lyons o'neill works to date

126
Works To Date

Upload: lyons-oneill

Post on 28-Mar-2016

216 views

Category:

Documents


1 download

DESCRIPTION

Lyons O'Neill Works To Date

TRANSCRIPT

Works To Date

!"#$%#&%'()(%'(%*#)+,-&'(+#,.#/&-&0#1#2*+34*3+$0#'("&5%#"(+-&4("#*,#*6(#4,%"*+34*&,%#&%'3"*+78#

9#7,3%5#$%'#'7%$:&4#4,:)$%7#;&*6#$#'&-(+"(#*($:#$%'#$#;&'(#+$%5(#,.#(<)(+&(%4(#;(#6$-(#$#)+,-(%#*+$4=#

+(4,+'#&%#'(0&-(+&%5#>3$0&*7#)+,?(4*"#&%#@,*6#*6(#AB#$%'#C3+,)(8#

D3+#),+*.,0&,#4,:)+&"("#$%#&:)+(""&-(#-$+&(*7#,.#;,+=#&%403'&%5#)+&-$*(#+("&'(%*&$0#'(-(0,):(%*"E#0$+5(F

"4$0(#4,::(+4&$0#)+,?(4*"E#(%-&+,%:(%*$0E#('34$*&,%E#$%'#0(&"3+(#@3&0'&%5"8##G(#$0",#6$-(#(<)(+&(%4(#&%#*6(#

4,%"(+-$*&,%#,.#6&"*,+&4#@3&0'&%5"#$%'#3%'(+*$=(#:,+(#")(4&$0&"*#4,::&""&,%"#&%403'&%5#50$""#"*+34*3+("#$%'#

@("),=(#$+*#&%"*$00$*&,%"8

G&*6#'&+(4*,+#&%)3*#,%#$00#)+,?(4*"#;(#$+(#4,::&**('#*,#3%'(+"*$%'&%5#40&(%*H"#%(('"#$%'#(<4(('&%5#(<)(4*$*&,%"8#

D3+#4,:@&%$*&,%#,.#'("&5%#0('#)+$4*&4(E#*+$%")$+(%*#4,::3%&4$*&,%#$%'#4+($*&-(#.0$&+#I#$0,%5#;&*6#,3+#&%%,-$*&-(#

$))+,$46#*,#)+,@0(:#",0-&%5#I#'(0&-(+"#,3*"*$%'&%5#-$03(#.,+#,3+#40&(%*"8

D3+#9))+,$46#J

# # )+,?(4*#'(0&-(+7E#=%,;0('5(#"6$+&%5#$%'#$#>3$0&*7#,3*4,:(8

K7,%"#DHL(&00

!"#$%&&#'%()$*'$*)+$,+-./0$&#'(+--

1#'2+(*$('0*+3*

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

4#%5.0/$6"%7.*8

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

9+8$:*%/+-$;$<'=="0.(%*.'0

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

KL

White Lodge

Details Sheet 1

Issued for Steelwork Tender onlyT1

C3

28-3-08

Mar 08

8003/300

1:5

DON KL

STATUS

PROJECT

SUBJECT

SCALE @ A1

BY

DRAWING No.

DATE

CHECKED

REV

REV COMMENTS DATE CHK

NOTES© 2008 Lyons O'Neill Ltd

Construction

Lyons O'NeillStructural Engineers

45 Great Guildford StreetLondon

SW1 0ES

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

1. This drawing is to be read in conjunction with allrelevant architects and engineers drawings

2. Do not scale this drawing

3. Refer to drawing No. 8003/999 for Structural

KLIssued for below groundConstruction only

C1 20-5-08

KLIssued for Construction. Revisedto suit architects comments

C2 22-7-08KLPlate above door revisedC3 29-7-08

55

200

10mm thick base plate boltedto slab with 2No. M12 bolts

100 x 10mm thick plate welded toend of mullion

Mullion fabricated from 1No. 150x10outer plate + 1No. 100x15 inner plate +190x10 outer plate. Outer plates plugwelded to inner plate @ centres tofabricator's details to prevent warping ofplates.

5

Mullions fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

190 x 85 x 10 thick 'T' section

10mm thick basplate bolted toangle with 2No. M8 countersunkbolts

5

Mullions fabricated from 1No. 150x10outer plate, 1No. 100x15 inner plate &1No. 190 x 10 outer plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates. 190 x 10 outer platenotched to recieve fabricated angle plate

190 x 85 x 10 thick fabricated'T' section bolted to plate with2No. M10 countersunk bolts

10mm thick end plate welded tofabricated angle and bolted to

plate with 2No. M10countersunk screws into tappedholes

5

Double glazed roof units :12 thick toughened outer +6 thick toughened inner

Sealant by others

Roof beams fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

5

Norton Thermalbondstructural spacer tapebetween glazing paneland roof beam (Typical)

Double glazed wall panels :12 thick toughened outer + 6 thicktoughened inner.

Mullions fabricated from 1No. 150x10outer plate, 1No. 100x15 inner plate &1No. 190 x 10 outer plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

10mm thick base plate boltedto slab with 2No. M12 bolts

150 thick RC slab with 2 layersA393 mesh, 1Top & 1 Bot.35mm cover to bottom and25mm cover to top reinforcement.On DPM, on 50mm sand blindingon 150 well compacted hardcore

Norton Thermalbond structuralspacer tape between glazing paneland mullion

FFL +0.000

SSL -0.150

25mm non-shrinkable groutand steel shims

150

5015

0

2535

Double glazed roof units :12 thick toughened outer + 6 thicktoughened inner

Roof beam fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

Mullions fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

16mm diameter countersunk bolt.Refer to Pin Detail.

50mm diameter x 10mm thick platewelded to each side of roof beam.

Double glazed wall panels :12 thick toughened outer + 6 thicktoughened inner.

5mm x 10mm wide neoprenespacer between outer plates

Norton Thermalbond structuralspacer tape between glazing paneland roof beam

Norton Thermalbond structuralspacer tape between glazing paneland mullion

Existing masonry wall

Channel built into existing wall tosupport new double glazed roof panels

Roof beam fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates. 10mm welded end plate.

Double glazed roof units :12 thick toughened outer + 6 thicktoughened inner

End plate bolted back to existing wall with2No. M16 countersunk resin anchors.

20 Min.

Existing masonry wall

Channel built into existing wall tosupport new double glazed roof panels

Roof beam fabricated from 2No.150x10 outer plates & 1No. 100x15inner plate. Outer plates plug weldedto inner plate @ centres to fabricator'sdetails to prevent warping of plates

Double glazed roof units :12 thick toughened outer + 6 thicktoughened inner. Provide extra spacerover roof rib.

Roof beam bolted back to existingwall with M10 countersunk resin anchors@ 600 centres

20mm shims and drypack

5

Norton Thermalbond structuralspacer tape between glazing paneland roof beam

100 x 10mm thick plate boltedto existing masonry wall withcountersunk M10 resin anchors@ 600 centres

10mm thick base plate boltedto slab with 2No. M12 bolts

20 M

in.

Mullion bolted back to existing wallwith M10 countersunk resin anchors@ 600 centres

Existing masonry wall

Mullions fabricated from 2No. 150x10outer plates & 1No. 100x15 inner plate.Outer plates plug welded to inner plate @centres to fabricator's details to preventwarping of plates.

10mm thick base plate. Bolted toslab with 2No. M12 bolts

5

Detail 1/300 (1:5) Detail 2/300 (1:5)

Detail 3/300 (1:5)

Detail 6/300 (Plan) (1:5)

Detail 7/300 (Plan) (1:5)

Detail 8/300 (1:5) Detail 9/300 (1:5) Detail 10/300 (1:5) Detail 5/300 (1:5)

Detail 4/300 (Plan) (1:5)

Steelwork Axonometric (N/A)

Detail 1/300

Detail 2/300

Detail 3/300

Detail 10/300

Detail 9/300

Detail 5/300

Detail 4/300

Detail 1/300

Detail 8/300

Detail 6/300

Detail 7/300

Pin Detail (1:2)

Eur Ing Kevin Lyons BEng (Hons) CEng MIStructEDirector

Career History Alan Baxter and Associates (1995 - 1996) Harris and Sutherland, Hong Kong (1996 - 1998) Techniker (1998 - 2005) Packman Lucas (2005 - 2008)

Experience

Kevin Lyons has over 20 years of experience in the design and delivery of a wide range of structures from concept to completion. He set up Lyons O’Neill after working in a few of London’s best known design based engineers and after working abroad for 2 years.

Kevin’s interest lies in finding appropriate and buildable design solutions as part of an integrated design team. Experience of working on site in Hong Kong and the UK has given Kevin a rounded perspective on both design and construction. He has also worked on a variety of projects from his work on the 115m high Cathay Pacific headquarters in Hong Kong to the new Porter Gallery at the V&A Museum in London.

Recently Kevin worked with Thomas Heatherwick on the Boiler Suit facade at London Bridge and the Porter Gallery at the V&A Museum. Lyons O’Neill’s recent work has won a Structural Steel award and has been short listed for the IStructe Structural Awards in three separate categories.

Kevin remains conversant in many materials having experience in building in all. Appropriateness of materials and buildability remain Kevin’s core drivers.

Guys Hospital Facade

Cathay Pacific Victoria & Albert Museum - Porter Gallary

Vivienne Westwood HQ

Damian O’NeillDirector

Career History Dewhurst MacFarlane & Partners (1987 - 1993) Techniker (1993 - 2007) Packman Lucas (2007 - 2008)

Experience

Damian has over 25 years experience in the engineering industry. He began as a technician at Dewhurst MacFarlane and went on to lead their draughting team where he was responsible for developing and managing the drawing packages for several major projects.

Drawing is the core of our communication and Damian is primarily responsible for production side of Lyons O’Neill and liases with the team to provide a fully co-ordinated design. Lyons O’Neill are increasingly using 3D models to illustrate and present solutions to the design team.

Damian is also heavily involved in the marketing side of the practice and is Director of a Business Networking group that meets weekly in London Bridge. This means Damian has a wide network of contacts within a range of different business areas mainly within the Construction sector.

The Weather Room

Vivienne Westwood HQ Castle Hill Dining Hall

!"#$%&'(#$")&*&+,$-."/#-/&0&123$"34#&'(#$")&,$-."/#-/%5

678&9:;2"/"#%!"#$%%$&'(")*+,-$.+("/+012&0$.+

!"#$%&'()*+,--'./+'.-0.#&'0,--,%1'.%2'.3-+'4$'2+5,&+'+%1,%++/,%1'&$-64,$%&'47.4'3$47'&6,4'47+'./87,4+846/+'.%2'./+'1/$6%2+2',%'9/.1:.4,&:;

<"-.;$3&=;));>&*&+!$"?;/#&@2"#)/5

678&9:;2"/"#%!"/+012&0$.+("3$'4"5&-+'*$-6("78112*-$.+

!<'+%1.1+2'=+5,%'.%2'7,&'4+.:'4$'9/$5,2+'47+'&4/6846/.-'+%1,%++/,%1'&699$/4'>$/'.'$%+?$>>':$2+/%'7$6&+@',%8$/9$/.4,%1'.'&,1%,>,8.%4'.:$6%4'$>'>.,/'>.8+2'8$%8/+4+'.%2'.'-./1+'&4++-'>/.:+A''B7+#'0$/C+2'8-$&+-#'.%2'+>>+84,5+-#'0,47'3$47':+'.%2'47+'./87,4+84'4$'.//,5+'.4'.'/$36&4'.%2'8./+>6--#'2+4.,-+2'&4/6846/.-'&$-64,$%'47.4'7.&'.--$0+2'$6/'5,&,$%'>$/'47+'7$6&+'4$'3+'8-+./-#'+D9/+&&+2@'07,-&4'.-&$'3+,%1'36,-2.3-+A''B7+#'7.5+'.-&$'8./+>6--#'.%2'/$36&4-#':$%,4$/+2'47+'E6.-,4#'$>'47+'0$/C'$%'&,4+A''<'8.%%$4'/+8$::+%2'47+,/'&+/5,8+&'4$$'7,17-#A;

A7);23&B;$9:.;$%7)&*&+=#;3&7C&!$"(;$>&@;8"/;2&!$74$;((#&0&<7>;2&D7$7:4.&7C&E")4%/7)5

678&9:;2"/"#%!"9:1+*-("3$'4"5&-+'*$-6(")*+,-$.+"

!=+5,%'7.&'9/$5,2+2'+D8+--+%4',%%$5.4,5+'&$-64,$%&'4$'5./,$6&'8$:9-+D',&&6+&A'F+'7.&'.-0.#&'3++%'7,17-#'/+&9$%&,5+'.%2'.22+2'5.-6+'4$'47+'9/$G+84&'47/$617'+D8+--+%4'6%2+/&4.%2,%1'.%2'1/+.4'8$::6%,8.4,$%A'<'-$$C'>$/0./2'4$'0$/C,%1'0,47'=+5,%'.%2'"#$%&'()*+,--'.1.,%A;

F;("#&@;$/#$&*&+A"$#-/7$&0&E##4;)%&!$7G#-/&H;);4#$%5

678&9:;2"/"#%!";*+,-"/+08%-0("<+*02&,=%+(";22>"?,%8+"

!=+5,%'/6%&'.'9/$.84,5+'.%2'<%%$5.4,5+'H4/6846/.-'I%1,%++/,%1'J$%&6-4.%8#'.4'"#$%&'()*+,--A'<'7.5+'6&+2'47+:'$%'.'%6:3+/'$>'&87$$-&'9/$G+84'.%2'47+#'-+.2'47+'2+&,1%'4+.:'9$&,4,5+-#'>/$:'.'&4/6846/.-'9+/&9+84,5+'4$'2+5+-$9'47+'8$%8+94'.%2'4$'2+-,5+/'.'&$6%2'4+87%,8.-@'0$/C.3-+'2+&,1%'&$-64,$%A'F,17-#'/+8$::+%2+2',>'#$6'./+'-$$C,%1'>$/'.'>$/0./2'47,%C,%1'.%2'9/$3-+:'&$-5,%1'.99/$.87'4$'H4/6846/.-'I%1,%++/,%1A;

I$#4&A7);4.#>&*&+A"$#-/7$&0&@JA&D:"23&@7)/$;-/7$%&!$7G#-/5

678&9:;2"/"#%K"I>>,8,+%4@'H$6%2'H4/6846/.-'H$-64,$%&@'K99/$.87.3-+'

!L+'.4'JMN'O6,-2'0$/C+2'0,47'=+5,%'M'N.:,.%'$>'"#$%&'()*+,--'$%'.%'.9./4:+%4'N+&,1%'M'O6,-2'H87+:+',%'*$/47'"$%2$%A'<'>$6%2'47.4'47+#'+:9-$#+2'+>>,8,+%4'.%2'&$6%2'&4/6846/.-'&$-64,$%&@'47+#'0+/+'5+/#'.99/$.87.3-+'$%'.--'.&9+84&'$>'47+'36,-2'.%2'.-0.#&'8.:+'4$'47+'4.3-+'0,47'0$/C.3-+',2+.&'.%2'&$-64,$%&A'<'0$6-2'7.5+'%$'7+&,4.4,$%',%'/+8$::+%2,%1'47+,/'9/.84,8+'4$'.%#'8-,+%4'&++C,%1'.'&4/6846/.-'+%1,%++/'.%2'<'-$$C'>$/0./2'4$'0$/C,%1'0,47'47+:'.1.,%'$%'$6/'%+D4'9/$G+84A;

I$#4&L7(;%&*&+,$-."/#-/&0&B7%/#$&L7(;%&,$-."/#-/%5

678&9:;2"/"#%!"5&&2.,-$.+("?$=*,&-("@26"-2"#2*A"#$-4

!<'7.5+'0$/C+2'0,47'N.:,.%'.%2'=+5,%'$%'.'%6:3+/'$>'/+&,2+%4,.-'.%2'8$::+/8,.-'9/$G+84&'.%2'8$:9+4,4,$%&A'L+'C++9'6&,%1'47+:'3+8.6&+'47+#'9/$5,2+'.%'+D+:9-./#'&+/5,8+'.%2'9/$5,2+'8/+.4,5+'&4/6846/.-'&$-64,$%&'47.4'+%7.%8+'47+'./87,4+846/+'0+'+%5,&,$%A'B7+,/'$>>,8+'7.&'.'#$6%1@',%%$5.4,5+'.%2'5,3/.%4'4+.:'47.4'./+'.'G$#'4$'0$/C'0,47A;

@.$"%/")#&=;22&*&+!$"?;/#&@2"#)/5

678&9:;2"/"#%!"B&>+*0-,&>$&'("C+D4&$D,%"E+-,$%"

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

F;%7)&M$#)&*&+'.;8#&,$-."/#-/:$#5

678&9:;2"/"#%K"5&&2.,-$.+("/+012&0$.+"

!L+'7.5+'0$/C+2'0,47'=+5,%'>$/'$5+/'4+%'#+./&'.%2'.-0.#&'.99/+8,.4+'7,&'8/,4,8.-'8$::+%4&A''K&'.'8$--.3$/.4$/'$%',%%$5.4,5+'9/$G+84&'7+',&',%5.-6.3-+'.%2'<'.:'.-0.#&'&6/+'47.4'+.87'.%2'+5+/#'8$%5+/&.4,$%'0,--'/+&6-4',%'.%',:9/$5+2'2+&,1%A''F+@'.%2'.--'.4'"#$%&'()*+,--'./+'.-0.#&'/+&9$%&,5+'.%2'8$::6%,8.4+'4$'6&'.%2'4$'.--':+:3+/&'$>'47+'2+&,1%'4+.:',%'.'8-+./'.%2'8$:9/+7+%&,5+':.%%+/A;

Sweethaws  Wood

Architect  :  Eldridge  Smerin  Architects

Elsham  Road

Architect  :  Eldridge  Smerin  Architects

Porter-­Leake  House

Architect  :  John  Pardy  Architects

Addison  Road

Architect  :  Michaelis  Boyd  Associates

King’s  Grove

Architect  :  Duggan  Morris  Architects

The  Weather  Room

Architect  :  Liddicoat  &  Goldhill

Private  Residential

16A King’s Grove, Peckham

Architect

Main Contractor

Location

Value

Duggan Morris Architects

ME Construction

Peckham, London

£180,000

A private house on a brown field site between existing domestic properties presented us with some unique buildability issues. Due to

acess limitations, all elements had to be brought through a narrow 2.4m wide access from the main road.

The selected structural scheme maximised the width of the site by tying in the existing boundarys without disturbing their Victorian

footings. The structure was then constructed using two steel frames for stability and then simple loadbearing walls. The large floor spans

were achieved by using lightweight timber ’I’ joists which could be handballed onto the site

Lyons O’Neill scheme drawing

Internal Photo Front elevation

Lyons O’Neill - Working Drawing

Steel Portal Frames

240 deep Finnforest 'FJI 240-89 joists@ 400 centres built into cavity wallwith plastic sleeves to manufacturersdetails. Provide 30mm deep timber packersto top, screwed with No. 12 screws.

Detail 2/310 (1:5)

Detail 1/310 (1:5)

Expamet M305 restraint straps @ 1200 centresscrewed to RHS and screwed to 3No. minimumjoists with 1No. No.12 woodscrew per joist.Provide solid blocking in line of straps.

Solid board material screwed to joists@ 300 centres and to RHS asshown

All and toArchitect's details

Ancon MDC/50/1.0 support system. Continuousangle complete with welded brackets backto RHS box section with M12 steelgrip bolts

to manufacturers details

Ancon SDB tie x 125mm long backto RHS using SDTSS-38-5PT self drillingself tapping screw to restrain brickwork

Ancon special tie to top of RHSbox section using SDTSS-38-5PT self drillingself tapping screw

Ancon SDB tie x 125mm long backto RHS using SDTSS-38-5PT self drillingself tapping screw to restrain brickwork

Ancon MDC/50/1.0 support system. Continuousangle complete with welded brackets backto RHS box section with M12 steelgrip bolts

to manufacturers details

All and to Architect'sdetails

Ancon SPS tie x 150 long to tie twoleafs together.

200 x 100 RHS sway frame memberwith welded to angle to suport window/door.Angle size and location to Architects details

240 deep Finnforest 'FJI 240-89 joists@ 400 centres with plastic sleevesto end bearing to manufacturersdetails

Expamet M305 restraint straps @ 600 centres@ 45° to timber joists screwed to RHS andscrewed to 3No. minimum joists with 1No. No.12woodscrew per joist. Provide solid blocking inline of straps.

All to Architect's details

Solid board material (under heatingtongue and groove boards) screwed tojoists @ 300 centres to provide diaphragmaction

200 x 100 RHS sway frame memberwith welded to angle to suport window/door.Angle size and location to Architects details

240 deep Finnforest 'FJI 240-89 joists@ 400 centres built into cavity wallwith plastic sleeves to manufacturersdetails. Provide 30mm deep timber packersto top, screwed with No. 12 screws.

Detail 6/310 (1:5)

Ancon special tie to top of RHSbox section using SDTSS-38-5PT self drillingself tapping screw

Ancon SDB tie x 125mm long backto lintel using SDTSS-38-5PT self drillingself tapping screw to restrain brickwork

All and to Architect'sdetails

Expamet M305 restraint straps @ 600 centres@ 45° to timber joists screwed to RHS andscrewed to 3No. minimum joists with 1No. No.12woodscrew per joist. Provide solid blocking inline of straps.

All to Architect's details

Solid board material (under heatingtongue and groove boards) screwed tojoists @ 300 centres to provide diaphragmaction

IG Box 200 x 150 high x 1.6mm thicklintel

Detail 7/310 (1:5)

Expamet M305 restraint straps @ 1200 centresscrewed to RHS and screwed to 3No. minimumjoists with 1No. No.12 woodscrew per joist.Provide solid blocking in line of straps.

Solid board material screwed to joists@ 300 centres and to RHS asshown

All and toArchitect's details

Ancon MDC/50/1.0 support system. Continuousangle complete with welded brackets backto RHS box section with SDTSS-38-5PT selfdrilling self tapping screws in pairs @ 200 centres.Support system to be full length of lintel

Ancon SDB tie x 125mm long backto lintel using SDTSS-38-5PT self drillingself tapping screw to restrain brickwork

Ancon SPS tie x 150 long to tie twoleafs together.

240 deep Finnforest 'FJI 240-89 joists@ 400 centres with plastic sleevesto end bearing to manufacturersdetails

IG Box 200 x 150 high x 1.6mm thicklintel

Ancon MDC/50/1.0 support system. Continuousangle complete with welded brackets backto RHS box section with SDTSS-38-5PT selfdrilling self tapping screws in pairs @ 200 centres.Support system to be full length of lintel

2

Detail 3/310 (1:10)

All andto Architect's details

Clay - FN 20N/mm2 bricks,type III mortar.2.5 vertical twist ties/m2,length to suit cavity

100 wide x 215 deep Naylor lintels150 x 50 C16 timber joists@ 400 centres

Solid board material screwed tojoists @ 300 centres

Detail 4/310 (1:10)

Clay - FN 20N/mm2 bricks,type III mortar.2.5 vertical twist ties/m2,length to suit cavity

240 deep Finnforest 'FJI 240-89 joists@ 400 centres built into cavity wallwith plastic sleeves to manufacturersdetails. Provide 30mm deep timber packersto top, screwed with No. 12 screws.

Solid board material (under heatingtongue and groove boards) screwed tojoists @ 300 centres

Expamet M305 wall restraint strapsbuilt into cavity wall as shown and

to joist with 3No. No.12 woodscrews

Detail 5/310 (1:10)

240 deep Finnforest 'FJI 240-89 joists@ 400 centres built into cavity wallwith plastic sleeves to manufacturersdetails

Solid board material screwed to joists@ 300 centres and to RSA withself drilling self tapping screws

Expamet M305 wall restraint strapsbuilt into cavity wall as shown and

to joist with 3No. No.12 woodscrews

Brickwork parapet to Architects details

240 deep Finnforest 'FJI 240-89 joists@ 400 centres built into cavity wallwith plastic sleeves to manufacturersdetails. Provide 30mm deep timber packersto top, screwed with No. 12 screws.

Solid board material (under heatingtongue and groove boards) screwed tojoists @ 300 centres

KL

16A King's Grove,London SE15

First Floor and Roof Details

May 08

8013/310

As Noted

DON KL

STATUS

PROJECT

SUBJECT

SCALE @ A1

BY

DRAWING No.

DATE

CHECKED

REV

REV COMMENTS DATE CHK

NOTES© 2009 Lyons O'Neill Ltd1. This drawing is to be read in conjunction with all

relevant architect's and engineers drawings and

2. Do not scale this drawing

Lyons O'NeillStructural Engineers

Unit 2 Windward HouseSquare Rigger Row

Plantation WharfLondon

SW11 3TU

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

Issued for TenderT1 11-5-09

C3

Construction

KLIssued for ConstructionC1 19-6-09

KLDetail 6 and 7 added, angle addedto sway frame

C2 26-8-09

KLDetail 5 revised. Joists reivisedto Finnforest

C3 8-10-09

Porter-Leake House, Twyford Moors

Architect

Main Contractor

Location

Value

John Pardey Architects

To Be Confirmed

Twyford Moors

Not Disclosed

Architects Design Sketch

Architects Elevations

This project presented a number of challenges for the team. As with any refurbishment project we worked hard to discover how the

existing building was working before we presented solutions to modify it. Along with the existing building investigations, we completed

a comprehensive site investigation to assess the ground conditions on this sloped site. Both the building and site revealed a number of

surprises once analysed fully which went on to heavily influence the final solutions.

We worked to produce a number of schemes at an early stage and illustrated these in sketch form to discuss with the Client. This allowed

both the Client and the Architect to be fully engaged in the structural process and to provide a well coordinated and coherent scheme.

Architects Impression

Lyons O’Neill Sketch

Sweethaws Wood, Redbridge

Architect

Main Contractor

Location

Value

Eldridge Smerin

Redwing Construction

Redbridge

Circa £1.2M

Fairfaced Concrete Sample Panel Cantilevered Roof Overhang

Architect’s Rendered Image

Architect’s Rendered Image - 1

Midway down a single track lane, this woodland retreat presented us with both access and buildabilty issues. Our structural solution had

to allow for small elements to create a larger whole. With a 15m clear span and the inability to get a significant crane to site we looked

hard at the buildability and sequence of construction to inform our solution.

The site constraints lead us to a standardised element with a standardised connection detail which allowed us to create a storey high

Vierendeel truss which sat comfortably within the zones created by the architecture. With all the structure exposed, understanding the

construction tolerances and the sequence meant we were able to develop a series of simple yet effective details to ensure crispness of

finish whilst maintaining ease of build.

15m Span Opening At Pool Level

Erection Of Steel Frame

Architect

Main Contractor

Location

Value

The Weather Room, Hertfordshire

Liddicoat & Goldhill

Stephens & James

Barnet, Hertfordshire

£80,000

We worked closely with our Architect here to produce a fully integrated structure with the lighting. We proposed a structural scheme

which allowed LED lighting strips to be inserted within the structural support fins. We were able to minimise the weight of the structure by

creating a hybrid form which uses the glass for stability. The frame was pre erected off site to ensure build quality and speed of erection on

site.

Internal view 1 - Day

View from the garden

Internal view - Night

Internal view 2 - Day

Internal view 3 - Day

Addison Road, London

Architect

Main Contractor

Location

Value

Michaelis Boyd Associates Ltd

J & Z Construction Ltd

Holland Park, London

Circa £1M

External view

Cantilevered rear structure Steel portal frame redistributing the loads

This project required some integrated temporary works and clear understanding of the building process. The rear two storey structure

in the rear elevation was required to hover above the glass rear extension. We achieved this by using the mass of the main structure

and cantilevering two steel beams out to pick it up. By inserting a new raft below the building, we were able to redistribute loads evenly

eliminating any differential movement.

Lyons O’Neill - Party Wall Elevations

Staircase

Stage 2 - Underpinning Works Carried Out By No. 85

1/301

Extg GL 49.880Extg GL 49.760

SSL 48.160FFL 48.330 FFL 48.330

Top of Existing Brick Wall 51.090

Assumed No. 83 External GL 49.880 15

0

Top of Existing Brick Wall 51.730

Top of Existing Brick Wall 51.110

New masonry wall built off

new RC retaining wall

Existing garage side extension

partially demolished

1/300

1/300

3/300

3/300 1/301

Existing corbel and wall

removed to 150 below

No. 83 external ground level

Garden wallGarden wall

Transitional mass concrete

underpins

RC retaining wall cast in

1m sections

Lintel in new wall to accomodate

existing wall butress

Transitional mass concrete

underpin

150 Mass concrete underpins to

transitional underpins. Provide

H16 dowels in centre of pin @

200 vertical centres

Provide H16 dowels in centre of

wall @ 200 vertical centres

Extg GL 50.010

Extg GL 49.300

Extg GL 49.770

Proposed GL 48.330

Proposed GL 49.300

Top Proposed Brick Wall 52.300

Top of Extg Demolished Brick Wall 51.270

Bottom of Corbel 49.270

New 215 brickwork garden wall

Underside of underpin

Existing side extension

demolished

47.680

47.990

48.360

Top Extg Brick Wall 51.270

4/300

4/300

2/300

2/300

2/301

2/301

Top of No. 85 underpin

New transitional mass

concrete underpin

New mass concrete underpin

to underside of existing

transitional underpin

48.030

Existing garden wall demolished and rebuilt with new 215 thick brickwork wall

1/304

1/304

New 215 brickwork garden wall

Timber roof props garden wall

15

0

48.430

25mm diameter cored weep holes

@ 1m centres at slight incline

Extg GL 50.010

Extg GL 49.300

Extg GL 49.770

Top Extg Brick Wall 51.270

Bottom of Existing Corbel 49.270

Existing garden wall Existing garden wall

Existing corbel footing

Top Extg Brick Wall 51.270

Existing side extension

Sections E-E and F-F

Party Wall Details Sheet 2

C5

Aug 09

8099/301

As Noted

DON KL

STATUS

PROJECT

SUBJECT

SCALE @ A1

BY

DRAWING No.

DATE

CHECKED

REV

REV COMMENTS DATE CHK

NOTES© 2009 Lyons O'Neill Ltd

Construction

1. This drawing is to be read in conjunction with all

relevant architect's and engineers drawings and

2. Do not scale this drawing

Lyons O'NeillStructural Engineers

Unit 2 Windward HouseSquare Rigger Row

Plantation WharfLondon

SW11 3TU

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

84 Addison Road

KLC1 17-8-09Issued for No.83 Party Wall

Agreement

KLC2 10-9-09Issued for No. 85 boundary wallAgreement

Section F-F and 2/301 updated

KLC3 18-9-09Ievel to section F-F

KLC4 23-9-09Ievel corrected and weep holes

added to section F-F

JVZC5 18-3-10Section E-E updated to suit

revised retaining wall

Section E - E - Elevation On No. 83 Party Wall (1:50)

Section F - F - Elevation On No. 85 Party Wall (1:50)

Extg GL 50.010

Extg GL 49.300

Extg GL 49.770

Top Extg Brick Wall 51.270

Bottom of Corbel 49.270

Existing garden wall

Existing side extension

Top Extg Brick Wall 51.270

47.680

47.990

48.360

Mass concrete underpin carried

out by No. 85

RC ground beam behind party

wall carried out by No. 85

TOC 49.560

TOC 49.180

TOC 48.880

Bottom of Corbel 49.120

Stage 3 - No. 84 works complete

Stage 1 - Boundary With No. 85 Existing Condition Section 1/301 (1:20)

Section 2/301 (1:20)

FFL +48.330

Existing Ground Level +49.760

Assumed Grd Level

15

0

Party

Wall CL

No. 83 No. 84

+47.660

SSL +48.160

Existing garden wall

T16 x 600 long dowels @ 600

centres resin to existing

wall and cast into new RC

retaining wall

New 330 thick RC retaining wall.

35

0

1600

New 150 thick RC ground bearing

slab with 2 layers A142 mesh.

Existing garden wall and footing

demolished to 150 below external

ground level

51.090

50mm concrete blinding

SSL +49.180 (8.900)

+47.980 Min (7.700)

EFL +49.350

Party

Wall CL

No. 84 No. 85

Proposed GL +48.330

No. 85 Addison Road.

Information taken from ABA drawing

No. 1019/15128 and Trigram drawing

No. 3450/PW01d. (Values in brackets

relate to Trigrams datum)

+51.270

Existing +49.770

Existing corbels demolished

FFL +48.330

Finishes to Architects

details

Note :

All and

to Architects details

+47.660

+48.010

SSL +48.160

+48.950

35

0

Steps

+49.120

Mass concrete stairs

50mm concrete blinding

Sub Structure well compacted

Existing garden wall replaced

with new 215 thick brickwork

wall

C5

Elsham Road, London

Architect

Main Contractor

Location

Value

Eldridge Smerin

Planning

Holland Park, London

£600,000

Architect’s Rendered Image - 1

Cross Laminated Timber Construction

Architect’s Rendered Image - 2

Situated on a narrow site with both width and height restrictions keeping the structural elements to a minimum was paramount. We

decided to proceed with a cross laminated timber construction which allowed us to maximise space and minimise construction depth. The

structure will be built in 3 days providing a platform and watertight environment from an early stage.

Rear Facade Cross Laminated Timber Frame

Third Floor Level

!"#$%&'()$*)&+,-../'",-01),1&2&345&'",-01),16

4#61/)-0//&50$0$7&8#//'",-01),1&2&345&'",-01),16

'$1-.$9&:.;)"&+,-../'",-01),1&2&+-#;)&'",-01),1*")

8#"".%0#$&+,-../'",-01),1&2&<#*/&="..>)6&'",-01),16

4#61/)-0//&4/#66"..?6'",-01),1&2&345&'",-01),16

@./A."1-&B$C#$1&+,-../'",-01),1&2&345&'",-01),16

!"#$%&'()

Castle Hill Primary School Extension, London

Architect

Main Contractor

Location

Value

ECD Architects

Thomas Sinden

Kingston, London

£2.5M

View From Playground

Curved Roof Overhang

As part of Kingston’s Primary Capital Programme we have worked with the design team to provide the school with 9 new classrooms and a

new dining hall structure. The site is surrounded by a number of mature trees and bounded on one side by the railway. These constraints

meant understanding the build sequence was an important part of the design process and a combination of minipiles and regular piles

allowed us to negate the issue of both the trees and the railway whilst retaining a quick and economical build. The conical roof of the

classrooms was created using a series of simple radial timbers in Kertolam timber which allowed the beams to be installed in one complete

length. The dining hall is constructed using an exposed glulam timber frame which provides a column free and attractive double height

space.

Classroom

Lyons O’Neill Drawing - Tree Root Influence Diagram

Anthony Roper Primary School

Architect

Main Contractor

Location

Value

Shape Architecture

WH Simmonds & Son LTD

Kent

£600,000

View From Approach Road

Internal Hall

Construction completed in March 2011 for this 2 form entry pre school building within green belt land in Kent. The building provides a light

touch onto the site and is fully demountable.

Steel Frame Erection

Lyons O’Neill Drawing - Foundation Plan

Grand Avenue Primary School, Kingston

Architect

Main Contractor

Location

Value

ECD Architects

Willmott Dixon

Kingston, London

Not Disclosed

Upper School - Construction stage

Lower School - Construction stage

As part of Kingston’s Primary Capital Programme we are currently working on a combination of new build and refurbishment work to

bring together a primary and middle school to become one institution. The build includes a new nursery, new and refurbished classrooms,

changing facilities, kitchen areas and a link bridge. Working with the team we looked for opportunities to reuse and refurbish existing

buildings rather than rebuild to both reduce cost and to reduce waste.

Steel Erection and Below Ground Construction

Lyons O’Neill Drawing - Drainage Plan

Tolworth Infant & Junior Schools, London

Architect

Main Contractor

Location

Value

ECD Architects

Modular UK

Tolworth, London

£1.5M

Internal Hall

Internal space

Vibro Stone Column Concrete Pads To Support Modules

This project combines a new dining facility for the school and a new children’s centre. Due to the need for the children’s centre to be at

ground floor level, the larger dining area overhangs, creating an interesting structural form. We have used pre-fabricated modules to ensure

a swift build whilst minimising costs. In addition to the modular build, we have used simple ground improvement techniques to reduce

foundation costs.

Completed Children’s Centre

Erection of Pre-Fabricated Modules

Harrodian Sports Hall, Barnes

Architect

Main Contractor

Location

Value

Paul Brookes Architects

Planning

Barnes

£6M

Architect’s Rendered Image - 3

Architect’s Rendered Image - 2

Architect’s Rendered Image - 1

We are currently working on the scheme for a new sports and entertainment complex at the Harrodian School in Barnes. The school is on

the site of the Former Harrods Sports Club and the original premises have been extended and converted for educational purposes. The

scheme involves sinking the building into the ground to allow the facility to present a minimal elevation to the surrounding properties as the

site is situated on Metropolitan open land. We have completed an extensive desk top study in conjunction with our Geotechnical consultant

to attempt understand the ground conditions as the site is close to a former reservoir and the banks of the Thames. The project is currently

in planning and we hope to begin work on the final scheme in 2012.

Architect’s Sections

Architect’s Plans

Castle Hill Primary School - Dining Hall, London

Architect

Main Contractor

Location

Value

ECD Architects

Thomas Sinden

Kingston, London

Not Disclosed

Piles and ground beams Timber glulam frames

Dining Hall - External View

The dining hall is constructed using an exposed glulam timber frame which provides a column free and attractive double height space.

Dining Hall

Lyons O’Neill Sketch - Dining Hall Structural Options

!"#"$%&'()*(+),#-.&/0"%1/%(2(34)/5(.&/0"%1/%,&1

3,&&(6)7-.&/0"%1/%(2(+0781(.&/0"%1/%,&1

39:(+0);(<)=1.&/0"%1/%(2(>)$%1&(?)=7$(.&/0"%1/%$

@07&4)%%1(+%&11%@4"1#%(2(A#B4"$0(6)$1(A$%7%1$

C"D"1##1(E1$%;))-(<:.&/0"%1/%(2(.#7&/0"%1/%(?%-

?7C"7#-1.&/0"%1/%(2(!/?7&1#(.&/0"%1/%,&1

!"#$%&'(')*++",-%$&

Lyons O’Neill - View 1 From Analysis Model

Steel Frame

Front Facade

The Client came to the design team with a tight site and a need to expand whilst mantaining operations. The Client also had a very hands

on approach to the works but little experience with building.

The existing portal frame shed was erected in the 1970’s on the site of a V1 rocket strike. We came up with a scheme which punctured

the existing structure whilst leaving it mainly unaltered. This gave us the ability to extend the existing footprint within the site boundary

whilst the structure remained 80% occupied. In puncturing the existing structure, we were also able to reuse the existing envelope further

reducing costs.

We worked hard to communicate the structural decisions and processes to enable the Client to engage in the process. This allowed the

structure to influence the design of the building providing a balanced and integrated end product.

Vivienne Westwood HQ - Elcho Street

Architect

Main Contractor

Location

Value

Anarchitect Ltd

Isle Construction

Wandsworth, London

Circa £2M

Bomb Damage Map

Rear View

RC Flat Slab & Columns Option

Front Elevation

!!!"#$%&&%&' ())*+ #&",-#&$!./0 123&&31##$ &$451456

We are currently working on a scheme for a new 5 storey mixed use office and workshop development in Wimbledon.

Working with the Architect we are researching different construction techniques to achieve a robust yet economical structure. The structure

will be highly exposed integrating the structural elements with the architecture. Our challenge is to combine practical construction methods

with industrial and robust finishes.

Burr Road, London

Architect

Main Contractor

Location

Value

Shape Architecture

Robertstown Ltd.

Wimbledon, London

£3.2M

Architects Visual

Architects Visual

Entrance Tunnel

The design of a central screen within the lobby of the Ministry of Sound night club was our challenge. The screen is formed of 11 frames that come to site prefabricated with the Microcables already attached. Each frame has 2 rows of 2.5mm diameter Microcables supported top and bottom that are arranged in a rhythm of colour. The top member is bolted to steel channel that is already fixed in place prior to frames coming to site. The bottom member of the frame is bolted to the existing balustrade which is cut down in height and the cables are tensioned in sequence to the correct tension. The wires can easily be replaced if required.

Ministry Of Sound

Architect

Main Contractor

Location

Value

Block Architecture

TBC

London

Not Disclosed

Welcome Desk

Lyons O’Neill frame axonometric Lyons O’Neill frame section

60 60

2.5mm Diameter 7x7 Flexible wire

rope by Ormiston Wire Limited.

6.0 Thimble by Ormiston Wire

limited

2.5mm Rope Grip by Gripple

Existing 50 x 50 SHS box frame

All to Architect's details

50 x 50 x 75 long x 3 thick folded

plate brackets @ 400 centres

bolted to existing box frame with

M12 (8.8) through bolts

123 x 40 x 1644 long 3 thick folded

channel bolted to brackets with

M6 (8.8) bolts

12mm wide x 15 long vertically

slotted hole. 5.5 edge distance

3mm thick Tee section

Tensioning devise by Gripple.

2.5mm diameter 7x7 Flexible wire

rope by Ormiston Wire Limited.

2.5mm diameter wire with end stop

connection to top detail

All to Architect's details

180 x 90 PFC bolted to existing

slab over with M12 resin anchors

@ each trough location

180 x 90 PFC with horizontally slotted

holes in Bolted to slab PFC

with M16 (8.8) through bolts @ 400

centres horizontally.

Provide 150 long x 78 wide holes @

225 centres to Light to architect's

details

Existing slab

60 60

Axonometric

Base detail

AxonometricHead detail

60 60

2.5mm Diameter 7x7 Flexible wire

rope by Ormiston Wire Limited.

6.0 Thimble by Ormiston Wire

limited

2.5mm Rope Grip by Gripple

Existing 50 x 50 SHS box frame

All to Architect's details

50 x 50 x 75 long x 3 thick folded

plate brackets @ 400 centres

bolted to existing box frame with

M12 (8.8) through bolts

123 x 40 x 1644 long 3 thick folded

channel bolted to brackets with

M6 (8.8) bolts

12mm wide x 15 long vertically

slotted hole. 5.5 edge distance

3mm thick Tee section

Tensioning devise by Gripple.

2.5mm diameter 7x7 Flexible wire

rope by Ormiston Wire Limited.

2.5mm diameter wire with end stop

connection to top detail

All to Architect's details

180 x 90 PFC bolted to existing

slab over with M12 resin anchors

@ each trough location

180 x 90 PFC with horizontally slotted

holes in Bolted to slab PFC

with M16 (8.8) through bolts @ 400

centres horizontally.

Provide 150 long x 78 wide holes @

225 centres to Light to architect's

details

Existing slab

60 60

Axonometric

Base detail

AxonometricHead detail

Located in Shoreditch, this mixed use development posed some interesting buildability issues within the fabric of this Victorian industrial

unit. After providing a condition survey of the existing building, we worked on producing a structural scheme for a 2 storey roof extension

which respected the existing structure. Small elements were used to create a larger whole ensuring all elements could be brought through

existing doorways. This provided an economical and traditional build which suited its setting and the type of contractor who would carry

out this scale of work.

Roof Extension - (Photo by Hannah Taylor)

Construction of Second Floor Extension View Through Rear Windows

LaViande, Shoreditch

Architect

Main Contractor

Location

Value

McLaren Architecture & Design

Miles Builders Ltd

Shoreditch, London

£150,000

Roof Extension - (Photo by Hannah Taylor)

B&Q Show House

Architect

Main Contractor

Location

Value

Foster Lomas Architects

N/A

Bolton

Not Disclosed

Front / Side Elevation

Side Elevation

Part of a series of new show houses within B&Q’s main stores to showcase all their domestic product lines. A series of room sets are

accomodated in the structure illustrating all the rooms in a typical house. The programme was tight with the project being designed and

built in just 5 weeks.

Construction

Front Elevation

Charlotte Street, Fitzrovia

Client

Main Contractor

Location

Value

English Rose Estates

N/A

Fitzrovia, London

Not Disclosed

Front Elevation

Conversion of an existing basement and ground floor office space of a 4 main storey building into a restaurant. The works involved the

removal of various internal load bearing masonry piers at each level, replaced with an arrangement of steel beams spanning onto the

existing party walls in order to provide a column free interior space. The new steels were either kept short or spliced to aid delivery of

these to site, undertaken through a standard doorway.

One of the main internal piers removed at ground floor level was heavily loaded - support to this load was provided using a double height

steel goalpost frame, bearing on a new mini reinforced concrete raft founded at basement level.

Lyons O’Neill Sketch Drawing

Lyons O’Neill Sketch Drawing

Architect - Denning Male PolisanoLocation - London, N7Project Value - £30m

Drayton Park

road to the east and railway lines and the Emirates stadium to the west was redeveloped to provide 225 residential units.

The reinforced concrete framed residential blocks are up to six-storeys in height, with the majority underlain by a single level basement car park.

A Thames Water trunk sewer runs directly below the buildings at the southern end of the site and a Victoria Line underground tunnel runs parallel to the western boundary of the site and partially under the north end of the site.

Given the constraints around the site, the largest part of the structural work was in designing substructures that would carry the building loads, provide the required areas of basement parking and were affordable for the client and acceptable to the three principle statutory authorities.

The substructure proposals used a combination of sheetpiling, bored piling, reinforced concrete rafts and transfer beams to ensure that the optimum design solution was used. In analysing and designing the superstructures, Packman

Excavation of basementSteel sheet piled wall to basement

Finite element model

!"#$%&'()*+&,"-.#/&-/'0'123',"-.#/&-/+

,4$&"567+'(#44,"-.#/&-/'0'2*"4'86'9)*"&44&

9.&'1:-.67%&,"-.#/&-/'0';.6<&',"-.#/&-/*"&

3"6=/)7'>6"?,"-.#/&-/'0'3&77#7%'@64&'>)4#+67)

2."#+/-.*"-.',A&7*&,"-.#/&-/'0'246"#$%&',"-.#/&-/+

2)B.65'24)+&,"-.#/&-/'0';.6<&',"-.#/&-/*"&

!"#$%&'

Christchurch Avenue

Architect

Main Contractor

Location

Value

Claridge Architects

Cube Construction

St Johns Wood, London

£2.0M

Architect’s Impression

Footings Construction

A £2.0M new build housing development consisting of 6 new townhouses. Due for completion July 2012.

Construction

Lyons O’Neill Drawing - Tree Root Influence

Beechmore Road Perspective

Site Overview

We are currently involved in producing a structural feasibility report for this new mixed use residential and retail development. In working

closely with the other consultants at this early stage, we are able to offer the client an added value building which represents the integrated

design approach.

Our main input is to consider basement construction techniques which maximise space whilst moderating cost. This issue will be the

difference between a single or double storey basement carpark which will dramatically effect cost.

141 - 152 Battersea Park Road, London

Architect

Main Contractor

Location

Value

Shape Architecture

TBC

Battersea, London

£15M

Courtyard

Battersea Park Road Perspective

View From Railway Line

View South West From Bridge House

Part of the Masterplan to redevelop the Bridge House and Marion Court estate off Hommerton High Street, Hackney. This project has all

the classic constraints of an East End site along with the additional problem of being located over the new Chelsea to Hackney Crossrail

line. Lyons O’Neill are currently developing the foundation options to give the Client the ability to understand the technical issues and to

make informed decisions on how best to progress the scheme. Along with the detailed design Lyons O’Neill worked on the desk study for

the site including a historical and UXB search.

The scheme is due on site in late October 2010.

Bridge House, Hackney

Architect

Main Contractor

Location

Value

ECD

Planning

Hackney, London

£5M

Lyons O’Neill drainage scheme

View South East From Ponsford Street

This project involved us working in partnership with a local developer to maximise the usable space on the site of a disused public house.

We looked at various methods of construction to both reduce time on site and the amount of spoil removed. Consideration of heave issues

at an early stage allowed us to programme works permitting heave pressures to relieve during the Christmas break. This allowed us to

remove the anti heave piles below the basement raft reducing both costs and programme time.

Cobham Close, London

Architect

Main Contractor

Location

Value

Shape Achitecture

Robertstown Ltd.

Battersea, London

£750,000

Contiguous Piled Wall and Capping Beam Construction of RC Walls

Excavated Basement With Contiguous Piles and Capping Beam Constructed

Lyons O’Neill Drawing - Foundation Plan

Construction

NOTES PROJECT

SUBJECT

SCALE @ A1

DRAWING No.

BY DATE CHECKED

REV

DATE CHKREV COMMENTS

Basement Plan

STATUS

DON1:50 May 07 KL

C37002/100Issued for ground worksTenderT1 24-08-07 KL

Cobham Close, London SW11

(Formally known as Ingenium)Structural Engineers

167 Battersea RiseWandsworth

LondonSW11 1HP

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

Lyons O'Neill

ConstructionIssued to building controlT2 15-10-07 KL

Issued for below ground ConstructionC1 15-11-07 KL

1. This drawing is to be read in conjunction with all relevant architects and engineers drawings and2. Do not scale this drawing3. Contractor to submit proposals of Caltite construction joints for Lyons O'Neill approval.

Piles moved to as built locations, Caltite wall setting out revised to suit.C2 17-11-07 KLIssued for Construction. Lintels updated.C3 08 KL

0 1 2 3 4 5 6 7 8 9 10 M

Basement Plan (1:50)

'A'

'A'

'B'

'A'

'A'

'B'

'B'

'B'

'B'

'B'

'B'

'B'

17516

SSL 15.020

SSL 14.795

SSL 14.795

SSL 15.020

SSL 14.795

SSL 14.795

SSL 14.795

Step

Step

Step

Step

Step

SSL 14.525

SSL 14.525

SSL 14.300

SSL 14.300

SSL 14.300

Step

Step

Step

SSL 15.020

SSL 15.020

Ste

pS

tep

Existing boundary wall footing and underpin

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

400 Thk RC raft

Ste

p

Ste

p

Ste

p

300 Thk RC retainingwall

300 Thk RC retainingwall

300 Thk RC retainingwall

300

300

300

300

300

300

300

300

300

300

300

300

300

Contiguous piled retainingwall

Plies marked ' ' to betrimmed back locally toachieve 150mm Caltite

Contiguous piled retainingwall

Existing footing trimmed locallyto allow for insertion of new RCwall

Temporary batter duringconstruction

Temporary batter duringconstruction

Temporary batter duringconstruction

All slab/wall penetrations smallerthan 150 diameter, to be set outby the Architect

2022

50

2500

165

2500

18

1337

75

510

Ste

p

75

Step

Step

50

50

50

50

Step

50

1688

1688

25

2600

50

50

50300

2325

75

50

50

1660

75

All brickwork and blockworksetting out to Architects details.

3/300

3/300

6/300

6/300

1/3001/300

4/3004/300

5/3005/300

2/3012/301

2/300

2/300

1/3011/301

1/3001/300

4/300 4/300

570

1030

625

1200

1200

625

405

905

'A'

'A'

'B'

'A'

'A'

'B'

'A'

'A'

'B'

'A'

'A'

'B'

1120

1280

925

925

1120

1175

925

925

925

925

1175

1120

1025

925

925

1120

725

725

680

1140

1140

680

725

725

1200

805

1160

755

150 thick Caltite liner wall

150

All contiguous concrete pilesshown in as built locations. Takenfrom survey information issuedby Natta Construction.

All contiguous concrete pilesshown in as built locations. Takenfrom survey information issuedby Natta Construction.

1822

240

1

B

C

D

E

A

2 3 4

F

G

H

65 87 9

4650

4650

2428 7020 1834 17881362 9300 2386

4111

4522

4522

4343

'A'

'B'

450 x 450 hole in slab for inspection chamber

275 diameter hole in slab for gulley

Lintel Schedule (Unless Noted Otherwise)

Span Type Wall Construction

750 - 1800 Catnic CG90/100 Cavity - 100+100+100

Nominal Height

140

1850 - 2100 Catnic CG90/100 Cavity - 100+100+100 160

2150 - 2400 Catnic CG90/100 Cavity - 100+100+100 180

2450 - 3000 Catnic CG90/100 Cavity - 100+100+100 220

Finite Element Model

Architect - Denning Male PolisanoLocation - London, N7Project Value - £30m

Drayton Park

road to the east and railway lines and the Emirates stadium to the west was redeveloped to provide 225 residential units.

The reinforced concrete framed residential blocks are up to six-storeys in height, with the majority underlain by a single level basement car park.

A Thames Water trunk sewer runs directly below the buildings at the southern end of the site and a Victoria Line underground tunnel runs parallel to the western boundary of the site and partially under the north end of the site.

Given the constraints around the site, the largest part of the structural work was in designing substructures that would carry the building loads, provide the required areas of basement parking and were affordable for the client and acceptable to the three principle statutory authorities.

The substructure proposals used a combination of sheetpiling, bored piling, reinforced concrete rafts and transfer beams to ensure that the optimum design solution was used. In analysing and designing the superstructures, Packman

Excavation of basementSteel sheet piled wall to basement

Finite element model

An existing brownfield site situated between Drayton Park road to the east and railway lines and the Emirates stadium to the west was

redeveloped to provide 225 residential units. The reinforced concrete framed residential blocks are up to six-storeys in height, with the

majority underlain by a single level basement car park.

A Thames Water trunk sewer runs directly below the buildings at the southern end of the site and a Victoria Line underground tunnel runs

parallel to the western boundary of the site and partially under the north end of the site.

Given the constraints around the site, the largest part of the structural work was in designing substructures that would carry the building

loads, provide the required areas of basement parking and were affordable for the client and acceptable to the three principle statutory

authorities.

The substructure proposals used a combination of sheetpiling, bored piling, reinforced concrete rafts and transfer beams to ensure that the

optimum design solution was used.Kevin Lyons engineered the structure whilst a Director at Packman Lucas

Drayton Park

Architect

Main Contractor

Location

Value

Denning Male Polisano Architects

O’Shea Contractors

London

£30M

Steel Sheet Piled Wall To Basement

Construction Of RC Ground Floor Slab

Architect - Denning Male PolisanoLocation - London, N7Project Value - £30m

Drayton Park

road to the east and railway lines and the Emirates stadium to the west was redeveloped to provide 225 residential units.

The reinforced concrete framed residential blocks are up to six-storeys in height, with the majority underlain by a single level basement car park.

A Thames Water trunk sewer runs directly below the buildings at the southern end of the site and a Victoria Line underground tunnel runs parallel to the western boundary of the site and partially under the north end of the site.

Given the constraints around the site, the largest part of the structural work was in designing substructures that would carry the building loads, provide the required areas of basement parking and were affordable for the client and acceptable to the three principle statutory authorities.

The substructure proposals used a combination of sheetpiling, bored piling, reinforced concrete rafts and transfer beams to ensure that the optimum design solution was used. In analysing and designing the superstructures, Packman

Excavation of basementSteel sheet piled wall to basement

Finite element model

Architect - Denning Male PolisanoLocation - London, N7Project Value - £30m

Drayton Park

road to the east and railway lines and the Emirates stadium to the west was redeveloped to provide 225 residential units.

The reinforced concrete framed residential blocks are up to six-storeys in height, with the majority underlain by a single level basement car park.

A Thames Water trunk sewer runs directly below the buildings at the southern end of the site and a Victoria Line underground tunnel runs parallel to the western boundary of the site and partially under the north end of the site.

Given the constraints around the site, the largest part of the structural work was in designing substructures that would carry the building loads, provide the required areas of basement parking and were affordable for the client and acceptable to the three principle statutory authorities.

The substructure proposals used a combination of sheetpiling, bored piling, reinforced concrete rafts and transfer beams to ensure that the optimum design solution was used. In analysing and designing the superstructures, Packman

Excavation of basementSteel sheet piled wall to basement

Finite element model

Aldermans Hill, London

Architect

Main Contractor

Location

Value

Curl La Tourelle

Cunnane & Donaghey

Palmers Green, London

£1.3M

Beam and Block Ground Floor Layout

Second Floor and Timber Roof Construction

8-9m Span Internal Space

A £1.3M Design & Build project where we have incorporated large open spans to give the developer and tenants a very flexible space. The

building will comprise of 8 flats at Ground and First floor levels and 2 penthouses at Second floor level. The project is due for completion

late 2011.

Lyons O’Neill Drawing - Roof Plan

Front Elevation

0 1 2 3 4 5 6 7 8 9 10 M

110-112 Alderman's Hill

Roof Plan

Sep 10

10119/107

1:50

DON KL

STATUS

PROJECT

SUBJECT

SCALE @ A1

BY

DRAWING No.

DATE

CHECKED

REV

REV COMMENTS DATE CHK

NOTES© 2011 Lyons O'Neill Ltd1. This drawing is to be read in conjunction with all

relevant architect's and engineers drawings andspecifications

2. This drawing is only to be scaled from for the purposesof estimating and approximate sizing only. If exactdimensions are relied upon, written dimensionssupersede any scaled dimension. Overall setting outis to Architect's details and this drawing thereforeshould be read in conjunction with their information.

Lyons O'NeillStructural Engineers

Unit 214 Weller Street

LondonSE1 1QU

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

KLIssued as a Record DrawingR1 15-2-12

R1

Record Drawing

Roof Plan (1:50)

TB1

Member Size

Timber Beam Schedule

3 No. 200 x 50 C24 timbers bolted together with M12 (8.8) bolts @ 600 centres.

TB2 2 No. 250 x 50 C24 timbers bolted together with M12 (8.8) bolts @ 600 centres.

TB4 2 No. 200 x 50 C24 timbers bolted together with M12 (8.8) bolts @ 600 centres.

TB5 200 x 50 C24 timber joist.

TB3 2 No. 150 x 50 C24 timbers bolted together with M12 (8.8) bolts @ 600 centres.

TB6 2 No. 250 x 50 C24 timbers with 250 x 15 S275 plate bolted together with M12 (8.8) bolts @ 600 centres.

TB7 250 x 50 C24 timber joist.

TB8 3 No. 250 x 50 C24 timbers bolted together with M12 (8.8) bolts @ 600 centres.

TB9 2 No. 200 x 50 C24 timbers with 200 x 15 S275 plate bolted together with M12 (8.8) bolts @ 600 centres.

Member Size

Timber Rafter Schedule

TR1 200 x 50 C24 @ 400 centres

Member Size

Timber Joist Schedule

TJ1 150 x 50 C24 @ 400 centres

Rafters - TR1

Flat Roof -

TJ1

TB1

TB1

TB1

TB1

Note :

All rafters to be TR1 - 200 x 50 C24timbers @ 400 centres unless notedotherwise

TB4

TB4

TB5 TB

5

TB5

TB5

TB5

TB5

TB7

TB5

TB5

TB5

TB5

TB5

TB7

TB7

TB7

TB5

TB5

TB5

TB5

TB5

TB5

TB7 TB7

Note :

All rafters to be TR1 - 200 x 50 C24timbers @ 400 centres unless notedotherwise

Turret structure :150 x 50 timber hip members andrafters. Provide ply sheathing toexternal face of timbers.

Rafters - TR1

Rafters - TR1

Rafters - TR1

Rafters - TR1

Rafters - TR1

Flat Roof -

TJ1

TB4

TB4

Flat Roof - TJ1

TB4

TB4

Flat Roof - TJ1

TB4

TB4

150 x 50 flat roof joistsat low level.

150 x 50 flat roof joistsat low level.

150 x 50 flat roof joistsat low level.

150 x 50 flat roof joistsat low level.

TB4 TB4

TB4

TB4 (on Slope)TB4 (on Slope)

TB4 (on Slope)TB4 (on Slope)

150 x 50 roof rafters thislocation only.

A

A

B

B

C

C

D

D

F

F

G

G

1 1

3 3

4 4

5 5

7 7

8 8

E

E

2 2

6 6

B10119/20110119/201

B

1011

9/20

0

A

10119/200

A

1237.53578

35803870

32881350

1015

3735 3015 3895 1880 5030 3735

Setting out of all service penetrationsto Architect's and Services Engineersdrawings.

!"#$%&"'()(*+,-&$*&#."$-#$(/(0+%#1(*&#."$-#$2&-

3%245(6-&7%47(8-4$&-*&#."$-#$(/(9-':%;#&%<$(=&"<<"4

>.-(?"7$-4"45(6%7$7*&#."$-#$(/(@%7$-&(?%A'7(*&#."$-#$7

BC=BDDDDD?EF*&#."$-#$(/(G.%4'(H"$#.-4(I*&$"7$J

G$&'$<%&:(H"%717*&#."$-#$(/(G$2:"%(E#$%K"

!"#$%&%'())*+,#-

Simple cable tensioning springs

7m high carbon fibre gullwing doors The gallery space

Viewed from both within the gallery and from the balcony above, the structure has the opportunity to present two faces. The structure is

essentially all external allowing the internal space to be free of obstruction and ultimately flexible to the curator.

The lightweight box is achieved by suspending the roof members with a series of 1.5mm diameter cables from a simple frame hidden

within the roof lantern. This allowed us to maximise the structural capacity of the sections creating a simple but elegant roof. The cables

were individually positioned through holes in the roof level frame and tied together before constructing the box. Once installed the cables

were draped and pushed through individual clutches to support the roof. Small springs were introduced to the cables to ensure tension was

always present even with variation of loading and construction tolerances. The installation process was prototyped to develop a sequence

of working which allowed the structure to be delivered within programme and budget.

The entrance to the space creates a transitional lobby where a perceptual shift from the V&A proper to the Contemporary program is

allowed to occur. It has been designed to offer different forms of access to the gallery through five seven-metre high rotating screens.

The screens can be reconfigured to the curatorial needs of each exhibition and are clad in reflective black carbon fibre sheeting, a very

lightweight skin more commonly found in aircraft manufacture.

Victoria & Albert, London

Architect

Main Contractor

Location

Value

Block Architecture

WS Aspinalls

Victoria & Albert Museum, London

£600,000

Lyons O’Neill Sketch

Cable roofspace

The Listening Posts

Architect

Main Contractor

Location

Value

Foster Lomas Architects

Competition

Aldgate, London

Not Disclosed

Architects Impression

Lyons O’Neill have been shortlisted along with 4 other practices for a new installation in the heart of the City. The sculpture marks a part of

London’s High Street 2012 initiative and will remain in place for the duration of the 2012 Olympic Games. It will stand on a site historically

known as ‘Ale-Gate’, so called because it was the only City gateway open to all. It is hoped the new landmark will underscore the fact that

the City now welcomes, rather than drives away, its neighbours.

We responded to both the temporary nature of the installation and the congested nature of the site by introducing a light touch structure

which can be installed using the minimum of plant and without closing the road. This fully interactive installation can be simply demounted

leaving the site exactly as it was and can easily be reinstalled in another location as a more permanent piece.

Lyons O’Neill Sketch - Structural Approach

Elevation

Young Persons Centre

Architect

Main Contractor

Location

Value

Meadowcroft Griffin Architects

Thomas Sinden

Ealing, London

£1.8M

Front View - Blockwork Infill Construction

Steel Frame Model Rear View - Steel Frame Erection

A £1.8M redevelopment of Ealing’s award winning youth centre using a lightweight steel structure to minimise the foundation impact on the

sensitive boundary conditions.

Lyons O’Neill - Stage ‘D’ Sketch

Lyons O’Neill - Steelwork Model

HIGH.....LOW, London

Architect

Main Contractor

Location

Value

Shona Ktchen (Artist)

N/A

Deptford, London

Not Disclosed

Architects Design

Connection Detail

A solar powered landmark synchronised with the tide, HIGH.....LOW serves as a tribute to the historical importance of Deptford’s all-but-

forgotten tidal creek.

The artwork, an illuminated sign made up of the words HIGH.....LOW, spans 21m and is 1.5m high.

Stratford Kiosks

Architect

Main Contractor

Location

Value

Studio Octopi

Competition Win

Stratford, London

£300,000

Architects Plan

Architect’s Rendered Image - 1

This was a winning scheme for the RIBA competition for a set of Kiosks at the entrance to Stratford Station. This Olympic project required

the kiosks not only to perform as a functioning retail unit but also provide a sense of space and for a portal for approaching spectators.

We used a combination of Reinforced concrete and CLT Panels to form this panalised building. The concrete base was extended up to

form a robust skirt and which also acted as a security barrier to the station and the buses which entered the adjacent station. The CLT

panels allowed the structure to be quickly assembled in the space as well as providing a self finishing structure. The use of screw piles for

foundations meant the structure is completely demountable if required.

Lyons O’Neill sequence of construction sketch

Architect’s Rendered Image - 1

!"#$%&'()%*"'+,(-./0$-0%1%23'(0$0%,(-./0$-03($

4.$56$'%783'($,(-./0$-0%1%9/5)/:6":%;/:<

&$#=(/+<$%&5'-$4":0('-0"(%1%>/<%>'6$#$:0%4"#?':@

AB/:<0":%C$D64":0('-0"(%1%>/<%>'6$#$:0%4"#?':@

E5$(=@%70($$0,(-./0$-0%1%7.'?$%,(-./0$-03($

7#/0.%F$(('-$,(-./0$-0%1%&F&%,(-./0$-06

!"#$%$&'#

Ovington Mews, London

Architect

Main Contractor

Location

Value

N/A

Basement Building Company

Chelsea, London

Not Disclosed

Basement & Ground Floor Construction

Basement

Ground Floor Construction

This two storey basement in an in fill site between a number of properties presented a number of challenges. Understanding the context

of the building in relation to the boundaries was key on this project. Having around 20 party wall awards a robust and consistent approach

was required as well as clear and informative drawings. A combination of traditional and innovative grouting techniques were used to

stabilise the ground and retain water during the works. Monitoring stations with trigger levels were agreed with the boundary Engineers to

ensure works progressed safely and without disruption.

RC Boundary Retaining Wall Construction

Lyons O’Neill - Boundary Wall Section Details

Many local authorities now require pre planning structural reports when considering basements. We have produced a number of these

reports and developed a report style which focuses on the process as much as the solution. This is to inform both professionals and lay

Clients our key decisions and to inform the planners of the viability of the scheme.

Lyons O’Neill - Scheme Section

Chelsea Square front elevation

8 Chelsea Square, Chelsea

Architect

Main Contractor

Location

Value

Wilkinson King

TBC

Chelsea, London

£1.5M

Lyons O’Neill - Sequence Of Construction Sketches

Home Park Road, London

Architect

Main Contractor

Location

Value

Quartet Architecture

Oakbuild London Ltd

Wimbledon, London

Not Disclosed

Site Construction - RC Capping Beam

Architect’s Section

This basement was located on a sloped site with some unique geotechnical issues. Being almost at the natural slip angle for London Clay,

stabilisation of the slope during the works was a key element of the works. Being able to illustrate the issue to the team and Client meant

that the position of the of the swimming pool was altered to provide a much cheaper retaining structure. This process of illustrating possible

solutions meant the Client had an understanding of his building and was able to make informed decisions on the structure. We looked

closely at the build process to help drive out key cost items and to enable party wall awards and planning to be easily achieved.

Lyons O’Neill Sketch - Construction Sequence

Site Construction - King Post Retaining Wall & RC Capping Beam

Final Construction Works Front Of Property

Temporary Propping Of Existing Ground Structure While Excavation Occurs Steel Frames In, Basement Slab Under Construction

This project required us to tunnel under an existing building whilst the Client was still in occupation. We investigated the build process

through drawing to come up with a permanent structure which also was used as the temporary works. We came up with a series of frames

which were introduced at 1.2m centres on mass concrete bases and underpins. Once these were installed and the slab supported, the

beams were spliced allowing a number of temporary columns to be removed and the spec opened up.

Pembridge Place, London

Architect

Main Contractor

Location

Value

N/A

Big Basement

London

Not Disclosed

Lyons O’Neill Sequence Of Construction Sketch

Steel Frames Supporting Existing Floor Over

Elerby Street, London

Architect

Main Contractor

Location

Value

Shape Architecture

AOI Developments Ltd

Fulham, London

N/A

Basement Construction

A more straight forward single basement construction and typical of a number of residential conversions. We looked at the build sequence

here and established it would be cheaper to rebuild the rear extension rather than retaining the structure which was proposed by a previous

Engineer. The savings on temporary works allowed the Client to extend the basement providing greater value a much more usable space.

Again this project required a pre-planning report and construction method statement which we provided at an early stage allowing for a

straight forward party wall and planning process.

NOTES PROJECT

SUBJECT

SCALE @ A1

DRAWING No.

DON

BY

Aug 09

DATE

KL

CHECKED

REV

DATE CHKREV COMMENTS

1. This drawing is to be read in conjunction with all relevant architects and engineers drawings and

2. Do not scale this drawing

Sections A - A and B - B

9112/200

18 Ellerby Street, SW6

STATUS

Lyons O'NeillStructural Engineers

Unit 2 Windward HouseSquare Rigger Row

Plantation WharfLondon

SW11 3TU

+44 (20) 7223 [email protected]

lyonsoneill.co.uk

© 2009 Lyons O'Neill Ltd

C2Issued for ConstructionC1 25-9-09 KLConstruction

1:50Updated to suit Contractors requirementsC2 7-10-09 KL

b a ` _ ^

45

0

25

0

25

0

40

0

30

0

Boundary

FFL 100.000

FFL 99.500SSL 99.422

FFL 96.330

SSL 96.060SSL 95.920

FFL 96.180

FFL 96.830

FFL 97.175

SSL 96.560SSL 96.440

TOC 99.310TOC 99.425

Doorhead 98280

TOS 102.334

TOC 99.705

45

0

300

25

0

Monopitch Roof Void

Detail 2/330

Detail 1/310

Detail 8/320Detail 7/320

Detail 2/310

Detail 9/320

Detail 4/320

Sections for detail reference location and

general building orientation only.

Refer to general arrangement's

and details for all other information

Section A - A (1:50) Section B - B (1:50)

Key Plan

^ ^

_

_

FFL 99.500SSL 99.422

FFL 96.330

SSL 96.060

TOS 102.334

TOC 98.490

Detail 6/320

Detail 1/330

Detail 1/340

No. 16No. 18No. 18No. 20

Note :

Fabrication drawings must be submitted

to Lyons O'Neill for approval 1 week

prior to fabrication.

C2 C2

Lyons O’Neill Drawing - Sections

Construction Site With Perimeter Temporary Works

Smith Terrace, Chelsea

Architect

Main Contractor

Location

Value

PTP Architects

Big Basement Company

Chelsea, London

Circa £1M

Lower Level Piling Construction Stage View looking out at rear

Lyons O’Neill Drawing - Section

We continued our work with the Big Basement Company on this 2-Storey basement on a constricted site in Chelsea. The scheme called

for demolition of the structure whilst only retaining the facade which presented a difficult set of temporary stability scenarios. We worked

closely with the Big Basement Company to come up with a sequence of construction which allowed the permanent floor structure to act as

both temporary and permanent works. This created a saving not only in cost of temporary works but also in time on site. The construction

sequence was illustrated to both investigate and explain the process and was used as part of the party wall submission accelerating the

process.

The high water level in the area meant we adopted a hybrid foundation solution to maximise the space available to the client whilst

maintaining stability of the surrounding structures. The solution involved a traditional underpin to the upper basement level which allowed

a full width basement and then progressing to a secant mini-piled wall solution below the water table. This secant piled retaining wall

structure penetrated into the clay strata below the site which allowed us to excavate below the water table in dry conditions.

Lyons O’Neill Drawing - Cross Section Details

Basement Construction

!"##$%&"'()*$#+,(!"--.#/0&+1/+(2(3"4-(5#$$61,(.#/0&+1/+,

7$#8$-6(3-"9"(!$+1-.#/0&+1/+(2(:-"#&%;1(.#/0&+1/+,

.(<$$=(>$#(?$'%$'

.#/0&+1/+(2(<&/0"#%(@"#6-"'%(.#/0&+1/+,

A4B,(!$,*&+"-.#/0&+1/+(2(C0$=",(!1"+01#D&/6

<&*-1B(E&--";1(!"--.#/0&+1/+(2(F:G(.#/0&+1/+,

C01(!"',$=(:"H.#/0&+1/+(2()0"*1(.#/0&+1/+4#1

!"#$%&'(')"*+,-"

Boiler Suit Detail Closeup On Cladding Braid

Construction Of Cladding Panel

Reveal detail

Our challenge on this project was to create a complex 3 dimensional form with simple 2 dimensional elements. The centrepiece of the

scheme is the ‘Boiler Suit’, a facade surrounding the boilers that power the hospital. The final facade is formed of 108 tiles made of 40km

of woven stainless-steel braid.

At night the Boiler Suit is illuminated ‘to provide a distinctive welcoming beacon for staff and visitors arriving at the hospital’.

The scheme also includes widened pavements, a one-way traffic system with designated drop-off points, new signage, CCTV, lighting and

a new build shop.

The project has been funded by the Pool of London Partnership, Guy’s and St Thomas’ Charity and the Friends of Guy’s Hospital.

Kevin Lyons engineered the structure whilst a Director at Packman Lucas

Guys Hospital, London

Architect

Main Contractor

Location

Value

Thomas Heatherwick

Crispin and Borst

London Bridge, London

£2M

Boiler Suit Over Boiler Room

Corner View On Boiler Room

Norfolk Plaza Hotel, London

Architect

Main Contractor

Location

Value

Claridge Architects

Planning

Paddington, London

£4.0M

Architects Impression - 1

Bomb Damage Map

Site: 29-33 Norfolk Square, London W2 Fig No: B

Date: 03 February 2011

Southern Testing: Keeble House, Stuart Way, East Grinstead, West Sussex RH19 4QA

ST Consult: Twigden Barns, Brixworth Road, Creaton, Northampton NN6 8NN

A £4M reburbishment of an existing hotel which consists of major internal alterations and a new bar at roof level.

Lyons O’Neill Scheme Drawing

Architects Impression - 2

Harrodian Sports Hall, Barnes

Architect

Main Contractor

Location

Value

Paul Brookes Architects

Planning

Barnes

£6M

Architect’s Rendered Image - 3

Architect’s Rendered Image - 2

Architect’s Rendered Image - 1

We are currently working on the scheme for a new sports and entertainment complex at the Harrodian School in Barnes. The school is

on the site of the Former Harrods Sports Club and the original premises has been extended and converted for educational purposes. The

scheme involves sinking the building into the ground to allow the facility to present a minimal elevation to the surrounding properties as the

site is situated on Metropolitan open land. We have completed an extensive desk top study in conjunction with our Geotechnical consultant

to attempt understand the ground conditions as the site is close to a former reservoir and the banks of the Thames. The project is currently

in planning and we hope to begin work on the final scheme late in 2011.

Architect’s Sections

Architect’s Plans

A Room For London - A World Apart

Architect

Main Contractor

Location

Value

Richard Markland Architects

Competition

London

N/A

Room Cantilevered Over Edge Of Building

Glass Floor Used At Cantileved Edge Front Elevation

It should feel slightly daring to be in this space; not dangerous but a definite shift from normality, a juxtaposition of the familiar pushed into

a new context. Uninitiated onlookers will wonder what it is at first: purely a sculpture or something more? On their daily commute they can

see how it changes in the light: reflecting conditions and giving new perspectives. They will become aware it is occupied which can only

add to the intrigue. Guests will become more comfortable over time as they absorb their new surroundings. Initial concerns about exposure

give way to the possibilities offered by their temporary home. How often will you get to lie in bed as the sun rises over the London skyline

all around you? Or lie in darkness and observe the city at night?

Main Frame Anchored To Slab

Exploded Axonometric

Hansom Cab, London

The Hanson Cab

Lyons O’Neill were commissioned to produce a condition report on this grade II public house constructed in the early 19th century. Our

study soon revealed that the structure, which appeared to be uneconomical to refurbish, could be made robust by some simple yet

effective remedial measures. This allowed our client to purchase the building with the confidence he could redevelop the residential space

above.

As part of the refurbishment work we developed a structural scheme which allowed a new access to the flats and toilet facility to be

created for the pub whilst it still operated. This was achieved by forming a lightweight structure which spanned across the roof of the

kitchens to the pub sitting purely on the external walls. The link between the pub and their new facilities will be switched over during a

fortnight of light refurbishment works to the pub allowing maximum trading time.

Architect

Main Contractor

Location

Value

Shape Architecture

Robertstown Ltd

Earls Court Road, London

£300,000

Existing Timber Trussed Spine Wall

Lyons O’Neill Drawing - General Arrangements

0 1 2 3 4 5 6 7 8 9 10 M

C beam overL

Existing roof joists over

to be trimmed and hung

off new steel beams

Existing joists

Existing joists

100 x 100 x 10 SHS on

440 long x width of wall

x 215 deep mass concrete

padstone

254 x 254 x 73 UC

25

4 x

10

2 x

22 U

B

25

4 x

10

2 x

22 U

B2

54 x

10

2 x

22 U

B

25

4 x

14

6 x

37 U

B

254 x 102 x 22 UB

Adjacent Property

Party Wall

9/300

9/300

8/3008/300

7/300

7/300

6/300 6/300

New cavity wall xed back

to existing masonry with

Fir x wall plate system

New cavity wall xed back

to existing masonry with

Fir x wall plate system

New door openings. 150 deep

precast lintels over. No. to suit

width of opening

254 x 146 x 37 UC

25

4 x

10

2 x

22 U

B

25

4 x

10

2 x

22 U

B

1/301

1/301

Brickwork skin supported on

Ancon Optima support system

200 x 50 C25 timber

joists @ 400 centres

200 x 50 C25 timber joists

@ 400 centres (Typical)

Existing joists

254 x 102 x 22 UB

Expamet M305 straps @ 1200 centres

built into cavity wall and xed to minimum

3No. joists with 1No. No.12 woodscrew per

joist. Provide blocking in line of strap.

Expamet M305 straps @ 1200 centres

screwed to UB beam and xed to minimum

3No. joists with 1No. No.12 woodscrew per

joist. Provide blocking in line of strap.

2/301 2/301

Exis

tin

g B

eam

15mm thick plate to top of

UB stopped 100mm from face

of wall

254 x 102 x 22 UB

Existing roof lights shown dotted.

Roo ights under steels to be

removed and openings sealed

prior to erection of steels.

Provide void in plate to allow

drainage.

Column under

3/301 3/301 254 x 102 x 22 UB

Adjacent Property

Party Wall

2/300

2/300

1/300

1/300

3/3003/300

4/3004/300

4/3004/300

Expamet M305 straps @ 1200 centres

built into concrete block and xed to

minimum 3No. joists with 1No. No.12

woodscrew per joist. Provide blocking

in line of strap. See detail 4/300.

200 x 50 C24 timber joists

@ 400 centres (Typical)

Double up joists around roof

voids. Bolted together with M12

(8.8) bolts @ 600 centres. (Typical)

5/3005/300

Part First Floor Plan (1:50)Part Ground Floor Plan (1:50)

NOTES PROJECT

SUBJECT

As Noted

SCALE @ A1

DRAWING No.

DON

BY

Date

DATE

KL

CHECKED

REV

DATE CHKREV COMMENTS

1. This drawing is to be read in conjunction with all relevant architects and engineers drawings

2. Do not scale this drawing

3. Refer to drawing No. 7001/999 for Structural Speci cation

Ground - Second Floor Plans

C27001/100Issued for ConstructionC1 30-10-07 KL

The Hansom Cab

Construction

STATUS

Structural Engineers

1 Arundel Court16 Beckenham Grove

BromleyKent

BR2 0XN

+44 (20) 3236 [email protected]

lyonsoneill.co.uk

Lyons O'Neill

© 2007 Lyons O'Neill Ltd

UC beam moved 600mm to remove need for cranked beam, steelwork revised to suit

architects comments. Column added at ground oor to prop existing beam girder.

C2 22-12-07 KL

Part Second Floor Plan (1:50)

C2

C2

C2

C2

C2

!"#$%#&'()*+#'&!"#

,-#&(.&/0-&1*

2*-0(34"0/5-0%

64"/7(3$"8(.&/0-&1*9*14&%(:-$$

We worked closely with the Architect to produce a series of structural options for this new village community centre. In various workshops we investigated and presented different materials, structural systems and arrangements to go forward to the feasibility study.

Architect’s Visual

Architect’s Visual

!"#$%#&'()*+#'&!"#

,-#&(.&/0-&1*

2*-0(34"0/5-0%

64"/7(3$"8(.&/0-&1*9*14&%(:-$$

Ripley Village Hall, Ripley

Architect

Main Contractor

Location

Value

ECD Architects

TBC

Ripley

£1.4M

Lyons O’Neill Sketch - Roof Options

!"#$%#&'()*+#'&!"#

,-#&(.&/0-&1*

2*-0(34"0/5-0%

64"/7(3$"8(.&/0-&1*9*14&%(:-$$

Architect’s Visual

Spitfire Memorial

Artist

Main Contractor

Location

Value

Christopher Draper

Competition

Southampton

N/A

Artist Vision

A shortlisted scheme for the erection of a 60m high memorial to Reginald Mitchell’s legendary Spitfire.

Competition held by the Daily Telegraph.

Lyons O’Neill - Sequence Of Construction Sketches

Sequence 1

Sequence 2

Sequence 3

Sequence 4

Stratford Kiosks

Architect

Main Contractor

Location

Value

Studio Octopi

Competition Win

Stratford, London

£300,000

Architects Plan

Architect’s Rendered Image - 1

This was a winning scheme for the RIBA competition for a set of Kiosks at the entrance to Stratford Station. This Olympic project required

the kiosks not only to perform as a functioning retail unit but also provide a sense of space and for a portal for approaching spectators.

We used a combination of Reinforced concrete and CLT Panels to form this panalised building. The concrete base was extended up to

form a robust skirt and which also acted as a security barrier to the station and the buses which entered the adjacent station. The CLT

panels allowed the structure to be quickly assembled in the space as well as providing a self finishing structure. The use of screw piles for

foundations meant the structure is completely demountable if required.

Lyons O’Neill sequence of construction sketch

Architect’s Rendered Image - 1

Our aim was to provide a simple form which respected the low lying setting and did not dominate the horizon. The site’s geology means

that the West bank has better founding conditions than the East pushing us towards a solution supported from one side only. After drawing

up various options it became clear that completely supporting from one side would provide too dominant a form which was something

we were working against. As a result we looked at a simply supported solution and tried to refine them to provide a slender elevation. We

settled on a simple parallel chord truss form and worked to reduce its elevation. To improve its depth we introduced a column on the West

Bank to balance the bridge’s forces and allow us to present a slimmer elevation. The form is tried and tested and is made up from simple

elements requiring low levels of fabrication. To reduce the dominance of the structural members we further refined the truss by using the

longitudinal cladding to laterally restrain the main members against buckling. This will allow us to further reduce their cross section and

therefore the bridge’s weight and cost.

Internal View

Bridge Elevation

!"#$%&'()*+,-(.-*/$,(0"12,3*3*"4

!"#$%&'()#

56,(7-*/$,(*'(&('%,4/,-(7"8(9"-1(36&3(-,*49"-:,'(36,(9%&34,''("9(36,('*3,;(!-&1&3*:&%%<(2,-:6,/("4(36,(3="(-,7#*%3(,17&4>1,43'("4(,*36,-('*/,("9(36,(-*+,-?(36,(9"-1(/",'(4"3(-,+,&%(6"=(*3("2,-&3,'('3-#:3#-&%%<(#43*%(<"#(&-,("4(*3;(@,(36*4>("9(36,(7-*/$,(&'(&4(*43-*$#*4$(%&4/':&2,(,%,1,43;(56,(7-*/$,(*'(:%&/(,83,-4&%%<(*4(9%&3(3*17,-(',:3*"4'(36&3(:6&4$,(36-"#$6(36,(2%&<("9(%*$63("4(36,('#-9&:,(&'(<"#(&22-"&:6;(

(56,(7%#--,/(3*17,-(:%&//*4$(36&3(9&/,'(&:-"''(36,('2&4(=*%%(-,&:3(3"(36,(/&*%<(:6&4$,(*4(%*$63(:"4/*3*"4';(A4('#4%*$63?(/&<%*$63("-(1""4%*$63(36,(9"-1(=*%%(:"4'3&43%<(:6&4$,(&'(<"#(:-"''(36,(7-*/$,;(56,(2%&<("9(%*$63(&4/('6&/"=("4(36,('#-9&:,'("9(36,(7-*/$,(&4/(36"',(=6"(:-"''(*3(,4-*:6,'(36,(,82,-*,4:,("9(36*'(2%&:,;

56,(7-*/$,(-,9%,:3'(36,(1&3,-*&%*3<("9(36,(2-,+*"#'(-&*%=&<(7-*/$,("4(36,('*3,(#'*4$(7"36('3,,%(&4/(3*17,-('3-#:3#-&%%<;(B&7*3&3(:"44,:3*+*3<(6&'(7,,4(&:6*,+,/( 36-"#$6( *43,$-&3*"4("9("+&%(2*2,'(7,4,&36( 36,(/,:>(&%%"=*4$(&4*1&%'( 3"( 3-&+,%(&:-"''( 36,(-*+,-;

%&'()#$*+$,-.#&/*0#

56,(7-*/$,(2-"+*/,'(&(3-&4'*3*"4(&:-"''(36,(-*+,-;(56,('3-#:3#-&%(3*17,-(:%&//*4$(9&/,'(&:-"''(*3'('2&4(7,:"1*4$(*4:-,&'*4$%<("2,4(9-"1(=,'3(3"(,&'3(-,9%,:3*4$(36,(1"3*"4(7%#-(<"#(,82,-*,4:,(=6*%'3(-*/*4$(&(7*>,;(C'(<"#(:-"''(<"#(&-,(,*36,-(-,%,&',/("43"(36,(9%&3(%&4/':&2,("9(36,(,&'3(,17&4>1,43("-(:"4'#1,/(7<(36,(=""/,/($-,,4=&<("4(36,(=,'3

%&'()#$*+$1*-(+0*2#

@,(/"(4"3(',,(36,(7-*/$,(&'(&(%&4/1&->(36&3("2,-&3,'(*4(:"43-&'3(=*36(36,(%&4/D':&2,( *4(=6*:6( *3('*3';(E#-(7-*/$,( *'(4"3(&('3&3,1,43( *4( 36,( %&4/':&2,(7#3(&4(,%,1,43("9(36,(%&4/':&2,(36&3(:-,&3,'(&(2%&:,;(C'(0&-%(C4/-,("7',-+,/(F':#%2D3#-,(*'(2%&:,G;(( A4("36,-(="-/'(=,(',,(36,(7-*/$,(&'(&(':#%23#-&%(,%,1,43(36&3(,46&4:,'(36,(H#&%*3*,'("9(36,('*3,?(-,*49"-:*4$(36,(',4',("9(2%&:,;

3.&40.4&*5$/6&7

E#-(&*1(=&'(3"(2-"+*/,(&('*12%,(9"-1(=6*:6(-,'2,:3,/(36,(%"=(%<*4$(',33*4$(&4/(/*/(4"3(/"1*4&3,(36,(6"-*I"4;(56,('*3,G'($,"%"$<(1,&4'( 36&3( 36,(@,'3(7&4>(6&'(7,33,-( 9"#4/*4$(:"4/*3*"4'( 36&4( 36,(J&'3('#$$,'3*4$(&('"%#3*"4('#22"-3,/(9-"1("4,('*/,("4%<;(C93,-(/-&=*4$(#2(+&-*"#'("23*"4'(*3(7,:&1,(:%,&-(36&3(:"12%,3,%<('#22"-3*4$(9-"1("4,('*/,(="#%/(2-"+*/,(3""(/"1*4&43(&(9"-1(&4/(%"">,/(9"-(&('*12%<('#22"-3,/('"%#3*"4(36&3(=,(:"#%/(-,9*4,(3"(2-"+*/,(&('%,4/,-(,%,+&3*"4;(

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

%&*0'-)$8#.*'5$9:;

KL11(36*:>(%#$(2%&3,(=,%/,/(3"(MBM

N&*4('*/,(3-#'','(9#%%<(=,%/,/&4/('2%*:,/("4('*3,(3"(9"-19#%%(%,4$36

<5*(('-)$8#.*'5$9:;

O4";(NKO(P&%+&4*',/(."%3'

KQL8RQ11(3*17,-(:%&//*4$(S(%&3,-&%(-,'3-&*43

5*17,-(-,:,'',/(3"(%":&3,(2%&3,

5"2(&4/(7"33"1(3-#''(7"%3,/(3"(1&*4(3-#''(%#$(2%&3,'(#'*4$('*12%,(7"%3,/(:"44,:3*"4

J&'3

@,'3

3=<!,>?$!>@AB83$@=3!$%A?C$9:;DE1A?$9:;DD

=1=FA!,>?$9:G;D

J&'3(J17&4>1,4356,(-,1"/,%*4$("9(36,(,&'3(,17&4>1,43(-,*49"-:,'(36,(9%&34,''("9(36,('*3,(36-"#$6(36,('#73%,(1&4*2#%&3*"4("9(36,($-"#4/(3"(9"-1(&('%"=%<(:#-+*4$(-&12(&4/('3,2'(3"(36,(-*+,-(7&4>(7,%"=;(56,($,"1,3-<("9(

36*'(,17&4>1,43(9%"='(/"=4(3"(1,,3(36,(-*+,-(&4/(*'(,43*-,%<('"93%<(%&4/':&2,/;

@,'3(J17&4>1,43@,(6&/(3"(2-"+*/,(&(9"#4/&3*"4(9"-(36,(&'<11,3-*:('3-#:3#-&%(':6,1,(&4/(=,(4,,/,/(3"(*43,$-&3,(&(-&12(&4/('3,2'(*43"(36,(4,=('3-#:3#-,;(@,(/-,=("4(36,(6#%%'(&4/(>,,%'("9(36,(/-<(/":>,/(7"&3'(*4(36,(4,&-7<(7"&3<&-/(2-"/#:*4$(&4(&4$#%&-(+&#%3,/('3-#:3#-,;(

!"#$%&'()*+,-(.-*/$,(0"12,3*3*"4

!"#$%&'()#

56,(7-*/$,(*'(&('%,4/,-(7"8(9"-1(36&3(-,*49"-:,'(36,(9%&34,''("9(36,('*3,;(!-&1&3*:&%%<(2,-:6,/("4(36,(3="(-,7#*%3(,17&4>1,43'("4(,*36,-('*/,("9(36,(-*+,-?(36,(9"-1(/",'(4"3(-,+,&%(6"=(*3("2,-&3,'('3-#:3#-&%%<(#43*%(<"#(&-,("4(*3;(@,(36*4>("9(36,(7-*/$,(&'(&4(*43-*$#*4$(%&4/':&2,(,%,1,43;(56,(7-*/$,(*'(:%&/(,83,-4&%%<(*4(9%&3(3*17,-(',:3*"4'(36&3(:6&4$,(36-"#$6(36,(2%&<("9(%*$63("4(36,('#-9&:,(&'(<"#(&22-"&:6;(

(56,(7%#--,/(3*17,-(:%&//*4$(36&3(9&/,'(&:-"''(36,('2&4(=*%%(-,&:3(3"(36,(/&*%<(:6&4$,(*4(%*$63(:"4/*3*"4';(A4('#4%*$63?(/&<%*$63("-(1""4%*$63(36,(9"-1(=*%%(:"4'3&43%<(:6&4$,(&'(<"#(:-"''(36,(7-*/$,;(56,(2%&<("9(%*$63(&4/('6&/"=("4(36,('#-9&:,'("9(36,(7-*/$,(&4/(36"',(=6"(:-"''(*3(,4-*:6,'(36,(,82,-*,4:,("9(36*'(2%&:,;

56,(7-*/$,(-,9%,:3'(36,(1&3,-*&%*3<("9(36,(2-,+*"#'(-&*%=&<(7-*/$,("4(36,('*3,(#'*4$(7"36('3,,%(&4/(3*17,-('3-#:3#-&%%<;(B&7*3&3(:"44,:3*+*3<(6&'(7,,4(&:6*,+,/( 36-"#$6( *43,$-&3*"4("9("+&%(2*2,'(7,4,&36( 36,(/,:>(&%%"=*4$(&4*1&%'( 3"( 3-&+,%(&:-"''( 36,(-*+,-;

%&'()#$*+$,-.#&/*0#

56,(7-*/$,(2-"+*/,'(&(3-&4'*3*"4(&:-"''(36,(-*+,-;(56,('3-#:3#-&%(3*17,-(:%&//*4$(9&/,'(&:-"''(*3'('2&4(7,:"1*4$(*4:-,&'*4$%<("2,4(9-"1(=,'3(3"(,&'3(-,9%,:3*4$(36,(1"3*"4(7%#-(<"#(,82,-*,4:,(=6*%'3(-*/*4$(&(7*>,;(C'(<"#(:-"''(<"#(&-,(,*36,-(-,%,&',/("43"(36,(9%&3(%&4/':&2,("9(36,(,&'3(,17&4>1,43("-(:"4'#1,/(7<(36,(=""/,/($-,,4=&<("4(36,(=,'3

%&'()#$*+$1*-(+0*2#

@,(/"(4"3(',,(36,(7-*/$,(&'(&(%&4/1&->(36&3("2,-&3,'(*4(:"43-&'3(=*36(36,(%&4/D':&2,( *4(=6*:6( *3('*3';(E#-(7-*/$,( *'(4"3(&('3&3,1,43( *4( 36,( %&4/':&2,(7#3(&4(,%,1,43("9(36,(%&4/':&2,(36&3(:-,&3,'(&(2%&:,;(C'(0&-%(C4/-,("7',-+,/(F':#%2D3#-,(*'(2%&:,G;(( A4("36,-(="-/'(=,(',,(36,(7-*/$,(&'(&(':#%23#-&%(,%,1,43(36&3(,46&4:,'(36,(H#&%*3*,'("9(36,('*3,?(-,*49"-:*4$(36,(',4',("9(2%&:,;

3.&40.4&*5$/6&7

E#-(&*1(=&'(3"(2-"+*/,(&('*12%,(9"-1(=6*:6(-,'2,:3,/(36,(%"=(%<*4$(',33*4$(&4/(/*/(4"3(/"1*4&3,(36,(6"-*I"4;(56,('*3,G'($,"%"$<(1,&4'( 36&3( 36,(@,'3(7&4>(6&'(7,33,-( 9"#4/*4$(:"4/*3*"4'( 36&4( 36,(J&'3('#$$,'3*4$(&('"%#3*"4('#22"-3,/(9-"1("4,('*/,("4%<;(C93,-(/-&=*4$(#2(+&-*"#'("23*"4'(*3(7,:&1,(:%,&-(36&3(:"12%,3,%<('#22"-3*4$(9-"1("4,('*/,(="#%/(2-"+*/,(3""(/"1*4&43(&(9"-1(&4/(%"">,/(9"-(&('*12%<('#22"-3,/('"%#3*"4(36&3(=,(:"#%/(-,9*4,(3"(2-"+*/,(&('%,4/,-(,%,+&3*"4;(

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

%&*0'-)$8#.*'5$9:;

KL11(36*:>(%#$(2%&3,(=,%/,/(3"(MBM

N&*4('*/,(3-#'','(9#%%<(=,%/,/&4/('2%*:,/("4('*3,(3"(9"-19#%%(%,4$36

<5*(('-)$8#.*'5$9:;

O4";(NKO(P&%+&4*',/(."%3'

KQL8RQ11(3*17,-(:%&//*4$(S(%&3,-&%(-,'3-&*43

5*17,-(-,:,'',/(3"(%":&3,(2%&3,

5"2(&4/(7"33"1(3-#''(7"%3,/(3"(1&*4(3-#''(%#$(2%&3,'(#'*4$('*12%,(7"%3,/(:"44,:3*"4

J&'3

@,'3

3=<!,>?$!>@AB83$@=3!$%A?C$9:;DE1A?$9:;DD

=1=FA!,>?$9:G;D

J&'3(J17&4>1,4356,(-,1"/,%*4$("9(36,(,&'3(,17&4>1,43(-,*49"-:,'(36,(9%&34,''("9(36,('*3,(36-"#$6(36,('#73%,(1&4*2#%&3*"4("9(36,($-"#4/(3"(9"-1(&('%"=%<(:#-+*4$(-&12(&4/('3,2'(3"(36,(-*+,-(7&4>(7,%"=;(56,($,"1,3-<("9(

36*'(,17&4>1,43(9%"='(/"=4(3"(1,,3(36,(-*+,-(&4/(*'(,43*-,%<('"93%<(%&4/':&2,/;

@,'3(J17&4>1,43@,(6&/(3"(2-"+*/,(&(9"#4/&3*"4(9"-(36,(&'<11,3-*:('3-#:3#-&%(':6,1,(&4/(=,(4,,/,/(3"(*43,$-&3,(&(-&12(&4/('3,2'(*43"(36,(4,=('3-#:3#-,;(@,(/-,=("4(36,(6#%%'(&4/(>,,%'("9(36,(/-<(/":>,/(7"&3'(*4(36,(4,&-7<(7"&3<&-/(2-"/#:*4$(&4(&4$#%&-(+&#%3,/('3-#:3#-,;(

River Douglas Bridge Competition, Lancashire

Architect

Main Contractor

Location

Value

Foster Lomas

N/A

Lancashire

£1.7M

Arial View On Bridge

Lyons O’Neill - Construction Sequance Sketch

!"#$%&'()*+,-(.-*/$,(0"12,3*3*"4

!"#$%&'()#

56,(7-*/$,(*'(&('%,4/,-(7"8(9"-1(36&3(-,*49"-:,'(36,(9%&34,''("9(36,('*3,;(!-&1&3*:&%%<(2,-:6,/("4(36,(3="(-,7#*%3(,17&4>1,43'("4(,*36,-('*/,("9(36,(-*+,-?(36,(9"-1(/",'(4"3(-,+,&%(6"=(*3("2,-&3,'('3-#:3#-&%%<(#43*%(<"#(&-,("4(*3;(@,(36*4>("9(36,(7-*/$,(&'(&4(*43-*$#*4$(%&4/':&2,(,%,1,43;(56,(7-*/$,(*'(:%&/(,83,-4&%%<(*4(9%&3(3*17,-(',:3*"4'(36&3(:6&4$,(36-"#$6(36,(2%&<("9(%*$63("4(36,('#-9&:,(&'(<"#(&22-"&:6;(

(56,(7%#--,/(3*17,-(:%&//*4$(36&3(9&/,'(&:-"''(36,('2&4(=*%%(-,&:3(3"(36,(/&*%<(:6&4$,(*4(%*$63(:"4/*3*"4';(A4('#4%*$63?(/&<%*$63("-(1""4%*$63(36,(9"-1(=*%%(:"4'3&43%<(:6&4$,(&'(<"#(:-"''(36,(7-*/$,;(56,(2%&<("9(%*$63(&4/('6&/"=("4(36,('#-9&:,'("9(36,(7-*/$,(&4/(36"',(=6"(:-"''(*3(,4-*:6,'(36,(,82,-*,4:,("9(36*'(2%&:,;

56,(7-*/$,(-,9%,:3'(36,(1&3,-*&%*3<("9(36,(2-,+*"#'(-&*%=&<(7-*/$,("4(36,('*3,(#'*4$(7"36('3,,%(&4/(3*17,-('3-#:3#-&%%<;(B&7*3&3(:"44,:3*+*3<(6&'(7,,4(&:6*,+,/( 36-"#$6( *43,$-&3*"4("9("+&%(2*2,'(7,4,&36( 36,(/,:>(&%%"=*4$(&4*1&%'( 3"( 3-&+,%(&:-"''( 36,(-*+,-;

%&'()#$*+$,-.#&/*0#

56,(7-*/$,(2-"+*/,'(&(3-&4'*3*"4(&:-"''(36,(-*+,-;(56,('3-#:3#-&%(3*17,-(:%&//*4$(9&/,'(&:-"''(*3'('2&4(7,:"1*4$(*4:-,&'*4$%<("2,4(9-"1(=,'3(3"(,&'3(-,9%,:3*4$(36,(1"3*"4(7%#-(<"#(,82,-*,4:,(=6*%'3(-*/*4$(&(7*>,;(C'(<"#(:-"''(<"#(&-,(,*36,-(-,%,&',/("43"(36,(9%&3(%&4/':&2,("9(36,(,&'3(,17&4>1,43("-(:"4'#1,/(7<(36,(=""/,/($-,,4=&<("4(36,(=,'3

%&'()#$*+$1*-(+0*2#

@,(/"(4"3(',,(36,(7-*/$,(&'(&(%&4/1&->(36&3("2,-&3,'(*4(:"43-&'3(=*36(36,(%&4/D':&2,( *4(=6*:6( *3('*3';(E#-(7-*/$,( *'(4"3(&('3&3,1,43( *4( 36,( %&4/':&2,(7#3(&4(,%,1,43("9(36,(%&4/':&2,(36&3(:-,&3,'(&(2%&:,;(C'(0&-%(C4/-,("7',-+,/(F':#%2D3#-,(*'(2%&:,G;(( A4("36,-(="-/'(=,(',,(36,(7-*/$,(&'(&(':#%23#-&%(,%,1,43(36&3(,46&4:,'(36,(H#&%*3*,'("9(36,('*3,?(-,*49"-:*4$(36,(',4',("9(2%&:,;

3.&40.4&*5$/6&7

E#-(&*1(=&'(3"(2-"+*/,(&('*12%,(9"-1(=6*:6(-,'2,:3,/(36,(%"=(%<*4$(',33*4$(&4/(/*/(4"3(/"1*4&3,(36,(6"-*I"4;(56,('*3,G'($,"%"$<(1,&4'( 36&3( 36,(@,'3(7&4>(6&'(7,33,-( 9"#4/*4$(:"4/*3*"4'( 36&4( 36,(J&'3('#$$,'3*4$(&('"%#3*"4('#22"-3,/(9-"1("4,('*/,("4%<;(C93,-(/-&=*4$(#2(+&-*"#'("23*"4'(*3(7,:&1,(:%,&-(36&3(:"12%,3,%<('#22"-3*4$(9-"1("4,('*/,(="#%/(2-"+*/,(3""(/"1*4&43(&(9"-1(&4/(%"">,/(9"-(&('*12%<('#22"-3,/('"%#3*"4(36&3(=,(:"#%/(-,9*4,(3"(2-"+*/,(&('%,4/,-(,%,+&3*"4;(

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

%&*0'-)$8#.*'5$9:;

KL11(36*:>(%#$(2%&3,(=,%/,/(3"(MBM

N&*4('*/,(3-#'','(9#%%<(=,%/,/&4/('2%*:,/("4('*3,(3"(9"-19#%%(%,4$36

<5*(('-)$8#.*'5$9:;

O4";(NKO(P&%+&4*',/(."%3'

KQL8RQ11(3*17,-(:%&//*4$(S(%&3,-&%(-,'3-&*43

5*17,-(-,:,'',/(3"(%":&3,(2%&3,

5"2(&4/(7"33"1(3-#''(7"%3,/(3"(1&*4(3-#''(%#$(2%&3,'(#'*4$('*12%,(7"%3,/(:"44,:3*"4

J&'3

@,'3

3=<!,>?$!>@AB83$@=3!$%A?C$9:;DE1A?$9:;DD

=1=FA!,>?$9:G;D

J&'3(J17&4>1,4356,(-,1"/,%*4$("9(36,(,&'3(,17&4>1,43(-,*49"-:,'(36,(9%&34,''("9(36,('*3,(36-"#$6(36,('#73%,(1&4*2#%&3*"4("9(36,($-"#4/(3"(9"-1(&('%"=%<(:#-+*4$(-&12(&4/('3,2'(3"(36,(-*+,-(7&4>(7,%"=;(56,($,"1,3-<("9(

36*'(,17&4>1,43(9%"='(/"=4(3"(1,,3(36,(-*+,-(&4/(*'(,43*-,%<('"93%<(%&4/':&2,/;

@,'3(J17&4>1,43@,(6&/(3"(2-"+*/,(&(9"#4/&3*"4(9"-(36,(&'<11,3-*:('3-#:3#-&%(':6,1,(&4/(=,(4,,/,/(3"(*43,$-&3,(&(-&12(&4/('3,2'(*43"(36,(4,=('3-#:3#-,;(@,(/-,=("4(36,(6#%%'(&4/(>,,%'("9(36,(/-<(/":>,/(7"&3'(*4(36,(4,&-7<(7"&3<&-/(2-"/#:*4$(&4(&4$#%&-(+&#%3,/('3-#:3#-,;(

!"#$%&'()*+,-(.-*/$,(0"12,3*3*"4

!"#$%&'()#

56,(7-*/$,(*'(&('%,4/,-(7"8(9"-1(36&3(-,*49"-:,'(36,(9%&34,''("9(36,('*3,;(!-&1&3*:&%%<(2,-:6,/("4(36,(3="(-,7#*%3(,17&4>1,43'("4(,*36,-('*/,("9(36,(-*+,-?(36,(9"-1(/",'(4"3(-,+,&%(6"=(*3("2,-&3,'('3-#:3#-&%%<(#43*%(<"#(&-,("4(*3;(@,(36*4>("9(36,(7-*/$,(&'(&4(*43-*$#*4$(%&4/':&2,(,%,1,43;(56,(7-*/$,(*'(:%&/(,83,-4&%%<(*4(9%&3(3*17,-(',:3*"4'(36&3(:6&4$,(36-"#$6(36,(2%&<("9(%*$63("4(36,('#-9&:,(&'(<"#(&22-"&:6;(

(56,(7%#--,/(3*17,-(:%&//*4$(36&3(9&/,'(&:-"''(36,('2&4(=*%%(-,&:3(3"(36,(/&*%<(:6&4$,(*4(%*$63(:"4/*3*"4';(A4('#4%*$63?(/&<%*$63("-(1""4%*$63(36,(9"-1(=*%%(:"4'3&43%<(:6&4$,(&'(<"#(:-"''(36,(7-*/$,;(56,(2%&<("9(%*$63(&4/('6&/"=("4(36,('#-9&:,'("9(36,(7-*/$,(&4/(36"',(=6"(:-"''(*3(,4-*:6,'(36,(,82,-*,4:,("9(36*'(2%&:,;

56,(7-*/$,(-,9%,:3'(36,(1&3,-*&%*3<("9(36,(2-,+*"#'(-&*%=&<(7-*/$,("4(36,('*3,(#'*4$(7"36('3,,%(&4/(3*17,-('3-#:3#-&%%<;(B&7*3&3(:"44,:3*+*3<(6&'(7,,4(&:6*,+,/( 36-"#$6( *43,$-&3*"4("9("+&%(2*2,'(7,4,&36( 36,(/,:>(&%%"=*4$(&4*1&%'( 3"( 3-&+,%(&:-"''( 36,(-*+,-;

%&'()#$*+$,-.#&/*0#

56,(7-*/$,(2-"+*/,'(&(3-&4'*3*"4(&:-"''(36,(-*+,-;(56,('3-#:3#-&%(3*17,-(:%&//*4$(9&/,'(&:-"''(*3'('2&4(7,:"1*4$(*4:-,&'*4$%<("2,4(9-"1(=,'3(3"(,&'3(-,9%,:3*4$(36,(1"3*"4(7%#-(<"#(,82,-*,4:,(=6*%'3(-*/*4$(&(7*>,;(C'(<"#(:-"''(<"#(&-,(,*36,-(-,%,&',/("43"(36,(9%&3(%&4/':&2,("9(36,(,&'3(,17&4>1,43("-(:"4'#1,/(7<(36,(=""/,/($-,,4=&<("4(36,(=,'3

%&'()#$*+$1*-(+0*2#

@,(/"(4"3(',,(36,(7-*/$,(&'(&(%&4/1&->(36&3("2,-&3,'(*4(:"43-&'3(=*36(36,(%&4/D':&2,( *4(=6*:6( *3('*3';(E#-(7-*/$,( *'(4"3(&('3&3,1,43( *4( 36,( %&4/':&2,(7#3(&4(,%,1,43("9(36,(%&4/':&2,(36&3(:-,&3,'(&(2%&:,;(C'(0&-%(C4/-,("7',-+,/(F':#%2D3#-,(*'(2%&:,G;(( A4("36,-(="-/'(=,(',,(36,(7-*/$,(&'(&(':#%23#-&%(,%,1,43(36&3(,46&4:,'(36,(H#&%*3*,'("9(36,('*3,?(-,*49"-:*4$(36,(',4',("9(2%&:,;

3.&40.4&*5$/6&7

E#-(&*1(=&'(3"(2-"+*/,(&('*12%,(9"-1(=6*:6(-,'2,:3,/(36,(%"=(%<*4$(',33*4$(&4/(/*/(4"3(/"1*4&3,(36,(6"-*I"4;(56,('*3,G'($,"%"$<(1,&4'( 36&3( 36,(@,'3(7&4>(6&'(7,33,-( 9"#4/*4$(:"4/*3*"4'( 36&4( 36,(J&'3('#$$,'3*4$(&('"%#3*"4('#22"-3,/(9-"1("4,('*/,("4%<;(C93,-(/-&=*4$(#2(+&-*"#'("23*"4'(*3(7,:&1,(:%,&-(36&3(:"12%,3,%<('#22"-3*4$(9-"1("4,('*/,(="#%/(2-"+*/,(3""(/"1*4&43(&(9"-1(&4/(%"">,/(9"-(&('*12%<('#22"-3,/('"%#3*"4(36&3(=,(:"#%/(-,9*4,(3"(2-"+*/,(&('%,4/,-(,%,+&3*"4;(

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

%&*0'-)$8#.*'5$9:;

KL11(36*:>(%#$(2%&3,(=,%/,/(3"(MBM

N&*4('*/,(3-#'','(9#%%<(=,%/,/&4/('2%*:,/("4('*3,(3"(9"-19#%%(%,4$36

<5*(('-)$8#.*'5$9:;

O4";(NKO(P&%+&4*',/(."%3'

KQL8RQ11(3*17,-(:%&//*4$(S(%&3,-&%(-,'3-&*43

5*17,-(-,:,'',/(3"(%":&3,(2%&3,

5"2(&4/(7"33"1(3-#''(7"%3,/(3"(1&*4(3-#''(%#$(2%&3,'(#'*4$('*12%,(7"%3,/(:"44,:3*"4

J&'3

@,'3

3=<!,>?$!>@AB83$@=3!$%A?C$9:;DE1A?$9:;DD

=1=FA!,>?$9:G;D

J&'3(J17&4>1,4356,(-,1"/,%*4$("9(36,(,&'3(,17&4>1,43(-,*49"-:,'(36,(9%&34,''("9(36,('*3,(36-"#$6(36,('#73%,(1&4*2#%&3*"4("9(36,($-"#4/(3"(9"-1(&('%"=%<(:#-+*4$(-&12(&4/('3,2'(3"(36,(-*+,-(7&4>(7,%"=;(56,($,"1,3-<("9(

36*'(,17&4>1,43(9%"='(/"=4(3"(1,,3(36,(-*+,-(&4/(*'(,43*-,%<('"93%<(%&4/':&2,/;

@,'3(J17&4>1,43@,(6&/(3"(2-"+*/,(&(9"#4/&3*"4(9"-(36,(&'<11,3-*:('3-#:3#-&%(':6,1,(&4/(=,(4,,/,/(3"(*43,$-&3,(&(-&12(&4/('3,2'(*43"(36,(4,=('3-#:3#-,;(@,(/-,=("4(36,(6#%%'(&4/(>,,%'("9(36,(/-<(/":>,/(7"&3'(*4(36,(4,&-7<(7"&3<&-/(2-"/#:*4$(&4(&4$#%&-(+&#%3,/('3-#:3#-,;(

The Listening Posts

Architect

Main Contractor

Location

Value

Foster Lomas Architects

Competition

Aldgate, London

Not Disclosed

Architects Impression

Lyons O’Neill have been shortlisted along with 4 other practices for a new installation in the heart of the City. The sculpture marks a part of

London’s High Street 2012 initiative and will remain in place for the duration of the 2012 Olympic Games. It will stand on a site historically

known as ‘Ale-Gate’, so called because it was the only City gateway open to all. It is hoped the new landmark will underscore the fact that

the City now welcomes, rather than drives away, its neighbours.

We responded to both the temporary nature of the installation and the congested nature of the site by introducing a light touch structure

which can be installed using the minimum of plant and without closing the road. This fully interactive installation can be simply demounted

leaving the site exactly as it was and can easily be reinstalled in another location as a more permanent piece.

Lyons O’Neill Sketch - Structural Approach

Elevation

Temporary Works

Architect

Main Contractor

Location

Value

Various

Various

N/A

N/A

King Post Retaining Wall King Post Retaining Wall

Steel Wailer Beam & Props

Lyons O’Neill are currently working on a number of temporary works schemes for main Contractors providing a responsive and cost

effective service

Construction Site With Perimeter Temporary Works

Phoenix Community Housing is a not-for-profit resident-led Housing Association in the Bellingham, Whitefoot and Downham area of

Lewisham, London. Properties were transferred from Lewisham Council in a large-scale voluntary transfer on 3rd December 2007 following

a positive ballot of all tenants. It is a new organisation, developed for this area, and has no connection with any other Housing Association.

On winning the framework bid Lyons O’Neill met with PCHA to discuss their brief and to determine whether there were any items we could

expand on which we could add value too. We quickly establish a need to take a global view of PCHA’s properties and database of issues.

Little information regarding the properties was transferred with the sale from Lewisham so PCHA were essentially starting with a clean slate.

Most of the properties sent through were suffering from movement and damage as a result. On receiving the first batch of properties to

review we undertook a desktop search on the properties to see if there were any environmental or historical land issues that may have been

an issue. It was quickly established that the majority of the properties were situated on Clay which instantly pointed to shrinkage and heave

issue. In addition to this our historical research showed that the properties in the main were constructed as part of the ‘Homes for Heroes’

programme after the first world war.

Surveys & Inspections

Architect

Main Contractor

Location

Value

Varies

Varies

Varies

Varies

Typical Property

Isometric Drawing Of The Main Structural Elements Of An Atholl 1920’s Dwelling

Exposed stanchions

Steel cladding sheets

2-storey T stanchionat separating wall

2-storey T stanchion

Angle cleats

Part timber roof construction shown dotted

Angle support for timber wall plate

RSJ spine beams

Distortion Survey

Distortion Survey

Partywall Elevation

Partywall Works

Architect

Main Contractor

Location

Value

Varies

Varies

Varies

Varies

With our experience in refurbishments and understanding of the building process we are increasingly working as Party Wall Engineers for a

number of Surveyors. With our pragmatic and robust approach to the realities of the building process we have been able to negotiate and

resolve on a number of complex boundary issues for a range of Clients including the Lyric Theatre, Hammersmith.

Lyons O’Neill Drawing - Partywall Sections

Lyric Theatre, London

Ballusted Fixing point detail Roof Hook Testing

Photo voltaic cells fixed in placed

As one of the UK’s largest installers of photo voltaic cells, Solarcentury have sought to develop standard fitting systems for a variety of roof

types. We have worked closely with them since 2000 working on various prototypes and installed systems.

We have also worked with a number of manufacturers doing research and development work on their products and getting them ready for

the UK market.

Solar Work

Architect

Main Contractor

Location

Value

Varies

Varies

Varies

Varies

Lyons O’Neill - Testing Brief Sketch

4

Figure 1: Test method for centrally loaded roof hook.

Figure 2: Test Method for eccentrically loaded roof hook

Drainage / Road Design

Architect

Main Contractor

Location

Value

Varies

Varies

Varies

Varies

Drainage Construction To Housing Development

Lyons O’Neill offer a full range of civil engineering expertise. A selection of common services provided are as follows:

+44 (0) 20 7223 [email protected]

45 Great Guildford StreetLondon

SE1 0ES