m56 scoping study final report · manchester airport and ljla are part of the tens. ♦ the m56...
TRANSCRIPT
Page 1 of 150
M56 Corridor Scoping Study
Final Report
JOB NUMBER: DOCUMENT REF: m56_scoping_study_final_report.doc
B GR/RF RF ACB ACB 24/09/04
A GR/RF RF ACB ACB 13/07/04
GR/RF GR ACB ACB 30/06/04
Originated Checked Reviewed Authorised Date
Revision PurposeDescription
M56 CORRIDOR SCOPING STUDY
Final Report
Page 2 of 150m56_scoping_study_final_report.doc
Contents
Section Page
Executive Summary 4
Glossary of Terms 13
1. Introduction 15
2. Scope and Objectives of the Study 16
3. Land Use and Planning Policy Context 23
4. Existing Travel Supply and Demand 35
5. Initial Baseline Assessment of Problems and Issues 57
6. Inventory of Problems and Issues and Potential Transport Measures
Identified Through Document Review and Stakeholder Consultation 67
7. Relating Identified Problems and Issues to Proposed Strategy Objectives 93
8. The Way Forward 104
References Forming Document Review 113
APPENDIX A 115
Terms of Reference for Study Objectives 115
APPENDIX B 122
Mersey Belt Study 122
APPENDIX C 125
Railway Station Audit 125
APPENDIX D 128
Key Highway Movements in Study Area 128
APPENDIX E 132
Key Rail Demand Movements in Study Area 132
APPENDIX F 137
Congestion Reference Flow 137
APPENDIX G 139
Potential Contribution of Identified Transport Measures to Strategy Objectives 139
M56 CORRIDOR SCOPING STUDY
Final Report
Page 3 of 150m56_scoping_study_final_report.doc
List of Tables
Table 2.1 – Proposed M56 Corridor Strategy Objectives 18
Table 4.1 – Existing Rail Service Provision in the Study Area 40
Table 4.2 – Existing Rail Routes in the Study Area 41
Table 4.3 – Existing Coach Services Relevant to the Study Area 42
Table 4.4 – Key Railheads within the M56 Corridor Study Area 42
Table 4.5 – Existing Rail Freight Services Relevant to the M56 Corridor Study Area 43
Table 4.6 – Existing Traffic Flows (2002) 44
Table 4.7 – Key Highway Movements in the Study Area 46
Table 4.8 – Summary of Key Rail Demand Movements in the Study Area 48
Table 5.1 – Existing Stress Levels (2002) on the Regional Road Network 57
Table 5.2 – Future Levels of Stress (2019) on the Regional Road Network 61
Table 5.3 – Rail Network Capacity Utilisation (2004 Network Rail Technical Plan) 63
Table 6.1 – Identified Highway Related Problems and Issues/Transport Measures in the Study Area 68
Table 6.2 - Identified Freight Related Problems and Issues/Transport Measures in the Study Area 78
Table 6.3 - Identified Passenger Rail Related Problems and Issues/Transport Measures in the Study Area 82
Table 6.4 – Identified Road Based Public Transport Related Problems and Issues/Transport Measures in
the Study Area 87
Table 6.5 – Identified Planning Policy and Land Related Problems and Issues in the Study Area 89
List of Figures
Figure 2.1 – M56 Corridor Study Area 19
Figure 2.2 – M56 Study Area and Regional Road Network 21
Figure 2.3 – M56 Study Area and Key Rail Network 22
Figure 3.1 – NWDA designated strategic regional sites 28
Figure 4.1 – Key Road Sections 35
Figure 4.2 – Standard of Highway Provision for the Key Road Network in the Study Area 39
Figure 4.3 – Existing Traffic Flows (2002 AADT) 45
Figure 4.4 – Daily Rail Passenger Boardings 47
Figure 4.5 - Percentage Private Vehicle Use as Mode to Work 49
Figure 4.6 - Percentage Public Transport as Mode to Work 49
Figure 4.7 - Percentage Rail Use as Mode to Work 50
Figure 4.8 - Percentage Bus and Coach Use as Mode to Work 50
Figure 4.9 - Average Distance (km) Travelled to Work 51
Figure 4.10 - Indices of Deprivation 51
Figure 5.1 – Existing Level of Stress for the Regional Road Network 59
Figure 5.2 – Number of Hours per Annum with Average Speeds Less Than 30mph 60
Figure 5.3 – Forecast 2019 Annual Average Daily Traffic (Central NRTF) 62
Figure 5.4 – Forecast Level Stress 2019 (Central NRTF) 62
Figure 5.5 – Train Capacity Utilisation 64
Figure 5.6 – Loading Gauge Map 65
M56 CORRIDOR SCOPING STUDY
Final Report
Page 4 of 150m56_scoping_study_final_report.doc
Executive Summary
INTRODUCTION
The M56 transport corridor broadly covers an area linking Manchester, Warrington and Chester to North Wales within the North West Region. The corridor is know to be an area of great economic potential,
particularly in knowledge-based industries. The M56/A5117(T)/A550(T) is the principal route through the corridor and with the M62 forms part of the main east-west transport spine in the North West that links the two Regional Poles of Manchester and Liverpool.
The primary objective of this scoping study is to make recommendations for further work to develop a long term strategy to address regional (as opposed to local) transport problems and issues in the M56 Corridor, including the contribution that public transport and other modes make.
M56 CORRIDOR STUDY AREA
The study brief defined the M56 corridor study area to be the area bordered by the Cheshire County
Council/Wirral Metropolitan Borough Council boundary and the River Mersey/Manchester Ship Canal to the north, the A5103(T) south from M60 to M56 to the east, the M56 from junction 1 to junction 7 includingManchester Airport and the A556/A54/A51/A55 south of Northwich and Chester to the Welsh Border. The
western limit of the study area was defined by the boundary between England and Wales.
It is our recommendation that the study area should be extended to logical transport decision points. For this reason the study area has been extended into the Wirral to encompass M53 junctions 5 and 6, and into
Wales to encompass the A55(T)/A494(T) Ewloe Interchange. For the purpose of this study it is consideredthat the English/Welsh border that dissects the study area is not relevant with respect to the operation of local economies, housing markets and travel areas.
M56 CORRIDOR OBJECTIVES
Whilst the study brief sets out the overall aims for the scoping study there was a need to develop a set ofobjectives for the long term strategy of the M56 corridor, within the framework of both the Government’s five key criteria for transport and wider regional objectives. Corridor objectives will help guide the identification of
measures that address the regional problems and needs of the study area, and need to designed to address problems rather than the symptoms arising from problems. The following core corridor objectives have been defined for the purpose of this study;
♦ enable economic regeneration and development in a manner that maximises achievement of
sustainability objectives;
♦ enhance accessibility and in particular to areas served by the corridor suffering from social exclusion including Merseyside, east Manchester, Halton and Ellesmere Port and Neston;
♦ enhance the image of the M56 transport corridor and provide high environmental and design quality;and
♦ management of natural, built and historic environment within the M56 transport corridor.
LAND-USE AND PLANNING POLICY
Regional Planning Guidance for the North West (RPG) identifies the centres of Liverpool and Manchester within the North West Metropolitan Area (NWMA) as the focus for future population and employment growth in the region, to support continued urban renaissance and support their regional role. Growth will also take
place in a number of sub-regional locations, including Stockport, Runcorn, Widnes, Ellesmere Port and Chester within this study area. The strategy seeks to maximise the use of previously developed land, which is in the main found within the urban locations identified above, to accommodate the growth. It also seeks to
reduce the need to travel by focussing major travel generators in urban centres and around public transport interchanges. The M56 has a strategic role in serving the NWMA.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 5 of 150m56_scoping_study_final_report.doc
The Regional Economic Strategy (RES) seeks to encourage knowledge based sectors in the region. It
identifies a number of sectors to be supported through a cluster based approach, including the provision of premises and incubators appropriate to their needs. Strategic Regional Sites have also been identified which will ensure that provision of sites suitable for the knowledge based sectors are available at a variety of
locations, including areas accessible to deprived communities which can capitalise on the existing presence of knowledge based activities.
The cross-border relationship between North East Wales and North West England area for economic and
social functions is recognised as a strength, although the associated travel patterns and peak timecongestion are a cause for concern.
Future development of the North Wales economy is likely to continue to capitalise on the strategic links via
the A55 with its neighbouring region and beyond using the motorway network. Accessibility to assets such as the airports at Liverpool and Manchester will be increasingly promoted and thus the M56 will continue to be a key factor in terms of the economic performance of the area.
EXISTING TRAVEL SUPPLY AND DEMAND
An important precursor to undertaking a multi-modal assessment of a transport corridor is that ofunderstanding the current pattern of movements on the transport network.
Regional Highway Network within the M56 Study Area
The M56/A5117(T)/A550(T)/A494(T) is the principal route through the corridor and serves a range of
strategic functions as follows:
♦ the M56(west of M6)/A5117(T)/A550(T)/A494(T) forms part of the Trans European Networks (TENs)
and is part of the E22 from Ireland, through North Wales (via Holyhead), that uses the M6 to join the M62 trans-pennine route to Hull.
♦ forms part of the main east-west transport spine in the North West linking North Wales and Cheshire with Greater Manchester and Yorkshire and Humberside.
♦ provides access to the Regional Pole of Manchester.
♦ the M56 forms part of the main road access to Manchester Airport. Access to the Liverpool John Lennon Airport (LJLA) can also be gained from M56 junction 12 and the Silver Jubilee Bridge. Both Manchester Airport and LJLA are part of the TENs.
♦ the M56 forms part of the strategic route for freight traffic destined for the Port of Liverpool, which
operates the UK’s largest Freeport zone, and port facilities at Garston and Birkenhead. It also provides access to the inland Port of Manchester (served by the Manchester Ship Canal).
The busiest section of the M56 is between junctions 4 and 3 (the A5103(T) Princess Parkway) with traffic flows in excess of 140,000 AADT. East of the A556(T) traffic flows on the M56 are still high at 110,000
AADT, before falling to 70,000 AADT between the A556(T) and M6. This reflects the strategic significance of the A556(T) which links the M6 at junction 19 and the M56 at junctions 7 and 8 and carries just under 50,000 AADT.
The M56 (west of M6) carries approximately 90,000 AADT, before falling to just over 30,000 AADT west of M53, with the majority of trips using the M53 south to Chester or north to Ellesmere Port and the Wirral.Further west on the A550(T) through Queensferry traffic flows rise sharply to over 50,000 AADT reflecting a
strong movement between North Wales and Ellesmere Port/Liverpool.
The M53 (south of the M56) carries just over 65,000 AADT, before dropping to 30,900 AADT south of the A56 reflecting the high proportion of trips which leave the M53 to travel into Chester
North of the M56 the A557/A533/A562/A561 route connects the M56 at junction 12 south of Runcorn with the A5300 ‘Knowsley Expressway’, with the Silver Jubilee Bridge carrying over 75,000 AADT.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 6 of 150m56_scoping_study_final_report.doc
In terms of key highway movements, these have been analysed for the following sections of regional
highway network;
♦ M56 between junctions 6 and 7 - the predominant movement is to/from M6 south (25%), trips that also use the A556(T). Longer distance M56 trips to M56 West/North Wales constitute 12% of the total.
♦ M6 between junctions 21 and 21a - the predominant movements are to/from M6 south (25%),Manchester (14%) and Manchester Airport (11%).
♦ M6 between junctions 16 and 17 - the predominant movements are to/from M6 North (24%),Manchester (21%) and Northwich/Mid-Cheshire (12%).
♦ Silver Jubilee Bridge– although only 20% of trips across the bridge are local (between Widnes and Runcorn) less than 50% of trips use the M56.
♦ A550(T) Queensferry - the predominant movements are to/from Ellesmere Port/Wirral (38%) and
onwards to Liverpool through the Mersey Tunnels (9%). Longer distance M56 trips to M56East/Manchester constitute 14% of the total.
Regional Rail Network within the M56 Study Area
The M56 Corridor is served by a number of railway lines each performing different roles. The West Coast Main Line runs south-north through the study area with a branch off towards Runcorn and Liverpool: stations are located at Warrington Bank Quay and Runcorn within the study area giving access to Virgin West Coast
services towards London and the borders/Scotland. This route is subject to major improvements as part of the West Coast Main Line upgrade with new tilting trains and line speed improvements.
Inter-regional links by rail are provided by the Arriva Trains Wales operated Manchester-Warrington-Chester-
North Wales and Crewe-Chester-North Wales services, which provide for both long distance movements as well as meeting more local needs from stations such as Helsby, Frodsham and Runcorn East.
A local rail link is provided by First North Western between Chester and Manchester via Northwich and
Altrincham with many intermediate (request only) calls. Local rail services are provided by First North Western and Merseyrail, these giving links around the Manchester area and Merseyside-Chesterrespectively.
An analysis has been undertaken of the LENNON rail ticketing data for the 2002-2004 financial year, along with that of the MOIRA train flow information. The main findings from this analysis are that;
♦ the Manchester-Altrincham-Northwich-Chester line is very self contained with few trips starting or
ending beyond the route;
♦ the West Coast Main Line carries through trips generally not starting or ending in the study area;
♦ the North Wales Coast Line carries longer distance through trips, primarily towards the South East and
Midlands (42%) but also towards Manchester (17%) and to Chester itself (24%); and
♦ most of the remaining routes are self-contained, with the potential exception of the Wrexham-Chester
line which shows appreciable levels of travel beyond Chester to either North Wales or the Wirral
Journey To Work Census Data
Use has been made of the 2001 census data to show the variation in mode of transport used to travel to work across the M56 transport corridor and surrounding area. The main findings from this analysis are that;
♦ the greatest concentrations of multiple-deprivation are the core areas of the Greater Manchester and
Merseyside conurbations with public transport (principally bus) accounting for up to 38% of the mode share for journeys to work and typically less than 10km in length. In Merseyside 40% of households have no access to car.
♦ the broad correlation between affluence and distance travelled to work supports the general trend that
with increased wealth people prefer to relocate to the urban fringes and surrounding rural areas but continue to work in the city centres, accepting the need to undertake a longer commute to work.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 7 of 150m56_scoping_study_final_report.doc
♦ without a high quality public transport network these longer journeys to work from the rural areas are
predominantly made by private vehicle, and this is typified by travel patterns across rural Cheshire.Where public transport services are poor, reliance on the car increases, such as in and around the areas of Northwich, Middlewich, Winsford and Kelsall. As the standard of public transport provision
improves so does the uptake to it, as exemplified by above average rail use for areas near the Crewe-Manchester spur of the West Coast Main Line.
♦ longer journeys to work and the reliance of car as the primary mode of travel from Flintshire, would
appear to support the finding from the ‘West Cheshire – North East Wales Sub Regional Study’ that despite a net migration of population from Chester to Flintshire, the predominant commute is west to
east ove r the English border to the major employers in the area including Airbus, MBNA and Vauxhall and which are poorly served by public transport;
♦ the relatively high use of public transport in east Wirral and relatively short journey length suggest that
the principal locations for employment are nearby in Wirral itself and Liverpool, rather than towards job opportunities to the south including; Chester (including Chester Business Park), Ellesmere Port(including Vauxhall Motors), Deeside Industrial Park and Broughton Airbus. This would appear to
support the finding from the ‘Mersey Dee Alliance Transport and Accessibility Improvement Study’ that there is currently inadequate affordable public transport services to facilitate access to these jobopportunities from areas of social exclusion.
Existing Air Passenger Demand
Manchester Airport is the largest airport in the North West and by far the largest airport in the UK outside the
South East, with a throughput of 20 million passengers per annum (mppa). It currently serves around 170 destinations world-wide and has a substantial network of long-haul scheduled services.
Liverpool John Lennon Airport has seen rapid recent growth and is an important gateway to Merseyside and
the second airport for the North West. Passenger numbers have quadrupled in the last five years, mainly as a result of developing alternative markets to Manchester such as ‘no-frill’ services. In 2003, the Airport handled 3.2 mppa.
Existing Freight Demand
Within the study corridor the key routes are provided in a north-south direction by way of the M6 motorway and West Coast Main Line; along with east-west movements from Holyhead and Deeside via the M56 itself.A summary of the key generators and attractors are;
♦ port facilities available on Merseyside/Wirral at such locations at Seaforth, Garston and Ellesmere Port;
♦ Deeside Industrial Park, including Corus and Toyota;
♦ Vauxhall Motors plant at Ellesmere Port;
♦ Ford-Jaguar plant at Halewood;
♦ Shell UK oil refinery at Stanlow;
♦ chemical manufacturing facilities at Runcorn; and
♦ salt industry around Northwich.
Elsewhere in the study corridor, the distribution and hi-technology industries have become focused along the M56 corridor generating freight movements individually of low volume but when aggregated making up substantial road flows.
An analysis has been made of the UK freight model as held and maintained by MDS Transmodal. From this model all flows by either rail or road which would be forecast to utilise the M56 study corridor have been extracted, based upon tonnes lifted by mode.
As one would expect the predominant road freight movements in the M56 corridor are those with either an origin or destination within the North West region. Road freight to/from Wales is the next strongest movement followed by the West Midlands and Yorkshire. The largest individual movement of road freight
are trips within the North West itself i.e. North West intra-regional trips account for over 36% of annual tonnes lifted by road freight in the M56 corridor.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 8 of 150m56_scoping_study_final_report.doc
The strongest “M56” corridor movement for rail freight is to/from the North West which is followed by the
movement of rail freight to/from Wales. The strongest individual movement is that between North East England and Wales, almost certainly based upon steel products. Overall, rail holds a market share of tonnes lifted in the M56 corridor of 8%, a figure close to the UK average of 6%.
The Port of Manchester (Manchester Ship Canal) handled around 8 million tonnes of freight. In 2001, mainly liquid bulk to and from the petro-chemical industry at Stanlow, but also dry bulk to Ellesmere Port and Runcorn. Upstream of Runcorn approximately 1 million tonnes of freight per annum are carried formed of dry
and liquid bulk cargoes, with a recent new service established bringing containers to Irlam Wharf direct from Southampton and Clydeport.
In 2002 Manchester Airport handled almost 116,000 tonnes of air freight, whilst Liverpool handled some
27,500 tonnes (of which almost half was mail). Air freight is in the main carried in the hold of passenger aircraft (known as belly-hold freight) as well as on dedicated all-cargo aircraft. At Manchester Airport some 60 percent of air freight is belly-hold.
INITIAL BASELINE ASSESSMENT OF PROBLEMS AND ISSUES WITHIN THE M56 STUDY AREA
An initial baseline assessment has been carried out as part of this study to examine the current problems and issues within the M56 study area associated with regional highway, rail and freight services and networks.
Level of Stress on the Regional Highway Network
The Congestion Reference Flow is used in comparison with the AADT to derive the stress factor for a link, which is used as a proxy for journey time reliability. Values greater than 0.75 are generally held to give cause for concern (as reflected in the Appraisal Summary Table worksheet for Journey Time Reliability).
The stress factor for a link is defined as the ratio between the annual average daily traffic (AADT) and the congestion reference flow (CRF), with a value of 100% relating to an AADT equivalent to the CRF, with approximately 250 hours of congestion per year in the peak direction.
On the basis of this analysis the following sections of regional highway network are shown to be over-capacity;
♦ M56 between junctions 6 and 7;
♦ A556(T) between M56 junctions 7/8 and M6 junction 19;
♦ A533 Silver Jubilee Bridge; and
♦ A51 east of Chester
All of these locations that have been identified as sections of road suffering from congestion in the peak periods.
However, on the basis of this simple method of analysis the A5117(T)/A550(T) through Deeside Park would
“appear” to be operating successfully. Clearly, this is not the case with the level of stress being significantly underestimated because the CRF formula takes no account of the limiting capacity of the at-grade junctions.
Indeed the CRF formula also takes no account of the interaction between junctions for example, the impact
of weaving traffic between closely spaced junctions. Thus it is reasonable to conclude that the existing levels of stress for sections of the M53 between junctions 5 and 11, and M56 between junctions 3 and 6 have been underestimated using this approach.
Network Capacity Utilisation
The 2004 Network Rail Business Plan provides information on how busy the rail network is in terms of thenumber of available train paths compared to the demand for them. Where capacity exceeds 90% it is considered serious operational problems would result with high levels of unreliability.
The key problem identified is that of the main West Coast Main Line south of Weaver Junction and at keypinchpoints of the Manchester “hub” area. Both of these issues are being addressed by the SRA as part of their Manchester Hub and West Coast Main Line strategies, along with the Regional Planning Assessments
M56 CORRIDOR SCOPING STUDY
Final Report
Page 9 of 150m56_scoping_study_final_report.doc
and Route Utilisation Strategies. For the remaining routes in the study area minimal line capacity problems
were identified.
Train Capacity Utilisation
A methodology similar to that used in the London and South East area has been adopted based upon advice from the SRA, which is broadly based upon PIXC – Passengers in Excess of Capacity. An analysis has
been undertaken for a weekday morning peak period (07:00-10:00) with an additional 35% allowed for standing over and above seated capacity.
On the basis of this analysis none of the routes show any morning peak period capacity problems. However,
it should be bourn in mind that the demand profile is not uniform over the 3 hour morning peak period (07:00-10:00) and therefore it is reasonable to conclude that the %train capacity utilisation for the morning peak hour will be higher than for the average morning peak period.
Rail Freight Network Constraints
Separate to the issues associated with the passenger rail network are the constraints which exist restricting the ability of freight trains to access certain areas of the country, namely route availability and loading gauge.
Within the M56 study area most of the routes are rated at the highest permissive axle load of RA10, with the
exception of the line north of Hooton to Birkenhead and Liverpool which is rated at a lower RA8, and north of Shotton to Bidston which is rated at RA7. As such there are minimal constraints upon the weight of rail vehicle that can be accommodated in the study area.
The loading gauge presents greater problems in the study area. The main north-south West Coast Main Line has been fully cleared to take the increasingly dominant 9’6” maritime containers, and so have the links to the rail hubs at Trafford Park in Manchester, and Seaforth and Garston in Merseyside. Away from this
corridor the majority of the rail network is rated at W8 with a small section of W7 on the Mid Cheshire line which means that the high containers cannot be conveyed on these routes. Increasingly container traffic is adopting the height of 9’6” as standard, which will lead to increasing problems for rail in maintaining
competitiveness with road for inter-modal (container based) traffic.
INVENTORY OF PROBLEMS AND ISSUES AND POTENTIAL TRANSPORT MEASURES IDENTIFIED THROUGH
DOCUMENT REVIEW AND STAKEHOLDER CONSULTATION
This study documents the full range of problems and issues and potential transport measures (relevant to the M56 corridor study area) that have been identified through document review and from stakeholder consultation. In addition to a description of the identified problem and issues and potential transport
measure the following information has been collated where available;
♦ status of the scheme/measure, with committed schemes highlighted in red;
♦ an indication of the likely cost of the scheme/measure; and
♦ an indication of the potential timescale for implementation.
It must be stressed that a detailed examination of the regional significance of the problems identified has not been undertaken as part of this scoping exercise, and therefore their presence should not be misconstrued as an endorsement of their regional importance.
THE WAY FORWARD
Detailed Examination of Problems and Issues
The priority for the next stage in an M56 Corridor Multi-Modal study is to undertake a detailed examination of
the problems and issues that have been identified through document review and from stakeholderconsultation. This review should ascertain the regional importance of the problem, i.e. to establish whether the problem has genuine regional significance or whether the problem is clouded by perception. This will
require;
M56 CORRIDOR SCOPING STUDY
Final Report
Page 10 of 150m56_scoping_study_final_report.doc
♦ linking the regional transport problems to the wider environmental, economic regeneration anddevelopment objectives for the corridor as outlined in current RPG and the RES;
♦ the development of a full demand matrix across all modes of travel to a common zoning system,
including new data collection where appropriate, to provide a detailed breakdown on trip makingpatterns;
♦ a more detailed baseline assessment of the problems and issues, including an assessment of the
balance of short and longer distance movements at key study area bottlenecks and congestion points;and
♦ a need to undertake a high level accessibility mapping exercise to determine the relative ‘generalisedcosts’ of the alternative modes of transport for key origin-destinations.
Preparing a Shortlist of Potential Measures
Having established problems and issues of regional importance (as opposed to local) it will be necessary to prepare a shortlist of potential measures which are appropriate for further consideration and discard those
that do not fulfil a strategic role, by giving consideration to;
♦ the extent to which the potential transport measures contribute to the defined set of corridor objectives;
♦ whether the potential measures are both “realistic and practicable” – issues such as possible timescale for implementation and general acceptability where relevant; and
♦ whether the cost of implementing a particular potential measure is broadly commensurate with the likely benefits and provides value for money.
Scenario Testing - Modelling
In order to test the effects of the different scenarios the modelling approach taken will be dependent upon the level of detail required:
♦ for regional transport problems that require corridor-wide consideration we would suggest that a skeletal multi-modal network is developed.
♦ for regional transport problems that do not require corridor-wide consideration a more localisedmodelling approach may be acceptable, such as;
− smaller scale but more detailed strategic multi-modal model;
− micro-simulation models and/or spreadsheet based models to assess the impact of highwaychanges; or
− direct demand modelling techniques to assess the impact of new railway facilities.
Scenario Testing – Transport Supply
Once a shortlist of potential measures has been prepared and discussed in consultation with the Study
Advisory Group the process of scenario testing can be undertaken.
Do-Minimum Scenario
The first stage of this exercise will be to define the do-minimum scenario, against which packages of
measures can be tested. The do-minimum scenario will comprise committed schemes i.e. schemes where a decision to proceed has been taken (even though statutory procedures may still have to be completed) and for which funding will be made available, and would be implemented regardless of whether this study took
place or not. This scoping study has already identified many of those schemes; including;
♦ A494(T)/A550(T) Widening Ewloe Interchange to Welsh/English border;
♦ A550(T)/A5117(T) Deeside Park Junction Improvements;
♦ M56 improvements between junctions 5 and 6;
♦ major schemes (above £5m) in the full LTPs; such as South Liverpool Parkway; and
♦ rail franchise commitments including, diversion of the current Liverpool-Manchester Airport service via Chat Moss, and new semi-fast Birmingham-Liverpool/Preston rail service operated by Central Trains.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 11 of 150m56_scoping_study_final_report.doc
Agreement on schemes/interventions that comprise the do-minimum scenario would be defined in
consultation with the Study Advisory Group.
Do Minimum Reference Case
This will be a development of the do-minimum scenario and will include a package of shortlisted schemes for
which there is a high likelihood of them being developed whether or not this study took place. It is our recommendation that the do-minimum reference case should comprise measures for which there isconsensus amongst the Study Advisory Group for the inclusion in the long term strategy for the M56 corridor
and for which there is a very high likelihood of them proceeding.
Demand Management/Making Best Use of Existing Infrastructure Scenario
Once the do-minimum reference case has been established priority should be given to “demand
management” and “making best use of infrastructure options” for both the regional highway and rail network.
It is recognised that the Regional Highway Network has a finite capacity and that demand already exceeds capacity in certain key locations leading to congestion and problems of journey time reliability, and that if
demand is unconstrained conditions will continue to deteriorate to unacceptable levels. Also delays caused by the increasing volumes of traffic, incidents and road works lead to frustration for road users and increased costs for industry. With vehicle ownership rising steadily, demand is forecast to increase further. The study
would draw on the recommendations from the Route Management Strategies as the basis of any scenario testing.
For rail reference will be made to the outputs of the North West Regional Planning Assessment to identify
the key areas of rail growth for the future. This should provide an indication of where capacity problems can be expected to occur and provide recommendations on how rail demand should be managed. In addition ahierarchy of services will be assessed. Such a process is being undertaken as part of the SRA-led Route
Utilisation Strategy (RUS) process, which is ongoing for Greater Manchester and Trans-Pennine and due to report in spring 2005. The recommendations from this process will provide a valuable input as to whether some of the measures that have been identified in this scoping study require further consideration in the
context of the M56 transport corridor.
Further Transport Scenarios
Further transport scenarios could range from Public Transport scenarios to Highway Improvements. Indeed
there may also be a need for further testing of combined scenarios to ensure that an optimal balance of measures is obtained.
Scenario Testing – Travel Demand
Land-use planning has a fundamental impact on the operation of the M56 corridor transport system. On the
one hand, regeneration of the NWMA for housing and employment could have a beneficial effect on the transport network as the provision of high quality housing in and near to the city centres could reduce longer commuting distances. New development and redevelopment in the regional poles and surrounding areas
could also enable easier access by sustainable modes of transport. However, development pressures will also remain outside the city centres and in existing employment locations.
The transport network should play an integrated role in assisting existing and future regeneration initiatives
and in aiding inward investment and supporting indigenous economic growth. It should also assist inaccommodating the forecast passenger growth at Manchester and Liverpool Airports. Any travel demand forecasting along the corridor should take into account the emerging policies in the Regional Spatial Strategy
and the RES.
Scenario Appraisal
Scenario appraisal should be undertaken in accord with the transport analysis guidance provided on the Department for Transport (DfT) website WebTAG. The website originally brought together the Department's existing documents, The Guidance on the Methodology for Multi-Modal Studies (GOMMMS) and Applying
the Multi-Modal Approach to Appraisal to Highway Schemes and Major Scheme Appraisal in Local Transport Plans. The material on the DfT WebTAG site supersedes these documents.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 12 of 150m56_scoping_study_final_report.doc
Compliance with WebTAG guidance requires that the scenarios are assessed against the Governments
five key criteria for transport:
♦ environment– to protect the built and natural environment (including the European Directive onStrategic Environmental Assessment 2001/42/EC);
♦ safety – to improve safety;
♦ economy – to support sustainable economic activity and get good value for money;
♦ accessibility – to improve access to facilities for those without a car and to reduce severance;
♦ integration – to ensure that all decisions are taken in the context of the Government’s integrated transport policy and other local policies.
The core corridor objectives for the M56 Corridor will be used to frame the appraisal process throughout any future stages of the study. Therefore, for the final scenario appraisal it will be necessary to assess the package of measures against the Governments’ key criteria for transport, the wider Regional objectives and
against the core corridor objectives. Thus, the following Appraisal Summary Tables will be required;
♦ within the framework of the Governments key criteria for transport;
♦ within the framework of the wider Regional objectives; and
♦ within the framework of the core corridor objectives.
In addition to the assessment against the Government’s five key criteria, consideration will also need to be given to the performance of the scenarios against:
♦ distribution and equity;
♦ financial sustainability and affordability; and
♦ practicality and public acceptability.
Partnership Working with Delivery Agencies
In pursuing a programme of further study for the M56 Corridor we consider that partnership working with the
delivery agencies is fundamental in order to ensure that their specific needs are met and that account is made of other ongoing and future work.
In addition to liaison on committed schemes, account will need to be taken of other studies, including;
♦ M56 Route Management Strategy;
♦ A556(T) Route Management Strategy;
♦ Strategic assessment of the proposed new Runcorn to Widnes Mersey crossing;
♦ North West Regional Planning Assessment for rail;
♦ Route Utilisation Strategies for rail; and
♦ the emerging Northern Way Growth Strategy.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 13 of 150m56_scoping_study_final_report.doc
Glossary of Terms
AADT Annual Average Daily TrafficAADT_H Annual Average Daily Traffic (Heavy Goods Vehicles only)
AADT%H Annual Average Daily Traffic (Percentage of Heavy Goods Vehicles)AAWT Annual Average Weekday TrafficAfS Action for Sustainability, the Regional Sustainable Development Framework
AST Appraisal Summary TableCRF Congestion Reference FlowCS Carriageway Standard;
D4M dual 4 lane motorway;D3M dual 3 lane motorway;D2M dual 2 lane motorway;
D3T dual 3 lane trunk road;D2T dual 2 lane trunk road;S2T single 2 lane trunk road;
D2P dual 2 lane all-purpose road;S4P single 4 lane all-purpose road; andS2P single 2 lane all-purpose road.
DfT Department for TransportERDF European Regional Development Structural FundsEWS English Welsh & Scottish Railway
GDP Gross Domestic ProductGOMMMS Guidance on the Methodology for Multi-Modal StudiesGONW Government Office for the North West
GPS Global Positioning SystemHA Highways AgencyITIS Integrated Transport Information Services
LENNON Latest Earnings Networked Nationally Over NightLJLA Liverpool John Lennon AirportLSP Local Strategic Partnerships
LTP Local Transport PlanMIDAS Motorway Incident Detection and Automated SignallingMidMan West Midlands to North West Conurbations Multi Modal Study
MOIRA Latest in a long line of demand models developed by the former British Rail OperationalResearch
mppa million passengers per annum
NRTF National Road Traffic ForecastsNWDA Northwest Development AgencyNWMA North West Metropolitan Area
NWRA North West Regional AssemblyODPM Office for the Deputy Prime MinisterPIXC Passengers in Excess of Capacity
PK%H Percentage of Heavy Goods Vehicles in the Peak HourPPG11 Planning Policy Guidance 11: Regional PlanningRDAs Regional Development Agencies
RES Regional Economic Strategy for the North WestRPA Regional Planning Assessment (Rail)RPG Regional Planning Guidance for the North West (RPG13). Including;
Policy EC3 Economic Growth and Competitiveness with Social Progress Policy EC3 –Knowledge-based Industries
Policy EC4 Economic Growth and Competitiveness with Social Progress Policy EC4 –
Business ClustersPolicy SD1 Spatial Development Policy SD1 – The North West Metropolitan Area –
Regional Poles and Surrounding Areas
M56 CORRIDOR SCOPING STUDY
Final Report
Page 14 of 150m56_scoping_study_final_report.doc
Policy SD2 Spatial Development Policy SD2 – Other Settlements within the North
West Metropolitan AreaPolicy SD3 Spatial Development Policy SD3 – Key Towns and Cities Outside the
North West Metropolitan Area
Policy SD4 Maintaining Urban Form and Setting, and the Treatment of NorthCheshire
Policy SD5 Spatial Development Policy SD5 – The Green Belts
RTS Regional Transport StrategyRMS Route Management Strategy (Road)RSS Regional Spatial Strategy
RUS Route Utilisation Strategy (Rail)SAG Study Advisory GroupSATURN Simulation and Assignment of Traffic to Urban Road Networks
SEMMMS South East Manchester Multi Modal StudySI Seasonality IndexSIA Strategic Investment Area
SRA Strategic Rail AuthoritySTRESS(%) Ratio of Annual Average Daily Traffic to Congestion Reference FlowTEE Transport Economic Efficiency
TEN Trans European NetworkTF for Wales Transport Framework for WalesTPI Targeted Programme of Improvements
UDP Unitary Development PlanUK United KingdomWCML West Coast Main Line
WebTAG Department for Transport website for Transport Analysis Guidance
M56 CORRIDOR SCOPING STUDY
Final Report
Page 15 of 150m56_scoping_study_final_report.doc
1. Introduction
1.1 Atkins Transport Planning, in conjunction with Roger Tym and Partners, has been appointed by the North West Regional Assembly, in partnership with the Northwest Development Agency, to
undertake a scoping study for the M56 Corridor. Regional Planning Guidance for the North West (RPG13), published in March 2003 included a proposal for a potential multi-modal study covering the M56 Corridor, this study is the first stage in that process.
1.2 The M56 transport corridor broadly covers an area linking Manchester, Warrington and Chester to North Wales within the North West Region. The corridor is know to be an area of great economic potential, particularly in knowledge-based industries. The M56/A5117(T)/A550(T) is
the principal route through the corridor and with the M62 forms part of the main east-westtransport spine in the North West that links the two Regional Poles of Manchester andLiverpool.
1.3 The primary objective of this scoping study is to make recommendations for further work to develop a long term strategy to address regional (as opposed to local) transport problems and issues in the M56 Corridor, including the contribution that public transport and other modes
make. It is intended that this scoping study will serve as the starting point to inform further work which will investigate the specific problems and issues identified in greater detail.
1.4 This report presents a summary of the result of the consultation and data assembly undertaken
for the study, and thereby presents the problems and issues evident in the M56 corridor, across all modes of transport.
1.5 The remainder of this report is structured in the following manner:
♦ Section 2 describes the scope and objectives of the study;
♦ Section 3 outlines the land use and planning policy context;
♦ Section 4 describes the current supply and demand for travel in the study area;
♦ Section 5 presents an initial baseline assessment of the problems and issues using existing information;
♦ Section 6 documents the full range of problems and issues, and potential transport
measures (relevant to the M56 corridor study area), that have been identified through document review and from stakeholder consultations;
♦ Section 7 relates the identified problems and issues to the proposed corridor objectives; and
♦ Section 8 outlines the way forward and makes recommendations for further work.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 16 of 150m56_scoping_study_final_report.doc
2. Scope and Objectives of the Study
OVERALL AIMS OF THE STUDY
2.1 The overall aim of the M56 Corridor Scoping Study, as developed in the Study Brief is to:
♦ identify regional (as opposed to local) transport problems and issues in terms of movement
within and through the study area for all modes, and identify measures both infrastructure and policy which are either being taken or otherwise committed to tackle strategic transport problems and issues;
♦ identify the impact of regional transport problems and issues, policies and proposals on local transport networks;
♦ identify key problems and issues that must be addressed in order to facilitate sustainable development; and
♦ make recommendations and suggest priorities for further work to address the identified regional problems and issues, taking full account of safety, economic, environmental and
social considerations, the needs of all uses of the transport network and those affected by it, and any potential impacts on local networks.
M56 CORRIDOR OBJECTIVES
Introduction
2.2 Whilst the study brief sets out the overall aims for the scoping study there is a need to develop a set of objectives for the long term strategy of the M56 corridor, within the framework of the
Government’s five key criteria for transport;
♦ to protect and enhance the built and natural environment;
♦ to improve safety for all travellers;
♦ to contribute to an efficient economy, and to support sustainable economic growth in appropriate locations;
♦ to promote accessibility to everyday facilities for all, especially those without a car; and
♦ to promote the integration of all forms of transport and land use planning, leading to a better, more efficient transport system.
2.3 The long term strategy for the M56 corridor will also take account of objectives within;
♦ the Government’s white paper for Air Transport;
♦ the Highways Agency’s business plan 2003/04;
♦ the Strategic Rail Authority’s strategic plan for 2003;
♦ the Countryside Agency’s ten principles for transport;
♦ the Regional Planning Guidance for the North West (RPG 13) which includes the Regional Transport Strategy (RTS);
♦ the Regional Economic Strategy for the North West (RES);
♦ Action for Sustainability (AfS), the Regional Sustainable Development Framework;
♦ the Welsh Assembly’s Transport Framework, Spatial Plan and National EconomicStrategy;
♦ the structure and local transport plans for Cheshire;
M56 CORRIDOR SCOPING STUDY
Final Report
Page 17 of 150m56_scoping_study_final_report.doc
♦ the unitary development and local transport plans for Greater Manchester, Merseyside, Halton and Warrington;
♦ the local development plans for Cheshire County Council, Ellesmere Port and Neston
Borough Council, Macclesfield Borough Council, Vale Royal Borough Council, Flintshire County Council and Wrexham Borough Council;
♦ strategies from other studies affecting the M56 transport corridor;
♦ the objectives of transport providers in the study area; and
♦ the plans, aims and objectives of local business and industry in respect of futuredevelopments and their impact on the transport network.
2.4 Details of these objectives are contained in Appendix A.
The Need for Corridor Objectives
2.5 Corridor objectives help guide the identification of measures that address the problems and needs of the study area. The development of local objectives will help to provide an early
opportunity to seek general agreement on the direction of the study. This will enable a broad consensus to be reached as to the nature of the problems to be addressed by the study and to be used as the framework for appraisal, against which potential long term strategy options can
be assessed.
The Nature Of Corridor Objectives
2.6 The fundamental requirement of the corridor objectives is that they are designed to address problems rather than the symptoms arising from problems. A particular example is congestion.
This is a symptom arising from a range of different problems relating to the imbalance between transport supply and demand. The relevant objectives need to avoid simply seeking to reduce congestion but rather seek to address the root causes underlying the congestion.
2.7 As well as nesting within the Government’s five key criteria for transport, which form acornerstone of the study and are a ‘given’ starting point, to ensure that any proposed strategy is feasible and can actually be delivered the study objectives need also to relate to:
♦ distribution and equity;
♦ affordability and financial sustainability; and
♦ practicality and public acceptability.
2.8 The corridor objectives also need to be defined in a manner that permit measurement, so that it
is possible to determine the degree to which the study objectives are achieved.
M56 Corridor Strategy Objectives
2.9 Tabulated below are the M56 core corridor strategy objectives, and sub-objectives. Against each core objective and sub-objective the primary source(s) from which the objective was
derived has been referenced.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 18 of 150m56_scoping_study_final_report.doc
Table 2.1 – Proposed M56 Corridor Strategy Objectives
Proposed Corridor Strategy Objectives Primary Source(s)
Enable economic regeneration and development in a manner that
maximises achievement of sustainability objectivesRPG, RES, AfS
♦ Support the delivery of strategic regional sites and support the growth of
existing and target sector industries in the M56 transport corridor
RES, AfS
♦ Support the Manchester Regional Pole RES, RPG
♦ Support the growth of Manchester and Liverpool Airports RES, RPG, Air Transport White Paper
♦ Encourage the reduction in the need to travel AfS
♦ Enhance transport network efficiency and improve journey time reliability including public transport services
RTS, HA, SRA, TF for Wales, NW Freight Strategy,
♦ Encourage mode shift from car where feasible RTS, Countryside Agency, SRA
♦ Encourage a shift of freight from road to other modes where feasible NW Freight Strategy, SRA
Enhance accessibility and in particular to areas served by the
corridor suffering from social exclusion including Merseyside, east Manchester, Halton and Ellesmere Port and Neston
RPG, TF for Wales
♦ Improve access for non-car users RPG, Countryside Agency
♦ Increase transport choice in rural areas Countryside Agency
♦ Improve interchange between transport modes RPG, Countryside Agency
♦ Effective use of new technology to enhance accessibility RPG
Enhance the image of the M56 transport corridor and provide high
environmental and design qualityRPG, AfS
♦ Improvements to and enhanced management of Trans-European Networks RPG
♦ Improve perception of personal security for public transport journeys Countryside Agency
♦ Improve road safety RPG, HA, NW Freight Strategy
Management of natural, built and historic environment within the
M56 transport corridorRPG
♦ Minimise the impacts of transport upon the built and natural environment HA, Countryside Agency, AfS
♦ Minimise the impacts of transport upon emissions AfS
♦ Encourage the use of environmentally sustainable modes of transport RPG, Countryside Agency
EXTENT OF THE STUDY AREA
2.10 The study brief defined the M56 corridor study area to be the area bordered by the Cheshire
County Council/Wirral Metropolitan Borough Council boundary and the RiverMersey/Manchester Ship Canal to the north, the A5103(T) south from M60 to M56 to the east,
the M56 from junction 1 to junction 7 including Manchester Airport and the A556/A54/A51/A55 south of Northwich and Chester to the Welsh Border. The western limit of the study area wasdefined by the boundary between England and Wales.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 19 of 150m56_scoping_study_final_report.doc
2.11 It is our recommendation that the study area should be extended to logical transport decision
points. For this reason the study area has been extended into the Wirral to encompass M53 junctions 5 and 6, and into Wales to encompass the A55(T)/A494(T) Ewloe Interchange. Forthe purpose of this study it is considered that English/Welsh border that dissects the study area
is not relevant with respect to the operation of local economies, housing markets and travel areas.
2.12 The study area is shown in Figure 2.1 below including the district/county boundaries.
Figure 2.1 – M56 Corridor Study Area
REGIONAL HIGHWAY NETWORK WITHIN THE M56 STUDY AREA
2.13 The M56/A5117(T)/A550(T)/A494(T) is the principal route through the corridor and serves a
range of strategic functions as follows:
♦ it forms part of the Trans European Networks (TENs). The M56(west of
M6)/A5117(T)/A550(T)/A494(T) is part of the E22 from Ireland, through North Wales (via Holyhead), that uses the M6 to join the M62 trans-pennine route to Hull and onward to Europe via the North Sea and Baltic ports to Scandinavia, the Netherlands, Germany,
Poland and beyond (this corridor has become to be known as the North European Trade Axis).
♦ forms part of the main east-west transport spine in the North West linking North Wales and Cheshire with Greater Manchester and Yorkshire and Humberside.
♦ provides access to the Regional Pole of Manchester.
♦ the M56 forms part of the main road access to Manchester Airport, the North of England’s largest Airport and the third largest in the UK. Access to the Liverpool John Lennon Airport
(LJLA) can also be gained from M56 junction 12 and the Silver Jubilee Bridge. Both Manchester Airport and LJLA are part of the TENs.
♦ the M56 forms part of the strategic route for freight traffic destined for the Port of Liverpool,
which operates the UK’s largest Freeport zone, and port facilities at Garston and
M56 CORRIDOR SCOPING STUDY
Final Report
Page 20 of 150m56_scoping_study_final_report.doc
Birkenhead. It also provides access to the inland Port of Manchester (served by the Manchester Ship Canal).
2.14 The M56/A5117(T)/A550(T)/A494(T) intercepts a number of other Trans-European, nationaland regional routes;
Trans-European Routes
♦ M6/A74(T) to Scotland
♦ M53/A55(T) to Wales and Welsh Borders
♦ A483(T) Chester to Wales
National/Regional Routes
♦ M53 to Kingsway Tunnel Approach
♦ A41(T)/A550(T) linking M53 and A5117(T) at Shotwick
♦ A556(T) linking M6 and M56
♦ A5103(T) Princess Parkway
♦ A557/A533/A562/A561 linking M56 and Liverpool John Lennon Airport via Runcorn
2.15 To south of the M56 is the A51/A54/A556 a parallel route to the M56 that links Chester with Northwich and the M6 at junction 19 west of Knutsford, which is also considered to be a route of regional significance.
2.16 The extent of the Regional Highway Network within the M56 corridor study area has beenconsidered in the context of a functional road hierarchy, since land-use and transport policies need to be complementary and it is considered that a formally defined Functional Road
Hierarchy will assist in planning such an interaction. Indeed, this approach was followed in the Submitted Draft Revised RPG (March 2004), and it is our recommendation this approach is followed for the purpose of this study.
2.17 That said, the Secretary of State has recently agreed to the withdrawal of the submitted revisions to RPG 13 in respect of transport matters. Instead, transport matters and the Regional Transport Strategy will be fundamentally revisited in the context of the Full Review of
RPG 13, to turn it into a Regional Spatial Strategy. Comments made on transport measuresduring the recent consultation exercise will be fed into this process, and will be taken into account in the development of the RSS, which will itself be the subject of widespread formal
and informal consultation.
2.18 It is recognised, therefore, that undue emphasis should not at this stage be placed on the hierarchy of roads in the M56 study corridor, which has yet to be discussed through the RSS
process.
2.19 Figure 2.2 below shows the extent of the Regional Highway Network in the M56 corridor study area.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 21 of 150m56_scoping_study_final_report.doc
Figure 2.2 – M56 Study Area and Regional Highway Network
REGIONAL RAIL NETWORK WITHIN THE M56 STUDY AREA
2.20 The M56 Corridor is served by a number of railway lines each performing different roles. The West Coast Main Line runs south-north through the study area with a branch off towards Runcorn and Liverpool: stations are located at Warrington Bank Quay and Runcorn within the
study area giving access to Virgin West Coast services towards London and theborders/Scotland. This route is subject to major improvements as part of the West Coast Main Line upgrade with new tilting trains and line speed improvements.
2.21 Inter-regional links by rail are provided by the Arriva Trains Wales operated Manchester-Warrington-Chester-North Wales and Crewe-Chester-North Wales services, which provide for both long distance movements as well as meeting more local needs from stations such as
Helsby, Frodsham and Runcorn East. The Crewe-Chester-Holyhead line itself is part of the TENs and Interreg II route linking Great Britain and Ireland to mainland Europe, and has seen a recent line speed improvement supported by the introduction of new class 175 trains.
2.22 A local rail link is provided by First North Western between Chester and Manchester via Northwich and Altrincham with many intermediate (request only) calls; it is known that the low speed and low frequency has led to railheading to the Metrolink service from Altrincham. Local
rail services are provided by First North Western and Merseyrail, these giving links around the Manchester area and Merseyside-Chester respectively.
2.23 Rail freight services and links within the study area are dominated by the main north-south
West Coast main line passing through Warrington Bank Quay, with Warrington itselfrepresenting a major hub for English Welsh and Scottish railways in the north west.Immediately outside of the study area major rail freight hubs exist at Manchester Trafford Park,
Crewe and in the Merseyside area at Ditton, Seaforth, Gladstone and Alexandra Docks, and atGarston.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 22 of 150m56_scoping_study_final_report.doc
2.24 Within the east-west study corridor rail freight is limited in nature, with the North Wales Coast
line no longer carrying container traffic to Holyhead. As such the only regular rail freight traversing this corridor are nuclear fuel to Valley power station, railway ballast fromPenmaenmawr quarry, steel traffic to/from Dee Marsh/Shotton, chemicals from Runcorn, and
aggregates from Derbyshire to Northwich. Rail no longer carries any oil traffic from therefineries at Ellesmere Port, nor car components or finished vehicles to/from Vauxhall at Ellesmere Port.
2.25 Figure 2.3 show the extent of the key rail network for this study, including freight lines.
Figure 2.3 – M56 Study Area and Regional Rail Network
M56 CORRIDOR SCOPING STUDY
Final Report
Page 23 of 150m56_scoping_study_final_report.doc
3. Land Use and Planning Policy Context
3.1 In this section we highlight the key objectives of strategic policy guiding the scale, location and nature of development that is likely to have an impact on the travel patterns along the M56
corridor. In doing so we will consider both land use and economic policy in North East Walesas well as North West England, where it relates to the study area.
REGIONAL PLANNING GUIDANCE
3.2 The main purpose of the Regional Planning Guidance for the North West (RPG13) is to provide
a regional spatial strategy within which local authority development plans and local transport plans can be prepared.
3.3 RPG will be replaced by Regional Spatial Strategies (RSSs) which unlike regional planning
guidance will form part of the development plan for purposes of determining planningapplications.
3.4 The main principles of RPG set out in PPG11 apply to RSSs. In particular RPG and future
RSSs revisions should:
♦ set out a spatial strategy;
♦ be concise;
♦ avoid unnecessary repetition of national policy;
♦ address specific regional or sub-regional planning issues;
♦ set out the regional transport strategy (RTS);
♦ be consistent and supportive of other regional strategies and statements in delivering sustainable development; and
♦ be outcome-centred and focused on delivery mechanisms.
3.5 RPG contributes to the sustainable development targets set out in Action for Sustainability (AfS), the Regional Sustainable Development Framework and prepares the longer-term
planning framework for the North West Development Agency’s Regional Economic Strategy.
3.6 There is no absolute hierarchy between RPG, the RES and AfS as they deal with different but connected aspects of public policy within the Region. However, they need to be
complementary with one another if the are to be successful. The AfS, developed by the North West Regional Assembly (NWRA), is a broader vision than both the RPG and the RES and sets the context for economic and spatial strategy and targets for enhancing quality of life.
3.7 The spatial development framework establishes guidelines for the distribution of development and the resources to help achieve an urban renaissance. Sustainable development will be achieved through supporting business growth; integrating planning of homes, workplaces,
infrastructure and services in mixed use and compact neighbourhoods; reducing the need to travel by locating travel generators in city, town and district centres and where public transport interchanges are found. Economic use of land is a key requirement, with priority given to
reusing existing buildings or previously developed land. This also supports development in the city and town centres where most of these opportunities are found, and where development can help tackle social exclusion. However, diversification of the rural economies is also supported,
through appropriate development in the market towns. The framework also seeks to protect and enhance natural and cultural resources including landscape, agricultural land and built heritage.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 24 of 150m56_scoping_study_final_report.doc
North of the M56 – North West Metropolitan Area
3.8 The primary focus for new development is the North West Metropolitan Area (NWMA). This
describes the area between the two major regional capitals of Liverpool andManchester/Salford, to the north of the M56, which is highly urbanised with numerous towns many of which have merged over time. Manchester City Centre currently has the greater range
of regional functions and greater economic strength while the renaissance of Liverpool is a high priority.
3.9 Within the NWMA, priority is given to the two city centres and their surrounding inner-city areas.
The aim of policy SD1 is to cement recent progress in both city centres as attractive locations to live and do business and thus fulfil their potential as regional ‘Poles’ stimulating regeneration in the rest of the conurbation and driving forward overall regional prosperity. Regeneration is also
encouraged in the central/inner parts of; Birkenhead; St Helens; Southport; Ashton-under-Lyne;Bolton; Bury; Oldham; Rochdale; Stockport; and Wigan.
3.10 As outlined in policy SD2 wide-ranging regeneration and environmental enhancement should
be secured elsewhere within the NWMA, and most especially in the older parts of themetropolitan settlements of; Runcorn; Widnes; Ellesmere Port; and Skelmersdale.
3.11 The focus in development within the NWMA will create a need for improved public transport
networks between and within all the specific area and towns listed in Policies SD1 and SD2, particularly rail services, and the introduction of management and other measures to ease the flow on the motorways.
3.12 Various regeneration initiatives are under way in the less prosperous parts of the North West Metropolitan Area;
♦ the whole of Merseyside holds European Regional Development Structural Funds (ERDF) Objective 1 status
♦ ERDF Objective 2 status in Greater Manchester, Halton and Ellesmere Port and Neston.
♦ north-western part of Vale Royal has transitional area status for the period 2000 to 2005.
♦ Regional Priority Area status of the North West Metropolitan Area
♦ Urban Regeneration Companies – New East Manchester, and Liverpool Vision, with
guaranteed significant NWDA funding for areas of intensive need, requiring focussed attention with opportunities for large scale redevelopment.
♦ Local Strategic Partnerships (LSPs) (Neighbourhood Renewal Funding) – Ellesmere Port
and Neston, Halton, Liverpool and Manchester. The NWDA will assist LSPs by supporting economic initiatives, set in the context of integrated and comprehensive community based regeneration plans.
♦ To note: there are areas of Flintshire within the ‘M56 Corridor Study Area’ which are Assisted Areas.
3.13 As set out in RPG there is a need (Policy SD5) to carry out a strategic study of Green Belt in Merseyside and Halton to determine the need, if any, for changes in the broad extent and location of Green Belt boundaries as a result of the long term development issues arising from
the current regeneration programmes, including Objectives 1 and 2. This study is now underway and is being led by NWRA although its outcome will not be available during the course of this M56 scoping study.
South of the M56 – North Cheshire
3.14 Policy SD3 focuses on the key towns and cities outside the NWMA, and relevant to this study
development will be concentrated in a number of major towns and cities, including Chester,
M56 CORRIDOR SCOPING STUDY
Final Report
Page 25 of 150m56_scoping_study_final_report.doc
Crewe, Macclesfield and Northwich, In the case of Chester and Crewe there should be regard
to their role as gateway and/or interchanges for visitors to the Region from adjoiningareas/regions and countries, and the need to provide high quality modern facilities to support these roles.
3.15 Policy SD4 is concerned with the maintaining urban form and setting, and the treatment of North Cheshire and acknowledges that;
“There is still considerable development pressures on areas at the outer edge of the North West
Metropolitan Area, especially in areas with good motorway access and close proximity to the airports. In recent years growth industries have sought locations for development in or near the Green Belt in the North Cheshire area, on the edge of established settlements, on formerly
developed brownfield sites, and sometime on green field sites.”
3.16 The role of knowledge-based industries and development of business clusters is covered in Policies EC3 and EC4 respectively;
“Knowledge-based industries will be supported, in accordance with the Core DevelopmentPrinciples, particularly the sequential approach set out in Policy DP1, and the SpatialDevelopment Framework. Development plans and other strategies should facilitate the
development of sites with direct access to research establishments, including universities, Higher Education Institutes and major hospitals. Priority locations will be in the mainconurbations, close to centres of research, or within science parks. Sites should be well located
in relation to transport infrastructure, especially public transport, and should be capable of providing high environmental quality. Access to education, skills and training should berecognised as key aspects of securing the development of this sector.”
“Development plans and other strategies including regeneration strategies should consider thepotential to promote the clustering of existing and new economic activities with the potential for sustainable growth. They should meet both the Region’s sectoral priorities and local needs by
making appropriate provision for premises, including business and science parks, in line with the sequential approach set out in Policy DP1 and the Spatial Development Framework.
Clusters designed to support knowledge-based industries should:
♦ make provision for networks based on information communication technologies; and
♦ as a preference be located near to Higher Education Institutes, major hospitals, research establishments or major technology-based businesses.”
3.17 With Policy SD4 adding;
“Allocations will need to be retained if they will enable significant growth in the national and the regional economy in respect of high technology and research enterprises, and if they allow for
the meeting of purely local needs.”
ACTION FOR SUSTAINABILITY
3.18 The North West’s original Regional Sustainable Development Framework and Action Plan entitled ‘Action for Sustainability’ was issued by the NWRA in July 2000. building on work instigated by the Government Office for the North West (GONW). It influenced both the RPG
and RES mainly because it informed the sustainability appraisal of both.
3.19 Further work in progressing sustainability within the region has led to the development of the Regional Sustainable Development Framework which establishes a high level regional vision
that provides a basis for all activities across the region and an updated action plan called Action
M56 CORRIDOR SCOPING STUDY
Final Report
Page 26 of 150m56_scoping_study_final_report.doc
for Sustainability (AfS) 2004-2006 which sets targets for a wide range of bodies in the region to
ensure a more sustainable future in the North West and globally.
REGIONAL ECONOMIC STRATEGY (MARCH 2003)
3.20 The Northwest Development Agency (NWDA) has been charged with pursuing the sustainable economic regeneration of the North West to make the Region more competitive and encourage
the sectors with the most potential for growth, industries that are able to compete not only nationally but with other parts of the world. The NWDA’s strategy is outlined in the Regional Economic Strategy (RES).
3.21 The RES is framed around ten strategic objectives which lie within five interlinked priorities:
♦ Business Development
♦ Regeneration
♦ Skills & Employment
♦ Infrastructure
♦ Image
3.22 The links between economic growth and regeneration are close. Improvements to overall regional prosperity will follow if individuals seeking work are able to access appropriate jobs and companies are able to access a suitably skilled workforce.
3.23 Investment in the region’s transport and communications infrastructure is required to enable businesses to function within the region, the UK and overseas. Business growth is currently inhibited by weaknesses in infrastructure, including delays caused by traffic congestion and the
absence of broadband in some areas. The availability of a range of employment sites is also identified as a requirement to support further economic growth.
3.24 Investment in first-class transport infrastructure is required to enable business and people to
access locations in the region, the UK and internationally, by road, sea and air. Accessbetween the major urban centres via the motorway network is causing concern as the routes involved include some of the most heavily used in the country, and their strategic role is being
adversely affected. The contribution of the strategic ports and airports to regional growth and regeneration and therefore the need for good access is highlighted.
Growth Potential of Business Sectors
3.25 The RES identifies a group of business sectors that are important either because of their
current growth or future growth potential:
Aerospace Digital Industries Maritime
Automotive Energy Sport
Aviation Environmental Technology Textiles
Chemicals Financial & Professional Services Tourism
Construction Food & Drink
Creative Industries Healthcare (incl. Biotechnology)
3.26 The NWDA suggest that the competitiveness in the North West would be improved by developing these sectors using a ‘cluster’ approach. Although the approach will vary across the
sectors highlighted actions include network development, skills development, supply chain management as well as provision of sites, incubators and innovation centres.
3.27 A ten year action plan is being developed for each sector to identify opportunities, barriers to
growth and a route map to coordinate the actions of the NWDA and other partners.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 27 of 150m56_scoping_study_final_report.doc
Knowledge-Based Industries
3.28 Developing the knowledge-based economy is considered to be central to Government policy of
competitiveness: “the creation and translation of knowledge into competitive products is vital to economic prosperity”. To this end the RES identifies the following key activities:
♦ encourage the development and implementation of the Northwest Science Strategy to
secure major science opportunities and facilities for the region to exploit, including the
creation of new business opportunities. The strategy is focused initially upon business clusters in five of the priority sectors in the RES, namely, Biotechnology, Aerospace, Chemicals, Environmental technologies, and Nuclear Energy.
♦ increase the capacity of Northwest universities to develop targeted national and
international centres of excellence in science, Research and Development and social sciences.
♦ Secure substantially increased investment in public and private Research andDevelopment through lobbying and targeted support to key businesses.
♦ Encourage the development of emerging technologies with potential for exploitation by business, and for other uses beneficial to the region.
♦ Encourage the strategic development of science parks to support the increased growth of knowledge intensive businesses.
3.29 In 2000 the NWDA commissioned the Mersey Belt Study which aimed to ensure that the NorthWest region as a whole had a realistic strategy for stimulating both indigenous and inward
investment in knowledge-based industries focusing on the Target Sectors. A summary of this study is provided in Appendix B.
Strategic Regional Sites
3.30 In order to support economic growth it is vital that the north west region has a balanced portfolio
of employment site in terms of quality and sustainable development. The NWDA has
designated 25 sites (shown in Figure 3.1) as critical to the effective implementation of the
RES, which are intended to;
♦ encourage knowledge based industry to develop within and close to areas of regeneration need
♦ build on the region’s existing “knowledge” assets, including universities and cluster of knowledge-based industries
♦ develop strategic distribution facilities, particularly rail and seaport related.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 28 of 150m56_scoping_study_final_report.doc
Figure 3.1 – NWDA designated Strategic regional sites
NWDA designatedStrategic regional sites
1 Ashton Moss, Tameside
2 Basford, Crewe
3 Cuerden Regional Business Park, Preston/Leyland
4 Daresbury Park, Runcorn
5 Kingmoor, Carlisle
6 Kings Business Park, Knowsley
7 Kingsway Business Park, Rochdale
8 Omega South, Warrington
9 Royal Ordnance Factory, Chorley
10 The Estuary, Liverpool (Speke Garston)
11 Wirral International Business Park
12 Barton, Salford
13 Birkenhead/Twelve Quays
14 Whitebirk
15 Carrington, Trafford
16 Chester Business Park
17 Davenport Green, Trafford
18 Ditton, Widnes
19 Lancaster University/ Bailrigg
20 Liverpool University Edge
21 Central Park, Manchester
22 Parkside Former Colliery
23 Wavertree Technology Park, Liverpool
24 Westlakes, Whitehaven
25 Alderley Park (Astra Zeneca), Macclesfield
M56 CORRIDOR SCOPING STUDY
Final Report
Page 29 of 150m56_scoping_study_final_report.doc
3.31 It is considered that the following sites designated by NWDA as strategic regional sites are of
particular relevance to the study area at;
Wirral Business Park (included in the current RPG13)
3.32 Wirral International Business Park is located on the west bank of the Mersey Estuary
approximately 6.5 km south of Birkenhead. Liverpool city centre and Liverpool John Lennon airport are 11 km and 22 km away respectively. From the south, the site is accessed via junction 5 on the M53, and from Liverpool and the north it is accessed vi a the Mersey Tunnel
(Queensway) and the A41. The site covers an area of 334 hectares of which approximately 70 hectares remain undeveloped. Only 31 hectares are currently suitable for immediatedevelopment. It is a largely a brownfield site with previous uses including two power stations,
oil storage and chemical works.
The Estuary, Speke/Garston (included in the current RPG13)
3.33 Esutary Business Park is on the site of the former Speke Airport. It is located on the north bank of the Mersey some 10 km south east of Liverpool city centre between Garston and Speke.
The site forms a key component of the Speke Halewood Strategic Investment Area, one of eight priority investment areas established by the 2000-2006 ERDF Objective 1 programme being taken forward by the Liverpool Land Development Company. From Liverpool access is
via the A561 Speke Road. Motorway access is from the M62/M57 interchange away and the A5300/A561. Liverpool John Lennon airport is immediately to the east whilst Lime Street station is approximately 10 km away. Planning permission was granted in 2003 for a major
transport interchange at Liverpool South Parkway (under construction) located 1.5 km from the business park. This will include enhanced bus and rail services to improve access to the Speke/Garston area including a direct shuttle bus to Liverpool John Lennon Airport.
Omega South, Warrington (included in the current RPG13)
3.34 Omega South (formerly known as Omega 600) is located approx. 5km north west of Warringtontown centre, bounded to the north by the M62, Burtonwood Road to the east and Lingley Green
Avenue to the south. The strategic regional site extends to 206 hectares of whichapproximately 130 hectares are intended for employment development within the target sectors. The remainder of the site, covering some 70 hectares, is allocated for non-strategic,
local employment needs in the draft Warrington UDP.
Daresbury Park (included in the current RPG13)
3.35 The Daresbury Park strategic regional site comprises the existing Business Park and land
adjacent to the Daresbury Laboratory complex. Daresbury Park is located immediately adjacent to junction 11 on the M56. The laboratory is located off the A56 Chester Road close to its junction with the A558 Daresbury Expressway. Both are greenfield sites.
Chester Business Park (not included in the current RPG13)
3.36 Business Park located 2.4 km south Chester close to the junction of the A55(T) and A483(T).Currently employs around 4,400 people and occupiers include M&S Financial Services, MBNA
Bank, Bristol Myers Squibb, Halifax Bank of Scotland and Scottish Power. The NWDA designated strategic regional site comprises the existing 9.8 hectare business park and 5 hectares of expansion land to the south adjoining the A55(T).
Ditton Strategic Rail Freight Park, Widnes (not included in the current RPG13 )
3.37 The site comprises 190 hectares of land on the western side of Widnes between Hale Bank and
the A562 Speke Road at Ditton. The site’s core (76 hectares) lies to the south of the Liverpool
M56 CORRIDOR SCOPING STUDY
Final Report
Page 30 of 150m56_scoping_study_final_report.doc
branch of the West Coast Main Line. The site is served by the freight-only line to Arpley,
Warrington which serves Fiddlers Ferry power station. Ditton is identified for a strategic rail freight park under Policy TPNEW3 of the Revised Draft Halton UDP. A public sector led consortium is developing proposals for the strategic rail freight park which will build on the
potential of two existing rail-freight businesses (Widnes Intermodal Rail Depot and Widnes Intermodal Freight Terminal).
Davenport Green (not included in the current RPG13)
3.38 The site extends to 136 hectares and is located to the east of Hale, close to junction 6 on the M56. The site is well located adjacent to Manchester Airport and the proposed Metrolink. The site is allocated as a major high amenity site for B1 uses (i.e. high quality science based/high
tech, R&D or headquarters) under proposal E13 of the existing Trafford UDP, which was adopted in 1996. Conditions attached to the planning consent require highway improvements before development is permitted.
SUSTAINABLE COMMUNITIES
3.39 The Deputy Prime Minister launched the Communities Plan (Sustainable Communities: Building for the future) on 5 February 2003. The Plan sets out a long-term programme of action for delivering sustainable communities in both urban and rural areas. It aims to tackle housing
supply issues in the South East, low demand in other parts of the country, and the quality of our public spaces.
3.40 The Plan includes not just a significant increase in resources and major reforms of housing and
planning, but a new approach to how we build and what we build.
3.41 A £22 billion programme of action aims to focus the attention and co-ordinate the efforts of all levels of Government and stakeholders in bringing about development that meets the
economic, social and environmental needs of future generations as well as succeeding now.
Making it happen: The Northern Way
3.42 A progress report by the Deputy Prime Minister on the Communities Plan with particular emphasis on the North and Midlands on 2 February 2004.
“The three northern regions have a home market of some 15 million people. They are also well placed to benefit from the expanding markets in Northern and Eastern Europe, and in Ireland. There are great opportunities to exploit transport links in the North - both those that already exist and the improvements that we intend to take forward. These include the upgrade of the
West Coast Main Line, widening the M6 from Birmingham to Manchester and majorimprovements to the M60, M62, M1 and A1(M). These and other improvements will help to ensure that the M6 and West Coast Main Line, the M1 corridor, the A1(M) and East Coast Main
Line, and the M62 and rail link across the Pennines, provide a framework for growth that can match the growth corridors of the Thames Gateway and the wider South East. The regional airports are growing too, especially Manchester, the largest airport outside London.
Seven of the nine new housing market renewal pathfinders and five of the provincial Core Cities span the existing transport corridors that link the northern conurbations. The corridor also takes
in three RDAs, 14 New Deal for Communities Areas and eight URCs.
To support that step change in development, we need a long-term vision that can fully exploit the economic and transport corridors that connect the North - a "Northern Way" which looks east to west as well as north to south. A new northern growth strategy which promotes greater inter-regional collaboration and boosts connectivity and transport links so that the sum of
activity and investment is greater than the parts.”
M56 CORRIDOR SCOPING STUDY
Final Report
Page 31 of 150m56_scoping_study_final_report.doc
3.43 The Northern Way report 'Moving Forward: the Northern Way Growth Strategy Report', will be
launched by John Prescott in September 2004. The report will look at ways to narrow the £29 billion gap between the North and the rest of the UK. It will also explore how the three Northern regions can work together to help the North to reach the national average of GDP per head by
2030. The report will consider a number of issues including skills, clusters and connectivitywithin and between city regions. Any long term strategy for the M56 corridor will therefore have take account of this long-term vision for the “Northern Way”.
PLANNING POLICY WALES (MARCH 2002)
3.44 This provides the context for developing a sustainable land use planning policy by local authorities in Wales. Key objectives include:
♦ promoting settlement patterns that minimise land take and urban sprawl, preferably re-
using suitable previously developed land or buildings and avoiding where possible
Greenfield development;
♦ locating development to minimise demand for travel, especially by private car;
♦ contributing to the protection of the environment, to improve quality of life and protect
ecosystems;
♦ ensuring the provision of sufficient quality housing in urban and rural communities;
♦ promoting access to employment, shopping, education and other social, welfare andleisure facilities;
♦ fostering improvements to transport facilities which maintain or improve accessibility to
services and facilities, and achieve employment, economic and environmental objectives;
♦ supporting social inclusion by improving access to development, including means other
than private car;
♦ promoting lasting, flexible employment opportunities and encouraging diversity in the local
economy.
PEOPLE, PLACES, FUTURES – THE WALES SPATIAL PLAN (CONSULTATION DRAFT 2003)
3.45 This plan is broader in coverage than land use planning alone in that it sets a strategic framework to guide future development and policy interventions, whether they are subject to
planning controls or not. It sets out the aspirations for sustainable development in different parts of Wales.
3.46 The Plan highlights that most transport movements in Wales take place along the northern and
southern coastal belts. The Deeside area is identified as having a particular problem (alongside Cardiff/Newport) with peak time congestion. The connections with England are recognised as forming important parts of the transport infrastructure in eastern Wales.
3.47 The importance of inter-regional commuting in Flintshire is recognised, with outflows of some 19,000 to England and inflows of around 8,000. Similar patterns are present for journeys for shopping and access to other services, including healthcare. Migration flows are also
significant with two thirds of migration into Flintshire originating from England.
3.48 North East Wales is characterised by its relatively large urbanised and industrial areas, diverse economic base, presence of national centres providing higher order services, the incidence of
development pressures on accessible rural areas as well as the congestion. It is recognised as a dynamic area, which demonstrated some of the highest population growth in Wales during the 1990s. Part of the success of the area is attributed to the good accessibility within the area and
with adjoining areas.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 32 of 150m56_scoping_study_final_report.doc
3.49 Key principles for development in the area include:
♦ Protecting accessible rural areas and managing urban expansion;
♦ Maximising use of brownfield development opportunities;
♦ Increasing the economic potential of links with adjoining English regions;
♦ Enhancing R&D, innovation, the knowledge economy and HE/FE as motors for economic
development;
♦ Making better use of infrastructure capacity with selective improvements to external
accessibility;
3.50 The Welsh Assembly’s commitment to improving transport infrastructure in the area (including
capacity improvements on the A494/A550 at Queensferry) is restated in the Plan. It also identifies a series of future challenges for the area, including a need to improve prosperity in the disadvantaged areas, and to consider the role of Wrexham as a potential regional centre. The
plan also identifies a need for the potential for further employment and housing to beinvestigated, while ‘green belts’ may be required to protect open spaces under pressure from development.
A WINNING WALES – THE NATIONAL ECONOMIC DEVELOPMENT STRATEGY (REVIEW 2004)
3.51 This is a 10 year strategy which seeks to develop in Wales a dynamic, inclusive and
sustainable economy, built on a platform of successful innovative businesses with high skilled employees. It contains many action points relating to the following aims:
♦ encouraging innovation
♦ encouraging entrepreneurship
♦ making Wales a learning country
♦ promoting information and communication technologies
♦ supporting business
♦ setting a fresh direction
♦ establishing Wales in the world
♦ improving Transport
♦ creating strong communities
♦ supporting rural Wales
3.52 Transport priorities include investment in the strategic transport corridors to improveaccessibility internally and with the rest of the UK; working with the UK Government to increase
freight transported by rail and a variety of measures to improve public transport provision and accessibility. The strategy also identifies a need to ensure that an adequate supply of quality industrial sites, premises and other infrastructure is in place. As well as supporting indigenous
business growth, the strategy also seeks to establish Wales in the international marketplace, exporting goods and services and attracting new business from outside the country.
NORTH WALES DEVELOPMENT STRATEGY (DRAFT FINAL FEBRUARY 2004)
3.53 This strategy seeks to unlock the economic potential of North Wales to bring about sustainable
prosperity for the region and its people. The goals are for North Wales to be:
♦ a technologically advanced and innovative region;
♦ a region with well connected and inclusive communities in both rural and urban areas;
♦ a region with an adaptable and appropriately skilled workforce;
M56 CORRIDOR SCOPING STUDY
Final Report
Page 33 of 150m56_scoping_study_final_report.doc
♦ a region where business and individuals capitalise on the distinct environment to deliver competitive advantage;
♦ a region where history, culture and strength of identity reinforce a unique quality of life;
♦ a region where all stakeholders and agencies work effectively together across a commonagenda to deliver shared priorities.
3.54 The Strategy acknowledges that economic performance has to be improved, especially with respect to competitiveness and productivity, which in turn reflect aspects such as lower skills
levels than the average across Great Britain. Economic performance is however far from uniform across North Wales, with the area bordering England (Flintshire and Wrexham), and which therefore has the closest relationship to the M56 corridor, acting as a driver within the
north Wales economy. Here, there are high levels of Gross Value Added, low unemployment, relatively high employment in technology and knowledge intensive industries and opportunities for high earning manufacturing jobs. The inter-linkages with North West England (especially in
terms of commuter flows) are acknowledged.
3.55 The Strategy proposes a number of actions which fall within 5 themes:
♦ Business and Enterprise
♦ Skills and Learning
♦ Community Cohesion
♦ Communications and Infrastructure
♦ The North Wales ‘offer’
3.56 In terms of the ‘Communications and Infrastructure’ theme, the objectives of the strategy are to
improve digital connectivity; maximise the impact of competitive locations by improving the land and property offer; and improving transport links and access to markets.
3.57 Locations along the A55 corridor are considered to be amongst the most competitive and thus
will be targets for business parks, strategic employment and mixed use site development. While these will be found along the length of the A55, the specific locations selected will reflect demand and the priorities set out in the Spatial Plan for Wales and thus are likely to include
provision close to the A55-M56 feeder routes.
3.58 The strategic linkages via the A55 to the wider North West and the area’s proximity toManchester, Liverpool and Birmingham airports are identified as strengths to be built upon, with
the potential for Manchester Airport in particular to be positioned as a business asset for North Wales, facilitating links with international partners.
3.59 Actions within the ‘North Wales offer’ theme relate to developing North Wales as a place to visit
(for both business and leisure), a place to live, a place to work and a place to do business. Components of the offer include the environment, visitor infrastructure, retail provision, education facilities, business support etc. The area’s relationships with neighbouring regions
(principally North West England to the east and the Greater Dublin area to the west) are considered to underpin North Wales’ ability to take advantage of its ‘offer’. The provision of a road and rail infrastructure which facilitates movement into and within the region (particularly by
public transport) is highlighted as a measure required to improve the quality of life for current and potential residents. Improvements to the transport gateways are identified to improve the visitor experience. The need to improve accessibility to employment opportunities for some
communities is also highlighted.
KEY POINTS
3.60 RPG for the North West identifies the centres of Liverpool and Manchester within the NWMA as the focus for future population and employment growth in the region, to support continued
M56 CORRIDOR SCOPING STUDY
Final Report
Page 34 of 150m56_scoping_study_final_report.doc
urban renaissance and support their regional role. Growth will also take place in a number of
sub-regional locations, including Stockport, Runcorn, Widnes, Ellesmere Port and Chester within this study area. The strategy seeks to maximise the use of previously developed land, which is in the main found within the urban locations identified above, to accommodate the
growth. It also seeks to reduce the need to travel by focussing major travel generators in urban centres and around public transport interchanges. The M56 has a strategic role in serving the NWMA.
3.61 The RES seeks to encourage knowledge based sectors in the region. It identifies a number of sectors to be supported through a cluster based approach, including the provision of premises and incubators appropriate to their needs. Strategic Regional Sites have also been identified
which will ensure that provision of sites suitable for the knowledge based sectors are available at a variety of locations, including areas accessible to deprived communities and which can capitalise on the existing presence of knowledge based activities. Eight of these are relevant to
this study area.
3.62 The cross-border relationship between North East Wales and North West England area for economic and social functions is recognised as a strength, although the associated travel
patterns and peak time congestion are a cause for concern.
3.63 Future development of the North Wales economy is likely to continue to capitalise on the strategic links via the A55 with its neighbouring region and beyond using the motorway network.
Accessibility to assets such as the airports at Liverpool and Manchester will be increasingly promoted and thus the M56 will continue to be a key factor in terms of the economicperformance of the area.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 35 of 150m56_scoping_study_final_report.doc
4. Existing Travel Supply and Demand
INTRODUCTION
4.1 An important precursor to undertaking a multi-modal assessment of a transport corridor is that of understanding the current pattern of movements on the transport network. Analysis has
been undertaken of both demand and supply, drawing upon the following data sources:
Travel Supply
♦ Highway: existing regional highway network.
♦ Rail: network information contained in the Network Rail North West Zone Sectional Appendix, along with public timetables. Supported by station site audits.
♦ Road passenger: public service timetables.
♦ Freight: rail freight ‘timetables’.
Travel Demand
♦ Highway: recent annual average daily traffic (AADT) flows from WSP Monitoring Reports
(on behalf of the Highways Agency), Cheshire LTP, Halton BC, and Welsh Assembly Government. Origin-destination data from SEMMMS, A556 RMS, New Mersey Crossing Study and Queensferry Transportation Study.
♦ Rail: LENNON rail ticketing data and MOIRA rail demand model.
♦ Journey to work census data.
♦ Road passenger: ticketing data supplied by National Express coaches.
♦ Freight: output data from the MDS Transmodal Great Britain Freight Model.
SUPPLY OF TRANSPORT SERVICES
Road Provision4.2 A description of the Regional Highway Network in the M56 corridor study area has been made
against a highway network divided in to discrete sections as shown below in Figure 4.1.
Figure 4.1 – Key Road Sections
M56 CORRIDOR SCOPING STUDY
Final Report
Page 36 of 150m56_scoping_study_final_report.doc
Section 1 - A494(T)/A550(T) between A55 and Welsh/English Border
4.3 The A494(T) is a dual two lane trunk road between the A55(T) and A550(T) with grade-
separated junctions at;
♦ A55(T) Ewloe Interchange;
♦ B5125 at Ewloe;
♦ Plough Lane junction;
♦ B5129/A550 at Queensferry;
4.4 The A550(T) which is currently being improved;
♦ A548 at Drome Corner providing access to Chester and Deeside Industrial Park; and
♦ A548 at Deeside Park Interchanges provides access to the Deeside Industrial Park including Connahs Quay, Flint and industrial estates along the Dee estuary.
4.5 In addition there is a main access provided to RAF Sealand and there is a junction with Old Ashton Hill on the eastbound carriageway and Clay Lane on the westbound carriageway.
There are also a number of minor accesses to properties and businesses.
4.6 West of the Ewloe interchange the A55 continues as a dual two lane trunk road along the North Wales coast to Bangor and to the Port of Holyhead on Anglesey.
Section 2 - A550(T)/A5117(T) between Welsh/English Border and M56
4.7 The A550(T) is a dual two lane trunk road between the Welsh/English border and the at-gradeA550/A5117 Woodbank traffic signals. The A550/A41 is a single carriageway providing a link to the M53 at junction 5 for traffic between the Wirral and North Wales.
4.8 The A5117(T) continues as a dual two lane trunk road with at-grade junctions at;
♦ A5117/A540 roundabout providing access to west Wirral, including Neston to the north of the A5117(T) and Chester to the south; and
♦ A5117/M56 roundabout near Backford Cross.
4.9 In addition there are over 30 minor accesses (for properties, minor side roads and fieldaccesses) on the A5117(T) between the A550 and M56.
Section 3 - M56 between A5117 and M6 at Lymm near Warrington
4.10 The M56 is a dual two lane motorway between its western terminus at junction 16 (M56/A5117
roundabout) and the M56/M53 Stoak Interchange (M56 junction 15/M53 junction 11), north of Chester. The M56/M53 Stoak Interchange is not an all movement junction and does not cater for trips between Merseyside and North Wales which are provided for by the A550/A41.
4.11 The M56 is a dual three lane motorway between the M56 Stoak Interchange and M56/M6 Lymm Interchange (M56 junction 9/M6 junction 20) which crosses the River Weaver and passes to the south of Runcorn and Warrington.
4.12 M56 junction 14 provides access to the Shell UK oil refinery at Stanlow to the north of M56 and Helsby to the south. Access is also provided for Chester motorway services, the only services on the M56.
4.13 There is no M56 junction 13. M56 junction 12 provides access to Runcorn and Merseyside (viathe Silver Jubilee Crossing of the River Mersey) to the north of the M56, and to Frodsham and Northwich to the south.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 37 of 150m56_scoping_study_final_report.doc
4.14 M56 junction 11 provides access to Warrington and to the East Runcorn Area to the north of the
M56. In the East Runcorn area are Daresbury Park, Daresbury Laboratory and Manor Park (Daresbury Park is a designated strategic regional site in RPG13). To the south of the M56 junction 11 provides access to Whitehouse Industrial Estate.
4.15 M56 junction 10 provides access to Warrington to the north of M56 and Northwich to the south.
Section 4 - M56/A5103(T) between M56/M6 Lymm Interchange near Warrington and M60 Manchester Outer Ring Road
4.16 The M56/M6 Lymm Interchange near Warrington is not an all movement junction, with no direct access between the M6(south) and M56(east), these movements being provided for by the
A556(T).
4.17 The M56 is a dual three lane motorway between M56 Lymm Interchange and M56 junction 6.M56 junctions 8 and 7 provide access via A56 to Hale, Altrincham and Sale to the north of M56,
and via A556(T) to Knutsford and M6, including destinations to Birmingham and beyond to the south.
4.18 M56 junction 6 provides access to Hale to the west of M56 and Wilmslow to the east. Access
to the Davenport Green (designated by NWDA as a strategic regional site) is also gained from M56 junction 6.
4.19 The M56 is a dual four lane motorway between M56 junctions 6 and 3. A spur is provided into
Manchester Airport from M56 junction 5 as well as providing access to Manchester Business Park.
4.20 M56 junction 4 provides access to Wythenshawe, while at M56 junction 3 the M56 turns
towards Stockport and east Manchester as a dual two lane motorway joining the M60 at junction 4 with the A5103(T) Princess Parkway continuing on towards Manchester City Centre.
4.21 The A5103(T) is a dual three lane trunk road between M56 junction 3 and M60 junction with a
grade separated junction at Northenden.
Section 5 – M53 between M53/A41 and M53/M56 Stoak Interchange
4.22 The M53 is a dual three lane motorway to the north of the M53/A41 at junction 5, and provides a link to the Mersey Tunnels at Wallasey and Birkenhead and access to the NWDA designated strategic regional site, Wirral International Business Park. The Kingsway Tunnel (Wallasey) is
an important Mersey crossing for heavy goods vehicles (hgvs), as hgvs over 3.5 tonnes are prohibited from using the Queensway Tunnel (Birkenhead).
4.23 The M53 is a dual two lane motorway between the M53/A41 at junction 5 and the M53/M56
Stoak Interchange at junction 11 passing through Ellesmere Port.
4.24 M53 junction 5 provides access to east Wirral to north of M53, and via A41/A550 provides a single two lane carriageway link bet ween the Wirral and North Wales, the traffic movement not
catered for at the M53/M56 Stoak Interchange.
4.25 M53 junctions 6 and 7 provide access to Overpool as well as the Oil Storage Depot at Eastham and the Vauxhall motor works. M53 junction 8 also provides access to Overpool as well as the
Oil Storage Depot at Overpool, industrial estate and paper works.
4.26 M53 junction 9 provides access to Ellesmere Port Boat Museum and surrounding area and the Shell UK oil refinery at Stanlow.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 38 of 150m56_scoping_study_final_report.doc
4.27 M53 junction 10 provides access to Cheshire Oaks Designer Outlet Village, the Blue Planet
Aquarium and surrounding areas to the west of M53 and an alternative access to the Shell UK oil refinery at Stanlow to the east.
Section 6 – M53/A55(T) between M53/M56 Stoak Interchange and A55(T)/A494(T)Ewloe Interchange
4.28 The M53/A55(T) route runs to the east and south of Chester, linking the M56 at junction 15
Stoak Interchange with the A494(T) at Ewloe in Flintshire, thereby providing an alternative to the M56/A5117(T)/A550(T)/A49A(T) through Queensferry for traffic movements between the M56 and North Wales.
4.29 The M53 is a dual two lane motorway between M53 junction 11 at Stoak and its southern terminus at junction 12 with a grade separated junction and access to Chester via the A56.
4.30 The A55(T) is a dual two lane trunk road with grade separated junctions at;
♦ A51 at Littleton to the east of Chester;
♦ A41 at Christleton to the south east of Chester;
♦ A483(T) at Chester Business Park (designated by NWDA as a strategic regional site) and park-and-ride site to the south of Chester;
♦ A5104 at Broughton near the Airbus factory to the south west of Chester; and
♦ A550 to the south of Hawarden.
Section 7 – A557/A533/A562/A561 North of M56 junction 12
4.31 North of the M56 the A557/A533/A562/A561 route connects the M56 at Junction 12 south of Runcorn with the A5300 ‘Knowsley Expressway’, Liverpool John Lennon Airport and theAssociated British Ports facility at Garston Docks, and includes a major crossing of the River
Mersey at Runcorn Gap. As such, it provides a strategic link from Cheshire and North Wales to Merseyside and the Port of Liverpool as well as providing access from the M56 to the threeNWDA designated strategic regional sites at Ditton (Widnes), The Estuary (Speke/Garston) and
Omega South (Warrington). The expressways provide a largely grade-separated network for the distribution of traffic into Runcorn and Widnes.
4.32 The Silver Jubilee Bridge, opened in 1961, together with its associated approach viaducts,
carries the route over the River Mersey and the Manchester Ship Canal at Runcorn Gap between Runcorn and Widnes. Originally constructed as a three lane single carriageway it was widened to four lanes of substandard width in 1977, with poor facilities for pedestrians and no
safe facilities for cyclists.
Section 8 – A556(T) between M6 junction 19 and M56 junction 7
4.33 East of the M6, the A556(T) links the M6 and M56 motorways to the west of Tatton Park in Cheshire and provides for traffic movements which cannot not be made at the M6/M56 Lymm Interchange.
4.34 The A556(T) is principally a single four lane trunk road with local widening to dual two lanecarriageway standard in the vicinity of M56 junctions 7 and 8 and M6 junction 19.
4.35 Along the A556 route, numerous field entrances and property frontages at Mere have direct
access onto the trunk road. Apart from the motorway junctions, there are two significant other junctions that connect the local roads to the A556(T). These are the Bucklow Hill junction that links with the A5034, and the Mere junction that connects the A50 between Knutsford and
Warrington, both are at-grade signal controlled junctions with restricted turning movements.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 39 of 150m56_scoping_study_final_report.doc
Section 9 – A51/A54/A556 between A55 and M6 junction 19
4.36 The A51/A54/A556 route links Chester with Northwich and the M6 at junction 19 west of
Knutsford and was formerly part of the National Trunk Road Network. It effectively parallels the M56, which lies some 10km further north, and provides access to and from Northwich.
4.37 The A54 leaves the A51 at Tarvin, 4,5km east of the A55(T), and is part single, part dual two
lane all-purpose road which bypasses Tarvin and Kelsall. To the east of Kelsall the route continues as the A556, which is also part single, part dual two lane all-purpose road, the dual carriageway having been constructed as a southern bypass of Northwich. With one exception,
all major junctions are either at-grade roundabouts or signal controlled junctions. The A556 continues as four lane single carriageway between the eastern end of the Northwich Bypass and the M6.
Standard of Highway Provision
4.38 The standard of highway provision is presented below in Figure 4.2, where
♦ D4M dual 4 lane motorway;
♦ D3M dual 3 lane motorway;
♦ D2M dual 2 lane motorway;
♦ D3T dual 3 lane trunk road;
♦ D2T dual 2 lane trunk road;
♦ S2T single 2 lane trunk road;
♦ D2P dual 2 lane all-purpose road;
♦ S4P single 4 lane all-purpose road; and
♦ S2P single 2 lane all-purpose road.
Figure 4.2 – Standard of Highway Provision for the Regional Highway Network in the Study Area
M56 CORRIDOR SCOPING STUDY
Final Report
Page 40 of 150m56_scoping_study_final_report.doc
Existing Rail Service Provision
4.39 The current passenger rail services in the study area are listed in Table 4.1 below. This shows
the current service provision as contained in the summer 2004 timetable, with speeds based on the average Monday-Friday timetable:
Table 4.1 – Existing Rail Service Provision in the Study Area
Route in Study Area Service Pattern Operator Frequency AverageSpeed*
Chester-Northwich-Manchester(“Mid Cheshire Line”)
Dedicated to route First North Western 30 mins peak
Hourly off-peak
32mph
Chester-Warrington-Earlestown-
Manchester (“North Cheshire Line”)
Holyhead/Llandudno-ManchesterPiccadilly
Arriva Trains Wales 30 mins peak
Hourly off-peak
39mph
Chester-Wrexham Chester-Wrexham-Shrewsbury/Birmingham
Arriva Trains Wales Hourly to every 2 hours 36mph
Chester-Crewe London/Crewe-Chester-LlandudnoJcn-Holyhead
Arriva Trains Wales Every 30 mins 70mph
Heswall-Shotton Wrexham-Shotton-Bidston Arriva Trains Wales Hourly 29mph
Chester-Hooton Chester-Hooton-Birkenhead-Liverpool Merseyrail Every 30 mins 24mph
Ellesmere Port-Hooton Ellesmere Port-Hooton-Birkenhead-Liverpool
Merseyrail Every 30 mins 20mph
Helsby-Ellesmere Port Hooton-Helsby-Warrington Bank Quay First North Western 4 trains per day each way 24mph
Frodsham-Runcorn Chester-Runcorn First North Western 1 train per week one-way n/a
Crewe-Runcorn-Liverpool (West Coast Main Line)
Birmingham-Crewe-Liverpool (calls Runcorn only)
Central Trains Hourly 47mph
Crewe-Liverpool (calls Winsford, Hartford, Runcorn)
Central Trains Every 2 hours 41mph
London Euston-Runcorn-Liverpool Virgin Trains Hourly 50mph
Notes: * = average speed for stretch of route within study area
4.40 It may be noted that certain routes have very low levels of train service, notably the Frodsham-Runcorn line (“Halton curve”) and between Helsby and Ellesmere Port. Both of these routes carry only a minimum level of service to avoid formal closure proposals, known as a
parliamentary service or “ghost train”.
4.41 Also to be noted are the relatively low average train speeds on many routes, with exception of the services running along the West Coast Main Line or the Crewe-Chester line. This is due to
the current condition of track and the frequent station stops involved.
4.42 Forthcoming proposals for rail network service changes include that of a new Central Train’s operated Birmingham-Crewe-Liverpool and Birmingham-Crewe-Warrington-Preston, these
services operating with high quality electric trains and stopping at key intermediate points including Hartford in the study area.
Current Status of Rail Network
4.43 The majority of stations in the study area are unmanned, with the exception of the main stations at:
♦ Chester
♦ Crewe
♦ Warrington (Bank Quay and Central)
M56 CORRIDOR SCOPING STUDY
Final Report
Page 41 of 150m56_scoping_study_final_report.doc
♦ Hartford
♦ Runcorn East
♦ Runcorn (main line)
♦ Northwich
♦ Knutsford
♦ Altrincham
♦ Ellesmere Port
♦ Hooton
4.44 Details of the current status of rail stations within the study area are contained in Appendix C,
covering issues such as provision of facilities, information and current condition. This shows that the condition of the majority of the stations is acceptable, but that those at Northwich, Lostock Gralam and Frodsham show particular need for upgrading.
4.45 The existing rail routes in the study area show different forms of operation and speed limits, as shown below.
Table 4.2 – Existing Rail Routes in the Study Area
Route Double/Single track Line Speeds Limits Form of Signalling
Chester-Northwich-Manchester
Mostly double excluding Stockport to Altrincham
(part) and Mouldsworth to Mickle Trafford
Max 60mph, sections at 40 & 20mph
Mainly mechanical. Signal boxes at: Chester, Mickle Trafford, Mouldsworth, Breenbank, Plumley,
Mobberley, Hale, Deansgate Jcn, Northenden Jcn
Chester-Warrington-Earlestown-Manchester
Double throughout Max 75mph, sections at 40 & 30mph
Mixture of electronic/mechanical. Signal Boxes at: Chester, Mickle Trafford, Helsby, Frodsham Jcn, Norton, Warrignton BQ
Chester-Wrexham Single throughout 60mph max, sections at
50mph
Mixture of electronic/mechanical. Signal Boxes at:
Chester, Wrexham
Chester-Crewe Double throughout Max 90mph, sections at 65/70/75mph
Mixture of electronic/mechanical. Signal Boxes at: Chester, Beeston Castle, Crewe Steel Works
Bidston-Shotton-Wrexham Double throughout Max 50mph, long sections at 40mph
Mixture of electronic/mechanical. Signal Boxes at: Sandhills, Dee Marsh Jcn, Wrexham.
Chester-Hooton Double throughout 60mph max Electronic from Chester
Ellesmere Port-Hooton Double throughout 60mph max Mechanical from Hooton, Ellesmere Port
Helsby-Ellesmere Port Double throughout 60mph max, sections of 50 & 20mph
Mechanical from Ellesmere Port, Stanlow, Helsby
Frodsham-Runcorn Single throughout 20mph Mechanical from Frodsham Jcn and Halton Jcn.
Crewe-Runcorn-Liverpool(West Coast Main Line)
Double throughout 110mph max on WCML, dropping to 90/80mph max on Liverpool branch
Mixture of electronic/mechanical. Signal Boxes at: Crewe, Winsford, Halton Jcn, Runcorn, Ditton, Speke Jcn, Allerton, Edge Hill
4.46 As Table 4.2 above shows, many of the study area routes suffer from low speed limits, in some cases caused by either poor condition of track or the instability of the ground conditions (from
salt workings in the Northwich area).
Road Based Public Transport Passenger Services
4.47 As a result of consultation with National Express coaches, as well as an analysis of coach timetables, it has been possible to form a view of the current road coach service using the M56
corridor. Table 4.3 shows the current service pattern based upon the summer 2004 timetable.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 42 of 150m56_scoping_study_final_report.doc
Table 4.3 – Existing Coach Services Relevant to the Study Area
Service No. Service M56 Area Calling Points Services per Weekday inEach Direction
325 Manchester-Birmingham Manchester, Manchester Airport 5 per day
328 Rochdale-Plymouth Manchester, Manchester Airport 1 per day
333 Blackpool-Bournmouth Manchester, Manchester Airport 1 per day
336 Penzance-Edinburgh Manchester Airport, Manchester 1 per day
341 Burnley-Paignton Manchester, Manchester Airport 1 per day
350 Liverpool-Clacton/Cambridge/Mansfield Liverpool, Manchester Airport, Manchester 3 per day
380 Manchester Airport-Newcastle Manchester Airport, Manchester 3 per day
381 Bradford-Manchester Airport Manchester, Manchester Airport 2 per day
383 Wrexham-NewcastleWrexham, Chester, Warrington, Manchester Airport, Manchester
1 per day
538Birmingham/Manchester Airport-
Glasgow/EdinburghManchester, Manchester Airport 2 per day
540 Rochdale/Manchester-London Manchester, Stockport, Manchester Airport 5 per day
550 Liverpool/Birkenhead-London Victoria Warrington, Stoke 5 per day
4.48 It is worth noting that the public timetables show an additional 15 minutes being allowed on weekdays for journeys which use the M56 past Manchester Airport.
4.49 Anecdotal evidence obtained shows that National Express have retrenched in recent years from serving Manchester Airport, in part due to the poor reliability of traffic conditions upon the M56.
Freight Supply
Existing Rail Freight Workings
4.50 Most of the rail routes within the study area carry railfreight on a regular basis. Tabulated below are the key railheads within the study area and the nature of goods handled.
Table 4.4 – Key Railheads within the M56 Corridor Study Area
Railhead Location Nature of Goods Handled Current Status
Dee Marsh Shotton Steel (Corus), Paper (Shotton paper) Active
Ince Marshes Ince near Helsby Fertilizer Disused
Stanlow Stanlow Oil products (Shell) Disused
Folly Lane Runcorn Chemical products Active (not currently used)
Oakleigh Northwich Limestone Active
Lostock Northwich Limestone Active
Middlewich Middlewich Salt Disused
Sandbach Sandbach Chemicals Active
Fiddlers Ferry Fiddlers Ferry Power station coal Active
Northenden Manchester Aggregates (Lafarge), domestic waste Active
Railnet Royal Mail Warrington Royal Mail terminal Currently disused
Dallam Warrington Russells (general goods) Currently disus ed
Ellesmere Port Ellesmere Port Former oil terminal/Manchester Ship Canal Currently disused
Eastham Eastham Currently disused
M56 CORRIDOR SCOPING STUDY
Final Report
Page 43 of 150m56_scoping_study_final_report.doc
4.51 Current rail freight services running on a regular basis along routes serving the M56 corridor are
summarised below.
Table 4.5 – Existing Rail Freight Services Relevant to the M56 Corridor Study Area
Operator Service Nature of goods conveyed Frequency of operation
EWS Warrington-Chirk Timber Daily + as required
EWS Warrington-Runcorn Chemicals 2 days a week
EWS Warrington-Dee marsh (Shotton) General traffic/paper Daily
EWS Warrington-Ditton General traffic Daily
EWS Margam/Llanwern-Dee Marsh (Shotton) Steel traffic 2 per day
Direct Rail Services Crewe-Valley Nuclear flasks As required
Freightliner Penmaenmawr-Crewe Ballast As required
EWS Tunstead-Oakleigh (Northwich) Lime stone Daily
EWS Liverpool Bulk Terminal-Fiddlers Ferry Power station coal Up to 6 trains per weekday
Existing water based freight operations and facilities
4.52 The Manchester Ship Canal has seen a recent stabilisation of carryings, with an increase in usage of the route upstream of Runcorn. The key freight carryings have until recently been that
of chemicals to Runcorn, as well as accessing Ellesmere Port, but significant fl ows now exist upstream including:
♦ grain for Cerestar at Trafford Park;
♦ wheat to Manchester Dry docks; and
♦ containers to Irlam Wharf using a new Southampton-Irlam-Clydeport service.
DEMAND FOR TRAVEL
Existing Highway Demand
Annual Average Daily Traffic Flows/Season
4.53 Annual average daily traffic (AADT) flows on the key road network have in the main been taken from Highways Agency’s report “Traffic Monitoring – North, 2002 Data Analysis Report”prepared by WSP Civils Limited. For sections where no data was available and sections of all-
purpose road this dataset has been supplemented with AADT flows taken from various other sources;
♦ Cheshire Local Transport Plan – 1999 AADT
♦ Halton Borough Council – 2000 AADT
♦ New Mersey Crossing Study – 2001 AADT
♦ A556 Route Management Strategy – 2003 AADT
♦ Welsh Assembly Government – 2003 AADT
4.54 In order to produce a consistent set of base flows all counts were factored to 2002 using National Road Traffic Forecasts (NRTF) observed growth factors.
4.55 The most important indicator of annual traffic patterns (profile of average daily flow over the
course the year) is the seasonality index (SI) which is defined as the ratio of the average August weekday to the average weekday (Monday to Friday) in the neutral months, April, May, June, September and October (excluding periods affected by Bank Holidays).
M56 CORRIDOR SCOPING STUDY
Final Report
Page 44 of 150m56_scoping_study_final_report.doc
4.56 Tabulated below are a summary of AADT, Annual Average Weekday Traffic (AAWT),
percentage of heavy good vehicles (AADT%H), number of daily goods vehicles (AADT_H), and seasonality index. For ease of reference the regional highway network has been divided intothe discrete sections shown in Figure 4.1.
Table 4.6 – Existing Traffic Flows (2002)
2002 Traffic LevelsSection Road Location
C’wayStandard AADT AAWT AADT%H AADT_H SI
1 A55(T) West of Ewloe D2T 52000 53600 11.1 5800 1.15
1 A494(T) A55(T)-A550(T) D2T 59000 60800 9.4 5500 1.12
1 A550(T) A494(T)-A548 D2T 51300 52900 8.4 4300
2 A550(T) A548-A5117(T) D2T 51300 54500 11.0 5600
2 A5117(T) A550(T)-M56 Jnc 16 D2T 37800 39600 13.8 5200 1.12
3 M56 Jnc 15-16 D2M 31600 34000 13.3 4200
3 M56 Jnc 14-15 D3M 91500 99100 13.0 11900 1.06
3 M56 Jnc 12-14 D3M 96800 105300 13.0 12600
3 M56 Jnc 11-12 D3M 84000 91200 13.0 10900
3 M56 Jnc 10-11 D3M 89000 97500 14.0 12500
3 M56 Jnc 9-10 D3M 88500 95200 14.0 12400
4 M56 Jnc 8-9 D3M 69600 75700 7.0 4900
4 M56 Jnc 7-8 D3M 58300 62700 11.0 6400
4 M56 Jnc 6-7 D3M 110200 118500 12.2 13400
4 M56 Jnc 5-6 D4M 121200 132200 12.2 14800 1.00
4 M56 Jnc 5 Airport Spur D3M 60000 61700 6.3 3800 1.04
4 M56 Jnc 4-5 D4M 129100 139400 10.9 14100 1.00
4 M56 Jnc 3-4 D4M 143300 155100 7.0 10000
4 A5103(T) M56 Jnc 3-M60 Jnc 5 D3T 103800 113200 4.0 4200 0.97
4 M56 Jnc 2-3 D2M 60700 65400 14.1 8600
4 M56 Jnc 1-2 D3M 86400 92900 14.1 12200
5 M53 Jnc 4-5 D3M 50500 55500 11.3 5700 0.98
5 A41/A550 M53 Jnc 5 – A5117(T) S2T 21400 22100 8.7 1900
5 M53 Jnc 6-7 D2M 52200 58000 11.7 6100
5 M53 Jnc 7-8 D2M 60000 64500 11.7 7000
5 M53 Jnc 9-10 D2M 53200 59300 15.4 8200 0.98
5 M53 Jnc 10-11 D2M 57400 63100 11.0 6300 0.99
6 M53 Jnc 11-12 D2M 65800 70800 10.0 6600
6 A55(T) M53 Jnc 12-A51 D2T 30900 34100 12.1 3700
6 A55(T) A5-A41 D2T 47700 51500 12.0 5700 0.94
6 A55(T) A41–A483(T) D2T 56900 58700 12.1 6900 1.04
6 A55(T) A483(T) - A550 D2T 24900 25700 10.1 2500
6 A55(T) A550-A494(T) D2T 38300 39500 9.7 3700
7 A533 Silver Jubilee Bridge S4P 77000 87000 16.0 12300
8 A556(T) M56 Jnc 7/8 – M6 Jnc 19 S4T 48200 49700 12.1 5800
9 A556 M6 Jnc 19 – A559 S4P 26300 27100 7.5 2000
9 A556 A559-A49 D2P 29800 32400 8.7 2600
9 A556 A49-A54 S2P 16900 17400 7.5 1300
9 A54 A556-A51 D2P/S2P 15800 16300 7.5 1200
9 A51 A54-A55(T) S2P 29500 30400 7.5 2200
M56 CORRIDOR SCOPING STUDY
Final Report
Page 45 of 150m56_scoping_study_final_report.doc
4.57 Figure 4.3 below provides a further graphical representation of existing traffic levels.
Figure 4.3 – Existing Traffic Flows (2002 AADT)
4.58 The main findings of this analysis are that;
♦ the busiest section of the M56 is between junctions 4 and 3 (the A5103(T) Princess
Parkway) with traffic flows in excess of 140,000 AADT, with approximately 60,000 AADT
using the M56 junction 5 spur of which the vast majority use the spur to access Manchester Airport.
♦ East of the A556(T) traffic flows on the M56 are still high at approximately 110,000 AADT,
with heavy goods vehicles accounting for 13,400 AADT_H. Traffic flows on the M56 reduce significantly to 70,000 AADT between the A556(T) and M6. This reflects the strategic significance of the A556(T) which links the M6 at junction 19 and the M56 at junctions 7 and 8 and carries just under 50,000 AADT.
♦ the M56 (west of M6 between junction 9 and 15 ) carries approximately 90,000 AADT with
heavy goods vehicles accounting for over 12,000 AADT_H. West of M53 traffic flows on the M56 reduce significantly to just over 30,000 AADT, with the majority of trips using the M53 south to Chester or north to Ellesmere Port and the Wirral. Further west on the
A550(T) through Queensferry traffic flows rise sharply to over 50,000 AADT reflecting a strong movement between North Wales and Ellesmere Port/Liverpool.
♦ the M53 (north of M56) carries typically between 50,000 and 60,000 AADT with heavy goods vehicles accounting for between 6,000 and 7,000 AADT_H.
♦ the M53 (south of the M56) carries just over 65,000 AADT, with heavy goods vehicles
comprising 6,600 AADT_H. Traffic flows on the A55(T) south of the M53 fall by more than half to 30,900 AADT reflecting the high proportion of trips which leave the M53 and use the
A56 into Chester. The eastern section of A55(T) Chester ring road between A51 and A483(T) has increased traffic flows with between 48,000 and 57,000 AADT. Traffic flows on the A55(T) between the A483(T) and A494(T) are substantially less with between
25,000 and 38,000 AADT. This reflects the finding that a significant proportion of traffic at the A55(T)/A483(T) junction south of Chester is between the A483(T) and A55(T) East.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 46 of 150m56_scoping_study_final_report.doc
♦ north of the M56 the A557/A533/A562/A561 route connects the M56 at junction 12 south of
Runcorn with the A5300 ‘Knowsley Expressway’. The Silver Jubilee Bridge carries over 75,000 AADT with heavy goods vehicles accounting for almost 12,500 AADT_H.
4.59 Table 4.6 shows that A55/A494/A550/A5117/M56 to the west of M6 has a relative high seasonality index which is consistent with its dual function as the main tourist route into North
Wales and use by commuting traffic. Tourism in North Wales is a major employer, currently 3.8 million visitors per annum to the area access vi a the M56. To the east of the M6 the M56 has a lower SI indicating that commuting traffic is the predominant influence on annual traffic patterns,
even with the presence of Manchester Airport which as one would expect has a SI above unity.
Key Highway Movements in the Study Area
4.60 An indication of the key highway movements in the study area has been gained by analyses of origin-destination data from the following sources;
♦ South East Manchester Multi Modal Study;
♦ A556 Route Management Study;
♦ New Mersey Crossing Study; and
♦ Queensferry Transportation Study.
4.61 These data sources enabled desire line diagrams to be produced for the following sections of regional highway network;
♦ M56 between junctions 6 and 7 SEMMMS
♦ M6 between junctions 21 and 21a SEMMMS
♦ M6 between junctions 16 and 17 A556 RMS
♦ Silver Jubilee Bridge New Mersey Crossing Study
♦ A550(T) Queensferry Queensferry Transportation Study
4.62 A summary of the key highway movements within the study area are shown in Appendix D and
reproduced below in tabular form.
Table 4.7 – Key Highway Movements in the Study Area
DESTINATION
M5
6 E
ast
/Mancheste
r
Mancheste
r
Airport
A56/S
outh
Mancheste
r
M6 S
outh
Nort
hw
ich/M
id-
Ch
esh
ire
M6 N
ort
h
Warr
ingto
n
M6
2 E
ast
M6
2 W
est
Runcorn
Wid
nes/S
Liv
erp
ool
Cheste
r
Wirra
l/E
llesm
ere
Port
L’p
ool/M
ers
ey
Tunnels
M56 W
est/N
ort
h
Wale
s
M56 J6-7
Westbound12% 25% 4% 9% 16% 7% 6% 1% 6% 12%
M6 J21-20
Southbound14% 11% 8% 25% 4% 1% 2% 1% 4% 10%
M6 J16-17Northbound
21% 4% 2% 12% 24% 7% 9% 9% 4%
SilverJubileeBridge
Southbound
4% 6% 12% 2% 4% 14 49% 7% 8% 8%
OR
IGIN
A550(T)QueensferryEastbound
14% 7% 3% 4% 4% 5% 3% 5% 7% 38% 9%
M56 CORRIDOR SCOPING STUDY
Final Report
Page 47 of 150m56_scoping_study_final_report.doc
4.63 The main findings of this analysis are;
♦ the predominant movement on the M56 between junctions 6 and 7 is to/from M6 south
(25%), trips that also use the A556(T). Longer distance M56 trips to M56 West/North Wales constitute 12% of the total.;
♦ the predominant movements on the M6 between junctions 21 and 20 (Thelwall) are to/from M6 south (25%), Manchester (14%) and Manchester Airport (11%);
♦ the predominant movements on the M6 between junctions 16 and 17 are to/from M6 North (24%), Manchester (21%) and Northwich/Mid-Cheshire (12%).
♦ Silver Jubilee Bridge – although only 20% of trips across the bridge are local (between Widnes and Runcorn) less than 50% of trips use the M56; and
♦ the predominant movement on the A550(T) through Queensferry are to/from Ellesmere
Port/Wirral (38%) and onwards to Liverpool through the Mersey Tunnels (9%). Longer distance M56 trips to M56 East/Manchester constitute 14% of the total.
Existing Rail Passenger Demand
4.64 An analysis has been undertaken of the LENNON rail ticketing data for the 2002-2004 financial year, along with that of the MOIRA train flow information.
4.65 Figure 4.9 shows the average number of daily passenger boardings at stations in the M56 study
corridor.
Figure 4.4 – Daily Rail Passenger Boardings
4.66 A summary of the key rail demand movements within the study area are shown Appendix E and reproduced below in tabular form.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 48 of 150m56_scoping_study_final_report.doc
Table 4.8 – Summary of Key Rail Demand Movements in the Study Area
Line Location WC
ML S
outh
Cre
we-
Cheste
r
Wre
xham
N W
ale
s C
oast
Wirra
l
Runcorn
Bridge
WC
ML N
ort
h
Chat M
oss E
Mid
-Cheshire
No
rth
-Cheshire
Cheste
r
Cheste
r-H
ooto
n
Elle
sm
ere
Port
Warr
ingto
n
Runcorn
Mid-Cheshire Hale-Ashley 1% 2% 68% 29%
WCML Crewe-Winsford 7% 41% 41% 6% 6%
Crewe-Chester-North
WalesCrewe-Chester
2% 48% 1% 49%
Shrewsbury -
Wrexham-Chester
Wrexham-
Chester 2% 15% 13% 2% 8% 59% 1% 1%
North Wales Coast Chester-Shotton 42% 1% 9% 3% 17% 1% 24% 2% 1%
Liverpool-Chester Eastham-Hooton 2% 2% 9% 49% 25% 13%
WCML (Liverpool
Spur)Ditton-Runcorn
94% 5%
WCML Wigan-WBQ 99% 1%
Chat Moss Line (W) WBQ-Chat M(W) 14% 13% 3% 18% 48% 3%
Chat Moss Line (E) WBQ-Chat M(E) 1% 34% 9% 43% 8% 5%
4.67 The main findings from this analysis are that;
♦ the Manchester-Altrincham-Northwich-Chester line is very self contained with few trips
starting or ending beyond the route;
♦ the West Coast Main Line carries through trips generally not starting or ending in the study
area;
♦ the North Wales Coast Line carries longer distance through trips, primarily towards the
South East and Midlands (42%) but also towards Manchester (17%) and to Chester itself (24%); and
♦ most of the remaining routes are self-contained, with the potential exception of the
Wrexham-Chester line which shows appreciable levels of travel beyond Chester to either
North Wales or the Wirral
Journey To Work Census Data
4.68 Use has been made of the 2001 census data to show the variation in mode of transport used to
travel to work across the M56 transport corridor and surrounding area, compared to the average of;
♦ Home Work 8.3%
♦ Car/Motorcycle 68.2%
♦ Taxi 0.8%
♦ Bus/Coach 8.3%
♦ Train/Tram 2.3%
♦ Cycle 2.4%
♦ Walk 9.2%
♦ Other 0.5%
4.69 Figures 4.5 to 4.8 below show the variation in mode of transport used for; private vehicle (car driver, car passenger and taxi); public transport as a whole; rail; and bus and coach.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 49 of 150m56_scoping_study_final_report.doc
Figure 4.5 - Percentage Private Vehicle Use as Mode to Work
Figure 4.6 - Percentage Public Transport as Mode to Work
M56 CORRIDOR SCOPING STUDY
Final Report
Page 50 of 150m56_scoping_study_final_report.doc
Figure 4.7 - Percentage Rail Use as Mode to Work
Figure 4.8 - Percentage Bus and Coach Use as Mode to Work
4.70 The census data has also been used to show below in Figures 4.9 and 4.10 the variation in;
♦ distance travelled to work across the M56 transport corridor and surrounding area,compared to the average of 13.2km; and
♦ indices of deprivation.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 51 of 150m56_scoping_study_final_report.doc
Figure 4.9 - Average Distance (km) Travelled to Work
Figure 4.10 - Indices of Deprivation
4.71 The main findings from this analysis are that;
♦ the greatest concentrations of multiple-deprivation are the core areas of the Greater
Manchester and Merseyside conurbations with public transport (principally bus) accounting
M56 CORRIDOR SCOPING STUDY
Final Report
Page 52 of 150m56_scoping_study_final_report.doc
for up to 38% of the mode share for journeys to work and typically less than 10km in length. In Merseyside 40% of households have no access to car.
♦ the broad correlation between affluence and distance travelled to work supports the
general trend that with increased wealth people prefer to relocate to the urban fringes and surrounding rural areas but continue to work in the city centres, accepting the need to undertake a longer commute to work.
♦ without a high quality public transport network these longer journeys to work from the rural
areas are predominantly made by private vehicle, and this is typified by travel patterns
across rural Cheshire. Where public transport services are poor, reliance on the car increases, such as in and around the areas of Northwich, Middlewich, Winsford and Kelsall. As the standard of public transport provision improves so does the uptake to it, as
exemplified by above average rail use for areas near the Crewe-Manchester spur of the West Coast Main Line.
♦ longer journeys to work and the reliance of car as the primary mode of travel from
Flintshire, would appear to support the finding from the ‘West Cheshire – North East Wales Sub Regional Study’ that despite a net migration of population from Chester to Flintshire the predominant commute is west to east over the English border to the major employers
in the area including Airbus, MBNA and Vauxhall and which are poorly served by public transport;
♦ the relatively high use of public transport in east Wirral and relatively short journey length
suggest that the principal locations for employments are nearby in Wirral itself andLiverpool, rather than towards job opportunities to the south including; Chester (including
Chester Business Park), Ellesmere Port (including Vauxhall Motors), Deeside Industrial Park and Broughton Airbus. This would appear to support the finding from the ‘Mersey Dee Alliance Transport and Accessibility Improvement Study’ that there is currently
inadequate affordable public transport services to facilitate access to these jobopportunities from areas of social exclusion.
Existing Air Passenger Demand
Manchester Airport
4.72 Manchester Airport is the largest airport in the North West and by far the largest airport in the UK outside the South East, with a throughput of 20 million passengers per annum (mppa). It currently serves around 170 destinations world-wide and has a substantial network of long-haul
scheduled services.
4.73 In 2002 the transport mode share for passengers was split;
♦ Private Car Drop Off 40.5%
♦ Airport Long Stay Car Park 8.0%
♦ Private Car Long Stay Car Park 7.5%
♦ Taxi/Minicab 29%
♦ Hire Car 2.0%
♦ Courtesy Bus 2.8%
♦ Bus/Coach 4.5%
♦ Train 5.6%
Liverpool John Lennon Airport
4.74 Liverpool John Lennon Airport has seen rapid recent growth and is an important gateway to
Merseyside and the second airport for the North West. Passenger numbers have quadrupled in the last five years, mainly as a result of developing alternative markets to Manchester such as ‘no-frill’ services. In 2003, the Airport handled 3.2 mppa.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 53 of 150m56_scoping_study_final_report.doc
4.75 In 2002 the surface access transport mode share for passengers was split;
♦ Private Car 67.5%
♦ Taxi/Minicab 20.4%
♦ Hire Car 4.2%
♦ Train 5.9%
♦ Bus/Coach 9.9%
♦ Other 2.5%
Existing Freight Demand
4.76 Within the study corridor the key routes are provided in a north-south direction by way of the M6 motorway and West Coast Main Line; along with east-west movements from Holyhead and Deeside via the M56 itself.
4.77 A summary of the key generators and attractors are;
♦ the multitude of port facilities available on Merseyside/Wirral at such locations at Seaforth, Garston and Ellesmere Port act with both road and rail benefiting from these flows;
♦ Deeside Industrial Park, including Corus and Toyota. Within the park there are a number
of large industries including paper, power, building products, motor components,electronics, engineering, food-related industries and specialist steel and plastic products;
♦ Vauxhall Motors plant at Ellesmere Port;
♦ Ford-Jaguar plant at Halewood;
♦ Shell UK oil refinery at Stanlow;
♦ chemical manufacturing facilities at Runcorn; and
♦ salt industry around Northwich.
4.78 Elsewhere in the study corridor, the distribution and hi-technology industries have become focused along the M56 corridor generating freight movements individually of low volume but
when aggregated making up substantial road flows.
4.79 An analysis has been made of the UK freight model as held and maintained by MDS Transmodal. From this model all flows by either rail or road which would be forecast to utilise
the M56 study corridor have been extracted, based upon tonnes lifted by mode.
4.80 Tables 4.9 below details the breakdown of the road freight origins and destinations which usethe M56 corridor. It should be noted that this table contains a small element of ‘noise’ with some
unusual movements predicted to use the M56 corridor, such as between the South West and the East Midlands, but only involving very small tonnages lifted.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 54 of 150m56_scoping_study_final_report.doc
Table 4.9 - Annual 000’s tonnes lifted by road freight in M56 corridor (2002)
East
Mid
lan
ds
Ea
st
En
gla
nd
Gra
ter
Lo
nd
on
No
rth
Ea
st
No
rth
We
st
Sco
tlan
d
So
uth
Ea
st
So
uth
We
st
Wa
les
We
st
Mid
lan
ds
Yo
rks
hir
e
To
tal
East Midlands- - - - 1,418 - - 2 187 5 7 1,619
East England- - - - 851 - - - 119 - 2 972
Greater London - - - - 55 - - - 1 - - 56
North East - - - - 552 - - - 260 72 - 885
North West 2,118 629 486 373 19,683 233 371 381 3,669 2,719 1,614 32,275
Scotland - - - - 602 - - - 326 14 - 943
South East - - - - 1,966 - - - 174 - 12 2,152
South West 2 - - - 494 - - - 86 - 72 654
Wales 356 266 1,047 172 2,922 224 201 117 9 439 857 6,612
West Midlands10 - - 90 3,618 30 - - 348 - 451 4,547
Yorkshire9 1 - - 2,344 - 3 92 747 259 - 3,455
Total 2,494 896 1,533 635 34,505 486 575 593 5,926 3,508 3,017 54,169
4.81 As one would expect the predominant road freight movements in the M56 corridor are those with either an origin or destination within the North West region. Road freight to/from Wales is
the next strongest movement followed by the West Midlands and Yorkshire. The largest individual movement of road freight are trips within the North West itself i.e. North West intra-regional trips account for over 36% of annual tonnes lifted by road freight in the M56 corridor.
4.82 Interestingly, road freight from the North West of England to South East/London has a low level of usage in the M56 corridor, with other routes obviously being preferred for this strong movement, such as along the parallel M62 or the main north-south M6 motorways.
4.83 The M56 therefore may be seen to perform only a limited freight role, with the total tonnes lifted
of 54.2 million comparing poorly to the UK wide total of 1,640 million tonnes lifted – only 3%.Table 4.10 below shows an analysis of the proportion of UK road freight which uses the M56 corridor for all or part of it’s journey.
Table 4.10 - Proportion of UK road freight tonnes lifted in M56 corridor (2002)
East
Mid
lan
ds
Ea
st
En
gla
nd
Gra
ter
Lo
nd
on
No
rth
Ea
st
No
rth
We
st
Sco
tlan
d
So
uth
Ea
st
So
uth
We
st
Wa
les
We
st
Mid
lan
ds
Yo
rks
hir
e
To
tal
East Midlands - - - - 15% - - 0% 8% 0% 0% 1%
East England - - - - 19% - - - 7% - 0% 1%
Greater London - - - - 2% - - - 0% - 0% 0%
North East - - - - 12% - - - 61% 5% - 1%
M56 CORRIDOR SCOPING STUDY
Final Report
Page 55 of 150m56_scoping_study_final_report.doc
East
Mid
lan
ds
Ea
st
En
gla
nd
Gra
ter
Lo
nd
on
No
rth
Ea
st
No
rth
We
st
Sco
tlan
d
So
uth
Ea
st
So
uth
We
st
Wa
les
We
st
Mid
lan
ds
Yo
rks
hir
e
To
tal
North West 31% 14% 14% 8% 14% 3% 7% 14% 58% 22% 12% 16%
Scotland - - - - 10% - - - 70% 1% - 1%
South East - - - - 34% - - - 7% - 0% 1%
South West 0% - - - 21% - - - 2% - 5% 0%
Wales 21% 16% 30% 24% 33% 16% 5% 2% 0% 7% 51% 7%
West Midlands 0% - - 6% 35% 2% - - 7% - 10% 3%
Yorkshire 0% 0% 0% - 14% - 0% 5% 34% 4% - 2%
Total 2% 1% 1% 1% 16% 0% 0% 0% 7% 2% 2% 3%
4.84 As this table clearly shows, the M56 appears to have a limited role in meeting the routeingneeds of UK plc for road freight movements. The shaded cells in Table 4.10 display where the
M56 carries over a quarter of the total road freight fl ows for this movement, and applies only to those movements which of necessity need to use the route, such as Wales to Yorkshire, andWales to the North West.
4.85 Tables 4.11 below details the breakdown of the rail freight origins and destinations which usethe M56 corridor.
Table 4.11 - Annual 000’s tonnes lifted by rail freight in M56 corridor (2002)
East
Mid
lan
ds
Ea
st
En
gla
nd
Gra
ter
Lo
nd
on
No
rth
Ea
st
No
rth
We
st
Sco
tlan
d
So
uth
Ea
st
So
uth
We
st
Wa
les
We
st
Mid
lan
ds
Yo
rks
hir
e
To
tal
East Midlands434 - 8 - 1 443
East England179 20 1 199
Greater London 4 - - 4
North East 40 1,172 8 1,220
North West 63 68 32 41 351 3 41 4 27 27 75 733
Scotland 69 80 15 165
South East 298 14 1 314
South West - 33 20 - 53
Wales 103 34 82 92 22 31 33 11 1 97 115 619
West Midlands- - 22 - 6 16 44
Yorkshire3 - - 173 - 1 58 116 351
Total 169 102 115 133 1,625 34 74 16 1,406 263 208 4,146
M56 CORRIDOR SCOPING STUDY
Final Report
Page 56 of 150m56_scoping_study_final_report.doc
4.86 Again, this table shows that the strongest “M56” corridor movement for rail freight is to/from the
North West which is followed by the movement of rail freight to/from Wales. The strongest individual movement is that between North East England and Wales, almost certainly based upon steel products.
4.87 Overall, rail holds a market share of tonnes lifted in the M56 corridor of 8%, a figure close to the UK average of 6%.
4.88 The Port of Manchester (Manchester Ship Canal) handled around 8 million tonnes of freight, in
2001, mainly liquid bulk to and from the petro-chemical industry at Stanlow, but also dry bulk to Ellesmere Port and Runcorn. Upstream of Runcorn approximately 1 million tonnes of freight per annum are carried formed of dry and liquid bulk cargoes, with a recent new service established
bringing containers to Irlam Wharf direct from Southampton and Clydeport.
4.89 In 2002 Manchester Airport handled almost 116,000 tonnes of air freight, whilst Liverpool handled some 27,500 tonnes (of which almost half was mail). Air freight is in the main carried
in the hold of passenger aircraft (known as belly-hold freight) as well as on dedicated all-cargoaircraft. At Manchester Airport some 60 percent of air freight is belly-hold.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 57 of 150m56_scoping_study_final_report.doc
5. Initial Baseline Assessment of Problems and Issues
5.1 This section of the report examines the current problems and issues associated with highway,rail and freight services and networks as derived from a desktop study of the existing
information available.
Analytical Representation of Highway Related Problems and Issues
Congestion Reference Flows
5.2 The Congestion Reference Flow (CRF) of a link is an estimate of the Annual Average Daily Traffic (AADT) flow at which the carriageway is likely to be ‘congested’ in the peak periods on an average day. For the purposes of calculating the CRF, ‘congestion’ is defined as the
situation when the hourly traffic demand exceeds the maximum sustainable hourly throughput of the link. At this point the effect on traffic is likely to be one or more of the following: flow breaks down with speeds varying considerably, average speeds drop significantly, the
sustainable throughput is reduced and queues are likely to form. This critical flow level can vary significantly from day to day and from site to site and must be considered as an average.The CRF is a measure of the performance of a road link between junctions. The effect of
junctions must be considered separately and has not been undertaken for this study.
5.3 Links of the same standard will have different CRF values determined by the proportion of heavy vehicles, the peak to daily ratio, the peak hour directional split and the weekday/weekly
flow ratio. The variation of the local daily/peak hour flow profile over the year indicates when the peak hours/periods occur. Thus a link which experiences the traditional morning and evening commuter peaks, and has AADT traffic levels equal to the CRF, is likely to be
‘congested’ for approximately 250 hours per year in the weekday peaks in the peak direction.(There being approximately 500 weekday peak hours in the year, half of which will have a higher than average demand flow).
5.4 Appendix F provides details of the formula used to calculate the congestion reference flow.
Existing Level of Stress on the Regional Highway Network
5.5 The CRF is used in comparison with the AADT to derive the stress factor for a link, which is used as a proxy for journey time reliability. Values greater than 0.75 are generally held to give
cause for concern (as reflected in the Appraisal Summary Table worksheet for Journey Time Reliability). The stress factor for a link is defined as the ratio between the annual average daily traffic (AADT) and the congestion reference flow (CRF), with a value of 100% relating to an
AADT equivalent to the CRF, with approximately 250 hours of congestion per year in the peakdirection.
5.6 Table 5.1 summarises the existing levels of stress on the regional highway network in the study
area.
Table 5.1 – Existing Stress Levels (2002) on the Regional Highway Network
2002 Traffic Levels
Section Road Location CS AADT PK%H CRF %STRESS
1 A55(T) West of Ewloe D2T 52000 9.6 68600 76%
1 A494(T) A55(T)-A550(T) D2T 59000 8.1 69700 85%
1 A550(T) A494(T)-A548 D2T 51300 7.2 70300 73%
2 A550(T) A548-A5117(T) D2T 51300 9.5 72400 71%
2 A5117(T) A550(T)-M56 Jnc 16 D2T 37800 11.9 76300 50%
M56 CORRIDOR SCOPING STUDY
Final Report
Page 58 of 150m56_scoping_study_final_report.doc
2002 Traffic Levels
Section Road Location CS AADT PK%H CRF %STRESS
3 M56 Jnc 15-16 D2M 31600 11.6 66400 48%
3 M56 Jnc 14-15 D3M 91500 11.3 116300 79%
3 M56 Jnc 12-14 D3M 96800 11.3 109400 88%
3 M56 Jnc 11-12 D3M 84000 11.3 112500 75%
3 M56 Jnc 10-11 D3M 89000 12.2 113100 79%
3 M56 Jnc 9-10 D3M 88500 12.2 115200 77%
4 M56 Jnc 8-9 D3M 69600 6.1 83200 84%
4 M56 Jnc 7-8 D3M 58300 9.6 102100 57%
4 M56 Jnc 6-7 D3M 110200 10.6 100800 109%
4 M56 Jnc 5-6 D4M 121200 10.1 138100 88%
4 M56 Jnc 5 Airport Spur D3M 60000 4.4 132500 45%
4 M56 Jnc 4-5 D4M 129100 7.1 175400 74%
4 M56 Jnc 3-4 D4M 143300 6.1 180200 80%
4 A5103(T) M56 Jnc 3-M60 Jnc 5 D3T 103800 3.4 112900 92%
4 M56 Jnc 2-3 D2M 60700 13.0 74300 82%
4 M56 Jnc 1-2 D3M 86400 12.3 98800 87%
5 M53 Jnc 4-5 D3M 50500 4.8 88700 57%
5 A41/A550 M53 Jnc 5 – A5117(T) S2T 21400 7.5 22800 89%
5 M53 Jnc 6-7 D2M 52200 4.9 58800 89%
5 M53 Jnc 7-8 D2M 60000 4.9 71900 83%
5 M53 Jnc 9-10 D2M 53200 8.9 70000 76%
5 M53 Jnc 10-11 D2M 57400 9.6 69600 82%
6 M53 Jnc 11-12 D2M 65800 8.7 68800 96%
6 A55(T) M53 Jnc 12-A51 D2T 30900 10.4 62000 50%
6 A55(T) A5-A41 D2T 47700 10.3 64700 74%
6 A55(T) A41–A483(T) D2T 56900 10.4 68000 84%
6 A55(T) A483(T) - A550 D2T 24900 8.7 69300 36%
6 A55(T) A550-A494(T) D2T 38300 8.3 69500 55%
7 A533 Silver Jubilee Bridge S4P 77000 12.0 58500 132%
8 A556(T) M56 Jnc 7/8 – M6 Jnc 19 S4T* 48200 10.4 44000 110%
9 A556 M6 Jnc 19 – A559 S4P 26300 5.6 46600 56%
9 A556 A559-A49 D2P 29800 3.6 46100 65%
9 A556 A49-A54 S2P 16900 5.6 46600 36%
9 A54 A556-A51 D2P/S2P 15800 5.6 23300 68%
9 A51 A54-A55(T) S2P 29500 5.6 23300 127%
5.7 Figure 5.1 reproduces the existing level of stress for the regional highway network in the study area.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 59 of 150m56_scoping_study_final_report.doc
Figure 5.1 – Existing Level of Stress for the Regional Highway Network
5.8 On the basis of this analysis the following sections of key road network are shown to be over-capacity;
♦ M56 between junctions 6 and 7;
♦ A556(T) between M56 junctions 7/8 and M6 junction 19;
♦ A533 Silver Jubilee Bridge; and
♦ A51 east of Chester
All of these locations that have been identified as sections of road suffering from congestion in the peak periods.
5.9 However, on the basis of this simple method of analysis the A5117(T)/A550(T) through Deeside Park would “appear” to be operating successfully. Clearly, this is not the case with the level ofstress being significantly underestimated because the CRF formula takes no account of the
limiting capacity of the at-grade junctions.
5.10 Indeed the CRF formula also takes no account of the interaction between junctions for example, the impact of weaving traffic between closely spaced junctions. Thus it is reasonable to
conclude that the existing levels of stress for sections of the M53 between junctions 5 and 11, and M56 between junctions 3 and 6 have been underestimated using this approach.
Existing Congestion Represented By Average Speeds Below 30mph
5.11 An alternative means of representing the level of stress of the key road network is by reference
to the number of hours per annum where average speeds have fallen below 30mph, as shown in Figure 5.2 below.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 60 of 150m56_scoping_study_final_report.doc
Figure 5.2 – Number of Hours per Annum with Average Speeds Less Than 30mph
5.12 Figure 5.2 above was produce using information supplied by Trafficmaster and provides further
evidence of the stress that the M56 east of junction 7 is under. It is unfortunate that similar data was not available for all of the regional highway network in the study area and in particular, the A556(T), M56/A5117(T)/A550(T)/A494(T) west of junction 15, and Silver Jubilee Bridge.
5.13 In addition the Highways Agency holds a journey time database for the motorway network, that can be interrogated at 15 time minutes intervals (or averaged according to need) by making ‘best’ use of data from three sources;
♦ MIDAS data
♦ Trafficmaster
♦ ITIS data – GPS generated data (albeit biased toward commercial vehicles and more expensive cars)
5.14 Although outside of the timeframe for completing this draft report it is considered thatinterrogation of this database would provide useful further information on existing conditions.
Future Level of Service on the Regional Highway Network
5.15 A preliminary estimate of the future levels of stress that can be expected on the regional
highway network, over a 15 year horizon, has been made by applying October 1997 NationalRoad Traffic Forecast factors, to the 2002 base flows. Historically, ‘Low’ and ‘High’ traffic growth profiles had been prepared, but these are now replaced by a single ‘central’ defaultgrowth profile. NRTF assumes a traffic growth factor of 1.35 between 2002 and 2019. It should
be noted that NRTF factors take no account of the possibility of road user charging being introduced at some date in the future.
5.16 In terms of the standard of highways provision for the future year regional highway network, no
highway improvements have been assumed to provide a worst case scenario.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 61 of 150m56_scoping_study_final_report.doc
5.17 Table 5.2 below summarises the future levels of stress on the regional highway network in the
study area assuming unconstrained traffic growth.
Table 5.2 – Future Levels of Stress (2019) on the Regional Highway Network
Carriageway 2019 Central NRTF
Section Road Location Standard AADT Stress
1 A55(T) West of Ewloe D2T 66900 98%
1 A494(T) A55(T)-A550(T) D2T 75900 109%
1 A550(T) A494(T)-A548 D2T 66000 94%
2 A550(T) A548-A5117(T) D2T 66000 91%
2 A5117(T) A550(T)-M56 Jnc 16 D2T 48600 64%
3 M56 Jnc 15-16 D2M 40600 61%
3 M56 Jnc 14-15 D3M 117700 101%
3 M56 Jnc 12-14 D3M 124500 114%
3 M56 Jnc 11-12 D3M 108000 96%
3 M56 Jnc 10-11 D3M 114500 101%
3 M56 Jnc 9-10 D3M 113800 115%
4 M56 Jnc 8-9 D3M 89500 108%
4 M56 Jnc 7-8 D3M 75000 73%
4 M56 Jnc 6-7 D3M 141700 141%
4 M56 Jnc 5-6 D4M 155900 113%
4 M56 Jnc 5 Airport Spur D3M 77200 58%
4 M56 Jnc 4-5 D4M 166000 95%
4 M56 Jnc 3-4 D4M 184300 102%
4 A5103(T) M56 Jnc 3-M60 Jnc 5 D3T 133500 118%
4 M56 Jnc 2-3 D2M 78100 105%
4 M56 Jnc 1-2 D3M 111100 112%
5 M53 Jnc 4-5 D3M 64900 73%
5 A41/A550 M53 Jnc 5 – A5117(T) S2T 27500 121%
5 M53 Jnc 6-7 D2M 67100 114%
5 M53 Jnc 7-8 D2M 77200 107%
5 M53 Jnc 9-10 D2M 68400 98%
5 M53 Jnc 10-11 D2M 73800 106%
6 M53 Jnc 11-12 D2M 84600 123%
6 A55(T) M53 Jnc 12-A51 D2T 39700 64%
6 A55(T) A5-A41 D2T 61300 95%
6 A55(T) A41–A483(T) D2T 73200 108%
6 A55(T) A483(T) - A550 D2T 32000 46%
6 A55(T) A550-A494(T) D2T 49300 71%
7 A533 Silver Jubilee Bridge S4P 99000 169%
8 A556(T) M56 Jnc 7/8 – M6 Jnc 19 S4T* 62000 141%
9 A556 M6 Jnc 19 – A559 S4P 33800 73%
9 A556 A559-A49 D2P 38300 83%
9 A556 A49-A54 S2P 21700 47%
9 A54 A556-A51 D2P/S2P 20300 87%
9 A51 A54-A55(T) S2P 37900 163%
M56 CORRIDOR SCOPING STUDY
Final Report
Page 62 of 150m56_scoping_study_final_report.doc
5.18 Figures 5.3 and 5.4 below present the future year traffic growth forecast flows and levels of
stress on the regional highway network in 2019.
Figure 5.3 – Forecast 2019 Annual Average Daily Traffic (Central NRTF)
Figure 5.4 – Forecast Level Stress 2019 (Central NRTF)
M56 CORRIDOR SCOPING STUDY
Final Report
Page 63 of 150m56_scoping_study_final_report.doc
5.19 It is evident from Table 5.2 above that the regional highway network has a finite capacity and in
its current form will be unable to accommodate unconstrained traffic growth over a 15 year horizon.
5.20 Even with peak spreading, which has the effect of increasing the CRF (and hence the
calculated level of stress), many of the forecast flows are unachievable, such as; across the Silver Jubilee Bridge, the A556(T) and M56 between junctions 6 and 7. Indeed, as previously stated the table above underestimates the level of stress on sections of road affected by the
interaction of junctions.
Analytical Representation of Rail Related Problems and Issues
5.21 Rail related problems as considered from an analytical approach considering three different aspects of capacity/constraints:
♦ Network Capacity Utilisation as depicted in the 2004 Network Rail Business Plan, showing how busy the rail routes are in the UK;
♦ train capacity utilisation effectively acting as a measure of peak period crowding; and
♦ rail freight network constraints.
5.22 Each of these will be considered in turn.
Network Capacity Utilisation
5.23 The 2004 Network Rail Business Plan provides information on how busy the rail network is terms of the number of available train paths compared to the demand for them. Where capacity
exceeded 90% it is considered serious operational problems would result with high levels of unreliability.
5.24 Table 5.3 shows the results of the 2000 analysis for the key rail corridors in question:
Table 5.3 – Rail Network Capacity Utilisation (2004 Network Rail Business Plan)
Route % utilisation
Chester-Northwich-Manchester 30-70%*
Chester-Warrington-Earlestown-Manchester 30-70%*
Chester-Wrexham 30-70%
Chester-Crewe 30-70%
Bidston-Shotton-Wrexham 30-70%
Chester-Hooton 30-70%
Ellesmere Port-Hooton 30-70%
Helsby-Ellesmere Port <30%
Frodsham-Runcorn n/a
Crewe-Runcorn-Liverpool (WCML)
Crewe-Weaver Junction
Weaver Junction-Warrington Bank Quay
Weaver Junction-Runcorn-Liverpool
>90%
70-90%
30-70%
Note: * indicates that 70-90% Network Utilisation was identified on approaches to Manchester Hub.
5.25 As this table shows the key problem identified is that of the main West Coast Main Line south of Weaver Junction and at key pinchpoints in the Manchester “hub” area. Both of these issues are
M56 CORRIDOR SCOPING STUDY
Final Report
Page 64 of 150m56_scoping_study_final_report.doc
being addressed by the SRA as part of their Manchester Hub and West Coast Main Line
strategies, along with the Regional Planning Assessments and Route Utilisation Strategies. For the remaining routes in the study area minimal line capacity problems were identified.
Train Capacity Utilisation
5.26 A methodology similar to that used in the London and South East area has been adopted
based upon advice from the SRA, which is broadly based upon PIXC – Passengers in Excessof Capacity. The process used is set out below:
♦ extract from MOIRA the flows of passengers along each link for passengers who arrive at
the major destination station between 0700 and 1000 on a weekday, the major stations in the study area being Manchester, Chester, Liverpool and Warrington;
♦ from estimates of the seating capacity provided by the Train Operating Companies over the same morning peak period (based on scheduled train services), and allowing for anadditional 35% to take account of standing over and above the seated capacity; and
♦ express percentage train capacity utilisation as the ratio of the number of passengers tototal passenger capacity (seating plus standing) over the weekday morning peak period.
5.27 Figure 5.5 below shows the results of such an analysis for the M56 corridor study routes, with colour coding set for train capacity utilisation.
Figure 5.5 – Train Capacity Utilisation
5.28 Figure 5.3 shows that none of the routes are subject to overcrowding problems when
considered in the context of the full morning peak period. However, it should be bourn in mind that the passenger demand profile is not uniform over the 3 hour morning peak period (07:00-10:00) and therefore it is reasonable to conclude that the %train capacity utilisation for the
morning peak hour will be higher than for the average morning peak period. This may require further investigation in any future stages of this study.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 65 of 150m56_scoping_study_final_report.doc
Rail Freight Network Constraints
5.29 Separate to the issues associated with the passenger rail network are the constraints which
exist restricting the ability of freight trains to access certain areas of the country. The two constraints applicable are route availability (RA) and loading gauge.
5.30 Route availability is a function of the permissible axle-loading along the line, and is expressed
as a rating between RA1 and RA10, with the higher the index the greater the axle load that can be carried. The rating is affected, in particular, by the strength of bridges along a route.
5.31 Within the M56 study area most of the routes are rated at the highest permissive axle load of
RA10, with the exception of the line north of Hooton to Birkenhead and Liverpool which is rated at a lower RA8, and north of Shotton to Bidston which is rated at RA7. As such there are minimal constraints upon the weight of rail vehicle that can be accommodated in the study area.
5.32 Loading gauge constraints describe the ability of a route to take different sizes of wagons over the network, and is a function of the clearances afforded by platforms, bridges and tunnels.
5.33 The loading gauge presents greater problems in the study area, as is evident from Figure 5.4.
This shows the loading gauge ratings in the study area, as obtained from the Network Rail Freight Commercial website and classified as:
♦ W7 (W6A-8’): able to accommodate 8’ high containers on normal height wagons;
♦ W8 (W6A-8’6”): able to accommodate 8’ 6” high containers on normal height wagons;
♦ W9 (SB1c): able to accommodate demountable loads (swap bodies) and 9’6” highcontainers using low floor/pocket wagons; and
♦ W10 (SB1c): able to accommodate 9’6” high containers on specific wagons.
Figure 5.6 – Loading Gauge Map
M56 CORRIDOR SCOPING STUDY
Final Report
Page 66 of 150m56_scoping_study_final_report.doc
5.34 As is evident from this figure the main north-south West Coast Main Line has been fully cleared
to take the increasingly dominant 9’6” maritime containers, and so have the links to the rail hubs at Trafford Park in Manchester, and Seaforth and Garston in Merseyside. Away from this corridor the majority of the rail network is rated at W8 with a small section of W7 on the Mid
Cheshire line which means that the high containers cannot be conveyed on these routes. Increasingly container traffic is adopting the height of 9’6” as standard, which will lead to increasing problems for rail in maintaining competitiveness with road for inter-modal (container
based) traffic.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 67 of 150m56_scoping_study_final_report.doc
6. Inventory of Problems and Issues and Potential Transport Measures
Identified Through Document Review and Stakeholder Consultation
6.1 The purpose of this section is to document the full range of problems and issues and potential
transport measures (relevant to the M56 corridor study area) that have been identified through document review and from stakeholder consultation. It must be stressed that a detailedexamination of the regional significance of the problems identified has not been undertaken as
part of this scoping exercise, and therefore their presence should not be misconstrued as an endorsement of their regional importance.
6.2 Section 7 of this report relates these problems and issues back to the corridor objectives
(outlined in Section 2), while Appendix G presents the results from a broad qualitativeassessment of the extent to which the transport measures identified through document review and stakeholder consultation could potentially contribute to the strategic objectives for the M56
corridor.
6.3 In addition to a description of the identified problem and issues and potential transport measure the following information has been collated where available;
♦ status of the scheme/measure, with committed schemes highlighted in red
♦ an indication of the likely cost of the scheme/measure, (estimated range where data not available);
− less than £5m;
− £5m to £50m;
− £50m to £100m; and
− greater than £100m.
♦ an indication of the potential timescale for implementation (estimated where no timescale provided in documented references, and categorised as either a;
− short term measure (0-5years);
− medium term measure (5-10years); or
− long term measure (over 10 years).
M56 CORRIDOR SCOPING STUDY
Final Report
Page 68 of 150m56_scoping_study_final_report.doc
Table 6.1 – Identified Highway Related Problems and Issues/Transport Measures in the Study Area
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
HP1 The M56 east of M6 is not part of Trans-
European Network Routes.
Trans-European Routes are designated to be
of highest strategic importance, with the principal function of catering for long distance
traffic movements linking origins and
destinations with international significance.
Indeed the M56(West of M6)/A5117(T)/A550(T)/A94(T)/A55(T) forms
part of E22 from Ireland, through North Wales
(via Holyhead), that uses the M6 to join the M62 trans-pennine route to Hull and onward to
Europe. However, the M56 east of M6 is not
part of the TENs even though both Manchester
Airport and Liverpool John Lennon Airport are a part of TENs. The status of A556(T) should
also be reviewed as it also part of the main
approach to Manchester Airport from M6
south.
Regional Planning
Guidance for the North
West
HS1 Designate the M56 east of M6 as a Trans
European Route
Short Term
HS2a Company travel plans including car sharing
incentives and flexible work practices
Short Term
HS2b School travel plans Short Term
HS2c Car pooling sites at motorway interchanges. Short Term
HS2d Dedicated lanes for road based public
transport services in conjunction
Medium Term
HS2e Dedicated lanes for high occupancy
vehicles
Medium Term
HS2f Road user charging Medium Term
HS2g Parking charges (including disincentives for “kiss-ride” at Airports) and workplace
charging
Short Term
HS2h Closure of motorway junctions Medium Term
HP2 General recognition of a need to better
manage highway demand together with the development of telecommunications to reduce
the need to travel.
The regional road network has a finite capacity
and that demand already exceeds supply in certain key locations leading to congestion and
problems of journey time reliability to all road
users.
Increases in traffic growth will
assert greater pressure on the road network with a subsequent
deterioration in the level of service
to all road users.
Issue raised at
stakeholderconsultation with
Warrington MBC and
Manchester Airport
HS2i Telecommunications – development of
technologies which will facilitate teleshopping, teleworking and video
conferencing
Short Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 69 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
HS3a Ramp metering on slip roads at appropriate junctions to ensure traffic joins motorways in
a controlled way, avoiding queues.
Less than £5m Medium Term
HS3b Use of the hard-shoulder as a running lane
to increase link capacity.
£5m to £50m Short Term
HS3c Electronic variable speed limit signs to smooth traffic flows at busy times
£5m to £50m Short Term
HS3d Other 'Active Traffic Management' systems including, enhanced message signs and
strategic incident diversion routes. For
particular application see problem ref. FP5.
Short Term
HS3e National Traffic Control Centre
♦ improve the information to travellers about delays and
recommended diversions using
electronic message signs
♦ offer new telephone and Internet services enabling travellers to
make more informed travel choices
♦ provide improved traffic information to the media and other
organisations
♦ supply information to the Government's Transport Direct
service (see HS3f below)
The Welsh Assembly have set up their own TCC – ‘’Traffic Wales’ based in
Coryton (South Wales).
NTCC already
operational
although the range of services are still
being rolled out.
Short Term
HP3 General recognition of a need to make better use of existing infrastructure.
A signif icant proportion of the regional road
network is running at or near capacity, resulting in unreliable journey times, frustration
to drivers and increased cost to industry. The
impact of inc idents and roadworks exacerbate
these problems.
With vehicle ownership rising steadily, demand is forecast to
increase further.
Highways Agency Business Plan –
2003/04
HS3f Government's Transport Direct service which will provide a comprehensive
route planning service covering all
modes of transport.
Short Term
HP4a Poor journey time reliability on the
A550(T)/A494(T) through Deeside and
Queensferry. This section is running at or near capacity during the peak periods. The duration
of the peak period is increasing as drivers alter
their travel times to reduce delays. Congestion
Historically traffic growth along this
corridor has been higher than
national growth and further expected growth will add
significantly to existing congestion.
These problems will be
Queensferry
Transportation Study,
September 2000
The Transport
Framework for Wales,
HS4a Review of options for solving capacity
problems on A55 Ewloe to Northop
Trunk Road
Forward
Programme 2002, Welsh Assembly
Government
£5m-£50m Medium Term
Unlikely to
proceedbefore April
2008
M56 CORRIDOR SCOPING STUDY
Final Report
Page 70 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
on the trunk road is a frequent occurrence and is severe at times.
exacerbated by planned developments in the Deeside
Industrial Park which may act as a
deterrent to tourist destinations including, North Wales coastal
areas, Snowdonia National Park
and Anglesey (and beyond to
Ireland via the ferry terminal at Holyhead).
HS4b A55/A494 Ewloe interchange improvement with a connection to A494
to Mould
Trunk Road Forward
Programme 2002,
Welsh Assembly Government
£5m-£50m Medium Term
Unlikely to
proceed
before April 2008
HS4c Widening A494 Drome Corner to Ewloe Trunk Road
ForwardProgramme 2002,
Welsh Assembly
Government
£5m-£50m Short Term
Procurementunder early
contractor
involvement(late 2006/07)
HP4b Safety issues on the A494(T)/A550(T) through
Queensferry and Deeside. The accident rate on this section is above the national average
and four times higher in places.
Future increases in traffic will add
significantly to the existing trafficsafety problems.
November National Assembly for Wales ,
November 2001
Trunk Road Forward Programme 2002,
Welsh Assembly
Government
HS4d Widening A494/A550 Deeside Park to
Drome
Trunk Road
ForwardProgramme 2002,
Welsh Assembly
Government
£5m-£50m Short Term
In progress
HP5a Poor journey time reliability on
A5117(T)/A550(T) between the end of the M56
and the Welsh border. Average speeds of 40mph in the peak as result of insuf ficient
junctions capacity. In the inter peak average
speeds still only reach 55mph as a result of the
high proportion of heavy goods vehicles and slow moving agricultural vehicles.
At the A5117/ (T)A540 roundabout in the
morning peak hour the mainline flow of traffic bound for Deeside Park and onwards to North
Wales has to give priority to the lesser
movement of commuters between Neston and
Chester creating significant delays. The reverse is true in the evening peak hour and
delays to traffic bound for Manchester.
HP5b Safety issues on A5117(T)/A550(T) between the end of the M56 and the Welsh border – last
three remaining at -grade junctions on E22 in
England. All three junctions have existing road safety problems.
♦ A550(T)/A5117(T) traffic signals most
heavily trafficked section of the A550(T),
Deeside Park Junctions
Study, 2001HS5 Deeside Park junctions improvement
scheme – on-line grade separation of the
at-grade three junctions along the route , together with the provision of a service
road combined with pedestrian/cyclist/
equestrian facilities. Improvements will
comprise new two-level junctions with the M56, A540 and A550(T).
Highways Agency
Targeted
Programme of Improvements
Scheme
£5m-£50m
(£21m –
Deeside Park 2001)
Short Term
Scheduled to
be open to traffic in 2007
M56 CORRIDOR SCOPING STUDY
Final Report
Page 71 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
with poor accident record, associated with high approach speeds and queuing
traffic give rise to high number of shunts
and loss of control accidents
♦ A5117(T)/A540 roundabout long queues
develop at peak times affecting both the
A5117(T) and A540. High approach speeds coupled with poor deflection,
particularly for westbound traffic gives
rise to high number of shunts and loss of control accidents.
♦ A5117(T)/M56 high approach speeds in
particular on the A5117(T) eastbound and M56 approaches, coupled with
substandard alignment on the M56
approach are cited as the cause of
accidents at this junction.
HS6a A550 Improvement Hooton to Sealand To be considered as
part of road based study for Wirral to
North Wales
£5m-£50m Long TermHP6 Access between the Wirral and Deeside
Park/North Wales. The M53/M56 Stoak Interchange has no connection between M53
North and M56 West Instead these
movements are catered for by the A41/A550
and as a result it is accepted that this section of trunk road should continue to be part of the
core trunk road network.
The A550 route is a standard single 2 lane carriageway and is approaching capacity
during peak periods.
Future increase in traffic growth
including planned developments in the Deeside Industrial Park are
likely to result in a deterioration in
the level of service on this section
of trunk road.
M53/A55/A483
Birkenhead to Welsh Border Route
Management Study.
HS6b Provision of M53/M56 Stoak Interchange
West/North Links
To be considered as
part of road based
study for Wirral to North Wales
£5m-£50m Long Term
HP7 Signing issues at the M53/M56 Stoak
Interchange and A55/A494 Ewloe Interchange.
Traffic on the M56 bound for North Wales is signed to follow the
M56/A5117(T)/A550(T)/A494(T), and likewise
traffic on the A55 bound for Manchester is
signed to follow the A494(T)/A550(T)/A5117(T)/M56.
When the CCTV camera located at the
A5117(T)/A550(T) identifies an incident or
significant congestion, there is the opportunity to activate the variable message signs (VMS)
on the M56 east of junction 15 and on the
A55(T) west of the Ewloe interchange to route traffic via the M53 and A55(T) to the south of
Issue raised at
stakeholder
consultation with both the Welsh Assembly
Government and the
Highways Agency.
HS7 Active traffic management at the M56/M53
Stoak Interchange
Less than £5m Short Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 72 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
Chester.
Whilst active traffic management is in
operation on the A55(T) this is not currently the
case on the M56. It is understood that VMS east of M56 junction 15 is in need of being
upgraded.
HP8 Close proximity of junctions on the M53 between junctions 5 and 11. The weaving
length between many of the junctions on this
section of motorway is not to standard (DMRB
Volume 6 Section 2 – TD 22/92). M53 Junction 5 to 6, 7 to 8, 8 to 9 and 10 to 11 all
have a weaving length below the desirable
minimum of 2km.
The close proximity of junctions and the impact
of weaving traffic is to reduce the capacity of
the motorway below its theoretical capacity.
Whilst this section of motorway generally operates satisfactorily some delays are already
experienced on the approaches to M53
junction 10 for traffic destined for Cheshire
Oaks Designer Outlet Village, the Blue Planet Aquarium together other facilities such as
cinemas and restaurants.
Planned development in the Ellesmere Port Economic
Development Zone will add further
pressure to this section of
motorway.
Issue raised at stakeholder
consultation with the
Highways Agency
HS8 Potential M53 highway improvementsjunctions 5 to 11
Although there are currently no scheme
proposals to improve for this section of
motorway the Highways Agency requirements are that any proposals for
significant development adjacent to this
section of motorway will need to be subject to a detailed traffic impact assessment and
may require the need for highway
improvements to be made. This is a
particular issue here given the close proximity of junctions.
Long Term
HP9a Delays at the A55/A483 interchange south of
Chester are a regular occurrence during the
peak periods.
These problems will be
exacerbated by development
proposals associated with Chester
Business Park. Chester Business Park is designated by the NWDA
as a strategic regional site. .
HP9b Safety at the A55/A483 interchange is a
concern.
HP9c Environmental issues at the A55/A483 interchange are also a concern.
Future increases in traffic will add
to the existing safety and
environmental problems.
M53/A55/A483
Birkenhead to Welsh
Border Route
Management Study
A5/A483 Shrewsbury to
Chester Road-Based
Study.
HS9 Major junction improvements to the
A55(T)/A483(T) Interchange. Preferred
option to provide increased capacity on the
roundabout to accommodate the dominant north to east bound movement from
A483(T) to A55(T), and to provide free flow
left turn slip roads.
(Proposals for a three level interchange are no longer being pursued).
A dedicated slip from the A483 on to the
eastbound A55 has recently been completed (June 2003).
Highways Agency
have been asked to
dev elop a schemed
to be considered for inclusion in the TPI.
£5 to £50m Medium Term
HP10a Delays on the A51 east of Chester frequently
occur during the peak periods as a result of overcapacity at A51/A55 and A51/A41
junctions.
HS10a A51 improvements east of Chester although
no studies or scheme proposals have been put forward by Cheshire CC to address the
problem of congestion.
Long Term
HP10b Strategic signing from the M6 may be a
contributory factor with Chester signed away
Cheshire County
Council Local Transport Plan 2001/02 –
2005/06
HS10b Highway authorities should give high priority
to ensuring that the Primary Route Network
Less than £5m Short Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 73 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
from the M6 at both junction 16 (A500/A51) and junction 18 (A54/A51).
Indeed a high proportion of heavy goods
vehicles from M6 south heading for the Wirral/Ellesmere Port/Deeside Park use the
A51 in preference to the M56 because of the
fuel cost savings that can be gained.
direction signing is up-to-date and consistent. In particular M6 to
Wirral/Ellesmere Port/Chester/North Wales.
HS5
HS7
Active traffic management at the M56/M53
Stoak Interchange (see HS5) and the
Deeside Park junction improvements (see
HS7) should improve the flow of traffic in the westbound direction.
Less than £5mHP11 Journey time reliability issues on the M56
between junctions 12 and 14 and as a result a
transfer of traffic to the already heavily
trafficked A56 through the villages of Helsby and Frodsham.
Flow breakdown in the westbound direction is
often the result of queuing traffic back from the Deeside junctions.
Delays in the eastbound direction can extend
back from the A557/M56 junction 12 Clifton
Interchange. The off -slip of the M56 eastbound carriageway has part-time signal control at
peak times to give priority over other traffic,
however there are still problems that result in
traffic backing back to the motorway.
Cheshire County
Council Local Transport
Plan 2001/02 –
2005/06
Halton Borough
Council, Local
Transport Plan 2001/02 – 2005/06
HS11 Improvements to M56 junction 12 need to be cons idered in light of the proposals for a
new Runcorn to Widnes Mersey Crossing
and the regeneration proposals in the Runcorn area.
Less than £5m Short Term
HP12a Delays on the approaches to the Silver Jubilee Bridge are a regular occurrence during the
extended peak periods. These delays also
affect the reliability of public transport.
Queues of up to 1.5km are regularly experienced on the Expressway approaches.
HP12b The Silver Jubilee Bridge was opened in 1961 as a three lane single carriageway but in 1977
it was widened to four lanes of substandard
width with poor facilities for pedestrians and no
safe facilities for cyclists.
The poor standard of the Bridge contributes to
the poor road accident rate in Halton – at
0.128% of the population, the number killed or
seriously injured on Halton’s roads is twice the national average.
Congestion and the poor standard of the bridge is a major constraint
to the development of integrated
sustainable transport strategies.
Traffic growth of over 17% over the last seven years is almost double
the national average and
increasing congestion on the Silver
Jubilee Bridge will be a constraint to economic regeneration both
locally and across the sub-region
and hamper the growth of major development areas, such as
Speke/Garston, Omega,
Daresbury, and Widnes
Waterfront.
Future growth in traffic flows
seeking to cross the bridge are
likely to be forced on to alternative
routes, impacting on the MerseyTunnels and the M6 Thelwall
Viaduct.
Halton Borough Council, Local
Transport Plan 2001/02
– 2005/06
New Mersey Crossing, Major Scheme
Appraisal, Halton
Borough Council 2003
HS12a Proposals for a major scheme for a new crossing of the River Mersey between
Runcorn and Widnes include;
♦ a new bridge crossing 1.6km east of the existing bridge. A dual 2 lane all
pupose standard linking between the
Central/Bridgewater/ Daresbury Expressway junction in Runcorn and
Ditton Roundabout in Widnes.
♦ the new crossing connecting directly into Central Expressway, with Central
Expressway crossing Daresbury
Expressway via a new high level fly -over.
♦ reduce the existing Silver Jubilee
Bridge to two lanes of vehicular traffic with improved pedestrian and cycle
facilities. Access to the bridge would
require negotiation of the severaljunction to dissuade strategic traffic
from using the bridge.
A major scheme bid has been submitted
to Government.
A strategic
assessment of the impact the new
crossing has on
travel patterns is
currently being undertaken including
the impact on M56
junctions 11 and 12, and M62 junctions 6
and 7.
More than £100m
(Between £291m
and £336m at
2002 estimates – Major Scheme
Appraisal for
New Mersey
Crossing)
Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 74 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
HP12c Delays of 10 minutes are frequently experienced on the A557 Weston Point
Expressway at Clifton Hall for southbound
traffic heading for M56 junction 12.
The strategic impact of any new crossing has travel patterns
including; the Mersey Tunnels; M6
Thelwall Viaduct; Warrington Mersey Crossing; M56 junctions 11
and 12; and M62 junctions 6 and 7
is required.
Issue raised at stakeholder
consultation with
Highways Agency
HS12b In addition highway improvements are proposed at both the Weston Point
Expressway Interchange at Clifton Hall and
the Southern Expressway Interchange at Halton Lodge.
Less than £5m Medium Term
HS13a As part of the Daresbury Park
development works include proposals to
upgrade M56 junction 11 slip roads and
signalise the westbound off-slip entry to the roundabout.
Works committed
under Section 278
agreement as part
of the Daresbury Park Phases 1-2
and Daresbury
Science Park planning approvals.
Less than £5m Short TermHP13a Delays at the A558 Eastern Expressway/A56
Daresbury Bypass roundabout junction with
regular queues during the peak periods
particularly on the A556 Eastern approach.The Eastern Expressway is a single
carriageway continuation of the Daresbury
Expressway dual carriageway.
The draft Halton UDP proposes a
development area for East
Runcorn as a sustainable
extension of the urban area to accommodate employment and
housing needs to 2016 and
beyond. The area includes the designated strategic regional site
at Daresbury Park including the
Daresbury Laboratory, proposed
Science Park site and adjoining sites.
Alternative sustainable access will
need to be explored to avoid
further pressure on the road network in the East Runcorn area.
East Runcorn
Development Area –
Sustainable Transport
Framework, Mott MacDonald 2003
HS13b In order to accommodate the level of
development to 2012 the following improvements to the existing highway
network have been proposed;
♦ Widening the A558 EasternExpressway to wide single
carriageway between Pitts Heath Land
and access to Daresbury Laboratory.Widening to dual carriageway is likely
to be prohibitive on cost grounds as
additional structures would be
required over railways etc.
♦ Dualling of the A558 Eastern
Expressway between access to Daresbury Laboratory and the A56
Daresbury Bypass
♦ Improvements to the A558 Eastern Expressway/A56 Daresbury Bypass
roundabout
♦ M56 junction 11 – full signalisation, widening of the circulating
carriageway and widening of entries
The proposals above take no account of
possible increases in traffic flow through
East Runcorn as a result of the proposed
new Runcorn to Widnes Mersey Crossing.
Identified in East
RuncornDevelopment Area
Sustainable
Transport Framework
Less than £5m
(£2.5m estimate in 2003)
Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 75 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
RS11a New rail station on West Coast Main Line at Daresbury Business Park
No prospect of funding in
short/medium term
Long Term
RS11b New rail station on North-Cheshire Line at
Delph Lane
No prospect of
funding in
short/medium term
Long Term
HP13b Some delays are currently experienced at the M56 junction 11 roundabout (partially
signalised), by A56 Daresbury Bypass traffic
during the peak hours.
Employment bus services linking Murdishaw
bus terminal and Runcorn east to;
♦ Manor Park and Daresbury Laboratory
♦ Abbots Park and Daresbury
Laboratory
Increase frequency on Runcorn-Sandymoor-Warrington
Hourly service on Runcorn-Darsebury -
Manchester Airpot route
Hourly bus service Runcorn-East Runcorn-
Northwich
Short Term
HP14 Congestion is a particular problem for north-south movements in Warrington which in part
is a result of;
♦ the New Town road network not being completed, so large areas of new
development have poor or constrained
access;
♦ impact and lack of control over,
motorway flows , and in particularly the M6 when incidents occur; and
♦ lack of bridge capacity across the
Manchester Ship Canal with fourcrossings carrying 60,000 AADT. The
single existing fixed bridge carrying the
B5156 has a weight limit of three tonnes.
Warrington Local Transport Plan
HS14 New crossing to the west of Warrington in conjunction with flood defence scheme.
£5m to £50m Long Term
HP15a Poor journey time reliability on the A556(T)
between M6 junction 19 and M56 junction 7.
This section of trunk road is running at capacity during extended peak periods.
H15b Safety issues on the A556(T) between M6 junction 19 and M56 junction 7, include;
speeding drivers; narrow carriageway widths;
right turning problems for numerous side-
A556 (M6 Junction 19
to M56 Junction 7)
Route Management Strategy – Public
Consultation March
2004
HS15a Short terms measures are currently under
consideration as part of a Route
Management Strategy for the A556(T), including
♦ full footway along length of route
♦ full crossing facilities at Mere (A50)
junction
♦ right turn bans a Moss Lane and Mere
A556 RMS Public
Consultation
Proposals, March 2004
Less than £5m Short Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 76 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
roads, private frontages and fieLd accesses. Golf Club junctions
HP15c Environmental issues on the A556(T) between
M6 junction 19 and M56 junction 7, include; pollution of air, noise, and water quality from
heavy volumes of traffic.
HS15b Medium term proposals include;
♦ dual carriageway between Mere and Bucklow Hill
♦ Mere junction improvements
♦ upgrade G-turn at Bucklow Hill
♦ emergency refuge lay -bys
♦ capacity/safety upgrade to M6 junction
19 and Bowdon roundabout
A556 RMS Public
ConsultationProposals, March
2004
£5m to £50m Medium Term
HP15d Congestion on the A556(T) has resulted in a
transfer of traffic on to alternative parallel routes such as the A535 and A34.
Issue raised at
stakeholderconsultation with both
Cheshire CC and
AGMA.
HS15c Longer term proposals include;
♦ dualling of the whole route (50mph speed limit) and connecting services
roads to carry local traffic and pedestrians/cyclists
♦ further improvements to Mere
Junction, to a “two level” junction
♦ convert any remaining accesses to
“left in and left out” only
♦ two level junction at Rostherne
Lane/Millington Lane
♦ free flow links to M6 junction 19 and
M56 junctions 7/8
Proposals for a new standard motorway link
have been rejected by the Secretary of State on environmental grounds. In
addition, the Secretary of State concluded
that alternative options to improve the M60
junction 20 Lymm interchange did not represent value for money and rejected
them.
A556 RMS Public
ConsultationProposals, March
2004
£50m-£100m Long Term
HP16 Poor journey time reliability on the M56
between junctions 7 and 3 and accessibility to
Manchester Airport.
Between M56 junctions 4 and 3 (the A5103 Princess Parkway) the motorway is operating
in excess of its operating capacity in the
morning and evening peak periods a problem
that is compounded by heavy weavingmovements such as M56 East (e.g. Stockport)
traffic heading for M56 West (e.g. Birmingham)
conflicting with Princess Parkway traffic
heading for Wythenshawe and Manchester
Manchester Airport is currently
operating at 20 mppa and
significant spare runway capacity
could enable the Airport to cater for 50 mppa, subject to environmental
considerations. It is forecast to be
handling around 40 mppa by 2015.
The area around Manchester Airport is subject to major business
park development pressures at
Manchester Business Park
(formerly known as Woodhouse
HS16a Widening scheme between M56
junctions 5 and 6, at-grade
improvements to M56 junction 6
roundabouts and a dual carriageway between M56 junction 6 and Terminal 2.
Scheme improvements to be in place
prior to Manchester Airport passenger
throughput exceeding 10,100 pph (currently forecast to be reached with a
annual throughput of between 30 and
37.5 mppa by 2014).
Scheme part of a
Section 278
agreement that
formed part of the planning consent of
the second runway
public inquiry.
Latest proposals shown at public
exhibition in 2002.
Section 278
agreement for
£5m-£50m
(£11.4m - M56
Western
AccessImprovements
2000)
Medium Term
Scheduled to
be completed
by 2009
M56 CORRIDOR SCOPING STUDY
Final Report
Page 77 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale for Implementation
Davenport Green includes the works
at M56 junction 6.
Airport.
Slow moving and queuing traffic is regular
experienced between M56 junctions 7 and 3.
The M56 is used heavily by commuter traffic into and out of Manchester City Centre from
the south and west and continued traffic
growth is resulting in extended peak periods.
Park) and Davenport Green.Davenport Green has been
designated by NWDA as a regional
strategic site.
HS16b Possible widening of M56 junctions 6 to 7. £5m-£50m
(Between £29m
and £34m –
A556 Area Study 2003)
Long Term
H17 Recognition that the growth in Manchester and Liverpool Airports
will not be sustainable if they rely
on the private car.
Manchester Airport Draft Ground Transport
Strategy
Liverpool John Lennon
Airport Surface Access Strategy
Details of all measures proposed to increase the public transport mode share at
Manchester and Liverpool Airports are not
been included in this report, as they are
covered in the respective ground transport strategy documents.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 78 of 150m56_scoping_study_final_report.doc
Table 6.2 - Identified Freight Related Problems and Issues/Transport Measures in the Study Area
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
FP1 In many supply chains, including ‘Just In Time’
systems, transport operators can be tightly
constrained to delivery time slots (by their
customers). In these circumstance the reliability and predictability of journey time can
be more important than minimising journey
time.
M56 Chester to M60 junction 4 has been
identified by members of FTA’s North West
Freight Council as one of the most congested
parts of the regional road network, carrying most of the region’s trade and in most urgent
need of upgrading and further investment.
This section of motorway is ranked 7th in the
FTA’s order of investment priorities for the North West Regional Road Network.
In addition congestion and journey time
reliability are identified as an issue for freight
movements on the cross-border A5117/A550 and A55/A483 routes between the North West
and North Wales. The Silver Jubilee Bridge
and A556(T) are identified as congestion pinchpoints.
North West Regional
Freight Strategy
FTA – North West
Trade Routes
Targeted highway measures are covered in
Table 6.1 above.
FP2 The drivers of freight vehicles are obliged to
take statutory breaks and rest periods as directed by EU drivers’ hours legislation.
There is a concern that the lack of a
comprehensive approach to the provision of
such facilities combined with pressure to develop land for other purposes has resulted
in goods vehicles being forced to park in less
suitable locations.
The Road Haulage Association list the
following truckstops in the study area;
♦ Category A - Poplar 2000 Services at Lymm (M6 Jnc 20, M56 Jnc 9) with 220
spaces, and
♦ Category C – M56 Truckstop at Lower Whitley (M56 Jnc 10, south on A49 to
junction with A533) with 60 spaces
North West Regional
Freight Strategy
M56 CORRIDOR SCOPING STUDY
Final Report
Page 79 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
FP3 It is recognised that road user
charging is under consideration as
a means of managing demand on
the highway network. Concern that the imposition of charges on
goods vehicles, to enter urban
areas in particular, could increase
transport costs with little potential improvements in efficiency.
It is understood that Government is
currently in the process of
developing a distance-basedcharging regime for commercial
vehicles for implementation in
2006, but the likely impact of this is not yet known.
North West Regional
Freight Strategy
FP4 Provision of up-to-date and consistent
direction signing can make a significant contribution to the safe and efficient operation
of the highway network. In addition to the
increased use if inappropriate routes by heavy
goods vehicles, inadequate and inconsistent direction signing can lead to congestion and
increased journey times/distance travelled.
North West Regional
Freight Strategy
FS4 Highway authorities should give high priority
to ensuring that the Primary Route Network direction signing is up-to-date and
consistent. (see HS10)
FP5 Limited use of new technology to provide
better driver information and to co-ordinate
flows.
For example, in the event of the closure of the Kingsway Mersey Tunnel crossing, enhanced
message signs could be used to forewarn hgv
drivers and thereby eliminate the need for a long detour to Silver Jubilee Bridge.
Issue raised at
stakeholder
consultation with FTA
FS5 MerseyTunnels (Merseytravel) and
Liverpool City Council are both seeking to
introducing an enhanced message signing
strategy to provide diversionary information in the event of incidents/ roadworks and
special events.
This strategy could be linked and extend to the adjacent motorway network Particular
application of measure ref. HS3d.
Short Term
FP6 The volume of heavy goods vehicles using the A56 Chester Road to access Whitehouse
Industrial Estate at Preston Brook. The
predominant movement is for good vehicles to
leave the M56 at junction 11 and use the A56 Chester Road.
Halton Borough Council, Local
Transport Plan
Merseyside Freight
Study
FS6 The concept of a new access to the M56 from Whitehouse Industrial Estate, between
junctions 11 and 12, has been put forward in
Halton BC’s LTP. No detailed layout (or
sketch arrangement) has been prepared for the new motorway access.
It should be point out that under current
guidelines there would be a presumption against a new motorway junction with direct
access to a development and in any event it
This scheme can only be considered
as an aspiration at
this stage
Unlikely to be implemented
in the
foreseeable
f uture
M56 CORRIDOR SCOPING STUDY
Final Report
Page 80 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
is unlikely that a new junction be introduced
without a departure from the appropriate
design standards (DMRB Volume 6 Section
2 – TD 22/92).
FS7a West Coast Upgrade proposed to provide
guaranteed timetabled hourly paths south of
Crewe. This will not resolve access to Trafford Park.
Long TermFP7 Restricted train paths on West Coast Main
Line (WCML) for freight limits scope for new
traffic/growth. Particular pinchpoints exist on double track sections south of Warrington
Bank Quay to Crewe. Also freight access to
Trafford Park through Manchester Piccadilly -Deansgate corridor
SRA target of 80% growth in rail
freight will exacerbate problem.
Solutions could include the proposals for Port Salford which
would involve direct access to
WCML via link to Chat Moss route.
Salford Port proposals
from Peel Holdings
FS7b Possible routeing of freight via reinstated Halton Curve to Chester and thence via
Chester and Shrewsbury.
Long Term
FS8a Network of routes cleared to W10 gauge to
accommodate deep sea containers of 9’6’’ height and 2.5m width. Enlargement of
Newton-le-Willows to proposed Port Salford
development to W10 would be key to proposals.
In conjunction with
Network Rail, the SRA is developing
proposals
Medium Term
FS8b The provision of W12 gauge to
accommodate inter-modal units, including swap bodies, for routes serving ports and
Channel Tunnel corridor.
Longer term
aspiration
Long Term
FP8 Restricted loading gauge problem on rail
freight routes. This limits the scope for conveyance of swap body (road-rail trailers) or
high cube containers.
As road haulage industry adopts
higher payload trailers/containersthe problem will become more
restricting without gauge
enhancements
FS8c W18 gauge for key links in the network for
‘piggyback’ trailer operation.
Longer term
aspiration
Long Term
FP9 Suspension of Freight Facilities Grants.Railfreight grants are required to pump prime
possible new entrants such as Vauxhall at
Elllesmere Port.
Suspension of Freight Facilities Grants in 2003 has no end in sight
North West Regional Freight Strategy
FS9 Reinstatement of Freight Facilities Grants Not aware of any timetable to reinstate
FFGs
Short Term
Facilities which provide quick, easy and
affordable means of transferring freight from
road to rail are a key component for encouraging greater use of rail freight for
customers with no direct rail access of their
own. A number of inter-modal terminals,
rail-linked warehouses and distribution centres need to be developed.
FP10 Lack of accessible inter-modal facilities for
customers with no direct rail or water access
of their own.
FS10a
The NWDA designated strategic regional site at Ditton, Widnes is identified as a
strategic rail freight park. The sites lies
to the south of the Liverpool branch of
the WCML and is served by the freight only line to Arpley, Warrington which
A public sector led consortium is
developing the
proposals which
will build on the potential of two
£5m-£100m Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 81 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
serves the Fiddlers Ferry Power Station. existing railfreight
business (Widnes
Intermodal Rail
Depot and Widnes International
Freight Terminal).
FS10b Proposals exist for rail/road/water facilities at Port Salford (Peel Holdings) and Trafford
Interchange (at Carrington).
Medium Term
FS10c New rail/water/road at Ince Marshes
proposed by Peel Holdings which would
enable access between rail, Ship Canal and
M56 to be easily made.
Medium Term
FS11a Reform of system of international route
licensing from regional airports, at Manchester in particular, continues to
constrain the growth of scheduled
international freight and passenger flights.
Recommendation in
North West Freight Strategy
Short Term
FS11b Seek fiscal measure which encourage the
growth of more sustainable air-freight, for
example, provision of more effective grant
regimes for the dev elopment of air freight facilities where appropriate, and by
encouraging the air freight industry to offer
comparable rates for freight with those at London airports
Recommendation in
North West Freight
Strategy
Short Term
FS11c Make best use of exis ting facilities and
explore potential for off-site facilities with appropriate transport links.
Recommendation in
North West Freight Strategy
Long Term
HS16a Improvement in surface transport infrastructure to Manchester Airport (see
HS16a) and relaxation of legal restrictions
on Manchester Airport’s local authority
owners under the Airports Act 1986, as they currently limit business opportunities and
partnerships (for example investment in
public transport) in which the airport can
participate
Recommendation in North West Freight
Strategy
FP11 Manchester Airport and LJLA can both
accommodate a substantial increase in freight throughput without needing a step change in
runway capacity. This should be utilised to
enable more services to be provided to reduce
the need for freight to be moved by road to airports in London and the South East. This is
currently constrained for a variety of reasons
including;
♦ system of international route licensing from Regional Airports
♦ lack of fiscal measures to encourage growth of more sustainable air-freight,
e.g. effective grant regimes
♦ surface access and provision of freight
facilities
FS11d Highway infrastructure improvements to
LJLA , including a new Eastern Access Route from the A561 to the new cargo
Recommendation in
North West Freight Strategy
Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 82 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
development areas.
HS12a New Mersey Crossing but ensure that
proposal takes account of issues of access
to LJLA (see HS12a)
FP12 Concern that ship canal carryings have seen a
long term decline since the 1950’s, though
stability was reached in the1990’s, despite the
availability of the necessary infrastructure.Remaining flows on the ship canal only travel
inland as far as Irlam on a regular basis.
However, the reduction in shipping levels has meant that the three swing bridges in
Warrington no longer open as often as in the
past, but when they do, extensive disruption is
caused. Increased use of the ship canal would therefore have an adverse impact in
Warrington.
Additional Ship Canal development
proposed by Peel Holdings at Port
Salford which could see additional
canal carryings upstream. Could lead to Warrington swing bridges
becoming a key constraint again.
North West Regional
Freight Strategy
Issue raised at
stakeholder
consultation with Warrington BC
FS12 Infrastructure exists to carry substantial
flows of freight for selected cargoes (e.g.
containers, bulks and wastes).
Recommendation in
North West Freight
Strategy
Short Term
Table 6.3 - Identified Passenger Rail Related Problems and Issues/Transport Measures in the Study Area
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where
available
MeasureRef.
Potential Measures Identified of
Documented References and/or
Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS1a Crewe station redevelopment (includingrebuilt concourse, better bus/taxi access,
new car park, remote check-in for
Manchester Airport) in order to fulfil its role
as a key regional hub,
Funding Partners being sought
£5m-£50m
£12.5m (MidMan
Study - 2002)
Short TermRP1 Poor station environment provided at a selection of stations, including Chester,
Crewe, Frodsham and Northwich, which leads
to a discouragement of rail traffic due to fears
of vandalism, personal security.
Social problems are likely to lead to greater vulnerability of stations
to vandalism. Where rail usage
declines vandalism is likely to
increase.
RS1b Major environmental improvements at
Chester rail station, accompanied by bus/rail/car/taxi/cycle interchange
Short Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 83 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS1c Upgrading of all stations to minimum
standards, encompassing information,
security, car/cycle parking, waiting
environment. Focus placed upon current known problems at Frodsham (including
potential park-and-ride), Northwich, and
Runcorn East. Working with Rail User
Groups.
Rail user groups are
promoting cases
improvements.
Short Term
RS2a New chord linking Victoria to Deansgate,
Oxford Road and Piccadilly station, along with improved approaches to Piccadilly
station.
Study currently being
undertaken of ‘Manchester Hub’ to
assess capacity
relief/enhancement
options
Long TermRP2 Poor journey time reliability for rail services in
and through the study area, particularly during the evening peak periods.
Reliability problems are often the result of
problems elsewhere on the rail network, with
Manchester Hub acting as the main bottleneck.
Forecast growth in rail usage will
lead to a greater pressure on existing rail network.
RS3b A new Manchester Airport Rail link (see
RS3b below) could open up opportunities
for alternative routes to Manchester from the south via the Airport for example North
Wales-Manchester Airport-Manchester.
This may then relieve the burden through Deansgate resulting improved journey time
reliability to other services.
RS3a Diversion of current Liverpool -Manchester Airport service via Chat
Moss route will improve journey time and
reliability, but will remove direct link Warrington-Manchester Airport.
Confirmedimplemention
Short Term
Late 2004
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west.
There are no direct services to Manchester
Airport from Chester/North Wales.
Journey times from Liverpool Lime Street to
Manchester Airport are longer than trans-
Pennine journeys from York.
Demand for air access will increase, as will demand upon rail
network capacity.
RS3b Manchester Airport Western Rail Link
including resignalling of the Styal line and additional platforms at Manchester Airport,.
Access by heavy rail from
Liverpool/Chester/North Wales directions.
Also can provide for circular Liverpool-Airport service, connecting Liverpool,
Warrington, Manchester Piccadilly, Airport,
Knutsford, Northwich, Runcorn, South Liverpool Parkway.
Alternatively capacity could possibly be
released through Deansgate resulting in
improved journey time reliability to other services .
Internal audit
undertaken by SRA with no funding
currently allocated to
advance scheme
Current North West Regional Planning
Assessment being
undertaken by SRA to advise on rail
options
More than
£100m
(£370m -
Railtrack 2000
NMS)
Long Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 84 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS3c Upgrade Hartford Station to increase
regional role on WCML by means of greater
service frequency and reinstatement of peak
time London services.
Short Term
RS3d Reopening to passenger services tied in
with Manchester Airport Western Rail link
(see RS3b) and new Liverpool circular service.
In current Cheshire
LTP
Medium Term
RS4a Upgrade of Halton curve to full two-wayworking with associated hourly Chester-
Liverpool via Runcorn rail service
In current Halton LTP £5m-£50m Long Term
RS4b South Liverpool Parkway (Allerton Interchange)
Under construction £5m-£50m
(£15.5m -
Merseyside
LTP APR July 2003)
Short Term
Identified in
LTP for
delivery in 2005/06
RS4c Dedicated high quality bus link between
South Liverpool Parkway and Liverpool Airport and serving The Estuary
development
In current
Merseyside LTP
Less than £5m Short Term
RP4a Potential exists for further improvement in public transport access to Liverpool John
Lennon Airport, with challenging modal shift
targets in Airport’s Surface Access Strategy .
RS4d Merseytram Line 3 between South Liverpool
Parkway and Liverpool Airport and serving
The Estuary development
Merseyside LTP
Annex E submission
due July 2004
More than
£100m
(Latest estimate
for Merseytram Line 1 £225m)
Long Term
RS4e Reopen Ditton Station in conjunction with housing development at Hale Bank
(500/600 houses)
In current Halton LTP Less than £5m Long Term
RS4f New Station at Beechwood In current Halton LTP Less than £5m Long Term
RP4b Poor accessibility and long rail journey times between Chester/Helsby/Frodsham area to
south Liverpool/Liverpool Airport.
Future plans for expansion of Liverpool Airport show increased
demand from Vale Royal/Halton
cross the Mersey to south
Liverpool.
Liverpool John Lennon Surface Access
Strategy
RS4g Electrification Ellesmere Port – Helsby.
Easy extension of current Merseyrail services to Helsby to provide better
connections and serve new housing/industry
at Ince/Elton
Medium Term
RP5 Poor level of service afforded along north-
south axis in mid Cheshire. Limited access
Cheshire CC LTP RS1a Crewe station planned for improved access
point to rail network (see RS1a)
M56 CORRIDOR SCOPING STUDY
Final Report
Page 85 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS5b SRA proposals for new semi-fast
Birmingham-Liverpool/Preston rail
service operated by Central Trains will
open up opportunities for improved service at Hartford/Winsford.
Confirmed
implementation
Short Term
RS5c Reopening of freight only Northwich-
Sandbach line. Would provide scope for diversion of current Crewe/South Wales
services via Manchester Airport and hence
into Piccadilly. (Linked to Western Airport Rail Link see RS3b)
In current Cheshire
LTP
Less than £5m Medium Term
RS5d New station at Middlewich Cheshire LTP Less than £5m Medium Term
points to rail network, with quality of Crewe
station poor in terms of parking, station
environment and interchange with bus/slow
modes.
RS5e Parkway station at M6 Sandbach, to be
served by reopened Middlewich and new
Airport western link trains as well as Wilmslow line trains .
Long Term
RP6a Rail passenger capacity issues on the North-
Cheshire Line (Chester-Warrington-Manchester) during peak periods.
RS6a Increased number of carriages during peak
periods for North Cheshire Line services
Short Term
RP6b Low level of off-peak service f requency on the North-Cheshire Line, currently hourly off -peak.
Issue raised at
stakeholderconsultation with
Cheshire CC
Cheshire CC LTPRS6b Minimum half hourly service In current Cheshire
LTPShort Term
RS7a Minimum half hourly service
Greenbank/Northwich or Knutsford to Manchester with scope for alternating
stopping/semi-fast services
In current Cheshire
LTP
Short Term
RS7b New Mid-Cheshire line Parkway located
near, Lostock Gralam near Northwich. One
option under consideration is to relocate the
station to make it more convenient for a proposed business park in the triangle
created by the convergence of the A556 and
A559 roads.
Feasibility study
recently
commissioned by
Mid-CheshireCommunity Rail
Partnership
Medium Term
RS7c Upgrade route to provide better line speed
to provide better journey times
In current Cheshire
LTP
Medium term
RP7 Poor level of service on the Mid-Cheshire Line
(Chester-Northwich-Manchester), including low line speeds, poor daytime frequencies
(hourly off -peak service) and lack of
interchange facilities.
Cheshire CC LTP
RS7d Use of diesel trams and potentially run them
on Metrolink
Conceptual idea
based on “Diesel
Trams for
Community Railways – AEA Technology ”
Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 86 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS7e Extension of Metrolink to Hale with single
track parallel running to heavy rail line
Has not been
progressed.
Long Term
RS7f New station at Mickle Trafford Has not been progressed.
Less than £5m Unlikely to be progressed
RP8 Inadequate publicity of available rail services including the North-Cheshire and Mid-
Cheshire Lines.
Issue raised at stakeholder
consultation with
Cheshire CC
RS8 Publicity awareness campaign to alert the public of available public transport services
including the North-Cheshire and Mid-
Cheshire Lines.
In current Cheshire LTP
Less than £5m Short Term
RP9 Fare anomalies for medium distance cross-
boundary travel.
Tensions in fares structures at the boundary
between areas where fares are set by PTEs and surrounding areas where fares are set by
the operator with SRA regulation.
As result of these anomalies passengers often choose to park-and-ride to a station within the
PTE area or are dissuaded from using rail at
all.
RS9 Extend PTE multi-modal ticket and fares
baskets to logical travel to work areas (e.g.
to Knutsford/Lostock Gralam by means of
Cheshire buying in to scheme).
Short Term
RS10a Minimum half hourly service In current Cheshire
LTP
Short Term
RS10b Electrification of the line between Bidston
and Woodchurch
Being promoted by
Merseyside PTE
Medium Term
RS10c Full electrification of the Wrexham to Bidston Line
Decrease journey times on the Wrexham -
Bidston line and would allow services to connect with Mersey Rail.
Identified in Queensferry Study.
No progress has
been made.
Long Term
RS10d Increase in line speed on Wrexham-Bidston
line from existing speed of 40-50 mph givinga reduction in journey time
Being promoted by
Flintshire County Council and
Merseyside PTE
Long Term
RP10 Poor level of service on the Wrexham-Bidston
line, and poor access to Deeside Park.
Cheshire CC LTP
Queensferry
Transportation Study
RS10e Provision of new station at Shotton possibly
along with a bus feeder network connecting
the new station with businesses on Deeside
Park
Identified in
Queensferry Study.
No progress has
been made.
Less than £5m
(£0.7m –
Queensferry
Study 2000)
Long Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 87 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
RS10f New chord linking Bidston-Wrexham line to
North Wales Coast line.
Would allow for direct services between
north Wales and the Wirral. If combined with electrification of the Wrexham - Bidston
line would allow for direct services between
north Wales and Liverpool.
Identified in
Queensferry Study.
No progress has
been made.
Long Term
Table 6.4 – Identified Road Based Public Transport Related Problems and Issues/Transport Measures in the Study Area
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
CP1 Lack of high quality road based public
transport services and interchange facilities to
support sustainable development and the
growth of Manchester Airport.
CS1a Regional network of high quality lim ited
express services on specific routes with
high-quality interchange facilities.
Cheshire CC are promoting Cheshire NET –Six express and key inter urban routes
using the motorway and primary route
network with high quality interchanges ;
♦ Manchester - South Manchester -
Manchester Airport Knutsford/Poplar
2000- Warrington South -
Runcorn/Darsebury - Chester
♦ Warrington – Birchwood -
Knutsford/Poplar 2000 - Stoke
♦ Warrington – Birchwood -
Knutsford/Poplar 2000- Macclesfield
♦ Warrington – Birchwood -
Knutsford/Poplar 2000 -
Wilmslow/Congelton - Hanley
♦ Manchester - South Manchester -
Manchester Airport -
Wilmslow/Congleton - Hanley
♦ Manchester – South Manchester -Manchester Airport - Knutsford/Poplar
2000 – Sandbach - Crewe
Interchange points may be park-and-rideonly sites or may also have interchange
facilities with other public transport services.
Further studies are
ongoing
£50
m-£100m
(£87m – Road
Based Public Transport and
Interchange
Strategy)
Short Term/
Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 88 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder
Consultation (Note: evidence base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures Identified of
Documented References and/or Stakeholder Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
Interchange scheme proposals include;
♦ Crewe Rail Gateway
♦ M56/M6 Interchanges at Services and
all junctions
♦ Sandbach Motorway Car Share/Kiss-
and-Ride Facility
♦ Knutsford/Poplar 2000 Area
Interchanges
♦ Mid-Cheshire Line Parkway – eg
Lostock Gralam
♦ Hartford Station Interchange
Enhancement
♦ Winsford Station Interchange
Enhancement
♦ Chester East Interchange and Park-
and-Ride
♦ Ellesmere Port South Interchange and
Park-and-Ride
♦ Halton South Interchange
♦ Warrington South Park-and-Ride
♦ Warrington Bus Station Upgrades
♦ Birchwood Interchange Warringon
♦ South Manchester Interchange
Upgrade (Barlow Moor)
CP2 Poor journey time reliability in Manchester
Airport area of M56 caused by peak time
congestion has led to avoidance of routeings and hence poor level of express coach
services to the airport.
Will get worse with increasing
highway traffic flows in proximity to
airport.
CS2 Manchester Airport strategic approaches
bus priority. Bus lanes (possibly on the hard
shoulder) and selected vehicle detection on strategic approaches to the Airport particular
from the M56.
Medium Term
CS3a Provision of public transport services Short Term
CS3b Fiscal measures to combat exclusion Short Term
CP3 Inadequate public transport provision in the Mersey Dee area (Wirral to Chester and
surrounding area including Deeside
Development Zone) to link people from areas of multiple deprivation to opportunities for
work.
Mersey Dee Alliance Transport Needs and
Accessibility
Improvement Study
CS3c New/improved public transport infrastructure Medium Term
M56 CORRIDOR SCOPING STUDY
Final Report
Page 89 of 150m56_scoping_study_final_report.doc
Table 6.5 – Identified Planning Policy and Land Related Problems and Issues in the Study Area
Problems and Issues Identified in Documented References and/or from Stakeholder Consultation (Note: evidence
base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures
Identified of Documented
References and/or
StakeholderConsultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
LP1 The overriding aim of Regional Planning Guidance for the North
West (RPG13) is to promote sustainable patterns of spatial development and spatial change.
Policies SD1-SD9 set out the Spatial Development Framework for
the North West, where the policies apply to areas/localities where
development and urban renaissance resources need to be focused.It was highlighted that particular regard should be given to Policy
SD1 which deals with the Regional Poles and surrounding areas
within the North West Metropolitan Area.
Regional Planning
Guidance for the North West (RPG13)
Issue raised at
stakeholder
consultation with GONW
LP2 A need to link people from areas of multiple deprivation to
opportunities for work. It is essential that adequate public transport
services are in place to provide this linkage.
Merseyside has a low car ownership with 40% of households without
a car.
Merseyside Local
Transport Plan
LP3 A need to develop the growth of knowledge-based industries in a
sustainable manner. The presumption should be that sites are
located such that the workforce have the best opportunity to make
the journey to work by sustainable forms of transport.
Concern from some stakeholders that the development of
knowledge-based industries adjacent to areas with a relatively low
skill base (those less able to make use of job opportunities) is
perhaps not the most sustainable form of development for these areas, generating longer trips to work than other sectors.
Issue raised at stakeholder
consultation with
Warrington BC
LP4 Concern that the problems of congestion experienced with the Silver Jubilee Bridge are having a negative impact on the local economy,
the Merseyside ERDF objective 1 and Regeneration Priority Area
and the North Cheshire ERDF Objective 2.
New Mersey Crossing Major Scheme
Appraisal
Halton BC Local
Transport Plan
LP5 Concern expressed that more development
in the M56 corridor is not sustainable in terms of north-south movements. In
addition to the pressures on the Silver
Jubilee Crossing there is concern that
development would put increased pressure on the road network in Warrington.
Issue raised at
stakeholderconsultation with
Warrington BC
M56 CORRIDOR SCOPING STUDY
Final Report
Page 90 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder Consultation (Note: evidence
base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures
Identified of Documented
References and/or
Stakeholder
Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
LP6 Manchester International Airport is identified in the RES as a key
contributor to economic regeneration and growth.
The area around Manchester Airport is subject to major business
park development pressures at Manchester Business Park (formerly
known as Woodhouse Park) and Davenport Green. Davenport
Green has been designated by NWDA as a strategic regional site.
Current congestion may detract from the attractiveness of this site to
prospective occupiers, thus constraining its contribution to regional
economic growth.
Major employment growth at Davenport
Green (estimated at 4,300) combined with growth in airport passenger levels and thus
direct airport related employment will lead to
increased traffic levels at this already
pressured location, possibly constraining the potential of each and thus the
achievement of regional economic
objectives.
Manchester Airport have concerns about motorway congestion associated with
adjacent developments.
Regional Economic
Strategy
Mersey Belt Study
LP7 Proposals to widen M6or new M6
expressway ( toll road – extending north
from Birmingham to Manchester between
junctions 11a and junction 19 of the existing M6) and improvements to the A556(T) may
result in induced (and reassigned) traffic
leading to further pressures on this section
of motorway, and M60 between junctions 6 and 12.
There already tensions between strategic
and local traffic on M60 junctions 6 and 12, and increase in traffic as a result of
improvements elsewhere may inhibit the
development potential of UDP allocations in
Salford and Trafford.
Issue raised at
stakeholder
consultation with
AGMA
M56 CORRIDOR SCOPING STUDY
Final Report
Page 91 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder Consultation (Note: evidence
base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures
Identified of Documented
References and/or
Stakeholder
Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
LP8 Liverpool John Lennon Airport is identified
in the RES as a key contributor to economic regeneration and growth. There are
strategic regional sites located adjacent to
the airport site at The Estuary, at Ditton
(Widnes) and Daresbury (Runcorn).
Although congestion is not currently
considered to be a problem in the area this
is qualified by diff iculties at the Silver
Jubilee Bridge linking the area to Runcorn and the M56. Increased traffic levels are
anticipated in future as a result of airport
passenger growth and increased demand
for workers at Liverpool Airport and TheEstuary/Ditton/Daresbury which are likely to
exacerbate problems on the bridge.
As there is no current alternative to road based access to these sites this will restrict
the accessibility of jobs to residents of
identified deprived areas. This contrasts
with the RES objective aim of enabling new jobs to be accessed by people living in
deprived areas.
Regional Economic
Strategy
strategic regional sites,
first monitoring report
Liverpool John Lennon
Airport Surface Access Strategy
LP9 Congestion at Queensferry having negative impact on business perceptions of border areas – but is subject to current improvement
scheme.
LP10 Linkages with North West region identified
as key to economic development of North
Wales. Congestion on approaches to M56
likely to restrict accessibility and thus will constrain opportunities for growth in these
areas (especially in the west, which are
amongst the worst performing areas in Europe – Objective 1) which rely on the
A55(T) for strategic access via the
motorway network to customers & suppliers
in the NW and beyond.
North Wales
Development Strategy
(draft)
Wales Spatial Plan
M56 CORRIDOR SCOPING STUDY
Final Report
Page 92 of 150m56_scoping_study_final_report.doc
Problems and Issues Identified in Documented References and/or from Stakeholder Consultation (Note: evidence
base for problem has not been established in all cases)Prob.
Ref.
Existing Problem and Issue Future Problem and Issue
Documented
References where available
MeasureRef.
Potential Measures
Identified of Documented
References and/or
Stakeholder
Consultation
Status (where
relevant)
Cost Range PotentialTimescale forImplementation
LP11 High travel to work movements across into
England already identified in Flintshire.Future employment and housing growth in
Flintshire focussed around Connah’s Quay,
Deeside and Queensferry, thus likely to
contribute to further increase in journeys in this area, for both leisure activities and work
related travel on both sides of the border.
Wales Spatial Plan
Development Plan Review
LP12 Considerable employment growth anticipated as strategic sites and other large
allocations come forward at Chester (c120
Ha). Population growth anticipated to be slower than in past and this is likely to
require, and encourage, workers to travel
from the surrounding area.
Strategic Regional Sites
Development Plan
Review
LP13 Northwich identified as focus for population
growth in Cheshire. Plans provide for
relatively high employment growth in district
to help reduce high commuting levels. Ifthis doesn’t come forward, commuting will
increase with implications for eastern part of
M56 to access Manchester area.
Road Based Study of
Mid Man Area (PBA)
Development Plan
Review
M56 CORRIDOR SCOPING STUDY
Final Report
Page 93 of 150m56_scoping_study_final_report.doc
7. Relating Identified Problems and Issues to Proposed CorridorStrategy Objectives
7.1 The purpose of this section is to relate the problems and issues identified through document
review and/or from stakeholder consultations to the proposed strategy objectives. It isimportant to stress that a detailed examination of these problems and issue to ascertain the strategic importance of the problem has yet to be undertaken, i.e. there is a need as part of the
next stage in the study to establish whether the problem has genuine regional significance or whether the problem is clouded by perception.
7.2 In undertaking this exercise it was necessary to review and modify the strategy objectives put
forward at inception stage, with the following changes;
♦ the sub-objective “Support the delivery of strategic regional sites and support the growth of
knowledge-based industries in North Cheshire” was broadened to “Support the delivery of strategic regional sites and the growth of existing and target sector industries in the M56
transport corridor”, since it was considered that the original sub-objective was to restrictive to a particular target sector industry.
♦ the separate sub-objectives “Enhance transport network efficiency including public
transport services” and “Improve journey time reliability” were combined into the single sub-objective “Enhance strategic transport network efficiency and improve journey time
reliability including public transport services”, since it was considered that in any qualitative assessment retaining the two original sub-objectives would have resulted in a double counting of benefits.
Table 7.1 - Relating Identified Problems and Issues to Proposed Corridor Strategy Objectives
Proposed Corridor Strategy Objectives
ENABLE ECONOMIC REGENERATION AND DEVELOPMENT IN A MANNER THAT MAXIMISES ACHIEVEMENT OF SUSTAINABILITY OBJECTIVES
Support the delivery of strategic regional sites and the growth of existing and target sector industries in the M56
transport corridor
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better manage highway demand to encourage sustainable development which in part is the responsibility of industry and can be facilitated through measures such as company
travel plans including car sharing incentives and flexible work practices.
For industry to play a part in better managing highway demand and promoting sustainable development through
measures such as company travel plans including car
sharing incentives and flexible work practices.
HP3/FP1 There is a need to make better use of existing infrastructure. A significant proportion of the
regional road network is running at or near capacity, resulting in unreliable journey times,
frustration to drivers and increased cost to industry (as a result of the impact on just-in-timedelivery systems). The impact of inc idents and roadworks exacerbate these problems.
Better use of existing infrastructure would smooth the flow
of traffic and minimise the breakdown of traffic, and
thereby improve journey time reliability and reduce cost to industry.
HP4a/
FP1/LP11
Congestion on the A494(T)/A550(T) between Ewloe Interchange and Welsh/English has a
significant impact on the operational performance of the route. This has a knock-on effect on local and national regeneration initiatives as they have a direct bearing on the perception of this
route as a gateway to/from North Wales and to Deeside Park Industrial Zone, and the reliance of
industry on just-in-time delivery systems. Linkages with the North West region are identified as key to economic development of North Wales. Congestion on approaches to M56 likely to
restrict accessibility and thus will constrain opportunities for growth in these areas which rely on
the A55(T) for strategic access via the motorway network to cus tomers & suppliers in the NW
and beyond.
Improved accessibility to/from North Wales and to
Deeside Park through improved journey time reliability.
Schemes to alleviate problem are included in the
Trunk Road Forward Programme 2002, Welsh
Assembly.
HP5a/
FP1/
LP11
The congestion and delay which arises at the three at -grade junctions on A5117(T)/A550(T)
between M56 and Welsh/English border has a significant impact on the operational performance
of the route. This has a knock-on effect on local and national regeneration initiatives as they have a direct bearing on the perception of this route as a gateway to/from North Wales and to
Deeside Park Industrial Zone, and the reliance of industry on just-in-time delivery systems.
Linkages with North West region identified as key to economic development of North Wales. Congestion on approaches to M56 likely to restrict accessibility and thus will constrain
opportunities for growth in these areas which rely on the A55(T) for strategic access via the
Improved accessibility to/from North Wales and to
Deeside Park through improved journey time reliability.
Scheme to alleviate problem is included in the Highways Agency Targeted Programme of
Improvements.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 94 of 150m56_scoping_study_final_report.doc
motorway network to customers & suppliers in the NW and beyond.
HP9a Delays at the A55(T)/A483(T) Interchange not only affect access to Chester from the south but
also have a negative impact on the development potential of the NWDA designated strategic regional site at Chester Business Park.
Improved accessibility to Chester and Chester Business
Park through reduce delays at the A55(T)/A483/(T) interchange.
HP11 Poor journey time reliability on the M56 between junctions 12 and 14 is currently the result of congestion from the Deeside junctions for westbound traffic and the M56 junction 12 roundabout
for eastbound traffic. These delays are likely to be exacerbated if plans for a new crossing of the
River Mersey proceed. If these problems are not addressed future access from the M56 could
have a negative impact on the local economy and access to the NWDA designated strategicregional sites at Ditton (Widnes) and The Estuary (Speke/Garston).
Ensure that accessibility to the Runcorn area and NWDA designated strategic regional sites at Ditton (Widnes),
Daresbury Park and The Estuary (Speke/Garston) are not
adversely affected in the future.
HP12a/
LP4
Problems of congestion experienced with the Silver Jubilee Bridge are having a negative impact
on the local economy, the Merseyside ERDF objective 1 and Regeneration Priority Area and the North Cheshire ERDF Objective 2, including access to the NWDA designated strategic regional
sites at Ditton (Widnes) and The Estuary (Speke/Garston).
Improved accessibility between the M56 and Merseyside
including access to the NWDA designated strategicregional sites at Ditton (Widnes) and The Estuary
(Speke/Garston).
HP13a Congestion and delays at the A558 Eastern Expressway/A56 Daresbury Bypass roundabout will
have a negative impact on the East Runcorn Development Area including the NWDA designated
strategic regional site at Daresbury Park.
Improved accessibility to the East Runcorn Development
Area including the NWDA designated strategic regional
site at Daresbury Park.
HP14/
LP5
There is concern that further significant development in the M56 corridor will put increased
pressure on the road network in Warrington, particularly for north-south trips in Warrington.
Access to the East Runcorn development area including the strategic regional site at Daresbury Park is already difficult from the north side of Warrington.
Improved accessibility between North Warrington, South
Warrington and Halton (including the NWDA designated
strategic regional site at Daresbury Park).
HP16/
LP7
Congestion and poor journey time reliability on the M56 between junctions 7 and 3 coupled with
the growth of Manchester Airport will hinder the development potential of target sector industries in and around Manchester Airport including Manchester Business Park and the NWDA
designated strategic regional site at Davenport Green.
Improved accessibility to the target sector industries in and around Manchester Airport including ManchesterBusiness Park and the NWDA designated strategic
regional site at Davenport Green.
Highway improvements are required under a Section
278 agreement that formed part of the planningconsent for Davenport Green.
FP10 There is a need to provide inter-modal freight facilities for customers with no direct rail access of their own to encourage a transfer of freight from road to rail/water. Proposals for a strategic rail
freight park at the NWDA designated strategic regional site at Ditton (Widnes) need to be
developed.
Access to inter-modal freight facilities for customers with no direct rail access of their own.
CP1 The lack of high quality road based public transport services and interchange facilities is a
hindrance to sustainable development particularly as many of the strategic regional sites and
industry in the study corridor are poorly served by rail.
Enhanced access to the strategic regional sites and
existing and target sectors industries in the study area by
sustainable means of transport.
CP3 The lack of high quality public transport services preventing people from areas of social exclusion
(often with no household car) access to opportunities for work.
Improved access to the strategic regional sites and
existing and target sectors industries in the study area for
people from areas of social exclusion.
Support the Manchester Regional Pole
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better manage highway demand to encourage sustainable development of the
Manchester Regional Pole which in part is the responsibility of business and can be facilitated through measures such as company travel plans including car sharing incentives and flexible
work practices . There is perhaps also a need to give considerat ion to the reallocation of road
space.
For business to play a part in better managing highway
demand and promoting sustainable development through measures such as company travel plans including car
sharing incentives and flexible work practices.
Consideration to the reallocation of road space encourage
more sustainable road based journeys to work.
HP3 There is a need to make better use of existing infrastructure. A significant proportion of the
regional road network is running at or near capacity, resulting in unreliable journey times,
frustration to drivers and increased cost to industry (as a result of the impact on just -in-timedelivery systems). The impact of inc idents and roadworks exacerbate these problems.
Better use of existing infrastructure would smooth the flow
of traffic and minimise the breakdown of traffic, and
thereby improve journey time reliability and reduce cost to industry.
HP15a/FP1
Congestion on the A556(T) between M6 junction 19 and M56 junctions 7 and 8 has a significant impact on the operational performance of the route. This has a knock-on effect on local and
national regeneration initiatives as they have a direct bearing on the perception of this route as a
gateway to Manchester from the M6 south, and the reliance of industry on just-in-time delivery
systems.
Improved accessibility between Manchester and the M6 south through improved journey time reliability.
HP16/
FP1
Congestion on the M56 between junctions 7 and 3 has a significant impact on the operational
performance of the route. This has a knock-on effect on local and national regeneration initiatives as they have a direct bearing on the perception of this route as a gateway to
Manchester from the south, and the reliance of industry on just -in-time delivery systems. This
section of motorway is ranked 7th in the FTA’s order of investment priorities for the North West
Regional Road Network.
Improved accessibility between Manchester and the M6
south/M56 west through improved journey time reliability.
LP8 The strategic implications that any proposals to improve the M6 and A556(T) may have on the
wider strategic road network need to be explored. There are concerns that strategic
reassignment may increase traffic on the M60 between junctions 6 and 12 may inhibit the development potential of UDP allocations in Salford and Trafford.
Full understanding of the strategic implications that
improvements to the M6 and A556(T) will have on the
wider strategic network.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 95 of 150m56_scoping_study_final_report.doc
RP2 Poor journey reliability of rail services in the study area (the Manchester Hub currently acts as
the main bottleneck) is having a negative impact on the sustainable development of the
Manchester Regional Pole.
Improved journey time reliability of rail services affected
by the Manchester Hub could encourage a transfer from
road to rail and be supportive of the sustainable
development of the Manchester Regional Pole.
RP9 The current rail fare pricing system and structure between the Manchester PTE boundary and
Cheshire encourages railheading and is not supportive of the sustainable development of the
Manchester Regional Pole
A change to the rail fare pricing system and structure
between Manchester PTE boundary and Cheshire could
encourage a transfer from road to rail and be supportive of the sustainable development of the Manchester
Regional Pole.
CP1 The lack of high quality road based public transport services and interchange facilities is not
supportive to sustainable development of Manchester Regional Pole particularly for commuters
for outlying rural areas with poor public transport services.
Improved road based public transport services and
interchange facilities could encourage a transfer from car
only journeys and be supportive of the sustainable
development of the Manchester Regional Pole
Support the growth of Liverpool John Lennon Airport and Manchester International Airport
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better manage highway demand to encourage sustainable development which
in part is the responsibility of both Manchester and Liverpool Airports including the contribution from company travel plans and parking charges/disincentives for “kiss-and-ride” journeys. There
is perhaps also a need to give consideration to the allocation of road space.
For the Airport to play a part in better managing highway
demand and promoting sustainable growth through measures such as company travel plans and parking
charges/disincentives for “kiss-and-ride” journeys.
Consideration to the reallocation of road space to
encourage more sustainable road based journeys to the airports.
HP3 There is a need to make better use of existing infrastructure. A significant proportion of the
regional road network is running at or near capacity, resulting in unreliable journey times, frustration to drivers, with the impact of inc idents and roadworks exacerbating these problems
and can lead to passengers missing flights.
Better use of existing infrastructure to smooth the flow of
traffic and minimise the breakdown of traffic, and thereby improve journey time reliability and access to both
airports.
HP4a Poor journey time reliability on A494(T)/A550(T) between Ewloe Interchange and Welsh/English
border is an issue for the growing number of passengers from North Wales. There are currently
680,000 ppa using Manchester Airport from North Wales.
Improved access to Manchester and Liverpool Airports
from North Wales.
HP5a Poor journey time reliability on A5517(T)/A550(T) between M56 and Welsh/English border is an
issue for the growing number of passengers from North Wales. There are currently 680,000 ppa
using Manchester Airport from North Wales.
Improved access to Manchester and Liverpool Airports
from North Wales.
HP12a Problems of congestion experienced with the Silver Jubilee Bridge will have a negative impact on
the development of Liverpool John Lennon Airport.
Improve surface access to Liverpool Airport from the M56.
HP16/
LP7
Congestion on the M56 between junctions 7 and 3 has a significant impact on the operational
performance of the route. Good surface access to Manchester Airport is essential if it is grow to
its potential of 50mppa, subject to environmental considerations.
Maintain good surface access to Manchester Airport.
Highway improvements are required under a Section
278 agreement that formed part of the planning consent of the second runway public inquiry (to be in
place before passenger throughput exceeds
10,000pph ~ between 30 and 37.5mppa).
HP17 The recognition that the growth in both Manchester and Liverpool Airports will not be sustainable
if reliance is placed on the private car.
An increase in the mode share to Manchester and
Liverpool Airports by sustainable means of transport.
FP11 The under-utilisation of air freight from Manchester and Liverpool Airport thereby is resulting
unnecessary transportation of freight by road to airports in London and the South East.
An increase in the volume of air freight from Manchester
and Liverpool Airports may result in a reduction in freight
carried by road to airports in London and the South East.
RP3 Poor rail access and long journey times to Manchester Airport from the west encourages
journeys by car and does not support the sustainable growth of the airport.
Improved rail access to Manchester Airport from the west
to encourage a transfer from car and be supportive of the
sustainable development of the airport.
Diversion of current Liverpool-Manchester Airport service via Chat Moss route will have some
improvement on journey time and reliability, but will
remove direct link Warrington-Manchester Airport to be implemented late 2004
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon
Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Improved access to Liverpool John Lennon Airport by
public transport to encourage a transfer from car and be supportive of the sus tainable development of the airport.
South Liverpool Parkway (Allerton Interchange) under
construction.
RP4b Poor rail access and long journey times between Chester/Helsby/Frodsham and Liverpool John
Lennon Airport (via Allerton Interchange) encourages journeys by car and does not support the
sustainable development of the airport.
Improved rail access to Liverpool John Lennon Airport
from Chester/Helsby/Frodsham to encourage a transfer
from car and be supportive of the sustainable development of the airport.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 96 of 150m56_scoping_study_final_report.doc
CP1 The lack of high quality road based public transport services and interchange facilities is a
hindrance to the sustainable development of both airports particularly from areas that are poorly
served by rail.
Improved road based public transport services and
interchange facilities could encourage a transfer from car
only journeys and be supportive of the sustainable
development of Manchester and Liverpool Airports.
CP2 Poor journey time reliability in Manchester Airport area of M56 caused by peak time congestion
has led to avoidance of routeings and hence poor level of express coach services to the airport.
Improved journey time reliability of road based public
transport to Manchester Airport to encourage a transfer
from car only and to be supportiv e of the sustainable development of the airport.
Encourage the reduction in the need to travel
ProblemRef
Problem Identified through Document Review and/or from Stakeholder Consultation(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better manage highway demand and encourage the reduction in the need to travel through measures such as the development of telecommunications.
Better management of highway demand should reducethe number of vehicle kilometres travelled.
Enhance strategic transport network efficiency and improve journey time reliability including public transport
services
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better manage highway demand since the regional road network has a finite
capacity and demand already exceeds supply in certain key locations leading to congestion and
problems of journey time reliability to all road users.
Better management of highway demand has the potential
of reducing total travel distance by car and improving
journey time reliability for targeted use.
HP3 A signif icant proportion of the regional road network is running at or near capacity, resulting in
unreliable journey times, frustration to drivers and increased cost to industry. The impact of incidents and roadworks exacerbate these problems.
Better use of existing infrastructure would smooth the flow
of traffic and minimise the breakdown of traffic, and thereby improve journey time reliability.
HP4a Poor journey time reliability on A494(T)/A550(T) through Queensferry and Dees ide. This section
is running at or near capacity during the peak periods. The duration of the peak period is increasing as drivers alter their travel times to reduce delays. Congestion on the trunk road is a
frequent occurrence and is severe at times. Tourism in North Wales is a major employer,
currently 3.8 million visitors per annum to the area access via the M56, increased congested
would have a detrimental impact on the growth of this industry.
Improved journey time reliability to all road users.
Schemes to alleviate problem are included in the Trunk Road Forward Programme 2002, Welsh
Assembly
HP5a Poor journey time reliability on A5517(T)/A550(T) between M56 and Welsh/English border.
Average speeds speed of 40mph in the peak as result of insufficient junctions capacity. In the inter peak average speeds still only reach 55mph as a result of the high proportion of heavy
goods vehicles and slow moving agricultural vehicles . Tourism in North Wales is a major
employer, currently 3.8 million visitors per annum to the area access via the M56, increased
congested would have a detrimental impact on the growth of this industry.
Improved journey time reliability to all road users.
Scheme to alleviate problem is included in the Highways Agency Targeted Programme of
Improvements.
HP7 The absence of an efficient active traffic management system at the M53/M56 Stoak Interchange
results in unnecessary delays to drivers bound for North Wales during peak congestion when a suitable alternative route is available. Tourism in North Wales is a major employer, currently 3.8
million visitors per annum to the area access via the M56, increased congested would have a
detrimental impact on the growth of this industry.
Improved journey time reliability to all road users.
HP9a Delays are regularly experienced at the A55(T)/A483(T) Interchange south of Chester during the
peak periods.
Improved journey time reliability to all road users.
HP10a Delays on the A51 east of Chester frequently occur during the peak periods as a result of
overcapacity at A51/A55 and A51/A41 junctions.
Improved journey time reliability to all road users.
HP11 Journey time reliability is an issue on the M56 between junctions 12 and 14. Flow breakdown in the westbound direction is often the result of queuing traffic back from the Deeside junctions.
Delays in the eastbound direction can extend back from the A557/M56 junction 12 Clifton
Interchange. As a result there can be a transfer of traffic to the already heavily trafficked A56
through the villages of Helsby and Frodsham.
Improved journey time reliability and a reduction in the amount of traffic that diverts to the A56 through the
villages of Helsby and Frodsham.
HP12a Delays on the approaches to the Silver Jubilee Bridge are a regular occurrence during the
extended peak periods. These delays also affect the reliability of bus services . Queues of up to 1.5km are regularly experienced on the Expressway approaches.
Reduced delays on the approaches to the Silver Jubilee
Bridge, and improvements to the reliability of bus services.
HP12c Delays of 10 minutes are frequently experienced on the A557 Weston Point Expressway at
Clifton Hall for southbound traffic heading for M56 junction 12.
Reduced delays for southbound traffic heading for the
M56 at junction 12.
HP15a Poor journey time reliability on the A556(T) between M6 junction 19 and M56 junction 7. This
section of trunk road is running at capacity during extended peak periods.
Improved journey time reliability to all road users.
HP15d Congestion on the A556(T) has resulted in a transfer of traffic on to alternative parallel routes
such as the A535 and A34.
Improvements to the A556(T) may reduce the amount of
strategic traffic transferring from the A556(T) to alternative
parallel routes such as the A535 and A34.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 97 of 150m56_scoping_study_final_report.doc
HP16 Poor journey time reliability on the M56 between junctions 7 and 3. Between M56 junctions 4
and 3 (the A5103 Princess Parkway) the motorway is operating in excess of its operating
capacity in the morning and evening peak periods a problem that is compounded by heavy
weaving movements such as M56 East (e.g. Stockport) traffic heading for M56 West (e.g. Birmingham) conflicting with Princess Parkway traffic heading for Wythenshawe and Manchester
Airport.
Slow moving and queuing traffic is regular experienced between M56 junctions 7 and 3. The
M56 is used heavily by commuter traffic into and out of Manchester City Centre from the south and west and continued traffic growth is resulting in extended peak periods.
Improved journey time reliability to all road users.
FP4 Provision of up-to-date and consistent direction signing can make a significant contribution to the efficient operation of the highway network. In addition to the increased use if inappropriate
routes by heavy goods vehicles, inadequate and inconsistent direction signing can lead to
congestion and increased journey times/distance travelled.
A reduction in unnecessary journey time/distance travelled.
FP5 Limited use of new technology to provide better driver information and to co-ordinate flows. For
example, in the event of the closure of the Kingsway Mersey Tunnel crossing, enhanced
message signs could be used to forewarn hgv drivers and thereby eliminate the need for a long
detour to Silver Jubilee Bridge.
Increased use of new technology to provide better driver
information and co-ordinate traffic flow.
RP2 Poor journey time reliability for rail services in and through the study area, particularly during the
evening peak periods.
Reliability problems are often the result of problems elsewhere on the rail network, with
Manchester Hub acting as the main bottleneck.
Improved journey reliability of rail services in the study
area.
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west. There are nodirect services to Manchester Airport from Chester/North Wales. Journey times from Liverpool
Lime Street to Manchester Airport are longer than trans-Pennine journeys from York.
Improved rail access and reduced journey times to Manchester Airport from the west.
Diversion of current Liverpool -Manchester Airport
service via Chat Moss route will have someimprovement journey time and reliability, but will
remove direct link Warrington-Manchester Airport to
be implemented late 2004
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon
Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Improved access and reduced journey times to Liverpool
John Lennon Airport by public transport.
South Liverpool Parkway (Allerton Interchange) under
construction.
RP4b Poor accessibility and long rail journey times between Chester/Helsby/Frodsham area to south
Liverpool/Liverpool Airport.
If required improved rail access and reduced journey
times between Chester/Helsby/Frodsham and south Liverpool/Liverpool John Lennon Airport (via Allerton
Interchange)
Encourage mode shift from car where feasible
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 There is a need to better mange highway demand and discourage use by car with the aim of supporting sustainable transport objectives.
Better management of highway demand through measure that discourage use by car.
RP1 Poor station environment provided at a selection of stations, including Chester, Crewe, Frodsham and Northwich, which leads to a discouragement of rail traffic due to fears of
vandalism, personal security.
Improved rail station environment could reduce personal security concerns and could contribute towards a mode
shift from car.
RP2 Poor journey time reliability for rail services in and through the study area, particularly during theevening peak periods.
Reliability problems are often the result of problems elsewhere on the rail network, with
Manchester Hub acting as the main bottleneck.
Improved journey reliability of rail services in the study area could encourage a mode shift from car.
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west. There are no
direct services to Manchester Airport from Chester/North Wales. Journey times from Liverpool
Lime Street to Manchester Airport are longer than Trans-Pennine journeys from York.
Improved rail access and reduced journey times to
Manchester Airport from the west could encourage a
mode shift from car.
Diversion of current Liverpool -Manchester Airport
service via Chat Moss route will have some
improvement on journey time and reliability, but will remove direct link Warrington-Manchester Airport to
be implemented late 2004.
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Improved access to Liverpool John Lennon Airport by public transport could encourage a mode shift from car.
South Liverpool Parkway (Allerton Interchange) under
construction.
RP4b Poor accessibility and long rail journey times between Chester/Helsby/Frodsham area to south
Liverpool/Liverpool Airport.
If required improved rail access and reduced journey
times between Chester/Helsby/Frodsham and south
Liverpool/Liverpool John Lennon Airport (via Allerton Interchange) could encourage a mode shift from car
M56 CORRIDOR SCOPING STUDY
Final Report
Page 98 of 150m56_scoping_study_final_report.doc
RP5 Poor level of service afforded along north-south axis in mid Cheshire. Limited access points to
rail network, with quality of Crewe station poor in terms of parking, station environment and
interchange wi th bus/slow modes.
Improved accessibility to rail services along a north-south
corridor in mid Cheshire could encourage a mode shift
from car.
New semi-fast Birmingham-Liverpool/Preston rail service operated by Central Trains confirmed open up
opportunities for improved service at
Hartford/Winsford
RP6a Rail passenger capacity issues on the North-Cheshire Line (Chester-Warrington-Manchester)
during peak periods.
If required increased rail passenger capacity for services
using the North-Cheshire Line during the peak periods
could encourage a mode shift from car.
RP6b Poor daytime frequencies on the North-Cheshire Line, currently a hourly off-peak service is
provided.
Appropriate level of service frequencies for the North-
Cheshire line to encourage a mode shift from car.
RP7 Poor level of service on the Mid-Cheshire Line (Chester-Northwich-Manchester), including low
line speeds, poor daytime frequencies (hourly off -peak service) and lack of interchange facilities .
If required improved level of service on the Mid-Cheshire
Line, could encourage a mode shift from car.
RP8 Inadequate publicity of available rail services including the North-Cheshire and Mid-Cheshire
Lines.
Improved publicity awareness of available public transport
services could assist in encouraging a mode shift from
car.
RP9 Fare anomalies for medium distance cross-boundary travel. Tensions in fares structures at the
boundary between areas where fares are set by PTEs and surrounding areas where fares are
set by the operator with SRA regulation As result of these anomalies passengers often choose to park-and-ride to a station within the PTE area or are dissuaded from using rail at all.
A change to the rail fare pricing system and structure
between Manchester PTE boundary and Cheshire could
encourage a transfer from road to rail.
RP10 Poor level of service on the Wrexham-Bidston line, and poor access to Deeside Park. If required improv ed level of service on the Wrexham-
Bidston Line and rail access to Deeside Park and/or improvements to road based PT could encourage a mode
shift from car.
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services with high quality
interchange facilities could encourage a mode shift from
car only trips
CP2 Poor journey time reliability in Manchester Airport area of M56 caused by peak time congestion
has led to avoidance of routeings and hence poor level of express coach services to the airport.
Improved journey time reliability to Manchester Airport by
road based public transport could encourage a mode shift
from car.
Encourage a shift of freight from road to other modes where feasible
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
FP7 Restricted train paths on West Coast Main Line for freight limits scope for new traffic/growth.
Particular pinchpoints exist on double track sections south of Warrington Bank Quay to Crewe.
Also freight access to Trafford Park through Manchester Piccadilly -Deansgate corridor
If required changes to the physical network to increase
train paths on West Coast Main Line for freight could
encourage a shift of freight from road to rail
FP8 Restricted loading gauge problem on rail freight routes. This limits the scope for conveyance of
swap body (road-rail trailers) or high cube containers.
If required removal of loading gauge problems on rail to
enable scope for conveyance of swap body or high cube
containers could encourage a shift of freight from road to rail.
FP9 Suspension of Freight Facilities Grants. A reinstatement of Freight Facilities Grants could help topump prime possible new entrants and could thereby
encourage a shift of freight from road to rail.
FP10 Lack of accessible inter-modal facilities for customers with no direct rail or water access of their own.
The provision of inter-modal freight f acilities could encourage a shift of freight from road to rail/water.
A public sector led consortium is developing
proposals for the Ditton Strategic Rail Freight Par.Following a Public Inquiry held in 2003 the Inspector
has supported the development. Ditton is a NWDA
designated strategic regional site.
FP11 Manchester Airport and LJLA can both accommodate a substantial increase in freight throughput
without needing a step change in runway capacity. This should be utilised to enable more
services to be provided to reduce the need for freight to be moved by road to airports in London
and the South East. This is currently constrained for a variety of reasons including;
♦ system of international route licensing from Regional Airports
♦ lack of fiscal measures to encourage growth of more sustainable air-freight, e.g. effective grant regimes
♦ surface access and provision of freight facilities
Increased volume of freight through Manchester and
Liverpool Airport could reduce the need for freight to be
moved by road to airports in London and the South East.
FP12 Concern that ship canal carryings have seen a long term decline since the 1950’s, though stability was reached in the1990’s, despite the availability of the necessary infrastructure.
Remaining flows on the ship canal only travel inland as far as Irlam on a regular basis.
Better use of the Manchester Ship Canal and Weaver Navigation to carry freight for selected cargoes such as
containers, bulks and waste, could encourage a shift of
freight from road to water transport.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 99 of 150m56_scoping_study_final_report.doc
ENHANCE ACCESSIBILITY AND IN PARTICULAR TO AREAS SERVED BY THE CORRIDOR SUFFERING FROM SOCIAL
EXCLUSION INCLUDING MERSEYSIDE, EAST MANCHESTER, HALTON AND ELLESMERE PORT AND NESTON
Improve access for non-car users
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west. There are no
direct services to Manchester Airport from Chester/North Wales. Journey times from Liverpool
Lime Street to Manchester Airport are longer than trans-Pennine journeys from York.
Improved rail access for non-car users to Manchester
Airport from the west.
Diversion of current Liverpool -Manchester Airport service via Chat Moss route will have some
improvement on journey time and reliability, but will
remove direct link Warrington-Manchester Airport to
be implemented late 2004.
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon
Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Improved access for non-car users to Liverpool John
Lennon Airport by public transport.
South Liverpool Parkway (Allerton Interchange) under
construction.
RP4b Poor accessibility and long rail journey times between Chester/Helsby/Frodsham area to south Liverpool/Liverpool Airport.
If required improved rail access for non-car users between Chester/Helsby/Frodsham and south Liverpool/Liverpool
John Lennon Airport (via Allerton Interchange)
RP5 Poor level of service afforded along north-south axis in mid Cheshire. Limited access points to
rail network, with quality of Crewe station poor in terms of parking, station environment and
interchange with bus/slow modes.
Improved accessibility to rail service along a north-south
corridor in mid Cheshire.
New semi-fast Birmingham-Liverpool/Preston rail
service operated by Central Trains confirmed open up opportunities for improved service at
Hartford/Winsford
RP10 Poor level of service on the Wrexham-Bidston line, and poor access to Deeside Park. If required improved level of service on the Wrexham-Bidston Line and rail access to Deeside Park and/or
improvements to road based PT.
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services with high quality
public transport interchange facilities could improve
access for non-car users.
CP2 Poor journey time reliability in Manchester Airport area of M56 caused by peak time congestion
has led to avoidance of routeings and hence poor level of express coach services to the airport.
An improved level of service and improving journey time
reliability to Manchester Airport by road based public
transport could improve access for non-car users
CP3 Inadequate public transport provision in the Mersey Dee area (Wirral to Chester and surrounding
area including Deeside Development Zone) to link people from areas of social exclusion to
opportunities for work.
The provision of good public transport provision to link
people from areas of social exclus ion to opportunities for
work could improve access for non-car users.
Increase transport choice in rural areas
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west. There are no
direct services to Manchester Airport from Chester/North Wales. Journey times from LiverpoolLime Street to Manchester Airport are longer than trans-Pennine journeys from York.
Improv ing rail ac cess to Manchester Airport from the west
may increase transport choice in rural.
Diversion of current Liverpool -Manchester Airport
service via Chat Moss route will have some
improvement on journey time and reliability, but will
remove direct link Warrington-Manchester Airport to be implemented late 2004.
RP5 Poor level of service afforded along north-south axis in mid Cheshire. Limited access points to
rail network, with quality of Crewe station poor in terms of parking, station environment and interchange with bus/slow modes.
Improved accessibility to rail service along a north-south
corridor in mid Cheshire may increase transport choice in rural areas.
New semi-fast Birmingham-Liverpool/Preston rail
service operated by Central Trains confirmed open up opportunities for improved service at
Hartford/Winsford
RP7 Poor level of service on the Mid-Cheshire Line (Chester-Northwich-Manchester), including low line speeds, poor daytime frequencies (hourly off -peak service) and lack of interchange facilities .
If required improved level of service on the Mid-CheshireLine, may increase transport choice in rural areas.
RP10 Poor level of service on the Wrexham-Bidston line, and poor access to Deeside Park. If required improved level of service on the Wrexham-Bidston Line and rail access to Deeside Park may
increase transport choice in rural areas and/or
improvements to road based PT.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 100 of 150m56_scoping_study_final_report.doc
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services with high quality
public transport interchange facilities may increase
transport choice in rural areas
Improve interchange between transport modes
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
RP1 Poor station environment provided at a selection of stations, including Chester, Crewe,
Frodsham and Northwich, which leads to a discouragement of rail traffic due to fears of
vandalism and personal security.
An improved rail station environment and improved
interchange facilities may reduce fears of vandalism and
personal security.
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon
Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Provision of high quality interchange facilities at South
Liverpool Parkway (Allerton) for improved access to
Liverpool John Lennon Airport by public transport.
South Liverpool Parkway (Allerton Interchange) under
construction.
RP7 Poor level of service on the Mid-Cheshire Line (Chester-Northwich-Manchester), including low line speeds, poor daytime frequencies (hourly off -peak service) and lack of interchange facilities .
If required improved level of service on the Mid-CheshireLine.
RP10 Poor level of service on the Wrexham-Bidston line, and poor access to Deeside Park. If required improved rail access to Deeside Park and/orimprovements to road based PT.
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services and high quality
interchange facilities.
ENHANCE THE IMAGE OF THE M56 TRANSPORT CORRIDOR
Improvements to and enhanced management of Trans-European Network
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP1 The M56 east of M6 is not part of Trans-European Network Routes even though both
Manchester Airport and Liverpool John Lennon Airport are a part of TENs.
Including the M56 (east of M6) as part of Trans European
Network Route, given that it is the highway link to
Manchester Airport which is a part of TENs. Review the status of A556(T) as it also forms part of the main
approach to Manchester Airport from M6 south.
HP2 The regional road network has a finite capacity and that demand already exceeds supply in
certain key locations leading to congestion and problems of journey time reliability to all road
users.
Schemes to better manage highway demand.
HP3 A signif icant proportion of the regional road network is running at or near capacity, resulting in
unreliable journey times, frustration to drivers and increased cost to industry. The impact of
incidents and roadworks exacerbate these problems.
Schemes to make better use of existing highway
infrastructure.
HP4 Congestion is a problem on the A494(T)/A550(T) through Queensferry and Deeside. This
section is running at or near capacity during the peak periods .
Improvements to the A494(T)/A550(T) between Ewloe
Interchange and Welsh/English border.
Schemes to alleviate problem are included in the Trunk Road Forward Programme 2002, Welsh
Assembly
HP5 Congestion and delays at the three at -grade junctions on A5117(T)/A550(T) between the end of
the M56 and the Welsh border
Improvements to the A550(T)/A5117(T) between M56 and
Welsh/English border.
Scheme to alleviate problem is included in the
Highways Agency Targeted Programme of Improvements.
HP7 The absence of an efficient active traffic management system at the M53/M56 Stoak Interchange
results in unnecessary delays to drivers bound for North Wales during peak congestion when a suitable alternative route is available
Introduction of active traffic management at the M53/M56
Stoak Interchange.
HP9 Congestion and delays at the A55(T)/A483(T) interchange to the south of Chester Major junction improvements to the A55(T)/A483(T)Interchange.
FP7 Restricted train paths on West Coast Main Line for freight limits scope for new traffic/growth.
Particular pinchpoints exist on double track sections south of Warrington Bank Quay to Crewe.Also freight access to Trafford Park through Manchester Piccadilly -Deansgate corridor
If required changes to the physical network to increase
train paths on West Coast Main Line for freight.
RP2 Poor journey time reliability for rail services in and through the study area, particularly during theevening peak periods.
Reliability problems are often the result of problems elsewhere on the rail network, with
Manchester Hub acting as the main bottleneck.
If required changes to the physical rail network.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 101 of 150m56_scoping_study_final_report.doc
Improve perception of personal security for public transport journeys
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
RP1 Poor station environment provided at a selection of stations, including Chester, Crewe,
Frodsham and Northwich, which leads to a discouragement of rail traffic due to fears of
vandalism, personal security.
An improved rail station environment and improved
interchange facilities may reduce fears of vandalism and
personal security.
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services with high quality
interchange facilities may assist in improving the perception of personal security for public transport
journeys.
Improve road safety
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 The regional road network has a finite capacity and that demand already exceeds supply in certain key locations leading to congestion and problems of journey time reliability to all road
users.
Better management of highway demand could reduce the number of vehicle kilometres travelled and hence a
reduction in accidents
HP3 A signif icant proportion of the regional road network is running at or near capacity, resulting in
unreliable journey times, frustration to drivers and increased cost to industry. The impact of
incidents and roadworks exacerbate these problems.
Better use of existing highway infrastructure may smooth
traffic flow and minimise the breakdown of traffic which
should result in a reduction of accidents.
HP4b Safety issues on the A494(T)/A550(T) through Queensferry and Deeside. The accident rate on
this section is above the national average and four times higher in places.
Improved safety on A494(T)/A550(T) between Ewloe
Interchange and Welsh/English border.
Schemes to alleviate problem are included in the
Trunk Road Forward Programme 2002, Welsh Assembly
HP5b Safety issues on A5117(T)/A550(T) between the end of the M56 and the Welsh border – last three remaining at -grade junctions on E22 in England. All three junctions have existing road
safety problems.
♦ A550(T)/A5117(T) traffic signals most heavily trafficked section of the A550(T), with poor accident record, associated with high approach speeds and queuing traffic give rise to high
number of shunts and loss of control accidents
♦ A5117(T)/A540 roundabout long queues develop at peak times affecting both the A5117(T)and A540. High approach speeds coupled with poor deflection, particularly for westbound
traffic gives rise to high number of shunts and loss of control accidents.
A5117(T)/M56 high approach speeds in particular on the A5117(T) eastbound and M56 approaches, coupled with substandard alignment on the M56 approach are cited as the cause of
accidents at this junction.
Improved safety on A5517(T)/A550(T) between M56 and Welsh/English border.
Scheme to alleviate problem is included in the
Highways Agency Targeted Programme of
Improvements.
HP9b Safety at the A55(T)/A483(T) interchange is a concern. Improved safety at the A55(T)/A483(T) Interchange south
of Chester.
HP12b The Silver Jubilee Bridge was opened in 1961 as a three lane single carriageway but in 1977 it was widened to four lanes of substandard width with poor facilities for pedestrians and no safe
facilities for cyclists.
The poor standard of the Bridge contributes to the poor road accident rate in Halton – at 0.128% of the population, the number killed or seriously injured on Halton’s roads is twice the national
average.
Improved safety in the vicinity of the Silver Jubilee Bridge.
HP15b Safety issues on the A556(T) between M6 junction 19 and M56 junction 7, include; speeding drivers; narrow carriageway widths; right turning problems for numerous side-roads, private
frontages and filed accesses.
Improved safety on the A556(T) between M6 junction 19 and M56 junctions 7 and 8.
FP2 The drivers of freight vehicles are obliged to take statutory to take statutory breaks and rest
periods as directed by EU drivers’ hours legislation. There is a concern that the lack of
comprehensive approach to the provision of such facilities combined with pressure to develop
land for other purposes has resulted in goods vehicles being forced to park in less suitable locations.
The Road Haulage Association list the following truckstops in the study area;
♦ Category A - Poplar 2000 Services at Lymm (M6 Jnc 20, M56 Jnc 9) with 220 spaces, and
♦ Category C – M56 Truckstop at Lower Whitley (M56 Jnc 10, south on A49 to junction with
A533) with 60 spaces
Adequate facilities for hgv drivers to take statutory breaks
and rest periods as directed by EU drivers’ hours
legislation.
FP4 Provision of up-to-date and consistent direction signing can make a significant contribution to the
safe and efficient operation of the highway network. In addition to the increased use if inappropriate routes by heavy goods vehicles, inadequate and inconsistent direction signing can
lead to congestion and increased journey times/distance travelled.
Ensuring that direction signing is up-to-date and
consistent . If it isn’t improved signing could reduceunnecessary distances travelled possibly leading to a
reduced number of accidents.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 102 of 150m56_scoping_study_final_report.doc
MANAGEMENT OF NATURAL, BUILT AND HISTORIC ENVIRONMENT WITHIN THE M56 TRANSPORT CORRIDOR
Minimise the impacts of transport upon the built and natural environment
ProblemRef
Problem Identified through Document Review and/or from Stakeholder Consultation(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 The regional road network has a finite capacity and that demand already exceeds supply in
certain key locations leading to congestion and problems of journey time reliability to all road users.
Better management of highway demand could reduce
demand and smooth traffic flows.
HP15c Environmental issues on the A556(T) between M6 junction 19 and M56 junction 7, include; pollution of air, noise, and water quality from heavy volumes of traffic.
Reduced impact of traffic on water quality on the A556(T)between M6 junction 19 and M56 junctions 7 and 8.
Minimise the impacts of transport upon emissions
ProblemRef
Problem Identified through Document Review and/or from Stakeholder Consultation(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
HP2 The regional road network has a finite capacity and that demand already exceeds supply in
certain key locations leading to congestion and problems of journey time reliability to all road users.
Better management of highway demand (including the
contribution from telecommunications) could reduce the number of vehicle kilometres travelled and reduce total
vehicle emissions.
HP9c Environmental issues at the A55/A483 interchange are also a concern. Reduced noise and air pollution at the A55(T)/A483(T)
Interchange south of Chester.
HP15c Environmental issues on the A556(T) between M6 junction 19 and M56 junction 7, include; pollution of air, noise, and water quality from heavy volumes of traffic.
Reduced noise and air pollution on the A556(T) between M6 junction 19 and M56 junctions 7 and 8.
Encourage the use of environmentally sustainable modes of transport such as walking, cycling and public
transport
Problem
Ref
Problem Identified through Document Review and/or from Stakeholder Consultation
(Note: evidence base for problem has not been established in all cases)
Possible Outcome From Any Mitigation Measures
RP1 Poor station environment provided at a selection of stat ions, including Chester, Crewe,
Frodsham and Northwich, which leads to a discouragement of rail traffic due to fears of vandalism, personal security.
An improved rail station environment may reduce
personal security concerns and could encourage increased use of environmentally sustainable modes of
transport (rail).
RP2 Poor journey time reliability for rail services in and through the study area, particularly during the evening peak periods.
Reliability problems are often the result of problems elsewhere on the rail network, with
Manchester Hub acting as the main bottleneck.
Improved journey reliability of rail services in the study area could encourage increased use of environmentally
sustainable modes of transport (rail).
RP3 Poor accessibility and long rail journey times to Manchester Airport from the west. There are no
direct services to Manchester Airport from Chester/North Wales. Journey times from Liverpool
Lime Street to Manchester Airport are longer than trans-Pennine journeys from York.
Improved rail access and reduced journey times to
Manchester Airport from the west could encourage
increased use of environmentally sustainable modes of transport (rail).
Diversion of current Liverpool -Manchester Airport
service via Chat Moss route will have some
improvement on journey time and reliability, but will remove direct link Warrington-Manchester Airport to
be implemented late 2004.
RP4a Potential exists for further improvement in public transport access to Liverpool John Lennon
Airport, with challenging modal shift targets in Airport’s Surface Access Strategy .
Improved access to Liverpool John Lennon Airport by
public transport could encourage increased use of
environmentally sustainable modes of transport
(bus/tram/rail).
South Liverpool Parkway (Allerton Interchange) under
construction.
RP4b Poor accessibility and long rail journey times between Chester/Helsby/Frodsham area to south Liverpool/Liverpool Airport.
Improved rail access and reduced journey times between Chester/Helsby/Frodsham and south Liv erpool/Liverpool
John Lennon Airport (via Allerton Interchange) could
encourage increased use of environmentally sustainable modes of transport (bus/tram/rail).
RP5 Poor level of service afforded along north-south axis in mid Cheshire. Limited access points to
rail network, with quality of Crewe station poor in terms of parking, station environment and interchange with bus/slow modes.
Improved accessibility to rail service along a north-south
corridor in mid Cheshire could contribute towards a mode shift f rom car.
New semi-fast Birmingham-Liverpool/Preston rail
service operated by Central Trains confirmed open up
opportunities for improved service at Hartford/Winsford
M56 CORRIDOR SCOPING STUDY
Final Report
Page 103 of 150m56_scoping_study_final_report.doc
RP6a Capacity issues on the North-Cheshire Line (Chester-Warrington-Manchester) during peak
periods.
Increased rail passenger capacity for services using the
North-Cheshire Line during the peak periods would
contribute towards increased use of environmentally
sustainable modes of transport (rail).
RP6b Poor daytime frequencies on the North-Cheshire Line, currently a hourly off-peak service is
provided.
If required increased rail passenger capacity for services
using the North-Cheshire Line during the peak periods
could contribute towards increased use of environmentally sustainable modes of transport (rail).
RP7 Poor level of service on the Mid-Cheshire Line (Chester-Northwich-Manchester), including low line speeds, poor daytime frequencies (hourly off -peak service) and lack of interchange facilities .
If required improved level of service on the Mid-CheshireLine, could contribute towards increased use of
environmentally sustainable modes of transport (rail).
RP8 Inadequate publicity of available rail services including the North-Cheshire and Mid-CheshireLines.
Improved public awareness of av ailable public transport services could assist in encouraging increased use of
environmentally sustainable modes of transport (rail).
RP9 Fare anomalies for medium distance cross-boundary travel. Tensions in fares structures at the
boundary between areas where fares are set by PTEs and surrounding areas where fares are
set by the operator with SRA regulation As result of these anomalies passengers often choose
to park-and-ride to a station within the PTE area or are dissuaded from using rail at all.
A change to the rail fare pricing system and structure
between Manchester PTE boundary and Cheshire may
reduce railheading and contribute towards use of
environmentally sustainable modes of transport (rail).
RP10 Poor level of service on the Wrexham-Bidston line, and poor access to Deeside Park. If required improv ements to the level of service on the
Wrexham-Bidston Line and rail access to Deeside Park and/or improvements to road based PT may encourage
use of environmentally sustainable modes of transport
(rail/bus)
CP1 Lack of high quality road based public transport services and interchange facilities to support
sustainable development and the growth of Manchester Airport.
Improved bus/coach express services with high quality
interchange facilities could encourage use of
environmentally sustainable modes of transport (bus)
CP2 Poor journey time reliability in Manchester Airport area of M56 caused by peak time congestion
has led to avoidance of routeings and hence poor level of express coach services to the airport.
Improved journey time reliability to Manchester Airport by
road based public transport could encourage use of
environmentally sustainable modes of transport (bus)
CP3 Inadequate public transport provision in the Mersey Dee area (Wirral to Chester and surrounding
area including Deeside Development Zone) to link people from areas of social exclusion to
opportunities for work.
Improved public transport provision to link people from
areas of social exclusion to opportunities for work could
encourage increase use of environmentally sustainable modes of transport (bus/rail).
M56 CORRIDOR SCOPING STUDY
Final Report
Page 104 of 150m56_scoping_study_final_report.doc
8. The Way Forward
INTRODUCTION
8.1 This report presents the outcome of the first stage in the processes of a multi-modal study. The work undertaken has sought to identify the scope of the M56 corridor study area and to identify
the key problems and issues within that study area, through a process of document reviews and stakeholder consultation. At this stage the work has not sought to ascribe any applicability of potential solutions/measures to the identified problems, nor to allocate a weight to the
magnitude of these problems.
8.2 This section considers the outputs of this Scoping Study, and then looks forward as to how the
study process should be progressed, addressing the known areas of insufficient knowledge as identified by the study. Following on from this the chapter will set out the recommended newdata collection requirements and potential modelling and appraisal methodology.
M56 CORRIDOR STUDY AREA
8.3 The study brief defined the M56 corridor study area to be the area bordered by the Cheshire County Council/Wirral Metropolitan Borough Council boundary and the RiverMersey/Manchester Ship Canal to the north, the A5103(T) south from M60 to M56 to the east,
the M56 from junction 1 to junction 7 including Manchester Airport and the A556/A54/A51/A55 south of Northwich and Chester to the Welsh Border. The western limit of the study area wasdefined by the boundary between England and Wales.
8.4 It is our recommendation that the study area should be extended to logical transport decision points. For this reason the study area has been extended into the Wirral to encompass M53
junctions 5 and 6, and into Wales to encompass the A55(T)/A494(T) Ewloe Interchange. Forthe purpose of this study it is considered that the English/Welsh border that dissects the study area is not relevant with respect to the operation of local economies, housing markets and
travel areas.
DETAILED EXAMINATION OF PROBLEMS AND ISSUES
8.5 The priority for the next stage in an M56 Corridor Multi-Modal study is to undertake a detailed examination of the problems and issues that have been identified through document review and
from stakeholder consultation. This review should ascertain the regional importance of the problem, i.e. to establish whether the problem has genuine regional significance or whether theproblem is clouded by perception. This will require;
♦ linking the regional transport problems to the wider environmental, economic regeneration and development objectives for the corridor as outlined in current Regional Planning Guidance and the Regional Economic Strategy;
♦ the development of a full demand matrix across all modes of travel to a common zoning
system, including new data collection where appropriate; to provide a detailed breakdown on trip making patterns including the following;
− trip purposes;
− trip lengths; and
− current mode share for key origin-destination movements.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 105 of 150m56_scoping_study_final_report.doc
♦ a more detailed baseline assessment of the problems and issues, including an
assessment of the balance of short and longer distance movements at key study area bottlenecks and congestion points; and
♦ a need to undertake a high level accessibility mapping exercise to determine the relative
‘costs’ of the alternative modes (in terms of the full range of factors; time, convenience, reliability, quality, monetary cost which all influence travel behaviour and choices) for key
origin-destinations, and to establish a benchmark that each mode must deliver for them to be a suitable alternative mode for that movement.
ADDITIONAL DATA REQUIREMENTS
8.6 In addition to the review of existing information we have identified a number of areas of uncertainty with regard to reliability and completeness of data, namely:
♦ potential need for further roadside interview data;
♦ patronage figures for strategic road based public transport;
♦ disaggregate data with regard to levels of patronage for rail services beyond that supplied via MOIRA/LENNON (which is only station based i.e. does not provide the ‘true’ origin and destination of trips).
8.7 Before embarking upon the definition of any new data collection we would propose that an further examination is undertaken, data assembled and details provided in respect of:
♦ 2001 journey to work census data providing origin-destination data at ward/output area level.
♦ Deeside Park Junctions TPI Study which includes M53, it is understood that registration surveys have been undertaken;
♦ New Mersey Crossing – it is understood that a SATURN model is being built to consider
the strategic reassignment effects of the proposed new crossing between Runcorn and Widnes;
♦ Manchester Airport passenger surveys, it is understood that passenger surveys were undertaken in September 2002;
♦ North West Regional Planning Assessment undertaken for the SRA;
♦ Train operator based ongoing passenger surveys; and
♦ National Express ticketing data.
8.8 Subject to the outcome above we would propose that a limited amount of new data collection may be necessary, covering the following areas of detail:
♦ boarding and alighting counts of users of National Express coach services using the M56 corridor; and
♦ face to face surveys of users of National Express coach services using the M56 corridor to obtain true origin-destination information;
♦ boarding and alighting counts of users of rail services in the M56 corridor on the Mid Cheshire and North Cheshire lines, as well as at Hartford and Winsford railway stations, primarily focussing upon peak time demand issues;
♦ face to face surveys with rail passengers on the Mid Cheshire and North Cheshire lines, as well as at Hartford and Winsford railway stations; and
♦ face to face surveys with Metrolink passengers at Altrincham to obtain information about current railheading from the M56/A556 corridor to this station.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 106 of 150m56_scoping_study_final_report.doc
PREPARING A SHORTLIST OF POTENTIAL MEASURES
8.9 Having established problems and issues of regional importance (as opposed to local) it will be
necessary to prepare a shortlist of potential measures which are appropriate for furtherconsideration and discard those that do not fulfil a strategic role, by giving consideration to;
♦ the extent to which the potential transport measures contribute to the defined set of
corridor objectives. It is suggested that this assessment should be based on a refined 7 point textual scale, utilising a clearly defined set of indicators;
♦ whether the potential measures are both “realistic and practicable” – issues such as possible timescale for implementation and general acceptability where relevant. Further
details on possible timescales for implementation will be sought from stakeholders at this stage; and
♦ whether the cost of implementing a particular potential measure is broadly commensurate
with the likely benefits and provides value for money. Further details on scheme costs will be sought from stakeholders at this stage.
SCENARIO TESTING - MODELLING
8.10 In order to test the effects of the different scenarios the modelling approach taken will be
dependent upon the level of detail required:
♦ for regional transport problems that require corridor-wide consideration we would suggest
that a skeletal multi-modal network is developed using the SEMMMS TRIPS model as its basis. Whilst it is recognised that the SEMMMS model is focussed on the Greater Manchester conurbation and in its current form is not be sufficiently robust to model
strategic transport choices along the M56 corridor, we feel that adoption of this model as a platform for a strategic network model could be developed at a reasonable cost. From the highway side the SEMMMS model could draw upon information contained in the A556
SATURN model which has been developed for the A556(T) RMS (which is itself based on the MIDMAN model), possibly the SATURN model which we understand is beingdeveloped by Giffords to assess the strategic reassignment effects of the proposed New
Mersey Crossing between Runcorn and Widnes (although we are currently unaware of details of this work), and potentially any modelling work associated with the Deeside Park Junctions TPI Study. In addition we would propose that a revised mode choice model
capability is included based upon new mode choice parameters (for example from the MIDMAN or M1 Multi-Modal studies) with improved long distance bus/coach, park-and-rideand light rail modelling capabilities.
♦ for regional transport problems that do not require corridor-wide consideration a more localised modelling approach may be acceptable, such as;
− smaller scale but more detailed strategic multi-modal model;
− micro-simulation models and/or spreadsheet based models to assess the impact of
highway changes. For example the Highways Agency are currently undertaking a study to carry out an initial assessment (using a spreadsheet based model) to assesshow the future development aspirations in the Halton area will affect the operation and safety of the trunk road network in the area; or
− direct demand modelling techniques to assess the impact of new railway facilities.
SCENARIO TESTING – TRANSPORT SUPPLY
8.11 Once a shortlist of potential measures has been prepared and discussed in consultation with
the Study Advisory Group the process of scenario testing can be undertaken.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 107 of 150m56_scoping_study_final_report.doc
Do-Minimum Scenario
8.12 The first stage of this exercise will be to define the do-minimum scenario, against which
packages of measures can be tested. The do-minimum scenario will comprise committedschemes i.e. schemes where a decision to proceed has been taken (even though statutory procedures may still have to be completed) and for which funding will be made available, and
would be implemented regardless of whether this study took place or not. This scoping study has already identified many of those schemes; including;
♦ A494(T)/A550(T) Widening Ewloe Interchange to Welsh/English border (committed
schemes included in Trunk Road Forward Programme 2002, Welsh AssemblyGovernment);
♦ A550(T)/A5117(T) Deeside Park Junction Improvements (committed scheme included in the Highways Agency’s Targeted Programme of Improvements);
♦ M56 improvements between junctions 5 and 6, (scheme part of a Section 278 agreement
that formed part of the planning consent of the second runway inquiry, there is also a
Section 278 agreement works at M56 junction 6 a part of the planning consent for the Davenport Green development);
♦ major schemes (above £5m) in the full Local Transport Plans; such as South Liverpool Parkway (Allerton Interchange); and
♦ rail franchise commitments including;
− diversion of the current Liverpool-Manchester Airport service via Chat Moss;
− new semi-fast Birmingham-Liverpool/Preston rail service operated by Central Trains which will open up opportunities for an improved service at Hartford/Winsford.
8.13 Agreement on schemes/interventions that comprise the do-minimum scenario would be defined in consultation with the Study Advisory Group.
Do Minimum Reference Case
8.14 This will be a development of the do-minimum scenario and will include a package of shortlisted
schemes for which there is a high likelihood of them being developed whether or not this study took place. It is our recommendation that the do-minimum reference case should comprise measures for which there is consensus amongst the Study Advisory Group for the inclusion in
the long term strategy for the M56 corridor and for which there is a very high likelihood of themproceeding.
8.15 At this point we would suggest that a review is undertaken to assess the extent to which these
measures will alleviate (or otherwise) the identified problems.
Demand Management/Making Best Use of Existing Infrastructure Scenario
8.16 Once the do-minimum reference case has been established priority should be given to “demand management” and “making best use of infrastructure options” for both the regional highway and
rail network.
Demand Management
8.17 It is recognised that the Regional Highway Network has a finite capacity and that demand
already exceeds capacity in certain key locations leading to congestion and problems of journey time reliability, and that if demand is unconstrained conditions will continue to deteriorate to unacceptable levels. It is considered therefore that there is a need to investigate how to better
manage demand together with developing new technologies to assist in reducing the need to travel. Whilst a range of highway demand measures have been identified the practicalities
M56 CORRIDOR SCOPING STUDY
Final Report
Page 108 of 150m56_scoping_study_final_report.doc
associated with their implementation and their impact on the M56 corridor transport system
have yet to be addressed. Some aspects of demand management have already been considered under a number of route management strategies and it is understood that M56 RMS is commence in the near future. The study would draw on the recommendations from the
Route Management Strategies for inclusion in any scenario testing.
8.18 For rail reference will be made to the outputs of the North West Regional Planning Assessment to identify the key areas of rail growth (and decline) forecast for the future. This should provide
an indication of where capacity problems can be expected to occur and providerecommendations on how rail demand should be managed.
Better Use of Existing Infrastructure
8.19 It is recognised that delays caused by the increasing volumes of traffic, incidents and road works lead to frustration for road users and increased costs for industry. With vehicleownership rising steadily, demand is forecast to increase further. It is considered therefore that
to tackle this rise there is a need to investigate how to make best use of the latest techniques and technology, and potential small scale infrastructure measures, in managing traffic on the network and minimise delays caused by roadworks and incidents. Whilst a range of highway
management measures have been identified the practicalities associated with theirimplementation and their impact on the M56 transport system have yet to be addressed. As with demand management, this study would draw on the recommendations from the Route
Management Strategies regarding better use of existing highway infrastructure as the basis of any scenario testing.
8.20 A similar consideration will be required of the rail network, with a hierarchy of services being
assessed . Such a process is being undertaken as part of the SRA-led Route Utilisation Strategy (RUS) process, which is ongoing for Greater Manchester and Trans-Pennine and due to report in spring 2005. The recommendations from this process will provide a valuable input
as to whether some of the measures that have been identified in this scoping study requirefurther consideration in the context of the M56 transport corridor.
Further Transport Scenarios
8.21 Further transport scenarios could range from Public Transport scenarios to Highway
Improvements. Indeed there may also be a need for further testing of combination scenarios to ensure that an optimal balance of measures is obtained.
Public Transport Scenarios
8.22 The focus of this scenario would be to make public transport as attractive and competitive as possible in order to encourage modal transfer and reduce car usage, in combination where necessary with highway demand and management measures.
8.23 Current funding would appear to suggest that there is limited prospect for significant rail investment in the near to foreseeable future. However, given the planned change in the rail industry structure following the recent Government White Paper, and combined with private
sector involvement, rail could continue to play a significant role in making a step change in accessibility to the key traffic attractors in the area. Therefore a realistic assessment needs to be made as to the role public transport can make in encouraging modal transfer and reduce car
usage. For this reason it is considered that public transport should be considered under two scenarios; short/medium term measures, and longer term measures.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 109 of 150m56_scoping_study_final_report.doc
Short/Medium Term Public Transport Scenario
8.24 Clearly at this stage in the study process precise details of measures that would comprise this scenario have yet to be defined. It would appear, however, that on the basis of the broad qualitative assessment undertaken as part of this scoping study (and from the
recommendations made in MIDMAN and the ongoing Road Based Public Transport andInterchange Study) that there is a need to explore the contribution that a step change in road based public transport provision would have in supporting sustainable development and the
growth of Manchester and Liverpool Airports, as part of any short/medium term public transport scenario.
Longer Term Public Transport Scenario
8.25 In October 2003, the SRA published The Railway Planning Framework; Regional Planning Assessments. A Regional Planning Assessment (RPA) will be produced for all areas covered by the rail network. These Assessments will form a framework for the Route Utilisation
Strategies, franchise replacement specifications and ongoing infrastructure enhancementconsiderations. The outcome of relevant regional and local studies will be incorporated into the RPA which will be reviewed every five years.
8.26 In the North West the initial RPA is ongoing at the moment, and is due to report late 2004/early 2005. This is likely to identify the future changes in the rail network over the next 10-20 years, but within a wider regional context as compared to the M56 corridor alone. This process will
provide valuable input as to whether some of the longer term rail measures that have been identified in this scoping study require further consideration in the context of the M56 transport corridor. Similarly, it is understood that as part of the Greater Manchester RUS issues
associated with the Manchester Hub will be examined.
Highway Improvement Scenario
8.27 Notwithstanding improved demand management measures, better use of existing infrastructure
and the introduced (where appropriate) of public transport services, it is possible that someproblems on the regional road network can only be solved, by providing targeted increases in highway capacity. Locations already identified by other studies and schemes put forward to
mitigate against these are well advanced; including
♦ A483(T)/A55(T) junction improvements;
♦ A556(T) highway improvements; and
♦ major new crossing of the River Mersey between Runcorn and Widnes;
SCENARIO TESTING – TRAVEL DEMAND
8.28 Land-use planning has a fundamental impact on the operation of the M56 corridor transport system. On the one hand, regeneration of the North West Metropolitan Area for housing and employment could have a beneficial effect on the transport network as the provision of high
quality housing in and near to the city centres could reduce longer commuting distances. New development and redevelopment in the regional poles and surrounding areas could also enable easier access by sustainable modes of transport. However, development pressures will also
remain outside the city centres and in existing employment locations.
8.29 The transport network should play an integrated role in assisting existing and futureregeneration initiatives and in aiding inward investment and supporting indigenous economic
growth. It should also assist in accommodating the forecast passenger growth at Manchester and Liverpool Airports. Any travel demand forecasting along the corridor should take into account the emerging policies in the Regional Spatial Strategy and the RES.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 110 of 150m56_scoping_study_final_report.doc
SCENARIO APPRAISAL
8.30 Scenario appraisal should be undertaken in accord with the transport analysis guidance
provided on the Department for Transport (DfT) website WebTAG. The website originally brought together the Department's existing documents, The Guidance on the Methodology for Multi-Modal Studies (GOMMMS) and associated supplements and errata, Applying the Multi-
Modal Approach to Appraisal to Highway Schemes (The Bridging Document) and MajorScheme Appraisal in Local Transport Plans . The material on the DfT WebTAG site supersedesthese documents.
8.31 Compliance with WebTAG guidance requires that the scenarios are assessed against the Governments five key criteria for transport:
♦ environment– to protect the built and natural environment (including the European Directive on Strategic Environmental Assessment 2001/42/EC);
− to reduce noise,
− to improve local air quality
− to reduce greenhouse gases
− to protect and enhance the landscape
− to protect and enhance the townscape
− to protect the heritage of historic resources
− to support biodiversity
− to protect the water environment
− to encourage physical fitness
− to improve journey ambience
♦ safety – to improve safety;
− to reduce accidents
− to improve security
♦ economy – to support sustainable economic activity and get good value for money;
− to improve transport economic efficiency
− to improve reliability
− to provide beneficial wider economic impacts
♦ accessibility – to improve access to facilities for those without a car and to reduce severance;
− to improve access to the transport system
− to increase option values
− to reduce severance
♦ integration – to ensure that all decisions are taken in the context of the Government’s integrated transport policy and other local policies;
− to improve transport interchange
− to integrate transport policy with land-use policy
− to integrate transport policy with other Government policies
8.32 The assessment of the degree to which central Government objectives are achieved should be carried out using an Appraisal Summary Table (AST) and supported by a short summary of key
impacts and accompanied by worksheets, including the Transport Economic Efficiency (TEE) table. The Appraisal Summary Table summarises the benefits and adverse impacts of the strategy package.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 111 of 150m56_scoping_study_final_report.doc
8.33 As the MMS process (defined in the GOMMMS guidance) is objective led, it was necessary to
identify a series of core corridor objectives at the beginning of the process describing the needs of the study area. These core corridor objectives have been framed both within theGovernment’s five key criteria for transport and the wider regional objectives.
8.34 The core corridor objectives for the M56 Corridor are set out in Section 2. These objectives will be used to frame the appraisal process throughout any future stages of the study. Therefore, for the final scenario appraisal it will be necessary to assess the package of measures against
the Governments’ key criteria for trans port, the wider Regional objectives and against the core corridor objectives. Thus, the following Appraisal Summary Tables will be required;
♦ within the framework of the Governments key criteria for transport;
♦ within the framework of the wider Regional objectives; and
♦ within the framework of the core corridor objectives.
8.35 In addition to the assessment against the Government’s five key criteria, consideration will also need to be given to the performance of the scenarios against:
♦ distribution and equity
♦ financial sustainability and affordability; and
♦ practicality and public acceptability
8.36 These issues essentially relate to the feasibility of solutions, as it will be important to ensurethat any proposed measures could actually be delivered.
♦ distribution and equity - designed to show the distribution of the overall impacts
summarised in the AST, thereby enabling a judgement to be made about the fairness of the impacts across those affected by the strategy.
♦ financial sustainability and affordability - the key question for Financial Sustainability is
the extent to which the scheme option is self-supporting from revenues i.e. can revenues
cover operating costs for each year during the operating period; can revenues cover all costs, including investment costs? If the scheme option is not be fully self supporting, what grant or subsidy is required to deliver the option? In assessing Affordability, it will be
necessary for the Study Advisory Group to take a view as to the likelihood of public funds being available to cover all costs.
♦ practicality and public acceptability – The strategy (or scheme option) may be desirable
but not fundable, or may create a majority of winners with a minority of uncompensated losers who will form a vocal opposition. There therefore needs to be an overall
assessment of the practicality of the strategy (or scheme option), and where relevant, what countervailing or complementary measures are needed to make the strategy practical, and consideration of priorities.
PARTNERSHIP WORKING WITH DELIVERY AGENCIES
8.37 In pursuing a programme of further study for the M56 Corridor we consider that partnership working with the delivery agencies is fundamental in order to ensure that their specific needs
are met and that account is made of other ongoing and future work.
8.38 In addition to liaison on committed schemes, account will need to be taken of other studies,including;
♦ M56 Route Management Strategy;
♦ A556(T) Route Management Strategy;
♦ Strategic assessment of the proposed new Runcorn to Widnes Mersey crossing;
M56 CORRIDOR SCOPING STUDY
Final Report
Page 112 of 150m56_scoping_study_final_report.doc
♦ North West Regional Planning Assessment for rail;
♦ Route Utilisation Strategies for rail; and
♦ the emerging Northern Way Growth Strategy.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 113 of 150m56_scoping_study_final_report.doc
References Forming the Document Review
Transport White Paper “A New Deal for Transport: Better for Everyone”, DETR, July 1998
A New Deal for Trunk Roads in England, DETR, July 1998
Future of Air Transport White Paper, DfT, December 2003
European Directive on Strategic Environmental Assessment 2001/42/EC
Highways Agency Business Plan 2003/04
Strategic Rail Authority Strategic Plan 2003 “Platform for Progress”
Transport in Tomorrow’s Countryside, Countryside Agency, April 2003
Network Rail Business Plan 2004
Guidance on the Methodology for Multi-Modal Studies, Volumes 1 and 2, DETR, March 2000
Planning Policy Guidance Note 13: Transport
A Better Quality of Life – A Strategy for Sustainable Development in the UK (DETR, 1999)
Regional Planning Guidance for the North West (RPG 13), ODPM, March 2003
Partial Review of Regional Planning Guidance for the North West (RPG13), North West Regional Assembly, March 2004
Regional Economic Strategy, Northwest Development Agency, March 2003
Strategic Regional Sites Designation Report, NWDA, December 2001
Strategic Regional Sites, First Monitoring Report, 2003
Strategic Regional Sites, Annual Monitoring Report, 2004
Mersey Belt Study, DTZ Pieda Consulting, May 2002
Mersey Belt Policy Statement 2003
South East Manchester Multi-Modal Study Final Report, September 2001
West Midlands to North West Conurbation Multi Modal Study Final Report, March 2002
West Midlands to North West Conurbation Multi Modal Study Decision Letter, DfT
A556 Area Study Technical Report (2002) and Supplementary Report (2003), Highways Agency
Deeside Park Junctions Study Final Report, September 2001
A5/A483 Shrewsbury to Chester Road-Based Study Final Report, April 2002
A556 (M6 Junction 19 to M56 Junction 17) Route Management Strategy, Public Consultation, March 2004
M6 Warrington to the Scottish Border Route Management Strategy, January 2004
M53/A55/A483 Birkenhead to Welsh Border Route Management Strategy, December 2002
Queensferry Transportation Study, September 2000
Mid Man Study Road Based Public Transport Interchange Strategy, July 2003
Mersey – Dee Alliance Transport Study
New Mersey Crossing Major Scheme Appraisal, Halton BC, 2003
East Runcorn Development Area Sustainable Transport Framework, 2003
M56 CORRIDOR SCOPING STUDY
Final Report
Page 114 of 150m56_scoping_study_final_report.doc
Highways Agency Halton Study, Draft Final Report, April 2004
Manchester Airport Ground Tr ansport Access Study
Manchester Airport Draft Development Strategy to 2015
Liverpool John Lennon Airport Surface Access Strategy, Issue Three, April 2004
North West Regional Freight Strategy, NW Freight Advisory Group, November 2003
Cheshire Local Transport Plan 2001/02 to 2005/06, Cheshire County Council
Greater Manchester Local Transport Plan 2001/02 to 2005/06
Merseyside Local Transport Plan 2001/02 to 2005/06
Halton Local Transport Plan 2001/02 to 2005/06, Halton Borough Council
Warrington Local Transport Plan 2001/02 to 2005/06, Warrington Borough Council
Transport Framework for Wales / Fframwaith Trafnidiaeth Cymru, Welsh Assembly Government,November 2001
Trunk Road Forward Programme / Blaenraglen Cefnffyrdd, Welsh Assembly Government, March 2002
M56 CORRIDOR SCOPING STUDY
Final Report
Page 115 of 150m56_scoping_study_final_report.doc
APPENDIX A
Terms of Reference for Study Objectives
M56 CORRIDOR SCOPING STUDY
Final Report
Page 116 of 150m56_scoping_study_final_report.doc
NATIONAL OBJECTIVES
Government's Five Over-Arching Objectives for Transport
♦ Protect and enhance the built and natural environment
♦ Improve safety for all travellers
♦ Contribute to an efficient economy, and to support sustainable economic growth in appropriate locations
♦ Promote accessibility to everyday facilities for all, especially those without a car
♦ Promote the integration of all forms of transport and land use planning, leading to a better, moreefficient transport system
Government's Sustainable Development Strategy
♦ Promote high and stable levels of economic growth and employment
♦ Ensure effective protection of the environment
♦ Promote social progress that recognises the needs of everyone
♦ Ensure the prudent use of natural resources
Future of Air Transport White Paper
♦ Recognise the importance of air travel to our national and regional economic prosperity, and that not providing additional capacity would significantly damage the economy and national prosperity
♦ Reflect people’s desire to travel further and more often by air, and to take advantage of the affordability of air travel and the opportunities this brings
♦ Seek to reduce and minimise the impacts of airports on those who live nearby, and on the naturalenvironment
♦ Ensure that, over time, aviation pays the external costs its activities impose on society at large – in other words, that the price of air travel reflects it environmental and social impacts
♦ Minimise the need for airport development in new locations by making best use of existing airports where possible
♦ Respect the rights and interests of those affected by airport development
♦ Provide greater certainty for all concerned in the planning of future airport capacity, but at the same time is sufficiently flexible to recognise and adapt to the uncertainties inherent in long-term planning
Highways Agency
♦ To give priority to maintenance whilst minimising whole life costs
♦ To develop its role as a network operator
♦ To reduce congestion and improve journey time reliability
♦ To carry out the targeted investment programme
♦ To minimise the environmental impact of the trunk road network
♦ To improve safety for all road users
♦ To work in partnerships that promote choice and information for travellers
♦ To be a good employer
Strategic Rail Authority
♦ Growth over the period of the Government's 10 Year Plan of 50% in passenger traffic (measure in passenger kilometres)
♦ Growth over the period of the Government's 10 Year Plan of 80% in freight traffic (measure in freighttonne kilometres)
♦ Reducing overcrowding on services within the London Area to meet standards set by the SRA
♦ Performance in the form of train service punctuality is to be improved
♦ Performance in the form of train service reliability is to be improved
Countryside Agency - Transport in Tomorrow's Countryside
♦ Transport policy should seek to make services and facilities more accessible and easier to reach, rather than simply increasing the amount and speed of travel.
♦ Services and transport should be linked together in a way that enhances quality of life and the economy in rural areas
M56 CORRIDOR SCOPING STUDY
Final Report
Page 117 of 150m56_scoping_study_final_report.doc
♦ Roads, railways and associated construction should fit in with the character of the countryside and improve the quality of life for all
♦ Using public transport should not cost more than travelling by car, and government funding should favour non-car transport, supported by longer term funding to enable new transport provision to work over time.
♦ Alternatives to car and lorry travel should be found, in order to reduce the rate of traffic growth in the countryside.
♦ As rail is less damaging to the environment than road and air travel, its use should be encouraged for long distance travel
♦ People should feel safe and secure when travelling in rural areas.
♦ More decisions affecting travel should be made locally.
♦ Good connections between different forms of transport should be available, so that people can use a combination of services with ease.
♦ Walkers, public transport users, cyclists and horse riders should be able to move around safely and freely, and be able to access services and the countryside easily.
REGIONAL OBJECTIVES
Regional Planning Guidance for the North West
♦ Achieve greater economic competitiveness and growth, with associated social progress
♦ Secure an urban renaissance in the cities and towns of the North West
♦ Ensure the sensitive and integrated development and management of the costal zone, and secure the revival of coastal resort towns
♦ Sustain and revive the Region's rural communities and the rural economy
♦ Ensure active management of the Region's environmental and cultural assets
♦ Secure a better image of the Region and high environmental and design quality
♦ Create an accessible Region, with an efficient and fully integrated transport system
Regional Transport Strategy
♦ Enhancement of Trans -European Networks
♦ Effective multi-modal solutions to the conveyance if goods, people and services at major hubs
♦ Effective planned and significantly more efficient transport interchanges
♦ Attractive gateways and transport corridors
♦ Scope for effective use of new technology to enhance travel
♦ A safe and pleasant environment complementary to the need to improve the Region's image and encourage more use of environmentally-friendly modes of transport (e.g. walking, cycling and canals)
Regional Economic Strategy
♦ Exploit the growth potential of business sectors
♦ Improve the competitiveness and productivity of businesses
♦ Develop and exploit the Region's knowledge base
♦ Deliver urban renaissance
♦ Deliver rural renaissance
♦ Secure economic inclusion
♦ Develop and maintain a healthy labour market
♦ Develop the strategic transport, communications and economic infrastructure
♦ Ensure the availability of a balanced portfolio of employment sites
♦ Develop and market the Region's image
North West Regional Freight Strategy
♦ To assist the promotion of sustainable economic growth
♦ To underpin the competitiveness of indigenous business, attract and retain inward investment and reduce the threat of peripherality in Europe by improving accessibility to, from and within the North West for those who use or operate freight transport
M56 CORRIDOR SCOPING STUDY
Final Report
Page 118 of 150m56_scoping_study_final_report.doc
♦ To provide a vibrant, efficient and safe freight industry in the North West by developing and maintaining a range of high quality transport networks and services
♦ To involve both private and public sector interests by encouraging partnership working to facilitate a better understanding amongst stakeholders of the needs of modern supply chains
Transport Framework for Wales
♦ Transport system that is more accessible to all people, including people with disabilities, youngpeople and those at a social disadvantage
♦ Transport system that is able to provide access and mobility to support commercial activity and facilitate implementation of the economic vision for Wales
♦ Transport system that is better integrated between different modes, and with land-use planning with care for the environment as a basic principle
♦ Transport system that is safer and health promoting
♦ Transport system that is more efficient in its use of resources
LOCAL OBJECTIVES
Cheshire Local Transport Plan
♦ To promote sustainable accessibility
♦ To improve travel safety and security
♦ To promote integration of all forms of transport
♦ To contribute to an efficient and sustainable economy
♦ To protect and enhance the environment
Merseyside Local Transport Plan
♦ To ensure that transport supports sustainable economic development and regeneration
♦ To moderate the upward trend in car use and secure a shift to more sustainable forms of transport such as walking, cycling and public transport
♦ To secure the most efficient and effective use of the existing transport network
♦ To enhance the quality of life of those who live, work in, and visit Merseyside
Halton Local Transport Plan
♦ To develop safe, efficient and inclusive integrated transport systems and infrastructure thatencourage s ustainable economic growth and regeneration
Warrington Local Transport Plan
♦ Enhance and protect the environment of the Borough
♦ Improve safety, personal security and health
♦ To contribute to an efficient economy and to support sustainable economic growth in Warrington
♦ Improve accessibility and mobility in the Borough
♦ To promote the integration of all forms of transport and land use planning
♦ Improve the quality of life and transport system and reduce social exclusion and poverty in the Borough
♦ Ensure best value and optimal use of resources is obtained from the LTP expenditure programme
Greater Manchester Local Transport Plan
♦ To strengthen, modernise and diversify the local economy in ways which are environmentallysustainable
♦ To support urban regeneration and bring disused and under-used urban land back into effective use
♦ To make Greater Manchester as a whole a more attractive, safer and healthier place to live, work and invest
♦ To focus these improvements in the Regional Centre, the town centres, and major employmentcentres (e.g. Manchester Airport, Salford Quays and Trafford Park)
♦ To reverse the decentralisation of population and economic activity, sustain the community and cultural life of urban centres and neighbourhoods, and ensure that everyone can participate in the opportunities that the County has to offer
M56 CORRIDOR SCOPING STUDY
Final Report
Page 119 of 150m56_scoping_study_final_report.doc
OTHER STRATEGIES AFFECTING THE STUDY AREA
South East Manchester Multi-Modal Study (SEMMMS)
♦ Promotion of environmentally sustainable economic growth
♦ Promotion of urban regeneration
♦ Improvement of amenity, safety and health
♦ Enhancement of the Regional Centre, town centres and local and village centres and the Airport
♦ Encouragement of the community and cultural life of neighbourhoods, and encouragement of social inclusion
West Midlands to North West Conurbations Multi-Modal Study (MIDMAN)
♦ To enable the M6 to retain a strategic role, this being measured by acceptable journey times, improved levels of journey time reliability and safety, and reductions in the diversion of strategic traffic onto local routes
♦ To enable the M6 to retain a strategic role for road freight
♦ To enable the public transport networks (e.g. the West Coast Main Line) to provide a quality of service to facilitate modal transport in the corridor so to attract the maximum numbers of passengersand volume of freight
♦ To achieve satisfactory levels of journey time, journey time reliability and safety around M6 junction 11a following the construction of Birmingham Northern Relief Road, these to be consistent with the adjacent length of the M6 motorway
♦ To reduce strategic traffic diverting off the M6 onto diversionary routes such as A34, A449, A5/A51, A50 (north of Stoke-on-Trent) and A536 so that these routes can maintain their sub-regional function
♦ To provide a transport solution between the M6 and M56 to perform the strategic role currently performed by the A556, this being assessed by acceptable journey times, and improved levels of journey time reliability and safety
♦ To achieve compatibility between the impact of major new developments in the corridor and other objectives of the Study
♦ To reduce noise in identified communities
♦ To improve local air quality
♦ To protect and enhance the landscape
♦ To protect and enhance biodiversity
♦ To improve access to and within areas identified for regeneration, particularly existing urban areas and transport interchanges
♦ To enhance accessibility in areas suffering from social exclusion such as Merseyside Objective 1 Area, east Manchester, the Mersey Belt and regeneration zones identified in the West Midlands
♦ To ensure integration between the transport strategy of the corridor with the Regional Planning Guidance and Regional Economic Strategies of the West Midlands and North West
A556 Area Study (Based on MIDMAN Objectives)
♦ To enable the M6 to retain a strategic role, this being measured by acceptable journey times, improved levels of journey time reliability and safety, and reductions in the diversion of strategic traffic onto local routes
♦ To enable the M6 to retain a strategic role for road freight
♦ To reduce the divers ion of strategic traffic diverting onto local highway routes
♦ To provide a transport solution to the A556 assessed by acceptable journey times and improved levels of journey time reliability and safety
♦ To reduce noise in identified communities
♦ To improve local air quality
♦ To protect and enhance the landscape
♦ To protect and enhance biodiversity
A550(T)/A5117(T) Deeside Park Junctions Study
A5/A483 Shrewsbury to Chester Road-Based Study
♦ To reduce congestion
♦ To resolve safety problems
M56 CORRIDOR SCOPING STUDY
Final Report
Page 120 of 150m56_scoping_study_final_report.doc
♦ To resolve environmental problems
♦ To facilitate economy activity in North Shropshire, North Wales and the North West
♦ To protect the local interests of the communities affected by the route
♦ To promote and support sustainable modes along the route
M6 Warrington to the Scottish Border Route Management Strategy
♦ To protect and enhance the built and natural environment.
♦ To improve safety for all travellers
♦ To contribute to an efficient economy to support sustainable economic growth in appropriate locations
♦ To promote accessibility to everyday facilities for all, especially those without access to a car
♦ To promote the integration of all forms of transport and land use planning, leading to a better, more efficient transport system
M62 Liverpool to Hull Route Management Strategy
♦ To reduce congestion
♦ To encourage integration
♦ To improve safety
♦ To enhance the environment
♦ To improve accessibility
M53/A55/A483 Birkenhead to Welsh Border Route Management Strategy
♦ To protect and enhance the built and natural environment.
♦ To improve safety for all travellers
♦ To contribute to an efficient economy to support sustainable economic growth in appropriate locations
♦ To promote accessibility to everyday facilities for all, especially those without access to a car
♦ To promote the integration of all forms of transport and land use planning, leading to a better, more efficient transport system
New Mersey Crossing Major Scheme Appraisal
♦ To relieve the Silver Jubilee Bridge, thereby removing the constraint on local and regionaldevelopment and better provide for local traffic needs. (The crossing must provide a viablealternative route to the Silver Jubilee Bridge)
♦ To maximise development opportunities
♦ To improve public transport links across the river
♦ To encourage the increased use of cycling and walking
Northwest Development Agency - Strategic Regional Sites First Monitoring Report (April
2003)
♦ Attracting and developing knowledge-base industry into and close to areas of regeneration need
♦ Developing knowledge-base industry related to university and other existing concentrations ofknowledge-based industry
♦ Regional distribution sites
♦ Servicing the needs of the established target sectors
Mersey Belt Study
♦ Promote an integrated approach to future planning which identified the steps needed to manage better all assets within the Mersey Belt Southern Crescent, so that economic potential could be encouraged and realised creatively, without compromising the principles of sustainable development
♦ Promote an integrated approach to future planning which supported and complemented regenerationin the Metropolitan Axis, by identifying realistic and sustainable opportunities to accommodate and deflect development pressures from the south to north of the River Mersey, in the short and long term
Greater Manchester Rail Study
♦ Understanding how rail in Greater Manchester can contribute to achieving the Government’stransport policy objectives and the 10 Year Plan targets for passenger and freight growth
M56 CORRIDOR SCOPING STUDY
Final Report
Page 121 of 150m56_scoping_study_final_report.doc
♦ Understanding what service improvements would be required to deliver significant increases in patronage
♦ Informing SRA’s franchise replacement process, particularly for the Trans-Pennine Express and Northern franchises, SRA’s Strategic Plan and Railtrack’s Network Management Statement
♦ Informing the development of Regional Planning Guidance, Regional Transport Strategy, LocalTransport Plans, and the conclusions of Multi-Modal Studies
Manchester Airport - Ground Transport Strategy
♦ To develop the airport as a major regional transport hub, with a network of high quality and frequent public trans port services from regional centres and cities (airport gateways).
♦ To achieve a progressive reduction in the proportion of vehicle trips by road relative to the number of air passengers. Our public transport use target is 40% (at 40 million terminating passengers).
♦ To actively encourage the use of public transport for journeys to and from the Airport, and reduce dependence on the private car as a means of Airport access.
♦ To offer a choice of efficient reliable, safe and quality transport services for all
♦ To ensure that lack of personal mobility will not be a barrier to public transport access
♦ To invest, in partnership with others, in transport schemes that provide the best value solutions in terms of overall cost, time and environmental quality
♦ To support the development and management of the strategic road network in order to maintain a high standard of access for all airport users and to complement public transport access.
♦ To encourage cycling and walking as a means of Airport access by development of safe and convenient routes
Manchester Airport - Draft Development Strategy to 2015
♦ Maximise the profitable growth of its airport related and other businesses in a manner that brings sustainable economic, financial and social benefits to the North West Region
♦ Grow our business as a fundamental element in the region’s infrastructure
♦ Maximise the capacity of all our assets whilst maximising the positive social and economic benefits that arise from the success of the business
♦ Minimise the negative environmental and community impacts arising from our activities
TRANSPORT PROVIDERS IN THE STUDY AREA
Network Rail - 2003 Business Plan
♦ Improve safety. To reduce the number of accidents
♦ Improve service performance. To enable greater punctuality and reliability of train services
♦ Increase system capability. To facilitate achievement of the SRA’s Strategic Plan and increase passenger and freight capacity
♦ Improve customer and stakeholder relationships. To increase the satisfaction of passenger and freight rail users and other stakeholders
♦ Improve financial control. To increase our financial efficiency and maximise what we can deliver for each pound spent
♦ Improve asset stewardship. To take better care of the infrastructure and deliver greater value for money
♦ Improve business performance. To make the most of our people’s skills and effort
M56 CORRIDOR SCOPING STUDY
Final Report
Page 122 of 150m56_scoping_study_final_report.doc
APPENDIX B
Mersey Belt Study
M56 CORRIDOR SCOPING STUDY
Final Report
Page 123 of 150m56_scoping_study_final_report.doc
MERSEY BELT STUDY
The NWDA commissioned in 2000 a study that aimed to ensure that North West region as a
whole had a realistic strategy for stimulating both indigenous and inward investment inknowledge-based industries focusing on the Target Sectors. The Mersey Belt Area wasbroadly defined as the following districts;
Cheshire Greater Manchester Unitary AuthoritiesChester Bolton HaltonEllesmere Port and Neston Bury Warrington
Macclesfield ManchesterVale Royal Oldham
Rochdale
Merseyside SalfordKnowsley StockportLiverpool Tameside
Sefton TraffordSt Helens WiganWirral
The Mersey Belt Study took account of the contrasts between north of the Mersey River (the Metropolitan Axis) and south of the Mersey River (Southern Crescent), where;
♦ Southern Crescent comprises wards within Chester, Ellesmere Port, Vale Royal,Macclesfield and wards of Halton, Warrington, Manchester, Trafford and Stockport which lie to the south of the River Mersey and the M60 motorway; and
♦ Metropolitan Axis comprises wards within Bolton, Bury, Knowsley, Liverpool, Oldham, Rochdale, Salford, Sefton, St Helens, Tameside, Wigan and Wirral and the wards of
Halton, Warrington, Manchester, Trafford and Stockport which lie to the north of the River Mersey and the M60 motorway.
The main objectives of the Mersey Belt Study were to promote an integrated approach to future planning which:
♦ identifies the steps needed to manage better all assets with the Southern Crescent, so that
economic potential can be realised creatively, without compromising the principles of sustainable development.
♦ supports and complements regeneration in the Metropolitan Axis by identifying realistic
and sustainable opportunities to accommodate and deflect development pressures from the south to north of the River Mersey in the short and long term.
The study identifies 40 sites (shown below) suitable for knowledge based industries as either
Category A or Category B site;
♦ Category A – 10 sites where public investment needs to be made, especially to improve accessibility, infrastructure and image
♦ Category B – 30 sites which are no less important for knowledge-based industry in policy
terms, but in general will have a lower call on public investment for site preparation and assembly
M56 CORRIDOR SCOPING STUDY
Final Report
Page 124 of 150m56_scoping_study_final_report.doc
North West Sites Considered Suitable for Knowledge Based Industries(Mersey Belt Study)
It should be noted that the terms ‘Metropolitan Axis’ and ‘Southern Crescent’ are used above only as a matter of historical record in referring to the Mersey Belt Study. RPG has reflected
the issues in its identification of the North West Metropolitan Area Regeneration Priority Area and in the special policy framework for North Cheshire.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 125 of 150m56_scoping_study_final_report.doc
APPENDIX C
Railway Station Audit
M56 CORRIDOR SCOPING STUDY
Final Report
Page 126 of 150m56_scoping_study_final_report.doc
Station Name Status Facilities Information Car/Cycle Parking Comments
Navigation Road Unmanned Shelter provided. None (phone on Metrolink platform).
Free car park. Car park soon to be expanded to 90 spaces.
Altrincham Manned Attached to
bus/Metrolinkinterchange. Canopies provided.
Local public address Associated car park.
Remote to station cycle rack.
Poor quality of
interchange pending redevelopment of site. Disabled access to
Chester-bound platformvia barrow crossing only.
Hale Manned
(early turn only)
Canopies over both platforms.
None except phone
on Manchester-bound platform.
Car parking (50p per day).
Ashley Unmanned Shelter on Chester–bound platform only.
None except phone
on Chester-boundplatform.
No defined spaces.
Mobberley Unmanned Shelters on both platforms.
None except phone
adjacent to Chester-bound platform.
A few car parking spaces (approx 8).
Knutsford Manned Canopy over
Manchester-boundplatform. Shelter on Chester-bound platform.
Payphone on
Manchester-boundplatform for times when station is
unstaffed (late evening).
Car parks on both sides (£2.50 per day).
Plumley Unmanned Shelters on both platforms.
Payphone on
Manchester-boundplatform
Free Car park.
Lostock Gralam Unmanned Shelter on Chester-bound platform only.
Payphone on
Chester-boundplatform.
Northwich Manned
(early turn only)
Canopy over
Manchester-boundplatform. Shelter on Chester-bound platform.
Payphone on
Manchester-boundplatform.
Free Car park.
Greenbank Unmanned Shelter on Chester-bound platform only.
None (payphone
across busy main road).
Free Car parking.
Cuddington Unmanned Shelters provided on both platforms.
None except
payphone on Manchester-boundplatform.
Free Car parking provided
Delamere Unmanned Shelters on both platforms.
None (call box nearby).
Free car parking.
Mouldsworth Unmanned Shelter on Manchester-bound platform only.
None except phone
on Chester-boundplatform.
Free Car parking.
Hartford Manned Shelters on both platforms.
Car parking. Disabled access via
ramp to Liverpool-boundplatform.
Acton Bridge Unmanned Simple shelter. Help point provided. Small number of spaces. No disabled access provided.
Warrington BQ Manned Shelters on both platforms
Real time info screens,
Helsby Unmanned Shelters on both platforms
Small number of spaces Station gardens
maintained by Rail User Group. Manned signal
box provides security presence.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 127 of 150m56_scoping_study_final_report.doc
Station Name Status Facilities Information Car/Cycle Parking Comments
Frodsham Unmanned Simple shelters on both platforms
Help point provided
– disconnected
since new franchise began!
Very limited parking
Runcorn East Manned Shelters on each platform
Car parking Security problems at car park and when station is unmanned
Runcorn (main line)
Manned Charged car park
M56 CORRIDOR SCOPING STUDY
Final Report
Page 128 of 150m56_scoping_study_final_report.doc
APPENDIX D
Key Highway Movements in Study Area
M56 CORRIDOR SCOPING STUDY
Final Report
Page 129 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 130 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 131 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 132 of 150m56_scoping_study_final_report.doc
APPENDIX E
Key Rail Demand Movements in Study Area
M56 CORRIDOR SCOPING STUDY
Final Report
Page 133 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 134 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 135 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 136 of 150m56_scoping_study_final_report.doc
M56 CORRIDOR SCOPING STUDY
Final Report
Page 137 of 150m56_scoping_study_final_report.doc
APPENDIX F
Congestion Reference Flow
M56 CORRIDOR SCOPING STUDY
Final Report
Page 138 of 150m56_scoping_study_final_report.doc
The CRF of a link is given by the formula:
CRF = CAPACITY * NL * Wf * 100/PkF * 100/PkD * AADT/AAWT
where, CAPACITY is the maximum hourly lane throughput (see note 1);
NL is the Number of Lanes per direction;
Wf is a Width Factor (see note 2);
PkF is the proportion (percentage) of the total daily flow (2-way) that occurs in the peak hour;
PkD is the directional split (percentage) of the peak hour flow;
AADT is the Annual Average Daily Traffic flow on the link;
AAWT is the Annual Average Weekday Traffic flow on the link.
Notes on Congestion Reference Flow (CRF) calculations
Note 1. CAPACITY - the maximum sustainable hourly lane throughput.
In reality this value varies day to day due to the prevailing conditions (for example, day/night, wet/dry, percentage heavy vehicles, regular/holiday traffic) and values used must be an average. For new links and existing links not currently experiencing congestion this can be estimated from the following relationship:
CAPACITY = [A - B * Pk%H]
where, Pk%H is the percentage of ‘Heavy Vehicles’ in the peak hour. The term ‘Heavy Vehicles’ always includesthe vehicle categories OGV1, OGV2 and PSV’s according to the COBA definition;
A and B are parameters dependant on road standard;
A B
Single Carriageway 1380 15.0
Dual Carriageway 2100 20.0
Motorway 2300 25.0
For existing links already experiencing congestion the maximum hourly throughput should ideally be an observed, robust estimate. This can be determined from observations on a minimum of ten days in fine, dry, daylight conditions. When observing the maximum hourly throughput the major problem is to determine when the link is actually operating at “capacity” (paragraph D.1 describes the likely traffic conditions at “capacity”).
Note 2. Carriageway Width Factor (Wf)
This factor is designed to adjust the CRF for all-purpose links, generally single carriageways, with non-standardlane widths. Carriageway width is defined as the total paved width of the carriageway less the width of ghost islands and hard strips.
Motorways - the width factor Wf should always be unity for motorways as there is no evidence to suggest that the maximum hourly throughput of motorway links is affected by minor changes in lane width.
All-purpose dual carriageways - to reflect the different standards of some dual carriageways. The width factor is given by:
Wf = Carriageway Width / (Number of Lanes * 3.65).
The majority of dual carriageways will have lane widths of 3.65 metres and hence a width factor of unity. Some will have reduced lane widths, generally those built to older design standards, and in these cases the width factor can be less than unity. Should the lane width be greater than 3.65 metres the width factor should be restricted to a maximum value of unity.
Single carriageways (2-lane) - the main purpose of the width factor is to differentiate between the different carriageway width standards of single carriageways. The width factor is given by:
Wf = (0.171 * Carriageway Width) - 0.25
Roads built to modern designs usually have 7.3 metre of 10 metre carriageways, that is, a width factor of unity or 1.46. The width of older roads can vary significantly but the width factor relationship is not valid for road widths less than 5.5 metres or greater than 11 metres. For roads with widths outside these limits the traffic analyst must use judgement to decide on the relevant value.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 139 of 150m56_scoping_study_final_report.doc
APPENDIX G
Potential Contribution of Identified TransportMeasures to Strategy Objectives
M56 CORRIDOR SCOPING STUDY
Final Report
Page 140 of 150m56_scoping_study_final_report.doc
Potential Contribution of Identified Transport Measures toStrategy Objectives
A broad qualitative assessment has been undertaken to assess the extent to which the
transport measures identified through documented references and stakeholder consultation could potentially contribute to the strategic objectives for the M56 corridor.
Each potential transport measure identified in Section 6, has been assessed against the
strategy sub-objectives outlined in Section 2, using a 5 point textual scale;
ü strongly supportive of the strategy sub-objective
ü slightly supportive of the strategy sub-objective
blank neutral
û slightly unsupportive of the strategy sub-objective
û clearly unsupportive of the strategy sub-objective
Potential measures were then grouped according to the likely timescale for their
implementation, namely;
♦ Short term measures which could be implemented within 5 years, subject to further
study (if necessary), funding availability (if required) and completion of the necessary statutory procedures;
♦ Medium term measure which could be implemented within 5 to 10 years, subject to
further study, funding availability and completion of the necessary statutoryprocedures; and
♦ Long term measures which have little prospect of being implemented within 10 years,
have yet to be fully appraised, are perhaps only viable as part of a package of measure, and for which funding is not currently available.
For clarity committed schemes have been highlighted in red.
M56 CORRIDOR SCOPING STUDY
Final Report
Page 141 of 150m56_scoping_study_final_report.doc
CONTRIBUTION OF POTENTIAL SHORT TERM MEASURES (0-5 YEARS) TO STRATEGY OBJECTIVES
Potential Short Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pea
n N
etw
ork
s
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
HS1Designate the M56 east of M6 as a Trans European
Route ü
HS2aCompany travel plans (including car sharing incentives
and flexible working patterns) ü ü ü ü ü ü ü ü ü ü
HS2b School travel plans ü ü ü ü ü ü ü ü ü
HS2c Car pooling sites at motorway interchanges ü ü ü ü û ü û ü û
HS2hParking charges (including disincentives for “kiss -and-
ride” at Airports) and workplace chargingü ü ü ü ü ü ü ü ü
HS2i Telecommunications ü ü ü ü ü ü ü
HS3b Use of motorway hard-shoulder as a running lane ü ü ü û ü û û ü û û û
HS3c Electronic variable message speed limit signs ü ü ü ü ü ü ü
HS3d
Other ‘Active Traffic Management’ systems including; enhanced message signs and strategic incident
diversion routes. Particular application of EMS could be
to provide to diversionary information in the event of an incident at one of the Mersey Crossings.
ü ü ü ü ü ü ü
HS3e Use information from the National Traffic Control Centre ü ü ü ü ü ü ü ü ü
HS3fGovernment’s Transport Direct service providing
comprehensive route planning service covering all modes of transport
ü ü ü ü ü ü ü ü ü ü ü ü
HS4c A494(T) widening Ewloe to Drome Corner ü ü ü û ü û û ü ü û ü û
HS4dA494(T)/A550(T) widening Dromer Corner to Deeside
Park ü ü ü û ü û û ü ü û ü û
M56 CORRIDOR SCOPING STUDY
Final Report
Page 142 of 150m56_scoping_study_final_report.doc
Potential Short Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pea
n N
etw
ork
s
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
HS5 Deeside Park junctions improvement scheme ü ü ü û ü û û ü ü û ü û
HS7Active traffic management at M56/M53 Stoak
Interchangeü ü ü ü ü
HS10bReview of Primary Route Network direction signing to
ensure it is up-to-date and consistent, including M6 to
Wirral/Ellesmere Port/Chester/North Wales ü ü ü ü ü ü ü
HS11 Improvements to M56 junction 12 ü ü ü ü ü
HS13a Minor improvements to M56 junction 11 ü ü
HS15a Minor improvements to A556(T) ü
FS9 Reintroduction of Freight Facilities Grants ü ü ü
FS11aReform of system of international route licensing from
regional airports ü ü
FS11b Fiscal measures to encourage growth of air-freight ü ü
FS12Make best use of the Manchester Ship Canal and
Weaver Navigation to carry increased volumes of
freight for selected cargoes.ü ü ü ü ü ü ü
RS1a
Crewe station redevelopment (including rebuilt
concourse, better bus/taxis access, new car park and remote check-in for Manchester Airport) in order to fulfil
its role as a key regional hub
ü ü ü ü ü ü ü
RS1bMajor environmental improvements at Chester rail station, accompanied by bus/rail/car/taxi/cycle
interchangeü ü ü ü ü ü ü
M56 CORRIDOR SCOPING STUDY
Final Report
Page 143 of 150m56_scoping_study_final_report.doc
Potential Short Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pea
n N
etw
ork
s
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
RS1c
Upgrading of all stations to minimum standards,
encompassing information, security, car/cycle parking,
waiting environment. Focus placed upon current known
problems at Frodsham (including potential park-and-ride), Northwich, and Runcorn East. Working with Rail
User Groups
ü ü ü ü ü ü ü
RS3aDiversion of current Liverpool-Manchester Airport rail service via Chat Moss ü ü ü ü ü
RS3cUpgrade Hartford Station to increase regional role on WCML by means of greater service frequency and
reinstatement of peak time London services.û ü ü ü ü
RS4bDevelopment of South Liverpool Parkway (Allerton Interchange) ü ü ü ü ü ü ü ü ü
RS4cDedicated high quality bus link between South Liverpool Parkway and Liverpool John Lennon Airport
as well as serving The Estuary developmentü ü ü ü ü ü ü ü
RS5bNew semi-fast Birmingham-Liverpool/Preston rail service operated by Central Trains for improved service
to Hartford/Winsfordü ü ü ü
RS6aIncreased number of carriages during peak periods for
North-Cheshire Line rail servicesü ü ü ü
RS6bMinimum half hourly daytime frequency for North-Cheshire Line rail services ü ü ü ü ü ü
RS7aMinimum half hourly service Greenbank/Northwich or Knutsford to Manchester with scope for alternating
stopping/semi-fast servicesü ü ü ü ü ü
RS8Publicity awareness campaign to alert the public of
available public transport servicesü ü ü ü ü
RS9Extend PTE multi-modal ticket and fares baskets to logical travel to work areas (e.g. to Knutsford/Lostock
Gralam by means of Cheshire buying in to scheme).ü ü ü ü ü
M56 CORRIDOR SCOPING STUDY
Final Report
Page 144 of 150m56_scoping_study_final_report.doc
Potential Short Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pea
n N
etw
ork
s
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
RS10aMinimum half hourly daytime frequency for Wrexham-
Bidston Line rail servicesü ü ü ü ü ü
CS1
Regional network of high quality express bus/coach
services with high quality interchange facilities.
Cheshire CC are promoting Cheshire NET express
services with high quality interchange facilities;
♦ Manchester - South Manchester - Manchester
Airport - Knutsford/Poplar - Warrington South -Runcorn/Daresbury - Chester
♦ Warrington - Birchwood - Knutsford/Poplar -Stoke
♦ Warrington - Warrington South – Northwich -Sandbach - Hanley
ü ü ü ü ü ü ü ü ü ü ü
CS3aProvision of public transport services to provide access
to jobs from areas of social exclusion ü ü ü ü ü ü ü
CS3bProvision of fiscal measures for public transport
services to promote access to jobs from areas of social exclusion
ü ü ü ü
CS4Increased bus services to support the East Runcorn
Development Area ü ü ü
M56 CORRIDOR SCOPING STUDY
Final Report
Page 145 of 150m56_scoping_study_final_report.doc
CONTRIBUTION OF POTENTIAL MEDIUM TERM MEASURES (5-10 YEARS) TO STRATEGY OBJECTIVES
Potential Medium Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
nin
th
e n
ee
d t
o t
rav
el
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pe
an
Ne
two
rks
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
HS2e Dedicated lanes for road based public transport only û û ü ü û ü ü û ü ü
HS2fDedicated lanes for high occupancy vehicles including
buses/coachesû û ü ü û ü ü û ü ü
HS2g Road user charging û û û ü ü ü ü ü ü
HS2h Closure of motorway junctions ü ü ü ü ü ü ü
HS3a Ramp metering ü ü ü ü ü ü ü
HS4a Capacity improvements to A55 Ewloe to Northop ü ü ü û ü û û ü ü û ü û
HS4bA55/A494 Ewloe Interchanges improvements with a
connection to A494 to Mouldü ü ü ü û
HS9Major junction improvements to the A55(T)/A483(T)
Interchange ü û ü û û ü ü û ü û
HS12aNew crossing of the River Mersey between Runcorn
and Widnes ü ü ü û ü û ü ü û ü
HS12bHighway improvements to the Weston Point
Expressway Interchange at Clifton Hall and Southern
Expressway Interchange at Halton Lodgeü ü ü ü
HS13bImprovements to the A558 Eastern Expressway, A56
Daresbury Bypass and M56 Junction 11 Roundabout ü ü ü
HS15bDualling of the A556(T) between Mere and Bucklow Hill
and associated junction improvements.ü ü ü ü ü ü
HS16
Highway improvements between M56 junctions 5 and 6
associated with the Section 278 agreements for the
future expansion of Manchester Airport and
development at Davenport Green
ü ü ü û ü û û ü û ü û
M56 CORRIDOR SCOPING STUDY
Final Report
Page 146 of 150m56_scoping_study_final_report.doc
Potential Medium Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
nin
th
e n
ee
d t
o t
rav
el
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pe
an
Ne
two
rks
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
FS8aNetwork of routes cleared to W10 gauge to
accommodate deep sea containers of 9’6’’ height and
2.5m widthü ü
FS10Development of a strategic rail freight park at Ditton
(Widnes) ü ü ü
FS11dHighway infrastructure improvements to Liverpool John
Lennon Airport, including a new Eastern Access Route
from the A561 to the new cargo development areasü ü ü
RS3dReopening to passenger services tied in with
Manchester Airport Western Rail link (see RS3b) and
new Liverpool circular service.ü ü ü ü ü
RS4g
Electrification Ellesmere Port – Helsby. Easy extension
of current Merseyrail services to Helsby to provide
better connections and serve new housing/industry at Ince/Elton
ü ü ü ü
RS5c
Reopening of freight only Northwich-Sandbach line.
Would provide scope for diversion of current Crewe/South Wales services via Manchester Airport
and hence into Piccadilly. (Linked to Western Airport
Rail Link see RS3b)
ü ü ü ü ü ü
RS5d New rail station at Middlewich û ü ü ü ü ü
RS7bNew Mid-Cheshire Line parkway station near Lostock
Gralam, near Northwichü ü û ü ü ü ü û ü ü
RS7cUpgrade route to provide better line speed to provide
better journey timesü ü ü ü ü
RS7dUse of diesel trams on Mid-Cheshire Line with the
potential to run them on Metrolinkü ü ü ü û ü
RS10bElectrification of the Wrexham-Bidston Line between
Bidston and Woodchurchü ü ü ü
M56
CO
RR
IDO
RS
CO
PIN
GS
TU
DY
Fin
al R
eport
Page
14
7 o
f 15
0m
56_scopin
g_stu
dy_fin
al_
report.d
oc
Po
ten
tial M
ed
ium
Te
rm M
ea
su
res
Support the delivery of
strategic regional sites
and growth of existing and
target sector industries in the M56 corridor
Support the Manchester
Regional Pole
Support the growth of
Manchester and Liverpool Airports
Encourage the reductionin the need to travel
Enhance strategic
transport network
efficiency and improve journey time reliability
Encourage mode shift
from car
Encourage a shift of
freight from road to other modes
Improve access for non-
car users
Increase transport choice
in rural areas
Improve interchange
between transport modes
Improvements to and
enhanced management of Trans-European Networks
Improve perception of
personal security for public transport journeys
Improve road safety
Minimise the impacts of
transport upon the built and natural environment
Minimise the impacts of
transport upon emissions
Encourage the use of
environmentally
sustainable modes of transport
CS
1b
Re
gio
na
l ne
two
rk o
f hig
h q
ua
lity e
xp
ress b
us/c
oa
ch
se
rvic
es w
ith h
igh
qu
ality
inte
rch
an
ge
facilitie
s
Che
sh
ire C
C p
rom
otin
g C
he
sh
ire N
ET
exp
ress s
erv
ice
s
with
hig
h q
ua
lity in
terc
ha
ng
e fa
cilitie
s;
♦W
arrin
gto
n–
Birc
hw
oo
d - K
nu
tsfo
rd/P
op
lar -
Ma
ccle
sfie
ld
♦M
an
ch
este
r- S
ou
th M
an
ch
este
r - Ma
nch
este
r
Airp
ort
- Wilm
slo
w/C
on
gle
ton
- Ha
nle
y
♦M
an
ch
este
r- S
ou
th M
an
ch
es
ter
- Ma
nch
este
r
Airp
ort
- Kn
uts
ford
– S
an
db
ach
- Cre
we
üü
üü
üü
üü
üü
ü
CS
2B
us p
riority
me
asu
res to
Ma
nch
este
r Airp
ort fro
m M
56
ûû
üû
üü
üû
üü
CS
3c
Ne
w/im
pro
ve
d p
ub
lic tra
nsp
ort in
frastru
ctu
re to
pro
vid
e
acce
ss to
job
s fro
m a
rea
s of s
ocia
l exclu
sio
nü
üü
üü
üü
üü
M56 CORRIDOR SCOPING STUDY
Final Report
Page 148 of 150m56_scoping_study_final_report.doc
CONTRIBUTION OF POTENTIAL LONG TERM MEASURES (10 YEARS AND BEYOND) TO STRATEGY OBJECTIVES
Potential Long Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pe
an
Ne
two
rks
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
HS6a A550(T) Improvement Hooton to Sealand ü ü ü û ü
HS6bProvision of M56/M53 Stoak Interchange west/north
linksü ü ü ü û ü
HS8Potential M53 highway improvements junctions 5 to 11
in the event of future development pressures ü ü ü û ü û û ü ü û û
HS10a A51 Improvements east of Chester ü
HS14New crossing of thee River Mersey and Manchester Ship Canal to the west of Warrington in conjunction with
flood defence schemeü ü ü ü û ü û ü û
HS15c
Full dualling of the A556(T) with connecting services
roads for local traffic along with further junction
improvements, and free flow links to M6 junction 19 and
M56 junctions 7 and 8.
ü ü ü û ü û û ü û ü û
HS16b Widening of M56 junctions 6 to 7 ü ü ü û ü û û û û û
FS7aWest Coast Main Line upgrade to provide guaranteed
timetable paths for freight south of Crewe ü ü ü ü ü
FS7bPossible routeing of freight via reinstated Halton Curve
to Chester and thence via Chester and Shrewsburyü ü ü
FS8bProvision of W12 gauge to accommodate inter-modal
units, including swap bodies, for routes serving ports
and Channel Tunnel corridorü ü ü ü
FS8cProvision of W18 gauge for key links in the network for
‘piggyback’ trailer operationü ü ü ü
FS11cOff site facilities for air freight with appropriate transport
links ü ü ü
M56 CORRIDOR SCOPING STUDY
Final Report
Page 149 of 150m56_scoping_study_final_report.doc
Potential Long Term Measures
Su
pp
ort
th
e d
eli
ve
ry o
f
str
ate
gic
re
gio
na
l s
ite
s
an
d g
row
th o
f e
xis
tin
g a
nd
targ
et
se
cto
r in
du
str
ies
in
th
e M
56
co
rrid
or
Su
pp
ort
th
e M
an
ch
es
ter
Re
gio
na
l P
ole
Su
pp
ort
th
e g
row
th o
f
Ma
nc
he
ste
r a
nd
Liv
erp
oo
l A
irp
ort
s
En
co
ura
ge
th
e r
ed
uc
tio
n
in t
he
ne
ed
to
tra
ve
l
En
ha
nc
e s
tra
teg
ic
tra
ns
po
rt n
etw
ork
eff
icie
nc
y a
nd
im
pro
ve
jo
urn
ey
tim
e r
eli
ab
ilit
y
En
co
ura
ge
mo
de
sh
ift
fro
m c
ar
En
co
ura
ge
a s
hif
t o
f
fre
igh
t fr
om
ro
ad
to
oth
er
mo
de
s
Imp
rov
e a
cc
es
s f
or
no
n-
ca
r u
se
rs
Inc
rea
se
tra
ns
po
rt c
ho
ice
in r
ura
l a
rea
s
Imp
rov
e in
terc
ha
ng
e
be
twe
en
tra
ns
po
rt m
od
es
Imp
rov
em
en
ts t
o a
nd
en
ha
nc
ed
ma
na
ge
me
nt
of
Tra
ns-E
uro
pe
an
Ne
two
rks
Imp
rov
e p
erc
ep
tio
n o
f
pe
rso
na
l s
ec
uri
ty f
or
pu
bli
c t
ran
sp
ort
jo
urn
ey
s
Imp
rov
e r
oa
d s
afe
ty
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n t
he
bu
ilt
an
d n
atu
ral
en
vir
on
me
nt
Min
imis
e t
he
im
pa
cts
of
tra
ns
po
rt u
po
n e
mis
sio
ns
En
co
ura
ge
th
e u
se
of
en
vir
on
me
nta
lly
su
sta
ina
ble
mo
de
s o
f tr
an
sp
ort
RS2aNew rail chord linking Victoria to Deansgate, Oxford
Road and Piccadilly station, along with improv ed
approaches to Piccadilly stationü ü ü ü ü ü ü û ü ü
RS3b
Manchester Airport Western Rail Link including
resignalling of the Styal line and additional platforms at
Manchester Airport,. Access by heavy rail from
Liverpool/Chester/North Wales direc tions. Also can provide for circular Liverpool-Airport service, connecting
Liverpool, Warrington, Manchester Piccadilly, Airport,
Knutsford, Northwich, Runcorn, South Liverpool Parkway.
Alternatively capacity could released the through
Deansgate resulting in improved journey time reliability
to other services
ü ü ü ü ü ü ü ü ü ü û ü ü
RS4aUpgrade of Halton curve to full two-way working with
associated Chester-Liverpool via Runcorn/South
Liverpool Parkway rail serviceü ü ü ü ü ü ü
RS4dMerseytram Line 3 with link between South Liverpool
Parkway and Liverpool John Lennon Airport and serving The Estuary Development
ü ü ü ü ü ü û ü ü
RS4eReopen Ditton rail station in conjunction with proposals
for housing development at Hale Bankû ü ü ü ü
RS4f New rail station at Beechwood û ü ü ü ü
RS5e
New parkway station at M6 Sandbach to be served with
reopened Middlewich and new Manchester Airport Western Link rail services as well as Wilmslow Line
services
ü ü û ü ü ü ü û ü ü
RS7eExtension of Metrolink to Hale with single track parallel
running to heavy rail ü ü ü ü ü
RS10cFull electrification of the Wrexham to Bidston Lineallowing services to connect to Mersey Rail ü ü ü
M56
CO
RR
IDO
RS
CO
PIN
GS
TU
DY
Fin
al R
eport
Page
15
0 o
f 15
0m
56_scopin
g_stu
dy_fin
al_
report.d
oc
Po
ten
tial L
on
g T
erm
Me
as
ure
s
Support the delivery of
strategic regional sites
and growth of existing and
target sector industries in the M56 corridor
Support the Manchester
Regional Pole
Support the growth of
Manchester and Liverpool Airports
Encourage the reduction in the need to travel
Enhance strategic
transport network
efficiency and improve journey time reliability
Encourage mode shift
from car
Encourage a shift of
freight from road to other modes
Improve access for non-
car users
Increase transport choice
in rural areas
Improve interchange
between transport modes
Improvements to and
enhanced management of Trans-European Networks
Improve perception of
personal security for public transport journeys
Improve road safety
Minimise the impacts of
transport upon the built and natural environment
Minimise the impacts of
transport upon emissions
Encourage the use of
environmentally
sustainable modes of transport
RS
10
dIn
cre
ase
in lin
e s
pe
ed
on
Wre
xh
am
-Bid
sto
n lin
e fro
m
exis
ting
sp
ee
d o
f 40
-50
mp
hü
üü
RS
10
eP
rovis
ion
of n
ew
rail s
tatio
n a
t Sh
otto
n w
ith n
ew
bu
s
fee
de
r ne
two
rk c
on
ne
ctin
g th
e n
ew
sta
tion
with
bu
sin
esse
s o
n D
ee
sid
e P
ark
üü
üü
ü
RS
10
fN
ew
rail c
ho
rd lin
kin
g th
e B
idsto
n-W
rexh
am
line
to th
e
No
rth W
ale
s C
oa
st lin
e a
llow
ing
dire
ct s
erv
ice
s
be
twe
en
Liv
erp
oo
l an
d N
orth
Wa
les
üü
üü
RS
11
aN
ew
sta
tion
on
WC
ML
at D
are
sb
ury
Bu
sin
ess P
ark
to
su
pp
ort th
e E
ast R
un
co
rn D
eve
lop
me
nt A
rea
üû
üü
ü
RS
11
bN
ew
sta
tion
on
No
rth-Ch
esh
ire L
ine
at D
elp
h L
an
e to
su
pp
ort th
e E
ast R
un
co
rn D
eve
lop
me
nt A
rea
üû
üü
ü