machining time calculation

9
ESTIMATION OF MACHINING TIME INTRODUCTION: Machining time: It is the time for which the machine works on the component that is from the time when the tool touches the work to when the tool leaves the component after completion of the operations. Terms used in the study of machining time: 1. Length of cut Length of cut = approach length + length of work piece to be machined + over travel 2. Feed 3. Depth of cut 4. Cutting speed Cutting speed = Πdn / 1000m / min CALCULATION OF MACHINING TIME FOR LATHE OPERATION: 1. Turning operation: Turning is the process of removing excess material from the work piece by means of a single point cutting tool. T= L / (F×N) 2. External relief turning: It is the operation of removal of material from a previously turned surface along the same axis and within the limits of turned area. T = L/ (F×N) × NUMBER OF CUTS

Upload: dellibabu509

Post on 27-Dec-2015

38 views

Category:

Documents


0 download

DESCRIPTION

Claculating machining time for Drilling, Turning

TRANSCRIPT

Page 1: Machining Time Calculation

ESTIMATION OF MACHINING TIME

INTRODUCTION:

Machining time:

It is the time for which the machine works on the component that is from the time when the tool

touches the work to when the tool leaves the component after completion of the operations.

Terms used in the study of machining time:

1. Length of cut

Length of cut = approach length + length of work piece to be machined + over travel

2. Feed

3. Depth of cut

4. Cutting speed

Cutting speed = Πdn / 1000m / min

CALCULATION OF MACHINING TIME FOR LATHE OPERATION:

1. Turning operation:

Turning is the process of removing excess material from the work piece by means of a

single point cutting tool.

T= L / (F×N)

2. External relief turning:

It is the operation of removal of material from a previously turned surface along the

same axis and within the limits of turned area.

T = L/ (F×N) × NUMBER OF CUTS

3. Chamfering:

It is the operation of removing material from the edges of external or internal diameters.

T= L / (F×N)

4. Facing:

It is the process of removing material from the ends of the job by moving the tool

perpendicular to the axis of the job.

Page 2: Machining Time Calculation

5. Knurling:

It is the operation of upsetting material so as to produced diamond shaped or

straight lined patterns on the surface of the material.

T = length of cut / feed

6. Drilling: It is the process of producing holes in a material.

7. Boring: It is the operation of enlarging or finishing an internal hole which has been

previously drilled.

8. Reaming: It is the process of removing a small amount of material from a previously

drilled hole.

9. Taping: It is the operation of cutting internal threads with the help of a tool called tap.

10. Threading:

It is the process of removing material to produce helix on external or internal circular

surface for fastening purposes.

ESTIMATION OF MACHINING TIME FOR SHAPING, PLANNING AND SLOTTING

OPERATION:

Formula used:

1. Effective cutting speed (c)

C = L / 1000 × N

Where, L = length of forward stroke

N = number of forward stroke per minutes

2. Cutting speed (s)

If k = time for return stroke / time for forward stroke

S = L (1+K) / 1000 × N

Page 3: Machining Time Calculation

3. Total time for one cut (T)

T = L / (S×1000) + (L×K) /S ×1000

4. Total time required

If p is the number of cuts required then

T = L (1+K) / S×1000× (W/F) ×P

ESTIMATION OF TIME FOR MILLING OPERATION:

Milling is the operation of removing material from a surface by using a rotary multi point

tool called cutter.

Formula used

Milling time: (T = L / F×N)

1. To find feed per revolution

Feed per revolution = feed per tooth × number of cutter teeth

2. To find the time taken per cut

Time taken per cut = (length of job + added table travel) / (feed per revolution × rpm)

Added table travel = ½ × (D- (D^2-W^2) ^ (1/2))

ESTIMATION OF TIME FOR GRINDING OPERATIONS:

Grinding is the process of metal removal by abrasion.

Formula used

Grinding time per cut = length of cut / (feed per revolution × rpm)

Length of cut, L = L0 – w + 5

Total grinding time = (L0 – w +5) / (w/2or w/4) × N ×Number of cut required

Rpm is given by N = 1000×S / 3.14 × D

Number of passes, n = d/t

Page 4: Machining Time Calculation

PROBLEMS:

Example: 1

Estimate the machining time to turn a 4 cm diameter MS bar 10cm long , down to 3.5cm

diameter in a single cut, using high speed steel tool. Assume the cutting speed of the tool to be

30m/min and a feed of 0.30mm/rev.

Solution:

N = 1000s / 3.14 D = 1000 ×30 / 3.14 × 40 = 238.7rpm

T = L / F×N = 1000 / .3 × 238.7 = 1.39min

Example: 2

An operator is required to tap a hole with 20mm dia tap to length of 35mm having 3

threads per cm. The cutting speed is 10m/min and the number of cut required is 4. The return

speed of the tap is to be 3 times the cutting speed. How much time will be taken to cut these

internal threads?

Solution:

N = 1000s / 3.14 D = 1000 × 10 / 3.14 ×20 = 159.15rpm

Pitch = 1/ threads per cm = 1/ 3 = 3.33mm

Time for taping per cut, T1 = L + (D/2) / (Pitch × rpm) = 0.27min

Return speed = 3 × cutting speed

Return time, T2 = 1 / 3 tapping time = 1/3 × 0.27 = 0.092min

Total time for one cut = T1 + T2 = 0.27 + 0.092 = 0.369min

Total time for tapping = 0.369 × 4 = 1.47min

Example: 3

A MS bar of 120mm long and 40mm diameter is turned to 38mm diameter and was again

turned to a diameter if 35mm over a length of 50mm as shown in figure. The bar was chamfered

at both the ends to give a chamfer of 45 degree×4mm after facing. Calculate the machining time.

Assume cutting speed of 50m per min and feed 0.3mm/rev the depth of cut is not to exceed 3mm

in any operation.

Page 5: Machining Time Calculation

FIGURE 11.16

Solution:

1. First operation: turning from 40mm diameter to 38mm diameter and 120mm long

N = 1000 × 50 / 3.14 × 40 = 397.89rpm

Time taken for turning, T1 = 120/.3 × 397.89 = 1.005min

2. Second operation: external relief from 38mm diameter to 35mm diameter and 50mm long

N = 1000×50 /3.14 × 38 =418.83 rpm

Time taken for external relief, T2 = 50/.3 × 418.83 = 0.4min

3. Third operation: facing of both ends

L = 38/2 = 19mm

N = 1000 × 50 / 3.14 × 38 = 418.83rpm

Time for facing one end = 19 /0 .3× 418.83 = 0.15min

Time for facing both ends, T3 = 0.15 × 2 = 0.30min

4. Fourth operation: chamfering 45degree × 4mm on both sides

N = 1000 × 50 / 3.14 × 38 = 418.83rpm

Time for chamfering on both sides, T4 = 0.032 × 2 = 0.064min

Machining time (or)

Total machining time, T = T1 + T2 +T3 +T4 = 1.005 +0.4 + 0.30 +0.064 = 1.77min

Page 6: Machining Time Calculation

Example: 4

Find the time required on the shaper to complete one cut on a plate 600 × 900mm, if the

cutting speed is 6m/min. The return time to cutting time ratio is 1:4 and the feed is 2mm per

stroke. The clearance at each end along the length is 75mm.

Solution:

Length of stroke = length of plate + clearance on both sides

= 900 + 2 × 75 =1050mm

T = L (1+k) / s×1000 × w/f

= 1050 × 1.25 / 6000 ×300

= 65.62min

Example: 5

A face milling cutter of 150mm diameter is used to give a cut on a block

500mm×250mm. The cutting speed is 50m /min and feed 0.2mm/rev. Calculate the time required

to complete one cut.

Solution:

N = 1000 × 50 / 3.14 × 150 =106.1rpm

L = 500mm, w = 250mm

Approach = 0.5D = 0.5 × 150 = 75mm

Over travel = 7mm

Added table travel = approach +over travel

=75 + 7 =82mm

Milling time per cut = (length of the job + added table travel) / feed per revolution

= 582 / 0.2 × 106.1 = 27.43min

Example: 6

Find the time required for doing rough grinding of a 15cm long steel shaft to reduce its

diameter from 4 to 3.8cm with the grinding wheel of 2cm face with assume cutting speed as

15m/min and depth of cut as 0.25min.

Solution:

For rough cut: feed = w/2 = 20/2 = 10mm/rev

Page 7: Machining Time Calculation

N =1000 × 15 / 3.14 × 40 = 119.37rpm

Number of passes required = depth of stroke to be removed / depth of cut

= ((40-38)/2) / 0.25 = 4

Length of cut, L =L0 – w + 5

= 150 – 20 + 5 =135mm

Total grinding time = length of cut / (feed per revolution × rpm) number of passes

= 135 / (10×119.37) ×4 = 0.452min