NSW Department of Education | School Infrastructure schoolinfrastructure.nsw.gov.au Manly Vale Public School Information for parents, carers, students and staff November 2018 Artist’s impression: eastern view of the new buildings Manly Vale Public School is being upgraded to deliver new facilities, innovative learning spaces and provide for growing student enrolments in the area. a new hall innovative learning covered outdoor learning areas (COLA) a canteen a library New modern and teaching spaces and facilities for up to 1,000 primary school students new classrooms 40 enhanced open spaces The NSW Government is spending $6 billion over four years to deliver more than 170 new and upgraded schools. A further $160 million has also been invested as part of the record $747 million maintenance investment announced last year. This is the largest investment in public education infrastructure in the history of NSW.

Upload: others

Post on 02-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Manly Vale Public School · 2020-02-07 · Manly Vale Public School Information for parents, carers, students and staff November 2018 Artist’s impression: eastern view of the new

NSW Department of Education | School Infrastructure

schoolinfrastructure.nsw.gov.au

Manly Vale Public School Information for parents, carers, students and staffNovember 2018

Artist’s impression: eastern view of the new buildings

Manly Vale Public School is being upgraded to deliver new facilities, innovative learning spaces and provide for growing student enrolments in the area.

a new hall

innovative learning

covered outdoor learning areas (COLA) a canteen

a library

New modern and teaching spaces and facilities for up to 1,000 primary school students new classrooms

40

enhanced open spaces

The NSW Government is spending $6 billion over four years to deliver more than 170 new and upgraded schools. A further $160 million has also been invested as part of the record $747 million maintenance investment announced last year. This is the largest investment in public education infrastructure in the history of NSW.

Page 2: Manly Vale Public School · 2020-02-07 · Manly Vale Public School Information for parents, carers, students and staff November 2018 Artist’s impression: eastern view of the new

NSW Department of Education | School Infrastructure

Artist’s impression: view from near the corner of Sunshine and Gibbs streets

Access

GIBBS STREETENTRANCE

ENTRANCE

EXCAVATIONS WORKS

EXISTING BUILDINGS TO BE DEMOLISHED

MANLY VALE PUBLIC SCHOOL

Artist’s impression of access to new school buildings for Term 1, 2019

The project is being delivered in three stages.

Construction of the redeveloped school has been progressing well and is on track for completion early 2020.

Stage 1Stage 1 will be completed in time for Day 1, Term 1, 2019. It will comprise the construction of:

• 40-classroom block• Library• Canteen• A covered outdoor learning area

Teaching staff will have access to their classrooms during the school holidays, as needed.

Stage 2• Completion of the new hall• Refurbishment of the existing

administration building

Stage 3• Demolition of existing hall and buildings.• External works including landscaping.

The first day of the 2019 school year will be exciting for the students, teachers and parents at Manly Vale Public School as they access the new school buildings on the back half of the school site.

There will be a 40-classroom block, library, canteen and covered outdoor learning area ready for use. These were part of Stage 1 of the upgrade of the school.

It is important to be aware that works on the front half of the school site will be progressing throughout 2019. These works include:

• Completion of the new hall and the refurbishment of the existing administration building

• Demolition of existing hall and buildings. • External works including landscaping.

What this means for students, teachers and parents is that there will be dedicated access paths (shown by dotted red lines in the adjacent picture) through the front of the school site to get to the new buildings.

School Access Term 1, 2019

Staged Delivery

schoolinfrastructure.nsw.gov.au

Access

Page 3: Manly Vale Public School · 2020-02-07 · Manly Vale Public School Information for parents, carers, students and staff November 2018 Artist’s impression: eastern view of the new

Traffic Management

In the Development Application, there is a Traffic Control Plan. The Traffic Control Plan outlines the need for:

• 5-minute parking zones for pick up andset down

• an extended bus zone to accommodatethree buses

• a wombat crossing.

Other traffic measures will be put in place including converting council spaces to two minutes, installation of flashing lights for school zones, installation of a gravel surface car park and staggering school start and finish times.

Artist’s impression of completed school viewed from the east

Diagram of traffic measures in Sunshine and Gibbs streets

The health, safety and well-being of students, staff and our neighbours is our highest priority, and all necessary processes and measures will be implemented to ensure that the material is removed safely.

Construction areas on the school site will be separated by temporary construction fencing, just as they have over the past year.

Suite 102, 29-31 Solent CctBaulkham Hills, NSW 2153

P 02 8883 1113

F 02 9659 1800

E [email protected]

W www.diversi.com.au

DRG No.:PROJECT No.:

DATEDESIGNED

SCALE

TITLE:

PROJECT:

DATE

CHECKED

APPROVED

18102DEPARTMENT OF EDUCATION

GIBBS & SUNSHINE STREET, MANLY VALEPROPOSED ROADWORKS DETAIL DESIGN

DATE

Rev.:DATEREV AMENDMENT / DESCRIPTION BY APP'D DATEREV AMENDMENT / DESCRIPTION BY APP'D

Copyright © 2014 DIVERSI CONSULTING PTY LTD. THIS DRAWING AND THE INFORMATION IT CONTAINS REMAIN THE PROPERTY OF DIVERSI CONSULITNG PTY LTD. THIS DRAWING CANNOT BE COPIED OR REPRODUCED IN ANY FORM OR USED FOR ANY OTHER PURPOSE OTHER THAN THAT ORIGINALLY INTENDED WITHOUT THE PRIOR WRITTEN APPROVAL OF DIVERSI CONSULTING PTY LTD. DRAWING DIMENSIONS IN MILLIMETRES UNLESS NOTED OTHERWISE

NOT FOR CONSTRUCTION

CLIENT

0 4.0 8.0 12.0m1:200

4.0m 2.0

A 24/10/2018 L.T.C. APPROVAL JGC PGD

A

24/10/2018

24/10/2018

24/10/2018

C.S.R.

1:200 (A1)

'FOR APPROVAL'

DA10P.G.D.

CIVIL WORKS PLAN

J.G.C

WOMBAT CROSSING

SPACE FOR 3 BUSES

MANLY VALE PUBLIC SCHOOL

Construction areas

Page 4: Manly Vale Public School · 2020-02-07 · Manly Vale Public School Information for parents, carers, students and staff November 2018 Artist’s impression: eastern view of the new

NSW Department of Education | School Infrastructure

Working with us

Our commitment to act in the best interests of our stakeholders and the local community is at the forefront of our work.

We know the decisions we make will have a direct impact on our students, parents and carers, our staff and the local community.

Websitewww.schoolinfrastructure.nsw.gov.au

[email protected]

Phone1300 482 651

schoolinfrastructure.nsw.gov.au

Tell us what you think

We continue to be committed to working together with our school community and other stakeholders to deliver the best possible learning facilities for students.

Artist’s impression of north-east outlook from new buildings

Your feedback is important to us. For more information, questions or to make a comment: