lysaghtarchitecturaldetailingmanualroofwallflashingv2june2013
TRANSCRIPT
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
1/40
1Lysaght arciecurl Deilin Mnul 2013
Architectural Detailing Manual
Architectural
Detailing Guide
Hw i i c
rf w
Cr, cci ii ip
h fr chic rf
Ui fhi cr
rchicur fur
Iur prcic xpi
Rf w hi
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
2/40
2Lysaght arciecurl Deilin Mnul 2013
Copyright, disclaimer, and limitation o liability
Copyright
Coyright in this inormation including any designs, text,
data, grahics and images belong to BlueScoe Steel Ltd,
trading as BlueScoe Lysaght excet as noted.
Thanks are given to the Ne Zealand Metal Rooing
Manuacturers Inc. or ermission to reroduce text,
grahics and draings rom their coyright ublication
- NZ METAL ROOF AND wALL CLADDING CODE OF
pRACTICE (Version 3: 2012). All rights reserved.
Any use o this ublication including reroduction,
modiication, distribution or reublication, in hole or in
art*, in any orm or medium, ithout ritten ermission o
BlueScoe Lysaght is rohibited.
Disclaimer
while every eort has been made to ensure the accuracy
o this inormation, BlueScoe Lysaght cannot be held
resonsible or any errors or omissions, hether caused bynegligence or any other reason, excet as limited by la.
product seciications can change ithout notice, and
there is an alloable variance in roduct dimensions rom
dierent manuacturing lants. BlueScoe Lysaght has the
right to revise the contents o the inormation sulied to
you rom time to time ithout reerence to you.
All inormation is rovided as a guide only. Beore
alication in a articular situation, BlueScoe Lysaght
recommends that you receive qualiied exert advice
conirming the suitability o roduct(s) and inormation in
question or the alication roosed.
Limitation o liability
This ublication is intended to be an aid or roessional
builders and is not a substitute or roessional judgement.
Terms and conditions o sale are available at local
BlueScoe Lysaght sales oces.
Excet to the extent to hich liability may not laully be
excluded or limited, BlueScoe Steel Limited ill not be
under or incur any liability to you or any direct or indirect
loss or damage (including, ithout limitation, consequential
loss or damage such as loss o rot or anticiated rot,
loss o use, damage to goodill and loss due to delay)hoever caused (including, ithout limitation, breach o
contract, negligence and/or breach o statute), hich you
may suer or incur in connection ith this ublication.
The LYSAGHT range o roducts is made by BlueScoe
Steel Limited trading as BlueScoe Lysaght.
Coyright BlueScoe Steel Limited Aril 17, 2013
produced at BlueScoe Lysaght Research & Technology
* Excet or material taken rom NZ METAL ROOF AND
wALL CLADDING CODE OF pRACTICE (Version 3: 2012)
here the ermission o the Ne Zealand Metal Rooing
Manuacturers Inc. must be sought.
Table o Contents
1. Introduction and Scoe ........................................................ 3
2. Design preliminaries .............................................................. 4
2.1 product selection ..................................................... 4
2.2 The urose o lashing .......................................... 4
2.3 Materials and inishes ............................................. 5
2.4 Comatibility.............................................................. 5
2.5 Suort sacings ..................................................... 6
2.6 Maximum lengths o rooing .................................. 6
2.7 Lo roo itches ....................................................... 6
2.8 wind orces on roos ............................................... 6
2.9 Codes and erormance tests ............................... 6
2.10 Seciications - rooing roiles .......................... 7
2.11 Seciications - alling roiles .......................... 8
3. Roo lashings .......................................................................... 9
3.1 Design ........................................................................ 9
3.2 Roo lashings ......................................................... 10
3.3 Flashing las ........................................................... 11
3.4 Aron lashing ........................................................ 11
3.5 Longitudinal lashings ........................................... 11
3.6 Transverse lashings .............................................. 12
3.7 Using notching tools .............................................. 13
3.8 Flashing at change o itch .................................. 14
3.9 Caed bent roos.................................................. 14
3.10 Gutter aron .......................................................... 15
3.11 Tyes o enetration lashing design ............... 16
3.12 Flashing large roo enetrations ....................... 17
3.13 Flashing small roo enetrations ....................... 19
3.14 Exansion .............................................................. 20
3.15 Standard roo lashings....................................... 21
3.16 Non standard roo lashings, caings ............ 24
3.17 Box gutters ............................................................ 25
3.18 Barge gutters and caing ................................ 26
4. Tyical all lashings ........................................................... 27
4.1 Cladding orientation .............................................. 27
4.2 walling roile running horizontally .................... 27
4.3 Tyes o lashings ..................................................28
4.4 Otional all trims ................................................. 29
4.5 Mid-all connections ........................................... 30
4.6 Internal all connections ..................................... 30
4.7 External corner connections ................................31
4.8 Flashing or horizontal cladding .......................... 31
4.9 Flashing or horizontal corrugate cladding ....... 32
4.10 Flashings or vertical cladding .......................... 32
4.11 windo lashings or metal cladding ............... 33
4.12 windo lashing tyes ........................................ 33
4.13 Flush indo lashings ....................................... 34
4.14 Recessed indo lashings .............................. 36
4.15 Butt indo lashings ......................................... 37
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
3/40
3Lysaght arciecurl Deilin Mnul 2013
Correct detailing o LYSAGHT roo and all lashing has
more than cosmetic imortance - it is essential in ensuring
the et eather erormance o the cladding.
Correct lashing and detailing ill imrove the overall
aearance o the inished job.
The advice given in this manual is consistent ith the
requirements o the Building Code o Australia and is aimed
at ensuring that correct ractice is seciied into building
contruction.
In many instances, alternative methods are examined to
rovide a clear understanding o the imlications arising
rom these alteratives.
And inally, the examles shon are tyical o the ork
to be carried out and may not aly to seciic situations
or seciic LYSAGHT cladding roducts. In all cases, a
qualiied tradesman should be engaged to ensure the
advice given here is alicable to your intended use.we hoe that the inormation sulied rovides clear,
concise direction in the correct design and detailing o roo
and all lashing or architects and draghtsmen.
The manual is set out in to arts, design and lashing.
For overall roo and all design, reer to the LYSAGHT
Rooing & walling Installation Manual. I these roducts are
to be used in cyclonic areas as deined in AS 1170.2; 2011,
you must also reer to the LYSAGHT Cyclonic Area Design
Manual.
Both these ublications are availble at: .lysaght.com
1. Introduction and Scope
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
4/40
4Lysaght arciecurl Deilin Mnul 2013
2 Design preliminaries
2.1 Product selectionwhen you incororate steel cladding into your building
LYSAGHT oers a ide range o roiles rom hich to choose.
whilst rooing and alling obviously have to kee out the
eather, they also have signiicant eects on the looks, cost
and durability o a building.
I you are unsure about any roduct eature, visit
.lysaght.com, call our inormation line or seek advice rom
the relevant secialists.
BlueScoe Lysaght has been sulying the Australian building
industry ith remium roducts or over 150 years, and our
technical literature rovides the engineering data to design
buildings using our roducts.
In articular, architects and builders should consult chaters
2 to 6 o the LYSAGHT Rooing & walling Installation Manual.
we urge the reader to consult this document or overall designand ixing advice, although selected arts o that inormation
are reeated here.
The aroriate design ill deend on your articular needs
and circumstances. You should get advice rom the relevant
qualiied secialists here required.
2.2 Purpose o lashingThe urose o a lashing is to divert ater aay rom any
oint o entry, and to make any building eatherroo.
Flashings and caings are stris o metal ormed to
eatherroo the edges o rooing and alling.
For the uroses o this chater, only the term lashing is used.
The olloing sections should be considered as a guide only.For a comrehensive account o lashing guidelines, reer to
HB39-1997.
Similar methods o lashing are used or dierent cladding-
roiles. You can adat the rinciles to suit your alication.
In all cases it is imortant to have amle cover rovided by the
lashing and roer turn-u o the cladding underneath.
Be careul hen moving beteen suorts. Do not alk in the
an immediately adjacent to lashings or translucent sheeting.
walk at least one an aay.
Lysaght has a range o standard lashings. we can also sulycustom lashings to your requirements ask your local service
centre or details.
Flashings are not only required to rovide eather-resistance
the many junctions on a roo or all structure, but are also
a very visible art o the roo and all cladding design, and
erorm an imortant role in the aesthetic aearance o the
building.
Exerience is required to design, cut and asten lashings that
ill last the lietime o the roo or all cladding, and secialist
assistance should be sought here this exerience is not
available.
All lashings must be designed to revent onding o ater
or build-u o debris. Flashings must be designed to rovide
eather-resistance or the roo or all cladding ithout
reliance on sealant as the rime means o roviding eather-
resistance.
Unainted galvanised steel is incomatible ith most inert
materials and is subject to inert catchment corrosion.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
5/40
5Lysaght arciecurl Deilin Mnul 2013
2.4 Compatibilitywhen to dissimilar metals are in contact and moisture is
resent, one metal is relatively rotected hile the other
suers accelerated corrosion. Galvanic or bimetallic corrosion
can also occur hen ater los over dissimilar metals.
The design o lashings has a direct relationshi to corrosion,
as the underlying design rincile is to kee the metal dry, toavoid any retention o moisture by debris, and to rovide all
lashings ith a minimum all o 11 or 12 to avoid onding.
The designer and rooing contractor should be aare o
comatibility issues hen combining materials in a roo
system or lacing assemblies such as air-conditioning units,
solar collectors and alkays on to o roo cladding. I
materials are combined incorrectly, severe localised corrosion
may occur.
It is very imortant that lashings be made rom materials
that are comatible ith the cladding (Section 2.10, LYSAGHT
Rooing & walling Installation Manual).
Lead lashing is not recommended, hoever it ill usually be
retained hen re-rooing, because it is usually cemented into
the structure. In these cases:
thetopsurfaceoftheleadflashingmustbepainted
ith a good quality exterior aint system (to limit
contamination ith lead comounds in ater running
o the lashing); and
theremustbeabarrierbetweentheleadflashingand
the cladding: either a lastic stri (such as olythene
damcourse), or aint.
Flashings should conorm to AS/NZS 2179.1:1994, and be
comatible ith the cladding (Section 2.10, LYSAGHT Rooing
& walling Installation Manual).
Materials or lashings are available in ZINCALUMEor
COLORBONDinishes.
2.3 Materials and inishesTo ensure equal durability, lashings, ridge caings, and
accessories should be manuactured rom the same material,
and have the same coating system, as the material used or
the roo and all cladding. when this is not ossible, or i
dierent materials are intended or seciied, the alternative
materials should be comatible or both contact and run-
o. Our most idely used cladding roiles are listed inTables 2.10.1 and 2.11.1. They are available in COLORBOND
reainted steel, or in unainted ZINCALUME aluminium/zinc
alloy-coated steel.
COLORBONDre-ainted steel has either a aluminium/
zinc alloy-coated steel or stainless steel base metal, ith a
range o organic coatings to coe ith exosure to a range o
environments.
COLORBONDis reainted steel or exterior rooing and
alling. It is the most idely used.
COLORBONDMETALLICis reainted steel or suerioraesthetic qualities dislaying a metallic sheen.
COLORBONDULTRAis reainted steel or severe coastal
or industrial environments (generally ithin about 100 to
200 metres o the source).
COLORBONDSTAINLESSis reainted stainless steel or
very severe coastal or industrial environments (generally
ithin about 100 metres o the source). It is subject to
availability and long lead times.
Check ith your local BlueScoe Lysaght oice or availability
o roiles, materials, inishes, colours, accessories; and orsuitability o the roduct.
Tables 2.10.1 and 2.11.1 list general inormation or roile
selection. Reer to our ublications on seciic roducts
or detailed seciications. There are also ublications on
ZINCALUMEsteel and COLORBONDreainted steel rom
our inormation line (page 1).
Typical material speciications
ZINCALUMEaluminium/zinc alloy-coated steel comlying
ith AS 1397:2011. Minimum yield strengths are 550Mpa
(G550), or 300Mpa (G300) deending on roile. Minimumcoating mass is AZ150 (150g/m2 )
COLORBOND is a re-ainted steel. The ainting comlies
ith AS/NZS 2728 and the steel base is an aluminium/zinc
alloy-coated steel comlying ith AS 1397:2011. Minimum
yield strengths are 550Mpa (G550), or 300Mpa (G300)
deending on roile.Minimum coating mass is AZ150
(150g/m2)
COLORBOND Ultra is a re-ainted steel. The ainting
comlies ith AS/NZS 2728 and the steel base is an
aluminium/zinc alloy-coated steel comlying ith AS
1397:2011. Minimum yield strengths are 550Mpa (G550),
or 300Mpa (G300) deending on roile. Minimum coating
mass is AZ200 (200g/m2)
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
6/40
6Lysaght arciecurl Deilin Mnul 2013
2.7 Low roo pitchesUnless there is adequate ositive all in a roo, there is
danger o onding, hich can lead to a reduced service lie,
articularly in coastal areas.
At lo sloes, say around 1 in 50 (1) sloe, all roo suorts
must be in the one lane because slight variations can result
in zero or negative all. This may occur even ater comletion
o the building as the result o settlement, timber aring or
shrinking, or extra loadings (like air conditioners).
Minimum recommended roo sloes are listed in Table 2.12.1
o the LYSAGHT Rooing and walling Installation Manual. As
a guide, herever ossible, you should design or a minimum
sloe o 1 in 30 (2). Roo sloes loer than the recommended
minimum may be available subject to enquiry and ill be
deendent uon the roo alication and building details.
2.8 Wind orces on roos
winds create considerable orces on both the toside andthe underside o roo cladding, and you must consider these
orces in the design and ixing o any roo. The orces are:
inward orcestending to collase the roo cladding
inards, caused by ind acting directly on the indard
side; and
outward orcestending to lit the roo cladding rom its
raming, and the entire roo structure rom the rest o the
building. Outard orces can be caused both by ulit
rom negative ind ressures, outside the building; and by
ositive ind ressure inside the building.
Generally the greatest ind orces imosed on roos are due
to the outard orces. Because the dead eight o rooing
materials is relatively small, the outard orces must be
resisted by the roo asteners.
It is very imortant that the battens and roo raming are
adequately ixed to the raters and alls, and that claddings
and lashings also be ixed to ithstand these ressures.
2.9 Codes and perormance tests
AS 1562.1:1992 seciies the design and installation o sheet
metal roo and all cladding. Our rooing roiles satisy all the
requirements o this standard, including the ability o the roo
to resist outard orces and concentrated loads. The testing
is erormed according to AS 4040.1:1992 and AS 4040.2:1992.
Flashings and caings, although not tested searately, must
comly to the ixing requirements o the cladding to deliver
equal erormance.
2.5 Support spacingsThe maximum recommended suort sacings are shon in
Tables 2.13.1 and 2.14.1 o the LYSAGHT Rooing and walling
Installation Manual. They are based on data in accordance ith
AS 1562.1:1992 Design and installation o sheet roo and all
cladding: Metal, and AS 4040.1:1992 Methods o testing sheet
roo and all claddingResistance to concentrated loads.
The sacings in the tables are recommended to roduce
adequate erormance o claddings under concentrated loading
(incidental or maintenance).
For suort sacings in ind conditions, reer to our
ublications on seciic roducts or ind ressure data.
In all cases, cladding is ixed to a suort o 1.0mm minimum
base metal thickness (BMT) and minimum yield stress o
550Mpa. I you ant to use metal battens thinner than 1.0mm,
seek advice rom our inormation line.
2.6 Maximum lengths o rooingThe valleys (or ans) o rooing have to carry ater to the
gutters. I the valleys overill in heavy rain, ater can lo into
the roo through the side-las and lashings.
Factors aecting aterroo and drainage caacity o the las
o a roile include:
thewidthanddepthofthevalleysorpans;
thepitchoftheroofrainflowsfasteronasteeper
itch;
rainfallintensityforthegeographicalarea;
thelengthoftherooffromridgetogutter;and
penetrationsthatcausenearbyvalleystocarryextra
rain diverted rom valleys obstructed by the enetration
(Figure 2.14.1).
The maximum recommended roo lengths or drainage or each
roile are given in Table 2.14.1 o the LYSAGHT Rooing and
walling Installation Manual.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
7/40
7Lysaght arciecurl Deilin Mnul 2013
Table 2.10.1Seciications o rooing & alling roiles
2.10 Speciications - rooing
FLATDEK II5
FLATDEK5
CUSTOM ORB4
CUSTOM BLUE ORB4
Eaves Overhang3
6.60.60
1650 1750 2200 150 450 2600 3200 3850 150
2050 2350 2800 200 500 3000 3450 3900 200
2350 3000 3600 250 550 3300 3600 3900 250
1500 1800 2100 200 600
2 See Section 2.15 of the LYSAGHT Roofing & Walling Installation manual.
5 FLATDEK & FLATDEK II are Home Improvement profiles. Please refer to the brochures for more installation details.
- 1800 2200 200 500 - 2150 3250 300
- 2100 3050 250 600 - 2500 3550 400
of the LYSAGHT Roofing & Walling Installation manual for explanation of stiffened.
KLIP-LOK 406
KLIP-LOK CLASSIC 700
KLIP-LOK 700 HI-STRENGTH
SPANDEK6
TRIMDEK
LONGLINE 305 (not tapered)
SPANRIB
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
8/40
8Lysaght arciecurl Deilin Mnul 2013
Table 2.11.1Seciications o roiles or alling only
Roofing & Walling profiles
Step
ES
IS
ES Single span
Spacing definitionsES = End spanIS = Internal span
O = Overhang
IS
O
O
walling roiles only
0.42 4.1 272 260 12 - 1000 1000WALLCLAD
WEATHERBOARD
TRIMWALL
EASY-CLAD
PANELRIB6
MINI ORB7
MULTICLAD
Overhang
mm
n/a
2.11 Speciications - walling
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
9/40
9Lysaght arciecurl Deilin Mnul 2013
3. Roo Flashing
3.1 DesignAll roo cladding edges located other than at the gutter, must
have a cover lashing astened on both aces.
Flashings at the erihery o roo or all cladding are subject
to high suction or negative ind loads that oten exceed all
other ositive imosed loads. As a result the ind design load
can be u to tice that o the main roo area and extra ixings
are required to ix lashings.
The design ind load seciic to any articular building, ill
determine the number and the sacing o lashing asteners.
There is hoever a minimum number o astenings that should
be rovided to avoid lexing, oil canning or atigue cracking
o metal cladding under luctuating loads and also to revent
noise or lutter.
Scres are reerred to rivets or astening lashings because
the larger diameter shank gives a greater shear caacity, andas they have a bigger head a asher can be used to increase
the ull over resistance er astener.
The ingress o rain into the roo or all cavity via the lashings
is redominantly caused by the ressure dierential beteen
the outside air and that inside the roo or all cavity.
This ressure dierential caused by ind gusting is a dynamic
one and luctuates greatly, hich means that a cyclic or
uming action can occur hen ater is sucked into the joint
or cavity that a lashing is covering.
An anti-caillary oset old, a clearance ga o u to 5mm ora sealant should be rovided on all lashing edges to avoid
caillary action here lashings are in close contact ith the
roo or all cladding.
Flashings, other than standard ridging, are roduced to
seciic order and are designed and manuactured rom
lat sheet or coil. I these lashings are required to match
the colour o the roiled cladding sheets it is necessary or
the re-ainted lat sheet or coil to be made by the samemanuacturer using the same rocess in order to avoid
dierential colour matching or ading.
preerred maximum length o lashing is 6m, ith exansion
joints rovided ater a maximum o to lengths o lashing
(12m) have been ixed together, as any la secured by rivets or
scres eectively becomes one length.
Flashings are restricted in length in the same manner as are
roo and all cladding sheets and are subject to the same
requirements and exansion rovisions.
The edges o all lashings must be saced at a minimumdistance o 2mm - 5mm aay rom an adjacent horizontal
surace to avoid moisture retention and deterioration at the
cut edge o coated steel lashings. This clearance alies
articularly hen a cut edge is very close to concrete or
laster or butyl rubber.
The end o all cladding should not extend don to any aron
lashing, but should have minimum clearance (CL) o 25mm and
a maximum clearance o 50mm.
c c
c
c
CL
CLCL
CL
Smooth
Smooth
cladding Profiledcladding
Profiled
Figure 3.3.1Barge
Figure 3.3.2Vertical aron
Figure 3.3.3paraet
C = Minimum cover
Cl = Clearance
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
10/40
10Lysaght arciecurl Deilin Mnul 2013
Figure 3.2.3Chased aron
Figure 3.2.6Vertical cladding
Figure 3.2.4Angle diverter
Figure 3.2.7Angled aron 110
Figure 3.2.5Angled aron 45
Figure 3.2.8To iece aron
Chased aron
Vertical cladding
Angle diverter
Angled aron 110
Angled aron 45
To iece aron
Sto endturned don
Diverter
Sto endturned don
Sto endturned don
Sto endturned don
3.2 Roo lashings
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
11/40
11Lysaght arciecurl Deilin Mnul 2013
Figure 3.5.1Tyical longitudinal lashings
pierce ixed roo sheet 150mm min.
Concealed ixed roo sheet Into ull an
(2/3 an covered)
3.3 Flashing lapsA la is that art o a lashing that overlas or covers any
ortion o the same shaed comonent, and is variously
described as an end la, overla or underla.
Las should comly ith the olloing criteria:
anoverlapmustruninthesamedirectionasthewateri.e.
donhill;anoverlapmustrunovernotunder;
anoverlapmustbeacrossthefalloratashallowangle;
watermustflowoveralapnotintoit;
alapmustbeself-drainingandnotrelysolelyonsealant;
alapmustbemechanicallyfixed;
asealedlapmusthaveaminimumofwidthof25mm;
3.4 Apron FlashingCladding should not it tightly don onto the horizontal surace
o any aron lashing as it ill retain moisture and collect dirtand debris and should have minimum clearance o 25mm.
3.5 Longitudinal lashingsLongitudinal lashings run arallel to the ans or valleys, and
are made to suit the cladding roile (Figure 11.2.1). They
should have an edge turned-don to di into the an or valley.
Flashing Cover
The minimum recommended cover o longitudinal lashings
over cladding should be as ollos: (as taken rom HB39-1997)
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
12/40
12Lysaght arciecurl Deilin Mnul 2013
Figure 3.6.1Tyical transverse lashings
3.6 Transverse lashingsTransverse lashings run across the ans or valleys (Figure
3.6.1). They usually have a stiening li, along the loer edge,
hich is turned-don to di into the an or valley. To maximise
eatherrooing, the bent li is roiled to it.
The turn-don or transverse lashings or CUSTOM ORB
and CUSTOM BLUE ORB can be ashioned to it the roile
by either notching or scribing to match the corrugations, or
lightly dressed into the valleys. The tye o ashioning (i any)
deends uon roile shae and the tye o material used to
lash. Fashioning is reerred or lo-sloe roos.
The turn-don or transverse lashings or ide anned
cladding is alays notched or scribed to it over the ribs.
Flashing Cover
BlueScoe Lysaght roduces a range o standard lashings
(hi, barge, aron). To increase eather-resistance, Lysaght
recommends you maximise the overla beteen lashings and
claddings. Reer to Table 8.1.2 in HB-39 or greater detail.
Fixing o Flashings
Longitudinal lashings shall be astened at maximum 500mm
centres. Transverse lashings shall be astened in accordance
ith HB39-1997, as detailed belo.
Notching tools
Hand-oerated notching tools cut one notch at a time. Each
tool matches only one cladding roile. There are to tyes
o tool; their use deends on hether or not the edge o the
lashing has irst been bent don.
Table 3.6.1Notching tools
Every 4th rib (minimum)
Every 3rd rib(minimum)
Every rib
KLIP-LOK 406
KLIP-LOK 700 HI-STRENGTH
KLIP-LOK CLASSIC 700
SPANDEK, TRIMDEK
Others subject to inquiry.
Proile Recommended Fixing Spacing (min.)
CUSTOM ORB/CUSTOM BLUE ORB Every 4th rib
SpANRIB Every rib
KLIp-LOK 406 Every rib
KLIp-LOK 700 HIGH STRENGTH Every rib
KLIp-LOK CLASSIC 700 Every ribLONGLINE 305 Every rib
SpANDEK Every 3rd rib
TRIMDEK Every rib
The above astener sacing relates to the stitching o lashings to
sheeting. It does not constitute the minimum number o asteners
required to ix the sheeting to urlins.
Flashings rovide the essential eatherrooing at the
edges, and they sharen the image o the inished job.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
13/40
13Lysaght arciecurl Deilin Mnul 2013
Figure 3.7.1Using notching tools
3.7 Using notching toolsAter the cladding is ixed and the turn-us inished, roceed
as ollos.
Placeaflashingwiththenotch-edgerestingontheribs.
Locateyournotchingtooloveraribwiththenotchinghead
against the lashing.
verticaltool: The body locates along the rib.
horizontaltool: the lugs on the underside locates on to
o the rib.
Raisethehandletoopenthetooland:
verticaltool: lit the lashing into the mouth o the tool;
horizontaltool: slide the mouth o the tool over the edge
o the lashing as ar as it ill go.
Pushdownonthehandletoperformthenotching.
Repeatforallribs,checkingineachcasethattheflashing
is correctly ositioned.
Ifyouareusingahorizontaltool,benddownthetongues
beteen the notches over a suitable straight edge (such as
a iece o timber).
Notching with tinsnips
I notching tools are not available, lashings can be notched
to the rib roile ith tinsnis (Figure 3.7.2). The rocedure is
sometimes knon as scribing. Ater the cladding is ixed and
the turn-us inished, roceed as ollos.
Placetheflashingwiththeturned-downedgeresting
on the ribs. Markoutthenotchingusingatemplatepositionedover
each rib.
Cutthenotcheswithtinsnips.
This rocedure is also used or hi caings.
Fasteners or transverse lashings
You must roerly ix both lashings and the ends o all sheets.
where the cladding is ierce-ixed through crests, and the
osition o the urlin allos it, the asteners used to ix the
sheets, may also ix the lashings.
On all other installations, ierce-ix your lashing to the ribs or
crests o the sheets.
Joining lashings
The overlas o transverse lashings should be sealed ith a
recommended sealant and astened. Beore inally ositioning
and ixing the la, turn over the to iece and aly a 3mm
bead o sealant across the lashing, about 12mm rom the end.
Figure 3.7.2Using a temlate to mark out or notching ithtinsnis
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
14/40
14Lysaght arciecurl Deilin Mnul 2013
3.8 Flashing at change o pitch
Figure 3.8.1Tyical lashing at changes o itch
3.9 Capped bent ribbed roosTray cladding can be used in continuous lengths rom eave to
eave by cutting the ribs and bending the ans at the ridgeline.
The same rocess is used on Mansard roos. Cas are itted
over the cut ribs, hich oen u hen the ans are bent.
Fitting the rib cas can be time-consuming and care must be
taken ith sealing to avoid any ossibility o leakage.
The ribs must be cut squarely, ith a metal cutting blade in a
oer sa, set to the deth o the rib minus 2mm.
In some states ressed steel cas may be available to suit
KLIp-LOK ribs, though the range o angles is limited. Cas can
be handmade to suit any angle rom lat sheet.
KLIp-LOKis most requently used or caed bent ribbed roos,
but LONGLINE 305, TRIMDEK or even SpANDEK can be used.
For these our roiles the rib cas can be made rom ieces
o rib roile cut rom a short length o cladding. A neutral-cure
silicon sealant should be used.
and on flanges.Figure 3.9.1Caed bent ribbed roo
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
15/40
15Lysaght arciecurl Deilin Mnul 2013
3.10 Gutter apronwhere the ends o roo cladding are exosed to contaminants
such as sea salt or industrial ollutants it is better ractice to
rovide an over lashing hich discharges into the gutter or
souting or the olloing reasons. (see Figure 3.10.1 & 3.10.2)
Itprovidesameasureofprotectiontotheundersideofthe
roo cladding and the underlay.
Itprovidessupportfortheroofingunderlaywhichissubject
to damage rom ind and UV.
WherePVCspoutingisused,thereisanairgapbetween
the souting and the ascia because o the thickness
o the brackets. In coastal locations here the ends o
roo cladding are exosed this unashed area becomes
suscetible to corrosion and a gutter aron can minimise this
risk.
Ifthereisnospoutingorithasalowfront.
Itprovidesprotectionagainstwind-borneembers.
Wheretheendsofroofcladdingareexposedinasevere
environment, contaminants can be driven u the ribs o the
cladding. Metal scriber lashings or iller blocks can be used
to revent or inhibit ventilation.
The over-lashing should extend 50mm into the gutter and the
underlay inishes on the don-sloe o the lashing. I there is
no over-lashing to the gutter the underlay should be extended
into the gutter by a minimum o 20mm..
Figure 3.10.1Gutter aron: Quad
Figure 3.10.2Gutter aron: TRIMLINE/SHEERLINE
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
16/40
16Lysaght arciecurl Deilin Mnul 2013
3.11 Types o penetration lashing design
penetration lashings can be divided into our dierent tyes.
Type A
Underlashings are those that drain at the lane o the roo
an.
Soaker (under) lashingsSuitableforallpitches;
Thepreferreddetail;
Makethesidecurbinlinewiththerib;
Leaveminimumallaroundclearanceof10mm;
Allupstandsminimumof100mm;
Drillforrivetsbeforesealing;
Sealedlapsmustbeminimum25mm;
Ordercladdingsheetslongerforlapping;
Type B
Overlashings are those that drain at the lane o the rib o the
roo.
These are also knon as watershed or back lashings.
watershed lashings (over or back)
Simple
Recommendedtofirstpurlinfromtheridgeif>300mmwide.
Notsuitableifover1.100mwide
Notuniversallyacceptedaesthetically
Canbeusedinconjunctionwithsprungorover-roofdesign.
Type C
Taered lashings that drain at the lane o the roo an at the
to, and
over the ribs at the bottom.
These are also knon as under/over or transition lashings.
Taered or transition lashings
Providesgreaterrun-offcapacity
Suitableforallroofs>5.
Usedforaretrofit
Requiressupport.
Type D
Soaker lashings that drain at the lane o the roo an at the
gutter
Simple
Providesgreaterrun-offcapacity
Suitableforallroofs>5
Usedforaretrofit
Requiressupport
Limitedto1.1mwideand2.4mlong
Type A Under soaker
Type C Under/over tapered
Type B Over watershed
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
17/40
17Lysaght arciecurl Deilin Mnul 2013
Figure 3.12.1Flashing method 1: Head gutter
Figure 3.12.2
Flashing method 2: Flat tray and sleeve
3.12 Flashing large roo penetrationspenetrations through ribbed cladding block the valleys (or
ans), and thus aect the ree lo o rainater don a roo.
All lashings have to eatherroo the cladding but on the
uhill side o large enetrations, they also have to channel
rainater sideays into valleys that run unobstructed to the
eaves.
Four methods are described here. In all methods the ends o
cut ribs may be closed o ith cas on the outside o the rib,
or ith lugs inside the ribs. plugs must be used on side-las
to allo the anti-caillary cavity to drain.
Note: For masonry construction, Building Code Australia
(BCA) requires the use o Damp Proo Course (DPC) to ensure
weather-proofng. For acceptable methods see BCA section
on weather-proofng masonry.
Support raming
wherever one or more o the sheet ribs are cut, you must
rovide raming to suort the cut ends o the roo claddingeach side o the enetration.
Existing lashing
I you have to re-use lead lashings that are built into the
structure, secial rotection is needed.
Method 1: Head gutter and apron lashings
This is oten the simlest method, and commonly used or
existing rotrusions (Figure 3.12.1).
Method 2: Flat tray and sleeve
To avoid itting and sealing end cas to all the sheet ribs on the
lo side o the enetration, an aron lashing can be itted tothe sleeve and sealed to the tray each side.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
18/40
18Lysaght arciecurl Deilin Mnul 2013
Method 3: Tray gutter or steeper roos
I the roo itch is more than, say 1 in 12 (5), you cut the roo cladding
suiciently high above the enetration to allo a tray gutter to raise
rainater over the to o the sheet ribs and divert it around the
enetration (Figure 3.12.3).
Method 4: Penetration close to ridge capping
I a roo enetration is close to a ridge caing (or lashing above the
enetration), you can it a simle lat tray, on to o the rooing, so that itextends rom under the caing don to a sleeve around the enetration.
Figure 3.12.4
Flashing method 4:penetrations close to ridge caing
Figure 3.12.3Flashing method 3:Tray gutter or steeer roos
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
19/40
19Lysaght arciecurl Deilin Mnul 2013
Figure 3.13.2Small enetration ith sleeve
(Dektite sleeve illustrated)
Figure 3.13.1Small enetration ith metal skirt and sleeve
3.13 Flashing small roo penetrationsA langed cylindrical sleeve is a airly simle method o
lashing around small enetrations (such as ie enetrations)
hich it beteen the ribs o a roo sheet, or enetrate only a
single rib.
To methods are described here. wherever rooing is cut, you
must consider roviding extra suort or the rooing aboveand belo the enetration. where one or more o the sheet
ribs are cut, you must rovide raming to suort at the cut
ends o the roo cladding each side o the enetration.
Method 1: Tapered metal skirt and sleeve
This method uses arts custom-abricated rom metal. There
is no ositive seal beteen inside the building and the outside
atmoshere (Figure 3.13.1).
Method 2: Sleeve
This is oten the simlest method (Figure 3.13.2). Flexible
langed sleeves can be bought or lashing around
enetrations o at least 350mm diameter. They overcome the
roblem o caing and sealing the oen ends o cut ribs. A
sleeve is commonly used, though silicone sealant has a ider
oerating temerature range and is available in a ider range
o colours.
The lange around the base o the sleeve can be contoured by
hand to match the cladding roile beore it is sealed and ixed
to the cladding.
Be careul not to dam any valleys or ans so that rainater
can drain reely rom the high side o the roo enetration.
Moisture held in such areas can cause deterioration o the
sheet coating, reduced lie exectancy or oor aearance.
where damming o any valley or tray is unavoidable, due to
the size o the ie enetration, treat the installation as a large
enetration.
Copper penetrations
All coer ie enetrations through ZINCALUME orCOLORBOND steel cladding must be hysically and
electrically isolated rom the cladding. This can be done by
using a sleeve o pVC olythene or similar lastic that is also
ultra-violet stable.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
20/40
20Lysaght arciecurl Deilin Mnul 2013
Table 3.14.2Maximum distance beteen to & bottom roso asteners on a sheet, beore exansion joint is
needed
Table 3.14.1Thermal exansion and contraction o steelcladding
3.14 ExpansionBackground on thermal expansion
All metals exand and contract ith changes in temerature.
Although steel is by ar the least aected o all the metals
commonly used or roo and all cladding, the changes in
length exerienced in very long runs o rooing are signiicant.
On a clear hot summer day, ith no ind, the steel
temerature in roo cladding can reach aroximately 50C
in COLORBOND SURFMIST, 60C in lain ZINCALUME and
more than 80C in COLORBOND NIGHT SKY.
Examles o the thermal changes in lengths o steel cladding
that ould result rom various temerature changes in the
steel are shon in Table 3.14.1.
The actual exansion or contraction beteen the end o a
sheet and the last suort ould only be a raction o the
igures shon because the movement in the length o ixed
cladding ould normally take lace rom the centre toards
each end o the sheet. The movement at each end is thus onlyhal the total exansion or contraction.
Transverse thermal exansion oses no roblems in ribbed
cladding because each rib absorbs some transverse
movement.
Expansion joints
Thermal exansion eects are mitigated by slight bending o
astener shanks, thermal movement o the building structure,
and slight lexing o the urlins (here they are not restrained
by cleats or bridging). Hoever, or very long runs o rooing,
you should include an exansion joint to overcome linear
thermal exansion.
Table 3.14.2 shos the maximum distance beteen the to
and bottom ros o asteners on a ierce-ixed sheet. For
LONGLINE in distances o greater than 35m, lease contact
your Service Centre or advice. I the total length o to sheets
ierce-ixed through the la, or a single sheet exceeds this
distance, then an exansion joint is needed. There should be
no more than one ierce-ixed end-la beteen exansion
joints.
An exansion joint involves overlaing the ends o the
uer sheets over the ends o the loer sheetsbut ith aclearance beteen them (about 15mm). A tyical overla is
250mm (this overla is not the same as the overhang in Table
3.7.1 hich does not aly to exansion joints). The clearance
is usually created by having all the urlins or the rooing on
the high side o the joint, higher than the rooing on the lo
side o the joint. An extra urlin is needed at the joint. A bale
lashing rovides eatherrooing. See Figure 3.14.1.
where there is a risk o high inds, or the ribs result in a large
oening, you may need rotection, such as extra lashing or
the inclusion o closed-cell oam inill stris.
250mm
minimumoverlap
Baffle flashing.Notch overribs & fasten tounderlappingsheet
25 mm min.
clearance
300mm
Trays turned up
Depth ofsheeting
plus15 mm
Added protectionif required
Sheetingturned down
/pans
Figure 3.14.1Exansion joint detail
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
21/40
21Lysaght arciecurl Deilin Mnul 2013
3.15 Standard roo lashingsLYSAGHT Standard lashings by region
Although some lashings are common to all regions, the
climactic conditions can cause variations in the local roduct
requirements. please check ith your local BlueScoe Lysaght
sales reresentative or the roduct oer in your area.
Other lashings are available as secial orders.
70
200
10
20160
Ne South wales
Barge capping
CUSTOM ORB & BLUE ORB
TRIMDEK & SpANDEK
KLIpLOK
70
190
10
30120
70
180
10
40120
Barge roll
50dia.
2400 mm length only
Ridge capping*Nominate roof itch
CUSTOM ORB & BLUE ORB
TRIMDEK & SpANDEK
KLIpLOK
CUSTOM ORB & BLUE ORB
100 18020
160
100 17030
120
100 16040
120
10
230140
20
*Nominateangle
10
220
14030
10
210
deg
140 40
190
50 16020
2400 mm length only
Barge roll capping
Spear point
180180
30 30120
170170
30 30120
160160
40 40120
50
127
19300
127
19
Tile flashingCUSTOM ORB & BLUE ORB
TRIMDEK & SpANDEK
KLIpLOK & SpANRIB
2020
11801180
140210 210
145145
145
545
Valley flashingValley flashing
Ribbed valley
Structural valley
Valley suort
Barge gutter
deg
deg
120
120
120
120
120
120120
120
Apron flashingCUSTOM ORB & BLUE ORB
TRIMDEK & SpANDEK
KLIpLOK & SpANRIB
160
*
*
*
*
145
140
*
*
*
*
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
22/40
22Lysaght arciecurl Deilin Mnul 2013
2525
120120
50
310
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
23/40
23Lysaght arciecurl Deilin Mnul 2013
100
KLIP-LOK Barge
10
294
550 or 770mm wide
150
150
7010
10
SPANDEK & TRIMDEK
SPANDEK & TRIMDEK
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
24/40
24Lysaght arciecurl Deilin Mnul 2013
3.16 Non standard roo lashings, cappings and gutters
A
B C
D
E
F
GHA
A
A
A
A
A
A
A
A
A
A
A
A
B
B
B
B
B
B
B
B
B
B
B
B
B
C
C
C
C
C
C
C
C
C
C
C
C
C
D
D
D
D
D
D
D
D
D
D
E
E
E
Profile typesType 1 (CF1)
Type 2 (CF2)
Type 3 (CF3)
Type 4 (CF4)
Type 5 (CF5)
Type 6 (CF11)
Type 7 (CF12)
Type 8 (CF13)
Type 9 (CF14)
Type 10 (CF15)
Type 11 (CF31)
Type 12 (CF32)
Type 13 (CF33)
Type 14 (CF35)
Order requirements
On a sketch sho
1. proile tye
2. Colour (or ZINCALUME
steel, or GALVABONDi
not COLORBOND steel)
3. Side on hich colour
is to be (use letters
shon belo)
4. Dimensions (use letters
shon belo)
5. Angles on all bends that
are not 90 degrees
6. Quantity and lengths
Preliminary
Check ith your local
BlueScoe Lysaght oice or:
1. Available girth range2. Available colours
3. proiles not shon
4. Maximum lengths
5. Lead times
6. Ho to handle
taered lashings
This age shos some non-standard roiles. please ask your local BlueScoe Lysaght oice or other otions.
egnarhtriG )mm(006001
057002
009003
0001004
0021005
(Up to 400mm girth)
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
25/40
25Lysaght arciecurl Deilin Mnul 2013
Figure 3.17.1Box gutter
Box gutter
Box gutter
3.17 Box guttersLYSAGHT standard design
Box gutters are designed to suit large ater carrying caacity
requirements, usualy on commercial buildings.
In eect, a box gutter oerates like an oen drain. Designing
or a box gutter requires adequate suort or the gutter
be rovided, both at the sides and belo, to rovide or theanticiated eight o the ater collected.
As ith all gutters, adequate all must be rovided as ell as a
rainhead or other large caacity drainage system.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
26/40
26Lysaght arciecurl Deilin Mnul 2013
3.18 Barge Gutters and cappingsBarge gutters are designed to rovide an otion or the
rainater carrying caacity or the sides o buildings.
This detail is the most common ay to lash the side o a steel
clad roo.
100mm
Barge
Barge flashing
150mm
150mm
150mm
Flange to match
profile depth
2-piece seamed
barge capping
required for
curved roofs
Barge
Purlin
Barge flashing
Figure 3.18.1Barge gutters and caings
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
27/40
27Lysaght arciecurl Deilin Mnul 2013
Figure 4.1.1Tyes o lashing las
4. Typical wall lashings
4.1 Cladding orientationCladding is usually installed ith the roile running vertically
or horizontally, though sheets have been laid diagonallythe
choice is aesthetic.
wind can drive rain hard against all lashings, so it is
imortant that you ay attention to the detailing o lashings
around indos, doors, re-entrant and external corners, to
ensure you get a atertight building. You also ant a neat
aearance.
we make all lashings or some all claddings (like
EASYCLAD and MINI ORB) hich are sometimes called trims.
where these are not suitable, custom-made lashings can be
easily roduced olloing the general rinciles described in
this section.
4.2 Walling proile running horizontally Itisusualtolaythefirstsheetatthebottomofawalland
ork uards toards the eaves. You ant the indo
and door lashings to it roerly into the valleys, so you
should locate the irst sheet relative to the heads and
sills o doors and indos. Thus, you irst have to decide
here the cladding ill eventually be located at the heads
o doorays and at the heads and sills o indos beore
you lace the irst sheet.
Wherepossible,selecttheverticalsizeofwindowssothat
the lashings at both heads and sills ill coincide neatly
ith the itch o your roile
Besurethatthecrestsoftheprofilealignwitheachother
on adjacent alls, either side o a cornerthis ensures
that horizontal lashings it roerly into all valleys.
Wherevalleyscreateavoidatflashings,useclosed-cell
oam lastic inill
Wherewind-drivenraincanbeexpected,turnbackthe
edges o lashing to restrict ater movement ast the
lashing.
Direction of water flow 150-200mm overlap
Continuous beads
of silicon
Continuous beads
of silicon
15mm
15mm
Straight overlap flashing Soaker (underlap) flashing
Openings
200/300
mm
Maximum as
recommended
for profile
Sheet Overhang Recommended Minimum Drainage
50mmm
inimum
25mm
(15mm min.)
Minimum fall
for drainage 5
Minimum fall
for drainage 5
Flashing is fixed using self drilling screws or rivets. Fixing as close as possibleto the edge reduces distortion. Wind exposed areas near the edge of the
building may require additional fixing.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
28/40
28Lysaght arciecurl Deilin Mnul 2013
10mm
minim
um
10mm
minim
um
10mm
minim
um
35typical
Drip Edge
10mm
minim
um
135typical
Edge Break Mountain Fold Turn Down
10
mm
minim
um
A small gapmay remain
after crushing.
Flatten
to suit depth of profile
Roof Underlap
Wall Side Underlap(Horizontal sheeting)
Wall Side Overlap(Horizontal sheeting)
Vertical Wall UnderlapVertical Wall Overlap Vertical Wall Overlap
Roof Overlap
100/150mm
100/150mm
100/150mm
150/25
0mm
150/25
0mm
50/100mm
Drip edge
50/100mm50/100mm
Figure 4.1.3Tyes o lashing las
Figure 4.1.1
Edge tyes
4.3 Types o lashings
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
29/40
29Lysaght arciecurl Deilin Mnul 2013
CD 3 Fascia to Sot Section,
Use ith pANELRIB, MINI
ORB, EASYCLAD, MULTICLAD
CD 1 Trim Channel
Use ith MULTICLAD,
EASYCLAD
CD 4 Feature Section Sot
Use ith pANELRIB, MINI
ORB, EASYCLAD, MULTICLAD
CD 20 Butt Joint trim - To
Hat. Use ith pANELRIB,
MULTICLAD and MINI ORB.
CD 15 Tee Section. Use ith
pANELRIB, MULTICLAD EASY-
CLAD and MINI ORB.
CD 8 purlin hat Section
Use ith MULTICLAD, EASY-
CLAD
CD 6 Internal Corner. Use
ith pANELRIB, MULTICLAD
EASYCLAD and MINI ORB.
CD 21 Butt Joint Trim -
Overla.
Use ith MULTICLAD
CD 22 Edge Trim
Use ith MULTICLAD and
MINI ORB. (Enquiry only in S.A.)
CD 23 External Corner. Use
ith pANELRIB, MULTICLAD
EASYCLAD and MINI ORB.
CD 24 Internal Corner. Use
ith pANELRIB, MULTICLAD
EASYCLAD and MINI ORB.
EC 3 Fascia Caing. Use
ith pANELRIB, MULTICLAD,
TRIMwALL, EASYCLAD and
MINI ORB.
CD 39 Trim Channel
Use ith EASYCLAD.
CD 40
Starter Cli
Use ith EASYCLAD.
CD 30 Fascia Caing. Use
ith pANELRIB, MULTICLAD,
TRIMwALL, EASYCLAD and
MINI ORB.
CD 27 Fascia to Sot
Section. Use ith pANELRIB,
MULTICLAD, EASYCLAD and
MINI ORB.
4.4 Optional wall trimsAvailable in ZINCALUME steel or COLORBOND steel*
38
38
28
28
28
22
17 15
28
1833
20
2838
20
25
28
1028
25
25
2.5
48
15
15
16
19
46
27
38
38
25
15 15
20 20
i i
28
28
15
75
145
45
50
38
15
20
22
CD 5 External Corner. Use
ith pANELRIB, MULTICLAD
EASYCLAD and MINI ORB.
Our range o all trims are available or the range o LYSAGHT
cladding roles to rovide an attractive comliment to alls,
ceilings or sots.
Some trims are used to start the installation o the alling
anels hilst others rovide the erect nishing touch.
Made rom COLORBOND or ZINCALUME steel*, they are an
attractive, long lasting addition to any alling installation.
Not all trims are available in all locations and some
dimensions may vary rom state to state - or local availability
o all trims, contact your local sales oce.*Other materials, such as stanless steel and COLORBOND Ultra are
available, subject to enquiry.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
30/40
30Lysaght arciecurl Deilin Mnul 2013
4.6 Internal wall connections
4.5 Mid wall connections
50mm
minimum
flange
50mm
minimum
30mm
min.
Depth to suit profile
Depth to
suit profile
Wallsupports
Continuoussilicon seal
Continuoussilicon seal
Sheet overlap
Verticalconnection
Cladding profile
Cladding profile
Flashing
Cladding profile
Claddingprofile
Cladding profile
Flashing
Flashing
Flashing
Notched to
suit profileFeathered edge
(165 typical)
Profiledepth
50mm(typical)
Profile depth+ 10-25mm
50mm(typical)
Internal Corner Trim
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
31/40
31Lysaght arciecurl Deilin Mnul 2013
4.7 External corner connections
4.8 Flashing or horizontal cladding
To suitprofile
To suit
profile
To suit profile
50mm
typical
External Corner Trim
50mm
typical
50mm
typical
50mm
typical
To suitprofile
To suit
profile
50mm
typical
50mm
typical
3030
50
75
50
30
10
10
10
10
1010
10
75
50 (75 without hem)
25 subject tocorrugation
10
50
1010
10
Flush under jamb
Flush jamb
Flush head
Flush sill
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
32/40
32Lysaght arciecurl Deilin Mnul 2013
Figure 4.10.1Flashings or vertical cladding
4.10 Flashings or vertical claddingThe lashing detailing or vertical cladding is similar to roo
cladding enetrations, as the ater rom the under has to
drain over at the indo or door head. The most satisactory
detail is to rovide a sheet la at the head lashing, hich
enables automatic eathering by roiling the vertical ustand
o the head lashing or by lattening the la.
This detail can be used or corrugated, ribbed and traezoidal
cladding. Do not sto end the lashing but turn it don as
draing 4.10.1 and 4.10.2
Figure 4.9.1Butt details
4.9 Flashing or horizontal corrugate claddingDesigners and contractors using horizontally ixed corrugate
sheets as a design eature on industrial develoments and
commercial buildings, as ell as in domestic situations should
recognise that a high standard o quality o detailing and
ixing o the cladding is required and that there are a number
o requirements hich dierentiate horizontal rom vertical
roiled cladding.
Because horizontal cladding emhasises the deects in the
line o the raming to a ar greater extent than does vertical
cladding, the lane o the suorts both horizontally and
vertically should be straight ithin a tolerance o 5mm in 10
metres, and there should be little or no tist beteen the
vertical and horizontal lanes o raming members.
The cladding contractor should insect and arove the
standard o raming beore the commencement o any cladding
installation.
Horizontal cladding should be ixed in the an as this rovidesa stronger, more economical and aesthetic astening than
crest or rib ixing. The number, sacing and the osition o
the asteners are determined by the ind design load or the
building.
A simle and aesthetically accetable butt detail to join
horizontal cladding is to rovide a vertical break at structural
steel rame centres by the use o a to hat or tee lashing
section, but it is necessary to establish the exact sheet length
required, and or these sheets to be cut accurately to ithin
1mm to rovide a neat joint.
when horizontal metal cladding is directly ixed to a lined and
insulated all, designers should be aare o the likelihood
o condensation and it is recommended that horizontal las
should be sealed ith la tae or sealant.
100mm crush and
old to be fattenedover a sacer bar
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
33/40
33Lysaght arciecurl Deilin Mnul 2013
4.11 Window lashings or metal claddingproiled metal cladding has been used or many years as
both vertical and horizontal cladding, articularly on garages
and arm buildings here the aesthetic requirements and
eathering may not have been the rime consideration. As
most o these buildings are oen and unlined, the cavity isnaturally vented and minor ater ingress can be tolerated,
but i the building is lined then there should be no ingress o
moisture. For this reason or lined and insulated buildings in
higher risk areas cavity construction is required. Buildings are
considered to be higher risk hen they are situated in a very
high ind design load areas (
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
34/40
34Lysaght arciecurl Deilin Mnul 2013
1
2
3
Figure 4.13.1 STAGE 1
1 Corrugate flattened
2 Underjamb folded out to suit profile
3 Closed cell filler block perforated for ventilation1
1
2
3
4
Figure 4.13.2 STAGE 21 All ends stopended
2 Underjamb folded out
3 Closed cell filler block adhered to profile with contact spray adhesive
4 25mm 12# fasteners hidden behind overjamb
4.13 Flush window lashingsThe height o the sill fashing may have to bealtered to suit the osition o the role.
Flush mounted indos or doors can have icture
rame fashings, hich means that the indorame is mounted externally to the cladding, orcan have timber acings, or a large number o
alternative designs.Both the fush and recess fashings have an under
jamb and a ront or ace jamb.
Trim sizes or aluminium indos are usually lus10mm on the jamb liner size, hoever in order
obtain a vertical ustand the trim size or fushfashing design requires lus 15mm vertically, toallo or a 10mm acker.
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
35/40
35Lysaght arciecurl Deilin Mnul 2013
1
2
Figure 4.13.3 FLUSH WINDOW HEAD FLASHING
1 10 angle minimum
2 Turn down end of extended head flashing
1
2
3
4
Figure 4.13.4 FLUSH WINDOW SILL FLASHING
1 Overjamb hemmed behind window
2 Underjamb hemmed on face and hooked above profile.NB depth of underjamb is 12mm greater than profile height
3 End of sill dog-eared and turned up 10mm to receive overjamb
4 Trim height increased 10mm to accommodate sill turn-up
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
36/40
36Lysaght arciecurl Deilin Mnul 2013
4.14 Recessed window lashingsA recessed indo fashing design is considered thebest otion or horizontal cladding but accurate fashing
measurement and installation are required to rovideeather-tightness.
N.B. For lined buildings a cavity is required orhorizontal metal cladding.
3030
3050
25
30
50
30
50
10
10
10
10
10
10
10
15
15
15
15
15
50 (75 without crush and fold)
Recessed under jamb
Recessed jamb
Recessed head
Recessed sill
1
2
RECESSED WINDOW
HEAD FLASHING
1 10 angle minimum
2 Turn down end ofextended headflashing
1
2
3
4
RECESSED WINDOW
SILL FLASHING
1 Overjamb hemmed behind window
2 Underjamb hemmed on face and hooked above profile.
Note: Depth of underjamb is 12mm greater than profile height
3 End of sill dog-eared and turned up 10mm minimum to receiveoverjamb
4 Trim height increased 10mm to accommodate sill turn-up.
Figure 4.14.1Recessed indo lashings (underlay is omitted or clarity)
Figure 4.14.2Recessed indo head (detail)
Figure 4.14.3Recessed indo sill (detail)
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
37/40
37Lysaght arciecurl Deilin Mnul 2013
1
4.15 Butt window lashings
Alternative details that allo the cladding toterminate u to a fashing ithout overfashing it,
require accurate tting in order to be eathertight.(see Figure 4.15.2). These details are knon asbutt fashings and can be used on fush or recess
designs, ith a one-iece jamb. They are only
suitable or areas ith lo or medium ind designloads or in rotected areas and require recisedesign, recision measurement and manuacture torovide a eather-tight solution.
Butt indo fashings also require accurateinstallation to rovide an aesthetically accetablesolution, they should allo or drainage o a large
catchment, they require extra timber or xing, andor these reasons they are not a reerred detail.
The total amount o ater draining rom the
catchment area above rom multi-storey constructioncan be considerable, and butt fashings should
disose o it as a enetration. The catchment iscalculated by multilying the idth o the indooening by hal the height.
10
10
10
10
10
10
15
15
15
15
25
25
25
50
50
50
50
25
subject tocorrugation
Butt jambButt sill
Butt head
50 (75 without crush and fold)
Figure 4.15.1Butt indo lashings (underlay is omitted or clarity)
Figure 4.15.2Butt indo head lashing Figure 4.15.3Butt indo sill lashing
10 angle minimum
1
2
3
4
5 BUTT SILL FLASHING
1 jamb overlaps sill
2 Jamb hemmed both sides
3 Extra timber required
4 Alternative soaker jamb taken to the ground
5 End of sill closed and scribed to profile
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
38/40
38Lysaght arciecurl Deilin Mnul 2013
1
4.16 Flashings or vertical cladding
windo and door fashings or vertical cladding are similarto those used or horizontal cladding hoever a cavity is not
required or vertical cladding.
The main dierence is that the module is running horizontallyand thereore some fexibility is required i the fashings are to
be equal on both sides. To rovide or this the trimming size o
the indo oening should be lus hal the module dimensionto allo adjustment or equalisation on both sides to occur.
Figure 4.16.1Head lashing or vertical oriented cladding
Figure 4.16.2Sill lashing or vertical oriented cladding (underlayis omitted or clarity)
1. Flatten corrugation la
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
39/40
39Lysaght arciecurl Deilin Mnul 2013
4.17 Alternative Flashing designs
There are other alternative design otions to those shon thatdesigners should consider or butt designs hich rovide aeather-roo indo fashing alternative. I the oening is
anelised the vertical jamb fashing can be extended rom so-t to the ground or single storey buildings or to a module breakin a multi-storey building as shon in draing 4.16.1.
This alternative rovides the oortunity to use the same oran alternative material at the head and sill areas and a to hatfashing is used to obtain a module break.
Figure 4.17.1Alternative lashing designs
Alternativematerial
-
7/27/2019 LysaghtArchitecturalDetailingManualRoofWallFlashingV2June2013
40/40
Fr chic quir c 1800 641 417,
email [email protected]
product Descritions
All descritions, secications, illustrations, draings, data, dimensions
and eights contained this catalogue, all technical literature and
ebsites containing inormation rom BlueScoe Lysaght are
aroximations only.
They are intended by BlueScoe Lysaght to be a general descrition
or inormation and identication uroses and do not create a sale by
descrition. BlueScoe Lysaght reserves the right at any time to:
(a) suly Goods ith such minor modications rom its draings
and secications as it sees t; and
(b) alter secications shon in its romotional literature to refect
changes made ater the date o such ublication.
Disclaimer, arranties and limitation o liabilityThis ublication is intended to be an aid or all trades and roessionals
involved ith seciying and installing LYSAGHT steel building roducts
and not to be a substitute or roessional judgement.
Terms and conditions o sale available at local BlueScoe Lysaght sales
oices.
Excet to the extent to hich liability may not laully be excluded or
limited, BlueScoe Steel Limited ill not be under or incur any liability to
you or any direct or indirect loss or damage (including, ithout limitation,
consequential loss or damage such as loss o roit or anticiated roit,
loss o use, damage to goodill and loss due to delay) hoever caused
(including, ithout limitation, breach o contract, negligence and/orbreach o statute), hich you may suer or incur in connection ith this
ublication.
Coyright BlueScoe Steel Limited 13 June, 2013