Current Activities this Week:
Underground Utilities:
Area 3 - Deep underground plumbing is complete to
Column Line 6.
Foundations:
Area 2 Concourse Level – Last D-Line Foundations is
complete.
Concrete Flatwork:
Area 3 Field Level – Prep work for lower dock slab on
grade has started. Area 4 – Cast-in-place concrete
risers are ongoing.
Structural Steel Erection:
Area 4 – Canopy Trusses are set from Column Lines
33-39. Area 4 – Metal decking installation in Sequence
3-3 is complete. Field Level Area 1 – Subroof decking
installation is ongoing
MEP Rough-in:
Area 3 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 9.22.2010
Re: Wizards Stadium Project
Update – Week of
9.20.2010
Field Level Area 3 – Slab preparation is
ongoing at lower dock area.
Field Level Area 1 – Subroof installation, 24”
storm line installation and metal framing are
ongoing.
Field Level Area 2 – CMU block wall
installation is ongoing.
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas E, F, G and H.
Area 2 and 3 Concourse Level – Masonry wall installation
At Main Concourse Buildings are ongoing.
Curtainwall:
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Foundations:
Area 3/4 Field Level – Foundations for “infill” area between
Column Lines 40-42 will be placed.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade at lower dock area will begin.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 3/4 – Structural steel erection for “infill” area will
begin.
MEP Rough-in:
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Area 1 – Shot of the West Building Field Side
Elevation showing progress of Canopy
Decking and Suite Soffit installation.
Concourse Level Area 3 – Filled and polished
CMU Block walls at the East Concourse
Buildings.
Area 4 – Canopy Truss erection is complete
in Sequence 3-6 from column lines 33-39.
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation at West
Elevation will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Curtainwall framing
at Field Side of Main Concourse will begin.
Area 1 – Sheathing installation is complete
at south end of West Building.
Area 1 – Shot of the west building showing
the progress of the exterior envelope.
Building the Future
Additional Photos:
Area 1 – Soffit framing and sheathing is
ongoing at all levels of the West Building.
Area 2/3 – Shot of truck dock area looking
northwest from under the State Avenue
Bridge.
Roof Level Area 1 – Installation of the
permanent roof has started.
Shot of the Stadium from Village West
Parkway and State Avenue showing
elevation change of roof canopy.
Area 1 – Shot of the West Building from the
southeast concourse.
Field Level Area 1 – Metal stud framing,
drywall and in wall MEP rough-in is ongoing.