Streamlining Earned Value Management
Proprietary & Confidential
Ron Babich, VPHard Dollar [email protected]
![Page 2: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/2.jpg)
Project COST Management
2Proprietary & Confidential
Design(Materials)
Estimating(Budget)
Scheduling(Time)
Progress(Project Controls)
Finance(Accounting)
![Page 3: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/3.jpg)
Overview
Building the Cost Model
Developing EVM Measurements
Case Study: Successful Process Readiness
![Page 4: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/4.jpg)
Capital Planning Project Variance
4Proprietary & Confidential
15%50%
Project Plan Costs
Plan Costs
![Page 5: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/5.jpg)
EVM Requirements
Effort RequiredWBS
Period of TimeSchedule
ProgressPerformance
Measurement Baseline
![Page 6: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/6.jpg)
Regulatory Requirements
6Proprietary & Confidential
RegulatoryRequirements
![Page 7: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/7.jpg)
7Proprietary & Confidential
RegulatoryRequirements
![Page 8: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/8.jpg)
Characteristics of Credible Cost Estimates
Clear Identification of Task
Broad Participation in Preparation
Availability of Valid Data
Standardized Structure For Estimate
Provision for ProgramUncertainties
Recognition of Inflation
Recognition of Excluded Costs
Independent Review Of Estimates
![Page 9: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/9.jpg)
Budget/Cost Estimate Challenges
9Proprietary & Confidential
Typical Challenges
![Page 10: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/10.jpg)
Auditors should…
10Proprietary & Confidential
Cost Element Valid and Applicable
Labor Includes Time Phase Break Down
Calculations on each element are correct
Program is Accurate TotalOf Sub-Elements
Escalation was applied Over time
![Page 11: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/11.jpg)
Case Study - NASA
0 of 10 Projects followed All Basic Steps
3 of 10 Projects included detailed WBS
2 of 10 Measure Cost/Performance Identify Risk
![Page 12: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/12.jpg)
Case Study – US Customs $1.05 BilCommercial Environmental Life Cycle
No Formal Cost Model
No Structured Documented Process for Determining Size/Reuse
No Relevant, Measured, Normalized Historical Cost Data to Calibrate Models
Spreadsheet
Size
Measurement
![Page 13: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/13.jpg)
What is Earned Value Management?
• Earned Value Management (EVM)…– Project management process that combines schedule
performance and cost performance
– Answers: What did we get for the money we spent?
– Used since the 1960’s by the Department of Defense
– Central part of CERT and C/SCSC (Cost/Schedule Control Systems Criteria)
– Was recently revised and adopted as ANSI/EIA 748
13Proprietary & Confidential
![Page 14: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/14.jpg)
Example: Rail Project
14Proprietary & Confidential
4 Miles
4 Weeks
Scope
Time
Cost $ 4 Mil
4 Miles
4 Weeks
Scope
Time
Cost $ 4 Mil
![Page 15: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/15.jpg)
What is Earned Value Management?
• The Essence of Earned Value Management (EVM)…
15Proprietary & Confidential
Budget X % Complete
= Earned Value
![Page 16: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/16.jpg)
What are the Benefits of EVM?
• Brings cost performance and schedule performance into a single unified view
• Provides a true picture of a project’s value at any point in time
• Ideal method of monitoring project status and likelihood of success
16Proprietary & Confidential
![Page 17: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/17.jpg)
EVM Give us…
17Proprietary & Confidential
Cash Flow
Predictive Profit/Loss
ScheduleScopeCost
Gov Report ComplianceProduction Factors
Operations Financial
Mitigate Risk
![Page 18: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/18.jpg)
Driving Trends Affecting EVM
• Owner Budgets are Being Reduced– Credit limitations– Less capacity for risk
• …Leading to Greater Owner Scrutiny of Project Health– Are we on track?– Have we over-paid?– What is the forecast?
• …Leading to Increased Adoption of EVM– In traditional markets: Aerospace, Defense– In new markets: Oil & Gas, Mining, Power, Civil, Commercial
18Proprietary & Confidential
![Page 19: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/19.jpg)
What are the Key Requirements of EVM?
• Step 1:– Define the work
19Proprietary & Confidential
![Page 20: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/20.jpg)
What are the Key Requirements of EVM?
• Step 2:– Assign budget (planned) values
20Proprietary & Confidential
![Page 21: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/21.jpg)
What are the Key Requirements of EVM?
• Step 3:– Schedule the work
21Proprietary & Confidential
![Page 22: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/22.jpg)
What are the Key Requirements of EVM?
• Step 4:– Cost-load the schedule
22Proprietary & Confidential
What does it tell the contractor?What are our expected costs over time
What does it tell the owner?What is our expected spend level over time
What do you need to track this value? Estimate / budget Cost-loaded schedule
Cost
Time
$500,000
$1,000,000
Budgeted Cost of Work Scheduled (BCWS)
![Page 23: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/23.jpg)
What are the Key Requirements of EVM?
• Step 5:– Track progress (% complete)
23Proprietary & Confidential
What does it tell the contractor?What should our costs have been based on the work we completed
What does it tell the owner?What should our spend level have been based on the work completed
What do you need to track this value? Estimate / budget Progress history (units completed)
Cost
Time
$500,000
$1,000,000
$450,000
Budgeted Cost of Work Scheduled (BCWS)Budgeted Cost of Work Performed (BCWP)
Earned Value
![Page 24: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/24.jpg)
What are the Key Requirements of EVM?
• Step 6:– Track actual costs (optional)
24Proprietary & Confidential
Cost
Time
$500,000
$1,000,000
$450,000
$400,000
Actual Cost of Work Performed (ACWP)
Budgeted Cost of Work Scheduled (BCWS)Budgeted Cost of Work Performed (BCWP)What does it tell the contractor?
What have our costs actually been for the work we completed
What does it tell the owner?What has our spend level actually been for the work completed
What do you need to track this value? Actual costs from accounting; or “Accrued” costs
Earned Value
![Page 25: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/25.jpg)
Where is EVM trackedby: Owners, PMO’s, CM’s, Contractors
• Spreadsheets
• Finance-focused systems– ERP– Accounting
• Project-focused systems– HD + Primavera– HD + MS Project
25Proprietary & Confidential
![Page 26: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/26.jpg)
System Process Keys
26Proprietary & Confidential
Schedule Cost
Scope
![Page 27: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/27.jpg)
Level of Detail in Planning
Specifics during detailed estimating:– Using more detail instead of less
– Detail the work into small manageable steps
– Rule of thumb: No activities >1 shift
![Page 28: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/28.jpg)
Measuring Craft Productivity
– Measure craft productivity through Earned Value Process
– Based on activity progress
– Information to forecast schedule and cost at completion
– Evaluate Resource Needs and Deployment
1
2
3
![Page 29: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/29.jpg)
Case Study Operations: Audience – Who Owns Tracking
– Field Superintendents
– General Foremen
– Project Controls Group
– Front-Line Supervisors (Foremen) are excluded
![Page 30: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/30.jpg)
Earned
Value Flow
Duplication of Data EntryAccuracy RiskTime Delays
![Page 31: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/31.jpg)
Earned Hours from Progress
Progress from Field
Budget Hours times %
Complete = Earned Hours
![Page 32: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/32.jpg)
![Page 33: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/33.jpg)
Case Study: Cost
Earned Hours Progress From
Schedule
Timesheet Hours From
Payroll
Actual Hours divided by
Earned Hours
BilledCost
DiscussForecast
Calculations
![Page 34: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/34.jpg)
Warning: Watch out for these common challenges
– Requests or tendencies to work on
jobs that are not in the schedule
– Sand bagging of progress
– Remaining duration on activities
– Rejections from Payroll
– Supervisors that may pencil whip a
timesheet or schedule
![Page 35: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/35.jpg)
Case Study: Your Role
– Ultimately it is your responsibility to assure that the
progress that is turned in is as accurate as possible
– When monitoring work in the field, take the current
schedule with you to verify
– If you have a supervisor that struggles with any part
of the schedule, get the Project Controls group to
help
– Clearly communicate the expectations to your
supervisors
![Page 36: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/36.jpg)
Case Study: Your Role
– Help to minimize down time between contractors,
crews etc…(this can be big)
– When PF’s are above 1.1 or below .80, go to the
field, find out why and communicate that to
management and project controls
– Monitor & Manage Material Movement
– Monitor & Manage Tools
– Monitor & Manage Equipment Utilization
– Manage Change Management
![Page 37: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/37.jpg)
Case Study: Your Role
– Monitor Time Sheet accuracy
– Continuous Communication with
Management on Schedule Status
– Make time at least once a day to verify
accuracy of current schedule and
communicate findings to Project Controls
– Have Daily discussions with Project
Controls on Current Cost Report
![Page 38: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/38.jpg)
Case Study: Your Role
– Document all delays
– Monitor and Manage Non-Working
Times
– Hold your supervisors accountable for
assuring that their progress is
accurate
– If you or one of your supervisors does
not understand something….. ASK
SOMEONE !
![Page 39: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/39.jpg)
Case Study: Recap
– Who is responsible for Accurate Progress?
– What is affected by incorrect Progress?
– Explain the flow process for calculating
Productivity (draw flow on board)
– What can you do to support Accurate
Progress?
![Page 40: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/40.jpg)
Case Study: Benefits of Accurate Progress
– Schedule Forecast
– Cost Forecast
– Manage Resources
– Enables the Owner to make sound Business
Decisions (Minimize Unit Down Time)
– It’s the Right Thing to Do
![Page 41: Melbourne streamlining earned value with hd published](https://reader035.vdocument.in/reader035/viewer/2022062703/55524dd5b4c9059a4f8b4e3b/html5/thumbnails/41.jpg)
Best Practice Checklist
Cost Estimate to Measure Original Plan
Strong leadership demands EVM
Stakeholders make it clear on accountability
Management mitigating risk on results
EVM at the program level
EVM planned detail
Use past performance – History!
Integrate: Cost, Schedule and Performance