mark stout erg masters project

Upload: mark-stout

Post on 07-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Mark Stout ERG Masters Project

    1/181

    ERG Masters Project Mark Stout 1

    Energy and Resources Group Mark StoutMasters Project 5/25/1997

    Comparative Power Analysis of the California Electric

    Utility Industry Deregulation Process

    The Electric utility is changing. But unlike the evolution of species, consciouscollective choice can influence the evolutionary drift of the industry.

    Rodney E. Stevenson and David W. Penn (1995)

    Table of Contents

    INTRODUCTION................................................................................................................................................4

    OBJECTIVES...................................................................................................................................................... 5

    METHODOLOGY .............................................................................................................................................. 5

    HISTORY OF ELECTRIC UTILITY INDUSTRY REGULATION............ ............. ............. ............. ............. . 8

    THE BIRTH OF STATE PUBLIC UTILITY COMMISSIONS................................................................................................ 8FEDERAL POWER ACT OF 1935................................................................................................................................. 9

    PUBLIC UTILITY HOLDING COMPANY ACT OF 1935................................................................................................... 9PUBLIC UTILITY REGULATORY POLICIES ACT OF 1978 ............................................................................................ 10ENERGY POLICY ACT OF 1992 ............................................................................................................................... 10

    CPUC BLUE BOOK PROPOSAL............................................................................................................................ 12

    FERC MEGANOPR .............................................................................................................................................. 13CPUC MAY 1995 DRAFT PROPOSALS AND STAKEHOLDER RESPONSES .................................................................... 14CPUC DECEMBER 1995 DECISION AND CALIFORNIA ASSEMBLY BILL 1890............................................................. 17

    RECENT STATE AND FEDERAL ACTIVITY ................................................................................................................ 20

    FACTORS BEHIND THE DRIVE FOR DEREGULATION............. ............. ............. ............. ............. .......... 21

    LARGE CONSUMER PRESSURE ................................................................................................................................ 21TECHNOLOGY ....................................................................................................................................................... 23

    ECONOMIC RENT................................................................................................................................................... 23ACADEMICS & IDEOLOGUES .................................................................................................................................. 23

    EXISTING COMPETITIVE FORCES ............................................................................................................................ 24OTHER INDUSTRIES AND COUNTRIES ...................................................................................................................... 24FEDERAL REGULATORY POLICY ............................................................................................................................. 24

    STATE REGULATORY POLICY ................................................................................................................................. 26

    ANALYSIS......................................................................................................................................................... 27

    SELECTION OF STAKEHOLDER GROUPS ................................................................................................................... 29

    OVERVIEW OF WHAT THE STAKEHOLDERS WANTED AND WHAT THEY GOT ............................................................. 29STAKEHOLDER INTERVIEWS CLUSTER ANALYSIS .................................................................................................... 36OFFICEHOLDER STAFF INTERVIEWS ........................................................................................................................ 40

    Officeholder Staff Comments on Who Got What They Wanted and Why:.............. ............. ............. ............. ..... 41

    Synthesis of Stakeholder & Staff Comments on Who Prevailed, and Why:.............. ............. ............. ............. ... 43

  • 8/3/2019 Mark Stout ERG Masters Project

    2/181

    ERG Masters Project Mark Stout 2

    Officeholder Staff Comments on Who Got Rolled Over, and Why: ............ ............. ............. ............. ............. ... 44

    Synthesis of Stakeholder & Staff Comments on Who Got Rolled, and Why:................. ............. ............ ............ 46

    RESTRUCTURING STAKEHOLDER CAMPAIGN CONTRIBUTION/GIFT ANALYSIS........................................................... 52

    CONCLUSION............. ............. ............. ............. ............. ............. ............. ............. ............. ............... ............. .. 60

    BIBLIOGRAPHY.............................................................................................................................................. 61

    APPENDIX A: SEMI-STRUCTURED INTERVIEW QUESTIONS...... ............. ............. ............. ............. ..... 66

    STAKEHOLDER INTERVIEWS ................................................................................................................................... 66OFFICEHOLDER STAFF INTERVIEWS ........................................................................................................................ 66

    APPENDIX B: STAKEHOLDER INTERVIEWS.... ............. ............. ............. ............. ............. ............. .......... 67

    INVESTOR-OWNED ELECTRIC UTILITIES ................................................................................................................. 67Pacific Gas & Electric.... ............. ............. ............. ............. ............. ............. ............. ....................... ............. .. 67

    San Diego Gas and Electric ............................................................................................................................ 70

    Southern California Edison............................................................................................................................. 74

    MUNICIPAL ELECTRIC UTILITIES ............................................................................................................................ 76California Municipal Utilities Association - Interview #1 ............ ............. ............. ............. ............. ............. ... 76

    California Municipal Utilities Association - Interview #2 ............ ............. ............. ............. ............. ............. ... 79Sacramento Municipal Utility District............................................................................................................. 80

    UTILITY LABOR UNIONS ........................................................................................................................................ 85Coalition of California Utility Employees - Interview #1 ............ ............. ............. ............. ............. ................. 85

    Coalition of California Utility Employees - Interview #2 ............ ............. ............. ............. ............. ................. 86

    INDEPENDENT PRODUCERS .................................................................................................................................... 88 American Wind Energy Association............ ............. ............. ............. ............. ............. ............. ....................... 88

    Independent Energy Producers........................................................................................................................ 92

    LARGE ELECTRICITY CONSUMERS.......................................................................................................................... 96 Agricultural Energy Consumers Association............ ............. ............. ............. ............. ............. ............. .......... 96

    California Industrial Users............ ............. ............. ............. ............. ............. ............. ............. ............. .......... 98

    California Large Energy Consumers Association - Interview #1 ............. ............. ............. ............. ............. ... 102

    California Large Energy Consumers Association - Interview #2 ............. ............. ............. ............. ............. ... 104

    California Manufacturers Association........................................................................................................... 107

    SMALL ELECTRICITY CONSUMERS........................................................................................................................ 111Latino Issues Forum ...................................................................................................................................... 111

    The Utility Reform Network........................................................................................................................... 114

    ENVIRONMENTAL ADVOCATES ............................................................................................................................ 119Environmental Defense Fund ........................................................................................................................ 119

    Natural Resources Defense Council - Interview #1 ............. ............. ............. ............. ............. ............. .......... 122

    Natural Resources Defense Council - Interview #2 ............. ............. ............. ............. ............. ............. .......... 125

    Sierra Club/Center for Energy Efficiency and Renewable Technologies........................................................ 127

    Union of Concerned Scientists....................................................................................................................... 133

    STATE INSTITUTIONS........................................................................................................................................... 137California Energy Commission.......... ............. ............. ............. ............. ............. ............. ................... ........... 137

    University of California, California Institute for Energy Efficiency ................... ................... ................... ...... 141ANONYMOUS STAKEHOLDER COMMENTS ............................................................................................................. 144Anonymous Comments #1: Parties who could have improved their performance ............ ............. ............. ..... 144

    Anonymous Comments #2: AB 1890 funding levels for Public Interest RD&D............ ............. ............. ......... 144

    APPENDIX C: OFFICEHOLDER STAFF INTERVIEWS ............. ............. ............. ............. ............. .......... 146

    California Public Utilities Commission ......................................................................................................... 146

    Legislative Conference Committee, Office of Senator Steve Peace ................................................................ 148

    Legislative Conference Committee, Office of Senator Byron Sher......... ............. ............. ............. ............. ..... 152

    Legislative Conference Committee, Office of Senator Bill Leonard ............................................................... 153

  • 8/3/2019 Mark Stout ERG Masters Project

    3/181

    ERG Masters Project Mark Stout 3

    Anonymous Officeholder Staff Interview #1 ................................................................................................... 155

    Anonymous Officeholder Staff Interview #2 ................................................................................................... 156

    APPENDIX D: CLUSTER ANALYSIS OF STAKEHOLDER INTERVIEW DATA............. ............. ......... 159

    APPENDIX E: RESTRUCTURING STAKEHOLDER CAMPAIGN CONTRIBUTION/GIFT ANALYSIS

    DETAIL............................................................................................................................................................ 162

    Table 1: Assemblymember Jim Brulte, 1995 Campaign Contributions ............. ............. ............. ............. ....... 162

    Table 2: Assemblymember Jim Brulte, 1996 Campaign Contributions ............. ............. ............. ............. ....... 163

    1995/1996 Stakeholder Gift Information for Assemblymember Jim Brulte ..................................................... 164

    Table 3: Senator Steve Peace, 1995 Campaign Contributions ....................................................................... 164

    Table 4: Senator Steve Peace, 1996 Campaign Contributions ....................................................................... 165

    1995/1996 Stakeholder Gift Information for Senator Steve Peace......... ............. ............. ............. ............. ..... 166

    Table 5: Senator Byron Sher, 1995 Campaign Contributions......... ............. ............. ............. ............. ............ 166

    Table 6: Senator Byron Sher, 1996 Campaign Contributions......... ............. ............. ............. ............. ............ 166

    1995/1996 Stakeholder Gift Information for Senator Byron Sher ............ ............. ............. ............. ............. ... 170

    Table 7: Senator Bill Leonard, 1995 Campaign Contributions ...................................................................... 170

    Table 8: Senator Bill Leonard, 1996 Campaign Contributions ...................................................................... 171

    1995/1996 Stakeholder Gift Information for Senator Bill Leonard.............. ............. ............. ............. ............ 171

    Table 9: Assemblymember Mickey Conroy, 1995 Campaign Contributions.......... ............. ............. ............. ... 172Table 10: Assemblymember Mickey Conroy, 1996 Campaign Contributions........ ............. ............. ............. ... 173

    1995/1996 Stakeholder Gift Information for Assemblymember Mickey Conroy........... ............. ............. ......... 173

    Table 11: Assemblymember Diane Martinez, 1995 Campaign Contributions ........... ............. ............. ............ 175

    Table 12: Assemblymember Diane Martinez, 1996 Campaign Contributions ........... ............. ............. ............ 176

    Table 13: Assemblymember Steve Kuykendall, 1995 Campaign Contributions......... ............. ............. ............ 177

    1995/1996 Stakeholder Gift Information for Assemblymember Diane Martinez ............ ............. ............. ....... 177

    Table 14: Assemblymember Steve Kuykendall, 1996 Campaign Contributions......... ............. ............. ............ 178

    1995/1996 Stakeholder Gift Information for Assemblymember Steve Kuykendall........ ............. ............. ......... 178

    1994/1995 Stakeholder Gift Information for CPUC President Daniel Fessler...... ............. ............. ............. ... 179

    1994/1995 Stakeholder Gift Information for Commissioner Gregory Conlon ........... ............. ............. ............ 181

    1994/1995 Stakeholder Gift Information for Commissioner Jesse Knight, Jr. ............. ............. ............. ......... 181

    1994/1995 Stakeholder Gift Information for Commissioner Norm Shumway............ ............. ............. ............ 181

    1994/1995 Stakeholder Gift Information for Commissioner Josiah Neeper ............ ............. ............. ............. . 1811994/1995 Stakeholder Gift Information for Commissioner Henry Duque ............. ............. ............. ............. . 181

  • 8/3/2019 Mark Stout ERG Masters Project

    4/181

    ERG Masters Project Mark Stout 4

    Introduction

    On September 23, 1996, Governor Pete Wilson signed into law California Assembly Bill

    1890 (AB 1890), which sets in motion a process of electric utility deregulation beginning in 1998.

    This bill is an important milestone in an ongoing process towards electric utility deregulation in

    California. California electric utilities have a combined annual revenue of roughly $23 billion

    dollars1, selling 250 billion kWh of electricity per year2, a product with well documented

    environmental impacts including local air pollution, acid rain and climate change.3 According to

    the Environmental Defense Fund, fossil fuel-based electricity generation is currently the largest

    source of greenhouse gas emissions and the largest source of air pollution in the U.S.4 Given the

    stakes involved with this industry, there will probably be significant winners and losers as a result

    of this legislation. The vision of electric utility deregulation legislated in AB 1890 is significantly

    different from that contained in the California Public Utility Commissions (CPUC) December,

    1995 Electric Restructuring Decision, which will be superseded to a great extent by the details of

    AB 1890. Various stakeholder groups, representing a spectrum of private and public interests

    attempted to influence both the CPUC and legislative processes, with varying success. This paper

    develops a comparison of which stakeholder groups got what they wanted, and why, contrasting

    the results of CPUC process resulting in their December, 1995 Decision with the California

    legislative process resulting in AB 1890.

    1 CPUC RD&D Working Group, 19962 California Energy Commission, 19953 Flavin and Lenssen, 19944 WWW page: http://www.edf.org/programs/Energy/green_power/a_better.html

  • 8/3/2019 Mark Stout ERG Masters Project

    5/181

    ERG Masters Project Mark Stout 5

    Objectives

    Evaluate which stakeholder groups got what they wanted:Each stakeholder group influencing the process pursued policy outcomes that they felt were in

    their self-interest. This paper determines which groups had their requests granted, and whichhad their requests ignored, looking at both the language of AB 1890, as well as the CPUCDecember, 1995 decision. Groups that fared better in one arena than the other arehighlighted.

    Determine why or why not a stakeholder group was successful in getting what theywanted out of each policy process:

    In many cases, interest groups were able to influence outcomes in the legislative and/or CPUC

    forums through well reasoned comment filings, direct lobbying, campaign contributions, aswell as other avenues. This paper explores what mechanisms the different interest groupsused to influence these policy outcomes, contrasting differences in techniques applied between

    the Legislature and CPUC, focusing on whether each decision making body or individual hadparticular avenues that were most effective.

    Methodology

    In order to answer the questions of which stakeholder groups got what they wanted and

    why, I based my research on an analysis of three categories of data: 1) background utility

    regulation literature, 2) semi-structured interviews with stakeholders as well as CPUC and

    legislative staff, and 3) archival analysis of CPUC filings, legislative language and videos, and

    state officeholder filings. Rather than approaching the data with a hypothesis to verify, I compare

    and cluster the data to allow patterns to flow out that can then generate theories. I compare the

    CPUC and legislative policy processes, determining similarities and differences in how each party

    fared in each forum, as well as why each party fared as they did. This data-driven approach to the

    generation of theory is based on the work of Glaser and Strauss, who contrast the use of data to

  • 8/3/2019 Mark Stout ERG Masters Project

    6/181

    ERG Masters Project Mark Stout 6

    generate grounded theory with the use of data to verify logico-deductive theory.5

    Below I

    describe the use of each of these data types.

    Background literature on electric utility regulation is used to provide a historical context

    for Californias electric utility deregulation, which is presented in the next two sections of this

    report, History of Electric Utility Industry Regulation and Factors Behind the Drive for

    Deregulation.

    Semi-structured interviews were conducted with 26 representatives of different

    stakeholder organizations. The semi-structured format allows flexibility in altering the flow of the

    interview, following up on interesting points as they arise. I selected an initial set of organizations

    to contact, trying to cover as wide a spectrum of stakeholder groups as possible, based on my

    experience representing a stakeholder organization on the issue of electric utility deregulation in

    the CPUC and legislative arenas. Most interviews were conducted in person, while several where

    over the phone. As I conducted interviews, subjects referred me to additional representatives to

    contact, both in their organizations as well as in others. An interview guide was used for

    recording notes, which were typed up later. Questions were developed for the interview guide to

    determine for each organization what outcomes were sought, what outcomes were obtained in

    each of the policy decisions, and what methods and strategies were used to influence each policy

    decision. A list of questions for the semi-structured stakeholder interviews is included in

    Appendix A. A full transcript of these interviews is included in Appendix B. These interview

    subjects are clustered into the following categories for analysis: investor-owned electric utilities,

    municipal electric utilities, utility labor unions, independent producers, large electricity consumers,

    5 Glaser and Strauss, 1967, Glaser, 1978.

  • 8/3/2019 Mark Stout ERG Masters Project

    7/181

    ERG Masters Project Mark Stout 7

    small electricity consumers, environmental advocates, and state institutions. The organizations

    represented by each interview subject are listed, by category, in the Table of Contents for

    Appendix B.

    Semi-structured interviews were conducted with two staff of the CPUC and three staff of

    members of the legislative Conference Committee on Electric Industry Restructuring. An

    interview guide was used, with questions developed to determine which stakeholder organizations

    were perceived by the staff as being most effective in influencing the respective policy outcome,

    and why; which stakeholder organizations were perceived as being able to set the terms of the

    debate, and why; as well as which stakeholder organizations were perceived as least effective in

    influencing that policy outcome, and why. A list of questions for the semi-structured officeholder

    staff interviews is included in Appendix A. A full transcript of these interviews is included in

    Appendix C.

    Finally, an archival analysis was performed on the CPUC formal filings, Fair Political

    Practices Commission records, Secretary of State Political Reform Division records, proposed

    and final legislative language, as well as legislative conference committee videos. The CPUC

    filings can be used to cross-check what each major interested party had originally requested from

    the process, tracking how that may change over time, as well as to determine policy outcomes

    from the CPUC. The California Fair Political Practices Commission archives an annual Statement

    of Economic Interest for each state office holder. The EIS forms for the CPUC Commissioners

    and Conference Committee members were examined to determine which organizations used trips,

    events, meals, and other gifts to gain access to decision makers. The California Secretary of State

    Political Reform Division keeps Officeholder, Candidate, and Controlled Committee Campaign

    Statements on file for each elected state officeholder and candidate. These Statements were

  • 8/3/2019 Mark Stout ERG Masters Project

    8/181

    ERG Masters Project Mark Stout 8

    examined to track campaign contributions to the legislative Conference Committee members. The

    Divisions March, 1997 report onLobbying Expenditures and the Top 100 Lobbying Firms6 also

    gives a big-picture view of overall lobbying expenditures by stakeholders. Proposed AB 1890

    language was examined to get a flavor for who was making proposals, and how much of it was

    getting incorporated into the final AB 1890 language. The legislative Conference Committee

    videos were used to gain insights into the dynamics of this public hearing process, cross-check

    interview impressions, and experience the witty banter between Senators Steve Peace and Bill

    Leonard.

    History of Electric Utility Industry Regulation

    Before examining which stakeholder groups were able to influence the California electric

    utility deregulation process, a historical look at Federal and state electric utility regulation is in

    order.

    The Birth of State Public Utility Commissions

    Electric utilities have been considered natural monopolies over most of this century, due

    to decreasing marginal costs and the savings gained by avoiding redundant distribution networks.

    However, they were not always viewed this way, as Davis explains: Prior to World War I, most

    cities believed regulation was superfluous. Competition could keep prices down. Cities would

    grant multiple franchises to electricity companies... The result was not healthy competition

    keeping down the consumers bill, but many weak companies that were soon bought out by a

    strong one, thus leading to a monopoly. In the face of this trend local governments began to view

    6 California Secretary of State, March, 1997.

  • 8/3/2019 Mark Stout ERG Masters Project

    9/181

    ERG Masters Project Mark Stout 9

    utilities as natural monopolies and hence inevitable. This being the case the best solution seemed

    to be regulation by public commission.

    The early 1900s were marked by the rapid increase in electric utility regulation by state

    public utility commissions (PUCs) to address this natural monopoly character. Beginning in 1907

    with New York and Wisconsin, by 1922 47 states and the District of Columbia were regulating

    electric utilities.7

    Federal Power Act of 1935

    The growing interconnection of local utilities in interstate grids, with at least 20% of

    electricity crossing state lines in 1935, led to the passage of the Federal Power Act. Based on the

    Interstate Commerce Clause, this act expanded the role of the Federal Power Commission to

    regulate wholesale electric transfers.8

    Public Utility Holding Company Act of 1935

    In order to establish market power which would otherwise have been illegal under anti-

    trust law, electric utilities developed a pyramid scheme based on holding companies that was

    effective at obscuring market dominance. Hempling explains, Before passage of the Public

    Utility Holding Company Act of 1935 (PUHCA), a small number of holding companies owned

    most utilities in the United States. A number of these holding companies owned, or were owned

    by, large nonutility companies such as electric equipment contractors. State and Federal

    regulation of rates and securities failed to keep up with sophisticated holding company attempts to

    evade regulation. This legislation sought to avoid market abuses by limiting the size and

    7 Davis, 166-167.

  • 8/3/2019 Mark Stout ERG Masters Project

    10/181

    ERG Masters Project Mark Stout 10

    investment options of utilities so that each was confined in scope to an integrated public-utility

    system.910

    Public Utility Regulatory Policies Act of 1978

    Passed by Congress as part of President Carters National Energy Plan, PURPA aimed to

    set standards for state PUC ratemaking that would promote energy savings and be partial to

    residential consumers over industrial consumers. It also opened the door for more widespread

    wholesale competition by requiring that regulated utilities purchase power from Independent

    Power Producers (IPPs) classified as Qualifying Facilities (QFs) at avoided cost. In capacity

    constrained systems, this was the marginal cost associated with procuring new generation

    capacity. Qualifying Facilities were primarily cogeneration and small renewable energy electricity

    producers. PURPA was very significant in creating a market for non-traditional generators. The

    Federal Energy Regulatory Commission (FERC), recent successor to the FPC, was charged with

    writing the rules required to implement this legislation.11

    Energy Policy Act of 1992

    EPAct continued the Federal trend, started by PURPA, towards more competition in

    electricity generation. This legislation allowed FERC to order utilities to provide transmission

    access at non-discriminatory rates, which is critical for wholesale competition. It also created new

    8 Pechman, 17.9 Hempling, 343.10 Davis, 166-167.11 Pechman, 16.

  • 8/3/2019 Mark Stout ERG Masters Project

    11/181

    ERG Masters Project Mark Stout 11

    classes of IPPs including Exempt Wholesale Generators, allowing larger generation plants to be

    exempt from traditional regulation.12

    While encouraging wholesale competition, EPAct also aimed to level the playing field for

    supply-side and demand-side (energy efficiency) resource options. Energy efficiency is often

    underinvested in due to the high transaction costs of decentralized customer decisions, inadequate

    information available to customers,13 and the transient nature of short term building owners and

    renters. These lead to what the National Association of Regulatory Commissioners calls the

    payback gap: substantially higher rate of return expectations for energy efficiency measures

    compared to supply-side investments.14 Also, regulated utilities were discouraged from pursuing

    demand-side resources because of a profit structure that was directly linked to the amount of

    energy sold. One prominent utility regulator remarked on the situation that had developed in the

    1980s:

    In the current scheme of regulation, utilities make money in only one way--selling[units of energy]. Utilities lose money when customers engage in conservation.

    They likewise lose money when the encourage customers to engage in

    conservation. This money-losing proposition is not significantly improved by anyof the conservation cost recovery or incentive mechanisms now in use.15

    EPAct attempts to correct this supply-side/demand-side imbalance by encouraging state

    Public Utility Commissions to consider, 1) implementing Integrated Resource Planning (IRP),

    which compares supply- and demand-side options systematically when seeking least-cost energy

    12 Stevenson, Discretionary Evolution..., 356.13 Stevenson, Social Goals... 407.14 Cavanagh, Energy Efficiency Solutions... 521.15 Cavanagh, Global Warming and Least-Cost... 356-357.

  • 8/3/2019 Mark Stout ERG Masters Project

    12/181

    ERG Masters Project Mark Stout 12

    supplies, 2) providing cost recovery for energy efficiency programs that are at least as profitable

    as supply side measures, and 3) rate changes to encourage efficiency and distribution of power.16

    CPUC Blue Book Proposal

    Californias Public Utility Commission is widely viewed as a trend-setter for state PUC

    electric utility regulation. In April of 1994, the CPUC issued a staff proposal regarding electric

    utility deregulation known as the Blue Book, sending a shockwave through the electric

    industry.17 A security analyst noted that the release of the Blue Book will:

    speed up the deregulation of the industry, especially since the California regulators

    have been considered in the past to be one of the leading regulatory commissionsand many states have followed their recommendations.

    18

    The proposed deregulated electricity market would allow individual customers to choose

    their electricity generation supplier using bilateral contracts in a system known as retail wheeling

    or direct access. This utility restructuring involves the divestiture of utility electricity generation

    facilities into separate companies from the original utility which would still be responsible for

    transmission and perhaps distribution. These generation companies would then compete with

    Independent Power Producers (IPPs) to provide power to a central electricity grid operator based

    on a combination of pool-based wholesale competition as well as direct contracts with individual

    customers. The Blue Book laid out an aggressive, customer class-staged schedule for direct

    access implementation, with large, industrial customers taking power at the transmission level

    eligible on January 1, 1996, all commercial customers eligible January 1, 1999, and if successful,

    all residential consumers eligible on January 1, 2002. A more definitive policy statement was

    16 Haddad, 6.

    17 Hoffman, 55.18 Mydans.

  • 8/3/2019 Mark Stout ERG Masters Project

    13/181

    ERG Masters Project Mark Stout 13

    scheduled to be issued by the CPUC in August of 1994.19

    Since the release of the Blue Book

    proposal, numerous other states have also proposed electric utility deregulation.20

    Many stakeholders, including private and public-interest organizations, were concerned

    about the content and timetable of this proposal. For instance, environmental organizations were

    frightened by the Commissions decision to move away from the current IRP process and

    mechanism for decoupling utility profits from sales volumes. In their place, the CPUC proposed,

    alternative frameworks based on let the market decide, such as green pricing, where

    customers voluntarily pay more to promote renewables, and asserted that, a vibrant market exists

    for energy efficiency services.21 This stakeholder response, coupled with a lack of prior

    coordination with the state Legislature, prompted the Assembly Committee on Utilities and

    Commerce and the Assembly Committee on Natural Resources to hold a joint oversight hearing

    on May 23, 1994, where CPUC President Fessler and Commissioner Knight testified on their

    proposal. This led to the passage of Assembly Concurrent Resolution 143, which requires the

    CPUC to engage in a series of public hearings, evidentiary hearings, and documentation resulting

    in a report back to the Governor and Legislature by January 31, 1995. This process tempered the

    CPUCs frenetic timetable, pushing back their goal for a policy decision until September of

    1995.22

    FERC MegaNOPR

    In March of 1995, FERC released a dual-issue Notice of Proposed Rulemaking, which had

    been dubbed the MegaNOPR. The first issue addressed open access to the transmission system

    19 CPUC, 1994, Blue Book.

    20 Wagner, 1.21 CPUC, 1994, Blue Book, 1995, Status Report.

  • 8/3/2019 Mark Stout ERG Masters Project

    14/181

    ERG Masters Project Mark Stout 14

    for wholesale transactions, forcing utilities to allow non-utility generators to use their transmission

    systems on a comparable basis at standard tariffs, meaning the utilities could not discriminate

    against other electricity suppliers. The MegaNOPR also granted utilities the ability to collect

    100% of their stranded costs due to wholesale transactions. Stranded costs are past investments

    rendered uneconomic (market value less than book value) by the competition brought about

    through deregulation. Although stranded costs due to wholesale competition would be much

    smaller then those posed by retail competition, some thought the MegaNOPR ruling may set a

    precedent for 100% stranded cost recovery at the retail level, which is usually considered state

    jurisdiction.23

    CPUC May 1995 Draft Proposals and Stakeholder Responses

    As a result of the Blue Book CPUC staff proposal, in May of 1995, the California

    Commissioners released two draft proposals for pursuing rate deregulation in California. The

    majority proposal known as PoolCo, favored by CPUC President Fessler and two other

    Commissioners, is based on a common wholesale power pool, scheduled and dispatched by an

    independent system operator (ISO). Generators are scheduled into the pool based on time-based

    bids submitted to the ISO. A common price for all electricity in the state would then be set by the

    market clearing price based on the bids. All power purchases would be made through the pool.

    Retail contracts with a particular generator could be handled with separate contracts for

    differences.24

    22 CPUC, 1995, Status Report.

    23 Asmus and Smeloff, 1997.24 CPUC PoolCo Proposal

  • 8/3/2019 Mark Stout ERG Masters Project

    15/181

    ERG Masters Project Mark Stout 15

    Commissioner Knights alternate proposal is based on direct access contracts between

    generators and customers. No central entity would schedule power generation, although

    generators would submit projections to an independent system operator (OPCO), who is

    responsible for maintaining transmission system reliability. Prices would be determined either

    through bilateral contracts between direct access customers and generators, or through the

    creation of optional pools which could manage bids in a manner similar to the PoolCo proposal. 25

    In response to the Commissioner proposals, a group of seemingly influential special

    interests, Southern California Edison Company (one of three regulated, investor owned utilities in

    California), California Manufacturers Association, California Large Energy Consumers

    Association, and Independent Energy Producers, at the prompting of California Governor Pete

    Wilson, met to iron out differences between them and draft their own industry restructuring

    proposal, know as the Memorandum of Understanding (MOU). In structure, it is a hybrid of

    the two proposals, including bilateral contracts for direct access customers, as well as a central,

    wholesale pool. Bids for generation into the pool would be processed by a Power Exchange

    (PX), and the actual generation scheduling and dispatch decisions would be made by a separate

    Independent System Operator based on transactions mediated by the PX as well as direct access

    contracts. Full stranded cost recovery is agreed to for Edison, the only IOU signing the MOU.

    The MOU also proposed a nonbypassable charge to fund public policy programs. Out of this

    surcharge, funding levels for energy efficiency, renewables, and R&D were not to exceed 3.3% of

    total utility revenue requirements as of January 1, 1995, low-income ratepayer assistance would

    be funded at an uncapped, as-needed basis, and low-income weatherization would be funded at

    25 CPUC Direct Access Proposal

  • 8/3/2019 Mark Stout ERG Masters Project

    16/181

    ERG Masters Project Mark Stout 16

    1995 levels.26

    The CPUC held a full-panel hearing to focus on the details of the MOU in

    September of 1995.27

    Outraged that they had been left out of the MOU negotiating process, and at the level of

    attention given to the MOU, a coalition of public interest groups and renewable energy advocates,

    including NRDC, EDF, UCS, Utilities Consumer Action Network, and Towards Utility Rate

    Normalization (TURN) submitted a Framework for Restructuring in the Public Interest to the

    CPUC. The Framework, as a response to the MOU, does not actually propose a specific electric

    utility industry structure, but spells out a set of public interest concerns that should be addressed

    by any industry restructuring including mitigation of market power; small customer equity;

    continuation of low income programs; and continued progress for energy efficiency and renewable

    resources. The Framework calls for less than 100% stranded cost recovery, with utility

    shareholders accepting some of the burden for past, uneconomic investments. By combining this

    with effective Performance Based Ratemaking, (PBR), the Framework demands that each

    individual utility customer, including residential and small commercial consumers, should see short

    and long term rate reductions. The Framework calls for equitable opportunities for small

    consumer participation in any move to allow direct access. To enhance energy efficiency efforts,

    a new mechanism is to be developed, in the spirit of the existing Electric Revenue Adjustment

    Mechanism (ERAM), to decouple utility profits from sales volume. A minimum level of

    renewables is proposed for each IOU supply portfolio to return the states resource diversity to

    1993 levels. As in the MOU, a non-bypassable systems benefits charge is proposed, but with

    increased funding levels to restore energy efficiency and R&D spending at pre-Blue Book levels,

    26 MOU Parties, 1995.

    27 Framework Parties, 1995.

  • 8/3/2019 Mark Stout ERG Masters Project

    17/181

    ERG Masters Project Mark Stout 17

    expand renewables development above 1993 levels while commercializing new renewable energy

    technologies, and allow for uncapped low-income programs.28

    CPUC December 1995 Decision and California Assembly Bill 1890

    Building on their previous proposals and stakeholder input, the CPUC released a policy

    decision on December 20, 1995 which laid out a more defined vision of a deregulated utility

    environment, with several key implementation areas to be hammered out by stakeholder working

    groups. The December Decision mirrored the market structure defined in the MOU, based on a

    wholesale Power Exchange, bilateral, direct access contracts, and an Independent System

    Operator centrally controlling Californias transmission system. The Decision called for 100%

    stranded cost recovery by IOUs over a five year period, through a Competitive Transition Charge

    (CTC), coupled with an IOU rate cap at January 1, 1996 levels. The Decision also called for the

    voluntary divestiture of 50% of fossil fuel generation plant owned by the two largest IOUs,

    PG&E (Pacific Gas and Electric) and SCE, with financial incentives tied to the level of divestiture.

    For public purpose programs, the Decision proposed a nonbypassable public goods charge

    (PGC), as well as a minimum renewables purchase requirement. Aside from funding levels for

    low-income rate discounts, which should, be based on need, the Decision does not define any

    public program funding levels, nor a renewables purchase requirement level, requesting input from

    stakeholder working groups, so that input can be made to the Legislature.29

    The spring and summer of 1996 saw a flurry of deregulation activity as PUC working

    groups fleshed out options for moving towards the PUC vision, while the state Legislature took

    up the issue of electric utility deregulation on their own terms. A legislative conference

    28 Framework Parties, 1995.

  • 8/3/2019 Mark Stout ERG Masters Project

    18/181

    ERG Masters Project Mark Stout 18

    committee on deregulation worked at breakneck speed, cutting deals with the stakeholders that

    would be required to deliver the votes within the committee. Even given the large economic

    and environmental stakes, the final product of this bipartisan conference committee handily passed

    on the Senate and Assembly floors with minimal debate, since it was perceived as a best effort

    compromise between the two main political parties. As the PUC stakeholder working group

    process drew to an end, Pete Wilson signed AB 1890 on September 2330, omnibus legislation

    which preempts much of the PUC vision31

    . While the pace of the PUC process was tempered so

    that their final policy decision could better reflect stakeholder interests, compared to the reckless

    pace of the legislative wrangling, neither process involved substantial public education or

    participation. Several public interest organizations served as advocates for small consumer and

    environmental protection, but some have argued that the environmental organizations are not

    effectively representing the interests of their constituencies32.

    California Public Utilities Commission President Conlon praised members of the legislative

    conference committee: "It is through their tireless efforts that this legislation was crafted to

    provide balance of interests between utilities, other market participants, and especially residential

    and small commercial California ratepayers."33 However, TURN, a prominent, small consumer

    group, has criticized AB 1890, arguing that it should not be used as a national model for

    protection of residential and small commercial consumer interests.34 There is concern that

    29 CPUC, December, 1995 Decision, 1996 Roadmap30 CPUC press release, 199631 Rader, 199632 Weisman, 1997, and confidential correspondence with stakeholder representative.33 CPUC press release, 199634 TURN press release, 1996

  • 8/3/2019 Mark Stout ERG Masters Project

    19/181

    ERG Masters Project Mark Stout 19

    substantial market power exists among California electric utilities35

    , which may lead to higher

    electricity rates for small consumers purchasing out of a centralized Power Exchange envisioned

    by both the CPUC Decision and AB 1890 . AB 1890s questionable protection against utility

    market power, along with a guaranteed 100% cost recovery for uneconomic utility assets, indicate

    that electric utility shareholders faired better in the negotiations than small consumers 36. Large

    industrial customers are also likely to benefit disproportionately because of their ability to take

    advantage of contracts made directly with low cost electricity generators.

    An argument can be made that the final legislation will result in lower funding for public

    purpose programs, including renewable energy and energy efficiency, than would have occurred

    under the CPUCs December 1995 vision, but due to the Decisions lack of clarity about support

    levels, this is difficult to say. From some perspectives, renewable energy concerns faired poorly in

    AB 1890, with uncertain funding allocations that may not be able to support the existing base of

    California renewable energy generators, as well as the loss of a strong policy mechanism,

    endorsed in the CPUC Decision, to ensure the maintenance and growth of this renewables base37

    .

    Such an outcome was not unforseeable. Weeks before the passage of AB 1890, in a speech

    before the California Manufacturers Association, AB 1890 author Jim Brulte, said that the

    Legislature was going to, roll over renewables and roll over enviros.38

    Some public interest advocates would argue that moving ahead with the deregulation

    process, with a mix of shortcomings and unexpected benefits in the legislation, is in the public

    interest since it moves California utilities away from the paralysis and backsliding on our

    35 Borenstein, 199536 Rader, 199637 Rader, 199638 Asmus, 1996.

  • 8/3/2019 Mark Stout ERG Masters Project

    20/181

    ERG Masters Project Mark Stout 20

    environment/equity agenda which had gripped the industry since the release of the Blue Book in

    1994. As Carter and Cavanagh have noted, If the bill had failed, the California PUC was on a

    clear course to abandon all [funding for public purpose programs] on grounds of lack of statutory

    authority.39

    Recent State and Federal Activity

    Since the signing of AB 1890 into law, the CPUC and California Energy Commission

    (CEC) have been working towards the implementation of this legislation. In March of 1997, the

    CEC released a report to the legislature with policy recommendations for the allocation of up to

    $540 million renewables funding codified in AB 1890. It divides up this amount into four

    accounts that vary over four years of funding. The overall levels are: 45 % existing technologies,

    30% new technologies, 10% emerging technologies, and 15% consumer-side incentives.40

    On

    May 6, 1997, the CPUC released its latest restructuring decision which surprised stakeholders by

    announcing that all customers, including residential and small commercial consumers, would be

    eligible for direct access January 1, 1998.41

    There are currently several electric utility restructuring bills in Congress, including a

    prominent one authored by Representative Dan Schaefer (R-CO), chair of the House Energy and

    Power Subcommittee.42 This bill includes a "minimum renewable energy generation

    39 Carter and Cavanagh, 1996

    40 CEC, 199741 Marshall, 199742 Weisman, 1997, Primed for Congressional Battle

  • 8/3/2019 Mark Stout ERG Masters Project

    21/181

    ERG Masters Project Mark Stout 21

    requirement".43

    The Department of Energy (DOE) has also been circulating a draft bill that

    includes a Renewables Portfolio Standard.44

    Factors Behind the Drive for Deregulation

    Now that I have reviewed the history of Federal and state electric utility regulation, it is

    time to gain a fuller understanding of why California has proceeded down the path towards

    deregulation. Many forces have come together to create the push for electric utility deregulation

    in California.45

    Large Consumer Pressure

    Large industrial energy consumers have the most to gain from the lower electricity prices

    that may accompany greater industry competition. Davis explains their reasoning: the electric

    companies are inefficient, too conservative, and overcapitalized due to state regulation. Because

    the PUCs determine the rates, services, and future expansion, the companies have no incentive to

    be efficient. There is literally no profit in it for them. The state commissions typically calculate a

    companys profits as a return on investment. Therefore, if a company wants more revenue it must

    invest more capital. It has an incentive to build a new plant even if it is not really needed.46

    In California, these concerns are represented by the California Large Energy Consumers

    Association (CLECA), 12 companies--most foreign-owned--that really soak up the juice. Retail

    wheeling sits at the top of the agenda of this coalition of steel, cement, and one of the largest gold

    mining firms in the world. Barbara Barkovich, a consultant representing CLECA explains their

    43 Levison, 1997, Restructuring Hearings on the Road

    44 Levison, 1997, DOE Restructuring Bill45 Stevenson, Discretionary Evolution..., 355.

  • 8/3/2019 Mark Stout ERG Masters Project

    22/181

    ERG Masters Project Mark Stout 22

    viewpoint, We do not advocate a slash and burn approach, to existing public interest programs.

    We just want to use competition to get the best price for power.

    CLECAs national counterpart is the Electricity Consumers Resource Council (ELCON),

    24 companies that account of over 4% of the nations electricity use. There are some who are

    concerned about ELCONs environmental ethics in pursuing electric utility restructuring. V. John

    White, executive director of the Center for Energy Efficiency and Renewable Technologies

    remarks, At least you can talk to CLECA, and they say they know renewables, such as wind

    power, are now competitive. Thats one reason why they want to cut their own deals... ELCON,

    on the other hand, has no respect for the environment. A consultant who shares Whites

    perception of ELCON notes that they want to push California to adopt a policy as,

    uncompromised as possible because they fear the California plan will become a model for the

    country. If there are provisions for renewables and conservation here, they will have to gulp and

    swallow elsewhere.47

    The Clean Air Act amendments of 1990 set a precedent for Federal

    legislation following Californias leadership on environmental programs. As Davis notes,

    Balancing the demand for federal standards with the urgent need to reduce emissions in

    California was one of the primary challenges confronting Congress and the executive branch...

    The California Air Resources Boards old tailpipe emissions standards for new cars and light-duty

    trucks sold in that state were adopted by Congress in 1990 as the standard to be met by all new

    vehicles.48

    Davis describes the transition that has occurred in the influence of state PUCs, In the past

    the commissions had found their main constituents to be residential customers. Now they found

    46 Davis, 192.

    47 Asmus, 1995, Retail wheeling..., 24-25.

  • 8/3/2019 Mark Stout ERG Masters Project

    23/181

    ERG Masters Project Mark Stout 23

    intense pressure from large industrial customers, who in the past had enjoyed privileged status

    with cheap rates, but now had to pay higher rates. 49

    Technology

    The development of gas turbine generation technology has greatly reduced the scale

    requirements for efficient electricity generation. This reduction in scale has brought down the

    capital requirements of entering the electricity generation industry, enabling increased

    competition. Advancements in transmission line technology now allow the efficient transmission

    of electricity for distances of hundreds of miles, greatly increasing opportunities for bulk power

    sales.50

    Economic Rent

    The potential to capture higher profits offers a significant incentive for well-positioned

    electric utilities to pursue an end to price controls and enhanced opportunities to sell excess

    power outside of their service area.51

    Academics & Ideologues

    Neo-classical economists have argued since the 1970s for the deregulation of the electric

    utility industry, basing their arguments on welfare economics as applied to the changing electric

    utility landscape.52 The new industrial organization espoused by these economists has served as

    48 Davis, 1993, 150.

    49 Davis, 1993, 195.50 Flavin and Lenssen, 1994.51 Stevenson, Discretionary Evolution..., 356-357.52 Gilbert, 84-108, Gordon, 447-475, Hoffman 55-62.

  • 8/3/2019 Mark Stout ERG Masters Project

    24/181

    ERG Masters Project Mark Stout 24

    the academic rationale for the recent flurry of deregulation activity being pushed by free-market

    ideology,53 allowing a policy trend that emphasizes markets rather than social welfare.

    Existing Competitive Forces

    Although electric utilities are often viewed as pure monopolies, competition takes on

    several forms in this market. Many electrical applications have substitutable fuels, such as natural

    gas for space heating. Utilities compete for industrial customers who are relocating, as well as

    those on the border of service districts. There is significant competition in the wholesale electric

    generation market.54

    Since 1992, over half of new U.S. generating capacity has been supplied by

    alternative, non-utility providers.55

    Other Industries and Countries

    The deregulation of the telecommunications and natural gas industries serves as an

    analogy to the potential for electric utility deregulation. Examples of national electric utility

    deregulation have already been provided by the United Kingdom and Norway, allowing frequent

    comparisons between the California Blue Books proposed wholesale pool and a similar pool

    already implemented in the UK.56

    Federal Regulatory Policy

    By requiring utilities to pay avoided costs to the new class of qualifying facilities, the 1978

    Public Utility Regulatory Policies Act greatly invigorated the wholesale market for electric power.

    With this act, the camel of competition forced its nose under the monopoly tent, and it was only

    53 Stevenson, Discretionary Evolution..., 357.

    54 Stevenson, Discretionary Evolution..., 355-356.55 Flavin and Lenssen, 1994.

  • 8/3/2019 Mark Stout ERG Masters Project

    25/181

    ERG Masters Project Mark Stout 25

    a matter of time before it worked its way inside.57

    The qualifying facility clause of PURPA was

    originally intended to encourage generation resource diversity. Davis notes that it became used as

    a tool to inject competition into a regulated system, Ironically, the ascension of Reagan

    administration advocates of competition amplified the effect of PURPA, the product of President

    Carter and the Democratic Congress. Under Chairman Martha Hesse in the late 1980s, FERC

    vigorously supported competition for electricity, a policy it had already implemented in its natural

    gas decisions.58

    The Energy Policy Act of 1992 built on this competitive momentum, by requiring that

    utilities provide non-discriminatory transmission access for wholesale transactions, creating new

    classes of larger non-utility generators, including the Exempt Wholesale Generator, and deleting

    portions of the Public Utility Holding Company act to facilitate establishment of EWG/IPP-

    affiliates by regulated utilities.

    The recent restructuring bills in Congress have given incentives to state governments to

    act, in order that they maintain control of the regulatory process at the state level. Federal

    legislation could force states into retail competition on a set timetable. A recent announcement

    from Representative Schaefers office reads, During the 105th Congress, Schaefer held nine

    legislative hearings and heard from dozens of witnesses on the issue of breaking up the electricity

    monopoly. The resulting testimony convinced Schaefer that the current monopoly system is

    harming consumers. He has since introduced legislation (HR 655) that will give all consumers

    choice of their electric provider by December 15, 2000.59 As one environmental representative

    56 POWER Working Group, 1.57 Cook, 78.58 Davis, 195.59 Levison, 1997, Restructuring Goes on the Road

  • 8/3/2019 Mark Stout ERG Masters Project

    26/181

    ERG Masters Project Mark Stout 26

    has noted, the DOE bill does not mandate retail markets by any date certain, though it urges

    states to consider retail competition.60

    State Regulatory Policy

    Bidding programs for wholesale electric generation have been established in California,

    Colorado, Connecticut, Maine, Massachusetts, New York, and Wisconsin. Calls for bids have

    often been oversubscribed by a wide margin. In 1994, Michigan initiated a five year retail

    wheeling experiment involving two utilities, the same year that Californias Blue Book proposal

    was released.61

    California Public Utility Commissioners Jesse Knight and Norm Shumway, both

    appointees of Governor Pete Wilson, were the key retail wheeling champions within the CPUC,

    according to Jeff Dassovich, an analyst with CPUCs Division of Strategic Planning. Dassovich

    explained that they were frustrated with the myriad of complex and controversial balancing

    accounts and rate adjustment mechanisms they had to contend with every 12 months as part of

    the rate-making process. They became increasingly perplexed about the arcaneness and gridlock

    that seemed to pervade the utility resource planning process,62

    a form of integrated resource

    planning know as the BRPU. One of the stated proposals of the Blue Book is to eliminate the

    Biennial Resource Planning Update (BRPU), a proceeding in which the Commission attempts to

    determine how much capacity will be needed and structures the acquisition process in great

    detail.63

    This move towards greater reliance on the marketplace to make supply decisions is

    clearly in line with the free-market ideologies of the Republican Governor. Commissioner Knight,

    60 Levison, 1997, DOE Restructuring Bill

    61 Stevenson, Discretionary Evolution..., 355-356.62 Asmus, 1995, Retail wheeling..., 24.

  • 8/3/2019 Mark Stout ERG Masters Project

    27/181

    ERG Masters Project Mark Stout 27

    in a fit of political posturing, writes, Freeing Californians from the monopoly grip of the utilities

    and granting consumers direct access to competitive power suppliers will greatly benefit the

    states economy and enhance the quality of life in my state.64

    As of October, 1995, nineteen state legislatures have reviewed bills in response to the

    potential for greater competition in the electric utility industry, including authorizations for

    legislative and regulatory study committees as well as direct access for certain customers to

    alternative generators.65

    Analysis

    The California electric utility deregulation experience has often been described as a

    stakeholder-driven process. Many of the outcomes of the deregulation policy formulation were a

    result of negotiations between organizations representing different stakeholder groups. Based on

    my experience as a representative for an environmental organization, as well as interviews for this

    analysis, it was clear that the general public was not very involved in the process. As a

    staffperson for a prominent officeholder noted during our interview, There was not enough

    education or public involvement. As it was too esoteric a topic, so there was not enough press

    coverage. [see Anonymous Officeholder Staff Interview #1]

    Because of this stakeholder-representative orientation, I decided it would be insightful to

    interview people who represented stakeholder organizations that were active in the process, as

    well as the staff of the officeholders they were trying to influence. There are limits to this

    approach, in that not all interest groups who might be impacted by the process participated in the

    63 CPUC Blue Book, 32.64 Knight, Jesse J., letter to the editor, Wall Street Journal, October 9, 1995, A15(Western).

  • 8/3/2019 Mark Stout ERG Masters Project

    28/181

    ERG Masters Project Mark Stout 28

    negotiations. Lukes has argued that there are three views or dimensions of power. His one-

    dimensional view of power is based around observable actions by stakeholders. As Polsby has

    written, power may be analyzed by looking at, who participates, who gains and loses, and who

    prevails in decision-making... presumably people participate in those areas they care about the

    most. Their values, eloquently expressed by their participation, cannot, it seems to me, be more

    effectively objectified. Lukes second, two-dimensional view of power accounts for the

    development of a mobilization of bias explaining how a political institution can systemicly be

    biased towards a particular outcome, even without observable actions or non-actions by that

    institutions agents. As Goventa comments, on Lukes second face of power, by which power

    is exercised not just upon participants within the decision making process but also towards the

    exclusion of certain participants and issues altogether. In Lukes third, most radical view of

    power, he argues, A may exercise power over B by getting him to do what he does not want to

    do, but he also exercises power by influencing, shaping, or determining his very wants... in a

    contradiction between the interests of those exercising power and the real interests of those they

    exclude.66

    By talking with active stakeholder representatives and officeholder staff, I primarily

    focused on Lukes first dimension of power, observable actions between participants. The

    officeholder staff were also able to add insight on who was able to set the terms of the debate

    (who decided which issues were excluded), opening up the analysis to the second view of power,

    but only at a superficial level. Unfortunately, these interviews do not shed much light on the

    65 Sikkema, 2.

    66 Lukes, 1974, Goventa, 1980, p. 3-32

  • 8/3/2019 Mark Stout ERG Masters Project

    29/181

    ERG Masters Project Mark Stout 29

    exercise of power from Lukes most radical view, since such a broad analysis would be outside

    of the scope of this project.

    Selection of Stakeholder Groups

    In selecting stakeholder groups to focus on, I tried to cover as wide a range of participants

    as possible, talking with at least one prominent representative from a number of categories:

    investor-owned electric utilities, municipal electric utilities, utility labor unions, independent

    producers, large electricity consumers, small electricity consumers, environmental advocates, and

    a state institutions. I chose these categories based on personal experience representing a

    stakeholder organization in the process, as well as considering those used in a status report from

    the CPUC to the Legislature.67 As I extended my analysis with a summary of campaign

    contributions from stakeholders to the conference committee members, one important sub-

    category emerged because of its dominance: Oil and natural gas companies are often both large

    energy consumers, as well as independent producers.68 I have broken oil and natural gas

    companies out as a separate category in the tabulations of campaign contributions.

    Overview of What the Stakeholders Wanted and What They Got

    Before analyzing who got what they wanted, I first review what the different stakeholder

    groups wanted and got in both policy outcomes, based on 26 stakeholder interviews [see

    Appendix B], their comments on restructuring filed with the CPUC69, the December, 1995 CPUC

    Decision, and the final AB 1890 language.

    67 CPUC, 1995, Status Report...

    68 CPUC, 1995, Status Report...69 CPUC, 1995, Status Report...

  • 8/3/2019 Mark Stout ERG Masters Project

    30/181

    ERG Masters Project Mark Stout 30

    Investor Owned Utilities: The IOUs want to protect shareholders by maintaining their stock

    price and maximizing profits. Most resist retail competition, and pursue 100% stranded cost

    recovery from ratepayers.

    December Decision outcome: The IOUs did get the ability to recover 100% of

    stranded costs, including billions of dollars in rate settlements for PG&Es Diablo

    Canyon and SCEs SONGS nuclear plants. A five year phase-in to direct access may

    have been a little too fast for Edison, which was the strongest proponent of starting

    with a wholesale-only PoolCo proposal.

    AB 1890 outcome: The legislation codified the utilities opportunity to recover 100%

    of stranded costs. While recovery period is limited to four years may limit their ability

    to achieve the full 100% cost recovery, they are comforted by a negotiated settlement

    that was reached to avoid future litigation.

    Municipal Utilities: The munis want to retain their autonomy in making their own policy

    decisions, while ensuring their financial solvency. Most resist retail competition and pursue the

    ability to recover 100% of stranded costs from ratepayers, who are also their shareholders.

    December Decision outcome: The CPUC Decision did not address municipal utilities,

    except for on the subject of reciprocity for allowing direct access, where there was

    considerable support for staying clear of muni autonomy: We have previously

    acknowledged that we do not have the authority to impose our vision on municipal or

    public power entities. Under legal mandates which we scrupulously respect the

    governance of these entities and their relation to their customers are committed to

    their duly constituted governing authorities. The inclusion of direct access was not

    embraced by munis.

  • 8/3/2019 Mark Stout ERG Masters Project

    31/181

    ERG Masters Project Mark Stout 31

    AB 1890 outcome: The municipal utilities lost autonomy in making decisions about

    direct access as a tradeoff to ensure their ability to collect stranded costs. An

    unexpected positive outcome was the improved leverage munis gained over IOUs,

    since AB 1890 required the munis and IOUs to work together on joint filings to FERC

    for the Power Exchange and ISO. As the lobbyist for the Sacramento Municipal

    Utility District points out, If the IOUs do not respect the munis, we can point to the

    legislation, enhancing our stature at the federal level. [see interview, Appendix B]

    The inclusion of direct access was not embraced by munis.

    Utility Labor Unions: Unions would like to protect the income of their members while faced

    by a down-sizing industry. They are strong proponents of maintaining system reliability as this

    requires adequate staffing, leading to an overlap of their interests with public interests. They

    resist retail competition, and pursue ratepayer support for worker severance payments and

    retraining.

    December Decision outcome: Although the Decision does allow for the collection of

    IOU employee severance and retraining costs in the CTC, it does not focus on

    maintaining system reliability.

    AB 1890 outcome: The legislation allows for the collection of IOU employee

    severance and retraining costs in the CTC, while going further to directly support the

    goals of system reliability through adequate inspection and maintenance. AB 1890

    also requires that IOU-divested generation plants come with two-year contracts for

    operation and maintenance by the existing staff.

  • 8/3/2019 Mark Stout ERG Masters Project

    32/181

    ERG Masters Project Mark Stout 32

    Independent Producers: Independent generators want to protect the sanctity of their existing

    contracts, ensuring their continued financial well-being, while having access to new customers

    made available to them. Most are proponents of direct access.

    December Decision outcome: Although the CPUC supports the renegotiation (buy-

    out) of Standard Offer contracts with qualifying facilities, it leaves these negotiations

    as voluntary, protecting the sanctity of the QF contracts. Short-run avoided cost

    (SRAC) payments to QFs are to be set to the market-clearing price in the Power

    Exchange, resulting in generally higher prices paid to generators. Independent

    producers gain access to new customers through the adoption of direct access.

    AB 1890 outcome: The legislation nearly mirrors the CPUC Decision in terms of

    impacts on independent producers.

    Renewable Technology Independent Producers: As a subset of independent generators, the

    renewables industry would like to rebound from difficult financial times many of them are

    facing due to the sunset or failure of previous policy support mechanisms. They would like

    continued funding to reflect the public goods benefits offered by their technologies (such

    decreased air pollution), while having access to new customers willing to pay more for

    green power.

    December Decision outcome: The CPUCs endorsement of the Renewables Portfolio

    Standard was applauded by existing renewable energy generators, although a lack of

    specificity in the policy language with regard to percentage levels for the minimum

    renewables purchase requirement was a cause for concern. Direct access with

    community-based aggregation of load would help facilitate the development of

    bilateral green pricing contracts with residential customers. As with non-renewable

  • 8/3/2019 Mark Stout ERG Masters Project

    33/181

    ERG Masters Project Mark Stout 33

    independent producers, SRAC set according to the Power Exchange market clearing

    price should result in higher payments to QFs under contract.

    AB 1890 outcome: Many renewables generators were disappointed with the

    replacement of a policy mechanism that had known outcomes, the RPS, with one that

    had known costs, renewables funding through a systems benefits charge. Some argue

    that the level of funding is too low to maintain the current state renewables base and

    will end in 2002, resulting in an industry shakeout. However, this industries financial

    woes are not solely because of deregulation, and AB 1890 does provide a significant

    amount of money to existing renewables developers to help mitigate any downsizing in

    the industry. As with non-renewable independent producers, SRAC set according to

    the Power Exchange market clearing price should result in higher payments to QFs

    under contract.

    Large Industrial & Agricultural Customers: The large consumers want the most efficient,

    competitive market possible to drive down rates. They support granting the IOUs less than

    100% stranded cost recovery, and want a choice of their electricity supplier, making them the

    strongest proponents of direct access.

    December Decision outcome: Large customers did get the market structure they

    desired, allowing bilateral, direct access contracts. They lost out on rather generous

    terms for collection of stranded costs by the IOUs, which could extend until 2005.

    AB 1890 outcome: Again, large customers won on the inclusion of direct access. As

    in the December Decision, IOUs still have the opportunity to collect 100% of their

    stranded costs, but limiting the competitive transition charge (CTC) cost recovery to

    4.25 years greatly increased large electricity consumers satisfaction with the deal.

  • 8/3/2019 Mark Stout ERG Masters Project

    34/181

    ERG Masters Project Mark Stout 34

    Small Consumers: Small consumer advocates want any restructuring that occurs to have net

    benefits for even the least well off individual. They resist retail competition, want an equitable

    user class phase-in schedule for direct access, and support community aggregation for

    residential ratepayers to take advantage of bilateral contracts with low cost generators. Low

    income consumer advocates want IOUs to continue their low income assistance programs

    (baseline rate, low-income weatherization) on an as-needed basis, and have adequate customer

    education programs and protection from fraud put into place.

    December Decision outcome: Small consumer and low income advocates lost in their

    opposition to a market structure allowing direct access, as well as in their opposition

    to 100% stranded cost recovery by the IOUs. Small consumers benefited from the

    inclusion of language on community aggregation to allow residential customers some

    benefits from direct access. Funding for low income programs was good, with no cap

    on low income rate assistance. In principle, the consumer education and protection

    language was well received, although more specific details were required.

    AB 1890 outcome: As in the CPUC Decision, small consumer and low income

    advocates lost in their opposition to a market structure allowing direct access, as well

    as in their opposition to 100% stranded cost recovery by the IOUs. Small consumers

    benefited from the inclusion of language on community aggregation to allow

    residential customers some benefits from direct access, although the anti-slamming

    language in the bill may make this unworkable if it is not fixed in this sessions clean-

    up legislation. Funding for low income programs was good, with no cap on low

    income rate assistance. Language on consumer education and protection did not go

    far enough in addressing the needs of a deregulated market.

  • 8/3/2019 Mark Stout ERG Masters Project

    35/181

    ERG Masters Project Mark Stout 35

    Environmental Organizations: Environmental organizations want the electric utility industry to

    evolve into a form which is environmentally and socially sustainable. These groups want to

    accelerate the removal of coal and nuclear plants from operation. They want the idea of least-

    cost planning through IRP to be protected. Mechanisms that continue to decouple utility

    profits from volume sales are pursued because of the positive impact they have on demand

    side management efforts (DSM). Direct access threatens to undermine both IRP and sales

    volume/profit decoupling. Environmentalists would like to see an end to the backsliding that

    has occurred in utility energy efficiency and R&D budgets. Most groups resist retail

    competition and support continued funding for new renewables, DSM, and public interest

    RD&D. There is a significant rift that has developed over whether existing renewables

    generators should continue to receive subsidies.

    December Decision outcome: Environmental advocates lost in their opposition to a

    market structure allowing direct access, as well as in their opposition to the tying of

    stranded cost recovery to continued operation of nuclear plants. The inclusion of the

    Renewables Portfolio Standard was heralded as strong renewables policy by some

    environmentalists, while others perceived it as continued charity for poorly-run

    businesses that had already received more than adequate support. The application of a

    public goods charge to pay for energy efficiency and public interest RD&D was good

    in principle, although a lack of specific funding levels was troubling.

    AB 1890 outcome: Environmental advocates lost in their opposition to a market

    structure allowing direct access, as well as in their opposition to the tying of stranded

    cost recovery to continued operation of nuclear plants. The rift in the community that

    had developed regarding renewables policy was only torn wider by renewables funding

  • 8/3/2019 Mark Stout ERG Masters Project

    36/181

    ERG Masters Project Mark Stout 36

    levels that may not support the existing base of generators while allowing some new

    development to be placed on line. The application of a public goods charge with

    statutory spending level floors for energy efficiency, renewable energy, public interest

    RD&D, and low income programs was well received, but there is ongoing debate as to

    whether the adopted levels represented too much of a compromise with more

    powerful players.

    Stakeholder Interviews Cluster Analysis

    Given the large amount of interview data to absorb from 26 stakeholder interviews,

    grouping the stakeholder interviews into categories allowed some overall patterns to emerge from

    this set of data. This clustering also allowed for a better correlation with a review of the

    officeholder staff comments. I used my original categories for this cluster analysis: investor-

    owned electric utilities, municipal electric utilities, utility labor unions, independent producers,

    large electricity consumers, small electricity consumers, environmental advocates, and a state

    institutions. Appendix B has a full transcript of each interview. The organizations represented by

    each interview is listed, by category, in the table of contents for Appendix B. Because of the

    time-intensive nature of this research, combined with limited time and resources available, each

    clustered category has a small number of organizations. Because of the subjective interpretations

    required to code qualitative interview responses, and the small number of organizations per

    category, the following cluster analysis should only be used to point out rough trends. The raw

    coded data for this analysis is included in Appendix D.

  • 8/3/2019 Mark Stout ERG Masters Project

    37/181

    ERG Masters Project Mark Stout 37

    The stakeholder representatives were asked what outcomes their organizations wanted to

    obtain from the California electric utility restructuring process as it was just unfolding. When

    combined with comments filed by that organization early in the restructuring process at the

    CPUC, this provides a baseline to determine if they got what they wanted.

    The stakeholder representatives

    were then asked how much of what their

    organization wanted was included in the

    CPUC December, 1995 Decision. As

    Figure 1 indicates, nearly half of the representatives say that their organization got most of what it

    wanted from the December Decision, a slightly smaller number of representatives report a mixed

    or unclear outcome, and the remaining minority claim that their organization got rather little.

    Figure 2 shows that all of the investor-owned utilities and independent producers, as well as the

    majority of large electricity consumers, say that their organizations got most of what they wanted

    Figure 1: How much of what your organization

    wanted was in the CPUC December Decision?

    Rather Little

    Mixed/Unclear

    Most

    Figure 2: How much of what your organization wanted was in the

    December Decision?

    0 1 2 3 4 5

    INVESTOR-OWNED

    ELECTRIC UTILITIES

    MUNICIPAL

    ELECTRIC UTILITIES

    UTILITY LABOR

    UNIONS

    INDEPENDENT

    PRODUCERS

    LARGE

    ELECTRICITY

    CONSUMERS

    SMALL

    ELECTRICITY

    CONSUMERS

    ENVIRONMENTAL

    ADVOCATES

    STATE

    INSTITUTIONS

    Rather Li

    Mixed/Un

    Most

  • 8/3/2019 Mark Stout ERG Masters Project

    38/181

    ERG Masters Project Mark Stout 38

    from the December Decision. The utility labor unions and municipal utilities representatives

    reported receiving relatively little from this policy outcome.

    The stakeholder representatives were also asked how much of what their organization

    wanted was included in AB 1890. As

    Figures 3 indicates, nearly half of the

    representatives say that their

    organization got most of what it

    wanted from AB 1890, a similar

    number of representatives report a

    mixed or unclear outcome, and the

    remaining minority claim that their

    organization got rather little. Figure 4

    shows that all of the investor-owned

    utilities and utility labor union

    representatives, as well as the majority

    of large electricity consumers, say that their organizations got most of what they wanted from AB

    1890. The small consumer and environmental organization representatives appear to have taken a

    step backwards in terms of getting what they wanted compared to the CPUC December Decision

    policy outcome.

    Rather Little

    Mixed/Unclear

    Most

    Figure 3: How much of what your

    organization wanted was in AB 1890?

  • 8/3/2019 Mark Stout ERG Masters Project

    39/181

    ERG Masters Project Mark Stout 39

    One of the interview questions

    asked which policy outcome was

    preferred by the subjects organization,

    either the CPUC December Decision

    or AB 1890. As Figures 5 indicates,

    most organizations preferred the

    language of AB 1890. Figure 6 shows

    that the only organizations interviewed

    that prefer the December Decision are

    among the environmental and

    independent power communities. It is

    clear from the interview transcripts

    that those few organizations that

    stated a preference for the

    December Decision did so based

    on their support for the

    Renewables Portfolio Standard

    that was selected by the

    Commissioners as a renewables

    policy, as opposed to the

    nonbypassable surcharge funding

    mechanism adopted in AB 1890

    Figure 4: How much of what your organization

    wanted was in AB 1890?

    0 1 2 3 4 5

    INVESTOR-OWNED

    ELECTRIC UTILITIES

    MUNICIPALELECTRIC UTILITIES

    UTILITY LABOR

    UNIONS

    INDEPENDENT

    PRODUCERS

    LARGE

    ELECTRICITY

    CONSUMERS

    SMALLELECTRICITY

    CONSUMERS

    ENVIRONMENTAL

    ADVOCATES

    STATE

    INSTITUTIONS

    Rather Little

    Mixed/Unclear

    Most

    Figure 5: What Policy Outcome Does Your

    Organization Prefer?

    AB 1890

    No preference /

    Unclear

    CPUCDecember

    Decision

  • 8/3/2019 Mark Stout ERG Masters Project

    40/181

    ERG Masters Project Mark Stout 40

    [see American Wind Energy Association, Natural Resources Defense Council #1, and Union of

    Concerned Scientists interviews]. PG&E and SDG&E indicated that part of their preference for

    AB 1890 was to avoid future

    litigation. As excerpted from the

    PG&E stakeholder interview,

    Although the CPUC Decision

    was financially easier on PG&E,

    restructuring as envisioned in the

    CPUC Decision would have been

    less likely to take place in an

    orderly manner due to legal

    wrangling and ongoing filings at

    the CPUC. Many of the other

    stakeholders consider AB 1890 an

    incremental, evolutionary step

    forward from the December

    Decision.

    Officeholder Staff Interviews

    Officeholder staff interviews are another data source that I now use to cross-check the

    previous cluster analysis on who did and did not get what they wanted out of the restructuring

    process, and to begin to build theories for why. I interviewed two subjects who were on the

    CPUC staff during the two years leading up to the December Decision, as well as three subjects

    Figure 6: What Policy Outcome Does Your Organization Prefer?

    0 1 2 3 4 5

    INVESTOR-

    OWNED ELECTRIC

    UTILITIES

    MUNICIPAL

    ELECTRIC

    UTILITIES

    UTILITY LABOR

    UNIONS

    INDEPENDENT

    PRODUCERS

    LARGE

    ELECTRICITY

    CONSUMERS

    SMALL

    ELECTRICITY

    CONSUMERS

    ENVIRONMENTAL

    ADVOCATES

    STATE

    INSTITUTIONS

    CPUC December Decision

    AB 1890

    No preference / Unclear

  • 8/3/2019 Mark Stout ERG Masters Project

    41/181

    ERG Masters Project Mark Stout 41

    who were staff for members of the legislative Conference Committee during the 1996 legislative

    session. The following are excerpts from the full interview transcripts in Appendix C.