ltlt1i~1p...oq1· '?j t>pw\t republic of the philippines . c:a\ (g.\1. q,olo department of...

13
OQ1· '?J t>Pw\t -..,.------ Republic of the Philippines . c:A\ (g. \1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENT ORDER No._5_0 __ Series of 2020 ~ ltlt1I~1P ) ) ) ) SUBJECT: Standard Project Logbook Format In order to ensure the uniformity of format during Project Implementation for monitoring and updating of day-to-day activities in the project site, this Standard Project (Construction & Materials) Logbook Format applicable for locally funded and foreign assisted projects is hereby issued to be utilized by all Implementing Offices of the Department. The issuance of the standard project logbook aims to establish consistency in the format and improve the Department's means of accomplishing the required project documents. This standard template can be downloaded from the DPWH Intranet (http:dpwhnet) under Construction Forms, and is advised to be printed in 50 or 100 pages, hardbound for each project. This Order shall take effect immediately. - ~--------:;7~ MARK A. VILLAR Secretary 6.1.3 RCNjECGjEAA Departrrent of Public Works and Highways Office of the Secretary 11111111111111111 "111111111111111111 WINOW02153

Upload: others

Post on 28-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

OQ1· '?J t>Pw\t-..,.------

Republic of the Philippines . c:A\ (g. \1. Q,olODEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

CENTRAL OFFICEManila

MAY 1 5 2020DEPARTMENT ORDER

No._5_0__Series of 2020 ~ ltlt1I~1P

))))

SUBJECT: Standard Project Logbook Format

In order to ensure the uniformity of format during Project Implementation for monitoring andupdating of day-to-day activities in the project site, this Standard Project (Construction& Materials) Logbook Format applicable for locally funded and foreign assisted projects ishereby issued to be utilized by all Implementing Offices of the Department.

The issuance of the standard project logbook aims to establish consistency in the format andimprove the Department's means of accomplishing the required project documents.

This standard template can be downloaded from the DPWH Intranet (http:dpwhnet) underConstruction Forms, and is advised to be printed in 50 or 100 pages, hardbound for eachproject.

This Order shall take effect immediately.

- ~--------:;7~MARK A. VILLARSecretary

6.1.3 RCNjECGjEAA

Departrrent of Public Works and HighwaysOffice of the Secretary

11111111111111111 "111111111111111111WINOW02153

Page 2: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

COVER PAGE (HARDBOUND - royal blue)

Side View Front View

Page 3: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

BACK PAGE (HARDBOUND - royal blue)

Rear View

Page 4: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

Republic of the PhilippinesDEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

(IMPLEMENTING OFFICE)(Office Address)

PROJECT PROFILEImplementing Office DPWH -Contract 10 :Project Name & Address

A. PROJECT DESCRIPTION

Station Limits :Scope/Description of Works :

:::

:::::

B. CONTRACT DATA

Province :Region :Project Category :Source of Fund(Locally Funded/Foreign Assisted)

ContractorConsultant :Original Contract AmountRevised Contract Amount due to Approved

VO# :VO# :VOl :

Start DateOriginal Contract DurationRevised Contract Duration due to Approved

TE # __ /VO# __ :TE# __ /VO# __ :TE# __ /VO# __ :

:Original Completion DateRevised Completion Date due to Approved

TE# __ /VO# __ :TE# __ /VO# __TE# __ /VO# __ :

:

Page 5: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

C. KEY PERSONNEL

C.l DPWH PERSONNEL:NAME ACCREDITATION NO./PRC NO.

Project Engineer -Materials Engineer -Project Inspectors -

---

C.2 CONSULTANTS PERSONNEL:NAME ACCREDITATION NO./PRC NO.

-----

C.3 CONTRACTOR'S PLEDGED KEY PERSONNEL:

NAME ACCREDITATION NO./PRC NO.

Project Engineer -Materials Engineer -Safety Engineer/Officer -Site Engineer/s -

------

D. UST OF CONTRACTOR'S PLEDGED EQUIPMENT

NO. OFEQUIPMENT DESCRIPTION NO. OF EQUIPMENT DESCRIPTIONUNITS UNITS

Page 6: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

Republic of the PhilippinesDEPARTMENT OF PUBUC WORKS AND HIGHWAYS

(IMPLEMENTING OFFICE)(Office Address)

12

CONTRACT ID NO.PROJECT COMPONENT 10PROJECT NAMELOCATIONCONTRACTORCONSULTANTDATE

9 3

WEATHER

MANPOWER ON SITE:

A.M. (outer circle)P.M. (inner circle)

LEGEND:

FAIRCLOUDYRAIN SHOWERHEAVY RAIN

6

MANPOWER No.Project ManagerProject EngineerMaterials EngineerProject InspectorsSurvey EngineerMechanical EngineerElectrical EngineerPlumbing/Sanitary EngineerSafety Officer/Safety & Health PersonnelOthers (specify) :

EQUIPMENT ON SITE:

Status TYPE OF EQUIPMENTNo. ofUnits

BulldozerBackhoeBackhoe with BreakerPayloaderDump TruckWater TruckConcrete PaverVibratory RollerBatching Plant, Concrete/AsphaltConcrete VibratorScreederOne Bagger MixerPlate CompactorWelding Machine

CONSTRUCTION ACTIVITIES:

MANPOWER No.ForemanDriverHeavy Equipment OperatorsLaborersMechanicAuto ElectricianLaboratory TechnicianCarpentersMasonsOthers (specify) :

Status TYPE OF EQUIPMENTNo. ofUnits

Asphalt PaverAsphalt DistributorAir CompressorTandem RollerPneumatic RollerElectric GeneratorConcrete CutterCrawler CraneSubmerssible PumpMaterial Testing EquipmentOthers (specify) :

Continued at the back of this pdge.

STATUS OF EQUIPMENT :

;

OperationalIdle

" Breakdownn a Not Applicable

Page No..

Page 7: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

REMARKS:

DPWH PERSONNEL ON-SITE:

NAME

CONSULTANTS PERSONNEL ON-SITE:

VISITORS ON-SITE:

Prepared by:

TIME-IN

Concurred by:

TIME-OUT SIGNATURE

Site Engineer /Site Inspector /Project Inspector (DPWH/Consultant)

Project Engineer (Contractor)

Noted by:

Project Engineer (DPWH)

Page No ..

Page 8: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

COVER PAGE (HARDBOUND - royal blue)

Side View Front View

Page 9: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

BACK PAGE (HARDBOUND - royal blue)

Rear View

Page 10: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

•Republic of the Philippines

DEPARTMENT OF PUBUC WORKS AND HIGHWAYS(IMPLEMENTING OFFICE)

(Office Address)

PROJECT PROFILEImplementing Office : DPWH -Contract ID :Project Name & Address

A. PROJECT DESCRIPTION

Station Limits :Scope/Description of Works :

:

::::::

B. CONTRACT DATA

ProvinceRegion :Project Category :Source of Fund(Locally Funded/Foreign Assisted)

ContractorConsultantOriginal Contract AmountRevised Contract Amount due to Approved

VO# :VO#VO# :

:Start DateOriginal Contract DurationRevised Contract Duration due to Approved

TE # __ /VO# __

TE # __ /VO# __ :TE # __ /VO# __ :

Original Completion DateRevised Completion Date due to Approved

TE# __ /VO# __ :TE # __ /VO# __

TE # __ /VO# __

Page 11: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

C. KEY PERSONNEL

C.l DPWH MATERIALS QUALITY ASSURANCE PERSONNEL:NAME ACCREDITATION NO./PRC NO.

Materials Engineer ------

C.2 CONSULTANTS QUALITY ASSURANCE PERSONNEL:

- NAME ACCREDITATION NO./PRC NO.

---

C.3 CONTRACTOR'S MATERIALS QUAUTY CONTROL PERSONNEL:NAME ACCREDITATION NO.{PRC NO.

Materials Engineer ----------

Page 12: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

CONTRACT ID NO.PROJECT COMPONENT IDPROJECT NAMELOCATIONCONTRACTORCONSULTANTDATE

CONSTRUCTION ACTIVITIES:

Republic of the PhilippinesDEPARTMENT OF PUBUC WORKS AND HIGHWAYS

(IMPLEMENTING OFFICE)(Office Address)

QUALITY CONTROLI ASSURANCE ACTIVITIES:

Page No.

Page 13: ltlt1I~1P...OQ1· '?J t>Pw\t Republic of the Philippines . c:A\ (g.\1. Q,olO DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CENTRAL OFFICE Manila MAY 1 5 2020 DEPARTMENTORDER No._5_0__ Series

REMARKS:

Prepared by:

Materials Engineer (DPWH/Consultant)

ConcUlTed by:

Noted by:

Materials Engineer (Contractor)

Project Engineer (DPWH)

Page No.