10-3 What is Project Management? Project: a series of related jobs usually directed toward some major output and requiring a significant period of time to perform Project management: the management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project LO 1TRANSCRIPT
![Page 1: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/1.jpg)
McGraw-Hill/Irwin
Copyright © 2011 The McGraw-Hill Companies, All Copyright © 2011 The McGraw-Hill Companies, All Rights ReservedRights Reserved
Chapter 10
Projects
![Page 2: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/2.jpg)
10-2
Learning Objectives
1. Explain what project management is and why it is important.
2. Identify the different ways projects can be structured.
3. Describe how projects are organized into major subprojects.
4. Understand what a project milestone is.5. Determine the “critical path” for a project.6. Demonstrate how to “crash,” or reduce the
length, of a project.
![Page 3: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/3.jpg)
10-3
What is Project Management?
• Project: a series of related jobs usually directed toward some major output and requiring a significant period of time to perform
• Project management: the management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project
LO 1LO 1
![Page 4: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/4.jpg)
10-4
Types of Development Projects
LO 2LO 2
![Page 5: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/5.jpg)
10-5
Structuring Projects
• Pure project• Functional project• Matrix project
LO 2LO 2
![Page 6: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/6.jpg)
10-6
Pure Project
• Advantages– The project manager has full authority– Team members report to one boss– Shortened communication lines– Team pride, motivation, and commitment are high
• Disadvantages– Duplication of resources– Organizational goals and policies are ignored– Lack of technology transfer– Team members have no functional area "home"
LO 2LO 2
![Page 7: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/7.jpg)
10-7
Functional Project
LO 2LO 2
![Page 8: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/8.jpg)
10-8
Functional Project Continued
• Advantages– A team member can work on several projects– Technical expertise maintained in functional area– Functional area is “home” after project completed– Critical mass of specialized knowledge
• Disadvantages– Aspects of the project that are not directly related to
the functional area get short-changed– Motivation of team members is often weak– Needs of the client are secondary and are
responded to slowly
LO 2LO 2
![Page 9: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/9.jpg)
10-9
Matrix Project
LO 2LO 2
![Page 10: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/10.jpg)
10-10
Matrix Project Continued
• Advantages– Better communications between functional areas– Project manager held responsible for success– Duplication of resources is minimized– Functional “home” for team members– Policies of the parent organization are followed
• Disadvantages– Too many bosses– Depends on project manager’s negotiating skills– Potential for sub-optimization
LO 2LO 2
![Page 11: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/11.jpg)
10-11
Work Breakdown Structure
• Statement of work (SOW): a written description of the objectives to be achieved
• Task: a further subdivision of a project– Usually shorter than several months– Performed by one group or organization
• Work package: a group of activities combined to be assignable to a single organizational unit
LO 3LO 3
![Page 12: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/12.jpg)
10-12
Work Breakdown Structure Continued
• Project milestones: specific events on the project
• Work breakdown structure (WBS): defines the hierarchy of project tasks, subtasks, and work packages
• Activities: pieces of work that consume time– Defined within the context of the WBS
LO 4LO 4
![Page 13: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/13.jpg)
10-13
An Example of a Work Breakdown Structure
LO 3LO 3
![Page 14: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/14.jpg)
10-14
Work Breakdown Structure, Large Optical Scanner Design
LO 3LO 3
![Page 15: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/15.jpg)
10-15
Project Control Charts
• Charts are useful because their visual presentation is easily understood
• Software is available to create the charts
• Gantt chart: a bar chart showing both the amount of time involved and the sequence in which activities can be performed
LO 3LO 3
![Page 16: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/16.jpg)
10-16
Sample of Graphic Project Reports
LO 3LO 3
![Page 17: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/17.jpg)
10-17
Earned Value Management (EVM)
• A technique for measuring project progress in an objective manner
• Has the ability to combine measurements of scope, schedule, and cost in a project
• Provides a method for evaluating the relative success of a project at a point in time
LO 3LO 3
![Page 18: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/18.jpg)
10-18
Essential Features of any EVM Implementation
1. A project plan that identifies the activities to be accomplished
2. A valuation of each activity work3. Predefined earning or costing rules to
quantify the accomplishment of work
LO 3LO 3
![Page 19: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/19.jpg)
10-19
Earned Value Management Charts
LO 3LO 3
![Page 20: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/20.jpg)
10-20
Project Tracking Without EVM
• Chart A shows the cumulative cost budget for the project as a function of time– Blue line, labeled BCWS
• Also shows the cumulative actual cost of the project– Red line
• Appears project was over budget through week 4 and then under budget
• What is missing is any understanding of how much work has been accomplished
LO 3LO 3
![Page 21: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/21.jpg)
10-21
Project Tracking With EVM
• Chart B shows the BCWS curve along with the BCWP curve from chart A
• Technical performance started more rapidly than planned but then slowed significantly and feel behind at week 7
• Chart illustrates the schedule performance aspect of EVM
LO 3LO 3
![Page 22: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/22.jpg)
10-22
Project Tracking With EVM Continued
• Chart C shows the same BCWP curve with actual cost data
• Project is actually under budget, relative to the amount of work accomplished
• Chart D shows all three curves together– Typical for EVM line charts
LO 3LO 3
![Page 23: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/23.jpg)
10-23
Example: Earned Value Management
LO 3LO 3
![Page 24: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/24.jpg)
10-24
Example: Budgeted Cost of Work Scheduled (BCWS)
A. 100% of $18K = $18KB. 100% of $10K = $10KC. 80% of $20K = $16KD. 15% of $40K = $6K
BCWS = $18K+$10K+$16K+$6K = $50K
LO 3LO 3
![Page 25: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/25.jpg)
10-25
Example: Budgeted Cost of Work Performed (BCWP)
A. 100% of $18K = $18KB. 80% of $10K = $8KC. 70% of $20K = $14KD. 0% of $40K = $0
BCWP = $18K+$8K+$14K+$0 = $40K
LO 3LO 3
![Page 26: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/26.jpg)
10-26
Example: Performance Measures
89.045$40$
5$45$40$
8.050$40$
10$50$40$
KK
ACBCWPCPI
KKACBCWPCV
KK
BCWSBCWPSPI
KKKBCWSBCWPSV
LO 3LO 3
![Page 27: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/27.jpg)
10-27
Network-Planning Models
• A project is made up of a sequence of activities that form a network representing a project
• The path taking longest time through this network of activities is called the “critical path”
• The critical path provides a wide range of scheduling information useful in managing a project
• Critical path method (CPM) helps to identify the critical path(s) in the project networks
LO 3LO 3
![Page 28: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/28.jpg)
10-28
Critical Path Method (CPM)
1. Identify each activity to be done and estimate how long it will take
2. Determine the requires sequence and construct a network diagram
3. Determine the critical path4. Determine the early start/finish and
late start/finish schedule
LO 5LO 5
![Page 29: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/29.jpg)
10-29
Example: Critical Path Method
LO 5LO 5
![Page 30: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/30.jpg)
10-30
Example: Activity Sequencing and Network Construction
LO 5LO 5
![Page 31: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/31.jpg)
10-31
Example: Finished Schedule
LO 5LO 5
![Page 32: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/32.jpg)
10-32
CPM with Three Activity Time Estimates
• If a single time estimate is not reliable, then use three time estimates– Minimum– Maximum– Most like
• Allows us to obtain a probability estimate for completion time for the project
LO 5LO 5
![Page 33: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/33.jpg)
10-33
Finding Activity Time and Variance
timeexpectedETmaximumb
likelymost mminimum
6
64
22
a
ab
bmaET
LO 5LO 5
![Page 34: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/34.jpg)
10-34
Example: Activity Expected Times and Variances
2
22
6
64
cp
ETDZ
ab
bmaET
LO 5LO 5
![Page 35: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/35.jpg)
10-35
Example: Network with Three Time Estimates
87.089.113835
Weeks35in Finishing ofy Probabilit
2
cp
ETDZ
LO 5LO 5
![Page 36: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/36.jpg)
10-36
Time-Cost Models and Project Crashing
• Basic assumption: Relationship between activity completion time and project costTime cost models: Determine the optimum point in time-cost tradeoffs– Activity direct costs– Project indirect costs– Activity completion times
LO 6LO 6
![Page 37: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/37.jpg)
10-37
Procedure for Project Crashing
1. Prepare a CPM-type network diagram2. Determine the cost per unit of time to
expedite each activity3. Compute the critical path4. Shorten the critical path at the least
cost5. Plot project direct, indirect, and total-
cost curves and find the minimum-cost schedule
LO 6LO 6
![Page 38: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/38.jpg)
10-38
Managing Resources
• In addition to scheduling each task, must assign resources
• Software can spot over-allocation– Allocations exceed resources
• Must either add resources or reschedule– Moving a task within slack can free up
resources
LO 1LO 1
![Page 39: McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects](https://reader036.vdocument.in/reader036/viewer/2022062401/5a4d1b0b7f8b9ab05998acdf/html5/thumbnails/39.jpg)
10-39
Tracking Progress
• Actual progress on a project will be different from the planned progress– Planned progress is called the baseline
• A tracking Gantt chart superimposes the current schedule onto a baseline so deviations are visible
• Project manager can then manage the deviations
LO 1LO 1