Page 1: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL Holdings (Pvt) Limited

LTL Holdings

LTL Holdings (Pvt) Ltd

67, Park Street, Colombo 02, Sri LankaTelephone : +94 (0) 112 695 007Fax: +94 (0) 112 684 900

Email : [email protected]

www.ltl.lk

Page 2: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

2

Contents

Vision/ Mission / 1Message from the CEO / 2 - 3LTL Holdings at a Glance / 4 - 5The story of LTL Holdings / 6 - 7Lakdhanavi / 8 - 11Offshore Projects / 12-13Lakdhanavi Renewable / 14 -17LTL Transformers / 18 - 21LTL Galvanizers / 22 - 25 CSR & Environment / 26 - 27Our Global Presence / 28

Page 3: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

1

VISIONBe a leader and become a global force through local engineering talent and innovation.

MISSIONProviding futuristic, sustainable energy solutions, through a knowledge organization culture.

Page 4: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

2

LTL Holdings in its corporate journey over past 35 years had achieved robust and healthy growth to become a leading Engineering Company in the Power Sector in Sri Lanka. Over the years, we diversified our business into power generation, electricity infrastructure development, galvanizing and transformer manufacturing thus covering the entire value chain of the power sector in Sri Lanka and successful in investing in power plants and completing Engineering, Procurement and Construction (EPC) contracts in Bangladesh, Tanzania, Uganda, Kenya, Ethiopia, and Oman.

The company’s initial business of manufacturing of transformers has grown significantly and today we manufacture and supply Sri Lanka’s entire distribution transformer requirements while exporting 50% of the production to many countries in the World.

Message from the CEO

Page 5: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

3

LTL Holdings is the largest independent power producer in Sri Lanka providing up to 300 MW of power to the national grid. LTL’s fully automated Galvanizing plant provides hot dipped galvanizing for transmission towers and other industries and capable of producing an output of 6.2 metric ton per hour to the highest international standards.

The people of LTL Holdings are inspired to take the next leap forward of the LTL Group with their tenacity, drive, and energy by leveraging our resources , ceaseless innovation, and application of advanced technology to achieve our corporate goals.

Our ultimate goal focuses on maximizing the value of our stakeholders. Given the holding company structure, LTL has achieved a greater stability while introducing uniform information management system, quality systems and corporate governance practices within its subsidiary companies. The continuous support from our diverse board of Directors, and line managers contribute immensely to maximize the growth in core businesses and explore key opportunities for potential diversification.

We thank for all the support and trust kept by our customers, technical partners, suppliers, and all other stakeholders. The confidence our customers kept on us kept us alive.

We have a clear vision for the future. We are working as a team to achieve it by building trust and confidence among our customers, partners, employees, and shareholders to enrich lives of people around us by creating an environmentally friendly prosperous society.

U D JayawardanaCEO of LTL Group

Page 6: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

4

LTL Holdings at a Glance

LTL Holdings is the leading engineering company in Sri Lanka, and is a specialist in the power sector, offering products and services along the value chain of the industry to Sri Lanka and to other countries across the globe. Our specialized professional services in Engineering, Procurement & Construction (EPC) and Operations & Maintenance (O&M), coupled with hi-tech production facilities give us a leading edge and competitive advantage in the South Asian region. We combine innovative thinking with industry best practices, to offer environmentally and socially responsible solutions that generate maximum and sustainable returns, to all stakeholders.

LTL Holdings

Lakdhanavi Limited

100% subsidiarySpecialist in EPC and

O&M services in Thermal Power generation

Lakdhanavi Renewable

100% subsidiarySpecialist in EPC & O&M services in Renewable Power generation

LTL Galvanizers

100% subsidiarySpecialist in steel

fabrications andHot dip galvanizing

LTL Transformers

100% subsidiarySpecialist in manufacturing transformers

The LTL Group

Page 7: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

5

Our skill base

LTL’s diversified base of specialized expertise spans the spectrum of professions from management, to engineering, and finance. This pool of technical knowledge is amply supported by an extensive base of highly experienced senior level professionals with many years of hands on exposure to all types of energy sector projects. This harmonisation of knowledge gained through experience and the dynamism of youth, has created a unique creative human resource pool that can add value and generate optimum solutions.

LTL Holdings

Engineering, Procurement & Construction Services

Steel Galvanizing & Fabrications

Transformer manufacturing

Operations & Maintenance services

Thermal & Renewable Power Generation

Consultancy, Design & Supervision

Independent Power Producer

The LTL Group’s expertise

Page 8: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

6

The story of LTL Holdings

1996 LTL initiates its own 24MW power plant to sell electricity to the national grid under a long term Power Purchase Agreement, becoming the first Independent Power Producer in Sri Lanka.

l LTL opens automated steel fabrication facility.

2000 LTL commissions a second galvanizing plant to meet rising demand. The new facility in Sapugaskanda (10km from Colombo) is one of the largest and most modern gas fired galvanizing plants in South Asia.

2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government of Sri Lanka.

2003 LTL’s subsidiary, Lakdhanavi Ltd in partnership with a publicly held diversified conglomerate, invests to set up a 100 MW thermal power plant in Puttalam, becoming the lowest cost Independent Power Producer in Sri Lanka.

l LTL steps into the global arena by exporting a Sri Lankan made transformer to Northern Iraq under a UN program.

1980 Lanka Transformers Ltd is commissioned as a joint venture between the Ceylon Electricity Board, Sri Lanka’s State owned energy utility and Bonar Long of Scotland, to facilitate technology transfer of transformer manufacturing.

1988 LTL introduces a ‘100% life time maintenance free,’ design for transformers.

l Mr. U D Jayawardana, a founding official of LTL, takes the reins as General Manager.

1991 LTL ventures into galvanizing to meet domestic rural electrification needs.

1995 Power generation is liberalized, allowing private investments in power plants in Sri Lanka.

Page 9: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

7

2011 Lakdhanavi wins a contract to build two, 100MW HFO power projects in Bangladesh. Despite a challenging environment, Lakdhanavi completes both projects within 7 months, establishing its reputation in the region for Engineering, Procurement & Construction [EPC].

2012 LTL initiates its first wind power project with the 10MW Pawandhanavi plant, in the western coast of Sri Lanka. The wind project is commissioned in just under 6 months and is one of the most successful projects of the Company.

2013 Lakdhanavi builds and commissions a 24MW thermal power plant in Jaffna in an impressive 185 days, setting the benchmark for EPC projects.

2014 Lakdhanavi constructs two, 52.2 MW, HFO power plants in Natore and Comilla, for the Bangladesh Power Distribution Board (BPDB), under a 15 year contract with the Government of Bangladesh.

2004 LTL acquires international accreditations and embarks on a global marketing campaign for international projects

2005 The second hydro power plant developed by LTL’s subsidiary Lakdhanavi, is connected to the national grid.

2006 The Government of Sri Lanka (GOSL) entrusts the design, financing and construction of Sri Lanka’s largest thermal power plant, the 300MW Combined Cycle Power plant , to LTL. Despite tight deadlines,

2008 LTL completes the first 200MW phase of the Simple Cycle by November 2008.

2010 Last 100 MW is included completing the Combined Cycle operation. The operation and maintenance contract is awarded to LTL’s subsidiary Lakdhanavi for 25 years by the Government of Sri Lanka.

Page 10: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

8

CEO’s Message

Page 11: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LakdhanaviLakdhanavi is Sri Lanka’s first and largest independent power producer and Sri Lanka’s largest Engineering, Procurement & Construction [EPC] contractor and O & M contractor, for major power projects, including combined cycle power plants, diesel engines based power plants, mini hydro power plants and wind power plants. The company has also made its mark globally.

Lakdhanavi Limited provides tailor-made turnkey power plant solutions within the entire plant life cycle. It has proven track record of operation in South East Asia, Middle East & Africa within the last decade.

Page 12: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

10

Lakdhanavi Limited

Awards & Quality Certification

Track Record

Since the construction of its first power station in 1997, Lakdhanavi has set an impressive track record in Sri Lanka and abroad.

l Completed the 15 year, Build Own & Operate

(BOO) contract for the Sapugaskanda power

plant in Sri Lanka, a 24MW diesel plant, built in

1997.

l Completed the EPC contract and a 10 year

O & M contract for the 100MW Heladhanavi

power plant at Puttalam, Sri Lanka. Since

commissioning in 2004, Lakdhanavi has

overseen.

l EPC and O & M Contract for Yugadhanavi

300MW Multi Fuel combined cycle power.

We undertake the following assignments on Coal fired Power Plants, Combined Cycle Power Plant, Diesel Engine power plants of any capacity

1. Develop ,Design, Finance, Insure, Construct ,Commission ,Own, Operate & Maintain on BOO or BOOT basis

2. Engineering, Procurement & Construction [EPC] Contract

3. Operation & Maintenance (O & M) contract

4. Technical service of all aspect of power plant operation and maintenance

5. Dismantle & relocation of power plants

Page 13: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

11

l Within the last two decades, Lakdhanavi has constructed and operated emergency power plants at

Sapugaskanda, Embilipitiya and Puttalam, in Sri Lanka, in capacities ranging from 20MW to 40MW.

l Lakdhanavi Completed EPC construction of 24 MW power plant in Chunnakam, Jaffna.

l Lakdhanavi Limited has diversified its presence in multiple fuel sources and is now expanding towards

capacities beyond 500 MW. From EPC services to O&M services, Lakdhanavi Limited has established its

name in local as well as overseas power markets.

24 MW Lakdhanavi Power Plant - Sapugaskanda, Sri Lanka.

Prudent Engineering Practices in Operations & Maintenance

24 MW Power Plant - Chunnakam, Jaffna, Sri Lanka

Construction of Emergency Power Plant - Embilipitiya

100 MW Heladhanavi Power Plant - Puttalam, Sri Lanka.

300 MW multi fuel, combined cycle- Kerawalapitiya, Sri Lanka.

Page 14: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

12

Offshore Projects

With international expansion opportunities opening up , Lakdhanavi made a strategic decision to move into the international arena during the last decade by leveraging its strong local identity, excellent track record and experience, in large scale power projects.

In Bangladesh, Lakdhanavi executed EPC contracts to construct heavy furnace oil power plants. The Company was also awarded the Operations & Maintenance (O&M) contract for some of these power plants.

l Lakdhanavi has completed the EPC contracts for two 100MW power plants (Meghnaghat IEL and Dutch Bangla) in Bangladesh.

l Lakdhanavi was the EPC contractor for the 52 MW Raj Lanka power plant, and the 52 MW Lakdhanavi Bangla power plant in Bangladesh. The 15 year O & M contract of the Raj Lanka plant and the Lakdhanavi Bangla power plant are operated by Lakdhanavi Ltd.

Power installations to the capacity of 52 MWs were constructed in Bangladesh on a Build Own and Operate (BOO) scheme for 15 years, and are now generating power for the Bangladeshi National Electricity Grid, under the ownership of LTL Holdings

The 52 MW power plant in Comilla, Bangladesh has made Lakdhanavi’s international reputation, for successful implementation of dual fuel operational schemes (HFO/Gas) in Bangladesh.

In the Sultanate of Oman, LTL has collaborated with the Ministry of Defence in constructing a power plant.

In Nigeria, LTL has been involved in the provision of emergency power.

100 MW Power Plant Meghnaghat - Bangladesh

100 MW Power Plant - Shiddhirganj, Bangladesh

Page 15: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

13

52 MW Lakdhanavi Bangla Power Plant - Comilla, Bangladesh

52 MW Raj Lanka Power Plant - Natore, Bangladesh Emergency Power Plant Sultanate of Oman

Page 16: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

14

CEO’s Message

Page 17: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

Lakdhanavi RenewableLakdhanavi Renewable, the renewable power projects arm of Lakdhanavi Ltd, pioneered the renewable energy industry in Sri Lanka. The Company has to date developed and delivered some of the most innovative improvements and approaches to the technical, commercial, and execution aspects of the renewable energy sector. The Company undertakes turnkey EPC contracts both locally and internationally.

Lakdhanavi Renewable is equipped with state of the art engineering software such as PVsyst, Steam Pro and WAsP and has continuous access to global developments in the field of renewable energy through its senior level network of contacts spanning major European and Asian manufacturing organizations. Access to specialized knowledge networks promote collaborations that lead to highly cost effective innovations.

Page 18: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

16

Lakdhanavi Renewable

Track Record

Lakdhanavi Renewable is the foremost Renewable Power EPC Contractor in Sri Lanka and is expanding its arms to the international arena

l LTL’s first Hydro Power Station the 2.2 MW Belihuloya power plant commences operations in 2002.

l The 4 MW Nividhu Asupiniella power plant commences operations in 2005

l LTL expands its renewable diversification by entering into Wind Power Generation in 2011 by constructing 10 MW Pawandhanavi Power Plant in Puttalam, Sri Lanka

Areas of expertise

l Executing feasibility studies for hydro power, wind energy, solar energy, biomass energy and waste to energy, projects

l Turnkey integrated EPC solutions for hydro power, wind power, solar power, biomass energy and waste to energy projects, including the following

Site selection, including soil investigations

Environmental Impact Assessment (EIA) / Initial Environmental Examination (IEE) studies

Conceptual and detailed engineering designs for civil, mechanical, electrical, control and instrumentation work of power plants

Procurement management

2.2 MW Belihuloya Power Plant

Power House of Belihuloya Power Plant

4 MW Nividhu Asupiniella Power Plant

Page 19: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

17

Construction, erection, commissioning and site management

Project management

Plant commissioning, start up, operations and maintenance

Value additions :

Long-term, senior-level relationships with key European and Asian manufacturing organizations to promote collaboration and innovation to reduce cost

Availability of state of the art engineering software such as PVsyst, Steam Pro, WAsP

10 MW Pawandhanavi Power Plant - Puttalam

Page 20: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

18

Page 21: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL Transformers LTL Transformers was established in 1982, as a joint venture of Ceylon Electricity Board the Power Utility of Sri Lanka and European investors initially to produce an indigenous transformer. The Company’s production line initially developed with an ongoing Technical Collaboration Agreement with ABB AS of Norway and then moved forward with our own technology. Today the Company’s state of the art production facilities manufacture very high quality transformers conforming to international standards and meet the entire Sri Lankan requirement while about 50% of its production are exported.

Over the time the production capacity expanded to 5MVA Power Transformers including special transformers such as Earthing, Dual Ratio, Isolation, Auto, Rectifier Transformers, Switchgear Panels, Package Substations and a host of others.

Page 22: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

20

LTL Transformers

Product range

Power & Distribution Transformers:

l Capacity from 5 kVA up to 5000 kVA

l Varying voltages up to 33 kV

l Frequency: 50/60 Hz or as per customer requirements

l Tap Types: Off Circuit Tap links/Off Circuit Tap Changer/On Load Tap Changer

l Temperature Rise: as per customer requirements.

l Silicone/Mineral Oil or other fluids filled Transformers as per customer specifications. Biodegradable oil is also available for environmentally sensitive areas.

l Cooling: ONAN / ONAF

Tank and Cooling designs:

l Hermetically Sealed type Transformers with corrugated tanks (fin walls)

l Hermetically Sealed type Transformers with gas cushions

l Conservator type Transformers with free breathing Compact and Package Substation with Transformer

l Oil immersed Transformers up to 2000kVA ; 33kV

Special Transformers:

l Rectifier / Converter Duty Transformers

l Earthing / Grounding Transformers

l Isolation Transformers

l Completely Self Protected Transformers

l Dual Voltage Ratio Transformers

l Multi Winding Transformers

l Auto Transformers

KEMA Certification

LTL Transformer Factory in Angulana, Sri Lanka

Page 23: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

21

l Low Voltage Air Cooled Transformers

l Pad Mounted Transformers (Dead Front) as per ANSI standards.

Our Support Services

l Transportation, Installation, Commissioning and Testing of Power Transformers up to 220 kVA/150 MVA at Power Plants, Grid Substations, etc, together with associated protection and firefighting systems

l Oil filtration and oil testing in transformers up to 150 MVA

l Maintenance of Power Installations in Industrial and Commercial Buildings , Power Utilities, Hospital Complexes and other such institutions under Annual Maintenance Contract or other terms as required by customers

l Repairs of Distribution Transformers

l Hiring of transformers for emergency short term requirements as substitutes

ISO Certification

MANAGEMENT SYSTEM CERTIFICATE

Certificate No:184442-2015-AQ-LKA-RvA

Initial certification date:13, August, 1997

Valid:13, August, 2015 - 12, August, 2018

This is to certify that the management system of

LTL Transformers (Pvt.) Ltd. (A subsidiary of LTL Holdings (Pvt.) Ltd.)No. 154/11, Railway Station Road, Angulana, Moratuwa, Sri Lankaand the sites as mentioned in the appendix accompanying this certificate

has been found to conform to the Quality Management System standard:ISO 9001:2008

This certificate is valid for the following scope:Design, manufacture and repair of transformers & switchgear panels

Manufacture of Components for transformers & switchgear panels

Place and date: For the issuing office:Chennai, 11, August, 2015 DNV GL – Business Assurance

ROMA, No. 10, GST Road, Alandur,Chennai, PIN - 600 016, India

Sivadasan MadiyathManagement Representative

Lack of fulfilment of conditions as set out in the Certification Agreement may render this Certificate invalid.ACCREDITED UNIT: DNV GL Business Assurance B.V., ZWOLSEWEG 1, 2994 LB, BARENDRECHT, NETHERLANDS. TEL:+31102922689.assurance.dnvgl.com

MANAGEMENT SYSTEM CERTIFICATE

Certificate No:184445-2015-AE-LKA-RvA

Initial certification date:11, January, 2007

Valid:13, August, 2015 - 12, August, 2018

This is to certify that the management system of

LTL Transformers (Pvt.) Ltd. (A subsidiary of LTL Holdings (Pvt.) Ltd.)No. 154/11, Railway Station Road, Angulana, Moratuwa, Sri Lankaand the sites as mentioned in the appendix accompanying this certificate

has been found to conform to the Environmental Management System standard:ISO 14001:2004

This certificate is valid for the following scope:Design, manufacture and repair of transformers & switchgear panels

Manufacture of Components for transformers & switchgear panels

Place and date: For the issuing office:Chennai, 11, August, 2015 DNV GL – Business Assurance

ROMA, No. 10, GST Road, Alandur,Chennai, PIN - 600 016, India

Sivadasan MadiyathManagement Representative

Lack of fulfilment of conditions as set out in the Certification Agreement may render this Certificate invalid.ACCREDITED UNIT: DNV GL Business Assurance B.V., ZWOLSEWEG 1, 2994 LB, BARENDRECHT, NETHERLANDS. TEL:+31102922689.assurance.dnvgl.com

MANAGEMENT SYSTEM CERTIFICATE

Certificate No:184414-2015-HSO-LKA-DNV

Initial certification date:31, December, 2009

Valid:13, August, 2015 - 12, August, 2018

This is to certify that the management system of

LTL Transformers (Pvt.) Ltd. (A subsidiary of LTL Holdings (Pvt.) Ltd.)No. 154/11, Railway Station Road, Angulana, Moratuwa, Sri Lankaand the sites as mentioned in the appendix accompanying this certificate

has been found to conform to the Occupational Health and Safety ManagementSystem standard:OHSAS 18001:2007

This certificate is valid for the following scope:Design, manufacture and repair of transformers & switchgear panels

Manufacture of Components for transformers & switchgear panels

Place and date: For the issuing office:Chennai, 11, August, 2015 DNV GL – Business Assurance

ROMA, No. 10, GST Road, Alandur,Chennai, PIN - 600 016, India

Sivadasan MadiyathManagement Representative

Lack of fulfilment of conditions as set out in the Certification Agreement may render this Certificate invalid.ACCREDITED UNIT: DNV GL Business Assurance India Private Limited, ROMA, No. 10, GST Road, Alandur, Chennai, PIN - 600 016, India.

Page 24: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

22

CEO’s Message

Page 25: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL Galvanizers From the humble beginnings of a leading Engineering company, startup almost 24 years ago, several expansions, and several acquisitions, LTL Galvanizers has risen to become the premier Steel Fabrication & Hot Dip Galvanizing company in Sri Lanka.

With its ultra-modern machineries & technologies, LTL Galvanizers provide services to a diverse range of industries and is renowned for liaising with customers to deliver the best solution for each project. As part of the LTL Holdings (Pvt) Ltd, LTL Galvanizers has the expertise, capacity and resources to handle the most demanding project, providing outstanding customer service using highest quality material and processes.

The company prides itself on being a leader in both material manufacturing and process innovation. As a representation of the synergy between industry and environment, LTL Galvanizers dedicated to continuous innovation and strive to provide a reliable and sustainable product.

Page 26: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

24

LTL Galvanizers

Manufacturing Expertize

l Structures required in power transmission & distribution

Substations, Towers, Cross arms

l Heavy & Medium scale pre-fabricated building structures

Ware houses, pipe racks, Ladders & stairways, Handrails & Gratings

l Communication towers

Telecommunication towers, Radio towers, Television masts

l Highway & Railway structures

Bridges, Fences, Sign board structures, light posts, Crash barriers

Fabrication of Steel Towers & Structures

LTL Galvanizers (Pvt) Ltd is furnished with ultra-modern CNC machineries and has a manufacturing capacity of 2,000 MT per month. Machineries include CNC Angle punching machines, CNC plate punching machines, CNC profile cutters, Semi-automatic plate shearing machines, and many other automatic and manually operated types of machinery. The company has proficiency in supplying customized steel structures according to the customer requirement.

Hot Dip Galvanizing

The Galvanizing facility is equipped with state-of-the-art plant and machinery from LOI-Thermoprocess of Germany, and updated regularly with the latest technologies as at today. The total production capacity of the plant is 2,500 MT per month.

Awards & Quality Certification

Page 27: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

25

LTL HOLDINGS

Galvanizing process is in accordance with the BS EN ISO 1461:2009 standard and also can be customized to conform with ASTM, AS, JIS and DIN standards.

Bath 01 (Steel Bath)

Dimensions Length : 7.0 mWidth : 1.3 mDepth : 2.1 m

Capacity 5,000 kg/hrMaximum length can dip 13.5 m

Bath 02 (Ceramic Bath)

Dimensions Length : 3.0 mWidth : 0.8 mDepth : 1.2 m

Capacity 1,200 kg/hr

Major Projects Completed Recently

132 kV Vavuniya - Kilinochchi Transmission Line132 kV Clean Energy Access Improvement Project Transmission Lines and Grid Substations33 kV Rural Electrification Project Uganda

Page 28: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

26

CSR & Environment

Social responsibility is a core governance principle at LTL Holdings. All our operational activities take into account potential social and environmental impacts, to minimize negative outcomes and maximize overall benefits. As an element of this business philosophy of minimum harm, LTL also conducts many social welfare projects.

Contributing to society

We believe in meaningful social contributions, that promotes overall social welfare. Over the years, the Company has generously extended its expertise towards public lighting systems and other public health and welfare activities, under this principle of uplifting overall social benefits.

These activities include lighting up many historic religious locations in Sri Lanka, including the ancient Ruwanweliseya Stupa, the Sri Maha Bodhiya and Lankaramaya.

Construction of a special ward with all medical facilities at Lady Ridgeway Childrens Hospital in Sri Lanka

The Company also contributes to many other social welfare programs on a regular basis.

Lighting Ruwanweliseya Stupa Anuradhapura, Sri Lanka (2500 years old heritage)

Lighting Sri Maha Bodhiya Anuradhapura, Sri Lanka(2500 years old heritage)

Constructed special ward with all medical facilities at Lady Ridgeway Childrens Hospital in Sri Lanka

Page 29: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL HOLDINGS

27

Environmental responsibility

Environmental conservation is a core element of our business, and has fuelled our drive to become a leading innovator in renewable energy production. Our efficient energy solutions contribute towards conservation of natural resources, and reducing the energy carbon footprint through the use of renewable energies.

100 MW Heladhanavi Power Plant Premises

Page 30: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

Our Global Presence

LTL HOLDINGS

Page 31: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government
Page 32: LTL Holdings · 2002 LTL’s first hydropower plant construction, the 2.2 MW Belihul Oya project, commences operations under a 15 year power purchase agreement with the Government

LTL Holdings (Pvt) Limited

LTL Holdings

LTL Holdings (Pvt) Ltd

67, Park Street, Colombo 02, Sri LankaTelephone : +94 (0) 112 695 007Fax: +94 (0) 112 684 900

Email : [email protected]

www.ltl.lk