manpower deployment table
DESCRIPTION
Manpower Deployment TableTRANSCRIPT
FAUZ Engineering PRIMAVERA PROJECT PLANNER Engro Rice Project REPORT DATE 19JUL10 RUN NO. 129 RESOURCE LOADING REPORT START DATE 10JUL10 FIN DATE 10SEP10* 22:13 DATA DATE 10JUL10 PAGE NO. 1 RL-09 Manpower Report PEAK USAGE FOR WEEK 5JUL 12JUL 19JUL 26JUL 2AUG 9AUG 16AUG 23AUG 30AUG 6SEPRESOURCE RESOURCE DESCRIPTION 2010 2010 2010 2010 2010 2010 2010 2010 2010 2010
FAB Fabricator 2 4 7 6 14 15 6FITTER Fitter 4 7 14 12 29 30 12HELPER Helper 3 5 6 13 21 27 26 18RIGGER Rigger 3 4 5 10 13 17 18 6T-WELDER Tack Welder 1 1 2 3 1 6 7 2WELDER Welder 3 4 6 13 10 14 12 REPORT PEAK 6 17 23 42 65 89 90 56