major mackenzie drive schedule ‘c’ environmental
TRANSCRIPT
Major Mackenzie Drive Schedule ‘C’ Environmental Assessment Study
From McNaughton Road / Avro Road to Keele Street
Regional Municipality of York December 20, 2018
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-1
Executive Summary
Introduction
The Regional Municipality of York (York Region) has completed a Schedule “C” Municipal Class
Environmental Assessment (EA) study to review the short-term transportation operational needs
along Major Mackenzie Drive West (referred to as Major Mackenzie Drive for the purpose of this
report), from McNaughton Road / Avro Road to Keele Street in the City of Vaughan.
York Region is responsible for monitoring its transportation network and implementing required
improvements in a timely manner. Concerns raised regarding traffic operations on Major Mackenzie
Drive within the study limits included challenging access to and from businesses, congestion, queuing
and need for pedestrian crossings. These issues led York Region to investigate short-term (2020)
operational improvements for the corridor. A future EA study will assess the long-term transportation
needs (as recommended by the YR-TMP 25-year outlook), including capacity and multi-modal
improvements.
York Region retained HDR to conduct the Major Mackenzie Drive Class EA study. This
Environmental Study Report (ESR) documents the study consultation and decision making rationale,
following the process outlined in the Municipal Engineers Association (MEA) Municipal Class EA
guidelines for Schedule ’C’ projects (October 2000, as amended in 2007, 2011 and 2015).
The study area crosses the West Don River tributary. Due to the poor structural condition of the
culvert at that location, replacement of the structure (ID 25-18 C1180) was recommended. On
account of the emergency nature of the culvert replacement, this work is being conducted separately
from the Major Mackenzie Drive Schedule “C” EA study in consultation with the Ministry of the
Environment, Conservation and Parks, Toronto Region Conservation Authority and City of Vaughan.
The culvert replacement is being undertaken as a Schedule “A” Class EA study.
Background
This EA study builds on the recommendations from the Region’s 2015 Traffic Operations Assessment
Memorandum which had previously been conducted to determine an appropriate solution to improve
traffic operations on Major Mackenzie Drive. The EA reconfirms the previous analysis findings,
reviews the needs and justification more closely in terms of corridor-specific constraints, and
evaluates alternative solutions and designs to address the existing issues along Major Mackenzie
Drive. Active transportation, access modifications and new pedestrian facilities were also examined to
improve conditions for all travel modes.
Study Purpose
York Region was notified by the City of Vaughan of a number of operational issues in the study
corridor, including challenging access to and from the land uses on either side of Major Mackenzie
Drive, and heavy through traffic and queuing, particularly in the eastbound direction at Keele Street.
The purpose of the Class EA study was to determine specific short-term transportation improvements
to Major Mackenzie Drive between McNaughton Road/Avro Road to the west and Keele Street to the
east for the horizon year of 2020. A future EA study will assess long-term transportation needs,
including capacity and multi-modal improvements to the corridor.
In particular, the EA study:
Reviewed existing conditions and operational challenges along this section of Major Mackenzie
Drive
Identified opportunities for improvement and possible solutions
Investigated and recommended alternative designs for the preferred solution
Collected, documented and assessed input and feedback from residents and affected groups
within the study area
Study Area
The study area is 1.4 km long and is bounded by McNaughton Road/Avro Road to the west and
Keele Street to the east, in the Village of Maple, located in the City of Vaughan. Major Mackenzie
Drive within the study limits is currently a 4-lane urban arterial road with a posted speed limit of 50
km/h. The street intersects McNaughton Road / Avro Road, Killian Road / Netherford Road, Gram
Street, Jackson Street and Keele Street.
This section of Major Mackenzie Drive is characterized by a combination of low-rise residential,
mixed-use, commercial as well as institutional buildings and has a number of closely spaced
driveways. The study area is presented visually.
The corridor was divided into three segments (west, central, and east) to develop a preferred
alternative design concept while taking into consideration existing conditions and the localized
constraints of each identified segment. The segment limits were generally defined and characterized
by existing and planned built form (intersecting streets, properties/land use and associated access)
and existing right-of-way for the purposes of generating alternative design concepts and evaluation.
* West Don River Crossing proceeding under separate EA – Schedule A
*
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-2
West Segment - McNaughton/Avro Road to Gram Street
The available ROW is approximately 36m
The boulevard is wider on the north side
Limited access points fronting onto the street
Raised centre roadway median in front of the plaza
Utility poles are located primarily on the south side; street lights on the north
West Don River tributary crossing
Central Segment Gram Street to Jackson Street
The available ROW varies between 25-28m
The boulevard is wider on the north side
Numerous closely spaced driveways
Located within the Village of Maple Heritage Conservation District
Utility poles/street lights located primarily on the south side adjacent to the road
East Segment Jackson Street to Keele Street
The available ROW is approximately 28m
Narrow ROW at the Keele Street intersection
Space limitations due to building facades directly abutting the property lines
Located within the Village of Maple Heritage Conservation District
Utility poles/street lights located on both sides of the road
Needs Assessment
The needs assessment involves the identification and evaluation of short-term needs of the
transportation network with respect to accommodating all users (pedestrians, cyclists, transit users,
and motorists). The purpose of the Needs Assessment is to identify and define conditions, safety, and
operational needs along Major Mackenzie Drive between McNaughton Road/Avro Road and Keele
Street.
Transportation Needs
A summary of transportation needs for the Major Mackenzie Drive corridor is summarized below:
Driving Under existing conditions, all signalized intersections within the study area are operating near
or over the available capacity during peak periods. The conditions are worse at the Major
Mackenzie Drive and Keele Street signalized intersection where the overall level of service
(LOS) is ‘F’ during the weekday AM and PM peak hours. Generally, traffic operations appear
to be worse in the afternoon compared to the morning peak period. Extensive queuing was
observed in the segment between Keele Street and Killian Road/Netherford Road, especially
in the eastbound direction, resulting from the high volumes of eastbound-through trips at
Keele Street.
Because of the existing congestion and the abundance of access points along Major
Mackenzie Drive, vehicles attempting to enter or exit the various driveways are often unable
to do so immediately. They must wait for gaps in opposing traffic, blocking vehicular flow and
further exacerbating congestion along the study area. Traffic conditions are not anticipated to
change significantly by 2020 due to the minimal growth in the study area.
The analysis of the five-year collision record (2009-2013) did not indicate any unusual
collision rates within the study area limits. The highest collision rate was observed at the
McNaughton Road/Avro Road intersection and in the segment spanning Jackson Street to
Keele Street. Existing congestion on Major Mackenzie Drive during peak periods may
increase motorist’s potential exposure to collisions. Conflicting pedestrian activities in the
area may become a greater safety issue as the area develops in the future.
Walking The look, feel, and function of the study corridor changes along its length as does the level of
comfort experienced by pedestrians. Overall, the pedestrian experience could be improved
as Major Mackenzie Drive receives for the most part a ‘D’ score, according to the multi-modal
level of service analysis performed. Generally, the north side of Major Mackenzie was found
to be more accommodating to pedestrians, through wider sidewalks and boulevards
separating them from vehicles. The large separation distance between the intersections at
Killian Road / Netherford Road and Keele Street was identified as an issue for pedestrian
safety by community members who, prior to this study, had circulated a petition requesting a
protected crosswalk to facilitate safe crossing in the area.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-3
Cycling
At the present time, cyclists do not have a dedicated space in the right-of-way as there are
no designated cycling facilities on Major Mackenzie Drive. Cyclists must share the roadway
with vehicles or ride on the sidewalks in the study area. Therefore, the cycling level of service
along the study area was found to be low, receiving a LOS E according to the multi-modal
level of service analysis performed.
Transit The corridor is served by four mixed traffic bus routes – Routes 560, 462, 4 and 4A– however
only Routes 4 and 4A provide regular service throughout the day. The average bus stop
spacing of 400m is well within the range set by York Region Transit`s Transit Services
Guidelines, which state that the typical bus stop spacing for local bus routes should typically
be between 300m and 500m. Because bus service is hindered by existing congestion,
improvements recommended under this EA study will also benefit transit operations.
Problem and Opportunity Statement
Major Mackenzie Drive is a continuous, regional arterial road which spans York Region from its
western boundary with Peel Region and its eastern boundary with Durham Region, providing a major
east-west transportation corridor connecting to north-south regional arterials and Highways 400 and
404.
The historic Village of Maple is centered at the intersection of Major Mackenzie Drive and Keele
Street. As such, between McNaughton Road/Avro Road and Keele Street, the surrounding land use
context is relatively urban and composed of low to mid-rise land uses including residential, mixed-
use, commercial and institutional buildings with a number of driveway accesses located on both sides
of the street.
Major Mackenzie Drive is both a busy traffic thoroughfare and an urban village core. The following
transportation issues were identified:
Due to heavy through traffic volumes, there are limited gaps in traffic flow, making access to and
from the commercial and residential parking lots challenging.
Delays in access to driveways exacerbate already heavy traffic queues by blocking through traffic
on Major Mackenzie Drive.
The intersection of Major Mackenzie Drive and Keele Street exceeds capacity during peak
periods resulting in significant eastbound queuing which further impacts driveway accesses west
of Keele Street.
The significant number of driveway access points creates conflict points reducing the pedestrian
and cyclist experience along the corridor.
Current conditions for mixed traffic transit services results in poor transit operating conditions
during peak hours.
Concerns regarding the lack of a pedestrian crossing between Killian Road / Netherford Road and
Keele Street were raised by members of the public through a signed petition
Potential opportunities to address the aforementioned transportation issues require further study and include:
Realignment and consolidation of commercial/residential access points.
Scheduling delivery during off-peak hours and at night.
Installation of a traffic signal and protected pedestrian crossing between Killian Road/Netherford
Road and Keele Street to enhance safety and accessibility.
Implementing a centre left-turn lane to provide additional space and storage for driveway access
movements.
Intersection improvements at Keele Street to reduce vehicle queuing and capacity issues.
Streetscaping enhancements to encourage walking
The addition of a protected crossing between Killian Road / Netherford Road and Keele Street.
As this study focuses on the short-term (2020) operational needs and opportunities of the corridor, a
future EA study will assess the long-term transportation needs, including capacity improvements. The
future EA will be undertaken on the basis of the recommendations/findings of the York Region
Transportation Master Plan 25-year outlook and long-term projects.
Public, Agency and Aboriginal Group Consultation
Public input was an important part of the Major Mackenzie Drive EA. The project team engaged the
general public online, through mail and email notifications, in print, and through public Open Houses
to ensure ample opportunity for participation in the planning process. An overview of the key
consultation milestones is provided.
Engagement Strategy Date
Notice of Commencement
March 30, 2017 and April 6, 2017 – Published in the
Vaughan Citizen newspaper with local circulation
March 30, 2017 – Notice Issued
Notice of Open House #1
October 12, 2017 and October 19, 2017 – Published
in Vaughan Citizen newspaper with local circulation
October12, 2017 – Notice Issued
Open House #1 October 25, 2017 (Vaughan City Hall)
Notice of Open House #2
April 26, 2018 and May 10, 2018 – Published in the
Vaughan Citizen, Thornhill Liberal East and West
newspapers with local circulation
April 26, 2018 – Notice Issued
Open House#2 May 15, 2018 (Vaughan City Hall)
Notice of Study Completion
December 20, 2018 & December 27, 2018
Published in the Vaughan Citizen and Thornhill Liberal
newspapers with local circulation
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-4
Public, stakeholder and agency consultation was critical to ensure concerns from residents and
affected groups within the study area are identified, documented, and assessed. A variety of
Stakeholder groups have been identified, including the individual agencies and utilities, Indigenous
groups, ratepayer organizations, specific interest groups, and the general public. All of these
stakeholders were contacted throughout the study and encouraged to provide input and become
involved in the development of the solutions and designs to address the problems and opportunities
identified for the study area.
Communication with stakeholder groups and the public took place through:
• Letters
• Emails
• Phone calls
• Notices
• Newspaper advertisements
• The project website (www.york.ca/wps/portal/yorkhome/transportation/Major-Mackenzie-Drive-
Keele-EA)
• Social media posts (York Region Twitter and Facebook accounts)
• Meetings
• Two rounds of Open Houses
York Region was the central link for all communications. The communication and consultation was
conducted in compliance with the Accessibility for Ontarians with Disabilities Act (AODA).
As part of the EA process, individual meetings and conference calls were held with agencies and
stakeholders such as the Ministry of Natural Resources and Forestry (MNRF), the Toronto Region
Conservation Authority (TRCA), the Ministry of Environment, Conservation and Parks (MECP,
formerly the MOECC), the City of Vaughan and individual property owners.
Aboriginal Group representatives were included in the mailing list for the project, and were contacted
via study notices throughout the study (including the Notice of Commencement, Notice of Public
Open Houses, and Notice of Completion). The project team followed up with those groups that had
not provided input, to ensure they had no concerns about the project. The mailing list was updated
periodically as the study progressed to reflect additional Aboriginal Group representatives or update
contact information as needed. No major concerns were raised throughout the study.
Alternative Solutions
Alternative solutions are functionally different ways of approaching and dealing with a problem or
opportunity. The following alternative solutions were considered to address the problems and
opportunities identified for the Major Mackenzie Drive EA study:
Alternative 1:
Do Nothing
Alternative 1 assumes that no transportation
improvements are made. As the existing
infrastructure is unable to accommodate current
needs, this alternative does not address the problem.
Alternative 2:
Transportation System Management
Alternative 2 proposes signal timing optimization and
coordination. Despite moderate improvements to road
operations, this alternative does not improve the
socio-economic environment and, on its own, cannot
address the problem and opportunity statement.
Alternative 3:
Widen for Centre Left-Turn Lane
This alternative proposes to implement a centre left-
turn lane to help reduce delays caused by cars
turning left into driveways. It is the option most likely
to yield the best transportation benefits but also has
the highest cost. The public expressed their support
for this alternative at Open House #1.
Alternative 4:
Intersection Improvements at Keele
Street
Alternative 4 recommends adding an eastbound right-
turn lane and extending the eastbound left-turn lane
at the Keele Street intersection. Having been
identified as a concern in the needs assessment,
intersection operations at Keele Street will improve
under this alternative.
Alternative 5:
New Traffic Signal / Pedestrian
Crossing between Killian Road and
Keele Street
Alternative 5 proposes adding a new traffic signal
and/or pedestrian crossing between Killian Road /
Netherford Road and Keele Street to facilitate safer
pedestrian movements and controlling vehicular flow
along this segment of the corridor. Analysis has
shown the potential for moderate improvement to
transportation operations. The public was supportive
about a new protected crossing between Killian Road
and Keele Street.
Alternative 6:
Consolidate Commercial Entrances
and Driveways
Alternative 6 proposes to minimize the number of
access points to reduce opportunities for traffic
blockage while eliminating conflict points and
improving pedestrian conditions. This alternative
being contingent on property owner consensus
makes it less likely to be adopted.
To determine the most appropriate solution for the corridor, the advantages and disadvantages of
each of the alternative solutions were evaluated on their abilities to meet socio-economic,
transportation, natural environment and financial goals and objectives.
Based on the evaluation process performed, the preferred solution consisted of the following:
Alternative 2: Transportation System Management
Alternative 3: Widening for a centre left-turn lane
Alternative 4: Intersection improvements at Keele Street (i.e. extended eastbound left-turn lane
and new eastbound right-turn lane)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-5
Alternative 5: New traffic signal / pedestrian crossing between Killian Road and Keele Street.
Stakeholder input supported the inclusion of active transportation facilities in the study area. The
preferred solution therefore also aimed to accommodate cyclists and pedestrians to the extent
possible. The feasibility of different active transportation facilities was reviewed as part of the
alternative design evaluation process.
Alternative Designs for the Preferred Solution
A long list of alternative design concepts was developed around three segments West, Central and
East, the limits of which were generally defined by existing and planned built form (intersecting
streets, properties/land use and associated access) and existing right-of-way for the purposes of
generating alternative design concepts and evaluation. The long list of alternative design concepts
was short- listed following stakeholder input and consultation. The long-list was reduced to the
following design concepts:
West Segment – Major Mackenzie Drive between McNaughton Road / Avro Road and Gram Street Alternative Design 3A (Reduced lane widths + CLTL + Sidewalks) Reconfigure/repurpose the existing roadway to add a centre left-turn lane from east of the
West Don River tributary to Gram Street while maintaining the sidewalks in their current
location. This option attempts to retain existing edges of pavement to the extent possible while
reconfiguring the roadway. Where required, widening will occur about the existing centerline
utilizing reduced lane widths.
Alternative Design 3B (Reduced lane widths + CLTL + MUP on one or both sides)
Reconfigure/repurpose the existing roadway to add a centre left-turn lane from east of the
West Don River tributary to Gram Street. Install an MUP on one or both sides. This option
attempts to retain existing pavement edges to the extent possible while reconfiguring the
roadway. Where required, widening will occur about the existing centerline utilizing reduced
lane widths.
Central Segment – Major Mackenzie Drive between Gram Street and Jackson Street
Alternative Design 2A (Reduced lane widths + CLTL + Sidewalks)
Maintain south edge of pavement and shift the centerline alignment north to implement a two-
way centre left-turn lane using reduced lane widths. Re-instate a sidewalk on the north side
and maintain the existing sidewalk on the south boulevard.
Alternative Design 2B (Reduced lane widths + CLTL + MUP on north side)
Maintain south edge of pavement and shift the centerline alignment north to implement a two-
way centre left-turn lane using reduced lane widths. Install an MUP on the north side and
maintain the existing sidewalk on the south side.
East Segment – Major Mackenzie Drive between Jackson Street and Keele Street
Alternative Design 1A (Standard lane widths + RTL + Sidewalks)
Implement an eastbound right-turn lane while shifting the centerline north and using standard
element widths, with the remaining ROW utilized for public space.
Alternative Design 1B (Reduced lane widths + RTL + Sidewalks)
Implement an eastbound right-turn lane while shifting the centerline north and using reduced
lane widths, with the remaining ROW utilized for public space.
To improve transportation conditions along Major Mackenzie Drive, Designs 3B, 2A, and 1B were
recommended for the west, central and east segment, respectively.
To address the lack of pedestrian crossings and to provide an additional protected crossing, 6
potential locations were examined, including:
1. Gram Street / 2414 Major Mackenzie Drive
2. 2354 Major Mackenzie Drive
3. 2332 Major Mackenzie Drive
4. Golden Spruce Lane / Jackson Street
5. East of Gram Street, Pedestrian Actuated
6. West of Jackson Street, Pedestrian Actuated
A traffic signal at Gram Street / 2414 Major Mackenzie Drive was selected based on a comprehensive
review of the alternatives.
Preferred Design
The preferred design for Major Mackenzie Drive was chosen after consideration of transportation
service for all road users (motorists, pedestrians, cyclists, and transit users) and impacts to the
environment, cultural heritage impact, and socio-economic impacts, safety, aesthetics, drainage,
driveway access, property requirements, and capital construction and maintenance costs.
The preferred design for each segment is one that reflects best the goals of the EA and balanced the
infrastructure improvements with the anticipated impacts. The preferred design was developed and
refined through extensive consultation with agencies, stakeholders, and the public.
The recommended improvements to Major Mackenzie Drive between McNaughton Road/Avro Road
and Keele Street are as follows:
Roadway The preferred design generally consists of a new two-way centre left-turn lane between Gram Street
and Jackson Street and a westbound left-turn lane at St. David’s Church access (as there are no
access points on the north side of Major Mackenzie Drive west of Killian Road / Netherford Road).
The roadway centreline will be shifted to the north between Gram Street and Keele Street to
accommodate the additional centre turning lane while maintaining the curb line on the south side of
Major Mackenzie Drive. Between the West Don River tributary (St. David’s Church) and Killian Road /
Netherford Road, the proposed lane modifications are to be completed within the existing pavement
edges to save costs and minimize disruption. The use of reduced lane widths is recommended for the
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-6
entire study area. A raised median is recommended to separate eastbound and westbound traffic at
certain locations such as between the 2266 Major Mackenzie Drive and Keele Street and St. David’s
Church and Killian Road / Netherford Road. At the eastern limit of the study area, a right-turn lane is
proposed to alleviate queuing at the Keele Street intersection. No property acquisition is required to
implement the preferred design.
Active Transportation The preferred design incorporates two-way off-road multi-use paths (MUP) on the north and south
sides of Major Mackenzie Drive between McNaughton Road / Avro Road and Killian Road /
Netherford Road. The design of the MUPs is based on Ontario Traffic Manual (2014) OTM Book 18 –
Cycling Facilities, which provides guidelines for the design of safe active transportation facilities and
intersection treatments. The MUPs will have a minimum 3.0 m width. The selection of material type
and treatment for the MUPs will be revisited and confirmed during detailed design. Public and
stakeholder consultation indicated support for the introduction of active transportation facilities into
the preferred design.
The south side of Major Mackenzie Drive will receive an enhanced 2.4m sidewalk from Killian Road /
Netherford Road to Gram Street. East of Gram Street, the existing sidewalk will be maintained to
Jackson Street. The north side of the road from Killian Road / Netherford Road to Keele Street as well
as the south side from Jackson Street to Keele Street will accommodate pedestrians to a greater
extent through a more generous public space and enhanced paving treatment.
Other Operational Improvements In addition to the aforementioned design solutions, the project team assessed access restrictions and
signalization to further improve operations along the study area. The following operational
improvements were recommended as part of the Preferred Design to supplement the roadway
geometric improvements:
New Traffic Signal at Gram Street and realignment of the 2414 Major Mackenzie Drive driveway
Right-in-right-out (RIRO) access at Jackson Street where westbound left turns onto and out of
Jackson Street are no longer permitted
¾ access at Golden Spruce Lane where eastbound-left movements are no longer permitted (only
right-in, right-out and left-in onto Golden Spruce Lane are allowed).
¾ access at 2266 Major Mackenzie Drive where eastbound left movements are still permitted
(only right-in, right-out and left-in into the parking lot are allowed.
It must be noted that Council approvals may be required for the implementation of the traffic signal at
Gram Street as the signal does not meet the Traffic Signal Warrant.
Signage and pavement markings will be included as part of the detailed design and will be in
accordance with the York Region Pedestrian and Cycling Planning and Design Guidelines and
Ontario Traffic Manual (OTM) Book 18: Cycling Facilities.
Streetscaping and Landscaping
The preferred design acknowledges that the study area lies within the Village of Maple Heritage
Conservation District and reflects the goals and objectives set out in the Village of Maple Heritage
Conservation District Plan (2006). Between Jackson Street and Keele Street, streetscaping features
involve planters, bollards, red unit pavers, ornamental lighting, bollards and street furniture. A visual
depiction of the preferred design is presented below, looking west at Major Mackenzie Drive and
Keele Street.
At the western edge of the study area, the preferred design includes a multi-use path (MUP) on the
north and south sides of the street. The MUPs are separated from the roadway by raised concrete
tree planters. The raised planter edges provide space for seating while a concrete median delineates
bi-directional vehicular traffic.
Public amenity areas are planned to connect Major Mackenzie Drive with the future recreational trail
along the West Don River Valley. The public amenity areas will enable trail access on both the north
and south sides of the street and will include benches, planting beds, shade trees and sitting blocks.
It must be noted that streetscape enhancements proposed by the City of Vaughan per the Village of
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ES-7
Maple Heritage Conservation District Plan will have to be coordinated with York Region at the
Detailed Design stages of the project. As these enhancements are not a regional standard, they are
eligible for partnership funding through York Region’s Municipal Streetscape Partnership Program.
Geotechnical and Pavement
A geotechnical assessment was conducted. The existing pavement structure on this section of Major
Mackenzie Drive does not satisfy York Region’s requirements for an arterial road and significant
strengthening is required to upgrade the road to support future traffic based on the projected growth.
A number of pavement rehabilitation options were reviewed. The preferred option based on the grade
raise restriction is full depth reconstruction.
Drainage and Stormwater
Overall, the existing drainage patterns and locations will not be altered with the proposed roadway
improvements. However, the improvements will result in an additional pavement area of 0.57
hectares within the existing right-of-way of Major Mackenzie Drive.
To augment the increase in pavement area, over-sized storage pipes are proposed immediately
upstream of the storm connection pipes/outfall to provide the required storage volume for peak flow
control. In addition, an oil-grit separator is proposed prior to discharge into the West Don River. The
OGS will provide water quality treatment to a 1.32 hectare pavement area. Proposed roadway
drainage will be collected by a series of catchbasins and conveyed by storm sewers to storm outlets
at each of the drainage outfall locations along the corridor. The roadway design should ensure that
major system runoff up to the 100 year event can safely be conveyed to watercourse locations and
should allow one lane in each direction to be clear of any flooding.
Preliminary Cost Estimate
Based on the preliminary cost estimates, the cost of the recommended improvements is estimated at
$6.0 million. The preliminary cost estimate includes cost for roadwork, active transportation,
illumination, utilities, landscaping, traffic signals and engineering. The costs associated with the
culvert replacement emergency work at the West Don River crossing is not included as part of the
Major Mackenzie Drive EA Study. These preliminary cost estimates are to be reviewed and confirmed
during detailed design.
Culverts and Structures
The findings of the Culvert Inspection Report indicated that the existing corrugated steel arch culvert
at the West Don River crossing is in very poor condition and that immediate replacement of the
culvert is recommended. Due to the urgent nature of the culvert works, the replacement project is
being undertaken separately as a schedule “A” Class EA and is not part of this study.
Environmental Effects and Mitigation
Anticipated impacts to the natural, socio-economic, and cultural environments together with proposed
mitigation measures were identified to address the implementation of the preliminary preferred
design. Socio-economic analysis included air quality and traffic noise/vibration analysis. Natural
environment impacts include aquatic habitat and fisheries, vegetation and vegetation communities,
wildlife and wildlife habitat, and contamination. Cultural impacts include built heritage and cultural
heritage landscape features, and archaeology.
In general, impacts associated with the proposed Major Mackenzie Drive improvements are minor in
nature and can be mitigated. Although the West Don tributary culvert replacement is a technically
complex undertaking, it is being completed as a separate EA that will ensure impacts are minimized.
Timing of Implementation and Future Commitments
The Major Mackenzie Drive EA study is not currently identified in York Region’s 10-year Capital
Construction Program (2018-2027). Subject to approval of the Environmental Assessment, the timing
of construction will be confirmed through the Region’s project prioritization process. The capital
construction program is reviewed annually and projects may be advanced (or deferred) subject to
other regional priorities and available funding.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | i
Table of Contents
Executive Summary ........................................................................................................................................ i
1 Introduction .......................................................................................................................................... 1
Study Area ................................................................................................................................. 1 1.1
Purpose of the Project ............................................................................................................... 1 1.2
Study Organization .................................................................................................................... 1 1.3
The Project Team ......................................................................................................... 1 1.3.1 The Consultant Team ................................................................................................... 2 1.3.2
Study Process ............................................................................................................................ 2 1.4
The Municipal Class Environmental Assessment (Class EA) ...................................... 2 1.4.1 Part II Orders ................................................................................................................ 2 1.4.2 Canadian Environmental Assessment Act (CEAA) ...................................................... 3 1.4.3
2 Provincial, Regional and Municipal Context and Growth ..................................................................... 3
Provincial Planning Context ....................................................................................................... 3 2.1
Regional Planning Context ........................................................................................................ 4 2.2
York Region Transportation Master Plan (2016) .......................................................... 5 2.2.1 Traffic Operations Assessment Memorandum (2015) .................................................. 6 2.2.2 Viva Network Expansion Plan Design .......................................................................... 6 2.2.3
Municipal and Other Relevant Planning Policies ....................................................................... 7 2.3
3 Public and Stakeholder Consultation ................................................................................................... 8
Consultation Approach .............................................................................................................. 8 3.1
Public Consultation .................................................................................................................... 8 3.2
Agency and Stakeholder Consultation..................................................................................... 10 3.3
Aboriginal Group Consultation ................................................................................................. 10 3.4
4 Existing Conditions ............................................................................................................................ 11
Existing Transportation Inventory ............................................................................................ 11 4.1
Road Network ............................................................................................................. 11 4.1.1 Network Connectivity and Continuity .......................................................................... 14 4.1.2 Existing Truck Restrictions ......................................................................................... 14 4.1.3 Transit Network ........................................................................................................... 14 4.1.4 Pedestrian and Cycling Facilities ................................................................................ 15 4.1.5 Driveways and Accesses ............................................................................................ 15 4.1.6
Socio-Economic Environment .................................................................................................. 16 4.2
Existing Land Use ....................................................................................................... 16 4.2.1 Archaeology ................................................................................................................ 16 4.2.2 Built Heritage and Cultural Landscape Features ........................................................ 19 4.2.3
Natural Environment ................................................................................................................ 19 4.3
Fisheries and Aquatic Habitat ..................................................................................... 19 4.3.1 Vegetation and Terrestrial Habitat .............................................................................. 20 4.3.2 Wildlife and Wildlife Corridors ..................................................................................... 20 4.3.3 Designated Natural Areas ........................................................................................... 20 4.3.4 Fluvial Geomorphology ............................................................................................... 20 4.3.5
Contamination .......................................................................................................................... 21 4.4
Source Water Protection .......................................................................................................... 23 4.5
Geotechnical Investigations .................................................................................................... 23 4.6
Drainage and Stormwater Management ................................................................................. 23 4.7
Watercourse Crossing Structures ........................................................................................... 24 4.8
Utilities and Other Services ..................................................................................................... 24 4.9
Water and Wastewater Management ......................................................................... 24 4.9.1 Illumination ................................................................................................................. 24 4.9.2
Road Geometrics..................................................................................................................... 24 4.10
Vertical and Horizontal Alignment .............................................................................. 24 4.10.1
Urban Development ................................................................................................................ 25 4.11
5 Needs Assessment............................................................................................................................ 25
Existing Transportation Operations ......................................................................................... 25 5.1
Traffic Volumes – Peak Hour Turning Movement Counts .......................................... 25 5.1.1 Existing Intersection Operations ................................................................................ 27 5.1.2 Queuing ...................................................................................................................... 29 5.1.3 Transit Service Quality ............................................................................................... 30 5.1.4 Pedestrian Quality of Service ..................................................................................... 30 5.1.5 Cyclist Quality of Service ............................................................................................ 31 5.1.6 Public Petition ............................................................................................................. 32 5.1.7
Future Transportation Conditions ............................................................................................ 33 5.2
Future Population and Employment Growth .............................................................. 33 5.2.1 York Region Model ..................................................................................................... 33 5.2.2 Future Road Network ................................................................................................. 34 5.2.3 Future Intersection Operations ................................................................................... 35 5.2.4
Traffic Safety Needs ................................................................................................................ 37 5.3
Collision Analysis ....................................................................................................... 37 5.3.1 Summary .................................................................................................................... 38 5.3.2
6 Problem and Opportunity Statement ................................................................................................. 39
7 Alternative Solutions .......................................................................................................................... 39
Generation of Alternative Solutions ......................................................................................... 39 7.1
2015 York Region Memo Alternative Solutions.......................................................... 39 7.1.1 Proposed Alternative Solutions .................................................................................. 40 7.1.2
Evaluation of Alternative Solutions .......................................................................................... 41 7.2
Evaluation Criteria ...................................................................................................... 41 7.2.1 Traffic Analysis ........................................................................................................... 41 7.2.2
Evaluation Matrix ..................................................................................................................... 43 7.3
Preferred Solution ................................................................................................................... 47 7.4
8 Alternative Designs for the Preferred Solution .................................................................................. 47
Generation of Alternative Design Concepts ............................................................................ 47 8.1
Constraints ................................................................................................................. 47 8.1.1 Corridor Segmentation ............................................................................................... 48 8.1.2
Alternative Design Cross-Sections .......................................................................................... 49 8.2
Summary of Cross-Section Long-list .......................................................................... 49 8.2.1 Design Team Workshop ............................................................................................. 50 8.2.2 Design Criteria ............................................................................................................ 51 8.2.3 Design Cross-Sections Short-list ............................................................................... 52 8.2.4 Evaluation of Alternative Designs .............................................................................. 56 8.2.5
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | ii
Recommended Design ............................................................................................................ 68 8.3
West Segment – McNaughton Road/Avro Road to Gram Street ............................... 68 8.3.1 Central Segment – Gram Street to Jackson Street .................................................... 68 8.3.2 East Segment – Keele Street to Jackson Street ........................................................ 68 8.3.3 Operational Improvements ......................................................................................... 69 8.3.4 Summary of Recommendations ................................................................................. 70 8.3.5
9 Project Description ............................................................................................................................. 70
Design Criteria ......................................................................................................................... 70 9.1
Road Geometry ........................................................................................................................ 72 9.2
Horizontal Alignment ................................................................................................... 72 9.2.1 Vertical Alignment ....................................................................................................... 72 9.2.2
Structural Design ..................................................................................................................... 72 9.3
Typical Cross-Sections ............................................................................................................ 72 9.4
West Segment – McNaughton Road / Avro Road to Gram Street ............................. 72 9.4.1 Central Segment – Gram Street to Jackson Street .................................................... 73 9.4.2 East Segment – Jackson Street to Keele Street ........................................................ 73 9.4.3
Cycling and Pedestrian Facilities ............................................................................................. 73 9.5
Intersections and Access Modifications ................................................................................... 74 9.6
Traffic Signals, Illumination and Signage ................................................................................ 74 9.7
Streetscaping and Landscaping .............................................................................................. 74 9.8
Property Requirements ............................................................................................................ 75 9.9
Drainage / SWM Plan .............................................................................................................. 75 9.10
Geomorphology ....................................................................................................................... 76 9.11
Geotechnical and Foundations Engineering ............................................................................ 76 9.12
Utilities ..................................................................................................................................... 76 9.13
Preliminary Cost Estimate ....................................................................................................... 77 9.14
Constructability, Staging and Detour Considerations .............................................................. 77 9.15
Construction Monitoring and Maintenance Considerations ..................................................... 77 9.16
10 Potential Environmental Effects and Mitigation ................................................................................. 78
Socio-Economic Environment .................................................................................................. 78 10.1
Property Impacts and Access ..................................................................................... 78 10.1.1 Development Impacts ................................................................................................. 78 10.1.2 Air Quality Assessment ............................................................................................... 78 10.1.3 Noise Impact Assessment .......................................................................................... 79 10.1.4
Natural Environment ................................................................................................................ 80 10.2
Vegetation and Vegetation Communities ................................................................... 80 10.2.1 Wildlife and Wildlife Habitat ........................................................................................ 81 10.2.2 Mitigation and Environmental Protection .................................................................... 81 10.2.3 Contamination ............................................................................................................. 82 10.2.4
Cultural Environment ............................................................................................................... 82 10.3
Built Heritage Features and Cultural Heritage Landscape Features .......................... 82 10.3.1 Archaeological Assessment ........................................................................................ 83 10.3.2
Climate Change ....................................................................................................................... 83 10.4
Approach to Climate Change Consideration .............................................................. 83 10.4.1 Potential Climate Change Effects ............................................................................... 83 10.4.2 Climate Change Mitigation .......................................................................................... 84 10.4.3
Source Water Protection ......................................................................................................... 84 10.5
Stormwater Runoff ..................................................................................................... 84 10.5.1 The Application of Road Salt ...................................................................................... 84 10.5.2 The Storage of Snow Related to Roadway Clearing Operations ............................... 84 10.5.3
Key Agency Comments ........................................................................................................... 85 10.6
Ministry of the Environment, Parks and Conservation (MECP) ................................. 85 10.6.1 Toronto and Region Conservation Authority (TRCA) ................................................. 85 10.6.2 City of Vaughan .......................................................................................................... 85 10.6.3
11 Timing of Implementation and Future Commitments ........................................................................ 86
Project Schedule ..................................................................................................................... 86 11.1
Lapse of Time ............................................................................................................. 86 11.1.1
Commitments for Future Work ................................................................................................ 86 11.2
Property Requirements .............................................................................................. 86 11.2.1 Archaeology................................................................................................................ 86 11.2.2 Cultural Heritage ........................................................................................................ 86 11.2.3 Noise .......................................................................................................................... 86 11.2.4 Natural Environment ................................................................................................... 86 11.2.5 Active Transportation Facilities .................................................................................. 86 11.2.6 Streetscaping and Landscaping ................................................................................. 87 11.2.7 Geotechnical and Pavement Design .......................................................................... 87 11.2.8 Groundwater, Hydrogeology, Drainage and Stormwater Management ..................... 87 11.2.9 Utilities ........................................................................................................................ 87 11.2.10 Constructability, Staging and Detours ........................................................................ 87 11.2.11 Additional Consultation and Coordination .................................................................. 87 11.2.12 Summary of Anticipated Permits and Approvals ........................................................ 87 11.2.13
Timing of Improvements .......................................................................................................... 87 11.3
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | iii
List of Tables Table 2-1: Provincial Planning Context ......................................................................................................... 3
Table 2-2: Regional Planning Context ........................................................................................................... 4
Table 2-3: Municipal and Other Planning Context ......................................................................................... 7
Table 3-1: Key Engagement Strategies and Milestones ............................................................................... 8
Table 4-1: Summary of Existing Drainage Areas ........................................................................................ 23
Table 4-2: Existing West Don River Culvert Data ....................................................................................... 23
Table 4-3: Hydraulic Analysis Results for the West Don River Culvert (Existing Condition) ...................... 24
Table 5-1: Turning Movement Count Locations and Dates ......................................................................... 25
Table 5-2: Signalized Intersection Level of Service (HCM 2000) ................................................................ 27
Table 5-3: Existing Signalized Intersection Traffic Operations .................................................................... 27
Table 5-4: Existing Unsignalized Intersection and Entrance Traffic Operations ......................................... 28
Table 5-5: Population and Employment Growth Assumptions (York Region EMME Model) ...................... 33
Table 5-6: York Region Unadjusted Model Volumes for Major Mackenzie Drive ....................................... 34
Table 5-7: Constant Annual Growth Rates (2011-2021 model) .................................................................. 34
Table 5-8: 2020 AM link volumes (Furnessed) ............................................................................................ 34
Table 5-9: 2020 Intersection Traffic Operations (Existing Intersection Configuration) ................................ 35
Table 5-10: Intersection Collision Rates ...................................................................................................... 37
Table 5-11: Segment Collision Rates .......................................................................................................... 37
Table 5-12: Intersection Collision Analysis .................................................................................................. 37
Table 5-13: Segment Collision Analysis ...................................................................................................... 38
Table 5-14: Collision Trends Summary ....................................................................................................... 38
Table 7-1: Improvements Analyzed in the York Region Memo (2015) ....................................................... 39
Table 7-2: Travel Time Savings (York Region Traffic Operations Assessment Memo 2015) ..................... 40
Table 7-3: Proposed Alternative Solutions .................................................................................................. 40
Table 7-4: Alternative Solution Evaluation Criteria ...................................................................................... 41
Table 7-5: Morning Peak Hour Travel Times .............................................................................................. 41
Table 7-6: Afternoon Peak Hour Travel Times ............................................................................................ 41
Table 7-7: Travel Time Savings Results...................................................................................................... 42
Table 7-8: AM Peak Hour Traffic Conditions at the Keele Street intersection ............................................ 42
Table 7-9: PM Peak Hour Traffic Conditions at the Keele Street intersection ............................................ 42
Table 7-10: Evaluation of Alternative Solutions Matrix ................................................................................ 44
Table 8-1: Design Criteria and Assumptions ............................................................................................... 51
Table 8-2: Evaluation Criteria for Alternative Designs ................................................................................. 56
Table 8-3: Evaluation of Alternative Cross-sections (West Segment) ........................................................ 57
Table 8-4: Evaluation of Alternative Cross-sections (Central Segment) ..................................................... 60
Table 8-5: Evaluation of Cross-section Alternatives (East Segment) ......................................................... 63
Table 8-6:Multi-modal Signal Warrant Analysis Results ............................................................................. 69
Table 9-1: Roadway Design Criteria ............................................................................................................ 70
Table 9-2: Active Transportation Design Criteria ........................................................................................ 71
Table 9-3: Access Design Criteria ............................................................................................................... 71
Table 9-4: Drainage Area Summary ............................................................................................................ 75
Table 9-5: Summary of Stormwater Management Plan .............................................................................. 75
Table 9-6: Geomorphic Assessment summary and Crossing Recommendations ..................................... 76
Table 10-1: Cultural Heritage Assessment Resources and Recommendations ......................................... 82
List of Exhibits
Exhibit 1-1: Study Area Map ......................................................................................................................... 1
Exhibit 1-2: Municipal Class EA Process ...................................................................................................... 2
Exhibit 2-1: Proposed ten year cycling network (Source: YR-TMP) ............................................................. 5
Exhibit 2-2: Proposed 2017-2021 Transit Network (Source: YR-TMP) ........................................................ 5
Exhibit 2-3: Proposed 2017-2021 Road network (Source: YR-TMP) ........................................................... 6
Exhibit 2-4: Viva Network Expansion Program – Silver Curbside Bus Route (Source: YRT/VIVA 2016-2020 Strategic Plan) .................................................................................................................................. 6
Exhibit 4-1: Conceptual Cross-Section of Existing Road Looking East ...................................................... 11
Exhibit 4-2: Existing ROW from McNaughton Road/Avro Road to Killian Road / Netherford Road (Source: York Maps) ............................................................................................................................................. 12
Exhibit 4-3: Existing ROW from Killian Road / Netherford Road to Keele Street (Source: York Maps) ..... 12
Exhibit 4-4: Existing Road Network and Lane Configurations .................................................................... 13
Exhibit 4-5: Surrounding Area ..................................................................................................................... 14
Exhibit 4-6: Location of YRT Bus Stops ...................................................................................................... 14
Exhibit 4-7: Barrie GO Line ......................................................................................................................... 14
Exhibit 4-8: North side of Major Mackenzie Drive looking west at Golden Spruce Lane ............................ 15
Exhibit 4-9: South side of Major Mackenzie Drive looking west at Jackson Street .................................... 15
Exhibit 4-10: North side of Major Mackenzie Drive looking west of Killian Road/Netherford Road ............ 15
Exhibit 4-11: South side of Major Mackenzie Drive looking west toward McNaughton Road/Avro Road .. 15
Exhibit 4-12: Location of commercial and residential driveway accesses .................................................. 16
Exhibit 4-13: Land uses along Major Mackenzie Drive ............................................................................... 16
Exhibit 4-14: Stage 1 Archeological Assessment Results .......................................................................... 18
Exhibit 4-15: Cultural Heritage Resources Identified in the Study Area ..................................................... 19
Exhibit 4-16: Potential Contaminated Sites in the Study Area .................................................................... 22
Exhibit 4-17: Source Protection Information in the Vicinity of the Study Area ............................................ 23
Exhibit 4-18: Development in the study area .............................................................................................. 25
Exhibit 5-1: 2015 Existing Weekday AM and PM Peak Volumes ............................................................... 26
Exhibit 5-2: AM Peak Hour Critical Movements .......................................................................................... 29
Exhibit 5-3: PM Peak Hour Critical Movements .......................................................................................... 29
Exhibit 5-4: Existing AM Peak Hour Queuing Conditions ........................................................................... 30
Exhibit 5-5: Segment PLOS 'B' ................................................................................................................... 31
Exhibit 5-6: Segment PLOS 'C' ................................................................................................................... 31
Exhibit 5-7: Segment PLOS 'D' ................................................................................................................... 31
Exhibit 5-8: Segment PLOS `E` .................................................................................................................. 31
Exhibit 5-9: Segment and Intersection PLOS along Major Mackenzie Drive .............................................. 31
Exhibit 5-10: No dedicated facility, cyclists operate in mixed traffic ............................................................ 32
Exhibit 5-11: Aerial view of McNaughton Road/Avro Road intersection, BLOS ‘E’ .................................... 32
Exhibit 5-12: Segment and Intersection BLOS along Major Mackenzie Drive ............................................ 32
Exhibit 5-13: Model traffic zones adjacent to EA Study Limits .................................................................... 33
Exhibit 5-14: 2020 AM Peak Hour Traffic at Signalized Intersection .......................................................... 35
Exhibit 5-15: 2020 PM Peak Hour Traffic at Signalized Intersections ........................................................ 35
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | iv
Exhibit 5-16: 2020 intersection level of service for drivers during weekday AM peak ................................ 36
Exhibit 5-17: 2020 intersection level of service for drivers during weekday PM peak ................................ 37
Exhibit 7-1: Signal and PXO Warrant Results ............................................................................................. 43
Exhibit 8-1: Constraints between McNaughton Road/Avro Road and Killian Road/Netherford Road ........ 47
Exhibit 8-2: Constraints between Killian Road/Netherford Road and Keele Street ..................................... 47
Exhibit 8-3: Corridor Segmentation ............................................................................................................. 48
Exhibit 8-4: Major Mackenzie Drive looking east at Keele Street ................................................................ 48
Exhibit 8-5: Looking east from 2414 Major Mackenzie Drive Plaza ............................................................ 48
Exhibit 8-6: Looking east along Major Mackenzie Drive from McNaughton Road/Avro Road .................... 49
Exhibit 8-7: Screening process and rationale established through the Design Team Workshop ............... 50
Exhibit 8-8: Alternative Design 3A (Reduced lane widths + CLTL + Sidewalks)......................................... 53
Exhibit 8-9: Alternative Design 3B (Reduced lane widths + CLTL + MUP on north side) ........................... 53
Exhibit 8-10: Alternative Design 2A (Reduced lane widths + CLTL + Sidewalks) ...................................... 54
Exhibit 8-11: Alternative Design 2B (Reduced lane widths + CLTL + MUP on north side) ......................... 54
Exhibit 8-12: Alternative Design 1A (Standard lane widths + RTL + Sidewalks) ........................................ 55
Exhibit 8-13: Alternative Design 1B (Reduced lane widths + RTL + Sidewalks) ........................................ 55
Exhibit 8-14: Recommended Design for the West Segment of Major Mackenzie Drive ............................. 68
Exhibit 8-15: Recommended Design for the Central Segment of Major Mackenzie Drive .......................... 68
Exhibit 8-16: Recommended Design for the East Segment of Major Mackenzie Drive .............................. 68
Exhibit 9-1: Recommended Design for the West Segment of Major Mackenzie Drive ............................... 72
Exhibit 9-2: Recommended Design for the Central Segment of Major Mackenzie Drive ............................ 73
Exhibit 9-3: Recommended Design for the East Segment of Major Mackenzie Drive ................................ 73
Exhibit 9-4: Preferred Design for Major Mackenzie Drive at Keele Street, looking west ............................ 74
Exhibit 9-5: Preferred Design for Major Mackenzie Drive at Saint David's Church, looking west ............... 74
Appendices
A. Preliminary Design Drawings
B. Agency and Stakeholder Correspondence
C. Consultation
D. Aboriginal Group Consultation
E. Archaeological Assessment
F. Cultural Heritage Assessment Report
G. Natural Heritage Report
H. Fluvial Geomorphology Assessment
I. Contamination Overview Study
J. Geotechnical Investigation
K. Drainage and Stormwater Management Report
L. York Region Traffic Operations Assessment Memorandum (2015)
M. Transportation Technical Report #1
N. Public Petition
O. Transportation Technical Report #3
P. Landscape and Streetscape Strategy
Q. Preliminary Cost Estimate
R. Noise Impact Assessment
S. Structural Inspection Report
T. Street Tree Inventory and Management Plan
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | v
This page is intentionally left blank.
December 20, 2018 | 1
1 Introduction
The Regional Municipality of York (York Region) has completed a Schedule “C” Municipal Class
Environmental Assessment (EA) study to review the short-term transportation operational needs
along Major Mackenzie Drive West (referred to as Major Mackenzie Drive for the purpose of this
report), from McNaughton Road / Avro Road to Keele Street in the City of Vaughan.
York Region is responsible for monitoring its transportation network and implementing required
improvements in a timely manner. Concerns raised regarding traffic operations on Major Mackenzie
Drive within the study limits included challenging access to and from businesses, congestion, and
queuing and pedestrian crossing. These issues led York Region to investigate short-term (2020)
transportation improvements for the corridor.
York Region retained HDR to conduct the Major Mackenzie Drive Class EA study. This
Environmental Study Report (ESR) documents the study consultation and decision making
rationale, following the process outlined in the Municipal Engineers Association (MEA) Municipal
Class EA guidelines for Schedule ’C’ projects (October 2000, as amended in 2007, 2011 and 2015).
The EA study was conducted primarily to address existing operational issues for a short term
(2020) horizon year. The horizon year was chosen as 5 years from the date Vaughan City Council
passed the resolution and identified the problem (November 2015). A future EA study will assess
the long-term transportation needs (as recommended by the YR-TMP 25-year outlook), including
capacity and multi-modal improvements.
The study area crosses the West Don River tributary. Due to the poor structural condition of the
culvert at that location, replacement of the structure (ID 25-18 C1180) was recommended. On
account of the emergency nature of the culvert replacement, this work is being conducted
separately to the Schedule “C” EA study in consultation with the Ministry of the Environment,
Conservation and Parks, Toronto Region Conservation Authority and City of Vaughan and is
ongoing at the time of completion of the study.
Study Area 1.1
The study area is 1.4 km long and is bounded by McNaughton Road/Avro Road to the west and
Keele Street to the east, in the Village of Maple, located in the City of Vaughan. Major Mackenzie
Drive within the study limits is currently a 4-lane urban arterial road with a posted speed limit of 50
km/h. The street intersects McNaughton Road/Avro Road, Killian Road/Netherford Road, Gram
Street, Jackson Street and Keele Street.
This section of Major Mackenzie Drive is characterized by a combination of low-rise residential,
mixed-use, commercial as well as institutional buildings and has a number of closely spaced
driveways. The study area is presented visually in Exhibit 1-1.
Exhibit 1-1: Study Area Map
Purpose of the Project 1.2
York Region was notified by the City of Vaughan of a number of operational issues in the study
corridor, including challenging access to and from the land uses on either side of Major Mackenzie
Drive, and heavy through traffic and queuing, particularly in the eastbound direction at Keele Street.
The purpose of the Class EA study is to determine specific short-term transportation improvements
to Major Mackenzie Drive between McNaughton Road/Avro Road to the west and Keele Street to
the east for the horizon year of 2020. A future EA study will assess long-term transportation needs,
including capacity and multi-modal improvements to the corridor.
In particular, the EA study will:
Review existing conditions and operational challenges along this section of Major Mackenzie
Drive
Identify opportunities for improvement and offer possible solutions, including the replacement of
the West Don River tributary culvert
Investigate and recommend alternative designs for the preferred solution
Collect, document and assess input and feedback from residents and affected groups within the
study area
Study Organization 1.3
The Project Team 1.3.1
The York Region Project Team consisted of:
Jackson Marin Project Manager
Billy Cheung Deputy Project Manager
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 2
The Consultant Team 1.3.2
The consultant team included:
Anthony Reitmeier Project Manager – HDR
Christine Hawryluk Deputy Project Manager – HDR
Karim Nahed Transportation Planning – HDR
Michelle Li Water Resources/Environmental Planning – HDR
Jonathan Chai Traffic Analysis Lead – HDR
Peter Yu Preliminary Design – HDR
Nicole Kochmanova Stage 1 Archaeology Assessment – Golder Associates Ltd.
Henry Cary Cultural Heritage Assessment – Golder Associates Ltd.
Michael Roy Natural Heritage – SLR Consulting Ltd.
Ahmed Siddiqui Geomorphology Assessment – Matrix Solutions Inc.
Darrin Sellick Foundations and Geotechnical – Golder Associates Ltd.
Michael Roy Contamination Assessment – SLR Consulting Ltd.
Shira Daltrop Noise Assessment – Golder Associates Ltd.
James McWilliams Streetscape Design – James McWilliams & Associates
Study Process 1.4
The Municipal Class Environmental Assessment (Class EA) 1.4.1
The Municipal Class EA is an approved Class EA process, in accordance with the Environmental
Assessment Act of Ontario (EAA) that applies to municipal infrastructure projects including roads,
water, and wastewater. This process provides a comprehensive planning approach to consider
alternative solutions and evaluate their impact on a set of criteria (e.g. technical, environmental,
social, cost) and determine any mitigating measures to arrive at a preferred alternative for
addressing the problem (or opportunity). The process involves consulting agencies (technical and
regulatory), Aboriginal groups, and public at the various project stages.
This Class EA was undertaken and prepared in accordance with the guidelines of the Municipal
Engineers Association Municipal Class Environmental Assessment (October 2000, as amended in
2007, 2011 and 2015). Due to the type of project, anticipated potential impacts, and estimated
construction cost, the EA was conducted in compliance with a Schedule “C” project. A Schedule
“C” project involves either the construction of new facilities or major expansions of existing facilities.
For the existing facilities, this could include road widening, adjustments, and operational
improvements. This study has completed the first four phases of the five-phase Class EA Process.
Exhibit 1-2 illustrates the sequence of activities within the approved Class EA process leading to
project implementation. The phases for this study are described below:
Phase 1 (Problem or Opportunity) – Identify the problem (deficiency) or opportunity.
Phase 2 (Alternative Solutions) – Identify alternative solutions to address the problem or
opportunity by taking into consideration the existing environment, and establish the preferred
solution taking into account public and review agency input.
Phase 3 (Alternative Design Concepts for Preferred Solution) – Examine alternative
methods of implementing the preferred solution, based on the existing environment, public and
review agency input, anticipated environmental effects, and methods of minimizing negative
effects and maximizing positive effects.
Phase 4 (Environmental Study Report) – Document in an Environmental Study Report a
summary of the rationale, the planning, design, and consultation process of the project. Place
the ESR on public record for a minimum 30 calendar days for review, and notify completion of
the ESR and provision for Part II Order requests.
Phase 5 (Implementation), which involves detailed design, preparation of contract drawings and
tender documents, construction, operation, and monitoring, is not part of this study. The ESR
provides information on the study background, problem statement, alternative solutions, alternative
designs, and the public consultation process.
Exhibit 1-2: Municipal Class EA Process
After the ESR is finalized, it is filed and placed on public record for a minimum of 30 calendar days
for review by the public and review agencies. At the time the report is filed, a Notice of Completion
of the Environmental Study Report will be advertised, advising the public and other stakeholders
where the Environmental Study Report may be seen and reviewed, and how to submit comments.
The Notice will also advise the public and other stakeholders of their right to request a Part II Order,
and how and when such a request must be submitted.
Part II Orders 1.4.2
Under the EAA, members of the public, interest groups, agencies, and other stakeholders may
submit a written request to the Minister of the Environment, Conservation and Parks (the Minister)
to require the proponent (York Region) to comply with Part II of the EAA (referred to as a Part II
Order) before proceeding with the proposed undertaking. Part II of the EAA addresses Individual
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 3
Environmental Assessments. The request for a Part II Order must also be copied to the proponent
at the same time it is submitted to the Minister. Written requests for a Part II Order must be
submitted to the Minister within the minimum 30 calendar day review period. The Minister or
delegate then reviews the Environmental Study Report to ensure that the MEA Schedule ‘C’ Class
EA process has been followed. The proponent and the requestor have an opportunity to discuss
and resolve the issues.
To submit a Part II Order request and obtain the necessary forms, the applicant can follow the new
process outlined online at the following link: https://www.ontario.ca/page/class-environmental-
assessments-part-ii-order
Once the proponent has satisfied the requestor’s concerns a requestor should promptly withdraw a
Part II Order request. If the proponent and requestor are unable to resolve the concerns, the
Minister or delegate will make a decision on a Part II Order:
1. Refer the matter to mediation before making a decision under the provisions of subsection
16(6) of the Environmental Assessment Act.
2. Deny the request for an order and inform the proponent and requestor of the decision and
rationale.
3. Deny the request for an order but impose conditions.
4. Require the proponent to comply with Part II of the Environmental Assessment Act which
requires the preparation of a term of reference and an individual environmental assessment.
The Minister’s decision on a Part II Order request is final.
Canadian Environmental Assessment Act (CEAA) 1.4.3
Under the Canadian Environmental Assessment Act, 2012 (CEAA 2012), a federal environmental
assessment study may be required to the physical activities that constitute a “designated project”,
under the project list identified in the Regulations Amending the Regulations Designating Physical
Activities, 2013. This project list ensures that federal environmental assessments are focused on
the major projects with the greatest potential for significant adverse environmental impacts to
matters of federal jurisdiction. The Major Mackenzie Drive EA study does not constitute a
“designated project” and therefore does not require a federal environmental assessment under the
CEAA, 2012.
However, the Minister of the Environment may order an assessment for any project not included in
the project list, where there may be adverse environmental effects related to federal jurisdiction.
2 Provincial, Regional and Municipal Context and Growth
A summary of the Provincial, Regional, and Municipal planning and policy context is provided in this
section as they relate to the Major Mackenzie Drive Class EA. As this EA considers operational
improvements to deal with pressing issues in the study area, the planning documents were
reviewed under that lens and focus mainly on recommendations and visions for the near-term
(2020).
Provincial Planning Context 2.1
Provincial planning policies were reviewed to identify their relevance to the Major Mackenzie Drive
Class EA. Provincial plans are identified and summarized in Table 2-1.
Table 2-1: Provincial Planning Context
Provincial Planning Document
Description/Relevance
Provincial Policy Statement (2014)
Provides direction on land use planning and development as well as the transportation system, including:
Providing appropriate development while protecting resources, public health and safety, and the natural and built environments
Building strong, healthy communities by supporting density and land uses which support active transportation, are transit-supportive, are freight-supportive
Safe, energy efficient, transportation systems that move people and goods
Integrated transportation and land use considerations at all stages of the planning process
Use of travel demand management (TDM) strategies to maximize efficiency
Land use pattern, density, and mix of uses to minimize length and number of vehicle trips, support current and future use of transit and active transportation
Oak Ridges Moraine Conservation Plan (2017)
Originally published in 2002, the ORMCP provides direction on how to protect the Moraine’s ecological and hydrogeological features. The study area does not fall within the boundary of the Oak Ridges Moraine.
Greenbelt Plan (2017)
Updated in 2017 as a result of the Co-ordinated Land Use Planning Review, the Greenbelt Plan identifies environmentally and agriculturally protected lands within the Greater Golden Horseshoe, where urbanization should not occur, in order to protect ecological features. Major Mackenzie Drive between McNaughton Road/Avro Road and Keele Street does not fall within the boundaries of the Greenbelt Plan. However, the West Don River tributary crossing is identified as an Urban River Valley and subject to the relevant policies, including 1.2.3 and 6.2(3).
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 4
Provincial Planning Document
Description/Relevance
Places to Grow Act / Growth Plan for the Greater Golden Horseshoe (2006, 2017)
Originally adopted in 2006, the 2017 update sets forth a framework for implementing the Government of Ontario’s 2041 vision for building stronger, prosperous communities by better managing growth in the region. Within York Region, four Regional Centres (Markham, Richmond Hill/Langstaff Gateway, Vaughan Metropolitan, and Newmarket) are designated as Urban Growth Centres. The Growth Plan contains policies applicable to infrastructure planning including directing intensification toward strategic growth areas, supporting a balanced, sustainable and connected transportation system for all modes, facilitating efficient goods movement in and out of employment areas.
The land around the Major Mackenzie Drive corridor is classified as a ‘Built-Up’ area in the plan.
The Regional Transportation Plan (2008, Approved Changes 2013)
The Regional Transportation Plan identifies a 25-year plan for the Regional Rapid Transit and Highway Network and sets forth a vision for Regional Express Rail (RER).
The plan does not specify any transportation improvements for the study area. However, upgrades to the Barrie Regional Rail line to accommodate full-day, two-way service are identified in the 15-Year Plan. The line operates between Union Station and Bradford and has a stop at Maple GO station, 700m east of the study area.
Provincial Co-ordinated Plan Review (2017)
The Province completed a simultaneous review of the Niagara Escarpment Plan, the Oak Ridges Moraine Conservation Plan, the Greenbelt Plan and the Greater Golden Horseshoe Growth Plan. This Coordinated Review of the four plans recognizes their common geography and the interconnected nature of their policies and provides an opportunity to assess progress to date, address challenges and make improvements to strengthen the plans and ensure a vibrant, healthy region for current and future generations. The Plan Review’s role is to develop consensus-based recommendations to the Ministers of Municipal Affairs and Housing, and Natural Resources and Forestry on ways to amend and improve the plans. The review recommends increased efforts to curb sprawl, build complete communities, grow the Greenbelt, support agriculture and address traffic congestion.
The proposed revisions were released in May 2017 and do not affect the study corridor.
Regional Planning Context 2.2
Regional planning policies were reviewed to identify their relevance to the Major Mackenzie Drive
Class EA. Regional plans are identified and summarized in Table 2-2.
Table 2-2: Regional Planning Context
Regional Planning Document
Description/Relevance
York Region Official Plan (YR-OP) (2013)
Provides direction to guide economic, environmental, and community-building decisions to manage growth. YR-OP incorporates the Planning for Tomorrow study, undertaken to identify how York Region will accommodate the several provincial planning initiatives. The main theme of the YR-OP is to move York Region towards sustainability, completed through policies that emphasize a reduction in automobile reliance and an increase in active transportation facilities.
The YR-OP transportation road network (Map 12 Street Network) designates a right-of-way (ROW) width of up to 45.0 m along the majority of Major Mackenzie Drive between McNaughton Road/Avro Road to west of Keele Street and up to 30.0 m in the vicinity of the Keele Street intersection.
York Region Strategic Plan (Vision 2051) (2011)
Vision 2051 is York Region’s long-term strategy. It identifies eight goal areas that will guide policies to create strong, caring, and safe communities designed with sustainability in mind. The Vision identifies actions to help achieve these goals, several pertaining to the design of future transportation facilities and the importance of their positive contribution to vibrant communities.
York Region Transportation Master Plan (YR-TMP) (2016)
Provides infrastructure and policy requirements for a 25-year outlook that allows York Region to achieve its strategic vision of an advanced, interconnected system of mobility within the Region. Further information pertaining to transportation infrastructure improvements as documented in the YR-TMP is described within Section 2.2.1 of this report.
York Region Traffic Operations Assessment Memorandum (2015)
This technical memo documents the study methodology, findings and recommendations to improve the operations of Major Mackenzie Drive from Killian Road to Keele Street.
Widening for a centre left-turn lane on Major Mackenzie Drive between Killian Road and Keele Street is feasible within the existing right-of-way. This study concludes that the overall benefits that would be realized by the construction of a left turn lane on Major Mackenzie Drive from Killian Road to Keele Street are low. The study also recommends that broader solutions to traffic congestion in this area be addressed through implementation of missing road links on Teston Road and Kirby Road.
VIVA Network Expansion Plan Design
The Viva Network Expansion Plan (VNEP) identifies rapid transit services and
infrastructure elements that are planned for implementation between 2015 and
2020. Further information pertaining to VIVA Next improvements is described in
Section 2.2.3. Work associated with the VNEP has not been programmed and
timing is to be confirmed.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 5
York Region Transportation Master Plan (2016) 2.2.1
York Region’s current Transportation Master Plan (YR-TMP) was completed in 2016. The purpose
of the YR-TMP is to support growth in York Region to the year 2041 by defining a long term
transportation vision based on integrated road and transit network planning. The plan aims to
establish “an interconnected mobility system that encourages active transportation, and is
supported by compact, complete communities to create a healthy, economically-vibrant, socially-
connected and sustainable Region”.
The major themes outlined in the YR-TMP include prioritizing active and shared modes of
transportation, integrating land use and transportation planning, protecting the environment,
enhancing cultural heritage and implementing transportation demand management techniques.
The following sections summarize the key elements of the YR-TMP and their relevance to the Major
Mackenzie EA study within the 2020 horizon year.
Cycling and Pedestrian networks 2.2.1.1
In its ten-year vision (2016-2026), the York Region Transportation Master Plan does not identify
cycling facilities along Major Mackenzie Drive, as can be seen in Exhibit 2-1.
Proposed Ten Year Cycling Network
Exhibit 2-1: Proposed ten year cycling network (Source: YR-TMP)
In the ultimate 2041 cycling network vision, the YR-TMP identifies Major Mackenzie Drive as a
future separated bike lane route for the entire study corridor, spanning from Keele Street to
McNaughton Road/Avro Road.
The specific configurations as well as the type of facility (cycle tracks, raised bike lanes, or multi-
use paths) will depend on the future (2041) typical cross-sections identified through a separate
Class EA process to assess long term needs for Major Mackenzie Drive.
In the long term, the Major Mackenzie Drive cycling facilities are proposed to connect to the Bartley
Smith Greenway North, which begins north of McNaughton Road/Avro Road, passing through
Mackenzie Glen District Park and ending at Teston Road.
At the time of writing of this report, a separate Class EA Study is being undertaken for Major
Mackenzie Drive between Highway 400 and Jane Street in accordance with the YR-TMP (2016)
recommendations. This EA is reviewing active transportation improvements as part of the overall
goal to accommodate population growth in York Region including the Vaughan Healthcare Centre
Precinct.
Transit network 2.2.1.2
Major Mackenzie Drive between McNaughton Road/Avro Road and Keele Street is planned to
become a Rapid Transit Corridor by 2021 with VIVA curbside service through the study area, as
shown in Exhibit 2-2.
Proposed 2017-2021 Transit Network
Exhibit 2-2: Proposed 2017-2021 Transit Network (Source: YR-TMP)
At the time of writing of this report, a separate Class EA Study is being undertaken for Major
Mackenzie Drive between Highway 400 and Jane Street and is considering Transit/HOV lanes for
that section of the corridor. Moreover, west of Jane Street, a transit terminal/hub is being planned
for on the south side of Major Mackenzie Drive. It is expected the terminal/hub would be used by
several transit agencies and offer connections to Canada’s Wonderland, future Vaughan Healthcare
Precinct and surrounding areas.
2017-2021 Road network 2.2.1.3
The YR-TMP does not identify Major Mackenzie Drive between McNaughton Road/Avro Road and
Keele Street as a candidate for widening by 2021, as shown in Exhibit 2-3.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 6
Proposed 2017-2021 Road Network
Exhibit 2-3: Proposed 2017-2021 Road network (Source: YR-TMP)
However, widening to six lanes is planned for Major Mackenzie Drive west of the study area
between Highway 27 and Jane Street in the 2017-2021 Road Network Plan. At the time of writing of
this report, a class EA study is being undertaken for Major Mackenzie Drive between Highway 400
and Jane Street to review capacity improvements in accordance with the YR-TMP.
Traffic Operations Assessment Memorandum (2015) 2.2.2
York Region received a request from the City of Vaughan through a Council Resolution to review
traffic congestion and vehicle delay related to ingress/egress at commercial and residential
driveways on Major Mackenzie Drive from Killian Road/Netherford Road to Keele Street. The
memorandum, completed in 2015 by the Roads and Traffic Operations group, documented the
study methodology and recommendations to improve traffic operations in the study area. The study
assessed the three following alternatives:
Alternative 1: Status Quo
Alternative 2: Intersection Improvements with Auxiliary Left-turn Lanes
Alternative 3: Intersection Improvements with Continuous Two-Way Centre Left-turn Lane
Findings of the memorandum are summarized:
The overall benefits that would be realized by the construction of a left-turn lane on Major
Mackenzie Drive from Killian Road to Keele Street are low.
High traffic volumes through Maple are the result of network discontinuity in the area including
missing road segments on Teston Road between Keele Street and Dufferin Street and on Kirby
Road between Dufferin Street and Bathurst Street.
Broader solutions to traffic congestion in this area to be addressed through implementation of
missing road links on Teston Road and Kirby Road as identified in the Transportation Master
Plan.
The complete memorandum completed by the York Region Roads and Operations Group can be
found for review under Appendix L.
Viva Network Expansion Plan Design 2.2.3
The Viva Network Expansion Plan (VNEP) identifies rapid transit services and infrastructure
elements that are planned for implementation between 2015 and 2020. The objective of the Viva
Network Expansion Plan is to enhance rapid transit service by optimizing existing Viva service
within dedicated rapidways, and by implementing additional Viva service to increase the
connectivity of York Region’s rapid transit network. The Viva Network Expansion Plan is consistent
with the rapid transit corridors identified in the YR-TMP.
As part of the VNEP, the Viva Silver Route initiative is currently in the final detailed design stage.
The design includes improvements to key intersections and transit stops along Jane Street and
Major Mackenzie Drive in the City of Vaughan and the Town of Richmond Hill. The route will
operate in mixed traffic with transit priority measures and curbside stations, at locations displayed in
Exhibit 2-4.
The VIVA Silver route will include a Viva station at Keele Street which will be accommodated by
widening the north side of Major Mackenzie Drive just east of Keele Street. Changes to the
intersection of Major Mackenzie Drive and McNaughton Road/Avro Road are also anticipated as
part of the VNEP Silver project, including two new far side bus stops and the associated intersection
improvement. The road widening required to accommodate bus bays may compromise valuable
pedestrian space, especially on the north and southeast quadrants of the McNaughton Road/Avro
Road intersection. Other streetscape upgrades are also included, such as the addition of
Accessibility for all Ontarians (AODA) compliant pedestrian ramps, the installation of VIVA bus
shelters and extension of an existing planter wall at the Keele Street intersection.
Exhibit 2-4: Viva Network Expansion Program – Silver Curbside Bus Route (Source: YRT/VIVA 2016-2020 Strategic Plan)
Work associated with the VNEP has not been programmed and timing is to be confirmed.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 7
Municipal and Other Relevant Planning Policies 2.3
City of Vaughan planning policies and the National Association of City Transportation Officials
(NACTO) guide were reviewed to identify their relevance to the Major Mackenzie Drive EA. A
summary is provided in Table 2-3.
Table 2-3: Municipal and Other Planning Context
Municipal Planning Document
Description/Relevance
City of Vaughan Official Plan Update (2010, October 2017 Office Consolidation)
The Official Plan addresses the City of Vaughan`s long-term planning requirements to the year 2031. In addition to consolidating all former land use policy into one document, the Official Plan provides policy directions to facilitate a sustainable and balanced transportation system.
Recognizing the dominant role the automobile has played in defining patterns of growth and development in Vaughan, the Plan`s focus is on strengthening the pedestrian, bicycle and transit networks and systems in the future.
Vaughan’ vision for the future can be summarized by the following: Build strong and diverse communities Promote moving around without a car Develop a green and sustainable city
City of Vaughan Transportation Master Plan (2012)
Through its Transportation Master Plan, the City of Vaughan has identified several measures designed to make more efficient use of its existing road system. Some of the measures support more sustainable modes of transportation, such as buses, rapid transit service, carpooling, walking and cycling. Other initiatives involve better integrating the transportation network with land-use planning.
No road widening is slated for the study area in the Vaughan TMP. The report designates Major Mackenzie Drive as a rapid transit corridor and proposes higher density residential and mixed-use development in key activity centres and along major transit corridors, such as Major Mackenzie Drive.
City of Vaughan Streetscape Manual and Financial Strategy – Heritage and Intensification Area (2014)
The City-Wide Streetscape Manual provides an integrated design framework to manage the design of streetscapes in Intensification Areas and Heritage Conservation Districts in the City of Vaughan. The Streetscape Manual is a reference tool developed to guide the design and construction of urban streetscapes in Vaughan with consideration of maintenance and operations.
The plan sets the following objectives, which are applicable to Major Mackenzie Drive within the study limits: Support active transportation Provide and maintain a consistent quality of design Design appropriate streets to context
Municipal Planning Document
Description/Relevance
Village of Maple Heritage Conservation District Road Policies (2007)
Major Mackenzie Drive from Keele Street to McNaughton Road/Avro Road is designated as a Village of Maple Heritage Conservation District under the City of Vaughan Official Plan and Village of Maple Heritage Conservation District Plan (VMHCDP).
The District Plan policy states that existing pavement widths should not be increased. However, the provision of on-street parking in off peak hours, which increases the sense of pedestrian safety, is supported. In general, all aspects of road design that improve pedestrian amenity and foster a walkable community are encouraged.
Block 27 Secondary Plan (Draft)
The Block 27 Secondary Plan Area is located north of Teston Road (Regional Road 49), east of Jane Street (Regional Road 5), south of Kirby Road and west of Keele Street (Regional Road 6) and comprises Lots 26 – 43 of Concession 4, in the City of Vaughan. Block 27 is intended to be a complete community that prioritizes people, sustainability and livability with a high quality of urban design. The community is planned to feature a range of low to mid-rise buildings that blend a variety of residential, retail and institutional uses. It will be anchored by a local centre that features both institutional uses such as schools, community facilities and the Kirby GO transit hub. The community will also provide an integrated and connected multimodal on and off-road transportation system including transit, walking and cycling. Finally, building upon the area’s abundant natural heritage features, a variety of parks and open 7 spaces will provide residents with space for leisure and recreation.
The Secondary Plan helped inform the population and employment forecasts for this EA study.
Block 41 Secondary Plan (Draft)
New Community Area Block 41 is approximately 441 hectares in area and includes the existing “Purpleville Estates” residential subdivision. It is traversed east-west by the TransCanada Pipeline and associated compressor station, and bordered by Teston Road to the south, Weston Road to the east, Kirby Road to the North and Pine Valley Drive to the west. New Community Area Block 41 will be planned as a complete community with a mix of residential housing, commercial uses, and community facilities such as schools, parks and recreational facilities.
The Secondary Plan helped inform the population and employment forecasts for this EA study.
NACTO Urban Design Guide (2016)
The National Association of City Transportation Officials (NACTO) represents cities on transportation issues of local, regional and national significance. The Guide outlines both a clear vision for complete streets and a basic road map for how to bring them to fruition, which are essential components to successfully re-imagining Major Mackenzie Drive.
For instance, recommendations on an optimum crosswalk spacing of 200 feet (60m) is one of many insightful pieces the Guide can bring to the Major Mackenzie Drive EA study.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 8
3 Public and Stakeholder Consultation
In accordance with the Municipal Class EA Schedule “C” process, three mandatory points of contact
with the public and review agencies are required for the EA study to:
Review the project and selection of the preferred solution towards the end of Phase 2 and obtain
comment and input;
Review alternatives in Phase 3 to assist in the selection of the preferred design for the chosen
solution and obtain comment and input; and
Announce the completion of the Environmental Study Report and placement of the ESR on public
record for a minimum 30-day review period.
The study has met the minimum mandatory points of contact as described in the following
sections.
Consultation Approach 3.1
Public, stakeholder and agency consultation was critical to ensure concerns from current and future
residents and affected groups within the study area are identified, documented, and assessed. A
variety of Stakeholder groups have been identified, including the individual agencies and utilities,
Indigenous groups, ratepayer organizations, specific interest groups, and the general public. All of
these stakeholders were contacted throughout the study and encouraged to provide input and
become involved in the development of the solutions and designs to address the problems and
opportunities identified for the study area.
Communication with stakeholder groups and the public took place through:
• Letters
• Emails
• Phone calls
• Notices
• Newspaper advertisements
• A project website (york.ca/ea)
• Social media posts
• Meetings
• Two rounds of Open Houses
York Region was the central link for all communications. The communication and consultation was
conducted in compliance with the Accessibility for Ontarians with Disabilities Act (AODA).
A mailing list of all residents in the study area was provided by York Region and was kept up-to-date
throughout the study. Both resident mailing and email lists were revised to include a current record of
mailing addresses and emails, including Open House attendees and all those who submit comments
or expressed an interest in the current study.
Moreover, a stakeholder contact list was developed and updated regularly based on responses and
on comments submitted. New additions to the contact list were subsequently sent project updates
and notices.
All individuals and agencies on the contact lists were contacted at the appropriate stages to inform
them of upcoming meetings and events.
Public Consultation 3.2
Public input was an important part of the Major Mackenzie Drive EA. The project team engaged the
general public online, through mail and email notifications, in print, and through public Open Houses
to ensure ample opportunity for participation in the planning process.
An overview of the key consultation milestones is provided in Table 3-1.
Table 3-1: Key Engagement Strategies and Milestones
Engagement Strategy Date
Notice of Commencement
March 30, 2017 and April 6, 2017 – Published in
Vaughan Citizen, newspaper with local circulation
March 30, 2017 – Notice Issued
Notice of Open House #1
October 12, 2017 and October 19, 2017 – Published
in Vaughan Citizen, newspaper with local circulation
October12, 2017 – Notice Issued
Open House #1 October 25, 2017 (Vaughan City Hall)
Notice of Open House #2
April 26, 2018 and May 10, 2018 – Published in
Vaughan Citizen, Thornhill Liberal East and West,
newspapers with local circulation
April 26, 2018 – Notice Issued
Open House#2 May 15, 2018 (Vaughan City Hall)
Notice of Study Completion
December 20, 2018 & December 27, 2018
Published in Vaughan Citizen and Thornhill Liberal
newspapers with local circulation
Detailed information on each of the key consultation events is provided in the following sections.
Consultation event summaries for the aforementioned events can be found in Appendix C.
Notice of Commencement
The notice of study commencement was published in the Vaughan Citizen on March 30, 2017 and
April 6, 2017. The notice was directly mailed to those on the mailing list including properties within the
study corridor, stakeholders and agencies, and placed on the study website.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 9
Open House #1 – October 25, 2017
The first Open House was held on Wednesday, October 25, 2017 in the multi-purpose room at
Vaughan City Hall. The purpose of Open House #1 was to present the preliminary findings of Phases
1 and 2 (Problem and Opportunity, and Alternative Solutions) for the Study Area and receive input
from the public and stakeholders.
Notice for this consultation event was provided through the following:
989 Mailed notices to residents and property owners adjacent to the Major Mackenzie Drive
corridor between McNaughton Road/Avro Road and Keele Street, and all others on the project
contact list (including agency and First Nations representatives and other stakeholders)
Emails to agencies identified previously as stakeholders and First Nations representatives
Posts on social media platforms:
o Study website (www.york.ca/wps/portal/yorkhome/transportation/Major-Mackenzie-
Drive-Keele-EA), and on the Region’s public notices page on October 12, 2017.
o York Region’s Facebook page (October 12, 2017 and October 19, 2017)
o York Region’s Twitter account (October 12, 2017 and October 19, 2017)
Local newspaper advertisement (print and online):
o Vaughan Citizen on October 12, 2017 and October 19, 2017.
Meeting with City of Vaughan Staff on October 12, 2017.
The open house consisted of a drop-in session from 6:30 pm to 8:30 pm. During this time, residents
and stakeholders had an opportunity to view project background displays and discuss their opinions
and concerns with the project team, which included representatives from York Region and HDR. Staff
from the City of Vaughan were in attendance at the Open House.
A total of 52 people signed in at Open House #1. Attendees were provided with a Comment Form for
them to fill out and return to the project team by November 10, 2017. A total of 11 forms were
submitted and additional comments were sent to the Project Team prior to and in the weeks that
followed the Open House.
The Region uploaded the display boards onto the study website. An online comment form was
provided and presented another opportunity for comment for those who did not attend the meeting.
The comments submitted most frequently noted the difficulty for drivers to enter and exit the
commercial plazas between Killian Road/Netherford Road and Keele Street. The provision of a centre
left turn lane was generally seen as a solution with potential to solve the current issues.
The full Open House #1 Summary is provided under Appendix C.
Open House #2 – May 15, 2018
The second Open House for the project was held on Tuesday, May 15, 2018 in the multi-purpose
room at Vaughan City Hall. The purpose of Open House #2 was to present the alternative designs
proposed to implement the preferred solution.
Notice for this consultation event was provided through the following:
984 Open House mailed invitations to residents, property owners and agencies adjacent to the
Major Mackenzie Drive corridor between McNaughton Road/Avro Road and Keele Street, and all
others on the project contact list
Emails to agencies identified previously as stakeholders and First Nations representatives
77 emails to residents and property owners that have demonstrated interest in receiving study
updates at Open House #1 (October 2017)
Posts on social media platforms:
o Study website (www.york.ca/wps/portal/yorkhome/transportation/Major-Mackenzie-
Drive-Keele-EA), and on the Region’s public notices page on April 26, 2018.
o York Region’s Facebook page ( April 26, 2018, May 3, 2018 and May 10, 2018)
o York Region’s Twitter account (April 26, 2018, May 3, 2018, May 10, 2018 and May 15,
2018)
Local newspaper advertisement (print and online):
o Vaughan Citizen, on April 26, 2018 and May 10, 2018
Meeting with City of Vaughan Staff on March 22, 2018 and on April 24, 2018 to present material
that will be displayed at the Open House
The open house consisted of a drop-in session from 6:30 pm to 8:30 pm. During this time, community
residents and stakeholders had an opportunity to view project displays and discuss their opinions and
concerns with the project team, which included representatives from York Region and HDR. Staff
from the City of Vaughan were in attendance at the Open House.
A total of 42 people signed in at Open House #2. Attendees were also provided with a Comment
Form for them to fill out and return to the project team by June 1, 2018. A total of eight forms were
submitted at the Open House and three subsequent comments were received by the Project Team in
the weeks that followed the Open House.
The Region uploaded the display boards onto the study website. An online comment form was
provided and presented another opportunity for comment for those who did not attend the meeting.
The proposed corridor improvements were generally well received and the public was especially
supportive of the streetscaping and active transportation considerations made.
The full Open House #2 Summary is provided under Appendix C.
Notice of Completion
The notice of study completion was published in the Vaughan Citizen and Thornhill Liberal on
December 20, 2018 and December 27, 2018. Social media posts regarding the notice of completion
were shared on the Region’s Facebook page. The notice was directly mailed to those on the mailing
list including properties within the study corridor, stakeholders and agencies, and placed on the study
website.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 10
Agency and Stakeholder Consultation 3.3
As part of the EA process, multiple technical staff from York Region and partner agencies as well as
representatives from area developer groups and other stakeholders were consulted on a regular
basis.
The following is a summary of the agencies and stakeholders contacted:
Ministry of Education
Ministry of Public Infrastructure
Ministry of the Environment, Conservation and
Parks (MECP, formerly MOECC)
Ministry of Transportation
Ministry of Natural Resources and Forestry
(MNRF)
Ministry of Aboriginal Affairs and Northern
Development
York Region Transit (YRT)
City of Vaughan, Heritage Vaughan
Committee
City of Vaughan, Community Services
City of Vaughan, Engineering & Public Works
Vaughan Chamber of Commerce
Vaughan Fire and Rescue Services
Toronto Region Conservation Authority
(TRCA)
Student Transportation Services of York
Region
Alectra Utilities
Rogers
Ministry of Municipal Affairs
Ministry of Tourism, Culture and Sport
Ministry of Municipal Housing
Ministry of Health and Long-Term Care
Metrolinx
Infrastructure Ontario
Ontario Provincial Police
Canadian Environmental Assessment
Agency
Canadian National Railway (CNR)
Environment Canada
Health Canada
Fisheries and Oceans Canada
Transport Canada - Ontario Region
Indigenous and Northern Affairs Canada
Parks Canada
York Region Catholic School Board
York Region District School Board
York Regional Police
Direction du Service de transport Francobus
Enbridge Gas
Bell
Developers
The Ministry of Indigenous Relations and Reconciliation was not contacted as per the MECP’s new
process. This was confirmed at the York Region and MECP meeting on March 31, 2017.
These agencies, stakeholders and staff members were invited to review and provide input on all
aspects of the study process, including: the problem and opportunity statement, evaluation criteria,
development and evaluation of alternatives, and the preferred alternatives. Comments and concerns
were incorporated or acknowledged throughout the study.
Agency consultation consisted of letters, emails, phone calls, exchanges of information, and
meetings. Individual meetings/conference calls were held with agency representatives and other
stakeholders as follows:
MECP: Meeting on June 16, 2017, December 11, 2017.
MNRF: meeting on June 27, 2018.
TRCA: meetings on June 16, 2017, December 7, 2017 and March 5, 2018.
City of Vaughan: meetings on December 7, 2017, March 5, 2018, March 22, 2018, April 24, 2018.
Agency-specific correspondence, including minutes from key meetings, is included in Appendix B.
Aboriginal Group Consultation 3.4
Aboriginal groups to be contacted regarding the study were identified by the MECP (formerly
MOECC) in a letter on June 2, 2017 in accordance with the Ministry`s new Aboriginal group
consultation process. The Aboriginal consultation program for the EA study involved representatives
from the following groups:
Alderville First Nation
Chiefs of Ontario
Curve Lake First Nation
Hiawatha First Nation
Mississaugas of the Scugog Island First
Nation
Mississaugas of the New Credit First Nation
Williams Treaties First Nations
Aboriginal community representatives were included in the mailing list for the project, and were
contacted via study notices throughout the study (including Notice of Commencement, Notice of
Open House (2), and Notice of Completion). The mailing list was updated to add additional Aboriginal
community representatives or updated with their contact information as requested throughout the
study, including the addition of Williams Treaties First Nations. Notices were distributed to all of those
on the mailing list at the time of each notice were issued.
Only representatives from the Mississaugas of the New Credit First Nation and the Curve Lake First
Nation contacted the project team to acknowledge receipt of some of the notices that were sent to
them. For the groups that did not respond, the project team followed up on July 5, 2017 by email to
confirm if they have any interest in the study and to provide the opportunity for any comments,
questions and feedback.
The Mississaugas of the New Credit First Nation (MNCFN) identified a low level of concern regarding
the project but requested that a Field Liaison Representatives (FLR) must be on location whenever
any fieldwork for environmental and/or archaeological assessments is undertaken. York Region
provided a response on September 11, 2017. As of the writing of this report, the Region is reviewing
the MNCFN agreement language for inclusion of FLR on regional projects.
Correspondence logging communication with Aboriginal community representatives is included in
Appendix D
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 11
This page was purposefully left blank
4 Existing Conditions The following section documents current conditions including existing transportation facilities, the
socio-economic environment, natural environment and existing infrastructure along the study corridor.
Existing Transportation Inventory 4.1
The current road, transit, cyclist, and pedestrian network for the Major Mackenzie Drive study corridor
is described in the subsequent sections.
Road Network 4.1.1
Within the study area, Major Mackenzie Drive is currently a 4-lane urban arterial road with a posted
speed limit of 50 km/h.
Exhibit 4-1 depicts a typical cross-section of Major Mackenzie Drive within the study limits, looking
east of Gram Street.
Exhibit 4-1: Conceptual Cross-Section of Existing Road Looking East (24 m ROW at 2332/2338 Major Mackenzie Drive looking east from Gram Street)
The intersections of Major Mackenzie Drive at McNaughton Road/Avro Road, Killian Road/Netherford
Road and Keele Street are signalized and have auxiliary eastbound and westbound left-turn lanes
(with medians). There are unsignalized intersections at Gram Street and Jackson Street; no turning
lanes are provided at either intersection. There are also a number of driveways and access points
along the corridor, especially between Gram Street and Keele Street (more details can be found in
Section 4.1.6).
The existing right-of-way (ROW) varies along the study corridor, generally ranging between 25 m and
28m from west of Gram Street to east of Keele Street. The remainder of Major Mackenzie Drive, from
McNaughton Road / Avro Road to west of Gram Street has a ROW generally of 36 m. The ROW is 66
m at the West Don River Tributary crossing, as shown in Exhibit 4-2 and Exhibit 4-3. The planned
street width for Major Mackenzie Drive as per the York Region Official Plan 2010 is up to 45 m west
of Killian Road / Netherford Road and 30 m east of it. The existing road network and lane
configurations are shown in Exhibit 4-4.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 12
Exhibit 4-2: Existing ROW from McNaughton Road/Avro Road to Killian Road / Netherford Road (Source: York Maps)
Exhibit 4-3: Existing ROW from Killian Road / Netherford Road to Keele Street (Source: York Maps)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 13
Exhibit 4-4: Existing Road Network and Lane Configurations (Source: Traffic Operations Assessment Memorandum 2015)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 14
Network Connectivity and Continuity 4.1.2
Major Mackenzie Drive is a continuous, regional arterial road which spans York Region from its
western boundary with Peel Region and its eastern boundary with Durham Region, providing a major
east-west transportation corridor connecting to north-south regional arterials and Highways 400 and
404. In the vicinity of the study area, it provides direct connections to Jane Street and the Highway
400 interchange to the west and Keele and Dufferin Street to the east.
East of the study limits, the Maple GO station provides residents with train service southbound
to Toronto Union Station and northbound to Barrie Allandale Station. A map showing the context of
the area surrounding the study limits is provided in Exhibit 4-5.
Exhibit 4-5: Surrounding Area
The study area presents a generally "asymmetric" street arrangement characteristic of residential
subdivisions, where the internal road network is separated from the main thoroughfare (Major
Mackenzie Drive) except for a few connections (in this case at the intersections at Gram Street,
Jackson Street, Killian Road / Netherford Road and McNaughton Road / Avro Road). The road
network north and south of Major Mackenzie Drive is largely discontinuous, and contains several
dead-ends and cul-de-sacs. The West Don River tributary valley system also creates a natural barrier
dividing the road network east-west.
Existing Truck Restrictions 4.1.3
According to the York Region TMP, Major Mackenzie Drive within the study limits is not considered a
Strategic Goods Movement Corridor. However, there are currently no truck restrictions within the
study corridor
Transit Network 4.1.4
Based on the York Region Transit (YRT) 2018 Service Plan, there are currently four YRT bus routes
serving the study area, including the 462 Maple High School Special, the 560 Maple Community and
the 4 and the 4A Major Mackenzie. The 560 Maple Community bus runs between Vaughan City Hall
and Vaughan Mills Shopping Centre every seventy-two minutes. The 462 Maple H.S Special travels
between Keele-Rutherford and Maple High School on weekday mornings exclusively. The 4 Major
Mackenzie bus serves as a local east-west route connecting Vaughan Mills Shopping Centre and
Hillmount Park. It has 30 minute service beginning at 6 a.m. and ending at 1 a.m. The 4A Major
Mackenzie bus follows a similar route to 4 Major Mackenzie bus, except that it terminates at Pine
Valley Drive in the west. The YRT westbound and eastbound stops along Major Mackenzie between
McNaughton Road/Avro Road and Keele Street are shown in Exhibit 4-6.
Exhibit 4-6: Location of YRT Bus Stops
The area is also served by the Barrie GO train line, which runs between Toronto Union Station and
Barrie Allandale Station. As of January 2018, train service operates approximately every 15-30
minutes in the morning peak period, every 30 minutes in the afternoon peak period and every hour at
other times. Outside of peak periods, most trains terminate at Aurora with connecting buses for
stations further north. On weekends and holidays, service operates approximately hourly between
Aurora and Toronto. Three daily trains in each direction cover the full route from Barrie to Toronto,
while the remainder have bus connections at Aurora station for stations further north.
Exhibit 4-7: Barrie GO Line
Context
0 0.2Kilometers
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 15
The Maple GO Train station is located approximately a kilometre east of the intersection of Keele
Street and Major Mackenzie Drive, as illustrated in Exhibit 4-5.
Pedestrian and Cycling Facilities 4.1.5
As of November 2018, cyclists do not have a dedicated space in the right-of-way as there are no
designated cycling facilities on Major Mackenzie Drive. Cyclists must share the roadway with vehicles
or ride on the sidewalks in the study area. However, the pedestrian realm is more developed,
especially on the north side of Major Mackenzie from Keele Street to Gram Street. This mainly
commercial section is equipped with wide boulevards and larger sidewalks, complete with planters
and street furniture, as depicted in Exhibit 4-8. The extensive streetscaping and interlocking red
paving treatment in that section is intended to act as a gateway to the Village of Maple Heritage
District and is a signature feature of the neighbourhood.
Exhibit 4-8: North side of Major Mackenzie Drive looking west at Golden Spruce Lane (Source: Google Maps)
In contrast, the south side of Major Mackenzie from Keele Street to Gram Street, shown in Exhibit
4-9 is more utilitarian and has standard sidewalks with no buffer protecting pedestrians from car
traffic. This can be attributed to the south side’s lower pedestrian activity, resulting from low-rise
residential uses along that stretch.
Exhibit 4-9: South side of Major Mackenzie Drive looking west at Jackson Street (Source: Google Maps)
For the section between Gram Street and St. David Catholic Church, pedestrians are separated from
vehicular traffic by a wide grassy boulevard, as per Exhibit 4-10.
Exhibit 4-10: North side of Major Mackenzie Drive looking west of Killian Road/Netherford Road (Source: Google Maps)
However, between the access to St. David’s Catholic Church and McNaughton Road/Avro Road, a
160 m segment on the south side of Major Mackenzie Drive has a guardrail between the sidewalk
and the road, as can be seen in Exhibit 4-11. The York Region Accessibility Design Guidelines for
Trails require the provision of a guardrail to protect pedestrians from adjacent steep slopes, as is the
case here due to the West Don River tributary creek crossing.
Exhibit 4-11: South side of Major Mackenzie Drive looking west toward McNaughton Road/Avro Road (Source: Google Maps)
It is noted that for the study area length of 1.2 km, there are only three protected pedestrian crossings
located at McNaughton Road / Avro Road, Killian Road / Netherford Road and Keele Street. These
crossings operate as part of the Traffic Control Signals at these intersections. The distance between
the eastern two intersections is particularly large at 685m and encourages jaywalking for pedestrians
looking to cross Major Mackenzie Drive between Killian Road / Netherford Road and Keele Street.
Driveways and Accesses 4.1.6
It is the policy of York Region to help optimize the transportation network by applying access
management procedures that limit the number of access points along a road. Between Keele Street
and McNaughton Road/Avro Road, Major Mackenzie Drive hosts several driveway accesses due to
the concentration of commercial services within the area. The access points used for commercial
parking and loading are numbered in Exhibit 4-12 according to the following list, from east to west:
1. 2269 Major Mackenzie Drive: 9994 Keele Street driveway
2. 2266 Major Mackenzie Drive: Shoppers Drugmart parking lot
3. 2316 Major Mackenzie Drive: Retail plaza access
4. 2332 Major Mackenzie Drive: Retail plaza access
5. 2338 Major Mackenzie Drive: Service access
6. 2354 Major Mackenzie Drive: Retail plaza access
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 16
7. 2396 Major Mackenzie Drive: Courtyards of Maple Condominiums Access
8. 2414 Major Mackenzie Drive: Maple Convenience & Post Office Access
9. 2535 Major Mackenzie Drive: Retail plaza eastern exit
10. 2563 Major Mackenzie Drive: Retail plaza central entrance and exit
11. 2571 Major Mackenzie Drive: Retail plaza western entrance
12. 2600 Major Mackenzie Drive: Apple Tree Montessori School Access
13. 2601 Major Mackenzie Drive: Saint David Catholic Church Access
Exhibit 4-12 also shows the prominence of driveways that service the residential properties fronting
Major Mackenzie Drive on the south side of the street. These additional residential access points
further exacerbate traffic conflicts for driveway ingress/egress, especially between Keele Street and
Gram Street.
Exhibit 4-12: Location of commercial and residential driveway accesses
Socio-Economic Environment 4.2
Existing Land Use 4.2.1
Land uses adjacent to Major Mackenzie Drive throughout the study limits are a mix of low-rise
residential and commercial. From McNaughton Road/Avro Road to west of the Killian-Lamar parkette,
natural areas span north-south along the Mackenzie Glen Park Creek. From the parkette to Killian
Road/Netherford Road , low-rise single family housing dominate on the north side while a low-rise
mixed use area is located on the south. Between Killian Road/Netherford Road and Gram Street, low-
rise residential uses front Major Mackenzie Drive from both sides. From Gram Street to Keele Street,
the study corridor is designated for low-rise mixed-use. Exhibit 4-13 shows the land use designations
along the corridor and surrounding area, as listed in the 2017 City of Vaughan Official Plan (Schedule
13 – Land Use).
Exhibit 4-13: Land uses along Major Mackenzie Drive (Source: City of Vaughan Official Plan 2010, October 2017 Office Consolidation)
Archaeology 4.2.2
A Stage 1 archaeological assessment was conducted as part of the Class EA for the proposed
operational improvements to Major Mackenzie Drive. The assessment involved a review of
documents pertaining to the project area including historic maps, topographic maps, satellite images
and local histories.
A desktop review was completed to evaluate whether the study area retained archaeological
potential. The desktop review identified parts of the study area as having archaeological potential
removed and parts of the study area as having no or low archaeological potential. The remaining
balance of the study area was identified as retaining archaeological potential.
Archaeological recommendations have been made based on the background historical research, a
desktop review of existing conditions, locations of known or registered archaeological sites, and
indicators of archaeological potential. These recommendations include the following:
1. The portions of the study area that were identified as having archaeological potential removed,
such as existing roadways (arterial roads, local roads), sidewalks, building footprints, single home
developments, multi-home developments, utilities, need to be confirmed through an on-site
property inspection during a Stage 2 archaeological assessment.
2. Portions of the study area that were identified as having no or low archaeological potential, such
as, the Don River West Branch watercourse and the steeply sloping portions of its valley lands,
need to be confirmed through an on-site property inspection during a Stage 2 archaeological
assessment.
3. Portions of the study area that were identified as retaining archaeological potential, such as the
grassed yards and the valley lands associated with the Don River West Branch, must be subject
to a Stage 2 archaeological assessment. These areas must be subject to test pit survey at 5m
intervals in accordance with Section 2.1.2 of the MTCS (2011).
4. Select portions of the northwest, northeast, and southeast corners of the Major Mackenzie Road
and Keele Street intersection retain archaeological potential for deeply buried archaeological
resources beyond the existing road right-of-way. Should the proposed development extend within
the property limits of 10020 Keele Street and 2266 Major Mackenzie Drive (northwest corner);
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 17
10037 Keele Street (northeast corner); and/or 9995 and 9983 Keele Street (southeast corner), a
Stage 3 archaeological assessment involving backhoe trenching would be required within the core
of the planned development area and over any areas of archaeological potential as per Section
2.1.7 of the MTCS Standards and Guidelines for Consultant Archaeologists (MTCS 2011: 36-38) .
The map of the results is displayed in Exhibit 4-14. The Stage 1 Archaeological Assessment is
provided in full under Appendix E.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 18
Exhibit 4-14: Stage 1 Archeological Assessment Results
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 19
Built Heritage and Cultural Landscape Features 4.2.3
A Cultural Heritage Assessment Report (CHAR) was conducted to inform the design of the proposed
operational improvements to Major Mackenzie Drive and is included in in Appendix F. Background
research and field investigations identified two the following built heritage and cultural landscape
features:
Two (2) protected heritage properties designated under Part IV of the Ontario Heritage Act,
located at:
o 2600 Major Mackenzie Drive
o West lot boundaries of 2414 Major Mackenzie Drive and 2 Gram Street
Fifty-one (51) protected heritage properties within the Maple Heritage Conservation District
designated under Part V of the Ontario Heritage Act
o Sixteen (16) of these properties are considered as “contributing” to the cultural heritage
value or interest of the Village of Maple Heritage Conservation District (HCD).
o Roads lined with maple and other mature trees, grassed boulevards, and building
setbacks that contribute to the cultural heritage landscape of the Village of Maple HCD
One (1) Ontario Archaeological and Historic Sites Board plaque.
Properties exhibiting cultural heritage value are shown in Exhibit 4-15.
Exhibit 4-15: Cultural Heritage Resources Identified in the Study Area
Natural Environment 4.3
The natural environment assessment comprised a review of fisheries and aquatic habitat, vegetation,
wildlife, and designated natural areas along the study corridor. The full Natural Heritage Report is
included in Appendix G. Key findings are summarized in the following sections.
Fisheries and Aquatic Habitat 4.3.1
The Don River Watershed lies primarily within the City of Toronto and the Regional Municipality of
York. The headwaters of the Don River originate in the Oak Ridges Moraine (ORM) and drain south
primarily through the Lake Iroquois Plain before out letting into Lake Ontario. The Don River has
approximately 34% impervious cover and has been significantly altered by development for over 150
years (TRCA, 2009).
Within the study area, the banks of the channel upstream of Major Mackenzie Drive are extensively
armoured. This includes a large component of gabion baskets, armour stone and the concrete
headwall of the culvert under the subject roadway. Although this armoured upstream section does
follow a natural meander, the steep gabion walls restrict opportunities for the stream to naturally
create point bars and other depositional areas. This section upstream of the culvert is narrower and
more channelized than downstream with an average wetted width of approximately 2.5 m compared
to 4 m downstream. In comparison, the downstream section lacks any hard armouring and has a
large number of point bars with varying widths of 1.25 m to 6 m. Water depths also followed a similar
pattern of more consistent levels upstream and more natural and variable levels downstream.
Upstream of the culvert, depths were fairly uniform at approximately 10 cm, whereas downstream of
the culvert they ranged from 5 to 60 cm. These deeper portions occur within pools and afford refuge
habitat during both low discharge and ice over conditions.
The substrates within the entire study area were dominated by coarse sand, gravel and cobble with a
high degree of substrate sorting throughout the channel. There also appears to be a significant
amount of cobble, gravel and other debris that have migrated from the upstream end of the site into
the culvert, creating riffles and shallow depositional areas within the culvert. Apart from the culvert,
the stream reach within the study area follows a somewhat regular riffle-pool-run sequence, indicative
of a relatively natural stream. The stream also follows a somewhat natural meander and could be
characterized as moderately sinuous. It also appears that over time the channel, both up and
downstream of Major Mackenzie Drive, has been down cutting and consequently the channel is
losing its connection to the floodplain.
General Fish Community 4.3.1.1
The Upper West Don has historically been home to the most diverse fish community within the Don
River system. However, urbanization and other land use change within the sub-watershed have
contributed to declines in the number of species present.
The majority of the 12 species of fish currently found within the watershed are generally very tolerant
to disturbance. All of the species comprising the fish community are considered to be common across
the landscape, and relatively tolerant to disruption and pollution. Based on thermal data collection and
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 20
interpretation by TRCA, the thermal regime within the Upper West Don River Sub-watershed is
considered warm water. Similarly, the fish community present represents a typical warm water stream
in Southern Ontario.
Aquatic Species at Risk 4.3.1.2
A review of fisheries collection records from the TRCA, MNRF and the Department of Fisheries and
Oceans (DFO) Distribution of Fish and Species at Risk maps indicates there are no aquatic species
at risk (SAR) known to be present within the study area or the Upper West Don River Sub-watershed.
Vegetation and Terrestrial Habitat 4.3.2
A plant inventory was completed along the riparian corridor of the West Don River within study area.
The majority of the plant species observed was non-native species indicative of past disturbance. Of
the native species present, all are considered common, widespread and abundant. No Butternut
Trees were encountered during site investigations conducted along the Upper West Don River
corridor or amongst the several hundred street trees throughout the study area that were assessed as
part of the Street Tree Management component of this study.
Vegetation communities along the riparian corridor of the Upper West Don River within study area
were delineated and characterized using the Ecological Land Classification (ELC) System for
Southern Ontario (Lee et. al., 1998). The dominant species identified along the Major Mackenzie
Drive study corridor fit into four community classifications, including: Cultural Thicket (CUT), Cultural
Woodland (CUW), Cultural Savannah (CUS) and Shallow Water Aquatic (MAS). No rare or
uncommon communities occur within the study area limits.
Wildlife and Wildlife Corridors 4.3.3
Mammals 4.3.3.1
Mammal species were observed directly and their presence was recorded through indirect evidence,
such as tracks, feces and sounds. Mammal species recorded during terrestrial and aquatic field site
visits included: Grey Squirrel (Sciurus carolinensis), Eastern Cottontail (Sylvilagus floridanus) and
evidence of White-tailed Deer (Odocoileus virginianus) and Common Raccoon (Procyon lotor). No
mammal species at risk are known to occur within the study area.
Birds 4.3.3.2
A total of 23 bird species were recorded during breeding bird surveys, conducted as part of the
Natural Heritage Assessment. This assemblage of birds is common in mixed habitat in southern
Ontario. These species reflect the habitat available for nesting which includes primarily urban habitat
(cultural communities), and portions of wetlands, riparian and forest patches associated with the West
Don River corridor. No species at risk were encountered during breeding bird surveys and in
particular, no evidence of Barn Swallow nesting was observed within the culvert under Major
Mackenzie Drive.
Linkage and Corridors 4.3.3.3
Due to the urbanized land use that dominates the study area, opportunities for wildlife passage are
primarily limited to the Upper West Don River corridor. This corridor is also identified as a Greenbelt
Plan External Linkage and as an Urban River Valley and is subject to the relevant policies, including
1.2.3 (integration of river valleys into urban areas) and 6.2(3) (growth needs of adjacent settlement
areas).
Here, the vegetated riparian corridor provides a linear habitat feature for common urban and urban
fringe wildlife species. The existing culvert under Major Mackenzie Drive provides a linkage along the
Upper West Don River, although dry land terrestrial passage through this culvert is non-existent as
the river exhibits permanent discharge that likely occupies the entire bottom of the culvert throughout
the year.
Designated Natural Areas 4.3.4
There are no Areas of Natural and Scientific Interest (ANSIs), Provincially Significant Wetlands or
Environmentally Sensitive Areas (ESAs) located within close proximity to the study area.
Fluvial Geomorphology 4.3.5
A desktop historical review and field assessment were completed to characterize the fluvial
geomorphology for the unnamed tributary of the West Don River crossed by Major Mackenzie Drive
within the study limits. The West Don River tributary is located approximately 1.18 km east of Jane
Street.
As part of the assessment, historical and recent aerial photographs were reviewed to delineate the
meander belt width on a reach basis at the crossing, as well as determine channel migration rates.
No significant rates of channel migration were noted during the time period analyzed as most
changes to channel platform were acknowledged to be a result of channel realignments.
To confirm existing geomorphic conditions, document evidence of active erosion, and verify the
results of the desktop assessment, observations and channel measurements were collected on
September 28, 2017 and included the following general observations:
A 2.85 x 4.70 m diameter corrugated steel pipe arch culvert currently conveys flows beneath
Major Mackenzie Drive. The culvert was found in poor condition but in its current state does not
pose any obvious barriers to fish passage channel were contributing to an increase in channel
stability.
Downstream of the crossing is a moderately sinuous channel, characterized by a low gradient.
Average bankfull width was measured to be 4.6 m while average bankfull depth was measured to
be 0.58 m. Riffles and pools were spaced approximately 10-15 m apart. Bank angles ranged
between 60 to 90 degrees, with localized erosion and undercuts present. Riparian vegetation
consisted of a mix of woody vegetation and herbaceous vegetation.
Upstream of the crossing is slightly steeper than downstream, with a lower sinuosity. The
upstream section of this reach was generally more ‘natural’ with little evidence of anthropogenic
channel modifications. Average bankfull width and depth were measured to be 3.8 m and 0.80 m,
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 21
respectively. A headwall was located on the eastern bank of the watercourse, near the
downstream extent of the reach, which had a dual-outlet configuration consisting of two 0.75 m
diameter concrete pipes and intended to convey flows from the adjacent stormwater
management facility.
In the case of the study reaches, the channel size is small with moderate vegetation cover.
However, localized erosion was noted within the channel. The reaches within the study area were
generally unconfined in their valley settings. The study reaches were identified to be in states of
adjustment or stressed (transitional). The 100-year migration rate, based on the average annual
rate of migration was estimated to be 8 m.
The findings from the fluvial geomorphology assessment can be found under Appendix H.
Contamination 4.4
The Contamination Overview Study (COS) consisted of a broad assessment of actual and potential
sources of contamination within the study area, based on a review of readily available information
regarding current and former land uses and visual site reconnaissance. Based on this information,
Areas of Potential Environmental Concern (APECs) were identified as having the potential for
subsurface impacts and recommendations were provided with regards to the needs for further
investigation. Exhibit 4-16 provides a map of the APECs, described in further detail below:
Only one existing gas station is found within the study area and is located at 2660 Major
Mackenzie Drive (Mac’s Gas Station and Convenience Store). This property is considered to
represent a higher potential of environmental concern as subsurface impacts (if present) from
this site could migrate south and southeast towards the roadway.
Four (4) properties within the study area were identified as having former private and retail fuel
tanks on site. These include:
1. Former Maple Airport
o Plane fuelling and maintenance may have occurred on the site and have the potential to lead
to impacts on soil and groundwater. However, this property was developed as a residential
development following the closure of the airport and, as such, this area is considered to
represent a low potential for environmental concern.
2. 2396 Major Mackenzie Drive – Historic Gas Station
o Formerly a gas station, this site was developed in 2013 into residential condos that include
commercial retail spaces on the ground level.
o Environmental investigations would have occurred at the site to confirm that the soil and
groundwater quality at the property meets the residential standards set forth by Ontario
Regulation 153 (as amended). It is unknown whether or not these investigations included
assessing soil and groundwater quality to the south of the southern property boundary (along
Major Mackenzie). As such, this site is considered to represent a higher potential of
environmental concern.
o
3. 2347 Major Mackenzie Drive
o A record for an active 2,300 L fuel oil underground storage tank was found during the site
reconnaissance.
o This property is currently operated as an accounting business.
o It is possible that subsurface impacts (if present) from this site could migrate towards the
roadway. As such, this property is considered to represent medium potential of
environmental concern.
4. 2141 Major Mackenzie Drive – Vaughan City Hall
o Historic air photos (1960 to 1988) show several smaller site buildings, and potential fill piles.
The scale for the air photos does not allow for a detail review of the site operations but given
the historical records, it appears that this property may have been a waste storage area and,
as such, would be categorized as an APEC.
o Given the location of this property (approximately 150 m east of the eastern site boundary)
and the grading and excavation activities at the site that would have occurred prior to the
construction of the current City Hall building (i.e. removal of surficial soils), this site is
considered to represent a lower potential of environmental concern.
A total of four (4) current & historical dry cleaning operations were located in the vicinity of the
study area.
1. Three of these four businesses had records for the generation of halogenated solvent waste.
The properties are located at 9929 Keele Street, 2354 and 2563 Major Mackenzie Drive.
2. The cleaner at 10040 Keele Street is not listed as a generator of hazardous waste. Its dry
cleaning activities are suspected to be completed off-site in a secondary location.
3. 2354 Major Mackenzie Drive is considered to be an area with a higher potential of
environmental concern.
4. 2563 Major Mackenzie Drive is considered to be an area with a higher potential of
environmental concern.
Historic spills were recorded at the intersection of Keele Street and Major Mackenzie Drive.
o Two historic diesel spills, and one historic coolant spill are listed within the Ontario Spills
Database.
o Only the volume of one of the diesel spills is provided in the database report (20 litres).
o There is a potential for subsurface impacts to exist in this intersection as a result of these
spills, and the degree of environmental concern these historic events may pose would be
correlated with the volume of the spills where a spill quantity is not listed. If the volume of
those spills is small these records would be considered to represent a lower potential of
environmental concern.
The Contamination Overview Study can be found under Appendix I.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 22
Exhibit 4-16: Potential Contaminated Sites in the Study Area
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 23
Source Water Protection 4.5
Based on correspondence from TRCA, the Major Mackenzie Drive EA study area is located in the
Toronto and Region Source Protection Area and transects the following vulnerable areas
identified under the Clean Water Act, 2006 (as illustrated in Exhibit 4-17):
Wellhead Protection Area (Quantity)
Highly Vulnerable Aquifers (HVA)
Potential threats associated with the Major Mackenzie Drive roadway improvements, per the Clean
Water Act, 2006, include:
The establishment, operation, or maintenance of a system that collects, stores, transmits, treats,
or disposes of sewage (limited to stormwater runoff)
The application of road salt
The storage of snow (limited to roadway clearing operations only)
Exhibit 4-17: Source Protection Information in the Vicinity of the Study Area
Geotechnical Investigations 4.6
A geotechnical assessment was conducted and is provided under Appendix J. The existing pavement
structure on Major Mackenzie Drive within the study limits does not satisfy York Region’s requirements
for an arterial road. Significant strengthening is required to upgrade the road to support future traffic
based on the projected growth.
Drainage and Stormwater Management 4.7
The portion of the Major Mackenzie Drive between McNaughton Road/Avro Road and Keele Street is
primarily an urban cross-section and the roadway and boulevard surfaces are drained by a network of
catchbasins and storm sewers, discharging to the watercourse crossing and municipal storm
drainage systems. Table 4-1 describes the various storm discharge locations as well as the
contributing right-of-way drainage area to each drainage outfall.
Table 4-1: Summary of Existing Drainage Areas
Description
ROW
Drainage
Area (ha)
Discharge Location
McNaughton Road/ Avro Road to Killian Road/
Netherford Road 2.03 Outlets to West Don River
Killian Road/ Netherford Road to 150m east of
Killian Road/ Netherford Road 0.66
Connects to existing
storm sewer system
150m east of Killian Road/ Netherford Road to
40m west of Jackson Street 1.36
Connects to existing
storm sewer system
40m west of Jackson Street to Keele Street 0.44 Connects to existing
storm sewer system
Keele Street to 200m east of Keele Street 0.69 Connects to existing
storm sewer system
Within the project limits, Major Mackenzie Drive traverses the West Don River watershed, and the
general drainage direction is from north to south. There is one watercourse crossing which conveys
the external drainage across the Major Mackenzie Drive right-of-way. Table 4-2 provides a
characteristics summary of the crossing.
Table 4-2: Existing West Don River Culvert Data
Structure Location
Description Culvert Type
Size (mm)
Length (m)
Inlet Elevation
(m)
Outlet Elevation
(m)
West Don River
tributary
1.18 km east of Jane Street
Corrugated Steel Arch
4720 x 3000 58.3 226.08 225.72
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 24
Pursuant to MTO Design Criteria, the design return period for the culvert crossing is the 50-year
event. The existing hydraulic assessment of the West Don River crossing was completed using the
HEC-RAS hydraulic model provided by TRCA to determine the existing hydraulic performance. The
hydraulic assessment was used to assess the freeboard and vertical clearance requirements
pursuant to the MTO Highway Drainage Design Standards. Based on the hydraulic analysis results,
the culvert crossing is in compliance with the Ministry of Transportation design Guideline, meeting the
1.0 m freeboard from the design high water level (50-Year storm event).
Table 4-3: Hydraulic Analysis Results for the West Don River Culvert (Existing Condition)
Structure
Peak Flow Rate
(m3/s) Road
Elev.
(m)
Water Surface Elevation
(m) Free-
board
50 yr
(m)
Remarks 50
Year
100
Year
Reg.
Storm
50
Year
100
Year
Reg.
Storm
West Don River tributary
10.05 12.32 51.49 233.35 227.40 227.60 230.39 5.95
No overtopping
under the
Regional Storm
The full Drainage Report and Stormwater Management Report can be found in Appendix K.
Watercourse Crossing Structures 4.8
Within the study corridor there is one crossing of the West Don River tributary located1.18 km East of
Jane Street (Culvert ID 25-18 C1180). The existing structure is a 4.7 m diameter multi-plate pipe
culvert that was constructed in 1968, with an approximate total length of 58 m and fill depth of 7 m.
Based on the findings of the visual inspection conducted by HDR in August 2017, the pipe culvert
was found to be in poor structural condition and immediate replacement was recommended. Based
on the ‘emergency’ nature of this culvert replacement, the work is being carried out as a separate
Class EA, Schedule “A” undertaking
The complete Structural Inspection Report can be found in Appendix S.
Utilities and Other Services 4.9
There are existing utilities within the study corridor, including a hydro pole line on the south side of
Major Mackenzie Drive between McNaughton Road/Avro Road and Keele Street.
A review indicated the following utilities are present within the study corridor:
Alectra Utilities
o Existing Electrical Underground plants were found.
o Above ground hydro poles are also located on the south side of Major Mackenzie Drive
Bell (Telecommunications)
o Existing Bell Canada underground plant were identified in the area.
Rogers
o Rogers Communications currently has existing underground plants and fiber optic cables.
Enbridge (Gas service)
o A gas pipeline (NPS 4 SC HP) runs along Major Mackenzie Drive on the south side from
McNaughton Road / Avro Road to Killian Road / Netherford Road before diverging to north
through to Keele Street.
Water and Wastewater Management 4.9.1
The City of Vaughan is replacing the existing 300 mm diameter cast iron and 350 mm diameter
ductile iron watermains on Major Mackenzie Drive from approximately 90 m west of Jane Street to
Keele Street with a 400 mm PVC pipe.
The proposed watermain will reconnect to the existing Wonderland water line approximately 90 m
west of Jane Street, and the 450 mm diameter watermain at Keele Street. The work will also include
the replacement of all substandard service connections from the main to the streetline, including curb
stops, as well as replacement of existing valves and valve chambers, fire hydrants, and connections
to existing watermains and/or chambers at the project limits. The construction is scheduled to be
completed by the end of fall 2018
Illumination 4.9.2
Major Mackenzie Drive within the study limits is illuminated primarily with conventional streetlight
systems. Along the north boulevard between Gram Street and Keele Street, varying decorative light
fixtures have been placed to enhance the public realm. From Gram Street westerly towards
McNaughton Road/Avro Road, standard light poles are placed approximately 55 meters apart on the
north side.
Light poles on the south side of Major Mackenzie Drive generally have 55 meter spacing between
McNaughton Road/Avro Road and Gram Street. The separation distance then decreases into the
range of 35 and 45 meters between Gram Street and Keele Street.
Road Geometrics 4.10
The present geometric conditions in the study area were compared with the York Region Design
Guidelines and Standards (December 2016 Version 1.20), as well as the Transportation Association
of Canada Geometric Design Guide (TAC 2017) and/or the Geometric Design Standards Manual for
Ontario Highways (GDSM 2002). For the most part, the reviewed road geometrics meet design
standards.
Vertical and Horizontal Alignment 4.10.1
The existing horizontal alignment is tangent East and West between McNaughton Road/Avro Road
and Jackson Street. There are two deflection points, at less than 0.5° without horizontal curves.
According to MTO GDSM 2002, the maximum deflection angle without horizontal curve is 0.5°.
Therefore, there are no horizontal alignment deficiencies along this segment of Major Mackenzie
Drive. From Jackson Street to west of Keele Street the horizontal alignment consist of two back to
back curves with radii of 1000 m. Both curves exceed the minimum radius of 200 m / 300 m (for 4%
super elevation and reverse crown respectively) but do not exceed the minimum radius (2000 m) for a
normal crown section. Based on TAC 2017 the pavement crossfall should be reverse crown (2%
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 25
superelevation). However, the existing crossfall at this location is at normal crown (-2%) and therefore
is below standard based on a design speed of 70 km/hr.
Urban Development 4.11
As of the completion of this report, only two lots are in the process of redevelopment, abutting the
study area. Forty-five (45) townhomes are under construction at 2269-2285 Major Mackenzie Drive
while a site plan application was received by the City of Vaughan in May 2018 for a mixed-use
development at 2338 Major Mackenzie Drive, as can be seen in Exhibit 4-18.
Exhibit 4-18: Development in the study area
Because this study is focused on reviewing access issues between McNaughton Road / Avro Road
and Keele Street, only the development within this section of the corridor was reviewed.
5 Needs Assessment The existing and future transportation operations within the corridor and resultant issues/needs are
discussed in the following sections.
Existing Transportation Operations 5.1
Existing traffic operation conditions are documented in the following sections, including traffic
volumes, intersection operations, active transportation and safety. The York Region model,
intersection signal timings and volume counts were provided to HDR for use in the analysis.
Traffic Volumes – Peak Hour Turning Movement Counts 5.1.1
Turning movement counts (TMCs) were extracted from the Region’s Traffic Operations Assessment
Memo (2015), the corridor specific study that was discussed in further detail in Section 0. To fill in
data gaps, additional TMCs were provided by York Region while some were obtained by HDR/OTI in
2017. A summary of the count locations and count dates are detailed in Table 5-1. Existing weekday
AM and PM peak hour traffic volumes and existing lane configurations are shown in Exhibit 5-1.
Table 5-1: Turning Movement Count Locations and Dates
Count Location Count Date Source
Major Mackenzie Drive @ Keele Street
Tuesday, March 15
th 2015
York Region
Major Mackenzie Drive @ 2266 Driveway
Major Mackenzie Drive @ Gold Spruce Lane-Jackson Street
Major Mackenzie Drive @ 2316 Driveway
Major Mackenzie Drive @ 2332 Driveway
Major Mackenzie Drive @ 2338 Driveway
Major Mackenzie Drive @ 2354 Driveway
Major Mackenzie Drive @ 2396 Driveway
Major Mackenzie Drive @ 2414 Driveway
Major Mackenzie Drive @ Gram Street
Major Mackenzie Drive @ Killian Road/Netherford Road
Major Mackenzie Drive @ St. David’s Church Entrance/Appletree Montessori School
Monday, April 25th
2017 OTI
Major Mackenzie Drive @ McNaughton Road/Avro Road Tuesday, March 15
th 2015
York Region
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 26
Exhibit 5-1: 2015 Existing Weekday AM and PM Peak Volumes
(Source: Traffic Operations Assessment Memo 2015)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 27
Existing Intersection Operations 5.1.2
Existing intersection operations were analyzed using the software program Synchro based on the
existing lane configurations shown in Exhibit 5-1. Synchro employs methodology from the Highway
Capacity Manual (HCM 2000) published by the Transportation Research Board National Research
Council. It can analyze both signalized and unsignalized intersections in a road corridor or network
taking into account the spacing, interaction, queues and operations between intersections.
The intersection analysis considers two separate measures of performance:
The level of service (LOS) for all intersection movements, which is based on the average
control delay per vehicle for each of various movements through the intersection, and for the
overall intersection, and
The capacity of all intersection movements, which is based on a volume to capacity ratio (v/c);
Level of service is based on the average control delay per vehicle for a given movement. Delay is an
indicator of how long a vehicle must wait to complete a movement and is represented by a letter
between ‘A’ and ‘F’, with ‘F’ being the longest delay.
HCM delays and corresponding letter grades are shown below in Table 5-2.
Table 5-2: Signalized Intersection Level of Service (HCM 2000)
Level of Service (LOS)
Control Delay per Vehicle (s)
Notes
A ≤ 10
Generally LOS A, B, and C are considered acceptable. B > 10 and ≤ 20
C > 20 and ≤ 35
D > 35 and ≤ 55 LOS D indicates that delays are more perceptible.
E > 55 and ≤ 80 LOS E and F indicate notable delays but may be acceptable in urban contexts and justify monitoring F > 80
The volume to capacity (v/c) ratio is a measure of the degree of capacity utilized at an intersection. A
v/c ratio less than 0.85 generally indicates that adequate capacity is available and vehicles are not
expected to experience significant queues and delays. As the v/c ratio approaches 1.0, traffic delay
and queuing conditions may occur. Once the demand exceeds the capacity (a v/c ratio greater than
1.0), traffic flow is unstable and excessive delay and queuing is expected. Under these conditions,
vehicles may require more than one signal cycle to pass through the intersection.
Signalized Intersection Level of Service 5.1.2.1
As was displayed in Table 5-1, current traffic volumes are based on traffic counts undertaken by York
Region on Tuesday, March 15th, 2015 between the hours of 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to
6:00 p.m. To fill in gaps in data, additional counts were collected by HDR/OTI during the same hours
on April 25th, 2017. Synchro default values were used in the analysis for all parameters including
saturated flow rates of 1,900 vehicle per hour green per lane (vphgpl) and lane widths of 3.5m.
Volume data including conflicting pedestrians, peak hour factors, and heavy vehicle percentages from
the relevant traffic counts were input into Synchro to analyze existing traffic operations at signalized
intersections, summarized in Table 5-3. Critical movements, defined as those yielding a volume to
capacity (v/c) ratio greater than 0.85 or with a level of service (LOS) of ‘E’ or ‘F’, are shown in bold in
Table 5-3. Generally, LOS ‘E’ or a v/c ratio of 0.85 justifies monitoring, while LOS ‘F’ or v/c ratio
exceeding 1.0 suggests the need for improvements.
Table 5-3: Existing Signalized Intersection Traffic Operations
(Source: Major Mackenzie Drive Traffic Operations Assessment Memorandum 2015)
Signalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95th
Queue (m)
Major Mackenzie Drive @ Keele Street F 1.13 F 1.15
EBL C 0.49 18 D 0.76 45
EBTR F 1.12 285 F 1.08 285
WBL F 0.92 64 F 0.91 82
WBTR F 1.13 318 F 1.15 331
NBL E 0.83 50 E 0.84 86
NBTR C 0.39 57 E 0.89 150
SBL C 0.55 54 D 0.70 34
SBTR E 0.96 200 D 0.44 61
Major Mackenzie Drive @ Killian Road/Netherford Road
C 1.08 C 0.88
EBL A 0.32 5 D 0.76 41
EBTR B 0.68 271 B 0.70 283
WBL B 0.26 14 D 0.53 31
WBTR C 0.75 240 C 0.83 251
NBL F 1.08 64 F 0.88 90
NBTR C 0.14 12 D 0.25 28
SBL E 0.22 23 D 0.05 9
SBTR D 0.68 58 B 0.31 20
Major Mackenzie Drive @ McNaughton Road/Avro Road
D 1.09 D 1.51
EBL F 1.09 76 F 1.51 135
EBT D 0.75 265 D 0.80 277
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 28
Signalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95th
Queue (m)
EBR A 0.02 0 A 0.01 0
WBL C 0.74 28 D 0.82 34
WBT D 0.91 311 C 0.88 304
WBR A 0.04 0 A 0.06 3
NBL E 0.25 10 D 0.09 12
NBTR E 0.74 100 F 0.93 144
SBL E 0.46 31 E 0.50 23
SBTR E 0.89 108 C 0.37 36
Notes: Operations shown in bold for critical movements only. LOS – Level of Service. V/C – Volume to Capacity Ratio. 95
th Queue – The 95
th percentile queue, shown in meters, is a Synchro output and is provided as a reference. See
Section 5.1.3 for additional discussion on queuing.
Under existing conditions, all signalized intersections within the study area are operating near or over
the available capacity during peak periods. The signalized intersection of Major Mackenzie Drive at
Keele Street is not operating well, with overall level of service ‘F’ during the weekday AM and PM
peak hours. The majority of movements at this intersection are operating with level of service ‘F’ and
‘E’ and with volume to capacity ratios higher than 0.83, with the exception of the southbound left-turn
and eastbound left-turn, which are operating with an AM and PM level of service ‘C’ and ‘D’,
respectively. The westbound left-turn has a LOS ‘F’ and is currently protected / permitted.
Conditions are marginally better at the intersection of Major Mackenzie Drive and Killian
Road/Netherford Road, where the overall level of service is ‘C’ and a v/c ratio of 1.08 and 0.88 during
the AM and PM peak hour, respectively.
At the western limit of the study area, the intersection of Major Mackenzie Drive and McNaughton
Road/Avro Road has a LOS ‘D’ in both AM and PM peak hours. Its eastbound-left approach has v/c
ratio of 1.5 during the PM peak hour, higher than all other results along the study corridor.
The 95th percentile queues are provided. Section 5.1.3 provides additional discussion on queuing.
Unsignalized Intersection Level of Service 5.1.2.2
The study area also has a large number of unsignalized driveway access points and two unsignalized
intersections. These locations were analyzed and the results are presented in Table 5-4.
Table 5-4: Existing Unsignalized Intersection and Entrance Traffic Operations
(Source: Major Mackenzie Drive Traffic Operations Assessment Memorandum)
Unsignalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95
th
Queue (m)
2266 Major Mackenzie Drive Driveway- Shoppers Drug Mart parking lot
B - - B - -
EBLT A 0.01 0 A 0.01 0
SBLR E 0.05 1 F 0.51 15
Major Mackenzie Drive and Jackson Street
B - - B - -
EBLT - - - A 0.02 1
WBLT A 0.01 0 A 0.02 1
NBLTR C 0.03 1 C 0.05 1
SBLTR F 0.08 2 F 0.47 9
2316 Major Mackenzie Drive Driveway- Retail Plaza Access
B - - B - -
EBLT A 0 0 A 0.01 -
SBLR B 0 0 B 0.01 -
2332 Major Mackenzie Drive Driveway- Retail Plaza Access
B - - B - -
EBLT A 0.01 0 A 0.01 0
SBLR B 0.01 0 F 0.22 6
2338 Major Mackenzie Drive Driveway- Service access
B - - B - -
EBLT A 0.01 0 - 0 0
SBLR B 0.06 1 F 0.07 2
2354 Major Mackenzie Drive Driveway- Retail plaza access
B - - A - -
EBLT A 0.01 0 A 0.09 2
SBLR B 0.01 0 F 1.13 4
2396 Major Mackenzie Drive Driveway- 2396 Major Mackenzie Drive- Courtyards
of Maple Condominiums Driveway B - - B - -
EBLT A 0 0 A 0 0
SBLR F 0.05 2 F 0.13 3
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 29
Unsignalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95
th
Queue (m)
2414 Major Mackenzie Drive Driveway- Maple Convenience & Post Office
Access B - - B - -
EBLT A 0.03 1 A 0.04 1
SBLR F 0.2 5 F 1.11 37
Major Mackenzie Drive/ Gram Street B - - C - -
WBLT A 0.61 0 A 0.05 1
NBLR C 0.07 2 F 0.37 11
2600-2601 Major Mackenzie Drive Driveway – St. David Catholic Church/Appletree Montessori
A - - A - -
EBT A 0.46 0.2 A 0.66 0.1
WBT A 0.51 0.1 A 0.57 0.2
At the macroscopic level, operations at driveways and non-signalized intersections appear to be
acceptable as the overall intersection level of service is ‘C’ or better during the AM and PM peak
periods. However, individual movements have lower levels of service which indicates the presence of
access issues. Conditions at these critical movements present the opportunity to improve operations.
For the most part, critical movements at unsignalized intersections and driveways are operating with
v/c ratios between 0.01 and 0.51. Some, like the southbound left-turn movement at Major Mackenzie
Drive and 2414 Driveway and at Major Mackenzie Drive and 2354 Driveway, have noticeably higher
v/c ratios (reaching 1.1 and 1.13 respectively), indicating demand exceeds capacity
Traffic operations appear to be worse in the afternoon compared to the morning peak period, as
illustrated by the lower LOS in the afternoon for the Gram Street, 2354 Driveway and 2332 Driveway
intersections. Furthermore, almost all intersections and driveways have a movement with level of
service F during the PM peak period. The southbound shared left/right turn movement at Major
Mackenzie Drive and 2414 Driveway experiences the worst queuing during the PM peak period, with
queues reaching 37m into the surface parking lot.
The LOS at critical movements during the AM and PM peaks are illustrated in Exhibit 5-2 and
Exhibit 5-3.
Exhibit 5-2: AM Peak Hour Critical Movements
Exhibit 5-3: PM Peak Hour Critical Movements
Queuing 5.1.3
Queuing was examined for all intersections between McNaughton Road/Avro Road and Keele Street
to better understand impacts to driveway access. There was extensive queuing observed in the
segment between Killian Road/Netherford Road and Keele Street. Queuing conditions were analyzed
for existing AM and PM peak hour for that segment, along with existing gap times for left- and right-
turning traffic at unsignalized accesses between Killian Road/Netherford Road and Keele Street. Both
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 30
AM and PM peak hour conditions were assessed using Simtraffic; however, the queue lengths and
issues were similar during both peak hours, therefore only the AM peak hour is presented in detail
below to demonstrate the queuing issues.
Simtraffic is capable of a more comprehensive queuing analysis compared to Synchro, as it simulates
upstream/downstream queuing effects, queue spillback, intersection spacing, and storage
deficiencies. The following section is intended to supplement the 95th percentile queuing results for
unsignalized intersections (shown in
on Major Mackenzie between Killian Road/Netherford Road and Keele Street.
There are numerous driveways west of Keele Street that provide access to commercial plazas on the
north side of Major Mackenzie Drive, as well as stop-controlled intersections on the south side of
Major Mackenzie Drive that provide access to built-out residential areas (e.g. Jackson Street, Gram
Street). Typical queues for the AM peak hour conditions are illustrated in Exhibit 5-4.
Exhibit 5-4: Existing AM Peak Hour Queuing Conditions
The SimTraffic analysis did not show any significant queuing west of Gram Street. However, between
Gram Street and Keele Street, there were long queues in the eastbound direction resulting from the
high volumes of eastbound-through trips at Keele Street. The eastbound queue at Keele Street also
extends more than 400m reaching Gram Street, as illustrated in Exhibit 5-4.
Due to the eastbound queue spillback and the absence of a two-way centre left-turn lane, eastbound
vehicles attempting to turn left into the various driveways on the north side of Major Mackenzie Drive
are often unable to do so immediately and contribute to through lane blockage. They must wait for
gaps in westbound traffic (i.e. first queue with eastbound-through traffic) which further exacerbates
eastbound through queues along the corridor. In addition, the eastbound queue does not provide
sufficient gaps for vehicles exiting from the unsignalized driveways on Major Mackenzie Drive,
causing significant delays to vehicles exiting southbound-left and northbound-right vehicles (many of
which operate at LOS ‘E’ or ‘F’, as detailed in Table 5-4.
As insufficient gaps are available due to eastbound traffic queues, access to and from unsignalized
intersections west of Keele Street is limited.
Transit Service Quality 5.1.4
The corridor is served by four mixed traffic bus routes – Routes 560, 462, 4 and 4A– however only
Routes 4 and 4A provide regular service throughout the day. During peak periods, Routes 4 and 4A
have a frequency of approximately 30 minutes. Furthermore, peak period travel times are significantly
hindered by existing traffic. The delay experienced by transit vehicles was examined for the study
corridor using the Google Maps travel time query. In September 2017, a 4 minute bus journey from
Keele Street to McNaughton Road/Avro Road during non-peak times becomes a 7 minute trip during
the morning peak period. The extra 3 minutes spent on the bus represent a 75% increase in travel
time; a notable decrease in transit quality of service caused by mixed traffic operations.
Transit quality of service was also assessed based on stop spacing, which is an important
consideration when determining the draw or appeal of a bus network. Within the study corridor, the
average bus stop spacing of 400m is well within the range set by York Region Transit`s Transit
Services Guidelines (2016), which states that the typical bus stop spacing for local bus routes should
typically be between 300m and 500m.
Pedestrian Quality of Service 5.1.5
To better understand the existing pedestrian conditions, a multi-modal level of service (MMLOS)
analysis was undertaken along the corridor. The methodology employed for this study is based on the
City of Ottawa MMLOS Guidelines, September 2015. These guidelines were selected over other
variations mainly for their intuitiveness, accommodation of contemporary facility designs, and explicit
recognition that pedestrian LOS should be based on user comfort, safety, and convenience and are
subjective in nature.
Pedestrian level of service (PLOS) is calculated at the intersection and mid-block in recognition that
pedestrian experience is determined by the conditions both between crossings and at the crossing
itself. The methodology generally follows a weakest link approach. This means that the segment is
scored at its weakest portion to account for the fact that the pedestrian experience is best defined by
the more dangerous segment.
The methodology for the evaluation of segment PLOS utilizes a look-up table approach based on
cross-section and roadway characteristics (e.g., sidewalk and boulevard width, traffic volumes,
presence of on-street parking, and operating speed). Intersection PLOS uses the Pedestrian
Exposure to Traffic at Signalized Intersections (PETSI) and assigns points based on a number of
crossing characteristics (e.g., crossing distance, presence of a median, presence of a crossing
refuge, turning restrictions, right hand turn characteristics, curb radii, etc.). This is calculated for each
crossing (e.g., north, south, east, west) and their averages are computed to derive an overall
intersection PLOS. However, each crossing’s score should be considered individually when
recommending improvements.
The study area is notable for the multiple driveway access points which, in addition to impeding the
flow of pedestrians on the sidewalks, create conflict points between humans and vehicles. The PLOS
methodology is not adapted to address the impacts of vehicle ingress/egress and may potentially
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 31
overestimate the conditions for pedestrians along Major Mackenzie Drive. These are important
constraints to keep in mind when assessing improvements to the pedestrian realm.
The look, feel, and function of the study corridor changes along its length as does the level of comfort
experienced by pedestrians.
Overall, the pedestrian experience could be improved as Major Mackenzie Drive receives, for the
most part, a ‘D’ score. Along the north side of the study corridor, the segment PLOS achieves scores
‘B’ and ‘C’ for the most part (see Exhibit 5-5 and Exhibit 5-6).
Conditions are worse along the south side, with scores varying between `D’ and `E’ (Exhibit 5-7and
Exhibit 5-8). The low scores can be attributed to high traffic volumes (i.e. greater than 3000 AADT),
1.5m sidewalks (minimum width to meet provincially accessible standards) and narrow buffers
between the roadway and the sidewalk.
Because the intersection PLOS methodology only applies to signalized intersections, the intersection
PLOS was evaluated for only 3 intersections along the study corridor. Keele Street and McNaughton
Road/Avro Road intersections both received a PLOS ‘E’ while the intersection at Killian
Road/Netherford Road scored a ‘D’. Intersection PLOS scores of ‘D’ are indicative of somewhat
shorter crossing distances (3-4 lanes), relatively small corner radii, and ladder crosswalk treatments.
Scores of ‘E’ tend to apply to intersections with longer crossing distances, simple transverse markings
and high turn speeds facilitated by large corner radii. For example, the intersection of McNaughton
Road/Avro Road and Major Mackenzie has a low score because pedestrians must cross a total of 5-6
lanes with no island refuge. Furthermore, the limited visibility of the crosswalk markings at that
location, combined with high turning speeds, makes the pedestrian experience less than desirable.
The MMLOS methodology does not incorporate considerations related to the spacing of protected
crossings for pedestrians. Given the larger distance (685 m) between the Killian Road / Netherford
Road and Keele Street signalized intersections, the actual pedestrian level of service is likely lower
than this methodology projects. The opportunity to cross Major Mackenzie Drive safely is limited
which poses an inconvenience to pedestrians and impacts the walking quality of service.
The results of the PLOS evaluation are summarized graphically in Exhibit 5-9.
Exhibit 5-9: Segment and Intersection PLOS along Major Mackenzie Drive
Cyclist Quality of Service 5.1.6
At present, cyclists are required to share the roadway with vehicles in the study area as there are no
designated cycling facilities on Major Mackenzie Drive.
MMLOS analysis was undertaken to assess the quality of the cycling environment along Major
Mackenzie Drive. As noted, the methodology employed for this study is based on the City of Ottawa’s
MMLOS Guidelines. Bicycling level of service (BLOS) is calculated at the intersection and mid-block
in recognition that, unlike vehicular LOS, a cyclist’s experience is determined by the conditions both
between crossings and at the crossing itself.
The BLOS methodology is similar to the PLOS method, and is based on roadway characteristics and
facility type and quality. The methodology measures each segment’s and intersection’s level of traffic
stress experienced by the cyclist, established in the Minnesota Transportation Institute Report No. 11-
19. The assessment is associated with a letter score from A to F.
Segment BLOS are calculated using a look-up table approach and considers facility type, street
width, operating speed, and parking characteristics. As with segment PLOS, segment BLOS is
calculated using a weakest link approach, meaning that the worst portion of a segment is used to
calculate its BLOS. This is in line with the methodology’s user-centric focus which evaluates a user’s
Exhibit 5-5: Segment PLOS 'B' (Source: Google Streetview)
Exhibit 5-6: Segment PLOS 'C' (Source: Google Streetview)
Exhibit 5-7: Segment PLOS 'D' (Source: Google Streetview)
Exhibit 5-8: Segment PLOS `E` (Source: Google Streetview)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 32
perceived safety from a network perspective (in this case the segment). Intersection BLOS is
calculated for each approach and for both left and right turning conditions. Scores are evaluated
using a look-up table approach. For a typical 4-way intersection, eight scores are calculated—a left
and right movement for each approach. To show one intersection BLOS, the scores are averaged.
Segment BLOS is most sensitive to facility type, with physically separated bikeways such as cycle
tracks, protected bike lanes and multi-use paths receiving a score of ‘A’. Scores for mixed-traffic and
on-street cycling lanes (without separation) are highly dependent on traffic volume and speed as well
as facility width (if applicable). A quiet 2-lane residential street with vehicle speeds less than or equal
to 40 km/h, for example, would score an ‘A’ while the same mixed-traffic facility would score an ‘F’ if
the speeds were greater than 60 km/h. Where there are no dedicated cycling facilities, high operating
speeds and wide roadways, the scores would generally tend lower – ‘D’ to ‘F’.
Major Mackenzie Drive between McNaughton Road/Avro Road and Keele Street does not
accommodate cyclists in a separate or designated facility. The segment BLOS is ‘E’ for the entire
study corridor, due to the four lane cross-section and 50 km/h posted speed (see Exhibit 5-10).
Intersections do not provide special accommodations of cyclists making left or right turns. Cyclists
operate in mixed traffic and must cross several lanes to make left turns and traversing long right turn
lanes. The signalized intersection at McNaughton Road/Avro Road (Exhibit 5-11) and at Keele Street
received an intersection BLOS score ‘E’ while Killian Road/Netherford Road received a score ‘D’.
The results of the BLOS evaluation are graphically summarized in Exhibit 5-12.
Exhibit 5-12: Segment and Intersection BLOS along Major Mackenzie Drive
Public Petition 5.1.7
Concerns were raised by study area residents regarding pedestrian safety through a petition signed
by 25 members of the Maple community. The petition called for the introduction of a protected
pedestrian crossing across the commercial plaza on the north side of Major Mackenzie Drive between
Keele Street and Killian Road/Netherford Road (a specific location was not noted). The crossing was
supported by residents in order to ensure the safe access given the number of shops and services
between Gram Street and Keele Street.
The petition can be found under Appendix N.
Exhibit 5-10: No dedicated facility, cyclists operate in mixed traffic (Source: Google Streetview)
Exhibit 5-11: Aerial view of McNaughton Road/Avro Road intersection, BLOS ‘E’ (Source: Google Maps)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 33
Future Transportation Conditions 5.2
Land use conditions surrounding Major Mackenzie Drive within the study limits are not anticipated to
change significantly by this study’s horizon year of 2020, as the areas north and south of the study
limits are already developed and not marked for intensification over the long term. The complete
report documenting the transportation system technical analysis for Phase 1 of this study is provided
under Appendix M.
Future Population and Employment Growth 5.2.1
Population and employment forecast assumptions were extracted from the York Region EMME Model
and are summarized in Table 5-5. A map illustrating these growth areas is provided in Exhibit 5-13.
Minimal growth in population and employment is anticipated by 2020.
Table 5-5: Population and Employment Growth Assumptions (York Region EMME Model)
Model
Zone
Population Employment
2011 2021 2031 2011 2021 2031
2099 1,521 1,557 1,554 418 519 522
2101 9,971 10,027 10,003 855 861 867
2105 1,655 1,639 1,635 689 837 839
2156 2,493 2,507 2,501 738 789 794
Total 15,640 15,730 15,693 2,700 3,006 3,022
In the traffic zones adjacent to the study corridor, population is anticipated to increase by 53 residents
between 2011 and 2031 while employment is expected to see an increase of 322 workers within that
time frame. Between 2011 and 2021, population is forecast to grow by 90 residents and employment
by 306 workers.
Exhibit 5-13: Model traffic zones adjacent to EA Study Limits
York Region Model 5.2.2
The key tool to assess future conditions and the development of the proposed transportation network
is the York Region Travel Demand Forecasting Model. The York Region Model is a conventional four-
step multi-modal transportation forecasting model that was last updated by York Region in 2014 and
validated to 2011 Transportation Tomorrow Survey (TTS) data and cordon counts. The York Region
Model is described at length in the York Region Travel Demand Forecasting Model Update Report
dated June 30, 2014 and a subsequent memorandum on the 2011 York Region Model Validation
dated August 8, 2014. These documents were used for background information on the application of
the Model for the 2016 York Region TMP (YR-TMP).
The Model predicts AM weekday peak period travel demands for motorized modes – transit,
automobile driver and automobile passenger. The Model includes the Greater Toronto and Hamilton
Area (GTHA) as well as external areas including the Counties of Peterborough, Simcoe, Dufferin, and
Wellington and the Regional Municipalities of Waterloo, Niagara Falls and Brant/Brantford. The model
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 34
zone system is based on the 2006 GTA traffic zone system, and further refined with an additional 41
disaggregated zones in York Region for a total of 519 zones for York Region. The modified zone
system is referenced as the 2011 zone system.
Traffic volumes were extracted for the 2011 and 2021 years. The 2021 scenario incorporates
projects from the 2017-2021 proposed transportation network, as per the YR-TMP. Growth rates were
derived from the growth in the ten year period between 2011 and 2021, then applied to existing traffic
volumes to estimate the 2020 volumes.
In May 2016, MTO released an amendment to the Growth Plan for the Greater Golden Horseshoe
(GGH) which identified a new 60% target for intensification. As forecasts for this 60% land use
intensification will take time to develop, York Region identified an interim 45% land use intensification
scenario. The 45% scenario was used for this analysis and incorporates refined population and
employment forecasts identified in the Draft Block 27 Secondary Plan and the Draft Block 41
Secondary Plan currently being studied in the City of Vaughan.
Table 5-6 shows the 2011 and 2021 York Region Model volumes for Major Mackenzie Drive.
Table 5-6: York Region Unadjusted Model Volumes for Major Mackenzie Drive
Year Intersection @ Major Mackenzie Drive
NBin NBout SBin SBout EBin EBout WBin WBout
2011 model volumes
McNaughton Road/Avro Road
N/A 155 414 N/A 1063 909 1433 1847
Killian Road/Netherford Road
105 100 334 102 909 932 1218 1433
Keele Street 226 372 1459 1721 932 739 1433 1218
2021 model volumes
McNaughton Road/Avro Road
N/A 143 381 N/A 1232 1089 1551 1932
Killian Road/Netherford Road
87 104 335 113 1089 1110 1366 1551
Keele Street 413 532 1685 1944 1110 879 1513 1366
Future Road Network 5.2.3
2020 Traffic Volumes 5.2.3.1
As specified previously, the Region’s EMME model provides the basis for the 2020 traffic volumes.
Due to the absence of new development or redevelopment planned along Major Mackenzie Drive
between existing (2017) and 2020, most growth will take place at major access locations/signalized
intersections in the study area, whereas growth at unsignalized intersections (i.e. driveways) and
residential access locations (e.g. Avro Road) is expected to be marginal. Therefore, traffic volume
analysis and intersections operations at signalized intersections only are summarized in the following
sections.
Once the 2011 and 2021 York Region model forecast volumes were extracted, compound annual
growth rates (CAGR’s) were calculated at the 3 signalized intersections in the study area. The CAGR
results are presented in Table 5-7.
Table 5-7: Constant Annual Growth Rates (2011-2021 model)
Intersection @ Major Mackenzie
CAGR from 2011 Model to 2021 Model (unadjusted)
NBin NBout SBin SBout EBin EBout WBin WBout
McNaughton Road/Avro Road
0% -0.80% -0.83% 0% 1.49% 1.82% 0.79% 0.45%
Killian Road/Netherford Road
-1.86%
0.39% 0.03% 1.03% 1.82% 1.76% 1.15% 0.79%
Keele Street 6.21% 3.64% 1.45% 1.23% 1.76% 1.75% 0.54% 1.15%
For locations with negative growth rates, a CAGR of 0.1% was assumed. Furthermore, no growth
was assumed for the McNaughton Road/Avro Road’s Northbound In and Southbound Out
approaches due to the unavailability of 2011 and 2021 model volumes. This is a reasonable
assumption given no growth is forecasted within this block (Model Zone 2099 in Table 5-5).
The volumes discussed in this section focus on the 2020 AM peak hour volumes which dictate the
need for operational improvements. 2020 AM peak hour approach volumes were used to forecast
turning movement counts along the corridor. These volumes were calculated by first determining
forecast link CAGR’s, applying the CAGR’s on existing approach volumes, and performing
Fratar/Furness operations on approach forecast volumes to estimate turning movement volumes.
The Fratar/Furness method is the application of a well-established bi-proportional updating algorithm.
At a high level, this algorithm takes existing turning movement volumes and 2020 AM peak hour entry
and exit approach volumes (target volumes) as inputs, and rebalances existing turning movement
volumes to match the 2020 target volumes. The Fratar/Furness method is an effective method for
future turning movement volume analysis as it takes into account existing travel patterns as part of its
rebalancing algorithm, while minimizing errors associated with traditional turning movement growth
analysis.
Using this approach, 2020 AM peak hour volumes in the study area were calculated as illustrated in
Table 5-8.
Table 5-8: 2020 AM link volumes (Furnessed)
Intersection @ Major Mackenzie Drive
2020 volumes
NBin NBout SBin SBout EBin EBout WBin WBout
McNaughton Road/Avro Road
262 320 659 442 1753 1775 1880 2017
Killian Road/Netherford Road 133 70 246 130 1691 1631 1637 1876
Keele Street 635 437 1271 1251 1484 1611 1583 1674
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 35
As illustrated in Table 5-8, the peak direction in 2020 AM peak hour traffic is westbound at
McNaughton Road/Avro Road, with approximately 2017 vehicles per hour, which marginally exceeds
the single lane capacity of about 900 vehicles per hour per lane for a volume to capacity ratio of 1.12.
Based on Highway Capacity Manual level of service definitions, link v/c ratios under 0.85 are
acceptable, 0.85 to 1.0 typically result in increased delays and queuing, and v/c ratios in excess of
1.0 have significant delays and queues. Further details on intersection traffic operations can be found
in the following section.
Future Intersection Operations 5.2.4
As previously mentioned, the Regions EMME model was utilized to estimate future 2020 traffic
conditions. The 2020 AM Peak hour traffic volumes were developed using EMME at a link volume
level of detail and further refined using a frataring/furnessing process to develop traffic volumes for
individual turning movements. Due to the absence of a PM Peak EMME model, the 2020 PM Peak
hour turning volumes were based on the calculated AM growth rates of a reversed movement, i.e. PM
NBT growth rate would be from the AM SB, NBR from WBL, EBL from SBR, etc. The resultant 2020
AM and PM peak hour turning movement volume projections (no widening scenario) are shown in
Exhibit 5-14 and Exhibit 5-15. Both 2020 AM and PM traffic operation analysis results are
summarized in Table 5-9. Critical movements, defined as those yielding a v/c ratio greater than 0.85
or with a level of service ‘E’ or ‘F’, are shown in bold.
Exhibit 5-14: 2020 AM Peak Hour Traffic at Signalized Intersection
Exhibit 5-15: 2020 PM Peak Hour Traffic at Signalized Intersections
Signal timings in the study area are optimized to accommodate any changes in volume growth
between existing and 2020 conditions. Generally, future signal timings are expected to be similar to
existing due to relatively low volume growth for all movements.
Table 5-9: 2020 Intersection Traffic Operations (Existing Intersection Configuration)
Signalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95
th
Queue (m)
Major Mackenzie Drive @ Keele Street
F 1.14 - F 1.13
EBL C 0.52 18 F 0.95 57
EBTR F 1.07 292 E 1.04 290
WBL F 1.02 65 F 1.06 96
WBTR E 1.05 303 F 1.07 321
NBL F 1.14 83 F 1.07 122
NBTR D 0.65 86 E 1.08 198
SBL D 0.64 59 E 0.79 39
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 36
Signalized Intersection & Movement
Weekday AM Peak Hour Weekday PM Peak Hour
LOS v/c 95
th
Queue (m)
LOS v/c 95
th
Queue (m)
SBTR F 1.14 241 E 0.80 88
Major Mackenzie Drive @ Killian Road/Netherford Road
C 1.07 - C 0.89
EBL A 0.35 5 E 0.81 41
EBTR B 0.72 278 B 0.73 267
WBL C 0.33 17 D 0.62 40
WBTR C 0.77 252 C 0.89 285
NBL F 1.07 63 F 0.89 95
NBTR C 0.15 13 D 0.20 30
SBL E 0.24 24 D 0.06 9
SBTR D 0.70 60 D 0.11 20
Major Mackenzie Drive @ McNaughton Road/Avro Road
D 0.95 - E 1.08
EBL E 0.88 89 F 1.09 134
EBT C 0.85 263 C 0.84 268
EBR A 0.02 0 B 0.01 0
WBL D 0.79 20 E 0.83 43
WBT D 0.95 292 E 1.05 398
WBR A 0.04 0 B 0.05 4
NBL E 0.22 3 D 0.09 11
NBTR E 0.80 70 F 0.94 129
SBL F 0.69 20 E 0.65 88
SBTR E 0.89 77 D 0.25 31
Notes: Operations shown for critical movements only. LOS – Level of Service. v/c – Volume to
Capacity Ratio. 95th Queue – 95th percentile queue shown in metres
Moreover, signal timings in the study area were optimized to accommodate any changes in volume
growth between existing and 2020 conditions. Generally, future signal timings are similar to that of
existing due to relatively low volume growth for all movements
Due to the relatively low magnitude of growth between existing and 2020 traffic volumes,
intersections operations are generally expected to be similar to existing conditions. However, there
are turning movements within the study area where the projected increase in traffic volumes from
existing conditions is expected to reach capacity:
AM Peak Hour:
Southbound through movement at Keele Street (increase from 0.96 to 1.14)
Westbound left-turn at Keele Street (increase from 0.92 to 1.02)
Northbound left-turn at Keele Street (increase from 0.83 to 1.14)
PM Peak Hour:
Westbound left-turn at Keele Street (increase from 0.91 to 1.06)
Northbound left-turn at Keele Street (increase from 0.84 to 1.07)
Northbound through-and-right turn at Keele Street (increase from 0.89 to 1.08)
Westbound through at McNaughton Road/Avro Road (increase from 0.88 to 1.0)
Under 2020 conditions, the signalized intersection of Major Mackenzie Drive at Keele Street is
expected to operate with overall level of service (LOS) ‘F’ during both the weekday AM peak and PM
peak hours. All movements except the southbound left-turn and eastbound left-turn are expected to
operate at LOS ‘F’ and with volume to capacity ratios higher than 1.00 during both AM and PM peak
hours. The westbound left-turn is expected to continue to operate at LOS ‘F’ and with a
protected/permitted phase already.
The overall intersection LOS at the intersection of Major Mackenzie Drive and Killian Road/Netherford
Road is ‘C’ for both the AM and PM Peak hour. At Major Mackenzie Drive and McNaughton
Road/Avro Road, the overall intersection LOS are ‘D’ and ‘E’ for the AM and PM peak hours,
respectively. The LOS results are depicted visually in Exhibit 5-16 and Exhibit 5-17.
2020 queuing conditions across the corridor were assessed and Major Mackenzie Drive. Given that
eastbound storage at Keele Street is only 30m, the intersection at this location has insufficient
storage in the eastbound direction to accommodate future queues, as demonstrated by the 95th
percentile queues in Table 5-9.
Exhibit 5-16: 2020 intersection level of service for drivers during weekday AM peak
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 37
Exhibit 5-17: 2020 intersection level of service for drivers during weekday PM peak
Traffic Safety Needs 5.3
Collision Analysis 5.3.1
Five-year (2009-2013) collision records were provided by the Region within the study limits. Between
Keele Street and McNaughton Road/Avro Road, there were 403 collisions of which 169 (42%) were
Property Damage Only (PDO), 73 (18%) were non-fatal injury collisions and 160 (40%) were non-
reportable collisions. No fatalities occurred in the study area within the 5-year time frame.
Collision rates for intersections were also retrieved from the Traffic Operations Assessment Memo
(2015) provided by York Region and are presented in Table 5-10 as collisions per million entering
vehicles (MEV). The location that shows the highest collision rates are the signalized intersection at
Major Mackenzie Drive and McNaughton Road/Avro Road, followed by the intersection at Keele
Street.
Table 5-10: Intersection Collision Rates
Intersection Total Collisions (2009-2013)
Average collisions per year
Intersection Collision Rate (MEV)
Major Mackenzie Drive & Keele Street 164 27.3 2.32
Major Mackenzie Drive & Jackson Street 8 1 0.18
Major Mackenzie Drive & Gram Street 19 3 0.42
Major Mackenzie Drive & Netherford Road/Killian Road
69 12 1.52
Major Mackenzie Drive & Avro Road/McNaughton Road
143 24 2.37
Total 403
Overall, intersections within the study area experienced collision rates below the MTO average rate of
2.7 collisions per million entering vehicles (MEV) for non-provincial roads/highways.
Collision rates per million vehicle kilometres (MVK) were also computed for segments using the
following formula:
𝑆𝑒𝑔𝑚𝑒𝑛𝑡 𝐶𝑜𝑙𝑙𝑖𝑠𝑖𝑜𝑛 𝑅𝑎𝑡𝑒 = 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐶𝑜𝑙𝑙𝑖𝑠𝑖𝑜𝑛𝑠 × 1,000,000
𝐴𝐴𝐷𝑇 × 365 × 𝐿𝑒𝑛𝑔𝑡ℎ × 𝑌𝑒𝑎𝑟𝑠
The 5-year Average Annual Average Daily Traffic (AADT) was retrieved from York Region’s AADT
Midblocks Report (2015). Midblock collisions were also provided for the analysis by York Region. The
results for segment collisions are depicted in Table 5-11.
Table 5-11: Segment Collision Rates
Segment Length
(km)
AADT (5yr-
Average)
Midblock Collisions
Average collisions per year
Segment Collision Rate
(MVK)
Major Mackenzie Drive between Jackson Street & Keele Street
0.14 36,822 22 3.7 2.3
Major Mackenzie Drive between Gram Street & Jackson Street
0.32 35,586 10 1.7 0.48
Major Mackenzie Drive between Killian Road/Netherford Road & Gram Street
0.22 31,062 3 0.5 0.24
Major Mackenzie Drive between McNaughton Road/Avro Road & Killian Road/Netherford Road
0.54 47,436 38 6.3 0.81
To supplement the collision analysis, the Regional Safety Study, Development of Safety Performance
Functions and Network Screening Final Report April 2013 was reviewed to identify intersections that
may be candidates for safety improvements. This report by York Region looked at 1,224 intersections
and 1,920 segments (non-intersection) using data from 2006 to 2010. The results from the Regional
study show how collision rates at intersections and segments within the Major Mackenzie Drive
corridor rank in comparison to others within the region from a safety perspective. The two parameters
extracted from the Regional study are Potential for Safety Improvement (PSI) and PSI Ranking.
These have been documented in Table 5-12 and Table 5-13.
Table 5-12: Intersection Collision Analysis
Intersection Collision Rate
(MEV)
Network Screening
PSI Rank Total PSI
Major Mackenzie Drive & Keele Street
2.32 39 71
Major Mackenzie Drive & Jackson Street
0.18 834 0
Major Mackenzie Drive & Gram Street 0.42 214 11
Major Mackenzie Drive & Killian Road/Netherford Road
1.52 649 0
Major Mackenzie Drive & McNaughton Road/Avro Road
2.37 57 50
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 38
Table 5-13: Segment Collision Analysis
Segment
Collision
Rate
(MVK)
Network Screening
PSI Rank Total PSI
Major Mackenzie Drive between Jackson Street & Keele
Street 1.9 38 36
Major Mackenzie Drive between Gram Street & Jackson
Street 0.4 1005 0
Major Mackenzie Drive between Killian Road/Netherford Road
& Gram Street 0.2 190 10
Major Mackenzie Drive between McNaughton Road/Avro
Road & Killian Road/Netherford Road 0.7 40 34
A higher PSI Ranking indicates a high potential for safety improvement. The PSI is the outcome from
a network screening analysis which is a process for reviewing a roadway network (intersections,
segments, ramps) in order to prioritize sites for improvement from highest to lowest. A network
screening process involves several analytical steps utilizing historical data of the network primarily
collision history.
The Network Screening analysis confirms the information provided by collision rates data. For
instance, the segment between Keele Street and Jackson Street has the highest calculated collision
rate and the highest PSI ranking or the highest potential for safety improvement.
It is important to note that of all reported collisions in the study area, no fatalities were recorded.
Pedestrian and Cyclist Collisions
Records from York Region’s Active Transportation Team were made available and show the following pedestrians and cyclist collisions since 2007:
9 collisions at Keele & Major Mackenzie intersection 3 collisions between Jackson Street and Keele Street 2 collisions at Netherford/Killian & Major Mackenzie intersection 4 collisions at McNaughton/Avro & Major Mackenzie intersection
As cyclists and pedestrians are more vulnerable on roads, conditions for them should be treated with
increased vigilance and importance despite the lower number of overall collisions observed for these
two modes.
Summary 5.3.2
Table 5-14 contains a summary of the key safety issues identified for the study corridor.
Table 5-14: Collision Trends Summary
Intersection Collision Trends
Major Mackenzie Drive & Keele Street
164 collisions (81 PDO, 25 Non-Fatal, 29 Non-Reportable)
40% of collisions were Rear-End initial impact while Angle collisions accounted for 18% of all collisions
Major Mackenzie Drive & Jackson Street
8 collisions (6 PDO, 2 Non-Fatal)
Rear-End and Angle collisions were the predominant impact types (75%)
Major Mackenzie Drive & Gram Street
19 collisions (9 PDO, 5 Non-Fatal, 5 Non-Reportable)
42% of collisions were Rear-End initial impact
Sideswipe (21%) and Angle (21%) collisions were equally common initial impact types
Major Mackenzie Drive & Killian Road/Netherford Road
69 collisions (31 PDO, 18 Non-Fatal, 20 Non-Reportable)
Rear-End collisions were the predominant impact type (68%)
Angle collisions made up 13% of collisions while Sideswipe accounted for 9% of the tolal count
Major Mackenzie Drive & McNaughton Road/Avro Road
143 collisions (49 PDO, 29 Non-Fatal, 66 Non-Reportable)
Rear-End collisions were the predominant impact type (59% or 85 collisions). Angle collisions made up 21% of collisions while Sideswipe accounted for 8% of the tolal count
Based on the 5-year collision data, there were no unusual collision rates observed along this segment
of Major Mackenzie Drive. Moreover, the Network Screening analysis confirms the information
provided by collision rates data. The segment between Jackson Street and Keele Street, which has
the highest calculated collision rate and the highest PSI ranking has the potential for safety
improvement.
The York Region Traffic Operations Assessment Memo (2015) provided the following list of potential
collision influencing factors:
Existing congested conditions on Major Mackenzie Drive during peak periods may increase
motorist’s potential exposure to collisions;
Limited continuous alternative east-west routes increase traffic congestion on Major Mackenzie
Drive causing closely spaced aggressive drivers, potentially influencing the high number of rear
end collisions; and
Conflicting pedestrian activities in the area may impose vehicular delays for turning vehicles at
intersections, which could also result in higher level of frustration for motorists.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 39
6 Problem and Opportunity Statement Major Mackenzie Drive is a continuous, regional arterial road which spans York Region from its
western boundary with Peel Region and its eastern boundary with Durham Region, providing a major
east-west transportation corridor connecting to north-south regional arterials and Highways 400 and
404. The historic Village of Maple is centered at the intersection of Major Mackenzie Drive and Keele
Street. As such, between McNaughton Road/Avro Road and Keele Street, the surrounding land use
context is relatively urban and composed of low to mid-rise land uses including residential, mixed-use,
commercial and institutional buildings with a number of driveway accesses located on both sides of the
street.
Major Mackenzie Drive is both a busy traffic thoroughfare and an urban village core. The following
transportation issues were identified:
Due to heavy through traffic volumes, there are limited gaps in traffic flow, making access to and
from the commercial and residential parking lots challenging.
Delays in access to driveways exacerbate already heavy traffic queues by blocking through traffic
on Major Mackenzie Drive.
The intersection of Major Mackenzie Drive and Keele Street exceeds capacity during peak
periods resulting in significant eastbound queuing which further impacts driveway accesses west
of Keele Street.
The significant number of driveway access points creates conflict points reducing the pedestrian
and cyclist experience along the corridor.
Current conditions for mixed traffic transit services results in poor transit operating conditions
during peak hours.
The lack of a pedestrian crossing along Major Mackenzie Drive between Killian Road / Netherford
Road and Keele Street (as well as the petition signed by the public)
Potential opportunities to address the aforementioned transportation issues require further study and
include:
Realignment and consolidation of commercial/residential access points.
Scheduling delivery during off-peak hours and at night.
Implementing a centre left-turn lane to provide additional space and storage for driveway access
movements.
Intersection improvements at Keele Street to reduce vehicle queuing and capacity issues.
Streetscaping enhancements to encourage walking
Installation of a traffic signal and protected pedestrian crossing between Killian Road/Netherford
Road and Keele Street.
As this study focuses on the short-term (2020) operational needs and opportunities of the corridor, a
future EA study will assess the long-term transportation needs, including capacity improvements.
7 Alternative Solutions
Alternative Solutions are functionally different ways of approaching and addressing a problem or
opportunity. The Class Environmental Assessment process requires documentation and
examination of all reasonable alternatives to address the problem; referred to as Alternative
Solutions.
Generation of Alternative Solutions 7.1
To inform the generation of alternative solutions, a review of the findings and recommendations
from the York Region Traffic Operations Assessment Memo (2015) was performed. The report is
referred to as the “York Region Memo (2015)” and is summarized in Section 7.1.1. The memo
recommendations helped inform the development of some of the Alternative Solutions identified
for this EA study, which are summarized in Section 7.1.2.
2015 York Region Memo Alternative Solutions 7.1.1
Prior to the commencement of this EA study, York Region’s Transportation Planning group
received a request to review the issues of traffic congestion and vehicle delay related to
ingress/egress at commercial and residential driveways on Major Mackenzie Drive from Killian
Road/Netherford Road to Keele Street. The findings of York Region’s work are documented in the
York Region Memo (2015) (Appendix L), which identified and assessed three alternatives and
are outlined in Table 7-1.
Table 7-1: Improvements Analyzed in the York Region Memo (2015)
Alternative Description
Alternative 1: Do Nothing
No infrastructure improvements Signal timing optimization
Alternative 2: Intersection Improvements with Auxiliary Left-turn Lanes
Addition of left-turn lanes on Major Mackenzie Drive at: o Gram Street intersection o Jackson Street intersection o 2396, 2354 and 2332 Major Mackenzie
driveways A 135 m raised centre median between Killian Road
and Gram Street Relocation of 2414 Major Mackenzie driveway to align
with Gram Street
Alternative 3: Intersection Improvements with Continuous Two-Way Centre Left-turn Lane
Addition of a continuous two-way centre left-turn lane from Gram Street to Jackson Street
Addition of a 135m raised centre median between Killian Road and Gram Street
Relocation of 2414 Major Mackenzie driveway to align with Gram Street
1 Plans and drawings depicting alternative solutions can be found in Appendix L.
The 2015 York Region Memo measured the impacts of each alternative based on the following
metrics to assess traffic operations:
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 40
Traffic Performance
The 2020 levels of service, volume-to-capacity ratios, delays and queuing were modeled for all
movements for signalized and unsignalized intersections. The traffic performance evaluation was
completed for the weekday AM and PM peak hours.
The implementation of a continuous centre left-turn lane (Alternative 3) yielded the highest benefit
to traffic performance. Non-signalized intersections experienced the best operations improvement
under Alternative 3, while traffic conditions at signalized intersections remained largely similar
between the alternatives assessed.
Travel Time Savings
Travel times for the 2020 scenarios were modeled using SimTraffic 8 simulation software and
were compared to actual 2015 travel times, which had been previously recorded through a survey
by York Region. Table 7-2 below displays the results of the travel time analysis.
Table 7-2: Travel Time Savings (York Region Traffic Operations Assessment Memo 2015)
Alternative AM travel time (s) PM travel time (s) Ranking
[best (1) to worst (4)]
2015 Actual Existing 146 (EB), 55 (WB) 142 (EB), 75 (WB) 4
Alternative 1: Do Nothing (2020)
100 (EB), 80 (WB) 80 (EB), 50 (WB) 3
Alternative 2: Intersection Improvements with Auxiliary Left-turn Lanes
110 (EB), 50 (WB) 60 (EB), 45 (WB) 2
Alternative 3: Intersection Improvements with Continuous Two-Way Centre Left-turn Lane
80 (EB), 40 (WB) 65 (EB), 40 (WB) 1
*Note: The above travel time savings are only used to illustrate the performance of the different alternative solutions.
They are the result of analysis conducted as part of the Traffic Operations Assessment, completed in 2015. For the
methodology used to derive these values, please refer to Appendix L.
The following summarizes the memo’s findings and conclusions:
Alternative 3 prevailed over Alternatives 1 and 2 from a traffic performance and travel time
improvement standpoint.
The overall benefits that would be realized by the construction of a left-turn lane on Major
Mackenzie Drive from Killian Road to Keele Street will produce moderate benefits.
Because high traffic volumes are the result of network discontinuity in the area, broader
solutions to traffic congestion are needed. Implementation of missing road links on Teston
Road and Kirby Road, as identified in the York Region Transportation Master Plan, is
recommended.
Based on the recommendations, an alternative with a continuous centre-left turn lane was carried
forward in the EA study for further consideration. As the 2015 York Region memo determined a
preference for a two-way centre left-turn lane compared to the implementation of auxiliary left-turn
lanes on Major Mackenzie Drive at Gram Street, Jackson Street and 2396, 2354 and 2332 Major
Mackenzie driveways, this alternative solution was not carried forward for further review in the EA
study.
Proposed Alternative Solutions 7.1.2
Based on the Needs Assessment and recommendations from the 2015 York Region Memo, a
variety of Alternative Solutions were developed for the study area. These alternatives range in
complexity, cost, and their ability to address the study area issues. Table 7-3 presents the
proposed alternative solutions considered to address the problems and opportunities identified for
the Major Mackenzie Drive EA study.
Table 7-3: Proposed Alternative Solutions
Alternative Description
Alternative 1: Do Nothing
Maintain existing conditions
Alternative 2: Transportation System Management
Signal coordination and timing optimization.
Alternative 3: Widen for Centre Left-Turn Lane
Provide a centre left-turn lane to help reduce delays caused by cars turning left into driveways.
Alternative 4: Intersection Improvements at Keele Street
Add an eastbound right-turn lane and extend the eastbound left-turn lane at the Keele Street intersection.
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and Keele Street
Add a new traffic signal and/or pedestrian crossing between Killian Road and Keele Street to facilitate safer pedestrian and vehicular movements along this segment of the corridor
Alternative 6: Consolidate Commercial Entrances and Driveways
Minimize the number of access points to reduce opportunities for traffic blockage while eliminating conflict points and improving pedestrian and cyclist conditions.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 41
Evaluation of Alternative Solutions 7.2
To determine the most appropriate solution for the corridor, the advantages and disadvantages of
each of the Alternative Solutions identified in Section 7.1.2 were evaluated. A list of criteria to
compare the alternatives was developed. The measure of the alternative’s success was its ability
to correct, minimize or mitigate impacts and / or meet the study goals.
Evaluation Criteria 7.2.1
The evaluation criteria used to compare the Alternative Solutions is listed in Table 7-4.
Table 7-4: Alternative Solution Evaluation Criteria
Category Criteria
Socio-Economic
Minimizes impacts to archaeology / cultural heritage resources
Accommodates existing and planned development
Complies with regional and municipal planning policies
Minimizes property acquisition
Improves quality of life
Improves air quality
Transportation Supports regional and municipal transportation planning strategies
Improves existing / future congestion
Improves road safety
Accommodates all road users, including pedestrians, cyclists and transit users
Addresses problem / opportunity statement
Natural Environment
Minimizes impacts to and enhances environmentally sensitive areas
Minimizes impacts to wildlife, vegetation, aquatic species and habitat, and
species at risk
Provides stormwater management improvements and mitigates erosion
Costs Optimizes capital costs
Optimizes operation/maintenance costs
Optimizes property acquisition costs
Traffic Analysis 7.2.2
The following describes the methodology and key findings used to assess the traffic operations of
the various alternatives.
Alternative 1: Do Nothing 7.2.2.1
The analysis and results depicting traffic conditions in 2020 if no improvements were undertaken
in the study area were prepared. The results of the “Do Nothing” analysis were used for
comparison purposes against other alternatives to identify their relevant benefits as described.
Alternative 2: Transportation System Management 7.2.2.2
While Transportation System Management, particularly traffic signal optimization, would provide a
general benefit to vehicular traffic on Major Mackenzie Drive, this alternative on its own is not
sufficient to address the issues identified in the problem statement, including safety and driveway
access concerns. As no traffic analysis was undertaken for this alternative on its own, Alternative
2 was reviewed in conjunction with others to improve operations in the study area
Alternative 3: Widen for Centre Left-Turn Lane 7.2.2.3
Travel times for the year 2020 were modeled for Major Mackenzie Drive between Keele Street
and Killian Road for the Alternative 1: “Do Nothing” and the Alternative 3: “Widen for Centre Left-
Turn Lane” scenarios using SimTraffic 8 simulation software. The results were reviewed to assess
the benefits of widening to accommodate a two-way centre left-turn lane. This methodology was
followed to facilitate comparisons with the York Region Traffic Operations Assessment Memo
(2015) results.
The results, extracted from SimTraffic reports, are illustrated in Table 7-5 and Table 7-6 the AM
and PM Peak hours.
Table 7-5: Morning Peak Hour Travel Times
Travel Direction Alternative 1
(Do Nothing) Travel Time (s)
Alternative 3 (CLTL)
Travel Time (s)
Time Savings (s)
Change (%)
AM – Eastbound 260.1 234.4 -25.7 -9.9%
AM – Westbound 71.8 69.6 -2.2 -3.1%
Source: SimTraffic Report
Table 7-6: Afternoon Peak Hour Travel Times
Travel Direction
Alternative 1
(Do Nothing)
Travel Time (s)
Alternative 3
(CLTL)
Travel Time (s)
Time
Savings (s) Change (%)
PM – Eastbound 201.2 177.1 -24.1 -12%
PM – Westbound 76.8 73.2 -3.6 -4.7%
Source: SimTraffic Report
The addition of a two-way centre left-turn lane led to a reduction in travel time for both directions
in the AM and PM peaks. The largest travel time savings occurred for vehicles travelling
eastbound during the morning peak while the largest incremental savings occurred for eastbound
travellers in the afternoon peak.
Westbound traffic also experienced shorter travel times, albeit to a lesser extent. Their time
savings ranged between 2 and 4 seconds.
Table 7-7 summarizes the time savings in 2020 with the implementation of a centre left-turn lane.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 42
Table 7-7: Travel Time Savings Results
Alternative
EA Study Travel Time (s)
EB WB
Alternative 1: Do Nothing (2020) AM 260.1 71.8
PM 201.2 76.8
Alternative 3: Widen for a centre left-turn lane
AM 234.1 69.6
PM 177.1 73.2
Travel Time Savings AM -25.7 -2.2
PM -24.1 -3.6
Total Travel Time Savings -55.9
The results show that the centre left-turn lane boasts benefits in terms of reducing delays and
total travel time by minimizing through lane blockage and improving overall capacity of Major
Mackenzie Drive within the study area. Additional benefits include safety enhancements when
making left-turns.
Alternative 4: Intersection Improvements at Keele Street 7.2.2.4
The 2020 levels of service, volume-to-capacity ratios and queuing were modeled to examine the
benefits of implementing localized intersection improvements such as eastbound-right and
eastbound-left turn lanes. As the critical section of the study corridor is located between Killian
Road/Netherford Road and Keele Street, traffic performance improvements for eastbound
movements at Keele Street can provide an accurate depiction of the outcomes anticipated. As
such the impacts of Alternative 4: “Intersection Improvements at Keele Street” were measured
only for the Keele Street eastbound movements and compared to the Alternative 1: “Do Nothing”.
Table 7-8 and Table 7-9 present the findings of the Synchro analysis for the AM and PM peak
hours.
Table 7-8: AM Peak Hour Traffic Conditions at the Keele Street intersection
AM Peak Movement V/C LOS Synchro 95th Queue (m)
Alternative 1: Do Nothing (2020)
EBL 0.52 C 17.9
EBT 1.07 F 292
EBR 1.07 F 292
Alternative 4: 60m EBL and 60m EBR Turning Lanes
EBL 0.52 C 17.9
EBT 0.94 D 237.1
EBR 0.24 A 21.4
Source: Synchro Report
Table 7-9: PM Peak Hour Traffic Conditions at the Keele Street intersection
PM Peak Movement V/C LOS Synchro 95th Queue (m)
Alternative 1: Do Nothing (2020)
EBL 0.95 F 57
EBT 1.04 E 289.9
EBR 1.04 E 289.9
Alternative 4: 60m EBL and 60m EBR Turning Lanes
EBL 0.92 F 57
EBT 0.9 D 218.3
EBR 0.25 A 19.9
Source: Synchro Report
During both AM and PM peaks, the eastbound-through (EBT) and eastbound-right (EBR)
movements experience improvements in their LOS and v/c ratio when compared to the Do
Nothing alternative. However, the eastbound-left (EBL) movement remains constant during the
morning and afternoon. The queues decrease for the EBT and EBR but remain the same for the
EBL movement.
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and 7.2.2.5Keele Street
The Ontario Traffic Manual (OTM 2007 – Book 12) was used as a basis to evaluate the warrant
for a traffic signal and/or pedestrian crossing between Killian Road/Netherford Road and Keele
Street (Alternative 5). Because it is unsignalized and located equidistant from adjacent crossings,
the Gram Street intersection was a good candidate from which to begin the assessment of
potential midblock crossings.
According to the OTM Book 12, for a pedestrian crosswalk (PXO) to be warranted, the total 8-
hour pedestrian volume crossing the main road at an intersection or midblock location must
exceed 100 “equivalent adult pedestrians” during the highest pedestrian traffic hours. In addition,
no signalized intersection must be located within 200m of the crossing evaluated.
The 8-hour pedestrian volume at the intersection of Gram Street and Major Mackenzie Drive is 42,
which is well below the OTM threshold. However, the signalized intersection at Killian Road is
approximately 230m away, which surpasses the acceptable 200m proximity limit set by the
Manual.
To investigate the potential for a traffic signal, volume warrants and collision experience were also
examined. Exhibit 7-1 summarizes the results of the signal and PXO warrant analysis.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 43
Exhibit 7-1: Signal and PXO Warrant Results
The volume warrants, collision experience and pedestrian volumes, as well as proximity to the
Killian Road/Netherford Road intersection, indicate that neither a traffic signal nor pedestrian
crosswalk is warranted at the Gram Street and Major Mackenzie Drive intersection. Although not
necessarily warranted, Alternative 5 is recommended for further consideration in light of public
support for a midblock pedestrian crossing.
Alternative 6: Consolidate Commercial Entrances and Driveways 7.2.2.6
Traffic analyses were not performed for this alternative. A qualitative assessment based on the
evaluation criteria was performed instead, and documented in Section 7.3.
Evaluation Matrix 7.3
Based on the evaluation criteria identified in Section 7.2.1 and the findings of the traffic analysis
presented in Section 7.2.2, an evaluation was conducted to compare the six Alternative Solutions
and determine the recommended alternative. The evaluation is provided in Table 7-10.
From a traffic perspective, based on the qualitative and quantitative analysis presented,
Alternative 1: Do Nothing is least preferred, while Alternative 3: Widen for Centre Left-turn Lane
and Alternative 4: Intersection Improvements at Keele Street are preferred.
A combination of solutions is recommended to tackle the operational concerns at Major
Mackenzie Drive within the study limits. In addition to the implementation of Alternatives 3 and 4,
it is proposed to undertake transportation system management strategies (Alternative 2) to
optimize signal timing and improve traffic flow in the study area. The addition of a new traffic
signal or pedestrian crossing (Alternative 5) is carried forward based on resident request for an
additional protected crossing and as a result of further discussion with York Region and feedback
from affected stakeholders and the community.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 44
Table 7-10: Evaluation of Alternative Solutions Matrix
Evaluation Criteria Alternative 1: Do Nothing
Alternative 2: Transportation System Management
Alternative 3: Widen for Centre Left-Turn Lane
Alternative 4: Intersection Improvements at Keele Street
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and Keele Street
Alternative 6: Consolidate Commercial Entrances and Driveways
Option Description Maintain existing conditions. Signal coordination and timing optimization.
Provide a centre left-turn lane to help reduce delays caused by cars turning left into driveways.
Add an eastbound right-turn lane and extend the eastbound left-turn lane at the Keele Street intersection.
Add a new traffic signal and/or pedestrian crossing between Killian Road and Keele Street to facilitate safer pedestrian and vehicular movements along this segment of the corridor.
Minimize the number of access points to reduce opportunities for traffic blockage while eliminating conflict points and improving pedestrian conditions.
Socio-Economic
Impacts to Archaeology / cultural heritage resources
No Impacts No impacts Potential impacts to
archaeological or cultural heritage resources.
Potential impacts to archaeological or cultural heritage resources.
No impacts Potential impacts to
archaeological or cultural heritage resources.
Accommodates Existing and Planned Development
Does not accommodate existing and planned development, as it does not improve roadway operations.
Accommodates existing and planned development by providing a general overall benefit to vehicles along the corridor.
Supports existing and planned development by improving traffic operations.
Supports existing and planned development by improving traffic operations.
Accommodates existing and planned development as it increases pedestrian access and safety.
Supports existing and planned development, by minimizing driveway conflict points (vehicle and pedestrian).
Compliance with Region’s Planning Policies
Does not oppose Region’s Planning Policies for the EA horizon year
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year.
Minimizes property acquisition
No property acquisition required
No property acquisition required
Potential for property acquisition
Potential for property acquisition
Potential for property acquisition required
Potential for property acquisition
Improves quality of life
Does not improve driving operations on Major Mackenzie Dr
Poor active transportation facilities
Congestion, delays, and air quality will continue to degrade , resulting in deteriorated quality of life
Potential improvement to the driving experience on Major Mackenzie Dr
Potential improvement to the driving experience on Major Mackenzie Dr
Potential improvement to air quality due to fewer idling vehicles, resulting in increased quality of life
Opportunity for landscape / streetscape improvements
Potential improvement to the driving experience at the intersection and adjacent segments of Major Mackenzie Dr
Potential opportunity to improve active transportation facilities
Potential improvement to air quality due to fewer idling vehicles, resulting in increased quality of life
Potential for impact to the driving experience on Major Mackenzie Dr
Improved pedestrian experience and safety
Increased access to existing and planned developments
Moderate improvement to the driving experience on Major Mackenzie Dr
Minimizing driveway conflict points (vehicle and pedestrian).
Improves air quality Does not improve air quality
Minimal potential improvement to air quality, due to optimization of vehicular flows
Potential for improvement in air quality due to fewer vehicles idling
Potential for improvement in air quality due to fewer vehicles idling
Does not improve air quality Does not improve air quality
Summary Not Preferred Neutral Neutral Neutral Preferred Not Preferred
Transportation/Technical
Transportation Master Plan (TMP)
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year
Does not oppose Region’s Planning Policies for the EA horizon year.
Does not oppose Region’s Planning Policies for the EA horizon year
Does not oppose Region’s Planning Policies for the EA horizon year
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 45
Evaluation Criteria Alternative 1: Do Nothing
Alternative 2: Transportation System Management
Alternative 3: Widen for Centre Left-Turn Lane
Alternative 4: Intersection Improvements at Keele Street
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and Keele Street
Alternative 6: Consolidate Commercial Entrances and Driveways
Option Description Maintain existing conditions. Signal coordination and timing optimization.
Provide a centre left-turn lane to help reduce delays caused by cars turning left into driveways.
Add an eastbound right-turn lane and extend the eastbound left-turn lane at the Keele Street intersection.
Add a new traffic signal and/or pedestrian crossing between Killian Road and Keele Street to facilitate safer pedestrian and vehicular movements along this segment of the corridor.
Minimize the number of access points to reduce opportunities for traffic blockage while eliminating conflict points and improving pedestrian conditions.
Improves Existing / Future Congestion
Does not improve congestion Anticipated growth, though
minimal, will worsen existing conditions
Moderate improvement to existing congestion
Improves operations by preventing turning vehicles from blocking through lanes
Improves operations by extending east-bound left-turn lane and addition of eastbound right-turn lane
Slight negative effect on traffic congestion
Minimal to no improvement on congestion
Improves Road Safety Does not improve road safety Minimal to no impact on
road safety Improves road safety Improves road safety
Improves road safety for all modes
Improvement in road safety to pedestrians by reducing the number of conflict points with vehicles
Accommodates All Road Users, Including Pedestrians, Cyclists, and Transit Users
Does not accommodate all road users
Does not accommodate active transportation users
Potential opportunity to accommodate active transportation users, where feasible
Does not accommodate active transportation users
Improved conditions for vehicles exiting/accessing Gram Street and pedestrian access to north side plazas
Similar to existing conditions, road users are accommodated.
Addresses Problem / Opportunity Statement
Does not address problem and opportunity statement
Does not address problem and opportunity statement on its own.
Addresses problem and opportunity statement
Addresses problem and opportunity statement
Addresses problem and opportunity statement
Addresses problem and opportunity statement
Summary Not Preferred Neutral Preferred Preferred Neutral Neutral
Natural Environment
Impacts to Designated Natural Areas (PSWs, ESAs & ANSIs)
No impacts No impacts No impacts No impacts No impacts No impacts
Impacts to Wildlife, Vegetation, Aquatic Species and Habitat, and Species at Risk
No impacts No impacts Potential minor impact to
wildlife No impacts No impacts No impact
Improves Drainage / Erosion No improvement to drainage /
erosion No improvement to
drainage / erosion
Potential impacts to drainage / erosion
Potential opportunity for improvements to storm drainage system including repair/ replacement of West Don River culvert.
Potential opportunity for improvements to storm drainage system.
No improvements to drainage / erosion
No improvements to drainage / erosion
Summary Neutral Neutral Neutral Neutral Neutral Neutral
Costs
Capital Costs No Capital costs One-time capital cost High capital costs from
infrastructure improvements to Major Mackenzie
High capital costs from infrastructure improvements to Major Mackenzie
Moderate capital costs Moderate capital costs
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 46
Evaluation Criteria Alternative 1: Do Nothing
Alternative 2: Transportation System Management
Alternative 3: Widen for Centre Left-Turn Lane
Alternative 4: Intersection Improvements at Keele Street
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and Keele Street
Alternative 6: Consolidate Commercial Entrances and Driveways
Option Description Maintain existing conditions. Signal coordination and timing optimization.
Provide a centre left-turn lane to help reduce delays caused by cars turning left into driveways.
Add an eastbound right-turn lane and extend the eastbound left-turn lane at the Keele Street intersection.
Add a new traffic signal and/or pedestrian crossing between Killian Road and Keele Street to facilitate safer pedestrian and vehicular movements along this segment of the corridor.
Minimize the number of access points to reduce opportunities for traffic blockage while eliminating conflict points and improving pedestrian conditions.
Operation / Maintenance Costs
Minimal operation/ maintenance costs
Minimal operation/ maintenance costs
Additional operation/ maintenance costs
Additional operation/ maintenance costs
Additional operation/ maintenance costs
Potential reduction in operation/ maintenance costs
Property acquisition costs No property acquisition costs No property acquisition
costs Potential for property
acquisition costs Potential for property
acquisitions costs Potential for property acquisition
costs No property acquisition costs
Summary Preferred Preferred Not Preferred Not Preferred Neutral Neutral
Overall summary
Comments
Does not impact or improve the socioeconomic or natural environment
Access to commercial properties will continue to suffer and result in potential loss of business
Does not improve transportation operations
Does not address problem and opportunity statement
Lowest cost
Does not impact or improve the socioeconomic or natural environments
May moderately improve transportation operations; targets drivers
Does not address problem and opportunity statement
Low cost
Impact to socio-economic environment (potential property acquisition) but provides opportunity for landscape / streetscape improvements
Potential improvement to air quality due to fewer idling vehicles
Most likely to yield best transportation benefits
Addresses problem and opportunity statement
Minor impact to natural environment
Highest cost Public support expressed Potential opportunity to
repair/replace culvert at West Don River
Requires removal of on-street parking
Impact to socio-economic environment (potential property acquisition)
Limited opportunity for landscape / streetscape improvements
Potential improvement to air quality due to fewer idling vehicles
Improvements to transportation operations
Addresses problem and opportunity statement
High cost Requires removal of on-street
parking near intersection
Improvement to the socio-economic environment (quality of life, improved access)
May moderately improve transportation operations and safety for vehicles and pedestrians
Addresses problem and opportunity statement
Moderate cost Public support for new crossing
expressed
Limited opportunities for driveway consolidation
Difficult to obtain property owner consensus
May improve transportation operations and safety by reducing the number of conflict point for vehicles and pedestrian
Moderate to high cost
Recommendation Not Preferred Preferred Preferred Preferred Preferred Not Preferred
Carry forward Alternatives 2,3,4 and 5
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 47
Preferred Solution 7.4
Based on the evaluation presented in the previous section, the preferred solution consists of the
following:
Alternative 2: Transportation System Management
Alternative 3: Widening for Centre Left-Turn Lane
Alternative 4: Intersection Improvements at Keele Street (i.e. extended eastbound left-turn lane
and new eastbound right-turn lane)
Alternative 5: New Traffic Signal / Pedestrian Crossing between Killian Road and Keele Street.
Discussions with the City of Vaughan resulted in the consideration of active transportation
improvements for the study area. The preferred solution therefore also aimed to accommodate
cyclists and pedestrians to the extent possible and was reviewed as part of the alternative design
evaluation process.
8 Alternative Designs for the Preferred Solution
Recommendations carried forward from Phase 2 – Alternative Solutions informed the development
of the Phase 3 - Alternative Designs.
While Section 7 confirmed a combination of solutions to address the problem and opportunity, this
section examines alternative methods for implementing the preferred solution. Section 8 documents
the process used in developing, assessing and evaluating alternative designs to select a preferred
design for the study corridor.
Generation of Alternative Design Concepts 8.1
Constraints 8.1.1
Existing conditions and constraints along the Study Area were assessed in the development of
alternative design concepts. The main constraints influencing the alternative designs are:
a. Available Right-of-Way (ROW)
b. West Don River Crossing
c. Village of Maple Heritage Conservation District Plan (VM-HCD)
d. Residential, Commercial, Low-Rise Mixed Land Use
e. Utilities
The study area context and constraints are presented visually in Exhibit 8-1 and Exhibit 8-2.
Exhibit 8-1: Constraints between McNaughton Road/Avro Road and Killian Road/Netherford Road
Exhibit 8-2: Constraints between Killian Road/Netherford Road and Keele Street
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 48
Corridor Segmentation 8.1.2
To better address the specific needs, constraints and challenges within the study area, the study
corridor was divided into three segments, East, Central and West, as shown in Exhibit 8-3.
Exhibit 8-3: Corridor Segmentation
For the purposes of the evaluation of alternative designs, the screening process was organized
moving from East to West along Major Mackenzie Drive. This was done because considerations for
the more constrained East segment helped define the design possibilities while guiding and informing
a continuous and sensible recommendation for the corridor.
The constraints pertaining to each segment are discussed along with their context to the development
of the alternative design options.
East Segment – Keele Street to Jackson Street
The existing available ROW along the East segment between Keele Street and Jackson Street is
approximately 28m.
In this segment, building faces directly abut property lines. Hydro poles are located on the south side
of the road and light poles are found on both sides. There is limited available right-of-way surrounding
the Keele Street intersection (see Exhibit 8-4). These characteristics pose a challenge in developing
cross-section alternatives that include all desired design features as opportunities for property
acquisition are limited.
The East segment also falls within the boundaries of the Village of Maple Heritage Conservation
District (VM-HCD) Plan which acknowledges the greater social and economic role of this segment
and aims to nurture a pedestrian-friendly commercial destination. Specifically the intersection of
Keele Street and Major Mackenzie Drive is located in the commercial core of the VM-HCD.
Exhibit 8-4: Major Mackenzie Drive looking east at Keele Street
Central Segment – Jackson Street to Gram Street
The existing available ROW along the Central segment between Jackson Street and Gram Street
varies between 25m and 28m. The boulevard is wider to the north and is more limited to the south
due to adjacent residences, as illustrated in Exhibit 8-5.
Exhibit 8-5: Looking east from 2414 Major Mackenzie Drive Plaza
Utility poles are located on both sides of Major Mackenzie Drive in this section. However, the poles on
the north side are more dispersed and are inset from the roadway, while those on the south side abut
the curb and are more abundant. These considerations are important when investigating the viability
of alternative cross-section designs to minimize potential relocation.
As part of the Heritage Conservation District, this segment is subject to urban design guidelines to
help retain the Village of Maple’s character, feel and identity. The plan encourages grassed
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 49
boulevards and plantings and supports all aspects of road design that improve the pedestrian
amenity.
West Segment – Gram Street to McNaughton Road/Avro Road
The existing available ROW in the West segment between Gram Street and McNaughton Road/Avro
Road is approximately 36m.
For the most part, private properties do not front onto Major Mackenzie Drive within this section with
the exception of Apple Tree Montessori School, Mac’s Gas Station, St. David’s Church and the
commercial plaza located at the south-west corner of Killian Road/Netherford Road and Major
Mackenzie Drive. A raised median separates eastbound and westbound traffic from Killian
Road/Netherford Road west to the Saint David’s Church Driveway.
Hydro poles are located primarily on the south side of Major Mackenzie Drive in this section while
light standards line the north side, as shown in Exhibit 8-6. Furthermore, the West Don River
tributary is present within this segment and crosses under roadway between St. David’s Church and
the Mac’s Gas Station.
There is greater potential for accommodating roadway and pedestrian realm improvements in
segment due to the wider right-of-way available.
The limits of the West segment fall outside the boundaries of the Heritage Conservation District Plan.
Exhibit 8-6: Looking east along Major Mackenzie Drive from McNaughton Road/Avro Road
Alternative Design Cross-Sections 8.2
The Class EA process requires the documentation and examination of all reasonable options in
Phase 3 of the study. This section details the development of the long-list of alternative cross-section
designs, the short-list screening process (i.e. design workshop), the cross-section element design
criteria and the alternative designs short-listed for detailed evaluation.
Summary of Cross-Section Long-list 8.2.1
The project team considered the following cross-section alternative designs for initial discussions. For
the purposes of the evaluation of alternative designs, the screening process was organized moving
from the East (most constrained) to the West (least constrained) along Major Mackenzie Drive so as
to help the selection process. The designs were prepared by segment based on 2016 York Region
Design Guidelines (YR-DGL, December 2016 version 1.2):
1 East Segment – Major Mackenzie Drive between Keele Street and Jackson Street
A. Implement an eastbound right-turn lane and shift the centerline alignment to the north, with
the remaining ROW utilized for public space.
Given the existing property/building constraints, this is the only alternative design that is
feasible. Widening the cross-section further to accommodate separated active
transportation facilities (cycling) is not possible without impacting the adjacent buildings.
Similarly widening about the centerline or shifting the alignment to the south would also
impact the adjacent buildings.
2 Central Segment – Major Mackenzie Drive between Jackson Street and Gram Street
A. Implement a CLTL with sidewalks on both the north and south sides
B. Implement a CLTL with multi-use path (MUP) on both or either side
C. Implement a Centre Left Turn Lane (CLTL) with separated off-road cycling facilities on both
the north and south sides
3 West Segment – Major Mackenzie Drive between Gram Street and McNaughton Road / Avro
Road
A. Implement a CLTL with sidewalks on both the north and south sides
B. Implement a CLTL with MUP on both or either side
C. Implement a CLTL with separated off-road cycling facilities on both the north and south sides
Only separated active transportation facilities were considered in the design development. Separated
facilities are characterized by a dedicated pathway in the boulevard space and commonly include off-
road bike lanes, cycle tracks and multi-use paths. These off-road facilities are preferred over on-road
ones, such as conventional bike lanes and lanes with marked buffers for several reasons, namely
because:
Separated facilities improve cycling safety and level of service by increasing the physical separation between motor vehicles and active modes.
Separated facilities avoid the potential for conflicts with curbside transit stops. The study area’s characteristics, including its high traffic volumes (Annual Average Daily Traffic is
greater than 15,000 vehicles) and moderate operating speed (greater than 50 km/h) make it more suitable for separated facilities rather than shared uses.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 50
Similarly, options for two-way off-road cycle track were dismissed to reduce conflict points at
intersections as pedestrians and turning drivers may not expect contra-flow bicycle traffic. Two-way
off-road cycle tracks also limit access to the other side of the street (and associated destinations) and
may require additional signal equipment at intersections.
Design Team Workshop 8.2.2
A design workshop was held with York Region internal stakeholders and project team staff on
January 8, 2018 to discuss the long-list of alternative designs and screen out options that are not
feasible. The workshop was attended by several York Region staff, including representatives from
Active Transportation, Streetscape, Corridor Control and YRT/VIVA departments.
The main objective of the workshop was to confirm which active transportation facilities are viable for
inclusion in the design and to confirm acceptable cross-section elements and associated widths (e.g.
travel lanes, sidewalk, multi-use path etc.). Design Criteria for the cross-section elements is
presented in Section 8.2.3 and summarizes the workshop recommendations.
As this EA was conducted to address short-term improvements, it was confirmed in the meeting that
the preferred design should avoid or limit property acquisition to the greatest extent possible.
Obtaining the full designated official plan ROW was not within the scope of this EA study as a future
EA study will determine a long-term solution for the corridor; including active transportation, transit
and road capacity needs.
The results of the design team workshop were reviewed and discussed with the City of Vaughan at a
meeting held on March 22, 2018.
Screening 8.2.2.1
The screening process followed for the long-list of alternative cross-section designs can be
synthesized into three main steps. The proposed alternatives must, first and foremost, fit within the
existing ROW as no property is intended to be acquired. Furthermore, to ensure consistency and
continuity of the proposed facilities throughout the study area, preference should be given to
improvements that can be accommodated in adjacent segment ROWs. Finally, the screening process
should prioritize the designs that strategically minimize and avoid impacts to surroundings based on
widening north, south or about the centerline. The preliminary screening process is shown in Exhibit
8-7.
Exhibit 8-7: Screening process and rationale established through the Design Team Workshop
With this process in mind, the long-list of cross-section alternative designs was screened and a short-
list developed. The screening process started by assessing the designs in the east then moved
westward. As the eastern section of the study area encompassed more challenges and constraints,
these considerations helped guide the selection of designs for the subsequent westerly segments.
Details supporting the recommendations from the screening process are outlined as follows:
1 East Segment - Major Mackenzie Drive between Keele Street and Jackson Street
A. Implement an eastbound right-turn lane using standard lane widths and shift the centerline
alignment to the north, with the remaining ROW utilized for the pedestrian boulevard.
This option was carried forward for review following discussion at the Design Workshop. This
design was short-listed for further evaluation.
Per York Region direction at the workshop, reduced lane widths were to be considered for this
alternative design (Alternative 1B).
B. Implement an eastbound right-turn lane using reduced lane widths and shift the centerline
alignment to the north, with the remaining ROW utilized for the pedestrian boulevard. This
design was short-listed for further evaluation.
In terms of alignment options, widening to the south and about the centreline were eliminated
from consideration for alternative designs 1A and 1B to avoid property impacts and minimize
i. Does the alternative fit within the existing ROW?
YES NO
ii. Consider modifications to the
alternative to reduce the
proposed ROW.
(E.g.: AT facility on one side of
the street, lane width reductions)
iii. Consider the continuity of design.
Preference is attributed to facilities that can
be accommodated in adjacent segments.
Screen out alternatives that do not provide
this continuity.
iv. Prioritize widening designs about alignments that
minimize impact on surrounding constraints and recommend
widening scenario to the north, south or centerline.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 51
relocating existing utilities adjacent to the south curb. Widening to the north was
recommended.
2 Central Segment - Major Mackenzie Drive between Jackson Street and Gram Street
A. Implement a CLTL with sidewalks on both the north and south sides.
This option was short-listed for further evaluation as it provides pedestrian connections
within the available right-of-way. Based on the recommendations from the workshop, reduced
lane widths will be used for this alternative design.
B. Implement a CLTL with a Multi-Use Path on both or either side
The option with MUP on both sides of the street was eliminated from consideration based on
property requirements. To reduce property impacts a modification to the design with a MUP
on the north side and a sidewalk on south side was considered. Although this modified option
does not have continuity with the adjacent segment to the east, transition to the active
transportation facility is accommodated. The modified option was short-listed for further
evaluation. Based on the recommendations from the workshop, reduced lane widths will be
used for this alternative design.
C. Implement a CLTL with separated off-road cycling facilities on both the north and south sides.
Separated off-road cycling facilities on both sides were eliminated from consideration as this
alternative exceeds the available ROW and would not have continuity with the adjacent
segment to the east. Reduction in cross-section element widths was examined but still
resulted in property impacts while only providing minimal separation distances to vehicular
and pedestrian traffic, which is not desired for high traffic areas. This option was not carried
forward.
In terms of alignment options, widening to the south and about the centreline were eliminated
from consideration to avoid property impacts and minimize relocating existing utilities adjacent to
the south curb. Widening to the north was recommended.
3 West Segment - Major Mackenzie Drive between Gram Street and McNaughton Road / Avro
Road
A. Implement a CLTL with sidewalks on both the north and south sides.
This option was short-listed for further evaluation as it provides pedestrian
connections within the available right-of-way. Based on the recommendations from the
workshop, reduced lane widths were preferred generally. No shifting of the centerline was
recommended throughout this section to minimize property/utility impacts and match the
existing 5-lane cross-section between Killian Road/Netherford Road and St. David’s Church.
B. Implement a CLTL with MUP on both or either side.
In order to maintain continuity to the central segment, this option is carried forward with the
same modifications recommended in the central segment. Therefore, an option with a MUP
on the north side and a sidewalk on south was carried forward for evaluation. Based on
the recommendations from the workshop, reduced lane widths will be used for this alternative
design. No shifting of the centerline was recommended throughout this section to minimize
property/utility impacts and match the existing 5-lane cross-section between Killian
Road/Netherford Road and St. David’s Church
C. Implement a CLTL with separated off-road cycling facilities on both the north and south sides.
Although there is sufficient ROW to accommodate this option, separate, off-road cycling
facilities on both sides were eliminated from consideration due to the lack of continuity and
connectivity with the central and east segments of the corridor. In addition, cycling facilities do
not exist west of McNaughton Road/Avro Road. This option was not carried forward.
According to these considerations, the long list presented in Section 8.2.1 was refined. The
design options carried forward for detailed evaluation are presented in Section 8.2.5.
Design Criteria 8.2.3
The standard and recommended element widths were reviewed and confirmed during the workshop
with York Region and are presented in Table 8-1. Standard widths are based on York Region/TAC
guidelines. Due to ROW constraints, standard widths could not be applied and recommended widths
were therefore based on discussions and direction received during the design workshop.
Table 8-1: Design Criteria and Assumptions
Element Standard
Width (m)
Recommended
Width (m)
Source / Notes
Through Lane 3.5m 3.3m YR-RDGL1 Pg. 46 DS-104 Curb Lane 3.75m 3.5m – 3.75m
Right-Turn Lane (RTL) 3.5m 3.5m
Left-Turn Lane (LTL) 3.5m 3.0m – 3.3m
Median Island
(adjacent to left-turn
lane)
1.4-1.7m 1.4m (monolithic) YR-RDGL1
Pg. 46
E-6.03/E-6.05
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 52
Element Standard
Width (m)
Recommended
Width (m)
Source / Notes
Two-way Centre Left
Turn Lane (TWCLTL)
4.0m- 5.0m 4.40m
(4.0m min.)
TAC 2017
Chapter 8
Pg. 29
Sect. 8.6.2
Sidewalk 1.5m (min.) - 3.0m
(max.)
1.5m (min.) YR-RDGL1 Pg.
57
Multi-Use Path 2.4m (min.) - 3.0m
(max.)
2.4m (min.) - 3.0m
(max.)
YR-RDGL1 Pg.
57
Boulevard 3.5m – 5.0m
Includes sidewalk, transit
facilities etc.
Varies YR-RDGL1 Pg.47
1 York Region Design Guidelines (December 2016 version 1.20)
Design Cross-Sections Short-list 8.2.4
This section summarizes the short-listed alternative designs resulting from the workshop and
preliminary screening process. Cross-sections are provided to illustrate each alternative.
West Segment – McNaughton Road / Avro Road to Gram Street 8.2.4.1
The short-listed designs to be carried forward for detailed evaluation for the West Segment are:
Alternative Design 3A (Reduced lane widths + CLTL + Sidewalks)
Reconfigure/repurpose the existing roadway to add a centre left-turn lane from east of the West
Don River tributary to Gram Street while maintaining the sidewalks in their current location. This
option attempts to retain existing edges of pavement to the extent possible while reconfiguring the
roadway. Where required, widening will occur about the existing centerline utilizing reduced lane
widths. Alternative design 3A is illustrated in Exhibit 8-8.
Alternative Design 3B (Reduced lane widths + CLTL + MUP on north side)
Reconfigure/repurpose the existing roadway to add a centre left-turn lane from east of the West
Don River tributary to Gram Street. Install a MUP on the north side and maintain the existing
sidewalk on the south side. This option attempts to retain existing pavement edges to the extent
possible while reconfiguring the roadway. Where required, widening will occur about the existing
centerline utilizing reduced lane widths. Design 3B is displayed in Exhibit 8-9.
Central Segment – Gram Street to Jackson Street 8.2.4.2
The short-listed designs to be carried forward for detailed evaluation for the Central Segment are:
Alternative Design 2A (Reduced lane widths + CLTL + Sidewalks)
Maintain the south edge of pavement and shift the centerline alignment north to implement a two-
way centre left-turn lane using reduced lane widths. Re-instate sidewalk on the north side and
maintain existing sidewalk on the south. Design 2A is illustrated in Exhibit 8-10.
Alternative Design 2B (Reduced lane widths + CLTL + MUP on north side)
Maintain the south edge of pavement and shift the centerline alignment north to implement a two-
way centre left-turn lane using reduced lane widths. Install MUP on the north side and maintain
the existing sidewalk on the south side. Design 2B is illustrated in Exhibit 8-11.
East Segment – Keele Street to Jackson Street 8.2.4.3
The short-listed designs to be carried forward for detailed evaluation for the East Segment are:
Alternative Design 1A (Standard lane widths + RTL + Sidewalks)
Implement an eastbound right-turn lane while shifting the centerline north and using standard
element widths, with the remaining ROW utilized for public space. Alternative Design 1A is shown
in Exhibit 8-12
Alternative Design 1B (Reduced lane widths + RTL + Sidewalks)
Implement an eastbound right-turn lane while shifting the centerline north and using reduced lane
widths, with the remaining ROW utilized for public space. Design Alternative 1B is shown in Exhibit
8-13.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 53
Exhibit 8-8: Alternative Design 3A (Reduced lane widths + CLTL + Sidewalks)
Exhibit 8-9: Alternative Design 3B (Reduced lane widths + CLTL + MUP on north side)
TWO WAY CLTL
TWO WAY
CLTL
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 54
Exhibit 8-10: Alternative Design 2A (Reduced lane widths + CLTL + Sidewalks)
Exhibit 8-11: Alternative Design 2B (Reduced lane widths + CLTL + MUP on north side)
CLTL
CLTL
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 55
Exhibit 8-12: Alternative Design 1A (Standard lane widths + RTL + Sidewalks)
Exhibit 8-13: Alternative Design 1B (Reduced lane widths + RTL + Sidewalks)
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 56
Evaluation of Alternative Designs 8.2.5
Evaluation Criteria 8.2.5.1
The evaluation of cross-section alternatives included the formulation of evaluation criteria and a
method to evaluate these criteria. The evaluation criteria were developed based on transportation
considerations as well as impacts to the natural, cultural, and social environments and
considerations pertaining to costs and infrastructure design. The assessment of alternative designs
was conducted through the lens of the study’s ultimate objectives to:
Improve the existing operational issues along Major Mackenzie Drive for the short-term;
Limit property impacts and avoid the need to obtain additional right-of-way (where feasible); and
Improve streetscaping and enhance the active transportation experience where feasible,
depending on the extent of impacts to accommodate these.
The alternative cross-section alternatives identified were evaluated based on the criteria listed in
Table 8-2 below.
Table 8-2: Evaluation Criteria for Alternative Designs
Category Criteria
Transportation Service
Improves Congestion and Delays
Maintains a Cyclist-Friendly Environment
Maintains a Pedestrian-Friendly Environment
Improves Safety for All Travel Modes
Maintains Mode Choice
Maintains Public Transit Service
Natural Environment
Minimizes Impacts to Environmentally Sensitive Areas
Minimizes Impacts to Wildlife, Vegetation, Aquatic Species and Habitat, and Species at Risk
Provides Stormwater Management Improvements and Mitigates Erosion
Improves Air Quality
Social Environment
Minimizes Impacts on Adjacent Areas
Improves Access to Adjacent Areas
Mitigates Traffic on Local Streets
Minimizes Traffic Noise
Preserves Archaeological and Cultural Heritage Features
Improves Visual Aesthetics
Improves Community Character and Quality of Life
Infrastructure Design
Minimizes above ground Utility Relocation
Minimizes Constructability Complexity
Minimizes Disruption due to Construction
Economic Environment and Cost Effectiveness
Optimizes Capital Costs
Optimizes Operation/Maintenance Costs
Optimizes Property Acquisition Costs
Evaluation 8.2.5.2
The cross-section alternative designs were evaluated using the established criteria listed in the
Section 8.2.5. Each criterion presents important considerations with respect to potential impacts,
and was considered with equal relevance in choosing a preferred cross-section design for each
segment.
The evaluations of the cross-section alternative designs for Major Mackenzie Drive are presented in
Table 8-3, Table 8-4 and Table 8-5 and by segment.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 57
West Segment – Gram Street to McNaughton Road/Avro Road
Table 8-3: Evaluation of Alternative Cross-sections (West Segment)
Evaluation Criteria
West Segment - Major Mackenzie Drive between Gram Street and McNaughton Road/Avro Road
Alternative Design 3A Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides.
Alternative Design 3B Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and an enhanced sidewalk on the south.
Transportation Service
Improves Congestion and Delays
The CLTL lane will facilitate ingress and egress to St. David’s Church, Apple Tree Montessori School. No significant change is anticipated for the commercial plaza as access will remain similar to the existing condition.
The CLTL lane will facilitate ingress and egress to St. David’s Church, Apple Tree Montessori School. No significant change is anticipated for the commercial plaza as access will remain similar to the existing condition.
Creates a Cyclist-Friendly Environment
Cyclists are not accommodated in dedicated facilities and have to share the road with vehicles and sidewalks with pedestrians.
Cyclists are accommodated through the MUP provided on the north side of the street under this design alternative.
Creates a Pedestrian-Friendly Environment
Pedestrians are accommodated on both sides of the street. Pedestrians are accommodated on both sides of the street.
Improves Safety for All Travel Modes
There is the potential for cyclist – vehicle conflicts due to lack of dedicated cycling facilities.
Cyclist – pedestrian conflict is also possible on both north and south sides if cyclists choose to ride on the sidewalk.
The potential for cyclist – vehicle conflict is drastically reduced through the provision of a MUP.
Though there is the potential of cyclist – pedestrian conflict on the MUP, it is to a much lesser extent than in Alternative Design 3A.
Improves Mode Choice May encourage driving or taking transit due to improvements to traffic flow.
Does not improve mode choice.
May encourage driving or taking transit due to improvements to traffic flow.
Provision of cycling facilities is known to increase the cycling mode share.
Continuous AT facilities provide first/last mile connections to transit.
Improves Public Transit Service
Improved traffic flow may provide benefits to planned transit operations. Improved traffic flow may provide benefits to planned transit operations.
Summary Less Preferred Preferred
Natural Environment
Minimizes Impacts to and Enhances Environmentally Sensitive Areas
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts to the West Don River tributary and surrounding wetland are anticipated to be the same for both Alternative Design 3A and 3B.
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts to the West Don River tributary and surrounding wetland are anticipated to be the same for both Alternative Design 3A and 3B
Minimizes Impacts to Wildlife, Vegetation, Aquatic Species and Habitat, and Species at Risk
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts on wildlife, vegetation, aquatic species and habitat in this segment are anticipated to be the same for both Alternative Design 3A and 3B.
No Species at Risk have been identified.
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts on wildlife, vegetation, aquatic species and habitat in this segment are anticipated to be the same for both Alternative Design 3A and 3B.
No Species at Risk have been identified.
Provides Stormwater Management Improvements and Mitigates Erosion
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts to stormwater management are anticipated to be the same for both Alternative Design 3A and 3B.
This alternative design only reconfigures the existing road pavement and does not have any widening associated. However, the culvert at the West Don River will be replaced under both Alternative Design 3A and 3B.
Impacts to stormwater management are anticipated to be the same for both Alternative Design 3A and 3B.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 58
Evaluation Criteria
West Segment - Major Mackenzie Drive between Gram Street and McNaughton Road/Avro Road
Alternative Design 3A Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides.
Alternative Design 3B Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and an enhanced sidewalk on the south.
Improve Air Quality
Potential improvement to air quality due to accommodation of the centre-left turn lane (reduction in idling vehicles).
Potential improvement to air quality due to accommodation of the centre-left turn lane (reduction in idling vehicles).
The provision of a multi-use path may improve air quality marginally over Alternative Design 2A by providing connections to additional MUPs despite the short length of this segment.
Summary Preferred Preferred
Social Environment
Minimizes Impacts on Adjacent Areas
The design has a minimal impact on the adjacent area as it uses the available ROW and reconfigures the existing road pavement (curb-to-curb).
The design has a minimal impact on the adjacent area as it uses the available ROW and reconfigures the existing road pavement (curb-to-curb).
Improves Access to Adjacent Areas
The two-way CLTL will improve vehicular access to the commercial plaza parking lots.
The two-way CLTL will improve vehicular access to the commercial plaza parking lots.
The proposed MUP will enhance the area’s accessibility to cyclists.
Mitigates Traffic on Local Streets
Improvement in traffic flow through the implementation of a two-way CLTL has the potential to divert traffic away from local streets.
Improvement in traffic flow through the implementation of a two-way CLTL has the potential to divert traffic away from local streets.
Minimizes Traffic Noise There is the potential for increase in noise levels with future traffic growth. There is the potential for increase in noise levels with future traffic growth.
Preserves Archaeological and Cultural Heritage Features
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
Improves Visual Aesthetics
Visual aesthetics are largely influenced by the public realm, streetscaping and public art, for which there are opportunities for under this design alternative.
Visual aesthetics are largely influenced by the public realm, streetscaping and public art, for which there are opportunities for under this design alternative.
Improves Community Character and Quality of Life
Community character and quality of life are largely influenced by the public realm and civic amenities. Opportunities exist for public realm/streetscaping improvements.
Community character and quality of life are largely influenced by the public realm and civic amenities. The MUP will contribute a missing piece of infrastructure that will improve the quality of life for cyclists. Opportunities also exist for public realm/streetscaping improvements.
Summary Less Preferred Preferred
Infrastructure Design
Minimize Utility Relocation
Minor impacts to utilities are anticipated as this alternative design primarily utilizes the existing road pavement (curb-to-curb) with widening limited in the vicinity of St. David’s church and the east end of the segment.
Minor impacts to utilities are anticipated as this alternative design primarily utilizes the existing road pavement (curb-to-curb) with widening limited in the vicinity of St. David’s church and the east end of the segment.
Minimize Constructability Complexity
A similar degree of constructability complexity is anticipated between the two alternative designs.
A similar degree of constructability complexity is anticipated between the two alternative designs.
Minimize Disruption due to Construction
Disruption is expected to widen the roadway (where applicable) to implement the CLTL.
There is the potential for temporary disruptions to driveways.
Disruption is expected to widen the roadway (where applicable) to implement the CLTL.
There is the potential for temporary disruptions to driveways.
Summary Preferred Preferred
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 59
Evaluation Criteria
West Segment - Major Mackenzie Drive between Gram Street and McNaughton Road/Avro Road
Alternative Design 3A Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides.
Alternative Design 3B Reconfigure the existing roadway to add a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and an enhanced sidewalk on the south.
Economy and Cost Effectiveness
Optimizes Capital Costs Capital costs are expected to be slightly lower than Alternative Design 3B as the
sidewalks can be maintained in their current condition. Capital costs are expected to be slightly higher than Alternative Design 3A due to the MUP addition on
the north side.
Optimizes Operation/Maintenance Costs
Operating and maintenance costs are expected to be similar to Alternative Design 3B.
Operating and maintenance costs are expected to be similar to Alternative Design 3A.
Optimizes Property Acquisition Costs
No property acquisition is required under this design. No property acquisition is required under this design.
Summary Preferred Less Preferred
Overall Recommendation
Not recommended Recommended
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 60
Central Segment – Jackson Street to Gram Street
Table 8-4: Evaluation of Alternative Cross-sections (Central Segment)
Evaluation Criteria
Central Segment - Major Mackenzie Drive between Jackson Street and Gram Street
Alternative Design 2A Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides by shifting the alignment to the north.
Alternative Design 2B Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and a sidewalk on the south side by shifting the alignment to the north.
Transportation Service
Improves Congestion and Delays
The two-way CLTL lane is expected to address traffic issues due to ingress and egress from commercial driveways, thus improving vehicular flows and delays.
The two-way CLTL lane is expected to address traffic issues due to ingress and egress from commercial driveways, thus improving vehicular flows and delays.
Creates a Cyclist-Friendly Environment
Cyclists are not accommodated under this alternative design (beyond existing conditions). Cyclists are not accommodated in dedicated facilities and have to share the road with vehicles and sidewalks with pedestrians.
Cyclists are accommodated through the MUP provided on the north side of the street under this design alternative.
Creates a Pedestrian-Friendly Environment
Pedestrians are accommodated on both sides of the street. However, the south side sidewalk is sub-standard width due to the constrained ROW.
Pedestrians are accommodated on both sides of the street. However, the south side sidewalk is sub-standard width due to the constrained ROW.
Improves Safety for All Travel Modes
There is the potential for cyclist – vehicle conflicts due to lack of dedicated cycling facilities.
Cyclist – pedestrian conflict is also possible on both north and south sides if cyclists choose to ride on the sidewalk.
The potential for cyclist – vehicle conflict is reduced through the provision of a MUP.
Though there is the potential of cyclist – pedestrian conflict on the MUP, it is to a much lesser extent than in Alternative Design 2A.
Improves Mode Choice May encourage driving or taking transit due improvements to traffic flow.
Does not improve mode choice for active modes.
May encourage driving or taking transit due improvements to traffic flow.
Provision of cycling facilities is known to increase the cycling mode share.
Improves Public Transit Service
Improved traffic flow may provide benefits to planned transit operations. Improved traffic flow may provide benefits to planned transit operations.
Continuous AT facilities provide first/last mile connections to transit.
Summary Less Preferred Preferred
Natural Environment
Minimizes Impacts to and Enhances Environmentally Sensitive Areas
There are no Areas of Natural and Scientific Interest Provincially Significant Wetlands or Environmentally Sensitive Areas located within this segment.
There are no Areas of Natural and Scientific Interest Provincially Significant Wetlands or Environmentally Sensitive Areas located within this segment.
Minimizes Impacts to Wildlife, Vegetation, Aquatic Species and Habitat, and Species at Risk
No anticipated impact on vegetation and habitat in this segment. Wildlife and aquatic species in the study area are largely tolerant of human disturbance.
No anticipated impact on vegetation and habitat in this segment. Wildlife and aquatic species in the study area are largely tolerant of human disturbance.
Provides Stormwater Management Improvements and Mitigates Erosion
This alternative design involves a widened pavement compared to existing conditions and may adversely impact stormwater runoff. The level of impact is anticipated to be similar to that of Alternative Design 2B.
This alternative design involves a widened pavement compared to existing conditions and may adversely impact stormwater runoff. The level of impact is anticipated to be similar to that of Alternative Design 2A.
Improve Air Quality Potential improvement to air quality due to accommodation to the centre-left turn lane
(reduction in idling vehicles).
Potential improvement to air quality due to accommodation to the centre-left turn lane (reduction in idling vehicles). The provision of a multi-use path may improve air quality marginally over Alternative Design 2A by providing connections to additional MUPs despite the short length of this segment.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 61
Evaluation Criteria
Central Segment - Major Mackenzie Drive between Jackson Street and Gram Street
Alternative Design 2A Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides by shifting the alignment to the north.
Alternative Design 2B Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and a sidewalk on the south side by shifting the alignment to the north.
Summary Less Preferred Preferred
Social Environment
Minimizes Impacts on Adjacent Areas
The design has a minimal impact on the adjacent area as it uses the available ROW while reducing the existing but under-utilized grass buffer on the north side.
The design will impose significant impact on the adjacent area (compared to Alternative 2A) as implementation of a MUP will limit streetscaping opportunities and cannot be accommodated in constrained locations without acquiring additional ROW.
Improves Access to Adjacent Areas
The two-way CLTL will improve vehicular access to the commercial plaza parking lots. The two-way CLTL will improve vehicular access to the commercial plaza parking lots.
The proposed MUP has the potential to enhance the area’s accessibility to cyclists.
Mitigates Traffic on Local Streets
Improvement in traffic flow through the implementation of a two-way CLTL has the potential to divert traffic away from local streets.
Improvement in traffic flow through the implementation of a two-way CLTL has the potential to divert traffic away from local streets.
Minimizes Traffic Noise There is the potential for increase in noise levels with future traffic growth. There is the potential for increase in noise levels with future traffic growth.
Preserves Archaeological and Cultural Heritage Features
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
Improves Visual Aesthetics
Opportunities for the enhancement of the social environment are limited to pedestrian realm enhancements. Compared to Alternative Design 2B, this option provides more opportunity for streetscaping and improvements to visual aesthetics.
Visual aesthetics are largely influenced by the public realm, streetscaping and public art, for which opportunities are limited under this design alternative. The majority of the available space will go toward servicing the MUP.
Improves Community Character and Quality of Life
Community character and quality of life are largely influenced by the public realm and civic amenities. This alternative design offers more opportunities for pedestrians and is in line with the City of Vaughan’s vision for the Village of Maple Heritage Conservation District.
Community character and quality of life are largely influenced by the public realm and civic amenities. The MUP will contribute a missing piece of infrastructure that will improve the quality of life for cyclists.
Summary Preferred Preferred
Infrastructure Design
Minimize Utility Relocation
Shifting the centerline north helps accommodate the road improvements while avoiding the relocation of utilities on the south side (e.g. hydro poles).
Impacts to utilities on the north side of the street are anticipated to be similar to Alternative Design 2B.
Shifting the centerline north helps accommodate the road improvements while avoiding the relocation of utilities on the south side (e.g. hydro poles).
Impacts to utilities on the north side of the street are anticipated to be similar to Alternative Design 2A.
Minimize Constructability Complexity
A similar degree of constructability complexity is anticipated between the two alternative designs.
A similar degree of constructability complexity is anticipated between the two alternative designs.
Minimize Disruption due to Construction
Disruption is expected to widen the roadway, to a lesser extent than Alternative Design 2B.
There is the potential for temporary disruptions to driveways.
Additional disruption is expected to widen the roadway due to property acquisition required.
There is the potential for temporary disruptions to driveways
Summary Preferred Not Preferred
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 62
Evaluation Criteria
Central Segment - Major Mackenzie Drive between Jackson Street and Gram Street
Alternative Design 2A Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with sidewalks on both sides by shifting the alignment to the north.
Alternative Design 2B Implement a two-way centre left-turn lane (CLTL) using reduced lane widths with a multi-use path on the north side and a sidewalk on the south side by shifting the alignment to the north.
Economy and Cost
Optimizes Capital Costs Capital costs are expected to be similar to Design 2B. Capital costs are expected to be higher than Alternative Design 2A due to property acquisition
costs.
Optimizes Operation/Maintenance Costs
Operating and maintenance costs are expected to be similar to Alternative Design 2B. Operating and maintenance costs are expected to be similar to Alternative Design 2A.
Optimizes Property Acquisition Costs
No property acquisition is anticipated under this design alternative. The extent of property acquisition required to accommodate a MUP may not be justified given the
absence of an overall cycling network in the immediate area and given the City of Vaughan’s vision for the Village of Maple.
Summary Preferred Not Preferred
Overall Recommendation
Recommended Not recommended
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 63
East Segment – Keele Street to Jackson Street
Table 8-5: Evaluation of Cross-section Alternatives (East Segment)
Evaluation Criteria
East Segment - Major Mackenzie Drive between Jackson Street and Keele Street
Alternative Design 1A Implement an eastbound right-turn lane while shifting the centerline north and using standard element widths. Maintain sidewalks on the north and south sides.
Alternative Design 1B Implement an eastbound right-turn lane while shifting the centerline north and using reduced lane widths. Provide enhanced sidewalks on the north and south sides.
Transportation Service
Improves Congestion and Delays
The right-turn lane is expected to reduce eastbound queuing, thus reducing traffic and delays.
The right-turn lane is expected to reduce eastbound queuing, thus reducing traffic and delays.
Creates a Cyclist-Friendly Environment
Cyclists cannot be accommodated in dedicated facilities due to the narrow ROW in this segment. Cyclists have to share the road with vehicles and sidewalks with pedestrians.
Cyclists cannot be accommodated in dedicated facilities due to the narrow ROW in this segment. Cyclists have to share the road with vehicles and sidewalks with pedestrians.
Creates a Pedestrian-Friendly Environment
Pedestrians are accommodated on both sides of the street. However, the sidewalks are narrower compared to those in Design Alternative 1B.
Pedestrians are accommodated on both sides of the street in increased capacity compared to Alternative Design 1A. Boulevards/sidewalks are slightly wider under this design alternative.
Improves Safety for All Travel Modes
There is the potential for cyclist - vehicle conflicts due to lack of dedicated cycling facilities.
The potential for cyclist - pedestrian conflicts on both north and south sides is relatively high if cyclists choose to ride on the sidewalk.
There is the potential for cyclist - vehicle conflicts due to lack of dedicated cycling facilities.
If cyclists choose to ride on the sidewalk, the potential for cyclist - pedestrian conflicts on both north and south sides is reduced compared to that in Alternative Design 1A, due to the additional space attributed to pedestrians in this design.
Improves Mode Choice May encourage driving or taking transit due to improvements to traffic flow. May encourage driving or taking transit due to improvements to traffic flow.
Improves Public Transit Service
Improved traffic flow may provide benefits to planned transit operations. Improved traffic flow may provide benefits to planned transit operations.
Summary Less Preferred Preferred
Natural Environment
Minimizes Impacts to and Enhances Environmentally Sensitive Areas
There are no Areas of Natural and Scientific Interest (ANSIs), Provincially Significant Wetlands (PSWs) or Environmentally Sensitive Areas (ESAs) located within this segment.
There are no Areas of Natural and Scientific Interest, Provincially Significant Wetlands or Environmentally Sensitive Areas located within this segment.
Minimizes Impacts to Wildlife, Vegetation, Aquatic Species and Habitat, and Species at Risk
No anticipated impact on vegetation and habitat in this segment. Wildlife and aquatic species in the study area are largely tolerant of human disturbance.
No anticipated impact on vegetation and habitat in this segment. Wildlife and aquatic species in the study area are largely tolerant of human disturbance.
Provides Stormwater Management Improvements and Mitigates Erosion
Wider roadway (pavement) may adversely impact stormwater runoff.
Narrower roadway (pavement) width compared to Alternative Design 1A
Potential for improved stormwater management through the incorporation of plantings and Low Impact Development (LID) in the wider pedestrian boulevard in this design.
Improve Air Quality
Potential for improvement to air quality due to reduced congestion (reduction in idling vehicles).
Minor improvement in air quality on adjacent streets due to reduction in traffic diversion.
Potential for improvement to air quality due to reduced congestion (reduction in idling vehicles).
Minor improvement in air quality on adjacent streets due to reduction in traffic diversion.
Summary Preferred Preferred
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 64
Evaluation Criteria
East Segment - Major Mackenzie Drive between Jackson Street and Keele Street
Alternative Design 1A Implement an eastbound right-turn lane while shifting the centerline north and using standard element widths. Maintain sidewalks on the north and south sides.
Alternative Design 1B Implement an eastbound right-turn lane while shifting the centerline north and using reduced lane widths. Provide enhanced sidewalks on the north and south sides.
Social Environment
Minimizes Impacts on Adjacent Areas
The design for this alternative uses the available ROW while reducing the pedestrian amenity, which may impact adjacent businesses adversely.
The design for this alternative uses the available ROW with less sacrifice to the pedestrian realm, which may benefit adjacent businesses.
Improves Access to Adjacent Areas
Proposed median island extension may impose right-in/right-out access restrictions for the Shoppers Drug Mart parking lot.
Proposed median island extension may impose right-in/right-out access restrictions for the Shoppers Drug Mart parking lot.
Mitigates Traffic on Local Streets
Improvement in traffic flow through the implementation of a right turn lane (RTL) has the potential to divert traffic away from local streets.
Improvement in traffic flow through the implementation of a RTL has the potential to divert traffic away from local streets.
Minimizes Traffic Noise There is the potential for increase in noise levels with future traffic growth and a right-turn
lane in closer proximity to properties on the south side.
There is the potential for increase in noise levels with future traffic growth and a right-turn lane in closer proximity to properties on the south side. However, reduced lane widths in this design have traffic calming consequences and may yield improvements to noise levels compared to standard lanes recommended in Design 1A (ITE: Canadian Guide to Neighbourhood Traffic Calming)
Preserves Archaeological and Cultural Heritage Features
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
No anticipated impact on archaeological and cultural heritage features due to previously disturbed conditions.
Improves Visual Aesthetics
Visual aesthetics are largely influenced by the public realm, streetscaping and public art, for which opportunities are limited under this design alternative.
Visual aesthetics are largely influenced by the public realm and streetscaping, for which opportunities are more available due to the larger sidewalks under this design alternative.
Improves Community Character and Quality of Life
Community character and quality of life are largely influenced by the public realm and civic amenities, for which opportunities are limited under this design alternative.
Community character and quality of life are largely influenced by the public realm and civic amenities, for which opportunities are more available due to the larger sidewalks under this design alternative.
Summary Less Preferred Preferred
Infrastructure Design
Minimize Utility Relocation Shifting the centerline north helps accommodate the road improvements while avoiding the
relocation of hydro poles to the extent possible.
Shifting the centerline north helps accommodate the road improvements while avoiding the relocation of hydro poles to the extent possible. Reduction in lane widths further reduces the potential for utility impacts.
Minimize Constructability Complexity
A similar degree of constructability complexity is anticipated between the two alternative designs.
A similar degree of constructability complexity is anticipated between the two alternative designs.
Minimize Disruption due to Construction
Significant disruption is expected to construct an additional lane. There is the potential for temporary disruptions to driveways.
Significant disruption is expected to construct an additional lane.
There is the potential for temporary disruptions to driveways
Summary Preferred Preferred
Economy and Cost Effectiveness
Optimizes Capital Costs Compared to Alternative Design 1B, lower capital costs are likely to be incurred under this
design due to the narrower pedestrian amenities which tend to drive costs. Capital costs have the potential to be slightly higher than Alternative Design 1A due to the wider
public realm which tends to drive costs.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 65
Evaluation Criteria
East Segment - Major Mackenzie Drive between Jackson Street and Keele Street
Alternative Design 1A Implement an eastbound right-turn lane while shifting the centerline north and using standard element widths. Maintain sidewalks on the north and south sides.
Alternative Design 1B Implement an eastbound right-turn lane while shifting the centerline north and using reduced lane widths. Provide enhanced sidewalks on the north and south sides.
Optimizes Operation/Maintenance Costs
Operating and maintenance costs are expected to be similar to Design 1B. Operating and maintenance costs are expected to be similar to Alternative Design 1A.
Optimizes Property Acquisition Costs
No property acquisition is anticipated under this design. No property acquisition is anticipated under this design.
Summary Preferred Less Preferred
Overall Recommendation
Not recommended Recommended
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 68
Recommended Design 8.3
West Segment – McNaughton Road/Avro Road to Gram Street 8.3.1
The recommended design for Major Mackenzie Drive between McNaughton Road / Avro Road and
Gram Street is Design 3B, as shown in Exhibit 8-14. The design requires the reconfiguration of the
existing roadway to add a centre left-turn lane (CLTL) east of the West Don River tributary with an
MUP on the north side. Following comments from the City of Vaughan, the enhanced sidewalk on the
south side was recommended to be modified to a 3.0m MUP similar to the north side. This option
attempts to maintain pavement edges, repurposes the space currently used by the median for the
CLTL. Reduced lane widths will allow for enhanced sidewalks. Advantages of this design also
include the minimization of construction activities, the provision of a multi-use path and cost
efficiencies.
No private properties front onto Major Mackenzie Drive between McNaughton Road / Avro Road and
Apple Tree Montessori School, so no auxiliary lane is needed for this section of Major Mackenzie
Drive. Also, between the Apple Tree Montessori and Gram Street, there are no accesses on the north
side of the study area. Therefore, the CLTL is only required in the westbound direction to facilitate
access to south side properties such as St. David’s Church and the commercial plaza located at the
south-west corner of Killian Road / Netherford Road. A raised median separating eastbound and
westbound traffic is proposed, spanning from Killian Road / Netherford Road west to the Church
Driveway. West of Gram Street, the CLTL will tie into the existing turn lane/centre median.
Central Segment – Gram Street to Jackson Street 8.3.2
The recommended design for Major Mackenzie Drive from Gram Street to Jackson Street is Design
2A, as shown in Exhibit 8-15. The design involves the installation of a centre left-turn lane (CLTL)
with sidewalks on the north and south sides. This design is to be implemented by shifting the
alignment to the north, maintaining the existing south curb and using reduced lane widths.
Advantages of this design include operational and access improvements, a maximized pedestrian
realm in the commercial section of the study area and the minimization of utility relocation and
property acquisition. Sidewalks may be enlarged where space permits.
East Segment – Keele Street to Jackson Street 8.3.3
The recommended design for Major Mackenzie Drive from Keele Street to Jackson Street is
Alternative Design 1B, as displayed in Exhibit 8-16. The design proposes to implement an
eastbound right-turn lane while shifting the centerline north using reduced lane widths and allocating
the remaining available space for the pedestrian realm.
Advantages of this design include improvements to traffic operations through the Keele Street
intersection, an enhanced pedestrian realm compared to other designs, and a potential for traffic
calming achieved through the reduction in lane widths.
Exhibit 8-14: Recommended Design for the West Segment of Major Mackenzie Drive
Exhibit 8-15: Recommended Design for the Central Segment of Major Mackenzie Drive
Exhibit 8-16: Recommended Design for the East Segment of Major Mackenzie Drive
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 69
Operational Improvements 8.3.4
Additional recommendations for operational improvements are identified in the following section.
Refer to the Transportation Technical Report #3, found under Appendix O, for the complete traffic
analysis, methodology and rationale followed for the development of signalization, access and
intersection modification recommendations for the study area.
Traffic Signals 8.3.4.1
The addition of traffic signals along the corridor can improve operations for vehicles while providing
protected crossings for pedestrians and cyclists. Several locations along the corridor were reviewed
for potential signalization to control both east-west and north-south traffic, or only east-west
movement.
The six options considered were:
1. New traffic signal with realignment of the 2414 Major Mackenzie Drive driveway to align with
Gram Street.
2. New traffic signals at 2354 Major Mackenzie Drive
3. New traffic signals at 2332 Major Mackenzie Drive
4. New traffic signals at Golden Spruce Lane and Jackson Street
5. Pedestrian actuated traffic signals approximately 50m east of Gram Street
6. Pedestrian actuated traffic signals approximately 50m west of Jackson Street
The results of the review are summarized in Table 8-6. The potential signal locations are evaluated
based on their adherence to York Region policies, the OTM signal warrant analysis and their
contribution to connectivity within the study area.
Table 8-6:Multi-modal Signal Warrant Analysis Results
Option Location Regional Road Spacing
OTM Signal Warrant Analysis
Connectivity Recommendation
1 Gram Street/2414 Major Mackenzie Drive
OK Not warranted High Carry Forward
2 2354 Major Mackenzie Drive
OK Not warranted Moderate Screen out
3 2332 Major Mackenzie Drive
OK Not warranted Low Screen out
4 Golden Spruce Lane / Jackson Street
Does not meet requirement - Screen out
Not analyzed due to spacing
Not analyzed due to spacing
Screen out
5 East of Gram Street, Pedestrian Actuated
OK N/A High Screen out
6 West of Jackson Street, Pedestrian Actuated
Close to requirement
N/A Moderate Screen out
Option 1 was recommended as the preferred option. It was carried forward instead of Option 5;
because the signalization of Gram Street combined with the proposed driveway realignment (at 2414
Major Mackenzie Drive) would facilitate safer traffic movements. These protected movements at
Gram Street would provide drivers with a safe alternative to the Killian Road/Netherford Road
intersection.
While it is acknowledged that the traffic signal warrant was not met, there is an operational benefit not
captured in the warrant analysis. This benefit is due to the proposed driveway relocation (at 2414
Major Mackenzie Drive) which removes the conflict between eastbound left-turning vehicles looking to
access 2414 Major Mackenzie Drive and westbound left-turning vehicles looking to access Gram
Street.
Further to the operational benefits noted, the signalization of Gram Street and 2414 Major Mackenzie
Drive provides an additional protected pedestrian crossing along the corridor while also increases the
capacity of Gram Street to handle growth and potential diversion of traffic. It is further noted that the
new signal will provide gaps in traffic at adjacent driveways to the east.
This option will reduce the spacing between protected crossings and is anticipated to decrease
jaywalking as pedestrians no longer have to walk to Keele Street or Killian Road / Netherford Road to
cross Major Mackenzie Drive safely.
It must be noted that Council approvals may be required for the implementation of the traffic signal at Gram Street as the signal does not meet the Traffic Signal Warrant despite the safety benefits associated.
Intersection Modifications at Jackson Street 8.3.4.2
Due to the proximity to the Keele Street intersection to Jackson Street, further access restrictions
are recommended at Jackson Street to improve traffic operations. Firstly, Jackson Street is
expected to have increased usage past the 2020 EA study horizon due to the proposed
development on the south side between Jackson Street and Keele Street. Currently, the eastbound
left turn storage lane at Keele Street and Major Mackenzie Drive spans the full 140 m segment
between Jackson Street and Keele Street. As a result, there is potential queue backup from the
eastbound left turn lane at Keele Street which would conflict with and block westbound left turning
vehicles at Jackson Street.
It is recommended that Jackson Street operate as right-in right-out (RIRO) access. This
improvement would facilitate safer turning movements and address driver difficulties. Notably,
drivers seeking to turn left out of Jackson Street have limited opportunities to do so due to limited
gaps particularly in proximity to anticipated queues on Major Mackenzie Drive at Keele Street. Left
turning vehicles entering and exiting Jackson Street can be accommodated via Gram Street. Based
on the existing counts (2015), westbound left turn volumes at Jackson Street were 2 and 8 during
the AM and PM respectively, no northbound left turn volumes were observed during the peak hours.
The proposed full signalization at Gram Street would provide sufficient capacity and a safer place to
accommodate these diverted volumes and the volumes to/from the new development.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 70
Access Modifications at Golden Spruce Lane 8.3.4.3
Due to anticipated conflicts with the eastbound left-turn storage at Keele Street, Golden Spruce
Lane is recommended for ¾ access where left-turns from this street onto Major Mackenzie
Drive eastbound would no longer be permitted. Eastbound left turning vehicles accessing
Golden Spruce Lane will still be permitted due to limited access options for eastbound traffic.
Vehicles exiting Golden Spruce Lane wishing to travel eastbound on Major Mackenzie Drive may do
so via the access off of Keele Street and subsequently making a left turn from Keele Street to Major
Mackenzie Drive.
Access Modifications at 2266 Major Mackenzie Drive 8.3.4.4
It is recommended that the Shoppers Drug Mart access on Major Mackenzie Drive (2266 Major
Mackenzie Drive) operate as ¾ access, where left-turns from the parking lot onto Major
Mackenzie Drive eastbound would no longer be permitted. Other movements such as left-into
the parking lot, right-in and right-out are still permitted under this ¾ access. Eastbound-left turning
vehicles accessing Shoppers Drug Mart will still be permitted due to limited access options for
eastbound traffic. Vehicles exiting the Shoppers Drug Mart parking lot wishing to travel eastbound
on Major Mackenzie Drive may do so by initially heading westbound and u-turning at Gram Street.
This improvement would facilitate safer turning movements and address driver difficulties due to
anticipated conflicts with the eastbound left-turn storage at Keele Street. It is recognized that this
recommendation modifies the existing turning movements into this driveway and is the only
driveway access for the business. A raised median will separate the eastbound-left at 2266 Major
Mackenzie Drive and the storage lane for the eastbound-left turn at Keele Street.
Summary of Recommendations 8.3.5
The recommended improvements to Major Mackenzie Drive between McNaughton Road / Avro Road
and Keele Street are as follows:
Centre left-turn lane from the West Don River tributary crossing to Jackson Street
Multi-use path on the north and south side from McNaughton Road / Avro Road to Killian Road /
Netherford Road
Enhanced sidewalk and public space on the north side from Killian Road / Netherford Road to
Keele Street and on the south side from Jackson Street to Keele Street (as space permits)
A 2.4 metre sidewalk on the south side between Netherford Road / Killian Road and Gram Street
New Traffic Signal at Gram Street and realignment of the 2414 Major Mackenzie Drive driveway
Right-in-right-out (RIRO) access at Jackson Street where westbound left turns onto and out of
Jackson Street are no longer permitted
¾ access at Golden Spruce Lane where eastbound-left movements are no longer permitted (only
right-in, right-out and left-in onto Golden Spruce Lane allowed).¾ access at 2266 Major
Mackenzie Drive where eastbound left movements are still permitted (only right-in, right-out and
left-in into the parking lot allowed.
Dedicated Right-turn lane at Keele Street
9 Project Description
Design Criteria 9.1
The criteria for roadway, active transportation and access design along Major Mackenzie Drive are
summarized in Table 9-1, Table 9-2 and Table 9-3, respectively.
Table 9-1: Roadway Design Criteria
ROAD DESIGN PARAMETERS
PRESENT CONDITIONS
DESIGN STANDARDS
PROPOSED STANDARDS
SOURCE
DESIGN CLASSIFICATION
4 Lane UAU70 4 Lane UAU70 4 Lane UAU70
TAC 2017 Chapter 2
Pg. 47 Table 2.6.2
DESIGN SPEED N/A 70 km/h 70 km/h (except east of Keele Street where
it is 50 km/h)
TAC 2017 Chapter 2
Pg. 47 Table 2.6.2
POSTED SPEED 50 km/h 50 km/h 50 km/h YR-RDGL Pg. 17
EQUIVALENT MINIMUM 'K'
FACTOR
30 crest 37 sag
17 crest 23 sag (headlight)
10-12 sag (comfort)
29 Crest 37 Sag
TAC 2017 Chapter 3
Pg. 59 Table 3.3.2 Pg. 62,63
Table 3.3.4 Table 3.3.5
GRADES MAXIMUM
1.1% 5%(Rolling) 1.2 %
YR-RDGL Pg. 18 TAC 2017 Chapter 3
Pg. 55 Table 3.3.1
RADIUS MINIMUM
East of Keele Street:
48m (Tangent between curves)
and 125m (Curve
Radius)
82m (min. Tangent) 200m - 4% Super
Elevation 300m - Reverse
Crown 2000m - Normal
Crown
East of Keele Street: 110 m
TAC 2017 Chapter 3
Pg. 23 Table 3.2.8
Maximum Rate of Super Elevation
(4% Max)
2.5% East of Keele
Street
4.0% East of Keele Street
4 %
TAC 2017 Chapter 3
Pg. 23 Table 3.2.8
PAVEMENT WIDTH 2 Lanes @ 3.5-3.75m
3.3m Through Lane 3.5m Curb Lane
3.5m Through Lane 3.75m Curb Lane
YR-RDGL Pg. 46
SHOULDER WIDTH (fully paved)
N/A N/A N/A N/A
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 71
ROAD DESIGN PARAMETERS
PRESENT CONDITIONS
DESIGN STANDARDS
PROPOSED STANDARDS
SOURCE
SHOULDER ROUNDING
N/A N/A N/A N/A
MEDIAN WIDTH N/A 4m min.
Centre left turn lane 4-4.4m Centre left
turn lane
TAC 2017 Chapter 7
Pg. 29 Sect. 8.6.2
R.O.W. WIDTH
25 m to 66 m
OP Map 12 45m max.
Between Netherford Road and Gram
Street 30m max.
Between Gram Street and Keele
Street
As existing conditions: R.O.W
width varies between 25m and 66m.
York Region Official Plan- Map
12
SIGNALS & ILLUMINATION
Full illumination, full signals
Replace illumination, replace
signals
Replace traffic signals at Keele Street
New signals at Gram Street
Replace illumination
N/A
EROSION & SEMENT
CONTROLS FOR DESIGN
(e.g. rip-rap, gabions, rock check dams)
(e.g. filter socks, vegetated mats)
(e.g. filter socks, vegetated mats)
As per the Greater Golden Horseshoe Area Conservation Authorities – ESC
Guidelines – December 2006
Table 9-2: Active Transportation Design Criteria
CYCLING AND PEDESTRIAN
DESIGN PARAMETERS
PRESENT CONDITIONS
DESIGN STANDARDS
PROPOSED STANDARDS
SOURCE
Cycling Facility Type (e.g. on-
street, off-street, MUP)
N/A 3.0m max 3.0m YR-RDGL
Pg. 57
Minimum Boulevard Width
1.9 m (including sidewalk)
3.5m min. from edge of pavement
(including sidewalk, transit facilities and
guiderail)
Varies throughout design
YR-RDGL Pg. 47
CYCLING AND PEDESTRIAN
DESIGN PARAMETERS
PRESENT CONDITIONS
DESIGN STANDARDS
PROPOSED STANDARDS
SOURCE
Proposed Sidewalk Width
1.5m (North side) 1.2m (South side)
1.5m width, 0.5m buffer(adjacent to
curb)
Varies.
Minimum 1.2m on south side between
Killian Road / Netherford Road and
Jackson Street
Up to 3.0m wide sidewalks, extending to the property line in the
Heritage District.
0.5m buffer (adjacent to curb)
YR-RDGL Pg. 57
Table 9-3: Access Design Criteria
ENTRANCE DESIGN
PARAMETERS
PRESENT CONDITIONS
DESIGN STANDARDS
PROPOSED STANDARDS
SOURCE
MINIMUM WIDTH 4 m Res. 6 m Com.
5 m Res. 9 m Com.
5 m Res. 9 m Com.
YR-RDGL DS-215 (Res.) DS-203 (Com.)
MINIMUM LENGTH (ROW to building)
8 m Res. 3 m Com.
N/A 8 m Res. 3 m Com.
As per local municipality
standard
MINIMUM RADIUS 0 m Res. 0 m Com.
5 m Res. 9 m Com.
5 m Res. 9 m Com.
YR-RDGL DS-215 (Res.) DS-203 (Com.)
MAXIMUM GRADE 7 % 10 % 10 % YR-RDGL Pg. 62
MAX. ALGEBRAIC GRADE CHANGE (4%
Max) 3 % 4% max. 4 % YR-RDGL Pg. 62
Design Standard References:
York Region Road Design Guidelines (December 2016, version 1.20);
TAC Geometric Design Guidelines (June 2017);
MTO Geometric Design Standards for Ontario Highways (June 2017).
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 72
Road Geometry 9.2
Horizontal Alignment 9.2.1
The horizontal alignment for the preferred design is generally consistent with the existing centreline of
Major Mackenzie Drive, with the exception of a northerly horizontal alignment shift west and east of
the intersection of Keele Street and Major Mackenzie Drive. West of the Keele Street intersection, the
alignment accommodates the required minimum roadway curvature radius of 2000 m based on a 70
km/h design speed. The resultant back-to-back curve minimizes the grading impact to the adjacent
properties on the south side and allows sufficient space for the new eastbound right turn lane. East of
the Keele Street intersection, the proposed alignment is designed with a roadway curvature radius of
110 m with a 50 km/h posted speed and 70 km/hr design speed (with the exception of east of Keele
Street where the design speed is also 50km/hr).
The central segment of the corridor from Jackson Street to Gram Street, the roadway horizontal
alignment is proposed to shift to the north and maintaining the existing south curb. The horizontal
alignment will tie into the existing centerline alignment west of Gram Street.
The proposed horizontal alignment is illustrated on the preliminary design drawings in Appendix A.
Vertical Alignment 9.2.2
The proposed vertical alignment was designed to generally follow the existing road profile where
possible.
Structural Design 9.3
The findings of the Culvert Inspection Report indicated that the existing corrugated steel arch culvert
at the West Don River crossing is in very poor condition. Immediate replacement of the culvert is
recommended. Due to the urgent nature of the culvert works, the replacement project is being
undertaken separately as a schedule “A” Class EA and is not part of this study.
Typical Cross-Sections 9.4
West Segment – McNaughton Road / Avro Road to Gram Street 9.4.1
The typical cross-section (looking east) for the West Segment is illustrated in Exhibit 9-1.
The typical cross-section generally consists of:
Two (2) 3.5 m curb lanes (one in each direction)
Two (2) 3.3 m through-lanes (one in each direction)
A raised median at McNaughton Road / Avro Road
A 4.4 m centre left-turn lane, depicted as a painted median.
A 3.0 m multi-use path on the north side of Major Mackenzie Drive between McNaughton Road /
Avro Road and Killian Road / Netherford Road
A 3.0m multi-use path on the south side of Major Mackenzie Drive between McNaughton Road /
Avro Road and Killian Road / Netherford Road
A 2.4 m sidewalk on the north side of Major Mackenzie Drive between Killian Road / Netherford
Road and Gram Street
A 2.4 m sidewalk on the south side of Major Mackenzie Drive between Killian Road / Netherford
Road and Gram Street
Exhibit 9-1: Recommended Design for the West Segment of Major Mackenzie Drive
During detailed design, illumination design will consider the type and location of poles and luminaires.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 73
Central Segment – Gram Street to Jackson Street 9.4.2
The typical cross-section (looking east) for the Central Segment is illustrated in Exhibit 9-2. The
typical cross-section generally consists of:
Two (2) 3.5 m curb lanes (one in each direction)
Two (2) 3.3 m through-lanes (one in each direction)
One 4.0 m two-way centre left-turn lane `
A 1.2 m sidewalk on the south side of Major Mackenzie Drive (which varies throughout the
segment)
A 1.5 m minimum sidewalk with public space extending to the property line on the north side of
Major Mackenzie Drive
Exhibit 9-2: Recommended Design for the Central Segment of Major Mackenzie Drive
East Segment – Jackson Street to Keele Street 9.4.3
The typical cross-section (looking east) for the East Segment is illustrated in Exhibit 9-3. The typical
cross-section generally consists of:
Two (2) 3.5 m curb lanes (one eastbound and one westbound)
Two (2) 3.3 m through-lanes (one in each direction)
One (1) 3.0 m left-turn lane (eastbound)
One (1) 3.5 m right-turn lane (eastbound)
A 1.4 m median (treatment for the median will be defined during detailed design)
A 3.0 m public space on the south side of Major Mackenzie Drive
A 2.5 m public space on the north side of Major Mackenzie Drive
Streetscaping through decorative pavers and planters within the boulevard
Exhibit 9-3: Recommended Design for the East Segment of Major Mackenzie Drive
Cycling and Pedestrian Facilities 9.5
The preferred design incorporates a one-way off-road multi-use path (MUP) on the north and south
side of Major Mackenzie Drive between McNaughton Road / Avro Road and Killian Road/Netherford
Road. The design of the MUP is based on Ontario Traffic Manual (2014) OTM Book 18 – Cycling
Facilities, which provides guidelines for the design of safe active transportation facilities and
intersection treatments. The multi-use trail on the north side will have a minimum 3.0 m width. The
selection of material type and treatment for the multi-use path will be revisited and confirmed during
detailed design. East of the Killian Road/Netherford Road intersection to Keele Street, the north
boulevard will maintain a sidewalk that will vary in width and be integrated with public space that is
adjacent to the commercial properties in this segment.
The south side of Major Mackenzie Drive will receive a 2.4m wide sidewalk from Killian Road /
Netherford Road through Gram Street, east of which the existing sidewalk will be maintained through
Jackson Street. The north side of the road from Killian Road / Netherford Road to Keele Street as well
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 74
as the south side from Jackson Street to Keele Street will accommodate pedestrians to a greater
extent through a more generous public space and enhanced paving treatment.
Public and stakeholder consultation indicated support for the introduction of active transportation
facilities into the preferred design.
Intersections and Access Modifications 9.6
Intersections will be designed in accordance with AODA standards and to facilitate the movement of
all road users, including pedestrians and cyclists. Intersection modifications for Major Mackenzie
Drive are summarized:
Between McNaughton Road / Avro Road and Killian Road / Netherford Road, the preferred road
design will match into the existing intersections. No physical modifications are anticipated for
these intersections as the road improvements will not necessitate changes to curb returns.
Signalization and driveway realignment will need to be undertaken at Gram Street to implement a
protected crossing. These modifications would facilitate safer traffic movements and enhance
pedestrian connectivity in the area. Works will be mostly confined to the north side of the street.
At Golden Spruce Lane, a ¾ access is proposed where eastbound left movements are still
permitted.
At Jackson Street where a Right-In-Right-Out access is proposed, physical modifications are in
the form of a concrete median that prevents left egress. Left-turning vehicles currently entering
and exiting Jackson Street can be accommodated via the proposed traffic signal at Gram Street.
At the Shoppers Drug Mart parking lot, a ¾ access is proposed where eastbound left movements
are still permitted.
At Major Mackenzie Drive and Keele Street, major intersection works will be required to
accommodate the eastbound right-turn lane as well as tie-in the east and west sides of the
intersection. The recommended design includes removal of the channelized right-turn island on
the north-east quadrant.
Traffic Signals, Illumination and Signage 9.7
A traffic signal is recommended at Gram Street along with the realignment of the driveway at 2414
Major Mackenzie Drive. Signal timing and phasing should be reviewed at this intersection and
monitored over time.
The existing traffic signals at Keele Street will require replacement as the recommended design shifts
the roadway alignment north. Temporary signals will also be required at this location during
construction.
Signage and pavement markings will be included as part of the detailed design and will be in
accordance with the York Region Pedestrian and Cycling Planning and Design Guidelines and
Ontario Traffic Manual (OTM) Book 18: Cycling Facilities.
Streetscaping and Landscaping 9.8
The preferred design was carried out in accordance with York Region’s Regional Streetscape Policy
which highlights the role of Regional streets in promoting high quality urban design, serving as
entryways to communities and encouraging the development of pedestrian-friendly and transit-
oriented neighbourhoods. To conform to this policy directive, streetscaping and landscaping were
used to enhance and improve the quality of urban design along Major Mackenzie Drive. The design
also follows York Region’s "Street Tree Preservation and Planting Design Guidelines".
The preferred design acknowledges the study area`s location within the Village of Maple Heritage
Conservation District (VM-HCD) and reflects the goals and objectives set out in the VM-HCD Plan
(2006). Between Jackson Street and Keele Street (East Segment), streetscaping features involve
planters, bollards, red unit pavers, ornamental lighting, bollards and street furniture. A visual depiction
of the preferred design is presented in Exhibit 9-4, looking west at Major Mackenzie Drive and Keele
Street.
Exhibit 9-4: Preferred Design for Major Mackenzie Drive at Keele Street, looking west
From McNaughton Road/Avro Road to Gram Street, the preferred design includes a multi-use path
(MUP) on the north side and south side of Major Mackenzie Drive. The MUPs are separated from the
roadway by raised concrete tree planters. The raised planter edges provide space for seating while a
concrete median delineates bi-directional vehicular traffic, as seen in Exhibit 9-5.
Exhibit 9-5: Preferred Design for Major Mackenzie Drive at Saint David's Church, looking west
Public amenity areas are planned to connect Major Mackenzie Drive with the future recreational trail
along the West Don River Valley. The public amenity areas will enable trail access on both the north
and south sides of the street and will include benches, planting beds, shade trees and sitting blocks.
The Landscape and Streetscape Plan is included in Appendix P.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 75
Property Requirements 9.9
The proposed operational improvements attempt to minimize property requirements, as such, there
are no property takings anticipated as per the preferred design. There is the opportunity to review
planter and decorative paving re-installment during detailed design.
Drainage / SWM Plan 9.10
The following sections summarize the drainage and stormwater management findings and
recommendations for Major Mackenzie Drive. Details are included in Appendix K.
Roadway Drainage 9.10.1.1
The study area is within the area regulated by the TRCA and a portion of the corridor is within the
regulatory floodplain of the West Don River. The proposed roadway improvements will not alter the
existing drainage pattern. A hydraulic analysis using HEC-RAS was completed for existing and
proposed conditions to demonstrate that the proposed culvert replacement work will not have a
negative impact on flood elevations and will meet the requirements of the MTO Drainage Design
Standards. The culvert replacement is being undertaken as a separate Class Environmental
Assessment due to the Emergency nature of the works.
The proposed roadway improvements will result in an additional pavement area of 0.57 hectares
within the existing right-of-way of Major Mackenzie Drive. The existing catchbasins along the
westbound curb will be relocated to accommodate the proposed northerly shift of the roadway.
Minor Drainage System
The storm sewer system draining the pavement for the ultimate roadway configuration is to be
designed for a 10-year storm event as per York Region Road Design Guidelines. Proposed roadway
drainage will be collected by a series of catchbasins and will be conveyed by storm sewers to existing
outfall locations. For the storm sewer discharge locations, refer to the Drainage Area Plans in
Appendix K. A summary of the drainage areas is provided in Table 9-4.
Table 9-4: Drainage Area Summary
Drainage
Area ID
From
Station To Station
Drainage
Area
(ha)
Discharge Location
A 10+020 10+590 2.03 Outlet to West Don River
B 10+590 10+700 0.46 Connect to existing storm sewer system at Sta. 10+620
C 10+700 11+070 1.11 Connect to existing storm sewer system at Sta. 10+910
D 11+070 11+250 0.48 Connect to existing storm sewer system at Sta. 11+105
E 11+250 11+450 0.69 Connect to existing storm sewer system at Sta. 11+204
Major Drainage System
The roadway design should ensure that the major system runoff up to the 100-year storm event can
be safely conveyed to watercourse locations and should allow one lane in each direction to be clear
of any flooding. The proposed roadway profile is consistent with the existing roadway profile. Major
system relief will occur at the major watercourse crossing at the West Don River. At roadway low
point locations, major system inlets will provide capture of the 100-year flow and direct it to the outfall.
For major system flow route details, refer to the Drainage Area Plans provided in Appendix K.
Stormwater Management Strategy 9.10.1.2
The proposed stormwater management plan for the project has been developed by examining the
opportunities and constraints within the entire project area. Runoff from the paved roadway area will
be conveyed to the proposed roadway storm sewer systems and discharge directly into a natural
watercourse (wetland/West Don River) or to the existing storm sewer systems south of Major
Mackenzie Drive. The total roadway pavement area will increase by 0.57 ha within the right-of-way.
Various stormwater best management practices (BMP) are proposed for quality treatment and peak
flow reduction of the runoff from the additional pavement area. As part of the SWM strategy, 1.32
hectares of pavement area will receive water quality treatment via a proposed oil-grit separator unit.
Table 9-5 provides a summary of the water quality treatment and peak flow control strategy proposed
to mitigate the increase in impervious surface within the project.
Table 9-5: Summary of Stormwater Management Plan
Drainage Area ID
Existing Pavement
Area (ha)
Proposed Pavement
Area (ha)
Additional Pavement
Area (ha)
Stormwater Management
Measures
Pavement Area
Treated (ha)
Preliminary Target
Quantity Control Release
Rate (m
3/s)
Preliminary Required Storage Volume
(m3)
A 10+020 to
10+590 1.13 1.32 0.19
OGS, Peak flow control and Storm sewer outfall mitigations
1.32 0.426 92.2
B 10+590 to
10+700 0.20 0.25 0.05
Peak flow control mitigation
- 0.063 22.7
C 10+700 to
11+070 0.69 0.87 0.19
Peak flow control mitigation
- 0.217 82.0
D 11+070 to
11+250 0.37 0.48 0.11
Peak flow control mitigation
- 0.116 45.1
E 11+250 to
11+450 0.57 0.60 0.03
Peak flow control mitigation
- 0.179 45.7
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 76
Drainage Area ID
Existing Pavement
Area (ha)
Proposed Pavement
Area (ha)
Additional Pavement
Area (ha)
Stormwater Management
Measures
Pavement Area
Treated (ha)
Preliminary Target
Quantity Control Release
Rate (m
3/s)
Preliminary Required Storage Volume
(m3)
Total Pavement Area Treated 1.32 ha
Required Pavement Area to be Treated 0.57 ha
Note: During detailed design stage, the preliminary target release rate and preliminary target storage
volume will be reviewed and reassessed based on the final roadway design.
Opportunities to implement storm sewer outfall mitigation to provide additional water quality control
and erosion control shall also be considered in series with the proposed oil-grit separator unit to
achieve the overall water quality target. Over-sized storage pipes are proposed immediately upstream
of the storm connection pipes/outfall to provide the required storage volume for peak flow control.
Supplemental measures are to be evaluated and designed in series with the proposed oil-grit
separator during detailed design to provide additional water quality mitigation to the storm sewer
outfall to the existing wetland and West Don River tributary.
Geomorphology 9.11
In accordance with the TRCA Crossing Guideline for Valley and Stream Corridors (TRCA, 2015), the
preferred approach for a crossing replacement for existing crossings should consider the meander
belt, 100-year erosion limit, and less preferentially, a geomorphic realignment of the channel.
Similarly, the Fluvial Geomorphic Guidelines prepared by the Credit Valley Conservation Authority
(CVC, 2015), recommends a span at minimum, three times the bankfull width of the channel.
In the case of the replacement crossing of Major Mackenzie Drive over the tributary of the West Don
River, a crossing that spans three times the bankfull width is recommended, as this provides an
appropriately conservative approach. An open concrete box culvert, which incorporates a natural bed
substrate, should be used. The substrate should be hydraulically sized to limit entrainment through
the anticipated range of flows.
Table 9-6 summarizes the recommendations for the proposed crossing, from a geomorphic
perspective.
Table 9-6: Geomorphic Assessment summary and Crossing Recommendations
Average Bankfull
Width (m)
Valley Setting
Meander Belt
Width (m)
RGA Score
100-Year Migration
Rate (m)
Existing Structure
Type
Existing Structure Opening Width (m)
Proposed Structure
Type
Opening Width
(m)
4.55 Unconfined
48 0.41 8
Pipe Arch
Culvert 3.0 x 4.7
Concrete
Box 12
3.80 48 0.25
Note that the culvert replacement will be undertaken as a separate Schedule ‘A’ Class EA and all the
permitting and approvals will be secured independently.
Geotechnical and Foundations Engineering 9.12
A geotechnical assessment was conducted and is provided under Appendix J. The existing
pavement structure on this section of Major Mackenzie Drive does not satisfy York Region’s
requirements for an arterial road and significant strengthening is required to upgrade the road to
support future traffic based on the projected growth.
A number of pavement rehabilitation options were reviewed, including
Option 1: Mill 90 mm / Pave 210 mm (EAM)
Option 2: Pulverize Existing Pavement Structure and underlying granular materials to 300 mm
and Pave 210 mm new HMA (CIREAM)
Option 3: Full Depth Reconstruction
Options 1 and 2 were rejected due to the presence of a number of intersections, commercial
driveways, manholes and catch basins, which will require frequent changes/adjustments due to the
length of the CIREAM/EAM train. The preferred option based on the grade raise restriction is Option
3. Full depth reconstruction entails removing the existing hot mix asphalt (HMA) and underlying
granular materials and subgrade soil to a depth of 910 mm below finished grade and placing the
following:
160 mm new HMA
200 mm new Granular A, base material
550 mm new Granular B, Type I, subbase material
The effective Structural Number (SN) for Option 3 is 145 mm and exceeds the144 mm required SN
for 20 year life.
Utilities 9.13
Existing utilities along the corridor based on available information are described in Section 4.9.
Coordination with the utilities stakeholders will be required during detailed design to confirm the
existing utility location and alignment, which may result in design adjustments and/or
changes/relocation due to the roadway improvement. Formal definition of impacts on utilities will be
determined during detailed design, in consultation with individual utility companies.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 77
Hydro poles are located primarily on the south side of Major Mackenzie Drive within the study corridor
while light standards line the north side. Based on the preferred design, it is not anticipated that
hydro pole relocations will be required.
The location and alignment of existing municipal services including storm sewers, sanitary sewers,
communication cable and watermain is to be confirmed during detailed design, which may result in
changes to the identified utility impacts. All utility information should be updated prior to construction
to ensure that the data is accurate and to finalize relocation requirement as necessary. During
detailed design, meetings will be held with utility companies as required where potential impacts to
existing or future services are identified.
Note that the culvert replacement will be undertaken as a separate EA and all utilities requiring
relocation including Alectra, Enbridge Gas, communication cables, sanitary sewers, watermain and
storm sewers within the culvert replacement project limits will be undertaken independently.
Preliminary Cost Estimate 9.14
Based on the preliminary cost estimates, the cost of the recommended improvements is estimated at
$6.0 million. The preliminary cost estimate includes cost for roadwork, active transportation,
illumination, utilities, landscaping, traffic signals and engineering. The costs associated with the
culvert replacement emergency work at the West Don River crossing is not included as part of the
Major Mackenzie Drive Operational Improvements Class EA. More details on the preliminary cost
estimate are provided in Appendix Q. These preliminary cost estimates are to be reviewed and
confirmed during detailed design.
Constructability, Staging and Detour Considerations 9.15
The proposed reconstruction of Major Mackenzie Drive includes the implementation of an eastbound
right-turn lane and shifting the centerline alignment to the north between Keele Street and Jackson
Street, widening the boulevard to implement a center left-turn lane, addition of multi-use paths and
sidewalks between Jackson Street and McNaughton Road/ Avro Road. The reconstruction should be
staged to maintain both local and through traffic within the Study Area to the extent possible, and
minimize disruptions. A minimum of one lane in each direction including an auxiliary lane for turning
movements should be maintained at all times during construction
The critical component of the construction will be the replacement of the West Don River tributary
culvert. Since the culvert replacement is proceeding as a separate undertaking outside of this Class
Ea, the anticipated road staging and detour considerations will be determined during the culvert
replacement detailed design. Any necessary interruptions to the traffic, including the potential need
for lane closures for the West Don River crossing replacement should be minimized to the extent
possible.
Construction Monitoring and Maintenance Considerations 9.16
The reconstruction of Major Mackenzie Drive should be staged to maintain both local and through
traffic within the Study Area to the extent possible, and minimize disruptions. Any necessary
interruptions to traffic, including the need for lane closures, should be minimized as feasible. No full
road closure is anticipated.
Property owners may experience temporary interruptions to their property access during construction.
To reduce this impact, all property owners should be notified prior to construction and in advance of
work related to their access. Detailed design plans should include details to describe how temporary
accesses will be maintained, and contract specifications should specify the allowable lengths of
closures and the notification requirements to property owners.
Construction of the improvements has the potential to create noise and dust for the adjacent property
owners. Construction noise is temporary and will vary periodically during the construction depending
on the specific activities being performed. Contract specifications should include provisions to define
the allowable work hours, in accordance with local ordinances, to minimize impacts to the adjacent
landowners in the evenings. However, some consideration should be given to the ability of completing
the work in a lesser duration by allowing longer work hours. The impact of construction noise will vary
based on the type of equipment used, number of pieces of equipment, time and duration of operation,
and the proximity to noise sensitive receivers in question. Construction noise can be kept to a
minimum through the use of well maintained equipment with appropriate noise controls by the
contractors.
It is recommended that during the construction period, the following be considered:
All pertinent noise by-laws are to be adhered to;
General noise control measures to be included in contract documents where applicable;
Any noise complaints or concerns to be investigated to ensure compliance with the noise control
measures as recommended in the contract documents. The contractor shall be warned for non-
compliance and the contract shall be enforced;
Additional noise control measures are to be investigated in accordance with the MECP sound
level criteria for construction equipment if a persistent complaint has been made.
Removal of the existing paved surface and existing landscaping will expose native soils to wind and
rain erosion, and result in a temporary increase in dust in the project area. This dust can become
airborne as construction traffic runs on the exposed ground, and may be noticeable by the adjacent
property owners. This increase in dust levels will be temporary, and the application of best
management practices, including the application of non-chloride dust suppressants, by the contractor
during their normal operations can help to minimize the exposure of native soils to wind and rain
erosion, and mitigate any air quality impacts caused by construction dust.
All waste generated during construction must be disposed of in accordance with ministry
requirements and best management practices. Contractors must be made aware of all environmental
considerations so that all environmental standards and commitments for both construction and
operation are met. Construction and post-construction monitoring plans should be developed during
detailed design in consultation with MECP and other regulatory agencies.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 78
10 Potential Environmental Effects and Mitigation
Socio-Economic Environment 10.1
Property Impacts and Access 10.1.1
No property requirements are associated with the proposed Major Mackenzie Drive operational
improvements, as presented in Section 9.9.
Moreover, no impacts to buildings are anticipated. Some existing driveways along the study area may
be impacted as part of the proposed improvements and may need to be re-graded when the ultimate
design is implemented. Specific locations are identified on the preliminary design plates.
In addition, access at the following locations is proposed to be modified:
Realignment of the driveway at 2414 Major Mackenzie Drive with Gram Street (full access
maintained)
Jackson Street, where a proposed raised median will make the street right-in-right-out
2266 Major Mackenzie Drive, where a ¾ access is proposed for the Shoppers Drugmart parking
lot
Full access is proposed to be maintained at all remaining existing access locations.
Development Impacts 10.1.2
The proposed design was developed in consideration of planned and ongoing development in the
study area such as at 2338 and 2269-2285 Major Mackenzie Drive. The recommended
improvements’ minimal effect on adjacent developments did not require extensive developer
consultation. Developers were invited to engage with the project to the extent of the other
stakeholders such as the public and property owners.
In the case of future redevelopment, developers are encouraged to work with the City of Vaughan to
minimize traffic impacts on the study area through the consolidation of access points.
Air Quality Assessment 10.1.3
A Category 3 Air Quality Impact Assessment was completed for this EA study per the MECP’s
protocol for traffic related air pollution for projects shorter than 2km.
Under the Category 3 AQIA, impacts to air quality can be assumed minimal for this EA for the
following reasons:
The study area is short in length (~1.4 km) and predominantly straight and flat.
The addition of centre-left turn lane is proposed to improve operations and reduce congestion
and idling within the corridor
The addition of an eastbound right-turn lane is proposed to improve operations at the Keele
Street intersection.
No widening for capacity improvements is proposed (i.e. no capacity increase for single occupant
vehicles)
Active transportation improvements are proposed
The qualitative review is provided in the subsequent section.
Qualitative Review 10.1.3.1
The MECP Air Quality in Ontario 2016 Report states in the executive summary that air quality is
improving and emissions are decreasing:
“Overall, air quality has improved significantly over the past 10 years due to substantial decrease in
harmful pollutants such as nitrogen dioxide sulphur dioxide and carbon monoxide that are emitted by
vehicles and industry.
There has also been a significant decrease in fine particulate matter
The continued decrease in these pollutants is due in part to Ontario’s air quality initiatives such as
Drive Clean testing of vehicle emissions”
York Region is managing emissions and greenhouse gases through sustainable transportation
infrastructure planning and implementation.
York Region is committed to ensuring the environmental health of its residents. In addition to the
Ontario initiatives, York Regions’ Corporate Air Quality Strategy, as approved by Council in 2008,
identifies region-wide initiatives (not just road corridor specific) which support the management of
emissions and green house gases.
Regional initiatives in support of the Corporate Air Quality Strategy are on-going, including:
York Region Transportation Master Plan - The TMP is a strategic planning document designed to
define the policies, programs and infrastructure improvements required to address York Region’s
transportation needs for the future. In order to support a more sustainable region, York Region is
actively taking steps to move more people by public transit, carpooling, on foot and by bicycle
and thus shift the focus away from single occupant motor vehicles to more sustainable travel
modes. To support increased transit operations, the Region is planning on implementing road
improvements including rapid transit and transit priority corridors.
York Region Pedestrian and Cycling Master Plan (PCMP) - Cycling and pedestrian facilities are
vital to the Regional multi-modal strategy by providing alternative transportation options. The
PCMP builds on connecting and expanding existing cycling and pedestrian facilities in the region
to establish an integrated and readily accessible region-wide network serving both urban and
rural areas. The PCMP supports a more sustainable Region with a goal of providing a range of
alternative transportation choices that will benefit residents, employees and visitors in York
Region by improving public health and air quality while reducing dependence on the private
automobile.
As a signatory to the Clean Air Council (CAC) Inter-Governmental Declaration on Clean Air & Climate
Change, the Region was also recognized for meeting targets of the CAC 2012-2014
InterGovernmental Declaration on Clean Air and Climate Change, including meeting the active
transportation plan target. One of the four priority action areas identified in the 2015-2018
InterGovernmental Declaration on Clean Air & Climate Change in accordance with the development
of healthy, lower carbon and sustainable communities is:
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 79
Development and implementation of active transportation and transportation demand
management into transportation planning, policy and decision making.
The 20/20 Way to Clean Air is another program supported and implemented by the Region. This
program provides the link between air pollution, energy use, climate change and public health and
acts as a guide to help participants cut down vehicle emissions and home energy use. In support of
this York Region offers active transportation options and programs including:
Metrolinx’s Smart Commute program - This Transportation Demand Management program offers
services to employers interested in promoting carpooling, transit and other sustainable means of
transportation to their workforce for commuting purposes. The goal is to reduce traffic congestion
and vehicle emissions throughout the GTA and surrounding areas.
Public Transit: York Region Transit / VIVA and GO Transit
School Transportation Options: Green Communities Active and Safe Routes to School
Tips to Reduce Energy Use on the Road
The recommendations from the Major Mackenzie Drive EA study support various Region
initiatives and plans to help improve the overall air quality in the Region by implementing
active transportation options that reduce emissions.
York Region is actively mitigating air pollutants through extensive tree planting initiatives
The planting of trees and vegetation promotes healthy and sustainable communities. Regional and
local municipalities throughout Ontario are working with MECP in taking on tree and vegetation
planting initiatives to mitigate air quality impacts resulting from the growing population and increasing
traffic volumes. Durham Region, for example, completed an EA in 2015 (Simcoe Street from Conlin
Road to Winchester Road Municipal Class EA Study), which proposed the widening Simcoe Street in
Oshawa to six lanes. Based on the Air Quality Assessment conducted as part of the EA and with the
support of MECP, Durham recommended mitigation measures to address air quality impacts that
involved adding vegetation and landscaping in the right-of-way.
For over 15 years, York Region continues to be pro-active in its region-wide and transportation
corridor-specific tree-planting initiatives. The addition of trees creates and maintains healthy natural
environments that promote healthy, sustainable communities. The York Region Official Plan sets
out a woodland cover goal of 25 percent. York Region is working to achieve the goal through various
programs, such as York Region’s Greening Strategy, the Region’s Streetscape Program,
Municipal Streetscape Partnership Program and Regional Streetscape Policy:
The Greening Strategy provides a framework for restoring habitat, increasing forest cover,
securing greenlands and their linkages and promoting and protecting the natural environment.
One of its targets is planting a minimum of 70,000 trees and shrubs annually. Over 91,000 trees
were planted in 2014 and over 95,000 trees were planted in 2015 under the Greening Strategy.
York Region’s Streetscape Program has an objective to achieve the successful coordination of
the road, sidewalks, trails, walking and transit facilities within Regional road corridors. Achieving
universal accessibility, focussing on pedestrian comfort and safety to encourage walking and
cycling are of prime importance. To establish an environment that is welcoming to all modes of
transportation, the program is focussed on increasing the number of trees within the boulevards
and medians and optimizing street tree health to improve air quality and reduce energy use.
The Municipal Streetscape Partnership Program (MSPP) assists York Region’s nine local
municipalities in cost sharing on streetscape design projects on Regional roads. The Region
commits up to $1 million annually towards this program. This funding program is critical to the
success of streetscape design in York Region. The MSPP benefits both local municipalities and
York Region in achieving higher quality streetscape design within our communities.
York Region developed its Regional Streetscape Policy to formalize a methodology for the
development of streetscapes that will reinforce the role of Regional Streets as an urban “place”.
Key requirements include enhanced tree planting and landscaping in the boulevards and
medians, continuous sidewalks and the consideration of cycling facilities where feasible.
The recommended design for the Major Mackenzie Drive Road corridor includes landscaping
in the right-of-way.
The recommended design includes planters and streetscaping elements as per the Streetscape
Program. The improvements include planting strips in the north and south boulevards to
accommodate new landscaping and street trees are also recommended. Planting plans will be
prepared during Detail Design to determine the specific spacing, locations and the types of trees to
be planted.
York Region will follow best practices to mitigate air quality issues during construction
During construction, the Region will follow best practices to mitigate air quality issues; for example,
vehicles/machinery and equipment should be in good repair, equipped with emission controls, as
applicable, properly maintained and operated within regulatory requirements. Construction-related air
quality impacts should be minimized through dust suppression. Dust control measures may include
the wetting of surfaces using a non-chloride based compound.
Noise Impact Assessment 10.1.4
A noise impact assessment was completed for the Major Mackenzie Drive EA study based on York
Region’s Noise Mitigation Policy, York Region’s Standard Operating procedures (SOP’s), as well as
the MECP Noise Protocol. The complete Noise Impact Assessment is provided under Appendix R.
Traffic Noise/Vibration 10.1.4.1
The Region’s Noise Policy stipulates that the noise impacts from Capital Road Projects shall consider
the outdoor living area (OLA) at residential dwellings. The OLA is considered to be those areas at
residential dwellings that are reverse or side frontage to the corridor.
Based on the results of the Noise Impact Assessment, the following conclusions were determined:
It is expected the project will result in future noise levels above 60 dBA at three (3) OLAs,
specifically at 59 Curtiss Road, 66 Mathewson Street and 44 Mathewson Street. Mitigation was
not considered at these OLAs as they were already shielded by existing acoustic barriers.
The project did not result in a change in noise levels of greater than 5 dB at any of the
representative OLAs.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 80
The predicted future noise levels met 60 dBA at two OLAs that were not shielded by existing
acoustic barriers. Mitigation was considered at these OLAs, but was not able to meet the Region’s
requirement of providing a minimum of 6 dB reduction. Therefore, noise mitigation at the two
OLAs is not recommended.
Construction Noise Assessment 10.1.4.2
The construction phase of any project is typically considered temporary or short term relative to the
entire life cycle of a project. The following is a summary of the items to be considered relating to
construction noise according to the MTO Noise Guide.
As construction noise could impact receptors in the vicinity of the study area, some general
recommendations to assist in minimizing noise impacts due to the project’s construction equipment
and activities are provided below:
All construction equipment should be properly maintained according to manufacturer’s
recommendations and be in accordance MOECC Model Municipal Noise Control by-law (i.e.,
NPC-115, etc.).
If any of the construction activities involve piling or blasting, they will need to be carried out in
accordance with OPSS 120 and MOECC NPC-119.
Construction equipment and/or activities typically known to be of annoyance (e.g., piling) should
consider one of the following:
o limit operating time within the daytime period when ambient noise levels are expected to be
higher;
o maintain an acceptable setback distance from the identified nearby NSAs;
o carry out additional noise studies or monitoring program to verify and document noise levels;
o implement temporary acoustic barriers or other localized noise mitigation measures; and
o investigate other alternative construction equipment or processes to complete the task.
Noise Complaints Process 10.1.4.3
A process for dealing with noise complaints during the construction phase is required. Noise
complaints are usually received directly from the complainant or a municipal by-law officer. Note that
compliance with noise guidelines or regulations does not ensure noise complaints will not occur. The
following is a general recommended process dealing with noise complaints based on Golder’s past
project experiences:
Identify an individual or group on the Project (i.e., Site Supervisor, Health and Safety
representative, etc.) to handle the noise complaints and someone that can be easily contacted.
Document the noise complaint. Include the date, time and the individual’s contact information from
whom the noise complaint was received. Specific information such as the location, duration, time
and type of sound heard (i.e., steady, impulsive, etc.) should be included as it will assist in the
investigation process. Be aware of any time constraints put in place by the municipality for the
noise complaint to be addressed.
Investigate the noise complaint and identify the source of the noise complaint. Document the
investigation.
If the noise complaint is justified, in that excessive noise levels were generated, minimize or
eliminate the source of the noise complaint. Document the action taken.
Follow up with the complainant and provide the results of the noise complaint investigation.
Natural Environment 10.2
The Natural Heritage Impact Assessment Report (NHIA) presents the findings and recommendations
of the natural heritage investigations including a discussion of the potential impacts and mitigation
associated with the preferred alternative. Due to the nature of the proposed undertaking and the
existing conditions consisting of a mature urbanized neighbourhood containing a combination of low-
rise residential and mixed-use commercial as well as institutional buildings, impacts to significant
aquatic and terrestrial natural heritage features are not anticipated to occur as result of this project.
The complete NHIA report can be found under Appendix G.
This project will involve the movement and/or removal of soils. Excess soil will be managed in
accordance with the MECP's current guidance document titled “Management of Excess Soil – A
Guide for Best Management Practices” (2014).
Vegetation and Vegetation Communities 10.2.1
Major Mackenzie Drive within the study limits is characterized by a mature urbanized neighbourhood
containing a combination of low-rise residential and mixed-use commercial as well as institutional
buildings. From a Natural Heritage perspective, significant natural heritage features do not occur
within the study area limits. The Upper West Don River tributary and a small provincially significant
wetland community occur adjacent to the subject Study Area between Avro Road and lands to the
west of Saint David’s Parish Church.
For this reason, the 261 streetscape trees identified as part of the Street Tree Inventory and
Management Plan comprise the single natural heritage feature of importance to the Class EA study.
The inventory, condition assessment and potential impacts of each of these trees together with tree
preservation measures and mitigation strategies are provided under separate cover in the Street Tree
Inventory and Management Plan (Appendix T).
Using an overlay of the preliminary design for the preferred roadway improvements, potential impacts
to street trees were determined to be minimal to the south and generally restricted to the north. While
there will be a road shift, potential impacts along the north side of Major Mackenzie Drive are
primarily associated with the upgrading of the existing sidewalk to a multiuse path, and replacement
of planters in some areas. Earthworks required for this work will potentially impact existing boulevard
trees situated between the sidewalk and road.
In total, approximately 100 trees are anticipated to be impacted and are recommended for removal.
Many of these trees are small and within the upper limits of suitably for transplanting. This
assessment also considered mature trees or mature trees on adjacent properties with the potential to
be impacted by the construction (e.g. roots damage, dripline encroachment, etc.) of the proposed
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 81
roadway and pathway improvements. Tree tolerance to disturbance varies according to species, size
and the type of stressor. Therefore, removal recommendations account for trees whose limits of
disturbance are undefined or where significant encroachments on the root system is likely, as a
precautionary approach to determining potential impacts.
The findings and recommendations of the Street Tree Inventory and Management Plan (Appendix T)
were used to inform the conceptual street scape enhancement plan also provided as part of the Class
EA study to reinstate and replace all trees removed or damaged due to the construction of the
preferred alternative.
Wildlife and Wildlife Habitat 10.2.2
In Ontario, preferred habitat for Little Myotis is generally considered to be restricted to anthropogenic
structures. Northern Myotis and Tri-coloured Bats are known to prefer woodlands to provide the micro
climates necessary for rearing young and are less likely to use individual landscaped street trees for
such habitat.
Many of the street trees inventoried within the right-of-way limits were not the typical species or size
preferred by SAR bats for maternity roosts sites. However, some trees are of suitable size, have
loose bark, cavities, and/or are species (i.e. Silver Maple, Norway Maple) to potentially provide
habitat opportunities (day roosts) for provincially endangered bat species (Northern Myotis, Little
Myotis and Tri-coloured Bats). These trees are mature street trees generally located along the south
side of Major Mackenzie Drive. The preferred alternative shifts the roadway to the north to
accommodate an additional turning lane and MUP. Limited works, including sidewalk replacement
and minor grading are anticipated along the south side of the road. Therefore, while potential exists
for some streetscape trees to provide summer day roost habitat for individual SAR bats, the potential
to result in harm (interference or removal of trees) to SAR bat habitat is low as a result of this project.
Current direction regarding SAR bats is evolving. On similar projects MNRF has requested avoidance
windows for tree removal as mitigation for bat habitat removal. This avoidance window is typically the
period between April to September when bats are likely to be most active. No hibernation habitat is
known to be present on site. It is recommended that during detailed design, consultation with MECP
and MNRF occur to confirm the avoidance window approach and the specific time period for the
protection of SAR bats.
Mitigation and Environmental Protection 10.2.3
During construction, mitigation encompasses implementation of all relevant standard and
nonstandard / site-specific protection measures and management practices including Operational
Constraints and Construction Specifications. These measures and all the site specific measures will
be refined during the detailed design phase. The mitigation measures will be finalized based on the
final design, and its potential effects on the aquatic and terrestrial environment. In addition,
comprehensive construction mitigation involves recognition and implementation of additional control
measures that may be identified through good construction practices and environmental inspection.
Erosion and Sediment Control 10.2.3.1
A comprehensive sediment and erosion control (ESC) plan will be developed in subsequent design
phases and implemented to prevent migration of sediment laden runoff (or other contaminants) from
the construction zone into stormwater catch basins or the adjacent Upper West Don River. This plan
will include inspection and maintenance of the measures until final cover is established. Specific
aspects will include:
Perimeter sediment fence installed between the work areas and the banks of the watercourse
adjacent to the area of construction;
Temporary sediment protection will be utilized around stormwater catch basins throughout the
active construction zone; and,
Sediment fence and catch basin protections will properly installed and regularly inspected and
maintained.
Tree Protection 10.2.3.2
Tree protection measures for streetscape trees will be required. Upon receiving the necessary
approvals and prior to the commencement of tree removals, areas designated for tree preservation
are to be delineated on site. Street tree protection and mitigation design drawings will be required as
part of the Detailed Design phase.
The following are key considerations of the tree protection plan to be provided as part of the detail
design and tendering phases of this project:
Minimum protection distances (no disturbance to soils), or Tree Protection Zones (TPZ) vary
based on a tree’s dripline. For street trees, the Region provides case by case guidance for
determining TPZs for roadway improvement projects, especially when driplines can be significant
and may impede work zones. The TPZ for trees to be protected are outlined in Street Tree
Inventory and Management Plan (Appendix T).
York Region’s Road Construction Guidelines and Standards should be consulted during the
development of the tree protection plan at detailed design.
Tree removals must occur in accordance with the federal Migratory Bird Convection Act and the
ESA, 2007.
Mulching of roots in a “doughnut” fashion not Volcano (outward not upward) is recommended for
all trees that are to be preserved.
Root pruning along planting beds to be replaced and those near utility trenches may also be
required. All tree pruning must be completed by an experienced ISA Certified Arborist and
monitored during construction.
Where sediment and erosion control may be required in conjunction with tree preservation fencing
along the TPZ, sediment fence should not be used as it is required to be trenched-in which can
damage tree roots. Instead, silt sock (or equivalent) of adequate size (to be determined by the
engineer) is to be used to avoid impacting tree roots.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 82
Contamination 10.2.4
Based on the results of the contamination overview study, the properties located at 2660 Major
Mackenzie Drive, 2563 Major Mackenzie Drive, 2396 Major Mackenzie Drive are considered to
represent a higher potential of environmental concerns due to historic site activities, and it is possible
that subsurface (soil and groundwater) impacts from these sites could migrate toward the roadway.
As no additional property is required to support the preferred design, a Phase I ESA is not anticipated
to be required.
Cultural Environment 10.3
Built Heritage Features and Cultural Heritage Landscape Features 10.3.1
From the results of background research, field investigations and impact assessment, detailed and
specific actions are recommended for the cultural heritage resources in the study area, and are
summarized in Table 10-1 as follows.
Table 10-1: Cultural Heritage Assessment Resources and Recommendations
Resource Type & Civic Address Conservation/Mitigation Measures
Protected Part IV heritage property:
2600 Major Mackenzie Drive
Monitor for vibration impact during excavation in the vicinity of
property and immediately cease work if vibration thresholds are
exceeded.
If design changes require an encroachment on any of these
properties, a CHIA should be conducted in accordance with the
City’s Guidelines for Cultural Heritage Impact Assessments.
Protected Part V heritage
properties:
2365 Major Mackenzie Drive
2347 Major Mackenzie Drive
2339 Major Mackenzie Drive
2333 Major Mackenzie Drive
2321 Major Mackenzie Drive
Monitor for vibration impact during excavation in the vicinity of
property and immediately cease work if vibration thresholds are
exceeded.
If design changes require an encroachment on any of these
properties, a CHIA should be conducted in accordance with the
City’s Guidelines for Cultural Heritage Impact Assessments.
Resource Type & Civic Address Conservation/Mitigation Measures
Protected Part V heritage
properties:
2414 Major Mackenzie Drive
2 Gram Street
1 Gram Street
2401 Major Mackenzie Drive
2396 Major Mackenzie Drive
2389 Major Mackenzie Drive
2377 Major Mackenzie Drive
2354 Major Mackenzie Drive
2355 Major Mackenzie Drive
2388 Major Mackenzie Drive
2332 Major Mackenzie Drive
2316 Major Mackenzie Drive
2327 Major Mackenzie Drive
2302 Major Mackenzie Drive
2311 Major Mackenzie Drive
2300 Major Mackenzie Drive
2298 Major Mackenzie Drive
2296 Major Mackenzie Drive
2301 Major Mackenzie Drive
No mitigation measures are required.
Protected Part V heritage
properties:
2291 Major Mackenzie Drive
9986 Keele Street
9980 Keele Street
10020 Keele Street
Monitor for vibration impact during excavation in the vicinity of
property and immediately cease work if vibration thresholds are
exceeded.
If design changes require an encroachment on any of these
properties, a CHIA should be conducted in accordance with the
City’s Guidelines for Cultural Heritage Impact Assessments.
Protected Part V heritage
properties:
2292 Major Mackenzie Drive
2290 Major Mackenzie Drive
2288 Major Mackenzie Drive
2286 Major Mackenzie Drive
2266 Major Mackenzie Drive
9994 Keele Street
No mitigation measures are required.
However, as no additional property nor encroachment onto heritage property is required to support
the preferred design, CHIAs are not anticipated to be required.
Additionally, the following actions are recommended the following actions to further reduce the
potential for indirect impact on the Maple Heritage Conservation District (HCD):
Develop Interpretive Signage: Interpretive Signage that follows Maple HCD guidelines should
be developed to encourage interaction with the HCD and to establish identity.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 83
Develop a Tree Preservation Plan: The maple trees are the namesake and distinctive feature of
the HCD. A preservation plan should be developed to ensure their retention and encourage
planting of species characteristic of the District, as identified by the Maple HCD objectives.
Develop a Streetscape Plan: As identified in the Maple HCD, all road improvements must
preserve and enhance the heritage character of the District and create a pedestrian and bike
friendly environment. For residential areas, streetscaping must enhance the historical character of
the road allowances. For commercial areas, streetscaping must create a pedestrian-friendly
shopping environment and provide amenities to serve visitors of all ages and mobility access
requirements.
Overall, the Major Mackenzie Drive expansion must comply with the design guidelines of the
Village of Maple Heritage Conservation District Plan (2007). Section 9.6 (Streetscaping) of the
HCD Plan specifically identifies that work within the road allowance should be designed and
executed to meet modern requirements, amenity and convenience, without detriment to the
heritage character of the district. The goals of streetscaping are to enhance the historical
character of the road allowances in the residential areas and create a pedestrian-friendly
shopping environment in the commercial core
Refer to the Appendix P for landscaping details proposed along the study corridor and Appendix
F for the Cultural Heritage Assessment Report.
Archaeological Assessment 10.3.2
The Stage 1 Archaeological Assessment determined that 31 previously registered archaeological
sites are located within the study area limits. In light of the results of this assessment, the following
recommendations are made:
1. The Portions of the study area that were identified as having archaeological potential removed,
such as existing roadways (arterials road, local roads), sidewalks, building footprints, single
home developments, multi-home developments, utilities, need to be confirmed through an on-
site property inspection during a Stage 2 archaeological assessment.
2. Portions of the study area that were identified as having no or low archaeological potential, such
as, the West Don River tributary (watercourse) and the steeply sloping portions of its valley
lands, need to be confirmed through an on-site property inspection during a Stage 2
archaeological assessment.
3. Portions of the study area that were identified as retaining archaeological potential, such as the
grasses yards and the valley lands associated with the West Don River tributary, must be
subject to test pit survey at 5m intervals in accordance with Section 2.1.2 of the Ministry of
Tourism, Culture and Sport Standards and Guidelines for Consultant Archaeologists (MTCS
2011).
4. The northwest, northeast, and southeast corner of the Major Mackenzie Drive and Keele Street
retains archaeological potential for deeply buried archaeological resources beyond the existing
road right-of-way. Should the proposed development extend within the property limits of 10020
Keele Street and 2266 Major Mackenzie Drive (northwest corner); and/or 9995 and 9983 Keele
Street (southeast corner), a Stage 3 archaeological assessment involving backhoe trenching
would be required within the core of the planned development area and over any areas of
archaeological potential as per Section 2.1.7 of the MTCS Standards and Guidelines (MTCS
2011: 36-38). However, as no additional property is required to support the preferred design,
additional archaeological work is not anticipated to be required.
Climate Change 10.4
Approach to Climate Change Consideration 10.4.1
The Ministry of the Environment, Conservation and Parks (MECP, formerly MOECC) guide
Consideration of Climate Change in Environmental Assessment in Ontario sets out ministry
expectations and supports the province’s Climate Change Action Plan by outlining climate change
considerations for Environmental Assessment studies.
The guide notes ‘climate consideration’ within a project means that consideration has been given to
methods to reduce greenhouse gas emissions and developing a design that is more resilient to future
changes in climate and helps maintain the ecological integrity of the local environment in the face of a
changing climate. Specifically, consideration should be given to mitigation (how the project might
mitigate climate change such as reducing greenhouse gas emissions and/or improving carbon
storage of the landscape or removal of carbon dioxide from the atmosphere) and adaptation
(measures to adapt to climate change or make the project more resilient to the effects of climate
change). Considering how a project may contribute to climate change, through its greenhouse gas
emissions or its effects on the natural landscape, is important to the planning process as it allows
proponents to consider climate mitigation measures to avoid, minimize, or offset such effects.
Planning and design of road infrastructure should take into consideration key factors and climate
change trends, such as building to withstand extreme precipitation and extreme heat. These climate
events will impact the physical infrastructures as well as those using the improved Major Mackenzie
Drive corridor in the future. It is understood that that impacts of climate change on transportation
systems are already visible and include:
More travel disruptions due to flooding, winter storms, and road washouts
Increased pavement damage from higher temperatures and freeze-thaw cycles
Increased maintenance requirements for roads, medians and boulevards including hardscape and
vegetative materials
Potential Climate Change Effects 10.4.2
During construction, road infrastructure being built should be as climate ready as possible. Potential
effects to consider include the greenhouse gas (GHG) emissions associated with the construction
period including the physical machinery and equipment, travel distance and time for construction
workers to get to and from the site, and the sourcing of building materials.
Climate change impacts related to this study are also related to operations and maintenance as the
transportation sector is one of the biggest contributors to CO2, a key greenhouse gas. Once Major
Mackenzie Drive has been improved, there is the potential for stormwater capacity and drainage
system issues as the amount of impervious surface areas will increase. Climate change will also
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 84
impact the study area in the future as extreme weather conditions will affect the conditions of the
roadways and will require more frequent repairs and updates as time passes.
Climate Change Mitigation 10.4.3
Consistent with York Region’s sustainability policies and practices, the project-specific
recommendations outlined in Section 9 directly support many of the climate change policies. For
example:
No additional vehicular lanes which would add capacity and increase greenhouse gas emissions
are proposed. Instead, a continuous two-way centre left-turn lane will be provided to improve
vehicular operations and address congestion, thereby reducing idling and curb greenhouse gas
emissions.
Active transportation facilities are recommended to accommodate cyclists and pedestrians,
therefore encouraging alternative modes of travel and reducing single occupancy automobile use.
Tree plantings are proposed to be accommodated in the boulevards, as space permits.
Low impact development strategies are proposed to be explored as feasible.
The proposed design makes use of an existing transportation route and proposes to
accommodate all road users in such a way that minimizes impacts to surrounding areas including
residences, business and valIeylands.
To mitigate potential effects during the construction phase of the project, the following best practices
are recommended:
Development and implementation of detailed erosion and sediment control measures to be
carried out during all construction phases in order to limit the amount of sediment/laden material
entering receiving drainage systems.
Dust suppression techniques to be employed for the duration of construction activities.
A traffic staging plan to be developed during detailed design to accommodate local access and
through traffic during construction to minimize excessive detouring and congestion in alternate
routes. Further opportunities to reduce idling to be considered during detailed design.
Movement and access to the site for construction vehicles is to be described in the contract
documents to be prepared at the time of detailed design.
To mitigate potential effects during the operational phase of the project, aligning with best practices
for infrastructure design, practices such as the improvement of hydrological data collection, use of
models and monitoring localized effects, more frequent monitoring and maintenance and
improvement of road design to be more climate change resistant are recommended.
In addition, measures to adapt to climate change impacts and minimize impacts to individuals using
Major Mackenzie Drive in the future may include (but are not limited to):
Erosion protection techniques will be developed during detailed design to limit the extent of
channel and bank erosion in the vicinity of the Major Mackenzie Drive crossing of the West Don
River tributary.
Updating plans for weather emergencies, lane closures and rerouting during severe weather
conditions/events, and traveler information systems to include future climate change projections.
As the amount of impervious surface areas will increase, appropriate stormwater capacity should
be considered to mitigate additional runoff, climate change and the likelihood of extreme
precipitation, as described in Section 9.10.
Source Water Protection 10.5
Potential impacts related to the threats described in Section 4.5, along with associated mitigation
measures, are described below.
Stormwater Runoff 10.5.1
The additional impervious surface associated with the roadway improvements (such as the
implementation of a continuous centre left-turn lane and the implementation of a multi-use path)
would reduce the amount of groundwater infiltration from the surface. To offset these impacts and
balance water quantity, the stormwater management strategy described in Section 9.10 recommends
the runoff be conveyed to the proposed roadway storm sewer systems and discharge directly into a
natural watercourse (wetland/West Don River tributary) or to the existing storm sewer systems south
of Major Mackenzie Drive.
The Application of Road Salt 10.5.2
Additional road salt associated with winter maintenance for the proposed roadway improvements
(such as the implementation of a continuous centre left-turn lane) may increase impacts to source
water protection areas. Consistent with best management practices and as suggested in the Clean
Water Act policies, York Region has developed a Salt Management Plan (2004) that ensures
effective winter maintenance for the safety of all roadway users while striving to minimize the amount
of salt entering the environment and at the same time meeting Provincial legislation related to road
maintenance standards for winter services.
The Storage of Snow Related to Roadway Clearing Operations 10.5.3
Although the proposed roadway improvements will result in additional areas to be maintained in the
winter (such as the implementation of a continuous centre left-turn lane and the implementation of a
multi-use path), the study area is not in close proximity to municipal wellheads or surface water
intakes. As such, snow storage in the boulevards is not anticipated to result in a serious threat to
source water protection areas.
In addition, York Region developed a Salt Management Plan (2004) that reduces the amount of salt
that is applied during winter maintenance activities, and therefore reduces the amount of salt present
in roadside snow banks. The stormwater management strategy (described in Section 9.10)
addresses other contaminants that may be present in roadside snow banks.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 85
Key Agency Comments 10.6
Key comments and requirements from agencies are outlined in the following sections. Details are
provided in the key correspondence in Appendix B,
Ministry of the Environment, Parks and Conservation (MECP) 10.6.1
MECP provided input throughout the study. MECP provided direction on the design approach with
regards to environmental factor areas such as ecosystem protection and restoration, surface water,
air quality, servicing and facilities, contaminated soils, and mitigation and monitoring. In particular:
All heritage features should be identified and described in detail to assess potential impacts and
to develop appropriate mitigation measures. MECP recommends further consultation with MNRF,
DFO and local conservation authority to determine if additional study will be required to preserve
these features. In addition, project team may consider the provisions of the Rouge Park
Management Plan.
Quality and quantity measures to treat stormwater runoff should be considered for all new
impervious areas and, where possible, existing surfaces. The ministry’s Stormwater Management
Planning and Design Manual (2003) should be referenced in the ESR and utilized when designing
stormwater control methods.
Potential impacts to groundwater-dependent features should be addressed. Any changes to
groundwater flow or quality from groundwater taking may interfere with the ecological processes
of streams, wetlands, or surficial features. Any potential effects should be identified, and
appropriate mitigation measures should be recommended.
The ESR should consider the potential impacts of adverse air quality and increased noise levels
during the operation of the undertaking due to potentially higher traffic volumes resulting from this
project. The proponent should explore all potential measures to mitigate significant noise impacts
during the assessment of alternatives.
As the removal and movement of soils may be required, appropriate tests to determine
contaminant levels from previously land uses or dumping should be undertaken. If the soils are
contaminated, the proponent will refer to Part XV. 1 of the Environmental Protection Act (EPA)
and Ontario Regulation 153/04: Records of Site Condition which details the requirements related
to site assessment and clean up.
Activities involving the management of excess soil should be completed in accordance with
MECP’s current guidance document titled “Management of Excess Soil – A Guide for best
Management Practices” (2014) available online
Design and construction reports and plans should be based on a best management approach that
centres on the prevention of impacts, protection of existing environment, and opportunities for
rehabilitation and enhancement of any impacted areas. Contractors must be made aware of all
environmental considerations so that all environmental standards and commitments for both
construction and operation are met.
Toronto and Region Conservation Authority (TRCA) 10.6.2
TRCA provided comments and worked closely with the project team throughout the course of the
study. TRCA provided direction on the design approach at the watercourse crossings. Direction
included:
Support for replacing the existing culvert at West Don River due to poor physical condition.
Request to consider wetland water balance.
Request to consider tree removal and compensation strategy on the existing natural heritage
system.
Request to consider opportunity to improve the channel at the West Don River Crossing and to
improve fish passage.
TRCA recommended carrying out hydraulic assessment, meandering belt assessment, fluvial
assessment as part of the ESR.
During detailed design, TRCA suggests consideration for the use of a soil trench system in the
median or boulevard, to address water quality and quantity control.
City of Vaughan 10.6.3
The City of Vaughan provided input throughout the study. The City requested the accommodation of
cyclist and pedestrian along the Study Area and further requested that active transportation facilities
and connections east and west of the corridor, as well as potential connection to/from Major
Mackenzie Drive to a potential future recreational trail adjacent to West Don River, be reviewed
during detailed design in consultation with City staff.
Throughout the project, the City indicated its desire to maintain the existing roadway width, protect
the large street trees and replicate the Maple streetscape character.
The City expressed concerns regarding the scope of the EA. It was clarified that this EA study is
being conducted to improve traffic operations – specifically access to properties on the north and
south sides of the street – in the short-term (2020 horizon year). It was emphasized that
improvements to increase capacity were not being considered. A larger EA, considering capacity and
multi-modal improvements will be done in the future, however the timing of this EA is not known.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 86
11 Timing of Implementation and Future Commitments
Project Schedule 11.1
As part of the Environmental Assessment process, this Environmental Study Report is to be filed and
placed on the public record for at least 30 calendar days for review by the public and review
agencies.
After the review period, provided that no Part II Orders are received, the Region may proceed to
Phase 5 of the Class EA process – design and construction. Property acquisition and utility relocation
will then be scheduled, followed by construction.
Lapse of Time 11.1.1
According to the Municipal Class EA, “If the period of time from the filing of the Notice of Completion
of ESR in the public record or the MECP’s denial of a Part II Order request(s), to the proposed
commencement of construction for the project exceeds ten (10) years, the proponent shall review the
planning and design process and the current environmental setting to ensure that the project and the
mitigation measures are still valid given the current planning period. The review shall be recorded in
an addendum to the ESR which shall be placed on the public record.”
Notice of Filing of Addendum shall be placed on the public record with the ESR, and shall be given to
the public and review agencies, for a minimum 30-day public review period. The notice shall include
the public’s right to request a Part II Order during the 30-day review period. If no Part II Order request
is received the proponent is free to proceed with implementation and construction.
Commitments for Future Work 11.2
The ESR identified specific items to be reviewed and confirmed during detailed design. Some of
these commitments will address specific concerns raised by property owners and review agencies
during the EA process. Items of particular interest to be addressed are outlined in the subsequent
section.
Property Requirements 11.2.1
Review design opportunities to confirm no property acquisition due to roadway improvement during
detailed design.
Construction easements are required on the north-east quadrant of Major Mackenzie Drive and
Keele Street (where retaining walls are proposed).
Permission to Enter Agreements to be obtained from landowners where access to their property is
required.
Archaeology 11.2.2
Conduct a Stage 2 Archaeological Assessment (AA) at locations possessing archaeological
potential as identified by the Stage 1 AA.
Findings from subsequent archaeological assessments are to be filed with the Ministry of Tourism,
Culture and Sport (MTCS) to obtain clearance for archaeology.
Cultural Heritage 11.2.3
Coordination with City of Vaughan Heritage staff and landowners regarding mitigation strategies
for the preferred design in the Village of Maple Heritage Conservation District.
Noise 11.2.4
No need for noise mitigation measures was identified through the Noise Impact Assessment found
under Appendix R.
All property owners should be notified prior to construction and in advance of work related to their
access.
Construction noise control measures are to be included in contract documents where applicable.
Contract specifications should include provisions to define the allowable work hours, in
accordance with local ordinances and municipal noise by-laws, to minimize impacts to the
adjacent landowners in the evenings.
Natural Environment 11.2.5
Some trees within the study Area are of suitable size, have loose bark, cavities, and/or are
species to potentially provide habitat opportunities (day-roosts) for provincially endangered bat
species (Northern Myotis, Little Myotis and Tri-coloured Bats). Although the potential to result in
harm (interference or removal of trees) to SAR bat habitat is low, consultation with MECP and
MNRF is recommended during detailed design to confirm the avoidance window approach and
the specific time period for the protection of Species at Risk bats.
This project will involve the movement and/or removal of soils. Excess soil will be managed in
accordance with the MECP's current guidance document titled “Management of Excess Soil – A
Guide for Best Management Practices” (2014).
Tree protection measures for streetscape trees will be required. Upon receiving the necessary
approvals and prior to the commencement of tree removals, areas designated for tree
preservation are to be delineated on site in accordance with the street tree protection plan and
provided on design drawings developed during the detailed design phase of the project. Roadway
Design
No impacts due to grading and retaining systems impacts
Active Transportation Facilities 11.2.6
Material type and treatment for multi-use path and sidewalks to be confirmed.
From McNaughton Road / Avro Road to Keele Street
December 20, 2018 | 87
Multi-use path treatment at intersections and across driveways to be confirmed during detailed
design.
North and south connections to the future trail West Don River tributary trail to be reviewed during detailed design in consultation with City of Vaughan staff.
Streetscaping and Landscaping 11.2.7
Streetscaping opportunities as identified in the preliminary designs are to be confirmed. The
Streetscaping Plan found in Appendix P is to be finalized during detailed design.
Geotechnical and Pavement Design 11.2.8
Additional geotechnical investigation for the culvert replacement is to be undertaken separately as
part of the West Don River culvert replacement detailed design.
Streetscape enhancements proposed by the City of Vaughan per the Village of Maple Heritage
Conservation District Plan will have to be coordinated with York Region at the Detailed Design
stages of the project. As these enhancements are not a regional standard, they are eligible for
partnership funding through York Region’s Municipal Streetscape Partnership Program.
Groundwater, Hydrogeology, Drainage and Stormwater Management 11.2.9
The West Don River culvert replacement will be undertaken as a separate EA and all the
permitting and approvals related to the water crossing will be done independently.
Water Quality treatment will be provided to offset, as a minimum, the increase in roadway
pavement area as a result of roadway widening. Options including the use of OGS units for
treating drainage from existing pavement are proposed.
Additional water quality control measures including Low Impact Development (LID) strategies are
to be reviewed during detailed design.
Detailed design to explore options to provide additional water quality treatment without
encroaching on the wetland, such as moving the outlet back from the wetland.
Environmental compliance Approval (ECA) will be required from MECP for stormwater
management facilities and storm sewers.
TRCA review and approval is required for all works related to drainage alterations and stormwater
management that discharges to West Don River.
Utilities 11.2.10
Location of existing utilities and resulting impacts and required relocations are to be confirmed
during detailed design including Rogers, Enbridge Gas, Alectra and Bell.
Coordination of utilities, including hydro pole relocation and overhead wiring, is to be reviewed
during detailed design.
Constructability, Staging and Detours 11.2.11
During detailed design, a traffic detouring strategy should be developed to provide motorist with
alternative routes around the construction zone. The plan should also address how access to all
properties along Major Mackenzie Drive will be maintained at all times.
The reconstruction should be staged to maintain both local and through traffic within the study
area to the extent possible, and minimize disruptions. Minimum of one lane in each direction
including an artillery lane for turning movement should be maintained at all times during
construction.
The culvert replacement at the West Don River tributary is being undertaken separately as a
schedule “A” EA and any anticipated road staging and detour consideration will be determined
during culvert replacement detailed design.
Additional Consultation and Coordination 11.2.12
Consult with affected property owners including those where access to their property will be
impacted.
Consult with regulatory agencies and individual municipalities as required.
Coordinate with City of Vaughan as required.
Coordinate with Aboriginal Groups as required.
Summary of Anticipated Permits and Approvals 11.2.13
Given that the culvert replacement will be undertaken as a separate EA, all the permitting and
approvals will be done independently. TRCA permit under Ontario Regulation 166/06 –
Development, Interference with Wetlands and Alterations to Shorelines and Watercourses will be
obtained separately. Environmental Compliance Approval (ECA) will be required from MECP for
stormwater management facilities and storm sewers.
Permission to Enter Agreements. Obtain clearance for archaeology from the Ministry of Tourism,
Culture and Sport based on findings from subsequent archaeological assessments.
Timing of Improvements 11.3
The Major Mackenzie Drive EA study is not currently identified in York Region’s 10-year Capital
Construction Program (2018-2027). Subject to approval of the Environmental Assessment, the timing
of construction will be confirmed through the Region’s project prioritization process. The capital
construction program is reviewed annually and projects may be advanced (or deferred) subject to
other regional priorities and available funding.
As this study focuses on the short-term (2020) operational needs and opportunities of the corridor, a
future EA study will assess the long-term transportation needs, including capacity improvements. The
future EA will be undertaken on the basis of the recommendations/findings of the York Region
Transportation Master Plan 25-year outlook and long-term projects.