MaxCell Installation Reports

BSNL Kerala Circle, Trivendrum, India

Amit DubeyMaxCell Market Manager - India

Page 2: MaxCell Installation Reports BSNL Kerala Circle, Trivendrum, India Amit Dubey MaxCell Market Manager - India

Date: 4 & 5th June 2010End User: BSNL Kerala Circle , Trivendrum Installer: MillikenVenue: StachueTelephone Exchange, TrivendrumClassification: Overlay

Amit DubeyMaxCell Market Manager - India

BSNL Trivendrum (India)

Installed Rope in 110-100mm Cable Installation EM

5621-3 MaxCell in 110-100mm duct overlay of 40-33mm duct

Page 3: MaxCell Installation Reports BSNL Kerala Circle, Trivendrum, India Amit Dubey MaxCell Market Manager - India

Section Conduit ID, mm

Existing Cable or sub duct OD mm

Pull Length

M

Sweeps, degrees

MaxCell Installations Cable Installation Final Fill

RatioStyle Time, min

Tension, kgs

OD, mm Time, min

Tension, kgs

1 100mm, 33mm

40 duct, empty

100, 100

Straight, straight

1x5621-3, 1x 3614-2

4, 5

1 Man

2 Man Hand Pull

18, 2 x

12mm

6, 6,8

2 Man HP 19.2%26.4 %

Remarks:-

- This trial was held in exchange compound because it required permission to open manhole and mainly because of coastal area and monsoon season all manhole were fill up with water.

- Formed a 100m lengthy 110-100 mm conduit, do sub-ducting with 40-33mm HDPE pipe .

- Overlay EM 5621-3 MaxCell in 110-100mm conduit, further installed EM 3614-2 MaxCell in empty 40-33 mm sub duct.

- Installed 18mm cable in EM 5621-3 MaxCell while 2 x 12mm in EM 3614-2 MaxCell in 40-33mm sub-duct successful.

- Concern BSNL Kerala Circle Chief General Manager (CGM) and his team agreed to discussed MaxCell application in monthly management meeting and to identify such site where duct is full and expansion and upgradation required in same route.

Date: 4 & 5th June 2010End User: BSNL Kerala Circle , Trivendrum Installer: MillikenVenue: StachueTelephone Exchange, TrivendrumClassification: Overlay

Amit DubeyMaxCell Market Manager - India

Installation Results:

Page 4: MaxCell Installation Reports BSNL Kerala Circle, Trivendrum, India Amit Dubey MaxCell Market Manager - India

Date: 4 & 5th June 2010End User: BSNL Kerala Circle , Trivendrum Installer: MillikenVenue: StachueTelephone Exchange, TrivendrumClassification: Overlay

Sub- ducting via 40-33mm in 110-100mm conduit

12mm Cable getting entry in 40-33mm sub duct

Amit DubeyMaxCell Market Manager - India

18mm cable getting enter in EM 5621-3 MaxCell 18mm cable pulling in EM

5621-3 MaxCell

Page 5: MaxCell Installation Reports BSNL Kerala Circle, Trivendrum, India Amit Dubey MaxCell Market Manager - India

Date: 4 & 5th June 2010End User: BSNL Kerala Circle , Trivendrum Installer: MillikenVenue: StachueTelephone Exchange, TrivendrumClassification: Overlay

Cable pulling in 40-33mm duct

Thanks for CGM Kerala Team

Amit DubeyMaxCell Market Manager - India

2nd Cable pulling in 2nd cell of EM 3614-221-3

MaxCell sub duct 40-33mm