madrid 27 th october 2009
DESCRIPTION
Results of the First Phase of the OS 11 th IG meeting. Madrid 27 th October 2009. Summary. Planning of the OS: First Phase Incidents found in the process. 1 – Planning of the OS. July – October 2009: Middle-July: Publication of the final versions of the documents: - PowerPoint PPT PresentationTRANSCRIPT
Madrid
27th October 2009
Results of the First Phase of the OS
11th IG meeting
2
Summary
1. Planning of the OS: First Phase
2. Incidents found in the process
3
1 – Planning of the OS
July – October 2009:
Middle-July: Publication of the final versions of the documents:
Information Memorandum and allocation Rules
Letter of commitment and requesting forms
Non disclosure Agreement (NDA) between TSO and Shippers
Contract Booking between each TSO and Shippers
End-July: Information meeting with the Shippers.
Before 31 July: Signature of the NDA between each TSO and Shippers.
30 September: Deadline for sending the request form and Letter of Commitment for the First Phase of the 2013 Capacities.
30 October: Publication of the results of the First Phase of the OS.
4
1 – Planning of the OS: First Phase
November 2009• Before November 30th: Signature of a capacity booking contract or transmission
contract between each TSO and interested subscribers (2013 capacities).
January 2010• Approval of GRTgaz and TIGF global investment programs by their respective Boards
of Directors (2013 capacities).
• Approval of GRTgaz and TIGF global investment programs by CRE (2013 capacities).
5
2 – Incidents founded in the processNº Incident OS Status
1 2013
2015
SOLVED
2 2015 ADMITTED
3 2015 ADMITTED
4 2015 ADMITTED
5 2015 ADMITTED
6 2015 SOLVED
7 2015 SOLVEDCONFIDENTIA
L