amp

    PLL

    PI

    PI

    Eq.1

    Eq.2

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 167 ISBN: 978-960-474-159-5

  • Vr_ref in this figure is the reference value of the

    generator side voltage Vr, Vr is adjusted by using PI

    controller in AVR for Vr_ref. In case of using AVR,

    VDVR changes depending on Vs and Vr. In addition to

    AVR, this control model can set amp (amplitude of

    VDVR) and (phase angle between current and

    VDVR). In case of setting amp and , it can control

    active and reactive power independently (Eq.2 in this

    figure). Eq.1 is used in case of using IPC as constant

    voltage. These schemes are showed in Fig.3 by phasor

    diagram.

    3 Model Configuration

    This section describes simulation model. The

    studied system is shown in Fig.1. It is 11.4 MVA (10

    MW) wind farm composed of 10 squirrel cage

    induction generators with a rating of 1.14 MVA (1

    MW). Each generator is connected to DVR by 1.2

    MVA transformer (TR2:690V/6600V). Shunt

    capacitors are adjusted so that the generator terminal

    voltage becomes 1.0 p.u. at nominal output power

    operation. Ratings of DVR and the series transformer

    are 11.4 MVA. These are connected to the power

    system by 11.4 MW transformer (TR1:

    6600V/66000V). Wind farm is finally connected to

    infinite bus through double circuit transmission line.

    These parameters are presented in Appendix (Table 1,

    2 and 3.). E.ON LVRT requirement [1] and 1.1 p.u.

    generator speed limit are assumed.

    4 Simulation Results

    In this section the simulation results are shown

    concerning the influence of DVR given to the power

    system and the wind generator when voltage sag

    occurred. Subsection 1 presents the results in case of

    using AVR for its original purpose (to keep terminal

    voltage to be constant during fault). In particular,

    relation between DVR capacity and generator

    stabilizing effect for various compensation voltage (by

    changing Vr_ref in Fig. 2) is studied. Subsection 2

    presents the case that DVR output inserts after fault

    clearance without compensation during fault. This

    subsection analyzes the influence when the DVR

    output voltage phase ( in Fig. 2) changes under the

    arbitrary voltage insertion.

    The generator delivers nominal power (0.877 p.u.

    11.4MVA base) to the power system under constant

    nominal wind in both simulations. A voltage sag

    occurs at infinite bus during t=1.0 to 1.1 s, which

    simulates three-phase balanced short circuit. All

    simulation cases are carried out numerically using

    EMTP-ATP.

    4.1 Stabilizing effects using AVR Fig. 4 shows the simulation results in case of using

    AVR. It compares the three cases; (1) no control, (2)

    voltage control with the reference value Vr_ref 1.0,

    and (3) 0.7 p.u. is used as the reference value. In case

    of 0.7 p.u. it is active only during fault (t= 1.0 to 1.1 s).

    In No control case, voltage oscillation and

    unsuccessful voltage recovery can be observed (see (a),

    (b)), and the generator reaches over-speed limit after

    t=3 s (see (c)). This oscillatory behavior of generator

    speed can be explained by the mechanical elasticity

    between the turbine and the generator. Active power

    output from generator is reduced greatly during the

    fault, which causes generator over-speeding in

    consequence (see (d)). In contrast, both case of using

    AVR can compensate terminal voltage, so that active

    power output of the generator increases during fault

    and generator speed is stabilized within one second

    though some speed increase is noted. As a result of this,

    the generator does not reach over-speed limit. The

    effects of reference value setting on the resultant

    acceleration cannot be observed too much. DVR

    output (apparent power) is momentarily exceeded 2.0

    p.u. (in case of Vr_ref=1.0) immediately after the fault

    clearance because of over voltage due to PI controller

    delay (see (e)). This problem is expected to be

    mitigated by adjustment of PI parameter. Energy

    storage capacity of DVR is shown in (f). Though it is

    true that the energy storage capacity in the case of

    Vr_ref=0.7 p.u. is lower than the case of 1.0 p.u., it

    does not increase simply by a factor of 0.7 because of

    taking time to stabilize generator.

    [IPC (AVR:variable VDVR, Eq.1: constant VDVR)]

    [ = 0 degree]

    (only active power)

    [ = -90 degree]

    (only reactive power)

    I Vr

    Vs VDVR

    I Vr

    Vs

    VDVR

    I

    Vr

    = -90

    Vs

    VDVR

    Fig.3 Phasor diagram of DVR control method

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 168 ISBN: 978-960-474-159-5

  • Fig. 5 shows the relation between the values of

    Vr_ref, maximum generator speed and energy storage

    capacity of DVR. Vr_ref is chosen from 0.4 p.u. to 1.0

    p.u. , energy capacity is measured at t=1.1 s (just after

    fault clearance) and t=4.0 s. All these cases can meet

    LVRT. Though the maximum speed is decreased and

    the absorbed energy at 1.1 s is increased as Vr_ref

    increases, the absorbed energy at 4.0 s in case of low

    Vr_ref (0.4 and 0.5 p.u.) is more than the case of

    Vr_ref=0.6. This result is caused by the fact that it

    takes time to stabilize due to low compensation

    voltage.

    By these results, it can be concluded that slightly

    lowering compensation voltage leads to the energy

    storage capacity reduction.

    4.2 Stabilizing effects in case of post-fault

    initiation of DVR This subsection studies the case that DVR is

    activated after fault clearance and does not use AVR.

    Compensation is started at t=1.12 s (1cycle delay after

    fault clearance), and DVR voltage amplifier amp

    (see Fig.2) is decreased from 0.1 p.u. to 0 p.u. in

    proportion to the elapsed time from control beginning

    to t=4.0 s in order to prevent over voltage after

    stabilization. DVR voltage phase (see Fig. 2) is set

    0 degree and -90 degree, and uses IPC (it follows

    supply side phase). The case of 0 and -90 degree

    correspond to active power absorption and reactive

    power injection respectively, which are defined active

    power compensation (APC) and reactive power

    compensation (RPC) respectively in this paper.

    Simulation results are showed in Fig. 6. It can be

    observed that the voltage is decreased greatly and

    generator speed increases temporarily in all cases

    Fig.5 Maximum generator speed and energy storage

    capacity of DVR in case that voltage reference of

    AVR is changed

    0

    0.3

    0.6

    0.9

    1.2

    1.5

    1

    1.02

    1.04

    1.06

    1.08

    1.1

    0 0.2 0.4 0.6 0.8 1

    Ma

    xim

    um

    gen

    era

    tor s

    pee

    d [p

    u]

    Vr_ref [pu]

    Maximum

    speed

    Energy

    (t=1.1s)

    Energy

    (t=4s)

    Ener

    gy [

    MJ]

    (f) DVR energy strage capacity (positive: absorb energy)

    Fig.4 Response of the wind turbine and DVR using AVR

    (a) DVR generator side voltage Vr

    (b) voltage at PCC

    (c) Generator speed

    (d) Generator active power output

    (e) DVR apparent power

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    0 0.5 1 1.5 2 2.5 3 3.5 4

    vo

    lta

    ge [p

    u]

    Time [s]

    No control Vref=1.0

    Vref=0.7

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    0 0.5 1 1.5 2 2.5 3 3.5 4

    vo

    lta

    ge

    [pu

    ]

    Time [s]

    No control Vref=1.0

    Vref=0.7 FRT(E.ON)

    0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    0 0.5 1 1.5 2 2.5 3 3.5 4

    Gen

    era

    tor S

    peed

    [p

    u]

    Time [s]

    No control Vref=1.0 Vref=0.7 speed limit

    -2.0

    -1.0

    0.0

    1.0

    2.0

    3.0

    4.0

    0.9 1 1.1 1.2 1.3 1.4 1.5

    gen

    era

    tor a

    cti

    ve p

    ow

    er

    [p

    u]

    Time [s]

    No control Vref=1.0

    Vref=0.7

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    0 0.5 1 1.5 2 2.5 3 3.5 4

    Ap

    pa

    ren

    t P

    ow

    er [

    pu

    ]

    Time [s]

    Vref=1.0

    Vref=0.7

    -0.20

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1.40

    0 0.5 1 1.5 2 2.5 3 3.5 4

    En

    ergy

    [M

    J]

    Time [s]

    Vref=1.0

    Vref=0.7

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 169 ISBN: 978-960-474-159-5

  • because DVR is activated after fault clearance (see (a),

    (b) and (c)). However, in all cases of activating DVR

    increases voltage after fault clearance, so that it finally

    successfully stabilizes generator speed. The effects of

    voltage compensation and rotation stabilization are the

    biggest in IPC, then RPC. They are smallest in APC. It

    is thought that this result, in which RPC has a better

    performance than APC, arises from the characteristic

    of induction generator. In high generator speed

    situation compared with nominal operation point,

    induction generator absorbs a large amount of reactive

    power, while it cannot generate active power too much.

    This is showed in Fig. 7. Therefore, the lack of

    reactive power supply from DVR causes voltage drop

    because APC cannot supply reactive power at all.

    Apparent power outputs from DVR (see (d)) of the

    three cases are almost the same, and they become

    obviously low capacity compared with the case of

    using AVR though simple comparison might be

    misleading because of difference in voltage output.

    Although they have almost the same apparent power

    output, active power outputs are not the same as

    shown in (e). APC absorbs the largest active power,

    while IPC is the second. RPC does not absorb or inject

    active power except for the small oscillation.

    Consequently, energy storage capacity of DVR in case

    of using RPC is zero, which result may be very helpful

    because energy storage device such as battery or

    electric double-layer capacitor are expensive now. In

    addition, the cases of IPC and APC need bigger energy

    storage at t=4 s compared with the case of using AVR

    because long compensation time is necessary.

    By these results, we conclude that it is possible to

    stabilize only by handling reactive power in case of

    activating DVR after fault clearance. But, this method

    cannot be used in the case that generator reaches speed

    limit during fault.

    Fig.7 An example of generator output speed curve

    0

    0.5

    1

    1.5

    2

    2.5

    3

    1 1.05 1.1 1.15 1.2 1.25 1.3

    Gen

    era

    tor O

    utp

    ut [p

    u]

    Generator speed [pu]

    Reactive Power

    Active Power

    Fig.6 Response of the wind turbine and DVR in case of

    starting operation after fault clearance

    (a) DVR generator side voltage Vr

    (b) voltage at PCC

    (c) Generator speed

    (d) DVR apparent power

    (e) DVR active power (positive: absorb power)

    (f) DVR energy strage capacity (positive: absorb energy)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    0 0.5 1 1.5 2 2.5 3 3.5 4

    vo

    lta

    ge [p

    u]

    Time [s]

    No control APC

    RPC IPC

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    0 0.5 1 1.5 2 2.5 3 3.5 4

    vo

    lta

    ge [

    pu

    ]

    Time [s]

    No control APC

    RPC IPC

    FRT(E.ON)

    0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    0 0.5 1 1.5 2 2.5 3 3.5 4

    Gen

    era

    tor S

    pee

    d [

    pu

    ]

    Time [s]

    No control APC RPC IPC speed limit

    0.00

    0.10

    0.20

    0.30

    0.40

    0.50

    0 0.5 1 1.5 2 2.5 3 3.5 4

    Ap

    pa

    ren

    t P

    ow

    er

    [pu

    ]

    Time [s]

    APC

    RPC

    IPC

    -0.20

    -0.10

    0.00

    0.10

    0.20

    0.30

    0.40

    0 0.5 1 1.5 2 2.5 3 3.5 4Acti

    ve P

    ow

    er

    [pu

    ]

    Time [s]

    APC

    RPC

    IPC

    -0.50

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    0 0.5 1 1.5 2 2.5 3 3.5 4

    En

    erg

    y [

    MJ]

    Time [s]

    APC

    RPC

    IPC

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 170 ISBN: 978-960-474-159-5

  • 5 Conclusions

    This paper analyzes LVRT enhancement of FSIG

    based wind farm using DVR by numerical simulation.

    It simulates two DVR control methods, one is to use

    AVR by limiting output, while the other is to control

    voltage phase of DVR which is activated after fault

    clearance. This study concludes the following points.

    (1) The stabilizing effect using AVR has good

    performance, but DVR capacity and energy

    storage capacity tend to become large.

    (2) Limiting output using AVR can reduce DVR

    capacity and energy storage capacity, but the

    required energy capacity might increase in case

    of low compensation voltage on the contrary.

    (3) The method in which DVR is deactivated during

    fault can also stabilize. In particular the method

    with only reactive power injection has advantage

    because of small storage capacity.

    6 Appendix

    Table 1 Wind generator parameters (1.14MVA base) Quantity Value

    Nominal apparent power 1.14[MVA]

    Nominal power 1.0[MW]

    Nominal Voltage 690[V]

    Nominal slip -0.0091[pu]

    Stator resistance/reactance 0.0063/0.089[pu]

    Rotor resistance/reactance 0.0095/0.092[pu]

    Magnetizing reactance 2.85[pu]

    Generator/Turbine inertia 0.5/3.0[s]

    Spring constant 0.55[pu]

    Table 2 Transformer parameters (self base) Quantity Value

    [TR1] Primary/secondary voltage 66/6.6[kV]

    [TR1] apparent power 11.4[MVA]

    [TR1] resistance/reactance 0.008/0.08[pu]

    [TR2] Primary/secondary voltage 6.6/0.69[kV]

    [TR2] apparent power 1.2[MVA]

    [TR2] resistance/reactance 0.008/0.08[pu] [TR_DVR] Primary/secondary voltage 6.6/0.44[kV]

    [TR_DVR] apparent power 11.4[MVA]

    [TR_DVR] resistance/reactance 0.008/0.08[pu]

    Table 3 Grid parameter (1000MVA base) Quantity Value

    Line resistance/reactance 0.286/3.217[pu]

    References:

    [1] J. Schlabbach, Low Voltage Fault Ride Through

    Criteria for Grid Connection of Wind Turbine

    Generators, 5th International conference on

    European Electricity Market 2008, pp. 1-4 (2008)

    [2] L. Holdsworth, I. Charalambous, J.B. Ekanayake

    and N. Jenkins, Power System Fault Ride

    Through capabilities of induction generator based

    wind turbines, Wind Engineering, Vol. 28, No. 4,

    pp. 399-412 (2004)

    [3] A. Kehrli, M, Ross, Understanding frid

    integration issues at wind farms and solution using

    voltage source converter FACTS technology,

    IEEE Power Engineering Society General Meeting,

    vol. 3, pp. 1822-1828 (2003)

    [4] T. Ahmed, O Noro, E. Hiraki, and M. Nakaoka,

    Terminal Voltage Regulation Characteristics by

    Static Var Compensator for a Three-Phase Self

    Excited Induction Generator, IEEE Trans.

    Industry Applications, Vol. 40, No. 4, pp. 978-988

    (2004)

    [5] L. Qi, J, Langston, and M. Steurer, Applying a

    STATCOM for Stability Improvement to an

    Existing Wind Farm with Fixed-Speed Induction

    Generators, IEEE Power and Engergy Society

    General Meeting, pp. 1-6 (2008)

    [6] M. F. Farias, M. G. Cendoya and P. E. Battaiotto,

    Wind Farms in Weak Grids Enhancement of

    Ride-Through Capability Using Custom Power

    Systems, IEEE/PES Transmission and

    Distribution Conference and Exposition Latin

    America 2008, pp. 1-5 (2008)

    [7] N.G.Jauamto, M. Basu, M.F. Conlon and K.

    Gaughan, Rating requirements of the unified

    power quality conditioner to integrate the

    fixed-speed induction generator-type wind

    generation to the grid, IET Renewable Power

    Generation, Vol. 3, pp. 133-143 (2009)

    [8] H. Gaztanaga, I. Etxeberria Otadui, S. Bacha and

    D. Roye, Fixed-Speed Wind Farm Operation

    Improvement by Using DVR Devices, IEEE

    International Symposium on Industrial Electronics

    2007 (ISIE 2007), pp. 2679-2684 (2007)

    [9] Andrew Causebrook, David J. Atkinson and Alan

    G. Jack, Fault Ride-Through of Large Wind

    Farms Using Series Dynamic Braking Resistors

    (March 2007), IEEE Trans. on Power Systems,

    Vol. 22, No. 3, pp. 966-975 (2007)

    [10] S. S. Choi, B. H. Li, and D. M. Vilathgamuwa,

    Dynamic Voltage Restoration with Minimum

    Energy Injection, IEEE Trans. on Power Systems,

    Vol.15, No.1, pp. 51-57 (2000)

    [11] Bharat Singh, and S. N. Singh, Wind Power

    Interconnection into the Power System: A Review

    of Grid Code Requirements, The Electricity

    Journal, vol. 22, Issue 5, pp. 54-63 (2009)

    RECENT ADVANCES in ENERGY & ENVIRONMENT

    ISSN: 1790-5095 171 ISBN: 978-960-474-159-5