mca13sgr s500 mica gis intervenor workshop aug 25 2009 …...mica gas insulated switchgear • gis...
TRANSCRIPT
Mica Gas Insulated Switchgear (GIS) Replacement Project Workshop26 August 2009
B-3
2
Agenda – Mica GIS Replacement Project
• BCUC Order • Mica Generating Station and GIS equipment• Need for the Project• Project Scope and Cost • Architecture Evaluation and Decision Making• Timing and Sequencing• Project Risks• Rate Impact• Consultation• Conclusions
3
Order Sought from BCUC
• 44.2 (3) (a) of the Utilities Commission Act (the UCA) • BCUC acceptance that the expenditures to replace the aging
GIS at Mica with new GIS equipment by 2013 are in the public interest
• Considerations:> the Government’s energy objectives; > BC Hydro’s most recent long term resource plan; > whether the expenditure schedule is consistent with section 64.01 and
64.02 of the UCA in respect of electricity self sufficiency and clean and renewable resources; and
> the interests of present and future ratepayers.• Project costs:
> Expected cost: $180.6 M> Authorized cost: $200.2 M
4
Mica Generating Station is on the Columbia River 135 km upstream from Revelstoke.
Mica Generating Station
Mica Generating Station and GIS Equipment
5
Mica Generating Station
• Mica supplies 16% of energy & 17% of capacity for BCH.• The expected cost of a forced or unplanned outage in any month could range from $0 to $20 million per month depending upon time of year and other conditions.• Replacement energy and capacity may need to be purchased from the market.
Underground powerhouse
Mica Generating Station and GIS Equipment
6
Lead Shafts 1- 3
• Mica 500 kV Switchgear conducts energy from the underground transformers to the transmission system at the surface.
• Energy is conducted via “Lead Shafts”. Lead Shafts are tunnels running between the powerhouse and surface.
Mica Gas Insulated Switchgear
Mica Generating Station and GIS Equipment
7
Mica Gas Insulated Switchgear
• GIS allows high voltage conductors to be deployed in limited spaces such as those in an underground powerhouse
• Sulphur Hexaflouride (SF6) is the insulating gas that allows theequipment to be compact when compared to air insulated switchgear.
Mica Generating Station and GIS Equipment
8
Mica Dam and Generating Station
• 3-D –Animation Video
Mica Generating Station and GIS Equipment
9
GIS Equipment: GIS Bus
ConductorBus Cone Insulator
Cut Away of GIS Bus
• Gas Insulated Bus includes:1. An inner conductor,2. SF6 insulating gas3. Outer housing
• Epoxy cones support conductor and insulate between conductor and housing.
Mica Generating Station and GIS Equipment
10
GIS Equipment: GIS Bus
• 3 phases of GIS Bus in Lead Shafts
• Total of 1200 m of Bus in Mica
Mica Generating Station and GIS Equipment
11
GIS: Disconnect Switches
GIS Bus
• Disconnect switches are used to isolate sections of the 500kV system.• Disconnect switches are manually operated.
Mica Generating Station and GIS Equipment
12
GIS: Circuit Breakers
A circuit breaker is an automatically-operated electrical switch designed to protect an electrical circuit from damage caused by overload.
Mica Generating Station and GIS Equipment
13
GIS: Surge Arrestors
Surge arrestors protect transformers and other equipment from over voltage spikes.
Mica Generating Station and GIS Equipment
Surge arrestor beingrepaired in 2008
14
Need for the Project:Independent GIS Condition Assessments
Key conclusions of independent assessments• BC Hydro can expect prolonged, multi-unit outages with the current
switchgear;> Disconnect switches and majority of bus in the transformer chamber require two unit
outages for repair work to proceed.• Surge arrestors and disconnect switches present the greatest risks;• Failure of the GIS in one lead shaft restricts the output to 1,500 MW
> During the repair period for such a failure, Mica is vulnerable to a full plant outage if a second GIS failure occurs
• There is a 99 % chance of GIS failure within ten years > Nine months after this prediction, a surge arrestor failed on Unit 3, which resulted in it
being out of service for ten weeks.• The Mica GIS is > 30 yrs old. It may be the last 500 kV GIS
equipment of its type still in operation in North America.
Need for the Project
15
Need for the Project:Condition Assessment Conclusions
G1
T1
Equipment is in GOOD Condition
Equipment is in FAIR Condition
Equipment is in POOR Condition
Equipment is in UNSATISFACTORY
Condition
Circuit Breaker
Disconnect Switch
Transformer
Generator
Surge Arrester
Transmission Line
Reactor
5L71 5L72
T2 T3 T4
G2 G4G3
Note: Circuit breakers in the Switchgear Building were replaced in 2007 and 2008 due to their unsatisfactory conditions.
16
Project scope
• Replace the original 500KV Gas Insulated Switchgear at Mica
• Develop a system that provides benefits by improving upon the current 500KV switchgear.
Project scope and cost
17
Project Benefits• Develop a more robust
architecture than the current architecture> Improved layout
• Disconnect switches> Remote operation
• Maintenance access• Environmental benefits
> Reduce SF6 leakage to <0.5% per year.
• Mica 5 & 6 > Enables BCH to maintain
Contingency Resource Plan (CRP) dates for Mica 5 & 6.
New Switchgear will be meet “Safety by Design” requirements. The Switchgear will be floor mounted. It will be accessible using
a new overhead crane.
Project scope and cost
18
Project Cost
$200.2Total Authorized Cost (note 6)19.6Project Reserve (Note 5)
$180.6Total Expected Cost7.5Identification and Definition Phase (loaded)
$173.1Sub-total: Implementation Phase Cost (Loaded) 21.3Interest During Construction (Note 4)
17.7Capital Overhead (Note 3)
$134.1Sub-total: Implementation Phase Cost (Direct)8.4Inflation and Escalation (Note 2 )
1.0Dismantling and Removal
11.3Contingency on Expected Cost
$113.4Sub-total: Construction Cost before Contingency (Note 1)18.8Project Management and Engineering
$ 94.6Direct Construction Cost
AMOUNT($ million)
PROJECT COMPONENT
Project scope and cost
19
Agenda – Mica GIS Replacement Project
• BCUC Order • Mica Generating Station and GIS equipment• Need for the Project• Project Scope and Cost • Architecture Evaluation and Decision Making• Timing and Sequencing• Project Risks• Rate Impact• Consultation• Conclusions
20
Project Requirements (summary)
• Maintain the reliability of the500kV GIS
• Realize project benefits:> Robust architecture> Disconnect switches> Maintenance access> Environmental benefits
• Develop a system level design that can be implemented without significant impacts upon the operating generating station
• Low life cycle cost
Architecture Evaluation and Decision Making
21
Architecture Evaluation
Revolutionary Architectures that did not include GIS were:1. moving the 500 kV transformers out of the Mica powerhouse to the surface;2. using an insulating gas other than SF6.
• Conclusions: Not viableEvolutionary Architectures were developed:
• Evolutionary switchgear designs were developed for more detailedconsideration.
Architecture Evaluation and Decision Making
22
Structured Decision Making Process
Final Structured Decision
making and ranking
Detailed Study, Estimating
Engineering Study
Engineering Analysis and
Constraints
Architecture Evaluation and Decision Making
23
Recommended Architecture
Not in the scope of this project
Style Legend
Not In Scope
Replace
Remain
G1
T1
Circuit Breaker
Disconnect Switch
Transformer
Generator
Surge Arrester
Transmission Line
Reactor
5L71 5L72
G2
T2
G3
T3
G4
T4
G5
T5
G6
T6
New
• New architecture substantially reduces consequences of future failures.• Lead shaft 3 improves system reliability and has construction benefits.• Architecture allow the realization of the additional project benefits.
24
Replacement SequencingSchedule for GIS component Installation/Replacement
1 2 3 4 5 6 7 8 9 10 11 12 13Low Cost
($6 M)Moderate
Cost ($12 M) High Cost
($19 M)
Activity 2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
Probability(33%)
Moderate Probability
(25%)
Low Probability
(15%)Alternative 1
Replace Existing GIS $61Lead shaft 3 and interface $56
PV of project costs $117 $117 $117 $117Range of Outage costs $5 $8 $8GHG Credit Cost $1 $1 $1Range of Adjusted PV of Project $123 $126 $126
Alternative 2 a
Replace Existing $54Lead shaft 3 and interface $53
PV of project costs $107 $107 $107 $107Range of Outage costs $13 $19 $18GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $122 $129 $128
Alternative 2 bReplace Existing $46Lead shaft 3 and interface $53
PV of project costs $99 $99 $99 $99Range of Outage costs $18 $28 $27GHG Credit Cost $3 $3 $3Range of Adjusted PV of Project $121 $130 $129
Alternative 3Replace Existing $65Lead shaft 3 and interface $53
PV of project costs $119 $119 $119 $119Range of Outage costs $11 $17 $19GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $132 $138 $140
Do Nothing - Defer implementaion of Project by 5 years
PV Project and Outage Costs(in $millions)
Outage probability increasing by 1% per year
Implement project piecemeal over time
Do Nothing - Defer implementaion of Project by 10 years
PV Project
Cost
Full implementation of Project by 2013
Alternative 4Replace existing GIS in tranformer chamber and switchgear building
$42
Lead shaft 3 and interface $56Lead shafts 1 and 2 $20
PV of project costs $118 $118 $118 $118Range of Outage costs $7 $10 $9GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $127 $130 $130
Same as Alternative 1 but defer replacement of lead shafts 1 and 2
Recommendation
25
Option/ Year
Present Value Cost ($millions) 20
10
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
$117 x x
$124 x x
$127 x x x x
$119 x x
$118 x x
$114 x x x x
$116 x x
LEGENDLead Shaft 3 and switchgear buildingLead Shaft 1Lead Shaft 2Base ComponentsPlanned Outage - 4 months xMica Unit 5 In-service date
MIC
A 5 IS
D
MIC
A 5 IS
D
5) Defer Lead Shaft 1&2 ten years
6) Defer Lead Shaft 3 ten years
7) Defer Lead Shaft 1 ten years
MIC
A 5 IS
D
1) Base Case - Do All Now
2) Defer Lead Shaft 1&2
3) Defer Lead Shaft 3
4) Defer Lead Shaft 1
Sensitivity Analysis of Mica 5 ISD
Option 1 is lowest cost riskregardless of Mica Unit 5In Service Date
Timing and sequencing
26
Construction Sequencing Animation
Timing and sequencing
27Mica Switchgear Project 1
Mica Switchgear Project Schedule July 09 –Dec 09
Lead Shaft 3
Jan 10 –Jun 10
Jun 10 –Dec 10
Jan 11 –Jun 11
Jan 12 –Jun 12
Jun 12 –Dec 12
Jan 13 –Jun 13
Stage 1
Stage 2
Stage 3
Jun 11 –Dec 11Design &
Manufacture
Stage 4
Stage 5
Stage 6
Stage 7
Stage 8
Stage 9
RingSwitchgear Building Ring Extension
Lead Shaft 3
InterfaceInterface existingGIS to Lead Shaft 3
Unit 3 & 4Mica Units 3 & 4
RingSwitchgear BuildingRing Bus
Units 1 & 2Mica Units 1 & 2
RingSwitchgear BuildingRing Bus
Lead Shaft 2 LS 2
Lead Shaft 1 LS 1
Completion CompletionSequencing of the work minimizes disruption to the operating plant. Replacement of the GIS for Units 1 – 4 can be completed in the spring of 2011 and 2012 when outage costs are low.
28
Project Risks
• Cost risks mitigated by BC Hydro’s decision to tender early and obtain firm pricing
• Schedule risks are mitigated by:> Including lead shaft 3 to reduce outage time and increase reliability during
construction> Apply CHC Collective Agreement
• Safety risks during construction are mitigated by:> BC Hydro and Contractor Safety Management Plans> Site Specific Safe Work Procedures> Monitoring by BC Hydro during construction
• Environmental risks are mitigated by:> Environmental Management & Environmental Protection Plans> During construction BC Hydro will have an on-site Environmental Monitor.
29
Annual Incremental Rate Impacts
0.00%
0.10%
0.20%
0.30%
0.40%
0.50%
0.60%
2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032
Fiscal Year
Per C
ent
Expected
Approved
30
Consultation
• BC Hydro has undertaken consultation with First Nations and with public stakeholders to identify issues specific to the Project.
• BC Hydro expects the Project will have minimal, if any adverse impacts. > Project will be implemented within Mica GS or on previously
disturbed ground. > There will be no impact on the Kinbasket or Revelstoke reservoirs.
• BC Hydro believes that the consultation conducted for the Project is adequate.
31
Conclusions
• BC Hydro is seeking BCUC acceptance that expenditures to replace the aging GIS at Mica with new GIS equipment by 2013 are in the public interest. Project costs are:> Expected cost: $180.6 M> Authorized cost: $200.2 M
• The condition of the original Mica 500kV switchgear poses the risk of forced outages
• The project will:1. replace the 500 kV GIS; and 2. improve upon the current GIS system.
• BC Hydro has planned work so that costs are understood• BC Hydro has identified and is managing project risks.