mats timeline for compliance

20
MATS Timeline

Upload: cleanairengr01

Post on 29-Nov-2014

123 views

Category:

Environment


0 download

DESCRIPTION

Utilities must comply with the new Mercury and Air Toxics Standards by April 16, 2015. This presentation discusses some of the upcoming milestones for compliance.

TRANSCRIPT

Page 1: MATS Timeline for Compliance

MATS Timeline

Page 2: MATS Timeline for Compliance

For most U.S. utilities, the compliance date for the Mercury and Air Toxics Standards (MATS)

is April 16, 2015

Page 3: MATS Timeline for Compliance

THAT’S LESS THAN 8 MONTHS AWAY

Page 4: MATS Timeline for Compliance

The compliance requirements are spelled out in Subpart UUUUU of 40 CFR Part 63

Page 5: MATS Timeline for Compliance

About 460 plants will be affected by these requirements

Page 6: MATS Timeline for Compliance

Compliance with the rule begins next April. Plants can demonstrate compliance through stack testing up to 12 months prior to this date, or….

Page 7: MATS Timeline for Compliance

They will have 180-days after 4/16 to demonstrate that they are meeting the

new emissions limits and work practices.

Page 8: MATS Timeline for Compliance

Unless they have filed for and weregranted a one-year extension.

In that case, the dates move to 2016.

Page 9: MATS Timeline for Compliance

There is a lot of work that needs to happen prior to next April. For example, utilities need to…

Page 10: MATS Timeline for Compliance

Submit the overall site-specific Monitoring Plan at least 60 days prior to any compliance tests or CEMS performance tests.

Example compliance test date of June 9-10

Page 11: MATS Timeline for Compliance

Submit a mercury CEMS Monitoring Plan by March 26, 2015.

Page 12: MATS Timeline for Compliance

Submit a CEMS QA/QC Plan prior to beginning any monitor certification tests.

Page 13: MATS Timeline for Compliance

Submit a site-specific Performance Evaluation Plan at least 60 days prior to any compliance or CEMS performance tests.

Page 14: MATS Timeline for Compliance

Notify the agency of compliance or CEMS performance test dates at least 60 days in advance.

Page 15: MATS Timeline for Compliance

Some compliance tests will consist of a 30-day performance test using the plant’s CEMS (or STMS) data.• Hg• PM• HCl

Page 16: MATS Timeline for Compliance

These CEMS must be certified PRIOR to that performance test.

RATA

Page 17: MATS Timeline for Compliance

Plants may opt to demonstrate ongoing PM and HCl compliance through quarterly testing instead of CEMS.

Page 18: MATS Timeline for Compliance

In those cases, the first quarterly test must be done within 180 days of the compliance deadline…

Page 19: MATS Timeline for Compliance

And must consist of three runs while the unit is operating at 90-110% of design capacity (or at maximum normal operating load).

Page 20: MATS Timeline for Compliance

For more information on MATS and MATS compliance

testing, contact CleanAir today.800-991-3300

[email protected]

Thanks!