Page 1: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

1020 8293 4943 [email protected]@mservices.co.uk www.mservices.co.ukTel: 020 8293 4943For more information call

Radbroke Technology Centre

LV Generator Installation

DURATION????

VALUE????

LOCATIONRadbroke

Page 2: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

2020 8293 4943 [email protected] 2020 8293 4943 [email protected]

BriefTo procure, deliver, and install N+1 level of LV generator resilience to Blocks 9 & 10 at Radbroke Hall. These generators were to be configured so that both generator sets can support Block 9 & 10, with 48 hours of fuel storage.

Page 3: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

3020 8293 4943 [email protected]

OverviewMetropolitan were engaged as the Principal Design and Build Contractor to deliver the first phase of the HV generator controls replacement at Radbroke. The scope of works for the project is summarised as follows:

The existing Blocks 9 & 10 Main LV Switchboard was a four-sectioned switch panel, fed via four separate HV transformers. The sections were labelled A, B, C & D respectively. Metropolitan reconfigured the panel to couple A&B and C&D, followed by isolation of the supply transformers [TX5 & TX6] and the removal of the existing LV cable link. Subsequently, we reconfigured the HV generator control cabling and philosophy, introducing new LV generator PLC controls. A non-paralleling exercise of opening the main LV switch to sections B & C, before closing the associated bus-coupler linking the new coupled sections together was carried out. This ensured that each coupled section was now fed via one incoming supply.

We installed a new LV generator connection panel with associated containment back to the main building. This allowed for the installation and connection of cabling, between the new connection panel/ and the Block 9 & 10 existing main LV switchboard, which had new incoming extensions installed during the panel modification stage.

Page 4: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

4020 8293 4943 [email protected]

With the new connection box successfully linked to the building infrastructure, we used this to connect new temporary generator sets for site back up power and performed on-site load generator testing to each set. This met a critical milestone set by the client to give LV back-up by a set date, critical to the client’s business operations. We performed mains failure testing, proving the temporary generators protected the business by local simulation.

Whilst the building was protected by the temporary generator sets, the installation of two new AVK 1350 kVA/ 1080 kW permanent LV containerised generators was carried out. This involved major civil works to provide suitable concrete plinths for the sets, and new security fencing to the perimeter.

Finally, once the new generators were installed, we planned and managed an out of hours change-over from the temporary LV generators to the new permanent LV sets.

A full commissioning plan was produced and executed, which included performing load tests, building mains failure tests and multiple failure scenarios of the local HV to test the new PLC configuration.

Page 5: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

5020 8293 4943 [email protected]

ProgrammeThe main challenge faced in planning these works, was that the client facility housed a live global operation centre within Block 10, and this could not be interrupted. Critical milestones had to be met throughout, and shutdown dates, once approved, had to be achieved to mitigate the client’s business risks. The approval of some key shutdown dates were sometimes very late in being issued, but we successfully achieved these dates on each occasion.

Page 6: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

6020 8293 4943 [email protected]

H&S RecordHealth and Safety records kept and issued on a weekly basis including, but not limited to :

• RAMs issued – uploading to ePermit system for production of and approval of work permits

• Toolbox talks• Plant check lists • CSCS checks• PAT testing• Weekly and monthly fire check lists• Daily safe starts• Limitation of access• Access permits• Permits for working on electrical

systems• Ladder permits• Ladder check lists• Weekly site inspection reports• CDM responsibilities as Principal

Contractor• Temporary works co-ordination

and record keeping

CollaborationBarclays Project Team:Project Director – Bobby Tulloch

Metropolitan Project Team:Associate Divisional Director – Mark FaySenior Project Manager – Mark Williams

Key Supply Chain• MSL Employees• Creatside – Cable Installation• Carson Powell – Civils• AVK – Generator Manufacturer• I.C.W Power Mode – Panel Modifications• E.On – BMS Specialist• Primal Systems Ltd – Fire Alarm Specialist• MEITS Consultants – M&E Consulting

Engineers• Paul Owen Associates - Civil Engineering

Page 7: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

7020 8293 4943 [email protected]

Page 8: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

8020 8293 4943 [email protected]

ResultsTwo fully operational 1350 kVA/ 1080 kW generators were delivered and integrated into one of our clients Global Mission Critical facilities. Both sectional handover dates were met, de-risking the potential for mains failure support via the existing HV Generator System.

The satisfaction from the client, as detailed within the testimonials received upon completion, reinforces the Metropolitan policy of delivering turnkey projects with Passion, Pride and Excellence. The success of this project has led to us securing Phase 2 of the upgrade, due to start imminently.

Page 9: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

9020 8293 4943 [email protected] 9020 8293 4943 [email protected]

TestimonialsJust to echo the herculean effort put in by ALL parties over the weekend-collectively, you have closed off a Major operational risk within our risk profile, which had my name all over it-THANK YOU.

We’ve got further continuation of works early next year - I urge ALL of you to have a good break over the Christmas period, recharge your internal batteries and again start the year with all guns blazing.

The Bank couldn’t continue without your collaborative approach and attention to detail - outside our world, not many people appreciate the efforts that Building Engineering / infrastructure achieve - all weathers, very long hours, environmental and space constraints, people, equipment failures - your name, we all get it, but we just get on with it.

ISS on site team - Very well done in supporting this extremely critical piece of asset replacement / risk mitigation.

MES/AVK/ICW - Exceptional great all-round team installation and ethos.

MEIT - Brilliant and exceptionally resilient design.

Kirk Miller UK Engineering Lead | Director | CRES and Location Strategy

Just a short note to thank everyone involved in the delivery of what has turned out to be a very successful project, with us collectively delivering the works on time, within budget and without operational impact.

Of course, most importantly without any health and safety issues.

None of which would have been possible, if it was not for the open & honest lines of communication, between each and every one of us, it was a true team effort.

Please pass on my thanks to your associated teams and suppliers that equally contributed to the success.

Well done and let’s keep up the momentum for Babbage house works.

Robert Tulloch CEng BEng Hons IET Engineering Manager | Vice President | CRES and Location Strategy

Page 10: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level

10020 8293 4943 [email protected] 10020 8293 4943 [email protected]

Meit Consultants have worked with MES successfully over a number of years with one of the most recent projects delivering a central infrastructure project for one of our large financial institutions. The project entailed supply, deliver and installing two new containerised generators that would support their mission critical site and deliver additional resilience. The works entailed not the primary electrical infrastructure works but also the associated structural works necessary to support the generators and their associated bulk fuel tanks.

MES operated as a competent Principal Contractor co0ordinating all other trades and connecting these new generators into the clients mission critical facility during planned change over weekend. The works were completed on time and inline with the clients requirements as a result MES have been selected to undertake the next generator replacement project for the same customer.

Alan Gibson Director | Meit Consultants

Testimonials

Find out how Metropolitan Services can exceed yourexpectations – get in touch with us today!

Call 020 8293 4943 or email [email protected]

Page 11: LV Generator Installation Radbroke Technology Centre...020 8293 4943020 8293 4943 .mseices.co.uk allmseices.co.ukall@mservices.co.uk 22 Brief To procure, deliver, and install N+1 level