LUBE PROJECT ON DIE NUMBER 48DDMO3IN

IET 120Online Fall 2013Tommy WalkerJames Johnson

Page 2: Lube Project on die number 48ddmo3in

The Problem The problem we

chose was to figure out a way to reduce the number of time die number 48DDMO3IN was pulled due to lack of lube.

As you can see this die has been pulled more than any other die.

Page 3: Lube Project on die number 48ddmo3in

Brainstorming

We came up with several different solutions for this problem. We looked at the simplest solution of having the operator apply the lube manually. We also looked at some complex solutions such as putting the lube system on a computer controlled system.

Page 4: Lube Project on die number 48ddmo3in

Examples of solutionsThis is the manual off and on button. The main problem with this is the operators may forget to turn it on .

Page 5: Lube Project on die number 48ddmo3in

Examples of solutionsThese are examples of programmable solutions for the problem. These are the best solution because you can program them to work with any machine.

Page 6: Lube Project on die number 48ddmo3in

Conclusion The best overall choice is a

programmable controller. While this has an expensive start up cost it pays for itself with time.

If we can reduce the number of time the die is pulled by half the savings would be tremendous.