lscc part bill cc form
TRANSCRIPT
-
7/27/2019 LSCC Part Bill CC Form
1/2
Dated Schedule Docket No.
1
2
3
4
5 K
6
7 D
8
(a) G
(b)
H
( c)
*
#
[PTO
By Cheque
Date of handing over of site in case of work, or date of written order to commence supply in case of supply of materials.
The total figure against item 8 should be tested to see that it agrees with the figure against item 7.
By recovery of amounts creditable to this work
I. ACCOUNT OF WORK
By recovery of amounts creditable to other or heads of
account work
Deduct intermediate payment already made as shown in entry "K" of the last Running Account Bill
... ...
Rs P
Total Payments now to be made as detailed below #
Deduct amount to be withheld at 71/2 percent of Rs . . .
Value of items actually measured clause 62(a) and (b) of the preliminary specification of M.D.S.S.
forming part of the contract, The details of which are given in the attached statement ... ... ...
Value of measured up additions or alterations executed up-to-date as " authorized extras ", the details of
which are given in the attached statement ...
Intermediate payment now to be made ( Items 5-6 )
Balance i.e., "up-to-date" intermediate payments ( Items 1+2+3-4)
No. PWA XXI
LUMP SUM CONTRACT
RUNNING ACCOUNT BILL
Name of The Contractor
[ See Local Ruling 1 and 5 under Article 125 in Section 5 of Chapter III of Andhra Pradesh Account Code, Vol III )
Cash Book Voucher No.
Reference to Agreement
Rs
*Date of commencement of work
P
Name of The Work
Serial number of this Bill No. and date of his previous bill for this workL.S.C.C.
Total
Approximate value of work done up-to-date excluding the items 1 and 2 above . ..
vvn
-
7/27/2019 LSCC Part Bill CC Form
2/2
1
2
)
)
**
*
**
STAMP
as an intermediate payment in connection with contract referred to above.
Amount in Indian language
Dated
Received (Rs Rupees
Rupees
II. CERTIFICATES AND SIGNATURES
I have satisfied myself to the best of my knowledge by * that the value of work
done up-to-date under item 3 of "I. Account of Work " of this bill is not less than Rs. conformably
with the contractor's agreement.
The detailed measurements of authorized additions and alterations up-to-date and of the items of work specified in item of
Account of this bill are recorded at page of Measurement Book No .
Dated Signature of the Officer
preparing the Bill
Signature of Contractor
Asst . Exe Engineer (R&B)
2
Full Signature of Contractor
Witness
Pay (Rs
Dy. Exe Engineer (R&B)
III. ACQUAINTANCE.
Paid by me Cash/ Cheque No. dated
Dated Signature of the Officer
authorizing payment
Rank
Rank
The payees acknowledgement should be for gross amount (paid as per item 8 a+b+c) of Account I, both in words and figures.
Payment should be attested by some known person when payee's acknowledgment is given by mark seal or thumb impression.
Dated initials of person actually making the payment.
Here specify the method employed for estimating the nature of work.
Of not less than that of a Sub-Divisional Engineer.Here specify the net amount payable , vide item (c ) of Account I, both in words and figures.
vvn