m. french - welcome to plant miller

Upload: recsco2

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 M. French - Welcome to Plant Miller

    1/17

    Morgan FrenchTechnology & Technology ManagementSouthern Company

  • 7/28/2019 M. French - Welcome to Plant Miller

    2/17

    History of Miller

    Plant Miller is named for James H. Miller Jr., who was asenior vice president and member of the board ofdirectors of Alabama Power Company. He was with

    Alabama Power Company for almost 30 years. Plant Miller first provided electricity in 1978 when the first

    of four generating units had been completed. Unit 1began commercial operation on 10/12/1978; Unit 2 on

    05/01/1985; Unit 3 on 5/01/1989; and Unit 4 on 3/05/1991.Each of its four units can generate 720 million watts ofelectricity. That is enough electricity to serve the needsof about 825,000 homes.

  • 7/28/2019 M. French - Welcome to Plant Miller

    3/17

    Plant Miller Facts

    Plant Miller is the largest coal-fuel power plant in the state.At the present, Plant Miller isalso the largest operating

    electric generating plant in thestate, surpassing all coal andoperating nuclear plants

    Plant Miller burns around9,600 tons of Powder RiverBasin (PRB) coal/day on eachunit or around 12,000,000 tonsper year

  • 7/28/2019 M. French - Welcome to Plant Miller

    4/17

    Plant Miller Facts Cont.

    Plant Miller cost $1.9billion dollars toconstruct. During

    construction 11.6 millioncubic yards of dirt androck were removed fromthe construction site, and485,000 cubic yards ofconcrete were used.

  • 7/28/2019 M. French - Welcome to Plant Miller

    5/17

    Miller Environmental Upgrades

    SCRs- Selective CatalyticReduction

    The Problem

    Whenever coal is burnedin air, the components ofair oxygen and nitrogencontent in the coal cancombine to form nitrogenoxides, or NOx.

    NOx is a green house gasand is regulated under theClean Air Act.

  • 7/28/2019 M. French - Welcome to Plant Miller

    6/17

    Miller Environmental Upgrades

    SCRs Cont. The Solution

    SCRs reduce NOX, by80-90%

    Units 3 and 4 placed inservice in 2003

    Units 1 and 2 placed inservice in 2005

    Cost of $400,000,000 The SCRs operate at around 700F.

    Ammonia is injected into the gasbefore it enters the SCR. Thecatalyst aids the NOx and theammonia mixing to produceharmless nitrogen gas and water.

  • 7/28/2019 M. French - Welcome to Plant Miller

    7/17

    Miller Environmental Upgrades FGDs- Flue Gas

    Desulfurization Scrubbers

    The Problem The coal burned to produce electricity

    contains sulfur, an element that when

    burned in air produces sulfur dioxide(SO2). The amount of SO2 emitted isdirectly related to the amount of sulfur inthe coal

    PRB coal contains approximately 0.4%sulfur while Eastern coal contains

    approximately 1% sulfur. SO2 can cause acid rain and is regulated

    under the Clean Air Act

  • 7/28/2019 M. French - Welcome to Plant Miller

    8/17

    Miller Environmental Upgrades

    FGDs Cont. The Solution

    Scrubbers reduce SO2emissions by 95-99%

    Reduces mercury and fineparticulate emissions

    In service dates: Unit 3 (December

    2009)

    Unit 4 (February 2010) Unit 2 (April 2010) Unit 1 (April 2011)

    Total Miller costapproximately $900million

  • 7/28/2019 M. French - Welcome to Plant Miller

    9/17

    Miller Environmental Upgrades

    The Process: CaCO3 + SO2 + 2 H2O +

    1/2 O2CaSO4 Limestone + SO2 + Water

    + OxygenGypsum

    On Average, for every tonof SO2 removed:

    * 1.7 tons of limestonemust be used

    * 3.5 tons of gypsumproduced

  • 7/28/2019 M. French - Welcome to Plant Miller

    10/17

    Plant Miller Today

  • 7/28/2019 M. French - Welcome to Plant Miller

    11/17

    Miller Environmental Controls

    Scrubber

    SO2Control New

    Stack

    Gypsum

    Coal Fired Boiler

    AirHeater

    BottomAsh

    CoalMill

    Flyash

    Low NOXBurners

    Fan

    OldStackSCR

    NOXControl ESP

    Since 2000 Plant Miller hasspent over $1billion on newEnvironmental controls

  • 7/28/2019 M. French - Welcome to Plant Miller

    12/17

    Future Environmental Controls/Tests

    Mercury Control Calcium Bromide Injection Scrubbers

    Coal additives Etc

    CO2 ADA Solid Sorbent

    Technology

  • 7/28/2019 M. French - Welcome to Plant Miller

    13/17

    Project Goals

    The overall objective of thisfunding stage is to validate solidsorbent-based post combustionCO2 capture through slipstreampilot testing.

    Project Goals: Achieve 90% CO2 Capture Make progress in limiting the

    increase of Levelized Cost of

    Electricity LCOE to 35% for acommercial unit

    Generate a high purity CO2stream

    Successfully scale sorbents

  • 7/28/2019 M. French - Welcome to Plant Miller

    14/17

    CO2 Removal Technology

    Process Flue gas passes through

    Adsorber module where sorbentparticle adsorbs CO2

    Regenerable solid sorbentcycles between Adsorber andRegenerator. Raising thetemperature of the of thesorbent releases CO2

    Flue GasPreparation

    CO2Adsorber

    Baghouse

    Regenerator

    Baghous

    e

    Flue Gas

    CO2

    Solid Sorbent

    HeatExchanger

    Process Blower

    1 MW Pilot

    Flue

    gas

  • 7/28/2019 M. French - Welcome to Plant Miller

    15/17

    Potential Benefits of Solid Sorbents Energy Penalty

    Sensible heat requirement is less although heat recovery should beconsidered

    Latent heat of evaporation Corrosion

    Less expensive materials of construction No corrosion inhibitors required

    Air Reduced emissions of amines

    Water Less cooling water required Minimal liquid waste

    Process Flexibility and Operability Can be applied to cycling plant load

    following

    No risk of foaming or other solvent-related challenges

  • 7/28/2019 M. French - Welcome to Plant Miller

    16/17

    Project Location

    Unit 1 Scrubber

    ~ 50-60~ 80-90

  • 7/28/2019 M. French - Welcome to Plant Miller

    17/17

    Questions??