materials and research division · 2009-11-06 · materials and research division experimental...
TRANSCRIPT
NORTH DAKOTA DEPARTMENT OF TRANSPORTATION
MATERIALS AND RESEARCH DIVISION
Experimental Study ND 2003-03
Dowel Bar Retrofit Mix MR0301
Final Report
March 2007
Prepared by
NORTH DAKOTA DEPARTMENT OF TRANSPORTATION BISMARCK, NORTH DAKOTA
www.dot.nd.gov
DIRECTOR Francis G. Ziegler, P.E.
MATERIALS AND RESEARCH DIVISION Ron Horner, P.E.
This page left blank intentionally
X
RCS HHO-30-19
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION EXPERIMENTAL PROJECT REPORT
EXPERIMENTAL PROJECT NO. CONSTRUCTION PROJ NO LOCATION STATE YEAR NUMBER SURF 1 ND 2003
-03
AC-IM-8-094(041)342 8
Cass County 28
EVALUATION FUNDING NEEP NO. PROPRIETARY FEATURE?
1 X HP&R 3 DEMONSTRATION Yes
EXPERIMENTAL PROJECT
48 2 CONSTRUCTION 4 IMPLEMENTATION 49 51 X No
SHORT TITLE TITLE 52 Dowel Bar Retrofit Mix MR0301
DATE MO. YR. REPORTING THIS FORM
140 03 -- 2007 1 INITIAL 2 ANNUAL 3 X FINAL
KEY WORD 1 145 Joints
KEY WORD 2
167 Load TransferKEY WORD 3 189 Dowels
KEY WORD 4 211 Rehabilitation
KEY WORDS
UNIQUE WORD 233
PROPRIETARY FEATURE NAME 255
Date Work Plan Approved
Date Feature Constructed:
Evaluation Scheduled Until:
Evaluation Extended Until:
Date Evaluation Terminated:
CHRONOLOGY
277 08-2003 281 08-2003 285 08-2008 289 293 04-2006 QUANTITY OF UNITS (ROUNDED TO WHOLE NUMBERS) UNITS UNIT COST (Dollars, Cents)
432
39.60
QUANTITY AND COST
297
1 LIN. FT 2 SY 3 SY-IN 4 CY 305
5 TON 6 LBS 7 X EACH 8 LUMP SUM
306
AVAILABLE EVALUATION
REPORTS
CONSTRUCTION 315 X
PERFORMANCE
X
FINAL
X
CONSTRUCTION PROBLEMS PERFORMANCE
EVALUATION
318
1 2 3 4 5
NONE SLIGHT MODERATE SIGNIFICANT SEVERE
319
1 2 3 4 5
EXCELLENT GOOD SATISFACTORY MARGINAL UNSATISFACTORY
APPLICATION 320
1 ADOPTED AS PRIMARY STD. 2 PERMITTED ALTERNATIVE 3 ADOPTED CONDITIONALLY
4 PENDING 5 X REJECTED 6 NOT CONSTRUCTED
(Explain in remarks if 3, 4, 5, or 6 is checked)
REMARKS
321 It is recommended that the NDDOT continue using the proprietary mixes currently allowed in the standard specifications due to higher costs and poor performance of the experimental mix. It is also recommended that special attention is given to the location of coreboards after the dowel bar mix is placed. Coreboard failures can be reduced or eliminated if the coreboard remains in the joint and not allowed to move into the dowel bar slot.
700
Form FHWA 1461
X
This page left blank intentionally
Experimental Study ND 2003-03
Dowel Bar Retrofit Mix MR0301
FINAL REPORT
Project AC-IM-8-094(041)342
March 2007
Written by
Bryon Fuchs
This page left blank intentionally
Disclaimer
The contents of this report reflect the views of the author or authors who are responsible for the facts and the accuracy of the data presented herein. The contents do not reflect the official views of the North Dakota Department of Transportation or the Federal Highway Administration. This report does not constitute a standard, specification, or regulation.
This page left blank intentionally
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division
I
TABLE OF CONTENTS
Purpose and Need ............................................................................................................. 1
Objective ............................................................................................................................ 1
Location ............................................................................................................................. 1
Traffic ................................................................................................................................. 3
Design ................................................................................................................................ 3
Construction ...................................................................................................................... 4
Testing ....................................................................................................................... 4
Post Construction Analysis ........................................................................................ 5
Evaluation .......................................................................................................................... 9
Control Section 1 ....................................................................................................... 9
Control Section 2 ..................................................................................................... 11
Experimental Section ............................................................................................... 13
Summary .......................................................................................................................... 15
Recommendation ............................................................................................................ 16
Appendix A: Mix Design ................................................................................................A-1
Appendix B: Load Transfer ...........................................................................................B-1
Appendix C: Compressive Strength ............................................................................ C-1
Appendix D: Flexural Strength..................................................................................... D-1
Appendix E: Freeze/Thaw ..............................................................................................E-1
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division
II
This page left blank intentionally
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 1
Dowel Bar Retrofit Mix MR0301 ND 2003-03
Purpose and Need
The North Dakota Department of Transportation (NDDOT) has been constructing
dowel bar retrofit projects since 1995 to restore load transfer across transverse joints in
plain jointed concrete pavements. While this rehabilitation has worked to restore load
transfer, the patch mix material previously used has had caused durability problems.
There are several commercially available patch mixes on the market and the
NDDOT had used a number of them. The mixes were considered expensive and
suffered from durability problems such as; raveling, shrinkage cracks, and spalling. The
mixes set up very quickly. This can lead to little or no mix under the dowel bar which
has led to the patch mix material breaking loose in the slot and losing load transfer.
There was a need for a low cost patch mix material using locally available
materials. North Dakota State University (NDSU), Civil Engineering Department, had
developed a patch mix designed specifically for this purpose.
Objective
The objective of this applied research was to evaluate the patch mix developed
at NDSU.
Location
NDDOT project number AC-IM-8-094(041)342 (westbound lane) near exit 342
was selected to incorporate this applied research. The project was located on Interstate
94 between the West Fargo Interchange and the Red River. Please refer to Figure 1 on
the next page.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 2
AC-IM-8-094(041)342, West Fargo interchange to the Red River (WB-RP 342.4870 to 343.3035 is the location of the research project)
Figure 1 - Project Location.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 3
Traffic
Two-way traffic is provided in the following table from RP 342.803 to 343.800.
Year Passenger Trucks Total 30th Max Hour Two-way Rigid ESALs 2002 10,550 2,050 12,600 1,260 2,870 2004 12,300 1,800 14,100 1,410 2,520 2006 13,325 2,275 16,600 1,560 2,685
Design
The design of the patch mix material was conducted by NDSU. Provided below
is a summary of the information that was presented to the contractor in order to
incorporate this experimental patch mix material onto the project. Refer to Appendix A
for the entire submittal package.
Description This work shall consist of retrofitting approximately one-half lane mile of epoxy-
coated dowel bars into existing concrete pavement using an experimental concrete mix.
Section 570 of the 2002 edition of the NDDOT Standard Specifications for Road and
Bridge Construction shall govern except where noted below.
Material 1. Patching Material. “Concrete Patch Mix ” shall be a mix prepared using the
following mix design:
Material Per CY Quantities
Cement (Type III – Lehigh) 850 lbs
Water 255 lbs
Fine Aggregate (Section 816.01) 1079 lbs
Coarse Aggregate (Section 816.02 – Granite) 1526 lbs
Air-entraining Admixture (Master Builders – Pave Air) 2.975 fl-oz
Accelerating Admixture (Master Builders – Pozzolith NC 534) 340 fl-oz
Water Reducer (Super Plasticizer) (Master Builders – Rheobuild 3000FC) 102 fl-oz
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 4
• The Dowel Bar Retrofit Mix shall have the following properties:
Maximum Water to Cement (W/C) Ratio 0.30
Slump 9” ± 1”
Air 6% ± 1%
Construction The primary contractor for project number AC-IM-8-094(041)342 was Wanzek
Construction, Inc located in Fargo, ND. The work related to the dowel bar retrofit was
subcontracted to Highway Services / Penhall Company (Penhall) located in Rogers,
MN.
The project engineer on this project was Joe Peyerl of the Fargo District,
NDDOT. The inspectors on this project were Robin Bellmore and Larry Ostenson from
the Fargo District.
The following personnel from Materials and Research Division were present on
site for the construction of the experimental dowel bar mix; Bryon Fuchs, Mike Marquart,
Steven Henrichs, Kyle Evert, and Tony Gross.
The experimental mix was change ordered onto this project at a cost of $39.60
per dowel bar. The bid price using “Five Star” patch mix was $25.00 per dowel bar.
The bid price was for approximately 1,056 bars.
The construction of the experimental mix occurred on August 14, 2003. The
contractor started placing the experimental mix in the dowel bar slots at 9:15 am. The
weather on this day during construction had an average temperature of 86°F, average
wind speed of 20 mph (gusts – 20 to 30 mph), 48% relative humidity and sunshine.
Testing
Throughout construction of the experimental mix, tests were conducted. The
tests were completed at the start of construction (set A), when approximately 25% (set
B), 50% (set C) and 75% (set D) of the mix was placed.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 5
The following table lists the averages for the four sets of tests conducted:
Test Set A Set B Set C Set D
Air (%) 5.1 5.5 4.3 5.1
Slump (in) 9.00 8.75 8.50 7.50
6-hr Comp Strength (psi) 5,060 5,610 5,390 5,110
7-day Comp Strength (psi) 8,820 9,180 9,990 9,280
28-day Comp Strength (psi) 10,260 10,370 11,370 11,280
28-day Flex Strength (psi) 980 1,100 1,090 1,190
Freeze/Thaw Durability-300 cycles (Factor) 93.1 89.8 98.9 96.9
Post Construction Analysis
The experimental project site was visited on September 24, 2003 and again on
October 8, 2003. Using an FWD, the load transfer across the transverse joints were
tested on October 14, 2003.
Three different sections were evaluated for visual distresses and load transfer.
Each section contains 72 transverse joints or 432 dowel bar slots. The following table
identifies the differences in each section.
Section Location Description
Control Section 1 RP 343.2082 to 343.3035 Five Star Mix used on majority of project
Experimental Section RP 343.1111 to 343.2067 MR0301 Mix
Control Section 2 RP 342.4870 to 343.0546 Five Star Mix using granite aggregate as used in the MR0301 Mix
Visual distresses were noted in each of the sections. The primary distress in
each section was longitudinal shrinkage cracks between the patch mix and existing
concrete. However, the experimental section had more longitudinal shrinkage cracks
than the other two sections evaluated. The depth of the shrinkage cracks was unknown
as cores were not taken.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 6
Provided in the following table is a summary of the sections evaluated.
Control Section 1 Experimental Section Control Section 2
Date of Construction 6-27-03 8-14-03 8-15-03
Average (high) Temp (°F) 58 (68) 86 (90) 86 (91) Average Wind Speed (gusts) (mph) 9 (N/A) 20 (23-30) 11 (N/A)
Humidity 78% 48% 64%
6-hour Comp Breaks (psi) 7,080 5,290 4,850
Load Transfer 97.1% 88.6% 84.6%
Production Rate 143 slots/hr 54 slots/hr 156 slots/hr
Percentage of slots distressed
Percentage of slots distressed 1.4% 32.4% 3.5%
Based on the above table, there were several items that stood out and they are
as follows:
• Environmental conditions
• Load transfer efficiency
• Production rate
• Longitudinal shrinkage cracks
Several of these items may have been caused by the same thing. The one item
that is not tied to the others is the production rate. The production rates in the control
sections were nearly three times the production rate than in the experimental section.
This was attributed to the mixing time requirements. Fifteen minutes of mix time was
substantially longer than the mixing time required for the current proprietary mixes (two
– three minutes.) The use of admixtures required more mixing time in order for them to
work as intended which slows production.
The increase in longitudinal shrinkage cracks in the experimental section may be
the result of either the environmental conditions, the use of a water reducing admixture
or both. The Portland Cement Association (PCA) publishes a book titled Design and
Control of Concrete Mixtures, 14th Edition states that water reducing admixtures may
cause an increase in drying shrinkage. The same publication also states that when
using high-range water reducers (this project used a high-range water reducer), the
drying shrinkage is comparable to concretes without high-range water reducers when
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 7
the water to cement ratios remains the same. Another publication, Properties of
Concrete, Fourth Edition written by A. M. Neville states lignosulfonate-based water
reducing admixtures (not used on this project) increase shrinkage, but other water
reducing admixtures do not affect shrinkage. This same publication also states that
super plasticizers (used on this project) do not influence shrinkage. Based on these two
sources, the water reducing admixture used should not have caused an increase in
longitudinal shrinkage in the experimental mix.
Based on the above information, environmental effects appear to have played a
major role in the longitudinal shrinkage cracks. Based on Figure 13-8 in the publication
Design and Control of Concrete Mixtures, 14th Edition, the rate of evaporation was
calculated for the mixes on the day they were placed. The exact concrete temperature
during placement was unknown in the two control sections and a reasonable
temperature was assumed. Provided in the following table was the rate of evaporation
calculated along with the input data.
Section Air Temperature Humidity Concrete
Temperature Wind Speed Rate of Evaporation
Control #1 58° F 78% *60° F 9 mph 0.035 lb (ft2/hr)
Control #2 86° F 64% *78° F 11 mph 0.04 lb (ft2/hr)
Experimental 86° F 48% 78° F 20 mph 0.18 lb (ft2/hr) *Assumed concrete temperature
As seen in the table above, the rate of evaporation in the experimental section far
exceeded those in the control sections. The wind speed was the major factor in this.
Even though curing compound was applied immediately, the wind will dry the pre-
wetted slot prior to the placement of the grout and the experimental mix. The other
factor that is not seen here is the temperature of the surrounding PCC Pavement.
During summer months, when the air temperature is around 90°F, the PCC pavement
can reach temperatures of 110°F plus. At these temperatures, the heat from the
pavement may also have contributed to the evaporation of water.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 8
Local PCC pavement temperature data (RWIS site at Red River Bridge, I-94) is
not available for the immediate area on August 14 & 15, 2003, however data was
available for June 27, 2003. The PCC pavement temperature stated on the previous
page is from another site with very similar environmental conditions (sun, wind, etc) on
these days (RWIS site west of Jamestown, ND, I-94).
Using RWIS data, the difference in pavement temperature ranged from
approximately 20°F to 42°F lower in June compared to August. This temperature
difference was important as it may indicate that the Experimental mix and Control
Section #2 mix set up quicker than Control Section #1 mix, which may result in a slightly
poorer bond to the existing concrete. The difference in the average ambient air
temperature was 28°F lower in June compared to August.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 9
Evaluations
Materials and Research conducted the first evaluation of the dowel bar slots on
September 28, 2004. The final evaluation was conducted on October 26, 2005. Control
section 1, control section 2, and the experimental section were evaluated visually for
distresses. Load transfers across the joints were performed on these sections with a
FWD.
Control Section 1
Photo 1 shows an overall view of control section 1.
Overall, control section 1 looks good. The number of visible distresses identified
has nearly doubled but the load transfer efficiency has remained the same. Control
section #1 is outperforming the other sections with lower visible distresses and higher
load transfer efficiency.
Provided in the following table is the percent of slots (there is a total of 432 slots)
with distresses in control section 1 and average load transfer efficiency within this
section. The percentage of transverse cracks is slightly lower than one year ago but the
amount of coreboard failures are up. The location of some transverse cracks suggests
that they may be the initial stages of coreboard failures. Coreboard failures are a result
of misalignment of the coreboard within the slot (coreboard does not remain in the joint).
Photo 1 - Overall view of control section 1.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 10
Control Section 1 Distress / Load Transfer Date
Visible Long. Cracks Transverse Crack Coreboard Failure Load Transfer October 2003 1.4% 0.0% 0.0% 97.1%
September 2004 9.3% 2.1% 0.5% 93.9%
October 2005 16.9% 1.9% 1.9% 93.6%
Photo 2 - Typical joint in control section 1.
Photo 3 - Spalling at joint and dowel bar slot.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 11
Control Section 2
Photo 5 shows an overall view of control section 2.
Overall, control section 2 looks OK. There has been a substantial increase in the
number of visible distresses identified in the period of a year and load transfer efficiency
has dropped. As the number and severity of the distresses increase, it is anticipated
that the load transfer will continue to drop in this section.
Provided in the following table is the percent of slots (there is a total of 432 slots)
with distresses in control section 2 and average load transfer efficiency within this
Photo 4 - Coreboard failure in control section 1.
Photo 5 - Overall view of control section 2.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 12
section. The location of some transverse cracks suggests that they may be the initial
stages of coreboard failures. Coreboard failures are a result of misalignment of the
coreboard within the slot (coreboard does not remain in the joint).
Control Section 2
Distress / Load Transfer Date Visible Long. Cracks Transverse Crack Coreboard Failure Load Transfer
October 2003 3.5% 0.2% 0.2% 84.6%
September 2004 18.3% 2.1% 0.2% 84.1%
October 2005 51.6% 33.3% 6.3% 80.5%
Photo 6 - Typical joint in control section 2 - spall area is in the original PCC pavement.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 13
Experimental Section
Photo 7 shows an overall view of the experimental section.
Overall, the experimental section is experiencing the most visible distresses of
the three sections evaluated. There has been an increase in the number of visible
distresses identified with a decrease in load transfer efficiency. As the number and
severity of the distresses increase, it is anticipated that the load transfer will continue to
drop in this section.
Provided in the following table is the percent of slots (there is a total of 432 slots)
with distresses in the experimental section and average load transfer efficiency within
this section. The location of some transverse cracks suggests that they may be the
initial stages of coreboard failures. Coreboard failures are a result of misalignment of
the coreboard within the slot (coreboard does not remain in the joint).
Experimental Section Distress / Load Transfer Date
Visible Long. Cracks Transverse Crack Coreboard Failure Load Transfer October 2003 32.4% 0.0% 0.7% 88.6%
September 2004 50.9% 1.2% 3.0% 83.1%
October 2005 79.6% 5.3% 4.6% 78.5%
Photo 7 - Overall view of the experimental section.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 14
Photo 8 - Typical joint in experimental section.
Photo 9 - Transverse crack location is likely the early signs of a coreboard failure.
Transverse crack
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 15
Summary
The production rates achieved during construction with the experimental mix will
not allow the experimental mix to be competitive on a construction cost basis with other
proprietary mixes currently used.
The long-term performance and continued load transfer of dowel bar retrofits
relies on the performance of the concrete patch mix and dowel bar itself. Over the
evaluation period, all sections experienced an increase in visible distresses. However,
the experimental mix has also shown more distresses than control section 1 or control
section 2. The load transfer efficiency is significantly lower in the experimental section
and control section 2 compared with control section 1. Provided in the following table is
a summary of the distress (in terms of percentage of slots) and load transfer efficiency
observed or measured to date.
Control Section 1 Experimental Section Control Section 2 Distress Oct-03 Sep-04 Oct-05 Oct-03 Sep-04 Oct-05 Oct-03 Sep-04 Oct-05
Visible crack-long. 1.4% 9.3% 16.9% 32.4% 50.9% 79.6% 3.5% 18.3% 51.6%
Transverse crack 0.0% 2.1% 1.9% 0.0% 1.2% 5.3% 0.2% 2.1% 33.3%
Coreboard 0.0% 0.5% 1.9% 0.7% 3.0% 4.6% 0.2% 0.2% 6.3%
Load Transfer 97.1% 93.9% 93.6% 88.6% 83.1% 78.5% 84.6% 84.1% 80.5%
Where as the load transfer and distress in control section 1 is relatively stable,
distress continues to increase and load transfer continues to decrease in the
experimental section and control section 2.
It is believed that the environmental conditions at the time of construction are, in
part, responsible for the distress noted initially and in subsequent evaluations. The
ambient air temperature, wind speed, and temperature of the surrounding concrete
have a dramatic affect on the rate of evaporation and rate of hydration of the concrete
patch mix.
Dowel Bar Retrofit Mix MR0301 ND 2003-03 Final Report
North Dakota Department of Transportation Materials & Research Division 16
The decline in load transfer efficiency in the experimental section and in control
section 2 appears to be related to the increased distress in the concrete patch mix for
these sections. Distress in control section 1 although increasing, is relatively low and
stable, and the load transfer efficiency for this section remains in the 90% plus range.
Recommendations
It is recommended that the NDDOT continue using the proprietary mixes
currently allowed in the standard specifications due to higher costs and poor
performance of the experimental mix.
It is recommended that special attention is given to the location of coreboards
after the dowel bar mix is placed. Coreboard failures can be reduced or eliminated if
the coreboard remains in the joint and not allowed to move into the dowel bar slot when
placing the concrete patch mix.
It is also recommended that tighter controls be placed on the allowable
environmental conditions at the time that concrete patch mix is being placed. The
effects of temperature, humidity, and wind speed can dramatically affect the rate of cure
and final condition of the concrete patch mix. These factors have been shown to
contribute to the formation of shrinkage cracks; as well as the development of bonding
problems with the side walls of the existing concrete. Ambient air temperatures must
be, at a minimum, within the manufacturer’s recommendations at the time of placing the
concrete patch mix. These concerns should be addressed in the Special Provisions for
future Dowel Bar Retrofit projects.
A-1
Appendix A: Mix Design
A-2
North Dakota Department of Transportation Dowel Bar Retrofit Mix “MR0301”
Description
This work shall consist of retrofitting approximately one-half lane mile of epoxy-coated dowel bars into existing concrete pavement using an experimental concrete mix. Section 570 of the 2002 edition of the NDDOT Standard Specifications for Road and Bridge Construction shall govern except where noted below. Material 1. Patching Material. “Concrete Patch Mix ” shall be a mix prepared using the
following mix design:
Material Per CY Quantities Cement 850 lbs Water 255 lbs Fine Aggregate 1079 lbs Coarse Aggregate 1526 lbs Air-entraining Admixture 2.975 fl-oz Accelerating Admixture 340 fl-oz Water Reducer (Super Plasticizer) 102 fl-oz
• The cement shall be a Type III (Lehigh) meeting the requirements of Section
804.01.
• The fine aggregate shall meet the requirements of Section 816.01 and have the following gradation:
Sieve Size % Passing 3/8” 100 #4 95-100 #8 45-65
#50 10-30 #100 0-10
#200 (Max) 3 • The coarse aggregate shall be granite obtained from Ortonville, MN. The
owner of the pit is Aggregate Industries. The coarse aggregate shall meet the requirements of Section 816.02 and have the following gradation:
Sieve Size % Passing 3/8” 100 #4 25-30 #8 10-20
#200 (Max) 1
A-3
• The concrete admixtures shall be the following:
Air-entraining Master Builders – Pave-Air Accelerator Master Builders – Pozzolith NC534 Water Reducer (Super plasticizer) Master Builders – Rheobuild 3000FC
• The Dowel Bar Retrofit Mix shall have the following properties:
Maximum Water to Cement (W/C) Ratio 0.30 Slump 9” ± 1” Air 6% ± 1%
Construction Requirements 1. A trial batch shall be conducted prior to placement in the slots in order to test the
material properties. Minor adjustments may be required in order to meet the mix requirements as stated in Section 570 of the specifications and the changes indicated above.
2. A grout mix shall be applied to the dowel bar slot after pre-wetting the dowel bar slot and prior to placement of the MR0301 patch mix in the slot. The patch mix shall be placed in the slot prior to the grout mix drying. Drying of the grout mix will be considered when the grout mix starts to turn white. If the grout mix starts to dry, the grout shall be removed and cleaned according to Section 570.04 C.2.c.
3. The recommended mixing procedure is as follows: a. Place the coarse aggregate into the mixer. b. Combine the super plasticizer and water. c. Add half the quantity of water with super plasticizer to the coarse
aggregate and mix for two minutes before adding other components. d. Add the fine aggregate (the air entraining admixture shall be added to the
fine aggregate as it is being added to the mix). e. Add the cement. f. Add the remaining quantity of water with super plasticizer. g. Add the accelerating admixture. h. After the last component is added, mixing shall continue for additional five
minutes and then stop the mixer for three minutes and then resume mixing for an additional two minutes.
4. The curing compound shall be applied immediately after the patch mix is finished. Method of measurement and basis of Payment
Installation of the Dowel Bars will be measured and paid for as “Dowel Bar Retrofit Type A” for each dowel installed and accepted by the Engineer. Payment shall be full compensation for all labor, equipment, and materials necessary to complete the work as specified.
A-4
This page left blank intentionally
B-1
Appendix B: Load Transfer
B-2
Control Section #1
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
343.2082 91.4% 91.2% 91.9% 343.2094 99.6% 96.5% 95.9% 343.2107 100.3% 99.7% 95.8% 343.2123 98.6% 93.8% 92.7% 343.2136 95.6% 97.3% 96.2% 343.2148 93.5% 94.6% 94.8% 343.2162 99.4% 98.1% 93.2% 343.2176 92.8% 94.6% 90.9% 343.2190 97.2% 98.5% 97.2% 343.2201 94.9% 94.6% 92.6% 343.2214 96.1% 97.0% 95.8% 343.2229 99.8% 96.0% 95.8% 343.2243 95.3% 98.1% 93.8% 343.2254 96.3% 95.6% 95.0% 343.2268 95.6% 95.2% 92.9% 343.2282 98.4% 95.6% 92.5% 343.2297 96.7% 93.2% 87.8% 343.2308 95.7% 93.8% 88.7% 343.2321 93.6% 90.9% 88.1% 343.2337 95.4% 93.9% 85.8% 343.2350 96.3% 95.1% 93.9% 343.2362 94.6% 92.5% 90.6% 343.2375 96.8% 91.2% 90.2% 343.2390 98.9% 96.0% 95.5% 343.2403 99.1% 91.7% 91.5% 343.2415 96.2% 93.1% 95.3% 343.2426 95.4% 92.7% 94.2% 343.2442 99.8% 96.2% 94.9% 343.2456 98.7% 98.2% 95.5% 343.2467 100.9% 97.0% 94.4% 343.2481 97.5% 96.9% 94.5% 343.2494 98.7% 97.1% 92.6% 343.2508 99.7% 97.1% 96.8% 343.2521 99.1% 98.0% 98.0% 343.2533 98.7% 95.7% 95.6% 343.2547 96.7% 93.8% 95.7% 343.2561 97.9% 95.6% 96.7% 343.2573 96.4% 91.9% 94.8% 343.2587 95.8% 94.1% 93.0% 343.2601 96.6% 93.1% 92.4% 343.2615 100.2% 93.6% 94.3% 343.2628 102.1% 94.3% 96.8%
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
343.2641 100.6% 96.0% 96.4% 343.2655 99.8% 93.4% 96.5% 343.2670 98.2% 95.9% 93.4% 343.2681 97.3% 94.9% 94.5% 343.2695 94.1% 92.8% 98.5% 343.2710 100.2% 92.3% 94.9% 343.2723 97.7% 93.2% 97.7% 343.2736 97.5% 89.4% 88.4% 343.2750 98.6% 94.5% 97.3% 343.2765 95.3% 94.5% 91.6% 343.2779 97.4% 93.0% 93.3% 343.2791 94.2% 87.9% 86.5% 343.2804 92.6% 95.0% 95.1% 343.2819 95.5% 89.3% 88.4% 343.2833 97.9% 92.8% 92.7% 343.2845 99.4% 92.2% 95.8% 343.2858 98.3% 92.0% 94.2% 343.2873 99.5% 93.1% 95.2% 343.2887 98.6% 90.6% 95.4% 343.2898 96.6% 93.2% 92.7% 343.2910 97.4% 93.8% 91.6% 343.2926 94.7% 92.7% 88.0% 343.2939 96.1% 95.0% 91.2% 343.2952 99.3% 90.7% 90.3% 343.2964 99.0% 95.0% 95.0% 343.2979 96.1% 89.5% 94.7% 343.2995 97.4% 86.8% 92.2% 343.3005 95.1% 85.9% 93.0% 343.3019 93.1% 88.9% 94.0% 343.3035 94.1% 96.6% 98.8%
B-3
Load TransferControl Section #1
0%10%20%30%40%50%60%70%80%90%
100%34
3.20
82
343.
2094
343.
2108
343.
2123
343.
2135
343.
2147
343.
2162
343.
2176
343.
2190
343.
2200
343.
2214
343.
2229
343.
2242
343.
2255
343.
2268
343.
2282
343.
2296
343.
2309
343.
2321
343.
2336
343.
2350
343.
2362
343.
2375
343.
2390
Station (RP+Feet)
Perc
enta
ge
14-Oct-03 28-Sep-04 26-Oct-05
Load TransferControl Section #1
0%10%20%30%40%50%60%70%80%90%
100%
343.
2403
343.
2415
343.
2426
343.
2442
343.
2456
343.
2467
343.
2481
343.
2494
343.
2508
343.
2518
343.
2531
343.
2546
343.
2561
343.
2573
343.
2587
343.
2600
343.
2615
343.
2627
343.
2641
343.
2655
343.
2669
343.
2682
343.
2694
343.
2710
Station (RP+Feet)
Per
cent
age
14-Oct-03 28-Sep-04 26-Oct-05
B-4
Load TransferControl Section #1
0%10%20%30%40%50%60%70%80%90%
100%34
3.27
23
343.
2737
343.
2751
343.
2765
343.
2778
343.
2790
343.
2804
343.
2819
343.
2833
343.
2843
343.
2857
343.
2872
343.
2886
343.
2898
343.
2910
343.
2925
343.
2938
343.
2951
343.
2963
343.
2979
343.
2993
343.
3005
343.
3019
343.
3035
Station (RP+Feet)
Per
cent
age
14-Oct-03 28-Sep-04 26-Oct-05
B-5
Control Section #2
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
342.4857 87.0% 86.0% 83.4% 342.4870 76.1% 83.6% 75.6% 342.4883 81.3% 88.3% 85.1% 342.4898 82.4% 83.6% 77.2% 342.4913 65.5% 83.6% 69.6% 342.4924 80.9% 82.6% 73.4% 342.4935 85.2% 88.8% 84.0% 342.4951 79.8% 71.2% 70.1% 342.4964 79.5% 73.6% 71.4% 342.4982 71.8% 64.6% 66.7% 342.4993 84.1% 78.8% 81.6% 342.5007 65.3% 65.2% 60.0% 342.5021 83.7% 79.0% 79.9% 342.5035 72.9% 74.5% 67.9% 342.5048 82.4% 76.8% 73.1% 342.5061 86.6% 79.8% 78.5% 342.5075 82.6% 87.6% 81.9% 342.5090 86.1% 81.5% 77.7% 342.5102 90.5% 89.1% 88.8% 342.5115 89.3% 85.8% 79.0% 342.5131 91.1% 87.7% 84.0% 342.5144 88.9% 89.2% 84.2% 342.5157 86.3% 88.2% 84.7% 342.5169 90.4% 88.2% 82.9% 342.5183 89.2% 87.9% 84.3% 342.5199 84.9% 83.4% 80.3% 342.5211 88.7% 85.4% 85.4% 342.5225 86.1% 82.3% 79.8% 342.5240 91.2% 88.9% 90.7% 342.5253 89.2% 91.8% 88.4% 342.5267 96.3% 91.5% 89.2% 343.0000 76.0% 79.4% 75.9% 343.0015 81.9% 81.7% 70.9% 343.0029 90.4% 87.7% 81.0% 343.0041 75.8% 81.8% 78.4% 343.0055 86.2% 86.0% 80.8% 343.0069 60.5% 62.8% 57.7% 343.0082 87.3% 87.1% 81.4% 343.0095 89.8% 90.5% 84.4% 343.0108 83.7% 82.8% 80.2% 343.0122 86.6% 84.0% 82.6% 343.0137 90.3% 91.3% 89.8%
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
343.0149 92.1% 87.4% 80.9% 343.0162 89.3% 88.2% 87.1% 343.0177 91.4% 90.3% 85.4% 343.0190 88.2% 89.5% 85.4% 343.0203 89.7% 86.2% 83.0% 343.0216 80.8% 80.5% 74.7% 343.0230 86.0% 87.8% 87.6% 343.0246 94.1% 91.9% 89.7% 343.0258 90.5% 83.8% 85.5% 343.0272 92.1% 89.2% 90.3% 343.0287 72.0% 77.6% 71.8% 343.0301 88.2% 86.4% 84.4% 343.0314 82.7% 78.1% 74.3% 343.0327 83.2% 79.3% 73.2% 343.0342 89.8% 85.0% 82.6% 343.0357 95.6% 93.7% 90.9% 343.0370 86.5% 85.5% 79.1% 343.0383 87.6% 88.8% 84.4% 343.0398 76.9% 78.5% 72.5% 343.0411 88.1% 84.8% 80.9% 343.0424 84.2% 87.7% 80.5% 343.0437 85.0% 82.6% 79.7% 343.0453 88.3% 87.4% 85.3% 343.0467 89.2% 89.4% 87.0% 343.0478 83.7% 81.6% 77.9% 343.0493 73.2% 78.9% 77.2% 343.0507 90.3% 89.7% 85.1% 343.0520 83.0% 86.9% 84.5% 343.0534 85.2% 83.5% 82.0% 343.0546 76.9% 89.3% 90.7%
B-6
Load TransferControl Section #2
0%10%20%30%40%50%60%70%80%90%
100%34
2.48
57
342.
4870
342.
4883
342.
4898
342.
4913
342.
4924
342.
4935
342.
4951
342.
4964
342.
4982
342.
4992
342.
5007
342.
5020
342.
5035
342.
5047
342.
5061
342.
5075
342.
5090
342.
5102
342.
5115
342.
5131
342.
5144
342.
5156
342.
5168
Station (RP+Feet)
Per
cent
age
14-Oct-03 28-Sep-04 26-Oct-05
Load TransferControl Section #2
0%10%20%30%40%50%60%70%80%90%
100%
342.
5183
342.
5199
342.
5212
342.
5225
342.
5240
342.
5254
342.
5267
343.
0000
343.
0015
343.
0029
343.
0041
343.
0053
343.
0068
343.
0082
343.
0094
343.
0107
343.
0122
343.
0137
343.
0148
343.
0160
343.
0176
343.
0190
343.
0202
343.
0215
Station (RP+Feet)
Perc
enta
ge
14-Oct-03 28-Sep-04 26-Oct-05
B-7
Load TransferControl Section #2
0%10%20%30%40%50%60%70%80%90%
100%34
3.02
30
343.
0246
343.
0258
343.
0272
343.
0288
343.
0301
343.
0313
343.
0327
343.
0344
343.
0358
343.
0370
343.
0383
343.
0398
343.
0412
343.
0424
343.
0438
343.
0452
343.
0466
343.
0478
343.
0493
343.
0508
343.
0521
343.
0534
343.
0546
Station (RP+Feet)
Perc
enta
ge
14-Oct-03 28-Sep-04 26-Oct-05
B-8
Experimental Section
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
343.1111 91.1% 85.1% 85.6% 343.1123 94.1% 91.8% 91.3% 343.1136 88.5% 86.1% 88.2% 343.1152 85.5% 84.3% 86.0% 343.1165 91.8% 85.6% 80.5% 343.1178 91.8% 88.9% 89.4% 343.1191 89.6% 84.9% 72.8% 343.1205 75.2% 74.0% 72.5% 343.1220 83.4% 78.5% 69.8% 343.1232 93.3% 90.4% 91.2% 343.1245 89.6% 89.1% 84.9% 343.1260 92.3% 93.6% 94.1% 343.1273 90.6% 85.7% 67.5% 343.1287 87.8% 83.0% 80.3% 343.1300 89.6% 86.8% 86.0% 343.1314 91.5% 94.3% 95.7% 343.1330 92.5% 85.4% 81.5% 343.1343 89.6% 84.5% 75.7% 343.1357 89.4% 77.1% 67.6% 343.1371 88.8% 89.2% 85.2% 343.1384 92.1% 81.0% 69.4% 343.1396 92.5% 83.9% 70.0% 343.1408 90.3% 86.5% 86.0% 343.1422 90.6% 89.5% 87.3% 343.1437 80.0% 75.3% 74.0% 343.1449 88.9% 88.0% 89.1% 343.1462 88.5% 84.6% 77.9% 343.1477 88.5% 86.9% 86.7% 343.1491 87.9% 79.6% 75.1% 343.1504 87.4% 84.9% 79.4% 343.1517 90.1% 90.9% 86.8% 343.1531 90.8% 88.6% 83.1% 343.1546 91.3% 90.6% 81.0% 343.1557 87.6% 86.5% 87.8% 343.1570 92.9% 84.8% 82.5% 343.1585 86.6% 86.6% 89.6% 343.1599 87.7% 83.6% 77.7% 343.1613 86.8% 85.7% 88.4% 343.1625 84.3% 80.0% 80.4% 343.1640 88.7% 80.2% 70.3% 343.1654 80.3% 74.6% 67.5% 343.1666 82.1% 78.7% 70.5%
Station (mile.feet)
2003 Load Transfer
2004 Load Transfer
2005 Load Transfer
343.1679 84.1% 83.2% 84.5% 343.1694 92.9% 84.5% 73.8% 343.1707 85.2% 80.1% 75.3% 343.1720 88.1% 73.4% 69.9% 343.1733 93.0% 81.3% 78.8% 343.1747 88.1% 84.3% 78.8% 343.1762 93.0% 86.0% 74.6% 343.1774 93.0% 85.9% 81.3% 343.1785 89.6% 79.2% 75.4% 343.1801 89.8% 82.6% 77.0% 343.1815 84.5% 74.8% 63.9% 343.1828 80.5% 65.7% 56.7% 343.1839 87.1% 75.7% 75.2% 343.1854 90.9% 83.8% 71.0% 343.1869 87.3% 75.1% 67.6% 343.1881 89.3% 81.3% 78.0% 343.1893 87.4% 77.9% 68.3% 343.1908 89.6% 92.7% 91.2% 343.1922 86.0% 81.8% 78.9% 343.1934 91.7% 84.8% 79.0% 343.1948 88.2% 81.3% 81.8% 343.1963 91.4% 82.0% 80.0% 343.1978 86.0% 74.4% 66.1% 343.1987 94.7% 92.7% 83.4% 343.1999 89.9% 88.5% 83.9% 343.2014 94.2% 86.1% 81.1% 343.2028 91.4% 78.4% 73.5% 343.2040 90.4% 78.1% 69.6% 343.2053 87.8% 76.9% 66.9% 343.2067 73.4% 63.9% 60.7%
B-9
Load TransferExperimental Section
0%10%20%30%40%50%60%70%80%90%
100%34
3.11
11
343.
1123
343.
1137
343.
1152
343.
1166
343.
1178
343.
1191
343.
1206
343.
1219
343.
1233
343.
1245
343.
1261
343.
1274
343.
1287
343.
1300
343.
1314
343.
1331
343.
1344
343.
1357
343.
1371
343.
1383
343.
1395
343.
1408
343.
1422
Station (RP+Feet)
Perc
enta
ge
14-Oct-03 28-Sep-04 26-Oct-05
Load TransferExperimental Section
0%10%20%30%40%50%60%70%80%90%
100%
343.
1437
343.
1449
343.
1462
343.
1477
343.
1491
343.
1504
343.
1515
343.
1531
343.
1546
343.
1556
343.
1570
343.
1585
343.
1599
343.
1613
343.
1625
343.
1639
343.
1653
343.
1667
343.
1680
343.
1693
343.
1707
343.
1721
343.
1733
343.
1746
Station (RP+Feet)
Per
cent
age
14-Oct-03 28-Sep-04 26-Oct-05
B-10
Load TransferExperimental Section
0%10%20%30%40%50%60%70%80%90%
100%34
3.17
60
343.
1774
343.
1786
343.
1801
343.
1815
343.
1828
343.
1840
343.
1854
343.
1869
343.
1881
343.
1892
343.
1906
343.
1921
343.
1933
343.
1947
343.
1962
343.
1978
343.
1986
343.
1999
343.
2013
343.
2027
343.
2040
343.
2052
343.
2067
Station (RP+Feet)
Perc
enta
ge
14-Oct-03 28-Sep-04 26-Oct-05
C-1
Appendix C: Compressive Strength
C-2
6-Hour Compressive Break – Five Star
C-3
6-Hour Compressive Break – Five Star with Granite Aggregate
C-4
6-Hour Compressive Break – Mix MR0301-Set A
C-5
6-Hour Compressive Break – Mix MR0301-Set B
C-6
6-Hour Compressive Break – Mix MR0301-Set C
C-7
6-Hour Compressive Break – Mix MR0301-Set D
C-8
7-Day Compressive Break – Mix MR0301-Set A
C-9
7-Day Compressive Break – Mix MR0301-Set B
C-10
7-Day Compressive Break – Mix MR0301-Set C
C-11
7-Day Compressive Break – Mix MR0301-Set D
C-12
28-Day Compressive Break – Mix MR0301-Set A
C-13
28-Day Compressive Break – Mix MR0301-Set B
C-14
28-Day Compressive Break – Mix MR0301-Set C
C-15
28-Day Compressive Break – Mix MR0301-Set D
C-16
This page left blank intentionally
D-1
Appendix D: Flexural Strength
D-2
28-Day Flexural Strength Set A = 982 psi Set B = 1,099 psi Set C = 1,093 psi Set D = 1,188 psi
E-1
Appendix E: Freeze/Thaw
E-2