Maplewood Marine Restoration Project

Construction Environmental Management Plan

Prepared for: Vancouver Fraser Port Authority 100 The Pointe, 999 Canada Place Vancouver, BC V6C 3T4 Prepared by: Hemmera Envirochem Inc. 18th Floor, 4730 Kingsway Burnaby, BC V5H 0C6 File: 989-565-05 July 2018

Page 2: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood Marine Restoration Project CEMP - i - July 2018

TABLE OF CONTENTS

1.0 INTRODUCTION ........................................................................................................................ 1

2.0 PROJECT INFORMATION ......................................................................................................... 1

2.1 LOCATION ........................................................................................................................ 1

2.2 PROJECT DESCRIPTION ..................................................................................................... 3

2.3 PROJECT SCHEDULE ......................................................................................................... 4

2.3.1 Timing Windows................................................................................................. 4

2.4 SITE DESCRIPTION ............................................................................................................ 5

3.0 CONTACT INFORMATION AND RESPONSIBILITIES ............................................................... 6

3.1 KEY PROJECT PERSONNEL ................................................................................................ 6

3.2 ENVIRONMENTAL MONITOR RESPONSIBILITIES ..................................................................... 6

3.3 HEP ENVIRONMENTAL MONITOR RESPONSIBILITIES (INDEPENDENT MONITOR) ........................ 7

3.4 APPLICANT/CONTRACTOR RESPONSIBILITIES ....................................................................... 8

3.5 RELEVANT ENVIRONMENTAL PERMITS ................................................................................. 8

4.0 MITIGATION MEASURES AND ENVIRONMENTAL SPECIFICATIONS .................................... 9

4.1 GENERAL PRACTICES - MARINE WORKS .............................................................................. 9

4.2 SITE ACCESS, MOBILIZATION AND LAYDOWN AREAS ............................................................. 9

4.3 SEDIMENT CONTROL AND MANAGEMENT ............................................................................. 9

4.4 MACHINERY AND EQUIPMENT ........................................................................................... 10

4.5 AIR QUALITY .................................................................................................................. 11

4.6 NOISE ........................................................................................................................... 11

4.7 AQUATIC SPECIES AND HABITAT ....................................................................................... 11

4.8 TERRESTRIAL VEGETATION AND WILDLIFE MANAGEMENT .................................................... 13

4.9 ARCHAEOLOGICAL RESOURCES ....................................................................................... 13

4.10 NAVIGATION ................................................................................................................... 14

5.0 FUEL MANAGEMENT PLAN ................................................................................................... 15

6.0 WASTE MANAGEMENT .......................................................................................................... 16

7.0 EMERGENCY RESPONSE ...................................................................................................... 17

7.1 EMERGENCY COMMUNICATION ......................................................................................... 17

7.2 SPILL RESPONSE PLAN ................................................................................................... 18

8.0 REFERENCES ......................................................................................................................... 20

Page 3: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood Marine Restoration Project CEMP - ii - July 2018

List of Tables

Table 1 Proposed Construction Schedule .................................................................................... 4

Table 2 Project Contact List ........................................................................................................ 6

Table 3 Main Permits, Documents, and/or Exemptions and Approvals Anticipated ....................... 8

Table 4 Emergency Contact Numbers ....................................................................................... 17

List of Figures

Figure 1 Project Site Location and Layout..................................................................................... 2

List of Abbreviations and Acronyms

Abbreviation or Acronym Definition

BMP Best Management Practice

CD Chart Datum

CEMP Construction Environmental Management Plan

CEP Centerm Expansion Project

CRA Commercial, Recreational or Aboriginal

D50 Average (Median) Diameter

EM Environmental Monitor

EPP Environmental Protection Plan

HEP Habitat Enhancement Program

IM Independent Monitor

MBCA Migratory Birds Convention Act

MMRP Maplewood Marine Restoration Project

PER Project and Environmental Review

Project Maplewood Marine Restoration Project

QEP Qualified Environmental Professional

VFPA Vancouver Fraser Port Authority

VHF Very High Frequency

Page 4: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood Marine Restoration Project CEMP - 1 - July 2018

1.0 INTRODUCTION

The Maplewood Marine Restoration Project (MMRP, or “Project”) is a habitat enhancement project

proposed by the Vancouver Fraser Port Authority (VFPA) Habitat Enhancement Program (HEP). HEP is a

VFPA program whose goal is to balance a healthy environment with infrastructure development

opportunities. HEP creates and enhances fish and wildlife habitat for habitat banking purposes, use as

offsetting for port infrastructure projects, or a combination of both. MMRP is a proposed HEP project

anticipated to enhance approximately seven hectares of low-value marine habitat into higher-value

marine habitat for fish, birds, and other wildlife. Proposed habitat enhancements include creation of a tidal

channel, subtidal rock reef habitat, eelgrass habitat, and intertidal flat habitat.

The following Construction Environmental Management Plan (CEMP) was developed with reference to

VFPA’s Project and Environmental Review Guidelines – Construction Environmental Management Plan

(PMV 2015). This CEMP, prepared by Qualified Environmental Professionals (QEPs), describes how the

Project will be managed during construction to avoid adverse impacts to the environment. This CEMP is

based on the design and Project details outlined in the 60% Design Report (AECOM 2018).

Once the Project is awarded, the selected Contractor will be responsible for developing a Project-specific

Environmental Protection Plan (EPP) to avoid potential adverse environmental impacts based on specific

equipment and refined construction methodologies. The Contractor’s EPP will be reviewed by VFPA’s HEP and will be provided to VFPA’s Project and Environmental Review (PER) team to confirm that it

conforms to the requirements of this CEMP and any conditions of regulatory approvals/permits.

Throughout construction, the Contractor will ensure that all Project construction activities adhere to this

CEMP and the Contractor’s EPP, in addition to applicable regulatory requirements.

2.0 PROJECT INFORMATION

2.1 LOCATION

The Project lies within VFPA jurisdiction on the north shore of Burrard Inlet, approximately two kilometres

east of the Ironworkers Memorial Bridge. The Project is immediately south of a wildlife conservation area

(the Maplewood Flats Conservation Area), which is leased to Environment and Climate Change Canada

and is managed by the Wild Bird Trust of British ColumbiaFigure 1.

The Project site covers approximately seven hectares and consists of two distinct areas: The Northeast

Basin, centered at approximately 49°18’10” N and 123°00’05” W; and, the Southwest Channel area

(located in the Southern Intertidal Area), centered at approximately 49°17’55” N and 123°00’25” W

(Figure 1).

Page 5: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 2 - July 2018

Figure 1 Project Site Location and Layout

Page 6: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 3 - July 2018

2.2 PROJECT DESCRIPTION

Habitat in the Northeast Basin will be created by beneficially using approximately 87,000 m3 of dredge

material from the Southern Intertidal Area (resulting from the creation of the proposed Southwest

Channel), and approximately 95,000 m3 of imported clean fill material, to raise the elevation of the

existing substrate. Fraser River sand, or a suitable clean alternate (e.g., approved Sechelt sand), is

proposed as the additional fill material. This imported material is anticipated to be placed over the

dredge material from the Southwest Channel to form the upper sediment layer in the Northeast Basin.

The newly created intertidal flat habitat and shallow subtidal eelgrass habitat in the Northeast Basin will

be located between approximately +2.0 m and -2.0 m chart datum (CD). Construction of a rock dyke is

required to contain the fill material needed to establish the intertidal and shallow subtidal areas in the

Northeast Basin. Subtidal rock reef habitat south of the rock dyke, at the southernmost end of the

Northeast Basin, will be constructed by placing appropriately sized rock material between approximately

-3.0 m and -4.0 m CD. The rock reef habitat will be constructed using rock of varying diameter, with an

average (median) diameter (D50) of approximately 600 mm. A total of approximately 8,500 m3 of rock

material is anticipated to be placed in the Northeast Basin.

Rock reef habitat will also be created in the Southern Intertidal Area following dredging of the Southwest

Channel. The Southwest Channel will improve tidal flushing in the Maplewood Basin and enhance

nutrient transport, improve water quality, reduce siltation of marine vegetation, and facilitate suspension

and distribution of eggs and larvae of pelagic spawning fish and invertebrates, including marine

vegetation spores. A total of approximately 14,000 m3 of rock material will be placed in the Southwest

Channel, both along the base of the channel to function as subtidal rock reef habitat, and along the side

slopes of the excavated Southwest Channel to protect against scour from tidal currents as well as to

function as rock reef habitat. The rocks along the side slopes will have a D50 of approximately 500 mm,

and the rocks on the base of the channel will have a D50 of approximately 600 mm. The rock in the

Southwest Channel will be placed between approximately +2.0 m and -4.0 m CD.

Barge-mounted construction equipment will be required to cross over the shallow Southern Intertidal

Area during a high tide before the start of dredging. It is anticipated that the Southwest Channel will be

dredged using a barge-mounted clam-shell dredge. To facilitate placement of material from the

Southwest Channel into the Northeast Basin, it is anticipated that dredging will start from the inner (i.e.,

northeastern) end of the channel to avoid transporting and potentially grounding loaded, or partially-

loaded, scows on the shallow Southern Intertidal Area. Once the Southwest Channel is dredged to

design grade (i.e., -4.0 m CD), it is anticipated that loaded material scows will be able to enter/exit the

Project site during low tides (utilizing the Southwest Channel). Construction methodology details will be

refined as the Project advances to a procurement-ready stage.

Following construction, stabilization, and a final survey of the eelgrass bed location, native common

eelgrass (Zostera marina) will be transplanted from suitable donor beds into the Northeast Basin.

Page 7: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 4 - July 2018

2.3 PROJECT SCHEDULE

Detailed design, permitting, and consultation and engagement will be undertaken throughout 2018 and

2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction

schedule (AECOM 2018) is provided in Table 1. A detailed schedule will be determined following

procurement and Contractor selection.

Table 1 Proposed Construction Schedule

Task Proposed Dates

Mobilization Q3 2019

Southwest Channel Dredging and Rock Placement Q3 2019 to Q1 2020

Fill Placement in Northeast Basin – Dredged Material Q3 2019 to Q1 2020

Construction of Containment Dyke Q3 2019 to Q1 2020

Subtidal Rock Reef Construction at Toe of Containment Dyke Q3 2019 to Q1 2020

Fill Placement in Northeast Basin – Imported Fill Q3 2019 to Q1 2020

Habitat Establishment (e.g., Eelgrass Transplantation) Q1 2020 to Q4 2021

2.3.1 Timing Windows

The annual marine/estuarine timing window of least-risk for Burrard Inlet is August 16th to February 28th.

This refers to the time period of reduced risk for important commercial, recreational or Aboriginal (CRA)

fish species. The majority of the construction work is scheduled to occur during this least-risk timing

window to mitigate risk of negative effects to juvenile salmonids. However, due to the potential material

settlement time required for sediment placement in the Northeast Basin, material placement may extend

beyond the end of the least-risk timing window (e.g., post-February 28th). Any work outside the window

would occur with appropriate mitigation in place.

The federal Migratory Birds Convention Act, 1994 (MBCA) exists to protect and conserve migratory

birds—as populations and individual birds—and their nests. Under the MBCA, no person shall, without

lawful excuse, be in possession of a migratory bird or nest, or, buy, sell, exchange or give a migratory bird

or nest or make it the subject of a commercial transaction. This Act restricts the deposit of harmful

substances in waters or areas frequented by migratory birds. As there is minimal anticipated overlap

between birds covered under the MBCA and Project construction activities, either spatially (i.e., no

construction activities proposed in the upland) or temporally (i.e., the majority of construction is proposed

Page 8: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 5 - July 2018

outside the general nesting period of migratory birds1 in the region: mid-March to mid-August),

contravention of the MBCA is not anticipated.

However, the Project site is located adjacent to upland areas where there is potential to indirectly affect

birds and their active nests (e.g., due to noise). Should construction activities overlap with the general

nesting period of migratory birds in the region, extra precaution will be exercised to avoid causing harm to

birds and/or their active nests and eggs.

2.4 SITE DESCRIPTION

The Project site was historically an intertidal flat. Throughout the 1900s it was altered by activities

associated with dredging, gravel extraction, logging operations, and industrial use, resulting in the

development of the relatively deep Maplewood Basin (comprising the Northeast Basin and larger Main

Basin), and an intertidal area to the south of the Maplewood Basin, where the Southwest Channel is

proposed. Due to the depth, the lower portions of Northeast Basin (approximately -9.0 m CD) and Main

Basin are subject to poor flushing. Biological surveys have shown that, generally, the Project site has

relatively low habitat value with low diversity and abundance of marine life (Balanced 2017). The basins

are dominated by fine sediments. There is also some wood debris accumulation present in the Northeast

Basin from historic log handling operations.

A biophysical survey of the Project site was conducted in the fall of 2017 and consisted of both

underwater dive surveys and land-based assessments. Additional information on the assessments and

existing biological conditions is available in the Biophysical Survey (Balanced 2017) and the Ecological

Conditions Report (Hemmera 2018a). Archaeological assessments of the Project site (including an

Archaeological Overview Assessment and a Preliminary Field Reconnaissance) were undertaken in early

2018 (ILP 2018).

1 The general nesting period for migratory birds in Canada (Government of Canada 2017) covers most federally protected

migratory bird species; raptor nesting windows are more varied, and are described in Guidelines for Raptor Conservation During Urban and Rural Land Development in British Columbia (MOE 2013).

Page 9: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 6 - July 2018

3.0 CONTACT INFORMATION AND RESPONSIBILITIES

3.1 KEY PROJECT PERSONNEL

The following table (Table 2) provides the contact information of some of the key Project personnel. As

the Project has not yet been awarded, this list is preliminary only and will be updated in the Contractor’s

EPP following tender and award of the Project.

Table 2 Project Contact List

Name Company Role Phone Number

Charlotte Olson VFPA HEP Project Manager 604-665-9590

Lisa McCuaig VFPA PER Regulator 604-665-9527

TBD TBD Construction Manager TBD

TBD TBD Construction Foreman TBD

TBD TBD Environmental Monitor TBD

TBD TBD HEP Environmental Monitor

(Independent Monitor) TBD

3.2 ENVIRONMENTAL MONITOR RESPONSIBILITIES

To ensure adherence to the environmental protection objectives and conditions of Project permits and the

requirements of this CEMP and the Contractor’s EPP, the Contractor will be required to retain a QEP in

the role of the Project’s Environmental Monitor (EM), who will work on behalf of the Contractor. The EM

will need to be approved by VFPA’s HEP prior to Project commencement to ensure they meet the

qualifications as outlined in the Project procurement documents. The EM will be responsible for ensuring

that mitigation measures are properly implemented by the Contractor and are functioning as intended.

The EM may indicate that the mitigation measures be adapted if the need arises. Typical responsibilities

of the EM include those identified below; however, specific items may be updated based on refinements

to the construction methodology following selection of the Contractor and throughout construction.

• The EM will review the Contractor’s work procedures to ensure functionality and compliance with

this CEMP, the Contractor’s EPP and applicable regulations, standards and best management

practices (BMPs).

• The EM will communicate the requirements of Project permits, this CEMP and the Contractor’s EPP to the Project construction team members during pre-job and tailgate meetings.

• An appropriate schedule for environmental monitoring will be established between the EM,

Project Manager and regulatory agencies. The EM will be on-site as per the schedule established

between parties prior to Project start. However, the monitoring frequency may be adapted

depending on specific site conditions and work progress.

Page 10: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 7 - July 2018

o Monitoring events will be undertaken throughout construction at an appropriate frequency

based on the specific work tasks (e.g., dredging and fill placement), and potential for

adverse effects to occur.

o Monitoring will be conducted with greater frequency during periods of inclement weather

(e.g., heavy precipitation, and rough oceanic conditions).

o Full-time monitoring will be undertaken during start-up of any new phases of the Project

and during installation of environmental protection measures (e.g., installation of a silt

curtain).

• The EM will remain on-call during non-critical work periods to respond to emerging environmental

issues.

• The EM will support and liaise directly with the Contractor to provide technical advice for the

purpose of resolving situations that may affect the environment. The EM will advise the

Contractor if construction activities have caused, or are likely to cause, an environmental incident

and make recommendations for corrective action.

• The EM will have the authority to modify and/or halt any construction activity at any time if

deemed necessary for the protection of the environment.

• The EM will maintain complete records of activities related to the implementation of the CEMP

and Contractor’s EPP. This will include any measurements taken (e.g., pH, turbidity, temperature,

conductivity, etc.), photographs, analyses, and incident reports. The EM will document any

potential adverse effects to the environment and will include the nature of the effect, its cause,

mitigation and/or remediation measures implemented, and whether a work stoppage was

ordered. This will be used by the EM to complete and submit environmental monitoring reports to

the Contractor, which will subsequently be submitted to VFPA’s HEP.

3.3 HEP ENVIRONMENTAL MONITOR RESPONSIBILITIES (INDEPENDENT MONITOR)

VFPA’s HEP will also retain a QEP in the role of the Project Independent Monitor (IM) to provide auditing

level environmental services for the Project. The IM will be responsible for:

• Reviewing the Contractor’s EM reports.

• Conducting periodic spot checks of the Project site to verify compliance with this CEMP, the

Contractor’s EPP and applicable regulations, standards and BMPs. If deemed necessary for the

protection of the environment, the IM will have the authority to issue stop work orders.

• Submitting reports to VFPA’s HEP.

Page 11: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 8 - July 2018

3.4 APPLICANT/CONTRACTOR RESPONSIBILITIES

The Contractor will be responsible for ensuring that the Project is undertaken in accordance with the

conditions of the permits/approvals, this CEMP and the Contractor’s EPP as well as any applicable

federal, provincial and municipal regulations. The environmental responsibilities of the Contractor are

identified below; however, specific items may be updated based on refinements to the construction

methodology following selection of the Contractor and throughout construction.

• The Contractor will review conditions of the CEMP and their EPP with their field staff and sub-

contractors prior to commencing work. The Contractor will be responsible for ensuring that their

field staff and sub-contractors understand the BMPs for this Project and know how to properly

install protection measures.

• The Contractor will comply with written or verbal instructions from the EM with respect to

conducting activities in compliance with the mitigation measures outlined in this CEMP and

Contractor’s EPP, and per applicable regulations, standards and permits.

• The Contractor will correct deficiencies and any non-compliance issues upon direction from the

EM whether written or verbal. Corrections should be made as soon as reasonably possible,

ideally within 24 hours.

3.5 RELEVANT ENVIRONMENTAL PERMITS

Environmental permits, documents and/or exemptions that are anticipated to apply to the Project are

highlighted in Table 3. Note that obtaining other construction-related permits (e.g., scientific fish

collection permits) will be the responsibility of the Contractor conducting the works and these have not

been accounted for in Table 3.

Table 3 Main Permits, Documents, and/or Exemptions and Approvals Anticipated

Name Agency Comments

Category C Project and Environmental Review Permit

Vancouver Fraser Port Authority

This CEMP is included as part of a formal application submission to VFPA. Note: As the Project is within VFPA’s jurisdiction, it is not anticipated that Transport Canada will play a role in the navigation permitting process.

Centerm Expansion Project (CEP) Fisheries Act Authorization

Fisheries and Oceans Canada

VFPA is proposing to use a portion of MMRP as a fisheries habitat offsetting site for the proposed CEP. Conditions of the CEP Fisheries Act Authorization may include requirements applicable to the construction of MMRP.

Disposal at Sea Exemption for Beneficial Use

Environment and Climate

Change Canada

The Project will be reviewed by the Disposal at Sea Program due to placement of material within their jurisdiction.

Page 12: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 9 - July 2018

4.0 MITIGATION MEASURES AND ENVIRONMENTAL SPECIFICATIONS

The following section outlines environmental standards, guidelines and BMPs applicable to the Project.

Additional mitigation measures may also be outlined in the VFPA PER permit or may be provided by

other regulatory agencies. These will be incorporated into the Contractor’s EPP developed for the Project.

4.1 GENERAL PRACTICES - MARINE WORKS

Marine construction-related activities may take place from marine-based barges, derricks and scows.

Potential negative effects to aquatic resources during construction-related activities will be mitigated by

implementing appropriate measures as outlined below.

• The majority of the construction work is scheduled to occur during the Burrard Inlet least-risk

timing window (i.e., August 16th to February 28th). Any work outside the window would occur with

appropriate mitigation in place.

• During severe weather conditions (e.g., >70 km/h winds), work may be suspended if the

effectiveness of mitigation measures is reduced (e.g., silt curtain application during dredging

activity).

• Barges and other vessels will not ground on the foreshore or seabed, or otherwise disturb the

foreshore or seabed (including disturbance as a result of vessel propeller wash), excepting only

such disturbance as is reasonably required resulting from the use of barge spuds and anchors.

4.2 SITE ACCESS, MOBILIZATION AND LAYDOWN AREAS

Prior to construction, the method by which the Contractor plans to access the Project site and mobilize

construction-related equipment will be clearly described. Any challenges for site access or mobilization

will be identified. It is currently anticipated that construction equipment will need to mobilize to access the

Maplewood Basin during high tidal conditions at commencement of construction. However, additional

information including a drawing/figure showing access points and anchoring areas at the Project site, is

anticipated to be incorporated into the Contractor’s EPP. Mobilization will be planned to minimize the

number of trips to and from the Project site.

4.3 SEDIMENT CONTROL AND MANAGEMENT

The Contractor will not permit sediment, sediment-laden waters, or other deleterious substances to enter

the water during the Project. As described below, the Contractor will carry out all physical activities in a

manner that prevents induced sedimentation and induced turbidity of local waters, and the release of

sediment, sediment-laden waters, and turbid waters to the aquatic environment.

• Appropriate dredging equipment will be selected and operated in a manner that reduces spillage.

Page 13: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 10 - July 2018

• The direct or indirect release or deposit of sediment or sediment-laden water into the aquatic

environment outside the active work area (e.g., outside any silt curtains used for the Project), will

be minimized during the works. In this regard, reference will be made to the water quality criteria

described in the British Columbia Water Quality Guidelines (MOE 2018).

• Rock and fill materials (i.e., sand/silt) used for the Project will be demonstrated to be clean and

free of environmental contamination.2

• The placement of rock and fill material will occur in a controlled manner to limit generation of

suspended sediment and increased turbidity.

• While it is anticipated that dredged and placed sand will settle out of suspension relatively quickly

due to the high settling velocity of sand and the relatively low velocity of waters at the Project site

(AECOM 2018), it is anticipated that silt curtains will be used (e.g., Type III silt curtains that are

designed to withstand current velocities of up to 1.5 m/s (AECOM 2018)). Silt curtains will be

used, where technically feasible, to limit the release of turbid waters during dredging of the

Southwest Channel and placement of fill in the Northeast Basin.

4.4 MACHINERY AND EQUIPMENT

For machinery and equipment working on the Project site, the Contractor will ensure that:

• All machines and equipment are in good operating condition and meet applicable requirements

for serviceability and exhaust emissions. Equipment will be free of leaks, excess oil and grease.

• Equipment is cleaned off, and visually inspected for, invasive species and noxious weeds prior to

arriving on, and leaving, the Project site.

• Daily inspections are undertaken for all equipment used on the job.

• Equipment used around water is equipped with biodegradable hydraulic fluid, as is practical.

• Equipment maintenance occurs off-site, where and when possible. If equipment maintenance is

required on-site, activities will be undertaken overtop an impermeable layer.

• No equipment is washed within the Project area or near open water.

• Equipment is operated at optimum rated loads and is turned off when not in use to minimize

exhaust and noise emissions. Equipment producing excessive exhaust or noise will be repaired

or replaced.

• Refueling of equipment occurs in a contained area as far away from the water as possible.

Funnels and drip trays will be used to control on-ground spillage of fuel. The refueling area will

have a spill containment kit immediately accessible and personnel will be knowledgeable in the

use of the kit. 2 Physical and chemical characterization of the potential Source Sites (Southwest Channel and Fraser River sands)

and the Receiving Site (Northeast Basin) sediments was completed by Hemmera in 2018. The analyses indicated that sediment from the Source Sites is of better quality than the Receiving Site, and placement of material from the Source Sites is not likely to degrade the receiving environment since the concentrations of potential contaminants of concern appear to be less than the Receiving Site sediments (Hemmera 2018b).

Page 14: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 11 - July 2018

4.5 AIR QUALITY

The Project will be undertaken from water by barge. Upland activities (e.g., excavation with potential to

result in dust generation and/or track out of vehicles) are not anticipated. However, air emissions such as

equipment exhaust and vapours associated with marine construction-related activities will be minimized

and managed to avoid adverse health, safety, nuisance and other environmental effects on- and off-site.

The following standard BMPs for air quality will be applied for machinery working on the Project site:

• All equipment, vehicles and stationary emission sources will be well-maintained and used at

optimal loads to minimize emissions.

• Vehicles or equipment producing excessive exhaust will be repaired or replaced prior to being

used on the Project.

• Once a diesel engine/generator has reached its operating temperature, the engine will not be left

idling when no work is required.

• Stationary emission sources (e.g., portable diesel generators, compressors, etc.) will be used

only as necessary and turned off when not in use.

• Equipment and vehicles will be turned off when not in active use.

4.6 NOISE

Work is anticipated to occur outside VFPA’s standard regular working hours (i.e., Monday to Saturday

between 7:00 am and 8:00 pm, excluding holidays). The affected surrounding community will be notified

(as appropriate) of the nature and duration of noisy operations in advance of work taking place and/or

when work is required outside regular working hours.

Noise generation and vibrations resulting from equipment and associated activities during construction

will be addressed through appropriate noise management practices. The following BMPs will be

implemented to minimize noise generation:

• All equipment will be properly maintained to limit noise emissions and fitted with functioning

exhaust and muffler systems. Machine covers and equipment panels will be well-fitted and will

remain in place to muffle noise. Bolts and fasteners will be tight to avoid rattling.

• Engines will be turned off when not in use.

4.7 AQUATIC SPECIES AND HABITAT

Aquatic species such as fish, marine mammals and marine invertebrates have potential to be

encountered and/or affected by Project works.

• To minimize the risk of direct or indirect effects on fisheries species, the heavy construction work

(dredging activities and placement of materials) will take place during the applicable annual least-

Page 15: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 12 - July 2018

risk timing window (i.e., August 16th to February 28th), where possible. However, due to the

potential material settlement time required for sediment placement in the Northeast Basin,

material placement may extend beyond the end of the least-risk timing window (e.g., post-

February 28th). Any work outside the window would occur with appropriate mitigation in place.

• In the Northeast Basin, a pre-construction dive survey will be conducted in advance of fill

placement to inform the appropriate level of mitigation and salvage effort required (e.g., to assess

the density of crabs in the fill area). An aquatic life salvage (e.g., for crabs with the use of

perimeter crab traps) may subsequently be conducted in the Northeast Basin prior to the

placement of rock and fill materials. Salvaged organisms will be relocated to similar habitat

outside the Northeast Basin.

• In advance of dredging of the Southwest Channel a salvage of marine organisms will be

undertaken either during a low tide and/or during high tide via divers. Salvaged marine organisms

will be relocated to nearby appropriate habitats not affected by construction.

• Species to be targeted with salvage efforts in the Northeast Basin and Southwest Channel will be

CRA invertebrate species that may be present within the Project area including, but not

necessarily limited to, Dungeness crab (Metacarcinus magister), red rock crab (Cancer

productus), California sea cucumber (Parastichopus californicus) and urchins (Strongylocentrotus

spp.). Fin fish will not be targeted by the salvage as they are likely to move out of the work area

as construction activities begin.

• Sensitive marine habitats (e.g., existing nearby kelp and eelgrass communities) will be

appropriately marked (e.g., with buoys), georeferenced, and avoided during in-water works.

• Slow commencement of in-water construction activities is recommended to encourage mobile

aquatic species to leave the construction area.

• Mitigation measures as outlined in the sections above (e.g., in relation to noise, sediment control

and machinery/equipment) will be implemented to minimize negative effects to aquatic species

and their habitat.

• Marine mammal safety zones will be established around the Project site, including a 1,000 m

safety zone for cetaceans (whales, dolphins, and porpoises) and a 150 m safety zone for

pinnipeds (seals and sea lions). If a marine mammal enters its respective safety zone during in-

water construction activities, a work stoppage will be implemented if the marine mammal is at risk

of physical harm or is observed to be disturbed by construction activities. Construction activities

may only resume once the marine mammal has been confirmed to have left the safety zone or

has not been sighted for 30 minutes. While it is not anticipated that construction activities will

result in noise levels that exceed the acoustics thresholds of fish and marine mammals (i.e., no

pile driving is proposed as part of the Project), if activities are anticipated to result in the

generation of loud underwater noises, a marine mammal observer will be required to monitor the

noisy work and implement an underwater noise monitoring program.

Page 16: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 13 - July 2018

• Dependent on the specific construction methodology proposed, additional mitigation measures

will be incorporated into the Contractor’s EPP, as appropriate.

4.8 TERRESTRIAL VEGETATION AND WILDLIFE MANAGEMENT

Terrestrial vegetation is not anticipated to be affected as a result of the Project. In general, Project-related

effects to local terrestrial wildlife surrounding the Project areas are anticipated to be minimal and are

primarily limited to possible interactions with bird species that may use the Project area for foraging

and/or the surrounding area for nesting purposes. As such, negative construction-related effects to

terrestrial species will generally be limited to noise disturbance (see Section 4.6). To avoid attracting

wildlife to the Project site, an effective garbage management system will be implemented during

construction.

The majority of work is anticipated to occur during the fisheries least-risk timing window, outside of the

general nesting bird window. However, should construction activities extend into the general nesting

period of migratory birds in the region, extra precaution will be exercised to avoid causing harm to birds

and/or their active nests and eggs.

A known osprey nest (protected under the BC Wildlife Act (s.34b)) is located on a piling approximately

130 m southeast of the Northeast Basin. Due to the sensitivity of the Project being located adjacent to a

conservation area, it is recommended that a 100 m buffer plus 1.5 tree lengths (conservatively considered

20 m for this osprey nest on a marine pile) be implemented during Project construction as a best

management practice. Land contouring, dredging, construction, or any other unusual or sudden loud

activity will not be conducted within this 120 m buffer during the osprey breeding window (i.e., March 21

to September 5). This is in accordance with Guidelines for Raptor Conservation during Urban and Rural

Land Development in British Columbia (MOE 2013).

4.9 ARCHAEOLOGICAL RESOURCES

A recorded archaeological site (a fishweir) is situated in the existing intertidal flats immediately southeast

of the Northeast Basin. To mitigate potential effects to this archaeological resource during habitat

enhancement initiatives in the Northeast Basin, a 25 m buffer (archaeological site work avoidance zone)

will be implemented around the archaeological site. Crews will be briefed on the location of this work

avoidance zone (ILP 2018).

If the Contractor encounters, or expects to encounter an actual or potential archaeological resource

during construction activities, they will implement a Chance Find Procedure in alignment with the

following:

Page 17: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 14 - July 2018

• Immediately stop any activities that might disturb the archaeological resource or the site in which

it is contained.

• Not move or otherwise disturb the artifacts or other remains present at the site.

• Mark the location of the site to prevent additional disturbances.

• Immediately notify VFPA by email and phone.

4.10 NAVIGATION

To avoid conflict with other vessels and water users, the following BMPs will be implemented:

• Prior to the commencement of any vessel-related activities, the appropriate Canadian Coast

Guard and Marine Communication and Traffic Services centre will be notified regarding the

issuance of a Notice to Shipping to advise the marine community of potential hazards associated

with the Project.

• At least two days prior to commencing any construction or physical activities, the Harbour Master

and VFPA Environmental Programs will be notified.

• All vessels and equipment will be positioned in a manner that does not obstruct the line of sight to

navigational aids or markers.

• All vessels will exhibit appropriate lights and day shapes at all times.

• The Contractor will monitor the Very High Frequency (VHF) channel used for Marine

Communications and Traffic Services in the respective area at all times and participate as

necessary.

• The Contractor will be familiar with vessel movements in areas affected by the Project.

• The Project activities will not impede navigation or interfere with vessel operations.

• During night hours, equipment will be moored outside the navigation channel and lit in

accordance with all applicable regulations.

Page 18: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 15 - July 2018

5.0 FUEL MANAGEMENT PLAN

The Contractor’s EPP will identify areas for equipment re-fueling and show this on a site plan. The fuel

management plan will provide a bulleted list of measures being incorporated during construction to

ensure the receiving environment is adequately protected from construction-related fuels and products on

the Project site. The following BMPs will be used for fuel management:

• Adequate spill containment materials will be within refueling areas at all time.

• Bulk fuel will not be stored within the Project area to prevent the possibility of leaks or

contamination.

• Where feasible, pre-fueling of equipment will occur prior to arrival within the Project area to

reduce the potential for spills and leaks.

• For refueling of skiffs and other mobile equipment, the following refueling procedures will be

implemented:

o Make sure the vessel is secure.

o Measure the quantity that is required, to be able to anticipate when the tank is nearly full.

o Never leave the area unattended while refueling.

• Where possible, one area will be designated for fuel transfer (e.g., a flat area that minimizes

potential for fuel spills to enter the marine environment).

• Fuel, oil, chemicals and other hazardous materials will be placed in a lockable enclosure of

sufficient volume to contain a spill.

• Refueling equipment and tanks will be clean and in good working order. Fuel tanks should be

situated within appropriate secondary containment (an impermeable containment facility capable

of holding 110% of the storage tank contents). This may be achieved through the use of double-

walled storage tanks or sit-in containers constructed out of impermeable material, such as

aluminum or plastic.

• If transferring fuel from a mobile tank to large machines, sorbent material will be placed around

the fuel inlet prior to dispensing. Pumping equipment with an approved hose and top-fill nozzle

will be used and a proper connection between the fuel source and machine will be verified. The

fill valve will be open while transferring fuel.

• Receiving tanks will not be overfilled.

• Smaller equipment will be placed in portable secondary containment and refuelled using

approved jerry cans.

• Any transportation of dangerous goods (i.e., fuel and lubricating oils) for construction equipment,

will be carried out in conformity with the federal Transportation of Dangerous Goods Act.

Page 19: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 16 - July 2018

6.0 WASTE MANAGEMENT

Minimal construction waste is anticipated to be generated based on the nature of the Project. However,

the Contractor will maximize opportunities to reduce, reuse and recycle waste materials generated on the

Project site. All debris and waste material will be collected in the immediate working area within the

Project site. Waste material will be disposed at suitable upland locations. Contractors will adhere to all

applicable legislation with respect to the handling, transportation, and/or disposal of all materials related

to this Project (waste or otherwise). These regulations may include (but not be limited to) the BC

Hazardous Waste Regulations, Spill Reporting Regulations, Workers Compensation Board Regulations,

Transportation of Dangerous Goods Regulations, etc. The following BMPs will be implemented with

respect to waste management:

• Clean up of barges will be an ongoing maintenance activity.

• Any debris that is inadvertently lost overboard and deposited (floating or sinking) within the

marine environment will be recovered as soon as possible.

• Hazardous wastes generated could include waste petroleum products (e.g., engine oils and

lubricants) from machinery and equipment, spent batteries, solvents and cleaning agents, etc.

Contractors will provide labelled separate containers for potentially hazardous waste such as oily

rags and hydrocarbon absorbent pads.

• All hydrocarbon products and other hazardous wastes potentially present during construction will

be identified. The associated Workplace Hazardous Materials Information System and Materials

Safety Data Sheets of these products will be made available to all construction team members.

• All recyclable or compostable materials will be collected separately from general waste as per

Metro Vancouver Regional District requirements.

Page 20: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 17 - July 2018

7.0 EMERGENCY RESPONSE

An integral part of effective environmental management during construction-related activities is a

comprehensive emergency response plan, which when initiated, allows for the rapid response of

emergency services and/or the containment and cleanup of environmental emergencies. The following

section provides a general outline for an effective response plan. The Contractor will be responsible for

ensuring a specific response plan is incorporated into their EPP.

7.1 EMERGENCY COMMUNICATION

The Contractor’s EPP will include a communication plan, including contact information for all parties who

are responsible for the Project, or are critical to the response or reporting of accidents or environmental

emergencies such as spills of oil, fuel or chemicals to a receiving waterbody. VFPA, Environment and

Climate Change Canada, Fisheries and Oceans Canada and the Provincial Emergency Management BC

Program (formerly the Provincial Emergency Program) are to be notified of reportable incidents. Below is

an example contact table (Table 4).

Table 4 Emergency Contact Numbers

Agency Phone Number

Emergency Services 911

VFPA Operations Centre 605-665-9086

Local Non-Emergency Police 604-985-1311

Local Non-Emergency Fire 604-990-3682

Lions Gate Hospital

(231 15th Street East, North Vancouver) 604-988-3131

Vancouver General Hospital

(899 W 12th Avenue, Vancouver) 604-875-4111

BC Emergency Spill Reporting Line 1-800-663-3456

Canadian Coast Guard

1-800-889-8852 (Marine Pollution)

1-250-363-6333 (Navigation Hazard)

1-800-567-5111 (Search and Rescue)

Page 21: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 18 - July 2018

7.2 SPILL RESPONSE PLAN

Prior to commencement, the Contractor’s EPP will establish an appropriate spill prevention, containment

and clean-up plan for hydrocarbon products (including fuel, oil, and hydraulic fluid) and any other

deleterious substances using standards, practices, methods and procedures to a good commercial

standard. The Contractor will ensure that appropriate spill containment and clean-up supplies are

available at the Project site at all times, and that all personnel working on the Project are familiar with the

spill prevention, containment and clean-up plan.

The EPP developed by the Contractor will include measures to be implemented as part of the spill

response plan such as:

• Identification of any/all hazardous materials/products as well as waste storage and secondary

containment. Materials Safety Data Sheets will be kept at the Project site and made available to

all construction team members.

• Identification of the locations of spill response equipment and materials for containment and

clean-up (spill kits and contents) as well as instruction on how to use them effectively. Locations

of product/material storage and spill kits should be readily identified on a figure or map and

posted in an appropriate location at the Project site.

The following represents the minimum scope for spill response/management procedures:

• Assess safety – ensure unnecessary people are kept clear of the area and that people with

proper training and equipment deal with the spill. Put on any required personal protective

equipment and consult Material Safety Data Sheets.

• Stop the source – if required, and when it is safe to do so, stop the spill at its source. This may

simply be righting an overturned container or sealing a hole.

• Contain and control the spill – the spill should be prevented from infiltrating into the ground or

entering a waterbody. If the spill occurs on water, booms should be immediately deployed to

prevent its spread.

• Clean up the spill – utilize appropriate absorbent pads or other materials based on the type of

substance spilled. The method of disposing of the waste is dependent on the amount and type of

deleterious substance that was spilled.

• Notify appropriate authorities – spills of a reportable quantity will be reported to the appropriate

agencies. Minor spills will be reported to the EM.

• Record the incident – make a note of what, how and where the incident happened as well as

what was done to clean it up. Depending on the spill, further assessment of the effect to land and

water and/or additional cleanup may be required.

Page 22: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 19 - July 2018

When reporting a spill, the caller will provide the dispatcher with the following information, as accurately

as possible:

• Name and contact phone number of the person initiating the call;

• Name and telephone number of the person who caused the spill;

• Location and time of the spill;

• Type and quantity of the substance spilled;

• Cause and effect of the spill;

• Details of action taken or proposed;

• Description of the spill location and surrounding area;

• Names of agencies/responders on scene; and

• Names of other persons or agencies advised or to be advised concerning the spill.

Page 23: Maplewood Marine Restoration Project Construction ...€¦ · 2019. Construction is anticipated to commence in mid- to late-2019. A preliminary proposed construction schedule (AECOM

Vancouver Fraser Port Authority Hemmera Maplewood CEMP - 20 - July 2018

8.0 REFERENCES

AECOM. 2018. Maplewood Marine Restoration Project: Habitat Design – 60% Design Report. Prepared

for the Vancouver Fraser Port Authority.

Balanced Environmental Services Inc. (Balanced). 2017. Biophysical Survey: Maplewood Flats, North

Vancouver, British Columbia. Prepared for AECOM.

Hemmera Envirochem Inc. (Hemmera). 2018a. Existing Ecological Conditions: Maplewood Marine

Restoration Project. Prepared for Vancouver Fraser Port Authority.

Hemmera Envirochem Inc. (Hemmera). 2018b. Maplewood Marine Restoration Project Sediment

Characterization. Prepared for Vancouver Fraser Port Authority.

Inlailawatash Limited Partnership (ILP). 2018. Maplewood Marine Restoration Project: Archaeological

Overview Assessment. Prepared for Vancouver Fraser Port Authority.

Ministry of Environment (MOE). 2013. Guidelines for Raptor Conservation During Urban and Rural Land

Development in British Columbia. Best Management Practices, B.C. Ministry of Environment.

<http://www.env.gov.bc.ca/wld/documents/bmp/raptor_conservation_guidelines_2013.pdf>.

Accessed 15 Aug 2013.

MOE. 2018. British Columbia Approved Water Quality Guidelines: Aquatic Life, Wildlife & Agriculture:

Summary Report. Water Protection & Sustainability Branch, Ministry of Environment & Climate

Change Strategy. Accessed May 2018 <https://www2.gov.bc.ca/assets/gov/environment/air-land-

water/water/waterquality/wqgs-wqos/approved-

wqgs/wqg_summary_aquaticlife_wildlife_agri.pdf>.

Port Metro Vancouver. 2015. Project and Environmental Review Guidelines – Construction Environmental

Management Plan (CEMP). Accessed April 2018 <https://www.portvancouver.com/wp-

content/uploads/2015/10/PER-Construction-Environmental-Management-Plan-CEMP-Guidelines-

FINAL-2015-10-16.pdf >.