MeChanICs Project meeting Welcome and introduction. G. Riddone, 22/03/2011. CLIC – 3 TeV. Accelerating structures. TD24#2 at CERN (12 GHz). TD18#3 at SLAC. TD18#2 at KEK. Cu OFE UNS C10100 Shape accuracy ± 2.5 µm Roughness Ra 0.025 µm Ø 45 to 80 mm, 30 disks Length 300 mm. PETS . - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MeChanICs  Project meeting Welcome and introduction

MeChanICs Project meetingWelcome and introduction

G. Riddone, 22/03/2011

Page 2: MeChanICs  Project meeting Welcome and introduction

CLIC – 3 TeV

G. Riddone, MeChanICs,22.03.2011 2

Page 3: MeChanICs  Project meeting Welcome and introduction

Accelerating structures

3

TD18#3 at SLAC

TD18#2 at KEK

TD24#2 at CERN (12 GHz)

G. Riddone, MeChanICs,22.03.2011

- Cu OFE UNS C10100- Shape accuracy ± 2.5

µm- Roughness Ra 0.025

µm- Ø 45 to 80 mm, 30 disks- Length 300 mm

Page 4: MeChanICs  Project meeting Welcome and introduction

PETS

4

PETS (12 GHz, TBTS)

PETS (11.4 GHz, test at SLAC)

G. Riddone, MeChanICs,22.03.2011

- Cu OFE UNS C10100- Shape accuracy ± 7.5

µm- Roughness Ra 0.1 µm- 8 octants- Length 300 mm

Page 5: MeChanICs  Project meeting Welcome and introduction

RF components

5

High-power dry load Hybrid

Variable high power splitter

G. Riddone, MeChanICs,22.03.2011

Page 6: MeChanICs  Project meeting Welcome and introduction

Baseline procedure

6

Diamond machining (sealed

structures)

H2 diffusion bonding/brazing at

~ 1000 ˚C

Cleaning with light etch

Vacuum baking650 ˚C > 10 days

J. Wuang

J. WuangG. Riddone, MeChanICs,22.03.2011

Engineering design (INPUT: RF design)

Page 7: MeChanICs  Project meeting Welcome and introduction

CLIC Two-beam module

G. Riddone, MeChanICs,22.03.2011 7

A. Samoshkin

CLIC at 500 GeV (4248 modules)26312 Accelerating structures13156 PETS~ 70000 RF components

CLIC at 3 TeV (20924 modules)142812 Accelerating structures71406 PETS~ 400000 RF components

Page 8: MeChanICs  Project meeting Welcome and introduction

Status

• Now: end of Critical Design phase feasibility demonstration

• From 2011/2011 project preparation phase starts• Qualification of new companies• Optimization of RF structure fabrication • Industrialization and cost optimization• ….

G. Riddone, MeChanICs,22.03.2011 8

Page 9: MeChanICs  Project meeting Welcome and introduction

G. Riddone, MeChanICs,22.03.2011 9

MeChanICs Projecthttps://indico.cern.ch/conferenceDisplay.py?confId=106300

• FP7/People/IAPP (Industry-Academia Partnerships and Pathways) project MeChanICs, “Marie Curie linking Industry to CERN”

• start September 1st 2010, 4 year project • to enhance knowledge exchange btwn Partners on precision

manufacturing by two-way intersectoral secondments • objective: enable & enhance long term industry participation

in CLIC, Compact LInear Collider, RF structure R&D