master plan briefing for the board of county commissioners€¦ · master plan phase 1 concept...
TRANSCRIPT
June 6, 2019
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Master Plan Briefing for the Board of County Commissioners
Fort Lauderdale-Hollywood International
FLL Master Plan Phase 1 Implementation Sequencing
Status Update of Terminal Modernization and Short-term Improvements
Master Plan Phase 1 Concept Overview
Other Non-Terminal Area Projects
2
Economic Impact (2019 Analysis)
Current Capital Improvement Plan (ACIP) and Financial Baseline
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Next Steps and Final Approvals
Status Update of Terminal Modernization and Short-term Improvements
3
Status Review of Terminal Modernization
4
Complete$376 millionT1
Substantial completion 3Q2021$278 million1,2/T2
Substantial completion: 3Q2021$305 million3/T3
Substantial completion: 2Q2020$688 million
T4
Under Construction
Terminal Modernization Program
Terminal connectors & bump-outs substantial completion: 4Q2021
Terminal Connectors & Bump-outs
Notes:
1/ Terminal 2 costs include part of the future terminal connectors and previously completed projects.
2/ Terminal 2 costs are being refined and updated which may result in an increase in project costs due to scope and other changes
3/ Terminal 3 costs include part of the future terminal connectors and previously completed projects.
Status Review of Short-term Improvements & Safety Related Projects
Wayfinding signage substantial completion: 1Q2020
Exit roadway and valet routing substantial completion: 2Q2021
Pedestrian signalization crosswalks substantial completion: 3Q2019
Rehab of North Runway including Phase 1 Taxiway: substantial completion: 3Q2019
Remaining north airfield taxiway substantial completion: 1Q2020
Short-Term Improvements
5
Garages RoadwaysCrosswalks
FLL Master Plan Phase 1 Implementation Sequencing
6
7
Placeholder for Updated Video
Master Plan Phase 1 Concept Overview (Previously referenced as Concept 6)
8
Recommended Master Plan Development Overview & Phasing
9
AIRSIDE
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Overnight Aircraft Parking
5-Gate Remote Terminal
Terminal Expansion Dependencies and Code Compliance
Utility Improvements
Terminal 4 Expansion
Crossfield Taxiway
Airfield Improvements
Airside Projects Total$1.9 Billion
Palm Garage RedevelopmentAPM Circulator
Intermodal Center (Phase 1) Airfield Access Gate
Supplemental Curb (Includes Palm demolition)
Central Utility Plant
Commercial Center – Phase 1 (Includes hotel)
Recommended Master Plan Development Overview & Phasing
10
LANDSIDE
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Landside Projects Total$1.4 Billion
Other Non-Terminal Area Projects
11
2
NORTHEAST QUADRANT
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
1
3
3 2
1
AIRFIELD SECURITY ACCESS GATE RELOCATION & ENHANCEMENT
(GATE 100)
4
BELLY CARGO FACILITY EXPANSION3
CENTRALIZED RECEIVING AND DISTRIBUTION FACILITY (CONSUMABLE GOODS)
2FUEL FARM EXPANSION
1
4
4
WESTSIDE DEVELOPMENT AREA
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
2
1
3
3
2
1
DEMAND DRIVEN AERONAUTICAL DEVELOPMENT PARCEL
4U.S. CUSTOMS & BORDER PATROL
(GENERAL AVIATION FACILITY)
3PUBLIC SAFETY BUILDING
2
AIRCRAFT RESCUE AND FIREFIGHTING (ARFF)
14
4
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Landside/Ground Transportation Support Functions
Other Cargo Development and Airline/Airport Support Development Opportunities
Non-Aeronautical Development Opportunities
Potential Acquisition Parcel for Airline/Airport or Non-Aeronautical DevelopmentRetention Parcels
Current Capital Improvement Plan (ACIP) and Financial Analyses
15
2019-2023 Airport Capital Improvement Program (ACIP) Plus Recommended Phase 1 Master Plan Development Projects
16
Current Airport Capital Program1/
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Phase 1 Master Plan Development Program
CASH EXISTING DEBT NEW DEBTPassenger
Facility Charges (PFCs)
Federal Aviation Administration (FAA)
Florida Department of Transportation
(FDOT)
Tenant or 3RD PARTY
1% 11% 71% 4% 5% 4% 4%
$1.5B $3.6B $5.1B
Total Airport Capital Improvement Plan
NOTES:1/ FLL’s current capital program assumes $519 in future bond issuances (new debt) to cover current and planned capital projects. The remaining project costs are funded by a variety of sources including but not limited to existing bonds, passenger facility charges (PFCs), federal and state grants and 3rd party investments.2/ The preliminary funding breakdown represents a series of conservative planning assumptions. Actual breakdowns subject to change based upon availability of funds and other funding mechanisms that BCAD may be able to utilize as part of the capital funding plan.
TABLE 1 – Recommended Phase 1 Master Plan Development - Preliminary Funding Breakdown2/
Cost Per Enplanement (CPE)
17
Cost Per Enplanement Metric – Broadly Defined
CPEs are difficult to compare between airports due to differences including:
• What is operated/provided by the airport operator
• What is included in the airline rate base
• What the airlines operate and pay for directly
• O&M Expenses
• O&M Reserve Requirement
• Debt Service
• Debt Service CoverageRequirement
• Fund Deposits
• Parking and Rental Car
• Ground/Building Rent
• General Aviation
• Terminal Concessions
• Commercial Property Revenue
• Landing Fees
• Terminal Rent
• FIS Fees
• Per Use Fees
• Remote Parking Fees
Expenses Non-Airline RevenueAirline Requirement
Airline Requirement
Enplaned Passengers
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
18
Summary of Demand Relative to Gate CapacityMillion Annual Enplanements (MAEP) Growth Projections
ENPL
ANEM
ENTS
15
17
19
21
23
25
MAEP
MAEP
181
MAEP
19 MAEP
21 MAEP
23.5 MAEP
66 Gates 71 Gates 77 GatesGATE CAPACITY
64 Gates
5-Gate Remote Terminal Opens
Phase 1 MPU Terminal Expansion
Opens2
NOTES:1/ BCAD reported actual enplanements as 18,008,451 for calendar year 20182/ Includes making G13 and G14 international capable and relocates 5 existing gates on the southside of Concourse F to the new Concourse G, converting them to international/domestic swing gates3/ See Appendix C for the preliminary gate realignment plan for G13 and G14 during construction of Phase 1 Terminal buildout
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
71 Gates77 Gates
Maximum Gate Utilization
Comparison of CPE Projections (2018 Dollars)
19PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
$25.00
$20.00
$15.00
$10.00
$5.00
$0.002019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
Fiscal Years
ACIP and MPU Phase 1, activity grows up to 23.5 million annual enplanements
ACIP only, activity caps at 19 million annual enplanements
$8.99
$13.52$14.70
$13.15
$8.96 $9.18$6.92 $7.18
2018 Dollars
4. Adjustment to 2018 dollars assumes 2.5% deflator. Doesn’t include adjustment for project or operating costs with inflation factor greater than 2.5%. 5. Net of PFCs and CFCs.6. Million Annual Enplanements (MAEP) derived by assuming a per gate enplanement capacity increase for the 66, 71 and 77 gate buildout.7. ACIP annual enplanements capped at 19 million beginning in 2021, which equates to 38 million annual passengers (MAP). 8. ACIP & MPU Phase I annual enplanements capped at 19 MAEP beginning in 2021, at 21 MAEP beginning in 2026, and 23.5 million beginning in 2033, which equates to 47 MAP.
NOTES:1. ACIP layer includes projects included in ACIP and land acquisition for facility support2. Projects are subject to change due to changes in project delivery dates.3. Commercial Center (Retail), Bus Lot Staging & Maintenance, Fuel Farm Expansion, & Belly Cargo Facility Expansion projects ($204M) are assumed to be funded separately (third party).
20
Existing Debt Service
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
($ in
000
s)
Debt Service
Orlando
Chicago O’Hare
Los Angeles
Fort Lauderdale
La Guardia
Tampa
Dallas-Fort Worth
Miami
Sources:1/ Miami: Preliminary Official Statement dated April 29, 2019 (series 2019A and B)2/ Tampa: Official Statement dated October 23, 2017 (series 2018E,F and A (PFC))3/ Orlando: Official Statement dated August 20, 2017 (series 2017A)4/ Fort Lauderdale: Broward County Aviation Department; Ricondo5/ Chicago O'Hare: Official Statement dated December 4, 2018 (series 2018A, B and C) 6/ LaGuardia: Official Statement dated May 2016 (series 2016A and B) 7/Los Angeles: Official Statement dated February 27, 2019 (Subordinate bonds series 2019A, B and C) 8/ Dallas Forth Worth: Dallas Fort Worth Continuing Disclosure Statements FY Ended Septemner 30, 2018
21
Recently Announced Additional Capital Programs
Sources:1/ Dallas News, https://www.dallasnews.com/business/dfw-airport/2019/05/20/american-airlines-dfw-airport-strike-deal-build-new-3billion-terminal (accessed May 28, 2019).2/ Miami Today, https://www.miamitodaynews.com/2019/05/28/miami-international-airport-due-billions-in-upgrades/ (accessed May 28, 2019).3/ Travel Age West, https://www.travelagewest.com/Travel/USA-Canada/Inside-Los-Angeles-International-Airport-s-14-Billion-Updates (accessed May 28, 2019).4/ BizJournals, https://www.bizjournals.com/orlando/news/2018/05/17/oia-board-oks-4-27-billion-capital-improvement.html (accessed May 28, 2019).5/ Construction Dive, https://www.constructiondive.com/news/construction-progresses-on-8b-laguardia-airport-expansion/528546/ (accessed May 28, 2019).6/ Reuters, https://www.reuters.com/article/us-chicago-airport/chicago-ohare-8-5-billion-expansion-plan-approved-by-city-council-idUSKBN1H43EZ (accessed May 28, 2019).
22
MAJOR COMPONENTS
Airport Code Timeframe Cost (Billions) Terminal Airside Landside Cargo APM CONRAC
Los Angeles LAX Through 2024 $11.9 • • • • •Chicago O'Hare ORD 2018-2028 $11.0 • • • • • •LaGuardia LGA 2016-2026 $9.1 • • •Atlanta ATL 2016-2034 $8.5 • • • •San Francisco SFO Through 2026 $7.3 • •Orlando MCO 2016-2025 $4.3 • • •Salt Lake City SLT 2014-2025 $3.6 • • • •Denver DEN 2018-2022 $3.5 • •Dallas Fort Worth DFW 10 years $3.4 • •Newark EWR 2017-2020 $3.0 •Seattle SEA 2017-2022 $3.0 • •Tampa TPA 2018-2028 $1.9 1/ • • • • • •Miami MIA 2015-2023 $1.5 2/ •Average $5.5
Large Airport Hubs – Capital Programs Comparison
Notes:1/ Excludes Phase 3 of the Master Plan Program, estimated at $798 million.2/ MIA’s capital program has been revised and was presented to the Board of County Commissioner’s (BOCC) Tourism and Ports Committee on May 15, 2019. The revised CIP was presented as a $4 - $5 billion program spanning from FY2020 through FY2035. Sources: Various bond offering documents, capital plan documents, and ratings agency press releases. See Table 2 for detail.
Economic Impact (2019 Analysis)
23
24
FLL Economic Impact (FY 2018)
Jobs Economic Activity
Airport Related$5.4 Billion
Visitor Industry$9.3 Billion 1/
Subtotal: $14.7 Billion
$22.8 Billion
$37.5 Billion
Airport Related30,986
Visitor Industry103,868 1/
Subtotal: 134,854
120,532
255,386
FLL Economic Impacts
Related Users 2/
Total
SOURCE: FLL Economic Impact Analysis, Martin Associates, February 2019NOTES:1/ Visitor Industry impacts are measured for Broward County only.2/ Related users are direct producers and consumers of air freight, as well as jobs with industry sectors in the state economy that also supply the direct manufacturers and consumers of air freight. Related user jobs are not directly dependent on FLL, as they can and do use other airports for the shipment of air freight.
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
Next Steps and Final Approvals
25
26
Public Workshop and Final Policy Advisory & Technical Advisory Committees
Airport Layout Plan (ALP) Submittal to FAA/FDOT
Key Upcoming Milestones
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY
PRELIMINARY DRAFT FOR DISCUSSION PURPOSES ONLY