    ID Unique_ID Task_Name Duration

    1 1 20 MW Solar PV Plant 226 days

    2 2 Start of Project 0 days

    3 3 System Design 64 days

    4 151 Pre Engineering/ Inputs 27 days

    5 152 Fault level/Equipment details / Civil and structure spec. 0 days6 153 DBR Approval, Site investigation report, Plot boundary 0 days

    7 154 Survey data from site 0 days

    8 149 Clearance for Modules and Inverters 0 days

    9 150 Soil Investigation report 0 days

    10 147 Electrical Soil resistivity report 0 days

    11 4 Design Clearance for Procurement 10 days

    12 5 BOQ for Manufacturing items 10 days

    13 6 BOQ for Procurement (Bought out items) 10 days

    14 8 Submission of drawings for Approval 57 days

    15 200 Design Basis Report 10 days

    16 201 Overall Layout 10 days

    17 202 Plot Marking & Grading plan 7 days

    18 203 DC single line diagram 5 days

    19 2347 Foundation stub drgs 5 days

    20 204 Structure design and Proto 10 days

    21 205 Structure drawings for mfg 5 days

    22 206 33 kV Power Evacuation Single line diagram 5 days

    23 314 Electrical Equipment Layout 7 days

    24 207 DC Cable trench for solar field 5 days

    25 208 Product Specification ( Module / Inverter/ Monitoring Box) 7 days

    26 209 DC electrical connection diagram 5 days27 210 Cabling 5 days

    28 327 Earthing 3 days

    29 2348 Compact Substation drgs 5 days

    30 2349 Invertor room drgs 7 days

    31 2350 Control room drgs 10 days

    32 2353 Road and drainage system 5 days

    33 2352 Fencing 5 days

    34 2392 Approval of drawings by Client 57 days

    35 2393 Design Basis Report 7 days

    36 2394 Overall Layout 7 days

    37 2395 Plot Marking & Grading plan 7 days

    38 2396 DC single line diagram 5 days

    39 2397 Foundation stub drgs 5 days

    40 2398 Structure design and Proto 7 days

    41 2399 Structure drawings for mfg 7 days

    42 2400 33 kV Power Evacuation Single line diagram 5 days

    43 2401 Electrical Equipment Layout 5 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    2/310

    44 2402 DC Cable trench for solar field 5 days

    45 2403 Product Specification ( Module / Inverter/ Monitoring Box) 7 days

    46 2404 DC electrical connection diagram 5 days

    47 2405 Solar field Earthing 5 days

    48 2406 Cabling and Earthing 5 days

    49 2407 Compact Substation drgs 7 days50 2412 Invertor room drgs 5 days

    51 2409 Control room drgs 5 days

    52 2410 Road and drainage system 5 days

    53 2411 Fencing 5 days

    54 7256 Supply Chain Management 137 days

    55 7257 Placement of Purchase Order 20 days

    56 7258 Stubs 15 days

    57 7259 DC Package 20 days

    58 7260 Solar PV Modules 20 days

    59 7261 Inverter 20 days

    60 7262 Combiner plug/ Pre-Combiner box 15 days

    61 7263 String Combiner box 15 days

    62 7264 MC4/MC3 Connectors 15 days

    63 7265 Montioring System 15 days

    64 7266 DC Cables (Solar Grade) 15 days

    65 7267 DWC Conduits 15 days

    66 7268 Al Middle Clamps 10 days

    67 7269 Al End Clamps 10 days

    68 7270 EPDM Rubber 10 days

    69 7271 AC Package 15 days

    70 7272 HT Panel 15 days71 7273 Inverter duty transformer & Auxilliary Transformer 15 days

    72 7274 AC Cables 15 days

    73 7275 Communication cable 15 days

    74 7276 Battery & Battery Charger 15 days

    75 7277 ACDB & DCDB (LT Panel) 15 days

    76 7278 Tariff Metering Panel 15 days

    77 7279 Load Break Switch 15 days

    78 7280 Compact Sub Station 15 days

    79 7281 Civil Items 7 days

    80 7282 Stubs (Augered) 7 days

    81 7283 Stubs (Pile) 7 days

    82 7284 Structures for Module mounting 7 days

    83 7285 MNRE Clearance and Readiness of Road Permits 100 days

    84 7286 MNRE Clearance _ LOT 1 39 days

    85 7287 All Developer and Client documents readiness by Client 10 days

    86 7288 Collection of Documents and Preparation of Files by L&T 7 days

    87 7289 Tentative Submission of ED/CD files for Exemption to RREC 5 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    3/310

    88 7290 Recommendation from RREC to MNRE 7 days

    89 7291 Exemption certificate issued by MNRE 10 days

    90 7292 MNRE Clearance _ Lot 2 55 days

    91 7293 All Developer and Client documents readiness by Client 15 days

    92 7294 Collection of Documents and Preparation of Files by L&T 10 days

    93 7295 Tentative Submission of ED/CD files for Exemption to RREC 5 days94 7296 Recommendation from RREC to MNRE 10 days

    95 7297 Exemption certificate issued by MNRE 15 days

    96 7298 MNRE Clearance _ Lot 3 55 days

    97 7299 All Developer and Client documents readiness by Client 15 days

    98 7300 Collection of Documents and Preparation of Files by L & T 10 days

    99 7301 Tentative Submission of ED/CD files for Exemption to RREC 5 days

    100 7302 Recommendation from RREC to MNRE 10 days

    101 7303 Exemption certificate issued by MNRE 15 days

    102 7304 Material Readiness at suppliers Place 67 days

    103 7305 Material readiness _ Lot 1 46 days

    104 7306 DC Package 46 days

    105 7307 Solar PV Modules 0 days

    106 7308 Inverter 0 days

    107 7309 Combiner plug/ Pre-Combiner box 0 days

    108 7310 String Combiner box 0 days

    109 7311 MC4/MC3 Connectors 0 days

    110 7312 Montioring System 0 days

    111 7313 DC Cables (Solar Grade) 0 days

    112 7314 DWC Conduits 0 days

    113 7315 Al Middle Clamps 0 days

    114 7316 Al End Clamps 0 days115 7317 EPDM Rubber 0 days

    116 7318 AC Package 35 days

    117 7319 HT Panel 0 days

    118 7320 Inverter duty transformer & Auxilliary Transformer 0 days

    119 7321 AC Cables 0 days

    120 7322 Communication cable 0 days

    121 7323 Battery & Battery Charger 0 days

    122 7324 ACDB & DCDB (LT Panel) 0 days

    123 7325 Load Break Switch 0 days

    124 7326 Compact Sub Station 0 days

    125 7327 Civil Items 0 days

    126 7328 Stubs (Augered) 0 days

    127 7329 Stubs (Pile) 0 days

    128 7330 Structures for Module mounting 0 days

    129 7331 Material readiness _ Lot 2 39 days

    130 7332 DC Package 39 days

    131 7333 Solar PV Modules 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    4/310

    132 7334 Inverter 0 days

    133 7335 Combiner plug/ Pre-Combiner box 0 days

    134 7336 String Combiner box 0 days

    135 7337 MC4/MC3 Connectors 0 days

    136 7338 Montioring System 0 days

    137 7339 DC Cables (Solar Grade) 0 days138 7340 DWC Conduits 0 days

    139 7341 Al Middle Clamps 0 days

    140 7342 Al End Clamps 0 days

    141 7343 EPDM Rubber 0 days

    142 7344 AC Package 38 days

    143 7345 HT Panel 0 days

    144 7346 Inverter duty transformer & Auxilliary Transformer 0 days

    145 7347 AC Cables 0 days

    146 7348 Communication cable 0 days

    147 7349 Battery & Battery Charger 0 days

    148 7350 ACDB & DCDB (LT Panel) 0 days

    149 7351 Load Break Switch 0 days

    150 7352 Compact sub station 0 days

    151 7353 Civil Items 0 days

    152 7354 Stubs (Augered) 0 days

    153 7355 Stubs (Pile) 0 days

    154 7356 Structures for Module mounting 0 days

    155 7357 Material readiness _ Lot 3 39 days

    156 7358 DC Package 32 days

    157 7359 Solar PV Modules 0 days

    158 7360 Inverter 0 days159 7361 Combiner plug/ Pre-Combiner box 0 days

    160 7362 String Combiner box 0 days

    161 7363 MC4/MC3 Connectors 0 days

    162 7364 Montioring System 0 days

    163 7365 DC Cables (Solar Grade) 0 days

    164 7366 DWC Conduits 0 days

    165 7367 Al Middle Clamps 0 days

    166 7368 Al End Clamps 0 days

    167 7369 EPDM Rubber 0 days

    168 7370 AC Package 38 days

    169 7371 HT Panel 0 days

    170 7372 Inverter duty transformer & Auxilliary Transformer 0 days

    171 7373 AC Cables 0 days

    172 7374 Communication cable 0 days

    173 7375 Battery & Battery Charger 0 days

    174 7376 ACDB & DCDB (LT Panel) 0 days

    175 7377 Load Break Switch 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    5/310

    176 7378 Compact Sub Station 0 days

    177 7379 Civil Items 0 days

    178 7380 Stubs (Augered) 0 days

    179 7381 Stubs (Pile) 0 days

    180 7382 Structures for Module mounting 0 days

    181 7383 Material readiness _ Lot 4 39 days182 7384 DC Package 30 days

    183 7385 Solar PV Modules 0 days

    184 7386 Inverter 0 days

    185 7387 Combiner plug/ Pre-Combiner box 0 days

    186 7388 String Combiner box 0 days

    187 7389 MC4/MC3 Connectors 0 days

    188 7390 Montioring System 0 days

    189 7391 DC Cables (Solar Grade) 0 days

    190 7392 DWC Conduits 0 days

    191 7393 Al Middle Clamps 0 days

    192 7394 Al End Clamps 0 days

    193 7395 EPDM Rubber 0 days

    194 7396 AC Package 38 days

    195 7397 HT Panel 0 days

    196 7398 Inverter duty transformer & Auxilliary Transformer 0 days

    197 7399 AC Cables 0 days

    198 7400 Communication cable 0 days

    199 7401 Battery & Battery Charger 0 days

    200 7402 ACDB & DCDB (LT Panel) 0 days

    201 7403 Load Break Switch 0 days

    202 7404 Compact Sub Station 0 days203 7405 Civil Items 0 days

    204 7406 Stubs (Augered) 0 days

    205 7407 Stubs (Pile) 0 days

    206 7408 Structures for Module mounting 0 days

    207 7409 Material readiness _ Lot 5 39 days

    208 7410 DC Package 33 days

    209 7411 Solar PV Modules 0 days

    210 7412 Inverter 0 days

    211 7413 Combiner plug/ Pre-Combiner box 0 days

    212 7414 String Combiner box 0 days

    213 7415 MC4/MC3 Connectors 0 days

    214 7416 Montioring System 0 days

    215 7417 DC Cables (Solar Grade) 0 days

    216 7418 DWC Conduits 0 days

    217 7419 Al Middle Clamps 0 days

    218 7420 Al End Clamps 0 days

    219 7421 EPDM Rubber 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    6/310

    220 7422 AC Package 38 days

    221 7423 HT Panel 0 days

    222 7424 Inverter duty transformer & Auxilliary Transformer 0 days

    223 7425 AC Cables 0 days

    224 7426 Communication cable 0 days

    225 7427 Battery & Battery Charger 0 days226 7428 ACDB & DCDB (LT Panel) 0 days

    227 7429 Load Break Switch 0 days

    228 7430 Compact Sub Station 0 days

    229 7431 Civil Items 0 days

    230 7432 Stubs (Augered) 0 days

    231 7433 Stubs (Pile) 0 days

    232 7434 Structures for Module mounting 0 days

    233 7435 Material available at Site 73 days

    234 7436 Material at site _ Lot 1 _ Delivery 1 46 days

    235 7437 DC Package 46 days

    236 7438 Solar PV Modules 0 days

    237 7439 Inverter 0 days

    238 7440 Combiner plug/ Pre-Combiner box 0 days

    239 7441 String Combiner box 0 days

    240 7442 MC4/MC3 Connectors 0 days

    241 7443 Montioring System 0 days

    242 7444 DC Cables (Solar Grade) 0 days

    243 7445 DWC Conduits 0 days

    244 7446 Al Middle Clamps 0 days

    245 7447 Al End Clamps 0 days

    246 7448 EPDM Rubber 0 days247 7449 AC Package 35 days

    248 7450 HT Panel 0 days

    249 7451 Inverter duty transformer & Auxilliary Transformer 0 days

    250 7452 AC Cables 0 days

    251 7453 Communication cable 0 days

    252 7454 Battery & Battery Charger 0 days

    253 7455 ACDB & DCDB (LT Panel) 0 days

    254 7456 Load Break Switch 0 days

    255 7457 Compact Sub Station 0 days

    256 7458 Civil Items 0 days

    257 7459 Stubs (Augered) 0 days

    258 7460 Stubs (Pile) 0 days

    259 7461 Structures for Module mounting 0 days

    260 7462 Material at site _ Lot 1 _ Delivery 2 46 days

    261 7463 DC Package 46 days

    262 7464 Solar PV Modules 0 days

    263 7465 Inverter 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    7/310

    264 7466 Combiner plug/ Pre-Combiner box 0 days

    265 7467 String Combiner box 0 days

    266 7468 MC4/MC3 Connectors 0 days

    267 7469 Montioring System 0 days

    268 7470 DC Cables (Solar Grade) 0 days

    269 7471 DWC Conduits 0 days270 7472 Al Middle Clamps 0 days

    271 7473 Al End Clamps 0 days

    272 7474 EPDM Rubber 0 days

    273 7475 AC Package 35 days

    274 7476 HT Panel 0 days

    275 7477 Inverter duty transformer & Auxilliary Transformer 0 days

    276 7478 AC Cables 0 days

    277 7479 Communication cable 0 days

    278 7480 Battery & Battery Charger 0 days

    279 7481 ACDB & DCDB (LT Panel) 0 days

    280 7482 Load Break Switch 0 days

    281 7483 Compact Sub Station 0 days

    282 7484 Civil Items 0 days

    283 7485 Stubs (Augered) 0 days

    284 7486 Stubs (Pile) 0 days

    285 7487 Structures for Module mounting 0 days

    286 7488 Material at site _ Lot 2 _ Delivery 1 39 days

    287 7489 DC Package 39 days

    288 7490 Solar PV Modules 0 days

    289 7491 Inverter 0 days

    290 7492 Combiner plug/ Pre-Combiner box 0 days291 7493 String Combiner box 0 days

    292 7494 MC4/MC3 Connectors 0 days

    293 7495 Montioring System 0 days

    294 7496 DC Cables (Solar Grade) 0 days

    295 7497 DWC Conduits 0 days

    296 7498 Al Middle Clamps 0 days

    297 7499 Al End Clamps 0 days

    298 7500 EPDM Rubber 0 days

    299 7501 AC Package 38 days

    300 7502 HT Panel 0 days

    301 7503 Inverter duty transformer & Auxilliary Transformer 0 days

    302 7504 AC Cables 0 days

    303 7505 Communication cable 0 days

    304 7506 Battery & Battery Charger 0 days

    305 7507 ACDB & DCDB (LT Panel) 0 days

    306 7508 Load Break Switch 0 days

    307 7509 Compact Sub Station 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    8/310

    308 7510 Civil Items 0 days

    309 7511 Stubs (Augered) 0 days

    310 7512 Stubs (Pile) 0 days

    311 7513 Structures for Module mounting 0 days

    312 7514 Material at site _ Lot 2 _ Delivery 2 39 days

    313 7515 DC Package 39 days314 7516 Solar PV Modules 0 days

    315 7517 Inverter 0 days

    316 7518 Combiner plug/ Pre-Combiner box 0 days

    317 7519 String Combiner box 0 days

    318 7520 MC4/MC3 Connectors 0 days

    319 7521 Montioring System 0 days

    320 7522 DC Cables (Solar Grade) 0 days

    321 7523 DWC Conduits 0 days

    322 7524 Al Middle Clamps 0 days

    323 7525 Al End Clamps 0 days

    324 7526 EPDM Rubber 0 days

    325 7527 AC Package 38 days

    326 7528 HT Panel 0 days

    327 7529 Inverter duty transformer & Auxilliary Transformer 0 days

    328 7530 AC Cables 0 days

    329 7531 Communication cable 0 days

    330 7532 Battery & Battery Charger 0 days

    331 7533 ACDB & DCDB (LT Panel) 0 days

    332 7534 Load Break Switch 0 days

    333 7535 Compact Sub Station 0 days

    334 7536 Civil Items 0 days335 7537 Stubs (Augered) 0 days

    336 7538 Stubs (Pile) 0 days

    337 7539 Structures for Module mounting 0 days

    338 7540 Material at site _ Lot 3 _ Delivery 1 39 days

    339 7541 DC Package 32 days

    340 7542 Solar PV Modules 0 days

    341 7543 Inverter 0 days

    342 7544 Combiner plug/ Pre-Combiner box 0 days

    343 7545 String Combiner box 0 days

    344 7546 MC4/MC3 Connectors 0 days

    345 7547 Montioring System 0 days

    346 7548 DC Cables (Solar Grade) 0 days

    347 7549 DWC Conduits 0 days

    348 7550 Al Middle Clamps 0 days

    349 7551 Al End Clamps 0 days

    350 7552 EPDM Rubber 0 days

    351 7553 AC Package 38 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    9/310

    352 7554 HT Panel 0 days

    353 7555 Inverter duty transformer & Auxilliary Transformer 0 days

    354 7556 AC Cables 0 days

    355 7557 Communication cable 0 days

    356 7558 Battery & Battery Charger 0 days

    357 7559 ACDB & DCDB (LT Panel) 0 days358 7560 Load Break Switch 0 days

    359 7561 Compact Sub Station 0 days

    360 7562 Civil Items 0 days

    361 7563 Stubs (Augered) 0 days

    362 7564 Stubs (Pile) 0 days

    363 7565 Structures for Module mounting 0 days

    364 7566 Material at site _ Lot 3 _ Delivery 2 39 days

    365 7567 DC Package 32 days

    366 7568 Solar PV Modules 0 days

    367 7569 Inverter 0 days

    368 7570 Combiner plug/ Pre-Combiner box 0 days

    369 7571 String Combiner box 0 days

    370 7572 MC4/MC3 Connectors 0 days

    371 7573 Montioring System 0 days

    372 7574 DC Cables (Solar Grade) 0 days

    373 7575 DWC Conduits 0 days

    374 7576 Al Middle Clamps 0 days

    375 7577 Al End Clamps 0 days

    376 7578 EPDM Rubber 0 days

    377 7579 AC Package 38 days

    378 7580 HT Panel 0 days379 7581 Inverter duty transformer & Auxilliary Transformer 0 days

    380 7582 AC Cables 0 days

    381 7583 Communication cable 0 days

    382 7584 Battery & Battery Charger 0 days

    383 7585 ACDB & DCDB (LT Panel) 0 days

    384 7586 Load Break Switch 0 days

    385 7587 Compact Sub Station 0 days

    386 7588 Civil Items 0 days

    387 7589 Stubs (Augered) 0 days

    388 7590 Stubs (Pile) 0 days

    389 7591 Structures for Module mounting 0 days

    390 7592 Material at site _ Lot 4 _ Delivery 1 39 days

    391 7593 DC Package 30 days

    392 7594 Solar PV Modules 0 days

    393 7595 Inverter 0 days

    394 7596 Combiner plug/ Pre-Combiner box 0 days

    395 7597 String Combiner box 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    10/310

    396 7598 MC4/MC3 Connectors 0 days

    397 7599 Montioring System 0 days

    398 7600 DC Cables (Solar Grade) 0 days

    399 7601 DWC Conduits 0 days

    400 7602 Al Middle Clamps 0 days

    401 7603 Al End Clamps 0 days402 7604 EPDM Rubber 0 days

    403 7605 AC Package 38 days

    404 7606 HT Panel 0 days

    405 7607 Inverter duty transformer & Auxilliary Transformer 0 days

    406 7608 AC Cables 0 days

    407 7609 Communication cable 0 days

    408 7610 Battery & Battery Charger 0 days

    409 7611 ACDB & DCDB (LT Panel) 0 days

    410 7612 Load Break Switch 0 days

    411 7613 Compact Sub Station 0 days

    412 7614 Civil Items 0 days

    413 7615 Stubs (Augered) 0 days

    414 7616 Stubs (Pile) 0 days

    415 7617 Structures for Module mounting 0 days

    416 7618 Material at site _ Lot 4 _ Delivery 2 39 days

    417 7619 DC Package 30 days

    418 7620 Solar PV Modules 0 days

    419 7621 Inverter 0 days

    420 7622 Combiner plug/ Pre-Combiner box 0 days

    421 7623 String Combiner box 0 days

    422 7624 MC4/MC3 Connectors 0 days423 7625 Montioring System 0 days

    424 7626 DC Cables (Solar Grade) 0 days

    425 7627 DWC Conduits 0 days

    426 7628 Al Middle Clamps 0 days

    427 7629 Al End Clamps 0 days

    428 7630 EPDM Rubber 0 days

    429 7631 AC Package 38 days

    430 7632 HT Panel 0 days

    431 7633 Inverter duty transformer & Auxilliary Transformer 0 days

    432 7634 AC Cables 0 days

    433 7635 Communication cable 0 days

    434 7636 Battery & Battery Charger 0 days

    435 7637 ACDB & DCDB (LT Panel) 0 days

    436 7638 Load Break Switch 0 days

    437 7639 Compact Sub Station 0 days

    438 7640 Civil Items 0 days

    439 7641 Stubs (Augered) 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    11/310

    440 7642 Stubs (Pile) 0 days

    441 7643 Structures for Module mounting 0 days

    442 7644 Material at site _ Lot 5 _ Delivery 1 39 days

    443 7645 DC Package 33 days

    444 7646 Solar PV Modules 0 days

    445 7647 Inverter 0 days446 7648 Combiner plug/ Pre-Combiner box 0 days

    447 7649 String Combiner box 0 days

    448 7650 MC4/MC3 Connectors 0 days

    449 7651 Montioring System 0 days

    450 7652 DC Cables (Solar Grade) 0 days

    451 7653 DWC Conduits 0 days

    452 7654 Al Middle Clamps 0 days

    453 7655 Al End Clamps 0 days

    454 7656 EPDM Rubber 0 days

    455 7657 AC Package 38 days

    456 7658 HT Panel 0 days

    457 7659 Inverter duty transformer & Auxilliary Transformer 0 days

    458 7660 AC Cables 0 days

    459 7661 Communication cable 0 days

    460 7662 Battery & Battery Charger 0 days

    461 7663 ACDB & DCDB (LT Panel) 0 days

    462 7664 Load Break Switch 0 days

    463 7665 Compact Sub Station 0 days

    464 7666 Civil Items 0 days

    465 7667 Stubs (Augered) 0 days

    466 7668 Stubs (Pile) 0 days467 7669 Structures for Module mounting 0 days

    468 7670 Material at site _ Lot 5 _ Delivery 2 39 days

    469 7671 DC Package 33 days

    470 7672 Solar PV Modules 0 days

    471 7673 Inverter 0 days

    472 7674 Combiner plug/ Pre-Combiner box 0 days

    473 7675 String Combiner box 0 days

    474 7676 MC4/MC3 Connectors 0 days

    475 7677 Montioring System 0 days

    476 7678 DC Cables (Solar Grade) 0 days

    477 7679 DWC Conduits 0 days

    478 7680 Al Middle Clamps 0 days

    479 7681 Al End Clamps 0 days

    480 7682 EPDM Rubber 0 days

    481 7683 AC Package 38 days

    482 7684 HT Panel 0 days

    483 7685 Inverter duty transformer & Auxilliary Transformer 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    12/310

    484 7686 AC Cables 0 days

    485 7687 Communication cable 0 days

    486 7688 Battery & Battery Charger 0 days

    487 7689 ACDB & DCDB (LT Panel) 0 days

    488 7690 Load Break Switch 0 days

    489 7691 Compact Sub Station 0 days490 7692 Civil Items 0 days

    491 7693 Stubs (Augered) 0 days

    492 7694 Stubs (Pile) 0 days

    493 7695 Structures for Module mounting 0 days

    494 7696 Material at site _ Lot 5 _ Delivery 3 39 days

    495 7697 DC Package 33 days

    496 7698 Solar PV Modules 0 days

    497 7699 Inverter 0 days

    498 7700 Combiner plug/ Pre-Combiner box 0 days

    499 7701 String Combiner box 0 days

    500 7702 MC4/MC3 Connectors 0 days

    501 7703 Montioring System 0 days

    502 7704 DC Cables (Solar Grade) 0 days

    503 7705 DWC Conduits 0 days

    504 7706 Al Middle Clamps 0 days

    505 7707 Al End Clamps 0 days

    506 7708 EPDM Rubber 0 days

    507 7709 AC Package 38 days

    508 7710 HT Panel 0 days

    509 7711 Inverter duty transformer & Auxilliary Transformer 0 days

    510 7712 AC Cables 0 days511 7713 Communication cable 0 days

    512 7714 Battery & Battery Charger 0 days

    513 7715 ACDB & DCDB (LT Panel) 0 days

    514 7716 Load Break Switch 0 days

    515 7717 Compact Sub Station 0 days

    516 7718 Civil Items 0 days

    517 7719 Stubs (Augered) 0 days

    518 7720 Stubs (Pile) 0 days

    519 7721 Structures for Module mounting 0 days

    520 5861 Construction 143 days

    521 5862 General Civil Works 112 days

    522 5863 Leveling, clearing, cleaning of site 45 days

    523 5864 Roads and pathways 90 days

    524 5865 Drainage System 90 days

    525 5866 Fencing Work 75 days

    526 5867 Block 1 62 days

    527 5868 DC Side 38 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    13/310

    528 5869 Foundation of Structure 7 days

    529 5870 Structure Erection 12 days

    530 5871 Module Installation 20 days

    531 5872 DC Cabling 31 days

    532 5873 Excavation 7 days

    533 5874 Conduiting 7 days534 5875 Cable Pulling pits 7 days

    535 5876 Cabling 10 days

    536 5877 Earthing 7 days

    537 5878 Installation of Combiner plug/ Pre-Combiner box 5 days

    538 5879 Installation of String Combiner box 5 days

    539 5880 Inverter room building 36 days

    540 5881 Foundation 15 days

    541 5882 Excavation 2 days

    542 5883 Dewatering 4 days

    543 5884 Dressing 2 days

    544 5885 PCC 2 days

    545 5886 Column Marking 1 day

    546 5887 Reinforcement cutting for MAT 1 day

    547 5888 Placing of Mat reinforcement 1 day

    548 5889 Shuttering for Foundation 1 day

    549 5890 Rcc for Footing 2 days

    550 5891 Shoe Marking 1 day

    551 5892 Column reinforcement fixing 2 days

    552 5893 Column Box & Bolt Fixing 2 days

    553 5894 Column RCC upto Plinth Beam 1 day

    554 5895 Curing for columns 4 days555 5896 Backfilling for foundation 3 days

    556 5897 Plinth beam 15 days

    557 5898 Plinth Beam Excavation 1 day

    558 5899 Plinth Beam Pcc 2 days

    559 5900 Reinforcement cutting 1 day

    560 5901 Plinth Beam Reinforcement placing 1 day

    561 5902 Plinth Beam Shuttering 1 day

    562 5903 Plinth beam Concreting 1 day

    563 5904 Plinth beam curing 4 days

    564 5905 Super structure 13 days

    565 5906 Brick work upto FFL 1 day

    566 5907 Steel Column Erection 2 days

    567 5908 Tie & Bracings 2 days

    568 5909 Truss Erection 3 days

    569 5910 Roof Sheet Fixing 2 days

    570 5911 Finishing 4 days

    571 5912 Foundation For Invertors 10 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    14/310

    572 5913 Compact Sub Station 40 days

    573 5914 Excavation 2 days

    574 5915 Foundation 7 days

    575 5916 Installation of Structures 4 days

    576 5917 Mounting of Equipments 3 days

    577 5918 Installation of Invertor duty Transformer 2 days578 5919 Stringing 2 days

    579 5920 Earthing 2 days

    580 5921 Installation of RMU 2 days

    581 5922 Cable Trench 4 days

    582 5923 Cabling 2 days

    583 5924 Connections and Terminations 2 days

    584 5925 Alignment of Isolator 1 day

    585 5926 Gas Filling of Circuit Breakers 1 day

    586 5927 Testing of Transformers 2 days

    587 5928 Testing of Equipments 2 days

    588 5929 Testing & Commissioning 2 days

    589 5930 Installation of Equipments 19 days

    590 5931 Installation of Inverters 2 days

    591 5932 Installation of Auxiliary Transformers 2 days

    592 5933 Installation of LT Panels 2 days

    593 5934 Installation of HT Panels 2 days

    594 5935 Installation of Load Break Switch 2 days

    595 5936 AC cabling and Terminations 5 days

    596 5937 Testing of Equipments 2 days

    597 5938 Testing and Commissioning 2 days

    598 5939 Block 2 62 days599 5940 DC Side 38 days

    600 5941 Foundation of Structure 7 days

    601 5942 Structure Erection 12 days

    602 5943 Module Installation 20 days

    603 5944 DC Cabling 31 days

    604 5945 Excavation 7 days

    605 5946 Conduiting 7 days

    606 5947 Cable Pulling pits 7 days

    607 5948 Cabling 10 days

    608 5949 Earthing 7 days

    609 5950 Installation of Combiner plug/ Pre-Combiner box 5 days

    610 5951 Installation of String Combiner box 5 days

    611 5952 Inverter room building 36 days

    612 5953 Foundation 15 days

    613 5954 Excavation 2 days

    614 5955 Dewatering 4 days

    615 5956 Dressing 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    15/310

    616 5957 PCC 2 days

    617 5958 Column Marking 1 day

    618 5959 Reinforcement cutting for MAT 1 day

    619 5960 Placing of Mat reinforcement 1 day

    620 5961 Shuttering for Foundation 1 day

    621 5962 Rcc for Footing 2 days622 5963 Shoe Marking 1 day

    623 5964 Column reinforcement fixing 2 days

    624 5965 Column Box & Bolt Fixing 2 days

    625 5966 Column RCC upto Plinth Beam 1 day

    626 5967 Curing for columns 4 days

    627 5968 Backfilling for foundation 3 days

    628 5969 Plinth beam 15 days

    629 5970 Plinth Beam Excavation 1 day

    630 5971 Plinth Beam Pcc 2 days

    631 5972 Reinforcement cutting 1 day

    632 5973 Plinth Beam Reinforcement placing 1 day

    633 5974 Plinth Beam Shuttering 1 day

    634 5975 Plinth beam Concreting 1 day

    635 5976 Plinth beam curing 4 days

    636 5977 Super structure 13 days

    637 5978 Brick work upto FFL 1 day

    638 5979 Steel Column Erection 2 days

    639 5980 Tie & Bracings 2 days

    640 5981 Truss Erection 3 days

    641 5982 Roof Sheet Fixing 2 days

    642 5983 Finishing 4 days643 5984 Foundation For Invertors 10 days

    644 5985 Compact Sub Station 40 days

    645 5986 Excavation 2 days

    646 5987 Foundation 7 days

    647 5988 Installation of Structures 4 days

    648 5989 Mounting of Equipments 3 days

    649 5990 Installation of Invertor duty Transformer 2 days

    650 5991 Stringing 2 days

    651 5992 Earthing 2 days

    652 5993 Installation of RMU 2 days

    653 5994 Cable Trench 4 days

    654 5995 Cabling 2 days

    655 5996 Connections and Terminations 2 days

    656 5997 Alignment of Isolator 1 day

    657 5998 Gas Filling of Circuit Breakers 1 day

    658 5999 Testing of Transformers 2 days

    659 6000 Testing of Equipments 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    16/310

    660 6001 Testing & Commissioning 2 days

    661 6002 Installation of Equipments 19 days

    662 6003 Installation of Inverters 2 days

    663 6004 Installation of Auxiliary Transformers 2 days

    664 6005 Installation of LT Panels 2 days

    665 6006 Installation of HT Panels 2 days666 6007 Installation of Load Break Switch 2 days

    667 6008 AC cabling and Terminations 5 days

    668 6009 Testing of Equipments 2 days

    669 6010 Testing and Commissioning 2 days

    670 6011 Block 3 62 days

    671 6012 DC Side 38 days

    672 6013 Foundation of Structure 7 days

    673 6014 Structure Erection 12 days

    674 6015 Module Installation 20 days

    675 6016 DC Cabling 31 days

    676 6017 Excavation 7 days

    677 6018 Conduiting 7 days

    678 6019 Cable Pulling pits 7 days

    679 6020 Cabling 10 days

    680 6021 Earthing 7 days

    681 6022 Installation of Combiner plug/ Pre-Combiner box 5 days

    682 6023 Installation of String Combiner box 5 days

    683 6024 Inverter room building 36 days

    684 6025 Foundation 15 days

    685 6026 Excavation 2 days

    686 6027 Dewatering 4 days687 6028 Dressing 2 days

    688 6029 PCC 2 days

    689 6030 Column Marking 1 day

    690 6031 Reinforcement cutting for MAT 1 day

    691 6032 Placing of Mat reinforcement 1 day

    692 6033 Shuttering for Foundation 1 day

    693 6034 Rcc for Footing 2 days

    694 6035 Shoe Marking 1 day

    695 6036 Column reinforcement fixing 2 days

    696 6037 Column Box & Bolt Fixing 2 days

    697 6038 Column RCC upto Plinth Beam 1 day

    698 6039 Curing for columns 4 days

    699 6040 Backfilling for foundation 3 days

    700 6041 Plinth beam 15 days

    701 6042 Plinth Beam Excavation 1 day

    702 6043 Plinth Beam Pcc 2 days

    703 6044 Reinforcement cutting 1 day

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    17/310

    704 6045 Plinth Beam Reinforcement placing 1 day

    705 6046 Plinth Beam Shuttering 1 day

    706 6047 Plinth beam Concreting 1 day

    707 6048 Plinth beam curing 4 days

    708 6049 Super structure 13 days

    709 6050 Brick work upto FFL 1 day710 6051 Steel Column Erection 2 days

    711 6052 Tie & Bracings 2 days

    712 6053 Truss Erection 3 days

    713 6054 Roof Sheet Fixing 2 days

    714 6055 Finishing 4 days

    715 6056 Foundation For Invertors 10 days

    716 6057 Compact Sub Station 40 days

    717 6058 Excavation 2 days

    718 6059 Foundation 7 days

    719 6060 Installation of Structures 4 days

    720 6061 Mounting of Equipments 3 days

    721 6062 Installation of Invertor duty Transformer 2 days

    722 6063 Stringing 2 days

    723 6064 Earthing 2 days

    724 6065 Installation of RMU 2 days

    725 6066 Cable Trench 4 days

    726 6067 Cabling 2 days

    727 6068 Connections and Terminations 2 days

    728 6069 Alignment of Isolator 1 day

    729 6070 Gas Filling of Circuit Breakers 1 day

    730 6071 Testing of Transformers 2 days731 6072 Testing of Equipments 2 days

    732 6073 Testing & Commissioning 2 days

    733 6074 Installation of Equipments 19 days

    734 6075 Installation of Inverters 2 days

    735 6076 Installation of Auxiliary Transformers 2 days

    736 6077 Installation of LT Panels 2 days

    737 6078 Installation of HT Panels 2 days

    738 6079 Installation of Load Break Switch 2 days

    739 6080 AC cabling and Terminations 5 days

    740 6081 Testing of Equipments 2 days

    741 6082 Testing and Commissioning 2 days

    742 6083 Block 4 62 days

    743 6084 DC Side 38 days

    744 6085 Foundation of Structure 7 days

    745 6086 Structure Erection 12 days

    746 6087 Module Installation 20 days

    747 6088 DC Cabling 31 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    18/310

    748 6089 Excavation 7 days

    749 6090 Conduiting 7 days

    750 6091 Cable Pulling pits 7 days

    751 6092 Cabling 10 days

    752 6093 Earthing 7 days

    753 6094 Installation of Combiner plug/ Pre-Combiner box 5 days754 6095 Installation of String Combiner box 5 days

    755 6096 Inverter room building 36 days

    756 6097 Foundation 15 days

    757 6098 Excavation 2 days

    758 6099 Dewatering 4 days

    759 6100 Dressing 2 days

    760 6101 PCC 2 days

    761 6102 Column Marking 1 day

    762 6103 Reinforcement cutting for MAT 1 day

    763 6104 Placing of Mat reinforcement 1 day

    764 6105 Shuttering for Foundation 1 day

    765 6106 Rcc for Footing 2 days

    766 6107 Shoe Marking 1 day

    767 6108 Column reinforcement fixing 2 days

    768 6109 Column Box & Bolt Fixing 2 days

    769 6110 Column RCC upto Plinth Beam 1 day

    770 6111 Curing for columns 4 days

    771 6112 Backfilling for foundation 3 days

    772 6113 Plinth beam 15 days

    773 6114 Plinth Beam Excavation 1 day

    774 6115 Plinth Beam Pcc 2 days775 6116 Reinforcement cutting 1 day

    776 6117 Plinth Beam Reinforcement placing 1 day

    777 6118 Plinth Beam Shuttering 1 day

    778 6119 Plinth beam Concreting 1 day

    779 6120 Plinth beam curing 4 days

    780 6121 Super structure 13 days

    781 6122 Brick work upto FFL 1 day

    782 6123 Steel Column Erection 2 days

    783 6124 Tie & Bracings 2 days

    784 6125 Truss Erection 3 days

    785 6126 Roof Sheet Fixing 2 days

    786 6127 Finishing 4 days

    787 6128 Foundation For Invertors 10 days

    788 6129 Compact Sub Station 40 days

    789 6130 Excavation 2 days

    790 6131 Foundation 7 days

    791 6132 Installation of Structures 4 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    19/310

    792 6133 Mounting of Equipments 3 days

    793 6134 Installation of Invertor duty Transformer 2 days

    794 6135 Stringing 2 days

    795 6136 Earthing 2 days

    796 6137 Installation of RMU 2 days

    797 6138 Cable Trench 4 days798 6139 Cabling 2 days

    799 6140 Connections and Terminations 2 days

    800 6141 Alignment of Isolator 1 day

    801 6142 Gas Filling of Circuit Breakers 1 day

    802 6143 Testing of Transformers 2 days

    803 6144 Testing of Equipments 2 days

    804 6145 Testing & Commissioning 2 days

    805 6146 Installation of Equipments 19 days

    806 6147 Installation of Inverters 2 days

    807 6148 Installation of Auxiliary Transformers 2 days

    808 6149 Installation of LT Panels 2 days

    809 6150 Installation of HT Panels 2 days

    810 6151 Installation of Load Break Switch 2 days

    811 6152 AC cabling and Terminations 5 days

    812 6153 Testing of Equipments 2 days

    813 6154 Testing and Commissioning 2 days

    814 6155 Block 5 62 days

    815 6156 DC Side 38 days

    816 6157 Foundation of Structure 7 days

    817 6158 Structure Erection 12 days

    818 6159 Module Installation 20 days819 6160 DC Cabling 31 days

    820 6161 Excavation 7 days

    821 6162 Conduiting 7 days

    822 6163 Cable Pulling pits 7 days

    823 6164 Cabling 10 days

    824 6165 Earthing 7 days

    825 6166 Installation of Combiner plug/ Pre-Combiner box 5 days

    826 6167 Installation of String Combiner box 5 days

    827 6168 Inverter room building 36 days

    828 6169 Foundation 15 days

    829 6170 Excavation 2 days

    830 6171 Dewatering 4 days

    831 6172 Dressing 2 days

    832 6173 PCC 2 days

    833 6174 Column Marking 1 day

    834 6175 Reinforcement cutting for MAT 1 day

    835 6176 Placing of Mat reinforcement 1 day

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    20/310

    836 6177 Shuttering for Foundation 1 day

    837 6178 Rcc for Footing 2 days

    838 6179 Shoe Marking 1 day

    839 6180 Column reinforcement fixing 2 days

    840 6181 Column Box & Bolt Fixing 2 days

    841 6182 Column RCC upto Plinth Beam 1 day842 6183 Curing for columns 4 days

    843 6184 Backfilling for foundation 3 days

    844 6185 Plinth beam 15 days

    845 6186 Plinth Beam Excavation 1 day

    846 6187 Plinth Beam Pcc 2 days

    847 6188 Reinforcement cutting 1 day

    848 6189 Plinth Beam Reinforcement placing 1 day

    849 6190 Plinth Beam Shuttering 1 day

    850 6191 Plinth beam Concreting 1 day

    851 6192 Plinth beam curing 4 days

    852 6193 Super structure 13 days

    853 6194 Brick work upto FFL 1 day

    854 6195 Steel Column Erection 2 days

    855 6196 Tie & Bracings 2 days

    856 6197 Truss Erection 3 days

    857 6198 Roof Sheet Fixing 2 days

    858 6199 Finishing 4 days

    859 6200 Foundation For Invertors 10 days

    860 6201 Compact Sub Station 40 days

    861 6202 Excavation 2 days

    862 6203 Foundation 7 days863 6204 Installation of Structures 4 days

    864 6205 Mounting of Equipments 3 days

    865 6206 Installation of Invertor duty Transformer 2 days

    866 6207 Stringing 2 days

    867 6208 Earthing 2 days

    868 6209 Installation of RMU 2 days

    869 6210 Cable Trench 4 days

    870 6211 Cabling 2 days

    871 6212 Connections and Terminations 2 days

    872 6213 Alignment of Isolator 1 day

    873 6214 Gas Filling of Circuit Breakers 1 day

    874 6215 Testing of Transformers 2 days

    875 6216 Testing of Equipments 2 days

    876 6217 Testing & Commissioning 2 days

    877 6218 Installation of Equipments 19 days

    878 6219 Installation of Inverters 2 days

    879 6220 Installation of Auxiliary Transformers 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    21/310

    880 6221 Installation of LT Panels 2 days

    881 6222 Installation of HT Panels 2 days

    882 6223 Installation of Load Break Switch 2 days

    883 6224 AC cabling and Terminations 5 days

    884 6225 Testing of Equipments 2 days

    885 6226 Testing and Commissioning 2 days886 6227 Block 6 62 days

    887 6228 DC Side 38 days

    888 6229 Foundation of Structure 7 days

    889 6230 Structure Erection 12 days

    890 6231 Module Installation 20 days

    891 6232 DC Cabling 31 days

    892 6233 Excavation 7 days

    893 6234 Conduiting 7 days

    894 6235 Cable Pulling pits 7 days

    895 6236 Cabling 10 days

    896 6237 Earthing 7 days

    897 6238 Installation of Combiner plug/ Pre-Combiner box 5 days

    898 6239 Installation of String Combiner box 5 days

    899 6240 Inverter room building 36 days

    900 6241 Foundation 15 days

    901 6242 Excavation 2 days

    902 6243 Dewatering 4 days

    903 6244 Dressing 2 days

    904 6245 PCC 2 days

    905 6246 Column Marking 1 day

    906 6247 Reinforcement cutting for MAT 1 day907 6248 Placing of Mat reinforcement 1 day

    908 6249 Shuttering for Foundation 1 day

    909 6250 Rcc for Footing 2 days

    910 6251 Shoe Marking 1 day

    911 6252 Column reinforcement fixing 2 days

    912 6253 Column Box & Bolt Fixing 2 days

    913 6254 Column RCC upto Plinth Beam 1 day

    914 6255 Curing for columns 4 days

    915 6256 Backfilling for foundation 3 days

    916 6257 Plinth beam 15 days

    917 6258 Plinth Beam Excavation 1 day

    918 6259 Plinth Beam Pcc 2 days

    919 6260 Reinforcement cutting 1 day

    920 6261 Plinth Beam Reinforcement placing 1 day

    921 6262 Plinth Beam Shuttering 1 day

    922 6263 Plinth beam Concreting 1 day

    923 6264 Plinth beam curing 4 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    22/310

    924 6265 Super structure 13 days

    925 6266 Brick work upto FFL 1 day

    926 6267 Steel Column Erection 2 days

    927 6268 Tie & Bracings 2 days

    928 6269 Truss Erection 3 days

    929 6270 Roof Sheet Fixing 2 days930 6271 Finishing 4 days

    931 6272 Foundation For Invertors 10 days

    932 6273 Compact Sub Station 40 days

    933 6274 Excavation 2 days

    934 6275 Foundation 7 days

    935 6276 Installation of Structures 4 days

    936 6277 Mounting of Equipments 3 days

    937 6278 Installation of Invertor duty Transformer 2 days

    938 6279 Stringing 2 days

    939 6280 Earthing 2 days

    940 6281 Installation of RMU 2 days

    941 6282 Cable Trench 4 days

    942 6283 Cabling 2 days

    943 6284 Connections and Terminations 2 days

    944 6285 Alignment of Isolator 1 day

    945 6286 Gas Filling of Circuit Breakers 1 day

    946 6287 Testing of Transformers 2 days

    947 6288 Testing of Equipments 2 days

    948 6289 Testing & Commissioning 2 days

    949 6290 Installation of Equipments 19 days

    950 6291 Installation of Inverters 2 days951 6292 Installation of Auxiliary Transformers 2 days

    952 6293 Installation of LT Panels 2 days

    953 6294 Installation of HT Panels 2 days

    954 6295 Installation of Load Break Switch 2 days

    955 6296 AC cabling and Terminations 5 days

    956 6297 Testing of Equipments 2 days

    957 6298 Testing and Commissioning 2 days

    958 6299 Block 7 62 days

    959 6300 DC Side 38 days

    960 6301 Foundation of Structure 7 days

    961 6302 Structure Erection 12 days

    962 6303 Module Installation 20 days

    963 6304 DC Cabling 31 days

    964 6305 Excavation 7 days

    965 6306 Conduiting 7 days

    966 6307 Cable Pulling pits 7 days

    967 6308 Cabling 10 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    23/310

    968 6309 Earthing 7 days

    969 6310 Installation of Combiner plug/ Pre-Combiner box 5 days

    970 6311 Installation of String Combiner box 5 days

    971 6312 Inverter room building 36 days

    972 6313 Foundation 15 days

    973 6314 Excavation 2 days974 6315 Dewatering 4 days

    975 6316 Dressing 2 days

    976 6317 PCC 2 days

    977 6318 Column Marking 1 day

    978 6319 Reinforcement cutting for MAT 1 day

    979 6320 Placing of Mat reinforcement 1 day

    980 6321 Shuttering for Foundation 1 day

    981 6322 Rcc for Footing 2 days

    982 6323 Shoe Marking 1 day

    983 6324 Column reinforcement fixing 2 days

    984 6325 Column Box & Bolt Fixing 2 days

    985 6326 Column RCC upto Plinth Beam 1 day

    986 6327 Curing for columns 4 days

    987 6328 Backfilling for foundation 3 days

    988 6329 Plinth beam 15 days

    989 6330 Plinth Beam Excavation 1 day

    990 6331 Plinth Beam Pcc 2 days

    991 6332 Reinforcement cutting 1 day

    992 6333 Plinth Beam Reinforcement placing 1 day

    993 6334 Plinth Beam Shuttering 1 day

    994 6335 Plinth beam Concreting 1 day995 6336 Plinth beam curing 4 days

    996 6337 Super structure 13 days

    997 6338 Brick work upto FFL 1 day

    998 6339 Steel Column Erection 2 days

    999 6340 Tie & Bracings 2 days

    1000 6341 Truss Erection 3 days

    1001 6342 Roof Sheet Fixing 2 days

    1002 6343 Finishing 4 days

    1003 6344 Foundation For Invertors 10 days

    1004 6345 Compact Sub Station 40 days

    1005 6346 Excavation 2 days

    1006 6347 Foundation 7 days

    1007 6348 Installation of Structures 4 days

    1008 6349 Mounting of Equipments 3 days

    1009 6350 Installation of Invertor duty Transformer 2 days

    1010 6351 Stringing 2 days

    1011 6352 Earthing 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    24/310

    1012 6353 Installation of RMU 2 days

    1013 6354 Cable Trench 4 days

    1014 6355 Cabling 2 days

    1015 6356 Connections and Terminations 2 days

    1016 6357 Alignment of Isolator 1 day

    1017 6358 Gas Filling of Circuit Breakers 1 day1018 6359 Testing of Transformers 2 days

    1019 6360 Testing of Equipments 2 days

    1020 6361 Testing & Commissioning 2 days

    1021 6362 Installation of Equipments 19 days

    1022 6363 Installation of Inverters 2 days

    1023 6364 Installation of Auxiliary Transformers 2 days

    1024 6365 Installation of LT Panels 2 days

    1025 6366 Installation of HT Panels 2 days

    1026 6367 Installation of Load Break Switch 2 days

    1027 6368 AC cabling and Terminations 5 days

    1028 6369 Testing of Equipments 2 days

    1029 6370 Testing and Commissioning 2 days

    1030 6371 Block 8 62 days

    1031 6372 DC Side 38 days

    1032 6373 Foundation of Structure 7 days

    1033 6374 Structure Erection 12 days

    1034 6375 Module Installation 20 days

    1035 6376 DC Cabling 31 days

    1036 6377 Excavation 7 days

    1037 6378 Conduiting 7 days

    1038 6379 Cable Pulling pits 7 days1039 6380 Cabling 10 days

    1040 6381 Earthing 7 days

    1041 6382 Installation of Combiner plug/ Pre-Combiner box 5 days

    1042 6383 Installation of String Combiner box 5 days

    1043 6384 Inverter room building 36 days

    1044 6385 Foundation 15 days

    1045 6386 Excavation 2 days

    1046 6387 Dewatering 4 days

    1047 6388 Dressing 2 days

    1048 6389 PCC 2 days

    1049 6390 Column Marking 1 day

    1050 6391 Reinforcement cutting for MAT 1 day

    1051 6392 Placing of Mat reinforcement 1 day

    1052 6393 Shuttering for Foundation 1 day

    1053 6394 Rcc for Footing 2 days

    1054 6395 Shoe Marking 1 day

    1055 6396 Column reinforcement fixing 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    25/310

    1056 6397 Column Box & Bolt Fixing 2 days

    1057 6398 Column RCC upto Plinth Beam 1 day

    1058 6399 Curing for columns 4 days

    1059 6400 Backfilling for foundation 3 days

    1060 6401 Plinth beam 15 days

    1061 6402 Plinth Beam Excavation 1 day1062 6403 Plinth Beam Pcc 2 days

    1063 6404 Reinforcement cutting 1 day

    1064 6405 Plinth Beam Reinforcement placing 1 day

    1065 6406 Plinth Beam Shuttering 1 day

    1066 6407 Plinth beam Concreting 1 day

    1067 6408 Plinth beam curing 4 days

    1068 6409 Super structure 13 days

    1069 6410 Brick work upto FFL 1 day

    1070 6411 Steel Column Erection 2 days

    1071 6412 Tie & Bracings 2 days

    1072 6413 Truss Erection 3 days

    1073 6414 Roof Sheet Fixing 2 days

    1074 6415 Finishing 4 days

    1075 6416 Foundation For Invertors 10 days

    1076 6417 Compact Sub Station 40 days

    1077 6418 Excavation 2 days

    1078 6419 Foundation 7 days

    1079 6420 Installation of Structures 4 days

    1080 6421 Mounting of Equipments 3 days

    1081 6422 Installation of Invertor duty Transformer 2 days

    1082 6423 Stringing 2 days1083 6424 Earthing 2 days

    1084 6425 Installation of RMU 2 days

    1085 6426 Cable Trench 4 days

    1086 6427 Cabling 2 days

    1087 6428 Connections and Terminations 2 days

    1088 6429 Alignment of Isolator 1 day

    1089 6430 Gas Filling of Circuit Breakers 1 day

    1090 6431 Testing of Transformers 2 days

    1091 6432 Testing of Equipments 2 days

    1092 6433 Testing & Commissioning 2 days

    1093 6434 Installation of Equipments 19 days

    1094 6435 Installation of Inverters 2 days

    1095 6436 Installation of Auxiliary Transformers 2 days

    1096 6437 Installation of LT Panels 2 days

    1097 6438 Installation of HT Panels 2 days

    1098 6439 Installation of Load Break Switch 2 days

    1099 6440 AC cabling and Terminations 5 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    26/310

    1100 6441 Testing of Equipments 2 days

    1101 6442 Testing and Commissioning 2 days

    1102 6443 Block 9 62 days

    1103 6444 DC Side 38 days

    1104 6445 Foundation of Structure 7 days

    1105 6446 Structure Erection 12 days1106 6447 Module Installation 20 days

    1107 6448 DC Cabling 31 days

    1108 6449 Excavation 7 days

    1109 6450 Conduiting 7 days

    1110 6451 Cable Pulling pits 7 days

    1111 6452 Cabling 10 days

    1112 6453 Earthing 7 days

    1113 6454 Installation of Combiner plug/ Pre-Combiner box 5 days

    1114 6455 Installation of String Combiner box 5 days

    1115 6456 Inverter room building 36 days

    1116 6457 Foundation 15 days

    1117 6458 Excavation 2 days

    1118 6459 Dewatering 4 days

    1119 6460 Dressing 2 days

    1120 6461 PCC 2 days

    1121 6462 Column Marking 1 day

    1122 6463 Reinforcement cutting for MAT 1 day

    1123 6464 Placing of Mat reinforcement 1 day

    1124 6465 Shuttering for Foundation 1 day

    1125 6466 Rcc for Footing 2 days

    1126 6467 Shoe Marking 1 day1127 6468 Column reinforcement fixing 2 days

    1128 6469 Column Box & Bolt Fixing 2 days

    1129 6470 Column RCC upto Plinth Beam 1 day

    1130 6471 Curing for columns 4 days

    1131 6472 Backfilling for foundation 3 days

    1132 6473 Plinth beam 15 days

    1133 6474 Plinth Beam Excavation 1 day

    1134 6475 Plinth Beam Pcc 2 days

    1135 6476 Reinforcement cutting 1 day

    1136 6477 Plinth Beam Reinforcement placing 1 day

    1137 6478 Plinth Beam Shuttering 1 day

    1138 6479 Plinth beam Concreting 1 day

    1139 6480 Plinth beam curing 4 days

    1140 6481 Super structure 13 days

    1141 6482 Brick work upto FFL 1 day

    1142 6483 Steel Column Erection 2 days

    1143 6484 Tie & Bracings 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    27/310

    1144 6485 Truss Erection 3 days

    1145 6486 Roof Sheet Fixing 2 days

    1146 6487 Finishing 4 days

    1147 6488 Foundation For Invertors 10 days

    1148 6489 Compact Sub Station 40 days

    1149 6490 Excavation 2 days1150 6491 Foundation 7 days

    1151 6492 Installation of Structures 4 days

    1152 6493 Mounting of Equipments 3 days

    1153 6494 Installation of Invertor duty Transformer 2 days

    1154 6495 Stringing 2 days

    1155 6496 Earthing 2 days

    1156 6497 Installation of RMU 2 days

    1157 6498 Cable Trench 4 days

    1158 6499 Cabling 2 days

    1159 6500 Connections and Terminations 2 days

    1160 6501 Alignment of Isolator 1 day

    1161 6502 Gas Filling of Circuit Breakers 1 day

    1162 6503 Testing of Transformers 2 days

    1163 6504 Testing of Equipments 2 days

    1164 6505 Testing & Commissioning 2 days

    1165 6506 Installation of Equipments 19 days

    1166 6507 Installation of Inverters 2 days

    1167 6508 Installation of Auxiliary Transformers 2 days

    1168 6509 Installation of LT Panels 2 days

    1169 6510 Installation of HT Panels 2 days

    1170 6511 Installation of Load Break Switch 2 days1171 6512 AC cabling and Terminations 5 days

    1172 6513 Testing of Equipments 2 days

    1173 6514 Testing and Commissioning 2 days

    1174 6515 Block 10 62 days

    1175 6516 DC Side 38 days

    1176 6517 Foundation of Structure 7 days

    1177 6518 Structure Erection 12 days

    1178 6519 Module Installation 20 days

    1179 6520 DC Cabling 31 days

    1180 6521 Excavation 7 days

    1181 6522 Conduiting 7 days

    1182 6523 Cable Pulling pits 7 days

    1183 6524 Cabling 10 days

    1184 6525 Earthing 7 days

    1185 6526 Installation of Combiner plug/ Pre-Combiner box 5 days

    1186 6527 Installation of String Combiner box 5 days

    1187 6528 Inverter room building 36 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    28/310

    1188 6529 Foundation 15 days

    1189 6530 Excavation 2 days

    1190 6531 Dewatering 4 days

    1191 6532 Dressing 2 days

    1192 6533 PCC 2 days

    1193 6534 Column Marking 1 day1194 6535 Reinforcement cutting for MAT 1 day

    1195 6536 Placing of Mat reinforcement 1 day

    1196 6537 Shuttering for Foundation 1 day

    1197 6538 Rcc for Footing 2 days

    1198 6539 Shoe Marking 1 day

    1199 6540 Column reinforcement fixing 2 days

    1200 6541 Column Box & Bolt Fixing 2 days

    1201 6542 Column RCC upto Plinth Beam 1 day

    1202 6543 Curing for columns 4 days

    1203 6544 Backfilling for foundation 3 days

    1204 6545 Plinth beam 15 days

    1205 6546 Plinth Beam Excavation 1 day

    1206 6547 Plinth Beam Pcc 2 days

    1207 6548 Reinforcement cutting 1 day

    1208 6549 Plinth Beam Reinforcement placing 1 day

    1209 6550 Plinth Beam Shuttering 1 day

    1210 6551 Plinth beam Concreting 1 day

    1211 6552 Plinth beam curing 4 days

    1212 6553 Super structure 13 days

    1213 6554 Brick work upto FFL 1 day

    1214 6555 Steel Column Erection 2 days1215 6556 Tie & Bracings 2 days

    1216 6557 Truss Erection 3 days

    1217 6558 Roof Sheet Fixing 2 days

    1218 6559 Finishing 4 days

    1219 6560 Foundation For Invertors 10 days

    1220 6561 Compact Sub Station 40 days

    1221 6562 Excavation 2 days

    1222 6563 Foundation 7 days

    1223 6564 Installation of Structures 4 days

    1224 6565 Mounting of Equipments 3 days

    1225 6566 Installation of Invertor duty Transformer 2 days

    1226 6567 Stringing 2 days

    1227 6568 Earthing 2 days

    1228 6569 Installation of RMU 2 days

    1229 6570 Cable Trench 4 days

    1230 6571 Cabling 2 days

    1231 6572 Connections and Terminations 2 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    29/310

    1232 6573 Alignment of Isolator 1 day

    1233 6574 Gas Filling of Circuit Breakers 1 day

    1234 6575 Testing of Transformers 2 days

    1235 6576 Testing of Equipments 2 days

    1236 6577 Testing & Commissioning 2 days

    1237 6578 Installation of Equipments 19 days1238 6579 Installation of Inverters 2 days

    1239 6580 Installation of Auxiliary Transformers 2 days

    1240 6581 Installation of LT Panels 2 days

    1241 6582 Installation of HT Panels 2 days

    1242 6583 Installation of Load Break Switch 2 days

    1243 6584 AC cabling and Terminations 5 days

    1244 6585 Testing of Equipments 2 days

    1245 6586 Testing and Commissioning 2 days

    1246 6587 Block 11 75 days

    1247 6588 DC Side 38 days

    1248 6589 Foundation of Structure 7 days

    1249 6590 Structure Erection 12 days

    1250 6591 Module Installation 20 days

    1251 6592 DC Cabling 31 days

    1252 6593 Excavation 7 days

    1253 6594 Conduiting 7 days

    1254 6595 Cable Pulling pits 7 days

    1255 6596 Cabling 10 days

    1256 6597 Earthing 7 days

    1257 6598 Installation of Combiner plug/ Pre-Combiner box 5 days

    1258 6599 Installation of String Combiner box 5 days1259 6600 Control room 53 days

    1260 6601 Foundation 15 days

    1261 6602 Excavation 4 days

    1262 6603 Dewatering 6 days

    1263 6604 Dressing 3 days

    1264 6605 PCC 2 days

    1265 6606 Column Marking 1 day

    1266 6607 Reinforcement cutting for MAT 1 day

    1267 6608 Placing of Mat reinforcement 1 day

    1268 6609 Shuttering for Foundation 1 day

    1269 6610 Rcc for Footing 2 days

    1270 6611 Shoe Marking 1 day

    1271 6612 Column reinforcement fixing 2 days

    1272 6613 Column Box Fixing 2 days

    1273 6614 Column RCC upto Plinth Beam 1 day

    1274 6615 Curing for columns 4 days

    1275 6616 Backfilling for foundation 3 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    30/310

    1276 6617 Plinth beam 15 days

    1277 6618 Plinth Beam Excavation 1 day

    1278 6619 Plinth Beam Pcc 2 days

    1279 6620 Reinforcement cutting 1 day

    1280 6621 Plinth Beam Reinforcement placing 1 day

    1281 6622 Plinth Beam Shuttering 1 day1282 6623 Plinth beam Concreting 1 day

    1283 6624 Plinth beam curing 4 days

    1284 6625 Super structure 24 days

    1285 6626 2 nd Shoe Marking 1 day

    1286 6627 Column Reinforcement ties upto roof 2 days

    1287 6628 Column box fixing upto 1st Floor 2 days

    1288 6629 Column concrete upto 1st Floor 3 days

    1289 6630 Brick work upto FFL 2 days

    1290 6631 Brick wall above FFL 4 days

    1291 6632 Earth filling for Grade slab 3 days

    1292 6633 Roof beam & slab shuttering 2 days

    1293 6634 Roof beam & slab reinforcement 2 days

    1294 6635 Roof concrete 1 day

    1295 6636 Finishing work 18 days

    1296 6637 Inner Plastering 1 day

    1297 6638 Outer plastering 1 day

    1298 6639 Finshing work with window & louver fixing 1 day

    1299 6640 0.0m leveling for PCC work 1 day

    1300 6641 Pcc for flooring 1 day

    1301 6642 Reinforcement for Grade slab concrete 1 day

    1302 6643 Shuttering for Grade slab 1 day1303 6644 Grade slab concrete 1 day

    1304 6645 Painting 1 day

    1305 6646 Finishing as per architectural work 1 day

    1306 6647 Compact Sub Station 40 days

    1307 6648 Excavation 2 days

    1308 6649 Foundation 7 days

    1309 6650 Installation of Structures 4 days

    1310 6651 Mounting of Equipments 3 days

    1311 6652 Installation of Invertor duty Transformer 2 days

    1312 6653 Stringing 2 days

    1313 6654 Earthing 2 days

    1314 6655 Installation of RMU 2 days

    1315 6656 Cable Trench 4 days

    1316 6657 Cabling 2 days

    1317 6658 Connections and Terminations 2 days

    1318 6659 Alignment of Isolator 1 day

    1319 6660 Gas Filling of Circuit Breakers 1 day

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    31/310

    1320 6661 Testing of Transformers 2 days

    1321 6662 Testing of Equipments 2 days

    1322 6663 Testing & Commissioning 2 days

    1323 6664 Installation of Equipments 15 days

    1324 6665 Installation of Inverters 2 days

    1325 6666 Installation of Auxiliary Transformers 2 days1326 6667 Installation of LT Panels 2 days

    1327 6668 Installation of HT Panels 2 days

    1328 6669 Installation of Load Break Switch 2 days

    1329 6670 AC cabling and Terminations 5 days

    1330 6671 Testing of Equipments 2 days

    1331 6672 Testing and Commissioning 2 days

    1332 6673 Overall Completion of Plant 0 days

    1333 6674 END 0 days

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    32/310

    Type Outline_Level Baseline_Duration Predecessors Start_Date

    Fixed Duration 1 0 days 5/5/2012 8:00

    Fixed Units 2 0 days 5/5/2012 8:00

    Fixed Duration 2 0 days 5/12/2012 17:00

    Fixed Duration 3 0 days 5/12/2012 17:00

    Fixed Units 4 0 days 2SS+15 days,9 5/22/2012 17:00Fixed Units 4 0 days 35FS+2 days 6/13/2012 17:00

    Fixed Units 4 0 days 2SS+7 days 5/12/2012 17:00

    Fixed Units 4 0 days 2SS+10 days,6 6/13/2012 17:00

    Fixed Units 4 0 days 2SS+7 days 5/12/2012 17:00

    Fixed Units 4 0 days 2SS+7 days 5/12/2012 17:00

    Fixed Duration 3 0 days 6/14/2012 8:00

    Fixed Units 4 0 days 6 6/14/2012 8:00

    Fixed Units 4 0 days 6,10 6/14/2012 8:00

    Fixed Duration 3 0 days 5/14/2012 8:00

    Fixed Units 4 0 days 5 5/23/2012 8:00

    Fixed Units 4 0 days 6 6/14/2012 8:00

    Fixed Units 4 0 days 7 5/14/2012 8:00

    Fixed Units 4 0 days 8 6/14/2012 8:00

    Fixed Units 4 0 days 16,17 6/26/2012 8:00

    Fixed Units 4 0 days 9,19 7/2/2012 8:00

    Fixed Units 4 0 days 20 7/13/2012 8:00

    Fixed Units 4 0 days 18 6/20/2012 8:00

    Fixed Units 4 0 days 16,17,18,22 6/26/2012 8:00

    Fixed Units 4 0 days 43 7/10/2012 8:00

    Fixed Units 4 0 days 38,42 7/2/2012 8:00

    Fixed Units 4 0 days 23 7/4/2012 8:00Fixed Units 4 0 days 26 7/10/2012 8:00

    Fixed Units 4 0 days 27 7/16/2012 8:00

    Fixed Units 4 0 days 16,23 7/4/2012 8:00

    Fixed Units 4 0 days 16,23 7/4/2012 8:00

    Fixed Units 4 0 days 16,23 7/4/2012 8:00

    Fixed Units 4 0 days 16 6/26/2012 8:00

    Fixed Units 4 0 days 16 6/26/2012 8:00

    Fixed Duration 3 0 days 5/22/2012 8:00

    Fixed Units 4 0 days 15 6/4/2012 8:00

    Fixed Units 4 0 days 16 6/26/2012 8:00

    Fixed Units 4 0 days 17 5/22/2012 8:00

    Fixed Units 4 0 days 18 6/20/2012 8:00

    Fixed Units 4 0 days 19 7/2/2012 8:00

    Fixed Units 4 0 days 20 7/13/2012 8:00

    Fixed Units 4 0 days 21 7/19/2012 8:00

    Fixed Units 4 0 days 22 6/26/2012 8:00

    Fixed Units 4 0 days 23 7/4/2012 8:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    33/310

    Fixed Units 4 0 days 24 7/16/2012 8:00

    Fixed Units 4 0 days 25 7/10/2012 8:00

    Fixed Units 4 0 days 26 7/10/2012 8:00

    Fixed Units 4 0 days 27 7/16/2012 8:00

    Fixed Units 4 0 days 28 7/19/2012 8:00

    Fixed Units 4 0 days 29 7/10/2012 8:00Fixed Units 4 0 days 30 7/12/2012 8:00

    Fixed Units 4 0 days 31 7/16/2012 8:00

    Fixed Units 4 0 days 32 7/2/2012 8:00

    Fixed Units 4 0 days 33 7/2/2012 8:00

    Fixed Duration 2 0 days 5/5/2012 8:00

    Fixed Duration 3 0 days 5/5/2012 8:00

    Fixed Units 4 0 days 5/5/2012 8:00

    Fixed Duration 4 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Duration 4 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Duration 4 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Units 5 0 days 5/5/2012 8:00

    Fixed Duration 3 0 days 5/29/2012 8:00

    Fixed Duration 4 0 days 5/29/2012 8:00

    Fixed Units 5 0 days 58,59,60,61,62,64,65, 5/29/2012 8:00

    Fixed Units 5 0 days 85 6/9/2012 8:00

    Fixed Units 5 0 days 86 6/18/2012 8:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    34/310

    Fixed Units 5 0 days 87 6/23/2012 8:00

    Fixed Units 5 0 days 88 7/2/2012 8:00

    Fixed Duration 4 0 days 6/21/2012 8:00

    Fixed Units 5 0 days 70,71,72,73,75,78,85 6/21/2012 8:00

    Fixed Units 5 0 days 91 7/9/2012 8:00

    Fixed Units 5 0 days 92 7/20/2012 8:00Fixed Units 5 0 days 93 7/26/2012 8:00

    Fixed Units 5 0 days 94 8/7/2012 8:00

    Fixed Duration 4 0 days 7/20/2012 8:00

    Fixed Units 5 0 days 63,91FS+10 days 7/20/2012 8:00

    Fixed Units 5 0 days 97 8/7/2012 8:00

    Fixed Units 5 0 days 98 8/18/2012 8:00

    Fixed Units 5 0 days 99 8/24/2012 8:00

    Fixed Units 5 0 days 100 9/5/2012 8:00

    Fixed Duration 3 0 days 7/12/2012 17:00

    Fixed Duration 4 0 days 7/12/2012 17:00

    Fixed Duration 5 0 days 7/12/2012 17:00

    Fixed Units 6 0 days 58FS+60 days,89 8/6/2012 17:00

    Fixed Units 6 0 days 59FS+60 days,89 8/6/2012 17:00

    Fixed Units 6 0 days 60FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 61FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 62FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 63FS+90 days,89 9/4/2012 17:00

    Fixed Units 6 0 days 64FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 65FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 66FS+45 days,89 7/12/2012 17:00

    Fixed Units 6 0 days 67FS+45 days,89 7/12/2012 17:00Fixed Units 6 0 days 68FS+45 days,89 7/12/2012 17:00

    Fixed Duration 5 0 days 7/13/2012 17:00

    Fixed Units 6 0 days 70FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 71FS+60 days,89 7/31/2012 17:00

    Fixed Units 6 0 days 72FS+30 days,95 8/23/2012 17:00

    Fixed Units 6 0 days 73FS+30 days,95 8/23/2012 17:00

    Fixed Units 6 0 days 74FS+69 days,89 8/10/2012 17:00

    Fixed Units 6 0 days 75FS+60 days,89 7/31/2012 17:00

    Fixed Units 6 0 days 77FS+45 days,89 7/13/2012 17:00

    Fixed Units 6 0 days 78FS+60 days,95 8/23/2012 17:00

    Fixed Duration 5 0 days 7/12/2012 17:00

    Fixed Units 6 0 days 80FS+10 days,89 7/12/2012 17:00

    Fixed Units 6 0 days 81FS+10 days,89 7/12/2012 17:00

    Fixed Units 6 0 days 82FS+15 days,89 7/12/2012 17:00

    Fixed Duration 4 0 days 7/20/2012 17:00

    Fixed Duration 5 0 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,105FS+10 days 8/17/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    35/310

    Fixed Units 6 0 days 89,106FS+10 days 8/17/2012 17:00

    Fixed Units 6 0 days 89,107FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,108FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,109FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,110 9/4/2012 17:00

    Fixed Units 6 0 days 89,111FS+7 days 7/21/2012 17:00Fixed Units 6 0 days 89,112FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,113FS+7 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,114FS+7 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,115FS+7 days 7/20/2012 17:00

    Fixed Duration 5 0 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,117FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 89,118FS+7 days 8/8/2012 17:00

    Fixed Units 6 0 days 95,119FS+7 days 8/31/2012 17:00

    Fixed Units 6 0 days 95,120FS+7 days 8/31/2012 17:00

    Fixed Units 6 0 days 89,121 8/10/2012 17:00

    Fixed Units 6 0 days 89,122FS+7 days 8/8/2012 17:00

    Fixed Units 6 0 days 89,123FS+7 days 7/21/2012 17:00

    Fixed Units 6 0 days 95,124FS+10 days 9/4/2012 17:00

    Fixed Duration 5 0 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,126FS+7 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,127FS+7 days 7/20/2012 17:00

    Fixed Units 6 0 days 89,128FS+7 days 7/20/2012 17:00

    Fixed Duration 4 0 days 7/28/2012 17:00

    Fixed Duration 5 0 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,131FS+10 days 8/29/2012 17:00

    Fixed Units 6 0 days 89,132FS+10 days 8/29/2012 17:00Fixed Units 6 0 days 89,133FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,134FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,135FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,136 9/4/2012 17:00

    Fixed Units 6 0 days 89,137FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,138FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,139FS+7 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,140FS+7 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,141FS+7 days 7/28/2012 17:00

    Fixed Duration 5 0 days 7/30/2012 17:00

    Fixed Units 6 0 days 89,142FS+7 days 9/12/2012 17:00

    Fixed Units 6 0 days 89,143FS+7 days 7/30/2012 17:00

    Fixed Units 6 0 days 95,144FS+7 days 8/23/2012 17:00

    Fixed Units 6 0 days 95,145FS+7 days 9/8/2012 17:00

    Fixed Units 6 0 days 89,146 8/31/2012 17:00

    Fixed Units 6 0 days 89,147FS+7 days 8/18/2012 17:00

    Fixed Units 6 0 days 89,148FS+7 days 8/16/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    36/310

    Fixed Units 6 0 days 95,149FS+10 days 8/23/2012 17:00

    Fixed Duration 5 0 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,152FS+7 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,153FS+7 days 7/28/2012 17:00

    Fixed Units 6 0 days 89,154FS+7 days 7/28/2012 17:00

    Fixed Duration 4 0 days 8/6/2012 17:00Fixed Duration 5 0 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,157FS+10 days 9/10/2012 17:00

    Fixed Units 6 0 days 89,158FS+10 days 9/10/2012 17:00

    Fixed Units 6 0 days 89,159FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,160FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,161FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,162 9/4/2012 17:00

    Fixed Units 6 0 days 89,163FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,164FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,165FS+7 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,166FS+7 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,167FS+7 days 8/6/2012 17:00

    Fixed Duration 5 0 days 8/7/2012 17:00

    Fixed Units 6 0 days 89,169FS+7 days 9/20/2012 17:00

    Fixed Units 6 0 days 89,170FS+7 days 8/7/2012 17:00

    Fixed Units 6 0 days 95,171FS+7 days 8/31/2012 17:00

    Fixed Units 6 0 days 95,172FS+7 days 9/17/2012 17:00

    Fixed Units 6 0 days 89,173 8/31/2012 17:00

    Fixed Units 6 0 days 89,174FS+7 days 8/27/2012 17:00

    Fixed Units 6 0 days 89,175FS+7 days 8/24/2012 17:00

    Fixed Units 6 0 days 95,176FS+10 days 9/4/2012 17:00Fixed Duration 5 0 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,178FS+7 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,179FS+7 days 8/6/2012 17:00

    Fixed Units 6 0 days 89,180FS+7 days 8/6/2012 17:00

    Fixed Duration 4 0 days 8/14/2012 17:00

    Fixed Duration 5 0 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,183FS+10 days 9/21/2012 17:00

    Fixed Units 6 0 days 89,184FS+10 days 9/21/2012 17:00

    Fixed Units 6 0 days 89,185FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,186FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,187FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,188 9/4/2012 17:00

    Fixed Units 6 0 days 89,189FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,190FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,191FS+7 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,192FS+7 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,193FS+7 days 8/14/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    37/310

    Fixed Duration 5 0 days 8/15/2012 17:00

    Fixed Units 6 0 days 89,195FS+7 days 9/28/2012 17:00

    Fixed Units 6 0 days 89,196FS+7 days 8/15/2012 17:00

    Fixed Units 6 0 days 95,197FS+7 days 9/8/2012 17:00

    Fixed Units 6 0 days 95,198FS+7 days 9/25/2012 17:00

    Fixed Units 6 0 days 89,199 8/31/2012 17:00Fixed Units 6 0 days 89,200FS+7 days 9/4/2012 17:00

    Fixed Units 6 0 days 89,201FS+7 days 9/1/2012 17:00

    Fixed Units 6 0 days 95,202FS+10 days 9/15/2012 17:00

    Fixed Duration 5 0 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,204FS+7 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,205FS+7 days 8/14/2012 17:00

    Fixed Units 6 0 days 89,206FS+7 days 8/14/2012 17:00

    Fixed Duration 3 0 days 7/18/2012 17:00

    Fixed Duration 4 0 days 7/18/2012 17:00

    Fixed Duration 5 0 days 7/18/2012 17:00

    Fixed Units 6 0 days 105FS+5 days 8/11/2012 17:00

    Fixed Units 6 0 days 106FS+5 days 8/11/2012 17:00

    Fixed Units 6 0 days 107FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 108FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 109FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 110FS+5 days 9/10/2012 17:00

    Fixed Units 6 0 days 111FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 112FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 113FS+5 days 7/18/2012 17:00

    Fixed Units 6 0 days 114FS+5 days 7/18/2012 17:00

    Fixed Units 6 0 days 115FS+5 days 7/18/2012 17:00Fixed Duration 5 0 days 7/19/2012 17:00

    Fixed Units 6 0 days 117FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 118FS+5 days 8/6/2012 17:00

    Fixed Units 6 0 days 119FS+5 days 8/29/2012 17:00

    Fixed Units 6 0 days 120FS+5 days 8/29/2012 17:00

    Fixed Units 6 0 days 121FS+5 days 8/16/2012 17:00

    Fixed Units 6 0 days 122FS+5 days 8/6/2012 17:00

    Fixed Units 6 0 days 123FS+5 days 7/19/2012 17:00

    Fixed Units 6 0 days 124FS+5 days 8/29/2012 17:00

    Fixed Duration 5 0 days 7/18/2012 17:00

    Fixed Units 6 0 days 126FS+5 days 7/18/2012 17:00

    Fixed Units 6 0 days 127FS+5 days 7/18/2012 17:00

    Fixed Units 6 0 days 128FS+5 days 7/18/2012 17:00

    Fixed Duration 4 0 days 7/21/2012 17:00

    Fixed Duration 5 0 days 7/21/2012 17:00

    Fixed Units 6 0 days 236FS+3 days 8/15/2012 17:00

    Fixed Units 6 0 days 237FS+3 days 8/15/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    38/310

    Fixed Units 6 0 days 238FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 239FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 240FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 241FS+3 days 9/13/2012 17:00

    Fixed Units 6 0 days 242FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 243FS+3 days 7/23/2012 17:00Fixed Units 6 0 days 244FS+3 days 7/21/2012 17:00

    Fixed Units 6 0 days 245FS+3 days 7/21/2012 17:00

    Fixed Units 6 0 days 246FS+3 days 7/21/2012 17:00

    Fixed Duration 5 0 days 7/23/2012 17:00

    Fixed Units 6 0 days 248FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 249FS+3 days 8/9/2012 17:00

    Fixed Units 6 0 days 250FS+3 days 9/1/2012 17:00

    Fixed Units 6 0 days 251FS+3 days 9/1/2012 17:00

    Fixed Units 6 0 days 252FS+3 days 8/20/2012 17:00

    Fixed Units 6 0 days 253FS+3 days 8/9/2012 17:00

    Fixed Units 6 0 days 254FS+3 days 7/23/2012 17:00

    Fixed Units 6 0 days 255FS+3 days 9/1/2012 17:00

    Fixed Duration 5 0 days 7/21/2012 17:00

    Fixed Units 6 0 days 257FS+3 days 7/21/2012 17:00

    Fixed Units 6 0 days 258FS+3 days 7/21/2012 17:00

    Fixed Units 6 0 days 259FS+3 days 7/21/2012 17:00

    Fixed Duration 4 0 days 7/26/2012 17:00

    Fixed Duration 5 0 days 7/26/2012 17:00

    Fixed Units 6 0 days 131FS+5 days 8/23/2012 17:00

    Fixed Units 6 0 days 132FS+5 days 8/23/2012 17:00

    Fixed Units 6 0 days 133FS+5 days 7/27/2012 17:00Fixed Units 6 0 days 134FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 135FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 136FS+5 days 9/10/2012 17:00

    Fixed Units 6 0 days 137FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 138FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 139FS+5 days 7/26/2012 17:00

    Fixed Units 6 0 days 140FS+5 days 7/26/2012 17:00

    Fixed Units 6 0 days 141FS+5 days 7/26/2012 17:00

    Fixed Duration 5 0 days 7/27/2012 17:00

    Fixed Units 6 0 days 143FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 144FS+5 days 8/14/2012 17:00

    Fixed Units 6 0 days 145FS+5 days 9/6/2012 17:00

    Fixed Units 6 0 days 146FS+5 days 9/6/2012 17:00

    Fixed Units 6 0 days 147FS+5 days 8/16/2012 17:00

    Fixed Units 6 0 days 148FS+5 days 8/14/2012 17:00

    Fixed Units 6 0 days 149FS+5 days 7/27/2012 17:00

    Fixed Units 6 0 days 150FS+5 days 9/10/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    39/310

    Fixed Duration 5 0 days 7/26/2012 17:00

    Fixed Units 6 0 days 152FS+5 days 7/26/2012 17:00

    Fixed Units 6 0 days 153FS+5 days 7/26/2012 17:00

    Fixed Units 6 0 days 154FS+5 days 7/26/2012 17:00

    Fixed Duration 4 0 days 7/30/2012 17:00

    Fixed Duration 5 0 days 7/30/2012 17:00Fixed Units 6 0 days 288FS+3 days 8/27/2012 17:00

    Fixed Units 6 0 days 289FS+3 days 8/27/2012 17:00

    Fixed Units 6 0 days 290FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 291FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 292FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 293FS+3 days 9/13/2012 17:00

    Fixed Units 6 0 days 294FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 295FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 296FS+3 days 7/30/2012 17:00

    Fixed Units 6 0 days 297FS+3 days 7/30/2012 17:00

    Fixed Units 6 0 days 298FS+3 days 7/30/2012 17:00

    Fixed Duration 5 0 days 7/31/2012 17:00

    Fixed Units 6 0 days 300FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 301FS+3 days 8/17/2012 17:00

    Fixed Units 6 0 days 302FS+3 days 9/10/2012 17:00

    Fixed Units 6 0 days 303FS+3 days 9/10/2012 17:00

    Fixed Units 6 0 days 304FS+3 days 8/20/2012 17:00

    Fixed Units 6 0 days 305FS+3 days 8/17/2012 17:00

    Fixed Units 6 0 days 306FS+3 days 7/31/2012 17:00

    Fixed Units 6 0 days 307FS+3 days 9/13/2012 17:00

    Fixed Duration 5 0 days 7/30/2012 17:00Fixed Units 6 0 days 309FS+3 days 7/30/2012 17:00

    Fixed Units 6 0 days 310FS+3 days 7/30/2012 17:00

    Fixed Units 6 0 days 311FS+3 days 7/30/2012 17:00

    Fixed Duration 4 0 days 8/3/2012 17:00

    Fixed Duration 5 0 days 8/3/2012 17:00

    Fixed Units 6 0 days 157FS+5 days 9/4/2012 17:00

    Fixed Units 6 0 days 158FS+5 days 9/4/2012 17:00

    Fixed Units 6 0 days 159FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 160FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 161FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 162FS+5 days 9/10/2012 17:00

    Fixed Units 6 0 days 163FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 164FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 165FS+5 days 8/3/2012 17:00

    Fixed Units 6 0 days 166FS+5 days 8/3/2012 17:00

    Fixed Units 6 0 days 167FS+5 days 8/3/2012 17:00

    Fixed Duration 5 0 days 8/4/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    40/310

    Fixed Units 6 0 days 169FS+5 days 9/18/2012 17:00

    Fixed Units 6 0 days 170FS+5 days 8/4/2012 17:00

    Fixed Units 6 0 days 171FS+5 days 8/29/2012 17:00

    Fixed Units 6 0 days 172FS+5 days 9/14/2012 17:00

    Fixed Units 6 0 days 173FS+5 days 9/6/2012 17:00

    Fixed Units 6 0 days 174FS+5 days 8/24/2012 17:00Fixed Units 6 0 days 175FS+5 days 8/22/2012 17:00

    Fixed Units 6 0 days 176FS+5 days 8/29/2012 17:00

    Fixed Duration 5 0 days 8/3/2012 17:00

    Fixed Units 6 0 days 178FS+5 days 8/3/2012 17:00

    Fixed Units 6 0 days 179FS+5 days 8/3/2012 17:00

    Fixed Units 6 0 days 180FS+5 days 8/3/2012 17:00

    Fixed Duration 4 0 days 8/7/2012 17:00

    Fixed Duration 5 0 days 8/7/2012 17:00

    Fixed Units 6 0 days 340FS+3 days 9/7/2012 17:00

    Fixed Units 6 0 days 341FS+3 days 9/7/2012 17:00

    Fixed Units 6 0 days 342FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 343FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 344FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 345FS+3 days 9/13/2012 17:00

    Fixed Units 6 0 days 346FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 347FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 348FS+3 days 8/7/2012 17:00

    Fixed Units 6 0 days 349FS+3 days 8/7/2012 17:00

    Fixed Units 6 0 days 350FS+3 days 8/7/2012 17:00

    Fixed Duration 5 0 days 8/8/2012 17:00

    Fixed Units 6 0 days 352FS+3 days 9/21/2012 17:00Fixed Units 6 0 days 353FS+3 days 8/8/2012 17:00

    Fixed Units 6 0 days 354FS+3 days 9/1/2012 17:00

    Fixed Units 6 0 days 355FS+3 days 9/18/2012 17:00

    Fixed Units 6 0 days 356FS+3 days 9/10/2012 17:00

    Fixed Units 6 0 days 357FS+3 days 8/28/2012 17:00

    Fixed Units 6 0 days 358FS+3 days 8/25/2012 17:00

    Fixed Units 6 0 days 359FS+3 days 9/1/2012 17:00

    Fixed Duration 5 0 days 8/7/2012 17:00

    Fixed Units 6 0 days 361FS+3 days 8/7/2012 17:00

    Fixed Units 6 0 days 362FS+3 days 8/7/2012 17:00

    Fixed Units 6 0 days 363FS+3 days 8/7/2012 17:00

    Fixed Duration 4 0 days 8/11/2012 17:00

    Fixed Duration 5 0 days 8/11/2012 17:00

    Fixed Units 6 0 days 183FS+5 days 9/15/2012 17:00

    Fixed Units 6 0 days 184FS+5 days 9/15/2012 17:00

    Fixed Units 6 0 days 185FS+5 days 8/13/2012 17:00

    Fixed Units 6 0 days 186FS+5 days 8/13/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    41/310

    Fixed Units 6 0 days 187FS+5 days 8/13/2012 17:00

    Fixed Units 6 0 days 188FS+5 days 9/10/2012 17:00

    Fixed Units 6 0 days 189FS+5 days 8/13/2012 17:00

    Fixed Units 6 0 days 190FS+5 days 8/13/2012 17:00

    Fixed Units 6 0 days 191FS+5 days 8/11/2012 17:00

    Fixed Units 6 0 days 192FS+5 days 8/11/2012 17:00Fixed Units 6 0 days 193FS+5 days 8/11/2012 17:00

    Fixed Duration 5 0 days 8/13/2012 17:00

    Fixed Units 6 0 days 195FS+5 days 9/26/2012 17:00

    Fixed Units 6 0 days 196FS+5 days 8/13/2012 17:00

    Fixed Units 6 0 days 197FS+5 days 9/6/2012 17:00

    Fixed Units 6 0 days 198FS+5 days 9/22/2012 17:00

    Fixed Units 6 0 days 199FS+5 days 9/6/2012 17:00

    Fixed Units 6 0 days 200FS+5 days 9/1/2012 17:00

    Fixed Units 6 0 days 201FS+5 days 8/30/2012 17:00

    Fixed Units 6 0 days 202FS+5 days 9/10/2012 17:00

    Fixed Duration 5 0 days 8/11/2012 17:00

    Fixed Units 6 0 days 204FS+5 days 8/11/2012 17:00

    Fixed Units 6 0 days 205FS+5 days 8/11/2012 17:00

    Fixed Units 6 0 days 206FS+5 days 8/11/2012 17:00

    Fixed Duration 4 0 days 8/15/2012 17:00

    Fixed Duration 5 0 days 8/15/2012 17:00

    Fixed Units 6 0 days 392FS+3 days 9/19/2012 17:00

    Fixed Units 6 0 days 393FS+3 days 9/19/2012 17:00

    Fixed Units 6 0 days 394FS+3 days 8/16/2012 17:00

    Fixed Units 6 0 days 395FS+3 days 8/16/2012 17:00

    Fixed Units 6 0 days 396FS+3 days 8/16/2012 17:00Fixed Units 6 0 days 397FS+3 days 9/13/2012 17:00

    Fixed Units 6 0 days 398FS+3 days 8/16/2012 17:00

    Fixed Units 6 0 days 399FS+3 days 8/16/2012 17:00

    Fixed Units 6 0 days 400FS+3 days 8/15/2012 17:00

    Fixed Units 6 0 days 401FS+3 days 8/15/2012 17:00

    Fixed Units 6 0 days 402FS+3 days 8/15/2012 17:00

    Fixed Duration 5 0 days 8/16/2012 17:00

    Fixed Units 6 0 days 404FS+3 days 9/29/2012 17:00

    Fixed Units 6 0 days 405FS+3 days 8/16/2012 17:00

    Fixed Units 6 0 days 406FS+3 days 9/10/2012 17:00

    Fixed Units 6 0 days 407FS+3 days 9/26/2012 17:00

    Fixed Units 6 0 days 408FS+3 days 9/10/2012 17:00

    Fixed Units 6 0 days 409FS+3 days 9/5/2012 17:00

    Fixed Units 6 0 days 410FS+3 days 9/3/2012 17:00

    Fixed Units 6 0 days 411FS+3 days 9/13/2012 17:00

    Fixed Duration 5 0 days 8/15/2012 17:00

    Fixed Units 6 0 days 413FS+3 days 8/15/2012 17:00

  • 7/30/2019 Master_MSP (8 Months)_Task Dumping

    42/310

    Fixed Units 6 0 days 414FS+3 days 8/15/2012 17:00

    Fixed Units 6 0 days 415FS+3 days 8/15/2012 17:00

    Fixed Duration 4 0 days 8/20/2012 17:00

    Fixed Duration 5 0 days 8/20/2012 17:00

    Fixed Units 6 0 days 209FS+5 days 9/27/2012 17:00

    Fixed Units 6 0 days 210FS+5 days 9/27/2012 17:00Fixed Units 6 0 days 211FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 212FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 213FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 214FS+5 days 9/10/2012 17:00

    Fixed Units 6 0 days 215FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 216FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 217FS+5 days 8/20/2012 17:00

    Fixed Units 6 0 days 218FS+5 days 8/20/2012 17:00

    Fixed Units 6 0 days 219FS+5 days 8/20/2012 17:00

    Fixed Duration 5 0 days 8/21/2012 17:00

    Fixed Units 6 0 days 221FS+5 days 10/4/2012 17:00

    Fixed Units 6 0 days 222FS+5 days 8/21/2012 17:00

    Fixed Units 6 0 days 223FS+5 days 9/14/2012 17:00

    Fixed Units 6 0 days 224FS+5 days 10/1/2012 17:00