Market based integration of windpower. Hans Erik Kristoffersen Energinet.dk. Capacity expansion – 4.600 MW offshore. Present. 2025. Example on balance with an additional 2500 MW off shore wind and 1000 MW on shore wind. Min. Production. Consumption. Windpower. - PowerPoint PPT PresentationTRANSCRIPT
Energinet.dk 1
Market based integration of windpower
Hans Erik Kristoffersen
Energinet.dk
Energinet.dk 2
Capacity expansion – 4.600 MW offshore
Potential expansion by the Danish Energy Agency – 2008
Capacity
MW
Anholt 2 x 200
Horns Rev 5 x 200
Læsø 3 x 200
Jammerbugt 4 x 200
0
500
1000
1500
2000
2500
3000
3500
4000
4500
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
MW
Offshore
Onshore
Energinet.dk 3
Example on balance with an additional2500 MW off shore wind and 1000 MW on shore wind
Present 2025
Windpower Min. Production Consumption ConsumptionMin. Production Windpower
Energinet.dk 4
Wind power and the spot-price
Wind powr forecast and spot price Western Denmark January 2009
0
500
1000
1500
2000
2500
1
MW
h/h
ou
r
0,00
200,00
400,00
600,00
800,00
1000,00
1200,00
1400,00
1600,00
DK
K/M
Wh
Wind power forecast Spot price Western Denmark
Energinet.dk 5
Curtailment of sales bids
Scarcity of transmissions capacity and consumption in a few hours during the year results in curtailment of sales bids. Current market rules makes market clearing impossible during these hours
With the current price floor producers do not react to the real price of electricity
Wind power only makes up half of the average production in hours with curtailment in Western Denmark
-> There is a need for increased flexibility in thermal power production
Negative spot-prices will introduce a market based solution for hours without market clearing today
Number of hours with curtailment
0
10
20
30
40
50
60
70
80
90
2004 2005 2006 2007 2008
Ho
urs Western Denmark
Eastern Denmark
Average power production in hours with curtailment 2008
0
500
1000
1500
2000
2500
3000
3500
Western Denmark Eastern Denmark
MW
h/h Wind Power
Small scale CHP
Central Power Plants
Energinet.dk 6
Subsidies for wind power in Denmark
Offshore wind farms- Tender process.
- Fixed Payment = Market Price + Subsidy.
- Payment for 20 TWh or 20 years
- Negative prices at Nord Pool Spot => No subsidies for offshore wind power when prices becomes negative (max 300 hours).
Time
€ cent/kWh
Time
€ cent/kWh
Onshore wind farms- Payment = Market Price + Price premium
- Price premium: DKK 0,25 per kWh for 22.000 full load hours + 0,023 DKK for balancing costs
- May also choose a decommissioning certificates of either DKK 0,12 or 0,08 DKK per kWh.
Biogas and biomass- Payment = Market Price + Price premium
- Price premium: DKK 0,745 per kWh for biogas and DKK 0,015 per kWh for biomass per kWh.
Energinet.dk 7