martin smith, tenix, presents at the ohs leaders summit 2013

21
Fatality Prevention and Project Lifecycle Risk Management- An Evolving Model Martin Smith Group GM Health, Safety, Quality and Environment

Upload: media-corp-international

Post on 25-Jun-2015

279 views

Category:

Technology


2 download

DESCRIPTION

OHS Leaders Summit, Tenix, health, safety, Media Corp International, Martin Smith

TRANSCRIPT

Page 1: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Fatality Prevention and Project Lifecycle Risk Management- An Evolving Model Martin Smith Group GM Health, Safety, Quality and Environment

Page 2: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Defining Key Terms

Project Life Cycle How a construction project is planned, controlled, and monitored from its inception to its completion including handover for operations (does not include pre-feasibility or feasibility studies) Fatality or Serious Injury Precursor A combination of hazard(s) and underlying causal factors that if left unaddressed can result in fatal or serious injury.

Single Layer Defence Only one layer of defence/control is in place to prevent the occurrence of a fatality or serious injury; typically PPE.

Page 3: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

The Key Question

Why do high performing organisations with developing/mature approaches to safety continue to have fatalities and/or single layer defence events?

Page 4: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

5

We needed to adjust our approach to recognising and managing fatality exposures (Technical and culture) Technical: • Re-design and implementation of safety systems • Challenge current Risk Model • Focus on likely precursors to fatalities • Ensure multiple layers of protection/control for high risk hazards • Develop capability at each level of the business

Re-thinking our strategy for fatal risk !!

How Have we Responded?

Page 5: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Fatality Prevention Framework

1. Re-define and sell the value proposition for Fatality Prevention 2. Assess current situation and determine required cultural and

technical shift 3. Identify and document precursors to fatalities 4. Conduct risk assessment and establish priorities for intervention 5. Ensure adequate levels of protection/control 6. Address underlying factors 7. Ensure adequacy of infrastructure (systems, metrics etc) 8. Institutionalise the approach

Page 6: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Fatality Prevention Protocols (FPP’s)

1. Traffic Management 2. Confined Space 3. Work Vehicles and Road Safety 4. Working at Heights 5. Electrical Hazards 6. Mobile Plant 7. Working with Live Services 8. Heavy Lifting (Cranes) 9. Temporary Works 10. Scaffolding

Page 7: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

8

Adapting the Risk Strategy (from Mercer 2012)

Risk Assessment: F(x): Severity +

Experience-Based Likelihood

Low Severity Exposure

Risk Assessment: F(x): Severity + Control-based

Likelihood

Likely Precursor to

Fatality or Serious Injury

Risk Mitigation: Low to Middle

Order from Control Hierarchy

Risk Mitigation: High Order from

Control Hierarchy; Layers of Protection

Hazard Identification

Page 8: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Establishing a More Effective Risk Management model

Focusing on the identification and management of fatal risk at the early stages of the project life cycle (PLC) (when the project management system is evolving) to ensure improved project delivery outcomes Integrating safety risk factors of different project stages and managing the high risk hazards based on PLC is an appropriate way to establish an effective risk management model for fatal risk control

Page 9: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Key Underpinning Assumption

Project safety risks develop based on a "chain effect" – high risk factors in one stage affect other stages, and high consequence/low probability events that happen during construction/operations are amplified in the later stages of the life of the project

Page 10: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Project Life Cycle Risk Management

Page 11: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Aligning the WHS Risk Management Program to Project Life Cycle

Page 12: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Bid Stage

• Preliminary Project SQE Risk Assessment • Conceptual Design Risk Assessment (as required) • Bid Commitment Review (Gate)

• HSQE Risk Management Plan • Project HSEQ Management Plan (s) Rev 2 • Mobilisation Work Activity Risk Assessment • Detailed Design Risk Assessment (as required)

Post Bid Stage Post Bid Stage

Bid Stage

Page 13: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Project Delivery Planning Stage

• HSQE Risk Management Plan • Project HSEQ Management Plan (s) Rev 2 • Mobilisation Work Activity Risk Assessment • Detailed Design Risk Assessment (as required)

Mobilisation Stage • Project Delivery Method Planning Review • Project Mobilisation Plan • Work Activity Risk Assessment-Mobilisation

Mobilisation Project Delivery Planning

Page 14: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Project Delivery Stage

• Constructability Review • Maintenance Review • Operation Review • Detailed Design Risk Assessment (as required)

Demobilisation Stage

• De-Mobilisation Plan • De-mobilisation Work Activity Risk Assessment

Project Delivery Demob

Page 15: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Constructability Review- 3D Modelling

Page 16: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Project Close Out Stage

• Close out review • Project Lessons Learnt Report

Close out

Page 17: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Bid Stage

Page 18: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

‘Five Pillars’ Management Reviews

1. To ensure that prospects are aligned with our philosophy and approach to safety (prior to developing the bid) 2. Ensure all fatal risks are identified with effective mitigation plans costed (prior to bid submission) 3. Deliver against project HSEQ Plans, mitigate risks including fatal risks (monthly) 4. Monitor Divisional performance to avoid surprises (monthly) 5. Ensure Divisions deliver on Zero Harm Plans (monthly)

Page 19: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

This is a Work in Progress... • Continue to analyse data for incident precursors and any

unexpected/hidden relationships at company level • Continue to provide training to key personnel on PLC risk management

and Fatality Prevention Protocols (Designers , BD, Estimators etc) • Maintain focus on higher-risk activities / operations through the

Executive and the Board • Codify FPP’s into WHSMS and make them habitual • Strengthen the audit program- Fatality Prevention Audits • Feed Lessons Learnt process into ‘Market to Contract’ Phase • Continue to evolve fatality prevention metrics that are predictive and

robust • Continue to have risk focused/discovery conversations

Page 20: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Should we Ever Declare Victory?

“Never in all history have we harnessed such formidable technology. Every scientific advancement known to man has been incorporated into

its design. The operational controls are sound and foolproof!”

E.J. Smith, Captain of the Titanic

Page 21: Martin Smith, Tenix, presents at the OHS Leaders Summit 2013

Thank You