Mandy BauldERCOTOctober 9, 2012

RTM SETTLEMENT TIMELINE

Page 2: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

2

Why are we talking about this?

– Multiple parties are interested in reducing the RTM Settlement timeline to help• Reduce collateral requirements

• Reduce risk of uplift

– The NPRR347 and NPRR391 invoicing and payment timeline changes shortened the total billing cycle by ~10-13 days

– Previous efforts made minimal change to the timeline for posting the RTM Statement

Page 3: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

3

Refresher – Current Settlement Timelines

Day-Ahead Market Real-Time Market

Statement Post Date OD + 2 OD + 9

Invoice Post Date OD + 2 OD + 14 to 24

Invoice Due Date OD + 5 OD + 21 to 30

Invoice Payout Date OD + 6 OD + 22 to 31

Invoice Frequency Business Daily Weekly

Current Protocol Requirements:

Day-Ahead Market Real-Time Market

Statement Post Date OD + 2 OD + 9

Invoice Post Date OD + 2 OD + 9

Invoice Due Date OD + 4 OD + 11

Invoice Payout Date OD + 5 OD + 12 to 18

Invoice Frequency Business Daily

After November 2012 Implementation (NPRR347 & NPRR391):

Note: The timelines are stated generally in relation to the Operating Date and do not reflect all variations due to holidays and bank holidays.

Page 4: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

4

High-Level Considerations

The existence and magnitude of the impacts mentioned below depends entirely on the extent of the reduction to the settlement timeline

Quality of Market Settlements – Potential impacts to data availability and accuracy:

• Unavailable input data• Inability to perform manual settlement calculations• Minimized data validation• Limited time for issue resolution

Staffing Impacts– Potential impacts to support weekend and holiday workloads and/or to execute existing functions

in shorter period of time

Page 5: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

5

Data Considerations

Increasing availability of AMS data is not the only data consideration. Various types of data is required for RTM settlements:

–Load Data• Usage is estimated if not available for use in the initial Data Aggregation process (OD + 7)• Approximately 70% of August 2012 initial settlement load was based on actuals• AMS (40%), Competitive IDR (24%), NOIE (26%), and NIDR (10%) all need to be considered

–Generation Data• Current processes strive to have the data available for use in the initial Data Aggregation process (OD+7)• ERCOT performance indicators require no more than 1% change after initial settlement

–Markets & Operations Data• Current processes complete the transfer data to the settlement system by end of day on OD+1. • Prices are not considered final until 1600 of the next Business Day after the Operating Day (6.3 (4))• Energy trades can be entered as late as 1430 on OD +1 (4.4.2(3))

–Manual Calculations or Data changes• Utilize upstream data and complete prior to use in settlement (OD+8)• Examples include: emergency energy settlements (manual overrides, QSGR dispatch, SCED failure),

processing VDIs, processing price corrections, and other ad-hoc data correction

Page 6: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

6

RTM Settlement Timeline

What’s next?– CWG quantifying the credit benefit– Request COPS to determine its next step.

• As a starting point, COPS may want to consider efforts to:

– Review the benefits described by CWG

– Define the scope of the effort

» Commissioner Anderson stated interest in a “material reduction” to the timeline. CWG is discussing an option of OD+3. Suggest that analysis includes discussion of an OD+3 option so that we are prepared with a specific response regarding considerations and feasibility of this option.

» Identify the availability timelines for all data and any opportunity for improvements (TAC discussion)

– Define guiding principles

– Define options

– Identify and document the impacts of each option on each segment (people, processes, technology)

– Develop a recommendation

• ERCOT can help facilitate the COPS effort and documentation of the findings

• Other?

Page 7: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

7February 10, 2009

APPENDIX

Page 8: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

8

Data Considerations

Type % of ERCOT Load*

% Availableon initial

settlement*

Interval Basis

Data Typically Settlement-

Ready

ASSUMPTIONS about Impacts and Challenges

AMS 39.6% 39.3% 15-min +4 to+6 - A reduced timeline would narrow the window for data submission , and correction if necessary, for use on initial settlement.

- Experience indicates that TDSPs target complete and accurate data submission for use on initial settlement.

- TDSPs – what would be the impact to maintain similar levels of actual data on initial settlement? Would there be impact to staffing or business processes on weekends and/or holidays?

COMP_IDR 23.9% 3.8% 15-min Monthly - Submittal based on TDSP monthly read cycles. Shortening the timeline will reduce available data based on the TDSP monthly read cycles.

NOIE 26.5% 24.8% 15-min +6 - A reduced timeline would narrow the window for NOIE data activities prior to use on initial settlement.

- Experience indicates that NOIEs target complete and accurate data submission for use on initial settlement.

- NOIEs – what would be the impact to maintain similar levels of actual data on initial settlement? Would there be impact to staffing or business processes on weekends and/or holidays?

NIDR 10.0% 1.7% Monthly Monthly - Submittal based on TDSP monthly read cycles. Shortening the timeline will reduce available data based on the TDSP monthly read cycles.

- NIDR represents a decreasing share of the ERCOT load, but assuming that NIDR will not drop to a 0% share

Total 100% 69.6%

Load Data Availability

* Percentages reported for August 2012

Page 9: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

9

Data Considerations

Generation Data Availability% Accurate and

Complete on Initial Settlement

(target and stretch KPIs)

Data Received

VEE Complete

and Issues Resolved

Data Used in

Settlement

ASSUMPTIONS about Impacts and Challenges

ERCOTPolled Settlement Meters

99% - 99.9% +1 +6 +7 - To maintain similar standards of data availability and accuracy on initial settlement, it is reasonable to assume that there may be ERCOT staffing impacts to execute business processes on weekends and/or holidays.

- TDSPs - what would be the impact to maintain similar standards of data availability and accuracy on initial settlement? Would there be impact to staffing or business processes on weekends and/or holidays?

Page 10: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

10

Data Considerations

Settlement CalculationsASSUMPTIONS about Impacts and Challenges

Accuracy on initial settlements - Current systems and processes transfer markets and operational data to the settlement system at various times through the day after the Operating Day. Timelines for upstream data availability and integration into the settlement system will be a limiting factor. Impact to integration activities would be relative to the magnitude of the reduction of the timeline.

- Certain settlement activities are handled on a manual basis prior to initial settlement. Examples of such processes that may be impacted include but are not limited to: emergency energy settlements for emergency base points or non-economic dispatch on a daily basis, price corrections on an ad-hoc basis, or data integration issues on an ad-hoc basis. Impact to settlement accuracy or completeness would be relative to the magnitude of the reduction in the timeline.

- If an additional settlement iteration is incorporated into the settlement schedule, it is reasonable to assume that there may be staffing and procedural impacts to ERCOT.

- QSEs/CRRAH – what would be the impact to support an additional settlement iteration? What is the impact of settlement is not “complete” on the first iteration?

Page 11: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

11

History of Settlement Timeline

Posting Date for Initial Settlement Statements

Effective Period

OD + 3 August 2000 – March 2002

OD + 17 March 2002 – January 2006

OD + 10 January 2006 - November 2011

OD + 9 December 2011 - current

Page 12: Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE

12

Other Markets

– Generally speaking, the FERC-jurisdictional ISOs/RTOs settle to cash clearing within 14 days

– Specific timelines vary across the ISOs/RTOs

http://www.cftc.gov/stellent/groups/public/@requestsandactions/documents/ifdocs/iso-rto4cappfercchart.pdf