memorandum for claimant - · pdf file17.10.1995 · memorandum for claimant iii 3....
TRANSCRIPT
14th Annual
Willem C. Vis (East) International Commercial Arbitration Moot Hong Kong
MemorandumforCLAIMANTCenterforArbitrationandMediationoftheChamberofCommerceBrazil-Canada
WrightLtd. v. SantosDKG
Abdul Ameer Faheem • Gharsanay Amin • Munira Aziz
Niyaz Muhammad Nickkhah • Sadaf Baseer • Samiullah Sharifi
AmericanUniversityofAfghanistan(AUAF)
On behalf of
Write Ltd.
232 Garrincha Street
Oceanside
Equatoriana
CLAIMANT
Against
SantosD KG
77 Avenida O Rei
Cafucopa
Mediterraneo
RESPONDENT
Memorandum for CLAIMANT
II
Table of Contents
Table of Contents.......................................................................................................................................II
TABLE OF ABBREVIATIONS..............................................................................................................IV
INDEX OF LEGAL AUTHORITIES...................................................................................................VIII
INDEX OF CASES..................................................................................................................................XX
LEGAL SOURCES AND MATERIAL..............................................................................................XXVII
STATEMENT OF FACTS........................................................................................................................1
SUMMARY OF ARGUMENTS...............................................................................................................2
ARGUMENTS............................................................................................................................................3
ISSUE ONE: CLAIMANT INITIATED THE ARBITRATION PROCEEDINGS ON TIME AND WITHIN 60 DAYS PERIOD SPECIFIED IN SECTION 21 OF THE DSA.........................................3
A. CLAIMANT'S ARBITRATION REQUEST IS ADMISSIBLE BECAUSE IT MEETS ALL THE REQUIREMENTS UNDER SECTION 21 OF DSA.................................................................4
1. CLAIMANT tried to resolve the dispute amicably in good faith through negotiation by considering the first step of dispute resolution mechanism adopted in section 21...........4
2. CLAIMANT initiated the arbitration proceedings on time considering the 60 days limitation set of on section 21 of DSA after the failure of negotiation...................................6
B. CAM-CCBC, THE GOVERNING RULE FOR THE CONTRACT COMPLIES WITH THE ARBITRATION REQUEST OF CLAIMANT..........................................................................7
C. THE INTERNATIONAL ARBITRATION PRACTICES DEEMS THE ARBITRATION PROCEEDINGS ON TIME AND ADMISSIBLE...............................................................................9
1. International arbitration practices are adopted in section 21 of the DSA which further accepts the day of commencement of arbitration on the day request is received by the administrator........................................................................................................................9
2. CLAIMANT's arbitration request meets the tests provided under Article 3 of CIArB........................................................................................................................................10
ISSUE TWO: THE ARBITRAL TRIBUNAL’S POWER IS LIMITED TO GRANT SECURITY FOR RESPONDENT’S COST UNDER DSA, TERMS OF REFERNCE AND THE GOVERNING RULES IN LINE WITH INTERNATIONAL ARBITRATION PRACTICES..................................11
A. UNDER THE DSA, TOR AND GOVERNING RULES SUCH AS CAM-CCBC AND UNCITRAL MODEL LAW, RESPONDENT IS NOT ELIGIBLE TO RECEIVE SECURITY FOR ITS COSTS..................................................................................................................................11
1. Silence of Development and Sales Agreement constitutes parties agreement on exclusion of security for cost....................................................................................................12
2. RESPONDENT’s request for security for cost was not included in the ToR............12
Memorandum for CLAIMANT
III
3. RESPONDENT’s request for security for cost is out of time based on the CAM-CCBC Rules..............................................................................................................................13
4. UNCITRAL Model Law limits the Tribunal’s power to award security for RESPONDENT’s costs.............................................................................................................14
B. THE INTERNATIONAL ARBITRATION PRACTICES LIMIT ARBITRAL TRIBUNAL’S POWER TO ORDER SECURITY FOR RESPONDENT’S COSTS.....................15
1. RESPONDENT failed to provide the likelihood of success for its claim in a prima facie test under Art. 2 of the CIArB........................................................................................15
2. RESPONDENT failed to show that CLAIMANT does not have funds to pay an adverse costs award..................................................................................................................17
3. RESPONDENT’s request to provide security for its cost is unfair under Art. 4 of CIArb........................................................................................................................................19
ISSUE THREE: CLAIMANT IS ENTITLED TO THE FULL PAYMENT IN THE AMOUNT OF US $22,723, 800 FOR THE FAN BLADES AND US$ 102,192.80 FOR THE FEE DEDUCTED FOR BANK CHARGES BASED ON THE DSA............................................................................................21
A. DSA, CISG AND UNIDROIT PRINCIPLES ENTITLE CLAIMANT TO THE FULL PAYMENT OF PURCHASE PRICE FOR THE FAN BLADES IN THE AMOUNT OF US$ 22,723, 800.............................................................................................................................................22
1. Parties’ intention behind adding fixed exchange rate provision in the addendum was only to govern the sale of the clamps, not the fan blades......................................................22
2. CISG entitles CLAIMANT to the full purchase price in the amount of US$22,723, 800 26
B. RESPONDENT IS OBLIGED TO PAY THE BANK CHARGES IN THE AMOUNT OF US$ 102,192.80 BASED ON THE DSA AND CISG..........................................................................28
1. Section 4(3) of the DSA obliges RESPONDENT to pay the levy charges in the amount of US$ 102,192.80........................................................................................................29
2. Art. 54 of CISG requires RESPONDENT to take all enabling steps, including paying the levy charges to make the full deposit of purchase price to CLAIMANT..........31
3. RESPONDENT’s analogy of Art.35 (2) CISG is not applicable in the current contract......................................................................................................................................33
CONCLUSION.........................................................................................................................................34
PROCEDURAL REQUEST....................................................................................................................35
REQUEST FOR RELIEF.......................................................................................................................35
Memorandum for CLAIMANT
IV
TABLE OF ABBREVIATIONS
AAA American Arbitration Association
ACICA Australian Center for International Commercial Arbitration
CAM-CCBC
Center for Arbitration and Mediation of the Chamber of
Commerce Brazil-Canada
Clm CLAIMANT
CIArB Chartered Institute of Arbitrators, Application for Security of
Cost
CEO Chief Executive Officer
CISG United Nation Convention of Contracts for the International
Sales of Goods
Co. Corporation
COO Chief Operating Officer
DIAC Dubai International Arbitration Center
DSA Development and Sales Agreement
EQD Equatorianian Dinar
et al. and others (et alii/et aliae/et alia)
Memorandum for CLAIMANT
V
Ex. Exhibition
e.g. For Example
HKIAC Hong Kong International Arbitration Center
ICC International Chamber of Commerce
ICDR International Center for Dispute Resolution
ICSID International Center for Settlement of Investment Disputes
i.e Pronoun (for example)
LAC Ljubljana Arbitration Centre
LCIA London Court of International Arbitration
Ltd. Limited
Mr. Mister
Ms. Miss
ML/2010 Money Laundering Law 2010
ML UNCITRAL Model Law
No. Number
Memorandum for CLAIMANT
VI
NCAP Notice for Commencement of Arbitration Proceedings
NY New York Convention
Ord of Pr. Order of the President of CAM-CCBC
P. Page
Para. Paragraph
PLC Private Limited Company
PO 1 Procedural Order No.1
PO 2 Procedural Order No.2
Res, RESPONDENT
Rec Record
SFC Security for Cost
SIAC Singapore International Arbitration Center
SoC Statement of Claim
SoR Statement of Response
Switz Switzerland
Memorandum for CLAIMANT
VII
TOR Terms of Reference
UK United Kingdom
UN United Nation
UNCITRAL United Nations Commission on International Trade Law
UNIDRIOT International Institute for Unification of Private Law
USA United States of America
USD United Stares Dollar
VIAC Vienna International Arbitration Center
Vol. Volume
Vs. Versus (Against)
YIA Yearbook International Arbitration
& And
Memorandum for CLAIMANT
VIII
INDEX OF LEGAL AUTHORITIES
A.O. RHODES – VIVOUR Security for the RESPONDENT’s costs of arbitral
proceedings with particular reference to the Arbitration
and Conciliation Act Cap 19, 1990 Laws of Nigeria
(ACA), News Journal of the Chartered Institute of
Arbitrators Nigerian Branch Vol. 2, 2005
cited as: A.O. Rhodes – Vivour
in para. 78
ALLISON E. BUTLER Allison E. Buttler, “A practical guide to the CISG:
Negotiations throughout litigation”, Aspen Publishers
(2007 Supplement).
http://cisg3.law.pace.edu/cisg/biblio/butler6.html
cited as: Allison E. Butler
in para. 110
ALI YESILIRMAK Provisional Measures in International Commercial
Arbitration, International Arbitration Law Library,
Volume 12; Kluwer Law International (2005); pp. 47 –
11
cited as: Ali Yesilirmak
in para. 73
Memorandum for CLAIMANT
IX
BORN GARY B. International Commercial Arbitration, 2nd edition,
Kluwer Law International
New York 2014, pp. 518, 538
cited as: Born
in para. 58, para. 59, para. 65
BLACKABY NIGEL &
PARTASIDES CONSTANTINE
WITH REDFREN ALAN &
HUNTER MARTIN
Redfern and Hunter on International Arbitration, Fifth
Edition, Student Version, August 2009
cited as: Blackaby et al.
in para. 40
CHARLES N. BROWER AND W.
MICHAEL TUPMAN
Court-Ordered Provisional Measures Under the New
York Convention
The American Journal of International Law
Vol. 80, No. 1 (Jan., 1986), pp. 24-42
Published by: American Society of International Law
cited as: Charles et al.
in para. 49
Memorandum for CLAIMANT
X
DENIS TALLON The Buyer's Obligations Under the Convention on
Contracts for the International Sale of Goods Published
in Galston & Smit ed., International Sales: The United
Nations Convention on Contracts for the International
Sale of Goods,
Matthew Bender (1984), Ch. 7, pages 7-1 to 7-20.
cited as: Tallon
in para. 125
DIETRICH MASKOW Commentary on Article 54 of CISG
Cite as Maskow, in Bianca-Bonell Commentary on the
International Sales Law, Giuffrè: Milan (1987) 383-393.
Reproduced with permission of Dott. A Giuffrè Editore,
S.p.A
Para,2.2.2. Page: 395
http://www.cisg.law.pace.edu/cisg/biblio/maskow-
bb53.html
cited as: Maskow
in para. 108, para. 125, para.126
Memorandum for CLAIMANT
XI
FRTIZ ENDERLEIN &
DIETRICH MASKOW
Commentary on Preamble of CISG
www.cisg.law.pace.edu/cisg/text/preamble.html
cited as: Enderlein & Maskow
in para. 112
GARY F. BELL Kroll/Mistelis/Perales/Viscasillas. eds, (Book),
Gary F. Bell, p. 858
cited as: F. Bell
in para. 110
HENRY DEEB GABREIL THE BUYER’S PERFORMANCE UNDER THE CISG:
ARTICLES 53-60 TRENDS IN THE DECISIONS
Journal of law and commerce: 274 JOURNAL OF LAW
AND COMMERCE [Vol. 25:273]
cited a:. Gabreil, P. 274
in para. 125
HOLTZMANN, NEUHAUS Chap IV, p. 530-547
cited as: Holtzmann, Neuhaus, et al.
in para. 58
Memorandum for CLAIMANT
XII
HONNOLD & FLECHTER Uniform Law for International Sales under the 1980
United Nations Convention , 4th edition
cited as: Honnold & Flechter
in para. 101
JULIAN D M LEW, LOUKAS A
MISTELIS, STEFAN M KROLL
Comparative International Commercial Arbitration,
Kluwer Law International, New York 2014
cited as: Julian
in para. 52, para. 54, para. 65
JOHN O. HONNOLD Article 8 words and phrases, Degrees of knowledge
http://www.cisg.law.pace.edu/cisg/text/words8.html
cited a: John O. Honnold
in para. 117
LUDMILLA HERBST Security for costs in commercial arbitration: playing hard
to get, The Lawyers Weekly, Canada, 2009
cited as: Ludmilla Herbst
in para. 47
Memorandum for CLAIMANT
XIII
LEIF SEVÓN Commentary on article 54 of CISG P.205
cited as: Leif Sevón
in para. 110
MALCOLM EVANS Commentary on the preamble of CISG
Cite as Evans, in Bianca-Bonell Commentary on the
International Sales Law, Giuffrè: Milan (1987) 23-25.
Reproduced with permission of Dott. A Giuffrè Editore,
S.p.A.
http://cisg.law.pace.edu/cisg/biblio/preamble-bb.html
cited as: CISG Preamble
in para. 112
MARIANNE ROTH MICHAEL
GEISTLINGER¸ MARIANNE
STEGNER
Yearbook on International Arbitration, Volume III,
Vienna, 2013
cited as: YIA, Vol III
in para. 73
Memorandum for CLAIMANT
XIV
MARTINEZ LUIS MANUEL,
HANESSIAN GRANT
ICDR Awards and Commentaries
CHAPTER 1, A GUIDE TO ICDR CASE
MANAGEMENT, September 2012
cited as: Martinez
in para. 39, para. 40
KATIA YANNACA-SMALL Arbitration Under International Investment Agreements:
A Guide to the Key Issues
Katia Yannaca-Small, Oxford University Press, 2010
cited as: Katia Yannaca
in para. 71
PETER SCHLECHTRIEM AND
PETRA BUTLER
UN Law on International Sales: The UN Convention on
the International Sale of Goods
cited as: Schlechtriem/Butler
in para. 94
Memorandum for CLAIMANT
XV
PETER SCHLECHTRIEM Uniform Sales Law: The UN-Convention on Contracts
for the International Sale of Goods: Manz, 1986
cited as: Schlechtriem
in para. 115, para. 134
PETER SCHLECHTRIEM Peter Schlechtriem Commentary on Article 8 of CISG
Published by Manz, Vienna: 1986.Reproduced with their
permission. Interpretation of Statements and Conduct
http://www.cisg.law.pace.edu/cisg/biblio/schlechtriem.h
tml
cited as: Schlechtriem
in para. 108, para. 125
PETER SCHLECHTRIEM Commentary on Art.53(2) of CISG
www.cisg.law.pace.edu/cisg/biblio/schlechterim10.html
P.6-20
Cites as: Schlechtriem
In para. 126
Memorandum for CLAIMANT
XVI
PETER SCHLECHTRIEM Uniform Sales Law in the Decisions of the
Bundesgerichshof
p.88
http://www.cisg.law.pace.edu/cisg/biblio/schlechtriem3
.html
cited as: Schlechtriem
in para. 110
PETRA BUTLER & ARJUN
HARINDRAANATH
Kroll/Mistelis/Perales/Viscasillas. eds, (Book),
Petra Butler/ and Arjun Harindraanath p. 797
cited as: Butler/Harindraanath
in para. 110, para. 126
PILAR PERALESVISCASILLAS Kroll/Mistelis/Perales/Viscasillas. eds, (Book),
Pilar Perales Viscasillas, P.121
cited as: Perales Viscasillas
in para. 90
Memorandum for CLAIMANT
XVII
PATRICK X. BOUT Trade Usages: Article 9 of the Convention on Contracts
for the International Sale of Goods, Commentary on
article 9, Pace essay submission (1998).
www.cisg.law.pace.edu/cisg/biblio/bout.html
cited as: Patrick X. Bout
in para. 121, para. 123
PETER ASHFORD Handbook on International Commercial Arbitration:
Second Edition, United States, 2014
cited as: Peter Ashford
in para. 67
RICHARD STONE The Modern Law of Contract 6th edition: Richard Stone,
P.228
cited as: Stone
in para. 101
SCHLECHTRIEM &
SCHWENZER
Commentary on the UN Convention on the International
Sales of Goods (CISG), 3rd Edition
Edited by: Ingerborg Schwenzer
cited as: Schlechtriem & Schwenzer
in para. 110, para. 126, para. 131
Memorandum for CLAIMANT
XVIII
STEPHEN COLBRAN Security for Costs of Arbitration Proceedings in England,
New Zealand and Australia, Australia, 1993
cited a: Stephen
in para. 47
STEPHEN COLBRAN Security for Costs against Corporations - s 1335
Corporations Act, Australia, 1993
cited as: Stephen Colbran
in para. 72
THOMAS H. WEBSTER Handbook of ICC Arbitration: Commentary, Precedents,
Materials, 3rd edition, UK 2014
cited as: Webster Commentary
in para. 26
VICTOR KNAPP Commentary on Art.54 of CISG
Bianca-Bonell Comentary on the International Sales
Law, Giuffre,
P.453
cited as: Knapp
in para. 111
Memorandum for CLAIMANT
XIX
WENDY/DUNCAN Wendy/Duncan, P. 33
cited as: Wendy/Duncan
in para. 58
WEIXIA GU Security for Costs in International Commercial
Arbitration, 2005
Kluwer Law International Journal of International
Arbitration, Issue 3 PP. 167-206
cited as: Weixia Gu
in para. 79
WEBSTER THOMAS H/
BUHLER DR MICHAEL
Handbook of ICC Arbitration Commentary, Precedents,
Materials,
Third edition, United Kingdom
cited as: Webster et al.
in para. 76
Memorandum for CLAIMANT
XX
INDEX OF CASES
ICC Awards
ICC Case No. 13070 (2006) Award in ICC No. 13070 in 2006 in Paris,
pp.434
cited as: ICC Case No. 13070 (2006)
in para: 77
ICC Case No. 10032 (1999) Award in ICC Case No. 10032 in 1999 in
Zurich, European Union
Yugoslavia vs. Serbia
cited as: ICC Case No. 10032
in para. 74
Vekoma B V vs. Moren Coal Corps Jurisdiction and Admissibility
Jan Paulsson
Published in November 2005
ICC Publication, Publication 693
cited as: Vekoma B V. Vs. Maran Coal Corp
in para. 22
Memorandum for CLAIMANT
XXI
ICSID Awards
Maffezini v. Spain (1999) Maffezini v. Spain in 1999, Spain,
International Centre for Settlement of
Investment Disputes, (ICSID).
cited as: Maffezini v. Spain
in para. 53, para. 67
Libananco v. Turkey (2008) Libananco v. Turkey in 2008, Libananco
International Center for Settlement of
Investment Disputes, (ICSID).
cited as: Libananco v. Turkey
in para. 68
Burimi S.R.L. v. Albania (2012) Burimi S.R.L. v. Albania in 2012,
International Centre for Settlement of
Investment Disputes, (ICSID).
cited as: Burimi S.R.L. v. Albania
in para. 72
Memorandum for CLAIMANT
XXII
Burimi S.R.L. and Eagle Games SH.A. v. Republic of Albania (2012)
Burimi S.R.L. and Eagle Games SH.A. v. Republic of Albania (2012)
International Centre for Settlement of Investment Disputes, (ICSID).
cited as: Burimi S.R.L. and Eagle Games SH.A. v. Republic of Albania (2012))
in para. 56
RSM production Corporation vs. Government
of Grenada (2010)
RSM production Corporation vs. Government
of Grenada in 2010
International Centre for Settlement of
Investment Disputes, (ICSID).
ICSID Case No. ARBII 0/6
cited as: RSM production Corporation vs.
Government of Grenada (2010)
in para. 70
Republic of Guinea v. Atlantic Triton
Company (1986)
Republic of Guinea v. Atlantic Triton
Company (1986)
International Centre for Settlement of
Investment Disputes, (ICSID).
cited as: Republic of Guinea v. Atlantic Triton
Company (1986)
in para. 71
Memorandum for CLAIMANT
XXIII
Clout Cases
Clout Case No. 142 Clout Case No. 142
Russia 17 October 1995 Arbitration proceeding 123/1992
Arbitration at Russian Federation Chamber of Commerce
and Industry [No. 123/1992 of 17 October 1995]
http://cisgw3.law.pace.edu/cases/951017r1.html
cited as: Clout Case No. 142
in para. 128, para. 129
Clout Case No. 104 Clout case No. 104
Court of Arbitration of the International Chamber of
Commerce
A/CN.9/SER.C/INDEX/1
19 September 1995
www.uncitral.org/clout/clout/data/oth/clout_case_104_leg-
1307.html
cited as. Clout case No. 104
in para. 132
Memorandum for CLAIMANT
XXIV
CLOUT case No. 652 CLOUT case No. 652
Tribunale di Padova (District Court Padova)
Italy, 10 January 2006
Italian company Vs. United Kingdom
http://cisgw3.law.pace.edu/cases/060110i3.html
cited as: CLOUT case No. 652
in para. 109
CLOUT case No. 608 CLOUT case No. 608
Tribunale di Rimini (District Court Rimini)
Italy, 26 November 2002
France Vs. Italy
http://cisgw3.law.pace.edu/cases/021126i3.html
citedas:CLOUT case No. 608
in para. 109
Memorandum for CLAIMANT
XXV
A. S.p.A. v. B AG (1997) A.S.p.A. v. B AG, case in 1997, Rules of Arbitration of
the Geneva Chamber of Commerce and Industry
cited as: A. S.p.A. v. B AG
in para. 80
Agriculture products case Agriculture products case
Tribunale di Padova, No.40552
Italy, 25 February 2004
Austria Vs. Italy
http://cisgw3.law.pace.edu/cases/040225i3.html
cited as: Agriculture products case
in para. 109
Kantonsgericht Schaffhausen Kantonsgericht Schaffhausen
Switzerland, 25 February 2002
Italy Vs. Switzerland
http://cisgw3.law.pace.edu/cases/020225s1.html
cited as: Kantonsgericht Schaffhausen
in para. 109
Memorandum for CLAIMANT
XXVI
American Cyanamid Co vs.
Ethicon LTD case (1975)
American Cyanamid Co vs. Ethicon LTD in 1975, United,
Kingdom, House of Lords
cited as: American Cyanamid Co vs. Ethicon LTD
in para. 82, para. 84
Medical Marketing v.
Internazionale Medico
Scientifica
Clout case No. 418
Tribunal: U.S. District Court, Eastern District of Louisiana
http://cisg3.law.pace.edu/cases/990517u1.html
cited as: Medical Marketing v. Internazionale Medico
Scientifica
in para. 137
Memorandum for CLAIMANT
XXVII
LEGAL SOURCES AND MATERIAL
ACICA RULES ACICA Expedited Arbitration Rules
1 January 2016
Article 4.2
AAA INTERNATIONAL
ARBITRATION RULES
Commercial Arbitration Rules and Mediation
Procedures, Including Procedures for Large
Complex Commercial Disputes Rules Amended and
Effective October 1, 2013 Fee Schedule Amended and
Effective July 1, 2016
R-4 (h)
CAM-CCBC ARBITRATION
RULES
Center for Arbitration and Mediation of the Chamber
of Commerce Brazil-Canada, Arbitration Rules, 2011
Article 2.6, Article 4, Article 4.1, Article 4.21, Article
6.2.
Memorandum for CLAIMANT
XXVIII
COMMENTARY ON CAM-CCBC
Commentary on Center for Arbitration and Mediation
of the Chamber of Commerce Brazil-Canada,
Arbitration Rules,
Wald Arnoldo / Borja Ana Gerdau/ Longo Bryan/
Terashima Edardo Ono/ de Melo Maria/ Vieira/
Filho Napoleao Casado and Gagliardi Rafael Villar.
CIARB, APPLICATION FOR
SECURITY FOR COST
International Arbitration Practice Guideline,
Application for Security for cost, CIArb, London,
Article 1.2, Article 2, Article 3, Article 4.
CISG Methodology Commentary about the preamble of CISG,
Authors: Andre Janssen and Olaf Meyer
P.137
COMMENTARY ON CIARB,
APPLICATION FOR SECURITY
FOR COST
International Arbitration Practice Guideline,
Application for Security for cost,
Chartered Institute of Arbitrators
CIArb, Practice and Standards Committee, Tim Hardy
et.al, London.
Memorandum for CLAIMANT
XXIX
CISG United Nations Convention on Contracts for the
International Sales of Goods,
Article 53, Article 54, Article 62.
COMMENTARY ON HONG
KONG INTERNATIONAL
ARBITRATION CENTRE
Commentary on HKIAC’s proposed administered
arbitration rules, March 20, 2008
Simon Chee Wai Hung
COMMENTARY ON UNCITRAL
ARBITRATION RULES
The UNCITRAL Arbitration Rules
Kluwer Law International,
David D. Caron et.al, P.517
DIAC RULES Dubai International Arbitration Centre,
2007
Article: 4.6
DIS- GERMAN INSTITUTION OF
ARBITRATION RULES
DIS- GERMAN INSTITUTION OF ARBITRATION
RULES
as from 1 July 1998
Article 2.6
Memorandum for CLAIMANT
XXX
EXPLANATORY NOTE ON
CAM-CCBC RULES
Approved by an extraordinary general meeting of
Brazil- Canada Chamber of Commerce on September 1,
2011 with amendments on April 28, 2016
GUIDELINE INTERNATIONAL ARBITRATION PRACTICE
GUIDELINE,
Chartered Institute of Arbitrators
Jurisdictional Challenges
London, United Kingdom
Founded in 1915 and with a Royal Charter granted in
1979 Article 3 commentary “Admissibility of Claims"
HKIAC ARBITRATION RULES Administered Arbitration Rules
Hong Kong International Arbitration Centre
November, 2013
Article 4.2, Article 4.7
ICA India Council of Arbitration
(with effect on and from1 January,
2014, Rule 15 (e))
ICC ARBITRATION RULES International Chamber of Commerce, Rules of
Arbitration, Paris, 2009
Memorandum for CLAIMANT
XXXI
ICDR INTERNATIONAL ARBITRATION
RULESINTERNATIONAL DISPUTE RESOLUTION
PROCEDURES (Including Mediation and Arbitration
Rules) Rules Amended and Effective June 1, 2014 Fee
Schedule Amended and Effective July 1, 2016
LCIA RULES UK, 2014 London Court of International Arbitration Rules
LJUBLJANA ARBITRATION
CENTER
Ljubljana Arbitration at the Chamber of Commerce and
Industry of Slovenia
Dispute Resolution Since 1928
Article 4
LUTTRELL S R, MOENS G A Commentary on the Arbitration Rules of the Australian
Centre for International Commercial Arbitration
MILAN CHAMBER OF
COMMERCE - INTERNATIONAL
ARBITRATION RULES
Milan Chamber of Commerce - International Arbitration
Rules
Appointing Authority under the Arbitration Rules of the
United Nations Commission for International Trade
Law (UNCITRAL)
Article 1.4, Article 3
Memorandum for CLAIMANT
XXXII
NEW YORK CONVENTION Convention on the Recognition and Enforcement of
Foreign Arbitral Awards, New York, June 10, 2958
Article V (1) (c)
RECOGNITION AND
ENFORCEMENT OF FOREIGN
ARBITRAL AWARDS
A Global Commentary on the New York Convention
Kluwer Law International; Kluwer Law
International 2010
pp. 257 – 280
SWISS RULES Swiss Rules of International Arbitration (Swiss Rule)
January 2006
Article 3.2, Article 3.5
SIAC RULES Arbitration Rules of the Singapore International
Arbitration Centre SIAC Rules 6th Edition, 1 August
2016
Article 3.3
SCC ARBITRATION RULES The Arbitration Institute of Stockholm/ Stockholm
International Arbitration Rules 2010
Article 4
Memorandum for CLAIMANT
XXXIII
THE ARBITRATION INSTITUTE
OF STOCKHOLM / STOCKHOLM
INTERNATIONAL
ARBITRATION RULES
The Arbitration Institute of Stockholm / Stockholm
International Arbitration Rules
Article 4
THE VIENNA RULES:
COMMENTARY ON
INTERNATIONAL
ARBITRATION IN AUSTRIA
Rules of Arbitration of the Vienna International
Arbitral Centre (VIAC), Vienna July 1, 2013,
Franz T. Schwarz, Christian W. Konrad
Kluwer Law International, Netherland, 2013
UNCITRAL MODEL LAW UNCITRAL Model Law on International Commercial
Arbitration 1985 with amendments as adopted in 2006,
Vienna June 21, 1985
UNIDROIT PRINCIPLES International Institute for the Unification of Private
Law
Article 4.1
VIAC RULES Rules of Arbitration
Vienna Rules in force as from 1 July 2013
Article 7
Memorandum for CLAIMANT
1
STATEMENT OF FACTS
1. Parties to this arbitration are Wright Ltd. “CLAIMANT” and SantosD KG “RESPONDENT”.
CLAIMANT is a highly specialized manufacturer of fan-blades for jet engines incorporated in
Equatoriana. RESPONDENT, a medium sized manufacturer of jet engines incorporated in
Mediterraneo.
2. CLAIMANT and RESPONDANT were subsidiaries of Engineering International SA (EISA) until
year 2010, which was a multinational, based in Oceania and active in various fields of engineering,
in particular turbines of all sorts. However, in June 2010, CLAIMANT was sold to Wright Holding
PLC. In July 2010, RESPONDENT was sold to a Private Equity Fund the SpeedRun.
3. In 2010, during their sale, CLAIMANT and RESPONDENT were in negotiations to jointly
“develop” a new fan blade for the next generation of RESPONDENT’s high-spec jet engine, JE
76/TL14b. [Clm, Ex.C1, P.9, Section 2].
4. RESPONDENT ordered to buy 2,000 of the swept fan blades for the first year [Clm, Ex.C2, P.9,
Section 2, Para. 3]. While entering into contract, the final cost of new blades in terms of
development and production were not clear. However, RESPONDNET insisted to fix a maximum
price to be paid so that it could offer itself a price for engine to Earhart [Clm, Ex.C1, P.8, Para.
4]. CLAIMANT determined the price range of blades on the basis of estimate, which is per blade
US$ 9,975 to US$ 13,125 [Clm, Ex.C2, P.10, Section 4] to which a certain profit will be added.
CLAIMANT estimated the production cost per blade around EQD 20,000, considering the recent
experience with TRF 192. According to the exchange rate, this cost would be around US$10,000,
since the exchange rate had stayed same for last three years and it has been around US$ 1 = EQD
2.00 and US$ 1 = EQD 2.02 [Clm, Ex.C1, P.8, Para. 4].
5. After the conclusion of contract for fan blades, RESPONDENT ordered to have the same amount
of clamps connecting the blades to the shaft of the fans. RESPONDENT at first wanted to buy the
clamps form another producer but due to the quality it decided to with CLAIMANT [Res, Ex.R2,
P.28]. CLAIMANT out of good faith and considering the limited size of the second contract
accepted RESPONDANT’s request and agreed on the fixed exchange rate for clamps only and
signed the addendum on October 24, 2010 [Res, Ex.R2, P.28]. Since influence of exchange rate
was limited due to the much lower amount of clamps.
Memorandum for CLAIMANT
2
6. On 14 January 2015, as per contract, CLAIMANT fulfilled its obligation and delivered requested
amount of fan blades and clamps to the RESPONDENT. Unfortunately, due to a mistake in
CLAIMANT’s accounting department, the invoice for the fan blades attached to the delivery was
wrong. Instead of providing for a price of US$ 22,723,800, the invoice was only for US$
20,438,560 it was because Mr. Lee the person who was responsible for creating the invoice, had
first prepared the invoice for the clamps using the fixed exchange rate as under the addendum.
When he prepared the invoice for the fan blades, he applied the same fixed exchange rate,
overlooking that for the price calculation for the fan blades the current exchange rate was to be
applied [Clm, Ex.C4, P.13].
7. Using the opportunity, RESPONDENT immediately paid the amount on CLAIMANT's account
at the Equatoriana National Bank and informed CLAIMANT via email on 15 January that a
payment of US$ 20,438,560 for blades and US$ 183,343.28 for clamps has been paid [Clm,
Ex.C3, P.12]. After doing an inquiry at the Equatoriana National Bank, Ms. Beinhorn found out
that the Equatoriana Central Bank had investigated the payment for money laundering as per
Regulation ML/2014C. 0.5% levy was deducted as per Section 11 of the Regulation.
8. CLAIMANT had made it clear that The BUYER will deposit the purchase price in full into the
SELLER’s the bank charges has to be covered by RESPONDANT [Clm, Ex.C2, P.10, Section 4,
Para. 3]. On 2 February 2015 Mr. Lindbergh denied any additional purchase price. [Clm, Ex.C7
P.16]. CLAIMANT by making several offers with the combination of reduction in the sales price
for the 2,000 fans tried to resolve the dispute amicably as per requirement under Section
21.However, RESPONDENT insisted on $ 9,744.28 per fan blade.
9. After all the efforts to resolve the dispute amicably Having no other choice, CLAIMANT,
respecting the section 21 of agreement, initiated the process of arbitration within 60 days and
informed the RESPONDENT on April 01 [Res, Ex.R3, P.29]. Parties signed the Terms of
Reference and agreed on the submitted issues on August 22, 2016. 15 days later on September 6,
2016 RESPODANT made the request of security for cost but it failed to provide any justification
or proof of their need of the security for their cost.
SUMMARY OF ARGUMENTS
10. RESPONDENT’s breach of its contractual obligations under the Development and Sales
Agreement (DSA), i.e., its failure to deposit the purchase price in full into CLAIMANT’s account
Memorandum for CLAIMANT
3
and not bearing the bank charges, eviscerates CLAIMANT’s contractual rights. With respect to
the good faith and section 21 of the DSA, CLAIMANT was open for any meaningful negotiation
till the last moment of the 60 days time period. CLAIMANT initiated arbitration proceedings
against RESPONDENT on time when found that it is not possible to resolve the dispute amicably
(I).
11. During the arbitration proceedings, RESPONDENT made a belated request for security of its costs
that it is likely to incur. Under the Development and Sales Agreement, Terms of Reference, other
governing rules, particularly Chartered Institute of Arbitrators, the arbitral tribunal power is
limited to grant security for RESPONDENT’s cost in this particular case (II).
12. Parties agreed in section 4 (3) of the DSA that the BUYER (RESPONDENT) will deposit the
purchase price in full into the SELLER’s (CLAIMANT’s) account and will bear the bank transfer
charges. RESPONDENT failed to perform its contractual obligations by not paying the purchase
price in full and bearing the bank transfer charges as agreed in the DSA. CLAIMANT is entitled
to the outstanding payments from RESPONDENT in the amount of US$ 2,285,240.00 for the fun
blades based on the current exchange rate of (US$ 1 = EQD 1.79) and US$ 102,192.80 for the fees
deducted by the central bank (III).
ARGUMENTS
ISSUE ONE: CLAIMANT INITIATED THE ARBITRATION PROCEEDINGS ON TIME
AND WITHIN 60 DAYS PERIOD SPECIFIED IN SECTION 21 OF THE DSA
13. RESPONDENT by taking advantage of the obvious mistake made in the first invoice, immediately
effected the payment [Clm, Ex.C3, P.12]. Even after CLAIMANT provided clarification on the
mistake and requested outstanding payment in the amount of US $ 2,285,240.00 [Clm, Ex.C5,
P.14], yet RESPONDENT rejected any additional payment [Clm, Ex.C7, P.16].
14. CLAIMANT tried to resolve the dispute amicably in good faith through negotiation considering
all the provisions mentioned on the section 21 of the DSA [PO2, P.58, para. 23; Res, Ex.R3, P.29].
However, RESPONDENT refused any further payment and was not willing to continue with the
contract on the purchase of another 2000 blades [PO2, P.58, para. 23]. This act of
RESPONDENT left no other choice to CLAIMANT other than initiating the arbitration
proceedings.
Memorandum for CLAIMANT
4
15. CLAIMANT valuing the long-term contractual relationship informed RESPONDENT that
CLAIMANT will remain open to negotiation, if RESPONDENT reconsiders its view, otherwise
CLAIMANT will initiate the arbitration proceedings [Res, Ex.R3, P.29]. RESPONDENT by not
showing any reaction to CLAIMANT's amicable efforts forced CLAIMANT to exercise its right
under section 21 of the DSA and initiate the arbitration proceedings [PO2, P.58, para. 23; Clm,
Ex.C2, P.11].
16. According to RESPONDENT, CLAIMANT has initiated the arbitration proceedings late [Res,
P.25, para. 13]. To the contrary, CLAIMANT will show that it has initiated the arbitration
proceedings on time for the following reasons: First, CLAIMANT's arbitration request meets all
the requirements of section 21 of DSA (A). Second, President of CAM-CCBC confirmed and
accepted the receipt of the arbitration proceedings since the arbitration request submitted by the
CLAIMANT was in compliance with the requirements of article 4.1 of CAM-CCBC (B).
According to the International Practices adopted in section 21 of the DSA, arbitration is
commenced on the day the request is received by the administrator, or secretariat making
CLAIMANT's arbitration request on time (C).
A. CLAIMANT'S ARBITRATION REQUEST IS ADMISSIBLE BECAUSE IT
MEETS ALL THE REQUIREMENTS UNDER SECTION 21 OF DSA
17. Section 21 of the DSA, the dispute resolution agreement provides that the first step to dispute
resolution is to resolve the dispute amicable through negotiation. If the parties failed to reach an
agreement, both have the right to initiate arbitration proceedings within 60 days after the failure of
negotiation [Clm, Ex.C2, P.11].
18. In the following, CLAIMANT put efforts to resolve the dispute amicably through negotiation (1)
when negotiation failed CLAIMANT initiated the arbitration proceedings within 60 days and
submitted the request on time (2).
1. CLAIMANT tried to resolve the dispute amicably in good faith through
negotiation by considering the first step of dispute resolution mechanism adopted
in section 21
19. Section 21 of the DSA provides “All disputes arising out of or in connection with this Agreement
shall be settled amicably and in good faith between the parties"[Clm, Ex.C2, P.10/11].
Accordingly CLAIMANT put efforts to have amicable solution for the dispute. CLAIMANT sent
Memorandum for CLAIMANT
5
an email to RESPONDENT on January 15 trying to negotiate and apologized for the mix up on
the invoices. Furthermore, CLAIMANT offered that the additional cost for the transfer of
remaining money will be borne by CLAIMANT [Clm, Ex.C5, P.14, para. 3], but RESPONDENT
did not respond.
20. CLAIMANT sent another email on February 9, 2015 stating that CLAIMANT has not received
the outstanding payment in the amount of US $ 2,285,240. The amount received on 29 January,
2016 is US$ 20,336,367.20 which is not effected based on the mistaken invoice [Clm, Ex.C6,
P.15]. In response, RESPONDENT completely rejected making any further payments [Clm,
Ex.C7, P.16]. CLAIMANT could initiate the arbitration proceedings. However, respecting the
long term-contractual relationship and the provision of amicable resolution in section 21 of DSA,
CLAIMANT agreed to have a meeting with RESPONDENT on March 31, 2016 to further discuss
and find amicable solution [PO2, P.58, para. 23].
21. In the meeting, CLAIMANT proposed several other offers to RESPONDENT. The offers included
reduction in the price of the fan blades as well as a firm confirmation to the delivery of fan blades
within the next five years [PO2, P.57, para. 23]. These efforts were again rejected by
RESPONDENT, because RESPONDENT was not willing to pay the due payment [PO2, P.57,
para. 23]. Subsequently, CLAIMANT sent an email on April 1, 2016 stating that if
RESPONDENT reconsiders its view, CLAIMANT will remain open to any meaningful
negotiation. CLAIMANT did not receive any response and was obliged to initiate the arbitration
proceedings [Res, Ex.R3, P.29, Para. 2].
22. In a similar case (Vekoma B V. Vs. Maran Coal Corp) where the seat of Arbitration was in
Switzerland, the CLAIMANT had only 30 days to initiate the Arbitration proceedings. The parties
had a similar agreement like the section 21 of the DSA on limitation of the time set of for 60 days
to initiate the arbitration proceedings. RESPONDENT challenged the admissibility of the case
based on lapse of time, but the arbitral tribunal rejected the request of RESPONDENT and
accepted the admissibility. Since, RESPONDENT did not respond to the last email sent by
CLAIMANT. CLAIMANT having good faith waited for the last responds of RESPONDENT in
order to make the final decision for initiation of the arbitration proceedings.
Memorandum for CLAIMANT
6
2. CLAIMANT initiated the arbitration proceedings on time considering the 60 days
limitation set of on section 21 of DSA after the failure of negotiation
23. Section 21 of the DSA provides “if no agreement could be reached, each party has the right to
initiate arbitration proceeding with 60 days after the failure of negotiation” [Clm, Ex.C2, P.11].
Based on the Law 9.307 1996 a contract having an arbitration clause any dispute arising between
the parties shall be resolved through arbitration [Wald et al. P.71]. CLAIMANT, after not
receiving the response to its email on April 01, 2016, found that negations have failed [Clm, Ex.R3,
P.29, Para. 2]. CLAIMANT initiated the arbitration proceedings on May 31, 2016 [Clm, P.2].
24. Article 4.2.of Arbitration Rule of International Chamber of Commerce (ICC), dictates that “the
date on which the Request is received by the Secretariat, shall, for all purposes, be deemed to be
the date of the commencement of the arbitration". It is found from the facts of the case that the
date of the commencement of arbitration is 31st May, 2016 [Ord of Pr. P.19, para. 1; NCAP, P.22,
para. 1]
25. Article 3.5 of Swiss rules and article 6.4 of DIS-German Institute of Arbitration rules states that if
the defects in the arbitration request is submitted within the applicable time-limit, then the
arbitration shall be deemed to have been validly filed on the date on which the initial version was
received by the Secretariat.
26. According to Thomas H. Webster and Dr. Michael Buhler under article 4 (2) the date of the receipt
of arbitration is the date of commencement of arbitration. Accordingly, ICC arbitration has to be
differentiated from the ad hoc arbitrations or the general provisions under the UNCITRAL Model
Law which provides that the date of commencement is the date when the RESPONDENT is
notified. Consequently, the date of receipt of the arbitration request by Secretariat will prevail and
be the date of commencement of arbitration [Webster Commentary, P.69, para. 4-12].
27. S R Luttrell and G A Moens, the two legal commentators have agreed on the commencement time
of Arbitration proceeding based on the ICC article 4.2, Article 5.2 ACICA, Article 3.2 of Swiss
Rules that the arbitral proceeding shall be deemed to commenced on the date the Notice of
Arbitration is received by the administrator, chamber of tribunal and registry, not the
RESPONDENT [Luttrell et al, P.8]. President's Order on the receipt of the arbitration request and
the Notice of Commencement of arbitration sent to RESPONDENT are the firm proofs that the
Memorandum for CLAIMANT
7
Arbitration Proceeding was initiated and accepted on May 31, 2016. [Ord of Pr. P.19, para. 1;
NCAP. P.22, para. 1].
28. CLAIMANT respected all the dispute resolution mechanisms provided under section 21 of the
DSA and initiated the arbitration proceeding on time on May 31, 2016 after negotiation failed on
April 1, 2016.
B. CAM-CCBC, THE GOVERNING RULE FOR THE CONTRACT COMPLIES
WITH THE ARBITRATION REQUEST OF CLAIMANT
29. In section 21 of the DSA, Parties have agreed to include CAM-CCBC as the governing rule [Clm,
Ex.C2, P.11]. Article 4.1. CAM-CCBC states, “The party desiring to commence an arbitration
will notify the CAM/CCBC, through its President”. CLAIMANT submitted the arbitration
proceeding request on May 31, 2016 [Clm, P.4] and the CAM-CCBC president confirmed the
receipt of request for arbitration [Ord of Pr. P.19, Para. 1].
30. As per Arlando Wald “Whenever a dispute arises out of such a contractual relationship, the
damaged party should notify the CAM-CCBC’s president, requesting the commencement of
arbitration. Such a notification must contain all the information and document listed under 4.1,”
[Wald et al. P.64. Para. 2]. CAM-CCBC after receiving the request did not reject the request but
the CAM-CCBC asked for amendments [Ord of Pr. P.19, para. 4].
31. Article 4.1 of CAM-CCBC provides certain requirements that has to be fulfilled for the
commencement of an arbitration, and CLAIMANT’s request for arbitration met all the
requirements under article 4.1 of CAM-CCBC. CLAIMANT was asked by the secretariat of CAM-
CCBC to bring the required amendments on two of the submitted documents within 10 days [Ord
of Pr. P.19, para. 3]. The power of attorney was submitted in the name of Wright Holding PLC
instead of Wright Ltd, and the registration fee was paid in amount of 400$ instead of 4000$ [Ord
of Pr. P.19, Para. 2]. CLAIMANT submitted the amended documents on 7 June 2016, which was
within the 10-day period allowed by CAM-CCBC [Clm, P.20].
32. Article 2.6 of CAM-CCBC states the duties of president of CAM-CCBC. Furthermore, Article 2.6
(f) of CAM-CCBC provides that the president of CAM-CCBC can issue the complementary rules
in order to remove doubts and provide guidance for proper application of CAM-CCBC rules, as
well as in cases of gaps. Additionally, Article 2.6 (i) dictates that the president can decide on
extension of time periods which do not came under the authority of the Tribunal.
Memorandum for CLAIMANT
8
33. Likewise, the explanatory note on the arbitration rules of CAM-CCBC, which was approved by
an extraordinary general meeting of Brazil-Canada Chamber of Commerce on 01 September, 2011
with amendments on 28 April, 2016, provides that amendments have no impact on the
administration of the arbitration proceedings of CAM-CCBC (Explanatory Note, CAM-CCBC).
34. Moreover, Hong Kong International Arbitration Center leaves no doubt about the fact that the day
of commencement of arbitration is the date when the request was submitted. These rules were
approved by the council of HKIAC for the parties who look for the requirements of an administered
arbitration. [Simon, P.13 of 17]. According to Article 4.2 of HKIAC, the arbitral proceedings shall
be deemed commenced on the date on which the notice of arbitration is received.
35. Additionally, Article 4.7 provides “If the Notice of Arbitration is incomplete or if the Registration
Fee is not paid, HKIAC may request the CLAIMANT to remedy the defect within an appropriate
period of time. If the CLAIMANT complies with such directions within the applicable time limit,
the arbitration shall be deemed to have commenced under Article 4.2 on the date the initial version
was received by HKIAC". Furthermore, the Notice for the commencement of arbitration confirms
that arbitration request was received in May 31, 2016 [NCAP, P.22, para. 1].
36. According to Simon, "HKIAC will only serve the Notice to the RESPONDENT only when the
CLAIMANT’s submitted Notice is adequate and its Council considers that there is a case to
arbitrate." CLAIMANT initiated the arbitration proceedings on time and CAM-CCBC requested
for amendments of two documents in order to make it adequate before sending the notice to
RESPONDENT [PO, P.19; NCAP, P.22]. According to Wald et al., a legitimate and on time
arbitration request can result in legal consequences one of which is setting aside the issue of time
limitation [Wald et al. P.66].
37. The arbitration initiation request met all the requirements under article 4.1 of CAM-CCBC.
Therefore, the president of CAM-CCBC exercising its power confirmed the receipt of the request
on May 31, 2016 and asked CLAIMANT to bring amendments on two of the documents. The
amendments which was asked have no impact on the administration of the arbitration proceedings.
Therefore, May 31, 2016 is the day of commencement of arbitration proceedings and was approved
by CAM-CCBC.
Memorandum for CLAIMANT
9
C. THE INTERNATIONAL ARBITRATION PRACTICES DEEMS THE
ARBITRATION PROCEEDINGS ON TIME AND ADMISSIBLE
38. CLAIMANT's initiated the arbitration proceeding within 60 days on May 31, 2016 after the failure
of negotiation on April 1, 2016. International Arbitration Proceedings deems CLAIMANT'
arbitration request to commence on May 31, 2016 (1). The arbitration request is in line with the
Chartered Institute of Arbitrators Guideline on Admissibility of Claims, which is one of the best
established commercial arbitration practice [CIArB, P.1, Para. 1] (2).
1. International arbitration practices are adopted in section 21 of the DSA which
further accepts the day of commencement of arbitration on the day request is
received by the administrator
39. Initiating the arbitration request is an important phase of the arbitration process [Martinez, P.10].
According to Section 21 of DSA, “The arbitration shall be conducted … in line with international
arbitration practice.” [Clm, Ex.C2, P.11]. Consequently, international practices deem the
arbitration to commence on the date on which the Statement of Claim is received by the
administrators. [VIAC Rules Art. 7; ICDR Art 2; SIAC Rules, Art. 3.3; AAA Rules R-4, (h); ACICA
Art. 4.2; LCIA Rules, Art.1.4, Swiss Law, Art. 3.2; Stockholm Arbitration Rules Art. 1-4, Milan
Chamber of Commerce, Art.1-4; Ljubljana Arbitration Rules; India International Arbitration
rules; DIAC Rules Art. 4].
40. Similar to CAM-CCBC the ICDR considers this situation to be dealt on two different ways. If any
of the requirements of Article 2.2 of ICDR is not met then it is determined by the ICDR, whether
to proceed with the administration or to make additional request from the CLAIMANT [Martinez,
P.11, para. 3]. ACICA international arbitration rules seated in Australia, has the objective to
facilitate and assist the international arbitration [Luttrell et al. P.1]. One of the vital points under
ACICA rules is that the arbitration starts when the Arbitration request is received by the registry
not when the notice of commencement is send to the RESPONDENT [Luttrell et al. P.8, para. 2].
"Time usually starts to run from the date which the cause of action arises" (Blackaby et al. P.243,
para 4. 05). Thus, the date when the notice of arbitration is received by the administrators is of
particular important since it guarantees the parties that the arbitration is set in motion [Warwas,
P.74, para. 2]
Memorandum for CLAIMANT
10
2. CLAIMANT's arbitration request meets the tests provided under Article 3 of
CIArB
41. Article 3 of CIArB articulates four key elements of the test for the admissibility of the claim.
CLAIMANT's arbitration request complies with all the elements of this test. First, The Arbitration
agreement under DSA includes condition precedent (multi-tier) arbitration clauses and
CLAIMANT's arbitration request meets the condition precedent to referring the dispute to
arbitration (i). Second, CLAIMANT initiated the arbitration proceeding within the time bar
limitation provided under the DSA, making it enforceable (ii).
i. CLAIMANT's arbitration request meets the conditions precedent to referring
the dispute to arbitration
42. Section 21 of the DSA states that parties shall solve the dispute amicably in good faith through
negotiation before commencing the arbitration proceedings [Clm, Ex.C1, P.11]. “In such a case,
arbitrators should decide whether (1) such a clause imposes an obligation and (2) if so, whether
such an obligation should be or has been satisfied". The amicable resolution clause in section 21
of the DSA, imposes a binding obligation on the parties; consequently, CLAIMANT tirelessly
tried to negotiate the dispute and resolve it in good faith [Clm, Ex.C5, P.14, para. 3; Ex.C6, P.15;
SOC, P.5, para. 9; PO2, P.58, para. 23; PO2, P.57, Para. 23; Res, Ex.R3, P.29, Para. 2].
CLAIMANT has fulfilled this obligation, and the arbitrators shall accept the request for arbitration
as procedurally admissible [Commentary on CIArb. Art.3, P.16].
ii. CLAIMANT initiated the arbitration proceeding within the time bar
limitation provided under the DSA, making it enforceable
43. Article 3 of CIArb obliges the arbitrators to examine the wordings of the arbitration clause and
determine whether the clause applies any limitations [Commentary on CIArb. Art. 3, P.16, Para.
(c)]. Section 21 of DSA, explicitly provides time limitation within which an arbitration request is
to be initiated [Clm, Ex.C1, P.11], which was respected by CLAIMANT and the initiation was on
time [Ord of Pr. P.19, para. 1; NCAP, P.22, para. 1]. The president's order and the notice of
commencement of arbitration are evidences that the arbitration proceedings were initiated on time,
for that it is admissible. [Ord of Pr. P.19, para. 1; NCAP, P.22, para. 1].
44. To conclude, based on the aforementioned laws and facts CLAIMANT tried to resolve the dispute
amicably in good faith through negotiation. When RESPONDENT did not show willingness to
Memorandum for CLAIMANT
11
amicable resolution, CLAIMANT was left with no other choice other than initiating the arbitration
proceedings. Furthermore, CLAIMANT sent the arbitration request on May 31, 2016 after the
failure of negotiation on April 1, 2016. May 31, 2016 shall be deemed to be the date of the
commencement of arbitration based on DSA, CAM-CCBC, and International Practices.
ISSUE TWO: THE ARBITRAL TRIBUNAL’S POWER IS LIMITED TO GRANT SECURITY
FOR RESPONDENT’S COST UNDER DSA, TERMS OF REFERNCE AND THE
GOVERNING RULES IN LINE WITH INTERNATIONAL ARBITRATION PRACTICES
45. RESPONDENT requested payment for security of its costs that it is likely to incur in this
arbitration proceedings. The amount requested covers both RESPONDENT’s legal costs for
services of its lawyer and expenses of arbitration including oral hearing, witnesses and experts. As
a first estimation, RESPONDENT requests for a minimum of US $ 200,000 [SFC, P.46, Para. 1].
46. No provision in the Development and Sales Agreement allows the parties for security for cost.
RESPONDENT is not entitled to the security for its costs because it does not meet the general
requirements and the standard conditions provided in the governing rules of the DSA. Therefore,
the Arbitral Tribunal’s power is limited to award RESPONDENT security for its cost.
RESPONDENT’s request is not in line with DSA, Terms of Reference (ToR), and governing rules
such as CAM-CCBC and UNCITRAL Model law (A). Furthermore, RESPONDENT failed to
meet elements of the tests and exceptional circumstances, which are prerequisite for such an award
under Chartered Institute of Arbitrators (CIArB) Guideline on Application of Security for Costs
and other relevant rules (B).
A. UNDER THE DSA, TOR AND GOVERNING RULES SUCH AS CAM-CCBC AND
UNCITRAL MODEL LAW, RESPONDENT IS NOT ELIGIBLE TO RECEIVE
SECURITY FOR ITS COSTS
47. The nature of this case and the laws adopted in the contract limit the authority of the Tribunal to
order security for RESPONDENT's cost. As per Ludmilla Herbst, a well-known litigator,
“Arbitrators have long been recognized as lacking inherent power to order security for costs”
[Ludmilla Herbst, the Lawyers Weekly]. Similarly, Stephen Colbran, puts more emphasize that the
arbitrators possess very limited power to grant security for cost [Stephen, P.275].
48. The Development and sales Agreement signed between parties, does not empower the Tribunal to
grant and award such a request (1). Terms of Reference as a core document of arbitration
Memorandum for CLAIMANT
12
proceeding further limits Arbitral Tribunal’s power to award the request (2). CAM-CCBC the
governing law in this particular case also limit the Tribunal’s authority (3). UNCITRAL Model
Law further puts limitation on the Tribunal for granting security for RESPONDENT’s cost (4).
1. Silence of Development and Sales Agreement constitutes parties agreement on
exclusion of security for cost
49. Development and Sales Agreement, which is the base for the relationship between the parties is
silent about security of cost and therefore it does not authorize the Arbitral Tribunal to grant
security for RESPONDENT’s cost [Clm, Ex.C2, P.11]. As per Art. 25 (4) of London Court of
International Arbitration (LCIA) Rules which states, “by agreeing to arbitration under the
Arbitration Agreement, the parties shall be taken to have agreed not to apply to any state court or
other legal authority for any order for security for Legal Costs or Arbitration Costs” Several
courts in United States have rejected security for cost request in the recent years because they were
in contrary with the arbitration agreement of parties [Charles et al. P.24].
50. Moreover, Art. V (1) (c) of the New York Convention and UNCITRAL commentaries also
underscores that the Arbitral Tribunal’s power is derived from consent of parties and therefore
Tribunal cannot exercise its power if the parties agreement does not exist on granting interim
measures [Kluwer Law International, Nicola Christine et al.; The UNCITRAL Arbitration Rules:
David D. Caron et al. , P.517]. These provisions clearly indicate that parties should follow their
Arbitration agreement as mentioned in the contract and RESPONDENT’s request is not included
in the Arbitration agreement section 21 of DSA.
2. RESPONDENT’s request for security for cost was not included in the ToR
51. Parties signed ToR for this Arbitration proceeding on August 22, 2016 [SoC, SFC, P.49, Para.2];
however, 15 days later on September 6, 2016 RESPONDENT submitted request for security of its
costs. Parties did not include security for cost request even in the ToR, which is the core document
of arbitration proceedings, which highlights that the parties agreed to exclude security for cost.
52. Furthermore, the request for security for cost after signing the ToR falls outside the limits of the
DSA. ICC Art. 19 provides that no new claim can be made after the ToR is signed, because it falls
outside the limits of the Terms of Contract. As per Julian D M Lew the author of Comparative
International Commercial Arbitration, ToR is a significant element of arbitration proceedings and
it is a pre-requisite for the initiation of arbitration. The key purpose of ToR is to specify claims
Memorandum for CLAIMANT
13
and subject matter [Julian, Chap. 21, P.528]. In addition, she further emphasizes, “…this is to stop
the parties from continually changing the content and nature of the claims” [Julian, Chap. 21,
p.528].
53. Similarly, in case Maffezini v. Spain in 1999 under ICSID rules, the Arbitral Tribunal rejected
RESPONDENT’s request for security of its costs, on the grounds of not being related to the subject
matter [Maffezini v. Spain (1999)]. In this current case, RESPONDENT’s request is not included
in subject matter fixed in the ToR. RESPONDENT’s request for security of its costs contradicts
with the key purpose of the ToR. The parties specified the claims and the subject matter of the
dispute in the ToR but security for cost was not included. The importance of ToR is further
highlighted in CAM-CCBC’s rules which is the main governing rule of this arbitration proceeding.
3. RESPONDENT’s request for security for cost is out of time based on the CAM-
CCBC Rules
54. Art. 4.21 of CAM-CCBC underlines that, “parties can change, modify or amend the claims and
causes of action until the date the Terms of Reference are signed.” This article does not allow the
Tribunal to decide on any issue brought before them after the ToR is signed. The importance of
ToR is more elaborated in the commentary of Art. 4.21, which deems ToR as core document of
arbitration proceedings. Further, it put emphasis that if there is any action taken against the ToR,
it will be subject to be challenged in the national courts [Wald et al., P.65]. Likewise, Julian
articulates, “the terms of reference are binding not only on the parties, but also on the arbitrators,
who must comply with parties’ intensions” [Julian, Chp. 21, P.529]. Taking that into
consideration, RESPONDENT’s request is late and is not in line with the ToR provisions.
55. RESPONDENT may raise that Art. 8.1 of CAM-CCBC Rules empowers Arbitral Tribunal for
granting provincial measures including injunctive and anticipatory. Nonetheless, security for cost
is used in a very restrictive manner and with greatest reluctance, further it is granted in exceptional
circumstances [Thomas et al.], however, those exceptional circumstances and tests were not met
by RESPONDENT as it will be more elaborated in following submissions. 56. In case, Burimi S.R.L. and Eagle Games SH.A. Vs. Republic of Albania in 2012 under ICSID
Rules, Arbitral Tribunal rejected respondent’s request for security of its cost because it failed to
prove that circumstances of the case require security for cost or any exceptional circumstances
exist. Respondent failed to prove that claimant has lack of funds [Burimi S.R.L. and Eagle Games
Memorandum for CLAIMANT
14
SH.A. v. Republic of Albania (2012)], similar to that in the current case RESPONDENT did not
provide evidences to show CLAIMANT’s financial insolvency; however, CLAIMANT does not
face any financial insolvency [PO 2, P 60, Para. 31] hence, the request needs to be refrained by
Arbitral Tribunal. Importantly, considering the circumstances of this particular case, UNCITRAL
Model Law also does not provide support to RESPONDENT’s request for security of its costs.
4. UNCITRAL Model Law limits the Tribunal’s power to award security for
RESPONDENT’s costs
57. In section 21 of DSA, the seat of this arbitration is agreed to be Vindobona, Danubia. This country
has enacted the UNCITRAL Model Law on International Commercial Arbitration, which makes
UNCITRAL ML applicable in this case [Clm, Ex.C2, P.11].
58. Art. 17 of UNCITRAL Model Law highlights the lack of international consensus particularly on
security for costs [Wendy/Duncan, P. 33]. This clearly indicates that the Article(s) on security for
costs in UNCITRAL are not a mandatory provisions and it does not allow the parties to expand
the Tribunal’s authority [Holtzmann, Neuhaus, et al., Chp IV, p.530-547]. Furthermore, in some
courts security for costs is not granted under Art. 17 UNCITRAL jurisdictions [Born, Vol. II,
P.2495]. The exercise of security for cost is commonly practiced in England or Commonwealth
jurisdictions. Tribunals without English or Commonwealth orientations are skeptical of their
authority to order security for costs on the bases that security for cost may deprive a party with
limited financial means of the opportunity to pursue its claim [Born, Vol. II, P.2495].
59. Courts in some UNCITRAL ML jurisdictions have held that Art. 17 does not grant authority to
the Arbitral Tribunal to order for security of costs [Born, Vol II, P.2495]. Party that is requesting
security for costs is, at least partly, “responsible for its counter parties financial condition” [Born,
Vol II, P. 2496]. It is important to note that it is currently RESPONDENT who did not perform its
contractual obligations and made CLAIMANT suffer this situation. That is why, the Arbitral
Tribunals are generally hesitant to grant orders for security for costs [ICC case no. 8670 (2000);
CIArB, P. 1, Para. 1]. It is also noticed that UNCITRAL ML from the session reports of the
working group decided not to tackle the matter of security for costs [Miles& Speller, P. 34].
60. Additionally, as per Art. 17 (e), the Arbitral Tribunal deems RESPONDENT’s request unnecessary
and inappropriate, because the financial situation of CLAIMANT has not changed since
conclusion of DSA in 2010 and this arbitration proceeding and CLAIMANT’s financial situation
Memorandum for CLAIMANT
15
is stable [Clm, Ex.C9, P.50, Para. 2]. The request is inappropriate because CLAIMANT has not
been charged of bankruptcy or financial insolvency [PO2, P.60, Para. 31].
61. RESPONDENT raises that based on UNCITRAL Rules on Transparency in Treaty-based Investor-
State Arbitration the Xanadu government awards should have been made public [SFC, P.46, Para.
4]. However, the claims against government of Xanadu was available in CLAIMANT’s balance
sheet [Clm, Ex.C9, P.50, Para. 3]. Importantly, Rogers, a scholar of international arbitration
makes a differentiation between investment arbitration which is raised by RESPONDENT and
commercial arbitration. Investment arbitration is concerned with the public; although, commercial
arbitration is more focused on private [Rogers, Catherine A]. Based on the aforementioned facts
of DSA, Terms of Reference, CAM-CCBC and UNCITRAL Model Law, Tribunal’s power is
limited to grant RESPONDENT’s request for security for cost.
B. THE INTERNATIONAL ARBITRATION PRACTICES LIMIT ARBITRAL
TRIBUNAL’S POWER TO ORDER SECURITY FOR RESPONDENT’S COSTS
62. Under section 21 of Development and Sales Agreement, parties agreed on application of
international arbitration practices [Clm, Ex.C2, P.11]. RESPONDENT’s request for security for
costs is not in line with the international arbitration practices, particularly the Chartered Institute
of Arbitrators Guideline on Application of Security Costs (CIArB), which is the current best
established practice in commercial arbitrations in relation to application for security for cost
[CIArB, P.1, Para. 1].
63. Art. 1 (2) of the CIArB articulates three key elements of the tests to be highly considered by
Arbitral Tribunal before deciding to order security for costs. Unlike, RESPONDENT’s claim for
security for cost does not comply with the three elements of this test. RESPONDENT failed to
present likelihood of success of its claim in a prima facie under Art. 2 of the CIArB (1).
RESPONDENT failed to show CLAIMANT’s inability to satisfy an adverse costs award, under
Art. 3 of the CIArB (2). RESPONDENT’s request for security of its costs would unjustly stifle a
legitimate claim, considering Art. 4 of CIArB (3).
1. RESPONDENT failed to provide the likelihood of success for its claim in a prima
facie test under Art. 2 of the CIArB
64. RESPONDENT failed to provide justifying reasons to be entitled for security for cost award [SFC,
P.49, Para. 2]. RESPONDENT has the burden of proof to provide facts for the support of its
Memorandum for CLAIMANT
16
claims, but it failed to do so. Art. 2 of CIArB states that the arbitral tribunal shall, “Take great care
not to prejudge or predetermine the merits of the case itself.” The commentary further elaborates
this article that, merits of the case shall not be pre-judged and pre-determined by the arbitrators
before the substantive hearings. Otherwise, this would compromise their impartiality and result in
their disqualifications from proceeding further [CIArB, P.5].
65. As per Julian D M Lew, Art. 5 (2) of London Court of International Arbitration (LCIA) Rules, the
arbitrators shall not pre-judge the merits and outcome of the case to any particular party since it
will undermine their independence and impartiality [Julian, p.256, Chap. 11]. Gary B. Born
further states in his book that, “an arbitral tribunal must refrain from prejudging the merits of the
case” [Born, Vol. II, P.2477]. He further mentions that there are doubts that the likelihood of
party’s success on merits has a key role to determine appropriateness of security for cost award
[IBIT].
66. The Vienna Rules Commentary on International Arbitration in Austria requires RESPONDENT
to show a high standard of proof that the CLAIMANT will almost certainly be unable to meet an
award of cost against it. In some existing decisions, the request for security for costs was rejected
as the RESPONDENT was unable to meet the burden of proof and substantiate its allegations that
the CLAIMANT will be unable to pay the costs [Franz/Christian, P.557].
67. If the Tribunal grants security for RESPONDENT’s cost at this preliminary stage of arbitration
proceeding it undermine their impartiality and independence since the decision of this proceeding
is not certain yet. According to Peter Ashford author of International Commercial Arbitration
Handbook, CLAIMANT is accused of financial insolvency by RESPONDENT, which is yet not
proven by the Arbitral Tribunal. Therefore, CLAIMANT is “innocent until proven guilty” [Peter
Ashford, P.383] and shall not be ordered for security of RESPONDENT’s costs. In case Maffezini
v. Spain in 1999, mentioned above, another reason the Arbitral Tribunal rejected RESPONDENT’s
request for security of its costs was because its claims were hypothetical same like
RESPONDENT’s claim in current case [IBIT].
68. In another ICSID Tribunal in Libananco, the case Libananco v. Turkey in 2008, the request for
security for cost was also rejected based on similar grounds of hypothetical claims by the party
[Libananco v. Turkey, 2008]. The mentioned cases share a common ground with the current case.
In all cases the party requesting for security of its costs was claiming on the basis of hypothetical
Memorandum for CLAIMANT
17
understandings. Similarly, RESPONDENT puts hypothetical reasons for its request of security for
costs. Therefore, RESPONDENT’s request is not eligible to be granted by Tribunal.
2. RESPONDENT failed to show that CLAIMANT does not have funds to pay an
adverse costs award
69. RESPONDENT raises that CLAIMANT has not complied with the payment award in the other
CAM-CCBC proceedings on January 2016 [Clm, P.46, Para. 2]. Although, CLAIMANT did not
comply because the award creditor owes an even larger amount to CLAIMANT’s parent company
as damages for the delivery of non-conforming goods. Furthermore, the claim is presently being
litigated in the courts of Ruritania and any sum awarded will be set off against the award [Clm,
P.49, Para. 3]. Likewise, RESPONDENT claims that the non-compliance with the payment order
raises serious doubts as to CLAIMANT’s financial situation, as per the wrongful allegations by
the article in the Carioca Business News. It further puts wrong allegations that CLAIMANT has
apparently done unsuccessful efforts to obtain outside funding for this arbitration [Res, P.46, Para.
3].
70. In an ICSID tribunal in 2010, case RSM production Corporation vs. Government of Grenada, the
Arbitral Tribunal rejected RESPONDENT’s request for security for cost. Like the current case,
RESPONDENT had claim that non-compliance of CLAIMANT with the payment of previous
orders shows that CLAIMANT has no incentive to comply with any award. Tribunal refrained
from granting the request basing that RESPONDENT did not provide sufficient support and proof
for such a conclusion [RSM production Corporation vs. Government of Grenada (2010)]. Hence,
the allegations in Carioca Business News are not reliable and does not meet the balance of
probability and are not based on merits [Clm, Ex.C9, P.50, Para. 2].
71. Under same tribunal, ICSID, in case Atlantic Triton, Tribunal refused granting security for
RESPONDENT’s cost because RESPONDENT did not provide reasons that the government of
Guinea would not perform its obligation if the final award hold it responsible [Republic of Guinea
v. Atlantic Triton Company (1986); Katia Yannaca]. Hence, taking these practices into
consideration, REEPONDENT’s request shall not be granted on the grounds that it could not
provide evidence and wrongfully put allegations on non-compliance of CLAIMANT.
72. Stephen Colbran, author of Security for Costs against Corporations mentions that RESPONDENT
must provide a credible evidence to prove CLAIMANT is unable to pay the security for cost
Memorandum for CLAIMANT
18
granted against it [Stephen Colbran, P.275]. In case, Burimi S.R.L. v. Albania decided by ICSID
Tribunal in 2012 was rejected because RESPONDENT’s claim was alleged without proving the
bankruptcy of CLAIMANT. Nonetheless, in the current case, RESPONDENT puts wrongful
allegations that CLAIMANT is under financial insolvency and bankruptcy. Even though,
CLAIMANT is not under any bankruptcy explicitly highlighted in Procedural Order 2 [PO2, P.60,
Para. 31]. Therefore, similar to Burimi S.R.L. v. Albania case, RESPONDENT’s requested is to
be rejected by Tribunal.
73. Essentially, CLAIMANT’s financial situation has been stable since 2010 until current arbitration
proceeding as provided, “The financial situation of Wright Ltd has not changed substantially or
unexpectedly between the conclusion of the Development and Sales Agreement in 2010 and the
initiation of these arbitration proceedings” [Clm, Ex.C9, P.50, Para. 2]. As per Yearbook
International Arbitration, RESPONDENT is required to prove that there has been a fundamental
change in financial situation of CLAIMANT [YIA, Vol III, P.167 Para (c)].Yesilirmak, a legal
scholar, further emphasizes that RESPONDENT will be awarded security for its costs, if there is
a change in the circumstance of CLAIMANT’s financial situation from the time parties signed
agreement [Ali Yesilirmak]. However, RESPONDENT was not able to provide evidence on
financial insolvency of CLAIMANT.
74. In an ICC Case no. 10032, in Zurich, Yugozalvia vs. Serbia, regarding the international embargo
declared in 1999 by the European Union on the Federal Republic of Yugoslavia and the
Government of the Republic of Serbia, the arbitral tribunal, explicitly expressed that
RESPONDENT need to show “that the factual situation at the present time is substantially
different from that which existed at the time the parties entered into their arbitration convention”
[ICC Case no. 10032], Similar to this case, CLAIMANT’s financial situation has not been changed
from the time of contract conclusion and this arbitration proceeding.
75. Moreover, CLAIMANT has access to sufficient financial resources which makes its financial
situation rock solid and paves the way to satisfy any cost award [Clm, Ex.C9, P.49]. Furthermore,
CLAIMANT has not been charged of any financial insolvency and bankruptcy [PO2, P.60, Para.
31]. RESPONDENT request for security of its cost is around USD $ 200,000; however,
CLAIMANT is one of the largest aircraft industry and is involved in large transactions. For
example, CLAIMANT has the US$ 12 million received from Xanadu government [PO2, P.58,
Memorandum for CLAIMANT
19
Para. 28]. Additionally, as per Art. 3 of the CIArb, if CLAIMANT has assets that will enable it to
pay the costs awarded, arbitrators shall refrain from granting security for cost. Hence, CLAIMANT
not only has other financial resources highlighted above but also assets for instance, development
work which went for TRF 305 reflected an increase in the position of assets for the CLAIMANT
[PO2, P.59, Para. 28]. This shows the ability of CLAIMANT to pay any costs awarded.
76. According to Handbook of ICC Arbitration Commentary, Precedents, Materials, security for cost
can be ordered only in exceptional circumstances. For instance, when there is a sufficient, clear
and present danger that CLAIMANT will not be able to provide the expenses because of its
insolvency. This, however, must be proved by RESPONDENT [Webster et al. P.432].
77. Echoing these concerns, a Tribunal sitting in Paris in 2006 rejected RESPONDENT’s request for
security costs in an ICC case No. 13070. This rejection was based on the lack of any exceptional
circumstances in RESPONDENT’s request. The Tribunal expressed that RESPONDENT failed to
provide specific and sufficient proof [ICC case No. 13070 (2006) P.434]. This is similar to the
current case, as RESPONDENT is unable to prove its claim and as well it does not meet any
exceptional circumstances.
3. RESPONDENT’s request to provide security for its cost is unfair under Art. 4 of
CIArb
78. Although RESPONDENT claims that ordering security for cost is necessary to efficiently protect
its rights [Res, P.46, Para. 5], CLAIMANT’s right to fully present its claim must also be protected.
Art. 4 of the CIArb states, “arbitrators should consider whether awarding security would unjustly
stifle a legitimate and material claim”. This is further highlighted by A.O. Rhodes Vivour author
of Security for the RESPONDENT’s Costs of Arbitral Proceedings with Particular Reference ACA
that CLAIMANT’s right to access the court shall be protected, if CLAIMANT is deprived of
access to court, it is unfair [A.O. Rhodes – Vivour].
79. The members of the drafting committee of CIArB state that the conduct of RESPONDENT should
be taken into account both before and during the Arbitration proceedings to determine fairness.
For instance, if the lack of funding has been caused by conduct of RESPONDENT, it would be
unfair to award security for cost request [Commentary of CIArB. P.32]. Here, the Tribunal should
deem award of security for cost unfair because lack of funding is caused by RESPONDENT’s
nonperformance of its contractual obligation. “CLAIMANT does not face any financial insolvency,
Memorandum for CLAIMANT
20
even if CLAIMANT faces with any lack of funding, it has been caused by RESPONDENT who had
not paid the price due under the Development and Sales Agreement” [Clm, P.49, Para. 4]. Weixia
Gu as well indicates that it is unfair if CLAIMANT’s financial situation is caused by the improper
behavior of RESPONDENT and in that instance Arbitral Tribunal needs to reject the request for
security for cost [Weixia Gu].
80. Furthermore, Swiss law and jurisdictions have been among the most reluctant ones toward security
for costs as one of the international practices which is also agreed by parties [Jean-Baptiste
Pessey]. In A. S.p.A. v. B AG case, arbitration proceedings conducted under the Rules of
Arbitration of the Geneva Chamber of Commerce and Industry, the CLAIMANT had applied for
security for costs on the grounds that the CLAIMANT had filed for liquidation after the start of
the proceedings. The tribunal refused to order security for costs and considered that the
CLAIMANT’s insolvency was a normal commercial risk that the RESPONDENT should bear [A.
S.p.A. v. B AG]. Similarly, in above mentioned case, Tribunal refused security for cost request on
the grounds of financial insolvency claim considering it normal commercial risk. Therefore,
Tribunal’s power is limited to grant RESPONDENT security for cost [Clm, Ex.C9, P.50, Para. 2].
81. According to CIArb Art. 4, “applications for security for costs should be made promptly, that is,
as soon as the risk or facts giving rise to the application are known or ought to have been known.”
Arbitrators should consider whether an application has been made at an appropriate time. If the
application is made after significant expense has been incurred, they may consider that this unfairly
disadvantages the other party and refuse the application and RESPONDENT’s claim is not in
compliance with the requirements set in Art. 4 (1) of CIArB.
82. RESPONDENT’s claim for security of its cost is similar to American Cyanamid Co vs. Ethicon
LTD case, decided in the UK House of Lords. In that case, one party requested for interim measures
to prevent the other party of infringing their patent. The party requesting for interim measures was
relying on balance of convenience but there was no rule that the court must first look at the
prospects of success of each party. Lord Diplock developed a set of guidelines for granting interim
measures whether an applicant’s case merited the granting of interim measures.
83. Lord Diplock rules that RESPONDENT must show that it is likely to win the case. RESPONDENT
is requesting interim measure without demonstrating enough evidence to win the arbitration. Even
if the RESPONDENT could present enough evidence, based on the holding of American
Memorandum for CLAIMANT
21
Cyanamid case law; it’s not required to order security costs based on the following three reasons.
First, there is no ruling for interim measures at this stage of proceeding. Second, there is no ruling
for balance of convenience to compel the Arbitral Tribunal to consider who is likely to succeed in
the case. Third, RESPONDENT’ claims on CLAIMANT’s financial position are inaccurate
[American Cyanamid Co vs. Ethicon LTD].
84. In conclusion, the Development and Sales Agreement, Terms of Reference, CAM-CCBC rules,
UNICTRAL Model and the International Rulings, particularly the International Chartered of
Arbitration guideline on Security for Cost limits the authorities of the Arbitral Tribunal to grant
security for RESPONDENT’s cost, and the Tribunal is requested not to order CLAIMANT for
RESPONDENT’s cost.
ISSUE THREE: CLAIMANT IS ENTITLED TO THE FULL PAYMENT IN THE AMOUNT
OF US $22,723, 800 FOR THE FAN BLADES AND US$ 102,192.80 FOR THE FEE
DEDUCTED FOR BANK CHARGES BASED ON THE DSA
85. In 2010, CLAIMANT and RESPONDENT were in negotiations to jointly develop a new fan blade.
During finalization of their DSA, the final production cost of new blades were uncertain. However,
RESPONDNET insisted to fix a maximum price to be paid so that it could offer itself a price for
engine to Earhart [Clm, Ex.C1, P.8]. Taking that into consideration, parties agreed on a formula
fixing a maximum and minimum price for the blades [Clm, Ex.C2, P.10], which also served as the
basis for risk sharing.
86. The DSA section 4 (1) requires RESPONDENT to pay the purchase price in full amount. The full
purchase price for the blades is USD 2,285,240.00; nevertheless, RESPONDENT made the
payment in the amount of USD 20,336,367.20 [Clm, Ex.C3, P.12]. Moreover, DSA explicitly
provides the agreement of parties that the bank charges must be borne by the buyer, which
RESPONDENT failed to meet its obligation.
87. In the following, CLAIMANT will submit that according to DSA, CISG, and UNIDRIOIT
principles, it is entitled to the full payment of purchase price for the fan blades in the amount of
USD 22,723, 800 (A). DSA and CISG further obliges RESPONDENT to pay bank transfer charges
in the amount of USD 102,192.80 (B).
Memorandum for CLAIMANT
22
A. DSA, CISG AND UNIDROIT PRINCIPLES ENTITLE CLAIMANT TO THE FULL
PAYMENT OF PURCHASE PRICE FOR THE FAN BLADES IN THE AMOUNT
OF US$ 22,723, 800
88. CLAIMANT incurred costs in the amount of EQD 19,586 per fan blade [Clm, Ex.C5, P.14, para.
2]. On the basis of the correct exchange rate charged at the time of the production of the fan blades,
the price per fan blade in US$ was US$10,941.90 which results in an overall purchase price of
US$ 22,723,800 for the 2,000 fan blades [Clm, Ex.C5, P.14, para. 2].
89. On January 14, 2015, after the production of the fan blades, CLAIMANT sent two invoices for the
fan blades and clamps [Clm, Ex.C3, P.5, para. 9]. On January 15, 2015, CLAIMANT informed
RESPONDENT about the mix up in CLAIMANT’s accounting department. CLAIMANT
mentioned that the invoice for the fan blades was prepared on the basis of fixed exchange rate
provision of the addendum, which should be applied only for clamps [Clm, Ex.C5, P.14, para. 5].
However, RESPONDENT still effected the payment based on the wrong invoices [Clm, Ex.C3,
P.12].
90. The principle of good faith requires RESPODNET that it should have informed CLAIMANT about
the mistake in the invoices. Based on Article 7(1) of CISG Convention, “In the interpretation of
this Convention, regard is to….. the observance of good faith in international trade”. Good faith
is one of the main principles of the convention. “The principle of good faith provides a basis for
the expectation that contractual duties will be performed. The principle of good faith imposes a
code of behavior on both parties, calling each to consider the interests of the other contracting
party” [Perales Viscasillas, P.121].
91. The DSA does not contain any provision regarding the applicability of fixed exchange rate for the
fan blades. Parties’ intention behind adding fixed exchange rate provision in the addendum was
only to govern the sale of the clamps not the fan blades (1). CISG entitles CLAIMANT to the
outstanding payment of purchase price in the amount of US$ 2,285,240.00 (2).
1. Parties’ intention behind adding fixed exchange rate provision in the addendum
was only to govern the sale of the clamps, not the fan blades
92. After the conclusion of the DSA, RESPONDENT realized that the suitable clamps cannot be found
from other suppliers, it approached CLAIMANT for the purchase of the clamps. Thus, an
addendum was added to the contract and signed by the parties [Clm, P.5, para. 8; Clm, Ex.C2,
Memorandum for CLAIMANT
23
P.11; Res, Ex.R5, P.3, para. 2]. Intention of the parties behind adding the addendum was to govern
the sale of the clamps. DSA and Addendum are different agreements; therefore, provisions of the
addendum shall not have any applicability on the DSA (i). Fixed exchange rate does not apply to
the DSA based on Art.8 of CISG and UNIDROIT principles (ii). Based on the objective intention,
fixed exchange rate is only applicable to the addendum (iii). Based on Art. 4.6 of UNIDROIT
principles (Contra proferentem rule), the text of addendum shall be interpreted against the drafter
(RESPONDENT) (iv). Parties have no established practice between them regarding the usage of
fixed exchange rate (v).
i. DSA and Addendum are different agreements; therefore, provisions of the
Addendum shall not have any applicability on the DSA
93. DSA and addendum are different agreements. In order to distinguish between the DSA and
addendum, Art.4 (4) of UNIDROIT principle requires considering the terms and references in light
of the whole contract or statements in which they appear. It is explicitly stated in the addendum
that, “the buyer may request the seller to produce and deliver 2,000 clamps. The price for the
clamps shall be on a cost coverage base and be paid in US$” [Clm, Ex.C2, P.11]. In the addendum,
the parties agreed to deliver the clamps on a cost coverage basis, where CLAIMANT did not
charge any profit to the cost of the clamps. However, based on the Section 4(1) of the DSA, the
purchase price of the fan blades is calculated based on a cost plus profit basis [Clm, Ex.C2, P.10].
94. The parties agreed on fixed exchange rate only for clamps, because fixed exchange rate would not
lead to a great risk in the addendum as the amount of the purchase price of the addendum was low
and no profit was expected out of this transaction. However, in the DSA parties agreed that
CLAIMANT will get profit out of the transaction. As a result, it is derived that parties’ intention
behind addendum was only regulating the clamps and fixed exchange rate does not have any
applicability on the fan blades. Schlechtriem and Butler, leading scholars, further elaborate that
the actual intent of the parties will determine the meaning of the statements or other legally relevant
conduct of the parties [Schlechtriem/Butler, P.56].
95. Furthermore, Paul Romario, CEO of RESPONDENT, in his witness statement said “After the
conclusion of the main agreement, it became clear that we would also need clamps from
CLAIMAINT” [Res, Ex.R5, P.31, para. 2]. Text of the addendum explicitly mentions that, “other
terms are as per main Agreement” and “the exchange rate for the agreement is fixed to US $
Memorandum for CLAIMANT
24
1=EQD 2.01” [Clm, Ex.C2, P.11]. The CEO of RESPONDENT clearly distinguishes the main
Agreement which is DSA and the agreement which is the addendum. This further clarifies the
intention of the parties that the fixed exchange rate provision is only applicable to the addendum.
ii. Fixed exchange rate does not apply to the DSA based on Art. 8 of CISG and
UNIDROIT principles
96. Based on Art.8 of CISG 4.1, and 4(3) of UNIDROIT principles, contract shall be interpreted based
on the common intention of the parties considering the circumstances. The circumstances include
negotiations, conduct of the parties after the conclusion of the contract, the nature and purpose of
the contract, and the meaning commonly given to the terms and expressions in the trade concerned
between the parties. Based on the circumstances, parties had the following intentions behind the
addendum.
97. First intention behind the Addendum was to govern sale of the Clamps. In an email sent by
RESPONDENT to CLAIMANT on August 22, 2010 under the subject line of “Clamps” [Res,
Ex.R2, P.28], RESPONDENT stated, “As already discussed we think the easiest way to regulate
the purchase of the clamps is to sign an addendum” [Res, Ex.R2, P.28, para. 3]. This indicates
that parties’ intention behind adding addendum was to govern the purchase of the clamps, and the
purchase price for the fan blades will remain as per the calculation formula in the section 4 of the
DSA. Besides that, the subject line of the email sent by RESPONDENT regarding the addendum
exactly mentions the “clamps”, which itself suggests that the purpose of addendum was to govern
the sale of the clamps [Res, Ex.R2, P.28].
98. Second intention behind the addendum was to deliver the clamps at the same time with the fan
blades, which is further elaborated in PO2 by RESPONDENT’s call of October 21, 2010, where
it informed COO of CLAIMANT that the purpose of adding the addendum was the same time
delivery of clamps with the fan blades [PO2, P.57, para. 16].This clearly indicates that the purpose
of addendum was to deliver both the clamps and the fan blades together.
99. Third intention behind the addendum was to set the cost for the clamps. The price for the clamps
in the addendum is on a cost coverage base, it is not made for governing the profit but only for the
cost of the clamps [Clm, Ex.C2, P.11, para. 4]. RESPONDENT’s interpretation of the addendum
to use fixed exchange rate to the whole contract is not correct, as it contradicts with the common
intention of the parties and with the main agreement which is DSA.
Memorandum for CLAIMANT
25
iii. Based on objective intention, fixed exchange rate is only applicable to the
clamps
100. Even if RESPONDENT claims that its intention behind fixed exchange rate was to govern the sale
of the fan blades, fixed exchange rate is only applicable to the clamps based on the reasonable
person test. Art.8 (2) of CIG and Art.4 (2) of UNIDROIT principles state that the statement and
other conduct of parties may also be interpreted according to the understanding and meaning that
a reasonable person of the same kind as the other party would have had in similar circumstances.
Based on the objective intention of the parties, reasonable person of the same kind would have had
the same interpretation that fixed exchange rate is only applicable to addendum. Therefore, based
on the objective interpretation, fixed exchange rate is only applicable to the clamps and it does not
have any applicability on the DSA.
iv. Based on Art. 4(6) of UNIDROIT principles (Contra proferentem rule) the
text of the addendum shall be interpreted against the drafter (RESPONDENT)
101. Based on the Contra Proferentem rule embodied in Art.4(6) of UNIDROIT principles when
contract terms are unclear, the provisions of the contract shall be interpreted against the party who
drafted the provision to ensure the principle of equality, good conscience, and justice [Stone,
P.228; Honnold & Flechter, P.98]. By drafting the addendum, RESPONDENT tries to get an
implicit understanding from the provision of the addendum. In the case under consideration, the
drafter of the addendum was RESPONDENT. Hence, the interpretation of the addendum shall be
against RESPONDENT, which means that fixed exchange rate shall only be applicable to the
clamps not to the fan blades.
v. Parties have no established practice between them regarding the usage of fixed
exchange rate
102. RESPONDENT might claim that fixed exchange rate was used in two previous contracts when
parties were subsidiaries of Engineering International SA [Res, Ex.R5, P.31].Although in both
previous contracts, CLAIMANT and RESPONDENT used fixed exchange rate [Res, Ex.R5, P.31].
Practices of those two contracts are not analogous in the current case, because factual aspects are
not the same based on the following reasons.
103. In previous two contracts both parties were subsidiaries of Engineering International SA, and
exchange rate during previous contracts would not make a significant difference [Res, P.24, Para.
Memorandum for CLAIMANT
26
8; Res, Ex.R5, P.31, Para. 2]. Since, Engineering International SA asked both parties to adopt the
exchange rate which was profitable for RESPONDENT for tax purposes [PO2, P.54, Para. 5].
However, after both parties were sold to different parent companies, the exchange rate could
become a major issue in the current contract. Since the production cost of the new fan blades was
not certain for the parties; therefore, it was impossible for the parties to adopt a fixed price in the
current contract. Therefore, the current contract is totally different from the previous contracts and
the fixed exchange rate shall not be applicable to the current contract.
104. Besides that, RESPONDENT may claim that in a meeting in November 2009, which was also
attended by CLAIMANT’s CEO, it had been discussed that “SantosD should be de-risked to make
it more attractive to potential buyers” [Res, Ex.R1, P.27]. However, parties shall not rely on the
discussions of this meeting regarding de-risking RESPONDENT. Since, there were no ongoing
contractual relations between the parties specifically regarding the DSA in 2009. The reason why
de-risking Santos was suggested, was to make it more attractive to potential buyers, as long as it
is subsidiary to Engineering International SA. Therefore, RESPODNENT shall not rely on the
discussions of the meeting of 2009.
105. Based on the governing laws of the DSA, namely CISG and UNIDROIT principles, and the Contra
proferentem role, the common intention of the parties behind the addendum was to govern the sale
of the clamps, simultaneous delivery of clamps with fan blades, and the cost of clamps based on
the cost coverage basis. Thus, fixed exchange rate does not apply to the fan blades and the
exchange rate charged at the time of the production of the fan blades is the applicable exchange
rate of the DSA.
2. CISG entitles CLAIMANT to the full purchase price in the amount of US$22,723,
800
106. CLAIMANT fulfilled all its contractual obligations by making the full delivery of goods that were
in conformity with the contract [Clm, Ex.C3, P.12]. RESPONDENT shall make the full payment
for fan blades to fulfill its contractual obligations. Art.53 of CISG requires RESPONDENT to pay
the full purchase price (i). Based on Art. 62 of CISG, RESPONDENT is obliged to pay the
outstanding payment in the amount of US$ 2,285,240 (ii). The Preamble of the CISG Convention
requires RESPONDENT to pay the full purchase price (iii).
Memorandum for CLAIMANT
27
i. Art.53 of CISG requires RESPONDENT to pay the full purchase price
107. RESPONDENT is obliged to pay the full payment of purchase price for the fan blades since Art.53
of CISG states, “The buyer must pay the price for the goods as required by the contract and this
Convention.”[CISG, Art.53]. RESPONDENT did not fulfill its contractual obligations by paying
only US$ 20,336,367.20 [Clm, Ex.C6, P.15, para. 1]. CLAIMANT incurred production cost in
the amount of EQD 19,586 per blade [Clm, Ex.C5, P.12, para. 2]. Considering the exchange rate
at the time of the production of the fan blades which is $1= 1.79 EQD [Clm, Ex.C4, P.13, para.
4], the cost per fan blade is US$ 10,941.90 and the total payment of purchase price for 2,000 fan
blades is US$ 22,723,800 [Clm, Ex.C5, P.14]. However, RESPONDENT did not fulfill its
contractual obligations by denying that any additional purchase price payment was due [Clm,
Ex.C7, P.16]. Therefore, RESPONDENT is obliged to pay the outstanding payment in the amount
of US$ 2285240 for the fan blades.
108. It is further supported by the commentaries of well-known legal scholars, Schlechtriem and
Maskow that the most important obligation of a buyer in a sales contract is to pay the full payment
[Schlechtriem, P.39; Maskow, P.384, para2.2]. Leif Sevon, a leading scholar, also says, “The main
obligation of the buyer is making the full payment of purchase price” [Leif Sevon, P.207]. Art.53
establishes the central obligation of the buyer called essentialianegotii [Butler/Harindranath,
P.797]. Based on Art.53 of CISG, RESPONDENT has the obligation to pay the full purchase price
for the fan blades.
109. According to the commentary of Henry Deeb Gabriel, “Article 53 recognizes the primacy of the
contract in defining the parties' obligations” [Gabriel, P.273]. Based on the DSA, Art.53 of CISG
and the aforementioned commentaries of leading scholars, RESPONDENT is obliged to pay the
full payment in the amount of US$ 22.723800 [Clm, Ex.C5, P.14, para. 2]. Similarly in [CLOUT
case No. 652; CLOUT case No. 608; Agriculture products case; Kantonsgericht Schaffhausen]
the tribunal obliged RESPONDENT to full payment of the purchase price under article 53 of
CISG; therefore, RESPONDENT is obliged to full payments under the contract.
ii. RESPONDENT is obliged to pay the outstanding payment in the amount of
US$ 2,285,240 as a remedy based on Art.62 of CISG
110. Art.62 of CISG states, “The seller may require the buyer to pay the price unless the seller has
resorted to a remedy which is inconsistent with this requirement”. It is emphasized in
Memorandum for CLAIMANT
28
commentaries by leading scholars that paying the partial amount of the purchase price is a breach
of contract which entitles the seller (CLAIMANT) to the remedy under Art.62 of CISG
[Butler/Harindraanath & F. Bell, P.798, 858; Allison E. Butler; Schlechtriem & Schwenzer,
P.802; Leif Sevón, P.205].
111. “The remedy provided under Art.62 of CISG does not create any new right to the seller or a new
obligation of the buyer. It is simply a pursuance of their initial rights and obligations under the
contract which the seller will initially require performance under Article 62 by initiating a legal
action against the buyer” [Knapp, P.453, para2.2]. Therefore, CLAIMANT approached the
arbitral tribunal to make RESPONDENT fulfill its contractual obligations by paying the
outstanding payment in the amount of US$2,285,240.00 [Clm, Ex.C2, P.15, para. 1].
iii. The preamble of CISG Convention requires RESPONDENT to pay the full
amount of purchase price
112. “Considering that the development of international trade on the basis of equality and mutual
benefit is an important element in promoting friendly relations among States”[Preamble, CISG].
Based on the preamble of CISG, RESPONDENT is obliged to pay the full purchase price agreed
in the DSA. Contract is based on mutual benefit of the parties, which requires them to perform
their respective contractual obligations [Enderlein & Maskow, P.19-20; Evan, P.24, para2.4;
Janssan & Meyer, P137; Mistelis, P.19]. However, RESPONDENT did not fulfill its contractual
obligations by denying to make the full payment, which undermines the principal of equality and
mutual benefit embodied in the preamble of CISG Convention.
113. The preamble of CISG Convention, Art.53 and Art.62 of CISG require the buyer (RESPONDENT)
to uphold its contractual obligation and make the full payment. Therefore, CLAIMANT is entitled
to the outstanding payment in the amount of US$ 2,285,240 for the fan blades.
B. RESPONDENT IS OBLIGED TO PAY THE BANK CHARGES IN THE AMOUNT
OF US$ 102,192.80 BASED ON THE DSA AND CISG
114. In section 4(3) of the DSA, both parties agreed that RESPONDENT will bear the bank charges for
depositing the full payment both for clamps and fan blades to CLAIMANT’s account. Hence, it
is RESPONDENT’s contractual obligation to pay the levy charges as part of the bank charges.
Section 4 (3) of DSA obliges RESPONDENT to pay the levy charges (1). Besides that, article 54
Memorandum for CLAIMANT
29
of CISG obliges RESPONDENT to pay the levy charges (2). RESPONDENT’s analogy of Art.35
(2) CISG is not applicable in the current contract (3).
1. Section 4(3) of the DSA obliges RESPONDENT to pay the levy charges in the
amount of US$ 102,192.80
115. The Equatoriana Central Bank had investigated the payment for money laundering as per
Regulation ML/2014C and deducted a levy of 0.5% based on Section 11 of the regulation [Clm,
Ex.C8, P.17]. Parties agreed and added in section 4 (3) of the DSA that “the buyer will deposit the
purchase price in full into the SELLER’s account at the Equatorianian National Bank. The bank
charges for the transfer of the amount are to be borne by the BUYER” [Clm, Ex.C2, P.11], but
RESPONDENT did not pay the levy charges. RESPONDENT knew or ought to have known about
the levy charges since it was foreseeable (i). RESPONDENT has the duty not to be unaware of the
levy charges (ii). Payment of levy charges by CLAIMANT in the past two contracts is not
analogous to the current contract (iii).
i. RESPONDENT knew or ought to have known about the levy charges, since it
was foreseeable
116. RESPONDENT might claim that levy charges were not foreseeable. However, UN-Model
Provisions on Money Laundering was considerably covered by Equatorianian press in December
2009 [PO2, P.55, para. 7]. Finally, ML/2010C regulation entered into force on January 1, 2010
and it was well publicized all over CLAIMANT’s and RESPONDENT’s place of business,
Mediterraneo, through the foreign press including newspapers [PO2, p.55, para. 7].
RESPONDENT had several sources to be aware of the levy charges in Mediterraneo and there was
no obstacle and impediment for RESPONDENT to be deprived of sufficient information regarding
levy charges in Equatoriana. Hence, levy charges were both foreseeable and reasonable to
RESPONDENT and it should pay the levy charges.
ii. RESPONDENT has the duty not to be unaware of the levy charges
117. In section 4(3) of the DSA, RESPONDENT agreed to pay bank charges. RESPONDENT was
obliged to pay any amount that is required for the transfer of the full purchase price in the
Equatoriana National Bank. RESPONDENT claims that it was unaware of the levy charges. John
O. Honnold, a leading legal scholar states in his commentary of Art.8 of CISG, “the Convention
differentiates among: (A) facts that a party 'knows' or of which he is 'aware'; (B) facts of which a
Memorandum for CLAIMANT
30
party 'could not have been unaware'; and (C) facts that a party knew or 'ought to have known.'
The facts one 'ought to have known' include those facts that would be disclosed by an investigation
or inquiry that the party should make” [Kluwer, 1999]. Since it was agreed in Section 4(3) of the
DSA, RESPONDENT could not have been unaware of the levy charges. RESPONDENT was
obliged to know the procedures to affect the payment [Clm, Ex.C2, P.10, para. 3].
118. Moreover, RESPONDENT could not have been unaware of the levy charges, especially by explicit
inclusion of the bank name in section 4(3) of the DSA [Clm, Ex.C2, P.10]. RESPONDENT should
have known the relevant procedures for transferring the payment for such a cross border transfer.
Therefore, RESPONDENT ought to have known about the levy charges and RESPONDENT must
pay it. ML/2010 C regulation says “Only after a clearance for the transfer is given will the amount
be credited to the relevant bank account with the respective commercial bank in Equatoriana, in
the present case the Equatoriana National Bank” [PO2, P.56, para. 10]. As stated above in PO2
that levy is a step which should be passed for transferring the money to the account of
CLAIMANT.
119. The payment to be deposited into the seller’s account should go through money clearance policy
under Equatoriana National Bank. This shows that the intention behind obliging RESPONDENT
to pay the bank charges is also to cover levy charges so that the full deposit of purchase price is
made into the seller’s (CLAIMANT’s) account.
120. The levy charges are part of money transfer procedure. If the party does not pass the levy
investigation/examination, the money will not be deposited to the account [PO2, P.56, para. 10].
Therefore, RESPONDENT was obliged to know the required steps in order to transfer the money
in to CLAIMANT’s bank account.
iii. CLAIMANT’s practice of paying levy charges in previous contracts is not
analogous to the current case, because the factual aspects of those contracts
are different from the current contract
121. CLAIMANT has paid levy charges in their two previous transactions, namely JetPropulse and
JumboFly [PO2, P.55, para. 8, 9]. RESPONDENT claims that CLAIMANT shall pay the levy
charges in the current transaction too based on article 9 of CISG which reads, “the parties are
considered to have impliedly made applicable to their contract or its formation a usage of which
the parties knew or ought to have known” [CISG, Art.9]. However, Patrick X. Bout, argues in a
Memorandum for CLAIMANT
31
commentary that practices are only applicable “if in an individual relationship between two parties
the parties act in a similar way in similar circumstances” and CLAIMANT’s previous contracts
had different circumstances than the current contract with RESPONDENT.
122. CLAIMANT’s contract with JetPropulse and JumboFly had totally different circumstance and they
are not similar with the current contract. In CLAIMANT’s both previous contracts, there was no
contractual obligation over the JetPropulse and Jumbofly to pay the cost for bank charges [PO2,
P.55/56, para. 8, 9]. They did not have any provision that would usher an obligation for payment
of bank charges by any of the parties. However, in current proceeding RESPONDENT has clearly
agreed under section 4 .3 of DSA to bear the bank charges [Clm, Ex.C2, P.10; PO2, P.54, para.
6].
123. Based on the commentary of a leading scholar, Patrick X. Bout, “if the circumstances are so
different from the previous case and the particular behavior is not justified, in this case the practice
shall not be valid”. As mentioned above, the previous contracts were under much different
circumstances and have no common grounds with the current contract. Therefore, RESPONDENT
cannot use CLAIMANT’s previous transactions as an established practice between them. Based
on the Section 4.3 of DSA, RESPONDENT shall pay the levy charges because RESPONDENT
has the duty not to be unaware of the levy charges since levy charges are foreseeable.
2. Art. 54 of CISG requires RESPONDENT to take all enabling steps, including
paying the levy charges to make the full deposit of purchase price to CLAIMANT
124. RESPONDENT shall pay levy charges based on article 54 of CISG which states, “the buyer’s
obligation to pay the price includes taking such steps and complying with such formalities as may
be required under the contract or any laws and regulations to enable payment to be made”.
Complying with all formalities, laws and regulations to affect the full payment is part of
RESPONDENT’s contractual obligations.
125. Article 54 is further elaborated in a commentary by a leading scholar, Deeb Gabreil, which says
that, “the buyer’s obligation is not only limited to owing the money but rather the obligation also
includes all steps which are necessary to ensure that the payment is actually made and the buyer
must bear the costs for measures necessary to enable him to pay the price” [Gabreil, P.274]. In
addition, the buyer's obligation to pay the price includes taking such steps and complying with
Memorandum for CLAIMANT
32
such governmental formalities as may be required under the contract or any laws and regulations
to enable payment to be made [Schlechtriem, P.320; Tallon, P.395, para.2 & Maskow, P.7].
126. Moreover, well-known scholars Schlechtriem & Schwenzer state, “All and any laws and
regulations that may have any effect on the payment by the buyer need to be observed by him. The
buyer is required to observe the laws and regulations of all the other countries that have an effect
on the payment. This includes even the laws and regulations in force in the country of the seller’s
place of business” [Schlechtriem & Schwenzer, P.812; Butler/Harindraanath, P.803]. The laws
that shall be observed by CLAIMANT includes laws and regulations related to foreign exchange,
transfer and clearance rules [Maskow, 397-400].
127. Article 54 of CISG obliges the buyer to comply with any law and regulations which might be
required to make the full payment. Thus, it includes ML/2010 C regulation for money laundering
which is a law adopted in CLAIMANT’s place of business. Unless the money does not go through
the clearance under this law, payment will not be affected into the seller’s account. This means
that ML/2010C regulation is a step to be taken in order to deposit the payment in CLAIMANT’s
account. Therefore, RESPONDENT is obliged to uphold the money laundering law at
CLAIAMANT’s place of business to make the full payment, and should bear the levy charges.
128. This is further supported by the Clout Case No. 142, where a German seller (CLAIMANT) brought
a claim against a Russian buyer (RESPONDENT) to the court. The only action taken by the buyer
was to send instructions to the bank for the amounts payable under the contract to be transferred,
but it had not taken any measures to ensure that the payment could actually be made. Therefore,
International Commercial Arbitration at the Russian Federation Chamber of Commerce and
Industry decided in favor of the [seller] under article 54 of CISG and ordered the buyer to make
the payment for the goods supplied.
129. In Clout case No. 142, the buyer was supposed to make the full payment and make sure the transfer
happens, which the buyer didn’t. Similarly, in the current case RESPONDENT failed to pay the
levy charges which is essential for depositing the full payment of purchase price. In both cases
RESPONDENT failed to fulfill its contractual obligations under article 54 of CISG. Since court
ordered RESPONDENT in Clout Case No. 142 to pay the bank charges which is similar to current
case, the tribunal should make the same decision and oblige RESPONDENT to pay levy charges.
Memorandum for CLAIMANT
33
130. Henry Deeb Gabriel, a leading scholar, says that “if a government charged a tariff on the export
of money, the buyer would be responsible for that extra cost (absent contrary agreement) as part
of the payment of the price” [Gabriel, P.274]. As the tariff charged by the government comes
under the scope of Art.54, ML/2010 C Money Laundering Regulation which charged levy as a
governmental formality comes under the scope of article 54 of CISG as well.
131. The buyer not taking enabling steps for making the full payment is in breach of contract. Therefore,
the seller is entitled to the remedies in case of breach of contract by the buyer [Schlechtriem &
Schwenzer, P.813]. Besides that, based on the principle of the cost of one’s own obligation, each
party has to bear the cost of its obligations [CISG Digest 2012]. RESPONDENT’s obligation
includes making the full payment of purchase price. The costs incurred for paying the full payment
of purchase price includes paying the levy charges; therefore, CLAIMANT has the duty to pay the
levy charge.
132. Moreover, based on Clout case No. 104, decided by the Court of Arbitration of the International
Chamber of Commerce, the buyer who only gave instructions to the bank for transferring money
but did not make sure that the payment is actually made was in breach of its contractual obligations.
133. RESPONDENT by merely affecting the payment, but not making sure if the payment is actually
transferred in full into the CLAIMANT’s account breached the contract. Hence, it entitles
CLAIMANT to remedies which is paying the levy charges. RESPONDENT’s act of denying the
levy payment is a breach of article 54 of CISG as well as the DSA, because article 54 of CISG in
a very explicit manner dictates the buyer to fulfill all its contractual obligations by paying the
contractual price and complying with all formalities that is required under the contract or any laws.
Taking the aforementioned laws, regulations and commentaries into account, it is clear that
RESPONDENT is obliged to pay the levy charges and denying the payment is breach of contract.
Therefore, the arbitral tribunal is kindly requested to oblige RESPONDENT to fulfill its
contractual obligation by paying the levy charges.
3. RESPONDENT’s analogy of Art.35 (2) CISG is not applicable in the current
contract
134. RESPONDENT claims that It is now largely accepted that unless the parties have agreed
differently the public law regulations at the seller’s place of business are relevant for the
conformity of delivery under Article 35 (2) CISG. The seller does not need to know the public law
Memorandum for CLAIMANT
34
regulations at the buyer’s place of business unless the buyer does not inform the seller about such
regulations [Res, P.26, para. 19]. RESPONDENT makes the analogy of the general role claiming
that CLAIMANT shall have informed RESPONDENT about the public law regulation. However,
RESPONDENT’s analysis of the rule is not correct which leads to a wrong conclusion based on
the following reasons.
135. The view that the public law regulations at the buyer’s place of business are relevant for the
conformity of the goods is challenged by many legal scholars. Scheleterim, a well-known leading
scholar, says “ordinary use will be defined by the standard terms of the country or region in which
the buyer intends to use the goods” [Schlechtriem, P6-20]. Schelechterim says that the regulations
of buyer’s place of business shall be applicable for the conformity of the goods because in this the
seller will know where the goods are intended to be used.
136. Therefore, “it will consider all the relevant factors influencing the possibility of their uses in that
country into consideration” [Schlechtriem, P.88]. This means that the public law regulation at the
buyer’s place of business are relevant for the conformity of the goods. In the current case,
RESPONDENT has the duty to comply with all the public law regulations at the CLAIMANT’s
place of business. This means that RESPONDENT has the obligation to comply with the
ML/2010C Regulation for money laundering.
137. Besides that, in Medical Marketing v. Internazionale Medico Scientifica case the court decided
that the public law regulations at the buyer’s place of business are relevant for the conformity of
the goods. The current case has a very similar nature to the above mentioned case where the public
law regulations at the CLAIMANT’s place of business are the relevant laws for the conformity of
the goods. Therefore, RESPNDENT is obliged to pay the levy charges.
138. Based on the DSA, CISG, and the UNIDROIT principles which are the governing laws of the
contract RESPODNET shall pay the outstanding payment in the amount of US$ 2,285,240 for the
fan blades and US$ 102192.80 for the levy charges.
CONCLUSION
139. RESPONDENT is trying to promote a bad culture by not obeying the provisions of the DSA and
other governing rules and practices. as per the abovementioned evidences with the support of DSA,
Terms of Reference, CISG, the international arbitration practices and other governing laws,
CLAIMANT’s Claims are admissible and on time (A). In addition, the tribunals power is limited
Memorandum for CLAIMANT
35
to grant RESPONDENT security for its cost, since the allegations made by RESPONDENT have
no grounds (B). Lastly, RESPONDENT is obliged to pay the full payment in the amount of US
$22,723, 800 and levy charges in the amount of US $ 102,192.80 (C). If CLAIMANT’s claims are
not fulfilled, it will lead to the breach of the DSA, and other mentioned governing laws. Therefore,
the tribunal is requested to serve the purpose of arbitration and grant CLAIMANT justice by
considering CLAIMANT’s claims fair and lawful.
PROCEDURAL REQUEST
Counsel, on behalf of CLAIMANT, respectfully requests the Arbitral Tribunal to:
1. Reject RESPONDENT’s objection over the admissibility of this arbitration proceeding
2. Reject RESPONDENT’s belated request for the Security for RESPONDENT’s cost.
REQUEST FOR RELIEF
Counsel, on behalf of CLAIMANT, respectfully requests the Arbitral Tribunal to:
1. Order RESPONDENT to pay the outstanding payment of purchase price in the amount of US$
2,285,240
2. Order RESPONDENT to pay the bank charges in the amount of US$ 102,192.80.
3. Order RESPONDENT to bear all the costs arising from this arbitration; and
4. Any other relief that the tribunal considers appropriate.
Respectfully submitted,
American University of Afghanistan, December 20, 2016