5 WEST 125 TH STREET MANHATTAN, NEW YORK Remedial Action Report NYC VCP Project Number: 13CVCP115M OER Project Number: 11EHAN269M Prepared For: CA 5-15 125 TH Street LLC & HARCO Consultants Corporation 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 [email protected] Prepared By: Paul Lageraaen, P.E. 575 Broad Hollow Rd, Melville, NY 11747 (631) 756 - 8000 [email protected] DECEMBER 2016

Upload: others

Post on 25-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 WEST 125TH STREET

MANHATTAN, NEW YORK

Remedial Action Report

NYC VCP Project Number: 13CVCP115M

OER Project Number: 11EHAN269M

Prepared For:

CA 5-15 125TH Street LLC & HARCO Consultants Corporation

511 Canal Street, Suite 400, New York, NY 10013

(212) 924 - 3100

[email protected]

Prepared By:

Paul Lageraaen, P.E.

575 Broad Hollow Rd, Melville, NY 11747

(631) 756 - 8000

[email protected]

DECEMBER 2016

Page 2: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

2

REMEDIAL ACTION REPORT

TABLE OF CONTENTS

TABLE OF CONTENTS ........................................................................................ 2 

LIST OF ACRONYMS .......................................................................................... 7 

CERTIFICATION .................................................................................................. 8 

EXECUTIVE SUMMARY .................................................................................... 9 

REMEDIAL ACTION REPORT ......................................................................... 16 

1.0  SITE BACKGROUND 16 

1.1  SITE LOCATION AND BACKGROUND .................................................... 16 

1.2  REDEVELOPMENT PLAN .......................................................................... 17 

1.3  DESCRIPTION OF SURROUNDING PROPERTY ..................................... 17 

1.4  SUMMARY OF PAST USES AND AREAS OF CONCERN ...................... 17 

1.5  SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL

INVESTIGATION ................................................................................................... 20 

1.6  SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION .............. 20 

2.0  DESCRIPTION OF REMEDIAL ACTIONS 22 

3.0   COMPLIANCE WITH REMEDIAL ACTION WORK PLAN 24 

3.1  HEALTH & SAFETY PLAN ......................................................................... 24 

3.2  COMMUNITY AIR MONITORING PLAN ................................................. 24 

3.3  SOIL/MATERIALS MANAGEMENT PLAN .............................................. 25 

3.4  STORM-WATER POLLUTION PREVENTION .......................................... 25 

3.5  DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN ............. 25 

4.0  REMEDIAL PROGRAM 27 

4.1  PROJECT ORGANIZATION ........................................................................ 27 

4.2  SITE CONTROLS .......................................................................................... 27 

4.3  MATERIALS EXCAVATION AND REMOVAL ........................................ 29 

Page 3: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

3

4.4  MATERIALS DISPOSAL ............................................................................. 33 

4.5  BACKFILL IMPORT ..................................................................................... 33 

4.6  DEMARACTION ........................................................................................... 33 

5.0  ENGINEERING CONTROLS 34 

6.0   INSTITUTIONAL CONTROLS 36 

7.0  SITE MANAGEMENT PLAN 36 

8.0   SUSTAINABILITY REPORT 37 

Page 4: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

4

FIGURES

Figure 1: Site Boundary Map

Figure 2: Site Location

Figure 3: Development Plan

Figure 4: Map of end-point sample locations

Figure 5: Map showing location and approximate depth of excavations

Figure 6: Map of soil/fill reuse and backfill placement locations

Figure 7: Map of location of Composite Cover System

Figure 8: Map of location of Vapor Barrier System

Figure 9: As-built design detail for Vapor Barrier System

Figure 10: Development Plan 2

Figure 11: Elevator Pit Plan

Figure 12: Cellar Level Reflected Ceiling Plan

Figure 13: Foundation Sections and Details

Figure 14: First Floor Reflected Ceiling Plan

Figure 15-18: Exterior Elevation

Figure 19: Foundation Plan

Figure 20-24: Section View

Page 5: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

5

TABLES

Table 1-4: Summary of end-point analytical results

Table 5: List of SCOs

Table 6: Disposal quantities and disposal facilities

Table 7: Backfill quantities and sources

Page 6: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

6

APPENDICES

Appendix A: Remedial Investigation Report

Appendix B: Remedial Action Work Plan

Appendix C: Daily and Monthly Reports to OER

Appendix D: Photographs of Remedial Action

Appendix E: Disposal Facility Approval Letter

Appendix F: Shipping and Disposal Manifests

Appendix G: Disposal Characterization Sample Laboratory Testing Results

Appendix H: End-point sample analytical laboratory data

Appendix I: As-built drawings and documentation for Engineering Controls

Appendix J: Letter to OER from architect

Appendix K: Letter to OER from H2M

Appendix L: Letter to NYCDEP from Kosuri

Page 7: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

7

LIST OF ACRONYMS

Acronym Definition

CAMP Community Air Monitoring Plan

DER-10 NYS DEC Division of Environmental Remediation Technical Guidance Manual 10

EC Engineering Control

HASP Health and Safety Plan

IC Institutional Control

NYC VCP New York City Voluntary Cleanup Program

NYC DEP New York City Department of Environmental Protection

NYC DOHMH New York City Department of Health and Mental Hygiene

NYC OER New York City Office of Environmental Remediation

ORC Oxygen Release Compound

PID Photoionization Detector

QA/QC Quality Assurance/Quality Control

QEP Qualified Environmental Professional

RAR Remedial Action Report

RAWP Remedial Action Work Plan

SCG Standards, Criteria and Guidance

SCO Soil Cleanup Objective

SMMP Soil/Materials Management Plan

SMP Site Management Plan

SVOCs Semi-Volatile Organic Compounds

UST Underground Storage Tank

VOCs Volatile Organic Compounds

Page 8: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125`h StreetRemedial Action Report

December, 2016

CERTIFICATION

I, Paul Lageraaen, certify the following:• I am currently a registered professional engineer licensed by the State of New York.• I performed professional engineering services and had primary direct responsibility for

implementation of the remedial program for the 5 West 125' Street site, site number13CVCP115M. I certify to the following:

• I have reviewed this document, to which my signature and seal are affixed.• The vapor barrier system and composite cover system constructed during this remedial action

were designed by me or a person under my direct supervision and achieve the goals established inthe Remedial Action Work Plan for this site.

• The vapor barrier system and composite cover system constructed during this remedial actionwere professionally observed by me or by a person under my direct supervision and are accuratelyreflected in the text and drawings for as-built design reported in this Remedial Action Report.

• The OER-approved Remedial Action Work Plan dated February 2013 and Stipulations in a letterdated March 20, 2013 were implemented and that all requirements in those documents have beensubstantively complied with. I certify that contaminated soil, fill, liquids or other material from theproperty were taken to facilities licensed to accept this material in full compliance with applicablelaws and regulations.

PE License Number O~ C{ ~!„ ,'1~ tr l,l

Signature "~/ ~/

l

Date /L~/(>/l;✓/ L/

I, Joseph Loesch, certify the following:

I am a Qualified Environmental Professional. I had primazy direct responsibility for implementationof the remedial program for the 5 West 125' Street site, site number 13CVCP115M. I certify to thefollowing:The OER-approved Remedial Action Work Plan dated Februazy 2013 and Stipulations in a letterdated March 20, 2013 were implemented and that all requirements in those documents have beensubstantively complied with. I certify that contaminated soil, fill, liquids or other material from theproperty were taken to facilities licensed to accept this material in full compliance with applicablelaws and regulations.

QEP Name J ~~Iw _ 1 ~{/ ~ S C

QEP Siena[ure

Date /~//~/~

~~

Page 9: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

9

EXECUTIVE SUMMARY

CA 5-15 125TH Street LLC and HARCO Consultants Corporation has enrolled in

the New York City Voluntary Cleanup Program (NYC VCP) to investigate and remediate

a property located at 5 West 125th Street in the Harlem section of Manhattan, New York.

A Remedial Investigation (RI) was performed to compile and evaluate data and

information necessary to develop a Remedial Action Work Plan (RAWP). A remedial

action was performed pursuant to an OER-approved RAWP in a manner that has

rendered the Site protective of public health and the environment consistent with the

proposed use of the property. This RAR describes the remedial action performed under

the RAWP. The remedial action described in this document provides for the protection of

public health and the environment, complies with applicable environmental standards,

criteria and guidance and applicable laws and regulations.

Site Location and Background

The Site is located at 5 West 125th Street in the Harlem section of Manhattan,

New York and is currently identified as Block - 1723 and Lots – 31, 45 and 144 on the

New York City Tax Map. The Site is bounded to the north and south by 126th Street and

125th Street respectively and by abutting commercial buildings to the east and west

beyond which is 5th Avenue and Lenox Avenue, respectively. The Site has an area of

27,500 square feet and prior to redevelopment site was most recently a vacant inactive

construction site that had been excavated to approximately eleven-feet below sidewalk

grade in 2008.

Summary of Redevelopment Plan

The Site has been redeveloped with a new six (6)-story mixed-use commercial

and residential building consisting of three (3) floors and a cellar for retail use, and three

(3) floors for residential use. Mechanical rooms and T.J. Maxx Retail Store are located in

the cellar. The foundation of the building was installed at 17 feet and 6 inches below

surface sidewalk grade (6.5 feet below existing site grade). The elevator installed in the

new development is approximately 20 feet and 6 inches below street grade. No

landscaped or open areas exist on the Subject Property. The building is setback 12’-3”

Page 10: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

10

from the curb on 125th Street and 13’-1” from the curb on 126th Street. The building and

cellar occupies the entire footprint of the lot. A total of 8,070 tons of soil/fill was

excavated and disposed off-Site. Groundwater was encountered during excavation for the

construction of the building cellar and dewatering was required.

The current zoning designation for the Site is R7A. The new use is consistent with

existing zoning for the property.

Summary of Description of Surrounding Property

The surrounding properties along 126th Street are residential with the exception of

a church directly north of the subject property and a self-service laundromat two

properties to the east along 126th street. The surrounding properties along 125th street are

mixed use residential and commercial. The adjoining property to the east along 125th

Street is an Applebee’s restaurant. All other properties along 125th Street consist of first

floor commercial space with residential space in the upper floors. Additionally, two-day

care facilities are identified on the 124th Street within 250-feet of the subject property.

No other sensitive receptors such as hospitals, schools, or daycare facilities were

identified within 500-feet of the subject property.

Summary of Past Site Uses of Site and Areas of Concern

Based upon the review of the Fire Insurance Maps and Regulatory Agency

documents from the Phase I Environmental Site Assessment (ESA) Reports dated August

2008 and prepared by EBI Consulting of Burlington Massachusetts, a Site history was

established. Historic use of the Site included a YMCA and associated dormitories,

residential and commercial buildings. Following the demolition of the YMCA and

associated buildings, the site was redeveloped as a parking lot and residential dwellings,

as shown on the 1951 Sanborn Fire Insurance map. The use of these properties was

consistent through the 1992 Sanborn map. No Recognized Environmental Conditions

(RECs) were identified in the Phase I ESA report.

The AOCs identified for this Site include:

1. Historic fill is present at the Site from grade to a depth ranging from 4 to 21

feet below sidewalk grade.

Summary of the Work Performed under the Remedial Investigation

Langan Engineering & Environmental Services performed the following scope of work at

Page 11: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

11

the Site in May of 2011:

1. Conducted a Site inspection to identify AOCs and physical obstructions (i.e.

structures, buildings, etc.);

2. Completed eight soil borings and collected of two soil samples per boring for

chemical analysis to evaluate soil quality; and

3. Installed and sampled three monitoring wells in order to assess site groundwater

conditions.

Summary of Findings of Remedial Investigation

1. Elevation of the property is approximately 25 feet.

2. Depth to groundwater is approximately 14.5 to 15 feet below sidewalk grade at

the Site.

3. Groundwater flow is generally from west to east beneath the Site.

4. Depth to bedrock is at the Site is approximately 48 to 63-feet below sidewalk

grade.

5. The stratigraphy of the Site, from the surface down, consists of fill overlying

successive strata of sand, silt and clay, glacial till, and rock. The fill layer,

consisting of sand and gravel with brick, concrete, wood, and miscellaneous

debris, was observed throughout the site to depths of approximately 4 to 21-feet

below sidewalk grade. The fill material is underlain by a 6 to 18-foot thick layer

of loose to medium dense fine to coarse sands, followed by silt and clay and an

approximately 6-foot thick layer of glacial till. Bedrock, consisting of a gneiss and

marble, was encountered at depths ranging from approximately 48 to 63-feet

below sidewalk grade.

6. Soil/fill samples collected during the RI showed no detectable concentrations of

PCBs. No VOCs were detected in soil, except for trace levels (2.3 ppb) of

tetrachloroethene in one soil sample. Select SVOCs, all polycyclic aromatic

hydrocarbons (PAHs) including benzo(a)anthracene (4.37 ppm), benzo(a)pyrene

(3.99 ppm), benzo(b)fluroanthene (3.06 ppm), benzo(k)fluroanthene (2.1 ppm),

chrysene (4.22 ppm), and indeno(1,2,3-cd)pyrene (2.17 ppm) were identified in

two of sixteen soil samples at concentrations found above their Track 1

Unrestricted Use and Track 2 Restricted Residential Use SCOs. Pesticides

Page 12: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

12

including 4,4-DDE (0.0214 ppm), 4,4-DDT (0.0814 ppm), dieldrin (0.0064 ppm)

and heptachlor (0.09 ppm) were detected above their Track 1 Unrestricted Use

SCOs in four shallow sample. Several metals including barium, chromium, lead,

mercury and zinc were detected above Track 1 Unrestricted Use SCOs and of

these lead (max. of 606 ppm) and mercury (max. of 0.84 ppm) also exceeded

Track 2 Restricted Residential SCOs in two soil samples. Overall, these results

are consistent with levels of pesticides, SVOCs, and metals found at sites

throughout NYC with historic fill material.

7. Groundwater samples collected during the RI showed no detectable PCBs or

SVOCs. One pesticide, 4,4-DDD was in one of three groundwater samples at

concentrations below NYSDEC Groundwater Quality Standards (GQS). One

VOC tetrachloroethene was detected in 1 groundwater samples at trace levels (1

ppb), below its GQS. Three metals, iron (338 ug/l), manganese (17,300 ug/l) and

sodium (349,000 ug/l), were detected above GQSs in dissolved groundwater

samples.

8. Soil vapor sampling was not conducted because the site was already excavated up

to a depth of 11 feet and groundwater was about one to two feet below grade.

Summary of the Remedial Action

The remedial action achieved protection of public health and the environment for

the intended use of the property. The remedial action achieved all of the remedial action

objectives established for the project and addressed applicable standards, criterion, and

guidance; was effective in both the short-term and long-term and reduced mobility,

toxicity and volume of contaminants; was cost effective and implementable; and used

standards methods that are well established in the industry.

A summary of the milestones achieved in the Remedial Action is as follows: A

Pre-Application Meeting was held on February, 4, 2013 and again on September 17, 2014

with a new consultant team. A Remedial Investigation (RI) was performed from May to

July, 2011. A RI Report was prepared to evaluate data and information necessary to

develop a Remedial Action Work Plan (RAWP). A Site Contact List was established. A

RAWP was prepared and released with a Fact Sheet on February 14, 2013 for a 30-day

Page 13: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

13

public comment period. The RAWP and Stipulation List dated March 20, 2013 was

approved by the New York City Office of Environmental Remediation (OER) on April 2,

2013. A Pre-Construction Meeting was held on April 4, 2013. A Fact Sheet providing

notice of the start of the remedial action was issued on April 2, 2013. The remedial action

was begun in October, 2013 and completed in December, 2015.

The remedial action consisted of the following tasks:

1. Prepared a Community Protection Statement and implemented a Citizen

Participation Plan.

2. Performed a Community Air Monitoring Program for particulates and volatile

organic carbon compounds.

3. Selected NYSDEC Part 375 Track 1 Unrestricted Use Soil Cleanup Objectives

(SCOs).

4. Mobilized site security, equipment, utility mark outs and marking & staking

excavation areas.

5. Performed Waste Characterization Study prior to excavation activities. Eight (8)

soil borings were performed during the Phase II investigation of the Subject

property. Waste characterization soil samples were collected from these borings

on May 26, 2011. Waste characterization samples were collected at a frequency

dictated by disposal facility(s).

6. The following excavations were performed: soil was removed to a depth of 17

feet 6 inches from sidewalk grade beneath the area of the new building (entire

property). No landscaped or open areas exist on the Subject Property. The

building is setback 12’-3” from the curb on 125th Street and 13’-1” from the curb

on 126th Street. The building and cellar occupies the entire footprint of the lot.

Additional excavation occurred to 20.5 feet below sidewalk grade for the

elevator pits. A total of 5,978 cubic yards of soil/fill was excavated and removed

from the property. Excavated 3,638 cubic yards of non-hazardous soil/fill and

transported to Sky Materials located at 4331 Middle Country Road in Calverton,

NY 11933; excavated 160 cubic yards of clean soil and transported to 55 Pearl

Street Brooklyn, NY 11201 utilizing the NYC Clean Soil Bank; excavated 2,180

Page 14: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

14

cubic yards of clean soil and transported to Fresh Kills in Staten Island utilizing

the NYC Clean Soil Bank.

7. Screened excavated soil/fill during intrusive work for indications of

contamination by visual means, odor, and monitoring with a PID.

8. Conducted materials management of excavated materials including temporarily

stockpiling and segregating in accordance with defined material types and to

prevent co-mingling of contaminated material and non-contaminated materials.

9. Appropriately segregated excavated media onsite prior to disposal. Transported

and disposed all soil/fill material at permitted facilities in accordance with all

applicable laws and regulations for handling, transport, and disposal, and the

RAWP.

10. Collected and analyzed end-point samples to determine attainment of SCOs.

Track 2 Restricted Residential SCOs were achieved.

11. As part of development, constructed an engineered Composite Cover System

consisting of 2-feet of concrete slab underlain by #57 Stone. The contractor for

the cover construction was Nova Concrete Contractors.

12. As part of development, installed a Vapor Barrier System that consisted of

Xypex Admix blended concrete mix to waterproof and protect the concrete

poured for the slab and basement walls. Aquifin Vaportight Coat SG2 (30 mils),

an interior applied barrier was also used to prevent capillary infiltration of oil,

Radon, and other gases and chemical from the ground and as a secondary

containment of water vapor. The product was applied to the below grade

concrete foundation walls and cellar floor slab. The contractor for the Vapor

Barrier System construction was Nova Concrete Contractors.

13. Performed all activities required for the Remedial Action, including permitting

requirements and pretreatment requirements, in compliance with applicable laws

and regulations.

14. Implemented storm-water pollution prevention measures in compliance with

applicable laws and regulations.

15. Submitted a Sustainability Report.

Page 15: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

15

16. Submitted a RAR that describes the Remedial Action, certifies that the remedial

requirements defined in the Remedial Action Work Plan have been achieved;

defines the Site boundaries; and describes any changes from the RAWP.

Page 16: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

16

REMEDIAL ACTION REPORT

1.0 SITE BACKGROUND

CA 5-15 125TH Street LLC and HARCO Consultants Corporation has enrolled in

the New York City Voluntary Cleanup Program (NYC VCP) to investigate and remediate

a property located at 5 West 125th Street in the Harlem section of Manhattan, New York.

The boundary of the property subject to this Remedial Action is shown in Figure 1 and

include, in their entirety, Manhattan Block 1723 and Lot(s) 31, 45 & 144. The Remedial

Action was performed pursuant to the OER-approved RAWP in a manner that has

rendered the property protective of public health and the environment consistent with its

intended use. This RAR describes the remedial action performed under the RAWP. The

remedial action described in this document provides for the protection of public health

and the environment, complies with applicable environmental standards, criteria and

guidance and applicable laws and regulations.

1.1 SITE LOCATION AND BACKGROUND

The subject property is located on 125th Street between 5th Avenue and Lenox

Avenue. The site is bounded to the north and south by 126th Street and 125th Street

respectively and by abutting buildings to the east and west in the Harlem neighborhood of

Manhattan, New York (Figure 1). The site has an area of approximately ±0.59-acre and

was a vacant inactive construction site that had been excavated to approximately eleven-

feet below sidewalk grade in 2008. This site is currently owned by the CA 5-15 125th

Street LLC. Historically, the site was operated as a YMCA and associated dormitories, a

commercial parking lot and residential dwellings. According to the New York City

Department of City Planning, the subject property is designated as E 201 (CEQR number

07DCP030M), Block 1723, Lots 31, 45 and 144.

The properties adjoining the site consist of residential to the north and northwest and

commercial development to the east, south and southwest. A site plan of the property is

provided as Figure 2.

Page 17: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

17

1.2 REDEVELOPMENT PLAN

The use of the Site consists of a six (6)-story mixed use commercial and

residential building consisting of three (3) floors and a cellar for retail use, and three (3)

floors for residential use. The foundation of the building was installed at 17 feet and 6

inches below surface sidewalk grade. The elevator installed in the new development was

approximately 20 feet and 6 inches below grade. No landscaped or open areas exist on

the Subject Property. The building occupies the entire footprint of the lot.

Groundwater was observed to be approximately 14.5 to 15 feet below sidewalk grade

during the May 2011 Phase II Environmental Investigation completed by Langan. The

site was excavated below the groundwater table to allow for the construction of the

building cellar. Dewatering was completed as part of the site redevelopment activities.

A map showing the building location, basement location and open space location is

shown in the Development Plan in Figure 10.

1.3 DESCRIPTION OF SURROUNDING PROPERTY

The properties adjoining the site consist of residential to the north and northwest and

commercial development to the east, south and southwest. Additionally, two-day care

facilities are identified on the 124th Street within 250-feet of the subject property. No

other sensitive receptors were identified within 500-feet of the subject property.

1.4 SUMMARY OF PAST USES AND AREAS OF CONCERN

Based upon the review of the Fire Insurance Maps and Regulatory Agency

documents from the Phase I Environmental Site Assessment (ESA) Report dated August

2008 and prepared by EBI Consulting, a Site history was established. Historic use

including YMCA and associated dormitories and residential and commercial buildings.

Following the demolition of the YMCA and associated buildings, the site was

redeveloped as a parking lot and residential dwellings through 1992. Most recently the

property was an inactive construction site with no improvements.

A remedial investigation was performed and the results are documented in a

companion document called “Remedial Investigation Report, 5 West 125th Street”, dated

July 2011 (RIR).

Page 18: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

18

The following previous environmental reports were completed for the subject

property:

• Phase I Environmental Site Assessment (ESA) Report dated 11 August

2008 prepared for RCG Longview Debt Fund IV, L.P. and Capital One Bank c/o RCG

Longview, prepared by EBI Consulting of Burlington Massachusetts and submitted to

NYCOER on 15 April 2011;

• Phase II Subsurface Investigation Workplan (SIW) dated 15 April 2011

prepared by Langan, revised 18 May 2011 based on NYCOER comments made on 16

May 2011; and,

• Phase II Subsurface Investigation Report dated 25 July 2011 prepared by

Langan.

• 125th Street Acoustical Measurement Protocol dated 15 June 2011

prepared by Cerami Associates, Inc.

A copy of the ESA report and SIW were provided previously under separate

cover.

Phase I ESA (2008)

The August 2008 ESA was completed for Block 1723 Lots 31, 45, 140 and 144.

The property that is the subject of this Work Plan is limited to Lots 31, 45 and 144, Lot

140 is not part of the proposed redevelopment. Historic use of the site was identified as a

YMCA and associated dormitories and residential and commercial buildings. Following

the demolition of the YMCA and associated buildings, the site was redeveloped as a

parking lot and residential dwellings, as shown on the 1951 Sanborn Fire Insurance map.

The use of these properties was consistent through the 1992 Sanborn map. No

Recognized Environmental Conditions (RECs) were identified in the Phase I ESA report.

The Phase I ESA documents that groundwater samples were collected to obtain a

NYCDEP Bureau of Wastewater Treatment permit for the discharge of groundwater from

the dewatering system that was installed to be operated during the excavation of

foundations for the building previously proposed at the site. Groundwater samples were

reportedly collected and tested for polychlorinated biphenyls via United States

Page 19: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

19

Environmental Protection Agency (EPA) Method 608, semi-volatile organic compounds

by EPA Method 625 and volatile organic compounds by EPA Method 624. None of

these compounds were reported above the laboratory method detection limits.

Phase II SIW (2011)

Based on the findings of the Phase I ESA a Phase II SIW was developed to assess

subsurface conditions at the site via the collection of soil and groundwater samples.

Based on the 16 May 2011 NYCOER comments, the soil vapor sampling that was

proposed in the Phase II Scope of Work, was deleted from the 18 May 2011 Work Plan

Addendum. The findings of this investigation are detailed in Section 4.0 below.

Phase II Site Investigation Report (2011)

In order to address NYCOER requirements pertaining to the (E)-designation of

the site, soil, and groundwater sampling as part of a Phase II Environmental Investigation

was completed by Langan. The scope of work for the Phase II Environmental

Investigation was designed to assess the RECs identified in the Phase I ESA.

The scope of work was designed to:

• Identify the potential presence and extent of impacted soil, and/or

groundwater at the site;

• Determine contaminant(s) of concerns that may be encountered during site

redevelopment activities for incorporation into a construction Health and Safety Plan, if

necessary; and,

• Evaluate remediation options for any impacted soil vapor, soil, and/or

groundwater in accordance with NYSDEC and NYCOER regulations, if required.

The AOCs identified for this site include:

1. Historic fill is present at the Site from grade to a depth ranging from 4 to

21 feet below sidewalk grade. Currently, entire site has been excavated to a depth of

approximately 11-feet below sidewalk grade as part of the previous site development.

Page 20: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

20

Historic fill is identified to be between 3 to 4-feet in thickness from the current site grade.

1.5 SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL

INVESTIGATION

1. Conducted a Site inspection to identify AOCs and physical obstructions (i.e.

structures, buildings, etc.);

2. Completion of eight soil borings and collection of two soil samples per boring

to assess soil conditions and potential health and safety issues regarding soil disturbance

during the proposed site renovation;

3. Installation and sampling of three monitoring wells in order to assess site

groundwater conditions; and,

4. Completion of a Phase II Subsurface Investigation Report.

1.6 SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION

1. Elevation of the property is approximately 25 feet.

2. Depth to groundwater is approximately 14.5 to 15 feet at the Site.

Approximately, 3.5 to 4-feet below the current site grade.

3. Groundwater flow is generally from west to east beneath the Site.

4. Depth to bedrock is at the Site is approximately 48 to 63-feet below

sidewalk grade. The stratigraphy of the Site, from the surface down, consists of fill

overlying successive strata of sand, silt and clay, glacial till, and rock. The fill layer,

consisting of sand and gravel with brick, concrete, wood, and miscellaneous debris, was

observed throughout the site to depths of approximately 4 to 21-feet below sidewalk

grade. The fill material is underlain by a 6 to 18-foot thick layer of loose to medium

dense fine to coarse sands, followed by silt and clay and an approximately 6-foot thick

layer of glacial till. Bedrock, consisting of a gneiss and marble, was encountered at

depths ranging from approximately 48 to 63-feet below sidewalk grade.

5. Soil/fill samples collected during the RI showed no detectable

concentrations of PCBs. No VOCs were detected in soil, except for trace levels (2.3 ppb)

of tetrachloroethene in one soil sample. Select SVOCs, all polycyclic aromatic

hydrocarbons (PAHs) including benzo(a)anthracene (4.37 ppm), benzo(a)pyrene (3.99

Page 21: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

21

ppm), benzo(b)fluroanthene (3.06 ppm), benzo(k)fluroanthene (2.1 ppm), chrysene (4.22

ppm), and indeno(1,2,3-cd)pyrene (2.17 ppm) were identified in two of sixteen soil

samples at concentrations found above their Track 1 Unrestricted Use and Track 2

Restricted Residential Use SCOs. Pesticides including 4,4-DDE (0.0214 ppm), 4,4-DDT

(0.0814 ppm), dieldrin (0.0064 ppm) and heptachlor(0.09 ppm) were detected above their

Track 1 Unrestricted Use SCOs in four shallow sample. Several metals including barium,

chromium, lead, mercury and zinc were detected above Track 1 Unrestricted Use SCOs

and of these lead (max. of 606 ppm) and mercury (max. of 0.84 ppm) also exceeded

Track 2 Restricted Residential SCOs in two soil samples. Overall, these results are

consistent with levels of pesticides, SVOCs, and metals found at sites throughout NYC

with historic fill material.

6. Groundwater samples collected during the RI showed no detectable PCBs

or SVOCs. One pesticide, 4,4-DDD was in one of three groundwater samples at

concentrations below NYSDEC Groundwater Quality Standards (GQS). One VOC

tetrachloroethene was detected in 1 groundwater samples at trace levels (1 ppb), below its

GQS. Three metals, iron, manganese and sodium, were detected above GQSs in

dissolved groundwater samples.

7. Soil vapor sampling was not conducted because the site is already

excavated up to 11 feet depths and groundwater is about one to two feet below existing

grades.

Page 22: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

22

2.0 DESCRIPTION OF REMEDIAL ACTIONS

The remedial action was performed in accordance with an OER approved

Remedial Action Work Plan and achieved the remedial action objectives established for

the project. The remedial action was evaluated in an alternatives analysis and was

determined to be protective of human health and the environment, compliant with

standards, criteria, and guidelines (SCGs), effective in the short-term, effective in the

long-term, capable of attaining appropriate levels of reduction of toxicity, mobility, or

volume of contaminated material, implementable, cost effective, acceptable to the

community, consistent with land uses, and sustainable.

A summary of the milestones achieved in the Remedial Action is as follows: A

Remedial Investigation (RI) was performed from May to July, 2011. A RI Report was

prepared to evaluate data and information necessary to develop a Remedial Action Work

Plan (RAWP). A Site Contact List was established. A RAWP was prepared and released

with a Fact Sheet on February 12, 2013 for a 30-day public comment period. The RAWP

and Stipulation List dated March 20, 2013 was approved by the New York City Office of

Environmental Remediation (OER) on November 09, 2011. A Fact Sheet providing

notice of the start of the remedial action was issued on February 2013. The remedial

action was begun in October, 2013 and completed in December, 2015.

The remedial action consisted of the following tasks:

1. Prepared a Community Protection Statement and implemented a Citizen

Participation Plan.

2. Performed a Community Air Monitoring Program for particulates and volatile

organic carbon compounds.

3. Selected NYSDEC Part 375 Track 1 Unrestricted Use Soil Cleanup Objectives

(SCOs).

4. Mobilized site security, equipment, utility mark outs and marking & staking

excavation areas.

5. Performed Waste Characterization Study prior to excavation activities. Eight (8)

soil borings were performed during the Phase II investigation of the Subject

property. Waste characterization soil samples were collected from these borings

Page 23: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

23

on May 26, 2011. Waste characterization samples were collected at a frequency

dictated by disposal facility(s).

6. The following excavations were performed: soil was removed to a depth of 17

feet 6 inches from sidewalk grade beneath the area of the new building (entire

property). No landscaped or open areas exist on the Subject Property. The

building is setback 12’-3” from the curb on 125th Street and 13’-1” from the curb

on 126th Street. The building and cellar occupies the entire footprint of the lot.

Additional excavation occurred to 20.5 feet below sidewalk grade for the

elevator pits. A total of 5,978 cubic yards of soil/fill was excavated and removed

from the property.

7. Excavated 3,638 cubic yards of non-hazardous soil/fill and transported to Sky

Materials located at 4331 Middle Country Road in Calverton, NY 11933;

excavated 160 cubic yards of clean soil and transported to 55 Pearl Street

Brooklyn, NY 11201 utilizing the NYC Clean Soil Bank; excavated 2,180 cubic

yards of clean soil and transported to Fresh Kills in Staten Island utilizing the

NYC Clean Soil Bank.

8. Screened excavated soil/fill during intrusive work for indications of

contamination by visual means, odor, and monitoring with a PID.

9. Conducted materials management of excavated materials including temporarily

stockpiling and segregating in accordance with defined material types and to

prevent co-mingling of contaminated material and non-contaminated materials.

10. Appropriately segregated excavated media onsite prior to disposal. Transported

and disposed all soil/fill material at permitted facilities in accordance with all

applicable laws and regulations for handling, transport, and disposal, and the

RAWP.

11. Collected and analyzed end-point samples to determine attainment of SCOs.

Track 2 Restricted Residential SCOs were achieved.

12. As part of development, constructed an engineered Composite Cover System

consisting of 2-feet of concrete slab underlain by #57 Stone. The contractor for

the cover construction was Nova Concrete Contractors.

Page 24: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

24

13. As part of development, installed a Vapor Barrier System that consisted of

Xypex Admix blended concrete mix to waterproof and protect the concrete

poured for the slab and basement walls. Aquifin Vaportight Coat SG2 (30 mils),

an interior applied barrier was also used to prevent capillary infiltration of oil,

Radon, and other gases and chemical from the ground and as a secondary

containment of water vapor. The product was applied to the below grade

concrete foundation walls and cellar floor slab. The contractor for the Vapor

Barrier System construction was Nova Concrete Contractors.

14. Performed all activities required for the Remedial Action, including permitting

requirements and pretreatment requirements, in compliance with applicable laws

and regulations.

15. Implemented storm-water pollution prevention measures in compliance with

applicable laws and regulations.

16. Submitted a Sustainability Report.

17. Submitted a RAR that describes the Remedial Action, certifies that the remedial

requirements defined in the Remedial Action Work Plan have been achieved;

defines the Site boundaries; and describes any changes from the RAWP.

3.0 COMPLIANCE WITH REMEDIAL ACTION WORK

PLAN

3.1 HEALTH & SAFETY PLAN

The remedial construction activities performed under this program were in

compliance with the Health and Safety Plan and applicable laws and regulations. The Site

Safety Coordinator was Joseph Loesch.

3.2 COMMUNITY AIR MONITORING PLAN

The Community Air Monitoring Plan provided for the collection and analysis of air

samples during remedial construction activities to ensure proper protections were

employed to protect workers and the neighboring community. Monitoring was

Page 25: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

25

performed in compliance with the Community Air Monitoring Plan in the approved

RAWP. The results of Community Air monitoring are shown in Appendix 3.

3.3 SOIL/MATERIALS MANAGEMENT PLAN

The Soil/Materials Management Plan provided detailed plans for managing all

soil/materials that were disturbed at the Site, including excavation, handling, storage,

transport and disposal. It also included a series of controls to assure effective, nuisance

free remedial activity in compliance with applicable laws and regulations. Remedial

construction activities performed under this program were in compliance with the SMMP

in the approved RAWP.

3.4 STORM-WATER POLLUTION PREVENTION

Storm water pollution prevention included physical methods and processes to control

and/or divert surface water flows and to limit the potential for erosion and migration of

Site soils, via wind or water. Remedial construction activities performed under this

program were in full compliance with methods and processes defined in the RAWP for

storm water prevention and applicable laws and regulations.

3.5 DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN

All work performed was in accordance with the OER approved RAWP at this Site with

the exception of the following deviations:

Remediation did not achieve Track 1 SCOs. Alternative 2- Track 2

Residential SCOs were achieved.

On July 1, 2013 OER was notified by letter from H2M of the revised project

description details. The previous development included the construction of a 4-

story commercial/retail building. The new development includes a 6-story

building with bottom three (3) stories and a cellar for commercial/retail use while

top three (3) stories are for residential use. There were no significant changes to

the foundation depth or details for the new development compared to the previous

development plan. The concrete mat slab for the new building was installed at a

depth of 17’-6” below grade surface (bgs) compared to the previous development

Page 26: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

26

depth of 16’-6” bgs. The total foundation area will be approximately 22,617 square

feet (s.f.). The total commercial/retail area including cellar will be approximately

99,225 s.f. The total residential area will be approximately 26,895 s.f. The building

will be set on a 2’-6” concrete mat slab with the bottom of the slab being set at an

elevation of 17’-6” bgs. The building will include two elevator pits and two escalator

pits set at elevations of 20’-6” bgs and 19’-8” bgs, respectively. The site has been

already excavated down to 10 feet bgs. The proposed depth of excavation will be

additional 7’-6” for the installation of the mat slab. The excavation depth for the

installation of the elevator and escalator pits will be additional 10’-6” and 9’-8”,

respectively. These changes are still protective of public health and environment.

Correspondence is attached in Appendix K.

On April 29, 2014 OER was notified by letter from Rosenbaum Design Group

Architecture of the revised vapor barrier product and specification. It was

determined that Aquafin Vaportight Coat SG2 to be an acceptable product to act

as an interior applied barrier to prevent capillary infiltration of oil, Radon, and

other gases and chemical from the ground and as a secondary containment of

water vapor. Xypex in the concrete was specified as the primary water

containment product. The product was applied to the below grade concrete

foundation walls and cellar floor slab. These changes are still protective of public

health and environment. Correspondence is attached in Appendix J.

Page 27: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

27

4.0 REMEDIAL PROGRAM

4.1 PROJECT ORGANIZATION

Principal personnel who participated in the remedial action include CA 5-15 West

125th Street LLC as owners of the property and Harco Consultants Corp. as the

construction managers of the proposed redevelopment. Ms. Ela Obara of Harco

Consultants Corp. had the primary oversight of the overall development of this project.

The Professional Engineer (PE) for this project was H2M architects + engineers (H2M),

as environmental consultant to the ownership. Mr. Hardik Parekh, P.E. of H2M was the

primary point of contact and Mr. Joseph Loesch of H2M was field supervisor during the

implementation of this RAWP.

4.2 SITE CONTROLS

Site Preparation

Prior to the initiation of the remedial activities, the Site was secured with plywood

fencing throughout the perimeter of the lot. All appropriate New York City Department

of Building permits, and NYC OER fact sheets and signage sheets were placed on the

fence. An OER Project Notice was erected at the project entrance and was in place

during all phases of the Remedial Action. A sub-surface utility survey was conducted

prior to all excavation activities. All underground utilities were terminated.

Excavation activities at the Site began on October 28, 2013. Nova Concrete

Contractors was contracted by H&H Builders to perform the site excavation activities.

Daily tailgate safety meetings were conducted by H&H Builders/H2M prior to all

excavation activities at the Site. The site safety briefing included a discussion of

potential work-zone hazards, proper handling of dangerous tools and equipment and

avoidance of unsafe work conditions.

According the RAWP, real-time air monitoring for volatile organic

compounds (VOCs) and particulate levels at the perimeter of the exclusion zone or work

area was warranted during all intrusive soil excavation work. As part of the Community

Air Monitoring Program (CAMP) highlighted in the Remedial Action Work Plan, H2M

utilized a Thermo PDR 1000, a portable real-time dust particulate meter monitor with

data-logging capabilities to monitor the particulate concentration during the soil

Page 28: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

28

excavation at the subject site. Additionally, H2M utilized a MiniRae 2000, a portable

photoionization detector to monitor VOC concentration.

An OER Project Notice was erected at the project entrance and was in place during

all phases of the Remedial Action.

Soil Screening

Soil excavation at 5 West 125th Street began on October 28, 2013. During excavation

activities, H2M conducted periodic visual/olfactory inspections of the soil being removed

from the Site. No issues of visual/olfactory contamination were encountered.

Additionally, a portable photoionization detector (PID) was utilized to screen for the

presence of volatile organic vapors within the work zone. Prior to entering the open

excavation, a fresh air calibration was performed to establish the background air of the

work zone. No exceedances in VOC concentrations were detected during excavation

activities at the subject property.

Stockpile Management

A total of 5,978 cubic yards of soil were excavated from the 5 West 125th Street property.

Soil stockpiles were appropriately graded to control run-off in accordance with the

Stormwater Pollution Prevention Plan (SWPPP) for 5 West 125th Street. Since the site

was previously excavated, on-site stockpiles were maintained as the truck ramp.

Truck Inspection

Stockpiled and direct load out soils were removed to an off-site disposal facility, Fresh

Kills Landfill (Fresh Kills) in Staten Island, NY; 55 Pearl Street (Pearl Street) in

Brooklyn, NY; and Sky Materials in Calverton, NY. Soil manifests were documented for

all loads leaving the Site. Nova washed and brushed residual soils from all truck tires

prior to leaving the jobsite. All trucks were covered prior to leaving the jobsite.

Site Security

The excavation site was secured with plywood fencing throughout the perimeter of the

125th Street and 126th Street lot.

Nuisance Controls

No issues of odors, dust circulation or neighborhood complaints were encountered

throughout the duration of excavation activities at 5 West 125th Street.

Reporting

Page 29: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

29

As requested by the OER, daily field reports were provided to the project manager. The

reports included a summary of daily field activities, locations of work zones, quantities of

soils excavated, status of on-site stockpiles, description of CAMP equipment location,

photographs of notable site conditions and activities and all relevant OER identification

numbers specific to the site. All daily and monthly reports are included in Appendix C.

Digital photographs of the Remedial Action are included in Appendix D.

4.3 MATERIALS EXCAVATION AND REMOVAL

Soil/Fill Excavation and Removal

. A total of 5,978 cubic yards of soil were excavated from the subject site. The initial

environmental investigation of 5 West 125th Street indicated that all soils excavated from

the subject site were suitable for off-site disposal. A map showing the location where

excavations were performed is shown in Figure 5. A map showing the approximate

source location of reused soil and the location of placement of reused soil is shown in

Figure 6. The Removal Action was performed under the oversight of Hardik Parekh.

Site work was performed by Nova Construction. Intrusive work began on October 28,

2013. CAMP was provided per the work plan during all activities involving soil

disturbance. Piles were driven along the perimeter of the site prior to any soil removal

activities were performed. Unused and scrap I-beams were removed from the Site as

necessary. Shoring was installed by NOVA along the eastern and western perimeter of

the property to prevent adjoining properties from shifting during construction. From

November 4, 2013 to November 7 a ramp dirt ramp was built in preparation for soil

transfer to 55 Pearl Street, Brooklyn as part of the OER Clean Soil Bank. A backhoe was

utilized to grade, stockpile and fill trucks with on-site soils. The ramp was built for truck

access from 126th Street and maintained in this orientation for the duration of the project.

From November 5, 2013 to November 6, 2013, piles were driven along 126th Street and

shoring installed. On November 11, 2013, a total of eight (8) 20-cubic yard truckloads of

clean soil were transferred from the Site to 55 Pearl Street, Brooklyn (OER Project#

11EHAN269M) by Jaym Trans LLC. Every effort was taken on-site to ensure that

Page 30: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

30

construction and demolition materials were not transferred to 55 Pearl Street; however,

soils were not mechanically separated. Trucks were washed and covered before leaving

the Site. From December 11, 2013 through September 23, 2014, Nova Construction

stockpiled and maintained a ramp for soil disposal. From December 12, 2013 through

January 6, 2014, #57 stone was delivered to the site from Sky Materials located at 4331

Middle Country Rd in Calverton, NY 11933. A total of twenty-four (24) 36-yard trucks

dropped off #57 stone for underlayment of the concrete slab and removed soil for

disposal at the Sky Material facility. Gravel was initially placed along the southern edge

of the Site. The gravel was used to build an underlayment for the concrete pad. The site

was graded to a depth of 17’ – 6”. As the property was graded to this depth, incoming

stone was placed at the 17’ 6” below sidewalk grade. From December 20, 2013 through

April 2, 2014, one hundred nine (109) 20-cubic yard trucks were loaded with on-site soils

and disposed of through the OER Clean Soil Bank at the Fresh Kills Landfill in Staten

Island, NY. Gravel bedding commenced along the southern extents of the property and

continued along the western half of the property as soils were excavated. A vibratory

roller was used by Nova Construction to compact the stone underlayment. Nova

Construction began to install reinforced bar for the concrete slab on December 31, 2013.

Between January 6, 2014 and January 29, 2014, the south west corner of the mat slab was

poured. On January 20, 2014, H2M collected three end points (EP-3, EP-4, EP-5, EP-X)

from the middle and southern portions of the site based on the approved work plan. EP-

X was a blind duplicate quality control sample of EP-4. The end-points were collected at

a depth of 17’ -6” below sidewalk grade. Between January 29, 2014 and March 11, 2014,

an elevator pit was excavated and framed in the northwest corner of the property.

Between March 28, 2014 and April 2, 2014, the elevator pit in the northwest corner of the

property was reinforced and poured. The bottom elevation for the retail freight elevator

pit was 19’-1” below sidewalk grade. Between April 2, 2014 and June 16, 2014, the

western half of the property was framed, reinforced and poured. Walls along the southern

and western sides were also framed, reinforced and poured during this time. Support

columns throughout the cellar level were framed, reinforced and poured during this

period. Work was performed in July 2014, to bed, frame and reinforce the southeastern

portion of the property. By July 30, 2014, the soil ramp was only in the northeast corner

Page 31: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

31

of the property. Nova Construction installed the first-floor decking on the western

portion of the property by this time. One cellar retail passenger elevator pit was installed

in August of 2014 in the southeast section of the Site to a total depth of 20’-3” below

sidewalk grade surface. End-point soil samples (EP-1, EP-2) were collected in the

northern portion of the property on September 15, 2014. By September 17, 2014, first-

floor decking was installed on the southern portion of the property. The final soil

removal from the Site occurred on September 23, 2014.

All slab and foundation wall concrete was poured with Xypex additive to ensure it is

vapor and liquid tight. Additionally, upon completion of the cellar, Nova Construction

applied 30 mils thickness Aquafin Vaportight Coat SG2 to the interior walls and cellar

slab. Inspections of the coating were performed by H2M on November 18, 2014,

December 10, 2015 and May 13, 2015. The inspections confirmed the proper installation

of the vapor barrier.

Permitting for dewatering was performed by Kosuri Engineering & Consulting P.C. A

Permit Application for Water Quality Control dated April 10, 2013 is attached as

Appendix L. The scope of work involved installation of dewatering sump and system

around the vacant site for the construction of a basement for a building. The work

involved installation of a sump pit in a controlled excavation to create a sump and install

a sump pump in order to pump water collected the sump pit to keep the allowable

pumping rates not to exceed the discharge limits of 9,500 gallons per day. The intention

was to limit the discharge to 9,500 gallons per day by performing controlled dewatering

areas to accomplish the intent of the design and limit the construction area to limit the

dewatering rates. On February 12, 2013 Holzmacher, McLendon & Murrell, P.C.

collected the dewatering sample on behalf of Harco Consultants and submitted to York

Analytical Laboratories. The sample was analyzed for NYCDEP Discharge Limitation

for Effluent to Sanitary or Combined Sewers. The excavation was dewatered by

pumping groundwater and passing it through a treatment system and discharging it into

36” combined sewer located on 125th Street. The pre-treatment system consisted of a

settling tank and an oil water separator tank.

Page 32: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

32

Soil Cleanup Objectives

The SCOs for this Remedial Action are NYSDEC Part 375 Track 1 Unrestricted Use

SCOs.

End Point Sample Results

Following the completion of the site excavation to a depth of 17’ 6” feet below sidewalk

grade surface, H2M collected post excavation samples from five locations as depicted in

the OER-approved end point sampling plan. The endpoint samples were labeled EP-1 to

EP-5 and collected from a depth of 17’ 6” below sidewalk grade. The samples were

submitted for analysis to NYS DOH ELAP certified York Analytical Laboratories of

Stratford Connecticut for the following parameters:

Volatile organic compounds by EPA Method 8260;

Semi-volatile organic compounds by EPA Method 8270;

Target Analyte List metals; and

Pesticides/PCBs by EPA Method 8081/8082.

Laboratory results were compared to NYSDEC 6NYCRR Part 375 Soil Cleanup

Objectives for Track 1 Unrestricted Use and Track 2 Residential Use.

Additionally, a blind duplicate of EP-4 (EP-X was collected to fulfill quality

assurance/quality control requirements. EP-X was analyzed for the same parameters as

the other five post-excavation samples collected.

A map of end-point sample locations is shown in Figure 4. A tabular summary of

end-point sampling results compared to SCO’s is included in Table 1. As shown on Table

1, endpoint samples showed no VOCs, SVOCs, pesticides, or PCBs detected above Track

1 SCOs. Endpoints samples detected chromium (max. 9.11 ppm), lead (max. 186 ppm),

and zinc (max. 126 ppm) above Track 1 SCOs. However, these detections were below

Track 2 Restricted Residential SCOs.

The SCOs for this project were not achieved. However, Track 2 Restricted

Residential SCOs, which are appropriate for the use of the property, were achieved.

Page 33: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

33

4.4 MATERIALS DISPOSAL

The material type, quantity and disposal location of material removed and disposed off-

Site is presented below:

Disposal Location/Address Type of Material Quantity

Sky Materials

4331 Middle Country Road

Calverton, NY 11933

Non-Hazardous

Soil 3,638 cubic yards

Fresh Kills Landfill

Staten Island, NY 10312

Clean Soil in NYC

Clean Soil Bank 2,180 cub yards

55 Pearl Street

Brooklyn, NY 11201

Clean Soil in NYC

Clean Soil Bank 160 cubic yards

Materials were removed from the Site beginning October 2013 and ending September

2014. Letters from CA 5-15 125TH Street LLC and HARCO Consultants Corporation to

disposal facility providing materials type, source and data, and acceptance letters from

disposal facility stating it is approved to accept above materials are attached in Appendix

E. Manifests are included in Appendix F. Characterization sample results are presented in

Appendix G. Table 6 summarizes the shipping date, trucking company name and truck

license plate number, and tonnage for each truck load.

4.5 BACKFILL IMPORT

Approximately 864 cubic yard of ¾” and 57 stone off-site backfill material was

imported to the Site by Sky Materials in Calverton, NY. The stone was spread over the

site and compacted prior to pouring the concrete slab on-site.

4.6 DEMARACTION

Track 2 Restricted Residential SCOs were achieved.

Page 34: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

34

5.0 ENGINEERING CONTROLS

A Track 2 Restricted Residential Remedial Action was achieved and Engineering

Controls are not required. However, as part of construction, several protective systems

were installed. These are:

(1) a Composite Cover System consisting of a 2 feet concrete building slab across

the building footprint;

(2) Vapor Barrier System;

Composite Cover System

As part of development, an engineered Composite Cover System has been built on the

Site. This Composite Cover System is comprised of

2-feet of reinforced concrete slab across the building footprint (entire site) underlain by

#57 stone. The contractor for the Composite Cover System construction was Nova

Concrete Contractors.

Appendix I shows the as-built design for each remedial cover type used on this Site.

Figure 7 and Figure 9 shows the location of each cover type built at the Site.

Photographs of construction of the Composite Cover System are included in Appendix D.

Vapor Barrier System

As part of development, a Vapor Barrier System has been built on the Site. This

Vapor Barrier System consists of Xypex Admix blended concrete mix to waterproof and

protect the concrete poured for the slab and basement walls. Aquifin Vaportight Coat

SG2 (30 mils), an interior applied barrier was also used to prevent capillary infiltration of

oil, Radon, and other gases and chemical from the ground and acts as a secondary

containment of water vapor. The product was applied to the below grade concrete

foundation walls and cellar floor slab. Appendix I shows the as-built drawings for the

vapor barrier and concrete foundation as well as manufacturer documentation for the

waterproofing and vapor sealer. Photographs of the construction of the vapor barrier

system are included in Appendix D. The professional engineer for the Vapor Barrier

Page 35: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

35

System was Hardik Parekh. The contractor for the Vapor Barrier System construction

was Nova Concrete Contractors.

Figure 10 shows the as-built design for the Vapor Barrier System used on this

Site. Photographs of installation of the Vapor Barrier System are included in Appendix

D. A copy of the certificate of warranty is included in Appendix J.

Page 36: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

36

6.0 INSTITUTIONAL CONTROLS

A Track 2 Restricted Residential Remedial Action was achieved and Engineering

Controls and Institutional Controls are not required.

7.0 SITE MANAGEMENT PLAN

A Track 2 Restricted Residential Remedial Action was achieved and Site

Management is not required.

Page 37: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

37

8.0 SUSTAINABILITY REPORT

This Remedial Action Work Plan provides for sustainable remediation and

redevelopment through a variety of means that are defined in this Sustainability Report.

Reuse of Clean, Recyclable Materials. Reuse of clean, recyclable materials reduces

consumption of non-renewable virgin resources and can provide energy savings and

greenhouse gas reduction since these materials can be locally-derived.

An estimate of the tonnage of recycled material reused on this project is 30 tons

of onsite soil. An estimated 2,340 tons of clean soil were transferred to accepting sites

within the NYC Clean Soil Bank.

Conservation of Non-Renewable Resources. Reduced consumption of non-

renewable resources such as soil and top-soil lowers the overall environmental impact of

the project on the region by conserving these resources.

Conservation of non-renewable resources was achieved by avoidance of the use of

virgin soil as backfill for completed excavation. An estimate of the tonnage of non-

renewable resources, the use of which will be avoided under this plan, is 30 tons.

Recontamination Control. Recontamination after cleanup and redevelopment is

completed undermines the value of work performed, may result in a property that is less

protective of public health or the environment, and may necessitate additional cleanup

work later that could impede future redevelopment. Recontamination can arise from

future releases that occur within the property or by influx of existing contamination from

off-Site.

To prevent the transport of contamination to the site from off-site sources, a vapor

barrier was incorporated into the foundation of the new building. Also, during the

removal of contaminated soil from the site, all trucks were washed at the exit to prevent

any contamination leaving the site that could potentially re-contaminate the property. In

addition, the entire site is covered with a composite cover system that will reduce the

potential for contamination of soil from the land surface. The area of the Site that utilizes

re-contamination controls under this plan is 27,500 square feet.

Paperless Brownfield Cleanup Program. CA 5-15 125th Street and HARCO

Consultants Corporation participated in OER’s Paperless Brownfield Cleanup Program.

Page 38: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

5 West 125th Street Remedial Action Report

December, 2016

38

Under this program, submission of electronic documents replaced submission of hard

copies for the review of project documents, communications and milestone reports. A

best estimate of the mass (pounds) of paper saved under this plan is 30 pounds.

Low-Energy Project Management Program. CA 5-15 125th Street and HARCO

Consultants Corporation participated in OER’s low-energy project management program.

Under this program, whenever possible, meetings were held using remote communication

technologies, such as videoconferencing and teleconferencing to reduce energy

consumption and traffic congestion associated with personal transportation. A gross

estimate of the number of miles of personal transportation that was conserved in this

process is 1,000 miles.

Page 39: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 1

SITE BOUNDARY MAP

Page 40: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 41: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 2

SITE LOCATION

Page 42: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 43: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 3

DEVELOPMENT PLAN

Page 44: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
telms
Rectangle
telms
Text Box
Residential Tower Above Floors 4-6
telms
Line
telms
Text Box
117 ft
telms
Text Box
126th Street
telms
Text Box
125th Street
telms
Text Box
Commercial Floors 1-3
telms
Text Box
Refer to Figures 11 & 12 for additional cellar details.
Page 45: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 4

MAP OF END-POINT SAMPLE LOCATIONS

Page 46: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 47: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 5

MAP SHOWING LOCATION AND APPROXIMATE DEPTH OF EXCAVATIONS

Page 48: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 49: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 6

MAP OF SOIL/FILL REUSE AND BACKFILL PLACEMENT LOCATIONS

Page 50: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 51: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 7

MAP OF LOCATION OF COMPOSITE COVER SYSTEM

Page 52: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 53: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 8

MAP OF LOCATION OF VAPOR BARRIER SYSTEM

Page 54: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 55: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 9

AS-BUILT DESIGN DETAIL FOR VAPOR BARRIER SYSTEM

Page 56: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 57: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 10

DEVELOPMENT PLAN

Page 58: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 59: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 11

ELEVATOR PIT PLAN

Page 60: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 61: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 12

CELLAR LEVEL REFLECTED CEILING PLAN

Page 62: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
jloesch
Typewritten Text
jloesch
Text Box
126th Street
jloesch
Text Box
125th Street
jloesch
Text Box
TJ Maxx Retail Space
Page 63: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 13

FOUNDATION SECTIONS AND DETAILS

Page 64: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 65: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 14

FIRST FLOOR REPLECTED CEILING PLAN

Page 66: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 67: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 15 - 18

EXTERIOR ELEVATIONS

Page 68: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 69: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 70: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 71: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 72: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 19

FOUNDATION PLAN

Page 73: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 74: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

FIGURE 20 - 24

SECTIONS VIEWS

Page 75: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 76: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 77: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 78: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 79: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net
Page 80: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

TABLE 1-4

SUMMARY OF END-POINT ANALYTICAL RESULTS

Page 81: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Sample ID: EP-1 EP-2 EP-3 EP-4 EP-5 EP-X

Sample Depth: 16' 16' 18' 18' 18' 18'

Sample Date: 9/15/2014 9/15/2014 1/29/2014 1/29/2014 1/29/2014 1/29/2014

Lab No.: 14I0951-01 14I0951-02 14A0898-01 14A0898-02 14A0898-03 14A0898-04

Sample Matrix: Soil Soil Soil Soil Soil Soil

Units: ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg

1,1,1,2-Tetrachloroethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1,1-Trichloroethane 680 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1,2,2-Tetrachloroethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1,2-Trichloro-1,2,2-trifluoroethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1,2-Trichloroethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1-Dichloroethane 270 19,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1-Dichloroethylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,1-Dichloropropylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2,3-Trichlorobenzene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2,3-Trichloropropane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2,4-Trichlorobenzene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2,4-Trimethylbenzene 3,600 47,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2-Dibromo-3-chloropropane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2-Dibromoethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2-Dichlorobenzene 1,100 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2-Dichloroethane 20 2,300 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,2-Dichloropropane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,3,5-Trimethylbenzene 8,400 47,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,3-Dichlorobenzene 2,400 17,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,3-Dichloropropane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,4-Dichlorobenzene 1,800 9,800 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

1,4-Dioxane 100 9,800 <53 <2.8 <22 <21 <22 <20

2,2-Dichloropropane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

2-Butanone NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

2-Chlorotoluene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

4-Chlorotoluene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Acetone 50 100,000 <5.3 6.5 J,B 3.0 J,B 3.6 CCV-E, J 3.8 CCV-E, J 4.1 CCV-E

Benzene 60 2,900 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Bromobenzene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Bromochloromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Bromodichloromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Bromoform NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Bromomethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Carbon tetrachloride 760 1,400 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Chlorobenzene 1,100 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Chloroethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Chloroform 370 10,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Chloromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

cis-1,2-Dichloroethylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

cis-1,3-Dichloropropylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Dibromochloromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Dibromomethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Dichlorodifluoromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Ethyl Benzene 1,000 30,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Hexachlorobutadiene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Isopropylbenzene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Methyl tert-butyl ether 930 62,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Methylene chloride 50 51,000 <5.3 <5.6 <2.2 <2.3 <1.1 <0.99

Naphthalene NS NS <2.7 <2.8 <1.1 4.2 J 3.3 J 2.3 J

n-Butylbenzene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

n-Propylbenzene 3,900 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

o-Xylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

p- & m-Xylenes NS NS <5.3 <5.6 <2.2 <2.1 <2.2 <2.0

p-Isopropyltoluene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

sec-Butylbenzene 11,000 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Styrene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

tert-Butylbenzene 5,900 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Tetrachloroethene 1,300 5,500 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Toluene 700 100,000 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

trans-1,2-Dichloroethylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

trans-1,3-Dichloropropylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Trichloroethylene NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Trichlorofluoromethane NS NS <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Vinyl Chloride 20 210 <2.7 <2.8 <1.1 <1.1 <1.1 <0.99

Xylene (total) 260 100,000 <8.0 <8.4 <3.3 <3.2 <3.3 <3.0

Vinyl acetate NS NS <2.7 <2.8 <1.1 <1.2 <1.1 <0.99

NS: No Standard Established.CCV-E: The value reported is estimated due to its behavior during continuing calibration verificationJ: Detected below the Reporting Limit but greater than or equal to the Method Detection LimitB: Analyte is found in the associated batch blankug/kg…micrograms per kilogramEP-X blind duplicate sample as part of the QA/QC analysis

Table 1

Endpoint Soil Samples Volatile Organic Analytical Results

5 West 125th Street, New York, NY

6 NYCRR Part 375-6.8(a)

Unrestricted Use Soil Cleanup Objectives

6 NYCRR Part 375-6.8(b)

Residential Use Soil Cleanup Objectives

Volatile Organic Compounds - EPA Method 8260

Page 82: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Sample ID: EP-1 EP-2 EP-3 EP-4 EP-5 EP-X

Sample Depth: 16' 16' 18' 18' 18' 18'

Sample Date: 9/15/2014 9/15/2014 1/29/2014 1/29/2014 1/29/2014 1/29/2014

Lab No.: 14I0951-01 14I0951-02 14A0898-01 14A0898-02 14A0898-03 14A0898-04

Sample Matrix: Soil Soil Soil Soil Soil Soil

Units: ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg

Acenaphthene 20,000 100,000 <425 <428 <45.6 <44.2 <45.8 <45

Acenaphthylene 100,000 100,000 <425 <428 <45.6 <44.2 <45.8 <45

Aniline NS NS <425 <428 <45.6 <44.2 <45.8 <45

Anthracene 100,000 100,000 <425 <428 <45.6 53.7 J 65.4 J <45

Benzo(a)anthracene 1,000 1,000 <425 571 J <45.6 119 J 79.6 J 75 J

Benzo(a)pyrene 1,000 1,000 <425 <428 <45.6 56.5 J <45.8 58.6 J

Benzo(b)fluoranthene 1,000 1,000 <425 <428 <45.6 78.7 J <45.8 <45

Benzo(g,h,i)perylene 100,000 100,000 <851 <857 <91.2 <88.5 <91.6 <90

Benzyl alcohol NS NS <851 <857 <91.2 <88.5 <91.6 <90

Benzo(k)fluoranthene 800 1,000 <425 <428 <45.6 84.6 J 60.7 J 58.2 J

Benzyl butyl phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

4-Bromophenyl phenyl ether NS NS <425 <428 <45.6 <44.2 <45.8 <45

4-Chloro-3-methylphenol NS NS <851 <857 <91.2 <88.5 <91.6 <90

4-Chloroaniline NS NS <851 <857 <91.2 <88.5 <91.6 <90

Bis(2-chloroethoxy)methane NS NS <425 <428 <45.6 <44.2 <45.8 <45

Bis(2-chloroethyl)ether NS NS <425 <428 <45.6 <44.2 <45.8 <45

Bis(2-chloroisopropyl)ether NS NS <425 <428 <45.6 <44.2 <45.8 <45

Bis(2-ethylhexyl)phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

2-Chloronaphthalene NS NS <425 <428 <45.6 <44.2 <45.8 <45

2-Chlorophenol NS NS <425 <428 <45.6 <44.2 <45.8 <45

4-Chlorophenyl phenyl ether NS NS <425 <428 <45.6 <44.2 <45.8 <45

Chrysene 1,000 1,000 <425 554 J <45.6 118 J 87.6 J 83.6

Dibenzo(a,h)anthracene 330 330 <425 <428 <45.6 <44.2 <45.8 <45

Dibenzofuran NS NS <425 <428 <45.6 <44.2 <45.8 <45

Di-n-butyl phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

1,2-Dichlorobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

1,4-Dichlorobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

1,3-Dichlorobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

3,3'-Dichlorobenzidine NS NS <1690 <1700 <181 <176 <182 <179

2,4-Dichlorophenol NS NS <851 <857 <91.2 <88.5 <91.6 <90

Diethyl phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

2,4-Dimethylphenol NS NS <425 <428 <45.6 <44.2 <45.8 <45

Dimethyl phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

4,6-Dinitro-2-methylphenol NS NS <851 <857 <91.2 <88.5 <91.6 <90

2,4-Dinitrophenol NS NS <1690 <1700 <181 <176 <182 <179

2,6-Dinitrotoluene NS NS <425 <428 <45.6 <44.2 <45.8 <45

2,4-Dinitrotoluene NS NS <851 <857 <91.2 <88.5 <91.6 <90

Di-n-octyl phthalate NS NS <425 <428 <45.6 <44.2 <45.8 <45

Fluoranthene 100,000 100,000 945 J 1260 J <45.6 <44.2 232 200

Fluorene 30,000 100,000 <425 <428 <45.6 320 <45.8 <45

Hexachlorobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

Hexachlorobutadiene NS NS <425 <428 <45.6 <44.2 <45.8 <45

Hexachlorocyclopentadiene NS NS <851 <857 <91.2 <88.5 <91.6 <90

Hexachloroethane NS NS <425 <428 <45.6 <44.2 <45.8 <45

Indeno(1,2,3-cd)pyrene 500 500 <425 <428 <45.6 <44.2 <45.8 <45

Isophorone NS NS <425 <428 <45.6 <44.2 <45.8 <45

2-Methylnaphthalene NS NS <425 <428 <45.6 <44.2 <45.8 <45

2-Methylphenol NS NS <851 <857 <91.2 <88.5 <91.6 <90

3- & 4-Methylphenols NS NS <851 <857 <91.2 <88.5 <91.6 <90

Naphthalene 12,000 100,000 <425 <428 <45.6 <44.2 <45.8 <45

3-Nitroaniline NS NS <851 <857 <91.2 <88.5 <91.6 <90

2-Nitroaniline NS NS <425 <428 <45.6 <44.2 <45.8 <45

4-Nitroaniline NS NS <851 <428 <91.2 <88.5 <91.6 <90

Nitrobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

4-Nitrophenol NS NS <851 <857 <91.2 <88.5 <91.6 <90

2-Nitrophenol NS NS <425 <428 <45.6 <44.2 <45.8 <45

N-nitroso-di-n-propylamine NS NS <425 <428 <45.6 <44.2 <45.8 <45

N-Nitrosodimethylamine NS NS <851 <857 <91.2 <88.5 <91.6 <90

N-Nitrosodiphenylamine NS NS <425 <428 <45.6 <44.2 <45.8 <45

Pentachlorophenol 800 2,400 <851 <857 <91.2 <88.5 <91.6 <90

Phenanthrene 100,000 100,000 861 J 796 J <45.6 236 250 139 J

Phenol 330 100000 <425 <428 <45.6 <44.2 <45.8 <45

Pyrene 100,000 100,000 847 J 1150 J <45.6 292 205 187

Pyridine NS NS <425 <428 <45.6 <44.2 <45.8 <45

1,2,4-Trichlorobenzene NS NS <425 <428 <45.6 <44.2 <45.8 <45

2,4,6-Trichlorophenol NS NS <425 <428 <45.6 <44.2 <45.8 <45

2,4,5-Trichlorophenol NS NS <425 <428 <45.6 <44.2 <45.8 <45

NS : No standard establishedJ: Detected below the Reporting Limit but greater than or equal to the Method Detection Limitug/kg…micrograms per kilogramEP-X blind duplicate sample as part of the QA/QC analysis

6 NYCRR Part 375-6.8(a)

Unrestricted Use Soil Cleanup Objectives

6 NYCRR Part 375-6.8(b)

Residential Use Soil Cleanup Objectives

Table 2

Endpoint Soil Samples Sem-Volatile Organic Analytical Results

5 West 125th Street, New York, NY

Semi-Volatile Organic Compounds - EPA Method 8270

Page 83: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Sample ID: EP-1 EP-2 EP-3 EP-4 EP-5 EP-X

Sample Depth: 16' 16' 18' 18' 18' 18'

Sample Date: 9/15/2014 9/15/2014 1/29/2014 1/29/2014 1/29/2014 1/29/2014

Lab No.: 14I0951-01 14I0951-02 14A0898-01 14A0898-02 14A0898-03 14A0898-04

Sample Matrix: Soil Soil Soil Soil Soil Soil

Units: mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg

Aluminum NS NS 4170 4500 1790 2220 2430 2490

Antimony NS NS <0.506 <0.510 <0.543 0.73 <0.545 <0.536

Arsenic 13 16 1.7 1.64 <1.09 <1.05 1.36 <1.07

Barium 350 350 152 156 17.2 39.2 36 46.7

Beryllium 7.2 14 <0.101 <0.102 <0.109 <0.105 <0.109 <0.107

Cadmium 2.5 2.5 <0.304 <0.306 <0.326 <0.316 <0.327 <0.322

Calcium NS NS 7680 9110 477 1700 774 1870

Chromium+ 30 36 9.01 9.11 7.05 6.15 5.65 5.85

Cobalt NS NS 4.52 4.15 2.22 2.67 3.47 3.41

Copper 50 270 22.2 18.1 7.92 10.6 13.3 11.7

Iron NS NS 8280 9090 4160 3930 5480 4600

Lead 63 400 165 186 2.34 35 16.2 36.9

Magnesium NS NS 2870 2970 1080 947 1220 1400

Manganese 1,600 2,000 430 341 294 316 105 358

Nickel 30 140 10.9 8.51 6.34 6.26 10.2 7.52

Potassium NS NS 926 836 394 392 573 435

Selenium 3.9 36 <1.01 <1.02 <1.09 <1.05 <1.09 <1.07

Silver 2 36 <0.506 <0.510 <0.543 <0.527 <0.545 <0.536

Sodium NS NS 120 115 27.8 81.4 50.9 75.1

Thallium NS NS <1.01 <1.02 <1.09 <1.05 <1.09 <1.07

Vanadium NS NS 13.6 12.2 5.81 6.38 7.76 7.63

Zinc 109 2,200 112 126 10.5 33.7 25.3 30.3

Mercury 0.18 0.81 0.0796 0.0829 <0.0326 <0.0316 <0.0327 <0.0322

NS : No standard establishedJ: Detected below the Reporting Limit but greater than or equal to the Method Detection Limit+: Guidance value for trivalent ChromiumYellow shaded values indicated exceedances of the Unrestricted Use SCOs, but below the Residential Use SCOsmg/kg…miligram per kilogramEP-X blind duplicate sample as part of the QA/QC analysis

Mercury by EPA Method 7473

Table 3

Endpoint Soil Samples Metals Analytical Results

5 West 125th Street, New York, NY

6 NYCRR Part 375-6.8(a)

Unrestricted Use Soil Cleanup Objectives

6 NYCRR Part 375-6.8(b)

Residential Use Soil Cleanup Objectives

Metals (Target Analyte List)

Page 84: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Sample ID: EP-1 EP-2 EP-3 EP-4 EP-5 EP-X

Sample Depth: 16' 16' 18' 18' 18' 18'

Sample Date: 9/15/2014 9/15/2014 1/29/2014 1/29/2014 1/29/2014 1/29/2014

Lab No.: 14I0951-01 14I0951-02 14A0898-01 14A0898-02 14A0898-03 14A0898-04

Sample Matrix: Soil Soil Soil Soil Soil Soil

Units: ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg

Toxaphene NS NS <84.6 <85.2 <90.6 <88 <91.1 <89.5

Methoxychlor NS NS <8.36 <8.42 <8.95 <8.69 <9 <8.84

Heptachlor epoxide NS NS <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Heptachlor 42 420 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

gamma-BHC (Lindane) 100 280 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endrin ketone NS NS <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endrin aldehyde NS NS <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endrin 14 2,200 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endosulfan sulfate 2,400 4,800 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endosulfan II 2,400 4,800 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Endosulfan I 2,400 4,800 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Dieldrin 5 39 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

delta-BHC 40 100 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

gamma-Chlordane NS NS <1.67 <1.68 - - - -

alpha-Chlordane 20 910 <66.8 <67.3 - - - -

Chlordane, total NS NS <1.67 <1.68 <7.16 <6.95 <7.20 <7.07

beta-BHC 36 72 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

alpha-BHC 20 97 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Aldrin 5 19 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

4,4'-DDT 3.3 1,700 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

4,4'-DDE 3.3 1,800 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

4,4'-DDD 3.3 2,600 <1.67 <1.68 <1.79 <1.74 <1.80 <1.77

Units: ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg ug/kg

Aroclor 1260 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1254 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1248 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1242 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1232 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1221 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Aroclor 1016 NS NS <16.9 <17.0 <18.5 <17.9 <18.5 <18.2

Total PCBs 100 100 <16.9* <17.0* <7.38 <7.16 <7.41 <7.29NS : No standard established-: Not analyzed for*: Analyte is not certified or the state of the samples origination does not offer certification for the Analytemg/kg…miligram per kilogramug/kg…micrograms per kilogramEP-X blind duplicate sample as part of the QA/QC analysis

Polychlorinated biphenyls (PCBs)-EPA Method 8082

Table 4

Endpoint Soil Samples Pesticides/PCBs Analytical Results

5 West 125th Street, New York, NY

6 NYCRR Part 375-6.8(a)

Unrestricted Use Soil Cleanup Objectives

6 NYCRR Part 375-6.8(b)

Residential Use Soil Cleanup Objectives

Pesticides - EPA Method 8081

Page 85: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

TABLE 5

LIST OF SCO’S

Page 86: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

6-6

375-6.8 Soil cleanup objective tables.(a) Unrestricted use soil cleanup objectives.

Table 375-6.8(a):Unrestricted Use Soil Cleanup Objectives

Contaminant CAS Number Unrestricted Use

Metals

Arsenic 7440-38-2 13 c

Barium 7440-39-3 350 c

Beryllium 7440-41-7 7.2

Cadmium 7440-43-9 2.5 c

Chromium, hexavalent e 18540-29-9 1b

Chromium, trivalent e 16065-83-1 30 c

Copper 7440-50-8 50

Total Cyanide e, f 27

Lead 7439-92-1 63 c

Manganese 7439-96-5 1600 c

Total Mercury 0.18 c

Nickel 7440-02-0 30

Selenium 7782-49-2 3.9c

Silver 7440-22-4 2

Zinc 7440-66-6 109 c

PCBs/Pesticides

2,4,5-TP Acid (Silvex) f 93-72-1 3.8

4,4’-DDE 72-55-9 0.0033 b

4,4’-DDT 50-29-3 0.0033 b

4,4’-DDD 72-54-8 0.0033 b

Aldrin 309-00-2 0.005 c

alpha-BHC 319-84-6 0.02

beta-BHC 319-85-7 0.036

Chlordane (alpha) 5103-71-9 0.094

TABLE 3 - SOIL CLEANUP OBJECTIVES

Page 87: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(a):Unrestricted Use Soil Cleanup Objectives

Contaminant CAS Number Unrestricted Use

6-7

delta-BHC g 319-86-8 0.04

Dibenzofuran f 132-64-9 7

Dieldrin 60-57-1 0.005 c

Endosulfan I d, f 959-98-8 2.4

Endosulfan II d, f 33213-65-9 2.4

Endosulfan sulfate d, f 1031-07-8 2.4

Endrin 72-20-8 0.014

Heptachlor 76-44-8 0.042

Lindane 58-89-9 0.1

Polychlorinated biphenyls 1336-36-3 0.1

Semivolatile organic compounds

Acenaphthene 83-32-9 20

Acenapthylene f 208-96-8 100 a

Anthracene f 120-12-7 100 a

Benz(a)anthracene f 56-55-3 1c

Benzo(a)pyrene 50-32-8 1c

Benzo(b)fluoranthene f 205-99-2 1c

Benzo(g,h,i)perylene f 191-24-2 100

Benzo(k)fluoranthene f 207-08-9 0.8 c

Chrysene f 218-01-9 1c

Dibenz(a,h)anthracene f 53-70-3 0.33 b

Fluoranthene f 206-44-0 100 a

Fluorene 86-73-7 30

Indeno(1,2,3-cd)pyrene f 193-39-5 0.5 c

m-Cresol f 108-39-4 0.33 b

Naphthalene f 91-20-3 12

o-Cresol f 95-48-7 0.33 b

Page 88: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(a):Unrestricted Use Soil Cleanup Objectives

Contaminant CAS Number Unrestricted Use

6-8

p-Cresol f 106-44-5 0.33 b

Pentachlorophenol 87-86-5 0.8 b

Phenanthrene f 85-01-8 100

Phenol 108-95-2 0.33 b

Pyrene f 129-00-0 100

Volatile organic compounds

1,1,1-Trichloroethane f 71-55-6 0.68

1,1-Dichloroethane f 75-34-3 0.27

1,1-Dichloroethene f 75-35-4 0.33

1,2-Dichlorobenzene f 95-50-1 1.1

1,2-Dichloroethane 107-06-2 0.02 c

cis -1,2-Dichloroethene f 156-59-2 0.25

trans-1,2-Dichloroethene f 156-60-5 0.19

1,3-Dichlorobenzene f 541-73-1 2.4

1,4-Dichlorobenzene 106-46-7 1.8

1,4-Dioxane 123-91-1 0.1 b

Acetone 67-64-1 0.05

Benzene 71-43-2 0.06

n-Butylbenzene f 104-51-8 12

Carbon tetrachloride f 56-23-5 0.76

Chlorobenzene 108-90-7 1.1

Chloroform 67-66-3 0.37

Ethylbenzene f 100-41-4 1

Hexachlorobenzene f 118-74-1 0.33b

Methyl ethyl ketone 78-93-3 0.12

Methyl tert-butyl ether f 1634-04-4 0.93

Methylene chloride 75-09-2 0.05

Page 89: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(a):Unrestricted Use Soil Cleanup Objectives

Contaminant CAS Number Unrestricted Use

6-9

n - Propylbenzene f 103-65-1 3.9

sec-Butylbenzene f 135-98-8 11

tert-Butylbenzene f 98-06-6 5.9

Tetrachloroethene 127-18-4 1.3

Toluene 108-88-3 0.7

Trichloroethene 79-01-6 0.47

1,2,4-Trimethylbenzene f 95-63-6 3.6

1,3,5-Trimethylbenzenef 108-67-8 8.4

Vinyl chloridef 75-01-4 0.02

Xylene (mixed) 1330-20-7 0.26All soil cleanup objectives (SCOs) are in parts per million (ppm).

Footnotesa The SCOs for unrestricted use were capped at a maximum value of 100 ppm. See Technical SupportDocument (TSD), section 9.3.b For constituents where the calculated SCO was lower than the contract required quantitation limit (CRQL), theCRQL is used as the Track 1 SCO value.c For constituents where the calculated SCO was lower than the rural soil background concentration, asdetermined by the Department and Department of Health rural soil survey, the rural soil backgroundconcentration is used as the Track 1 SCO value for this use of the site.d SCO is the sum of endosulfan I, endosulfan II and endosulfan sulfate.e The SCO for this specific compound (or family of compounds) is considered to be met if the analysis for thetotal species of this contaminant is below the specific SCO. f Protection of ecological resources SCOs were not developed for contaminants identified in Table 375-6.8(b)with “NS”. Where such contaminants appear in Table 375-6.8(a), the applicant may be required by theDepartment to calculate a protection of ecological resources SCO according to the TSD.

Page 90: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

6-10

(b) Restricted use soil cleanup objectives.

Table 375-6.8(b): Restricted Use Soil Cleanup Objectives

Contaminant CASNumber

Protection of Public Health Protectionof

EcologicalResources

Protectionof

Ground-waterResidential Restricted-

Residential Commercial Industrial

Metals

Arsenic 7440-38-2 16f 16f 16f 16f 13f 16f

Barium 7440-39-3 350f 400 400 10,000 d 433 820

Beryllium 7440-41-7 14 72 590 2,700 10 47

Cadmium 7440-43-9 2.5f 4.3 9.3 60 4 7.5

Chromium, hexavalent h 18540-29-9 22 110 400 800 1e 19

Chromium, trivalent h 16065-83-1 36 180 1,500 6,800 41 NS

Copper 7440-50-8 270 270 270 10,000 d 50 1,720

Total Cyanide h 27 27 27 10,000 d NS 40

Lead 7439-92-1 400 400 1,000 3,900 63f 450

Manganese 7439-96-5 2,000f 2,000f 10,000 d 10,000 d 1600f 2,000f

Total Mercury 0.81j 0.81j 2.8j 5.7j 0.18f 0.73

Nickel 7440-02-0 140 310 310 10,000 d 30 130

Selenium 7782-49-2 36 180 1,500 6,800 3.9f 4f

Silver 7440-22-4 36 180 1,500 6,800 2 8.3

Zinc 7440-66-6 2200 10,000 d 10,000 d 10,000 d 109f 2,480

PCBs/Pesticides

2,4,5-TP Acid (Silvex) 93-72-1 58 100a 500b 1,000c NS 3.8

4,4’-DDE 72-55-9 1.8 8.9 62 120 0.0033 e 17

4,4’-DDT 50-29-3 1.7 7.9 47 94 0.0033 e 136

4,4’- DDD 72-54-8 2.6 13 92 180 0.0033 e 14

Aldrin 309-00-2 0.019 0.097 0.68 1.4 0.14 0.19

alpha-BHC 319-84-6 0.097 0.48 3.4 6.8 0.04g 0.02

beta-BHC 319-85-7 0.072 0.36 3 14 0.6 0.09

Chlordane (alpha) 5103-71-9 0.91 4.2 24 47 1.3 2.9

Page 91: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(b): Restricted Use Soil Cleanup Objectives

Contaminant CASNumber

Protection of Public Health Protectionof

EcologicalResources

Protectionof

Ground-waterResidential Restricted-

Residential Commercial Industrial

6-11

delta-BHC 319-86-8 100a 100a 500b 1,000c 0.04g 0.25

Dibenzofuran 132-64-9 14 59 350 1,000c NS 210

Dieldrin 60-57-1 0.039 0.2 1.4 2.8 0.006 0.1

Endosulfan I 959-98-8 4.8i 24i 200i 920i NS 102

Endosulfan II 33213-65-9 4.8i 24i 200i 920i NS 102

Endosulfan sulfate 1031-07-8 4.8i 24i 200i 920i NS 1,000c

Endrin 72-20-8 2.2 11 89 410 0.014 0.06

Heptachlor 76-44-8 0.42 2.1 15 29 0.14 0.38

Lindane 58-89-9 0.28 1.3 9.2 23 6 0.1

Polychlorinated biphenyls 1336-36-3 1 1 1 25 1 3.2

Semivolatiles

Acenaphthene 83-32-9 100a 100a 500b 1,000c 20 98

Acenapthylene 208-96-8 100a 100a 500b 1,000c NS 107

Anthracene 120-12-7 100a 100a 500b 1,000c NS 1,000c

Benz(a)anthracene 56-55-3 1f 1f 5.6 11 NS 1f

Benzo(a)pyrene 50-32-8 1f 1f 1f 1.1 2.6 22

Benzo(b)fluoranthene 205-99-2 1f 1f 5.6 11 NS 1.7

Benzo(g,h,i)perylene 191-24-2 100a 100a 500b 1,000c NS 1,000c

Benzo(k)fluoranthene 207-08-9 1 3.9 56 110 NS 1.7

Chrysene 218-01-9 1f 3.9 56 110 NS 1f

Dibenz(a,h)anthracene 53-70-3 0.33e 0.33e 0.56 1.1 NS 1,000c

Fluoranthene 206-44-0 100a 100a 500b 1,000c NS 1,000c

Fluorene 86-73-7 100a 100a 500b 1,000c 30 386

Indeno(1,2,3-cd)pyrene 193-39-5 0.5f 0.5f 5.6 11 NS 8.2

m-Cresol 108-39-4 100a 100a 500b 1,000c NS 0.33e

Naphthalene 91-20-3 100a 100a 500b 1,000c NS 12

Page 92: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(b): Restricted Use Soil Cleanup Objectives

Contaminant CASNumber

Protection of Public Health Protectionof

EcologicalResources

Protectionof

Ground-waterResidential Restricted-

Residential Commercial Industrial

6-12

o-Cresol 95-48-7 100a 100a 500b 1,000c NS 0.33e

p-Cresol 106-44-5 34 100a 500b 1,000c NS 0.33e

Pentachlorophenol 87-86-5 2.4 6.7 6.7 55 0.8e 0.8e

Phenanthrene 85-01-8 100a 100a 500b 1,000c NS 1,000c

Phenol 108-95-2 100a 100a 500b 1,000c 30 0.33e

Pyrene 129-00-0 100a 100a 500b 1,000c NS 1,000c

Volatiles

1,1,1-Trichloroethane 71-55-6 100a 100a 500b 1,000c NS 0.68

1,1-Dichloroethane 75-34-3 19 26 240 480 NS 0.27

1,1-Dichloroethene 75-35-4 100a 100a 500b 1,000c NS 0.33

1,2-Dichlorobenzene 95-50-1 100a 100a 500b 1,000c NS 1.1

1,2-Dichloroethane 107-06-2 2.3 3.1 30 60 10 0.02f

cis-1,2-Dichloroethene 156-59-2 59 100a 500b 1,000c NS 0.25

trans-1,2-Dichloroethene 156-60-5 100a 100a 500b 1,000c NS 0.19

1,3-Dichlorobenzene 541-73-1 17 49 280 560 NS 2.4

1,4-Dichlorobenzene 106-46-7 9.8 13 130 250 20 1.8

1,4-Dioxane 123-91-1 9.8 13 130 250 0.1e 0.1e

Acetone 67-64-1 100a 100b 500b 1,000c 2.2 0.05

Benzene 71-43-2 2.9 4.8 44 89 70 0.06

Butylbenzene 104-51-8 100a 100a 500b 1,000c NS 12

Carbon tetrachloride 56-23-5 1.4 2.4 22 44 NS 0.76

Chlorobenzene 108-90-7 100a 100a 500b 1,000c 40 1.1

Chloroform 67-66-3 10 49 350 700 12 0.37

Ethylbenzene 100-41-4 30 41 390 780 NS 1

Hexachlorobenzene 118-74-1 0.33e 1.2 6 12 NS 3.2

Methyl ethyl ketone 78-93-3 100a 100a 500b 1,000c 100a 0.12

Page 93: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Table 375-6.8(b): Restricted Use Soil Cleanup Objectives

Contaminant CASNumber

Protection of Public Health Protectionof

EcologicalResources

Protectionof

Ground-waterResidential Restricted-

Residential Commercial Industrial

6-13

Methyl tert-butyl ether 1634-04-4 62 100a 500b 1,000c NS 0.93

Methylene chloride 75-09-2 51 100a 500b 1,000c 12 0.05

n-Propylbenzene 103-65-1 100a 100a 500b 1,000c NS 3.9

sec-Butylbenzene 135-98-8 100a 100a 500b 1,000c NS 11

tert-Butylbenzene 98-06-6 100a 100a 500b 1,000c NS 5.9

Tetrachloroethene 127-18-4 5.5 19 150 300 2 1.3

Toluene 108-88-3 100a 100a 500b 1,000c 36 0.7

Trichloroethene 79-01-6 10 21 200 400 2 0.47

1,2,4-Trimethylbenzene 95-63-6 47 52 190 380 NS 3.6

1,3,5- Trimethylbenzene 108-67-8 47 52 190 380 NS 8.4

Vinyl chloride 75-01-4 0.21 0.9 13 27 NS 0.02

Xylene (mixed) 1330-20-7 100a 100a 500b 1,000c 0.26 1.6All soil cleanup objectives (SCOs) are in parts per million (ppm).

NS=Not specified. See Technical Support Document (TSD).

Footnotesa The SCOs for residential, restricted-residential and ecological resources use were capped at a maximum valueof 100 ppm. See TSD section 9.3.b The SCOs for commercial use were capped at a maximum value of 500 ppm. See TSD section 9.3.c The SCOs for industrial use and the protection of groundwater were capped at a maximum value of 1000 ppm. See TSD section 9.3.d The SCOs for metals were capped at a maximum value of 10,000 ppm. See TSD section 9.3.e For constituents where the calculated SCO was lower than the contract required quantitation limit (CRQL), theCRQL is used as the SCO value.f For constituents where the calculated SCO was lower than the rural soil background concentration asdetermined by the Department and Department of Health rural soil survey, the rural soil backgroundconcentration is used as the Track 2 SCO value for this use of the site.g This SCO is derived from data on mixed isomers of BHC.h The SCO for this specific compound (or family of compounds) is considered to be met if the analysis for thetotal species of this contaminant is below the specific SCO. i This SCO is for the sum of endosulfan I, endosulfan II, and endosulfan sulfate.j This SCO is the lower of the values for mercury (elemental) or mercury (inorganic salts). See TSD Table 5.6-1.

Page 94: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

1 Original should read “Tables 375-6.8(a) and (b)”

6-14

375-6.9 Development or modification of soil cleanup objectives.(a) Applicability. This section identifies when and the procedures under which a contaminant-

specific soil cleanup objective may be developed or modified.(1) Soil cleanup objectives for contaminants not included in Tables 375-6.8(a) and (b) may be

developed by the remedial party or required by the Department.(2) Soil cleanup objectives for contaminants included in Tables 375-6.8(a) and (b), may be

modified based on site-specific data if desired by the remedial party; as set forth in:(i) subpart 375-3 for Tracks 3 or 4, as set forth in paragraphs 375-3.8(e)(3) or (4),

respectively; or(ii) subparts 375-2 and 375-4, as set forth in subparagraph 375-2.8(b)(1)(iii) and

subparagraph 375-4.8(c)(1)(iii).(3) Protection of ecological resources soil cleanup objectives were not developed for certain

contaminants, which are identified in Table 375-6.8(b) as “NS”. Where such contaminants: (i) appear in Table 375-6.8(a), the applicant may be required by the Department to

calculate a protection of ecological resources soil cleanup objective for the contaminant for use in Track 1 andapply such soil cleanup objective where it is lower than the soil cleanup objective set forth in Table 375-6.8(a);or

(ii) are identified as impacting or threatening an ecological resource for a restricteduse remedial program the Department may require a protection of ecological resources soil cleanup objective bedeveloped.

(b) New soil cleanup objectives must:(1) Be developed utilizing the same methodologies that were used by the Department to

develop the respective soil cleanup objective, as provided in the Technical Support Document.(2) Apply the following caps, as set forth in section 9.3 of the Technical Support Document,

on any soil cleanup objective included in Tables 375-6.8(a) and (b), with the exception of metals, as set forth inparagraph (3) below, developed for:

(i) unrestricted use, residential use, restricted-residential use and the protection ofecological resources, a maximum value of 100 ppm;

(ii) commercial use, a maximum value of 500 ppm; and(iii) industrial use and the protection of groundwater a maximum value of 1000 ppm,

and(3) Apply a cap for metals at a maximum value of 10,000 ppm.

(c) Development of unrestricted use soil cleanup objectives. The unrestricted use soil cleanupobjective for a compound will be the lowest of the soil cleanup values, calculated as set forth in appendix E ofthe Technical Support Document, for the protection of groundwater, protection of ecological resources andprotection of public health.

(d) Development of restricted use soil cleanup objectives. The protection of: (1) Groundwater soil cleanup objective will be the values calculated for the protection of

groundwater as set forth in appendix E of the Technical Support Document;(2) Ecological resources soil cleanup objectives will be the values calculated for the

protection of ecological resources as set forth in appendix E of the Technical Support Document; and(3) Public health cleanup objective will be the values calculated for the protection of public

health for the identified use of the site, as set forth in appendix E of the Technical Support Document. (e) Modification of soil cleanup objectives. The contaminant-specific soil cleanup objectives setforth at Tables 675-6.8(a) and (b)1 may be modified by site specific data as set forth in this subdivision.

Page 95: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

6-15

(1) Contaminant-specific soil cleanup objectives modified in accordance with this subdivisionmay be utilized by the remedial party for a site remedial program undertaken pursuant to:

(i) subpart 375-3 in Tracks 3 or 4, as set forth in paragraphs 375-3.8(e)(3) or (4),respectively; or

(ii) subparts 375-2 and 375-4, as set forth in subparagraph 375-2.8(b)(1)(ii) andsubparagraph 375-4.8(c)(1)(ii).

(2) For the calculation of a protection of groundwater or ecological resources contaminant-specific soil cleanup objective, the site-specific percentage of total organic carbon in the soil at the site may besubstituted in the algorithms provided in appendix E of the Technical Support Document.

(3) For the calculation of a protection of public health contaminant-specific soil cleanupobjective, site-specific data may be used to modify two of the five exposure pathways, as follows:

(i) for the particulate inhalation pathway six parameters rely on site-specific data; and(ii) for the volatile inhalation pathway, four parameters rely on site-specific data.

(4) The algorithms to be used for each protection of public health pathway and details on theparameters which can be substituted are included in appendix E of the Technical Support Document.

(f) Use of soil cleanup objectives developed or modified. Once approved by the Department,contaminant-specific soil cleanup objectives developed or modified as set forth in this section may be utilized bythe Department at other sites consistent with paragraphs (1) and (2) below.

(1) Contaminant-specific soil cleanup objectives developed for contaminants not included inTables 375-6.8(a) and (b), as set forth in subdivision 375-6.9(b) above, will be used as guidance and shall beconsidered by the Department for inclusion in the Tables in this subpart during any subsequent reevaluation ofthe soil cleanup objectives, as set forth by ECL 27-1415.

(2) Contaminant-specific soil cleanup objectives modified for site specific parameters, as setforth in subdivision 375-6.9(e) above, may be utilized at sites manifesting similar parameters, if approved by theDepartment.

Page 96: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

TABLE 6

DISPOSAL QUANTITIES AND DISPOSAL FACILITIES

Page 97: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Date Trucking Company Truck Number/License Plate Manifest # Disposal Facility Quantity (yds)11/11/2013 Jaym Transportation LLC 969 / NJ AN-206Z 2767 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 7 / NJ AM-115U 2369 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 7 / NJ AM-115U 2370 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 1 / NJ AN-949X 2784 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 969 / NJ AN-206Z 2277 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 1 / NJ AN-949X 2787 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 7 / NJ AM-115U 2371 55 Pearl Street - Clean Bank 2011/11/2013 Jaym Transportation LLC 1 / NJ AN-949X 2783 55 Pearl Street - Clean Bank 2012/12/2013 Sky Materials 39 / 31687 TR 20331 Sky Materials 3612/12/2013 Sky Materials 41 / 32939 TR 16286 Sky Materials 3612/12/2013 Sky Materials 32 / 14172 TC 15336 Sky Materials 3612/12/2013 Sky Materials 40 / 15270 TC 16307 Sky Materials 3612/13/2013 Sky Materials 40 / 15270 TC 16311 Sky Materials 3612/13/2013 Sky Materials 33 / 25246-TR 15423 Sky Materials 3612/16/2013 Sky Materials 38 20139 Sky Materials 3612/16/2013 Sky Materials 41 / 32939 TR 16298 Sky Materials 3612/16/2013 Sky Materials 39 / 31687 TR 20336 Sky Materials 3612/16/2013 Sky Materials 33 / 25246-TR 20055 Sky Materials 3612/16/2013 Sky Materials 40 / 15270 TC 16315 Sky Materials 3612/17/2013 Sky Materials 41 / 32939 TR 10628 Sky Materials 3612/17/2013 Sky Materials 39 / 31687 TR 20340 Sky Materials 3612/18/2013 Sky Materials 39 / 31687 TR 20343 Sky Materials 3612/18/2013 Sky Materials 40 / 15270 TC 16318 Sky Materials 3612/18/2013 Sky Materials 41 / 32939 TR Sky Materials 3612/19/2013 Sky Materials 40 / 15270 TC 16323 Sky Materials 3612/19/2013 Sky Materials 39 / 31687 TR 20347 Sky Materials 3612/19/2013 Sky Materials 41 / 32939 TR 10637 Sky Materials 3612/20/2013 Sky Materials 40 / 15270 TC 20349 Sky Materials 3612/20/2013 Sky Materials 39 / 31687 TR 20803 Sky Materials 3612/20/2013 Sky Materials 41 / 32939 TR 10641 Sky Materials 3612/20/2013 Jaym Transportation LLC 1 / NJ AN-949X 118100 Fresh Kills - Clean Bank 2012/20/2013 Jaym Transportation LLC 7 / NJ AM-115U 118101 Fresh Kills - Clean Bank 2012/20/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118102 Fresh Kills - Clean Bank 2012/23/2013 Sky Materials 41 / 32939 TR 10647 Sky Materials 3612/23/2013 Sky Materials 40 / 15270 TC 20808 Sky Materials 3612/23/2013 Sky Materials 38 20154 Sky Materials 3612/23/2013 Jaym Transportation LLC 1 / NJ AN-949X 118103 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC M. Chiles #3 118104 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 7 / NJ AM-115U 118105 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 777 118106 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC Geormari #01 118107 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118108 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 7 / NJ AM-115U 118109 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 1 / NJ AN-949X 118110 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC M. Chiles #3 118111 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 777 118112 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC Geormari #01 118113 Fresh Kills - Clean Bank 2012/23/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118114 Fresh Kills - Clean Bank 2012/24/2015 Sky Materials 37 20872 Sky Materials 3612/24/2013 Sky Materials 41 / 32939 TR 19976 Sky Materials 3612/24/2013 Sky Materials 33 / 25246-TR 20077 Sky Materials 3612/26/2013 Jaym Transportation LLC 1 / NJ AN-949X 118115 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC Geormari #01 118116 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118117 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC 777 118118 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC Andrades #3 118119 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC M. Chiles #3 118120 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC 1 / NJ AN-949X 118121 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118122 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC Geormari #01 118123 Fresh Kills - Clean Bank 2012/26/2013 Jaym Transportation LLC 777 118124 Fresh Kills - Clean Bank 20

Table 6Disposal Qauntities and Facilities

5 West 125th Street, New York, NY

Page 98: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

12/26/2013 Jaym Transportation LLC Andrades #3 118125 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC 1 / NJ AN-949X 118126 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC M. Chiles #3 118127 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC Geormari #01 118128 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118129 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC 777 118130 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC 1 / NJ AN-949X 118131 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC M. Chiles #3 118132 Fresh Kills - Clean Bank 2012/27/2013 Jaym Transportation LLC Geormari #01 118133 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC Geormari #01 118134 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 1 / NJ AN-949X 118135 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC Andrades #3 118136 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 777 118137 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC M. Chiles #3 118138 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118139 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 1 / NJ AN-949X 118140 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 777 118141 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC Geormari #01 118142 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC M. Chiles #3 118143 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118144 Fresh Kills - Clean Bank 2012/30/2013 Jaym Transportation LLC Andrades #3 118145 Fresh Kills - Clean Bank 2012/30/2013 Sky Materials 37 16705 Sky Materials 3612/31/2013 Jaym Transportation LLC Geormari #01 118146 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 1 / NJ AN-949X 118147 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC Andrades #3 118148 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 777 118149 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC M. Chiles #3 118150 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118151 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC Geormari #01 118152 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC Andrades #3 118153 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 777 118154 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC M. Chiles #3 118155 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 969 / NJ AN-206Z 118156 Fresh Kills - Clean Bank 2012/31/2013 Jaym Transportation LLC 1 / NJ AN-949X 118157 Fresh Kills - Clean Bank 2012/31/2013 Sky Materials 37 Sky Materials 361/6/2014 Sky Materials 41 / 32939 TR 19991 Sky Materials 361/6/2014 Sky Materials 39 / 31687 TR 20310 Sky Materials 36

3/11/2014 Jaym Transportation LLC 7 / NJ AM-115U 118158 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 1 / NJ AN-949X 118159 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC Andrades #3 118160 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 777 118161 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118162 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC M. Chiles #3 118163 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 777 118164 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC Andrades #3 118165 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118166 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC M. Chiles #3 118167 Fresh Kills - Clean Bank 203/11/2014 Jaym Transportation LLC 1 / NJ AN-949X 118168 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 1 / NJ AN-949X 118169 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC Andrades #3 118170 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 7 / NJ AM-115U 118171 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 777 118172 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118173 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC M. Chiles #3 118174 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC Andrades #3 118175 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 7 / NJ AM-115U 118176 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 777 118177 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118178 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC M. Chiles #3 118179 Fresh Kills - Clean Bank 203/12/2014 Jaym Transportation LLC 1 / NJ AN-949X 118180 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 1 / NJ AN-949X 118181 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC M. Chiles #3 118182 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118183 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 7 / NJ AM-115U 118184 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 1 / NJ AN-949X 118185 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118186 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC M. Chiles #3 118187 Fresh Kills - Clean Bank 203/27/2014 Jaym Transportation LLC 7 / NJ AM-115U 118188 Fresh Kills - Clean Bank 20

Page 99: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

3/28/2014 Jaym Transportation LLC 1 / NJ AN-949X 118189 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC Andrades #3 118190 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118191 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC M. Chiles #3 118192 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC 7 / NJ AM-115U 118193 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC Andrades #3 118194 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC 1 / NJ AN-949X 118195 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC 7 / NJ AM-115U 118196 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC M. Chiles #3 118197 Fresh Kills - Clean Bank 203/28/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118198 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 1 / NJ AN-949X 118199 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC Andrades #3 118200 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118201 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC M. Chiles #3 118202 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 7 / NJ AM-115U 118203 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC Andrades #3 118204 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 1 / NJ AN-949X 118205 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 7 / NJ AM-115U 118206 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC M. Chiles #3 118207 Fresh Kills - Clean Bank 204/2/2014 Jaym Transportation LLC 969 / NJ AN-206Z 118208 Fresh Kills - Clean Bank 20

6/17/2014 Sky Materials Sky Materials 366/19/2014 Sky Materials 45 23599 Sky Materials 206/19/2014 Sky Materials 47 23091 Sky Materials 206/20/2014 Sky Materials 44 19329 Sky Materials 206/20/2014 Sky Materials 46 21664 Sky Materials 207/14/2014 Sky Materials 42 22458 Sky Materials 357/14/2014 Sky Materials 47 21701 Sky Materials 357/14/2014 Sky Materials 43 27216 Sky Materials 357/15/2014 Sky Materials 44 25898 Sky Materials 357/15/2014 Sky Materials 41 22738 Sky Materials 357/15/2014 Sky Materials 46 25946 Sky Materials 357/16/2014 All Suffolk Materials Inc. 15 8901 Sky Materials 357/16/2014 All Suffolk Materials Inc. 1 8951 Sky Materials 357/16/2014 All Suffolk Materials Inc. 57 1506 Sky Materials 357/16/2014 All Suffolk Materials Inc. 3 8804 Sky Materials 357/16/2014 All Suffolk Materials Inc. 1 5488 Sky Materials 357/16/2014 Sky Materials 48 21998 Sky Materials 357/16/2014 Sky Materials 46 22753 Sky Materials 357/16/2014 Sky Materials 45 25921 Sky Materials 357/16/2014 Sky Materials 43 27175 Sky Materials 357/16/2014 All Suffolk Materials Inc. 77 270948 Sky Materials 357/16/2014 All Suffolk Materials Inc. 23 264567 Sky Materials 357/16/2014 Sky Materials 44 19293 Sky Materials 357/16/2014 All Suffolk Materials Inc. 77 270949 Sky Materials 357/16/2014 All Suffolk Materials Inc. 23 264544 Sky Materials 357/16/2014 All Suffolk Materials Inc. 1 8853 Sky Materials 357/16/2014 All Suffolk Materials Inc. 1 8952 Sky Materials 357/17/2014 All Suffolk Materials Inc. 3 8806 Sky Materials 357/17/2014 All Suffolk Materials Inc. 63 4944 Sky Materials 357/17/2014 Sky Materials 44 19356 Sky Materials 357/17/2014 All Suffolk Materials Inc. 77 18056 Sky Materials 357/17/2014 All Suffolk Materials Inc. 23 21012 Sky Materials 357/17/2014 All Suffolk Materials Inc. 15 8902 Sky Materials 357/17/2014 All Suffolk Materials Inc. 3 8805 Sky Materials 357/17/2014 All Suffolk Materials Inc. 57 1507 Sky Materials 357/17/2014 Sky Materials 125 26678 Sky Materials 357/17/2014 All Suffolk Materials Inc. 1 8953 Sky Materials 357/17/2014 All Suffolk Materials Inc. 5489 Sky Materials 357/17/2014 All Suffolk Materials Inc. 1 8854 Sky Materials 357/18/2014 Sky Materials 44 19359 Sky Materials 357/18/2014 Sky Materials 46 22758 Sky Materials 357/21/2014 Sky Materials 46 25850 Sky Materials 357/21/2014 All Suffolk Materials Inc. 15 8904 Sky Materials 357/21/2014 All Suffolk Materials Inc. 63 4923 Sky Materials 357/21/2014 All Suffolk Materials Inc. 1 8855 Sky Materials 357/21/2014 All Suffolk Materials Inc. 23 21022 Sky Materials 357/21/2014 All Suffolk Materials Inc. 77 186 Sky Materials 357/21/2014 All Suffolk Materials Inc. 3 8807 Sky Materials 35

Page 100: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

7/21/2014 All Suffolk Materials Inc. 57 1508 Sky Materials 357/29/2014 All Suffolk Materials Inc. 1 8856 Sky Materials 357/29/2014 All Suffolk Materials Inc. 72 3541 Sky Materials 357/29/2014 All Suffolk Materials Inc. 98 5463 Sky Materials 357/29/2014 All Suffolk Materials Inc. 1 8857 Sky Materials 357/29/2014 All Suffolk Materials Inc. 72 3542 Sky Materials 357/29/2014 All Suffolk Materials Inc. 15 8906 Sky Materials 357/30/2014 All Suffolk Materials Inc. 77 18080 Sky Materials 357/30/2014 All Suffolk Materials Inc. 3 8808 Sky Materials 357/30/2014 All Suffolk Materials Inc. 57 1511 Sky Materials 357/30/2014 All Suffolk Materials Inc. 3 8809 Sky Materials 359/15/2014 All Suffolk Materials Inc. 3050 60312 Sky Materials 209/15/2014 All Suffolk Materials Inc. 3070 63055 Sky Materials 209/15/2014 All Suffolk Materials Inc. 6 7113 Sky Materials 209/15/2014 All Suffolk Materials Inc. 6 7116 Sky Materials 209/16/2014 All Suffolk Materials Inc. 6 7117 Sky Materials 209/16/2014 All Suffolk Materials Inc. Eagle 1 22186 Sky Materials 209/16/2014 All Suffolk Materials Inc. 3070 62609 Sky Materials 209/16/2014 All Suffolk Materials Inc. 3050 60316 Sky Materials 209/17/2014 All Suffolk Materials Inc. 44 22188 Sky Materials 209/17/2014 All Suffolk Materials Inc. 3070 62611 Sky Materials 209/17/2014 All Suffolk Materials Inc. 3050 60318 Sky Materials 209/17/2014 All Suffolk Materials Inc. 44 22190 Sky Materials 209/17/2014 All Suffolk Materials Inc. 6 7122 Sky Materials 209/18/2014 All Suffolk Materials Inc. 77 20180 Sky Materials 209/18/2014 All Suffolk Materials Inc. 15 20475 Sky Materials 209/18/2014 All Suffolk Materials Inc. 63 21736 Sky Materials 209/18/2014 All Suffolk Materials Inc. 44 22192 Sky Materials 209/22/2014 All Suffolk Materials Inc. 44 22198 Sky Materials 209/22/2014 All Suffolk Materials Inc. 77 20186 Sky Materials 209/22/2014 All Suffolk Materials Inc. 15 20484 Sky Materials 209/22/2014 All Suffolk Materials Inc. 3 21367 Sky Materials 209/23/2014 All Suffolk Materials Inc. 15 20487 Sky Materials 209/23/2014 All Suffolk Materials Inc. 3 21373 Sky Materials 209/23/2014 All Suffolk Materials Inc. 57 20255 Sky Materials 20

Total Yardage 597855 Pearl Street - Clean Bank 160

Fresh Kills - Clean Bank 2180Sky Materials 3638

Page 101: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

TABLE 7

BACKFILL QUANTITIES AND SOURCES

Page 102: MANHATTAN, NEW YORK Remedial Action Reportprtl-drprd-web.nyc.gov/html/oer/downloads/pdf/repository/NYCBCP... · 511 Canal Street, Suite 400, New York, NY 10013 (212) 924 - 3100 Nicole@hhbuilders.net

Date Material Source & Trucking Company Material Ticker No. Quantity (yds)10/11/2013 Sky Materials 3/4 STONE 159962 3612/12/2013 Sky Materials 57 STONE 160442 3612/12/2013 Sky Materials 57 STONE 160441 3612/13/2013 Sky Materials 57 STONE 160450 3612/13/2013 Sky Materials 57 STONE 160451 3612/17/2013 Sky Materials 57 STONE 160463 3612/17/2013 Sky Materials 57 STONE 160464 3612/18/2013 Sky Materials 57 STONE 20342 3612/18/2013 Sky Materials 57 STONE 160472 3612/19/2013 Sky Materials 3/4 STONE 160491 3612/19/2013 Sky Materials 57 STONE 160492 3612/20/2013 Sky Materials 57 STONE 160502 3612/20/2013 Sky Materials 57 STONE 160504 3612/20/2013 Sky Materials 57 STONE 160505 3612/24/2013 Sky Materials 57 STONE 160537 3612/24/2013 Sky Materials 57 STONE 160538 3612/24/2013 Sky Materials 57 STONE 160539 3612/30/2013 Sky Materials 57 STONE 16704 3612/30/2013 Sky Materials 57 STONE 160556 3612/31/2013 Sky Materials 57 STONE NA 3612/31/2013 Sky Materials 57 STONE 160571 361/6/2014 Sky Materials 57 STONE 160579 361/6/2014 Sky Materials 57 STONE 160580 36

6/19/2014 Sky Materials 57 STONE 160950 36864

Table 7Backfill Quantities and Sources

5 West 125th Street, New York, NY