Measure H Projects Update presented to Landscape/Aesthetics Committee As of 1/16/2019

Upload: others

Post on 29-Apr-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Measure H Projects Updatepresented to Landscape/Aesthetics

Committee

As of 1/16/2019

Page 2: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Regional Public Safety Training Center

Project Start:  8/2018

Est. Completion:2/2019

Project Start:  6/2018

Est. Completion:1/2019

Ribbon Cutting Ceremonyand Dedication

Wednesday, February 134:00 PM

Page 3: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Athletic Fieldhouse with Restrooms

October 2018

November 2018

January 2019

Project Start:  8/2018

Est. Completion:2/2019

Page 4: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Solar Project – East Lot

Project Start:  10/2018

Est. Completion:6/2019

Main campus power shutdown:  Spring Break(week of April 14th)

Page 5: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design

Project Est. Start:  Late 2019/Early 2020

Est. Completion:2020/2021

Page 6: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design (continued)

Page 7: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design (continued)

Page 8: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design (continued)

Page 9: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design (continued)

Page 10: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

CIS Building Design (continued)

11,893 SF

Page 11: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Facilities Master Plan ‐ Landscaping

11

Page 12: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Facilities Master Plan Potential Tree Mitigation Sites

12

Page 13: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Facilities Master Plan ‐ Landscaping

13

Page 14: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Projects Update

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Approval Received

Construction Commenced/To Commence:• Regional Public Safety Training Center – Phase One (to be completed 1/2019)• Athletic Fieldhouse with Restrooms (to be completed 2/2019)• Athletic Fieldhouse with Restrooms Infrastructure (to be completed 6/2019)• Gymnasium Air Conditioning (to be completed 3/2019 / electrical hookup 4/2019)• Solar Project – East Parking Lot (to be completed 6/2019) • Campus Safety Relocation – Interior remodel (commenced Friday, 1/18/19; to be completed 6/2019)

In Bid Process:• Veterans Center Building (Bid opening 2/7/19)

Prepping for Bid:• Regional Public Safety Training Center Classroom Buildings

Page 15: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Projects Update (continued)

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Under DSA Review• CTE Building and Covered Storage• Tehama Campus Student Services Building

Design / Construction Documents Phase• CIS Building

Page 16: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

Non-DSA Projects179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Current/Upcoming Projects• Interior / Exterior Lighting Project – Prop 39 & Bond (to be 

completed 5/2019)

• HSUC Folding Wall Replacement (summer project)• SC Main Campus Keying & Access Control (summer/fall project)• SC Safety & Security Standards 

In Progress• Campus Wide Infrastructure Projects (water, sewer, storm 

drain, electrical, fire alarm, technology fiber, gas lines)  Ongoing

Page 17: Measure H Projects Update...2019/02/06  · Non-DSA Projects 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Current/Upcoming Projects • Interior / Exterior Lighting

17

For more information…About SC / Bond Information / 2016 Bond Measure H

[email protected] / 242‐7699

Theresa Markword, Bond Program Manager