master plan to make chandigarh a solar city

173
Master plan to make Chandigarh a Solar City Prepared for Chandigarh Renewable Energy Science and Technology Promotion Society (CREST) Chandigarh Project Report No. 2008RT03 The Energy and Resources Institute

Upload: vuongduong

Post on 03-Jan-2017

248 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Master plan to make Chandigarh a Solar City

Master plan to make Chandigarh a Solar City

Prepared for

Chandigarh Renewable Energy Science and Technology Promotion Society (CREST) Chandigarh

Project Report No. 2008RT03 The Energy and Resources Institute

Page 2: Master plan to make Chandigarh a Solar City
Page 3: Master plan to make Chandigarh a Solar City

Final report July 2009

Master plan to make Chandigarh a Solar City

Prepared for

Chandigarh Renewable Energy Science and Technology Promotion Society (CREST), Chandigarh

Project Report No. 2008RT03

w w w . t e r i i n . o r g The Energy and Resources Institute

Page 4: Master plan to make Chandigarh a Solar City

© The Energy and Resources Institute 2009

Suggested format for citation

T E R I. 2009

Master plan to make Chandigarh a Solar City

New Delhi: The Energy and Resources Institute

[Project Report No. 2008RT03]

For more information Project Monitoring Cell

T E R I Tel. 2468 2100 or 2468 2111

Darbari Seth Block E-mail [email protected]

IHC Complex, Lodhi Road Fax 2468 2144 or 2468 2145

New Delhi – 110 003 Web www.teriin.org

India India +91 • Delhi (0) 11

Page 5: Master plan to make Chandigarh a Solar City

Contents

Page no.

Executive summary ........................................................................................................... i Master Plan ................................................................................................................... ii Capacity building and awareness generation ................................................................ v

CHAPTER 1 Introduction .................................................................................................... 1 Methodology ................................................................................................................. 2

1. Baseline determination ......................................................................................... 2 2. Energy planning ................................................................................................... 3 3. Master Plan ........................................................................................................... 3

CHAPTER 2 Review of global „Solar City‟ projects ........................................................... 5 Introduction .................................................................................................................. 5 Institutions involved on Solar Cities ............................................................................. 5

International Solar Cities Initiatives (ISCI) ............................................................. 6 European Solar Cities Initiatives .............................................................................. 6 Solar city task force .................................................................................................. 6 European solar cities projects ................................................................................... 7 Energie-Cités Association ......................................................................................... 8 ICLEI-Local Governments for Sustainability ........................................................... 8

Programme on solar cities ............................................................................................ 8 Australia National Solar Cities Program .................................................................. 8

Case studies .................................................................................................................. 9 Solar city: Adelaide, Australia .................................................................................. 9 Solar city, Barcelona, Spain ..................................................................................... 10 Solar city, Linz, Austria ........................................................................................... 10 Solar city, Cape Town, South Africa ........................................................................ 10 Solar city, Daegu, Korea .......................................................................................... 11 Solar city, Oxford, UK .............................................................................................. 11 Solar city, Freiburg, Germany ................................................................................. 12 Solar City, Gelsenkirchen, Germany ....................................................................... 12 Solar City, Goteborg, Sweden .................................................................................. 12 Gwangju, Korea ....................................................................................................... 13 The Hague, Netherlands .......................................................................................... 13 Minneapolis, USA .................................................................................................... 14 Portland, USA .......................................................................................................... 14 Qingdao, China ........................................................................................................ 15 Santa Monica, USA .................................................................................................. 15 Sapporo, Japan ........................................................................................................ 16

CHAPTER 3 National and international practices ......................................................... 19 Energy conservation in buildings ................................................................................ 19

Achieving energy efficient buildings ....................................................................... 19 Policy review ................................................................................................................ 31

Energy conservation and efficiency ......................................................................... 31 „Development of Solar Cities‟ scheme of MNRE .................................................... 32 „GRIHA‟ scheme ..................................................................................................... 33 Renewable energy ................................................................................................... 34

CHAPTER 4 Energy baseline of Chandigarh ................................................................... 39 About the city .......................................................................................................... 39 Electricity consumption scenario ............................................................................ 41 Consumption scenario of petroleum products ....................................................... 44 Residential .............................................................................................................. 45 Commercial ............................................................................................................ 50

Page 6: Master plan to make Chandigarh a Solar City

Municipal services .................................................................................................. 52 Industrial ................................................................................................................ 54 GHG emissions ....................................................................................................... 56

CHAPTER 5 Energy planning ........................................................................................ 59 Projected population .............................................................................................. 59

Energy demand forecast up to 2018 ............................................................................ 61 Per capita electricity consumption .......................................................................... 61 Total electricity consumption ................................................................................. 62 Electricity consumption in residential sector ......................................................... 63

Renewable energy resource availability ...................................................................... 74 Biomass potential .................................................................................................... 74

Energy efficiency: Options for energy savings and demand reduction ...................... 78 Options for energy savings and demand reduction ............................................... 78 Supply side options based on renewables .............................................................. 84 Techno-economics of Energy conservation measures ........................................... 94 Overall scenario of Chandigarh as Solar City ......................................................... 95

CHAPTER 6 Action plan ................................................................................................ 99 Capacity building and awareness generation ............................................................ 104

Annexure 1: Technical details of street lighting in Chandigarh ................................ 107 Annexure 2: Technical details of municipal water pumping in Chandigarh ............. 109 Annexure 3: „Trend analysis‟ – Methodology adopted for projection ...................... 113 Annexure 4: Energy efficient schemes of BEE and BSES .......................................... 115 Annexure 5: Energy efficiency measures for air conditioning ................................... 121 Annexure 6: Astronomical timer switch for street lighting ....................................... 125 Annexure 7: “Demonstration and Promotion of Solar Photovoltaic Devices/ Systems in Urban Areas & Industry” scheme of MNRE .............................................................. 127 Annexure 8: RETScreen Worksheets for SPV based power generation .................... 129 Annexure 9: Pre-feasibility study for setting up 25 MWp (total) grid-connected solar PV power plant in Chandigarh ...................................................................................... 133 Annexure 10: Budget estimates for implementation of different activities to make Chandigarh as a Solar City ............................................................................................ 153

List of figures Figure 4.1 Satellite image of Chandigarh city ............................................................... 39

Figure 4.2 Population growth in Chandigarh from 1961 to 2001 ................................ 40 Figure 4.3 Land use pattern of Chandigarh .................................................................. 41 Figure 4.4 Per capita electricity consumption for Chandigarh and India ..................... 42

Figure 4.5 Sector-wise annual electricity consumption (in MU) ................................. 43 Figure 4.6 Sectoral Electricity use pattern of Chandigarh ............................................ 43 Figure 4.7 Annual electricity consumption in Chandigarh (in MU) ............................ 44

Figure 4.8 House use pattern of Chandigarh ................................................................. 46 Figure 4.9 (a) Distribution of households by number of dwelling rooms ..................... 46 Figure 4.9 (b) Distribution of households by family sizes ............................................ 47 Figure 4.10. Distribution of households by source of lighting ...................................... 47 Figure 4.11Total electricity consumption in the residential sector of Chandigarh........ 48

Figure 4.12. Electricity consumption pattern in residential sector ................................ 48 Figure 4.13 Total number of LPG connections in Chandigarh ..................................... 49 Figure 4.14 Kerosene consumption in Chandigarh ...................................................... 50 Figure 4.15 Growth of Commercial Consumers in Chandigarh .................................... 50

Figure 4.16 Per Capita electricity consumption in commercial sector .......................... 51 Figure 4.17 Total electricity consumption in commercial sector .................................. 52 Figure 4.18 Street lights in Chandigarh (V3 Road) ....................................................... 52

Page 7: Master plan to make Chandigarh a Solar City

Figure 4.20 Electricity consumption in Industrial Sector of Chandigarh ...................... 55 Figure 4.21 GHG emissions based on electricity, LPG and Kerosene consumption of

Chandigarh ............................................................................................................. 57 Figure 5.1 Population trends in Chandigarh from 1961 to 2021 .................................. 60

Figure 5.2 Per capita income of Chandigarh ................................................................ 61 Figure 5.3 Per capita electricity consumption in Chandigarh....................................... 62 Figure 5.4 Annual electricity consumption (in MU) .................................................... 63 Figure 5.5 Total electricity consumption in the residential sector up to 2018 .............. 64 Figure 5.6 LPG consumption projections (BAU scenario) .......................................... 65

Figure 5.7 Kerosene consumption and projection up to 2018 ...................................... 65 Figure 5.8 Petrol consumption and projection up to 2018............................................ 66 Figure 5.9 High Speed Diesel consumption and projection up to 2018 ........................ 67 Figure 5.10 Light Diesel Oil (LDO) consumption and projection up to 2018 .............. 68

Figure 5.11 Furnace Oil consumption and projection up to 2018 ................................. 68 Figure 5.12 Low sulphur heavy stock consumption and projection up to 2018 ............ 69 Figure 5.13 Projected growth commercial customers up to 2018 ................................ 69 Figure 5.14 Per Capita annual electricity consumption in commercial sector ............. 70

Figure 5.15 Total Annual Electricity consumption in commercial sector (MU) .......... 71 Figure 5.16 Electricity consumption in Industrial sector.............................................. 72 Figure 5.17 Annual Electricity consumption in various sectors of Chandigarh ........... 72

Figure 5.18 GHG emissions from energy supplied to Chandigarh city ....................... 73 Figure 5.19 MSW (tonnes/day) generation in Chandigarh ........................................... 76 Figure 5.20 Solar Radiation pattern of Chandigarh ...................................................... 77

Figure 5.21 Business as usual (BAU) and solar city (SC) scenario of residential sector

................................................................................................................................ 79 Figure 5.22 BAU and Solar city scenarios for commercial sector ............................... 81 Figure 5.23 Energy consumption in municipal water pumping in BAU and SC

scenarios ................................................................................................................. 84 Figure 5.24 Solar water heating systems in residential and commercial sectors........... 85

Figure 5.25 Solar water heating options under BAU and solar city scenarios ............. 87 Figure 5.26 Schematic of a roof top grid connected solar PV system .......................... 88 Figure 5.27 Satellite view of Sector-17 of Chandigarh and potential areas for roof top

................................................................................................................................ 88 Figure 5.28 Satellite view of Sector-9 of Chandigarh and potential areas for roof top

SPV ......................................................................................................................... 89

Figure 5.29 Performance of Roof top SPV Systems in Chandigarh ............................ 89 Figure 5.30 Electricity generation pattern of roof top SPV in Chandigarh .................. 91

Figure 5.31 Large solar PV power plant proposed in ‘Patiyala ki rao’ area ................ 92

Figure 5.32 Potential area for SPV power plant at Landfill Site of Chandigargh .. 93 Figure 5.33 Energy generation/saving in Chandigarh under solar city scenario .......... 96

Figure 5.34 Overall scenario of Chandigarh as solar city ............................................ 97 Figure A2.1 Water pumping station in Chandigarh (Kazauli water works) ............... 111 Figure A3.1 Sample of trend analysis using MS-EXCEL ......................................... 113 Figure A6.1 Astronomical time switch for street lighting .......................................... 125 Figure A9.1 City map of Chandigarh ......................................................................... 134

Figure A9.2 Sun-path diagram for Chandigarh (using ECOTECJ software) ............ 135 Figure A9.3 Variation of daily Global and Diffuse solar radiation over Chandigarh 136

Figure A9.4 Variation of annual average ambient temperature and relative humidity

over Chandigarh ................................................................................................... 137 Figure A9.5 Classification of solar PV technologies.................................................. 138

Page 8: Master plan to make Chandigarh a Solar City

Figure A9.6 Schematic diagram of a grid connected solar PV system ...................... 141 Figure A9.7 Land use pattern of Chandigarh ............................................................. 144

Figure A9.8 Schematic of ‘Solar tree’ ........................................................................ 147 Figure A9.11 Grid map of Chandigarh city ............................................................... 149

Page 9: Master plan to make Chandigarh a Solar City

List of tables Table E1 Targets for energy conservation generation and green house gas emission

reduction................................................................................................................... ii Table 2.1 Checklist of parameters and initiatives taken up .......................................... 16 Table 3.1 Suggested energy efficiency measures for commercial buildings ................ 25 Table 3.2 Alternative technologies to improve energy efficiency of HVAC systems .... 27 Table 3.3 Potential technologies for water heating ..................................................... 30 Table 4.1 Consumption pattern of petroleum products in Chandigarh ....................... 45 Table 4.2 Industrial production of Chandigarh city ................................................... 54 Table 5.1 Forests of Chandigarh City ............................................................................ 74 Table 5.2 Daily and monthly pattern of solar radiation over Chandigarh ................... 77 Table 5.3 Summary of electricity consumption in BAU scenario and solar city

scenario ................................................................................................................... 84 Table 5.4 Performance of proposed Roof Top SPV systems in Chandigarh ............... 90 Table 6.1 Targets for energy conservation generation and green house gas emission

reduction................................................................................................................. 99 Table 6.2 Budget estimated for implementation of different activities for making

Chandigarh as a Solar City .................................................................................... 103 Table A5.1 Energy savings in window ACs ................................................................. 121 Table A5.2 Desirable wind speeds (m/s) for thermal comfort conditions ............... 123 Table A9.1 Daily and monthly variation of solar radiation over Chandigarh ............ 136 Table A9.2 Performance results of a SPV power plant of the the capacity of 1 MW . 143 Table A9.2 Action plan of solar PV based power plant of the capacity of 25 MW in

Chandigarh (selection of the locations) ................................................................. 145 Table A9.3 Potential locations where solar PV based power plants can be installed 146

Page 10: Master plan to make Chandigarh a Solar City
Page 11: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Executive summary

In India, it is seen that every year there is an increase of 20-30%

in energy requirement in the residential sector and 8-10%

increase in commercial sector; leading to a situation where

there are both, energy as well as peak deficits. In case of

Chandigarh, as per Department of Environment, Chandigarh

Administration, per capita electricity consumption has been

reported as 1162 kWh in 2006-07. The projections shows

gradual increase in per capita electricity consumption of the city

and might be 1246 kWh in 2008. The total electricity

consumption of the city has been reported as 1157.5 MU during

2007-08. Taking in to account the exponentially increasing

energy demand, it became obvious to Chandigarh Union

Territory that this trend is not sustainable in the long run. It felt

that measures such as reducing energy demands and switching

from fossil fuel to renewable energy technologies would go a

long way in addressing these concerns.

As has been the case with the wide-scale introduction of

renewable energy technologies for a variety of applications in

the country; Chandigarh UT took initiative to develop

Chandigarh city as a solar city. The Chandigarh Renewable

Energy, Science and Technology Promotion Society (CREST)

had been given the mandate to prepare the plan to achieve this

objective. In essence, the Solar City programme strives to

integrate:

Energy conservation measures to reduce the energy

demand, and

Utilization of locally available resources such as solar energy

to meet these reduced energy demands

This Master Plan for Solar City is a dynamic document meant to

change with time, experience, and need. The development of

master plan has benefited from the active participation of

CREST, Public Works Department, Municipal Corporation UT,

Chandigarh Administration, Municipal Water Supply

Department, Forest Department, power utilities, electricity

department of Chandigarh Administration; and other agencies

with energy-related responsibilities.

The whole exercise of developing a Master Plan for making

Chandigarh a solar city has been a collaborative endeavour

along with all the major stakeholders in the city. Developing the

city as a solar city requires an integrated urban planning

approach, which simultaneously involves reducing reliance on

fossil fuels by the application of energy conservation and

efficiency measures and by replacing/complementing the

Page 12: Master plan to make Chandigarh a Solar City

ii Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

conventional energy generation with the renewable energy. As

decided in the beginning, this exercise did not include the

industrial and transportation sectors. The key components of

the study comprised

Base line determination,

Energy planning

– Energy use projections

– Energy efficiency measures and audit

– Utilization of available renewable energy sources and

Developing an Master Plan

The Master Plan has been developed on the basis of different

energy saving and renewable energy options, along with those

technological options that are feasible in long term only.

Master Plan Based on the analysis of potential for demand side measures

along with that of supply side augmentation through renewable

energy technologies, the following targets are proposed for

Chandigarh in order to develop it as a “Solar City”. These

targets are based on the detailed energy audits in Chandigarh

and renewable resource potential assessment.

Table E1 Targets for energy conservation generation and greenhouse gas

emission reduction

Description

Target

Short Term

(till 2012)

Medium Term

(till 2015)

Long Term

(till 2018)

1. Energy Conservation* Reduction in present energy consumption

1.1 Residential sector 10% 15% 20%

1.2 Commercial sector 10% 15% 20%

1.3 a Municipal sector (Water pumping) 1.5% 3.0% 4.0%

1.3 a Municipal sector (Street lighting) 1.5% 3.0% 4.0%

2. Coverage of solar water heating systems (as a proportion of

total heating demand in residential and commercial sectors)

10% 25% 45%

3. Roof Top solar energy based electricity generation 2.5 MW 5.0 MW 10.0 MW

4. Large solar energy based electricity generation at Landfill

site

3.0 MW 5.0 MW 5.0 MW

5. Large solar energy based electricity generation at Patiyala ki

Rao site

5.0 MW 15.0 MW 25.0 MW

GHG emission reduction (tCO2/annum) 90973 214051 404969

* As a percentage of reduction in energy consumption over projected consumption in BAU scenario

The short-term targets for energy conservation are based on the

energy conservation options identified in the energy audit. To

achieve the medium and long-term targets the key

implementation points of the proposed Master Plan to make

Chandigarh a Solar City is summarized below:

Page 13: Master plan to make Chandigarh a Solar City

iii Executive summary

T E R I Report No. 2008RT03

Implementation plan

A “Solar City Cell” may be established within Municipal

Corporation of Chandigarh.

For implementation of Solar City project, an empowered

committees may be set up to provide overall guidance under

the chairmanship of the Finance Secretary.

The Solar City Cell may take advantage of programmes like

Jawaharlal Nehru National Urban Renewal Mission

(JNNURM) for implementation of the master plan.

The Solar City Cell may also take advantage of the grant-in-

aid (for energy consultancy as well as incremental cost of

building construction for a few buildings) being provided by

Bureau of Energy Efficiency (BEE) to design a few pilot

energy efficient buildings in the city, in accordance with

Energy Conservation Building Code (ECBC). The possibility

of availing incentives provided by the central government

for Green Rating for Integrated Habitat Assessment

(GRIHA) rated buildings may also be explored.

The Solar City Cell may work proactively:

– To get ECBC notified immediately

– To ensure that the building bye-laws are changed in

accordance with it

– To ensure that all upcoming non-residential buildings

are brought under the ambit of ECBC and incorporate

the relevant green buildings elements.

– To ensure that the major new commercial complexes

including those for ITES services are „GRIHA1‟ certified.

The state government may mandate CREST/Engineering

Department to distribute the quality CFLs to its consumers

at concessional prices or on easy payment terms.

For instance, in Delhi, BSES is promoting CFLs through

“Buy One Get 1 Free CFL Offer”. There is no restriction

on the number of CFL bulbs a customer can buy.

CREST may initiate a dialogue with the power utility for

introducing rebate on electricity tariff for the domestic

consumers, which employ solar devices.

To begin with, the energy conservation measures in the

municipal services may be taken up immediately.

At least 20% of the energy needed for water heating in the

residential and commercial buildings may be required to

come from solar energy, by 2010.

CREST may initiate DPR preparation for

– 10 MW solar PV based roof top power plant and

– 5 MWp solar PV based power plants in landfill site of the

city

– 25 MWp large solar PV based power plant in „Patiyala

ki Rao’ area of Chandigarh.

1 GRIHA

Page 14: Master plan to make Chandigarh a Solar City

iv Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Utilizing central government schemes, CREST/ Municipal

Corporation may initiate installation of solar-based LED

traffic lights, solar street lights, building integrated solar PV,

and other relevant solar products on a priority basis.

CREST may mount a focused and sustained campaign on

“Solar City” covering all media resources - including print,

radio, and television.

In order to showcase Chandigarh City as a Solar City, the

following may be taken up on priority.

– Urja Park: Energy– cum–Science Park may be

established in a central location in Chandigarh as an

inviting place for social gatherings and to provide public

education about issues of sustainable energy in a

friendly, non-technical atmosphere.

– Urja Bhawan: CREST office and Solar City Cell may be

housed in a new building, constructed in accordance

with ECBC and other efficient/green building concepts.

The newly constructing Paryaran Bhawan may also have

Building Integrated Solar PV as well as Solar based

space conditioning system.

The following projects may be taken up through public-

private partnership:

– Setting up solar powered, LED Display Boards at the

strategic locations in the City. These boards would not

only display the fact that Chandigarh is a `Solar City‟ but

also display pollution levels, temperatures updates, and

messages useful to general public.

– Provision of solar powered lights and fountains in the

prominent public gardens and parks in the city (such as

Botanical Gardens, Bougainvillea Garden, Rajendra

Park, Rock garden, Rose Garden, Shivalik Garden,

Shanti Kunj, Leisure Valley etc.,) thereby spreading the

Solar City message.

Prominent office complexes like the Delux building,

additional building, UT secretariat, Police HQ, Punjab

secretariat, Haryana secretariat, museums, etc. may also

have solar powered displays as well as battery operated

vehicles for intra-complex transportation.

CREST along with PSEB and power utilities may begin

engaging the public through sustained awareness campaigns

about the benefits of energy conservation and renewable

energy; including local elected representatives and school

children.

In Delhi, BSES has been educating its consumers

about the need to conserve power though Synergy – its bi-

monthly, bi-lingual newsletter, newspaper inserts, and

pamphlets distributed at meals from time to time.

Likewise, NDPL has launched Energy Conservation

campaign in Schools.

Page 15: Master plan to make Chandigarh a Solar City

v Executive summary

T E R I Report No. 2008RT03

CREST may start organizing a series of training programme

on `Green buildings‟ for the planners; architects;

electrical, Heating Ventilation and Air Conditioning

(HVAC), and lighting consultants; and engineers involved in

the building sector.

CREST, in close cooperation with the BEE, may initiate

creation of accredited certifiers who can then be engaged by

the house owners/builders/developers for obtaining the

energy conservation compliance certificates.

CREST may initiate public-private partnership (e.g. working

closely with the associations of the local traders and

manufacturers) to propagate energy efficient appliances,

which include ‟Energy Star‟ appliances.

Under Solar City endeavour, one of the key action points

could be to replace traffic signals having incandescent lamps

with those with energy saving LEDs, along with solar

controllers. Similarly, CFL based streetlights; lights in the

parks, gardens, and roundabouts may be replaced with solar

lights.

To encourage adoption of energy conservation, energy

efficient equipment/appliances, as well as renewable energy

systems; CREST may introduce specific, time-bound

financial incentives for Chandigarh.

Towards this, the route of Energy Services Company

(ESCOs) may also be explored.

CREST may assist Municipal Corporation, Engineering and

other concerned departments in accessing capital for energy

conservation and efficiency projects at favourable terms. For

this purpose, State Energy Conservation Fund, as prescribed

by EC Act 2001, may be accessed.

The industrial sector is also one of the major energy

consuming sectors. CREST, may enhance the present

scheme for promoting energy audits in the industrial scoter.

Further, CREST may undertake awareness campaign in

industries in Chandigarh for energy conservation. This can

be undertaken in partnership with the local industry

association.

Capacity building and awareness generation In order to inculcate energy conservation techniques in the

common architecture. It is essential that all the practitioners

be properly trained in energy-efficient or “Green”

architecture. CREST may, therefore, organize a series of

training programme for the planners; architects; electrical,

HVAC, and lighting consultants; and engineers involved in

the building sector, These courses, tailor-made to suit

different levels, would have to be imparted to all the

professionals, in public as well as in private sector – on a

regular basis.

Page 16: Master plan to make Chandigarh a Solar City

vi Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Suitable training modules, including the regular updates,

may have to be developed and delivered for

– accreditation of professionals for building certification

and

– for the quality improvement of the accredited certifiers.

Of particular importance is the training for front-line

workers and technicians regarding energy conservation and

efficiency, this would not only ensure successful

implementation of such measures but also their

sustainability and replication.

Specific training programmes are required for those in the

supervisory role, for effective monitoring of energy demand,

enabling them to take preventive/corrective actions in time.

The public awareness and education being central to

successful changeover to solar city, it is imperative for

CREST to engage the public through sustained awareness

campaigns and communicate the benefits of energy

conservation and renewable energy to different user-groups;

including local elected representatives.

CREST may mount a focused and sustained campaign on

“Solar City” and its features encompassing all media

resources - including print, radio, and television. Apart from

specific recommendations, such campaigns must inform

public about the places from energy efficient/renewable

energy devices and services can be procured.

A key component of the awareness creation campaign would

be to capture school children‟s attention towards energy-

efficiency and clean future. Thus, the campaign for the

school children will include the following elements:

– Inter-school essay and drawing competitions

– Inter-school quizzes

– Workshops and seminars

– Exhibitions and demonstrations

– Field trips

CREST may involve power utilities to mount a public

campaign on energy conservation utilizing the regular

communication that power utilities or PSEB send to its

consumer‟s e.g. monthly electricity bills.

Page 17: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 1 Introduction

Climate change and fossil fuel depletion are the two major

concerns of the current millennium that threaten our ability to

survive on this planet. The fundamental problems pertain to an

excessive dependence on fossil fuels to meet increasingly,

energy-intensive life styles. There is a large difference in „energy

consumption‟ between the urban and rural area. Indeed, the

urbanization coupled with the rising income levels leads to

higher energy requirements. It has been observed that the

household energy accounts for about half of India's total energy

consumption. It is seen that every year there is an increase of

20-30% in energy requirement in the residential sector and 10-

15% increase in commercial sector. This has led to a situation

where there are both, energy as well as peak deficits.

As per Engineering Department (Electricity Wing),

Chandigarh Administration, the maximum electricity demand

of the city has been reported as 284 MW; while the average

power requirement is approximately 3.25 MU per day. The per

capita electricity consumption in Chandigarh has been reported

as 1162.0 kWh during 2006-07 as per Envis Centre, Department

of Environment of Chandigarh Administration. Since

Chandigarh city has no generating capacity of its own, it gets

67% of its power through Mohali (PSEB), about 10% through

Dhulkote (BBMB) and remaining 23% through Nalagarh. The

transmission and distribution losses have been reported as

18.67 % by Engineering Department (Electricity Wing),

Chandigarh Administration.

However, it is obvious that this trend is not sustainable in

the long run. Therefore, measures such as reducing energy

demands and switching from fossil fuel to renewable energy

technologies to complement the conventional energy sources

have become imperative.

The Chandigarh Renewable Energy, Science and Technology

Promotion Society (CREST); Department of Science and

Technology Chandigarh took the initiative to develop the

Chandigarh as a solar city. CREST has been given the mandate

to prepare and implement the plan to achieve this objective.

This Master Plan for Solar City is a dynamic document

meant to change with time, experience, and need. The

development of master plan has benefited from the active

participation of CREST, Public Works Department, Municipal

Corporation UT, Chandigarh Administration, Municipal Water

Supply Department, Forest Department, power utilities,

electricity department of Chandigarh Administration; and other

agencies with energy-related responsibilities.

Page 18: Master plan to make Chandigarh a Solar City

2 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

The philosophy behind Master Plan is to ensure that

Chandigarh‟s energy demands are met in affordable,

technologically advanced, and environmental friendly manner.

It means that after cost-effective efficiency and demand

response, the city relies on renewable sources of power and

distributed generation, to the extent possible. It may be noted

that there is an important role of research, development and

demonstration activities that are critical to realizing these goals.

Methodology The whole exercise of developing a Master Plan for making

Chandigarh a solar city has been a collaborative endeavour of

TERI and CREST, along with all the other major stakeholders in

the city. Developing the city, as a solar city requires an

integrated urban planning approach, which simultaneously

involves reducing reliance on fossil fuels by the application of

energy conservation and efficiency measures and by

replacing/complementing the conventional energy generation

with the renewable energy. As decided in the beginning, this

exercise did not include the industrial and transportation

sectors. The key components of the study comprised;

Baseline determination

Energy planning, and

Developing a Master Plan

1. Baseline determination In this initial phase, all the information was collected to prepare

the energy base line for Chandigarh.

General information on infrastructure, population and its

distribution, household income, education, employment

Energy demand – Data on sectoral energy demand in

residential, commercial, municipal services, and industrial

For the residential sector detailed statistical review,

interaction with various government officials of Chandigarh

Administration and Chandigarh Municipal Corporation (viz.

Housing Board, City Planning Department etc.) was carried

out to understand the demand in various sectors.

Energy audit has been carried out of the following municipal

services

– Street lighting and

– Water pumping

Resource assessment for solar, wind, biomass as well as

municipal solid waste

Review of renewable energy and energy efficiency programs

and policies

Page 19: Master plan to make Chandigarh a Solar City

3 Introduction

T E R I Report No. 2008RT03

2. Energy planning Using energy planning tools like RETScreen and LEAP

softwares, different scenarios were developed and analyzed in

order to explore the opportunities of

Reducing the demand based on energy conservation and

energy efficiency measures and

Meeting the energy requirements through renewable based

systems.

This was followed by a techno-economic evaluation of various

energy conservation and renewable energy options; and finally,

setting up targets for energy consumption and GHG emissions

for the city.

3. Master Plan The Master Plan has been developed on the basis of different

energy saving and renewable energy options, along with those

technological options that are feasible in long term only.

Page 20: Master plan to make Chandigarh a Solar City

4 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 21: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 2 Review of global „Solar City‟ projects

Introduction A large proportion of the world's population lives in cities,

towns and urban regions, in which three-quarters of the overall

energy consumption occurs. Urbanization and economic

development are leading to a rapid rise in energy demand in

urban areas. The urban areas are heavily dependent on fossil

fuels for the maintaining of essential public services, for

powering homes, transport, infrastructure, industry and

commerce etc. It is generally recognised that a transformation

of the present energy system is required in order to secure the

energy supply and to mitigate the risks of climate change. The

transformation can be possible by a shift towards renewable

energy systems (RES) and a more rational use of energy (RUE).

One of the ways/approach to achieve such a transformation

might be to convert more number of cities into Solar Cities.

Solar cities in a broader term include several initiatives,

activities and technologies, which includes renewable energy,

energy efficiency, sustainable transport options, architectural

innovations etc. The term “Solar cities” defined by

several initiatives such as International Solar cities

Initiatives and European Solar cities initiatives also

include a "climate-stabilization" aspect, whereby cities

responsibly set per-capital targets for future

greenhouse-gas emissions at levels consistent with

stabilizing future levels of atmospheric carbon-dioxide

and other greenhouse gases and also includes

introduction of green house gas emissions reduction

over long term time frame.

Institutions involved on Solar Cities Several institutions working on solar cities are given below:

International Solar Cities Initiatives (ISCI)

European Solar cities Initiatives (ESCI)

Solar city Task force

International Solar Energy Society (ISES), European Solar

cities Projects

European Green Cities Network

Energie Cites Association

ICLEI-Local Governments for Sustainability

Ministry of New and Renewable Energy (MNRE)

The following section discusses briefly about the initiatives and

activities undertaken by these institutions.

Page 22: Master plan to make Chandigarh a Solar City

6 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

International Solar Cities Initiatives (ISCI) International solar cities initiative is the group who had

organized the first International solar Cities Congress in Daegu,

Korea in 2004.The primary focus of ISCI is to set up the target

for introduction of renewable energy and reduction of

greenhouse gas emissions on a longer term.

European Solar Cities Initiatives The aim of the initiative is to support the European energy and

climate policy by stimulating the interests of European "high

performance" cities and surrounding regions (prospective

"Solar Cities"), the European research community and the

European sustainable energy industry.

The Initiative will mobilise a critical mass of participants to

find efficient and rapid ways to implement RES and RUE in

European cities through research, development, demonstration

and information dissemination activities and through

stakeholder participation (citizen and others). The goal is to

speed up the transformation of the European cities into Solar

Cities.

A working definition of a Solar City is a city that aims at

reducing the level of greenhouse gas emissions through a

holistic strategy for the introduction of RES and RUE to a

climate-stable and thus sustainable level in the year 2050.

The scientific and technical objectives are:

To better understand the energy needs of cities for different

energy qualities and for different European regions,

To better understand the potential of different forms of RES

for and for RUE in cities in different European regions,

To identify or develop optimal strategies for rapid

integration of RES and RUE in the energy systems of cities

for different regions in Europe,

To identify RES and RUE best suited for different categories

of urban areas and different city surface uses,

To optimise the performance of RES and RUE for city

applications,

To find ways of improving the adoption of RES and REU

technology by small and medium-sized enterprises (SMEs),

To identify the different actors in a community and identify

their needs, possibilities and limitations

Solar city task force Solar city task force is an advisory service to assist towns, cities

etc integrating renewable energy technologies, and energy

conservation and efficiency measures in order to reduce the

green house gas emission. A general methodology has been

developed based on the experiences and best practices adopted

by different institutions internationally for providing such

services.

Page 23: Master plan to make Chandigarh a Solar City

7 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

European solar cities projects The European Solar Cities Project (EU Solar Cities) aims at

promoting the wider and large-scale use of renewable energy

(RE) within the context of long-term planning for sustainable

urban development. It is basically a study that addresses the

planning and application of technologies for utilizing

Renewable Energy Sources (RES) and Rational Use of Energy

(RUE)(in other words adopting Energy efficiency measures) in

an urban context and their relevance for reducing CO2

emissions.

Solar city is seen as a city that has made firm commitments

in order to reduce greenhouse gas emission targets while

incorporating renewable energy technologies.

Within the scope of this project several activities were

conducted:

The collection and assessment of information about

different activities and programmes of selected European

cities and city networks, with a description on their

implementation and an assessment of their impact.

The examination of these activities assisted in the

development of two guide books for city actors, namely:

– Good Practice Guide

- Guide on CO2 Reduction Potential in Cities

The results encompass a range of informative materials, with

recommendations for replication to city actors and local

governments.

The Good Practice Guide is useful for city actors that require

ideas and information for planning their own activities and

strategies to implement clean energy sources and promote the

reduction of harmful emissions. A set of generic good practices

have been identified, which represent a good starting point for

cities that require an introduction to the concept of

implementing RES and RUE strategies and activities.

The CO2 Reduction Potential Assessment and Issues

Impacting on CO2 balances, is a comprehensive report that

addresses reduction targets and baseline studies. This is

particularly useful for guiding cities interested in implementing

a strategy, with basic steps identified to assist this process.

It has to be noted that there are many different approaches

that are, and can be, used by cities, with different baselines and

varied ways of presenting emissions reduction results. Although

scientists are not unanimous in agreeing to the best way to

measure emissions, or the most effective way to calculate

emissions reduction, the project team has the view that a delay

in implementing strategies and activities that will adequately

reduce harmful emissions is in itself the most damaging

approach.

Under this study, eight cities were identified. Cities were

selected from Austria, Belgium, Denmark, France, Germany and

Page 24: Master plan to make Chandigarh a Solar City

8 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Italy. Sixty-three city good practices from seven cities and one

housing association have been identified. Every city needs to

consider the result of its actions in terms of energy used and the

effect it has on the environment.

A range of good practices recommended for replication have

been identified, and present a guide to urban actions that

contribute to sustainability in cities, and actions that strengthen

networks.

63 city good practices

22 city network good practices

Energie-Cités Association Energie-Cités was established as an association of European

local authorities in 1990 in order to implement the following at

the local level.

Reducing energy consumption while reducing local

emissions and effluents,

Stimulate local growth by making use of locally available

resources,

Developing innovative town or city

Energie-Cités builds European projects for helping its members

to develop a local sustainable energy policy.

With over 140 members in 24 countries and representing

more than 500 towns and cities, Energie-Cités is the association

of European local authorities for the promotion of local

sustainable energy policies.

ICLEI-Local Governments for Sustainability ICLEI is a democratically governed membership association of

cities, towns, counties, metropolitan governments, and local

government associations. Its mission is to "build and serve a

worldwide movement of local governments to achieve tangible

improvements in global sustainability with special focus on

environmental conditions through cumulative local actions."

Within ICLEI the Cities for Climate Protection campaign, a

"performance-oriented campaign that offers a framework for

local governments to develop a strategic agenda to reduce global

warming and air pollution emissions." That campaign now has

over 500 local government participants representing 8% of

global carbon-dioxide emissions.

Programme on solar cities

Australia National Solar Cities Program Australia National Solar Cities Program was launched in 2004,

providing 75 million Australian dollors in funding over eight

years for solar city related projects at least in four Australian

cities. The solar cities programme will run from 2004-05 to

Page 25: Master plan to make Chandigarh a Solar City

9 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

2012/13, with the focus on programme design and site selection

in the first year. The programme aims to support at least four

solar city projects in grid-connected urban centres across

Australia. Three cities have already been identified (i.e.

Adelaide, Townsville, Blacktown) Solar cities will be

implemented by the Department of the Environment and

Heritage in an purpose of demonstrating that how solar power,

smart meters, energy efficiency and new approaches to

electricity pricing can combine to provide a sustainable energy

future in urban locations throughout Australia.

„Solar Cities‟ Programme in India India‟s first initiative towards solar city was undertaken by the

Government of Gujarat, which decided to make its capital city

„Gandhinagar‟ as a Solar City. A Master Plan for the same was

prepared by TERI in 2007 and now its implementation is being

carried out.

Ministry of New and Renewable Energy (MNRE),

Government of India recently announced a program for

development of solar cities. A total of 60 cities or towns are

proposed to develop as solar city during the 11th five year plan

period of MNRE.

Case studies2

Solar city: Adelaide, Australia It is the first solar city project in Australia. The Adelaide green

city program has formulated within the contest of several other

planning and strategic agendas. Adelaide City Council in 2004

adopted a three-year strategic city management plan in order to

make the city as green city.

The primary goal in the Adelaide programme is

Zero net greenhouse gas emission in building by 2012 and in

transport by 2020

Recognized internationally as a green city by 2010

The green city programme is financed partly by new national

government A$ 75 million fund for solar cities, partly by South

Australia state government and partly by the city government.

The green city project in Adelaide includes incorporation of

Solar technology: Solar PV systems have been installed

in major public building such as museum, art gallery,

parliament house, schools etc. Grid interactive system with

smart electricity meter are being considered in the

2 Case studies are taken from Renewable Energy Information on Markets, policy, investment and future pathways by Eric Martinot from following references; http://www.martinot.info/solarcities, www.solarcity.com/

Page 26: Master plan to make Chandigarh a Solar City

10 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

residential sector which can sell power back in to the grid at

peak times.

Energy efficiency measures in commercial

buildings: Under the project, ten major commercial office

buildings are considered for conducting the energy audit in

each of the building. Each building is then assigned with an

“energy star” rating of one to five. The objective of the audit

is to increase the rating of each building by at least one star.

Eco-housing

Energy audit

Solar city, Barcelona, Spain Solar city concept in Barcelona was started with the “Barcelona

solar thermal ordinance” which represents a major milestone

in Urban Energy Policy. The ordinance is a part of “energy

improvement plan to the year 2010 for renewable energy and

energy efficiency”. As per the ordinance, at least 60% of the

domestic hot water energy demand and 100% of swimming pool

heating of all new buildings above a certain size (292MJ/day of

hot water energy consumption) has to be met through solar

thermal collectors.

Before the ordinance, Barcelona had 1650 m2 of solar

thermal collectors installed or 1.1 m2/1000 people and with the

enactment of the ordinance and by 2004, it had increased to

21,500 m2 or 16.5 m2/people. The city‟s objective is to install

96,000 m2 of solar hot water system by 2010.

Besides Barcelona, other cities in Spain such as Madrid,

Burgos, Sevilla, Onil etc had also adopted solar thermal

ordinance. Although the current ordinance takes care of solar

hot water system only, it is expected that future revision might

take place with incorporation of other renewable energy

applications as well.

Solar city, Linz, Austria It is an integrated solar village for 1300 households on the

outskirts of Linz. The city administration and 12 separate

building contractors jointly developed the village design.

This solar village consists of 2-4 storey buildings with south

facing facades, passive solar heating while ensuring energy

efficient constructions. It also includes installation of solar PV

systems for electricity generation.

The total construction cost of the project is 200 million

euros.

Solar city, Cape Town, South Africa A solar city initiative in Cape Town was started with its

Integrated Metropolitan Environmental Policy (IMEP), which

envisages several targets, vision statements etc.

The following 4 primary targets are set in order to realize the

vision for Cape Town in 2020:

Page 27: Master plan to make Chandigarh a Solar City

11 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

1. 10% contribution from renewable energy sources by 2020

2. 10% households have solar water heater by 2010

3. 90% of households have CFL by 2010

4. 5% reduction in local government electricity consumption

by 2010

It was found that transport sector contributes half of the total

energy consumption of the city and the most significant green

house gas emissions from city and public facilities were from

landfill gas, streetlights and city government buildings and

vehicles. Hence initial projects have focused on landfill sites,

city government buildings and vehicles.

In Cape Town pilot projects and full-scale implementation

are planed in various sectors such as residential, commercial,

industrial, transport etc.

Solar city, Daegu, Korea Daegu solar city programme is based on its master plan to the

year 2050, which has systematically incorporated renewable

energy into city development. In 2002, the center for solar city

Daegu was established by the city and Kyungpook National

University for research, planning, financial sourcing, linking

local policy with national policy etc.

Solar city programme includes installation of following

1. Solar hot water system. About 3400 m2 have been

installed since 2002 in public facilities like orphanages and

nursing homes.

Solar photovoltaic system. 635 kW of PV have been

installed in schools, parks, and other public buildings.

About 550 out of 1700 buses are already run through CNG

and the target is to convert all buses to CNG-fueled by

2008.

Wind, small hydro, and landfill gas projects are planned. A

"green village" is planned, along with a "solar campus"

program to apply solar technologies to schools and

universities.

Solar city, Oxford, UK The Oxford Solar Initiative was started in 2002 as a partnership

between the city, Oxford Brooks University, and the local

community. The primary target of the initiative is to convert

10% of all homes in the city to have solar energy by 2010. Some

short-term targets such as installation of energy efficiency

measures, solar hot water system, reduction of CO2 emission,

capacity building for the local government are also included in

the initiatives.

The oxford solar city initiatives have three primary goals as

mentioned below.

1. To add a sustainable energy element to urban planning

strategies;

Page 28: Master plan to make Chandigarh a Solar City

12 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

2. To set targets, conduct baseline studies, and develop long-

term scenarios; and

3. To develop sustainable urban energy technologies

As part of the initiative, Oxford has been conducting analyses of

the CO2 emissions of its built environment using geographic

information systems (GIS) to predict baseline energy use for

each house.

Oxford has also introduced the concept of “solar street" in

which all the homes on one street have solar hot water and solar

power. These solar power systems are connected to the electric

grid via a "power gate" that allows the community to obtain

Renewables Obligation Certificates (ROC) from the utility for

the power generated.

As far as the availability of financial assistance to

homeowners is concerned, following two types of assistance are

available.

(1) For energy efficiency improvements, the grants cover

typically 60-100% of the full cost of wall and loft insulation,

hot water tank insulation, condensing boilers, heating

controls, and efficient light bulbs (which are provided free

of charge).

(2) For renewable energy, the grants cover up to 50% of the full

cost of solar electric systems and up to £500 for solar hot

water systems.

Solar city, Freiburg, Germany In 1996, a greenhouse gas emissions target was set, at 25%

below 1992 levels by 2010 in Freiburg. In 2002, the city council

set another target, 10% of all electricity from renewables by

2010 (in 2002 the level was 3.7%). The policy measures include

city-financed solar projects, other demonstration projects,

leasing of roof surfaces to solar power generators, research,

subsidies, zoning, urban planning, and education. There are 3.5

MW of PV and 8700 m2 of SHW in the city currently.

Solar City, Gelsenkirchen, Germany The city of Gelsenkirchen itself is a coal-and-steel industrial city

that advocates are hoping to transform into an "energy city."

The city has begun to incorporate solar into housing plans and

conduct information and marketing campaigns and training

programs, as well as assisting local businesses.

The Gelsenkirchen Science Park was home in 1995 to the

largest roof-mounted solar PV plant, 210 kW that existed at the

time. Since then, the park is being transformed into a base for

local production and R&D for clean energy technologies.

Solar City, Goteborg, Sweden Göteborg city has a long-term commitment to sustainable

energy, including energy-efficient buildings, renewable energy,

Page 29: Master plan to make Chandigarh a Solar City

13 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

energy-efficient urban planning, and ultimately "energy storage

in a hydrogen society." The project Göteborg 2050 is developing

long-term visions of a future city and region.

The project is a collaborative effort between universities, the

city government, and the city's energy utility; which includes

research, scenario development, support for strategic planning,

dialogue with the public, and demonstration projects. The

project calls its methodology "backcasting", in which one starts

with a description of the present situation and trends, then

considers alternative scenarios for the future that are

considered more sustainable, and then works backwards to

consider processes for changing current trends, strategic

planning, and Master Plan s that will lead along pathways to the

alternative scenarios. The city has also pioneered the design

and construction of a number of demonstration homes that use

only solar energy for heating and hot water, even in the winter.

Gwangju, Korea Gwangju receives the most sunlight of any Korean city. The city

anticipates solar heating and power will be key technologies.

Collective-heat systems and other innovations in energy supply

will accompany the demand-side and renewables investments.

There are also public education programs, research on energy

efficiency improvements, and technology R&D programs to

develop the city's own industry towards solar and other clean

energy. The policies promoting the use of solar energy were

adopted in 2004. The city of Gwangju has a target to reduce

greenhouse gas emissions by 20% by 2020. Intermediate goals

are an 8% reduction in energy demand by 2011 [baseline not

stated], and renewable energy targets for 1% of energy supply by

2011 and 2% by 2020; while the share of renewables, in 2004,

was 0.5%.

The Hague, Netherlands The Hague commissioned a profile of the carbon dioxide

emissions from the city in 2001. It found that for the 220,000

homes, residential emissions were 1.1 Mt/year, or about 5

tons/home. Transport emissions were 0.4 Mt, or about 2

tons/home and the combined emissions of industry,

commercial, and public sectors were 1.0 Mt/year. The Hague, a

city with very little heavy industry, are 2.5 Mt/year for 463,000

residents, or 5.4 tons CO2/person/year. The Hague published

an environmental policy planed in 2001. The basic objectives are

to make the municipal government "CO2-neutral" by 2006 and

the entire city CO2-neutral in the longer-term. "CO2-neutral"

means that all CO2 emissions are either eliminated or offset by

emissions reductions elsewhere.

The city is currently trying to learn the lessons from 15

demonstration projects that have been described in a

"sustainable projects construction book" issued in September

Page 30: Master plan to make Chandigarh a Solar City

14 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

2004. It envisions future visions, policies, grant schemes, and

oversight of both the overall process and individual projects

implemented by the private sector. The city has allocated budget

for sustainability, and has one million euros to spend from

2004-2008. One project moving ahead is a district-heating

supply plant utilizing seawater heat pumps. The city's approach

is to lead but to allow the private sector to do the bulk of the

work. As the Vice Mayor wrote, "When the municipality takes on

the role of lead player, it is surprising to see how many

organizations in the community and how many private

companies are willing to join in efforts towards sustainable

development". Households in The Hague are already significant

consumers of green power; 30% of all households are buying

green power.

Minneapolis, USA The city currently purchases 10% of its municipal power as

green power from renewable energy. It has a renewable energy

development fund of $8.5 million annually. With this, the city

plans to encourage development of small-scale renewable

energy projects in the future, including use of renewables in

schools, libraries, and parks. It would like to create a distributed

generation grid that can be islanded from the main utility

system when necessary. The city sees the benefits of renewables

in terms of public safety (backup for emergencies), lower costs

for some public works, and a tool for community development.

The city is also developing two pilot biomass projects using

wood and agricultural wastes. Local power utilities are required

to invest 2% of the revenue from power sales into energy

conservation programs.

Portland, USA Portland has an extensive history of land-use and transportation

planning, based on its urban growth boundary, created some 30

years ago. The boundary has concentrated growth and allowed

greater use of public transit, bicycles, and walking, reducing

energy consumption in transport. Zoning codes provide

incentives for building along transit corridors and parking limits

for new construction.

Portland adopted a local energy policy back in the late 1970s,

the first of its kind in the United States. Portland's first

greenhouse gas reduction plan was adopted in 1993, also the

first local plan in the United States. The plan was updated in

2001 with a goal of reducing greenhouse gas emissions to 10%

below 1990 levels by 2010. The plan also includes a target of

supplying 100% of the municipal government's electricity needs

from renewable energy by 2010 (the level was 10% in 2004).

From 1990 to 2003, Portland's per-capita greenhouse gas

emissions decreased by 13%. Total emissions are only slightly

above 1990 levels, despite a 16% increase in population.

Page 31: Master plan to make Chandigarh a Solar City

15 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

Gasoline use fell by 8% per capita. Electricity use for households

fell by 10%.

Incentives for renewable energy include a 25% residential

energy tax credit, a 35% commercial business tax credit, and

funds from the Energy Trust of Oregon. The Energy Trust of

Oregon collects a 3% "public purpose" tax on utility bills, about

$60 million/year. $10 million/year of that goes to renewable

energy projects. Other funding comes from carbon offsets, green

certificataes, and municipal bonds.

Portland's "green building" program integrates energy and

water conservation with recycled building materials and other

environmental strategies. The city requires all new city facilities

to meet LEED, the standard of the US Green Building Council.

Any private construction project that uses city funding for

affordable housing or major commercial development must also

satisfy the LEED standard. Portland now has more LEED-

certified buildings finished or underway than any other city in

the United States.

Qingdao, China

Qingdao is promoting four types of renewable energy:

Solar hot water and power. The use of solar hot water in

Qingdao has been growing at 15% per year, and there are

now 150,000 m2 installed (equal to roughly 0.03

m2/person).

Seawater heat pumps. The first pilot project is being

developed.

Wind power. There are now 16 MW installed.

Biomass gasification. There are 15 biomass gasification

plants operating, utilizing waste crop stalks and supplying

gas to 3000 households.

Santa Monica, USA In 1994, Santa Monica adopted a Sustainable City Plan which

includes goals for greenhouse gas emissions reductions. Since

then, the city has increased renewable energy generation and

purchases, improved energy efficiency, and fostered alternative

fuel vehicles. The city now purchases 100% of municipal

electricity needs from green power suppliers. In addition, the city

has 300 kW of solar PV installed. There are green building

guidelines and a mandate for green buildings for new city

facilities. The city has converted its fleet of garbage trucks and

buses to run on natural gas. Other city vehicles are natural gas

fuelled or electric/gas hybrids. Electric vehicle charging stations

exist around the city. Together, the above measures by 2000 had

reduced greenhouse gas emissions by 5% below 1990 levlels. For

the future, a new Community Energy Independence Initiative

proposes to generate 100% of the city's energy needs within city

borders, based on cogeneration and renewable energy.

Page 32: Master plan to make Chandigarh a Solar City

16 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Sapporo, Japan The city of Sapporo has a stated goal of a 10% reductions in CO2

emissions per capita by 2012 (relative to 1990 levels). This is

consistent with Japan's overall 6% emissions reducation target

under the Kyoto Protocol. However, Sapporo's emissions in

2000 were 16% above 1990 levels, meaning a substantial

reduction will be required in the future (a situation typical of

virtually all Kyoto Protocol signatories). The city groups its

activities into four categories: public awareness (called "sense of

crisis"), measures aimed at stimulating citizen initiative (called

"movement"), incentives (called "propagation to citizens and

business operators"), and city-sponsored activities (called

"initiatives of the city government").

The city has purchased 55 low-emissions vehicles for its use,

including 34 natural-gas cars and garbage trucks. There are five

solar power demonstration projects in schools (typically 10kW

size, providing 7-8% of school's power consumption), as well as

other public facilities like the zoo. As for private development,

one suburban residential complex with 500 homes to be

constructed by 2008 is expected to have 1500 kW PV (3 kW per

home). In the future, the city plans to use snow in wintertime to

displace cooling energy demand and continue R&D on fuel cells

and hydrogen, including hydrogen transport and storage and

efficient natural gas reforming.

To summarize, Table 2.1 gives a checklist of

parameters/activities, which have been included in different

case studies.

Table 2.1 Checklist of parameters and initiatives taken up

City RE

goals

CO2

goals

SHW Solar

PV

Transport Buildings Planning Demos

Adelaide, Australia √ √ √ √

√ √ √ √

Cape Town, South

Africa

√ √ √

Daegu, Korea √ √ √ √ √

Linz, Austria √

Oxford, UK √ √ √ √ √ √

Freiburg, Germany √ √ √ √ √

Gelsenkirchen, Germany √ √

Goteborg, Sweden √ √

Gwangju, Korea √ √ √

The Hague, Netherlands √

Minneapolis, USA √ √

Portland, USA √ √ √ √ √ √ √ √

Qingdao, China √ √

Santa Monica, USA √ √ √ √

Sapporo, Japan √ √ √

Page 33: Master plan to make Chandigarh a Solar City

17 Review of global „Solar City‟ projects

T E R I Report No. 2008RT03

Parameters

RE goals Targets or goals set for the future share of energy

from renewable energy.

CO2 goals Future CO2 emissions targets set, usually on a city-

wide or per-capita basis, and often referenced to the

emissions of a base year (like 1990 or 2000).

SHW Policies and/or incentives for solar hot water

enacted.

Solar PV Policies and/or incentives for solar power enacted.

Transport Policies and/or urban planning approaches for

sustainable transport enacted/being used.

Buildings Energy-efficient building codes, standards, and/or

incentives enacted.

Planning Overall urban planning approaches with

consideration for future energy consumption and

sources.

Demos Specific projects, subsidized by public funds or

otherwise financed as one-time demonstrations or

limited-scale investments in any of the above

categories.

Page 34: Master plan to make Chandigarh a Solar City

18 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 35: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 3 National and international practices

Energy conservation in buildings Residential, public and commercial buildings consume a large

amount of energy mostly for lighting, appliances, space heating

and water heating. In order to improve energy efficiency and

conserve energy through the concept of the „solar city‟, existing

buildings and new buildings must evolve to incorporate energy

efficiency and energy conservation measures.

To encourage global best practice in Chandigarh, this section

considers how energy efficiency is incorporated into building

codes in Australia, Canada, the U.S.A and India, and how

building practices are managed internationally and in India.

These countries are considered as they are some of the world‟s

leaders in energy efficient building design and also have a

similar climate to India.

Strategies to achieve energy efficient buildings according to

international practice will be discussed here for the main

components of a building in order to achieve energy efficiency

and conservation in the developing „solar city‟ of Chandigarh.

Information on technologies and energy saving methods

outlined in this chapter aim to assist the Chandigarh Renewable

Energy, Science & Technology Promotion Society (CREST) in

going beyond basic energy efficiency strategies and to provide

more the tools for innovative designs for new and retrofit

buildings.

Achieving energy efficient buildings As Chandigarh lies in the composite climate3, any energy

efficient building system must be designed according to this

climate. This should also be a major consideration when looking

at international practices that /are suitable to follow.

Energy conservation regulations

Australia

Building controls and regulations in Australia are the

responsibility of the States and Territories. The BCA provides a

nationally uniform code for technical requirements in buildings.

The BCA 1996 (the current BCA) is a performance-based code

subject to State and Territory variations. Local councils and

private certifiers are responsible for administering the BCA and

some local councils use planning legislation to enforce energy

efficiency measures for buildings in their region.

3 according to ECBC 2006 climate zone map of India

Page 36: Master plan to make Chandigarh a Solar City

20 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

In Australia there exists the Green Building Council of

Australia (GBCA), which considers best practice for building

energy. They have a Memorandum of Understanding with

Building Construction Interchange and they have ensured that

energy efficiency is incorporated into their Building Codes of

Australia (BCA). They promote sustainable buildings by

recognising them through the Green Star rating system, which

ranks buildings according to certain ecological and

environmental criteria4. It is based on the British BREEAM

(Building Research Establishment Environmental Assessment

Method) and America‟s LEED (Leadership in Energy and

Environmental Design). This system was created for the

property industry to encourage green building design and create

awareness of the benefits. Not only can they market green

buildings to consumers on the basis of cost savings, but also

green buildings have an attached sense of leadership in the

property industry at present.

Currently the system of rating is for office buildings, followed

by health centres and educational facilities. Soon it will also be

developed for some multi-unit residential complexes but has yet

to be developed for housing.

The main reason that commercial buildings have been

targeted first is due to their huge contribution to emissions in

Australia. They contribute 8.8% (particularly offices and

hospitals) to total emissions and this must be reduced in order

for Australia to meet their international emissions obligations5.

For residential buildings it is suitable to refer to guidelines by

the Australian Greenhouse Office6.

The GBCA also works closely with the Canadian Green

Building Council (CaGBC) but have not developed sustainable

practices as far as the Canadian Council.

Canada

In Canada there exists the National Building Code of Canada

2005 (NBC 2005). This is for use by officials, educators and

construction professionals. However this code does not directly

deal with energy conservation and hence there is a separate

Model National Energy Code for Houses 1997 (MNECH) and

Model National Energy Code for Buildings 1997 (MNECB). The

MNECH allows designers the freedom to choose the level of

energy efficiency they wish to achieve for a given climate and

type of fuel used in the home. This code is applicable to

residential buildings up to three storeys high and additions to

buildings up to 10m2. The MNECB considers minimum

requirements for building features, which dictate energy

4 http://www.gbcaus.org/gbc.asp?sectionid=15&docid=881#a 5 http://www.gbcaus.org/gbc.asp?sectionid=90&docid=954 6 http://hia.com.au/hia/channel/Builder/region/National/classification/Greensmart/Resources/Passive%20Design.aspx

Page 37: Master plan to make Chandigarh a Solar City

21 National and international practices

T E R I Report No. 2008RT03

efficiency. It considers regional construction costs, regional

heating fuel types and costs, and regional climatic differences.

This code considers the building envelope, water heating,

lighting, HVAC systems, and electrical power.

For best practice in Canada for residential buildings there is

the EnerGuide offered by the government and also R-2000

houses scheme. Both these offer buildings that are achieve best

practices in energy efficiency and builders who engage with

these schemes will do so to provide high quality housing for

buyers and a reduction in energy costs for the buyer. Several

provinces/territories are currently considering incorporating

the MNECB in their building regulations. If adopted by a

province, territory or municipality, the provisions of the

MNECB will become law in that region. The same is the case for

MNECH. These energy efficiency codes are to be used

alongside the NBC 2005.

Some of the Canadian provinces and the Government have

energy efficiency acts and the MNECB and MNECH refer to

these and give minimum energy requirements. If local

legislation exists then this is followed. If it does not exist at

federal or province level then the MNECB/MNECH is followed.

However the codes are not mandatory unless stated in local

legislation.

The CaGBC have chapters across Canada that work to

promote green building concepts in their respective local areas.

They use the LEED rating system for Canada and help local

property developers understand how to make buildings more

energy efficient. The CaGBC also aims to take building practice

beyond the MNECB and MNECH.

U.S.A

In the U.S.A building codes vary across the country from State

to State. There are three tiers of National, State and Local level

all of which can have legislation that applies to buildings in a

specific region. Depending on the State, building codes can

apply directly to green building design or can incorporate

features such as energy efficiency without directly referring to

green building design. Some states (earlier Washington offered

subsidies) subsidise the use of renewable energy in buildings to

encourage people to invest.

In the US there exists International Energy Codes (IEC) and

the American National Standards Institute/American Society of

Heating, Refrigerating and Air-Conditioning Engineers

standards (ANSI/ASHRAE/IESNA Standard 90.1)

requirements. There has been a Building Energy Codes

program, which encourages the adoption of building energy

codes by state governments7.

7 http://www.energycodes.gov/implement/pdfs/ta_com.pdf

Page 38: Master plan to make Chandigarh a Solar City

22 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

India

In India there exist the National Building Codes 2005 (NBC

2005) and the new Energy Conservation of Buildings Codes

2006 (ECBC 2006). The national building codes only consider

regulations in building construction primarily for the purposes

of regulating administration, health and safety, materials and

construction requirements and building and plumbing services

whereas the ECBC 2006 consider energy conservation and

energy efficiency in buildings „to provide minimum

requirements for the energy-efficient design and construction of

buildings.‟ The NBC 2005 refers to a wide variety of building

type and ownership (government, non-government etc.)

whereas ECBC 2005 only refers to commercial buildings and

some building complexes.

The ECBC 2006 mainly considers administration and

enforcement, the building envelope, HVAC, service hot water

and pumping, lighting and electric power to encourage

conservation of energy. These are considered in new buildings

and additions to existing buildings.

At present the Energy Conservation Act 2001 empowers the

state governments to adjust the codes according to local

conditions. This encourages inconsistency in building practices

across to country and can lead to huge deviations from the

existing codes. There are currently state designated agencies for

implementation of this code for example in Chandigarh, the

Chandigarh Renewable Energy, Science & Technology

Promotion Society (CREST) is the state designated agency for

implementing the Energy Conservation Act 2001 and hence

ECBC 2006. In Pondicherry and the Andaman and Nikobar

Islands, the local Electricity Department is responsible for

enforcing energy conservation policy and regulations at local

level. The regulating authority is different for each state and is

responsible for enforcing the adapted building codes for that

state. Experts (architects and engineers) check the plans for new

buildings or changes to existing buildings and permit the

builder to carry out construction if the designs meet code

requirements. They are rejected and sent for alteration if they

do not meet requirements. After the building is built it must

again be certified as complete by the state designated agency

before it is used.

The Bureau of Energy Efficiency is working on certifying

Energy Auditing Agencies in order to evaluate buildings energy

use, which will enable better regulation of energy conservation

in buildings.

In order to encourage green rating practices of buildings,

The Energy and Resources Institute (TERI) has developed the

TERI-GRIHA rating.

Points are given for different criterion at the site planning,

building planning and construction, and the building operation

and maintenance stages of the building life cycle.

Page 39: Master plan to make Chandigarh a Solar City

23 National and international practices

T E R I Report No. 2008RT03

All buildings, except for industrial complexes and housing

colonies, which are in the design stage, are eligible for

certification under the TERI system. Buildings include offices,

retail spaces, institutional buildings, hotels, hospital buildings,

healthcare facilities, residences, and multi-family high-rise

buildings.

Buildings are evaluated and rated in a three-tier process. The

preliminary evaluation is done to estimate the number of points

the project is likely to get. Then relevant documents will be

submitted for each criterion (format provided by TERI-

GRIHA). Then the documents will be evaluated and re-

evaluated after adjustment by the TERI evaluation committee.

The evaluation committee awards the final score for the project,

which is then presented to an advisory committee. The final

rating is valid for a period of 5 years from the date of

commissioning of the building.

Each criterion has a number of points assigned to it. The

system is a 100-point system consisting of some core points,

which are mandatory (or partly mandatory) and the rest are

optional. There is then a one to five star certification system to

finally rate the building8.

In India, as has been the case with the introduction of wide-

scale introduction of renewable energy technologies for a

variety of applications Ministry of New and Renewable Energy

announced the scheme „Development of Solar Cities’ under

which an indicative target of 60 cities/towns with at least one in

each State has been set for the 11th Plan period. The Ministry of

New and Renewable Energy (MNRE) proposed to develop 60

such cities during the current Plan period (2007-12). The

targets will be achieved by providing support for preparation of

a Master Plan for their city; setting up of a „Solar City Cell‟ in the

Council/Administration, organizing training programmes/

workshops/ business meets for various stakeholders such as

elected representatives of the municipal bodies, municipal

officials, architects/engineers, builders and developers,

financial institutions, NGOs, technical institutions,

manufactures and suppliers, RWAs etc. and on creation of

public information and awareness.

Lighting Lighting is a component of buildings that contributes up to 20%

of buildings electricity consumption in an air-conditioned

building. In a non air-conditioned building it is the most

significant source of energy consumption.

When designing a lighting system, the critical factors

according to U.S.A based Energy Design Resources are as

follows.

8 reference TERI-GRIHA document

Page 40: Master plan to make Chandigarh a Solar City

24 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Design according to lighting demand and distribute any

glare that is present.

Maximise use of natural daylight but avoid direct sunlight

and install appropriate controls for lights.

Use high-efficiency fluorescent systems for commercial

spaces.

For further lighting requirements (e.g. atmospheric) use

incandescent and compact fluorescence sources.

Make use of high intensity discharge systems such as pulse

start metal halide for outdoor systems, and ceramic metal

halide if colour quality is a concern (such as in retail

outlets)9.

TERI-GRIHA rating system contains a set of basic requirements

in order to optimise the buildings design for reducing energy

demand from lighting. The main aim is to apply passive solar

techniques to buildings to enhance the use of natural sunlight in

order reduce energy consumption from lighting.

The criteria commitments outlined in the TERI-GRIHA are

as shown in the box below.

Criteria for lighting 12.1.1 Arrange spaces with respect to favourable orientations 12.1.2. Shade the east-west walls using shading devices 12.1.3. Do solar path analysis to arrive at an appropriate size of shading device for each orientation or, use shading norms prescribed in SP 41: 1987 – Functional requirement of buildings. Also adhere to Solar Heat Gain Coefficient as per ECBC 2006. 12.1.4. Perform daylight simulation and ensure that all living spaces shall have a minimum of 75% area with daylight factor as prescribed in Bureau of Indian Standards (SP41:1987 Functional requirement of buildings) under overcast conditions. 12.1.5. Perform lighting simulation to demonstrate that the lighting levels in indoor spaces are maintained as recommended in National Building Code 2005, Bureau of Indian Standards, Part-8 building services, Section 1, Lighting and ventilation, Table 8.

Source: TERI-GRIHA

The majority of these practices refer more to commercial

buildings because lighting systems in households are less

complex. For the residential sector the largest saving potential

is by replacing all incandescent lights with compact fluorescent

lighting (CFL)10, which produces a saving of approximately 75-

85%. Those commercial buildings that have already made this

switch and must incorporate better-designed lighting systems

according to the information outlined in this section in order to

improve efficiency and maximise use of natural sunlight.

The Canadian organisation, Natural Resources Canada

offers advice for energy efficient measures that are summarised

in the table below. These are suitable for the Chandigarh‟s hot-

dry climate and also those that directly have an effect on energy

consumption.

9 http://www.energydesignresources.com/docs/db-01-lighting.pdf 10 Sustainable Building Design Manual, Volume 2, Published by TERI.

Page 41: Master plan to make Chandigarh a Solar City

25 National and international practices

T E R I Report No. 2008RT03

Table 3.1 Suggested energy efficiency measures for commercial buildings

Technology Description Building use and type Benefit and limitations

External Shading

Device

Incorporated in building façade to

limit internal heat gain from solar

radiation. Often in the form of

horizontal sunshades attached above

windows on south facing walls.

Vertical louvers for east and west

facing windows are also effective

High rise office; low rise office; low

rise apartment; retail; food service;

institutional; arena; used for new

and existing buildings

Reduces cooling loads but does

increase capital costs and

maintenance.

Shading with

Vegetation

Deciduous vegetation planted

primarily on southwest and west side

of building to block sun.

High rise office; low rise office;

high rise apartment; low rise

apartment; retail; food service;

institutional; arena

Reduces air conditioning needs

and creates a cooler building

climate. Reduces heat loss from

wind also. However plants must

be chosen to adapt to local

climate. It requires maintenance

also and it needs space available

for planting.

High Intensity

Discharge (HID)

Lamps

Produce light by striking an electrical

arc across tungsten electrodes

housed inside a specially designed

inner glass tube. Typically used when

large amount of light for large area is

required.

High rise office; institutional; retail;

arena; parking garage; food

service; warehouse and industry;

residential; used in new and

existing buildings

Increases energy efficiency of

lighting. Initial cost is higher than

conventional lamps but energy

saving is 15 to 25% for these

energy saving lamps.

Dimmable

Compact

Fluorescent lamps

(CFL‟s) and

electronic

dimmable ballasts

Dimming results in lower energy

usage

High rise office; low rise office; low

rise apartment; arena; institutional;

retail; food service; used in new

and existing buildings

Lowers energy consumption and

has longer lamp life. However,

higher cost and larger fixtures

required.

Daylighting

controls

Controls that respond to levels of

natural light by dimming or turning off

electric light

High rise office; low rise office;

retail; food service; institutional;

used in new and retrofit buildings.

High costs and rapid change in

lighting can be disturbing.

However it reduces electricity

use.

T8 fluorescent

lamps

16mm diameter high-efficiency

fluorescent lamp produced in metric

sizes.

High rise office; low rise office; low

rise apartment; retail; food service;

institutional; arena; used in new

and existing buildings.

Increases energy efficiency and

lower operating costs. However

may increase glare.

Indirect lighting

systems

Direct indoor lighting to floors and

ceilings where it is reflected back to

room

High rise office; low rise office;

retail; food service; institutional;

used in new and existing buildings

Eliminates glare and shadows,

reduces electricity use and

cooling loads, and reduces

required light levels. However,

requires high ceiling height and

perhaps higher initial costs.

Information adapted from Canadian strategies for commercial buildings11 and Sustainable Building Design Manual12 (a

collaboration of UK, Spain and Indian expertise in energy efficiency)

11 www.advancedbuildings.org 12 Sustainable Building Design Manual, Volume 2, Published by TERI

Page 42: Master plan to make Chandigarh a Solar City

26 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Support mechanisms

The US government offers a federal tax deduction for reduction

in energy use in lighting systems that go beyond the ASHRAE

guidelines. This incentive allows energy efficient lighting to be a

cost effective measure13. The Chandigarh Renewable Energy

Science and Technology promotion society (CREST) currently

offer subsidies for indoors and outdoors solar lighting devices

for community and individual users14. This should be further

promoted in the „solar city‟ to encourage people to adopt these

energy efficient technologies.

Heating, Ventilation, and Air-Conditioning (HVAC) systems There is a huge potential for energy saving through more energy

efficient HVAC systems, as they are known to contribute 40-

50% of a building‟s electricity consumption if the building is air-

conditioned15.

Natural ventilation, a certain minimum equipment

efficiencies, HVAC controls, piping and ductwork, condensers

and solar water heating in new (or addition to existing)

commercial air-conditioned buildings should all comply with

guidelines in ECBC 2006 and NBC 2005. NBC 2005 specifies

ventilation requirements for household spaces and hence it is

recommended that these be used as the standard for the „solar

city‟.

Criteria for HVAC systems 13.1.1. Follow mandatory compliance measures as recommended in ECBC 2006. 13.1.2. Show that energy consumption in energy systems in a building under a specified category is less than the benchmarked energy consumption figure, through a simulation exercise. The energy systems include air conditioning, indoor lighting systems, water heating, air heating and circulation devices within the building. 13.1.3. The annual energy consumption of energy systems in a fully non-air conditioned building for day use should not exceed 26 kWh/m2. 13.1.6. Quantify energy usage for all electrical, mechanical, and thermal systems for which either electrical or thermal energy is being used and which are (water and air), and air circulation. To convert thermal energy to electrical energy the following table should be used 13.1.7. Perform hourly calculations to show that in non air conditioned areas, the thermal comfort conditions as specified in NBC 2005, Part 8 Building services; section 1 – lighting and ventilation; Desirable wind speeds m/s for thermal comfort conditions, Table 9 and 10 are met for 9% of all occupied hours. 13.1.8. Perform hourly calculation to show that in air conditioned areas the thermal comfort conditions as specified in the NBC 2005, part 8 Building services; section 3- Air conditioning, heating and mechanical ventilation, section 4.4.3 inside design conditions are met for 100% of all occupied hours.

Source: TERI-GRIHA

13 http://www.advancedbuildings.net/lighting.htm 14 15 Milli Majumdar, Energy Efficiency in Green Buildings – An Integrated Approach to Building Design, Published in Green Business Directory.

Energy unit Conversion factor for kWh Litres of light diesel oil 8.3 Litres of high speed diesel 8.5 Kg of liquefied petroleum gas 13.9 Standard cubic metres of Pipe Natural Gas 7.0

Page 43: Master plan to make Chandigarh a Solar City

27 National and international practices

T E R I Report No. 2008RT03

The guidelines for alterations to heating, ventilation and air

conditioning in existing buildings are given in ECBC 2006,

Section 6.1.1.3. This is particularly important for Chandigarh

where existing infrastructure must be improved upon to achieve

the concept of the „solar city‟. The criteria are shown in the box

below that relate to HVAC systems.

Aside from these criteria for the TERI-GRIHA rating scheme

and building code commitments there are a variety of

technologies that can be implemented to achieve energy

efficiency over and above the minimum Indian standards.

The Australian Greenhouse Office offers suggestions for

improving the efficiency of HVAC systems in existing buildings

at no cost such as:

Keep heating and cooling off when not in use

Keep doors and windows closed in air conditioned spaces

Turn off equipment when not in use

Adjust thermostats to a higher temperature setting (ACs)

Allow free airflow

Use a zoning system (not all areas of building have to be

cooled and/or heated)16

These measures require users of buildings to maintain the

building and help achieve energy efficiency.

Natural Resources Canada and Sustainable Building Design

Manual offer further solutions to improve energy conservation

in HVAC systems by more energy efficient systems and

technologies. These are outlined in Table 3.2 below.

Table 3.2 Alternative technologies to improve energy efficiency of HVAC systems

Technology Description Building type and use Benefits and limitations

Radiant heating and

cooling

Heating and cooling system

relying primarily on radiation

heat transfer. Typically

heated or chilled water is

circulated through ceiling and

floor panels to condition the

space

High rise office; low rise office;

high rise apartment; low rise

apartment; residential;

institutional; retail; used in new

and existing buildings.

Lower parasitic energy

consumption (for pumps and fans).

Improved thermal efficiency in

comparison to conventional plants.

However may need additional air

conditioning system to prevent

condensation on cooling panels

and higher cost than air-based

systems. Requires air tight and

energy efficient building envelope.

Low NOx burners Natural gas burners with

improved efficiency and less

nitrous oxide emissions

Low rise office; high rise office;

low rise apartment; high rise

apartment; retail; food service;

institutional; used in new and

existing buildings

Increased energy efficiency and

less polluting although it has

higher cost and requires more

maintenance than conventional

systems.

Passive solar heating Use of sun‟s energy to meet Low rise office; low rise Reduces space heating costs and

16 http://www.greenhouse.gov.au/challenge/publications/factsheets/fs2.html

Page 44: Master plan to make Chandigarh a Solar City

28 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Technology Description Building type and use Benefits and limitations

building heating demands apartment; retail; arena; used

for new and existing buildings

provides natural lighting but

restricted to buildings with low

internal heat gains and can cause

high night time heat loss. Not

advised for buildings with large

internal heat gains.

Gas Engine-driven

chillers

An air-conditioning chiller

powered by a natural gas

engine

High rise office; high rise

apartment; retail; institutional;

used in new and existing

buildings

Lower peak electricity demand,

lower cooling costs, and free heat

recovery however uses

refrigerants and requires greater

maintenance.

Alternative

refrigerants

Refrigerants that do not

destroy the earth‟s ozone

layer

High rise office; low rise office;

high rise apartment; low rise

apartment; retail; food service;

arena; institutional; used in new

and existing buildings

Conserves atmospheric ozone and

lowers greenhouse gas emissions

but may be less efficient and less

stable.

Gas fired

chiller/heater

A natural-gas powered

mechanical appliance that

supplies chilled water for air-

conditioning or for process

cooling, as well as hot water

for space heating

High rise office; high rise

apartment; retail; food service;

institutional; used for new and

existing buildings

Eliminates the use of ozone-

depleting refrigerants and reduces

air conditioning costs. However, it

has a higher initial cost and there

are physical constraints when

installing in existing buildings.

Desiccant Cooling/

Dehumidification

Use of chemical or physical

absorption of water vapour to

dehumidify air and reduce the

latent cooling load in a

building HVAC system

High rise office; low rise office;

high rise apartment; arena;

used in new and existing

buildings.

Reduces energy required to

dehumidify and cool ventilation air

and reduces condensation.

Improves efficiency of refrigeration

equipment by operating at higher

evaporator temperatures and

higher Coefficient of Performance.

Also allows alternative AC

approaches. However it has high

initial cost and most effective in

large building with centralised

HVAC equipment.

Enthalpy heat

exchangers

Transfers sensible and latent

heat between two air streams.

High rise office; low rise office;

high rise apartment; low rise

apartment; retail; food service;

institutional; arena; used for

new and existing buildings.

Conserves sensible and latent

heat. Reduces cooling load during

summer and doesn‟t require heat

for regeneration. However it has a

large and bulky configuration.

Energy recovery

ventilators

Device providing ventilation

for dilution or source-control

applications.

High rise office; low rise office;

high rise apartment; low rise

apartment; food service; arena;

institutional; retail; used in new

Improves internal air quality,

energy efficiency and lowers peak

energy demand.

Page 45: Master plan to make Chandigarh a Solar City

29 National and international practices

T E R I Report No. 2008RT03

Technology Description Building type and use Benefits and limitations

and existing buildings.

Natural ventilation

and cooling

Use of outdoor airflow into

buildings to provide

ventilation and space cooling.

High rise office; low rise office;

high rise apartment; low rise

apartment; retail; food service;

institutional; industrial; only for

new buildings

Provides ventilation without using

fans and free cooling without

mechanical systems. Reduces

construction and operating costs of

building and no fan noise.

However less easy to control and

larger temperature fluctuations.

Occupants must adjust windows to

encourage the effect.

Most of these systems are suitable for commercial buildings.

Due to the composite climate of Chandigarh it is important to

prioritise the avoidance of passive heating in buildings and

installing energy efficient cooling equipment.

Support mechanisms

Chandigarh does not currently offer subsidies for most energy

efficient HVAC systems. There is a subsidy for natural water

coolers at present. Various states in the U.S.A, such as

California17, offer financial incentives for more energy efficient

HVAC systems. This encourages their use in new buildings and

when retrofitting existing buildings.

Service hot water and pumping In terms of energy consumption, water heating accounts for

approximately 20% of residential energy use and about 7% of

commercial energy use18. The use of energy by systems in a

building can be reduced by using more energy efficient hot

water heating and pumping systems as well as better

maintenance of existing systems so that they are only in use

when required.

ECBC 2006 gives minimum equipment efficiencies, and

piping insulation criteria to encourage energy efficiency in

service hot water and pumping systems for new and existing

commercial buildings.

It is particularly important to note ECBC’s

requirement that 1/5th of the design capacity for water

heating in residential facilities, hotels, and hospitals

with centralised heating systems, should be provided

by solar water heating systems.

To go beyond basic equipment energy efficiency requirements

in building codes and regulations, one can look further to

international standards.

17 http://www.green.ca.gov/EnergyPrograms/Rebates.htm#hvac 18 http://www.advancedbuildings.org/_frames/fr_t_heat_water_loop.htm

Page 46: Master plan to make Chandigarh a Solar City

30 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

The Australian Greenhouse Office give no cost suggestions to

save energy in water heating and pumping,

Reduce thermostat settings so it is not unnecessarily high.

Turn water heaters off when not required in building.

If using a circulating pump then this should be turned off

outside of usage hours.

Only switch on extra water heaters when needed for the

specific tasks that they are installed for rather than

continuously running them19.

The Sustainable Building Design Manual and Natural Resources

Canada website offer solutions to saving energy using more

energy efficient technologies in water heating and pumping.

Potential technologies are given in Table 3.3 below.

Table 3.3 Potential technologies for water heating

Technology Description Building type and use Benefits and limitations

Direct contact

water heaters

This is a water heating

device without a heat

exchanger and in which

flue gases are in direct

contact with the water

High rise apartment; food

service; institution; used in new

and existing buildings

Increased efficiency and reduced NOx

and CO emissions. However it has a

higher cost and is less effective in

closed loop applications.

Ground source

heat pumps

(geothermal

heating)

Extracts heat stored in the

upper layers of the earth.

Low rise office; low rise

apartment; retail; food service;

institutional; used in new and

existing buildings.

Can reduce energy for space heating,

cooling, water heating in large

buildings by as much as 50%.

Require less mechanical room space,

and has reduced operation and

maintenance costs. However initial

and design costs are higher.

Requires additional site coordination

and supervision.

Solar water

heating

The use of the sun‟s

energy to heat water rather

than gas or electricity.

Residential; high rise office; low

rise office; high rise apartment;

low rise apartment; retail; food

service; institutional; arena;

used in new and existing

buildings.

At minimum operational costs it can

provide most of a buildings hot water

requirements. Reduces use of

electricity and/or fossil fuels. However

will need a conventional back up

system to boost temperature but use

will be limited in a hot dry climate

such as that of Chandigarh.

The savings will mostly be in commercial buildings because the

cost of implementing these technologies in each residence will

be costly.

Support mechanisms

There are no subsidy support mechanisms for solar heating

systems in particular which will be the preferred option for

Chandigarh due to this technology being suitable in the climate

of the proposed „solar city‟.

19 http://www.greenhouse.gov.au/challenge/publications/factsheets/fs8.html

Page 47: Master plan to make Chandigarh a Solar City

31 National and international practices

T E R I Report No. 2008RT03

Building envelope

The building envelope includes fenestration (including vertical

fenestration and glazing), opaque construction, building

envelope sealing (affects air leakage), roofs, walls and skylights

(for commercial buildings).

The Sustainable Building Design Manual recommends that

the ECBC 2006, which is mostly based on the ASHRAE codes of

the U.S.A, should be used for insulation values and SHGC

values in the building envelope in particular.

Electric power Some savings in energy can also be achieved through improving

electric power systems of buildings. ECBC 2006 suggests

suitable maximum transformer power losses for air-conditioned

commercial buildings in India and encourages the use of energy

efficient motors.

Policy review In the context of developing Chandigarh as a Solar City, an

exercise has been undertaken to review the pertinent policies,

legislations, and regulations that have bearing on the planning

and implementation processes. Essentially this review has been

carried out to give a sense of the measures already in place that

could be used for (a) facilitation, (b) enforcement, and (c)

implementation of solar city plans. The main areas of the focus

were policies and legislation that promote energy conservation

and renewable energy utilization. The following section

describes key features of such measures as applicable to

Chandigarh.

Energy conservation and efficiency As per Energy Conservation Act 2001, the state government is

empowered with a number of enforcing powers such as:

The State Government may, by notification, in consultation

with the Bureau of Energy Efficiency (BEE) amend the

energy conservation building codes to suit the local climatic

conditions specify and notify energy conservation building

codes with respect to use of energy in the buildings.

Direct every owner or occupier of a building or building

complex to comply with the provisions of the energy

conservation building codes.

Direct, if considered necessary for efficient use of energy and

its conservation, any consumer referred to get energy audit

conducted by an accredited energy auditor

Take all measures necessary to create awareness and

disseminate information for efficient use of energy and its

conservation.

Page 48: Master plan to make Chandigarh a Solar City

32 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Arrange and organise training of personnel and specialists

in the energy conservation techniques for efficient use of

energy and its conservation.

Take steps to encourage preferential treatment for use of

energy efficient equipment or appliances.

Besides, the EC Act 2001 mandates the State Government to

constitute the State Energy Conservation Fund for the purposes

of promotion of efficient use of energy and its conservation

within the State.

On its part, CREST offers 50% subsidy on the energy audit

charges (or Rs.20,000) whichever is less.

„Development of Solar Cities‟ scheme of MNRE Ministry of New and Renewable Energy of India recently

announced a program for „Development of solar cities‟. A total

of 60 cities/towns covering all parts of the country are proposed

to be developed as solar cities during the 11th five year plan

period of MNRE. A criterion has also been developed in the

scheme for selection of the cities. The major activities of the

programme are

Preparation of master plan

Setting up of „Solar City Cell‟ in the city

Organize training programme /workshops/business

meets/awareness camps etc.

Preparation of proposals for carbon financing and

Organizing publicity and awareness campaign through

media.

The indicative guidelines for preparation of master plan are

given as following;

a. Projection for energy demand and supply for 10 years

Sector wise

Total

b. baseline of energy utilization & GHG emissions

Residential

Commercial / industrial

Institutional

Municipal Services

GHG Emission

c. Energy Planning (Sector wise)

Resources

Option for energy saving & demand reduction

Supply side option based on renewables

Techno-economics of energy conservation & measures

d. Year wise goals of saving in conservation energy through

demand side management & supply side measures based on

renewables

e. Master Plan for achieving the set goals and expected GHG

abatements

Page 49: Master plan to make Chandigarh a Solar City

33 National and international practices

T E R I Report No. 2008RT03

f. Budget estimates and potential sources of funding from

respective sources (both public and private)

„GRIHA‟ scheme GRIHA is an indigenous green building rating system developed

for the Indian construction scenario. It was developed by The

Energy and Resources Institute (TERI) and has now been

adopted by the Ministry of New and Renewable Energy (MNRE)

as the National Green Building Rating System for India. GRIHA

incorporates within itself various other building codes and

guidelines like the National Building Code, Energy Conservation

Building Code, Ministry of Environment and Forests clearance

for construction, Pollution Control guidelines by the Central

Pollution Control Board etc.

GRIHA is a rating system which assesses the environmental

performance of buildings on a scale of 0-104 points with a

minimum of 50 points required for a building to be certified a

GRIHA building. On the basis of number of points scored, a

building can be rated between 1 & 5 stars, I star being the lowest

and 5 star being the highest level of environmental performance.

GRIHA evaluates green building performance on the basis of

various aspects like water and waste management, energy, site

preservation, indoor comfort and air quality and innovation

points. The maximum weight is given on the points for energy,

43 out of a total of 104 points are dedicated towards energy.

There are three broad aspects within energy which are tackled in

GRIHA namely:

1. Embodied Energy: This is the energy which goes into the

construction of the building and building materials. This

usually forms almost 20% of the total energy consumed by

buildings over their complete life cycle. Thus using low

energy materials which are locally available for construction

and have low embodied energy leads to energy savings.

2. Operational Energy: This constitutes almost 80% of the

total energy consumed by buildings over their entire life. At

present most of the initiatives being taken up by various

stakeholders are dedicated towards reducing the

operational energy requirement of buildings by adopting

various energy efficiency measures. Various features like

solar passive building design and mechanical systems with

high energy efficiency can help in reducing the amount of

energy required during the operation of the building.

3. Renewable Energy: After reducing the energy requirement

of the building, the next step is to ensure that this energy

has least possible carbon footprint. Renewable sources of

energy like solar power, wind power etc. assist in providing

energy to buildings and reduce the amount of energy

required from conventional sources, thereby further

reducing their carbon footprint and GHG emissions.

Page 50: Master plan to make Chandigarh a Solar City

34 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Site preservation and reduction the negative impacts of site

interventions form the next most important aspect of GRIHA.

The process of constructing buildings has a negative impact on

the site and its surrounding habitat. Construction of buildings

leads to destruction of habitat, loss of fertile soil, felling of trees

etc. There are various criteria within GRIHA dedicated towards

ensuring that the impact of constructing the building on a

particular site is minimized. Various aspects like site selection,

top soil preservation, air pollution control, tree plantation,

reduction of heat island effect are taken into consideration.

GRIHA also covers aspects of green buildings like waste and

water management. There are various standards to follow in

order to reduce building water consumption while

simultaneously recycling water and recharging ground aquifers.

GRIHA lays emphasis on the various national water quality

standards as well. Waste is required to be managed, recycled,

reused and appropriately and sensitively disposed. A green

building which is unable to provide good comfort levels to its

users and creates an unhealthy environment for them is not

desirable. Thus GRIHA has criteria dedicated towards

maintaining good indoor comfort levels and air quality.

GRIHA as a rating tool emphasizes upon using traditional

construction techniques and knowledge in order to construct

green buildings. This promotes and encourages the principles of

traditional building systems which have been gathered and

refined over centuries. Another unique feature of GRIHA is that

it rates non air-conditioned, semi air-conditioned as well as fully

air-conditioned buildings. This promotes the use of natural

ventilation as a design strategy breaks the paradigm that green

buildings are necessarily air-conditioned.

Renewable energy The policy directives for promotion of renewable energy, for

2006–07, as prescribed by MNRE and CREST are as follows.

Solar photovoltaic systems New and emerging applications of SPV technology and other

applications will be supported on case-to-case basis.

For the purchase of Solar Photovoltaic (SPV) systems and

power plants, soft loans are offered. The scheme is

implemented through IREDA and designated banks.

Streetlight Solar Control Systems: MNRE supports

municipal corporation to install a maximum of 20 numbers

of `Streetlight Solar Control Systems‟ of 5 Wp SPV module

capacity; with up to 100 streetlights per system, with a grant

limited to 25% of the cost (or Rs.5,000 per system).

Dusk-to-dawn solar street lighting systems: Solar street

lighting systems of 74/75Wp SPV modules and 11 W/ 18 W

CFLs are supported with MNRE grant limited to 50% of the

cost (or Rs.10,000 for 11 W CFL/Rs. 12,000 for 18 W CFL,

Page 51: Master plan to make Chandigarh a Solar City

35 National and international practices

T E R I Report No. 2008RT03

whichever is less). Maximum 100 streetlights per Municipal

Corporation will be supported. CREST, in addition, provides

a subsidy of 25% of the street light cost.

Solar illuminated hoardings: Solar PV systems up to 1 kWp

of SPV module capacity illuminating a minimum of 2 sq.m.

of hoarding area, at least for 6 hours, are supported with

MNRE grant limited to 50% of the cost (or @ Rs.

15,000/100Wp hoarding, whichever is less). A maximum of

20 such holdings will be supported per Municipal

Corporation.

Solar Traffic Signals: Solar traffic systems with minimum

500 Wp SPV modules for four- road junctions will be

supported with MNRE grant limited to 50% of the cost (or

Rs.2.5 lakhs whichever is less). A maximum of 5 such

systems per state capital will be supported.

Solar Road Studs: 50% of the cost, or Rs. 1,000 for each

stud, whichever is less, will be provided as MNRE support. A

maximum of 100 studs per state capital will be supported.

Solar Blinkers: Solar Blinkers with minimum 37 Wp module

capacity and 24 hour operation will be supported with

MNRE grant limited to 50% of the cost (or Rs.7,500,

whichever is less). A maximum of 100 solar blinkers will be

supported.

Solar water heating systems Soft loan up to 85% of solar water heating system cost is

available from the Indian Renewable Energy Development

Agency (IREDA) and designated banks, for a maximum of 5

years duration. The applicable rate of interest is

2% to domestic users

3% to institutional users not availing accelerated

depreciation

5% to industrial/commercial users availing

depreciation

For those institutional and commercial establishments

that do not avail MNRE‟s soft loan scheme; capital

subsidy @ Rs. 1100 per sq.m. of collector area for

registered institutions and @ Rs. 825 per sq.m for

commercial establishments is provided.

CREST is providing subsidy @ 25% of the total system cost

up to 300LPD System (Domestic).

“Demonstration and Promotion of Solar Photovoltaic Devices/ Systems in Urban Areas & Industry” (Roof top SPV systems)

Central Financial Assistance for following systems @ Rs. 150

per watt of SPV panels up to a capacity of 1 kW each with

required storage batteries (preferably 6 hours ) to a maximum

of 50% of cost of system to urban local bodies/ SNAs/

Institutions not availing depreciation benefits and @ Rs. 100

per watt to a maximum of 33% of the cost of systems with

similar conditions to commercial establishments/ industry

Page 52: Master plan to make Chandigarh a Solar City

36 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

availing depreciation benefit will be available, whichever are

applicable. In specific cases, where battery storage is not

required, the support will be @ Rs. 115 per watt and Rs. 75 per

watt respectively:

Generation based incentives scheme of MNRE MNRE is actively promoting the establishment of grid

connected solar power plants of large capacity (megawatt scale)

by providing generation based incentives for the first time. The

purpose is to develop and demonstrate the technical

performance of grid-interactive solar power generation so as to

bring down the cost of the grid connected solar systems. The

silent features of the incentive schemes are as following;

a. MNRE may provide, via IREDA (Indian Renewable Energy

Development Agency), a generation based incentive of

maximum Rs 12 per kWh to the eligible projects, which are

successfully commissioned by 31st December 2009. This

will be done after taking into account the power purchase

rate (per kWh) provided by the SERC (State Electricity

Regulatory Commission) or a utility for that project.

b. Any project that is commissioned beyond the above date

would be eligible for a maximum with a 5% reduction and

ceiling of Rs 11.40 per kWh.

c. Further the incentive will continue to decrease, as and when

the utility signs a PPA (power purchase agreement) for

power purchase at a higher level. The proposal annual

escalations agreed with the utility, as in force, should be

reflected in the PPA.

d. The incentive approved for a project may be available for a

maximum period of 10 years from the date of approval and

regular power generation from the project. This will be

subject to the condition that the utility under consideration

continuous to purchase power from the grid-interactive

power plant.

JNNURM The Jawaharlal Nehru National Urban Renewal Mission

(JNNURM) is a project of the central government. Through this

project, the central government will fund cities for developing

urban infrastructure and services. The cities will have to carry

out mandated reforms in return. The aim is to encourage

reforms and fast track planned development of identified cities.

Focus is to be on efficiency in urban infrastructure and service

delivery mechanisms, community participation, and

accountability of ULBs / Parastatal agencies towards citizens.

The mission will last for a period of seven years starting

December 2005. The total central government funding will be

Rs. 50,000 crores. Adding the contribution of states and

municipalities, the amount will go up to to Rs. 1,25,000 crores

Page 53: Master plan to make Chandigarh a Solar City

37 National and international practices

T E R I Report No. 2008RT03

over the seven year period. The objectives of the JNNURM are

to ensure that the following are achieved in the urban sector;

(a) Focused attention to integrated development of

infrastructure services in cities covered under the Mission

(b) Establishment of linkages between asset-creation and asset-

management through a slew of reforms for long-term

project sustainability

(c) Ensuring adequate funds to meet the deficiencies in urban

infrastructural services

(d) Planned development of identified cities including peri-

urban areas, outgrowths and urban corridors leading to

dispersed urbanisation

(e) Scale-up delivery of civic amenities and provision of utilities

with emphasis on universal access to the urban poor

(f) Special focus on urban renewal programme for the old city

areas to reduce congestion

The JNNURM is designated to support;

(a) Water supply including setting up of desalination plants

(b) Sewerage and sanitation

(c) Solid waste management including hospital waste

management

(d) Construction and improvement of drains and storm-water

drainage system

(e) Road network

(f) Urban transport

(g) Construction and development of bus and truck terminals

(h) Renewal and re-development of inner city areas

(i) Development of heritage areas

(j) Preservation of water bodies

(k) Integrated development of slums

(l) Provision of basic services to the urban poor &

(m) Street lighting

Thus, it is clear that there exist many provisions that empower

both, the Chandigarh UT as well as CREST, to translate solar

city integrated plan in to action. This is further facilitated by the

existing policy directives for the promotion of energy

conservation and renewable energy.

Page 54: Master plan to make Chandigarh a Solar City

38 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 55: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 4 Energy baseline of Chandigarh

Energy baseline is essentially the amount of energy that would

be consumed annually without implementation of energy

conservation measures based on historical metered data,

engineering calculations, submetering of buildings or energy

consuming systems, building load simulation models, statistical

regression analysis, or some combination of these methods.

Baseline study is essential to study the energy conservation

measures in a city based on the profile of energy consumption

under Business as Usual scnario (BAU). This chapter focuses

on the present energy consumption in residential, commercial

and industrial sector with its overall energy consumption

scenario for Chandigarh.

Figure 4.1 Satellite image of Chandigarh city (Source: www.Googleearth.com)

About the city The Union Territory of Chandigarh (latitude 30.74oN, longitude

7.-6.79oE and altitude 321 meters) is located in the foothills of

the Shivalik hill ranges in the north, which form a part of the

fragile Himalayan ecosystem. It covers an area of approximately

Page 56: Master plan to make Chandigarh a Solar City

40 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

114 km². and shares its borders with the states of Haryana in

the south and Punjab in the north. The surrounding districts are

of Mohali, Patiala and Ropar in Punjab and Panchkula and

Ambala in Haryana. A satellite image of the city is presented in

following figure 4.1.

Chandigarh has a sub-tropical continental monsoon climate

characterized by a seasonal rhythm: hot summers, slightly cold

winters, unreliable rainfall and great variation in temperature (-

1 °C to 41.2 °C). The 20 year average rainfall for Chandigarh is

1100.7 mm20. The area experiences four seasons21;

Summer or hot season (mid-March to Mid-June)

Rainy season (late-June to mid-September)

Post monsoon autumn/transition season (mid September to

mid-November) and

Winter (mid November to mid-March).

In order to identify the energy conservation potential in

Chandigarh, it is important to understand the profile of energy

consumption under the Business As Usual (BAU) scenario. This

chapter focuses on the present energy consumption in

residential, commercial and industrial sector with its overall

energy consumption scenario.

Figure 4.2 Population growth in Chandigarh from 1961 to 2001 (Source: Census of India 2001)

The population of Chandigarh has been reported as 9,00,635 as

per census 2001. Figure 4.2 graphically presents the cumulative

population of Chandigarh up to 2001, which shows gradual

increase trend in the population over the last four decades. The

20 http://en.wikipedia.org/wiki/Chandigarh 21 http://chandigarh.nic.in/

Page 57: Master plan to make Chandigarh a Solar City

41 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Transportation, 1.12%

Public/Semi Public,

8.92%

Industrial, 5.04%

Special area, 9.65%

Agriculture & water

bodies, 9.96%

Resedential/Commerci

al, 64.82%

decreasing trends of population growth rate have been observed

as 114.6 percent in 1971, 75.55 percent in 1981, 42.16 percent in

1991 and 40.28 in 2001 in Chandigarh.

Chandigarh city covers an area of approximately 114 km2 (i.e.

28169.9 acres). In addition 25.42 km2 of hilly catchments area is declared as Wildlife Sanctuary. It has been observed

that the residential and commercial sectors cover the maximum

area of the city. This sector covers an area of 73.9 km2, followed

by agriculture & water bodies (11.36 km2), industrial (5.75 km2),

public/semi-public (10.71 km2) and transportation (1.28 km2)

and around 9.65% (11 km2) is categorized as special area. The

land use pattern of Chandigarh is presented in Figure 4.3.

Figure 4.3 Land use pattern of Chandigarh (Source: http://chandigarh.gov.in/knowchd_stat_ab07.asp)

Electricity consumption scenario The peak electricity demand of Chandigarh is around 284 MW

which is being met from different Central/State Generating

stations22. The UT Chandigarh has no generating capacity of its

own. At present, the City is receiving 67% of its power through

Mohali (PSEB), about 10% through Dhulkote (BBMB) and

remaining 23% through Nalagarh. The connected load of the

Chandigarh is reported as 901.78 MW; while the maximum

demand is approximately 284 MW. The connected load of public

lighting has been reported as 3.51 MW.

22 http://chandigarh.gov.in/engg_web/pages/about_us.html

Page 58: Master plan to make Chandigarh a Solar City

42 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 4.4 Per capita electricity consumption for Chandigarh and India (Source: www.indiastat.com and www.chandigarh.gov.in)

Chandigarh city ranks first in India in the Human Development

Index23, quality of life and e-readiness; hence per capita

electricity consumption of the city is much higher than that for

India. The per capita consumption of electricity in Chandigarh

has increased from 253 kWh in 1967-68 to 1224 kWh in 2007-

08. Accordingly the electricity consumption has increased from

0.138 MU per day to 5.5 MU on a particular day. Figure 4.4

presents the pattern of per capita electricity consumption in

Chandigarh from the year 2000 to 2006.

The major energy consuming categories are residential,

commercial/Institutional (offices and shops), municipal

services, industrial and transport. In the energy baseline study,

all the above sectors except transportation have been

considered. Within the selected sectors i.e. residential,

commercial and municipal services, the major energy sources

are electricity, LPG, and kerosene. The petroleum products are

mainly used in transportation sector followed by industries.

Figure 4.5 depicts sector wise consumption of electricity in

2006; when total consumption was reported as 1064 MU.

23 The Human Development Index (HDI) is an index used to rank countries by

level of "human development", which usually also implies to determine whether a

country is a developed, developing, or underdeveloped country.

Page 59: Master plan to make Chandigarh a Solar City

43 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Figure 4.5 Sector-wise annual electricity consumption (in MU) (Source: www.chandigarh.nic.in/statistics)

The Residential sector of Chandigarh is the major electricity

consumer and utilizes 36.68 percent of the total electricity

consumption of the city as pet the Engineering Department

(Electricity Wing), Chandigarh Administration. Further the

commercial and industrial sectors consume 29.29 percent and

25.6 percent of the electricity respectively and so on. Figure 4.6

presents the sectoral electricity consumption pattern of the city

in 2006-07.

Figure 4.6 Sectoral Electricity use pattern of Chandigarh (Source: www.chandigarh.nic.in/statistics and Data provided by Engineering Department (Electricity wing), Chandigarh Administration)

8.40%

Miss, 6.75%

Industrial (Low and

Medium Voltage),

12.57%

Commercial, 29.29%

Industries (High

Voltage), 13.03%

Agriculture, 0.14%

Public lighting, 1.51%

Domestic, 36.68%

0

50

100

150

200

250

300

350

400

Domestic Commercial Industrial Public Lighting Agriculture Others

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

Page 60: Master plan to make Chandigarh a Solar City

44 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

As shown in Figure 4.7 the annual electricity consumption of

the city is growing. The total electricity consumption has been

reported as 1064.34 MU during 2007-08. The daily average

power requirement was reported to be around 3.249 MU.

Figure 4.7 Annual electricity consumption in Chandigarh (in MU) (Source: www.chandigarh.nic.in/statistics and http://chandigarhenvis.gov.in/beta/asp/header.asp)

Consumption scenario of petroleum products The transport, industrial and domestic sectors are the major

consumers of petroleum products (viz. petrol, diesel, LPG, etc.).

LPG and kerosene are utilizable mainly in domestic and

commercial sectors; while others products are mainly consumed

by industries and vehicles. Table 4.1 presents the year wise

consumption of various petroleum products in the city.

It has been noticed that consumption of petrol and high

speed diesel is consistently increasing due to increasing the

vehicular population of the city; while that of light diesel oil

(LDO), Furnace oil, and low sulphur oil petroleum products are

getting reduced due to reduction/shift of industrial sector of the

city. The use of Kerosene is significantly reduced because of the

shift towards LPG and electricity.

Page 61: Master plan to make Chandigarh a Solar City

45 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Table 4.1 Consumption pattern of petroleum products in Chandigarh

Year

Petrol Incl.

ULP

(Kilo Liters)

High speed

Diesel

(Kilo Liters)

Kerosene

(Kilo Liters)

Light Diesel

Oil (Kilo

Liters)

Furnace Oil

(Metric Ton)

Low Sulphur

heavy Stock

(Metric Tons)

L.P.G

Connections

(Numbers)

1999-00 89332 93764 19547 5217 10235 18888 266281

2000-01 71390 76707 17628 2699 3359 2829 277186

2001-02 65737 72900 17162 1192 1047 4850 285404

2002-03 76570 65218 17570 3116 9219 9219 295731

2003-04 81190 71576 17026 1640 4470 5094 308508

2004-05 85104 76682 15740 728 12322 5702 290090

2005-06 101090 89810 15560 675 13108 4938 305000

2006-07 107445 100340 14060 515 5330 5571 324000

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

The details of energy consumption in various sectors of

Chandigarh city have been provided in the subsequent sections.

Residential Chandigarh is the first planned city of the country and has

highest per capita income (Rs 1, 10,676 in 200824) in India.

Hence it might be assumed that maximum of the households

are in medium and high income levels. According to Census

2001 there are 244134 houses in Chandigarh; out of which

26428 houses are located in rural area and 217706 houses are in

urban area of the city. It has been observed that more than 90

percent houses are permanent type, 7 percent are semi-

permanent and around 3 percent are temporary houses in the

city. Figure 4.8 presents the use pattern of census houses in the

city.

It has been noticed that residential sector comprises 83.9

percent houses of the city followed by 9.9 percent by

commercial category. Remaining 6.2 percent houses are used

for school & colleges, hospitals & dispensary, hotel, lodges,

guest houses and place of worship etc.

24 http://www.indianexpress.com/news/chandigarh-tops-again-in-per-capita-income/

Page 62: Master plan to make Chandigarh a Solar City

46 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 4.8 House use pattern of Chandigarh

(Source: Census of India 2001)

The distribution of total households of the city has been made on the

basis of number of members and numbers of dwelling room in the house.

The city has maximum one dwelling room houses (41.9 %) followed by

two rooms (24.8%), three rooms (18.6%) and up to six rooms and above

(3.3%). It has been observed that the average family size of the city is 4.4

persons per household and median 2 of the number of rooms.

Household statistics of the city has been presented for

distribution by size of house and size of family by in Figures 4.9 (a)

and 4.9 (b) respectively.

Figure 4.9 (a) Distribution of households by number of dwelling rooms

(Source: Census of India 2001)

Three rooms,

18.60%

Five rooms,

2.80%

Four rooms,

7.70%

Six rooms and

above, 3.30%

No exclusive

rooms, 1.00%

One room,

41.90%

Two rooms,

24.80%

Other, 0.60%

Residence , 83.90%

Residence-cum-other use,

1.90%

Other non-residental use,

2.40%

Shop, Office , 9.90%

Hospital, Dispensary, etc.,

0.20%

Place of worship, 0.20%

Hotel, Lodge, Guest House,

etc., 0.20%School, College, etc., 0.30%

Factory, Workshop,

Workshed, etc., 1.10%

Page 63: Master plan to make Chandigarh a Solar City

47 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Figure 4.9 (b) Distribution of households by family sizes

(Source: Census of India 2001)

The residential houses of the Chandigarh city are almost fully

electrified. As there are 201878 total number of households in

the city; out of which 96.8 percept were electrified in 2001 and

using electricity for lighting application. Figure 4.10 presents

the distribution of households by source of lighting.

Figure 4.10. Distribution of households by source of lighting (Source: Census of India 2001)

The electricity consumption in residential sector of Chandigarh

is rapidly increasing as shown in Figure 4.11. The total

electricity consumption in residential sector was reported as

435.35 MU in 2007; while it was 357 MU in 2004.

Electricity,

96.80%

Solar Energy,

0.10%

Kerosene, 2.80%

Others, 0.30%

Four members,

25.40%

Six to eight

members, 18%

Five members,

19.10%

Nine members

& above, 3.50%

One member,

8.90%

Two members,

11.10%

Three members,

14.10%

Page 64: Master plan to make Chandigarh a Solar City

48 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 4.11Total electricity consumption in the residential sector of Chandigarh (Source: Environnent Information System (ENVIS Centre) Chandigarh)

The load distribution pattern in residential sector of Chandigarh

has been assumed similar to a planned city; which shows energy

consumption pattern in domestic applications. The break up of

the electric consumption in the residential sector is presented in

Figure 4.12; which shows that cooling and lighting consumes

more than 70 percent of the electricity.

Figure 4.12. Electricity consumption pattern in residential sector (Source: Steps towards an Energy Efficient Building25)

25 Goel V., (2006), Steps Towards A Energy Efficient Building, in proceeding of Workshon on Developing energy efficiency and conservation program for Delhi, TERI New Delhi.

Other, 18%

Evaporative coolers,

4%

Television, 4%

Others, 10%

Room AC, 7%

Refrigerator, 13%

Lighting, 28%

Fan, 34%

Page 65: Master plan to make Chandigarh a Solar City

49 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

LPG and kerosene LPG is being used in most of the houses of the city for

domestic/cooking application in the city. The number of LPG

connections in the city is continuously; as the growth has been

estimated as 6.23 percent during 2006-07. Figure 4.13 gives

the cumulative number of LPG connections from 2004-05 to

2006-07.

Figure 4.13 Total number of LPG connections in Chandigarh

(Source: Environment Information System (ENVIS Centre) Chandigarh)

As the Chandigarh city is almost electrified26 and maximum

houses use LPG for cooking, the consumption of kerosene is

reducing slightly; as it is still being use in villages27 and rural

areas under Chandigarh UT. The total consumption of kerosene

was 14060 kilo liters in 2007. Figure 4.14 present the pattern of

kerosene use in the city from 2000 to 2007.

26 The distribution of households by source of lighting in Chandigarh has been reported as 96.8 percent as per census 2001. 27 At present there are 13 villages in Chandigarh city and nine villages are under the Municipal limits of Chandigarh since 2006. (http://mohfw.nic.in/NRHM/State%20Files/chandigarh.htm)

Page 66: Master plan to make Chandigarh a Solar City

50 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 4.14 Kerosene consumption in Chandigarh (Source: Environment Information System (ENVIS Centre) Chandigarh)

Commercial The commercial sector comprises around 10 percent of the

houses of Chandigarh. The total number of commercial

consumers in 2006 was 22810; while there were only19579

commercial consumers in 2000. Figure 4.15 presents the

growth of commercial consumers in Chandigarh from 2001 to

2007.

Figure 4.15 Growth of Commercial Consumers in Chandigarh

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

Page 67: Master plan to make Chandigarh a Solar City

51 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

As the commercial consumers are increasing along with the

annual electricity consumption in the commercial sector, the

per capita electricity consumption in commercial sector is

estimated based on the time from 2004 to 2007; which was

15428 kWh in 2007. The per capita electricity consumption in

commercial sector of Chandigarh has been presented in Figure

4.16 from the year 2004 to 2007.

Figure 4.16 Per Capita electricity consumption in commercial sector (Source: Environnent Information System (ENVIS Centre) Chandigarh)

As shown in Figure 4.17 the total annual electricity consumption

for the commercial sector has increased to 351.92 MU in 2007;

from 262 MU in 2004.

Page 68: Master plan to make Chandigarh a Solar City

52 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 4.17 Total electricity consumption in commercial sector (Source: Environnent Information System (ENVIS Centre) Chandigarh)

Municipal services

Street lighting A detailed energy audit study on street lighting of Chandigarh

City was carried out by TERI. In the study, it was found that the

following types of lights were used for street lighting in

Chandigarh

High Pressure Sodium Vapour lamps of 250W, 150W;

Metal Halides of 70W;

T12 lamps; and

High-pressure mercury vapour lamps of 150W.

Figure 4.18 Street lights in Chandigarh (V3 Road)

Page 69: Master plan to make Chandigarh a Solar City

53 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

The study estimated numbers of each type of light, approximate

annual hours of operation and the power consumption for each

type of lighting. The electricity consumption for street lighting

at 100% operating load is estimated to be 24.2MU. (The details

of street lighting systems of Chandigarh city are given in

Annexure- 1). However, according to Electricity Department

(Electricity Wing) of Chandigarh Administration, the annual

consumption of electricity for street lighting is 16.5 MU in 2007

at operating load of 68%. This difference may be due to the fact

that some of the streetlights not in working condition. For the

analysis, it has been assumed that the consumption is 16.5MU.

Considering the fact that the population growth for Chandigarh

city will not lead to city‟s expansion, the number of streets and

hence street lighting electricity consumption will increase in the

business as usual scenario and the load is taken to be constant

till the year 2018.

The detailed connected load, types of lamps and fixtures and

measurements/observations are also given in Annexure-1. The

following type of lamps and fixtures are being used in street

lighting in Chandigarh.

Type of fixtures:

GE Fixture

Crompton Greaves fixture

Type of lamps:

High Pressure Sodium Vapour lamps of 250W, 150W;

Metal Halides of 70W;

T12 lamps; and

High-pressure mercury vapour lamps of 150W.

As per Engineering Department (Electricity wind), Chandigarh

Administration, there are approximately 40,000 street lights in

Chandigarh, out of which 20000 are maintained by Municipal

corporation and 20000 by Chandigarh Administration.

Water pumping Chandigarh City is being supplied from two sources of water

i.e., Tubewell and Bhakra Canal. 64Millions gallons/day is being

supplied by Bhakra Canal and 20 million gallons /day by tube

well. There is one main pumping station in Chandigarh, Kazauli

water works (Figures 4.19 a and b). Total sanction load is 9102

KW for Kazauli. The raw water from Kazauli is treated at the

water softening plant in sector 39. The treated water gets

further distributed to sector 37, 32, 26, and 12. At these sectors

booster pumps are installed which helps in distribution of water

at suitable pressure to the individual sectors across Chandigarh.

The Kazauli water station is being divided in 4 phases. Phase 1

has 3 pumps of 950 hp of which 1 is standby. Phase 2 has 3

pumps of 950 hp of which 2 are running. Phase 3 has 3 pumps

Page 70: Master plan to make Chandigarh a Solar City

54 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

of 1050 hp of which 2 are running. Phase 4 has 3 pumps of 972

hp of which 2 are running. The running hours for pumps are 24

hrs. The details of water pumping electricity consumption are

given in Annexure-2. The total energy consumption for water

pumping in 2008 has been obtained as 75.15 MU.

The above reported values of water pumping are based only

on the pumps of higher capacity. It has been observed that there

are approximately 250 small capacity booster pumps across all

the sectors. The average capacity of 7.5 hp has been considered

for these pumps for the annual estimation of electricity

consumption in water pumping services in Chandigarh. It has

been estimated that the annual electricity consumption in water

pumping was 81.27 MU in 2008.

Industrial The gradual industrial growth has been observed over the past

40 years in the city. Chandigarh has seen a growth in all the

areas including industrial sector. There are 8 units in the large

and medium sector and about 2019 registered and functional

units in the Small Scale Sector. These units are offering

employment to about 16642 persons. These units are mainly

ancillary in nature. They are engaged in the manufacturing of

industrial fasteners, steel, and wooden furniture, machine tools,

pharmaceuticals, electrical/ electronic items, sanitary fittings,

sports goods, plastic goods, and knitting-needles etc. There are

about 20 major exporting units28.

Table 4.2 Industrial production of Chandigarh city

Industries

Year 2000-

2001

Year 2001-

2002

Year 2002-

2003

Year

2003-2004

Year 2004-

2005

Year 2005-

2006

Year 2006-

2007

Food Products 2642.70 2642.70 2704.92 5699.46 6749.26 6887.00 6955.87

Beverages Tobacco 0.00 19.15 19.15 0.00 0.00 0.00 0.00

Cotton Textile 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Woolen Silk

Synthetics Textiles 2298.00 2298.00 2318.74 0.00 0.00 68.87 68.87

Wooden Furniture 2470.35 2470.30 2470.35 8087.66 8453.27 8608.75 8677.62

Paper Printings Allied

Industries 3734.25 3734.25 3817.21 15657.05 15595.75 15840.10 15987.74

Leather Fur Products

Except Repair 248.95 287.25 287.28 482.09 619.83 688.70 688.70

Rubber Plastic

Petroleum Coal 4940.70 4959.85 5022.07 8746.49 9090.84 9297.45 9435.19

Chemicals Products

Except Petroleum 689.40 689.40 730.88 11156.60 11675.90 12052.25 12052.25

Non Metallic Products 766.00 766.00 766.00 0.00 0.00 0.00 0.00

Metal Alloy Industries 1340.50 1397.45 1604.85 13185.30 14418.35 14807.05 14807.05

Metal Products 18767.00 18767.00 18974.40 36236.92 37832.28 38567.20 39600.25

28 State of Environment, Chandigarh-2008, ENVIS Centre, Department of Environment, Chandigarh Administration, Chandigarh.

Page 71: Master plan to make Chandigarh a Solar City

55 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Industries

Year 2000-

2001

Year 2001-

2002

Year 2002-

2003

Year

2003-2004

Year 2004-

2005

Year 2005-

2006

Year 2006-

2007

Machinery Except

Electrical Machinery 1685.20 1685.20 1685.20 12313.60 12396.60 12396.60 12386.60

Electrical Machinery 3102.20 3121.45 3142.19 4427.38 4331.98 4476.55 4820.90

Transport

Equipments 5247.10 5285.40 5285.40 8532.88 9090.84 9090.84 9228.58

Other Industries 3944.90 3964.05 4047.01 2465.79 2584.82 2750.80 2961.41

Repair Personal

Services 5515.20 5515.20 5515.20 969.18 974.28 1101.92 1377.40

Total (Lac units) 57392.45 57602.7 58390.82 127960. 133814. 136638.0 139048.4

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

The industrial sector of Chandigarh city uses electricity as well

as petroleum products as fuel. Maximum petroleum products

are used by industrial and transportation sectors. As per the

Electricity Wing, Electricity Department of Chandigarh

Administration the electricity consumption was more then 25

percent in industrial sector. The electricity consumption in

industrial sector was reported as 272 MU during 2006. Figure

4.20 present the electricity consumption in industrial sector of

Chandigarh city from 2004 to 2006.

Figure 4.20 Electricity consumption in Industrial Sector of Chandigarh

Page 72: Master plan to make Chandigarh a Solar City

56 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

GHG emissions

Chandigarh is receiving 52% of its power through Mohali

(PSEB), about 8% through Dhulkote (BBMB) and remaining

40% through Nalagarh. Due to significant changes in the grid

structure, the Indian electricity system is now divided into two

main grids, namely new Integrated Northern, Eastern, Western,

and North-Eastern regional grids (NEWNE) and the Southern

Grid. In Chandigarh city, the power is drawn from the NEWNE

Grid. The average specific emission factor for NEWNE grid has

been reported as 0.81tCO2/MWh as per Central Electricity

Authority29.

The LPG consumption has been estimated for year 2007

based on the population growth rate and assumed that per

family 2 cylinders of 14 kg are required per month. It has been

estimated that the LPG consumption during 2007 in

Chandigarh was 93375.29 tonnes. Similarly kerosene

consumption of the city has been reported as 14060 kilo liters in

2007.

The GHG emission has been estimated based on total

electricity consumption, LPG consumption and kerosene

consumption of the city up to 2007. The emission factor (EF) as

0.81tCO2/MWh for electricity generation; while the emission

factors30 71.5 tCO2/TJ and 63.0 tCO2/TJ have been taken for

LPG and Kerosene respectively.

It has been estimated that the GHG emission through

electricity consumption was 937316 tCO2, 271190 tCO2 by LPG

and 35889 tCO2 through kerosene in 2007; which is mainly by

major energy consuming sectors namely residential,

commercial and industrial etc. The GHG emission in

Chandigarh city from 2004 to 2007 has been presented in

Figure 4.21.

29http://cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm 30http://cdm.unfccc.int/UserManagement/FileStorage/6HGTVUO4OT44ZX5O5BQBHK1AEEAOI1

Page 73: Master plan to make Chandigarh a Solar City

57 Energy baseline of Chandigarh

T E R I Report No. 2008RT03

Figure 4.21 GHG emissions based on electricity, LPG and Kerosene consumption of Chandigarh

0 200000 400000 600000 800000 1000000 1200000 1400000

2004

2005

2006

2007

Yea

r

GHG Emissions (tCO2)

GHG Emission (tCO2)_Kerosene GHG Emission (tCO2)_LPG

GHG Emission (tCO2)_Electricity GHG Emission_Total (tCO2)

Page 74: Master plan to make Chandigarh a Solar City

58 Integrated action plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 75: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 5 Energy planning

Energy planining is essentially a process of developing long-range

policies to help guide the future of a local, national, regional or

even the global energy system. It is the most important step

towards ensuring sustainable energy supply. A solar city should

encompass all the measures to use the natural resources available

and also to reduce the energy demand. This is possible only

through intelligent planning and diligent implementation.

This chapter looks into the energy conservation measures

necessary to reduce energy demand and assess the renewable

energy resources available through which energy could be

generated to reduce dependence on fossil fuels which will also

pave a path to meticulous planning.

The energy planning of Chandigarh city has been developed

based on three building block approaches as following;

Energy Demand Forecast up to 2018

Renewable Energy Resource Availability

Energy Efficiency: Options for energy savings and demand

reduction

It has been observed from the energy baseline study of Chandigarh

that the energy demand of the city is increasing rapidly due to (a)

increasing population (b) increasing GDP and (c) increasing

standard of living. The energy demand projections have been made

by taking in to account these factors.

Projected population The population of the city has been reported as 900635 as per

census 2001. An exponential trend in the population growth

has been obtained when projected based on the census data of

the years from 1961 to 2001. Figure 5.1 graphically presents the

projection of cumulative population and population growth rate

up to 2021.

The population projections have been carried out on the

basis of time series data from 1961 to 2001. The demographic

data indicates that between 1961 and 1971 the population

increased by 114.6 percent. According to the 1981 census it grew

by another 75.55 percent followed by 42.16 percent in 1991 and

40.33 percent in 2001 (with a total population of 900635).

It has been noticed that the population growth rate is

gradually decreasing since last four decades and is predicted to

be around25.71 percent up to 2021. On the basis of time series

data the population of the city up to 2021 is predicted as

1536726 and the present annual growth rate has been estimated

as 3.57 percent.

Page 76: Master plan to make Chandigarh a Solar City

60 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.1 Population trends in Chandigarh from 1961 to 2021

Chandigarh city has the highest per capita income as compared

with the country. A significant difference has been obtained

between the per capita income of Chandigarh and India. During

1999-2000 the per capita income of Chandigarh was Rs.

41385.00 while the same for India was Rs. 15881.00. The per

capita income of at current prices has reached to Rs. 1,10,676.0

in 2007, whereas for India the same is reached up to Rs.

32299.0. Hence the human development and quality of life in

the city is quite high as compared with the other cities.

Figure 5.2 presents the trends of increase in the per capita

income of Chandigarh (NSDP-Net State Domestic Product)

from 1999 to 2007. As Chandigarh has highest per capita

income in the country hence the per capita energy consumption

is comparably very high.

257251

451610

642015

119881

900635

1222398

1536726

100000

300000

500000

700000

900000

1100000

1300000

1500000

1961 1971 1981 1991 2001 2011 2021

Pop

ula

tion

0

20

40

60

80

100

120

140

160

180

200

Pop

ula

tion

Gro

wth

Rate

(%

)

Population Population Growth Rate (%)

Page 77: Master plan to make Chandigarh a Solar City

61 Energy planning

T E R I Report No. 2008RT03

41386

46660

52385

58772

66512

75181

86629

99262

110676

0

20000

40000

60000

80000

100000

120000

1999 2000 2001 2002 2003 2004 2005 2006 2007

Year

An

nu

al

Per C

ap

ita

In

co

me (

Rs)

Figure 5.2 Per capita income of Chandigarh

(Source: www.indiastat.com)

Energy demand forecast up to 2018 The energy demand forecast of Chandigarh has been carried out

using time series data of last 4 to 7 recent years. Statistically the

projections are assumed as of best reliability if the correlation

coefficient (R2) comes more than 0.95. In the present

projections the correlation coefficient has obtained always more

than 0.95 up to 1.0; which shows better confidence level of the

projections. All projections have been made up to 2018. A brief

detail of statistical methodology adopted for projections has

been described in Annexure-3.

Per capita electricity consumption In has been observed that the per capita consumption of

electricity in Chandigarh has increased from 253 kWh in 1967-

68 to 1224 kWh in 2007-08. On the basis of time series based

data of last seven years it is estimated that the per capita

electricity consumption will be increased up to 1607 kWh in

2014 (short term); and up to 2018 (long term) it will be 1916

kWh. Hence the per capita electricity will be increased up to 60

percent of its present value up to 2018. The projection trend of

per capita electricity consumption with years is presented in

Figure 5.3.

Page 78: Master plan to make Chandigarh a Solar City

62 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.3 Per capita electricity consumption in Chandigarh (Source: www.indiastat.com and www.chandigarh.gov.in)

Total electricity consumption On the basis of time series data of last current four years the

total electricity demand has been projected over the period till

2018. The total electricity consumption has been reported as

1064.34 MU during 2007-08. It has been estimated that the

total electricity consumption of the city will increase up to 2195

MU in 2014; while up to 2018 it will come to 3089 MU. Figure

5.4 presents the projection of the annual electricity

consumption up to 2018.

0

250

500

750

1000

1250

1500

1750

2000

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Per C

ap

ita

Ele

ctr

icit

y C

on

sum

pti

on

(k

Wh

)

Page 79: Master plan to make Chandigarh a Solar City

63 Energy planning

T E R I Report No. 2008RT03

Figure 5.4 Annual electricity consumption (in MU) (Source: www.indiastat.com and www.chandigarh.gov.in, Chandigarh Administration and Environment

Information System (ENVIS Centre) Chandigarh)

Electricity consumption in residential sector The time series forecasting has been made on basis of the data

of electricity consumption in residential sector from 2004 to

2007. It is estimated that the total electricity consumption in

residential sector will increase up to 1246 MU in 2014 and 2103

MU in 2018; while it was reported as 435MU in 2007. Figure

5.5 presents the projection of electricity demand in residential

sector up to 2018.

0

400

800

1200

1600

2000

2400

2800

3200

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

To

tal

An

nu

al

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

Page 80: Master plan to make Chandigarh a Solar City

64 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.5 Total electricity consumption in the residential sector up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

LPG The number of LPG connections in the city is continuously

increasing and the growth has been 6.23 percent during 2006-

07. In order to estimate the consumption of LPG in residential

sector the number of total population in 2008 has been

calculated based on present annual population growth rate (i.e.

3.57 %). It has been estimated that the population of the city

will increase to 1151295 in 2008; while it was 900635 in 2001.

The family size of the city has been taken as 4 persons per

household as per census 2001.

Assuming 2 LPG cylinders consumption per month for each

household of 14 kg each, the total annual LPG consumption in

residential sector of the city has been estimated to be 96708.79

tonnes.

Taking the annual population growth rate of 3.57 percent;

further the annual LPG consumption has been projected up to

2018; which increase to 11,1276.09 tonnes in 2012, 123624.28

tonnes in 2015, and 137342.74 tonnes in 2018 as shown in

Figure 5.6.

0

300

600

900

1200

1500

1800

2100

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Ele

ctr

icit

y C

on

sum

pti

on

in

Resi

den

tia

l S

ecto

r

(MU

)

Page 81: Master plan to make Chandigarh a Solar City

65 Energy planning

T E R I Report No. 2008RT03

Figure 5.6 LPG consumption projections (BAU scenario)

Kerosene A linear decreasing trend of the kerosene consumption pattern

in Chandigarh city has been observed from last seven year data.

Taking it forward it is estimated that the annual kerosene

consumption will reach 10092 kiloliters up to 2014 and 7541

kilo liters by 2018 (Figure 5.7).

Figure 5.7 Kerosene consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

To

tal

Kero

sen

e C

on

sum

pti

on

(K

ilo

Lit

ers)

0

20000

40000

60000

80000

100000

120000

140000

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

To

tal

An

nu

al

LP

G C

on

sum

pti

on

(to

nn

es)

Page 82: Master plan to make Chandigarh a Solar City

66 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Petroleum products The petroleum products namely petrol, high speed diesel oil,

light diesel oil, furnace oil and low sulphur heavy stock are in

use in Chandigarh. Petrol and diesel are mainly using by

transportation sector while light diesel oil, furnace oil and low

sulphur heavy stock are mainly used by industries.

The petrol consumption in Chandigarh city has been

reported as 65737 kilo liters in 2007. On the basis of time series

data it has been obtained that the petrol consumption in the city

will be increase by 169454 kilo liters by 2012, 216220 kilo liters

by 2015 and 270403 by 2018. Figure 5.8 presents the pattern of

petrol consumption in Chandigarh city.

Figure 5.8 Petrol consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

Consumption of diesel oil is also increasing effectively in the

city, which is mainly used by vehicles in transportation sector.

Chandigarh city has been reported as 65737 kilo liters in 2007.

Diesel consumption in the city has been reported as 100340 kilo

liters during 2007. On the basis of time series data it has been

obtained that the diesel consumption in the city will be increase

by 197603 kilo liters by 2012, 283765 kilo liters by 2015 and

390970 by 2018. Figure 5.9 presents the pattern of petrol

consumption in Chandigarh city.

0

50000

100000

150000

200000

250000

300000

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Petr

ol

Co

nsu

mp

tio

n (

Kil

o L

iters)

Page 83: Master plan to make Chandigarh a Solar City

67 Energy planning

T E R I Report No. 2008RT03

Figure 5.9 High Speed Diesel consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

Light diesel oil (LDO), furnace oil and low sulphur heavy stock

petroleum products are mainly being use by industries. As the

industries are being shifting outskirts of the city hence the

annual consumption pattern of these products is not essentially

following any specific trend. Hence it is not possible to project

the demand of these petroleum products with a high confidence

level. The linear projections based on the time series data shows

that the use of these petroleum fuels will be negligible up to

2012. The projections have their limitations due to random

pattern of the consumption data. Figure5.10 to 5.12 presents the

projection of the consumption of light diesel oil, furnace oil and

low sulphur heavy stock by 2018 respectively.

0

50000

100000

150000

200000

250000

300000

350000

400000

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Hig

h S

peed

Dis

sel

(Kil

o L

iters)

Page 84: Master plan to make Chandigarh a Solar City

68 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.10 Light Diesel Oil (LDO) consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

Figure 5.11 Furnace Oil consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

0

100

200

300

400

500

600

700

800

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Lig

ht

Die

sel

Oil

(K

ilo

Lit

ers)

0

2000

4000

6000

8000

10000

12000

14000

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Fu

rn

ace O

il (

MT

)

Page 85: Master plan to make Chandigarh a Solar City

69 Energy planning

T E R I Report No. 2008RT03

Figure 5.12 Low sulphur heavy stock consumption and projection up to 2018

(Source: Environnent Information System (ENVIS Centre) Chandigarh)

Commercial consumers The total number of commercial consumers in 2006 was 22810.

On the basis of time series data based projection the number of

commercial consumer is expected to increase to 28823 by 2014

and 33525 by 2018 as shown in Figure 5.13.

Figure 5.13 Projected growth commercial customers up to 2018

(Source: Census of India 2001, Environment Information System (ENVIS Centre) Chandigarh)

0

5000

10000

15000

20000

25000

30000

35000

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Nu

mn

er

of

Co

mm

erc

ial

Co

nsu

mers

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Lo

w S

ulp

hu

r H

ea

vy

Sto

ck

(M

T)

Page 86: Master plan to make Chandigarh a Solar City

70 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Per capita electricity consumption in commercial sector In order to estimate electricity consumption in commercial

sector, per capita electricity consumption has been worked out

from last four years. Per capita electricity consumption in this

sector was 15428 kWh in 2007. As shown in Figure 5.14 per

capita electricity consumption in commercial sector works out

to be 39,685 kWh in 2014 and 64,276 kWh in 2018.

Electricity consumption in commercial sector The total electricity demand has been forecasted based on two

approaches as following;

(a) time series data and

(b) per capita electricity consumption and number of

commercial consumers

Figure 5.14 Per Capita annual electricity consumption in commercial sector

0

10000

20000

30000

40000

50000

60000

70000

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

Per

Cap

ita E

lectr

icit

y C

on

su

mp

tio

n (

MU

)

Page 87: Master plan to make Chandigarh a Solar City

71 Energy planning

T E R I Report No. 2008RT03

Figure 5.15 Total Annual Electricity consumption in commercial sector (MU)

The projection of total electricity consumption in commercial

sector has been carried out by averaging the projections from

these two approaches. As shown in Figure 5.15, it has been

estimated that the total electricity consumption will reach 1096

MU in 2014 and 1946 MU in 2018.

Electricity consumption in industrial sector The industrial sector of the city is third major electricity

consumer. The electricity consumption in industrial sector has

been reported as 272 MU in 2006. The time series based

projections shows that the electricity demand in industrial

sector will increase to 903 MU in 2014, and 1528 MU in 2018

as shown in Figure 5.16.

Hence the residential sector has been found the major

energy consumer sector in the city followed by commercial and

industrial sectors. Figure 5.17 presents the comparative pattern

of annual electricity consumption in various sectors with the

total electricity consumption up to 2018.

0

200

400

600

800

1000

1200

1400

1600

1800

2000

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

Page 88: Master plan to make Chandigarh a Solar City

72 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.16 Electricity consumption in Industrial sector (Source: Environment Information System (ENVIS Centre) Chandigarh)

Figure 5.17 Annual Electricity consumption in various sectors of Chandigarh (Source: Environment Information System (ENVIS Centre) Chandigarh)

0

200

400

600

800

1000

1200

1400

1600

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Ele

ctri

city

Co

nsu

mp

tio

n (

MU

)

0

500

1000

1500

2000

2500

3000

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

An

nu

al

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

Total Electricity Consumption (Mkwh) Resedential Sector (MkWh)

Commercial Sector (MkWh) Industrial Sector (MkWh)

Page 89: Master plan to make Chandigarh a Solar City

73 Energy planning

T E R I Report No. 2008RT03

GHG Emission As the power is drawn from the NEWNE Grid in Chandigarh

city hence average specific emission factor for NEWNE grid (i.e.

0.81tCO2/MWh) has been considered for estimation of GHG

emission projection. Similarly the emission factors for LPG and

kerosene have been considered as 71.5 tCO2/TJ and 63.0

tCO2/TJ respectively.

The city was emitting 937316 tCO2 through electricity,

271190 tCO2 through LPG and 35889 tCO2 through kerosene in

2007. On the basis of time series projection of total electricity

requirement of the city and its multiplication with the average

emission factor of NEWNE grid it has been projected that the

GHG emission will be increased as 1482192 tCO2 by 2012;

1982163 tCO2 by 2015 and 2501971 tCO2 in 2018. The GHG

emission through LPG will be increased by 322179 tCO2 by

2012; 359042 tCO2 by 2015 and 398885 tCO2 by 2018.

Similarly the GHG emission will be decreased to 29015 tCO2 in

2012, 24132 tCO2 in 2015 and 19250 tCO2 by 2018.

Hence it has been estimated that the total (electricity, LPG

and kerosene) GHG emission in Chandigarh will increase to

1834386 tCO2 in 2012, 2325337 tCO2 in 2015 and 2920105 tCO2

in 2018. Figure 5.18 presents the projection of GHG emission

up to 2018 in Chandigarh city.

Figure 5.18 GHG emissions from energy supplied to Chandigarh city

0

500000

1000000

1500000

2000000

2500000

3000000

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

GH

G E

mis

sio

ns

(tC

O2)

GHG Emission_Kerosene (tCO2) GHG Emission_LPG (tCO2)GHG Emission_Electricity (tCO2) GHG Emission_Total (tCO2)

Page 90: Master plan to make Chandigarh a Solar City

74 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Renewable energy resource availability

Biomass potential Chandigarh covers an area of approximately 114 km2 (i.e.

28169.9 acres). In addition 25.42 km2 of hilly catchments

area is declared as Wildlife Sanctuary.

Table 5.1 Forests of Chandigarh City

S. No. Name of the forests Area in hectares

1. Sukhna Wildlife Sanctuary 2610.97

2. Lake Reserve Forests 130.19

3. Sukhna Choe Reserve Forests 375.91

4. Patiali-ki-Rao forests 142.42

5. Forest area at Brick kiln Manimajra 5.00

Total 3264.49

The National Forest Survey has rated Chandigarh as the

greenest city in India with the highest green cover of 35.7 per

cent; while New Delhi comes second with a forest cover of 19.78

per cent. Total forest area in U.T. Chandigarh is 3064.49 ha as

mentioned in Table 5.1. Out of the total green cover 3264 ha is

actual forest and 3063 ha of forest area is under reserved

category. In the forests of the city approximately 94 % is the

reserve forest, while rest 6% (approximately 201 ha) is non-

reserve forest, from where only the biomass can be collected.

In addition, Chandigarh city is also known as city of gardens.

Out of a total area of 20000 acres acquired for the first phase of

the city, about 2000 acres are meant for development of

gardens and parks. The total tree cover area of the city has been

reported as 8 km2. The total number of fallen trees during

2006-07 has been reported as 77910031.

As the major portion of forests are reserve and presently the

garden waste and the fallen leaves through trees are being

dumped at the landfill area in Sector-38 with municipal solid

waste, therefore there is negligible scope for biomass based

power generation in Chandigarh.

Municipal solid waste potential Municipal solid waste includes predominantly household or

domestic waste with sometime the addition of commercial

wastes; which are in either solid or semisolid form. The

collected municipal waste is still to be separated out or

reprocessed. Essentially the MSW is divided in to following

categories;

Biodegradable waste: food and kitchen waste, green waste

and paper

Recyclable material: paper, glass, bottles, cans, and certain

plastics

31 (Source: Environment Information System (ENVIS Centre) Chandigarh)

Page 91: Master plan to make Chandigarh a Solar City

75 Energy planning

T E R I Report No. 2008RT03

Inert waste: construction and demolition waste, dirt, rocks

and debris

Composite waste: waste clothing, tetra packs and plastic and

Domestic hazardous water and toxic waste: medicines,

paints, chemicals etc.

Chandigarh city with an approximate population of approx 9

lakh generates 380 tonnes of municipal solid waste per day. The

city houses 244,134 families, which are source of approximately

80% of municipal waste; while the collection efficiency of the

city is 97 percent32. The vegetable and fruit markets contribute

to an extent of 20% of the total municipal waste. The

quantification of the waste is not available for smaller markets

and restaurants and hotels.

Waste generated from the city is collected through a

combination of tractor trolleys for leaves and wastes and

containers for inert construction wastes. For the disposal of the

solid waste in a scientific manner a landfill site of 46 acres area

exists at village Dadu Majra, Sector-38. The city waste collected

from all sectors is being transported to the dumping ground for

„land filling‟. Recently Central Pollution Control Board (CPCB)

has sectioned a demonstration project for management of MSW

in the city. Under this project the existing landfill site is

proposed to be scientifically designed to convert it into sanitary

landfill site. The project will include house to house garbage

collection work for which cycles casts are being provided to

resident welfare associations which are perused to dispose off

garbage at designated „Sahaj Safai Kendras‟. In collaboration

with Chandigarh municipality, Jaypee Industries has set up

pallet manufacturing unit of the installed capacity to process

500 ton per day of municipal solid waste, which is converted

into refuse-derived fuel to be used in a thermal power plant. As

such there is no other MSW available now in the city.

On the basis of time series data of daily production of MSW

in Chandigarh it has been estimated that the city will generate

473 tonnes per day MSW in 2014 and 535 tonnes per day by

2018 (Figure 5.19).

32 Report of „State of Environment, Chandigarh-2008, ENVIS Centre,

Department of Environment, Chandigarh Administration.

Page 92: Master plan to make Chandigarh a Solar City

76 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.19 MSW (tonnes/day) generation in Chandigarh (Source: State of Environment report, Chandigarh-2008)

Hence there is no additional availability of MSW in Chandigarh

for power generation. The capacity of existing MSW plant of

Jaypee Industries may be increased 10-15 percent in long term

when additional MSW will be available with increasing

population of the city.

Solar energy Chandigarh is located in the sunny belt of the country and

receives a good amount of solar radiation over the year. It has

been observed that the annual global solar radiation over the

city is 1944 kWh/m2, while the annual diffuse radiation is 846

kWh/m2. The global solar radiation over the inclined surface (at

latitude) is estimated as 2155 kWh/m2 annually. Figure 5.20

presents the daily values of solar radiation on horizontal and

inclined surface in Chandigarh for of each month. The month-

wise values of solar radiation received by a surface on horizontal

and inclined surface are summarized in Table 5.2.

200

250

300

350

400

450

500

550

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Year

MS

W G

en

era

tio

n (

ton

nes/

Da

y)

Page 93: Master plan to make Chandigarh a Solar City

77 Energy planning

T E R I Report No. 2008RT03

Figure 5.20 Solar Radiation pattern of Chandigarh (Source: Handbook of Solar Radiation written by A Mani, Allied Publisher, 1980,)

Table 5.2 Daily and monthly pattern of solar radiation over Chandigarh

Month

Daily Monthly

Global

Solar

Radiation

(kWh/m2)

Diffuse Solar

Radiation

(kWh/m2)

Global Solar

Radiation on

Latitude

(kWh/m2)

Global Solar

Radiation

(kWh/m2)

Diffuse Solar

Radiation

(kWh/m2)

Global Solar

Radiation on

Latitude (kWh/m2)

Jan 3.78 1.45 5.45 117.1 45.0 169.0

Feb 4.61 1.83 5.84 129.1 51.3 163.6

Mar 5.60 2.25 6.33 173.7 69.8 196.1

Apr 6.53 2.62 6.55 195.8 78.7 196.4

May 7.04 2.88 6.46 218.3 89.4 200.3

Jun 6.24 3.29 5.55 187.1 98.8 166.6

Jul 5.91 3.28 5.36 183.3 101.6 166.0

Aug 5.29 3.10 5.10 164.1 95.9 158.2

Sep 5.81 2.48 6.24 174.3 74.5 187.1

Oct 5.29 1.81 6.61 164.1 56.2 205.0

Nov 4.34 1.39 6.21 130.3 41.7 186.2

Dec 3.46 1.40 5.16 107.4 43.5 159.9

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Da

ily

So

lar R

ad

iati

on

(k

Wh

/m2)

Global Solar Radiation (kWh/m2) Global Solar Radiation on Latitude (kWh/m2)

Page 94: Master plan to make Chandigarh a Solar City

78 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Energy efficiency: Options for energy savings and demand reduction

Options for energy savings and demand reduction

Residential sector The residential sector of Chandigarh is the major consumer of electricity. The current electricity consumption of the residential sector is 497 MU which constitutes 39% of the total electricity consumption. The share of the residential sector in the total connected load and consumption is growing. Reduction in the demand would help in conservation of energy.

Energy saving measures: The major energy saving measures

in residential sector is as follows:

Replacing the conventional T-12 (40 Watt) copper ballast

tube lights with the energy efficient T-5 (28 Watt) electronic

ballast tube lights. The saving would be about 42% per tube

light.

Replacing the conventional Ceiling Fans which consumes

(70-80 watt) with energy efficient Fans (which consumes 50

Watt). The savings occur will be 37% per fans.

Replacing the existing unitary air conditioners with the

BEE star labelled Air conditioners.

The overall electricity saving which can be achieved by implementing all above measures would be approximately 20% of the total consumption in residential sector of the city.

If the energy efficient devices, as mentioned above are used

in residential sector, the total consumption would reduce up to

397.6MU from 497 MU in 2008. However, the 100%

replacement would be difficult and not take place in short term.

With active promotion and facilitation the process can be

accelerated.

It has been assumed that by 2009, there would be 5%

replacement only and therefore the consumption would be

572MU compared with 577 MU consumption in BAU scenario

in 2009. Replacement of 30 % devices has been assumed by

2012(short term) resulting in reduced consumption of 894.13

MU under Solar City scenario as against 924 MU in BAU

scenario and it has been observed that the electricity

consumption in residential sector of the city will increase up to

924 MU as BAU scenario and will be 894.13 MU under Solar

City scenario.

Similarly 60% replacement has been assumed by 2015

(medium term) and 90% by 2018 (long term). The electrical

energy demand after incorporating the energy saving options in

residential sector in Solar City scenario (SC) is shown in Figure

5.21. It has been obtained that the energy savings will be 89 MU

in 2018; while in BAU scenario it is estimated as 2103 MU and

2014 MU under SC scenario (i.e. 4.23 % of total electricity

consumption in BAU scenario by 2018).

Page 95: Master plan to make Chandigarh a Solar City

79 Energy planning

T E R I Report No. 2008RT03

Box: CFL programme of BSES, Delhi

BSES Yamuna, one of the distribution companies in Delhi launched on October 25, 2006 “Buy One, Get One Free CFL” scheme. As per BSES, this scheme launched in association with Indo Asian Fusegear Limited (a CFL manufacturer) has exceeded all expectations. In about five months‟ time over 3.5 lakh CFLs have been sold. Savings accruing from these CFLs is estimated to result in a reduction in maximum demand by nearly 23 MW at a given point of time – enough to power eight average shopping malls in Delhi and saving of over 33 million units of electricity annually.

An interesting trend observed was that the 15 Watt CFL is the most popular among the customers (over 1.47 lakh CFLs bought) followed by the 20 W CFL (over 1 lakh CFLs sold).

Figure 5.21 Business as usual (BAU) and solar city (SC) scenario of residential sector

Commercial sector Engineering Department (Electricity Wing), Chandigarh

Administration indicates that the commercial sector consumes

410 MU, which is about 30% of the total electricity consumption

of Chandigarh city.

The energy efficiency in commercial sector plays a very

important role in managing city‟s electrical energy demand.

Energy systems in commercial sector mainly include lighting

and space cooling system (fans, air conditioners etc.). Many

studies indicate that not much attention has been paid towards

energy efficiency in the design of these energy systems. Such

energy systems therefore, waste energy in commercial buildings

due to poor efficiency, poor operating practices. Lack of

appropriate controls adds to the energy wastage. Hence there

exists a significant potential to improve energy efficiency in

existing commercial buildings and subsequent reduction of

commercial sector electrical energy demand at city level.

Energy saving measures: According to ECBC 2007 the major

energy saving measures in residential sector is as follows:

Optimising the building envelope as per ECBC standard.

Replacing the conventional T-12 (40 Watt) copper ballast

tube lights with the energy efficient T-5 (28 Watt) electronic

ballast tube lights. It will give a saving of 42% per tube light.

0

300

600

900

1200

1500

1800

2100

2009 2012 2015 2018

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

BAU SC

Page 96: Master plan to make Chandigarh a Solar City

80 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Replacing or optimising the existing HVAC system as per

ECBC standard and BEE star rated.

Replacing the existing the unitary air conditioners with the

BEE label Air conditioners.

The overall saving which can be achieved by implementing all

those measures would be 20% of the total consumption. If the

energy efficient devices, as mentioned above are used in

commercial sector, the total consumption would reduce up to

328 MU from 410 MU in 2008. Full 100% replacement of these

devices would be practically difficult due to resource

constraints. However, these could be attempted through an

Energy Services Company (ESCO) mode where, the ESCO

would make the investment for energy conservation measures

and recover the investment through energy savings. The ESCO

route could be tried in the office complex initially for ease of

implementation. Further, in addition to ESCO mode, the use of

energy efficient devices should be promoted through public

private partnership. Such an example is in Delhi implemented

by the Delhi Transco with manufacturer of CFLs. The details of

the „Buy One get One‟ programme for promotion of CFLs, being

implemented in Delhi, as well as BEE‟s „Bachat Lamp Yojana‟

are given in Annexure-4.

It has been assumed that the commercial sector of

Chandigarh will replace above suggested devices in following

manner; 10 percent by 2009, 40 percent by 2012 (short term),

70 percent by 2015 and 100 % by 2018. Thus the electricity

consumption will be reduced to 475 MU in SC scenario from 483

MU in BAU scenario in 2009. In 2012 (short term) the energy

consumption will be reduced to 763 MU from 796 MU. The

electricity consumption will be reduced to be 1216 MU from

1273 MU in 2015 (medium term) and 1864 MU from 1946 MU

in 2018 (long term). The projected savings of electricity

consumption due to these options would be about 4% over the

implementation period (i.e. 2018). Figure 5.22 presents the

energy consumption in BAU scenario and solar city scenario as

following.

Page 97: Master plan to make Chandigarh a Solar City

81 Energy planning

T E R I Report No. 2008RT03

Figure 5.22 BAU and Solar city scenarios for commercial sector

In addition to above measures there is a possibility of energy

saving in air conditioning units. These are mainly „behavioural‟

practices than technical interventions. Such good practices for

improving energy efficiency of air conditioners are given in

Annexure-5.

Street lighting A comprehensive survey of existing street lighting systems has

been conducted and meetings with officials responsible for

designing, installation and operation and maintenance were

held. During the visit and discussion with the officials it has

been found out that the roads at the Chandigarh are divided on

the basis of the width of the roads.

The classification of the roads is given below in the

decreasing order of the width.

V3

V4

V5

V6

The design of the street lighting is based on the central verge.

V3, V4, V5 is being controlled by MCC and V6 is being

controlled by Chandigarh administration. The specifications and

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2009 2012 2015 2018

Ele

ctr

icit

y C

on

sum

pti

on

(M

U)

BAU SC

Page 98: Master plan to make Chandigarh a Solar City

82 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Box. ‘Bachat Lamp Yojana’ of BEE Bachat Lamp Yojana, which is a CDM based CFL scheme is an innovative initiative put in place by the Central Government to enhance lighting efficiency in the Indian household sector by making Compact Fluorescent Lamps available at prices comparable to that of Incandescent Lamps. The scheme seeks to leverage the high cost of the CFLs through the CERs generated out of the project. This is a public-private partnership between the Government of India, Private sector CFL Manufactures /Traders (Project Developers) and State level Electricity Distribution Companies to provide the framework to distribute high quality CFLs at about Rs.15 per piece to the households of the country. Under the scheme only 60 Watt and 100 Watt incandescent Lamps have to be replaced with 11to15 Watt and 20 -25 Watt CFLs respectively. The Government would develop a programmatic approach (PoA) within which, individual CFL supplier would develop CDM projects. The Bureau of Energy Efficiency (BEE), being the statutory body set up under the Energy Conservation Act, 2001 by the Government of India, will coordinate the Small-Scale Programme of Activities (SSC-PoA) and will facilitate implementation of the programme in various States through their respective Electricity Distribution Companies (DISCOMs) with the assistance of the CFL suppliers. The development of the SSC-PoA is a voluntary action on the part of BEE and it would not seek any commercial revenues from the SSC-PoA. On the other hand, it will on behalf of the Government of India take the responsibility of monitoring of all project areas after the DISCOMs and the CFL suppliers have entered into a tripartite agreement (TPA) with BEE.

types of lamps being use in various roads the city are as

following;

Lamps used in V3 are 250 and 150 W SVL.

Lamps used in V4 are 150 W SVL

Lamps used in V6 are Tube lights which will get replaced by

70 W SVL.

Based on the energy audit of street lighting and the data

collected from the Municipal Corporation of Chandigarh it has

been observed that the street lighting system currently used in

Chandigarh uses the fixtures with conventional ballasts. There

is a good potential of reducing the consumption by installing

Multi tab ballast with astronomical timer switch. The brief

details of astronomical timer switch technique are presented in

Annexure-6.

Replacing existing ballast with energy saving multi-tab ballast

with astronomical switch

During the audit it has been observed that the operating load

remains same throughout the night. Keeping this in mind it is

suggested to install the multi tab ballast which varies the load of

the lamp according to the traffic load during the night. Multi tab

ballast comes with a facility of setting the time for which the

lamp will run up to its full capacity. So, during the evening

operating hours the timer is set for the full loading of lamp and

during midnight onwards it will be set for 50% loading of the

lamp. Astronomical timer switch will help in reducing the

wastage of lighting consumption as due to seasonal variation

the operating hours of street lighting does change. So, the

switch doesn‟t allow street light to get on before the dusk and

after the dawn.

As the city has already adopted energy efficient lamps hence

the potential of energy savings are limited (approximately 25%)

in the city.

Projected load for street lighting

The influx of population in the city requires augmentation of

streetlights. Presently there are approximately 40,000 street

lights in Chandigarh. The number of street lights and hence the

load may be increase with increasing population and expansion

of the city. Taking in to account the present population growth

rate it has been estimated that there will be 46025 street lights

in 2012, 51133 in 2015 and 56807 in 2018 respectively.

Simultaneously the connected load of street lighting will

increase to 4.21 MW in 2012, 4.68 MW in 2015 and 5.20 MW in

2018.

Assuming the present use pattern of street lighting in the

city the consumption pattern has been estimated as 18.99 MU to

2012, 21.09 in 2015 and 23.43 MU in 2018; while it was 16.5 MU

in BAU scenario.

Page 99: Master plan to make Chandigarh a Solar City

83 Energy planning

T E R I Report No. 2008RT03

Box: CFL program of Himachal Pradesh Government Himachal Pradesh Government, launched the Energy saving CFL “ Atal Bijli Scheme “on November 23, 2008. It has been estimated that CFL lighting would reduce energy consumption by as much as 70 to 150 MW in peak hours. Atal Bijli Bachat Yojana will annually contribute to saving 270 million units of energy that could be made available for other categories. There are about 16.3 lakh domestic electricity consumers registered in the state and the government has marked a budget of Rs 80 crore for the scheme. Domestic consumers energy bills are expected to reduce by as much as 30 percent after switching over to CFL lighting. The government also proposes to use the scheme earning carbon credits when traded over the power exchange. The scheme qualifies for earning through Certified Emission Reductions (CER) under Clean Development Mechanism (CDM).On acquiring approval of CDM executive board of United Nations Framework Convention on Climate Change (UNFCCC), state electricity board is entitled for about 1,88,496 CERs, which can fetch an additional revenue of Rs 20 crore.

Load reduction potential

At present the total estimated peak load of exiting street lighting

system is approximately 3660.0 kW. After implementing of

above option there is possibility to reduce connected load by 915

kW. Hence there exists a potential to reduce street lighting

system‟s load by 25 percent approximately in Chandigarh.

Hence using above energy efficiency measure in street lighting

the electricity consumption can be reduced to 12.375 MU from

16.5 MU in BAU scenario.

Further it has been assumed that 100 percent

implementation of suggested energy efficient measure will be

carried out by 2012 and further similar approach has been

adopted for medium term and long term projections. Hence

solar city scenario will remain constant along with increased

demand of electricity for street lighting in the city.

Municipal water pumping

A detailed energy audit of pumps supplying water to

Chandigarh city was undertaken by TERI in order to assess the

electricity consumption in pumping for the city. The

Chandigarh City is being supplied from two sources of water

i.e., Bhakra Canal and Tube well. The water from the Bhakre

canal is being supplied from Kazauli water pumping station. It

has been observed that the total annual operating energy

consumption of pumping stations is approximately 79.2 MU.

The electrical energy demand reduction and conservation

option is discussed below.

Replacing existing inefficient booster pumps with energy

efficient pumps

During the energy audit it has been observed that the booster

pumps installed are running at 55% efficiency. The current

operating electrical demand of booster pumps is 1865 kW. The

operating electrical demand will reduce to 1465kW by installing

the energy efficient pumps, with 70% efficiency.

The total operating load of water pumping is estimated to be

10433 kW and this sector has a potential of reduction in load

demand by 400kW i.e. 4% of the total load approximately.

The 0ption given above could be implemented in the

municipal water-pumping sector up to 2018 with 10 %

replacement per year. The electricity required for water

pumping by 2018 has been estimated based on the population

growth rate of the city. It has been obtained that the electricity

consumption for water pumping systems will be increased to

91.1MW by 2012, 101.2 MW in 2015 and 112.5 in 2018. Figure

5.23 present the annual electricity consumption up to 2018

under BAU and solar city scenarios. It has been observed that

between 2009 and 2018 the energy savings will increase from

0.9 MU to 12.8 MU.

Page 100: Master plan to make Chandigarh a Solar City

84 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.23 Energy consumption in municipal water pumping in BAU and SC

scenarios

From the above energy efficiency and conservation measures it

is estimated that the electricity consumption can be reduced by

4.5 percent up to 2018. Table 5.3 presents the summary of

electricity consumption under BAU and solar city scenarios

under short, medium and long term durations.

Table 5.3 Summary of electricity consumption in BAU scenario and solar city scenario

Year

Residential sector

(MU)

Commercial Sector

(MU)

Street lighting

(MU)

Water pumping

(MU)

BAU SC BAU SC BAU SC BAU SC

2009 577 572 483 475 16.50 16.50 82.03 81.10

2012 Short term 924 894 796 763 18.99 14.24 91.13 86.99

2015 Medium

term 1433 1373 1273 1216

21.09 15.82 101.24 93.19

2018 Long term 2103 2014 1946 1864 23.43 17.57 112.48 99.70

Supply side options based on renewables In addition to the energy conservation measures, use of

renewable sources for thermal (heating) as well as power

generation were analyzed in a solar city scenario.

50

60

70

80

90

100

110

120

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

Year

An

nu

al

Ele

ctri

city

Co

nsu

mp

tio

n (

MU

)

BAU SC

Page 101: Master plan to make Chandigarh a Solar City

85 Energy planning

T E R I Report No. 2008RT03

Solar water heating systems It is a well-known fact that solar energy can be used for water

heating. Solar water heater is a commercialized technology in

India. A 100 litres capacity SWH can replace an electric geyser

for residential use and saves 1500 units of electricity annually.

The use of 1000 SWHs of 100 litres capacity each can

contribute to a peak load shaving of 1 MW. A SWH of 100 litres

capacity can prevent emission of 1.5 tonnes of carbon-dioxide

per year33. Figure 5.24 presents the schematic and photographs

of typical ETC based solar water heating systems.

Figure 5.24 Solar water heating systems in residential and commercial sectors

Many states including Delhi, Haryana etc. have taken initiative

and made use of solar water heating systems in industries,

hospitals, hotels, motels, large canteens, and commercial

buildings, mandatory.

It has been assumed that the residents of the Chandigarh city

use electricity for water heating. As Chandigarh is located in

composite climatic zone, it requires water heating and only for

four months in winters (from November to February). As the

city is developed under master plan hence solar water heating

systems can be made mandatory in residential and commercial

sectors.

It has been noticed from „energy use pattern‟ in residential

sector of composite climatic zone34, that the water heating

application consumes approximately 26% of the total energy,

which works out to be 130 MU in 2008 (BAU scenario).

33 http://mnes.nic.in/swhs-features.htm 34 Jain Manisha (2006), Energy Efficiency in Residential Sector of Delhi, in proceedings of Workshop on ;Developing an energy efficiency and conservation program for Delhi‟, TERI New Delhi, India.

Page 102: Master plan to make Chandigarh a Solar City

86 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Steps taken by Govt. of National Capital Territory of Delhi towards implementation of Solar Water Heaters Govt. of NCT Delhi has notified, vide office order no. F/ No.11(149)/2004/Power/2387 dated 28.09.06 for mandatory use of solar water heating system in following categories of the buildings- 1) Industries where water is required for processing, 2) Hospitals and nursing homes, 3) Hotels and Motels, 4) Jail Barracks, 5) Large canteens 6) Corporate buildings with plot area greater than 500 m2 , 7) Residential buildings having an area of 500 m2 or above excluding Delhi Cantonment Area 8) all govt. department buildings of NCT of Delhi, schools, educational institutions etc. Govt. also made mandatory the use of ISI marked motor pump sets, power capacitors foot valves in agriculture sector. Govt. ordered that all discoms and municipal council of Delhi shall make the amemends in the load demand notice for new connections to ensure use of only ISI marked pumps its accessories and other ISI marked pumps in NCT of Delhi. It asked the designated agency to ensure the implementation of these directions in the NCT of Delhi as per the provisions of the Energy Conservation Act 2001. Apart from this mandating of the use of SWH the govt. of NCT of Delhi is promoting the use of SWH by granting cost subsidy as an incentive to domestic consumers only. Accordingly govt. of NCT of Delhi has decided to give a subsidy of Rs. 6000/- per consumer as lump sum grant (Rs. 100 per month for a period of 5 years). The subsidy amount id provided through Delhi Energy Efficiency and Renewable Energy Management Centre of Delhi Transco Limited after conducting third party inspection. Financial Incentives from Central Government: The central govt. through Ministry of New and Renewable Energy provides interese subsidy to make soft loans available @ 2% interest to domestic users, 3% to industrial users not availing accelerated depreciation and 5% to industrial/commercial users availing accelerated depreciation from IREDA, public/private sector banks, RBI approved non-banking agencies etc.

Hence it is obtained that the electricity consumption for water

heating application in the city is 130 MU in 2008 (BAU

scenario).

Solar Water

Heating is one of the

technologies being

promoted by CREST

by providing subsidy

@ 25% of the total

system cost up to

300LPD System

(Domestic)35. As per

the information

provided by

CREST

approximately

66800 LPD

domestic Solar

Water Heating

Systems of different

capacities have been

supplied, installed

and commissioned

by the Department

through the different

BIS approved

manufacturers in

Chandigarh from

1999 to 2008.

However it would

take some time by

which all the households could make a changeover to solar water

heating systems (SWHs). In BAU scenario it has been assumed

that all water heating in the city is through the electricity.

Therefore, it is assumed that solar water heating technology will

be adopted by 2.5 % residents in the years 2009, 2010, 2011 and

2012 (i.e. 10 percent for short term targets). It is presumed that

well adoption and successful implementations of the technology

will accelerate the use of SWHs. In the medium term the

implementation of SWHs has been decided as 15 percent (i.e. 5%

in the years 2013, 2014 and 2015). The increasing pattern has

been assumed as constant (i.e. 5.0 %) during years 2016 and

2017 and increased by 10 percent by 2018 (long term). The

assumption has been made that the 45 percent households will

be using SWHs up to 2018. Figure 5.25 presents the BAU as well

as solar city scenario up to the 2018.

35 http://chandigarh.nic.in/dept_snt.htm#ncse

Page 103: Master plan to make Chandigarh a Solar City

87 Energy planning

T E R I Report No. 2008RT03

0

100

200

300

400

500

600

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

Year

An

nu

al

En

erg

y C

on

sum

pti

on

(M

U)

BAU SC

Figure 5.25 Solar water heating options under BAU and solar city scenarios

Rooftop solar PV Chandigarh city is well planed with proper orientation of the

building of residential as well as commercial/Institutional

sectors. It has been observed that the residential & commercial

sectors cover 73.9 km2 area

in the city out of total area

of 114 km2. Roof top solar

PV based grid connected

system may be well quite

feasible in the city. It has

been observed that the

commercial building,

Government buildings,

markets etc. have very large

roof areas which are not

being used. The grid

connected solar PV systems

of 100 to 500 kW capacities

are technically feasible in

commercial buildings while 25-50 kW capacity systems might

be feasible in residential sector. Figure 5.26 presents the

schematic of a grid connected roof top solar PV system.

Ministry of New and Renewable Energy (MNRE) has recently

announced the rooftop solar PV policy. The scheme on

Scheme on “Demonstration and Promotion of Solar Photovoltaic Devices/ Systems in Urban Areas & Industry” (Major focus on Roof top SPV Systems) MNRE through its scheme issued vide Sanction No. 3/7/2008-UICA(SE) dated 17th February, 2009. declaredits policy for financial support fot rooftop solar PV systems for replacing diesel gensets in institutions, govt buildings, commercial establishments, malls motels, hospitals etc. facing huge power shortages during daytime. According to this the MNRE will give Rs. 75 per watt of spv panels to a maximum of 30% of the cost of systems to profit making bodies and Rs. 100 per watt to a maximum of 40% of the cost of systems to nonprofit making bodies for both with or without grid interactive systems. Total target is 4.25 MW during rest of the 11th plan for system capacities varying between 25 to 100 kW with no restriction of targets to states. Proposals in prescribed format to be considered on first-cum-first basis through SNAS.

Page 104: Master plan to make Chandigarh a Solar City

88 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

“Demonstration and Promotion of Solar Photovoltaic Devices/

Systems in Urban Areas & Industry” focus on roof top SPV

Systems of MNRE is given in Annexure-7.

Figure 5.26 Schematic of a roof top grid connected solar PV system

Sector 17 and Sector 9 etc. of Chandigarh are commercial

sectors where the large commercial, institutional and

government office etc. exists. Roof top solar from 100 to 250

kWp capacities might be recommended for these sectors.

Figures 5.27 and 5.28 respectively represents satellite images of

Sector 17 and Sector 9 of the city where the potential areas for

roof top SPV are marked.

Figure 5.27 Satellite view of Sector-17 of Chandigarh and potential areas for roof top

Page 105: Master plan to make Chandigarh a Solar City

89 Energy planning

T E R I Report No. 2008RT03

Figure 5.28 Satellite view of Sector-9 of Chandigarh and potential areas for roof top SPV

In order to evaluate the performance of grid connected roof top

solar PV in Chandigarh, a simulation program has been

developed using RETScreen software. The capacities of the SPV

systems have been chosen from 25 kWp to 500 kWp. The annual

electricity generated by the SPV system of above capacities has

been presented in Figure 5.29.

Figure 5.29 Performance of Roof top SPV Systems in Chandigarh

42.6081.73

163.45

408.63

817.27

0

100

200

300

400

500

600

700

800

900

25 50 100 250 500

Solar PV System Capacity (kWp)

An

nu

al

Ele

ctr

ica

l O

utp

ut

(MU

)

Page 106: Master plan to make Chandigarh a Solar City

90 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

As the city has high potential of roof top solar PV; hence 10

MWp total capacity has been suggested to be installed by 2018

under solar city scenario. In 2009 and 2010 the total capacity

of 500 kWp has been suggested, while in 2011 and 2012 (short

term) the capacity increases to 750 kWp. In the medium term

strategy the capacity has been decided as 1.0 MWp from 2013 to

2015; while from 2016 to 2018 the capacity is proposed to

increase up to 1.5 MWp. Table 5.4 presents the results obtained

from RETScreen for the adopted methodology.

Table 5.4 Performance of proposed Roof Top SPV systems in Chandigarh

Year

Capacity

(kWp)

Effective Area

(m2)

Total Area

(m2) Output (MWh)

2009 500 3496.5 5594.4 800.15

2010 500 3496.5 5594.4 800.15

2011 750 5244.8 8391.68 1200.23

2012 750 5244.8 8391.68 1200.23

2013 1000 6993.0 11188.8 1600.31

2014 1000 6993.0 11188.8 1600.31

2015 1000 6993.0 11188.8 1600.31

2016 1500 10489.5 16783.2 2400.46

2017 1500 10489.5 16783.2 2400.46

2018 1500 10489.5 16783.2 2400.46

Total 10 MWp 69930.1 111888.2 16003.06

The cumulative electricity generation pattern of the proposed

roof top SPV systems for Chandigarh over the period of 2009 to

2018 has been presented in Figure 5.30. It has been estimated

that up to 2018 the roof top solar PV of the capacity of 10 MWp

will generate 16003.06 MWh and replace 12962 tCO2 annually.

The sample calculations using RETScreen software is presented

in Annexure 8.

Page 107: Master plan to make Chandigarh a Solar City

91 Energy planning

T E R I Report No. 2008RT03

Figure 5.30 Electricity generation pattern of roof top SPV in Chandigarh

Grid connected solar PV power plants Larger grid connected solar PV based power plants might be

another renewable energy based option for Chandigarh. A 25

MWp grid connected solar PV based power plant is being

considered in „Patiyala ki Rao‟ area. For solar PV based power

plant of 25 MWp capacity based on the best available sole cell

technology 174,825 m2 area is required; which will generate

approximately 39,723,379 kWh (39.7 billion units) of electricity

annually in Chandigarh. The action plan submitted to CREST

for developing the solar PV based power plant of 25 MWp

capacity is attached in Annexure-9. Figure 5.31 presents the

satellite image on „Patiyala ki rao‟ area where the large solar PV

based power plant of the capacity of 25 MWp might be installed

in public private partnership (PPP) mode.

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

An

nu

al

Ele

ctr

icit

y G

en

era

tio

n (

MW

h)

an

d G

HG

Red

ucti

on

(tC

O2)

Total Electricity Generation (MWh) GHG Reduction (tCO2)

Page 108: Master plan to make Chandigarh a Solar City

92 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.31 Large solar PV power plant proposed in „Patiyala ki rao‟ area

As the cost of land is very expensive in Chandigarh therefore it

is not possible to get a separate piece of land in the city. The

potential areas have been identified in the action plan

submitted to CREST. The landfill area of 45 acres has been

identified a potential location in the city where a solar PV based

power plant of the capacity of 5MWp may be installed. It has

been estimated using RETScreen software that a solar PV power

plant of 5 MWp capacity may generate 8001.53 MWh of

electricity and requires 14 acres area which is 30 percent of the

total area. Figure 5.32 presents the satellite image on Landfill

Site area where the large solar PV based power plant of the

capacity of 5 MWp might be installed.

Patiyala ki RaoPatiyala ki Rao

Page 109: Master plan to make Chandigarh a Solar City

93 Energy planning

T E R I Report No. 2008RT03

Figure 5.32 Potential area for SPV power plant at Landfill Site of Chandigargh

In addition to the planned use of solar water heating systems,

solar photovoltaic systems can also be used for various

applications in Chandigarh.

All the traffic signals in Chandigarh may be made „solar‟ by

2012.

Use of solar blinkers on roads might be an effective approach

towards highlighting the „solar city‟ concept within the city and

energy saving.

As the city is well planed hence solar cookers might have

good potential in the city. Box type solar cookers are best suited

for domestic sector while Parabolic concentrating solar cookers

(SK-14) might find feasibility in institutional segments of the

city. Steam solar cookers might find the good place in

institutional sector of the city.

Solar powered, LED Display Boards could be set up at the

strategic locations in the City. These boards would not only

display the fact that Chandigarh is a „Solar City‟ but also display

pollution levels, temperatures updates, and messages useful to

general public.

Provision of solar powered lights and fountains in the

prominent public gardens and parks in the city (such as

Botanical Gardens, Bougainvillea Garden, Rajendra Park, Rock

garden, Rose Garden, Shivalik Garden, Shanti Kunj, and Leisure

Valley) could be made thereby spreading the Solar City

message.

Landfill Site(Area=45 acres)

Jaypee’s MSW Treatment Plant

Landfill Site(Area=45 acres)

Jaypee’s MSW Treatment Plant

Page 110: Master plan to make Chandigarh a Solar City

94 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Biomass and Municipal Solid Waste Since maximum forest area (> 90 percent) of the city lies under

the reserve forest area hence biomass availability is very limited

in the city. In addition the available biomass is being dumped in

the landfill site with municipal solid waste; hence its utilization

might be possible with MSW.

Chandigarh City produces around 138700 tonnes of

municipal solid waste per annum. The municipal solid waste is

expected to contain a large amount of organic fraction, as the

major source is household and vegetable markets. Presently all

MSW and biomass available in the city is being use for pallet

manufacturing and electricity generation in the plant installed

by Jaypee Industries near Dadu Majara landfill site. Hence

there is no more potential for electricity generation through

MSW and biomass in Chandigarh Presently. In future, the

capacity of the existing plant could be enhanced.

Techno-economics of Energy conservation measures

Residential and commercial Retrofit options for common area lighting and their life cycle

costs have been undertaken. As per the information provided by

per Engineering Department (Electricity Wing), Chandigarh

Administration, the consumer tariff of Rs.2.29/kWh(average)

and Rs 3.36/kWh (municipal services) have been taken in order

to carry out the life cycle cost analysis for the retrofits.

1. Replacement of incandescent lamps with compact

fluorescent lamps (CFL) in common area lighting within the

building. Common area lighting includes portico, reception,

and lift landing area, corridors and staircases.

2. Replacement of existing fluorescent lamps in common areas

with T-5 lamps

Street lighting Replacement of existing ballast with the multi tab ballast with

astronomical timer switch.

The simple pay back periods for these retrofits are given below.

Present Power Requirement 3660 kW

Expected power required 2745.0 kW

Reduction 915.0 kW

kWh saving @ 12hr for 365 days 4007700.0 kWh

kWh saving 4.0 MU

Monetary Saving @2.29 Rs 9177633 Rs

Monetary Saving @3.36 Rs 13465872 Rs

Cost of Implementation @ 5500 Rs/ballast 110000000 Rs

Payback @ 2.29 12.0 years

Payback @ 3.36 8.2 years

Page 111: Master plan to make Chandigarh a Solar City

95 Energy planning

T E R I Report No. 2008RT03

Municipal pumping Present Power Requirement 1865 kW

Expected power required 1465.4 kW

Reduction 399.6 kW

kWh saving @ 6hr for 365 days 875217.9 kWh

kWh saving 0.9 MU

Monetary Saving @2.29 Rs 2004249 Rs

Monetary Saving @3.36 Rs 2940732 Rs

Cost of Implementation @ 35000 Rs/pump 8750000 Rs

Payback @ 2.29 4.4 years

Payback @ 3.36 3.0 years

Solar water heaters

Assumption:- Each household having 4 person will need a

100 lit per day solar water heating system. This system will

meet about 74% of the total annual hot water requirement

excluding summer season during which hot water requirement

is not considered.

Cost of solar water heater system for one household (1100 LPD)

Rs 20,000/-

Cost of one LPG cylinder (14kg)Electricity saved per year (910kWh@ 2.99 Rs/kWh) assuming escalation of 5% per year in electricity charges

Rs 2728/-

Subsidy @ Rs 1500 per sq m are of collector

Rs 5000/

Pay back period

6.6 years

Economic considerations for implementation of RET‟s for power generation

Solar based power generation (10MWp) Roof Top Rs 200 crores

Large Solar PV based Power plant (5 MWp) at landfill site Rs 100 crores

Large Solar PV based Power plant (25 MWp) at Patiyala ki Rao Rs 500 crores

Overall scenario of Chandigarh as Solar City The overall scenario of Chandigarh as solar city is based on the

suggested energy efficiency and conservation measures,

implementation of solar water heaters in residential sector and

roof top solar PV in commercial/institutional sectors. The roof

top solar PV has been found only renewable energy based

electricity generating option in the city while solar water

heaters, and other energy efficiency measures contribute

towards electricity/energy saving. The energy savings from

various energy efficiency measures and solar water heaters

along with electricity generation from roof top solar PV and

large PV based power plant at landfill site from 2009 to 2018

has been presented in Figure 5.33; which shows that solar water

heaters are the potential energy saving technology option.

Page 112: Master plan to make Chandigarh a Solar City

96 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure 5.33 Energy generation/saving in Chandigarh under solar city scenario

The overall solar city scenario of Chandigarh is presented in

Figure 5.34. In this case the solar city scenario is based on the

sum of energy savings as well as electricity generated through

roof top solar PV. It has been observed that implementing the

suggested measures and power generation techniques of

specified capacities, Chandigarh will be able to generate

500MU, electricity under solar city scenario in 2018. The

projected energy saving has been obtained as more than 15

percent of the total energy demand of residential, commercial

and industrial sectors by 2018; which is more than that of the

criteria (10%) defined in the guidelines of solar city of Ministry

of New and Renewable Energy, Govt. of India.

0

400

800

1200

1600

2000

2400

2800

3200

2009 2012 2015 2018

Year

To

tal

Ele

ctr

icit

y C

on

sum

pti

on

(M

kW

h)

BAU_Total Electricity Consumption (MU)

SC_Total Electricity Consumption (Generation and savings) (MU)

Page 113: Master plan to make Chandigarh a Solar City

97 Energy planning

T E R I Report No. 2008RT03

Figure 5.34 Overall scenario of Chandigarh as solar city

0

50

100

150

200

250

300

350

400

450

500

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Years

En

erg

y S

av

ing

/Gen

era

tio

n (

MU

)

Street lighting Water pumpingTotal Electricity Generation (Roof top SPV) Residential sectorCommercial Sector Solar Water HeatingLandfill (5 MW) Patiyale ki Rao (25 MW)Total

Page 114: Master plan to make Chandigarh a Solar City

98 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 115: Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

CHAPTER 6 Action plan

To meet the growing energy needs of Chandigarh city,

optimizing energy conservation and resource efficiency is

needed which would thus reduce per capita electricity demand.

This would minimize the need for new generation and reduce

GHG emissions. It would enable a cleaner environment with

reduced greenhouse gases and other pollutants, thereby

addressing the environmental concerns.

As a matter of priority, in order to develop Chandigarh as a

Solar City, the principal government agencies should be

committed to:

Discussing critical energy issues jointly through open

meetings and ongoing informal communication.

Sharing of information and analyses to minimize

duplication, maximize a common understanding and ensure

a broad basis for decision-making.

Continuing progress in meeting the environmental goals

and standards, including minimizing the energy sector‟s

impact on local and global environment.

Based on the analysis of potential for demand side measures

along with that of supply side augmentation through renewable

energy technologies, the following targets are proposed for

Chandigarh in order to develop it as a “Solar City”. These

targets are based on the detailed energy audits in Chandigarh

and renewable resource potential assessment.

Table 6.1 Targets for energy conservation generation and green house gas emission reduction

Description

Target

Short Term

(till 2012)

Medium Term

(till 2015)

Long Term

(till 2018)

1. Energy Conservation* Reduction in present energy consumption

1.1 Residential sector 10% 15% 20%

1.2 Commercial sector 10% 15% 20%

1.3 a Municipal sector (Water pumping) 1.5% 3.0% 4.0%

1.3 a Municipal sector (Street lighting) 1.5% 3.0% 4.0%

2. Coverage of solar water heating systems (as a proportion of

total heating demand in residential and commercial sectors)

10% 25% 45%

3. Roof Top solar energy based electricity generation 2.5 MW 5.0 MW 10.0 MW

4. Large solar energy based electricity generation at Landfill

site

3.0 MW 5.0 MW 5.0 MW

5. Large solar energy based electricity generation at Patiyala ki

Rao site

5.0 MW 15.0 MW 25.0 MW

GHG emission reduction (tCO2/annum) 90973 214051 404969

* As a percentage of reduction in energy consumption over projected consumption in BAU scenario

Page 116: Master plan to make Chandigarh a Solar City

100 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

The short-term targets for energy conservation are based on the

energy conservation options identified in the energy audit. To

achieve the medium and long-term targets the key

implementation points of the proposed Integrated.

Development Plan to make Chandigarh a Solar City is

summarized below:

Implementation plan

A “Solar City Cell” may be established within Municipal

Corporation of Chandigarh.

For implementation of Solar City project, an empowered

committees may be set up to provide overall guidance under

the chairmanship of the Finance Secretary.

The Solar City Cell may take advantage of programmes like

Jawaharlal Nehru National Urban Renewal Mission

(JNNURM) for implementation of the master plan.

The Solar City Cell may also take advantage of the grant-in-

aid (for energy consultancy as well as incremental cost of

building construction for a few buildings) being provided by

Bureau of Energy Efficiency (BEE) to design a few pilot

energy efficient buildings in the city, in accordance with

Energy Conservation Building Code (ECBC). The possibility

of availing incentives provided by the central government

for Green Rating for Integrated Habitat Assessment

(GRIHA) rated buildings may also be explored.

The Solar City Cell may work proactively:

– To get ECBC notified immediately

– To ensure that the building bye-laws are changed in

accordance with it

– To ensure that all upcoming non-residential buildings

are brought under the ambit of ECBC and incorporate

the relevant green buildings elements.

– To ensure that the major new commercial complexes

including those for ITES services are „GRIHA36‟ certified.

The state government may mandate CREST/Engineering

Department to distribute the quality CFLs to its consumers

at concessional prices or on easy payment terms.

For instance, in Delhi, BSES is promoting CFLs through

“Buy One Get 1 Free CFL Offer”. There is no restriction

on the number of CFL bulbs a customer can buy.

CREST may initiate a dialogue with the power utility for

introducing rebate on electricity tariff for the domestic

consumers, which employ solar devices.

To begin with, the energy conservation measures in the

municipal services may be taken up immediately.

At least 20% of the energy needed for water heating in the

residential and commercial buildings may be required to

come from solar energy, by 2010.

36 GRIHA

Page 117: Master plan to make Chandigarh a Solar City

101 Action plan

T E R I Report No. 2008RT03

CREST may initiate DPR preparation for

– 10 MWp solar PV based roof top power plant and

– 5 MWp solar PV based power plants in landfill site of the

city

– 25 MWp large solar PV based power plant in „Patiyala

ki Rao’ area of Chandigarh.

Utilizing central government schemes, CREST/ Municipal

Corporation may initiate installation of solar-based LED

traffic lights, solar street lights, building integrated solar PV,

and other relevant solar products on a priority basis.

CREST may mount a focused and sustained campaign on

“Solar City” covering all media resources - including print,

radio, and television.

In order to showcase Chandigarh City as a Solar City, the

following may be taken up on priority.

– Urja Park: Energy– cum–Science Park may be

established in a central location in Chandigarh as an

inviting place for social gatherings and to provide public

education about issues of sustainable energy in a

friendly, non-technical atmosphere.

– Urja Bhawan: CREST office and Solar City Cell may be

housed in a new building, constructed in accordance

with ECBC and other efficient/green building concepts.

The newly constructing Paryaran Bhawan may also have

Building Integrated Solar PV as well as Solar based

space conditioning system.

The following projects may be taken up through public-

private partnership:

– Setting up solar powered, LED Display Boards at the

strategic locations in the City. These boards would not

only display the fact that Chandigarh is a `Solar City‟ but

also display pollution levels, temperatures updates, and

messages useful to general public.

– Provision of solar powered lights and fountains in the

prominent public gardens and parks in the city (such as

Botanical Gardens, Bougainvillea Garden, Rajendra

Park, Rock garden, Rose Garden, Shivalik Garden,

Shanti Kunj, Leisure Valley etc.,) thereby spreading the

Solar City message.

Prominent office complexes like the Delux building,

additional building, UT secretariat, Police HQ, Punjab

secretariat, Haryana secretariat, museums, etc. may also

have solar powered displays as well as battery operated

vehicles for intra-complex transportation.

CREST along with PSEB and power utilities may begin

engaging the public through sustained awareness campaigns

about the benefits of energy conservation and renewable

energy; including local elected representatives and school

children.

Page 118: Master plan to make Chandigarh a Solar City

102 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

In Delhi, BSES has been educating its consumers

about the need to conserve power though Synergy – its bi-

monthly, bi-lingual newsletter, newspaper inserts, and

pamphlets distributed at meals from time to time.

Likewise, NDPL has launched Energy Conservation

campaign in Schools.

CREST may start organizing a series of training programme

on `Green buildings‟ for the planners; architects;

electrical, Heating Ventilation and Air Conditioning

(HVAC), and lighting consultants; and engineers involved in

the building sector.

CREST, in close cooperation with the BEE, may initiate

creation of accredited certifiers who can then be engaged by

the house owners/builders/developers for obtaining the

energy conservation compliance certificates.

CREST may initiate public-private partnership (e.g. working

closely with the associations of the local traders and

manufacturers) to propagate energy efficient appliances,

which include ‟Energy Star‟ appliances.

Under Solar City endeavour, one of the key action points

could be to replace traffic signals having incandescent lamps

with those with energy saving LEDs, along with solar

controllers. Similarly, CFL based streetlights; lights in the

parks, gardens, and roundabouts may be replaced with solar

lights.

To encourage adoption of energy conservation, energy

efficient equipment/appliances, as well as renewable energy

systems; CREST may introduce specific, time-bound

financial incentives for Chandigarh.

Towards this, the route of Energy Services Company

(ESCOs) may also be explored.

CREST may assist Municipal Corporation, Engineering and

other concerned departments in accessing capital for energy

conservation and efficiency projects at favourable terms. For

this purpose, State Energy Conservation Fund, as prescribed

by EC Act 2001, may be accessed.

The industrial sector is also one of the major energy

consuming sectors. CREST, may enhance the present

scheme for promoting energy audits in the industrial scoter.

Further, CREST may undertake awareness campaign in

industries in Chandigarh for energy conservation. This can

be undertaken in partnership with the local industry

association.

Budget estimation for Solar City initiative

The action plan for making Chandigarh has various components

and actions which include implementation of energy

conservation in Government buildings, as well as commercial

and residential sectors. Further the action plan also includes

activities related to implementation of different renewable

Page 119: Master plan to make Chandigarh a Solar City

103 Action plan

T E R I Report No. 2008RT03

energy technologies for different applications. These actions are

of different types like direct implementation, awareness

creation, providing subsidy and other promotional measures.

Based on the different activities/ initiatives suggested in the

action plan a tentative budget for undertaking these activities

has been prepared for short term (till 2012), medium tem (till

2015) and long term (till 2018). The budget estimated for

making Chandigarh as a solar city is given in table 6.2.

Table 6.2 Budget estimated for implementation of different activities for making Chandigarh as a Solar City

Sector (s) Proposed Measures Targets Role of CREST/Chandigarh Administration

2012 (Short Term)

2015 (Medium term)

2018 (Long Term)

Residential

Solar water heating systems

824500 lit per day capacity systems in 2009-10. Increase of 5% in installed capacity every year

1.Promotion and awareness creation 2.Providing subsidy support in initial phase (first 100000 lit capacity systems

53.47 (Million Rupees)

77.21 (Million Rupees)

101.94 (Million Rupees)

Promote use of efficient LPG stoves and efficient cooking devices such as microwaves

Achieve 10% reduction in projected LPG consumption as compared to BAU

Awareness creation 2.0 (Million Rupees)

1.0 (Million Rupees)

Promote use of alternate lighting systems such as SPV systems in villages to reduce kerosene consumption

Targets can be decided by CREST after survey of requirements

Awareness creation. Subsidy for five years for say 1500 Solar Home Systems

6.0 (Million Rupees)

1.50 (Million Rupees)

Promote use of roof top solar PV systems

10 MWp capacity systems by 2018

Subsidy support for first 10 MWp capacity systems of up to 5kWp capacity each as per MNRE guidelines

Promote energy conservation through promotion of energy efficient devices (CFL, air conditioners, microwaves, washing machines, TV, etc)

Increased use of these devices in the city

Awareness creation, specific support schemes for CFL and Air conditioners?

6.0 (Million Rupees)

1.50 (Million Rupees)

Commercial

Promotion of energy efficiency through awareness creation

achieve 10% share of energy efficient devices in the city

Promotional schemes and awareness creation

10.0 (Million Rupees)

2.5 (Million Rupees)

Replacement of existing ballasts by efficient ballasts in all street lights

100% replacement of ballasts

Investments/ financial support to CMC (Chandigarh Municipal Corporation)

110.0 (Million Rupees)

Replacement of booster water pumps in drinking water schemes with energy efficient pumps

Replacement of 250 nos of pumps of each 10 HP capacity

Investments/ financial support to CMC

8.12 (Million Rupees)

2.56 (Million Rupees)

Promotion of solar water heating systems in industries, hotels, hostels etc

100000 lit per day capacity systems in three years

Subsidy and awareness creation , providing soft loans / reduction in electricity bills/ cess for others

1.69 (Million Rupees)

0.56 (Million Rupees)

Promotion of energy At least 50% of the Implementation of 10.0 (Million 2.5 (Million

Page 120: Master plan to make Chandigarh a Solar City

104 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Sector (s) Proposed Measures Targets Role of CREST/Chandigarh Administration

2012 (Short Term)

2015 (Medium term)

2018 (Long Term)

efficient green buildings new building are certified under GRIHA or similar rating systems

Schemes through facilitation and cost sharing schemes

Rupees) Rupees)

Promotion of roof top systems in commercial /government, institutional and industrial buildings

Total 10 MWp capacity solar systems

Financial support to the utility for purchase of power at higher rate/ preferential tariff

400.0 (Million Rupees)

300.0 (Million Rupees)

300.0 (Million Rupees)

Power generation

Solar PV power plant 25 MWp power plants in phased manner

Subsidy support / Capital investments / preferential tariff / Soft loans

800.0 (Million Rupees)

1100.0 (Million Rupees)

600.0 (Million Rupees)

Solar PV power plant 5 MWp power plants in phased manner in Landfill area

Subsidy support / Capital investments / preferential tariff / Soft loans

300.0 (Million Rupees)

200.0 (Million Rupees)

Awareness creation

Establishment of 'Chandigarh Solar City Cell'

To set up Solar City Cell to develop, implement and monitor various schemes, to coordinate the development of Chandigarh as Model Solar City

Funding , creation and establishment of the cell and monitor its working

10.0 (Million Rupees)

7.5 (Million Rupees)

5.0 (Million Rupees)

Awareness creation for all schemes, development of solar city park and exhibitions

Awareness creation Develop and fund awareness creation/promotional schemes (included in the above)

Total

171728 (Million Rupees)

1696.83 (Million Rupees)

1006.94 (Million Rupees)

The year wise breaks up of above activities are given in

Annexure- 10.

Capacity building and awareness generation In order to inculcate energy conservation techniques in the

common architecture. It is essential that all the practitioners

be properly trained in energy-efficient or “Green”

architecture. CREST may, therefore, organize a series of

training programme for the planners; architects; electrical,

HVAC, and lighting consultants; and engineers involved in

the building sector, These courses, tailor-made to suit

different levels, would have to be imparted to all the

professionals, in public as well as in private sector – on a

regular basis.

Suitable training modules, including the regular updates,

may have to be developed and delivered for

– accreditation of professionals for building certification

and

– for the quality improvement of the accredited certifiers.

Page 121: Master plan to make Chandigarh a Solar City

105 Action plan

T E R I Report No. 2008RT03

Of particular importance is the training for front-line

workers and technicians regarding energy conservation and

efficiency, this would not only ensure successful

implementation of such measures but also their

sustainability and replication.

Specific training programmes are required for those in the

supervisory role, for effective monitoring of energy demand,

enabling them to take preventive/corrective actions in time.

The public awareness and education being central to

successful changeover to solar city, it is imperative for

CREST to engage the public through sustained awareness

campaigns and communicate the benefits of energy

conservation and renewable energy to different user-groups;

including local elected representatives.

CREST may mount a focused and sustained campaign on

“Solar City” and its features encompassing all media

resources - including print, radio, and television. Apart from

specific recommendations, such campaigns must inform

public about the places from energy efficient/renewable

energy devices and services can be procured.

A key component of the awareness creation campaign would

be to capture school children‟s attention towards energy-

efficiency and clean future. Thus, the campaign for the

school children will include the following elements:

– Inter-school essay and drawing competitions

– Inter-school quizzes

– Workshops and seminars

– Exhibitions and demonstrations

– Field trips

In this endeavour, Chandigarh‟s Eco Clubs may be involved

actively.

CREST may involve the Engineering Department to mount a

public campaign on energy conservation utilizing the regular

communication that power utilities or PSEB send to its

consumer‟s e.g. monthly electricity bills.

Page 122: Master plan to make Chandigarh a Solar City

106 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 123: Master plan to make Chandigarh a Solar City

107 Annexures

T E R I Report No. 2008RT03

Annexure 1: Technical details of street lighting in Chandigarh

Fixture Details

Total fixtures maintained by Municipal cooperation of Chandigarh 20,000

Total Number of lamps 20,000

Connected load details

250 Sodium Vapor lamps

Number of Fixture 1000

Number of Lamps 1000

Wattage of each lamp 250 W

Wattage of ballast 30 W

Total Wattage of 1 lamp 280 W

Total Load 280 KW

150 W Sodium vapor and Mercury vapor Lamps

Number of Fixture 18500 fixture

Number of Lamps 18500 lamps

Wattage of each lamp 150 W

Wattage of ballast 30 W

Total Wattage of 1 lamp 180 W

Total Load 3330 KW

70 W Metal halide lamps

Number of Fixture 500 Fixtures

Number of Lamps 500 lamps

Wattage of each lamp 70 W

Wattage of ballast 30 W

Total Wattage of 1 lamp 100 W

Total Load 50 KW

Total Load 3660 KW

Page 124: Master plan to make Chandigarh a Solar City

108 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 125: Master plan to make Chandigarh a Solar City

109 Annexures

T E R I Report No. 2008RT03

Annexure 2: Technical details of municipal water pumping in Chandigarh

Kazauli Pump Station Actul Readings

Location

Make Numbers Power Capacity head

Total

Rated HP

Total

Operating

HP

Rated

Efficiency

Total Running hp m3/hr m hp hp

Phase -1

Mothers +

platt 3 2 950 2052 100 2850 1900 88

Phase -2

Mothers +

platt 3 2 950 2052 100 2850 1900 88

Phase -3

Mothers +

platt 3 2 1050 2052 100 3150 2100 79

Phase -4

Mothers +

platt 3 2 972 2052 100 2916 1944 86

Total HP 11766 7844

WTP Sector -12 Mather+platt

1 1

215 925 40 215 0 70

Mather+platt 200 925 40 200 200 75

Mather+platt 3 2 375 1091 62 1125 750 73

Kirloskar 1 1 100 525 49 100 100 104

Sector 32 Kirloskar 2 2 150 1890 15 300 300 77

Phase 3

Sector 12 Mather+platt 2 1 362 953 62 724 362 66

Sector 12 WiPil 1 1 335 392 61 335 335 29

Sector 38 1 1 65 236 59 65 65 87

Sector 32 2 1 169 2052 18 338 169 89

Phase 4

Sector-52 Wipil 2 1 167 2052 18 334 167 90

Wipil 2 1 167 2052 18 334 167 90

Submersible

pumps

4 7.5 30 0 0

Sector 32 Mather+platt 2 2 100 946 18 200 200 69

MES

1 1 250 378 110 250 250 67

1 1 250 378 111 250 250 68

1 1 170 338 85 170 170 69

1 1 170 338 85 170 170 69

Total 5140 3655

Booster pumps Across

Chandigarh city 250 250 10 2500 2500

Total Load 19406 13999

Page 126: Master plan to make Chandigarh a Solar City

110 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Installed Consumption

Kazauli WTP

Booster

Pumps

Total kW 8777 3834 1865

Operating hours 24 24 6

Number of days 365 365 365

kWh consumption 76890339 33589694 4084350

Total Installed consumption 114564384 kWh

114.6 MU

Operating Consumption

Kazauli WTP

Booster

Pumps

EE Booster

Pumps

Total kW 5852 2727 1865 1465

Operating hours 24 24 6 6

Number of days 365 365 365 365

kWh consumption 51260226 23885279 4084350 3209132.143

Total Operating consumption 79229855 kWh

79.2 MU

Page 127: Master plan to make Chandigarh a Solar City

111 Annexures

T E R I Report No. 2008RT03

Figure A2.1 Water pumping station in Chandigarh (Kazauli water works)

Page 128: Master plan to make Chandigarh a Solar City

112 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 129: Master plan to make Chandigarh a Solar City

113 Annexures

T E R I Report No. 2008RT03

Annexure 3: „Trend analysis‟ – Methodology adopted for projection

„Trend analysis‟ is a well known statistical tool used for

projection of time series data. The exercise is usually carried out

in a built in tool box on MS-EXCEL which requires time series

data as base values. A graph of time series data is plotted in

which time is selected as X-axis value and the data which has to

be projected is selected as Y-axis value. Higher quantum of

input values is recommended for high level of projection. Figure

A3.1 presents a sample of trend analysis.

Figure A3.1 Sample of trend analysis using MS-EXCEL (Source: http://www.uniphiz.com/findgraph/eur-usd-740-600.gif )

In the first step the graph of time series is plotted. Further the

trend line over the data points is added which might be linear,

polynomial of n degree (n=1,2,3….), logarithmic etc. The

reliability and best fitting of trend line is given on the basis of

correlation coefficient (R2); which is essentially the strength and

direction of a mathematical relationship between a set of time

series data. The confidence interval of the projected values

found very high if the value of R2 is more than 0.95.

Page 130: Master plan to make Chandigarh a Solar City

114 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

When the correlation coefficient is found suitable for

projections that the mathematical equation of trend line is

obtained, which is a function of the values on X and Y axis. Now

if one has to project the ground data for a longer period the

value of X-axis parameter is changed and new values obtained

for the pre-specified time/year. Following steps are involved in

trend analysis in MS-EXCEL for time series projection:

1. Selection of data

2. Graph between Two set of value in which X-axis is time

dependent

3. Addition of the trend line over the line of graph

4. Estimation of correlation coefficient of trend line

5. Estimation of mathematical equation of trend line

6. projection of value based on trend line equation

Page 131: Master plan to make Chandigarh a Solar City

115 Annexures

T E R I Report No. 2008RT03

Annexure 4: Energy efficient schemes of BEE and BSES

A4.1 „Bachat Lamp Yojana‟ of Bureau of Energy Efficiency

Lighting accounts for almost 20% of the total electricity

demand in the country, and contributes almost fully to the peak

load as well. The vast amount of lighting in the country is

provided by incandescent bulbs, which are extremely energy

inefficient. Only about 5% of the electricity is converted into

light, the rest is lost as heat. In recent years, energy efficient

lamps have been introduced into the Indian market, with the

Compact Fluorescent Lamp (CFL) providing an energy-efficient

alternative to the incandescent lamp. A CFL uses only one-fifth

as much electricity as an incandescent lamp to provide the same

level of illumination. CFLs have almost completely penetrated

the commercial market, and the sales of CFLs in India have

grown from about 20 million in 2003 to more than 100 million

in 2007. However, penetration into households has been very

limited, largely because of the high price of the CFLs. The price

of CFLs is still in the Rs.80-100 price range, whereas the

incandescent bulbs are in the Rs.10-15 price range.

Initiatives to help decrease the price of CFLs to be

comparable with that of incandescent bulbs are therefore

necessary in order to enhance the penetration of CFLs in

households and are a policy goal that has been spelt out in the

agreed action points in the meeting of all State Chief Ministers

chaired by the Prime Minister of India. It is estimated that

about 400 million light points in India today are lighted by

incandescent bulbs; their replacement by CFLs would lead to a

reduction of over 10,000 MW in electricity demand. This would

not only reduce emissions by way of efficient end use of

electricity, but would also result in the reduction of peak load in

the country which currently faces a shortage of upto 15%. The

price barrier, as indicated above, will be overcome by using the

CDM revenue stream to enable faster penetration.

“Bachat Lamp Yojana” seeks to utilize the Clean

Development Mechanism (CDM) of the Kyoto Protocol to bring-

down the price of CFLs. This public-private partnership

between the Government of India, Private sector CFL

Manufactures /Traders (Project Developers) and State level

Electricity Distribution Companies would provide the

framework to distribute high quality CFLs at about Rs.15 per

piece to the households of the country. Under the scheme only

60 Watt and 100 Watt incandescent Lamps have to be replaced

with 11to15 Watt and 20 -25 Watt CFLs respectively.

The Government would develop a programmatic approach

(PoA) within which individual CFL supplier would develop

CDM projects. The Bureau of Energy Efficiency (BEE), being

the statutory body set up under the Energy Conservation Act,

Page 132: Master plan to make Chandigarh a Solar City

116 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

2001 by the Government of India, will coordinate the Small-

Scale Programme of Activities (SSC-PoA) and will facilitate

implementation of the programme in various States through

their respective Electricity Distribution Companies (DISCOMs)

with the assistance of the CFL suppliers. The development of

the SSC-PoA is a voluntary action on the part of BEE

and it would not seek any commercial revenues from

the SSC-PoA. On the other hand, it will on behalf of the

Government of India take the responsibility of monitoring of all

project areas after the DISCOMs and the CFL suppliers have

entered into a tripartite agreement (TPA) with BEE. The main

roles of the three parties are listed below:

CFL manufacturers and yraders

Providing CFLs with lumen output +/- 10% of the baseline

i.e. (lumen output of 100 Watt & 60 Watt ) Incandescent

Lamps at price comparable to those of Incandescent Lamps

(i.e. Rs 15), in exchange for functioning Incandescent

Lamps that are currently being used in the households. A

maximum of 4 CFLs shall be replaced per household. These

CFLs shall be compliant with the existing National

Regulations in force.

Free replacement of fused distributed CFLs, within 2 years

for 6000 hour CFL and within 3 years for 10000-hour

lamps, during the life of the CDM Project.

Collection of fused CFLs through buy-back schemes, and

arrangements for their safe disposal.

Pre-project survey to estimate the annual electricity saving

potential and baseline penetration of CFL in a selected SSC-

CPA area.

Distribution of CFLs in association with DISCOM within its

customer area.

Securing financing of initial investment for the cost

differential (no subsidy form the Govt. of India towards

reducing cost of the CFL lamps).

Preparing CDM Small-Scale Programme Activity Design

Documents (SSC-CPA-DD) for their CDM Small-Scale

Programme Activity (SSC-CPA) and submitting it to BEE.

Getting the SSC-CPA–PDD validated by a Designated

Operational Entity of CDM Executive Board.

Getting the SSC-CPA –PDD registered with the UNFCCC

(including payment of any fees to UNFCCC).

DISCOM in SSC-CPA area

Extend facilities to the SSC-CPA project investor to

Define geographic boundary of customer area of a DISCOM.

Define a residential household based on State level

definition and tariff category.

Safe storage of replaced ILBs for independent inspection

and safe disposal.

Page 133: Master plan to make Chandigarh a Solar City

117 Annexures

T E R I Report No. 2008RT03

Prepare database of all grid connected residential

households to include name of users/ address/ average

annual electricity consumption for each SSC-CPA project

area

Selection of Baseline Survey Group (BSG), Project

sample monitoring group (PSMG), Project spot-

check group (PSCG).

BEE:

Extensive awareness and information campaign in

association with DISCOMs.

Development of Small-Scale Programme of Activities Design

Document (SSC-PoA-DD).

Registration of the SSC-PoA with UNFCCC CDM Executive

Board.

Managing the monitoring of lighting appliance utilization

hours within the PSMG households using the approved

small scale methodology of the UNFCCC (EB) and analysis

of the monitored data.

Supporting the CFL suppliers/ DISCOMs to prepare SSC-

CPA-DDs.

Inclusion of SSC-CPAs to the SSC-PoA upon satisfaction of

the eligibility criteria stipulated in the SSC-PoA-DD.

Official communication with the CDM–EB, DOE and Indian

DNA.

Allocation of CERs to the SSC-CPA project participant /

DISCOMs according to their share in emissions reductions

in a specified period.

Decide any transaction cost on SSC-CPA for functioning as

managing entity for SSC-CPA

A4.2 „Buy One Get One‟ programme of BSES

BSES' “Buy One Get 1 Free CFL Offer” gets enthusiastic

response Over 96,000 CFL pieces sold in little over one month

BSES‟s drive for judicious use of electricity receives

tremendous response

Proves consumers aware of the need for energy

conservation

Over 96,000 CFLs already sold – this in effect should reduce

power demand by over 6 MW

15 W CFL (equivalent to 75 W) is the most popular category

West Delhi has maximum takers for the CFL energy

conservation scheme, closely followed by South Delhi

Yellow light emitting 1+1 CFL option will now be made

available to customers – at same price

BSES‟ innovative energy conserving scheme – Buy One Get One

Free CFL offer – has been received very enthusiastically by its

consumers. The scheme not only helps Delhi conserve scarce

Page 134: Master plan to make Chandigarh a Solar City

118 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

and precious electricity but also helps BSES customers make

substantial monetary saving.

The scheme launched in tandem with Indo Asian Fusegear

Limited – one of India‟s largest manufacturers and exporters of

CFL – on the auspicious day of Eid (October 24, 2006) by the

Hon‟ble Power Minister Shri Haroon Yusuf has turned out to be

a big hit. In little over one month over 96,000 CFL‟s have been

bought by thousands of BSES customers from the 52 special

kiosks put up at BSES Customer Care Centres and select Cash

Counters. “This discounted rate CFL offer for energy saving is

available only till December 31, 2006”, said a BSES official.

Area 11 W 15 W 20W Total

West 10040 15122 9164 34326

South 9868 13130 8644 31642

East 6474 9854 6682 23010

Central 1340 3346 2400 7086

Total 27722 41452 26890 96064

The data collated has revealed interesting trends. The data

indicates BSES‟ West Delhi customers have taken the lead in

energy conservation with over 34,000 CFL‟s being sold. South

Delhi is a close second with over 31,500 CFL‟s being bought

from the stalls. East and Central are at the third and the fourth

spot with over 23,000 and 7000 CFL‟s being bought.

Another interesting trend observed was that the 15 Watt CFL

(equivalent to 75 Watt at Rs 150 for 2) is the most popular

among the customers - with over 41,000 being sold. The 11 W

CFL (equivalent to 60 W at Rs 135 for 2) sold nearly 27,000

pieces closely followed by the 20 W CFL (equivalent to 100 W at

Rs 200 for 2) which sold over 26,500 CFL‟s

“Substituting the normal incandescent bulbs with these low

consumption, high brightness output CFL‟s will lead to massive

savings. Savings accruing from the over 96,000CFL‟s sold from

BSES‟ outlets will lead to a reduction in maximum demand by of

over 6.2 MW at a given point of time– enough to power two

average shopping malls in Delhi and lead to energy saving of

over 9 million units annually” said a BSES official.

In view of the encouraging response to the

scheme, BSES has now decided to put on offer the

yellow light emitting CFL’s at the same price and

wattage, said the BSES spokesperson. To avail the

existing as well as new offer of yellow light emitting CFLs, all

that a customer has to do is visit any of BSES‟ 33 Customer

Care Centers and 32 select Cash Counters, show copy of their

last paid bill (from September 1 onwards) and avail the offer.

Also there is no restriction on the number of CFL bulbs a

customer can buy”

Page 135: Master plan to make Chandigarh a Solar City

119 Annexures

T E R I Report No. 2008RT03

“A recent study has shown that Delhi can save around 450

MW of electricity by simply switching over to CFL bulbs.

Additional 175 MW electricity can be saved by just switching

off electrical gadgets from the mains, instead of the keeping

them in the stand by mode” said a BSES official and added

Savings of up to Rs 391 per year can accrue with just one CFL

bulb. Imagine the magnitude of savings accruing to a family

if all the bulbs are replaced with CFL‟s.

According to a BSES spokesperson “BSES has been

educating its consumers about the need to conserve power

though Synergy – its bi-monthly, bi-lingual newsletter that

goes to its 23 lakh customers, newspaper inserts and

pamphlets distributed at melas from time to time. We

request our consumers to avail this special limited period

offer that will not only help Delhi over come the power crisis

but also bring about substantial monetary savings”

BSES, Delhi’s premier power distribution company,

is committed to ensuring quality and reliable

electricity supply to all its consumers.

Page 136: Master plan to make Chandigarh a Solar City

120 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 137: Master plan to make Chandigarh a Solar City

121 Annexures

T E R I Report No. 2008RT03

Annexure 5: Energy efficiency measures for air conditioning

Energy conservation measures for air conditioners In addition to the above mentioned energy conservation

measures, there are certain „Behavioural best Practices” which

can reduce energy consumption in air conditioners. These

measures are explained below. The analysis in solar city

scenario does not consider energy saving due to these measures

as it is difficult to quantify the energy saving that would be

achieved. Further, these measures need awarness creation so

that these measures are adopted by general public, thus a

awarness campaign has been suggested for these measures.

Option-A: Changing the set point in window ACs The efficiency of window ACs can be enhanced by increasing the

temperature of the air supplied into the room. This is based on

the principle that the efficiency of the system decreases to

produce lower air temperatures. Therefore it is recommended to

increase the temperature of the supply air from window AC. It

was observed that the thermostat position in most of the

window ACs was in the „coolest‟ mode. The reason for the

extreme setting is to achieve cooling in the shortest time. This

may lead to excessive cooling and also the AC runs at a low

efficiency in the „coolest mode‟. The lesser the temperature

difference between indoors and outdoors, the higher the

efficiency of the AC system. So, it is always recommended to set

the thermostat as high as possible so as to achieve comfortable

indoor conditions.

Studies have shown that 3.6 % reduction in energy

consumption is achieved for every degree Centigrade raise in

the supply air temperature for a window AC. It was observed

that a few window ACs in Old Sachivalaya building were

operating at a supply air temperature of 8.5 deg C. At this

temperature the efficiency of the AC could be very low. Also, for

maintaining comfortable indoor conditions, it is recommended

to have the supply air temperature at 13 deg C. The estimated

energy savings by increasing the supply air temperature is given

in the table below.

Table A5.1 Energy savings in window ACs

Supply air

temperature

measured

Supply air

temperature

recommended

Increase in

temperature

Estimated energy

savings per AC

8.5 deg C 13 deg C 4.5 deg C 16%

Supply air temperature of 8.5 deg C corresponds to the „coolest‟

temperature setting in the window AC. And a supply air

temperature of 13 deg C corresponds to a „medium‟ temperature

Page 138: Master plan to make Chandigarh a Solar City

122 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

setting in the window AC. It was observed during the study that

the supply air temperature in the various window ACs at old

Sachivalaya building varied between 8.5 deg C and 14.5 deg C,

though a majority of the ACs were operating with supply

temperature in the lower range (less than 10 deg C).

The recommended temperature setting, with reference to the

inefficient setting is shown in the Figure A5.1 below.

Figure A5.1 Temperature setting – „Coolest‟ (Inefficient)

Figure A5.2 Temperature setting – „Medium‟ (Efficient)

Split ACs and new window ACs are available with digital display

panel where the temperature which to be maintained in room is

generally set and displayed. The users are generally advised by

the manufacturer to set a temperature between 18 to 20 o C.

However, the temperature required for adequate comfort

conditions in an air conditioned room varies between 23 ~ 26 o

C. Therefore it is recommended that in air conditioned

executive offices, a set point temperature of 26 ~ 27 o C shall be

set and the ceiling fan shall be switched on. This would provide

the best comfort at the minimum consumption of energy.

Option-B Changing the operating pattern of window ACs When the executive offices in the building are not occupied,

heat is accumulated in the rooms due to heat gains from walls

and windows. Therefore, when officers are expected to arrive in

a particular office, the ACs have to be switched on sometime

Page 139: Master plan to make Chandigarh a Solar City

123 Annexures

T E R I Report No. 2008RT03

before their arrival so as to get the room to a comfortable

condition. If this duration is too long, it may lead to wastage of

energy and also over-cooling of the room in some cases. This

can be prevented by following the guidelines mentioned below.

The parameters controlling the comfort conditions are

temperature, humidity and air movement. Though temperature

and humidity are the most significant, air movement is also

important as it provides a feeling of freshness and increases the

effect of cooling. According to the National Building Code of

India 2005, the thermal comfort of a person lies between the

temperature range 25 – 30 0C. In hot and dry climates like

Chandigarh, air movement would be necessary to achieve

adequate thermal comfort. Table A5.2 gives the desirable wind

speeds for thermal comfort at different temperature and

humidity conditions. For achieving wind speeds greater than 2

m/s, mechanical means of ventilation such as fans are required.

Table A5.2 Desirable wind speeds (m/s) for thermal comfort conditions 37

Dry bulb

temperature

(deg C)

Relative humidity (%)

30 40 50 60 70 80 90

28 * * * * * * *

29 * * * * * 0.06 0.19

30 * * * 0.06 0.24 0.53 0.85

31 * 0.06 0.24 0.53 1.04 1.47 2.10

32 0.20 0.46 0.94 1.59 2.26 3.04 **

33 0.77 1.36 2.12 3.00 ** ** **

34 1.85 2.72 ** ** ** ** **

35 3.20 ** ** ** ** ** **

*None ** Higher than those acceptable in practice

Figure A5.3 Window AC with Ginie

In the offices, it is recommended that the ACs are switched on

about 30 minutes before the arrival of the officers with the

temperature setting in the „medium‟ position as shown in the

previous section, and by switching on the ceiling fans. Ceiling fans

induce air movement and result in uniform distribution of cool air

37 Part 8, Section 1, National Building Code of India 2005

Page 140: Master plan to make Chandigarh a Solar City

124 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

inside the room. They also enhance the cooling effect produced by

the ACs and thus help in achieving comfortable indoor conditions

for the guests. This measure results in energy savings (though not

quantifiable) and does not require any investment.

Option-C: Installation of energy saving equipment on window ACs A power saving equipment (genie) can be installed on the

existing window or split AC to enhance the performance of the

unit. The principle behind the working of this equipment is that

it increases the area of the condenser thereby reducing the

condenser temperature. This results in an increased efficiency

of the cooling system. The estimated energy savings through

this equipment is 10 to 20% as per the manufacturer), which is

achieved through:

Option-C: Installation of energy saving equipment on window ACs 1. Direct fall in amperage

2. Fall in grill temperature

One of the manufacturers of such a device (Genie) is given below.

Option D: Location of equipments near the window AC It was observed at a few places that file boxes and tables etc. were

placed very near to the window AC. This affects the performance of

the AC because they obstruct the air flow and the temperature

sensed by the thermostat. Even though the room temperature is

uncomfortable, the temperature sensed by the thermostat is lower

and results in the AC running for a shorter duration than required.

The occupant feels that the AC is not performing well and he

immediately changes the set point temperature to lower value

which leads to the energy wastage. So, care has to be taken to

ensure that no equipments are placed very near to the ACs.

Page 141: Master plan to make Chandigarh a Solar City

125 Annexures

T E R I Report No. 2008RT03

Annexure 6: Astronomical timer switch for street lighting

Astronomical time switch for switching on street lights,

advertisement hoarding lights, sign board lights at sunset time

& switching off at sunrise time without any light sensor. Sunset

& sunrise time is generated every day by microcontroller based

astronomical time switch using astronomic software for any

geographic location [latitude, longitude & time-zone]. With

twilight setting lights can be switched on earlier from sunset

time [for indoor lights] or delayed from sunset time [for

outdoor lights] by 0 to 60 minutes, similarly switch off will be

delayed [for indoor lights] or earlier [for outdoor lights] than

sunrise time. To save electrical power, partial lights can be

switched off at any set time late night after sunset, if required

can be switched on again early morning at any set time before

sunrise. If 2kw of light load is switched off for 6 hours every

night, it can save 360 units of electrical power every month.

Municipal, city corporation can use it for street lights.

Industries, commercial establishment & housing societies can

use it for compound & other lights. In case of power failure set

parameters are saved in memory & clock runs on internal

battery.

Figure A6.1 Astronomical time switch for street lighting (Source: suppliers.jimtrade.com)

Page 142: Master plan to make Chandigarh a Solar City

126 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 143: Master plan to make Chandigarh a Solar City

127 Annexures

T E R I Report No. 2008RT03

Annexure 7: “Demonstration and Promotion of Solar Photovoltaic Devices/ Systems in Urban Areas & Industry”

scheme of MNRE

Page 144: Master plan to make Chandigarh a Solar City

128 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 145: Master plan to make Chandigarh a Solar City

129 Annexures

T E R I Report No. 2008RT03

Annexure 8: RETScreen Worksheets for SPV based power generation

Page 146: Master plan to make Chandigarh a Solar City

130 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 147: Master plan to make Chandigarh a Solar City

131 Annexures

T E R I Report No. 2008RT03

Page 148: Master plan to make Chandigarh a Solar City

132 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 149: Master plan to make Chandigarh a Solar City

133 Annexures

T E R I Report No. 2008RT03

Annexure 9: Pre-feasibility study for setting up 25 MWp

(total) grid-connected solar PV power plant in Chandigarh

The Union Territory of Chandigarh, also known as the modern

India‟s first planned city, is located at latitude 30o40‟-30o46‟N,

longitude 76o42‟-76o51‟E and altitude 350 meter above sea level.

It is located on the foothills of the Shivalik ranges of Himalaya,

which form a part of the fragile Himalayan ecosystem.

Chandigarh is also the capital of the states of the Punjab and

Haryana, however, administratively, the city is under the

jurisdiction of the Central Government and hence classified as a

Union Territory. It has two satellite cities namely Panchkula

and Mohali. These three cities are also collectively known as the

Chandigarh Tri-city.

The Union territory of Chandigarh is going green by

incorporating sustainable development principles in its urban

planning and development. In a bid to promote sustainable

development , renewable energy utilisation, create awareness

about dangers of global warming and promote climate change

mitigation within its territory, the Chandigarh administration

has decided to develop it as „Solar City' by 2012. TERI has been

retained as consultant to prepare the Chandigarh Solar City

master plan.

As part of this activity, TERI has studied the possibility of

setting up 25 MW capacity solar photovoltaic power plant.

Chnadigarh is dependent on Central and State government run

power plants to meet its electricity demand. This plant, which is

proosed to be installed at multiple locations, would be

Chandigarh‟s first self owned power plant.

Page 150: Master plan to make Chandigarh a Solar City

134 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure A9.1 City map of Chandigarh

(Source: http://chandigarh.gov.in/)

Objective The study report covers the pre-feasibility analysis for installing

solar PV power plants totalling to 25 MWp capacities in the city

of Chandigarh.

Solar radiation over Chandigarh Chandigarh is located in the sunny belt of the country and

receives a good amount of solar radiation over the year. It has

been observed that the annual global over the cities is 1944

kWh/m2, while the annual diffuse radiation is 846 kWh/m2. As

the solar pannels are fixed on inclined surfaces and the angle of

inclination ia usually takes as equal to latitude of the location.

The global solar radiation over the inclined surface has been

estimated as 2155 kWh/m2 annaually. The sun-path diagram for

the location of Chandigarh is presented in Figure A9.2, which

indicates that the annual daylength is more than 10 hours.

Page 151: Master plan to make Chandigarh a Solar City

135 Annexures

T E R I Report No. 2008RT03

Figure A9.2 Sun-path diagram for Chandigarh (using ECOTECJ software)

Figure A9.3 presents the daily values of solar radiation on

horizontal and inclined surface in Chandigarh for one

represntative day of each month. The month-wise values of

solar radiation received by a surface on horizontal and inclined

surface are summarized in Table A9.1.

Page 152: Master plan to make Chandigarh a Solar City

136 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Da

ily

So

lar

Ra

dia

tio

n (

kW

h/m

2)

Global Solar Radiation (kWh/m2) Diffuse Solar Radiation (kWh/m2)

Global Solar Radiation on Latitude (kWh/m2)

Figure A9.3 Variation of daily Global and Diffuse solar radiation over Chandigarh

Table A9.1 Daily and monthly variation of solar radiation over Chandigarh

Month Daily Monthly

Global

Solar

Radiation

(kWh/m2)

Diffuse Solar

Radiation

(kWh/m2)

Global Solar

Radiation on

Latitude

(kWh/m2)

Global Solar

Radiation

(kWh/m2)

Diffuse Solar

Radiation

(kWh/m2)

Global Solar

Radiation on

Latitude (kWh/m2)

Jan 3.78 1.45 5.45 117.1 45.0 169.0

Feb 4.61 1.83 5.84 129.1 51.3 163.6

Mar 5.60 2.25 6.33 173.7 69.8 196.1

Apr 6.53 2.62 6.55 195.8 78.7 196.4

May 7.04 2.88 6.46 218.3 89.4 200.3

Jun 6.24 3.29 5.55 187.1 98.8 166.6

Jul 5.91 3.28 5.36 183.3 101.6 166.0

Aug 5.29 3.10 5.10 164.1 95.9 158.2

Sep 5.81 2.48 6.24 174.3 74.5 187.1

Oct 5.29 1.81 6.61 164.1 56.2 205.0

Nov 4.34 1.39 6.21 130.3 41.7 186.2

Dec 3.46 1.40 5.16 107.4 43.5 159.9

Climate of the city Chandigarh is situated in the composite climatic zone of India;

hence summers are very hot and winters are cool. The annual

ambient average temperatures is obtained as 21-22oC. Figure

A9.4 presents the variation of ambient temperature and relative

Page 153: Master plan to make Chandigarh a Solar City

137 Annexures

T E R I Report No. 2008RT03

humidity throughout the year. The 20 year average rainfall for

Chandigarh is 1100.7 mm.

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Am

bie

nt

Tem

pera

ture (oC

)

Rela

tiv

e H

um

idit

y (

%)

Ambient Temperature (oC) Relative Humidity (%)

Figure A9.4 Variation of annual average ambient temperature and relative humidity over Chandigarh

(Source: http://eosweb.larc.nasa.gov/ )

Hence solar radiation and climatic parameters are favorable towards solar PV based power generation in

Chandigarh. A brief technological overview of

commercially available solar technologies is given below.

Solar PV technologies Solar Photovoltaic (SPV) technology is primarily a solid-state

semiconductor- based technology, which converts a fraction of

the incident solar radiation (photons) in to direct electricity. PV

system can deliver electric energy to a specific appliance and/or

to the electric grid. Photovoltaic systems are flexible and

modular; hence the technology can be implemented on virtually

any scale size, connected to the electricity network or used as

stand-alone or off grid systems, easily complementing other

energy sources. PV offers several advantages viz. (i) hybrid with

other energy resources; both conventional and renewable, (ii)

off-grid or grid-connected systems (iii) flexibility towards

implementation and (iii) environmental advantages.

There are several ways of classifying the solar cell depending

upon the type of absorbing material used, manufacturing

technique /process adopted, type of junction formed. Solar cell

technologies may be broadly classified as:

Page 154: Master plan to make Chandigarh a Solar City

138 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Wafer based crystalline silicon solar cell technology It

consists of single crystal silicon (c-Si) solar cell and multi-

crystal silicon (mc-Si) solar cell

Thin-film solar cell technology, which includes, Copper

Indium Diselenide (CIS) Copper Indium Gallium Diselenide

(CIGS), Cadmium Telluride (CdTe), Amorphous silicon (a-

Si) etc. and,

Emerging technologies such as thin-film silicon, Dye

Sensitized Solar Cells(DSSC), polymer organic solar cells, etc

have come up in recent times.

An overview of solar PV technologies is represented in Figure A9.5.

Figure A9.5 Classification of solar PV technologies

The highest efficiency achieved by the available c-Si solar

modules is much higher as compared to thin film solar

cells/modules. As far as the commercially attained efficiencies

for different cell technologies is concerned, the efficiency of

crystalline silicon solar modules is in the range of 13-16% where

as the thin film solar cells are in the range of 6-9%. Similarly as

far as the long term stability of solar modules are concerned, c-

Si module manufacturers can give warranty for 90% of its rated

power for 20 years and 80% of its rated power for 30 years from

the date of system acceptance whereas thin film modules with

only 10 years of warranty are available in the market.

Wafer based crystalline silicon solar cell technology Wafer based solar cells are produced by converting a very thin

wafer (typically about 200 to 300 μm thick) of pure silicon

(>99.9% purity) into a semiconductor solar cells by doping it

with suitable N and P type materials. Wafer based solar cells

are of two types; mono crystalline silicon cells (c-Si) and poly or

multi-crystal silicon (mc-Si) solar cell

Mono crystalline solar cells Mono crystalline solar cells are manufactured using silicon

wafers saw-cut from a single cylindrical crystal of silicon. Mono

crystalline silicon cell are the most efficient and durable among

Solar cell

New emerging technology

Wafer based Silicon (Market share 90.6%)

Thin-film (Market share 9.4%)

a-Si Sheet / ribbon Si

Compound semiconductor

(CdTe, CIS, CIGS)

Mono –crystalline

Multi –crystalline

Thin film Crystallin

e Si

Dye Sensitized, polymer, CNT etc

Page 155: Master plan to make Chandigarh a Solar City

139 Annexures

T E R I Report No. 2008RT03

various solar cell technologies. These cells are commercially

available in efficiency range of 13 to 18%.

Poly crystalline solar cells Poly crystalline solar cells are made from an ingot of melted and

recrystallised silicon. Poly crystalline silicon cells are cheaper to

produce than mono crystal solar cells. Some companies have

developed and commercialised new production techniques such

as Edge Fed Growth (EFG) which reduce the wastage of

material during wafer cutting and hence reduce the cost of

production. Poly crystalline cells are slightly less efficient than

mono crystalline cells. At present, cells with efficiencies in the

range of 13 to 16% are commercially available in the market.

Thin-film solar cells A number of new solar cell technologies using other

semiconductor materials such as Copper Indium Diselenide

(CIS), Copper Indium Gallium Diselenide (CIGS), Cadmium

Telluride (CdTe), are now commercially available. These solar

cells are manufactured by depositing thin film of the

semiconductor material on suitable metallic or non-metallic

substrate. These are, therefore, called as thin film solar cell

technologies.

Amorphous silicon (a-Si) solar cells Amorphous silicon cells are also manufactured using thin film

deposition techniques. Amongst the thin film solar cell

technologies, a-Si solar cells/modules are most widely used.

CIGS solar cells CIGS solar cells are one of the most promising thin film

technologies due to their high-attained efficiency (around 19%)

with extended operational lifetime without significant

degradation. The efficiency achieved by commercially available

modules is in the range of 8-10%. These cells are expensive and

are currently used for space applications where less weight and

higher efficiency are most important.

CdTe solar cell CdTe solar cell technology is one of the oldest thin film

technologies and the efficiency of commercially available

modules is in the range of 7-9%. However the limited

availability of base materials like Cd and the cost associated

with it and possible pollution of environment due to release of

Cd are some of the main limitations in using CdTe solar cells for

large scale use. Some European nations in particular have

strong reservations against use of any solar cell technology in

which Cd is used.

Some of the advantages of thin film solar cell/module over

wafer based solar module is its lightweight, ease in production

Page 156: Master plan to make Chandigarh a Solar City

140 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

technique and flexibility in depositing modules on various

substrates. Thus it allows the flexibility in the PV integration

into buildings.

Thin film solar cells are likely to be cheaper than wafer based

solar cells since their manufacturing processes are simple and

they use lesser materials as compared to wafer based solar cells.

However, these cells are less efficient and their performance

degrades during the use and hence these are not preferred for

large capacity systems.

New emerging technologies Dye Sensitized solar Cell (DSSC), Organic Photovoltaic (OPVs)

using Carbon Nano-Tubes (CNT), polymer solar cells etc are

some of the emerging technologies and expected to be an

attractive alternative to traditional silicon-based solar cells.

These can be printed on flexible foils and can be produced in

different shapes and thus can effectively be used by adding

them into window glass of a building. These are not yet

commercially available in open market.

Recommendation on selection of technology If the extent of commercialization and maturity level of

different solar cell technologies in terms of its market

availability, commercially attained efficiencies, life and long

term stability etc is assessed, it is obvious that crystalline silicon

solar modules are preferred over thin film solar modules. Thin-

film solar modules can be considered for small scale

demonstration purposes in the building, keeping its lightweight,

flexible, aesthetic look into consideration.

Study of major solar photovoltaic plants of similar scales

reveals that crystalline silicon (either mono- or poly- or both) is

best option for such plant. As can be seen in further discussions

where design calculations for thin film technology cells were

also carried out, crystalline silicon is best technology

considering the constraint of area at site.

Grid connected solar PV systems A recent development in renewable energy technology is grid-

interactive or two way grid interconnection. If the system

generates more solar power than need of users, the excess is

exported back to the main grid. These systems use sophisticated

control equipment so that when the renewable energy system

produces more power than need, the excess power is fed back

into the grid. When the system doesn't produce enough power,

then one can get power from the grid. These systems are

popular for residential and domestic sectors, homeowners and

small businesses where a critical backup power supply is

Page 157: Master plan to make Chandigarh a Solar City

141 Annexures

T E R I Report No. 2008RT03

required for critical loads such as refrigeration, water pumps,

lighting etc.

Grid connected solar PV systems offer a unique opportunity

to silently and cleanly generate significant amounts of energy,

which are designed to operate in parallel with, and

interconnected, with the electric utility grid. A grid-connected

solar electricity system links several solar panels together

through an inverter to the power grid. No electrical storage

batteries are required, as excess electricity generated by the

solar panels. Figure A9.6 presents the schematic of a grid-

connected solar PV power plant.

Figure A9.6 Schematic diagram of a grid connected solar PV system

Grid-interactive systems A grid-interactive photovoltaic system is connected to the utility

grid. A specially designed inverter (s) is/are used to transform

the PV-generated DC to AC electricity at the grid voltage. Grid-

interactive systems can be designed with or without battery

storage. The main advantage of this system is that the power

can be fed into the grid or can be drawn from the grid as and

when required. The proposed solar power system at the

Presidential Estate is grid interactive type without battery

storage.

A brief study of major photovoltaic plants was carried out by

TERI to assess the state of the art of technology. There are more

than 50 solar power plants of 1 MW and above capacity installed

in different countries and many more are under construction.

Grid connected megawatt capacity solar systems occupy major

market share in the world photovoltaic market.

A typical arrangement of grid interactive solar PV power

plant is shown in Figure 6. The main components of typical

solar PV grid interactive power plant are

Solar modules or array

Page 158: Master plan to make Chandigarh a Solar City

142 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Interconnecting wiring

Inverter or set of inverters to convert DC voltage of solar

module to AC voltage

Step up transformer

Control cum monitoring system

Earthing, and lightening protection system

Normally the system operates in grid-connected mode, serving

the on-site loads or sending excess power into the grid. The

connection to the grid requires a special meter which can run

forwards and backwards (net metering) and if a feed in tariff is

paid an additional meter to measure PV production is needed.

Grid connected photovoltaic systems can be separated into

three main categories

1. Domestic photovoltaic systems: These are typically rated at

between 0.5 and 5kWp and are mounted on roof tops of

individual households. The domestic systems are usually

single phase connected to the domestic supply 220V.

2. Commercial or industrial roof top PV systems: These are

typically in range of 10 kW up to 100 kW and are installed

on roof tops of commercial and industrial buildings.

3. Large scale (1MW and above) SPV power plants: These are

installed either on ground area or on large roof tops as

independent power plants of more than 1 MW capacity.

MNRE has recently announced Generation Based Incentives

(GBI) for such systems. These systems offer economy of

scale and large scale production. Worldwide the current

trend is to install such type of systems.

Grid failure or non availability of grid during daytime due to

power cut is reality in countries like India. In such situation

solar power cannot be fed into the grid. To overcome this

situation a new combination of grid connected systems with

small battery bank is developed. During the periods of non

availability of grid the battery bank simulated the grid

conditions and solar system then can supply power to selected

critical loads. Such systems are being developed in India.

Simulation of grid-connected SPV power plant of the capacity of 25 MW In order to estimate the performance of a grid-connected solar

PV based power plant of the capacity of 25 MW in the location

of Chandigarh, a simulation model has been developed using

internationally approved computer software named RETScreen.

RETScreen is an excel based software which calculated the

performance and commercial viability of renewable energy

technology projects. For SPV project evaluation is takes into

account the solar radiation availability and climatic conditions

of the place (Chandigarh in this case) and the model gives the

power output throughout the year. Table A9.2 presents the

Page 159: Master plan to make Chandigarh a Solar City

143 Annexures

T E R I Report No. 2008RT03

output and required area of a solar PV power plant of the

capacity of 1 MW using various commercially available solar PV

modules.

Table A9.2 Performance results of a SPV power plant of the the capacity of 1 MW

Solar cell

technology

Efficiency

(%)

SPV power

plant capacity

Units generated

(kWh)

Area required

(m2)

Mono-Si 14.3 1 MW 1570935.0 6993.0

Poly-Si 12.3 1 MW 1570935.0 8130.0

a-Si 5 1 MW 1674326.0 20000.0

CdTe 7 1 MW 1628943.0 14286.0

CIS 7.5 1 MW 1533823.0 13333.0

Spherical-Si 9.4 1 MW 1570935.0 10638.0

It can be observed that in order to install solar power plants of

the capacity of 25 MW through the best available solar cell

technology 174,825 m2 area is required. This power plant will

generate approximately 39,723,379 kWh (39.7 billion units)

of electricity annually in Chandigarh.

It is clear that the land requirement will depend on the type

of solar cell used. RETScreen model estimates the effective area

of solar cells. In order to estimate total required area the

shading between solar arrays is estimated. Usually it is taken as

1.6 times to the effective area. Hence the total area required for

installation of solar PV power plant is 279720m2 (approximately

69–70 acres).

Land use pattern of Chandigarh and selection of area Chandigarh covers an area of approximately 114 km2 (i.e.

28169.9 acres). In addition 25.42 km2 additional hilly

catchments area is declared as Wildlife Sanctuary. Hence

less than 0.25 percent area of Chandigarh is enough for the

solar PV based power plant of the capacity of 25 MW. The land

is very costly in Chandigarh therefore it is not possible to get a

separate piece of land in the city. The land use pattern of

Chandigarh is presented in Figure A9.7.

Page 160: Master plan to make Chandigarh a Solar City

144 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Figure A9.7 Land use pattern of Chandigarh

(Source: http://chandigarh.gov.in/knowchd_stat_ab07.asp)

It has been observed that the residential and commercial

sectors account the maximum area of the city. This sector covers

an area of 73.9 km2, followed by agriculture & water bodies

(11.36 km2), industrial (5.75 km2), public/semi-public (10.71

km2) and transportation (1.28 km2) and around 9.65% (11 km2)

is categorized as special area. The area of the municipal

Corporation is 79.74 sq. km out of 114 sq. km.

Land cost is always a major share associated with the solar

PV based power plant. In order to make the approach viable in

Chandigarh the land has been identified within the existing plan

of the city. Chandigarh has 3245 hectares (8018.5 acres) under

forest and most of it is hilly.

Typically, each sector measures 800 meters by 1200

meters, covering 250 acres area. Out of a total area of 20,000

acres acquired for the of city development about 2000 acres are

meant for development of parks/gardens.

Hence taking in to account the financial viability it is not

possible to install a single unit of solar PV based power plant of

the capacity of 25 MW in the city. Therefore the segmented

approach of the power plant has been adopted and it is decided

that the size might be vary from 1 to 5 MW. The rooftop has not

been considered because Govt. of India (MNRE) is planning to

develop separate policy for roof top based solar PV power

plants; which might be grid-connected or off grid.

64.82%

5.04%

8.92%

1.12%

9.96%

9.65%

Residential/commercial Industrial Public/Semi-public

Transportation Agricultural & water bodies Special area*

Total area: 114 sq. km.

Page 161: Master plan to make Chandigarh a Solar City

145 Annexures

T E R I Report No. 2008RT03

Identified and potential areas The areas identified for solar PV based power plants of

different capacity in the city along with recommended

size/capacities of solar PV power plants are presented in Table

A9.2. Only large gardens/parks (area > 18 acres) have been

considered for the analysis. The sizing and estimation of area

and annual cost has been carried out by using the best available

solar cell of the efficiency of 14.3%.

Table A9.2 Action plan of solar PV based power plant of the capacity of 25 MW in Chandigarh

(selection of the locations)

S. No.

Location

Sector

Total area (acres)

Recommended size/capacity

(MW)

Area required (acres)

Percentage of total area (%)

1. Botanical Garden-1 Sector -1 88.0 2.0 5.60 6.4

2. Botanical Garden-2 Sector -14 117.0 2.0 5.60 4.8

3. Bougainvillea Garden Sector -3 20.0 1.0 2.8 14.0

4. Bamboo Valley Sector -23 22.7 1.0 2.8 12.3

5. Fitness Trail & Flower Garden

Sector -10 90.0 2.0 5.60 6.2

6. Mango Garden Sector -1 100.0 2.0 5.60 5.6

7. Landfill area Sector -38 45.0 5.0 14.00 31.1

8. Leisure Valley Sector -10 70.0 2.0 5.60 8.0

9. Rajendra Park Sector -1 400.0 5.0 14.00 3.5

10. Zakir Rose Garden Sector-16 42.07 1.0 2.80 6.7

11. Shanti Kunj Sector 16 18.0 1.0 2.80 15.6

12. Shivalik Garden Manimajara 18.0 1.0 2.80 15.6

Total 1030.8

acres

25 MW

69.98

acres

6.8%

The minimum size (i.e. capacity) of solar PV based taken as 1

MW. The GBI (Generation Based Incentives) scheme of

Ministry of New and Renewable Energy is applicable only for

the solar power plants above the capacity of 1 MW. The power

plant of the capacity of 1 MW can be segmented in small plants

of minimum 250 kW capacity but they should at one location.

Hence small gardens and parks are not considered in the action

plan.

Above areas/ locations have been identified based on the

area availability and grid feasibility for power evacuation. It has

been observed that only 6.8 % of the area of these

gardens/parks is enough to install solar PV based power plant

of the capacity of 25 MW. For the landfill site maximum area is

taken into account for solar PV which was indicated by the

authorities. In other locations 7-15 percent of the total area is

targeted for different capacities.

Municipal Corporation of Chandigarh is managing about

1900 small and big Parks in the city. In addition some potential

location are also available in the city where solar PV based

power plants of different capacities might be installed are

outlined in Table A9.3.

Page 162: Master plan to make Chandigarh a Solar City

146 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Table A9.3 Potential locations where solar PV based power plants can be installed

S. No.

Location

Sector

Total area

(acres)

1. Bamboo Valley Sector -23 22.7

2. Bougainvillea Garden Sector -3 20.0

3. Bulbous Garden Sector -23 3.6

4. Cactus Garden Near Panchkula 7.0

5. Children‟s Traffic Park Sector -23 12.5

6. Dream Park Sector-23 -NA-

7. Forest area at Brick kiln Manimajra 13.7

8. Garden of Annuals Sector -44 5.50

9. Garden of Fragrance Sector -36 14.3

10. Garden of Shrubs Sector -46 6.61

11. Hibiscus Garden Sector -36 8.0

12. Jawahar Park Sector-9 -NA-

13. Lake Reserve Forests 260.9

14. Mini Rose Garden Sector -24 3.5

15. Moonlit Park Sector-22 -NA-

16. Patiali-ki-Rao forests 336.5

17. Pink Cassia Garden Sector -29 6.0

18. Poinsettia & Lxora Garden Sector -11 5.73

19. Rock Garden Sector - 1 12.0

20. Smriti Upvan Sector- 1 -NA-

21. Sukhna Choe Reserve Forests 956.6

22. Sukhna Wildlife Sanctuary 6451.9

23. Terrace Garden Sector 33 10.0

24. Topiary Garden Sector -35 6.0

Apart from this the roof areas of car parking lots in the central

markets of all sectors can effectively used for this application.

The parking side of Sukhna Lake, rock garden, railway station is

also a very good area where a solar PV based power plant can be

installed.

Architectural design strategy: Solar Tree TERI has proposed the concept of „solar trees‟ for those

locations where installation of solar PV based power plant on

ground is difficult. The preliminary designing has been carried

out using RETScreen and ECOTECH softwares. Figure A9.8

presents the basic approach of solar tree.

A system of “Solar Trees” raises the arrays to the level of

the height of existing mature tree is proposed solar “trees” are

omitted where natural existing valuable trees are preserved.

Page 163: Master plan to make Chandigarh a Solar City

147 Annexures

T E R I Report No. 2008RT03

Figure A9.8 Schematic of „Solar tree‟

Each “Solar Tree” will be around 12 m in height so as to clear

all full grown natural trees and will have a platform of about 12

m x 12 m size on the on the top and this platform will have

octagonal shape. This platform will be used for mounting solar

modules. Figure A9.9 shows plan of four solar trees together.

These trees would be the basic building blocks of the proposed

solar PV system.

Figure A9.9 “Solar Tree” arrangement, plan showing four solar trees together

Page 164: Master plan to make Chandigarh a Solar City

148 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Module orientation and mounting Solar modules orientation and mounting is most important

aspect of any solar system. It is important to have module free

from shadow during the most hours of the day to maximise the

output.

In the proposed design, the modules will be mounted on

“Solar Tree” in the horizontal plane facing south direction with

an inclination of 280 to the horizontal. The inclination is equal

to the latitude of Chandigarh (300 N). This orientation

optimises the solar energy falling on the surface of the modules.

The distance between the rows of modules would be kept in

such a fashion that the modules would not cast shadows on each

other on Dec 23rd from 10 AM to 3 PM. It may be noted that the

sun‟s elevation in the sky is lowest on Dec 23rd and hence it is

selected as the design date.

The Figure A9.10 presents show the simulated position of

sun in the sky and shadow of modules at 9 AM and 10 Am on

Dec 23rd.

Figure A9.10 PV panels on a PV tree

January – December, no shadow on adjacent PV panels, from 10:00–15:00 hrs

January – November, no shadow on adjacent PV panels from 10:00–16:00 hrs

Power evacuation The past decade has seen the emergence of solar PV as the

World‟s most dynamically growing renewable energy sources.

Up till now the solar PV have been used for off grid areas where

the extension of grid is not possible. Recently the advancement

Page 165: Master plan to make Chandigarh a Solar City

149 Annexures

T E R I Report No. 2008RT03

of control systems and regulatory support the focus is shifting

from standalone mode to grid-connected system.

Power evacuation facility is essential for grid connected solar

PV based power plants. It has been noticed that the Chandigarh

city is surrounded by 66 KVA transmission line, while internal

parts of the city have 33 KVA line. The resedencial supply is

through 11 KVA transmission line. Hence grid connectivity is

not a barrier towards installing solar PV based plants inside the

city. Figure A9.11 presents the grid map of Chandigarh city. The

major issues associated with grid connected solar PV system

power evacuation are briefly addressed as following.

Figure A9.11 Grid map of Chandigarh city

Solar PV system Interconnection

Grid interactive PV system has the advantage of more effective

utilisation of generated power. However the technology

requirement of both from the utility and PV system side need to

be safeguarded for effective utilisation of system. Safety and

reliability of system could be accomplished through Power

conditioning unit (inverter) that may include maximum power

point tracker, and protection equipment.

Page 166: Master plan to make Chandigarh a Solar City

150 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Power conditioning equipment The Power Conditioning Unit (PCU) used for grid interactive is

to directly convert the input power to A.C, single phase or three

phases depending on the kind of inverter used. It doesn‟t

require the charge controller but it requires a facility to regulate

the amount of power extracted from the array (Maximum power

point controller). Maximum Power Point Tracking Control

system is capable of constantly obtaining the maximum output

according to the quantity of available solar radiation. The MPPT

feeds the maximum DC Power generated from PV array to the

Inverters.

Inverters are used for converting Direct current to

Alternating current. Inverter output depends on the inverter

power, for small power of some 100 W the voltage is 12 or 24 V

or even more for higher powers are required. According to

working principle different kind of inverters such as central,

string or module inverters are used in large applications. The

most common configuration, however used in PV system are

“Master slave” criteria in which the succeeding inverters are

switching On only when enough solar radiation is available or in

case main inverter is malfunction.

Isolation between AC and DC (High Tension transformer) It is necessary to prevent the direct current flowing from PV

system to the utility network. Installing an isolating transformer

at the output side of inverter that isolates the DC circuit and the

AC circuit can do this. However in this case, a transformer of

commercial voltage and frequency increases the size and weight

of entire inverter system. In addition, inverters of transformer

less system are commercially available in which a circuit for

detecting DC component superimposed on AC circuit and a

grounding detection circuit in the DC circuit is required.

However, size and weight can be minimized because the

transformer is omitted from the PV system.

Inverter start-up and stop operation for normal operation To start up the operation of grid connected photovoltaic system,

voltage and frequency of the utility‟s network must be with in

the specified range and solar PV system must generate power in

the presence of solar radiation. As a result, most of the inverters

start operation after checking out the frequency condition with

in the operational range at the utility‟s network, monitoring the

DC output from PV systems and then performing the check and

waiting for few seconds to several minutes. In addition most of

the commercially available inverters stop operation

immediately if the voltage condition at the utility network

deviates from operational range.

Page 167: Master plan to make Chandigarh a Solar City

151 Annexures

T E R I Report No. 2008RT03

Financial details It is widely accepted that because of high upfront capital cost,

per unit cost of power generation from solar PV is higher than

not only conventional sources of energy but some of the

renewable energy sources based electricity as well. Although the

cost of solar PV has reduced by the factor of ten in last one and a

half decade or so it is still an expensive technology. This high

upfront cost coupled with comparatively low operating

efficiencies becomes the major barrier in wide scale

implementation of the technology especially in developing

countries like India.

Solar system cost The solar system costs are dependent on two major parameters

Module prices

Inverter prices and

Module area required which in turn decides the quantity and

costs of mounting structures, cabling etc which are directly

proportional to the number of modules and their

efficiencies. Thus although it is advisable to have high

efficiency modules to reduce the balance of system (system

components other than module) costs, their availability and

prices are also crucial. Typically module costs are about 60

to 70% of the system costs.

In spite of high costs the current market for solar

photovoltaic stands at over 11 billion dollar and has resulted

in the decrease of the cost per peak watt reduced to Rs 150

to 200 in 2007 from Rs 3500 to 4000 in1980‟s.

Conventional solar PV power plant Costs of solar PV systems in India has been following

international trends in past few decades and with the recent

announcement of commissioning of large scale manufacturing

plants in India, it is anticipated that cost of solar PV will come

down significantly over the years due to economies of scale.

Despite the fact solar PV cost is reducing every year, solar PV

is not economically comparable to other sources of power

generation sources. The estimated cost of power generation

from solar PV in India is in the range of Rs 15-20/kWh

depending on size of the system.

Solar PV power plant based on „Solar Trees‟ Considering the current market prices for imported modules of

185 Wp capacity from Germany which are in the range of Rs

250 to 300 per Wp, proposed system having 3.8 MWp capacity

would costs around Rs 147 crores (Rs 1470 million). The cost of

solar system of 1 MWp capacity would be around Rs 29 crores.

Page 168: Master plan to make Chandigarh a Solar City

152 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Highlights: Generation based incentives scheme of MNRE MNRE is actively promoting the establishment of grid

connected solar power plants of large capacity (megawatt scale)

by providing generation based incentives for the first time. The

purpose is to develop and demonstrate the technical

performance of grid-interactive solar power generation so as to

bring down the cost of the grid connected solar systems. The

silent features of the incentive schemes are as following;

a. MNRE may provide, via IREDA (Indian Renewable Energy

Development Agency), a generation based incentive of

maximum Rs 12 per kWh to the eligible projects, which are

successfully commissioned by 31st December 2009. This

will be done after taking into account the power purchase

rate (per kWh) provided by the SERC (State Electricity

Regulatory Commission) or a utility for that project.

b. Any project that is commissioned beyond the above date

would be eligible for a maximum with a 5% reduction and

ceiling of Rs 11.40 per kWh.

c. Further the incentive will continue to decrease, as and when

the utility signs a PPA (power purchase agreement) for

power purchase at a higher level. The proposal annual

escalations agreed with the utility, as in force, should be

reflected in the PPA.

d. The incentive approved for a project may be available for a

maximum period of 10 years from the date of approval and

regular power generation from the project. This will be

subject to the condition that the utility under consideration

continuous to purchase power from the grid-interactive

power plant.

Page 169: Master plan to make Chandigarh a Solar City

153 Annexures

T E R I Report No. 2008RT03

Annexure 10: Budget estimates for implementation of different

activities to make Chandigarh as a Solar City

Page 170: Master plan to make Chandigarh a Solar City

154 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Page 171: Master plan to make Chandigarh a Solar City

155 Annexures

T E R I Report No. 2008RT03

Budget for solar city Chandigarh Project

Sector (s) Proposed measures

Targets Role of the CREST/Chandigarh Administration

Budget for CREST (Rs)

2009-10 20010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Residential

Solar water heating systems

824500 lit per day capcity systems in 2009-10. Increase of 5% in installed capacity every year

1.Promotion and awareness creation 2.Providing subsidy support in initial phase (first 100000 lit capacity systems

13367500 13367500 13367500 13367500 25735000 25735000 25735000 25735000 25735000 50470000

Promote use of efficient LPG stoves and efficient cooking devices such as microwaves

Achieve 10% reduction in projected LPG consumption as compared to BAU

Awareness creation 500000 500000 500000 500000 500000 500000

Promote use of alternate lighting systems such as SPV systems in villages to reduce kerosene consumption

Targets can be decided by CREST after survey of requirements

Awareness creation. Subsidy for five years for say 1500 Solar Home Systems

1500000 1500000 1500000 1500000 1500000

Promote use of roof top solar PV systems

10 MWp capacity systems by 2018

Subsidy support for first 10 MWp capacity systems of upto 5kWp capacity each

Page 172: Master plan to make Chandigarh a Solar City

156 Master plan to make Chandigarh a Solar City

T E R I Report No. 2008RT03

Promote energy conservation through promotion of energy efficient devices (CFL, air conditioners, microwaves, washing machines, TV, etc)

Increased use of these devices in the city

Awareness creation, specific support schemes for CFL and Air conditioners?

1500000 1500000 1500000 1500000 1500000

Commercial/ industrial Including municipal services

Promotion of energy efficiency through awareness creation

achieve 10% share of energy efficient devices in the city

Promotional schemes and awareness creation

2500000 2500000 2500000 2500000 2500000

Replacement of existing ballasts by efficient ballasts in all street lights

100% replacement of ballasts

Investments/ financial support to CMC (Chandigarh Municipal Corporation)

36666667 36666667 36666667

Replacement of booster water pumps in drinking water schemes with energy efficient pumps

Replacement of 250 nos of pumps of each 10 HP capacity

Investments/ financial support to CMC

1750000 1925000 2117500 2329250 2562175

Promotion of solar water heating systems in industries, hotels, hostels etc

100000 lit per day capacity systems in three years

Subsidy and awareness creation , providing soft loans / reduction in electricity bills/ cess for others

562500 562500 562500 562500

Promotion of energy efficient green buildings

At least 50% of the new building are certified under GRIHA or similar rating systems

Implementation of Schemes through facilitation and cost sharing schemes

2500000 2500000 2500000 2500000 2500000

Page 173: Master plan to make Chandigarh a Solar City

157 Annexures

T E R I Report No. 2008RT03

Promotion of roof top systems in commercial /government, institutional and industrial buildings

Total 10 MWp capacity solar systems

Financial support to the utility for purchase of power at higher rate/ preferential tariff

100000000 100000000 100000000 100000000 100000000 100000000 100000000 100000000 100000000 100000000

Power generation

Solar PV power plant

25 MWp power plants in phased manner

Subsidy support / Capital investments / preferential tariff / Soft loans

100000000 200000000 200000000 300000000 300000000 400000000 400000000 400000000 200000000

Awareness creation

Establishment of 'Chandigarh Solar City Cell'

To set up Solar City Cell to develop, implement and monitor various schemes, to coordinate the development of Chandigarh as Model Solar City

Funding , creation and establishment of the cell and monitor its working

2500000 2500000 2500000 2500000 2500000 2500000 2500000 2500000 2500000

Awarenes creation fo all schemes, development of solar city park and exhibitions

Awareness creation

Develop and fund awareness creation/promotional schemes (included in the above)