M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… SUPERCONDUCTING CIRCUITS RE- COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

Upload: carlos-wolf

Post on 01-Jan-2016

50 views

Category:

Documents


1 download

DESCRIPTION

M . Pojer, on behalf of the usual bunch of suspects…. Superconducting circuits re-commissioning after the 2011 Christmas break. Cryogenics master plan. N & w-e. 7/24. Fundamental dates. Starting from w.6 (Feb.6) the machine shall be patrolled - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: M .  Pojer, on behalf of the usual bunch of suspects…

M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS…

SUPERCONDUCTING CIRCUITS RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

Page 2: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 2RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

CRYOGENICS MASTER PLAN

N & w-e 7/24

Page 3: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 3RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

FUNDAMENTAL DATES

• Starting from w.6 (Feb.6) the machine shall be patrolled• From Feb.6, start of ElQA on sector 67 (the day after on S23)• From Feb.8, start of powering tests (Phase II directly), after cable connection

and PC unlocking

• Shifts proposal (experts in CCC [EPC-QPS-MP3]/OP)– A shift (17:00-23:00) for the first two weeks (till Feb.19), w-e excluded / A– 2 shifts (M+A – 7:00-15:00-23:00) for the first 2 w-e / M+A– 2 shifts starting from w.8 (Feb.23) / 7/24– PIC on call

AM+A

AM+A

A+N

7/24

Cham

onix

Page 4: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 4RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

POWERING PARAMETERS

Page 5: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 5RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

STRATEGY FOR ELQA

Page 6: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 6RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

STRATEGY FOR ELQA

No specific ElQA test will be done in the tunnel as the boards will be singularly tested and transported in a safe envelope. Coherency check done by CRYO during cool-down!

Page 7: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 7RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

THE BASELINE (T.B.C. IN CHAMONIX) IS 4 TEV

• Reconfiguration of PCs (HW and SW limits)• Main circuits (6770 A required for RB; commissioned up to 6850 A)

– No extra powering tests / no pyramids– No need for reconfiguration of energy extraction – needed for 5 TeV– Inductance coefficients recalculation (1 ramp at least)– No quench issue till ~5 TeV (RB.A78 had a training quench below!)– RB.A78 - ElQA tested up to 1.6 kV instead of 1.9 kV due to bad insulation on magnet B30.R7

(NC 1060444) --> ok for 4 TeV, veto to be lifted for higher energies

2011 baseline

Page 8: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 8RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

THE BASELINE (T.B.C. IN CHAMONIX) IS 4 TEV

• IPQ/Ds– No extra powering tests (change of I_nom)– No issue to go to 4 TeV (weakest magnet is RD2.R8, which is limited to 6.8 TeV)

• IT– Normally commissioned to 5 TeV– IT.R1 - weak electrical insulation of QH YT1121 to coil and/or ground (NC 1017174)

--> performance of a new high capacitance PS under evaluation; verification if the energy deposited by the new DQHDS is also enough for 4 TeV ongoing (K.Dahlerup-Petersen)

• Correctors– All yearly commissioned to at least 5 TeV– Some limitations on a few 120 A correctors (not for 4 TeV)– Cooling problems on the 120 A correctors of ITs (agreement with ABP to commission them for

use in MDs, but not needed even below 1 m b*)

EDMS doc. No1113965

Page 9: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 9RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

PROPOSED PARAMETERS

Page 10: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 10RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

PROPOSED PARAMETERS

Page 11: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 11RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

MAIN CHANGES

Page 12: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 12RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

SOFTWARE AND TOOLS

• Kajetan and Michael are working on a new GUI for follow-up, but also execution of tests. Debugging ongoing…

Page 13: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 13RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

EXOTIC STUFF: QPS ACTIONS

• RQTD/F threshold increase done• RQ9/10 threshold has been changed but a controller upgrade still has to be done• R2E related upgrade:

– Automatic power cycle option in 8 units in the machine not yet done– Splice detection firmware upgrade (in units located in high radiation areas) is still an option– New IPQ cards for radiation upgrade to be done once we have the cards (maybe on the first technical stop) – no

specific test more than the normal campaign is needed to validate the change– Crate controller upgrade in cell 8/9 still to be done (Reiner commented that it’s anyway possible to run without

it)

• A procedure on the heaters firing at 200 V is being prepared (Knud). Markus underlined that the java program to fire the heaters will have to be tested as soon as possible.

• No IPQs IPDs and ITs heater will be fired during IST (it’s done during the commissioning step of PIC2)• During the PIC2 tests, for most circuits the QPS trip signal is given by the sequencer, for some circuits

this is being done by a QPS expert. Can this be done by an operator or MP3 member?• F3/F4 circuit breaker: half of the machine done, still to be decided whether the other half will also be

done (Reiner and Knud think we better do it)• Installation of new signal cabling for the magnet and busbar voltage to the DQQDI detectors on all

RQ8/9/10 circuits: a meeting will be held this afternoon to discuss it• Undulator test will be organized on the spare in SM18. Special tests of the undulator in LHC: not clear,

check with A.Siemko• EE system of 4-5 600 A circuits has been changed (PNO.b1 has to be done) – list will be provided by

Knud• The campaign to change the switches of the QHPS will be finished before the HW commissioning

campaign, then Knud stressed that heaters discharge procedure is important

Page 14: M .  Pojer, on behalf of the usual bunch of suspects…

1/24/2012 14RE-COMMISSIONING AFTER THE 2011 CHRISTMAS BREAK

POSSIBLE IMPACT OF RF RE-COMMISSIONING (FROM P. BAUDRENGHIEN)

• Planning:– The RF should have a first sector cold on Feb 20, and the second on Feb 22-23– P. Maesen would start conditioning around Feb 22– By Feb 27th we would have a few cavities conditioned and we start the setting-up of

the RF loops. This will last till March 7th

• Modifications during shutdown:– Replacement of 8 drivers (out of 16)– Replacement of 4 klystrons (out of 16)– Replacement of ALL SMC cables in the UX45 faraday cage

• Consequences:– We will find problems when we start setting-up the RF between Feb 27th and March

7th. That will call for access in UX45 (not tunnel). Access is possible only if the magnets are at injection energy. So we will need to share time between powering tests and RF access