    Manzanilla-Mayaro Road Rehabilitation

    Project

    Programme for Upgrading Roads Efficiency

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    2/21

    The Manzanilla-Mayaro Road was rendered

    impassable as a result of severe structural breaches

    in the roads subsurface layers. A prima facie

    investigation pointed to the persistent inclementweather experienced over several days preceding

    the disaster as the precipitative cause of flooding

    and the resultant collapse of the roadway.

    CHALLENGE

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    3/21

    The Manzanilla/Mayaro Road:

    Approximately 20km in length.

    Connects Sangre Grande to Mayaro which

    comprises villages of Ortoire, St. Joseph, Beau

    Sejour, Plaisance, Pierreville, Beaumont, St. Ann's,Radix, Ste. Marguerite, Lagon Doux, Grand Lagoon

    and Lagon Palmiste.

    BACKGROUND

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    4/21

    LOCATION

    Figure 1 : Location Plan

    Alternative routes: Cunapo Southern Road and Plum Mitan

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    5/21

    LOCATION

    Figure 1 : Location Plan

    Alternative routes: Cunapo Southern Road and Plum Mitan

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    6/21

    PROJECT APPROACH

    In order to develop an all-encompassing solution to a

    disaster of this scale, the expertise and experience of a jointtask force was engaged, comprising :

    Highways Division

    Coastal Protection Unit Environmental, Health & Safety Unit

    PURE Unit (MOWI)

    Engineering Corps TT Army

    UWI (Department of Civil and Environmental

    Engineering and the Geomatics Department, of the

    Faculty of Engineering)

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    7/21

    PROJECT APPROACH

    Input was also sought from major stakeholders including:

    Environmental Management Agency

    Zoological Society

    Utility Agencies

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    8/21

    OBSERVATIONS

    Figure 2 : Existing Road Structure mainly consisting of layers of : Sand

    Boulders, Asphalt

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    9/21

    OBSERVATIONS

    Five road failures were initially observed:

    Figure 3: Failed Area #1

    Failed Area #1

    Distance from beach facility - 1.2kmLength 124m

    E 0713895

    N 1160844

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    10/21

    OBSERVATIONS

    Failed Area #2

    Length 106m

    E 0713944

    N 1160646

    Figure 4: Failed Area #2

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    11/21

    OBSERVATIONS

    Figure 5: Failed Area #3

    Failed Area #3

    Length 40m

    E 0713944

    N 1160311

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    12/21

    OBSERVATIONS

    Failed Area #4

    Length 140m

    E 0714022

    N 1159501

    Figure 6: Failed Area #4

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    13/21

    OBSERVATIONS

    Failed Area #5 -

    Length 140m

    E0714048

    N 1159145

    Figure 7: Failed Area #5

    Since our initial condition survey, latest reports indicate that a

    sixth failure has emerged and the other five failures have

    significantly deteriorated .

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    14/21

    PROJECT APPROACH

    Concurrent pursuit of both short- term and long

    term solutions in a phased integrated approach to

    Achieve project objectives.

    Phase 1 - Short Term: Restore Connectivity

    Reinstatement of roadway.

    Installation of Subsurface drainage.

    Phase 2 Medium to Long Term: Holistic water

    management - Coastal Protection Unit will discuss

    Coastal Protection.

    Wetland Conservation

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    15/21

    Road condition survey- 100%

    Topographical surveys- 100%

    Aerial reconnaissance - 100%.

    Report acquisition- In progress

    Geotechnical investigations- 90%

    Hydrological information.- In progress

    Tidal information.- In progress

    Bathymetric surveys.- To commence shortly

    Phase 1.1- DATA ACQUISTION

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    16/21

    Phase 1.2 SCOPE DEFINITION

    The philosophy for the restoration works are:

    A sustainable approach (temporary works will form

    part of the permanent solution.)

    Energy saving strategies for the restoration works

    will be considered such as; use of recycling

    technologies for salvaged and recovered materials

    will underlie the design. Establishment of utility corridor within the cross-

    section of the roadway.

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    17/21

    DESIGN CONCEPT

    Road structure founded on a reinforced flexiblestone, overlaid with a recycled stabilised layer

    comprising salvaged aggregate and asphaltic

    materials, and surfaced with hot mix asphalt.

    Encasement of the subsurface aggregate layers

    within water permeable geotextile membrane

    allows for water through flow while securing the

    structural integrity of the road.

    Geometry of the roadway will be constructed as

    to maintain the hydraulic balance.

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    18/21

    Phase 1.3 -PROJECT COST-TIME

    1.3.1 Preliminary Budget and schedule

    Estimated STAGE A Cost of Phase 1 construction -Approximately TT$57M

    Estimated Construction Duration: Two months.

    Projected Start Date: To be determined

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    19/21

    Phase 1.4 -CONSTRUCTION

    During this phase emphasis will be placed on

    Delivering connectivity at the shortest time frame.

    Construction of Temporary works - Coffer

    damming and dewatering in-order to mitigate

    flooding of the work zone.

  • 8/10/2019 Manzanilla-Mayaro Road Presentation from PURE

    20/21

    FIRST PHASE MISSION

    Restoration of Connectivity

    Reinstatement of roadway.