may 8, 2012 commission presentation
DESCRIPTION
TRANSCRIPT
I-74 Iowa-Illinois Corridor
Presentation to:
Iowa DOT CommissionMay 8, 2012Ames, Iowa
Mitchell Dillavou– Director, Engineering Bureau
• Original bridge Original bridge opened.opened.
• Cost: $1.5 millionCost: $1.5 million
19351935
• Second bridge Second bridge opened.opened.
• Cost: $6.2 millionCost: $6.2 million
19601960
1970’s1970’s
• Iowa and Illinois took Iowa and Illinois took over ownershipover ownership
• Toll Booths Removed.Toll Booths Removed.
• I-74 was connected.I-74 was connected.
TodayToday• 2010 traffic: 61,500 2010 traffic: 61,500
vehicles per dayvehicles per day
• 2035 estimated 2035 estimated traffic: 98,500 VPDtraffic: 98,500 VPD
• Poor geometrics for Poor geometrics for an interstate routean interstate route
• The bridges are The bridges are functionally obsoletefunctionally obsolete
1998 Major Investment Study Needed Improvement Locations
I-74 Corridor Study Milestones
2000: I-74 Corridor Study began
2003: Draft Environmental Impact Study completed
2005: Preferred Alternative identified
2006: Main Span Bridge Type chosen
2007: Preliminary Engineering completed
2009: Final Environmental Impact Study, and
Federal Highway Admin. Record of Decision
Corridor Study Limits
Mississippi River Crossing
Preferred Alternative
•Approach view
•River view•Aerial view
•Bettendorf shoreline view
• Scheme 1 - Basket Handle True Arch Twin Bridge
•Motorist’s view
Finalist Bridge Types
•Scheme 2 - Modified Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers
•Motorist’s view
•Aerial view •River view
•Approach view
•Bettendorf shoreline view
Finalist Bridge Types
•Scheme 3 - Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers
•Approach view
•River view•Aerial view
•Bettendorf shoreline view
•Motorist’s view
Finalist Bridge Types
• Scheme 4 - Cable Stayed Single Bridge with Semi-Fan Stay Arrangement
•Approach view
•River view
•Motorist’s view
•Bettendorf shoreline view
•Aerial view
Finalist Bridge Types
Selected Alternative: Basket Handle True Arch Twin Bridge
I-74 Project Locations
Central Section Cost Estimate (YOE)
Central Section Design Preliminary Design• Completed in April 2009• $9.1 Million in Consultant Services (Iowa share)• $0.3 Million Iowa DOT Staff
Final Design• $9.7 Million expended to date (Iowa Share)• 71% Complete• $13.0 Million Consultant Services funds to be
expended (Iowa share)• $5.5 Million Iowa DOT Staff funds to be
expended
Iowa ROW Summary
ROW Purchased (Central & North Sections)• 47 Parcels• $6.9 Million
ROW to be Purchased (Central Section)• 79 Parcels• $16.9 Million
Illinois ROW Summary
ROW Purchased• 7 Parcels• $0.7 Million
ROW to be Purchased• 59 Parcels• $3.8 Million
Iowa Investment to Date
• ROW $ 6.9 Million• Design $19.5
Million• Construction $16.3
Million• Iowa DOT Staff $ 2.1 Million
Total $44.8 Million
Iowa Cost EstimatePhase I
2013-2017
ROW $16.9 M
Construction $13.7 M
Maintenance of Existing Bridges $ 2.3 M
Iowa DOT Staff $ 5.5 M
Consultant Engineering (design) $13.0 M
$51.4 M
Iowa Cost EstimatePhase II – Central Section
Beyond 2017, $ in YOEMain Span $118.2 M
Approach Span $123.1 M
Viaducts $128.9 M
Mainline Roadway $ 40.2 M
Bridge Demolition $ 15.3 M
Maintenance of Existing Bridges $ 3.5 M
Lighting, Signing, Landscaping, ITS $ 23.5 M
Consultant Engineering (Constr.) $ 40.9 M
Iowa DOT Staff $ 1.0 M
$494.6 M
Illinois Cost EstimatePhase II – Central Section
Beyond 2017, $ in YOE
Main Span $118.2 M
Approach Span $123.1 M
Viaducts & Mainline Roadway $356.1 M
Bridge Demolition $ 17.2 M
Lighting, Landscaping, ITS $ 10.1 M
Consultant Engineering (Constr.) $ 40.9 M
$665.6 M
Central Section Cost EstimateYOE
IOWA ILLINOIS
$494.6 M $665.6 M
Iowa Cost Estimate
Totals• Completed Work $ 44.8 M
• Phase I $ 51.4 M
• Phase II $494.6 M
• Phase III (North Section) $202.5 M
Total Cost $793.3 M
Anticipated Maintenance Cost (Iowa Share)
Option 1 – In service until 2025• Main Bridge $ 3.0
M• Approach Bridges $ 2.8
M• Total $ 5.8 MOption 2 – In service until 2035• Main Bridge $14.2
M• Approach Bridges $ 8.7
M• Total $22.9 M
Corridor Federal Funding
• Earmarks $74.6 Million• Unobligated Amount $ 7.2 Million
Questions?