Luyster Creek Energy Project at Astoria Generating Station
2
Who’s Who
Astoria Generating Company, L.P.
• A US Power Generating company
(USPowerGen)
• Owner/Operator of the Astoria,
Gowanus and Narrows Generating
Stations
• Supplies about 20% of the New York
City electric generating capacity
1. Retirement of existing Unit 20
2. Construction of a 410 MW, State-of-the-Art,
Siemens H-series modern combined cycle
unit at the existing oil farm
3. Capping emissions from the existing Units 40
and 50 and the new LCEP Equipment
4. Displacing, in part, existing No. 6 fuel oil with
ultra low-sulfur diesel
5. Productive reuse of an existing industrial site
6. Reduction of water usage by displacing some
once-through cooling.
Proposed Project
Result: Increases
generation at Astoria by
approximately 16%
(225 MW)
The Luyster Creek Energy Project is :
4
Parcel Ownership/Easements
AGC • Existing Units
• Existing Fuel Oil Tank Farm
• A-10 Dock
Con Edison
NRG NRG Gas Turbines
NYPA Poletti Combined Cycle Power Project
Suez Astoria I and II Power Projects
1,344 MW capacity
3 dual-fueled steam units -
natural gas and No. 6 oil
1 steam unit natural gas only
1 black start combustion
turbine gas only
EXISTING
UNITS
Existing Units
5
Parcel Ownership/Easements
AGC • Existing Units
• Existing Fuel Oil Tank Farm
• A-10 Dock
Con Edison
NRG NRG Gas Turbines
NYPA Poletti Combined Cycle Power Project
Suez Astoria I and II Power Projects
LCEP EQUIPMENT:
410 MW, State-of-
the-Art, Siemens H-
series modern
combined cycle unit
LCEP Location
6
Fuel Oil Farm
P R I V A T E & C O N F I D E N T I A L
Artist Rendering
USPowerGen developed an Enhanced
Public Participation Plan identifying
• Meetings planned
• Stakeholders
• Languages for which translation
can be provided
• Notice period for all formal
meetings (3 weeks)
• Dissemination of information
on-line and in public places
• Progress reporting
• Numerous opportunities to
comment during process
Website: www.uspowergen.com
Public Participation Plan
Luyster Creek Energy Project
8
January 2010 Submit EAF – Complete
March 2010 - May 2015 Meetings with Public Officials and Organizations - Ongoing
May 2015 Complete construction
December 2011 Findings and permits issued
December 15 2010 Submit Draft EIS - Complete
April 2013 Construction begins
December 2010 - August 24, 2011 DEC consideration and Public Meetings
- Started
September – October 2010 Information Sessions/Scoping Meetings (5) - Complete
9
Project Schedule