  • 7/31/2019 Mba 205

    1/23

    OPERATIONS RESEARCH

    MBA Online Examination

    1)The following covers the scope for operations research (d)

    a)Industry & agriculture

    b)Defence

    c)Planning

    d)All

    2)The following covers the scope of OR in management (e)

    a)Allocation and distribution

    b)production and procurement

    c)functional areas

    d)R&D

    e)all

    3)_______ techniques have been used in planning, scheduling and controlling construction of dams(a)

    a)PERT & CPM

    b)transportation

    c)assignment

    d)none

    4)Phases of OR (e)

    a)Formulating the problem

    b)constructing a model and deriving a model

    c)deriving and testing

  • 7/31/2019 Mba 205

    2/23

    d)control and implementation

    e)all

    5)_______ model variables are completely defined and the outcomes are certain (b)

    a) probabilistic

    b)deterministic

    c)both

    d)none

    6)________ is used to solve problems in which either the objective function and /or one or more of the

    constraints are non-linear in nature. (a)

    a)non linear programming

    b)linear programming

    c)assignment

    d)Hungarian model

    7)_______ models are used to make a series of interrelated decisions for multistage problems (a)

    a)dynamic programming

    b)linear programming

    c)transportation

    d)non linear programming

    8)_______ is applied for situations which have multiple goals and objectives (b)

    a) linear programming

    b)goal programming

    c)non linear programming

  • 7/31/2019 Mba 205

    3/23

    d)none

    9)The computational procedure of _______ method is based on the fundamental property that the

    optimal solution to an LP problem , if it exists, occurs only at one of the corner points of the feasible

    region. (a)

    a)simplex

    b)BIG M model

    c)Hungarian

    d)goal programming

    10)If the objective function in an LP problem is max case, then the constraints are of (a)

    a)/ type

    c)=type

    d)all

    11)If the objective function of an LP problem is min case, then the inequality constraints should be

    converted in to equalities by by _____ s1 and _______ A1 (b)

    a)Adding, subtracting b) subtracting ,Adding

    c)subtracting, subtracting d) adding, adding

    12)If the objective function of an LP problem is min case, the constraints are of (a)

    a)>/ typeb)

  • 7/31/2019 Mba 205

    4/23

    14)In BIG M method ,________ variables should be added (b)

    a)semi variables b)artificial c)fixed d)decision

    15)Allocation should be made from north west corner region in ______ model of transportation

    problems. (a)

    a)NWC b)VAM c)LCM d)all

    16)In _______ method, row penalties and column penalties are taken by subtracting smallest and next

    smallest valued cells (b)

    a)NW C

    b)VAM method

    c)LCM method

    d) all

    17)The cell with least cost is taken for allocation initially in _______ method (a)

    a)least cost method

    18)For performing optimality test _______ can be used (d)

    a)stepping stone method

    b)MODI method

    c)only a

    d)both a and b

    19)For minimization of cost as objective function, under net contribution most ________ value should

    be taken (b)

    a)positive b)negative c)both d)none

  • 7/31/2019 Mba 205

    5/23

    20)For max case, under net contribution,_______ value should be taken. (a)

    a)+ve

    b)-ve

    c)none

    d)both

    21)________ method can be used for solving assignment problems (d)

    a)goal programming

    b)bellmans recursion

    c)objective programming

    d)Hungarian method

    22)Dynamic programming was originated in the year 1952 by (a)

    a)Richard Bellman

    b)dantzing

    c)George

    d)legrange

    23)________ principle of optimality forms the basis of dynamic programming techniques (a)

    a)Bellmans

    b)G.B.Dantzing

    c)both a &b

    d)none

    24)The situations that vary with time and are considered dynamic in nature and the technique dealing

    with these types of problems is called (b)

  • 7/31/2019 Mba 205

    6/23

    a) linear programming

    b)Dynamic programming

    c)goal programming

    d)integer programming

    25)Dynamic programming was initially referred to as the (a)

    a)stochastic linear programming

    b)linear programming

    c)integer programming

    d)goal programming

    26)The essence of ______ is to produce a model which imitates a real system, so that the model may be

    used as a basic for testing the policies (c)

    a)queuing theory b)goal programming c)simulation d)BIG M

    27)The type of allocation model which involves the association of a number of jobs to the same number

    of resources(men) (d)

    a)Goal programming b)simulation c)game theory d)Assignment model

    28)The assignment problem becomes more complex if some of the jobs require more than one resource

    or if the resource can be used for more than one job. Such a problem is called (a)

    a)transportation problem b)Goal programming c)simulation d)game theory

    29)The study of the effect of discrete changes in the values of the parameters on the optimal solution is

    called post optimality analysis or _______ analysis (a)

    a)sensitivity analysis

    b)capita rationing

  • 7/31/2019 Mba 205

    7/23

    c)decision tree

    d)none

    30)To solve linear programming problems _______ developed simplex method (a)

    a)George Dantzig

    b)nepolean

    c)George Hopkins

    d)Samuel john son

    31)Non linear programming problems can be solved by using (b)

    a)Simplex

    b) It has no specific method

    c)Hungarian method

    d)Dual simplex

    32)In the folloing L.P problem

    Max Z=3X1+2X2;

    X1+2X2

  • 7/31/2019 Mba 205

    8/23

    c)the area inbetween inward and outward regions

    d)none

    34) In the graphical method of solving LP problem, while identifying feasible region for

  • 7/31/2019 Mba 205

    9/23

    39)In FIFO queueing model, the arrival time follows (c)

    a)Exponential distribution b)probability distribution c)poisons distribution d)none

    40)Formula for expected number of customers in the queue is given by (b)

    a) P0=1-/

    b)Lq= 2/ (- )

    c)Lq= / -

    d)none

    41) Formula for expected length of non empty queue (a)

    a) / -

    b) a) P0=1-/

    b)Lq= 2/ (- )

    c)Lq= / -

    42)Random numbers are used in ______ technique (b)

    a)Markovian analysis

    b)simulation

    c)simplex

    d)bellmans

    43)Types of simulation (d)

    a)system b)monte carlo c)only a d)both e)none

    44)________ method uses random numbers and is used to solve problems which involve condition of

    uncertainty and where mathematical formulation is impossible (a)

  • 7/31/2019 Mba 205

    10/23

    a)monte-carlo simulation

    b)system

    c)simulation

    d)none

    45)If supply demand in transportation model problems, ________ is to be done (c)

    a)equating b)progression c)balancing d)imbalance

    46)If supply>demand (a)

    a)insert a column with zeros and requiredemand

    b)insert a row with zeros and requiredemand

    c)both a & b

    d)none

    47)If Supply < demand (a)

    a)insert a row with zeros and required supply

    b)insert a column with zeros and required demand

    c)both a & b

    d)none

    48)In decision tree analysis the point where 2 or more events evolve is called (a)

    a)a node

    b)a network

    c)cell

    d)activity

  • 7/31/2019 Mba 205

    11/23

    49)decision making is chosing (c)

    a)chosing among decisions

    b)chosing among activities

    c)one among number of alternatives

    d)all

    50)Full form of PERT is (d)

    a)Project Evaluation and Review Technique

    b)Process Evaluation and Review Technique

    c)Programme Evolution Review technique

    d)Programme Evaluation and Review Technique

    51)Out of three methods of transportation,least cost method,vogels approximation method and north

    west corner rule,_________ gives the optimal solution (a)

    a)VAM

    b)LCM

    c)NWC

    d)all

    52)While finding optimal solution using MODI method, closed loops should be formed taking cells as

    corner cells (c)

    a)variable b) solution cells c)basic cells d)non basic cells

    53)There should be only______ positive and __________negative sign for each of the rows and

    Columns. (a)

  • 7/31/2019 Mba 205

    12/23

    a)1 & 1 b) 0 & 1 c) 1& 0 d)none

    54)If number of basic cells are less than (m+n-1) allocations(occupied cells) the problem is said to be

    ______ transportation problem. (a)

    a)degenerate b) non degenerate c)basic d) non basic

    55)If the number of basic cells=(m+n-1)allocations then that condition is _________ condition (a)

    a)non degenerate b )degenerate c)basic d) non basic

    56)Slack variables refer to__________ resources (b)

    a)used

    b)unused

    c)reused

    d)never used

    57)_______ variables are temporary slack variables which are used for purposes of calculation, and are

    removed later. (a)

    a)artificial b)basic c)non basic d)fixed

    58)________ is the amount of resources by which the L.H.S of the equation exceeds the

    minimum limit . (a)

    a)surplus variables

    b)artificial

    c)basic

    d)non basic

  • 7/31/2019 Mba 205

    13/23

    59)For / type of constraint,________ surplus variables and ________ artificial variables.(c)

    a)subtract,subtract

    b)add,subtract

    c)subtract,add

    d)add,none

    61)For = type of constraint, __________ variables should be added. (a)

    a)artificial b)basic c)non basic d)none

    62)S1,S2,Sn are ________ variables (a)

    a)basic

    b)non basic

    c)artificial

    d)solution

    63)x1,x2,x3 are ________ variables (c)

    a)basic

    b)artificial

  • 7/31/2019 Mba 205

    14/23

    c)non basic variables

    d)all

    64)If all the variables are non negative, a basic feasible solution of a LP problem is called (a)

    a)basic feasible solution

    b)unbounded

    c)infeasible

    d)degenerate

    65)The coefficient of artificial variables a1,a2,an are represented by a very high value M, and hence

    the method is known as (C)

    a)Small M

    b)maximization problem

    c)Big M method

    d)dual

    66)Another way to solve minimization problems is by converting the objective function as a

    maximization problem by multiplying the equation by (a)

    a)-1 b)1 c)2 d)-2

    67)In assignment models, if the given problem is a square matrix, the problem is termed as a _______

    assignment problem. (a)

    a)balancing

    b)imbalance

  • 7/31/2019 Mba 205

    15/23

    c)equilibrium

    d)disequilibrium

    68)If the given problem is not a square matrix, the problem is termed as an ________ assignment

    problem.

    a)unbalanced

    69)In assignment models, if number of lines drawn =order of matrix, then it can be considered

    that______ is reached. (a)

    a)optimality b)result c)solution d)all

    70)If number of allocations, N=m+n-1, then ______does not exist. (b)

    a)non degenerousy b)degenerousy c)feasibility d)unbounded

    71)If number of allocations,Nm+n-1, then ________ does exist. (a)

    a)non degenerousy b)degenerousy c)feasibility d)unbounded

    72)In a degenerasy condition, allocate a small positive quantity________ to one or more unoccupied cell

    that have lowest transportation costs, so as to make m+n-1 allocations. (a)

    a)

    b)*

    c)

    d)

    73)Expected number of customers in the system (a)

    a)Ls= /(1- )

  • 7/31/2019 Mba 205

    16/23

    b)Ls= .(1- )

    c)Ls= 2/(1- )

    d)none

    74)probability that there are n customers in the system (a)

    a)Pn=[ / ]^n .P0

    b) Pn=[ / ]^n /P0

    c) Pn=[ / ]^n

    d)none

    75)Average waiting time for a customer (a)

    a)W=1/ (1- )

    b) W=1/ (1- )

    c) W=1/ 2(1- )

    d) W=1/ (1- )2

    76)Average waiting time in the queue (a)

    a)Wq= / .( - )

    b) Wq= / /( - )

    c) Wq= / .( - )

    d)none

    77)Probability that there is atleast one customer or queue is busy (b)

    a)Pb=P0

    b)Pb=1-P0

  • 7/31/2019 Mba 205

    17/23

    c)Pb=1/P0

    d)Pb=P02

    78)Traffic intensity is given by (b)

    a) .

    b) /

    c) 2.

    d)none

    79)_______is used when there are multiple goals (a)

    a)goal programming

    b)linear programming

    c)dynamic programming

    d)integer programming

    80)While selecting key row in linear programming problem in simplex method is to be taken as

    a)min[xb/xk] of all rows

    b) max[xb/xk] of all rows

    c) max[xb/xk] of all columns

    d)none

    81)If one customer arrives for every 4 min, then _________ customers arrives per hour (a)

    a)15

    b)12

    c)19

  • 7/31/2019 Mba 205

    18/23

    d)20

    82)If a server takes 2.5 min to serve a customer then_______ number of customers can be served in an

    hour (c)

    a)20

    b)21

    c)24

    d)18

    83)In queuing theory arrival rate is represented by symbol (c )

    a)

    b)

    c)

    d)*

    84) In queuing theory service rate is represented by symbol ( b)

    a)

    b)

    c)

    d)#

    85)In MM1 ,infinite queue model, customers are served on ________ basis ( c)

    a)LILO

    b)FILO

    c)FIFO

    d)LIFO

  • 7/31/2019 Mba 205

    19/23

    86)In the Hungarian method, select the smallest element from uncovered elements and subtract from

    remaining elements not covered by lines and add at intersection of lines if_______ (c)

    a)if optimality is reached.

    b)if feasibility is reached

    c)if optimality is not reached

    d)none

    87)________- model helps in solving problems on distribution and transportation of resources from one

    place to another. (a)

    a)Transportation

    b)sequencing

    c)scheduling

    d)Linear programming

    88)In __________ models, un balanced problems can be solved by introducing dummy sources and

    dummy destinations. (b)

    a) sequencing

    b) Transportation

    c)Linear programming

    d)scheduling

    89)One of the following is not a property of LP model (e)

    a)Relationship among decision variables must be linear in nature.

    b)A model must have an objective function

    c)Resource constraints are essential

    d)A model must have a non negativity constraint.

    e)ALL

  • 7/31/2019 Mba 205

    20/23

    90)________is the study of how changes in the co efficient of a linear programming affect the optimal

    solution (d)

    a)sensitivity analysis

    b)post optimality analysis

    c)none

    d)both a & b

    91)The elements of a queuing system are (e)

    a)The arrival pattern

    b)The service mechanism and queue discipline

    c)The number of customers allowed in the system

    d)The number of service channels

    e)all

    92)________ model aims at minimizing the deviations from the predetermined goals (a)

    a)goal programming

    b)integer programming

    c)dynamic programming

    d)none

    93)__________ is a scientific method of providing executive departments with a quantitative basis for

    decisions regarding the operations under their control. (d)

    a) goal programming

    b)integer programming

    c)dynamic programming

    d)operations research

  • 7/31/2019 Mba 205

    21/23

    94) The answer to the questionHow and when orders can be placed? can be answered through (a)

    a)inventory models

    b)simulation

    c)game theory

    d)none

    95)In goal programming Dur represents________ achievement of a goal. (a)

    a)under

    b)over

    c)complete

    d)none

    96) 95)In goal programming Dor represents________ achievement of a goal. (b)

    a)under

    b)over

    c)complete

    d)none

    97)Setting min stock level of bicycles in a cycle store is an example for ______- model. (a)

    a)inventory models

    b)simulation

    c)game theory

    d)none

  • 7/31/2019 Mba 205

    22/23

    98)The Primal programme can be rewritten by transposing(reversing)the rows and columns of the

    algebraic statement of the problem. Inverting the programme in this way results in ________

    programming (b)

    a)primal

    b)dual

    c)both

    d)none

    99)Opening another reservation counter at the railway station is an example for _______ model (c )

    a)inventory

    b)simulation

    c)queuing

    d)LP

    100)Determination of number of bomb hits to destroy enemys nuclear plant. (c)

    a)inventory

    b)queuing

    c)simulation

    d)none

    101)Deciding the quantities of 3 products to be produced per week by the company. (a)

    a)allocation

    b)queuing

    c)inventory

    d)simulation

  • 7/31/2019 Mba 205

    23/23