managing circular debtmowp.gov.pk/mowp/userfiles1/file/capping circular debt...circular debt (cd)...

22
Managing Circular Debt SEPTEMBER 2015

Upload: others

Post on 12-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Managing Circular Debt

SEPTEMBER 2015

Page 2: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Table of Contents

Contents

Executive Summary __________________________________________________________ 1

Strategic Highlights _________________________________________________________ 1

Introduction _________________________________________________________________ 5

History since 2013 __________________________________________________________ 5

Major Contributors to Circular Debt _____________________________________________ 7

Government Objectives and Strategy for Tackling CD ______________________________ 8

Dealing with Sector Inefficiencies ________________________________________________ 9

Technical and Non-technical Losses ____________________________________________ 9

Low Collections by DISCOs from Private and Government Consumers _______________ 10

QESCO and K-Electric Tube-Wells ____________________________________________ 11

Discrepancies in Tariff Regime _________________________________________________ 13

Policy Induced Debt ________________________________________________________ 13

Late Payment Surcharge ____________________________________________________ 14

Delays in Tariff Determination ________________________________________________ 15

Fiscal Requirements and Government Inefficiencies ________________________________ 16

Tariff Differential Subsidy ___________________________________________________ 16

GST Non Refunds _________________________________________________________ 16

Azad Jammu and Kashmir (AJ&K) ____________________________________________ 17

FATA ___________________________________________________________________ 18

Page 3: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Table of Tables

Table of Tables

Table 1: Year on Year Circular Debt Flows (FY 2015-2018) ....................................................... 2

Table 2: Year on Year Circular Debt Stock (FY 2015-2018) ....................................................... 2

Table 3: Quarter on Quarter Circular Debt Flows (FY 2015-2018) .............................................. 3

Table 4: Quarter on Quarter Circular Debt Stock (FY 2015-2018) .............................................. 3

Table 5: Outstanding PHCL Debt ................................................................................................ 4

Table 6: Flow Buildup Scenarios ................................................................................................. 4

Table 7: Comparison of Losses in FY2014 and FY2015 ............................................................. 9

Table 8: Expected Reduction in CD Flows From Improved DISCO Performance ..................... 10

Table 9: Plan for Reduction of Government Receivables .......................................................... 11

Table 10: Reduction in CD Flows from QESCO Area and Tube wells ...................................... 12

Table 11: Plan for Reduction of PHCL Debt .............................................................................. 13

Table 12: Flow of CD Resulting from Policy Induced Debt Costs.............................................. 13

Table 13: Stock of Policy Induced Debt Service Costs .............................................................. 14

Table 14: Year on Year Stock Position ...................................................................................... 14

Table 15: Expected Reduction in CD Flows From Delays in Tariff Determination .................... 15

Table 16: Impact of AJK Transfer on to Government Budget .................................................... 17

Page 4: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

List of Abbreviations

Abbreviations

ATC Aggregate Technical And Commercial Losses

CPPA Central Power Purchasing Agency

CD Circular Debt

CCI Council of Common Interests

DISCOs Distribution Companies

ECC Economic Coordination Committee

GENCOs Generation Companies

GOP Government of Pakistan

IPP Independent Power Producer

MDT Minimum Determined Tariff

MOWP Ministry of Water and Power

MYT Multi-Year Tariff

NTDC National Transmission & Despatch Company

PHCL Power Holding Company Limited

TDS Tariff Differential Subsidy

IESCO Islamabad Electricity Supply Company Limited

FESCO Faisalabad Electricity Supply Company Limited

LESCO Lahore Electricity Supply Company Limited

QESCO Quetta Electricity Supply Company Limited

GEPCO Gujranwala Electricity Supply Company Limited

MEPCO Multan Electricity Supply Company Limited

PECO Peshawar Electricity Supply Company Limited

TESCO Tribal Electricity Supply Company Limited

HESCO Hyderabad Electricity Supply Company Limited

SEPCO Sukkur Electricity Supply Company Limited

Page 5: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 01

Executive Summary

Executive Summary

Strategic Highlights

The Government of Pakistan (GOP) under a circular debt management plan intends to reduce

circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial

Year Ending June 30, 2018 (FY2018) while keeping within the targets of 0.4% of GDP for

subsidies to the power sector (about Rs. 128 billion) and 4% fiscal deficit. At the end of each

month, the CD will be maintained below the cap of Rs. 314 billion. The circular debt

management plan (or capping mechanism) will include reducing the increase of CD (flow) as

well as the stock (outstanding amount). Policy induced public sector power entity debt

including Power Holding Company Limited (PHCL) debt will be reduced from Rs 335 billion to

Rs 220 billion by FY2018. Public sector power companies’ collections are planned to increase

by 5% by FY2018 and losses are planned to reduce by 1.7% by FY2018 through efficiency

gains, privatization, and private sector participation. Collection from government customers will

be rationalized and subsidies will be on actual basis and paid according to schedule.

GOP will continue to take measures to rationalize the tariff which covers all cost including debt

servicing and ensure sufficient budgetary provision of subsidies for Baluchistan tube-wells,

FATA and AJK consumers. A summary forecast of yearly CD flows and stock in the most likely

case is shown in Table 1 and Table 2 respectively outlining the contributing factors and their

respective contributions. A more detailed quarterly forecast of CD flows and stock for last

quarter of FY2015 and FY2016 in the most likely case is shown in Table 3 and Table 4.

Page 6: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 02

Executive Summary

Table 1: Year on Year Circular Debt Flows (FY 2015-2018)

Flow Summary

Actual Projected

(Rs. In Million)

FY2015 FY2016 FY2017 FY2018

Sector Inefficiencies

Excess line losses

49,937 31950 17,948 10,533

QESCO and K-Electric tube-wells

33,504 2,328 2,377 2,253

Private receivables including FATA

41,058 41,398 25,937 21,280

Discrepancies in tariff regime

Late payment surcharge

8,272 4,971 3,950 1,658

Debt Service for Policy Incurred Debt

22,558 - - -

Delay determinations

10,600 7600 4,560 1,824

Fiscal requirements and government inefficiencies

AJK supplies

15,238 - - -

GST Non Refund

14,296 - - -

Other government receivables

13,831 3,420 1,893 1,454

Total

209,294

91,668 56,664 39,002

Table 2: Year on Year Circular Debt Stock (FY 2015-2018)

Stock Summary

Actual Projected

(Rs. In Million)

FY2015 FY2016 FY2017 FY2018

Sector Inefficiencies

Excess line losses 81,657 96,732 108,430 112,713

QESCO and K-Electric tube-wells

54,688 49,016 43,393 37,646

Private receivables including FATA

43,249 30,647 31,584 30,363

Discrepancies in tariff regime

Late payment surcharge 13,388 1,079 - -

Debt Service for Policy Incurred Debt

34,015 22,203 17,828 13,453

Delay determinations 17,220 11,320 10,880 7,704

Fiscal requirements and government inefficiencies

AJK supplies 24,372 17,872 11,372 4,872

GST Non Refund 22,899 1,899 - -

Other government receivables

22,130 17,551 11,443 4,898

Total

313,618

248,318 234,930

211,649

Page 7: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 03

Executive Summary

Table 3: Quarter on Quarter Circular Debt Flows (FY 2015-2018)

Flow Summary

Estimated Projected

(Rs. In Million)

Q4-FY2015 Q1-2016 Q2-2016 Q3-2016 Q4-2016

Sector Inefficiencies

Excess line losses 11,600

11,006

8,338

6,003

6,603

QESCO and K-Electric tube-wells 7,900

696

500

500

632

Private receivables including FATA 11,820

14,357

10,838

7,729

8,473

Discrepancies in tariff regime

Late payment surcharge 2,089

1,395

1,150

1,118

1,308

Debt Service for Policy Incurred Debt 8,710 - - - -

Delay determinations 2,600

2,000

2,000

1,800

1,800

Fiscal requirements and government inefficiencies

AJK supplies 4,200 - - - -

GST Non Refund 3,899 - - - -

Other government receivables 3,800

1,128

740

648

904

Total

56,618

30,582

23,566

17,799

19,721

Table 4: Quarter on Quarter Circular Debt Stock (FY 2015-2018)

Stock Summary

Estimated Projected

(Rs. In Million)

Q4-FY2015 Q1-2016 Q2-2016 Q3-2016 Q4-2016

Sector Inefficiencies

Excess line losses 81,657 92,663 90,875 93,503 96,732

QESCO and K-Electric tube-wells

54,688 47,384 47,884 48,385 49,016

Private receivables including FATA

43,249 57,606 41,444 35,674 30,647

Discrepancies in tariff regime

Late payment surcharge

13,388 14,783 5,133 852 1,079

Debt Service for Policy Incurred Debt

34,015 30,472 22,203 22,203 22,203

Delay determinations 17,220 19,220 14,470 12,895 11,320

Fiscal requirements and government inefficiencies

AJK supplies 24,372 17,872 17,872 17,872 17,872

GST Non Refund 22,899 1,899 1,899 1,899 1,899

Other government receivables

22,130 15,258 15,998 16,646 17,551

Total

313,618 297,156 257,779 249,928 248,318

Page 8: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 04

Executive Summary

Expected Sale Proceeds: The expected sale proceeds will be used/adjusted to pay off

principal amount of PHCL debt.

The amount of outstanding PHCL debt after principal repayments from privatization proceeds

will be as follows:

Table 5: Outstanding PHCL Debt

Stock Summary Actual Projected

(Rs. In Million) FY2015 FY2016 FY2017 FY2018

Policy induced Public Sector Power Entity Debt

335,000

335,000 272,500 220,000

Privatization may envisage that if any write-offs are required then they may be handled with the

advice of Financial Advisors (FAs) and would take care of outstanding liabilities of the

company.

We have examined various scenarios for flow buildup. The most likely scenario is as follows:

Table 6: Flow Buildup Scenarios

Scenarios - Flow Buildup Projected

(Rs. In Million) FY2016 FY2017 FY2018

Likely Scenario 91,668 56,664 39,002

Page 9: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 05

Introduction

Introduction This working paper addresses the CD issue in the Pakistan power sector and describes a

mechanism to: (i) maintain a cap of Rs. 314 billion1 on the CD (ii) reduce circular debt from Rs.

314billion (as of end June 2015) to Rs 212 billion by FY2018 and (iii) reduce PHCL debt from

Rs 335 billion to Rs 220 billion by FY2018. CD is the amount of payables within the Central

Power Purchasing Agency (CPPA) that it cannot pay to power generation companies

(Independent Power Producer (IPP), government owned thermal generation companies

(GENCOs), the hydropower producer (WAPDA Hydel) and National Transmission & Despatch

Company (NTDC). The revenue shortfall cascades through the entire energy supply chain,

from electricity generators to fuel suppliers, refiners, and producers; resulting in a shortage of

fuel supply to the GENCOs and IPPs and thereby reduce power generation and thus increase

in load shedding.

History since 2013

CD first emerged in FY 2007 as an outstanding overdue liability to power supply companies

(GENCOs, IPPS and their fuel suppliers). The tariffs determined by NEPRA were increased

while government notified customer tariffs were not raised to the same level. Tariff differential

subsidies, the difference between these two tariffs, were not paid in a timely manner

exacerbating the financial situation of the power sector while the increasing dependence on

imported fuel and its rising cost multiplied the effect. Since that time, CD has restricted

utilization of the power sector in Pakistan, suppressing utilization of existing generation

capacity as well as investment in new capacity. Issues related to litigation with power

producers, and non-payment on several accounts to power generation companies are

attributable to this phenomenon. Various governments have tackled or tried to tackle the issue

of CD. Most of these efforts were restricted to injection of cash into the sector to ease the

liquidity crunch that was the result of CD. The standalone approach of cash injection gave only

1 This is the gross amount of payables owed to power generation companies and National

Transmission Despatch Company (NTDC) including the due and overdue amounts at the end of each month. The end of month figure is quoted in this paper because it is a close approximation of over dues.

Page 10: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 06

Introduction

a temporary relief, and the issue emerged again with larger impact. The reforms attempted did

not have the full intended effect.

The current government has adopted a different approach. When it took charge in May 2013

the CD stood at Rs. 503 billion. Power sector entities were at the brink of financial collapse and

the entire sector was touching levels of financial meltdown. The logical approach was to

immediately ease the liquidity crunch. That was done through a cash injection of Rs. 480

billion. But the issue was not left at this level. While the sectoral entities were eased of the

financial crunch, parallel diagnostics and analysis were initiated to understand the dynamics

and causes of the buildup of the CD. The outcome of the exercise was to understand the

reasons, their contribution, their solution and a reduction in the buildup and elimination of CD.

The stock of CD, however, continued to accumulate and had reached Rs. 244 billion by July

2014, an average monthly increase of Rs 18 billion compared with the FY 2013 accumulation

of Rs 20 billion per month. In FY 2015 the stock had increased to Rs. 321 billion by November

2014, showing an average addition in the flow of Rs. 15 billion each month. Had this trend of a

monthly Rs. 15 billion increase continued, the CD at the end of March 2015 would have been

Rs. 382 billion. A tariff increase and surcharges which would decrease CD, scheduled in July

2014 were delayed to October 2014 and January 2015.

In December 2014, the CD stood at Rs. 280 billion, Rs. 102 billion less than would otherwise

have accrued, for the following reasons:

i. Merit-Order dispatch of power generation plants reduced the generation cost by

Rs. 21 billion in the months of November and December 2014. Efficient plants

were dispatched first and thus expensive power generated by inefficient GENCOs

was dispatched last.

ii. Vigilant monitoring by the Ministry of Water and Power (MOWP) improved

recoveries of current dues from 86% in November 2013 to 91% in December 2014.

iii. Targets were given to public sector distribution companies (DISCOs) for recovery

of past receivables from both the private and government consumers which stood

at Rs. 5.8 billion in January 2015 and Rs. 5.3 billion in February 2015.

The improvements in transparency of merit order, planned structural reforms to increase

accountability by separating CPPA from NTDC, overseen by a strengthened NEPRA will

support improved performance in the short term. GOP will continue, as owner, to enforce the

terms of NTDC and DISCOs’ performance contracts and report to the public in its regular

Page 11: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 07

Introduction

quarterly monitoring reports. MOWP has introduced a rigorous system for monitoring daily,

weekly and monthly performance under the personal supervision of the Secretary.

In addition the following two factors also reduced the stock of CD during FY 2015:

i. Commercial borrowing of Rs. 25 billion in December 2014 and Rs. 40 billion in

January 2015, which was done through PHCL.

ii. The falling prices of oil reduced the value of electricity lost.

Now the total payables to power generation companies has decreased further and as of end

March 2015, the CD stood at of Rs 279 billion.

History has shown that these measures alone are likely to be insufficient to bring the flows to

zero until the actual performance of all of the DISCOs matches the levels considered by the

regulator to be efficient. Moreover, alternative revenue provisions are needed where DISCOs

cannot recover their costs from tariffs including proper fiscal provisions that cover all subsidies.

Major Contributors to Circular Debt

The major sources and contributors of buildup of CD are as follows.

• Sector inefficiencies

The sector’s inefficiencies stem from DISCOs having higher levels of losses and lower levels of

collections than those allowed by the regulator. Some DISCOs are at or close to the NEPRA-

determined levels of losses and collections. Less well performing DISCOs experience levels of

losses that are up to 5-10% worse than those allowed, and of collections that are up to 20-30%

lower than the 100% recovery assumed by the regulator, as owner of these entities. In FY

2014, sector inefficiencies added Rs. 88 billion to CD and accounted for Rs. 60 billion for FY

2015 up to March 2015.

• Discrepancies in tariff regime

Beside sector inefficiencies noted above, tariffs do not capture the full cost of supply of

electricity. Factors include delay in determination by NEPRA. Until recently the late payment

surcharge charged by IPPs due to late or short payment of invoiced amounts but not allowed to

be collected in the tariff and service of debt incurred to pay for operational inefficiencies

beyond the NEPRA target were also not permitted to be collected in the tariff.

• Fiscal requirements and government performance

Page 12: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 08

Introduction

Some costs are imposed on the DISCOs by virtue of government policy. These include the

subsidy for those who consume less than 300kWh/month. In addition, government has agreed

a special tariff for electricity supply to AJK which does not reflect cost. To compensate, the

government provides subsidies to DISCOs. However, these subsidies are sometimes under

budgeted or provided late which increases the CD. Furthermore, Federal and Provincial

government departments often fail to pay their bills, which adds to the stock of payables,

imposing further costs on the DISCOs. In addition, GST collected by the tax authorities on

unpaid bills is not refunded to the DISCOs, leaving them out of pocket.

Government Objectives and Strategy for Tackling CD

The objective of the GOP is to have a financially self-sustaining power sector to support

economic growth which implies the elimination of the CD. To that end, GOP will pursue the

following strategies:

- Improved Efficiencies. The strategy for improving efficiency is based on a gradual

decrease in the losses and increase in the collections from consumers. Working on the

same strategy, collections have seen an improvement in FY 2015 in the range of

89.2% as opposed to the previous rate of recoveries in FY 2014 of 87%. Losses

stabilized at 18.7% in the same period. The plan for management of CD until the end

of FY 2018 is based on the same strategy and principles.

- Surcharges: Surcharges are levied under Section 31(5) of the Regulation of Electricity

Generation, Transmission and Distribution Act 1997 (the NEPRA Act). Surcharges will

be set at the level that will rationalize subsidies and allow recovery of full cost of supply

of electricity.

- Privatization Receipts: With the majority of DISCOs in the privatization plan of the

GOP, the receipts from privatization will be partially used to reduce/offset the stock of

the PHCL debt and will reduce the need for budget to finance costs that cannot be met

from other revenue sources. The CD management plan is thus dependent on the

privatization of the DISCOs and GENCOs.

Page 13: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 09

Dealing with Sector Inefficiencies

Dealing with Sector Inefficiencies

Technical and Non-technical Losses

The FY2015 tariff determination process was completed in the second week of April 2015

when the last determination of a DISCO was issued. Table 7 shows a comparison of losses

that the regulator has allowed in the determination for each company.

Table 7: Comparison of Losses in FY2014 and FY2015

Description LESCO GEPCO FESCO IESCO MEPCO HESCO QESCO PESCO/ TESCO

SEPCO Total

Allowed Losses (%) FY 2015

11.75% 9.98% 9.50% 9.44% 15.00% 20.50% 17.50% 26.00% 27.50% 15.3%

Actual Losses (% ) FY 2015

10.8% 11.2% 9.1% 9.8% 15.7% 27.9% 23.5% 37.4% 36.5% 18.7%

Allowed Losses (%) FY 2014

9.01% 9.98% 9.50% 9.45% 15.00% 15.00% 18.00% 20.00% 17.00% 13.05%

Action Plan: NEPRA issued the tariff determinations for FY 2014 for most of the DISCOs in

January 2014. Allowed losses for DISCOs for 2013-14 were 13.02% compared to 18.7%. The

5.6% difference between determined loss and actual loss accumulated as CD of Rs 33.6 billion

in FY 2014. The determinations for FY 2015 allowed 15.3% compared with expected losses of

18.70%, narrowing the gap between allowed and actual losses but will still result in

accumulation of CD of Rs. 32 billion due to increase in generation. In the short term there is

little that can be done about the flow because the tariffs have been determined. NEPRA as a

condition of its determinations requires DISCOs to conduct a study on technical losses to

justify the need for increase and to set out future loss reduction initiatives, to be conducted by

independent consultants but the results are unlikely to show an effect until FY2016

determinations. For the purposes of this CD management plan, it is assumed that reductions

in losses will reduce the flow of CD from Rs. 32 billion to Rs. 11 billion as per Table 8.

The privatization program will also be likely to reduce excess line losses, to the extent of the

companies that will be privatized. With expected privatization of three DISCOs in FY2016,

multi-year tariff (MYT) will have been determined instead of annual tariff determinations and

this will give incentivizes to the new owners to improve losses against NEPRA benchmarks; in

any event, the costs of any underperformance will be the responsibility of the new owner. For

the DISCOS not privatized, the surcharge mechanism will still be used to rationalize subsidies

Page 14: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 10

Dealing with Sector Inefficiencies

and recover costs of service. Table 8 shows the expected reduction in flows of circular debt as

a result of this part of the management plan.

Table 8: Expected Reduction in CD Flows From Improved DISCO Performance

Excess Losses (Rs. In Million)

Actual

FY2015 FY2016 FY2017 FY2018

Per Annum Build Up of Flow 31,950 17,948 10,533

Low Collections by DISCOs from Private and Government

Consumers

Collections from private sector in most of the DISCOs have been an issue which contributed to

the buildup of CD. Actual recovery fluctuates between 89-91% for the current financial year,

whereas tariff determinations assume 100%. Low collections have created a shortfall of Rs.

114 billion from private consumers since the clearance of CD in July 2013. This less than

100% collection is more pronounced in the five poorest performing DISCOs namely PESCO,

TESCO, HESCO, SEPCO and QESCO.

Action plan: The plan is divided into three parts. For all five distribution companies,

recoveries will be managed through power rationing. Experience in K-Electric has shown that

this kind of approach can improve collections significantly and quickly. For all DISCOs, the

aggregate technical and commercial losses (ATC) for each feeder will be categorized by feeder

into four: low (<10% ATC), medium (11-20% ATC), high (21-40% ATC) and very high (>40%

ATC). The second part of the plan is to outsource to the private sector collections of bills in

areas where recoveries are weakest, based on the same categorization mentioned in the

preceding paragraph. This will build on experiences in K-Electric, LESCO, MEPCO and

PESCO areas. Tender for further outsourcing in MEPCO, PESCO, TESCO, HESCO, SEPCO

QESCO and MEPCO will be advertised within next three months, with a view to contracts

being in place by the start of November 2015.

The third part will address collection of Federal and Provincial government bills. For all Federal

accounts, MOWP will notify DISCOs that non-payment beyond the billing cycle of 45 days

should result in disconnection, per commercial procedures. MOWP will move a summary to

the Council of Common Interests (CCI) proposing more stringent requirements for Provincial

Page 15: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 11

Dealing with Sector Inefficiencies

departments. It will request CCI to approve 100% deduction at source in the case of non-

payment and disconnection for non-payment beyond normal commercial terms. MOWP will

require DISCOs to take more rigorous action following disconnection, requiring prepayment for

electricity before reconnection is approved.

The Government has already started action of collection from private consumers including

initiation of revenue based load shed mechanism based on feeder wise AT&C losses. If the

recovery is not affected, then the recovery will be ensured through law enforcement agencies

(NAB and FIA) and incentive packages. The rationing system was introduced from August 1,

2015.

Current Portion of Stock: The current portion of stock on the account of government entities

is Rs. 22 billion and will be adjusted to Rs. 5 billion from at-source deductions as well as

improved recoveries during the period FY 2016-FY2018.

Current Portion of Flow: Given that the practice of deducting at source is to be further

strengthened, such that all current billing is either to be covered by payments from Federal and

Provincial agencies, or from source, the flow will reduce to zero as soon as the CCI decision is

implemented. Table 9 shows the plan for reducing government receivables.

Table 9: Plan for Reduction of Government Receivables

Other Government Receivables (Rs. In Million) FY2016 FY2017 FY2018

Yearly Energy Supplies (GWh) 2,080 2,163 2,250

Annual Billing 22,803 25,236 29,083

Per Annum Build Up of Flow 3,420 1,893 1,454

QESCO and K-Electric Tube-Wells

History: There are around 29,000 tube-well customers in QESCO and K-Electric licensed

areas covering Baluchistan. Between 2001 and 2010, tube-well owners were charged a flat

rate of Rs. 4,000 per month/tube-well, which was increased to Rs. 6,000 per customer per

month in 2012. Amounts between Rs. 6,000 and 75,000 per month are shared in the

proportion of 60:40 between the Government of Baluchistan and the Federal Government. The

owner is responsible for all payments above Rs. 75,000 in any one month.

Page 16: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 12

Dealing with Sector Inefficiencies

Action Plan: The customer contribution has been further increased to Rs. 10,000 per

customer per month for initial consumption at the start of FY2016. The balance up to Rs.

75,000 will continue to be covered by the Baluchistan and Federal Governments. Customers

not paying their share either up to Rs. 10,000 or above Rs. 75,000 will be disconnected on

normal commercial terms and will not be reconnected until arrears have been paid and meter

has been installed for the connection. In order to curtail further buildup of flow, supply of

electricity will be limited to billing of Rs. 75,000/tube well/month in QESCO licensed tube-well

areas consequently ensure that flow buildup does not increased more than amounts projected

in Table 10 below.

Table 10: Reduction in CD Flows from QESCO Area and Tube wells

Tube-Wells in QESCO Area

Amounts in Rs. Millions FY2016 FY2017 FY2018

Per Annum Build Up of Flow 2,328 2,377 2,253

Page 17: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 13

Discrepancies in Tariff Regime

Discrepancies in Tariff Regime

Policy Induced Debt

History: Leading up to 2008, DISCOs borrowed for operational costs which NEPRA did not

allow to be recovered through the tariff. This debt is now in the process of being transferred to

DISCO balance sheets in the total amount of Rs. 335 billion. The loans have tenors ranging

from 5 to 7 years with reschedule and rollover options and interest payment rebates if

payments are made promptly. NEPRA continues to disallow the cost of debt service in the

tariff.

Action Plan: The government intends to reduce the PHCL debt from Rs. 335 billion to Rs.

220 billion by end of FY 2018. Principal will be paid from proceeds of privatization of power

sector assets. To the extent possible privatization receipts will be used to cover the full

outstanding amount. The projected reduction is shown in Table 11 below:

Table 11: Plan for Reduction of PHCL Debt

Amounts in Rs. Million FY 2015 FY 2016 FY 2017 FY2018

Balance o/s 335,000 335,000 272,500 220,000

Planned reduction amount - 0 62,500 52,500

Current portion of flow: The amount to be recovered through debt servicing surcharge is

estimated at Rs. 30 billion and is sufficient to curtail further buildup of CD on this account. Table

12 shows that with principal repayments of Rs. 0, Rs 62.5 billion and Rs. 52.5 billion in

FY2016, FY2017 and FY2018 respectively, the accrued mark-up on outstanding loans will

decrease from Rs. 30 billion in FY2016 to Rs. 20 billion in FY2018. The surcharge will be

adjusted periodically to ensure complete elimination of flow on account of debt servicing cost

beginning FY2016. The debt servicing amount is dependent on many factors including interest

rate and utilization of privatization proceeds and therefore adjustments will be made on an

annual basis to meet zero flow target for each year.

Table 12: Flow of CD Resulting from Policy Induced Debt Costs

Policy-Induced Debt (Rs. In Million) FY2016 FY2017 FY2018

Page 18: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 14

Discrepancies in Tariff Regime

PHCL Loans Outstanding

335,000 272,500 220,000

Markup on Outstanding Loans

30,150 24,225 19,800

Total Units Available for Sale (Gwh) 79,924 85,498 93,087

Privatization Proceeds to Pay PHCL Loans 0

62,500

52,500

Total Amount of Build Up

30,150 24,525 19,800

Amount Recovered Through Surcharges (adjusted for life line

and non-recoveries) 30,150 24,525 19,800

Per Annum Build Up of Flow 0 0 0

Stock of Debt: The total year-on-year outstanding CD stock after taking into account

surcharge payments attributable to debt service will be reduced in the annual increments

shown in Table 13 below.

Table 13: Stock of Policy Induced Debt Service Costs

Amount in Rs. Millions Actual Projected

FY2015 FY2016 FY2017 FY2018

Policy Induced Debt Service 34,015 22,203 17,828 13,453

Late Payment Surcharge

History: Another cost not considered by the regulator while determining the cost of service is

the late payment interest (Kibor + 4%) imposed by the IPPs as per their power purchase

agreements. It becomes due if payments for capacity or energy components are below

invoiced amounts. Since the sector recoveries are to the tune of 89.2% from consumers, IPPs

have often received short payments. For FY2015 the regulator has allowed the cost of late

payment surcharges to be recovered from the consumer tariff. An estimated Rs. 13.0 billion of

the stock of CD remains to be recovered.

Action plan: Taking into account buildup of flow as well as stock settlement, year on year CD

figures will be as shown in Table 14.

Table 14: Year on Year Stock Position

Actual Projected

Rs. In Million FY2015 FY2016 FY2017 FY2018

Late Payment Surcharge 13,388 1,079 - -

Page 19: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 15

Discrepancies in Tariff Regime

Current portion of flow: Owing to the regulatory change, it is expected that by FY2017, there

will be no or minimum flow of late payment surcharge.

Delays in Tariff Determination

History: Delays in the annual tariff determination for DISCOs stem from late submission of

tariff petitions by DISCOs and the time it takes for NEPRA to conduct the determinations. The

slow determination process has been made worse by poor quality petitions, the one-year tariff

cycle and the need for all determinations to be conducted at once which has effectively

resulted in the need to go at the pace of the slowest.

Action plan: The privatization program in which three DISCOs will be privatized in FY2016 is

expected to reduce the problem because the cost of delays is shifted to the new owner which

should be better positioned to manage the regulatory delay. Over the plan period seven

DISCOs will be privatized. In addition by the end of the plan period, all DISCOS will have

shifted to the MYT procedure, with the first three to five Discos expected to move in the first

year. The MYT procedure reduces the workload in NEPRA in the longer run, thus allowing

faster determinations, and in intermediate years adjustments to tariffs are formula-based and

thus do not require lengthy determination periods.

For its part, GOP will increase its supervision of those DISCOs it continues to own to ensure

that they are prompt in submitting tariff petitions and are responsive to any further

requirements of NEPRA.

Flows: A residual flow of about Rs. 1.8 billion is expected to remain from delays in tariff

determination and it will be reduced as shown in Table 15. Late determinations can have a

positive or a negative effect. A delay when costs are falling will bring forward revenues when

costs are rising they will defer revenues. The flow projections in this plan assume rising costs

of generation.

Table 15: Expected Reduction in CD Flows From Delays in Tariff Determination

Delay in Determinations (Amount in Rs. Millions) FY2016 FY2017 FY2018

Delay in Determinations-Current Flow Build Up Per Annum 7,600 4,560 1,824

Per Annum Build Up of Flow Through Policy Actions 7,600 4,560 1,824

Page 20: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 16

Fiscal Requirements and Government Inefficiencies

Fiscal Requirements and Government Inefficiencies

Tariff Differential Subsidy

History: Late payment of subsidies impacts buildup of CD. Subsidies which are under

budgeted or where the budget amounts are breached due to external factors like court cases,

add to the buildup of CD. It is government policy to focus tariff differential subsidy (TDS) on

residential connections consuming up to 300 kWh/month which now account for about 76% of

the TDS and for which GOP intends to budget fully.

The balance of the TDS has historically been used to maintain uniform tariff for all DISCOs and

the NEPRA determined average tariff cannot be reached unless surcharges are allowed.

NEPRA does not allow for charging of tariff above the determined tariff. Thus under uniform

tariff, only the minimum determined tariff can be charged. Without the surcharge, the tariff

differential subsidy increases.

Action Plan: The government intends to shift the cost of the uniform tariff from the TDS

budget. For all tariff categories where subsidies are zero, an equalization surcharge has been

levied the proceeds of which are used to fund the uniform tariff policy. The surcharges are

consolidated into a “Universal Obligation Fund” to cross subsidize those DISCOs who have

determined tariffs above the uniform tariff.

Flow: The government is committed to fully budget for the TDS, including any amount that

may be needed until surcharges for the Universal Obligation Fund can be reinstated. There

will thus be no incremental flow to the CD from this source.

Stock: There is no stock of CD attributable to late or non-payment of TDS.

GST Non Refunds

GOP levied Tariff Rationalization Surcharge in order to meet the NEPRA Determined Revenue

Requirement of DISCOs by reducing the budget of Tariff Differential Subsidy within the limit of

0.3% of GDP. The levying of surcharges will also increase the tax revenue of Federal

Government as sales tax is applicable on the amount of electricity cost billed to consumer

Page 21: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 17

Fiscal Requirements and Government Inefficiencies

under Rules 14 (CHAPTER III) of Sales Tax Special Procedures Rules, 2007 for Collection and

Payment of Sales Tax on Electric Power.

With the application of sales tax on the amount of tariff rationalization surcharges billed by

DISCOs to consumers, the amount of output tax will increase accordingly as compared to the

input tax charged on the cost of electricity by CPPA (G) which would then result in a

decreasing trend of circular debt stock from FY 2016 to 2018. Further, any variation in the fuel

price is a pass through item and any adverse variation in cost of power purchase is recovered

from consumer along-with sales tax as fuel price adjustment that also ensure recovery of

increase in input cost from consumer as output tax.

Azad Jammu and Kashmir (AJ&K)

History: AJ&K receives power in bulk from three distribution companies: IESCO, PESCO and

GEPCO. Currently AJ&K is paying Rs. 2.59/kWh against the GOP notified tariff of Rs.

11.87/kWh and the NEPRA determined tariff of Rs. 14.38/kWh. The concessional power tariff

of Rs. 2.59/kWh for AJ&K tariff was determined by a subcommittee constituted under the

Mangla Raising Agreement signed between Government of AJ&K and GOP in 2003. As of

June 2015, AJ&K’s portion of stock is Rs. 24.4 billion to the total stock outstanding of Rs. 314

billion. In terms of flow, per annum build up on account of flow is Rs. 15.2 billion per annum or

Rs. 1.3 billion per month. To stop increase in the flow of CD on account of AJ&K, two options,

are under consideration. One option considers the possibility of lowering the supply and the

other of increasing revenues from consumers; a combination of the two is also possible.

If neither option resolves the difference between AJ&K tariff and NEPRA determined tariff,

GOP will pick up any remaining balance. It will make necessary budgetary adjustments in tariff

cycle of FY 2016 which will completely eliminate buildup of flow of CD on account of AJ&K.

The analysis in this paper has been made conservatively - on an assumption that in cases

where options A and B fail, GOP will have to pick the entire flow on account of AJ&K. With

AJ&K’s consumption steady in the range of 1400GWh per annum, the per annum impact on

account of additional GOP support to AJ&K will range from Rs.12.8 to Rs. 13.7billion per

annum. Table 16 shows the impact under this worst case.

Table 16: Impact of AJK Transfer on to Government Budget

AJ&K (Rs. In Million) FY2016 FY2017 FY2018

Number of Units Sold from Mangla (Gwh) 8,000 8,000 8,000

Number of Units Sold to AJK (Gwh) 1,469 1,469 1,469

Page 22: Managing Circular Debtmowp.gov.pk/mowp/userfiles1/file/Capping Circular Debt...circular debt (CD) from Rs. 314 billion (as of end June 2015) to Rs. 212 billion by Financial Year Ending

Pg. 18

Fiscal Requirements and Government Inefficiencies

NEPRA Determined Tariff (Rs./kWh) 11.54 11.98 12.65

AJK Consumer Tariff under Mangla

Agreement 2.84 3.09 3.34

Difference between NEPRA and AJK

Determined 8.70 8.89 9.31

Subsidy Per Annum (Rs. Million) 12,779 13,060 13,673

Subsidy from Federal Budget 100% 100% 100%

Subsidy from Federal Budget (worst

case) 12,779 13,060 13,673

Remaining Amount - - -

Per Annum Build Up Flow - - -

FATA

History: GOP has split out Tribal Electricity Supply Company Limited (TESCO) from the

original company PESCO to determine its billing and subsidy requirements. TESCO is now an

autonomous DISCO and manages its operations independently in that area. GOP policy is

that the residential consumers of FATA should receive free electricity and hence, although

there are tariffs determined and notified for all consumer categories, Federal Government

budgets a subsidy to cover the cost of the residential consumers. FATA receivables are

included within the private receivables category.

Action Plan: The government has decided to revisit its policy of provision of unlimited free

electricity to residential consumers. It will ration electricity up to the quantity matching the

budgeted subsidy. If collections can be improved, more electricity will be provided. Since most

of the TESCO’s billing is domestic consumers (90%) and are entirely subsidized by the GOP,

efforts will be made to recover 25% of the billing from TESCO consumers while the remaining

75% will be budgeted by the Federal government and paid for on behalf of consumers. Non-

recoveries in FATA are projected at PKR 14.2 – 17.5 billion over FY16-18