INSTRUCTIONS TO TENDERERS REGARDING TENDER FORMS DOWNLOADED FROM INTERNET 1. Tender document is to be down loaded from the Internet, printout is to be taken on A4 size paper, and details are to be entered by the tenderer at the various locations in the document. It is advisable that the downloaded tender document is printed through laser/ inkjet printer only. Submission of Xerox or photocopy of the tender document is prohibited. 2. This downloaded Tender document (in full – Volume-I, Volume-II and Volume III) along with the various documents are required to be submitted as per the tender conditions in a sealed cover duly subscribing the name of the work, tender notice no. and date etc and the same shall be dropped before the stipulated date and time in the tender box as specified in the tender notice. 3. The cost of the Tender document as indicated in the Tender Notice will have to be deposited by the Tenderer in the form of bank draft in favour of Financial Advisor and Chief Accounts Officer/Construction/Southern Railway, Egmore along with the Tender document. This should be enclosed as a separate Demand Draft. A single demand draft for the cost of tender document and Earnest Money Deposit will not be accepted. Tenders not accompanied with the demand draft towards the requisite cost of the tender document will be summarily rejected. 4. The Earnest Money Deposit required for this work as stipulated in the tender document is to be submitted separately. 5. Tenderers are advised to download the tender documents well in advance and submit the tender before the stipulated time. It is the responsibility of the tenderer to check any correction or any modifications published subsequently in Web site and the same shall be taken into account while submitting the tender. The Tenderers shall download corrigendum (if any), print it out, sign and attach it with the main tender document. Tender documents not accompanied by published corrigendum(s) are liable to be rejected. Railways will not be responsible for any postal delay/ delay in downloading of tender document from the internet.

Upload: suzanne-cannon

Post on 18-Nov-2014

192 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: MEMU Master

INSTRUCTIONS TO TENDERERS REGARDING TENDER FORMS DOWNLOADED FROM INTERNET

1. Tender document is to be down loaded from the Internet, printout is to be taken on A4 size paper, and details are to be entered by the tenderer at the various locations in the document. It is advisable that the downloaded tender document is printed through laser/ inkjet printer only. Submission of Xerox or photocopy of the tender document is prohibited.

2. This downloaded Tender document (in full – Volume-I, Volume-II and Volume III) along with the various documents are required to be submitted as per the tender conditions in a sealed cover duly subscribing the name of the work, tender notice no. and date etc and the same shall be dropped before the stipulated date and time in the tender box as specified in the tender notice.

3. The cost of the Tender document as indicated in the Tender Notice will have to be deposited by the Tenderer in the form of bank draft in favour of Financial Advisor and Chief Accounts Officer/Construction/Southern Railway, Egmore along with the Tender document. This should be enclosed as a separate Demand Draft. A single demand draft for the cost of tender document and Earnest Money Deposit will not be accepted. Tenders not accompanied with the demand draft towards the requisite cost of the tender document will be summarily rejected.

4. The Earnest Money Deposit required for this work as stipulated in the tender document is to be submitted separately.

5. Tenderers are advised to download the tender documents well in advance and submit the tender before the stipulated time. It is the responsibility of the tenderer to check any correction or any modifications published subsequently in Web site and the same shall be taken into account while submitting the tender. The Tenderers shall download corrigendum (if any), print it out, sign and attach it with the main tender document. Tender documents not accompanied by published corrigendum(s) are liable to be rejected. Railways will not be responsible for any postal delay/ delay in downloading of tender document from the internet.

6. The tenderers may please note that the rates/ single percentage for schedule items shall be written in figures and words. Each page of the tender document shall be signed by the tenderer.

7. Tenderers are free to download the tender document at their own risk and cost, for the purpose of perusal as well as for using the same as tender document for submitting the offer. Master copy of the tender document is available in the Railway office as specified in the tender notice. After the award of work an agreement will be prepared based on the master copy of tender document available in the above office. In case of any discrepancy between the tender document downloaded from the Internet and the master copy, the latter shall prevail and will be binding on the tenderers. No claim on this account will be entertained.

8. If any change/ addition/ deletion is made by the Tenderer/ Contractor and the same is detected at any stage even after the award of the tender, the full earnest money deposit will be forfeited and the contract will be terminated at

Page 2: MEMU Master

his/ their risk and cost. The tenderer will also be liable to be banned from doing business with Railways and/ or prosecuted.

9. The following declaration shall be given by the Tenderers while submitting the tender.

DECLARATION

(a) I/We have downloaded the tender form from the internet site www.tenders.gov.in, www.southernrailway.org or www.srailway.com and I/we have not tampered/ modified the tender forms in any manner. In case, if the same is found to be tampered/ modified I/we understand that my/our tender will be summarily rejected and the full earnest money deposit will be forfeited and I/we am/are liable to be banned from doing business with Railways and/or prosecuted.

(b) A demand draft No.__________________ dated _______ for Rs._________ issued by _____________________________________________________ has been enclosed towards the cost of the tender document.

Signature if the Tenderer :

Date :

Address :

Page 3: MEMU Master

SOUTHERN RAILWAY

TENDER DOWNLOADED FROM INTERNET

TENDER NOTICE No. PTJ/SG/CN/2009-10/OT/01 dated 02.12.2009

DUE ON : 28.12.09 UPTO 11:00 hours

To

Executive Signal and Telecommunication Engineer, Construction , Southern Railway, Podanur-641023

This page is to be pasted on top of the sealed cover used for submitting the tender without which the tender will not be

opened.

Page 4: MEMU Master

nùÊIÉhÉ ®äú±É´ÉäSOUTHERN RAILWAY

( ʺÉMÉxÉ±É B´ÉÆ nÚù®ú ºÉÆSÉÉ®ú ʴɦÉÉMÉ )

SIGNAL & TELECOMMUNICATION DEPARTMENT

¦ÉÉMÉ - 1VOLUME - 1

INSTRUCTIONS TO TENDERERS AND SCHEDULE FOR SIGNALLING WORKS

ʺÉMÉxÉ±É EòɪÉÉç Eäò ʱÉB ÊxÉÊ´ÉnùÉnùÉiÉÉ+Éå EòÉä +xÉÖnäù¶É B´ÉÆ EòɪÉÇ EòÒ +xÉÖºÉÚSÉÒ

Name of Work:

“Signalling and telecom arrangements in connection with inspection and stabling facilities for BGAC-MEMU at PGT .”

ÊxÉÊ´ÉnùÉ nùºiÉÉ´ÉäVÉ ºÉÆ0 ÊnùxÉÉÆEò :TENDER NOTICE NO. PTJ/SG/CN/2009-10/OT/01 dated 02.12.2009

DUE TO BE OPENED ON : 28.12.2009

ÊxÉÊ´ÉnùÉEòÉ®ú EòÉ xÉÉ¨É :

Name of the Tenderer:

Page 5: MEMU Master

Page 1 of 33

i) Name of the Tenderer to whom the Tender document is issued

::

ii) Address ::::

iii) Serial No.assigned to the Tender document

::

iv) Date of Sale ::

v) Signature of the Upper Subordinate of the branch concerned.[Name to be shown in BLOCK LETTERS]

::::

Page 6: MEMU Master

Page 2 of 33

STANDARD REGULATIONS FOR TENDERS AND CONTRACTS

Sl.No. CONTENTS Page

1 Meaning of Terms 3

2 Contract Documents 6

3 Condition of Tender 7

4 Annexure I 11

5 Acceptance of Tender 12

6 Annexure II 13

7 Chapter I 14

8 Instructions to Tenderers & conditions of tendering 15

9 Earnest Money Deposit 16

10 Eligibility Criteria 17

11 Errors, Omissions & Discrepancies 19

12 Completion Period 20

13 Chapter II 21

14 Schedule 22 to 25

15 Chapter III 26

16 Annexure B2 29

17 Chapter IV 30

18 Statement of Deviation 31

19 Volume II

20 Volume III

Page 7: MEMU Master

Page 3 of 33

SOUTHERN RAILWAY

REGULATIONS FOR TENDERS AND CONTRACTSFOR THE GUIDANCE OF TENDERS & CONTRACTS

ENGINEERING WORKS

MEANING OF TERMS

1. In these Regulations for Tenders and Contracts the following terms shall have the meanings assigned hereunder except where the context requires otherwise :-

a) "Railway" shall mean the President of the Republic of India or the Administrative Officers of the Southern Railway or of the Successor Railway authorised to deal with any matters which these presents are concerned on his behalf.

b) "General Manager" shall mean the officer in administrative charge of the whole of Southern Railway and shall mean and include the General Manager of the Successor Railway including Construction.

c) "Chief Engineer" shall mean the officer-in-charge of the Signal and Telecommunication Department of Southern Railway and shall mean and include the Engineer-in-Chief and Chief Engineer (Construction/ Projects/ Planning & Projects).

d) "Tenderer" shall mean the person, the firm or company who tenders for the works with a view to execute the works on contract with the Railway and shall include their personal representatives, successors and permitted assigns.

e) "Limited Tenders" shall mean tenders invited from all or some Contractors on the approved list of contractors with the Railway.

f) "Open Tenders" shall mean tenders invited in open and public manner with adequate notice.

g) "Works" shall mean the works contemplated in the drawings and schedules set forth in the Tender forms and required to be executed according to specifications.

h) "Specifications" shall mean the specifications for materials and works, Southern Railway, with up to date correction slips issued under the authority of Chief Engineer and as amplified, added to or superseded by special specifications/conditions if any, appended to the Tender Forms.

i) "Schedule of Rates of Southern Railway" shall mean the schedule of rates issued under the authority of the Chief Engineer from time to time with up to date correction slips.

j) "Drawings" shall mean the drawings, plans and tracings or prints thereof annexed to the Tender Forms, and/or issued for the execution of the work.

2. Words importing the singular number shall also include the plural and vice versa where the context requires.

3. These Regulations for Tenders and Contracts shall be read in conjunction with the General Conditions of Contract which are referred to herein and shall be subject to modifications, additions or super session by special conditions of contract and/ or special specifications, if any, annexed to the Tender Forms.

Page 8: MEMU Master

Page 4 of 33

4. A contractor who has not carried out any work so far on this Railway should furnish particulars regarding:

a) His position as an independent Contractor.

b) His capacity to undertake and carry out works satisfactorily, as vouched for by a responsible official or firm.

c) His Previous experience on works similar to that to be contracted for, in proof of which original certificates or testimonials may be called for and their genuineness verified, if need be, by reference to the signatories thereof.

d) His knowledge from actual personal investigation of the resources of the zone or zones in which he offers to work.

e) His ability to supervise the work personally or by competent and duly authorised agents.

f) His financial position.

5. Should a Tenderer find discrepancies in, or omissions from the drawings or any of the Tender Forms or should he be in doubt as to their meaning, he should at once notify the authority inviting tenders who may send a written intimation to all Tenderers. It shall be understood that every endeavour has been made to avoid any error which can materially affect the basis and scope of the tender and the successful Tenderer shall take upon himself and provide for the risk of any error which may subsequently be discovered and shall make no claim on account thereof.

6.(a) The Tenderer shall be required to deposit the full earnest money deposit with the Tender as a security deposit for the due performance of the stipulation to keep the offer open till such date as might be specified in the tender. It shall be understood that the tender documents have been sold/issued to the Tenderer and the Tenderer is permitted to tender in consideration of the stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Chief Engineer/ Dy.Chief Engineer/ Executive Engineer (Construction/ Projects) of Southern Railway. Should the Tenderer fail to observe or comply with the said stipulation, the full earnest money amount shall be forfeited to the Railway. b) If the tender is accepted this earnest money will be retained as part security for the due and faithful fulfilment of the contract in terms of Clause 16 of the General Conditions of Contract. The earnest money of other Tenderers shall, save as herein before provided, be returned to them, but the Railway shall not be responsible for any loss or depreciation that may happen thereto while in their possession, nor be liable to pay interest thereon. c) Applicable to Tenderers who have deposited lump sum Deposit. The Tenderer shall hold the offer open till such date as may be specified in the tender. It is understood that the tender documents have been sold/issued to the Tenderer and the Tenderer is permitted to tender in consideration of the stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Chief Engineer/ Dy.Chief Engineer /Executive Engineer (Construction), Southern Railway. Should the Tenderer fail to observe or comply with the said stipulation the full earnest money deposit shall be forfeited to the Railway from the lumpsum earnest money deposited by him with the Railway and he will be debarred from tendering further unless he replenishes the amount of so forfeited to the Railway and maintains his lumpsum deposit. (NOT APPLICABLE)

Page 9: MEMU Master

Page 5 of 33

7.(a) Before submitting a tender, the Tenderer will be deemed to have satisfied himself by actual inspection of the site and locality of the works, that all conditions liable to be encountered during the execution of the works are taken into account and that the rates he enters in the Tender Forms are adequate and all inclusive to accord with the provisions in Clause 37 of the General Conditions of Contract for the completion of the works to the entire satisfaction of the Engineer. (b) When work is tendered for by a firm or company of Contractors, the tender shall be signed by the individual legally authorised to enter into commitments on their behalf.

The Railway will not be bound by any power of attorney granted by the Tenderer or any changes in the composition of the firm made subsequent to the execution of the contract. It may, however, recognize such power of attorney and changes after obtaining proper legal advice, the cost of which will be chargeable to the Contractor. 8. Tenders received will be opened and, if practicable the names of the Tenderers and rates will be read out by the Chief Engineer (Construction/ Projects) or his representatives at the stipulated date and time mentioned in the tender notice, in the presence of such of the Tenderers, or their agents as may choose to attend.

9. The Railway reserves the right of not to invite tenders for any work or works, or to invite open or limited tenders, and when tenders are called, to accept a tender in whole or in part or reject any tender or all tenders without assigning any reasons for any such action.

Page 10: MEMU Master

Page 6 of 33

CONTRACT DOCUMENTS 10. The Tenderer whose tender is accepted shall be required to attend the Office of the Chief Engineer/ Dy.Chief Engineer, Executive Engineer (Construction/ Projects) as the case may be in person, or if a firm or corporation, a duly authorised representative shall so attend, and to execute the contract documents within 7 days after notice that the contract has been awarded to him/them. Failure to do so shall constitute a breach of the contract effected by the acceptance of the tender in which case the full value of the earnest money accompanying the tender shall stand forfeited without prejudice to any other rights or remedies.

In the event of any Tenderer whose tender is accepted refuses to execute the contract documents as herein before provided, the Railway may determine that such Tenderer has abandoned the contract and thereupon his tender and the acceptance thereof shall be treated as cancelled and the Railway shall be entitled to forfeit the full amount of the earnest money and to recover liquidated damages for such default.

11. The Tenderer, whose tender is accepted shall sign the agreement in the proforma at page 11.

12.(a) The tender shall be submitted in the prescribed form annexed hereto duly quoting the offer as stipulated in the Special Conditions of Contract. The quotations will be subject to the general instructions contained in Pages I to III of the Schedule of Rates and Special Conditions of Contract attached to the tender to which the Tenderers' special attention is drawn. The percentage and rates quoted must be clearly written in figures and in words, and the percentage (In case of BSR items) will apply to all the items in all the chapters covered in the schedule of BSR items. (NOT APPLICABLE)

(b) In the case of tenders for collection and training out of ballast, the percentage quoted

will apply to all the items in Chapter XX only. Tenderers are not permitted to quote different percentages for different chapters or different items, and in the percentage quoted no fraction is permitted. The percentage/rates quoted must be firm, precise and unconditional. (NOT APPLICABLE)

(c) If any item is excluded by the Tenderer while submitting his tender, the Chief Engineer

(Construction/ Projects) may reject the tender. In the case of tenders for collection and training out of ballast 14 cu.dm. of stone ballast shall be submitted as sample alongwith test certificate as required by the specifications for ballast to show the quality from each of the depots concerned alongwith the tender. (STRUCK THROUGH NOT APPLICABLE)

13. A copy of the printed Basic Schedule of Rates, (2000) Southern Railway may be had

from the Office of the Chief Engineer (Construction) on payment of Rs.300.00 (all inclusive).

Place Signature of Tenderer / TenderersDate :

Page 11: MEMU Master

Page 7 of 33

CONDITIONS OF TENDER

1. The drawings for the works can be seen in the Office of Chief Engineer, Construction/

Projects, Southern Railway, Chennai - 600 008 or the concerned Dy.Chief Engineer/ Executive Engineer, Southern Railway as mentioned in the special conditions of contract during office hours.

2. General Conditions of Contract, Basic Schedule of Rates and Specifications for Materials and Works of Southern Railway can be seen at the Office of Chief Engineer, Construction/ Projects, Southern Railway, Chennai - 8 3. The Tenderer/Tenderer(s) shall quote rate as mentioned in the special conditions of contract. The quantities shown in the attached Schedules are given as a guide and are approximate only and are subject to variation according to the needs of the Railway. The Railway accepts no responsibility for their accuracy. The Railway does not guarantee work under each item of the Schedule.

4. Tenders containing erasures and alterations of the tender documents are liable to be rejected. Any corrections made by the Tenderer/Tenderers in his/their entries must by attested by him/them.

5. The works are required to be completed within the time period stipulated in the special conditions of contract. The work is deemed to commence from the date of issue of letter of acceptance. The work other than earthwork will have to be maintained for the period as mentioned in the special conditions of contract after the completion of the work. 6.(A) The Tenderer/Tenderers is/are required to deposit as Earnest Money amount in any one of the following forms (Refer Volume III):

(i) In cash paid to the Railway Administration's Chief Cashier at Chennai - 3.

(ii) By Money Order in favour of the Railway Administration's Chief Cashier at Chennai - 600 003.

(iii) By Pay Orders or Demand Drafts in favour of Financial Advisor and Chief

Accounts officer, Metropolitan Transport Project , Southern Railway, Egmore, Chennai - 600008.

(iv) By Deposit Receipts in favour of Financial Advisor and Chief Accounts officer, Metropolitan Transport Project , Southern Railway, Egmore, Chennai - 600008.

No interest shall be payable on the Earnest Money deposit.

Note: (1) Cash and Money Orders will not be accepted by the Chief Cashier after 14.00 hrs.

(2) Cheques, Guarantee Bonds, War Bonds and Government Securities (Stock Certificates, Bearer Bond, Promissory Notes, and Cash Certificates) will not be accepted towards earnest money.

(3) Pay Orders, Demand Drafts, and Deposit Receipts should be enclosed along with the

tenders.

6-B) The Tenderer shall hold the offer open till such date as may be specified in the tender. It is understood that the tender documents have been sold/issued to the Tenderer and the Tenderer is being permitted to tender in consideration of the stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Chief Engineer (Construction/ Projects) of Southern Railway. Should the Tenderer fail to observe or comply with the foregoing stipulation the amount deposited as security for the due performance of the above stipulations shall be forfeited to the Railway. If the tender is accepted the amount of earnest money will be held as security deposit for the due and faithful fulfilment of the contract. The earnest money of other Tenderers will save as hereinbefore provided, be returned to the unsuccessful

Page 12: MEMU Master

Page 8 of 33

Tenderers but the Railway shall not be responsible for any loss or depreciation that may happen to security for the due performance of the stipulation to keep the offer open for the period specified in the tender documents or to the earnest money while in their possession, nor be liable to pay interest thereon.

7. It shall not be obligatory on the said authority to accept the lowest tender and no Tenderer/Tenderers shall demand any explanation for the cause of rejection of his/their tender.

8. If the Tenderer deliberately gives/Tenderers deliberately give wrong information in his/their tender or creates/create circumstances for the acceptance of his/their tender, the Railway reserves the right to reject such tender at any stage. The entire EMD with Railway will be forfeited. In addition, action will be taken to suspend the business with the tenderer for a specified period of not less than six months at the discretion of the Administration. 9. If a Tenderer expires after the submission of his tender or after the acceptance of his tender, the Railway shall deem such tender as cancelled. If a partner of a firm expires after the submission of their tender or after the acceptance of their tender the Railway shall deem such tender as cancelled, unless the firm retains its character.

10. The earnest money including the amount taken as security deposit for the due performance of the stipulation to keep the offer open till the date specified in the tender will be refunded to the unsuccessful Tenderer/Tenderers within a reasonable time. The earnest money deposited by the Successful Tenderer/Tenderers will be retained towards the security deposit for the due and faithful fulfilment of the contract but shall be forfeited if the Contractor fails/ Contractors fail to execute the Agreement or start the work within reasonable time (to be determined by the Engineer-in-charge) after notification of the acceptance of his/their tender.

11. The Tenderer is / Tenderers are required to produce along with his/their tender an authorised copy of the Income-Tax Clearance Certificate or a sworn affidavit duly countersigned by the Income-tax Officer to the effect that he has/they have no taxable income. Documents testifying to the Tenderer/Tenderer's previous experience and financial status should be produced when desired by the Chief Engineer, Construction/ Projects, Southern Railway, Chennai - 600 008. 12. Tenders must be enclosed in sealed covers, superscribing name of work for which it is tendered and must be sent by Registered Post to the address of the Executive Signal & Telecommunication Engineer, Construction/ Southern Railway, Podanur so as to reach his office not later than 11:00 hrs on the date mentioned in the tender notice or deposited in the special box allotted for the purpose in the Office of the Executive Signal & Telecommunication Engineer, Construction/ Southern Railway, Podanur . This will be sealed at 11:00 hrs on the same date.

13. Non compliance with any of the conditions set forth hereinabove is liable to result in the tender being rejected.

14. The authority for the acceptance of the tender will rest with the Chief Engineer, Construction/Projects, Southern Railway, Chennai - 600 008, who does not bind himself to accept the lowest or any other tender nor does he undertake to assign reasons for declining to consider any particular tender or tenders. 15. The successful Tenderer/Tenderers shall be required to execute an Agreement with the President of India acting through the Chief Engineer/Dy.Chief Engineer/ Executive Engineer (Construction/ Projects) of the Southern Railway for carrying out the work according to the General Conditions of Contract and Specifications for Works and Materials 1969 of the Railway including the corrections slips from time-to-time.

16. The tenderer shall keep the offer open for a minimum period stipulated in the tender from the date of opening of the tender within which period the Tenderer cannot withdraw his offer, subject to the period being extended further if required, by mutual agreement from time-to-time. Any contravention of the above condition will make the Tenderer liable for forfeiture of his initial security.

17. The Administration does not agree to pay Sales tax in addition to the price quoted.

Page 13: MEMU Master

Page 9 of 33

18. Should a Tenderer be a retired Engineer of the gazetted rank or any other gazetted officer working before his retirement, whether in the executive or administrative capacity, or whether holding a pensionable post or not, in the Engineering Department of any of the Railways owned and administered by the President of India for the time being, or should a Tenderer being partnership firm have as one of its partners a retired Engineer or a retired gazetted officer as aforesaid, or should a Tenderer being an incorporated company have any retired Engineer or retired officer as one of its directors, or should a Tenderer has in his employment any retired engineer or retired gazetted officer from the said service and in cases where such Engineer or officer had not retired from Government service at least two years prior to the date of submission of the tender as to whether permission for taking such contract, or, if the Contractor be a partnership firm or an incorporated company, to become a partner or Director as the case may be or to make employment under the Contractor, has been obtained by the Tenderer or the Engineer or the officers as the case may be from the President of India or any officer duly authorised by him in this behalf, shall be clearly stated in writing at the time of submitting the tender. Tenders without the information above referred to or a statement to the effect that no such retired Engineer or retired gazetted officer is so associated with the Tenderer, as the case may be, shall be rejected.

19. Should a Tenderer or Contractor being an individual on the list of approved Contractors, have a relative employed in gazetted capacity in the Signal and Telecommunication Department of the Southern Railway, or in the case of partnership firm or company incorporated under the Indian Company Law should a partner or a relative of the partner or a shareholder or a relative of a shareholder be employed in gazetted capacity in Signal and Tele communication Department of the Southern Railway, the authority inviting tenders shall be informed of the fact at the time of submission of tenders, failing which the tender may be rejected, or if such fact subsequently comes to light, the contract may be rescinded in accordance with the provision on Clause 62 of the General Conditions of Contract.

Place : Signature of Tenderer. Date :

Page 14: MEMU Master

Page 10 of 33

Proforma to be filled in and signed by the Tenderer and submitted along with the tender with reference to Clauses 18 and 19 of the Conditions of Tender

Strike out whichever is not applicable

I. The undersigned :

(a) is a retired gazetted officer holding prior to retirement a pensionable/non-pensionable

post in Signal and Telecommunication Department of ________________ Railway.

(b) is a partnership firm having as one of its partners a retired Engineer or a retired gazetted officer as aforesaid.

(c) is an incorporated company having any such retired Engineer or retired officer as aforesaid, as one of its directors.

(d) is having in my employment any retired Engineer or retired gazetted officer as aforesaid.

(e) has no such retired Engineer or retired gazetted officer so associated with me as stated above.

II. If falling under any of the above categories (a) to (d) particulars of the officer may be furnished hereunder : (1) Post held before retirement …. _________________________________

(2) Date of retirement …. _________________________________

(3) If not retired at least two years prior to date of submission of tender state whether permission for taking such contracts has been obtained from the President of India or any officer duly authorised in this behalf.

…. _________________________________

III. If the Tenderer or in the case of a firm or company, any of the shareholders has a relative or relatives employed in gazetted capacity in the Engineering Department of the Railways, particulars of such relatives in the Railway may be furnished hereunder :-

(1) Name .. ____________________________ (2) Designation .. ____________________________ (3) Relationship .. _______________________________

Signature of Tenderer

Page 15: MEMU Master

Page 11 of 33

ANNEXURE I

TENDER To Name of Work:

To

The President of India,Acting through the Executive Signal & Telecommunication Engineer, Construction/ Southern Railway, Podanur

1. We ______________________________________________________ have read the various conditions of Tender attached hereto and hereby agree to abide by the said conditions. We also agree to keep this Tender open for acceptance for a period of __________ days from the date fixed for opening the same and in default thereof will be liable for forfeiture of our “Earnest Money Deposit”. We offer to do this work at the rates quoted in the attached schedule and hereby bind ourselves to complete this work within ______ months from the date of issue of execution of agreement or date of issue of letter of intent whichever is earlier. We also hereby agree to abide by the General and Special conditions of Contract and to carry out the work according to the specifications for materials and works laid down by the Railways for the present Contract.

2. A sum of Rs.________ is herewith forwarded as “Earnest Money Deposit”. The full value of the same shall stand forfeited without prejudice to any other rights or remedies if,

a. We do not execute the Contract document within 14 days after receipt of notice issued by Railways that such documents are ready, or

b. We do not commence the work within 7 days after receipt of orders to that effect.

3. Until a formal agreement is prepared and executed, we agree that the letter of acceptance of the Tender shall constitute a binding contract between us subject to modifications, as may be mutually agreed to between us.

Signature of the Contractor Contractor’s address & date

Signature of witnesses

1.

2.

Page 16: MEMU Master

Page 12 of 33

FOR OFFICIAL USE ONLY

ACCEPTANCE OF TENDER

I accept the Tender and agree to pay the rates mentioned by Railways, enhanced

by ...........................percent/ AT PAR in respect of schedules in Annexure ‘A ‘ and at the rates

as entered in respect of schedules of Annexure ‘B’(items not covered by Annexure-‘A’). Based

on these rates the value of contract works out to Rs.............................................

(Rupees ........................................... only)

Executive Signal and Telecommunication Engineer Construction), Southern Railway.Podanur

on behalf of President of India Witnesses Division __________________ 1. _________________________ Date : __________________2. _________________________

Page 17: MEMU Master

Page 13 of 33

ANNEXURE II

AGREEMENT FOR WORKS

I.CONTRACT AGREEMENT No.CLT/SG/CN/CONT/Calicut dated ARTICLES OF AGREEMENT MADE This ____Day of ________ Two Thousand and Nine between the “President of India" acting through the Executive Signal & Telecommunication Engineer, Construction,Podanur-641023 of Southern Railway Administration hereinafter called the "Railway" of the one part and .....................................,hereinafter called the "Contractor" of the other part. II. WHEREAS the Contractor has agreed with the Railway for the performance of the work setforth in the schedule hereto annexed and in conformity with specifications of the Southern Railway and special conditions and special specifications and drawings hereto annexed, if any, and General Conditions of Contract AND WHEREAS the performance of the said work is an act in which the public are interested.

III. AND WHEREAS the contractor has deposited a sum of Rs. .(Rupees .................................... only) vide dated issued by i, towards the Earnest money AND WHEREAS the balance of security deposit after adjustment of Earnest money of Rs. , Originally paid by the contractor is at the instance of the Contractor recovered at 10 percent of the value of the running bill till all the amount of Security deposit of Rs............................... is fully recovered. IV.AND WHEREAS the contractor has submitted a Performance guarantee for Rs.......................(Rupees ..............................................................) vide............................... dated ................., .issued by .................................. and valid till ..............at 5% of the contract value to the Railways for due fulfilment of contract conditions .

V. NOW THIS INDENTURE WITNESSTH that in consideration of the payments to be made by the Railway, the Contractor will duly perform the said works in the said schedules setforth and shall execute the same with great promptness, care and accuracy in a workmanlike manner to the satisfaction of the Railway and will complete the same in accordance with the said specifications and said drawings and said conditions of contract within ............... the stipulated period as mentioned in the special conditions of contract from the date of issue of letter of acceptance and will maintain the said works as stipulated in the schedule attached from the certified date of their completion and will observe, fulfil and keep all the conditions therein mentioned (which shall be deemed and taken to be part of this contract as if the same had been fully set forth herein), AND the Railway doth hereby agree that if the Contractor shall duly perform the said works in the manner aforesaid and observe and keep the said terms and conditions, the Railway will pay or cause to be paid to the Contractor for the said works on the final completion thereof the amount due in respect thereof, at the rates set forth in the annexure annexed.

VI. It is hereby agreed and declared that all the provisions of the said specifications, conditions of contract which have been carefully read and understood by the Contractor, and the printed Schedule of Rates including the General Instructions contained in Pages I to III thereof, shall be binding upon the Contractor and upon the Railway Administration as if the same had been repeated herein and shall be read as part of these presents. VII. The cost of stamp duty on the agreement shall be borne by the Railway Administration. Signature of witnesses with {1. __________________ Contractor ______________________address to signature of Contractor {2. __________________ Address ______________________

Date : ________________________

Designation ________________Southern Railwayfor President of India.

Page 18: MEMU Master

Page 14 of 33

CHAPTER – I

Name of Work:

To

The President of India,Acting through the Executive Signal & Telecommunication Engineer, Construction, Podanur, Southern Railway,Podanur – 641023.

1. We ______________________________________________________ have read the various conditions of Tender attached hereto and hereby agree to abide by the said conditions. We also agree to keep this Tender open for acceptance for a period of __________ days from the date fixed for opening the same and in default thereof will be liable for forfeiture of our “Earnest Money Deposit”. We offer to do this work at the rates quoted in the attached schedule and hereby bind ourselves to complete this work within ______ months from the date of issue of execution of agreement or date of issue of letter of intent whichever is earlier. We also hereby agree to abide by the General and Special conditions of Contract and to carry out the work according to the specifications for materials and works laid down by the Railways for the present Contract.

2. A sum of Rs.____________ in the form of Cash/ Banker’s Cheque/ Demand Draft/ Fixed Term Deposit Receipt No.____________ dated ______ issued by Bank _____________________________________ branch ______________ is herewith forwarded as “Earnest Money Deposit”. The full value of the same shall stand forfeited without prejudice to any other rights or remedies if,

a. We do not execute the Contract document within 14 days after receipt of notice issued by Railways that such documents are ready, or

b. We do not commence the work within 7 days after receipt of orders to that effect.

3. Until a formal agreement is prepared and executed, we agree that the letter of acceptance of the Tender shall constitute a binding contract between us subject to modifications, as may be mutually agreed to between us.

Signature of the Contractor Contractor’s address & date

Signature of witnesses

1.

2.

Page 19: MEMU Master

Page 15 of 33

INSTRUCTIONS TO TENDERERS AND CONDITIONS OF TENDERING

1 INVITATION OF TENDERS:

XSTE/Construction/ Podanur invite Sealed Tenders for the work as mentioned below:

“Signalling and telecom arrangements in connection with inspection and stabling facilities for BG AC—MEMU at PGT .”

2. SCOPE OF WORK:

2.1 The scope of this work along with the list of stations where the works are to be carried out and the relevant signaling plan/sketch No. are furnished in Chapter IV of Volume-I.

2.2 Clarification about the latest policies/ practices for execution can be received from the Office of CSTE/Construction, Egmore, Chennai-600 008.

3 SUBMISSION OF OFFERS:

3.1 All offers in the prescribed forms ( Vol.I , Vol.II &Vol.III ) should be submitted before the time and date fixed for the receipt of the offers. Offers received after the stipulated time and date will be summarily rejected.

3.2 In case the date of opening happens to be a holiday, the tender will be received and opened at the same time on the next working day.

3.3 All offers shall be either type written or written neatly in indelible ink in English. Each page of the offer must be numbered consecutively. A reference to total number of pages comprising the offer must be made at the top right hand corner of the top page.

3.4 All copies of the tender paper (Vol.I,Vol.II & Vol.III) shall be signed in ink by the tenderer, on each page including closing page, in token of his having studied the Tender papers carefully.

3.5 RATES IN FIGURES & WORDS:- All prices and other information like discounts, etc. having a bearing on the price shall be written both in figures and in words in the prescribed offer form. In case of difference in words and figures the amount written in words will be taken into consideration.

3.6 ATTESTATION OF ALTERATION:- No scribbling is permissible in the tender documents. Tender containing erasures and alterations in the tender documents are liable to be rejected. Any correction made by the tenderer in his entries must be self-attested.

3.7 The tenderer shall submit his tender duly filled up along with the following in a Sealed Cover:

i) Offer letter complete. ii) The rates/ Single percentage for the complete schedule of works as detailed in Chapter-II of

Volume-I (both in figures and words).

i. A Receipt for having deposited the Earnest money for Rs.21,560.00.00 . The EMD submitted should cover the entire validity period of the offer. Tenders not accompanied by the requisite EMD will be summarily rejected. Use of discharged instruments towards EMD for other tenders is prohibited.

iv) Turnover:

Documentary proof of turnover shall be submitted in any of the following means: (If stipulated in the eligibility criteria of Tender Notice).

(a) ITCC submitted along with the tender. The contract amount of the latest three years will be taken for verifying the credentials.

Page 20: MEMU Master

Page 16 of 33

(b) Documentary evidence duly certified by Chartered Accountant/Company Auditor, audited balance sheet, certificate issued by Railway Officers not below the rank of JA grade.

v) A copy of partnership deed and affidavit for proprietorship.

vi) Tenderer's credentials.

vii) If the tenderer wants to give any deviation, the statement of Deviations for any clause or sub-clause of “General Conditions of Contract”, “Special Conditions of Contract”, “Instructions to tenderers and conditions of tendering”, which he proposes with detailed justification for deviation proposed should be submitted in the format given as Form No.I in Vol.I.

viii) Similar works executed. Particulars regarding supplies of similar equipments, testing and commissioning and details of project or major works executed of similar nature.

(a) For the purpose of single similar nature of work, the Experience Certificate should be attached to the tender document as per proforma given as Form No.II in Vol.I, which can be filled up and signed by the tenderer, in case the format issued by the Executive is different. The certified copies of relevant Experience Certificate are also to be enclosed.

(b) With respect to Railways, the experience certificate should have been issued by atleast a JA Grade Officer. With respect to other Government departments and PSUs, the certificate issued at the level of Executive Engineer and above can be taken as valid.

ix) Solvency Certificate issued by Bank/Revenue authority: (If stipulated in the eligibility criteria of Tender Notice).

a) Solvency certificate should be issued either by revenue authorities not below the rank of Tahsildar/Sub-Divisional Officer and/or by Manager of Scheduled/ Nationalised banks. The solvency certificate should not be older than one year from the date of opening of the tender.

b) The solvency certificate should be in the proforma (format enclosed as Form No.III of Vol.I) particularly when issued by other than Revenue Authorities.

x) Should a tenderer be a retired Engineer of the Gazetted Rank or any other Gazetted Officer working before his retirement, whether in the Executive or Administrative capacity or whether holding a pensionable post or not in the Engineering Department of any of the Railways owned and administered by the President of India for the time being or should a tenderer being partnership firm have as one of its partners a retired Engineer or a retired Gazetted Officer as aforesaid, or should a tenderer being an incorporated company have any such retired Engineer or retired Officer as one of its Directors, or should a tenderer have in his employment any retired Engineer or retired Gazetted Officer as aforesaid, the full information as to the date of retirement of such Engineer or Gazetted officer from the said service and in case where such Engineer or Officer has not retired from Government Service at two years prior to the date of submission of the Tender as to whether permission for taking such contract, or if the contractor be a partnership firm or an incorporated company to become a partner or Director as the case may be, or to take employment under the contractor, has been obtained by the Tenderer or the Engineer or the Officer as the case may be from the President of India or any Officer duly authorized by him in this behalf shall be clearly stated in writing at the time of submitting the tender. Tenders without the information above referred to or a statement to the effect that no such retired Engineer or Retired Gazetted Officer is so associated with the Tenderer, as the case shall be rejected.

xi) Complete technical data and particulars of the equipment offered, as specified in the Tender papers together with descriptive literature, leaflets, etc.

3.8 Non-compliance with all or any of the condition said forth therein above is liable to result in the tender being rejected.

Page 21: MEMU Master

Page 17 of 33

3.9 Tender Committee may at their discretion call for the originals of the credentials for verification from the tenderers or any clarifications/confirmations on the contents of the documents submitted.

3.10 In case the Certificates/Documents produced are proved to be false/ fabricated, the entire earnest money is liable to be forfeited in addition to banning their business with the organisation for a specified period of not less than six months at the discretion of the Administration.

4. ELIGIBILITY CRITERIA AND CREDENTIALS:

4.1 Tenderers are required to satisfy the following eligibility criteria (for advertised tender value exceeding Rs.20 lakhs and upto Rs.5 Crores :-

Sl.No. Certificate Minimum Criteria

1 Should have completed in the last three financial years (i.e. current year and three previous financial years)

At least one similar single work, for a minimum value of 35% of advertised tender value of work.

2 Total contract amount received during the last three financial years and in the current financial year.

Should be a minimum of 150% of advertised tender value of work. The tenderer has to produce attested certificate from the employer/client, audited balance sheet duly certified by the chartered accountant etc., with the tender offer.

Note: One single similar nature of work means:

MACLS with Route Relay Interlocking/Relay interlocking

4.2 Documentary proof (in the form of attested copies of certificates) of satisfaction of eligibility criteria should be furnished along with the tender documents. The offers of tenderers who do not pass the prescribed eligibility criteria will be rejected.

4.3 The tender committee shall examine the overall financial soundness of the tenderers based upon the volume of work handled, turnover balance sheet etc.

5 LOCAL CONDITIONS:

5.1 Need of tenderer’s careful study of conditions & site conditions:

The intending tenderer is advised to study tender papers, concerned specification and other instructions carefully. The tenderer shall inspect the proposed site of work and acquaint himself with the site conditions, working hours, layout of land, trees and shrubs that he will have to cut, type of strata likely to be met while excavation, stacking space for materials, approach roads, pathways available etc. and all relevant items connected with execution for the work. No claim shall be entertained for the contractors making his own arrangements for approach roads from outside Railway Land and contractors will bear entire expenses such as road taxes, payment for right of way, etc. to outsiders and for constructions of approach roads, etc. The submission of tender shall be deemed to have been done after careful study and examination of the tender papers with full understanding of the implication thereof, unless otherwise, specifically commented upon by the tenderer in his quotation. Failure to adhere to any one or all these instructions may render his offer liable to be ignored without any reference.

5.2 No request for the change of price or time schedule of delivery of stores shall be entertained after the offer is accepted by the Railways on account of any local condition or factor.

5.3 In the event of the tenderer desiring to have an independent field survey before furnishing his quotations, he may apply to Railways for permission in this regard. Such permission will be given in writing by the Railways but the expenses in this regard will be borne by the tenderer completely.

Page 22: MEMU Master

Page 18 of 33

5.4 Should a tenderer find discrepancies in, or omission from the drawing or any of the Tender papers or he has any doubt to their meaning, he should at once notify the Railway who may send a written clarification to all tenderers.

6 TENDERERS TO ADVISE STRENGTH OF STAFF:

6.1 Tenderer should advise the number of Engineer, Supervisors and Cable Jointers/Artisans employed by him or going to be employed with their names, qualifications, bio-data and experience in this particular trade under consideration along with the Tender.

6.2 Irrevocable letters of commitment of the said supervisors and key technicians/artisans for doing the works shall be furnished along with tender papers, if they are not already in employment of the tenderer.

7 CONSORTIUM BID:

Consortium/Joint ventures will not be accepted and all the credentials in proof of fulfilling eligibility criteria specified in the tender documents have to be in the name of sole tenderer only.

8 VALIDITY OF OFFER:

8.1 The tenderer shall keep the offer open for a minimum period of 120 days from the date of opening of tender. Within that period, the tenderer cannot withdraw his offer subject to the period being extended further if required by mutual agreement from time to time. Any contravention of the above condition will make the tenderer liable for forfeiture of his Earnest Money Deposit.

9. UNIT PRICES:

9.1 The unit prices quoted by the Contractor should be inclusive of all Taxes, viz. Octroi and levies imposed by the Central and State Governments and taken into consideration of all relevant factors unless otherwise authorised by the concerned State Government Sales Tax Authorities.

9.2 The description of items are given as a guide and the quantities given are approximate only and are subject to variation according to the needs of the Railways. The Railways accept no responsibility for their accuracy. The Railways do not guarantee work under each item of schedule.

9.3 The unit prices offered against the various items will include besides Labour the following elements of cost:

9.3.1 Cost of all materials required for laying the cables, casting of foundations, erection of Signals, Apparatus cases, Junction Boxes, Installation of track circuits and Point machines including their transport to site and all other incidentals connected therewith excluding the materials supplied by the Railways.

9.3.2 Cost of transportation of materials including loading, unloading, handling charges, etc. supplied by the Railways from place of delivery to the site of work.

9.3.3 Collection of balance cables, materials left over after the work, if any and materials released and handing over to the Railway Engineers at specified location.

9.3.4 All other miscellaneous expenses necessary for the execution of the work and fulfilment of the contractual obligations.

9.4 The contractor shall be responsible for undertaking repairs if any, to crates, cable drums packing cases, etc. for safe transport of materials from Railway’s specified depot to the site of work. The contractor should also undertake necessary repairs to crates drums etc. in respect of unused materials required to be returned to the purchaser. No extra payment will be made on this account.

Page 23: MEMU Master

Page 19 of 33

9.5 Materials to be supplied by the tenderer and by Railways are indicated separately in Vol.I. However, any particular item of material not included in the Contractor’s list or in the Railway’s list, but if still required to complete the works, the tenderer shall include such items of materials in his tender and quote for the same.

10 RATES DURING NEGOTIATION:

The tenderer shall not increase his quoted rates in case the Railway Administration negotiates for reduction of rates. Such a negotiation shall not amount to cancellation or withdrawal of the original offer and the rates originally quoted will be binding on the tenderer.

11 NON TRANSFERABILITY AND NON REFUNDABILITY:

The tender documents are not transferable. The cost of tender paper is not refundable

12 ERRORS OMISSIONS & DISCREPANCIES:

The Contractor(s) shall not take any advantage of any mis-interpretation of the conditions due to typing or any other error and if in doubt, shall bring it to the notice of the Engineer, without delay. In case of any contradiction only the printed rules and books should be followed and no claim for the misinterpretation shall be entertained.

13 WRONG INFORMATION BY THE TENDERER:

If the tenderer deliberately gives wrong information in his tender, creates circumstances for the acceptance of his tender, the Railway reserves the right to reject such tender at any stage.

14 AUTHORITY FOR ACCEPTANCE :

The authority for the acceptance of the tender will rest with the competent authority of the Southern Railway on behalf of President of India. It shall not be obligatory on the said authority to accept the lowest or any tender or to assign any reason for non-acceptance or rejection of a tender. The Railway reserves the right to accept any tender in respect of the whole or any portion of the work specified in the tender paper or to sub-divide the work among different Tenderers or to reduce the work or to accept any tender for less than the tendered quantities without assigning any reason whatsoever.

It shall not be obligatory on the said authority to accept the lowest tender and no tenderer shall demand any explanation for the cause of rejection of his tender.

15 AGREEMENT:

The successful tenderer shall be required to execute an agreement with The President of India acting through the Executive Signal and Telecommunication Engineer/ Construction, Southern Railway, Podanur -641023 or his accredited officer for carrying out the work according to the General Conditions of the Contract and specifications of contract including the correction slips issued from time to time.

16 FOREIGN EXCHANGE:

No foreign exchange and/ or import license will be released/ provided to the contractor in connection with this contract.

17 TENDERERS’s ADDRESS:

Tenderer shall state in the tender his postal address fully and clearly. Any communication sent to the tenderers by post at his said address, shall be deemed to have reached the tenderer duly & timely, not withstanding the fact that the communication could not reach the tenderer at all or in time for whatever reason. Important documents shall be sent by Registered post.

Page 24: MEMU Master

Page 20 of 33

The tenderers shall go through the instructions contained in the “Regulation for tenders and contracts and conditions of Tender” before submitting their offers. All the relevant blank spaces in the booklet must be suitably filled in and returned with the tender documents duly signed by the tenderers.

18 EXECUTIVE INCHARGE OF WORK:

Indicated in Chapter-II of Volume-I

19 SCHEDULE OF WORK:

The schedule of works are indicated in Chapter-II of Volume-I. The tenderer should quote the rates for all the schedules of work in both words and figures.

20 COMPLETION PERIOD OF WORK: The work is to be completed within FOUR months from the date of issue of Letter of Acceptance.

21 LIST OF MATERIALS TO BE SUPPLIED BY RAILWAYS:

List enclosed in Chapter III of Vol.I as Annexure B-1.

22 LIST OF MATERIALS TO BE SUPPLIED BY CONTRACTOR:

List enclosed in Chapter III of Vol.I as Annexure B-2.

23 STORES DEPOT FROM WHERE THE MATERIALS SUPPLIED BY RAILWAYS ARE TO BE COLLECTED BY THE CONTRACTOR:

Indicated in Chapter-II of Volume-I.

24. DETAILS TO BE SUBMITTED ALONG WITH THE TENDER:

a. List of personnel, organisation available on hand and proposed to be engaged for the subject work.

b. List of plant & machinery available on hand (own) and proposed to be inducted (own and hired to be given separately) for the subject work.

c. List of works completed in the last three financial years giving description of work, organisation for whom executed, approximate value of contract at the time of award, date of award and date of scheduled completion of work. Date of actual start, actual completion and final value of contract should also be given.

d. List of works on hand indicating description of work, contract value, approximate value of balance work yet to be done and date of award.

Note: 1) In case of items (c) and (d) above, supportive documents/ certificates from the

organisations with whom they worked/ are working should be enclosed.

2) Certificates from private individuals for whom such works are executed/ being executed shall not be accepted.

* * * * * * * *

Page 25: MEMU Master

Page 21 of 33

CHAPTER - II

A B S T R A C T S U M M A R Y

Name of Work: “Signalling and telecom arrangements in connection with inspection and stabling facilities for BG AC –MEMU at PGT”

Tender Notice No. PTJ/SG/CN/2009-10/OT/01 dated 02.12.09

Executive in-charge: XSTE/CN/PTJ

Stores depot for collecting Railway materials: Calicut/Palghat/Podanur

Railway assessed value of the Tender for the 50 items of schedule in Annexures-A

Rs.10,65,223.60

Single percentage quoted by the Tenderer(in figures and words)

Tenderers to note:

1. Tenderers are requested to quote in the above tabular column only the Overall Single Percentage in figures and words in comparison with the estimated value of the Tender. 2. Tenderers shall not quote individual item wise rates for schedules in Annexures-A

SIGNATURE OF TENDERER

EXAMPLE FOR FILLING UP SINGLE PERCENTAGE:

If the Tenderer intends to quote on par with estimated rates, he shall write “RATES ON PAR”.

If the Tenderer intends to quote IN EXCESS OVER the estimated rates, he shall write “+[PLUS] %”.

If the Tenderer intends to quote LESS than the estimated rate, he shall write “- [MINUS] %”.

Page 26: MEMU Master

Page 22 of 33

SCHEDULEName of work: “Signalling and telecom arrangements in connection with inspection and stabling facilities for BG AC-MEMU at PGT”

Executive in-charge: XSTE/CN/PTJ

Materials supplied by Railways shall be collected by the Contractor from the stores depot at Calicut/Palghat /Podanur

The tenderers are requested to quote only one overall single percentage for the schedule items in Annexure-A and individual item wise rate for Annexure-B. For detailed description of schedules in

Annexure –A, refer Chapter II enclosed.

TENDERERS SHALL NOTE THAT THE RATES SHOWN BELOW AGAINST EACH SCHEDULE IN ANNEXURE-A ARE THE RAILWAY ASSESSED RATES FOR THE RESPECTIVE SCHEDULE ITEMS

AND THE SINGLE PERCENTAGE QUOTED BY THE TENDERERS WILL BE APPLIED ONLY ON THESE RATES.

Sl No

SOR BRIEF DESCRPTION OF WORK UNIT QTY RATE AMOUNT

  ANNEXURE A      

1 1001Excavation of cable trench 1 m depth x 0.3 m width

Mtrs 2000 25.80 51600.00

2 1003Construction of masonry duct in hard rocky area

Mtrs. 30 293.40 8802.00

3 1004Excavation of cable trench across metalized/mechademised roads

mtrs 50 325.50 16275.00

4 1007Provision of RCC pipe at 1 m depth for track/road crossing

per RCC pipe

40 417.60 16704.00

5 1010bProvision of GI pipe 100 mm dia 4.5mm thick

Mtrs. 150 783.60 117540.00

6 1011Laying of signalling/power/telecommunication cables

Mtrs. 5500 7.80 42900.00

7 1013 Placing of one rows of country bricks Mtrs. 2000 42.40 84800.00

8 1015Refilling of cable trench 1m depth by 0.3m width

Mtrs. 2000 6.20 12400.00

9 1017 Supply of RCC cable marker Nos. 70 144.60 10122.00

10 1018Placing of cable marker and concreting (RCC type)

Nos. 70 113.20 7924.00

11 1019Excavation of cable coil pit to a size of 1.0m depth x1.0m length 1.0m of breadth

Nos. 4 389.70 1558.80

12 2001Excavation of pit, casting concrete foundation and erection of apparatus case full size

Nos. 5 8,367.00 41835.00

13 2002Excavation of pit, casting concrete foundation and erection of apparatus case half size

Nos. 5 5836.00 29180.00

14 2004Erection of CJ box and concreting(for cable throughing)

Nos. 4 2782.00 11128.00

15 2005Erection of CJ boxes and concreting ( for point machine )

Nos. 2 2804.00 5608.00

Page 27: MEMU Master

Page 23 of 33

16 2008 a) shifting apparatus case (full) Nos. 2 2281.00 4562.00

17   c) shifting apparatus case (quarter) Nos. 1 1183.00 1183.00

18 2009Termination of new main /tail cables on the existing terminals

Per Terminal

Block200 29.70 5940.00

19 2010 aTermination on 25/60mm PBT terminals (new location)(Phynolic sheet)

Per Terminal

Block500 74.10 37050.00

202010

b Termination on PBT fuse block (new location) (Phynolic sheet)

Per Fuse Block

10 98.10 981.00

21 2011 a Termination of cables on 25/60mm PBT terminals (existing location)

Per Terminal

Block100 62.50 6250.00

22 2011b Termination of cables on PBT fuse block (existing location)

Per Fuse Block

10 86.60 866.00

232012

b Wiring of Signal/ Point/ LC control circuit (up to 8 relays)

Set 2 3647.00 7294.00

24 2012 c Wiring of Signal/ Point/ LC control circuit (up to 12 relays)

Set 1 4707.00 4707.00

25 2016 a Alteration to painting particulars (apparatus case - Full size)

Nos. 1 863.00 863.00

26 2018Excavation of pit, casting concrete foundation for cls up to 4 aspects

Nos. 2 4455 8910.00

27 2019Erection of surface base, signal pole, mounting of CL signal up to 4 aspects

Nos. 2 4066.00 8132.00

28 2021 Erection of Ground type shunt signal Nos. 1 1574.00 1574.00

29 2022 Erection of post type shunt signal Nos. 2 1218.00 2436.00

302023

bInstallation of stencil type route indicators Nos. 1 1483.00 1483.00

31 2025 Erection of calling on signal Nos. 1 1115.00 1115.00

32 2031 a Provision of track circuit in RE area (point zone)

Nos. 1 10487.00 10487.00

33 2033 a Alteration track circuit at feed end Nos. 1 1938.00 1938.00

342033

bAlteration track circuit at relay end Nos. 1 1844.00 1844.00

35 2034 Provision of rail joint insulation Nos. 4 261.20 1044.80

36 2036Supply and provision of earth electrodes (GI)

Nos. 10 1763.00 17630.00

37 2038 Installation of point machine(IRS/5E type) Nos. 2 7259.00 14518.00

38 3002a. Fixing of PBT terminal blocks (25mm/60mm centre) and termination

Per Terminal

Block60 71.30 4278.00

39  b. Fixing of PBT fuse block with ND fuses and termination

Per Fuse Block

10 95.20 952.00

40 3005Fixing and wiring of additional relay in relay rack/location

Per Relay

125 341.60 42700.00

Page 28: MEMU Master

Page 24 of 33

41 3006Carrying out alterations to the existing relays wiring

Per Relay

700 320.90 224630.00

42 3010Carrying out alterations to the existing control panel

LS. 1 7049.00 7049.00

43 3011Provision of signaling arrangement during noninterlocked working

LS. 1 16635.00 16635.00

44 3013Supply and installation of DTMF way station equipment with control phone and power supply

set 2 12971.00 25942.00

45 4014Installation and wiring of electric key transmitter

Nos. 2 2463.00 4926.00

46 4016Erection and painting of boards with legends

Nos. 1 1844.00 1844.00

47 4019 aSupply and installation of magneto telephone with NiCad pack

Nos. 4 5409.00 21636.00

484029

bTesting and commissioning of station more than five roads

LS. 1 27775.00 27775.00

49 4030Preparation and submission of as made drawings

per 'A3' size sheet

240 167.80 40272.00

50 5029 Transportation of signaling materials /ton km 20000 2.37 47400.00

Annexure 'A' total 1065223.60

Single percentage quoted

Annexure 'A' total

Annexure B UNIT QTY RATE AMOUNT

1Supply and installation of telecom cable termination box 20pair and terminating the cable in the box fixed on TW plank of 25mm thickness

Nos. 2

2

 Supply of heat shrinkable cable jointing kit for quad cable confirming to RDSO spec:IRST6-77-2006(Rev-I)

Nos. 3

3

 Shifting of boom locking arrangement at LC.This work includes leveling of ground, erection of additional trestles, concreting of ‘A’ base and fixing of cranks and rod run to extend the rod up to the newly erected boom as required at site and painting of rods, cranks and trestles. Welding of rods/joints is to be done as required.{32mm MS rods, trestles, cranks, MS pin and ‘A’ bases will be supplied by the Railways. Cement, sand, Jelly, Paint , spit pins, bolts with nuts and all other miscellaneous materials shall be supplied by the contractor.}

Nos. 1

  Annexure 'B' total  

Page 29: MEMU Master

Page 25 of 33

  Annexure 'A' total    

  Grand total    

Signature of the tendererwith address

Chapter – III

Annexure-B1

Page 30: MEMU Master

Page 26 of 33

Materials to be supplied by the Contractor

WITH CONSIGNEE INSPECTION

1. Track feed battery charger to charge up to 4 cells

2. Cable markers – RCC type

3. ‘E’ type locks with keys.

4. GI earth pipe to drawing No.SG/CN/9.& SEE/ 60C

5. RCC pipes with collars

6. Wire PVC 16/0.2mm, 3/0.75mm and 7/1.4mm copper.

7. Insulations for Points and crossings

8. Cement

9. Enameled number plates/ marker boards

10. EWS locks with keys (one key for 10 locks)

11. Foundation bolts, nuts & washers for apparatus cases of size 20mmx460mm to Drg.No.SA 112 A/M

12. Foundation bolts, nuts & washers for Colour light Signals 24mmx915mm conforming to Drg.No SA 116 A/M.

13. G.I. Pipes 35mm dia with check nuts for CT Boxes

14. G.I. wire for earthing

15. GI Pipes 50mm dia-3.65mm thick and 100mm dia-4.50mm thick conforming to IS-1239 amended up to date, with coupling and bends for cable laying on bridges and for tail cables on signal post telephones etc.

16. Hard wood shelf plank 37mm thick for apparatus cases and CT boxes

17. DTMF way station equipment.

18. ND fuses & HRC fuses of required ratings

19. Laminated Termite proof particles board - Exterior Grade 25mm thick

20. Control telephone.

21. Phynolic synthetic industrial fibre base fine weave cotton fibre sheet - 6mm thick to IS specification 2036 - 1995 - Type F5 sheet of 6mm thick for termination of cables in apparatus cases and diagnostic panel, and 3mm thick for FTOT/ relay rack blanking.

22. Rubber mat not less than 6mm thick to withstand 650V.

23. Battery charger-12V for DTMF equipment.

24. Magneto telephone

25. T.W. planks 25mm thick, for fixing track feed resistance, anti-tilting arrangements for shelf type relays, for fixing EKT and for manufacturing Termination Box, Tool Box.

26. TW planks 50X150mm, 50mmx50mm, 25mmx100mm and 25mmx150mm thick for control panel frame, cable clamps and fixing cables.

27. 2BA Terminals with clips.

28. Acid/Salammoniac.

29. Adhesive paste.

30. Alca `P' solder eyre flux.

Page 31: MEMU Master

Page 27 of 33

31. Aluminium name plates for cable tags.

32. Bricks of size 220mmx100mmx60mm.

33. Cable compound.

34. Charcoal.

35. Clamps for fixing PVC pipes.

36. Coal Bengal.

37. Coloured twine balls.

38. Common salt for earthing.

39. Copper Battery lugs and eye lugs.

40. Copper eyelets for 16/0.2mm and 1/1.5 sq.mm wires

41. Copper tape 20mm x 1.5mm for Bus Bar.

42. Cotton waste.

43. Decolum sheet for decorative purposes.

44. Electrolytic condensers of rating depending on the circuitory requirements. The voltage rating shall not be less than twice the working voltage of the circuit.

45. Emery and sand papers.

46. Fire wood

47. Fixing bolts and nuts (brass) for Terminal blocks and Fuse Blocks in FTOT & for fixing plug in type relays, 50 Way terminal board etc.

48. Flexible conduit Pipes

49. Grease yellow.

50. Honey bee wax.

51. Insulating tapes.

52. Kerosene Oil.

53. Lead wool for packing signal poles.

54. Lens guard for colour light signal units.

55. MS angles 75X75X10mm and 50X50X8mm for providing interconnections.

56. MS angles 25mmx25mmx6mm, 50mmx50mmx6mm for manufacturing relay fixing frames.

57. MS flats 50mmx6mm & 25mmx6mm for manufacturing relay frames, Signal collar rings, clamps for bridges, boards, for fixing equipments in apparatus cases and also for fixing `E' type locks on doors of apparatus cases, and for latching arrangement.

58. Oil axle mineral.

59. Paints of all kinds for IS Specification including anticorrosive paints.

60. Petroleum jelly.

61. Pipe locks/G.I. Locks/NAVTAL locks-6 levers/Padlocks - 50mm with keys.

62. PVC hose pipes of sizes.

63. PVC sleeves of sizes.

64. PVC/Nylon sleeves (Sq.type) for writing cable core particulars

65. Raw wood varnish.

66. River sand (Coarse/Fine)

Page 32: MEMU Master

Page 28 of 33

67. Rosin core best quality 80/20.

68. Rubber gromites.

69. Solder soft high grade.

70. Split pins for all mechanical fittings.

71. Stone Jelly (20-25mm)

72. Tags for terminals.

73. Terminal lugs (copper) for all sizes of wires.

74. Turpentine

75. Wire netting arrangement for CLS units

76. Wood screws (Brass of sizes & nails of sizes)

77. Track feed resistance

78. ‘B” type choke

79. CT Box 20 pair

80. Thermo shrinkable jointing kit to Spe.:IRS,TC-77-2006{Rev.I}

Note: (i) All materials have to be supplied as per specification and drawings referred in chapter in chapter V, Volume.II.

(ii) The inspection of materials will be governed by para.19 of special conditions of Contract chapter-I, volume.II.

(iii) The dimensions of teakwood, hardwood, plywood and termite proof particles board are for finished products only.

**********

Page 33: MEMU Master

Page 29 of 33

Annexure-B2

Materials to be supplied by Railways

1. All types of plug-in type relays with plug boards, fixing bolts and nuts, and retaining clips except those supplied by the Contractor.

2. Annunciator

3. Apparatus cases – Full/ Half/ Quarter size

4. Boards without legends

5. Electrical detector

6. Gate warning equipment for LC gates

7. Offset bracket – small and large size

8. Control panel

9. Magneto telephone with cells for NI working

10. Rails of different lengths for fixing CT Boxes

11. SM Slide instrument

12. Illuminated diagram board

13. Underground cables except those supplied by the Contractor

14. Block instruments of required type

15. Colour light signal units

16. CLS pole 3.6 & 4.6 m length along with ladder and platform

17. PBT terminals and fuse blocks

18. Track lead junction box

Page 34: MEMU Master

Page 30 of 33

Chapter – IV

Name of Work: “Signalling and telecom arrangements in connection with inspection and stabling facilities for BG AC –MEMU at PGT”

Executive in-charge: XSTE/CN/PTJ

Stores depot from where the materials supplied by Railways are to be collected by the Contractor: Calicut/Palaghat/Podanur

Scope of work:

The scope of this work is broadly for the laying of signalling and telecommunication cables, erection of colour light signals, apparatus cases, wiring of shelf type/ plug-in type relays at apparatus cases, erection of cable termination rack and termination, erection and wiring of Control Panel, erection of relay rack and wiring of relays and provision of interconnections including wiring of spare contacts for data logger and terminating in the 50 way terminal boards, installation of secondary cells and power equipments, supply of Signalling equipments, releasing of existing Signalling gadgets, testing and commissioning the entire installation.

The station, where the works are to be carried out and the type of Signalling proposed are given below:

Sl.No. Name of station Type of Signalling1. Palaghat MACLS

Page 35: MEMU Master

Page 31 of 33

FORM No.I

STATEMENT OF DEVIATIONS

PROFORMA FOR STATEMENT OF DEVIATIONS

1. The following are the particulars of deviations from requirement of the Instructions to Tenderers, General & Special Conditions of Contract.

1.1 Instructions to Tenderers

CLAUSE DEVIATION REMARKS(INCLUDING JUSTIFICATION)

1.2 General Conditions of Contract.

CLAUSE DEVIATION REMARKS(INCLUDING JUSTIFICATION)

1.3 Special Conditions of Contract.

CLAUSE DEVIATION REMARKS(INCLUDING JUSTIFICATION)

2. The following are the particulars of deviations from requirement of the technical specifications:

(Separate statement for each specification)

CLAUSE DEVIATION REMARKS(INCLUDING JUSTIFICATION)

Note:

Where there is no deviation, the statement should be returned duly signed with an endorsement indicating “No deviations”.

*********

Page 36: MEMU Master

Page 32 of 33

FORM No.II

PROFORMA FOR FURNISHING EXPERIENCE CERTIFICATE

Name and address of DepartmentName and address of UnitName and Address of ContractorName and Type of WorkNature of work executed

Agreement No.& DateValue of AgreementOriginal CurrencyActual date of completion No. of extensions granted.

S.No. Nature of work (major sub work) Details of work (tick items which are applicable)

Value as per Agreement (*)

Value as per actual execution (based on payments made so far) (*)

Remarks

1. Cable laying and jointing.1.1 Signalling cable1.2 OFC1.3 Quad 4/61.4 PUF cable2. Signal Installation2.1 Mechanical/Relay Interlocking.2.2 MACLS/Mechanical MAUQ/LQ3. Track Circuiting 3.1 DC3.2 Axle Counter3.3 AFTC4. Point gear installation4.1 Point machine4.2 Mechanical FPL5. Interlocking of LC gate6. Interlocking of Siding point7. Installation of OFC indoor equipment8. Designing of Signalling circuits9. Whether any penalty is imposed10. General Remarks about performance(*) Details under relevant columns are to be filled up.

Place:Date: Signature & Seal of Authority issuing Certificate

Page 37: MEMU Master

Page 33 of 33

FORM No.III

FORMAT FOR SOLVENCY CERTIFICATE (Issued by Scheduled/Nationalised Banks)

This is to certify that …………………………………… (name of the tenderer) is a

customer in our bank maintaining …………………. Account (Nature of Account).

The party is financially sound and is considered respectable and solvent to the extent of

a sum of Rs. ……… (amount both in figures & words) as disclosed by the information and

records which are available with us.

Date: (Signature of the Manager)

Name of the Bank

**********

Page 38: MEMU Master

Page 1 of 113

VOLUME – II

CHAPTER-I SPECIAL CONDITIONS OF CONTRACT

CHAPTER-II MASTER LIST OF SOUTHERN RAILWAY S.O.R

CHAPTER-III TECHNICAL SPECIFICATION OF SIGNALLING WORKS

CHAPTER-IV LIST OF DRAWINGS

CHAPTER-V SPECIFICATIONS DRAWINGS OF SIGNALLING MATERIALS

Page 39: MEMU Master

Page 2 of 113

CHAPTER – I

SPECIAL CONDITIONS OF CONTRACT

LOCAL CONDITIONS

PROCUREMENT OF STORESMATERIALS TO BE SUPPLIED BY RAILWAYSEARNEST MONEY & SECURITY DEPOSITQUANTITYLANGUAGEADOPTION OF METRIC SYSTEMUSE OF TECHNICAL TERMS AND CONDITIONSDRAWINGS AND SPECIFICATIONSCLARIFICATION REQUIRED BY THE TENDERER/CONTRACTORDISCREPANCIES IN DRAWINGS AND OTHER DOCUMENTSSUPPLY OF ELECTRIC POWERINTERPRETATION OF THE CONDITIONSFUTURE DEVELOPMENTSMOBILISATION ADVANCEEXECUTION OF WORK & VARIATION IN QUANTITIESATTENDING TO DEFECTSMAINTENANCE/GUARANTEEINSPECTION OF MATERIALSFACILITIES FOR TEST & EXAMINATIONCERTIFICATE OF INSPECTION & APPROVALINSURANCETAXES-CENTRAL, STATE, LOCALPRICE/WAGE ESCALATION CLAUSESAFETY PROVISION FOR CARRYING OUT OF WORKSCONTRACTOR’s DRAWINGSSITE FACILITIESSTORAGE OF PETROLEUMSERVICE ROADSROYALTIES &PATENT RIGHTSCOMPLETION PERIODNIGHT WORKPAYMENTSDEDUCTION OF INCOME TAXINCOME TAX CLEARANCE CERTIFICATELABOUR LICENCESITE CLEARANCEFORCE MAJEURE CLAUSESETTLEMENT OF DISPUTE & ARBITRATION

--ssSss--

Page 40: MEMU Master

Page 3 of 113

VOLUME - II

CHAPTER I

SPECIAL CONDITIONS OF CONTRACT

GENERAL:

0.1 The Special Conditions Of Contract contained herein shall be supplemented to the “General Conditions of Contract”. In the event of any conflict or inconsistency between them, the Special Conditions of contract contained herein shall prevail.

0.2 The technical specifications of contract as incorporated in this contract document and drawings supplied with tender will form the basis for execution of the work.

0.3 The STANDARD GENERAL CONDITIONS OF THE CONTRACT [ CE - 493A] for Civil Engineering works of Southern Railway as amended upto date will form part of the contract Agreement and for all purposes be treated as if the same have been incorporated herein. The contractor shall obtain copy of the STANDARD GENERAL CONDITIONS OF CONTRACT FOR CIVIL ENGINEERING WORKS from the Chief Engineer, Southern Railway, Park Town, Chennai - 600 003, on production of Cash Receipt for the sum of Rs.40/- plus tax as leviable paid to the Chief Cashier, Southern Railway, Chennai - 600 003, or any Station Master on Southern Railway.

0.4 SCOPE OF WORK: Specified in chapter IV of Vol. I

1.0 LOCAL CONDITIONS:

1.1.1 NEED OF TENDERER FOR CAREFUL STUDY OF TENDER & SITE CONDITIONS:

The intending tenderer is advised to study tender papers, concerned specification and other instructions carefully. The tenderer shall inspect the proposed site of work and acquaint himself with the site conditions, working hours, layout of land, trees and shrubs that he will have to cut, type of strata likely to be met within the borrow pits, stacking space for materials, approach roads, pathways available etc. and all relevant items connected with execution for the work. No claim shall be entertained for the contractors making his own arrangements for approach roads from outside Railway Land and contractors will bear entire expenses such as road taxes, payment for right of way, etc. to outsiders and for constructions of approach roads, etc. The submission of tender shall be deemed to have been done after careful study and examination of the tender papers with full understanding of the implication thereof, unless otherwise, specifically commented upon by the tenderer in his quotation. Failure to adhere to any one or all these instructions may render his offer liable to be ignored without any reference.

1.1.2 No request for the change of price, or time schedule for completion of works shall be entertained after the offer is accepted by the Railways on account of any local condition or factor.

Page 41: MEMU Master

Page 4 of 113

1.2 CONSORTIUM BIDS:

1.2.1 In view of nature of work covered in the tender documents, it is anticipated that some of the intending bidders will pool their resources and experience to form consortia. In their own interest, the bidders who form such consortia are advised to investigate capabilities, availability of resources, experienced personnel, financial soundness, past experience and concurrent engagements of constituting partners.

1.2.2 Consortia of bidders, if any must clearly define role/scope of work of each partner/member. Further the legal agreement for a consortium must accompany the bid and should clearly define the leader of such a consortium who will be the prime contractor and will be responsible for timely completion of work as also during execution of work, if awarded, coordinate with Railways on behalf of the consortium, receive payments for the works executed and be liable for due performance of the contract in all respects.

1.2.3 Qualification documents, details etc., must however, be provided for each member firm complete in all respects strictly in requisite proforma.

1.2.4 A consortium formed will not be subject to alteration with regard to change in constituting firms and/or re-orientation of roles. Any changes, if proposed by consortium to take advantage of certain developments during evaluation stage will render the bid liable to be rejected. As all details are required to be furnished along with the bids and should be critically examined during evaluation of bids, it is imperative that such details should have been thoroughly examined as a safeguard against a possible disqualification of bids on these grounds.

1.2.5 All partners of the consortium shall be jointly and severally liable to the purchaser for the execution of the entire contract in accordance with its terms.

2.0 PROCUREMENT OF STORES :

2.1 For the execution of the works, the contractor shall procure items of materials inclusive of miscellaneous and consumable items of Stores as detailed in Vol.I

2.2 All signalling and telecom. materials to be supplied by the contractor shall be subject to inspection by Railway’s nominee as per Clause 19 of Special Conditions of Contract.

2.3 All the materials and equipments to be supplied and used for execution of work shall be to IRS wherever available, or to ISS, if IRS is not available. In case of materials for which neither IRS nor ISS is available, detailed specifications with drawing have to be supplied by the contractor for approval of the Railway Administration.

2.4 Materials not covered in RDSO’s approved list of items and to be supplied by the contractor shall be of the best quality and from manufacturers of reputed establishments. The contractor shall produce test, warranty certificates from the manufacturers and the pamphlets in four copies to the Railways. Materials covered under RDSO’s approved list of items should be procured from those firms approved by RDSO only.

Page 42: MEMU Master

Page 5 of 113

2.5 Materials to be supplied by the tenderer/contractor and by Railways for the execution of work are indicated in Vol.I separately. However, any particular item of materials not included in the contractor’s list or in the Railway’s list, but if still required to complete the works, the tenderer shall include such items of materials in his tender and quote for the same.

2.6 The specification for each material to be procured and used by the tenderer shall be as indicated against each item of material vide Chapter III of Vol.II

2.7 The contractor, will however have to procure all the tools and plants required for executing the labour portion of the work and before the actual commencement of the work, the contractor will satisfy the Railway engineer that he has procured all the necessary tools and plant required of good quality. The contractor shall engage his own labour and supervisor for the execution for work covered in the contract.

3. MATERIALS TO BE SUPPLIED BY RAILWAYS FOR THE EXECUTION OF THE WORK:

Materials as indicated in Annexure B-2 in Vol.I shall be supplied to the contractor by the Railways free of cost at the stores depot indicated therein. The rates quoted by the contractor should include the cost of transportation of materials supplied by the railways from the place of delivery to site of work..

4 EARNEST MONEY AND SECURITY DEPOSIT:

4.1 EARNEST MONEY: (Refer Volume III)

The tenderer shall deposit in favour of the Railway official, the required sum as indicated in the Tender Notice/Vol.I towards EMD as per the slab given below.

SLAB OF EARNEST MONEY:

Value of the tender EARNEST MONEY DEPOSIT

Upto Rs.5 Lakhs 2.5% ad-valorem subject to maximum of Rs.10,000/-

Rs.5 Lakhs to Rs.20 Lakhs 2.00% - maximum of Rs.20,000/-Rs.20 Lakhs to Rs.50 Lakhs 1.00% - maximum of Rs.35,000/-Above Rs.50 Lakhs 0.75% - maximum of Rs.50,000/-

Tenderer should submit, along with the tender, requisite Earnest money deposit and tenders unaccompanied by requisite Earnest Money deposit will be summarily rejected. Earnest Money in form of Guarantee Bonds shall not be accepted.

The Earnest Money may be furnished either in cash (paid to the Chief Cashier) or in any one of the following:

Page 43: MEMU Master

Page 6 of 113

4.1.1 Deposit receipts, Pay Orders, demand drafts: These forms of earnest Money could be either of the State Bank of India or of any of the Nationalised banks. No confirmatory advice from the reserve Bank of India will be necessary.

4.1.2 Deposit receipt executed by the Scheduled banks (other than the State Bank of India and the Nationalised Banks) approved by the Reserve Bank of India for this purpose. The Railways will not, however, accept deposit receipt without getting in writing the concurrence of the Reserve Bank of India.

4.1.3 The Earnest Money deposit in cash should be made to the Chief Cashier, Southern Railway, Park Town, Chennai-600 003 or to any Station Master of Southern Railway and cash receipt obtained from him should be furnished along with the tender.

LSEMD HOLDERS TO NOTE

THE TENDERERS ARE REQUIRED TO SUBMIT EARNEST MONEY DEPOSIT FOR THIS WORK SEPERATELY EVEN IF THEY ARE STANDING EARNEST MONEY DEPOSIT HOLDERS (LSEMD HOLDERS). TENDERS SUBMITTED WITHOUT EARNEST MONEY DEPOSIT WILL BE SUMMARILY REJECTED EVEN IF THE TENDERER HAPPENS TO BE A STANDING EARNEST MONEY DEPOSIT HOLDER (LSEMD HOLDER).

4.2 Tenderer shall hold the offer open for a period as indicated in Vol.I from the date fixed for opening the same, it being understood that the tender documents have been issued to the tenderer and the tenderer has been permitted to tender in consideration of the stipulation on his part that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof, in any manner not acceptable to the Chief Signal & Telecommunication Engineer (Construction), Southern Railway, Egmore, Chennai-600 008

NOTE: IN CASE THE TENDERER WITHDRAWS HIS OFFER WITHIN THE VALIDITY DATES OF HIS OFFER, THE FULL EARNEST MONEY SHALL BE FORFEITED.

4.3 The Earnest Money including the amount taken as Security deposit for the due performance of the stipulation to keep the offer open till the date specified in the tender will be refunded to the unsuccessful tenderers within a reasonable time. The Earnest Money deposited by the successful tenderer will be retained towards the Security deposit for the due and faithful fulfillment of the contract but shall be forfeited if the contractor fails to execute the Agreement Bond or start the work within the reasonable time (to be determined by the Engineer-in-charge) after notification of the acceptance of his tender. Railway shall not be responsible for any loss or depreciation that may happen to the Security for the due performance of the stipulation to keep the offer open for the period specified above, nor be liable to pay interest thereon.

4.4 SECURITY DEPOSIT: (Refer Volume –III)

4.4.1 After awarding the contract, the successful tenderer has to pay the Security deposit as per the rates shown in the table below:

Page 44: MEMU Master

Page 7 of 113

Value of the contract SECURITY DEPOSITUpto Rs.1 Lakh 10% of the contract valueRs.1 Lakhs to Rs.2 Lakhs 10% of the first Rs.1 Lakh and 7 .5% of the balanceRs.2 Lakhs to Rs.2 Crores 10% of the first Rs.1 Lakh, 7.5% for the next Rs.1 Lakh

& 5% for the balance subject to a maximum of Rs.3 Lakhs

Above Rs.2 Crores 5% of the contract value (Not applicable) Refer Volume – III.

4.4.2 The total security deposit recoverable from the contractor including the amount of Earnest Money deposited with the tender as given in Vol.I will not exceed the Security amount recoverable at the rate mentioned above. Contractor may either deposit the balance amount in cash or in the form of Government Securities or the same can be deducted if he so desires from his “on account” bill at the rate of 10% of the value of the said bills until the sum of deduction plus the amount of Earnest Money deposited taken together equal to the requisite amount of Security deposit.

4.4.3 The Tenderer/Contractor shall sign against the mode chosen by him for furnishing security deposit and strike off other options. The discretion of accepting the chosen mode will however be with the Railway.

(a) In cash in Indian Currency to be paid to the Chief Cashier, Southern Railway, Park Town, Chennai- 600 003

(OR)(b) Approved Banker’s bond from any Nationalised Bank as per specimen obtainable

from the office of the Chief Signal & Telecommunication Engineer, Construction, Southern Railway, Park Town and executed on stamp paper of sufficient value.

(OR)

(c) Deposit receipts of approved bankers for the required amount and period. (OR) (d) Government of India Securities at market value or National Savings Certificate or

Treasury Savings Certificate at 5% below par. (OR) (e) Recovery at 10% from each of the running bills of the contractor. (OR) (f) Twelve year National Defence Certificate/or Ten Year Defence bonds at their

surrender value. (OR)(g) Railway bonds issued by Indian Railway Finance Corporation, New Delhi.

Signature of Tenderer/Contractor.

(NOTE): In the case of Government Securities a margin shall be allowed for possible fluctuations in the market value and the tenderers will be called upon to mode good any deficiency in this respect, if necessary. No interest will be payable on the security deposit but Government Security deposited in terms of those mentioned above will be repayable with interest accrued thereon if those carry any interest.

5 QUANTITY:

Page 45: MEMU Master

Page 8 of 113

It will not be binding on the Railway Administration to give the works at all the stations or all the items of work at a station on contract and the Railway Administration may decide to do any or all the items of supply or work involved at a station in the above list departmentally without assigning any reason for the same. Also, the Railway Administration may give the work at different stations to different tenderers or different items of work at the same station to different tenderers without assigning any reason for the same.

6 LANGUAGE:

All documents to be submitted in connection with this contract shall be written in ENGLISH.

7 ADOPTION OF METRIC SYSTEM:-

Dimensions, weights etc., shall be quoted in Metric system.

8 USE OF TECHNICAL TERMS AND CONDITIONS, DRAWINGS AND SPECIFICATIONS:-

Definition of technical terms and symbols used in circuits shall be as per Indian Standard Specifications and where such specifications are not available, they should be of British Standard Specification.

9 DRAWING AND SPECIFICATIONS:-

Copies of the IRS drawings and specifications according to which the works have to be executed, have to be obtained by the Tenderer direct from the Director General, RDSO, S&T Wing, Alambagh, Lucknow-5.

10 CLARIFICATION REQUIRED BY THE TENDERER/CONTRACTOR:-

Any clarification required by the Contractor may be obtained from the Chief Signal & Telecommunication Engineer (Construction), Southern Railway, Egmore, Chennai-600 008. After award of contract, the field executive who is incharge of the work as indicated in Vol.I may be referred.

11 DISCREPANCIES IN DRAWINGS AND OTHER DOCUMENTS:

The tenderer shall carry out at his expense any alteration of the work due to any discrepancies, errors or omissions in the drawings or other particulars submitted by him. Any approval given by the Railway for this purpose shall in no way absolve the contractor from any or all responsibilities for the correct function of the equipment. In this regard, the sole responsibility rests with the contractor in all respect. Any fittings or accessories which may not be specifically mentioned in the specification of tender documents or the letter of acceptance of the tender or the agreement executed thereof but which are usual or necessary as per normal Signal Engineering practice are to be provided by the contractor without extra charge so that the plant is complete in all respects.

Page 46: MEMU Master

Page 9 of 113

12 SUPPLY OF ELECTRIC POWER:

The Railway shall provide single phase LT power supply for soldering, lighting and minor drilling works, wherever electric supply is available. The charges for electric consumption at site in connection with the erection, have to be borne by the contractor at the rate specified by the Railway.

13 INTERPRETATION OF THE CONDITIONS:

With his tender the tenderer shall submit a note stating his interpretation of the specification wherever he desires to clarify any aspects of his offer. In respect of matters or issues not covered by this note, it shall be assumed that the quotation conforms to the specifications laid down in the tender documents. The interpretation of the Railway where such interpretation found necessary shall be final and binding on the tenderer.

14 FUTURE DEVELOPMENTS:

If during the period between the date of tender and signing of the contract, there have been any developments resulting in improvements or advancements, technical or mechanical in regard to the equipment to be installed, its designs or fabrications, the tenderer shall make available to the Railway all information pertaining to the same. In the light of such information the Railway may modify the orders to take advantage of these developments on the basis of mutually agreed terms.

15 MOBILISATION ADVANCE(Only if the estimated value of the work exceeds Rs.1 Crore):

15.1 The contractor may be granted a recoverable interest bearing mobilization advance upto 10% of the Contract Value provided he specifically applies for it while Tendering. If the Tenderer fails to apply specifically for mobilization advance while giving his offer in the tendering stage in cases where grant of mobilization advance is permissible, no subsequent requests from him for grant of this advance will be entertained. The rate of interest is 18% per annum.

15.2 The advance will be granted in two instalments, viz., 5% of the contract value on signing of the Contract Agreement and the balance 5% after mobilization of site establishment, setting up Offices, bringing in equipments and actual commencing of works. Each instalment will be released on submission of an irrevocable Guarantee Bond from a Nationalised Bank in a form acceptable to the Railways for the amount of the instalment together with interest charges calculated to the end of the Contract period. The Tenderer who seeks mobilisation advance should be specific about the course of action proposed to be followed in producing Guarantee Bonds in satisfaction of Railways. Each Guarantee bond should be for not less than Rs. One Lakh. These Guarantee Bonds shall be returned as and when the value of the advance and interest is recovered from the running bills.

15.3 The recovery of the advance and interest thereupon will be made through the `On Account’ bills, pro rata commencing when the value of the work executed under the contract reaches 15% of the contract value and completed when the value of the work executed under the contract reaches 85% of the contract value, or the assessed value of the work whichever is less.

Page 47: MEMU Master

Page 10 of 113

15.4 Interest will be recoverd on the advance outstanduing for the period commencing from the date of payment of advance till date of particular on account bill(through which recovery of principal is effected) and adjusted fully against such on acount bills along with pro-rata principal recovery. In the event of any shortfall the same will be carried forward to the next on account bill and will attract interest at 18%.

15.5 The Bank Guarantee for advance should clearly cover principal plus interest.NOTE: The various instruments as listed for Performance guarantee will also be acceptable for Mobilization Advance.

16 EXECUTION OF WORK:

16.1 Materials required for installation at the station shall be made available to the contractor at the Railway’s depot as indicated in Vol.I and the contractor shall take delivery of such materials at this depot and make his own arrangements for the transport of the materials at the works spot at his own cost. The contractor shall be responsible for checking before taking delivery that all the materials given to them are in good condition. The contractor shall be responsible for undertaking repairs if any, to crates, cable drums packing cases, etc. for safe transport of materials from Railway’s specified depot to the site of work. The contractor should also undertake necessary repairs to crates drums etc. in respect of unused materials required to be returned to the purchaser. No extra payment will be made on this account. Extra care should be taken in the transportation of sophisticated Electrical and Electronic equipments like relays, SSI equipment, power equipments, etc. to prevent from damage during transit. Further, these equipments should be stored in a covered place to protect from heat, dust, water, etc. These equipments should be installed and brought in use before the expiry of the shelf life.

16.2 The rates quoted by the Contractor in the schedule shall be inclusive of all the charges viz., labour and transportation of materials including loading, unloading and shifting from the Stores depot to work spot, etc. and all the materials to be supplied by them as indicated in Vol.I. No other charges shall be payable by the Railway.

16.3 The materials that shall be handed over to the Contractor at any time for execution of the work shall depend upon the particular item of work in the Schedule to be done at a particular time and also the progress of work. The contractor shall furnish an indemnity bond for a sum equal to the cost of materials proposed to be taken by him. The quantity of materials that shall be given by the Railway at a time shall not exceed the value of the indemnity bond that is furnished by the contractor.

16.4 The materials issued by the Railways shall be used solely and economically for the purpose of the works covered under this contract only. The materials shall be used in such quantities and manner as indicated in the relevant specifications or drawings or as approved by the Engineer whose decision thereon shall be final. Waste or damage to such materials in any manner shall not be caused by the Contractor.

16.5 The contractor will be liable to render full accountal for all the materials issued by the Railway. If any quantity of Railway materials is consumed in excess or wasted or damaged or lost or otherwise not satisfactorily accounted for, recovery shall be made from the contractor at the book rate or last purchase rate or the prevailing market rate whichever is higher plus 5% on account of initial freight, 2% on account of incidental charges together with supervision charges at 12.5% on the total cost inclusive of materials, freight

Page 48: MEMU Master

Page 11 of 113

and incidental charges. Freight between the Railway sources of supply and the site of work shall be to the contractor’s account.

16.6 If at any time, any material which the contractor would normally have to arrange for himself for executing the works, is supplied by the Railways, either at the contractor’s request or suo-moto in order to prevent possible delay in the execution of the work due to contractor’s inability to make adequate arrangements for the supply thereof or otherwise such materials will be made available to the contractor in the Railways Stores as indicated in Vol. I . All handling thereof will be the contractor’s responsibility. Recovery of the cost of such supply materials will be made from the contractor’s bills as per extant rules of the Railway.

16.7 VARIATION IN QUANTITIES :

16.7.1 The drawings referred to in the list of plans, if any, are intended only to give a rough and general idea of the location and rough details of work to be done. No claim whatsoever will be admissible in respect of any alteration/addition/change in the type of works.

16.7.2 The quantities of various items given in the schedules for the works to be executed are only approximate and are only for the guidance of the contractor. As far as possible, they have been assessed correctly but are likely to vary during the execution of the work. The contractor’s attention is drawn to Clause 42 of the General Conditions of Contract dealing with variation in quantities.

16.7.3 For increase upto 25% of the quantities indicated in schedule, the contractor shall not be entitled for any compensation and will be paid for such increase in the quantities at the agreement rate.

16.7.4 In the event of reduction in the quantities to be executed for any reason whatsoever, the contractor shall not be entitled for any compensation but shall be paid only for the actual quantity of work done, at the agreemental rates.

16.7.5 When the gross value of the work to be executed is likely to increase in excess of 25% of the original value of the agreement, the contractor should notify the Engineer in-charge atleast THIRTY DAYS before such necessity arises.

16.7.6 When the operation of the quantities results in the agreement value exceeding by 25% to 50%, for the first 15% increase, the payment will be reduced straightaway by 2% in the incremental value of the agreement and for the next 10% increase in the value the payment will be reduced straightaway by an additional reduction of 2% in the further incremental value of the agreement.

16.7.7 Notwithstanding the above adhoc reduction, Railway reserves the right to refix the rates, by mutual consent, of those items in the schedule, where the quantities have exceeded by 25% of the agreemental quantities.

16.7.8 Execution of quantities beyond +50% of overall value shall not be generally permitted. The rate for quantities in excess of 50% of the items shall be decided between the Railway and the contractor in advance of execution of the quantities involved, if in the opinion of the Railway, such quantities are also to be executed by the same contractor. In the event

Page 49: MEMU Master

Page 12 of 113

of mutually agreed rate not being arrived at, the Railway shall be entitled to execute the excess work by other means and the contractor shall have no claims on this account.

16.7.9 VITIATION CLAUSE:

In the event of Vitiation occurring due to increase or decrease in quantities, among the first, second and third lowest valid tenderers, the vitiation shall be to contractor’s account. The total value of the work done shall be calculated at the rate offered by those tenderers and the amount payable shall be limited to the lowest aggregate value as worked out. Vitiation as above shall be worked out as a whole for agreement including all variations in quantities.

16.10 The contractor shall give written notice of 15 days to the Engineer before commencement of any particular item of work, at any station so that the engineer can make adequate arrangements for supply of the materials required and for supervising that work. The contractor will programme his work in such a manner so as not to interfere in the working and movement of trains. No extra payment shall be allowed on this account and for taking any precaution or wastage of contractor's labour, time, etc. due to train working.

16.11 RETURN OF EMPTY CABLE DRUM/RELEASED MATERIALS:

The contractor has to return any cut pieces of cables, wires, etc., that may be left out and surplus materials from the drums and other packing materials that might have been handed over to him. No extra payment will be made for this and the unit price quoted against the various items should include this work also. The surplus materials have to be handed over to the Stores of the Engineer-in-Charge of the work as mentioned in Vol.I. Failure on the part of the contractor to return the empty cable drums will entail the contractor to pay the charges as indicated against various sizes of empty cable drums at the time of final payment, indicated as hereunder:

16.11.1 Empty Signalling cable drums upto 12 Core capacity Rs.100/- each (Rupees One Hundred only).

16.11.2 Empty Signalling cable drums above 12 Core and upto 31 Core capacity and Telecommunication cable drums Rs.150/- each (Rupees One Hundred and Fifty only).

16.11.3 Empty Power cable drum Rs.125/- each (Rupees One Hundred and twenty Five only).

16.12 The contractor shall take proper written acknowledgement from the Engineers Representative for all the materials returned by him.

16.13 All tools that are required by the contractor for the purpose of transportation of the materials, digging, concreting and erection, wiring and painting works shall be brought by the contractor himself. This shall include spare parts, fuel and consumable and miscellaneous stores-details furnished in Vol.I .The rates quoted by the contractor shall be deemed to be inclusive of all charges for such items and inclusive of labour required to ensure efficient and methodical execution of work.

16.14 RATES DURING NEGOTIATION:

Page 50: MEMU Master

Page 13 of 113

The tenderer shall not increase his quoted rates in case the Railway Administration negotiates for reduction of rates, such a negotiation shall not amount to cancellation or withdrawal of the original offer and the rates originally quoted will be binding on the tenderer.

16.15 NEGOTIATION OF RATES FOR ITEMS NOT MENTIONED IN SCHEDULE :

If during the execution of the work the contractor is called upon to carry out any new item of work not included in accepted Schedule, if any, it should not be executed before a rate has been agreed to by the Railways in the manner as indicated in General Conditions of Contract and Instructions for tenderers.

16.16 INSPECTION OF FOUNDATION :

Before casting of foundation, the contractor’s representative and the Engineer’s representative shall jointly inspect the quality and depth of pits, quality of bricks, concrete mixture, etc. and ensure compliance with the Drawings and Specifications.

16.17 INSPECTION OF TRENCHES, CHASES &FILLINGS:

Before the cable are actually laid, the Contractor’s representative and the Engineer’s representative shall jointly inspect the quality and depth of trenches, chases, for temped filling. The measurements for all these items will be suitably recorded by the Engineer’s representative who will permit the laying of cables after issuing the certificate in Form 8 that the above work have been done as required by the specifications.

16.18 Due care shall be exercised to ensure that while doing the dismantling work, no released material is damaged by the contractor. Proper account is to be taken at the field jointly with Railway Representative before releasing. After releasing the materials, the released materials can be stocked neatly at a place indicated by Railways (preferably near road approach) at the station. The released unwanted materials may be watched and guarded till the same is auctioned. The Contractor shall take proper written acknowledgement from the Engineer’s Representative for all the materials returned by him.

16.19 Following field Books of supervisors shall be maintained:

i) Site Order Book – For all instructions issued to the contractor or his representative with their replies.

ii) Note Book – For recording progress of work, satisfactory or unsatisfactory working of contractors, matters for reference to supervisors, dates of all inspection, details on various points considered worthy of remarks.

These books are considered as official records to be produced whenever required by the supervisors.

16.20 RECEIPT OF MATERIALS FROM CONTRACTOR:

16.20.1 As soon as the materials are accepted by the Railway from the contractor, DMTR entries are to be made immediately. While taking materials from the contractor, delivery challans

Page 51: MEMU Master

Page 14 of 113

issued by the firm who has sold the materials to the contractor/trader and inspection certificate shall be insisted upon.

16.20.2 Fabricated items which are to be supplied by the contractor are to be checked thoroughly with the drawings regarding quality of the materials, gauge dimensions, etc. as per the schedule. Wherever any material is received from field/contractor, the detailed nomenclature shall be entered in the DMTR. In case of an equipment, the details of manufacturer’s name, year of manufacture, RDSO Test Certificate No., Serial No., Contractor’s name and Agreement No. and place of installation shall be mentioned both in the DMTR and the ledgers.

16.20.3 Materials are normally to be delivered at designated Stores by the contractor. If they are delivered at site due to logistics/exigencies, the supervisor/officer receiving such materials (after verification of due inspection) shall arrange for necessary entries in the designated Stores’ DMTR within a week.

16.20.4 Issue of materials to the contractor:

Whenever any material is issued to the contractor for carrying out a work, the particulars are to be entered in the DMTR.

16.21 INSPECTION OF WORKS:

16.21.1 The Engineer or his representative may inspect and test the various portions of the work at all stages and shall have full power to reject all or any portion of the work that he may consider to be defective or inferior in quality of materials workmanship or design in comparison to what is called for in the specification. In the event of rejection of any work already executed and not in accordance with specification as in this tender and/or as determined by the Engineer or which the Contractor has been apprised, the contractor shall carry out alterations/ replacements to such works to the satisfaction of the Engineer for which no additional expenses will be borne by the Railway.

16.21.2 The contractor shall submit detailed test procedure for each equipment, sub-system and system as a whole to the Railways. The Railways shall discuss with the contractor and modify the test procedure as may be required to ensure that the requirement of tender specifications are complied. The finalized test procedure shall, only, act as a broad guideline and Railway shall be free to carry out any other tests that may be considered essential. The test procedure shall give details of all equipment, test and measuring instruments required to perform the tests which shall be provided by the contractor free of cost.

17 ATTENDING TO DEFECTS:

The contractor shall rectify defects that may arise in the work executed for a period of three months after completion of work, such defects being due to bad workmanship on the part of the contractor or otherwise. Should any dispute arise so as to correctness of the defect pointed out, the Engineer’s decision in this regard is final and binding.

Page 52: MEMU Master

Page 15 of 113

18 MAINTENANCE/GUARANTEE: 18.1 The contractor shall guarantee satisfactory working of the installation erected by him for a

period of twelve calendar months being from date of issue of completion certificate as stated in Clause 47 of the General Conditions of the Contract.

18.2 During this period, the contractor shall keep all materials, tools and other requisite equipment readily available and shall carry out at his own expense all modification, additions or substitutions that may be considered necessary for satisfactory working of the contract work or equipments. Final decision in respect of unsatisfactory working of the contract work or equipments or faulty use of designs or workmanship, etc., shall rest with the Chief Signal & Telecommunication Engineer (Construction), Southern Railway, Egmore,Chennai-600008 and the same shall be binding on the contractor.

18.3 During the aforesaid period of Guarantee, the contractor shall be liable at his own cost for all repairs or replacements of any parts that may be found defective in the contract work or equipment irrespective of whether any defect arise as a result of faulty design, materials, workmanship, installation or otherwise provided that such defective parts are not repairable at site are promptly removed to the contractor’s works, for repairs if so replaced by him by new ones in order to remove the defects at his own expenses. In case minor repairs are carried out by the Railway at site, the cost of such repairs plus departmental charges shall be borne by the contractor.

18.4 In support of this guarantee the contractor shall furnish a Bank Guarantee for the value of Security deposit of the contract from a Nationalised Bank fully indemnifying the Railway against all losses incurred by the Railway during the guarantee period. If the security deposit is furnished in the form of Bank Guarantee as prescribed in Clause 16 of the General Conditions of Contract, the same Bank Guarantee shall be valid to cover not only the whole period of supply and installation of the equipment on order but also to cover a period of guarantee for twelve months from the date of issue of completion certificate. If the security deposit is paid in cash or in the form of Government Securities, the same shall be paid to the contractor after the expiration of the period of maintenance as specified above and after the contractor furnished Bank Guarantee for the value of Security Deposit of the contract amount to cover the period of Guarantee for twelve months from the date of issue of completion certificate.

19 INSPECTION OF MATERIALS:

19.1 Materials to be supplied by Contractor shall be of best quality and shall conform to the relevant specifications, Designs and Drawings. The materials shall be procured by the Contractor/s from manufacturers of repute or their authorised dealers as approved by the Engineer-in-Charge.

19.2 The Contractor/s may be required to produce test certificate from the Manufacturer, wherever called for by the Engineer-in-Charge.

19.3 The contractor should procure signalling/telecom items which appear in the RDSO approved list normally from the Part I suppliers. The contractor shall take prior approval of the Railways before placing orders on the firms. In case, there are no firms in Part-I list. Prior approval of Railways should be obtained before placing order on Part-II firms.

Page 53: MEMU Master

Page 16 of 113

19.4 The items which are included in the list of RDSO approved suppliers (Electrical Signalling items) shall be inspected by RDSO and Mechanical Signalling items shall be inspected by RITES except petty items which shall be inspected by representative of the Engineer-in-Charge. In case the value of Electrical sigg. items is less than Rs.One Lakh, the inspection shall be carried out by RITES. In exceptional cases, the consignee inspection shall be carried out by an Officer nominated by the Engineer-in-charge of the work. Even in these cases, the materials shall be procured from RDSO approved sources.

19.5 The following critical items will continue to be inspected by RDSO irrespective of its

value:

(a) All types of signalling relays(b) Block instruments(c) Axle Counter equipments(d) Signal machines(e) Point machines(f) Colour Light Signal transformers(g) Electrical signal lamps(h) Voltage stabilizers and other power supply equipment(i) Electric signal reversers(j) Signal roundels and lenses(k) Electric lever lock and circuit controller(l) Circuit controller(m) Electric key transmitter(n) Terminal blocks (PBT type)(o) Electric Point and lock detector

19.6 All materials that are not covered under specification, designs and drawings of RDSO, Railway Board, etc., will be procured by the Contractor from the manufacturers of repute/their authorized dealers, after the approval of the Engineer-in-charge.

19.7 Materials to be supplied by the contractor shall be put up for inspection of Engineer or his representative for checking its quality/suitability before they are finally used/installed by the Contractor and necessary inspection certificate to be obtained. The Contractor shall therefore arrange to get the material inspected in advance, preferably in bulk and not in piece-meal. The Contractor shall give the Railway 10(Ten) days notice, when the materials are ready for inspection.

19.8 The inspection charges levied by RDSO/RITES will be on Railway’s account.

19.9 All materials to be supplied by contractor should be offered by him/them for RDSO’s/RITES inspection, well in time, so as not to delay the progress of work at any stage at any of the stations in any way on this account.

19.10 If required, the Contractor shall provide at point of production, apparatus and labour for making required tests under the supervision of the Railway. Tests may be made either at point of production, on samples submitted or at the destination.

Page 54: MEMU Master

Page 17 of 113

20 FACILITIES FOR TEST & EXAMINATION:

The contractor shall provide, without any extra charges, all materials, equipments, tools and labour of every kind which the RDSO/RITES or their nominee may consider necessary for any tests and examinations which they or their nominee shall require to be made on the contractor's premises and shall pay all cost attendant there upon. The contractor shall also provide and deliver free of charge at such places as the RDSO/RITES or their nominee may nominate such materials as they or their nominee may require for the independent testing organisation. The cost of any such tests will be defrayed by the Railways unless it is stated in the specification that it is to be paid by the Contractor.

21 CERTIFICATE OF INSPECTION AND APPROVAL:

21.1 No stores will be considered ready for delivery until RDSO/RITES or their inspecting officer nominated by them have certified in writing that the material has been inspected and approved by them.

21.2 Facilities must be provided by the contractor to the Railway or their nominee for inspection of the stores, equipments and structures at all stages of their assembly, manufacture and fabrication.

22 INSURANCE:-

22.1 The contractor shall take out and keep in force a policy or policies of insurance against all liabilities of the Contractor or the Railway at common law or under any statute in respect of accidents to persons who shall be employed by the Contractor in or about the site or the Contractor’s Office for the purpose of carrying out the contract works on the site. The contractor shall take about and keep in force a policy or policies of Insurance against all recognized risks to their office accommodation and storage for which he is liable. Such insurance shall in all respects be subject to the approval of the Railway.

22.2 The Contractor shall take out and keep in force a policy or policies or insurance for all materials handed over to him irrespective of whether used up in the portion of work already done or kept for use for the balance portion of the work until such works are handed over to the Railway. For this purpose, the works are deemed to have been handed over when final acceptance certificate is issued by the Engineer after the completion of all the acceptance test to be conducted on the works. The contractor shall not be liable for losses/damages to the materials either used up in the portion of work done or the materials kept for use at site, in consequence of mutiny or other similar causes over which the contractor has no control and which cannot be insured. Such losses or damages shall be the liability of the Railway.

22.3 The Contractor should, however, insure the stores brought to site, against risks in consequence of war and invasion, as required under the Emergency Risk(Good) Insurance Act in force.

22.4 The Contractor shall take out all insurance covers in connection with this contract with the General Insurance Corporation of India.

23 TAXES – CENTRAL, STATE, LOCAL:-

Page 55: MEMU Master

Page 18 of 113

23.1 This tender falls under Civil Works Contract / All other works contract which attracts specific percentage of sales tax under the concerned act. Sales Tax on the Works Contracts, as applicable in terms of the concerned state Government Sales Tax Act, as amended from time to time shall be deducted from the running bills of the e contractors for payment to the State Government. The Railway administration will give a certificate towards the tax deducted at source to enable them to file Sales Tax Return before the concerned authorities. No refunds of Sales tax deducted at source will be made by Railway. The Sales Tax elements that might have gone into prices of various raw materials used by the contractor in the works concerned, distinct from the Sales Tax deducted as above, will also not be reimbursed by the Railway. The percentage of tax to be recovered shall be indicated by the Bill Passing Units.

23.2 The tenderer should quote prices inclusive of Sales Tax, Octroi and all other levies and duties imposed by the State and Central Governments and other miscellaneous expenses unless otherwise authorised by the concerned State Government Sales Tax Authorities.

23.3 No foreign exchange and/or import license will be released/provided to the contractor in connection with this contract.

23.4 Form of certificate for making Government purchases (Form ‘D’) will be issued for all supply items of the contract, if specifically demanded by the tenderer, while submitting the tender.

24 PRICE/WAGE VARIATION CLAUSE:

Railway is not agreeable to any price/wage escalation clause.

25 SAFETY PROVISION FOR CARRYING OUT WORKS:-

PROTECTION TO WORKS:-

25.1 The contractor shall take all precautionary measures in order to ensure protection of his own personnel moving about or working on the Railway premises and shall have to conform to the rules and regulations of the Southern Railways. While the work under the contract is in progress, if and when, there is likely to be any danger to the persons employed by the contractor due to running of traffic or while working on Railway premises, the Contractor shall apply in writing to the Railway to provide flagmen or look-out men for protection. The Railway will, however, decide as to whether it is necessary to post such flagmen and look-out men for various types of works and also the number of such men required to protect the contractor’s staff working at site. The flagmen and look-out men will be Railway Servants and no expenses on this account will be recovered from the contractor.

25.2 The contractor’s employees and workers shall not for any reason operate any appliances or installations of the Railway concerning the Safety of train movements, but they should whenever necessary notify to the appropriate Railway staff who will then take necessary steps.

Page 56: MEMU Master

Page 19 of 113

25.3 Suitable ladders for climbing the posts and slings for supporting men on the post shall be used. Ropes as required shall be used for erection of the poles. The size of the rope shall be adequate. The contractor shall take necessary precautions for working near the power lines. If at any time the Railways find the safety arrangements are inadequate or insufficient, the contractor shall take immediate corrective action as directed by the Railway’s representative at site. Any direction in the matter shall in no way absolve the contractor of his sole responsibility to adopt safe working methods.

25.4 Necessary personal safety equipment as considered adequate by the Engineer-in-charge should be kept available for the use of the persons employed at the site and maintained in a condition suitable for immediate use and the contractor should take adequate steps to ensure proper use of equipment by those concerned.

25.5 No electrical apparatus which is liable to be a source of danger, used by the operator shall

remain electrically charged.

25.6 Suitable face masks should be supplied for use by the workers when paint is applied in the form of spray.

25.7 BLASTING OF ROCKS:

Blasting of rocks for foundation work shall be done only after due notice is given to the Railway’s time/s and dates for blasting operations agreed to by the Railway. Blasting, if required to be done in vicinity of the track shall not be undertaken until the Railway flagmen on duty, take necessary steps to protect trains and the track, to be protected by the contractor against damage by blasted rocks. The contractor shall follow detailed instructions which will be issued to him regarding blasting operations in the vicinity of tracks.

25.8 SAFETY FOR PASSENGER WHILE WORKING BY CONTRACTOR IN STATION LIMITS:

While working within station limits especially on passenger platforms, the contractor shall ensure that at all times sufficient space is left for free movement of passenger traffic. He must cover and or barricade the excavations carried out in such areas and continue to maintain these, till the work is completed with a view to avoid any accident of public or to a Railway staff.

25.9 AVOIDING INFRINGEMENT OF INDIAN RAILWAY ACT:

The works must be carried out most carefully without any infringement of the Indian Railway Act or the General and subsidiary rules in force on the Railway, in such a way that they do not hinder Railway operation nor affect the proper functioning of or damage any Railway equipment, structure or rolling stock except as agreed to by the Railway, provided that all damage and disfiguration caused by the contractor to any Railway or Public properly must be made good by the contractor at his own expenses failing which cost of such repairs shall be recovered from the contractor.

25.10 RECOVERY OF COST OF SAFETY OF TRACK AFFECTED:

Page 57: MEMU Master

Page 20 of 113

If safety of track etc., is affected, as a consequence of works undertaken by the contractor, the contractor shall take immediate steps to restore normal conditions. In case of delay the Railway shall, after giving due notice to the contractor, in writing take necessary steps and recover the cost from the contractor.

25.11 No work on the points, track circuits, equipments involving working signalling gears, internal wiring, cable termination, etc., should be done unless and until contractor’s technical supervisors are present at site.

26 CONTRACTOR’s DRAWINGS:

26.1 Any work done by the contractor prior to the approval of the contractor’s drawings will be done at the risk of the contractor unless previously authorized in writing by the Railway.

26.2 The tenderer shall be responsible for the correctness of the drawings furnished by him. The contractor shall carryout any alterations of the works due to any discrepancies, errors or omissions in the drawings or other particulars, submitted by him. Any approval given by the Railway for this purpose shall in no way absolve the tenderer from full responsibility for the execution of the contract in all respects.

26.3 After the contract is awarded, the contractor shall furnish to the Railway as required, prints of contractor’s drawings that form an essential part thereof. No change shall be made in any approved drawings without the written consent of the Railways.

26.4 After completion of the execution of the contracts, the contractor shall submit to the Railway all corrected R.P. Film/cloth tracings of drawings furnished by him and six sets of copies of final drawings for each stations.

26.5 Not withstanding the fact the Railway might have approved or the contractor’s design, drawings and specifications the contractor is responsible for the correctness of the entire scheme as a whole and its satisfactory performance to the specifications as laid down by the Railway. The Railway’s responsibility is only for the correctness of the signaling plans.

26.6 In the event of any breach of the aforesaid conditions, the contractor shall in addition to throwing himself open to action for contravention of terms of the agreement and or for original breach of trust, be liable to account to Government for all moneys, advances or profits resulting or which in the usual course would have resulted by reason of such breach.

27 SITE FACILITIES:

27.1 The quoted rates would be deemed to include charges for any and all site facilities that are considered necessary for the execution of the work unless otherwise indicated in the contract. In this connection specific attention is drawn to stipulation in clause 6 of the General Conditions of the Contract and intending tenderer are advised to acquaint themselves well with site conditions.

Page 58: MEMU Master

Page 21 of 113

27.2 The land that can be made available by the Railway free of charge for the use of the contractor or his field office, stacking yard, stores depot and workshops may be ascertained by inspection at site. No assurances can be given regarding the vulnerability of such land to flooding during high floods. The Railways undertakes no responsibility or liability in this regard.

27.3 Land required for contractor’s labour camps, staff colony or for any purposes other than those mentioned in ParaNo.27.2 will have to be arranged by the contractor at his own cost.

28 STORAGE OF PETROLEUM:

No petroleum, spirit within the meaning of the Indian petroleum Act shall be stored at site or adjacent land until the approval of the Railway and necessary license under the Act has been obtained by the contractor.

29 SERVICE ROADS:

The contractor will be permitted to make use of existing service roads free of cost. New Service roads, required by the Contractor in connection with the work whether within or outside Railway Land for carriage of materials or for other purpose whatsoever, will have to be constructed and maintained by the contractor at his own cost. For the purpose of construction of service roads on Railway land, permission will be given to the contractor at Railway’s discretion free of any charges. If any land other than Railway’s land is necessary to be acquired or entered upon for the purpose, then such land acquisition or permission to enter upon the land will have to be arranged for by the contractor at his own cost. The contractor will indemnify the Railway against claims for any damages whatsoever on this account. Railway however, reserves the right to make use of such serviceable roads without any charges.

30 ROYALTIES AND PATENT RIGHTS:-

The Contractor shall defray the cost of all royalties, fees and other payments in respect of patents, patent rights and licenses which may be payable to patentee, licensee or other person or corporation and shall obtain all necessary licenses. In case of any breach (whether willfully or inadvertently) by the contractor on this provision, the contractor shall indemnify the Railway and their office servants, representatives, against all claims, proceedings, damages, cost, charges, expenses, loss and liability which they or any of them may sustain, incur or be put to by reasons or in subsequence directly or indirectly or any such breach and against payment of any royalties, damages or other money which the Railway may have to make to any person or holder entitled to patent right in respect of the users of any machine, instrument, process, article or things constructed, manufactured, supplied or delivered by the contractor or to his order under this contract.

31 COMPLETION PERIOD :- Indicated in Vol.I

32 NIGHT WORK:-

The provision in clause 23 of the General Conditions of the contract should be noted regarding execution of work between sunset and sunrise. If the Railway is however,

Page 59: MEMU Master

Page 22 of 113

satisfied that the work is not likely to be completed in time except by resorting to night work by special order, the contractor would be required to carryout the work even at night, without conferring any right on the contractor for claiming compensation.

33 PAYMENTS:- 33.1 The Contractor shall be entitled to be paid from time to time by way of `On Account'

payment as per clause 46(i) of General Conditions of Contract. The “ON ACCOUNT” Payment shall not exceed 95% of the total on account payment due to the contractor on the rates indicated in the Schedules. For this purpose, the payment to the contractor at each on account stage shall be restricted to 95% of the amount calculated on the basis of rates indicated in the Schedules.

33.2 Such ‘On Account” payments will be made for each item of schedule at each station as per the accepted schedule of rates provided that such works are completed in all respects to the satisfaction of the Engineer except for such items of schedules which involve only supply of materials for which payment shall be made at 90% of the rates of the schedules provided an indemnity bond is executed by the Contractor duly indemnifying the Railways against all damages, costs, charges, expenses, loss and liability, which the Railways may sustain, incur or be put to by reasons or in subsequence directly or indirectly due to the Contractor not fulfilling the portion of the Contract involving the installation, testing and commissioning of the items supplied by the Contractor. The supply of the material will be deemed to have been completed only on physical receipt of the material by the Railways' representative duly inspected by the authorised Inspecting agency as stipulated in clause 19. The balance 5% payment will be released after installation and testing of the equipment.

33.3 On account payment in respect of other than supply items shall not exceed 95% of the

total payment due to the Contractor on each On account bill, of the rates indicated in the Schedule of work. For this purpose, the payment to the Contractor at each On account stage shall be restricted to 90% of the amount calculated on the basis of the rates indicated in the Schedule of work. The balance 5% payment shall be made after submission of all `As-made' documents of the relevant Schedules.

33.4 ‘On Account’ payment in respect of items involving supply and installation, 70% of the accepted rate for the schedule item will be paid on complete supply of the equipments listed in the schedule after due inspection, against production of indemnity bond and other formalities as applicable to other supply items in the schedule. The remaining 25% payment will be released only after successful installation and testing of the equipment.

33.5 FINAL PAYMENT:

On the basis of completion certificate issued by the Engineer for all the works in all the sections covered in this contract, the final bill for the balance payment for each item/sub-item of work shall be submitted by the Contractor along with a clear “NO CLAIM CERTIFICATE’. The completion certificate shall be issued by the Engineer only when he has accepted the work wholly after conducting the acceptance tests on each item of work.

34 DEDUCTION OF INCOME TAX - TAX AT SOURCE:-

Page 60: MEMU Master

Page 23 of 113

Income tax and surcharge, if any, as notified y the Income Tax department will be deducted at source from each bill, unless otherwise authorized by Income Tax Department.

35 INCOME TAX CLEARANCE CERTIFICATE:

The Tender must be accompanied by an authentic and current valid ITCC. If for any reasons, the tenderer/contractor is unable to submit the ITCC along with the tender, he shall clearly understand that no payment will be released to him even if tender is accepted in his favour till such time he produces the current ITCC. Till such time, he shall neither claim any payment nor the Railway will make him any payments. The intention is that no payments will be released without a current ITCC during the entire period of Contract unless so authorised by the Income Tax authorities.

36 LABOUR LICENCE:

36.1 The Contractors are required to produce licence as enjoined in the Government of India Contractor labour(Regulation and Abolition) Act, 1978. They shall not be allowed to undertake or execute any work through contract labour except under and in accordance with a licence issued under the said act in that behalf by the authorized Licencing Officer.

36.2 In terms of Child Labour(Prohibition & Regulation) Act 1986, any child below the age of 14 should not be engaged for the work by the contractor.

37 SITE CLEARANCE:

At the end of the work in each section the contractor shall as a part of his contractual obligation leave the area completely cleared of rubbish and obstructions of all kinds according to the instructions of the Railway’s representative. Besides, he shall take all necessary steps in the course of the execution of work to avoid the presence of loose earth and ballast on platforms, in drains, on the track formation and pathways in the vicinity. If within a fortnight of completion of the particular item of site work the refuge is not cleared the Railway will arrange to get them moved at the cost of the contractor. However, before the Railway actually gets the site cleared. Intimation in writing shall be sent to the contractor.

38 FORCE MAJEURE CLAUSE:

If at any time, during the continuance of this Contract, the performance, in whole or part, by either party, of any obligation under this contract shall be prevented or delayed by reason of any war, hostility, act of the public enemy, Civil Commotion, Sabotage, Fires, Floods, Earth quakes, explosions, strikes, epidemics, quarantine, restrictions lockouts, any statute, statutory rules, regulations, order of requisitions issued by any Government Department or Competent Authority or acts of God (here-in-after referred to as event) then provided notice of the happening of any such event is given by either party to the other within twenty one days from the date of occurrence thereof neither party shall by reason of such even be entitled to terminate this Contract nor shall either party have any claim for damage against the other in respect of such non- performance or delay in performance, and the obligations under the Contract shall be resumed as soon as practicable after such event has come to an end or ceased to exist, PROVIDED FURTHER

Page 61: MEMU Master

Page 24 of 113

that if the performance in whole or part of any obligation under this Contract is prevented or delayed by reason of any such event beyond a period as mutually agreed to by the Railways and the Contractor after any event or 60 days in the absence of such an agreement whichever is more, either party may at its option terminate the Contract provided also that if the contract is so terminated under this clause the Railways may at the time of such termination take over from the Contractor at prices as provided for in the contract, all works executed or works under execution.

39 SETTLEMENT OF DISPUTE AND ARBITRATION:

Arbitration in this tender will be governed by the Arbitration and Reconciliation Ordinance 1996, laid down in Para 63 & 64 of General Conditions of Contract.

39.1 MATTERS FINALLY DETERMINED BY THE RAILWAY:

All disputes or differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the works or after its completion and whether before or after the determination of the contract, shall be referred by the contractor to the Railway and the Railway shall within 120 days after receipt of the contractor’s representation make and notify decisions on all matters referred to by the contractor in writing provided that matters for which provision has been made in clauses 8(a), 18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57A, 61(1), 61(2) and 62(1)(b) of the General conditions of the contract or in any clause of the Special Conditions of Contract shall be deemed as “excepted matters” and decisions of the Railway authority thereon shall be final and binding. on the contractor provided further that `excepted matters’ shall stand specifically excluded from the purview of the arbitration clause and not be referred to arbitration.

39.2 DEMAND FOR ARBITRATION: (i) In the event of any dispute or difference between the parties hereto as to the construction

or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the “excepted matters" referred to in clause 63 of these conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters, shall demand in writing that the dispute or difference be referred to arbitration.

(ii) The demand for arbitration shall specify the matters which are in question or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute(s) or difference(s) in respect of which the demand has been made together with counter claims or set off shall be referred to arbitration and other matters shall not be included in the reference.

(ii)(a) The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway.

(b) The claimant shall submit his claim stating the facts supporting the claims along with all relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitration Tribunal.

Page 62: MEMU Master

Page 25 of 113

(c) The railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal thereafter, unless otherwise extension has been granted by Tribunal.

(iii) No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defence thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it.

(iv) If the Contractor(s) does/do not prefer his/their specific and final claims in writing, within a period of 90 days of receiving the intimation from the Government that the final bill is ready for payment, he/they will be deemed to have waived his/their claim(s) and the Railway shall be discharged and released of all liabilities under the contract in respect of these claims.

39.3 OBLIGATION DURING PENDANCY OF ARBITRATION: Work under the contract shall, unless otherwise directed by the Engineer, continue during the arbitration proceedings, and no payment due or payable by the Railway shall be withheld on account of such proceedings, provided, however, it shall be open for Arbitral Tribunal to consider and decide whether or not such work should continue during arbitration proceedings.

39.4.1 In cases where the total value of all claims in question added together does not exceed Rs.10,00,000/- (Rupees Ten Lakhs only), the Arbitral Tribunal consist of a sole arbitrator who shall be either the General Manager or a gazetted officer of Railway not below the grade of JA grade nominated by the General Manager in that behalf. The sole arbitration shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by Railway.

39.4.2 In cases not covered by Clause 39.4.1, the Arbitral Tribunal shall consist of a panel of three Gazetted Rly. Officers not below JA grade, as the arbitrators. For this purpose, the Railway will send a panel of more than 3 names of Gazetted railway Officers of one or more departments, of the Railway to the contractor who will be asked to suggest to General Manager upto 2 names out of the panel for an appointment as contractor’s nominee. The General Manager shall appoint at least one out of them as the contractor’s nominee and will, also simultaneously appoint the balance number of arabitrators either from the panel or from outside the panel, duly indicating the ‘presiding arbitrator’ from amongst the 3 arbitrators so appointed. While nominating the arbitrators it will be necessary to ensure that one of them is from the Accounts Department. An Officer of selection grade of the Accounts department shall be considered of equal status to the officers in SA grade of other departments of the Railways for the purpose of appointment of arbitrators.

39.4.3 If one or more of the arbitrations appointed as above refuses to act as arbitrator, withdraws from his office as arbitrator, or vacates his/their office/offices or is/are unable or unwilling to perform his functions as arbitrator for any reason whatsoever or dies or in the opinion of the General manager fails to act without undue delay, the General Manager shall appoint new arbitrator/arbitrators to act in his/their place in the same manner in which the earlier arbitrator/arbitrators had been appointed. Such re-constituted Tribunal may, at its discretion, proceed with the reference from the stage at which it is left by the previous arbitrator(s).

Page 63: MEMU Master

Page 26 of 113

39.4.4 The arbitral Tribunal shall have power to call for such evidence by way of affidavit or otherwise as the Arbitral Tribunal shall think proper, and it shall be the duty of the parties hereto to do or cause to be done all such things as be necessary to enable the Arbitral Tribunal to make the award without any delay.

39.4.5 While appointing arbitrator(s) under sub-clause 39.4.1, 39.4.2 and 39.4.3 above, due care shall be taken that he/they is/are not the one/these who had an opportunity to deal with the matters to which the contract relates or who in the course of his/their duties as Railway Servant(s) expressed views on all or any of the matters under dispute or differences. The proceedings of the Arbitral Tribunal or the award made by such Tribunal will, however, not be invalid merely for the reason that one or more arbitrator had, in the course of his service, opportunity to deal with the matters to which the contract relates or who in the course of his/their duties expressed views on all or any of the matters under dispute.

39.4.6 The arbitral award shall state intenwise, the sum and reasons upon which it is based.

39.4.7 A party may apply for corrections of any computational errors, any typographical or clerical errors or any other error of similar nature occurring in the award and interpretation of a specific point of award to tribunal within 30 days of receipt of the award.

39.4.8 A party may apply to tribunal within 30 days of receipt of award to make an additional award as to claims presented in the arbitral proceedings but omitted from the arbitral award.

39.5 In case of the Tribunal, comprising of three Members, any ruling of award shall be made by a majority of Members of Tribunal. In the absence of such a majority, the views of the presiding Arbitrator shall prevail.

39.6 Where the arbitral award is for the payment of money, no interest shall be payable on whole or any part of the money for any period till the date on which the award is made.

39.7 The cost of arbitration shall be borne by the respective parties. The cost shall inter-alia include for the arbitrator(s) as per the rates fixed by the Railway Administration from time to time.

39.8 Subject to the provisions of the aforesaid Arbitration and Conciliation Act 1996 and the rules there under and any statutory modification thereof shall apply to the arbitration proceedings under this clause.

--SSsSS--

Page 64: MEMU Master

Page 27 of 113

SOR - 2007 - DETAILED DESCRIPTION OF SCHEDULES

SOR No.

Brief description of work UnitRate

Rs. P.1001 Excavation of cable trench in all kinds of soil except hard rocky

areas including clearing of roots of trees, rocks, bushes etc. to a depth of 1.0 Mtrs and to a width of 0.3 Mtrs. Laying of cables is not included in this schedule.

Mtrs 25.80

1002 Excavation of cable trench in all kinds of soil except hard rocky areas including clearing of roots of trees, rocks, bushes etc. to a depth of 1.0 Mtrs and to a width of 0.5 Mtrs. Laying of cables is not included in this schedule.

Mtrs. 32.10

1003 Excavation of cable trench in hard rocky area to a depth of 0.5 Mts. and to a width of 0.5 Mtrs. construction of masonry duct as per drawing No.SBC/SG/CN/SK/343-A for cable laying and filling the inner space with river sand. Laying of cables is not included in this schedule.

[Bricks, river sand, cement and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Mtrs. 293.40

1004 Excavation of cable trench across Metalised/Mecademised Roads to a width of 0.3 and a depth of 1m, laying of RCC pipes 100mm inner dia and 150mm outer dia with collars, for laying of cables, refilling the cable trench made across Metalised/Mechanised roads and re-surfacing to its original position. Laying of cables is not included in this schedule.

[RCC pipe 100mm ID, 150mm OD, 2 mts. long with collar and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Mtrs. 325.50

1005 Removing/breaking of existing RCC slabs on the Passenger Platform, trenching to a depth of 0.6m to accommodate the additional cables, replacing the slabs removed after the cables are laid and replastering with cement mortor, refilling the trench by ramming and consolidating it as per the instructions of Railway Represntative at site. Laying of cables is not included in this schedule.[Cement, river sand and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Mtrs. 142.80

1006 Excavation of trench along route of existing cable duct, opening the slabs to accomodate additional cable laying, replacing the slabs removed after the cables are laid and replastering with cement mortor, and refilling the trench by ramming and consolidating it as per the instructions of Railway Represntative at site. Laying of cables is not included in this schedule.

[Cement, river sand and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Mtrs. 93.30

Page 65: MEMU Master

Page 28 of 113

1007 Excavation of trench to a depth of 1 Mtr. from ground level for track/ road crossing of cables, supply and laying of RCC pipes 100mm inner dia, 150mm outer dia 2 Mtrs. long with collar, refilling of trench by ramming and consolidating it as per the instructions of Railway representative at site. During excavation of trench it has to be ensure that the excavated soil does not mix with the ballast available. Laying of cables is not included in this schedule.[RCC pipes 2m long, 100m inner dia & 150mm outer dia with collar and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 417.60

1008 Excavation of trench to a depth of 0.5 Mtr. from ground level for track/ road crossing of cables, supply and laying of RCC pipes 100mm inner dia, 150mm outer dia 2 Mtrs. long with collar, refilling of trench by ramming and consolidating it as per the instructions of Railway representative at site. During excavation of trench it has to be ensure that the excavated soil does not mix with the ballast available. Laying of cables is not included in this schedule.[RCC pipes 2m long, 100m inner dia & 150mm outer dia with collar and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 339.90

1009 Excavation of trench to a depth of 1 Mtr. from ground level for track/ road crossing of cables, supply and laying of double walled corrugated pipes (103.5mm inner dia & 120mm outer dia), refilling of trench by ramming and consolidating it as per the instructions of Railway representative at site. During excavation of trench it has to be ensure that the excavated soil does not mix with the ballast available. Laying of cables is not included in this schedule.[Double walled corrugated pipe - 103.5mm inner dia & 120mm outer dia conforming to specification No. IS 14930(Part 2) : 2001 with socket/ coupler and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Mtrs. 292.80

1010a.

Provision of GI pipes-(50mm dia-3.65mm thick)/ (100mm dia- 4.5mm thick) for cable laying with off set at both ends and with coupling wherever required as per site requirement over the Bridges/ Drainage/ Culverts with brick masonary supports of size 300mm x 300 mm x 300 mm at an interval of 2M in box type bridges and suitable MS Clamps at an interval of 2 Mtrs. in Girder bridges in and closing the ends with brick masonary abutments of size 0.5m x 0.5m x 0.5 m, as per the instructions of Railway representative at site. Laying of cables is not included in this schedule.[GI pipes (50mm dia-3.65mm thick)/ (100mm dia-4.5mm thick), bricks, sand, cement, MS fixing clamps, bolts and nuts and all other miscellaneous materials required for the work shall be supplied by the Contractor].

   

a. Provision of GI pipes 50mm dia-3.65mm thick Mtrs. 386.80

  b. Provision of GI pipes 100mm dia - 4.5mm thick Mtrs. 783.60

1011 Laying of signalling/power/telecommunication cables as per cable plan in cable trenches, masonary ducts, RCC Pipes, DWC pipes, GI Pipes etc.

Mtrs. 7.80

Page 66: MEMU Master

Page 29 of 113

(Supply of cables is not included in this schedule).1012 Placing of one layer of country bricks of size approximately 220mm x

100mm x 60mm lengthwise vertically in the trench[Country bricks of size 220mm x 100mm x 60mm (approximately) shall be supplied by the Contractor].

Mtrs. 20.80

1013 Placing of one row of country bricks of size approximately 220mm x 100mm x 60mm breadthwise horizontally above the cables in 0.3m width trench.[Country bricks of size 220mm x 100mm x 60 mm (approximately) shall be supplied by the Contractor].

Mtrs. 42.40

1014 Placing of two rows of country bricks of size approximately 220mm x 100mm x 60mm breadth wise horizontally above the cables in 0.5mm width trench.[Country bricks of size 220mm x 100mm x 60mm (approximately) shall be supplied by the Contractor].

Mtrs. 80.90

1015 Refilling of cable trench 1m depth by 0.3m width throughout, with earth after laying of cables, and consolidating the trench by ramming and levelling.

Mtrs. 6.20

1016 Refilling of cable trench 1m depth by 0.5m width throughout, with earth after laying of cables, and consolidating the trench by ramming and levelling.

Mtrs. 7.80

1017 Supply of RCC cable markers as per drawing No.CSTE/CN/OFC/1. The lettering on the cable marker shall be "SIG" / "TELE" / "OFC" as per the instructions of Railway representative at site.

Nos. 144.60

1018 Digging of pit to a depth of 800mm of size 300mmX300mm, casting of concrete foundation of size 300mmX300mmX300mm and Placing of RCC cable markers on top of the foundation and refilling the pit and consolidating it by ramming. The cable markers shall be provided at an interval of 20 Mtrs. within station limits and 50 Mtrs. outside station limits throughout the cable route, diversions and also at every track/road/crossing.

Nos. 113.20

1019 Excavation of cable coil pit to a size of 1.0mx1.0m and depth of 1.0m for coiling the signal/power cable in rear of relay rooms/ AFTC huts, apparatus cases etc., as per the instructions of Railway representative at site. The work includes coiling the underground cables, and placing closely one layer of country bricks of size approx. 220mm x 100mm x 60mm breadth wise above the cables to cover all the cables in the cable pit, closing and consolidating the pit by ramming and leveling.

[Country bricks of size 220mm x 100mm x 60mm (approximately) shall be supplied by the Contractor].

Nos. 389.70

2001 Excavation of pit, casting concrete foundation and erection of apparatus case full size as per Drg. No.SG/CN/02/6 and fixing of 2 Nos. of 'E' type locks, one for the front door and another for the back door, fixing of one hard wood shelf plank 37mm thick and painting the apparatus case inside and outside with one coat of red-oxide and two

Nos. 8367.00

Page 67: MEMU Master

Page 30 of 113

coats of aluminium paints.(Supply of apparatus case is not included in this schedule).[Foundation bolts & nuts, 'E' type locks, cement, river sand, stone jelly of size 20/25 mm, hardwood plank of 37mm thick, paints, varnish, fixing bolts & nuts and all other miscellaneous materials required for the work shall be supplied by the Contractor.]

2002 Excavation of pit, casting concrete foundation and erection of apparatus case half size as per Drg, No.SG/CN/02/7, fixing one 'E' type lock for the front door and latching arrangement for the back door, and fixing of one hardwood shelf plank 37mm thick and painting the apparatus case inside and outside with one coat of red-oxide and two coats of aluminium paints.(Supply of apparatus case is not included in this schedule).[Foundation bolts and nuts, cement, 'E' type locks, river sand, stone jelly of size 20/25mm, 37mm hard wood planks, latching arrangments, paints, varnish, fixing bolts & nuts and all other miscellaneous materials required for the work shall be supplied by the Contractor]

Nos. 5836.00

2003 Excavation of pit, casting concrete foundation and erection of apparatus case Quarter size as per Drg. No.SG/CN/02/8 and fixing of one hardwood base plank 37mm thick, provision of one EWS lock, and painting the apparatus case inside and outside with one coat of red-oxide and two coats of aluminium paints.(Supply of apparatus case is not included in this schedule).[Foundation bolts and nuts, cement, river, sand, stone jelly of size 20/25mm, 37mm hard wood planks, EWS locks, paints, varnish, fixing bolts and nuts and all other miscellaneous materials required for the work shall be supplied by the Contractor]

Nos. 5068.00

2004 Excavation of pit, erection of cable termination boxes on rails and concreting as per Drg. No.SG/CN/02/8, drilling of suitable holes in the box, fixing of 2 Nos. of GI pipes 32mm dia and 300mm long at the bottom with clamp nuts - 12 mm thick, one at the inner side and another at the outer side for each pipe for cable throughing, fixing of hardwood plank 37mm thick on the bottom, provision of one EWS lock, and painting the boxes inside and outside with one coat of red-oxide and two coats of aluminium paints.(Supply of CT boxes is not covered in this schedule. Rails of different length shall be supplied by Railways. The contractor shall cut lengthy rails wherever required.)[Cement, river sand, stone jelly of size 20/25mm, paint, varnish, GI Pipes 32mm dia with clamp nuts - 12mm thick - 2 Nos. for each pipe, fixing bolts and nuts with washers, EWS locks, paints and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 2782.00

Page 68: MEMU Master

Page 31 of 113

2005 Excavation of pit, erection of cable termination boxes on rails and concreting as per Drg. No.SG/CN/02/8, drilling of suitable holes in the box, fixing of 2 Nos. of GI pipes 32mm dia and 300mm long at the bottom with clamp nuts - 12 mm thick, one at the inner side and another at the outer side for each pipe for cable throughing and one GI pipe 150mm long 32mm dia for drawal of jumper wires for Point machines etc., fixing of hardwood plank 37mm thick on the bottom, provision of one EWS lock, and painting the boxes inside and outside with one coat of red-oxide and two coats of aluminium paints.(Supply of CT boxes is not covered in this schedule. Rails of different length shall be supplied by Railways. The contractor shall cut lengthy rails wherever required.)[Cement, river sand, stone jelly of size 20/25mm, paint, varnish , GI Pipes 32mm dia - 300mm long - 2 Nos and 150mm long - 1 No., clamp nuts - 12mm thick - 2 Nos. for each pipe, fixing bolts and nuts with washers, EWS locks, paints and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 2804.00

2006 Fabrication and erection of rail staging, concreting, construction of stock brick, masonry support, supply and provision of concrete slabs 3 Nos. of size 300mm x 1700mm x 80mm for platform on stage support for erecting apparatus case full size on embankment and casting concrete foundation and erection of apparatus case full size over the compacted earth and masonary , fixing 2 Nos. of 'E' type locks, one for the front door and another for the back door, supply and fixing of one hardwood shelf plank of 37mm thick and painting the boxes inside and outside with one coat of red-oxide and two coats of aluminum paints.(Supply of apparatus case is not included in this schedule. Rails of different lengths will be supplied by Railway and the Contractor has to cut the rails to required lengths).[Cement river sand, jelly of size 20/25 mm, stock bricks, MS base plates, fixing bolts and nuts, fabricating materials, MS Clamps for fixing rails, MS rods for reinforcement of slabs, hardwood plank 37mm thick, 'E' type locks, paints and varnish and all miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 11788.00

Page 69: MEMU Master

Page 32 of 113

2007 Fabrication and erection of rail staging, concreting, construction of stock brick masonry support, supply and provision of concrete slabs for platform, 3 Nos. of size 3000mm x 1000mm x 80mm for platform stage support for apparatus case half size on embankment and casting concrete foundation and erection of apparatus case half size over the compacted earth and masonary work. Fixing one No. 'E' type lock for the front door and the latching arrangements for the back door and fixing one H.W shelf plant of 37mm thick and painting the boxes inside and outside with one coat of red-oxide and two coats of aluminium paints. (Supply of apparatus cases is not included in this schedule. Rails of different lengths will be supplied by Railways and the Contractor has to cut the rails to the required lengths).

['E' type locks, foundation bolts, Cement, river sand, stone jelly of size 20/25 mm, stock brick, MS base plates, fixing bolts and nuts, fabricating materials, MS clamps for fixing rails, MS rods for reinforcement of slabs, hardwood plank 37mm thick, paints, varnish and other miscellaneous materials required for thework shall be supplied by the Contractor].

Nos. 8333.00

2008 Excavation of pit in and around the existing location boxes very carefully without damaging the working cables and shifting and turning the location boxes to clear of the infringement as instructed by the Railway representative at site. The work includes ensuring the safety of the signalling system, releasing the cable coils to give access for shifting/ turning the location boxes. Necessary masonary work and earth work in and around the location boxes to the required lever shall be done as instructed by the Railway representative at site. If the existing earth connections to the location boxes are disturbed, the earth wires shall be properly re-connected.[All materials required for the work shall be supplied by the Contractor].

   

a. Shifting of apparatus case (full) Nos. 2281.00

  b. Shifting of apparatus case (half) Nos. 1494.00

  c. Shifting of apparatus case (Quarter) Nos. 1183.00

Page 70: MEMU Master

Page 33 of 113

2009 Termination of new main/ tail cables on the existing terminals/ fuse blocks in apparatus cases/ battery boxes/ CT boxes/ cable termination tacks as per approved circuit diagram. The terminal particulars are to be repainted/corrected on the doors of apparatus cases/ battery boxs/ cable termination boxes and FTOT index board as instructed by Railway representative at site. This work includes closing the opening created for entry of new cables in the apparatus cases with masonary brick work and sealing the bottom of the apparatus cases/ cable termination racks with cable compound.[Paints, wire PVC 3/0.75mm and 16/0.2mm copper, sealing compound, bricks, cement, river sand and all other required miscellaneous materials shall be supplied by the contractor].

Per Terminal

29.70

2010 Termination of main, tail, Signalling and power cables and internal wiring on terminal/ fuse blocks in new apparatus cases, cable termination boxes and in gate lodges excluding cable termination rack at relay room. The work includes fixing of all new cables by teakwood clamp on teakwood base plank, fixing of Phynolic synthetic industrial fibre base fine weave cotton fibre board 6mm thick for terminal board to suit each apparatus case, varnishing all teakwood items, fixing of terminals/ fuse blocks on the terminal board, drilling of necessary holes, termination of cables, wiring, identification of cables using aluminium tags with letters punched neatly, as per approved circuit diagram and cable plan, painting of particulars on sleeves and also on the inner side of the doors of apparatus cases. After terminations are over, the side openings of apparatus case foundation shall be closed with brick work, cement plastered, the inter-space filled with river sand up to base level and the bottom surface shall be sealed with sealing compound.

   

  (Supply of PBT terminals and Fuse blocks is not covered in this schedule).

[Cement, teakwood cable clamp 50mm x 50mm, base planks 100mm x 25mm, Phynolic synthetic industrial fibre base fine weave cotton fibre sheet - 6mm thick to IS specification 2036 - 1995 - Type F5, PVC/Nylon sleeves, varnish, paints, bolts, nuts and washers, Non-deteriorating type of fuses of various capacities, Aluminium cable tags, sealing compound, country bricks 220mm x 100mm x 60mm, copper bus bars, brass screw, river sand, wire PVC3/0.75mm copper and other miscellaneous materials shall be supplied by the Contractor].

   

  a. Termination on 25/60mm PBT terminals (new location)(Phynolic sheet)

Per Terminal

74.10

  b. Termination on PBT fuse block (new location) (Phynolic sheet) Per Fuse

98.10

2011 Termination of main, tail, Signalling and power cables and internal wiring by fixing additional terminals/ fuse blocks on the existing terminal boards of apparatus cases, cable termination boxes etc. The work includes fixing of all new cables by teakwood clamp on teakwood base plank, varnishing all teakwood items, fixing of

   

Page 71: MEMU Master

Page 34 of 113

terminals/ fuse blocks, on the existing terminal boards, drilling of necessary holes, termination of cables, wiring, identification of cables using aluminium tags with letters punched neatly, as per approved circuit diagram and cable plan, painting of particulars on sleeves and also on the inner side of the doors of apparatus cases. After terminations are over, the side openings of apparatus case foundation shall be closed with brick work, cement plastered, the inter-space filled with river sand upto base level and the bottom surface shall be sealed with sealing compound.

  (Supply of PBT terminals and Fuse blocks is not covered in this schedule).

[Cement, teakwood cable clamp 50mm x 50mm, base planks 100mm x 25mm, PVC/Nylon sleeves, varnish, paints, bolts, nuts and washers, Non-deteriorating type of fuses of various capacities, Aluminium cable tags, sealing compound, country bricks 220mm x 100mm x 60mm, copper bus bars, brass screw, river sand, wire PVC3/0.75mm copper and other miscellaneous materials shall be supplied by the Contractor].

   

  a. Termination of cables on 25/60mm PBT terminals (existing location)

Per Terminal

62.50

  b. Termination of cables on PBT fuse block (existing location) Per Fuse

86.60

2012 Manufacture and supply of M.S. relay frames of suitable size to hold upto 4/ 8/ 12/ 20 relays as required by Railways and fixing them in apparatus cases for all types of signal control circuits, LC gate control circuit, lever lock control circuits and Point control circuits, fixing of plug boards, relays, resistors and electrolytic condensors on Phynolic synthetic industrial fibre base fine weave cotton fibre sheet - 6mm thick to IS specification 2036 - 1995 - Type F5, wiring and termination as per approved circuit diagram and painting the particulars.(Supply of all types of relays, plug boards, connectors, retaining clips and 50 way terminal boards is not covered in this schedule).[Wire PVC copper, 3/0.75mm and 16/0.2mm copper, Phynolic synthetic industrial fibre base fine weave cotton fibre sheet - 6mm thick to IS specification 2036 - 1995 - Type F5, for fixing resistors and condensors, MS flats 25mm x 6mm brass bolts and nuts, paints, soldering materials, resistors, condensors and all other miscellaneous materials required for the work shall be supplied by the contractor.)

   

  a. Wiring of Signal/ point/ LC control circuit (upto 4 relays) Set 2104.00

  b. Wiring of Signal/ Point/ LC control circuit (upto 8 relays) Set 3647.00

  c. Wiring of Signal/ Point/ LC control circuit (upto 12 relays) Set 4707.00

  d. Wiring of Signal/ Point/ LC control circuit (upto 20 relays) Set 5666.00

2013 Painting of existing apparatus cases with out disturbing the terminations and equipments inside. The work involves scraping of old paint, applying one coat of Red oxide and two coats of Aluminium paint on the inside and outside the apparatus cases, as instructed by

   

Page 72: MEMU Master

Page 35 of 113

Railway representative at site.[Aluminium paint, red-oxide and all other miscellaneous materials required for the work shall be supplied by the Contractor].

  a. Painting of existing apparatus case - Full size Nos. 916.00

  b. Painting of existing apparatus case - Half size Nos. 871.00

2014 Fixing and wiring of platform repeaters. The work involves fixing of platform repeater using suitable fixing arrangements at places indicated, wiring the same and painting as per the instructions of Railway representative at site. The signal shall be connected to the apparatus case using cables neatly clamped. The work also includes provision of one EWS lock(Supply of repeater signals and cables is not included in this schedule).[Wire PVC 3/0.75mm copper, paint, EWS lock and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 2886.00

2015 Painting of existing colour light Signals as per standard practice. The work involves scraping of old paint, applying one coat of Red oxide and two coats of Aluminium/ enamel paint on the Signals - complete as instructed by Railway representative at site.[Aluminium paint, red-oxide and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 977.00

2016 Alterations to painted termination/ wiring particulars of functions in the existing apparatus cases, cable termination boxes, etc., on the PVC/ nylon sleeves and painting of new nomenclature on the existing signalling gadgets. This work includes carrying out alterations of particulars on the inner side of the doors of apparatus cases, re-numbering of apparatus cases and cable termination boxes.[Paints and all other miscellaneous materials required for the work shall be supplied by the Contractor].

   

  a. Alteration to painting particulars (apparatus case - Full size) Nos. 863.00

  b. Alteration to painting particulars (apparatus case - half size) Nos. 449.00

  c. Alteration to painting particulars (apparatus case-quarter size/ CT box)

Nos. 311.00

2017 Filling earth around location boxes/signal foundations for a width of 0.5m on all sides, up to a level 150mm below the foundation top. This work includes consolidation of earth by watering and ramming.

cum 93.30

2018 Excavation of pit, casting concrete foundation as per Drg.No.SG/CN/02/9 using metallic templates, for erection of colour light signals up to 4 aspects.

[Foundation bolts, cement, river sand, stone jelly of size 20/25mm dia and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 4455.00

2019 Erection of surface base, signal pole, mounting of colour light signal upto 4 aspects complete on Signal pole/ Off-set bracket, (for LED/ filament bulbs) with lenses, triple pole lamp holder, filament switching units, CLS transformer, current regulators (whichever is applicable),

Nos. 4066.00

Page 73: MEMU Master

Page 36 of 113

fixing of ladder with platform complete and concreting of ladder shoe, fixing of number plates, marker board, lens guard, termination of tail cables, wiring of signal unit with PVC wire 3/0.75mm copper, provision of EWS locks, and painting of one coat of red oxide and two coats of aluminium/ enamel paints. When the aspect is fixed on Off set bracket using 'U' bolts and nuts through bolts shall be provided by drilling a hole in the signal pole to prevent the offset bracket from sliding down.

  (Supply of surface base, Off set bracket, CLS pole, CLS aspect complete, ladder with shoes and platform, LED aspects, current regulators, lamp holders, lamps, filament switching unit and CLS transformer is not covered in this schedule).['U' bolts and nuts, through bolts and nuts, cement, stone jelly 20/25mm dia, river sand, Signal Collar Rings, wire PVC 3/0.75mm copper, lens-guard, all fixing bolts and nuts, lead wool, paints PVC/Nylon sleeves, enameled number plates. enameled marker boards, EWS locks, and all other miscellaneous materials for the work shall be supplied by the Contractor].

   

2020 Excavation of pit and casting concrete foundation as per Drg, No.SG/CN/02/10 using metallic templates, for erection of ground type colour light shunt signal.[Foundation bolts and nuts, cement, river sand, stone jelly of size 20/25mm and all other miscellaneous materials for the work shall be supplied by the Contractor].

Nos. 2128.00

2021 Erection of Ground type shunt signal complete including surface base, signal pole, lenses, bulbs with holders, fixing of lens guards, number plate, termination of tail cables, wiring of signal unit with PVC wire 3/0.75mm copper, provision of EWS locks and painting of one coat of red oxide and two coats of Aluminium/ enamel paint.(Supply of Ground type shunt signal complete including surface base, signal pole, holder, bulbs, and lenses is not covered in this schedule).[Wire PVC 3/0.75mm copper, lens guards, EWS locks, Enamelled number plates, bolts and nuts, lead wool, paints and all other miscellaneous materials shall be supplied by the Contractor.]

Nos. 1574.00

2022 Fixing of Off set brackets using 'U' bolts and nuts, erection of Post type shunt Signals, termination of tail cables and wiring using wire PVC 3/0.75mm copper, provision of EWS lock and painting of one coat of red-oxide and two coats of aluminium/ enamelled paint. The work also includes drilling suitable holes on the CLS post and provision of a through bolt with nut to prevent the Off-set bracket from slipping down. (Supply of Post type Shunt Signals and Off set brackets is not covered in this schedule).['U' bolts and nuts, through bolts with nut, wire PVC 3/0.75mm copper, EWS lock, Enamelled number plates, wire mesh, PVC/Nylon sleeves, paints and all other miscellaneous materials shall be supplied by the contractor].

Nos. 1218.00

2023 Fixing Multi lamp/ Stencil type route indicators - complete, termination of tail cables, wiring as per approved circuit diagram using wire PVC 3/0.75mm copper, provision of EWS - required Nos., and

   

Page 74: MEMU Master

Page 37 of 113

painting.(Supply of route indicators is not covered in the schedule)[Fixing bolts and nuts, EWS locks, wire PVC 3/0.75mm copper, wire mesh, PVC/Nylon sleeves, paints and all other miscellaneous materials shall be supplied by the Contractor].

  a. Fixing and wiring of Multi lamp route indicator Nos. 1758.00

  b. Fixing and wiring of Stencil type route indicator Nos. 1483.00

2024 Fixing of junction type route indicators - 1 way to 5 way - complete/ fixing of additional limb to the existing route indicators, termination of tail cables, wiring as per approved circuits diagram using wire PVC 3/0.75mm copper, provision of required No of EWS locks, wire mesh, and painting.(Supply of junction type Route Indicators - complete, and additional limb is not covered in this schedule).[3/0.75mm wire PVC, fixing bolts and nuts, EWS locks, wire mesh, PVC/Nylon sleeves, paints and all other miscellaneous materials shall be supplied by the Contractor].

   

  a. Fixing and wiring of direction type route indicator - 1 way Nos. 1186.00

  b. Fixing and wiring of direction type route indicator - 2 way Nos. 1376.00

  c. Fixing and wiring of direction type route indicator - 3 way Nos. 1565.00

  d. Fixing and wiring of direction type route indicator - 4 way Nos. 2370.00

  e. Fixing and wiring of direction type route indicator - 5 way Nos. 2558.00

  f. Fixing and wiring of additional limb to existing route indicator Nos. 559.00

2025 Fixing of Off set brackets using 'U' bolts and nuts, erection of Calling On Signals/ 'A' marker lights, termination of tail cables and wiring using wire PVC 3/0.75mm copper, provision of EWS lock, number plates/ marker boards and painting. The work also includes drilling suitable holes on the CLS post and provision of a through bolt with nut to prevent the Off-set bracket from slipping down(Supply of Calling On Signal/ 'A' marker light and Off set brackets is not covered in this schedule).['U' bolts and nuts, through bolts with nut, wire PVC 3/0.75mm copper, EWS lock, Enamelled number plates, wire mesh, PVC/Nylon sleeves, paints and all other miscellaneous materials shall be supplied by the contractor].

Nos. 1115.00

2026 Releasing of existing tail cables and drawal of new tail cables for colour light signals upto four aspects with or without route indicator, post type shunt signal and Calling on signals, termination of new tail cables and wiring using wire PVC 3/0.75mm copper. This work includes drawal of new tail cables into the signal post duly releasing the existing tail cables from the relevant signals.[Wire PVC 3/0.75mm copper, paints and all other miscellaneous matrials shall be supplied by the Contractor].

Per Cable

631.80

2027 Excavation of pit in and around the existing signals very carefully without causing damage to the working cables and shifting the Signals along with the concrete foundations to a nearby position so as to clear the infringement from the nearest track centre as instructed by Railway

Nos. 1619.00

Page 75: MEMU Master

Page 38 of 113

representative at site. The existing cable coils shall be released carefully so as to give access for shifting. Necessary masonary work and earth work shall be carried out in and around the signals after shifting as instructed by Railway representative at site. [All materials required for the work shall be supplied by the Contractor].

2028 Removal of existing CLS units, fixing of new CLS units upto four aspects, directly or using off set brackets duly drilling holes on the signal poles, provision of EWS locks wherever necessary, termination of tail cables and wiring using wire PVC3/0.75mm copper and painting of aspect. The new tail cables shall be taken through the signal poles and the unwanted cables duly released.(Supply of CLS unit is not included in this schedule).[EWS locks, Wire PVC 3/0.75mm copper lense guard, wire netting arrangements, paints and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 4629.00

2029 Manufacture and supply of Enameled Number plates with fixing arrangements and fixing them on the existing Signals as per the instructions of Railway representative at site.[Enamelled number plates with fixing arrangements with bolts and nuts shall be supplied by the Contractor].

Nos. 266.20

2030 Supply and provision of Screening arrangement for Signals in RE area as per standard practice and as per the instructions of Railway representative at site.[All materials required for this work shall be supplied by the Contractor].

Nos. 777.70

2031 Provision of Single rail track circuit to suit RE Standard as per approved signalling plan using Plug-in type track relays. This work includes provision of double bonding, and parallel jumpering, provision of bond wire clips, provision of track lead connections with 8 SWG GI soft wire with necessary arrangements for fixing lead wires to the sleeper, provision of TLD boxes 2 Nos. at Relay end, 2 Nos. at Feed end and 2 Nos for parallel jumpering for each Track Circuit, and termination of jumpers and tail cables in track lead junction boxes, installation of relays, track feed battery chargers to charge upto 4 cells, track feed resistance, 'B' type choke' and charged secondary cells - 80 AH capacity in apparatus cases and wiring with wire PVC 3/0.75mm copper. The work also includes painting of track cct No. with Feed end/ Relay end details on the TLD boxes. The work also includes provision of insulations for gauge tie plates and nose crossing plates. Provision of rail joint insulation is not covered in this schedule.

   

  (Un insulated gauge type place and nose crossing plate will be supplied by Railways. Supply of track relays, secondary cells (2V - 80AH), TLD boxes with stumps is not covered in this schedule).[Track feed battery charger(to charge upto 4 cells, track feed resistance, 'B' type choke, Gauge tie plate and nose crossing plate insulations, PVC/Nylon bushes for TLD boxes, PVC sleeves, all types of fixing bolts and nuts with spring and flat washers, teakwood stand for fixing track feed resistance, GI bond wire 8 SWG, Channel

   

Page 76: MEMU Master

Page 39 of 113

bond pins, bond wire clips, paints and all other miscellaneous materials shall be supplied by the contractor. Secondary cells-80 AH capacity shall be charged by the contractor through reputed charging agencies].

  a. Provision of track circuit in RE area (point zone) Nos. 10487.00

  b. Provision of track circuit in RE area (other than point zone) Nos. 9444.00

2032 Provision of DC double rail track circuit to suit Non-RE Standard as per approved signalling plan using Plug-in type track relays. This work includes provision of double bonding, and parallel jumpering, provision of bond wire clips, provision of track lead connections with 8 SWG GI soft wire with necessary arrangements for fixing lead wires to the sleeper, provision of TLD boxes 2 Nos. at Relay end, 2 Nos. at Feed end and 2 Nos for parallel jumpering for each Track Circuit, and termination of jumpers and tail cables in track lead junction boxes, installation of relays, track feed battery chargers to charge upto 4 cells, track feed resistance, and charged secondary cells - 80 AH capacity in apparatus cases and wiring with wire PVC 3/0.75mm copper. The work also includes painting of track cct No. with Feed end/ Relay end details on the TLD boxes. The work also includes provision of insulations for gauge tie plates and nose crossing plates. Provision of rail joint insulation is not covered in this schedule.

   

  (Un insulated gauge type place and nose crossing plate will be supplied by Railways. Supply of track relays, secondary cells (2V - 80AH), TLD boxes with stumps is not covered in this schedule).[Track feed battery charger(to charge upto 4 cells, track feed resistance, Gauge tie plate and nose crossing plate insulations, PVC/Nylon bushes for TLD boxes, PVC sleeves, all types of fixing bolts and nuts with spring and flat washers, teakwood stand for fixing track feed resistance, GI bond wire 8 SWG, Channel bond pins, bond wire clips, paints and all other miscellaneous materials shall be supplied by the contractor. Secondary cells-80 AH capacity shall be charged by the contractor through reputed charging agencies].

   

  a. Provision of track circuit in Non-RE area (point zone) Nos. 6124.00

  b. Provision of track circuit in Non-RE area (other than point zone) Nos. 5082.00

2033 Alteration to existing DC Track Circuit to suit RE/Non RE standard as per approved signalling plan. This work includes provision of double bonding and parallel jumpering, provision of bond wire clips, wherever required, shifting of relay end and feed end equipments and re-wiring them, provision of track lead connections wherever necessary using 8 SWG GI soft wire with necessary arrangements for fixing lead wires to the sleeper, provision of TLD boxes and termination of jumpers and tail cables in track lead junction boxes, shifting of Track feed/Track relay set wherever required and wiring with PVC 3/0.75mm copper wire.

   

 (Supply of TLD boxes and stumps for fixing TLD Boxes is not covered in the schedule. Existing Track relays, Track Feed Resistance, Track feed battery chargers, `B' type Chokes and Charged secondary Cells shall used for this work).

   

Page 77: MEMU Master

Page 40 of 113

[Wire PVC 3/0.75mm, PVC/ Nylon bushes for TLD boxes, PVC sleeves, all types of bolts and nuts with spring and flat washers, teakwood stand for fixing track feed resistance, GI bond wire 8 SWG, Channel bond pins, bond wire clips, paints and all other miscellaneous materials shall be supplied by the Contractor].

  a. Alteration to existing track circuits at feed end Nos. 1938.00

  b. Alteration to existing track circuits at relay end Nos. 1844.00

2034 Provision of Rail Joint Insulations. This work includes milling of fish plates, provision of rail joint insulation with MS backing plates etc., and insulating the joints as per Railway standard.(Supply of Rail Joint insulations, un milled fish plates, fish bolts and nuts is not covered in this schedule).

Set. 261.20

2035 Supply and provision of Rail Joint Insulations. This work includes milling of fish plates, provision of rail joint insulation with MS backing plates etc., and insulating the joints as per Railway standard.(Supply of Un milled fish plates, fish bolts and nuts are not covered in this schedule).[Rail joint insulation complete set with MS backing plates shall be supplied by the Contractor].

Set. 801.80

2036 Provision of earth electrodes as per drawing No.SG/SN/02/13 and earthing of metallic sheath and armor of all cables in all apparatus cases, relay room, equipment room, SM's room for block and control, and earthing of all equipments in apparatus cases, power room, relay rack, cable termination rack, control panel, signals, lever frames with GI- 4 SWG soft wire and soldering the earth wire. The work includes painting of earth resistance value on the earth pit.[GI wire - 4 SWG, cement, GI earth electrodes, common salt, charcoal, country bricks, river sand, soldering materials and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 1763.00

2037 Provision of earthing arrangement for AFTC locations etc. The earth electrodes shall be similar to model SEE 60/C (of Safe Earth Electrode) of GI pipe 60.4mm Outer dia and 4.5mm thick, with a length of 3 mtrs. Copper strip of 32mmX4mmX2mm cross sectional area of Primary conducting area of 256 sq.mm shall be used. The earth electrode shall be erected in a pit of dia 300mm & depth of 3mtrs. The pit shall be filled with anti corrosive conductive compound surrounding the earth electrode. The pit shall be watered adequately for 5 days. A brick chamber surrounding the earth shall be constructed with a dimension of 450mmX450mm outer and 300mmX300mm inner. The height shall be 350mm with 150mm below the ground.[Earth electrode similar to model No.SEE 60/C, bricks, cement, river sand, GI earth wire 4 SWG, solder, nuts, bolts and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 13865.00

Page 78: MEMU Master

Page 41 of 113

2038 Installation of combined type point machine - 5E/ IRS type and connecting all ground connections including wiring and termination in point machine and interconnections between point machine and CT box through PVC hose pipe with 3/0.75mm and 7/1.40mm copper wire and painting. This work includes provision of insulation to stretcher bars, switch extension pieces and throw bar lug/"D" bracket wherever required, cutting of notches on the pinions of point machines to suit crank handle configuration.(Combined type point machine with ground connection, un insulated stretcher bar, throw bar lug and switch extension pieces without holes will be supplied by Railways.[All types of insulations connected to point work, pipe lock of square spigot, coal bengal, all type of bolts and nuts, washers spring/flat wire PVC 7/1.4mm copper, PVC hope pipe, paints, PVC/nylon sleeves and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 7259.00

2039 Supply of Colour light Signal pole 140mm dia, 4.6m/ 3.6m tall with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of colour light Signal pole (4.6m) Nos. 2860.00

  b. Supply of colour light Signal pole (3.6m) Nos. 2059.00

2040 Supply of surface base to suit CLS Signal pole 140mm dia with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 2746.00

2041 Supply of ladder with platform and shoes to suit CLS pole 4.6m/ 3.6m tall, with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of ladder with platform and shoes for 4.6m CLS pole Nos. 2631.00

  b. Supply of ladder with platform and shoes for 3.6m CLS pole Nos. 2517.00

2042 Supply of post type shunt signal - complete with lens, hood etc., with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 2517.00

2043 Supply of Ground type shunt signal - complete with surface base, signal pole, lens, hood etc., with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 2860.00

2044 Supply of Colour Light Signal Multi Unit type - complete for 4/ 3/ 2 aspect with mounting socket, with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of colour light Signal unit - 4 aspect Nos. 9724.00

  b. Supply of colour light Signal unit - 3 aspect Nos. 8580.00

  c. Supply of colour light Signal unit - 2 aspect Nos. 6864.00

Page 79: MEMU Master

Page 42 of 113

2045 Supply of Junction type route indicator – 5 unit arm – 1/ 2/ 3/ 4/ 5 way with mounting sockets, Lamp holder for SL 33 lamps and Lenses for route indicators with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of Junction type route indicator - 1 way Nos. 10296.00

  b. Supply of Junction type route indicator - 2 way Nos. 13156.00

  c. Supply of Junction type route indicator - 3 way Nos. 16016.00

  d. Supply of Junction type route indicator - 4 way Nos. 18876.00

  e. Supply of Junction type route indicator - 5 way Nos. 21736.00

2046 Supply of Calling On Signal / 'A' marker light - complete with lens and holder with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of Calling On Signal Nos. 1716.00

  b. Supply of 'A' marker light Nos. 1716.00

2047 Supply of Off-set brackets - large/ small made of cast iron with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of Off-set bracket (large) Nos. 1716.00

  b. Supply of Off-set bracket (small) Nos. 1144.00

2048 Supply of cable termination box made of cast iron with MS sheet iron door, with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 4235.00

2049 Supply of track lead junction box - FRP type with terminals and stump with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 915.00

2050 Supply of PBT terminals 25mm/ 60mm centre and PBT Fuse blocks with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of PBT terminal - 25mm center Nos. 40.00

  b. Supply of PBT terminal - 60mm center Nos. 60.00

  c. Supply of PBT fuse block (without ND fuse) Nos. 80.00

2051 Supply of Low maintenance secondary cells of the following capacities with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of secondary cells-2V-80AH capacity Nos. 1384.00

  b. Supply of secondary cells-2V-120AH capacity Nos. 2076.00

  c. Supply of secondary cells-2V-200AH capacity Nos. 3460.00

  d. Supply of secondary cells-2V-300AH capacity Nos. 5190.00

  e. Supply of secondary cells-2V-400AH capacity Nos. 6920.00

Page 80: MEMU Master

Page 43 of 113

2052 Supply of lamp proving relays for Off aspect with plug boards, connectors and retaining clips with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 3992.00

2053 Supply of electronic time delay units (120/60 secs) with plug boards, connectors and retaining clips with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 2422.00

2054 Supply of apparatus cases (full/ half/ quarter size) to suit Southern Railway standard with necessary inspection as per specification/ drawing/ description enclosed in this document:

   

a. Supply of apparatus case - Full size Nos. 8115.00

  b. Supply of apparatus case - Half size Nos. 5172.00

  c. Supply of apparatus case - Quarter size Nos. 3543.00

2055 Supply of Signal aspects - LED type with current regulator for the following types, with necessary inspection as per specification/ drawing/ description enclosed in this document.

   

  a. Supply of LED aspect for main signal (Green) Nos. 8237.00

  b. Supply of LED aspect for main signal (Yellow) Nos. 7207.00

  c. Supply of LED aspect for main signal (Red) Nos. 7207.00

  d. Supply of LED aspect for shunt signal Nos. 4221.00

  e. Supply of LED aspect for junction type route indicator Nos. 4221.00

  f. Supply of LED aspect for Calling On signal Nos. 5148.00

  g. Supply of LED aspect for "A" marker light Nos. 5148.00

2056 Supply of lamp proving relays for LED aspects with plug boards, connectors and retaining clips with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 3850.00

2057 Supply of QBCA1 - heavy duty contact relays with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 3593.00

2058 Supply of QTA2 - track relays with plug boards, connectors and retaining clips with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 2395.00

2059 Supply of QSPA1 type relays with plug boards, connectors and retaining clips with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 3327.00

2060 Supply of Electric key transmitter - rotary type of required ward Nos. with keys, with necessary inspection as per specification/ drawing/ description enclosed in this document.

Nos. 4004.00

2061 Supply of cable termination rack to hold 500 terminals - 60mm centre, with necessary inspection, as per specification/ drawing/ description enclosed in this document.

Nos. 14500.00

2062 Supply of relay rack to hold 168 relays, with necessary inspection, as per specification/ drawing/ description enclosed in this document.

Nos. 14550.00

Page 81: MEMU Master

Page 44 of 113

2063 Supply of 'A' type foundation made of cast iron, as per specification/ drawing/ description enclosed in this document, with necessary inspection.

Nos. 1350.00

3001 Concreting and erection of cable termination rack 500/210/140 Terminals capacity on teakwood base frame of size 50mmx150mm of suitable length and width with rectangular slt in the centre for taking in the cables, and painting as per standard practice.(Supply of cable termination racks is not included in this schedule).

[Foundation bolts and nuts with washers, cement, sand, stone jelly, teak wood base frame 50mmx150mm of suitable length and breadth, paints and all other miscellaneous materials required for the work shall be supplied by the contractor]

   

a. Concreting and erection of cable termination rack - 210/140 terminal capacity.

Nos. 4597.00

  b. Concreting and erection of cable termination rack - 500 terminal capacity

Nos. 6660.00

3002 Fixing of PBT terminal block/ PBT fuse block, rubber gromites, clamping of cables using teakwood cable clamps and base planks, termination of cables, provision of ND type fuses of required capacities, provision of copper bus bar for supply terminals, wiring, provision of termination particulars diagram board using plywood of thickness 12mm - teakwood finish of size 1800mm x 1200mm with Aluminium grooved channel frame in the relay room. The blank spaces over the top of the cable termination rack shall be covered with phynolic sheet of thickness 3mm wherever required. The termination and cable core particulars shall be painted on the PVC/ nylon sleeves. The work also includes identification of cables using aluminium tags provided on each cable with letters punched neatly.

   

  (Supply of PBT terminal blocks 25mm & 60mm centres and PBT Fuse blocks is not covered in the schedule).[Wire PVC 3/0.75mm copper, brass bolts and nuts and washers, for fixing PBT terminal/Fuse Block, other fixing bolts and nuts, rubber gromites, PVC/ Nylon sleeves, copper bus bars, teakwood 50mm x 50m for cable clamps, 25mmx 100mm for base planks, termination particualars board - plywood of thickness 12mm - teakwood finish of size 1200mm x 1800mm with aluminium grooved channel frame, phynolic sheet 3mm thick, paint and all other miscellaneous materials shall be supplied by the Contractor].

   

 

a. Fixing of PBT terminal blocks (25mm/60mm centre) and termination

Per Terminal Block

71.30

 

b. Fixing of PBT fuse block with ND fuses and termination

Per Fuse Block

95.20

Page 82: MEMU Master

Page 45 of 113

3003 Concreting and erection of Relay racks- 68/56-relay capacity using 'J' type bolts and painting of relay rack as per the instructions of Railway representative at site.(Supply of relay rack is mot covered in this schedule).['J' type bolts and nuts with washers, nylon bushes, concreting materials, paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

   

  a. Concreting and erection of Relay Rack - 168 relay capacity Nos. 3128.00

  b. Concreting and erection of Relay Rack - 56 relay capacity Nos. 1350.20

3004 Fixing of plug boards, 50 way terminal blocks and wiring of relays as per the approved circuit diagram using wire PVC 16/0.2mm copper. Suitable wire supporting tray with cover made of PVC shall be provided horizontally and vertically in the relay racks shall be provided. While running the wires on the aluminium ladder proper care shall be taken to provide smooth materials like rubber beading in the openings on phynolic sheets, to avoid damage to wires. The work also includes wiring of contacts for data logger and terminating them in 50 way terminal boards for future use, provision of relay index board made of plywood of thickness 12mm - teakwood finish of size 1200mm x 1800mm with aluminium grooved channel frame, provision of hard wood stand of decolumn finish of size 500mm x 700mm x 25mm fixed on MS angles grouted on the walls for keeping 'As made' sheets. The work also includes provision of Double Key Door lock arrangement for the Relay room. After the completion of bell testing the relays shall be individually tested and plugged carefully without disturbing the wiring.

Per Relay

503.00

  (Supply of relays, plug boards, connectors and retaining clips and 50 way terminal boards is not covered in this schedule).[Wire PVC 16/0.2mm copper, 2 BA terminals, hard wood plank of size 500mmx 700mmx25mm with decolumn finish, MS angles of size 25mmX25mmX6mm, relay fixing bolts and nuts, teakwood plank 25mm thick for fixing resistors and condensors, Plywood of thickness 12mm-teakwood finish of size 1200mmX1800mm with aluminium grooved channel frame for relay index board, paints, soldering materials, bunching thread, wire wound resistance, condensor, wire supporting tray with cover of suitable size made of PVC, double key door lock arrangement, paint, varnish and all other miscellaneous materials required for the work shall be supplied by the Contractor].

   

3005 Fixing of additional plug boards, 50 way terminal blocks and wiring of additional relays as per the approved circuit diagram using wire PVC 16/0.2mm copper. Additional wire suporting tray with cover made of PVC shall be provided wherever required. Alterations to Relay particulars shall be incorporated in the relay Index board.(Supply of relays, plug boards, connectors and retaining clips and 50 way terminal boards is not covered in this schedule).[Wire PVC 16/0.2mm copper, 2 BA terminals, teakwood plank 25mm thick for fixing resistors and condensors, soldering materials, bunching thread, wire wound resistance, condensor, wire supporting tray with cover of suitable size made of PVC, paint, varnish and all

Per Relay

341.60

Page 83: MEMU Master

Page 46 of 113

other miscellaneous materials required for the work shall be supplied by the Contractor].

3006 Carrying out alterations to the existing relays in the relay racks/apparatus cases as per the approved circuit diagram using wire PVC 16/0.2mm copper. The work includes releasing the unwanted wires carefully without disturbing the wiring.Wire PVC 16/0.2mm copper, soldering materials, bunching threads, condensors, resistances and teakwood plank for fixing them and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Per Relay

320.90

3007 Erection and concreting of SM's control panel on teakwood base frame 50mm x 150mm of suitable length and breadth, varnishing, termination of cables and wiring of knobs, buttons, indications, counters, etc., as per the approved circuit diagram with wire PVC 16/0.2mm copper. The work includes manufacture and provision of extension tables using hardwood with decolumn finish, fixing of one voltmeter, required No. of buzzers and wiring. The termination particulars shall be painted on the back doors of the panel.(Supply of SM's control panel is not included in the schedule).[Foundation bolts and nuts with washers, concreting materials, wire PVC 16/0.2mm copper, 50mmx150mm teakwood base frame, hardwood extension table with decolumn finish using 25mm thick planks and 75mmx75mm reapers, soldering materials, buzzers to work on 24VDC, one voltmeter 0-300V AC and all other consumable materials required shall be supplied by the Contractor].

   

  a. Erection, concreting and wiring of SM's control panel (upto 5 roads) Nos. 20279.00

  b. Erection, concreting and wiring of SM's control panel (more than 5 roads)

Nos. 30331.00

3008 Provision of Interconnections between relay racks, cable termination racks, SM's control panel, battery room, power room, termination and wiring. The work involves laying of underground cables in the duct as wells as with clamping arrangements on the walls, supply and fixing of aluminium ladders and supports with 3mm thick phynolic sheet for running the cables in the relay room. Interconnection shall be carried out with signalling multi core cable (skinned/ unskinned) and power cables as per the instructions of Railway representative at site. The work also include termination of the interconnection cables on 50 way terminals in the relay rack/ control panel, cable termination rack etc. After the interconnection cables are laid, the ducts shall be filled with river sand and closed. Wherever required the cables shall be taken to other floors in the building by clamping them on MS angles and flats grouted on the walls.

   

  (Supply of interconnection cables is not included in this schedule).[2BA terminals, Aluminium ladder arrangements using 37mmx37mmx5mm aluminium angles and 25mmx6mm aluminium flats, aluminium supports, phynolic sheet - 3mm thick for bottom of aluminium ladders, MS angles and flats, bolts and nuts, concreting materials, and all other materials required for the work shall be supplied by the contractor].

   

Page 84: MEMU Master

Page 47 of 113

  a. Provision of interconnection at stations (upto 5 roads). LS 34268.00

  b. Provision of interconnection at stations (more than 5 roads). LS 73744.00

3009 Installation of power equipments like battery chargers, transformers, transformer rectifiers, invertors, DC-DC converters etc., in the apparatus cases and wiring the same using wire PVC 7/1.4mm and 3/0.75mm copper as per the approved wiring diagram and painting of particulars in the inside of the doors of the apparatus cases. The work also includes provision of protective arrangements in bare terminals carrying high voltages.(Supply of power equipments is not included in this schedule).[Wire PVC 7/1.4mm and 3/0.75mm copper, protective arrangements, paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 785.30

3010 Carrying out alterations to the existing SM's control panel. The work includes drilling of holes on the Top plate wherever required, fixing and wiring of LEDs with holder, closing of unwanted holes, carrying out painting alterations on the panel, termination of additional cables and carrying out alteration to the existing wiring as per approved circuit diagram, releasing of unused wires, and painting of particulars as per the instructions of Railway representative at site.[LED lamps with holder, paint, soldering materials and all other miscellaneous materials required for the work shall be supplied by the Contractor].

LS 7049.00

3011 Provision of signalling arrangement during Non-Interlocked working of Signals and Points, such as erection and wiring of temporary relay racks and wiring of relays, SM's slide instruments, wiring alterations in the cable termination rack, apparatus cases, signals, Control panel etc, as per the instructions of Railway representative at site. This work includes temporary provision of PA system and Magneto telephone communication at places required which will be returned to the Contractor after the completion of NI working.(Supply of relay rack, relays, and SM slide instrument is not included in this schedule).[All other miscellaneous materials required for the work shall be supplied by the Contractor].

LS 16635.00

3012 Supply and wiring of LEDs with resistance on cable termination rack for indicating "FUSE BLOWN OUT" for each circuit. The LEDs and resistances shall be fixed on a phynolic sheet 50mm width and 3mm thick. The phynolic sheet shall be fixed by the side of the corresponding Fuse Blocks. Separate switch shall be provided for each circuit.[LEDs 10mm, holders, resistance, switch, phynolic sheet, soldering materials and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Per Fuse

28.80

3013 Supply and installation of 4 wire DTMF based way station equipment complete as per RDSO specification No.IRS.TC-60/93 and 4 wire control telephone with audio visual indication and reset button fitted on telephone conforming to specification No.IRS-TC-38/97. This

Set. 12971.00

Page 85: MEMU Master

Page 48 of 113

work also includes supply and wiring of power supply arrangements for way station equipment conforming to specification IRS.TC.72/97.[All the materials required for the work shall be supplied by the Contractor].

3014 Supply and provision of Rubber mat of not less than 6mm thick and with an insulation to withstand 650VAC, on the floor at places as indicated by railway representative at site.

sft 73.40

3015 Supply, fabrication and provision of suitable battery stand in the battery room using M.S.Angles 65mmx65mmx8mm and MS flats 50mmx6mm covered with 100mmx50mm hardwood reapers, and installation of secondary cells. The work involves charging of secondary cells, fixing and connecting the batteries with strips, manufacture and fixing of teakwood terminal box, termination of cables, wiring with suitable wire PVC 7/1.40mm and 3/0.75mm copper through suitable PVC pipes/ casing properly clamped, provision of battery particulars board - 12mm thick plywood - teakwood finish with aliminium grooved channel frame, painting of battery particulars, and provision of hydrometer -1 No. on a stand and battery tester-1 No. Charging of secondary cells shall be done by the contractor through reputed agencies.

   

  (Supply of secondary cells is not covered in this schedule).[MS angles 65mm x 65mm x 8mm, MS flats 50mm x 6mm, teakwood plank 25mm thick for manufacturing termination box with locking facility, hardwood reapers 100mmx50mm of required lengths, wire PVC 7/1.4mm and 3/0.75mm copper, anti-corrosive paint, varish, PVC pipes/ casing, and all other miscellaneous materials required for this work shall be supplied by the contractor].

   

  a. Provision of battery stand and installation of 2V-400AH cell per cell

791.00

  b. Provision of battery stand and installation of 2V-300AH cell per cell

696.60

  c. Provision of battery stand and installation of 2V-200AH cell per cell

584.00

  d. Provision of battery stand and installation of 2V-120AH cell per cell

484.40

  e. Provision of battery stand and installation of 2V-80AH cell per cell

445.50

3016 Charging and installation of secondary cells of the following capacities, on existing battery stand/ RCC slabs in the battery room. The work involves charging of secondary cells, fixing and connecting the batteries with strips, manufacture and fixing of teakwood terminal box, termination of cables,wiring with suitable wire PVC 7/1.40mm and 3/0.75mm copper through suitable PVC pipes/ casing properly clamped, provision of battery particulars board - 12mm thick plywood - teakwood finish with aliminium grooved channel frame, painting of battery particulars, and provision of hydrometer -1 No. on a stand and battery tester-1 No. Charging of secondary cells shall be done by the contractor through reputed agencies.(Supply of secondary cells is not covered in this schedule).

   

Page 86: MEMU Master

Page 49 of 113

[Teakwood plank 25mm thick for manufacturing termination box with locking facility, wire PVC 7/1.4mm and 3/0.75mm copper, anti-corrosive paint, varish, PVC pipes/ casing, and all other miscellaneous materials required for this work shall be supplied by the contractor].

  a. Installation of 2V-400AH on existing stand/slabs per cell

619.70

  b. Installation of 2V-300AH cell on existing stand / slabs per cell

525.30

  c. Installation of 2V-200AH on existing stand/slabs per cell

430.80

  d. Installation of 2V-120AH on existing stand/slabs per cell

358.60

  e. Installation of 2V-80AH on existing stand/slabs per cell

319.70

3017 Installation of charged secondary cells of the following capacities in apparatus cases, connecting them with strips, wiring with wire PVC 3/0.75mm copper and termination. This work also includes charging of cells through reputed agencies. The details of the batteries shall be written on the inside of the doors of the apparatus cases.(Supply of secondary cells is not included in this schedule).[Wire PVC 3/0.75mm copper, connecting strips, paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

   

  a. Installation of 2V-120AH cell in apparatus case per cell

258.60

  b. Installation of 2V-80AH cell in apparatus case per cell

219.70

3018 Supply and installation of Battery chager 110V/24V-15A in the apparatus cases, and wiring the using wire PVC 3/0.75mm copper as per approved circuit diagram. The work also includes painting of particulars on the inside of the doors of the apparatus cases.[Battery charger 110V/24V-15A, wire PVC 3/0.75mm copper, fixing materials, paint, and all other miscellaneous materials required for this work shall be supplied by the Contractor].

Nos. 24147.00

3019 Supply and installation of Battery chager 110V/24V-10A in the apparatus cases, and wiring the using wire PVC 3/0.75mm copper as per approved circuit diagram. The work also includes painting of particulars on the inside of the doors of the apparatus cases.[Battery charger 110V/24V-10A, wire PVC 3/0.75mm copper, fixing materials, paint, and all other miscellaneous materials required for this work shall be supplied by the Contractor].

Nos. 19647.00

3020 Supply, installation and wiring of Transformer rectifier 110VAC/24V DC - 2A capacity at Power room/apparatus cases and connecting it to the relevant circuit as per approved circuit diagram using wire PVC 3/0.75mm copper and painting of particulars as per Railway practice.Transformer rectifier 110V AC/24VDC - 2A capacity, wire PVC 3/0.75mm copper and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 5315.00

3021 Supply, installation and wiring of Transformer 110VAC/110VAC - Nos. 4182.00

Page 87: MEMU Master

Page 50 of 113

500VA capacity at Power Room/Apparatus cases and connecting it to the relevant circuit as per approved circuit diagram using wire PVC 3/0.75mm copper and painting of particulars as per standard Railway practice.[Transformer 110V AC/110VAC - 500VA capacity, wire PVC 3/0.75mm copper and all other miscellaneous materials shall be supplied by the Contractor].

3022 Supply, installation and wiring of Transformer 400VAC/110VAC - 500VA capacity at Power Room/Apparatus cases and connecting it to the relevant circuit as per approved circuit diagram using wire PVC 3/0.75mm copper and painting of particulars as per standard Railway practice. The work also includes provision of protective arrangements to cover the bare terminals with high voltages.[Transformer 400V AC/110VAC - 500VA capacity, wire PVC 3/0.75mm copper and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 4213.00

3023 Supply, fabrication and provision of suitable power equipment stand in the power room at stations (with more than 5 roads) using M.S.Angles 65mm x 65mm x 8mm and MS flats 50mmx6mm covered with 100mmx50mm hardwood reapers, as per the instructions of Railway representative at site, installation of power equipments and wiring the same using wire PVC 7/1.4mm and 3/0.75mm copper as per approved wiring diagram, fabrication and installation of Power panel Box type using powder coated 16G MS sheet with inbuilt locking facility with a power distribution board fitted inside made of Phynolic synthetic industrial fibre base fine weave cotton fibre sheet of size 1200mm X 1200mm X10mm. Terminations using circuit breakers, HRC fuse blocks and PBT terminals shall be provided on the phynolic sheet. Voltmeters, ammeters and by pass switches shall be fitted on the front side of the MS power panel. This work includes installation of power distribution diagram board using plywood of thickness 12mm-teakwood finish of size 1200mmX1800mm with aluminium grooved channel frame and painting of particulars on power distribution diagram board. The work also includes provision of single key door lock arrangement for the power equipment room.

Set. 101359.00

  (Supply of power equipments is not covered in this schedule).[MS angles 65mmx65x8mm, Phynolic synthetic industrial fibre base fine weave cotton fibre sheet of size 1200x1200x10mm, Hard Wood planks for reapers 100x50mm, Power coated 16G MS sheet, teakwood base planks 25mm x 150mm and 50mm x 50mm for fixing cables, 50mm, bolts & nuts required for manufacturing power panel & power rack, circuit breakers, HRC Fuses with base and carrier, ammeters, voltmeter- 3 Nos., by-pass switches for stabilisers-63A capacity - 3 Nos., power distribution diagram board using Plywood of 12mm thickness - TW finish of size 1200X1800mm with Aluminium grooved channel frame, paints, wire PVC 7/1.4mm and 3/0.75mm copper, Single Key Door lock arrangement, and all other miscellaneous materials required for the work shall be supplied by the contractor].

   

3024 Installation of power equipments on the existing stands/ RCC slabs in the power room stations (with more than 5 roads) and wiring the

Set. 90822.00

Page 88: MEMU Master

Page 51 of 113

same using wire PVC 7/1.4mm and 3/0.75mm copper as per approved wiring diagram, fabrication and installation of Power panel Box type using powder coated 16G MS sheet with inbuilt locking facility with a power distribution board fitted inside made of Phynolic synthetic industrial fibre base fine weave cotton fibre sheet of size 1200mm X 1200mm X10mm. Terminations using circuit breakers, HRC fuse blocks and PBT terminals shall be provided on the phynolic sheet. Voltmeters, ammeters and by pass switches shall be fitted on the front side of the MS power panel. This work includes installation of power distribution diagram board using plywood of thickness 12mm-teakwood finish of size 1200mmX1800mm with aluminium grooved channel frame and painting of particulars on power distribution diagram board. The work also includes provision of single key door lock arrangement for the power equipment room.

  (Supply of power equipments is not covered in this schedule).[Phynolic synthetic industrial fibre base fine weave cotton fibre sheet of size 1200x1200x10mm, Power coated 16G MS sheet, teakwood base planks 25mm x 150mm and 50mm x 50mm for fixing cables, 50mm, bolts & nuts required for manufacturing power panel & power rack, circuit breakers, HRC Fuses with base and carrier, ammeters, voltmeter- 3 Nos., by-pass switches for stabilisers-63A capacity - 3 Nos., power distribution diagram board using Plywood of 12mm thickness - TW finish of size 1200X1800mm with Aluminium grooved channel frame, paints, wire PVC 7/1.4mm and 3/0.75mm copper, Single Key Door lock arrangement, and all other miscellaneous materials required for the work shall be supplied by the contractor].

   

3025 Supply, fabrication and provision of suitable power equipment stand in the power room at stations (up to 5 roads) using M.S.Angles 65mmx65mmx8mm and MS flats 50mmx6mm covered with 100mmx50mm hardwood reapers, installation of power equipments and wiring the same using wire PVC 7/1.4mm and 3/0.75mm copper as per approved wiring diagram, manufacture of power panel using phynolic sheet 1200mm x 1200mm x 10mm and erecting it using MS angles 25mm x 25mm x 6mm and fixing of meters, stabilizer and ammeter by pass switches, HRC fuse blocks, PBT terminals 60mm centre and connecting the power equipments to the power panel. as per approved power diagram, in the power room. This work also includes provision of power distribution diagram board using plywood of thickness 12mm-teakwood finish of size 1200mm x 1800mm with aluminium grooved channel frame and painting of particulars on power distribution diagram board. The work also includes provision of single key door lock arrangement for the power equipment room.(Supply of power equipments like battery charger, transformers, transformer rectifiers, voltage stabilizers, DC-DC converter, invertors etc., is not included in this schedule).

Set. 76766.00

Page 89: MEMU Master

Page 52 of 113

  [MS Angles 50mm x 50mm x 8mm and 25x25x6mm, MS flat 50mm x 6mm, hardwood reapers 100mm x 50mm of required lengths, phynolic sheet of size 1200x1200x10mm, teakwood planks 25x150mm for fixing cables, teakwood cable clamps 50x50mm, bolts & nuts required for manufacturing power panel, HRC Fuses base and carrier, Ammeters, Voltmeters, main switch, by-pass switches for ammeter and stabilisers-63A capacity, power distribution diagram board using Plywood of 12mm thickness - teakwood finish of size 1200X1800mm with Aluminium grooved channel frame, paints, PBT terminal blocks 60mm centre wherever required, wire PVC 7/1.4mm and 3/0.75mm copper, Single Key Door lock arrangement, and all other miscellaneous materials shall be supplied by the contractor].

   

3026 Installation of power supply equipments for stations (upto 5 roads) on existing equipment stand/ RCC slabs and wiring the same using wire PVC 7/1.4mm and 3/0.75mm copper, manufacture of power panel using phynolic sheet 1200mm x 1200mm x 10mm and erecting it using MS angles 25mm x 25mm x 6mm and fixing of meters, stabiliser and ammeter by pass switches, HRC fuse blocks, PBT terminals 60mm centre and connecting the power equipments to the power panel.as per approved power diagram, in the power room. This work also includes provision of power distribution diagram board using plywood of thickness 12mm-teakwood finish of size 1200mm x 1800mm with aluminium grooved channel frame and painting of particulars on power distribution diagram board. The work also includes provision of single key door lock arrangement for the power equipment room.(Supply of power equipments like battery charger, transformers, transformer rectifiers, voltage stabilisers, DC-DC convertor, invertor etc., is not included in this schedule).

Set. 66728.00

  [MS Angles 25x25x6mm, Hylum Sheet of size 1200x1200x10mm, teakwood planks 25x150mm for fixing cables, teakwood cable clamps 50x50mm, bolts & nuts required for manufacturing power panel, HRC Fuses base and carrier, Ammeters, Voltmeters, main switch, by-pass switches for ammeter and stabilisers-63A capacity, power distribution diagram board using Plywood of 12mm thickness - teakwood finish of size 1200X1800mm with Aluminium grooved channel frame, paints, PBT terminal blocks 60mm centre wherever required, wire PVC 7/1.4mm and 3/0.75mm copper, Single Key Door lock arrangement, and all other miscellaneous materials shall be supplied by the contractor].

   

3027 Installation of double line SGE type block instruments on the block counter. The work involves termination of cables on the test panel and block counter, block wiring, interconnection between test panel and block instrument by underground signalling cable and painting the instrument as per the instructions of in consultation with Railway representative at site.(Supply of block instruments, block counters and underground cables is not covered in this schedule).[Phynolic sheet for fixing terminals, wire PVC 16/0.2mm copper, 3/0.75mm, paint, and all other miscellaneous materials required for the

Nos. 5357.00

Page 90: MEMU Master

Page 53 of 113

work shall be supplied by the contractor].3028 Installation of single line push button token less block instruments on

teakwood base frame. The work involves termination of cables on the test panel, block wiring including duplicating switch for "Train Arrival" and interconnection between test panel and block instrument by underground signaling cable and painting the instrument in consultation with Railway representative at site.(Supply of block instrument and underground cables is not included in this schedule).[Wire PVC 16/0.2mm copper, 3/0.75mm, Teak Wood base frame of size 50mmx 150mm, foundation bolts, paint, concreting materials and all other miscellaneous materials required for the work shall be supplied by the contractor].

Nos. 7522.00

3029 Installation of single line token block instruments on the block counter. The work involves termination of cables on the test panel and block counter, block wiring, interconnection between test panel and block instrument by underground signaling cable and painting the instrument as per the instructions of in consultation with Railway representative at site.(Supply of block instruments, block counters and underground cables is not covered in this schedule).[Phynolic sheet for fixing terminals, wire PVC 16/0.2mm copper, 3/0.75mm, paint, and all other miscellaneous materials required for the work shall be supplied by the contractor].

Nos. 6223.00

3030 Installation of single line FM type token less block instruments on the block counter. The work involves termination of cables on the test panel and block counter, block wiring, interconnection between test panel and block instrument by underground signaling cable and painting the instrument as per the instructions of in consultation with Railway representative at site.(Supply of block instruments, block counters and underground cables is not covered in this schedule).[Phynolic sheet for fixing terminals, wire PVC 16/0.2mm copper, 3/0.75mm, paint, and all other miscellaneous materials required for the work shall be supplied by the contractor].

Nos. 8107.00

3031 Manufacture and fixing of glass fronted TW Test panel, lightning dischargers with base, DPDT switches etc. This work includes bringing of control and block wires separately for each block and control from wall brackets to the test panel through PVC pipes of size 25mm dia suitably clamped and terminating them in the test panel as instructed by Railway representative at site with PVC 3/0.75mm copper .[Glass fronted test panel made of 25mm thick TW with individual locking facilities for block and control, 4 Nos. of DPDT Switches, PBT Terminal 60mm centre, lightning discharger with base, PVC tubes 15/20mm of size, wire PVC 3/0.75mm copper and all other required miscellaneous materials shall be supplied by the contractor].

Set 5220.00

3032 Installation of SM's slide instrument (upto 24 slides) in station/ cabin on block counters/ hard wood plank (not less than 25mm thick) supported by MS angle 65 x 65 x 8 mm duly grouted on wall. This

Nos. 6910.00

Page 91: MEMU Master

Page 54 of 113

work includes provision of a teakwood termination box with locking arrangement, termination of cable inside the box and wiring of SM's control instrument. The cable shall be taken through GI pipe duly clamped the wall.(Supply of SM slide instrument is not covered in this schedule).[Brass screws, paints, GI lock, phynolic sheet 6mm thick, wire PVC 16/0.2mm and 3/0.75mm copper, and other required miscellaneous materials shall be supplied by the Contractor].

3033 Supply, erection and wiring of diesel generator set, 6KVA, 230VAC, single phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 2 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 200542.00

3034 Supply, erection and wiring of diesel generator set, 7.5KVA, 230VAC, single phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 2 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 211399.00

3035 Supply, erection and wiring of diesel generator set, 10KVA, 230VAC, single phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 2 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 250470.00

3036 Supply, erection and wiring of diesel generator set, 15 KVA, 230VAC, 3 phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This

Nos. 256485.00

Page 92: MEMU Master

Page 55 of 113

work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 4 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

3037 Supply, erection and wiring of diesel generator set, 20KVA, 230VAC, 3 phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 4 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 298151.00

3038 Supply, erection and wiring of diesel generator set, 25KVA, 230VAC, 3 phase - KIRLOSKAR make with CPCB type approved Acoustic enclosure as per the instructions of Railway representative at site. This work includes supply of control panel, exhaust pipe, changeover switch, phase selection switch and provision of interconnections between the DG set, control panel, changeover switch, phase selection switch, and painting.[Diesel generator set with CPCB approved acoustic enclosure, iron clad changeover switches 4 pole 3 position - 63 amps capacity, phase selction switch 4 pole, 2 position - 63 amps capacity, exhaust pipe, asbestos rope, wire PVC 7/1.4mm copper, PVC pipes and bends, clamps and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 345204.00

3039 Supply and wiring of Diagnostic panel in the relay room similar to control panel for dispalying aspects and conditions of signals, points, track circuits, LC gates etc., by using LEDs and phynolic sheet of size 600mmx900mmx5mm.Wiring to be done similar for control panel.[Phynolic sheet of size 600mmx900mmx5mm, LED-5mm/ 3mm size, with holders, wire PVC, soldering materials, paint, frame for the boards, fixing bolts and nuts with washers and all other miscellaneous materials required for the work shall be supplied by the contractor)

Nos. 27704.00

Page 93: MEMU Master

Page 56 of 113

3040 Supply and installation of distilled water plant similar to `KILBURN' make capacity 3.5 to 4.5 Lits. per hour, with two detachable heating elements of 1500W each to work on 230VAC, single phase, fitted with automatic cut-outs and removable connectors, with Stainles Steel boiling chambers, condensor pipe, toughened glass lid; The work includes supply and installation of fibre tank `SINTEX' make - 200 lts, capacity, provision of water supply connection from water tap to water tank, water tank to distilled water plant using G.I Pipes 25mm dia and with regulating valves, provision of separate power supply socket and wiring. This work includes fixing of 2 Nos. of rails on the wall and grouting as instructed by Railway representative at site.(Cut rails will be supplied by Railways).[Distilled water plant, sintex tank 200 Litres capacity, GI pipe 25mm dia, power plug with socket, regulating valves, jelly, cement, sand and other materials shall be supplied by the Contractor].

Nos. 13822.00

4001 Installation of 2 Slide SM's control Instrument at LC gate on a hard wood plank (not less than 25mm thick) supported by MS angle 65 x 65 x 8 mm duly grouted on wall. This work includes provision of small termination box with locking arrangement, termination of cable inside the box and wiring of SM's control instrument. The cable shall be taken through GI pipe duly clamped the wall.(Supply of SM slide instrument is not covered in this schedule).[Brass screws, paints, GI lock, PBT terminals, phynolic sheet 6mm thick, wire PVC 16/0.2mm and 3/0.75mm copper, and other required miscellaneous materials shall be supplied by the Contractor].

Nos. 3172.00

4002 Installation of Illuminated Diagram Board above the SM's control Instrument at Level Crossing gates, wiring the same including interconnections and painting.(Supply of Illuminated Diagram board is not included in this schedule).[wire PVC 16/0.2mm copper, soldering materials, LEDs, resistances and all other required miscellaneous materials shall be supplied by the Contractor.].

Nos. 2768.00

4003 Excavation of pit, concreting `A' type foundation and fixing ground lever frames single/double as per Drg.No.SG/CN/02/11 complete with ground connection. The work includes concreting of `A' type foundations and fixing of HP lock and connecting the ground lever frame with the HP lock using MS rod as instructed by Railway representative at site. (Supply of ground lever frames, hand plunger locks and `A' type foundations is not covered in this schedule).[cement, river sand, stone jelly of size 20/25mm, `E' type locks, fixing bolts and nuts with washers and all other miscellaneous materials shall be supplied by the Contractor.}

Nos. 3896.00

4004 Interlocking of level crossing gate with Swing Gates: This work consists of fixing of gate locks on the gates and fixing of `E' type locks - 1 No. for each gate as per instructions of Railway representative at site.The arrangement shall be painted as per standard Railway practice.

Nos. 4549.00

Page 94: MEMU Master

Page 57 of 113

(Supply of gate locks is not covered in this schedule).[`E' type locks with keys of required ward, MS plates, paints, all types of bolts and nuts and all other miscellaneous materials shall be suuplied by the Contractor]

4005 Interlocking of level crossing gate with Lifting Barrier: This work consists of fixing of one `E' type lock on the Lifting barrier winch with suitable plate, cutting of notches on the drum of the plate, fixing and levelling of trestles, rod roller assembly, levelling and concreting of `A' type foundations, fixing of rod diversion cranks, vertical cranks, running of rods (app. 30mtrs.) and connecting them to lever tail at one end and boom locking arrangement at the other end, and painting as per standard practice.

(Supply of rods, `A' type foundations, trestles, segments, rod roller assembly complete and cranks is not covered in this schedule).[cement, river sand, stone jelly of size 20/25mm dia, coal bengal,`E' type locks with keys of required ward, MS plates 20mm thickness, paints, all types of bolts & nuts and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 11137.00

4006 Casting concrete foundation of size 900mmX900mmX900mm for pedestal, 400mmX400mmX600mm for meeting post, fixing of lifting barrier boom, contact makers, termination of cables, wiring and painting as per the instructions of Railway representative at site.(Supply of pedestals, meeting posts, contact maker, electric lifting barriers, rail posts, cranks and ‘A’ type foundation is not covered in this schedule).[Concreting materials, bolts and nuts, wire PVC 3/0.75mm copper and all other miscellaneous materials required for the work shall be supplied by the Contractor].

per boom

9507.00

4007 Provision of of boom locking arrangement for both the lifting barrier which involves running of about 30m to 50m of rodding with a spacing of 2m interval between trestles with rod roller segments, fixing of about 8 Nos. of cranks on 'A' type foundation/ MS plates and concreting of 'A' bases to a size of 1mX0.6mX0.5m as instructed by Railway representative at site. Solid joints shall be provided wherever required and joining of rodding/ joints shall be done by smithy welding.(Supply of MS rods cranks, trestles, segments, rollers etc., is not covered in this schedule).[All other materials required for the work shall be supplied by the Contractor].

per LC

5624.00

4008 Fixing and wiring of Two Nos. of Electronic Gate Warning equipment for each level crossing gate, one on each road warning signal, amplifier in the apparatus case with wire PVC 3/0.75mm and 16/0.2mm copper, and painting.(Electronic Gate Warning Equipment and amplifier will be supplied by Railways).[All wiring, fixing and painting materials shall be supplied by Contractor].

Set 1938.00

4009 Design, fabrication and supply of Gate Indication Panel of 16 SWG, Nos. 6319.00

Page 95: MEMU Master

Page 58 of 113

powder coated MS sheet of size 390mm x 240mm x 100mm approximately consisting of different colour LEDs with holders suitable to work on 12VDC supply. Indications on the front panel shall be as per typical diagram supplied by Railways. All descriptions on the front panel have to be screen printed. The Panel shall then be wired using wire PVC 16/0.2mm copper as per the approved circuit diagram and installed in the gate lodge as instructed by Railway representative at site.[All materials required for the work shall be supplied by the Contractor].

4010 Installation of hand plunger lock with "E" type locks and keys [single/double] on gauge tie plate for locally operated siding point/trap point, connecting the point to ground frame and adjusting them. The work includes cutting suitable notches on split stretcher bars, provision of suitable MS cover of 3mm thick for the hand plunger lock, provision of point/trap indicator and painting.(Supply of hand plunger locs and point/ trap indicator is not covered in this schedule).[Un-cut split stretcher bars for HP Lock Single/Double, "E" type lock with keys, MS cover 3mm thick, coal bengal, fixing bolts and nuts with washers, paint and all other miscellaneous materials required for the work shall be supplied by the contractor].

   

  a. Installation of H.P.locks (double) Nos. 6909.00

  b. Installation of H.P.locks (Single) Nos. 5470.00

  c. Fixing of point/ trap indicator Nos. 995.00

4011 Fixing of electrical detectors on extended gauge tie plate, providing insulations, connecting ground connections, wiring with wire PVC 3/0.75mm copper, connecting the detector and TLD box through a hose pipe, drawal of jumper wires from the detector to TLD box and painting.(Supply of Electrical detectors complete, switch extension pieces, ground connections, extended gauge tie plate, TLD boxes with stumps is not covered in this schedule).[Wire PVC 3/0.75mm copper, PVC hose pipe, all fixing bolts and nuts, all types of insulations, paint and all other miscellaneous materials required for this work shall be supplied by the contractor).

Nos. 2908.00

4012 Supply and installation of teakwood glass fronted box of size 300mm x 600mm x 75mm with hooks to keep various keys with description engraved on the tags.[TW Glass fronted box of size 300mmx600mmx 75mm with built in lock, hooks, engraved tags and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 2748.00

Page 96: MEMU Master

Page 59 of 113

4013 Manufacture and supply of teak wood tool box of size 1000X750X100mm made of 25mm thick teak wood persplex sheet fronted 6mm (Colourless) fixed on the wall at a convenient location as instructed by Railway representative at site. The board should have provision of pad lock and locking arrangements and shall be equiped with the following tools:

c. Digital Mulltimeter similar to Model No.Rish Multi 15S with suitable carrying case and test probes.

b. Multimeter similar to Model No.HM 102 BZ Hungchung with test probes with suitable carrying case.- 1 No.c. Centre zero ammeter 30-0-30 Amps - 1 No.d.. Screw drivers of different types and sizes with common handle - 1 set

e. Spanner double ended 33mm - 1 No. f. Spanners double ended 3/8x1/2" - 1 No.g. Spanners double ended 5/8x3/4" - 1 No. h. Spanners double ended 7/8x1" - 1 No. i. Hammer 1 1/2 lbs ball pane - 1 No. j. Hacksaw frame - 1 No. k. Adjustable screw spanner 12" - 1 No. l. Insulated cutting pliers- 1 No.m. Insulated nose plier- 1 No. n. Electric soldering iron 230V 60W Soldron/Philips make - 1 No.o. Megger 500V/ 500Mohms. with Probe - 1 No.

Set 14400.00

  The above tools shall be purchased from Reputed manufacturers only in consultation with the Railway representative at site.[Teak wood tool box made of 25mm teak wood plank, Perspex sheet, all the tools mentioned above, padlock and other miscellaneous items shall be supplied by the Contractor].

   

4014 Fixing of EKT instrument with (or) without crank handle or on suitable fixtures at station/apparatus case, provision of economizer push switch with locking facility, wiring with wire PVC 16/0.2mm copper, termination of cables and jumper wires on PBT terminal in a teakwood terminal box covered with decolum along with locking facility and painting.(Supply of electric key transmitter and crank handles is not covered in this schedule).[wire PVC 16/0.2mm copper, wire wound resistance, decolum covered terminal box with locking facility by using 25mm thick teakwood, bolts and nuts, paints, push switches, padlocks and other miscellaneous materials required for this work shall be supplied by the contractor].

Nos. 2463.00

4015 Fixing of 'E' type lock in the emergency gate key contact box to be fixed on suitable fixtures at station/ LC gate lodges in a separate box

Nos. 2707.00

Page 97: MEMU Master

Page 60 of 113

covered with decolum finish with sealing and locking facility, wiring with 3/0.75sq.mm copper wire, termination of cables and jumper wires on PBT terminals and painting.[E' type lock with long plunger for emergency gate key, PVC 3/0.75mm copper, teakwood planks 25mm thick, bolts and nuts, decolam sheets, paints, padlocks, 1 NO + 1 NC limit switch and all other miscellaneous materials required for the work shall be supplied by the contractor].

4016 Casting concrete foundation and erection and painting of boards with `LEGEND' such as "Draw close if signal is at on" at the required places as per the Signalling plan. The work involves concreting of rail post to a size of 600mm x 600mm x 900mm, and fixing the board to the rail using MS clamps, bolts and nuts.(Supply of boards is not covered in this schedule. Rails of different lengths will be supplied by Railways and the Contractor has to cut them to the required lengths)[Stone jelly of size 20/25mm dia, river sand, cement, M.S.flats, fixing bolts and nuts, paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 1844.00

4017 Painting, erection and concreting of Goods warning boards on rails as per the Signalling plan. The work includes manufacturing of clamps and fixing the board to the rails, supply and fixing of scotch lite reflectors and concreting the rail post to a size of 600mmx600mmx900mm.(Supply of goods warning boards is not covered in this schedule. Rails of different lengths will be supplied by Railways and the Contractor has to cut them to the required lengths).[Stone jelly of size 20/25mm dia, river sand, cement, M.S.flats, scotch lite strips (14 Nos) for each board, fixing bolts and nuts, paint and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 2491.00

4018 Installation of post type telephone on home signal post inside post type telephone box, provision of Limit switch, as required by Railways and wiring. The tail cable for Signal Post Telephone Box shall be taken through GI pipe of 50mm dia properly clamped. [Post type telephone box, Wire PVC 3/0.75mm copper, Nicady power pack 4v-2.2AH with suitable charger to work on 110v Ac, Magneto Telephone, Limit Switch having configuration of 1NO+1NC, fixing bolts and nuts, GI pipe 50mm dia and all other miscellaneous materials shall be supplied by the Contractor].

Nos. 6939.00

Page 98: MEMU Master

Page 61 of 113

4019 Supply and installation of magneto telephone handle type alomg with Ni-cad power pack 4V-2.2AH with charger to work on 110VAC, at the station house, LC Gate and top points. For telephones connected in pair with Signal Post Telephones, the work involves provision of teakwood box with locking facility for fixing the magneto telephone and provision of buzzers to work on 24VDC.[Magneto telephone handle type with Ni-cad power pack 4V-2.2AH with charger to work on 110VAC, wire PVC 16/0.2mm copper, and all other miscellaneous materials shall be supplied by the Contractor. For sub-item (b) the Contractor shall also supply a teakwood box with locking facility mounted on the wall and buzzer to work on 24V DC].

   

  a. Supply & wiring of magneto telephone at station/ LC gates/ apparatus cases

Nos. 5409.00

  b. Supply and wiring of magneto telephones in pair with SPT Nos. 6089.00

4020 Fixing of Annunciator at SM's Room as required by Railways, wiring it as per circuit diagram and painting of particulars. The work includes connecting 1 No. of magneto telephone with Ni-cad power pack 4V-2.2AH with charger to work on 110VAC and connecting the annunciator to the different telephone circuits. The particulars of the circuits and the ringing codes shall be painted on the top of the annunciator box. (Supply of annunciator is not included in this schedule). [Magneto telephone handle type with Nicad power pack 4V-2.2AH with charger to work on 110VAC, wire PVC 16/0.2mm copper, paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 5703.00

4021 Installation and wiring of existing Way station equipment DTMF and control telephones. The work involves fixing the released way station equipment on the wall at an appropriate place in consultation with Railway representative at site, wiring and interconnecting the same with test panel, control telephones and batteries. (Supply of way station equipment, control telephones and batteries is not included in this schedule). [Wire PVC 3/0.75mm & 16/0.2mm copper, MS clamps for fixing arrangements, PVC tubes 25mm dia for interconnections and all other miscellaneous items required for the work shall be supplied by the Contractor].

Set. 3656.00

Page 99: MEMU Master

Page 62 of 113

4022 Supply and installation of Signal post telephone with facility of paging and talk-back including voice communication equipment with suitable switching arrangement at the Signal post and at SM's room as per specification enclosed in this document. This includes drawal of tail cable through GI pipe 25mm dia and 2 mtrs long duly clamped to Signal post with bend as required at site, termination of tail cable at one end in the apparatus case and other end in the console. In the SM's room, console shall be fixed on a table top. The wiring shall be done using wire PVC 16/0.2mm copper. [Talk-back equipment complete including housing box, wire PVC 16/0.20mm and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Set. 8211.00

4023 Excavation of pit and construction of masonary platform as per drawing No. SG/CN/02/12 with bricks of size 200mmx100mmx60mm (app) at the foot of signal post telephones as per the instructions of Railway representative at site.[Country bricks of size 220mmx100mmx60mm (app), cement, river sand and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 2314.00

4024 Painting of existing boards like LEGEND boards, warning boards, STOP boards etc., as per standard practice and as per the instructions of Railway representative at site.(Supply of boards is not included in this schedule).[Paint and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 528.00

4025 Alteration to existing Illumination diagram board. The work involves drilling of holes and fixing of LEDs and wiring using wire PVC 16/0.2mm copper, removing the unwanted LEDs and wires, closing the holes, and carrying out painting alterations as per the instructions of Railway representative at site.[All materials required for this work shall be supplied by the Contract].

Nos. 1710.00

4026 Supply and installation of yard layout diagram board in the station master's room. The board shall be made of Phynolic synthetic industrial fibre base fine weave cotton fibre board (matt finish) 6mm thick size 1800mm X 1200mm with aluminium channel frame. The yard layout shall be neatly painted and fixed as instructed by Railway representative at site.[All materials required for the work shall be supplied by the Contractor].

Nos. 7238.00

Page 100: MEMU Master

Page 63 of 113

4027 Provision of fire fighting equipments. The work involves supply and installation of the following equipments at places as instructed by Railway representative at site.a. Photo Electric Smoke Detector (similar to Vigilant Model : DS-7001 of M/.s.Naveen Alarm Systems) - 8 Nos.b. Two Zone Fire alarm panel (similar to Model : NSB 400 of M/s.Naveen Alarm Systems) - 1 No.c. ABC 5 Kg. capacity stored pressure fire extinguisher - 2 Nos.d. Hooter to work on 24 VDC - 1 No.Wiring shall be done using underground cable as per the instructions of Railway representative at site.(Supply of underground cable is not covered in this schedule).[Photo electric smoke detector, 2 zone fire alrm panel, fire extinguisher, hooter and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Set. 28367.00

4028 Supply of 2 pin socket - 5A with switch, fixing the same on the hardwood plank available and extending the 110VAC using wire PVC 3/0.75mm copper, in al the apparatus cases, as per the instructions of Railway representative at site.[2 pin socket - 5A with switch, wire PVC 3/0.75mm copper and all other miscellaneous materials required for the work shall be supplied by the Contractor].

Nos. 291.00

4029 Testing and commissioning the entire signalling installations jointly with the Railway representative at site at the stations/ LC gates covered under vaious scheduls of the Contract, and ensuring that all the signalling gears are installed and adjusted as per the existing rules. The work also involves supply of required number of bound registers with good quality papers with all updated details of cable meggering, relays, batteries, block joints, route cancellation, relay room key entries, block instrument key, earth resistance etc., and handing over to Railways.(Supply of 'As mades' is not covered in this schedule).

   

  a. Testing and commissioning of stations (upto 5 roads) LS. 15915.00

  b. Testing and commissioning of stations (with more than 5 roads) LS. 27775.00

  c. Testing and commissioning of LC gates LS. 6061.00

4030 Submission of all relevent final `Asmades' of circuit diagrams, contact analysis charts, termination particulars of apparatus cases and cable termination rack, power supply arrangements, relay index board, cable plans, cable route plans, red boundary plans and all other particulars covered under various schedules. All 'As mades' shall be prepared by the Contractor in AUTOCAD 2000 and submitted in CDs. One copy of the 'As mades' shall be submitted before Bell Testing the circuits. The final negatives shall be made in R.P film. All 'As mades' except cable plan and cable toute plan shall be prepared in A3 size.On approval the contractor shall submit along with the negatives, 8 copies in each, duly making booklet neatly bound. Out of 8 sets, 2 sets of drawings and other plans shall be kept in thick plastic cover with hanger arrangements for each cover (2 sheets back to back in one plastic cover) and handed over to Railways. The approved circuit diagram will be issued by Railways in soft copy as well as two sets of hard copies.

Per 'A3' size negative sheet

167.80

Page 101: MEMU Master

Page 64 of 113

  Wherever alterations to existing circuits are involved, the existing as-made circuit diagrams will be supplied by Railways either in CDs or RP film. The Contractor shall incoporate the details of all the new wirings and alterations in the CD/ RP film and submit them to Railways. On approval 8 copies shall be made for As-made circuit diagrams also as mentioned above.

   

4031 Designing of Signalling plan in AUTOCAD 2000 and submission of negatives in 85/90 gsm tracing paper in 'U' size along 2 copies and also the soft copy in compact disks induplicate. First, 2 sets of prints shall be supplied to Railways for checking. One set will be returned by Railways to the contractor for making corrections in AUTOCAD. The final corrected drawings shall be supplied to Railways on 85/90 gsm tracing paper and 2 CDs.(Approved permanent way plan will be supplied by Railways).

per 'U' size sheet

3341.00

4032 Designing of circuits diagrams/ table of control in AUTOCAD 2000 (including contact numbers on the circuit) and submission of negatives in 85/90 gsm tracing paper in 'A3' size along 2 copies and also the soft copy in compact disks induplicate. First, 2 sets of prints shall be supplied to Railways for checking. One set will be returned by Railways to the contractor for making corrections in AUTOCAD. The final corrected drawings shall be supplied to Railways on 85/90 gsm tracing paper and 2 CDs.Approved Signalling plan will be supplied by Railways for preparing table of control. Approved table of control will be supplied by Railways for preparing circuits diagrams).

per A3 size sheet

380.00

5001 Releasing of existing relay racks/ cable termination racks along with all the terminals, fuse blocks, relays, with jacks, holding clips etc., 50 way boards, terminals, connecting wires, cables etc., carefully without causing any damage, accounting and stacking them neatlty at a place as instrutrc by Railway representative at site. After releasing, the floor shall be levelled and cement plastered.

Per rack

826.50

5002 Releasing of existing Route Indicators of different types including tail cables, carefully without causing any damage, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Nos. 623.50

5003 Breaking of concrete and releasing of STOP board/Warning board/ LEGEND boards along with rails, accounting and stacking them neatly at a place as instructed by Railway reoresentative at site. Also the resultant pits shall be re-surfaced and consolidating by ramming and levelling.

Nos. 625.00

5004 Releasing of existing point lay-out with facing point lock, split stretchers, electrical detector, lock bars, point/trap indicators cranks, rods etc., carefully without damaging the materials accounting and stacking them neatly at a place as instructed by Railway representative at site.

Set 1140.00

Page 102: MEMU Master

Page 65 of 113

5005 Releasing of hand plunger lock single/double along with switch extension pieces, stretcher bars, point/ trap indicators and other fixtures carefully without damaging the materials accounting and stacking them neatly at a place as instructed by Railway representative at site.

Set 952.50

5006 Releasing of Protection bar with all other connected accessories carefully without damaging the materials accounting and stacking them neatly at a place as instructed by Railway representative at site.

Nos. 616.50

5007 Releasing of S.M's Control instrument upto 24 Slides, Illuminated Diagram, block counter and other connected gadgets without any damage to the materials, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Set 1919.00

5008 Releasing of existing apparatus cases (Full/ Half/ Quarter size) without damage after releasing the shelf planks, Terminal blocks, Fuse Blocks, Terminal Boards, Relays of all types EKTs, Secondary Cells, power equipments, 'E' type locks, etc., and breaking the concrete foundation. After releasing, the resultant pits are to be closed and consolidated by ramming and levelling. The released materials shall be accounted and stacked at a place as instructed by Railway representative at site.

Nos. 1202.50

5009 Releasing of existing sheet iron battery boxes without damage after releasing the shelf planks, Terminal blocks, Fuse Blocks, Terminal Boards, Relays of all types EKTs, Secondary Cells, power equipments, 'E' type locks, etc., and breaking the concrete foundation. After releasing, the resultant pits are to be closed and consolidated by ramming and levelling. The released materials shall be accounted and stacked at a place as instructed by Railway representative at site.

Nos. 1062.50

5010 Breaking of concrete and releasing the existing cable termination boxes, after releasing the base plank, Terminal blocks, Fuse Blocks, Terminal Boards, cut rails, pipes, etc., closing the resultant pits and consolidating it by ramming and levelling. The released materials shall be accounted and staled neatly at a place as instructed by Railway representatice at site.

Nos. 797.00

5011 Releasing of existing SM's control panel including base plank, and other gadgets connected very carefully without causing any damage to the panel, acounting and stacking them neatly at a place as instructed by Railway representative at site. The resultant pit in the flooring shall be removed of all cable bits, levelled and cement plastered.

Set 2180.00

5012 Dismantling and releasing of existing Colour light Signals complete (upto 4 aspects) with or without Route Indicators, calling on signals, shunt signals etc., carefully without any damage to the gadgets, accounting and stacking them neatly at a place as instructed by Railway representative at site. The work includes breaking the concrete foundation, closing the resultant pit and resurfacing it by ramming and levelling.

Nos. 1233.00

Page 103: MEMU Master

Page 66 of 113

5013 Dismantling and releasing of existing Point machines (all types) including ground connections and other accessosories available complete without any damage to the gadgets, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Nos. 1077.50

5014 Dismantling and releasing of ground lever frame along with all connected gadgets like lever locks, `E' type locks, HP locks, etc., accounting and stacking them neatly at a place as instructed by Railway representative at site. The work also involves breaking and removal of concrete foundation and the resultant pit shall be filled and consolidated by ramming and levelling.

Set. 2216.00

5015 Releasing of Secondary cells and battery stands available in the battery room along with connecting strips, wires and terminal boxes carefully without causing any damage to the batteries, accounting and stacking them neatly at a place as instructed by Railway representative at site. After releasing any holes in the walls/ flooring shall be filled with cement mortar and plastered.

Set 2155.00

5016 Releasing of existing Block Instruments (all types), Block counters, batteries, block filter, block bell equipment etc., carefully without any damage, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Nos. 716.50

5017 Releasing of existing block/ control wiring along with DPDT switches, Lightning dischargers, wires, boards including the junction box in station buildings, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Set 1497.00

5018 Releasing of point rods with rod roller trestles, complete assembly. This includes releasing of all cranks, compensators and 'A' type concrete foundation on the rod run. The resultant pits are to be covered with earth and consolidated by ramming and levelling.

   

  a. Releasing of tressles 1/2 way Nos. 34.90

  b. Releasing of tressles 3/4 way Nos. 47.30

  c. Releasing of point roddings Per Rod/Mtr.

5.90

  d. Releasing of 'A' type foundations Nos. 250.00

5019 Releasing of rail post, aerial line wires, cross arms, insulators, stay rods etc., accounting and stacking them at a place as instructed by Railway representative at site.

   

  a. Releasing of cross arms Nos 10.30

  b. Releasing of insulators with stalks Nos. 5.80

  c. Releasing of line wire per wire/mtr.

0.90

  d. Releasing of rail post Nos. 313.00

  e. Releasing of stay set complete Set 109.40

5020 Dismantling and releasing of existing single arm semaphore signal Nos. 1233.00

Page 104: MEMU Master

Page 67 of 113

along with signal mechanism/ machines and all other fittings complete carefully, accounting and stacking them neatly at a place as instructed by Railway representative at site. The work also includes breaking and removal of signal foundation and refilling the resultant pit by ramming and levelling.

5021 Releasing of existing 2/3/4 doll bracketed semaphore signals along with fittings complete, including signal dolls, signal machine, signal arms complete with lenses, contact maker etc., carefully, accounting and stacking them neatly at a place as instructed by Railway representative at site. The work also includes breaking and removal of signal foundation and refilling the resultant pit by ramming and levelling.

   

  a. Releasing of 2 doll semaphore signals Set 2778.00

  b. Releasing of 3 doll semaphore signals Set 4166.00

  c. Releasing of 4 doll semaphore signals Set 4633.00

5022 Releasing of existing single wire/ double wire lever frame in the cabins along with complete fittings like levers, compensators, locking tray, lever locks, contact makers, 'E' type locks, floor board planks, stantions, ladder, leadin, lead out, terminations, interconnections, etc,. accounting and stacking them neatly at a place as instructed by Railway representative at site.

   

  a. Releasing of cabin (10 - 16 levers) Set 8121.00

  b. Releasing of lever frame (upto 8 levers) Set 3750.00

  c. Releasing of cabin (17 to 24 levers) Set 8621.00

  d. Releasing of cabin (25 to 36 levers) Set 10777.00

  e. Releasing of cabin (37 to 42 levers) Set 12932.00

5023 Releasing of single wire/ double wire transmission wires, winding them on kreels, releasing of stumps and bridge stakes, accounting and stacking them at a place as instructed by Railway representative at site.

   

  a. Releasing of transmission wires Per Wire m

0.90

  b. Releasing of single wire/ double wire bridge stalks Nos 8.70

  c. Releasing of single wire/ double wire stumps Nos 5.80

5024 Releasing of all the S & T gadgets at LC gates like SM slide instruments, illuminated diagram board, block counter, termination box, telephones, emergency key box, etc and concerned wiring, accounting and stacking them neatly at a place as instructed by Railway representative at site. After releasing any holes on the walls/ floor are to be filled with cement mortar and plastered.

Set 3839.00

5025 Releasing of existing ground type shunt signals along with surface base, signal post etc carefully without any damage, accounting and stacking them neatly at a place as instructed by Railway representative at site. The work also includes breaking and removal of concrete foundation and refilling of the resultant pit by ramming and levelling.

Nos. 875.00

Page 105: MEMU Master

Page 68 of 113

5026 Releasing of existing TLD boxes with stumps and terminals after releasing all the bond wires. The released materials shall be accounted and stacked neatly at a place as instructed by Railway representative at site.

Nos. 64.50

5027 Releasing of all power equipments including equipment stands, terminal boards, power panel etc., in the power room carefully without causing any damage to the equipments after disconnecting all the supply wires. The released equipments shall be accounted and stacked at a place as instructed by Railway representative at site. After releasing any holes in the walls/ flooring shall be filled with cement mortar and plastered.

Set 5111.00

5028 Releasing of existing control equipments - complete including way station equipments, telephones, power supply foe way station equipment and telephones, along with all wiring, accounting and stacking them neatly at a place as instructed by Railway representative at site.

Set. 2428.00

5029 Transportation of Signalling materials by road as per the instructions of Railway representative at site. The work also includes loading and unloading of the materials.

per ton. Km.

2.37

5030 Engaghing mechanical excavators like JCB or other machinaries for regrading and levelling the formation, dismantling any infringing structures, clearing and removing debris etc., with all leads and lifts etc., complete and as per the instruction of Railway representative at site.

per hour

650.00

Page 106: MEMU Master

Page 69 of 113

CHAPTER – III

TECHNICAL SPECIFICATIONS OF WORK

CABLE LAYINGERECTION OF APPARATUS CASESMAIN SIGNALS SHUNT SIGNALSTRACK CIRCUITSPOINT MACHINESCABLE TERMINATION RACK(FTOT)RELAY ROOMERECTION AND WIRING OF CONTROL PANELINTERCONNECTIONSPOWER SUPPLY ARRANGEMENTINSTALLATION OF SECONDARY CELLS AT BATTERY ROOM/ LOCATIONBLOCK INSTRUMENTSINSTALLATION OF DISTILLED WATER PLANTINSTALLATION OF SM’s SLIDE INSTRUMENT AT STATION/LCSUPPLY AND INSTALLATION OF SOLAR PANELERECTION AND WIRING OF ILLUMINATED DIAGRAM INTERLOCKING OF LEVEL CROSSING GATESINSTALLATION OF ELECTRIC LEVER LOCK & CIRCUIT CONTROLLERINSTALLATION OF STAND-BY DIESEL GENERATOR SETINSTALLATION OF DIAGNOSTIC PANELELECTRIC KEY TRANSMITTER AT STATION HOUSEINTERLOCKING OF SIDING POINTS/TRAP POINTSFIXING OF FACING POINT LOCKFIXING OF ELECTRICAL DETECTORTELEPHONESMASONARY PLATFORM FOR POST TYPE TELEPHONESINSTALLATION OF ANNUNCIATORPROVISION OF TEAKWOOD KEY BOX & TOOL BOXERECTION OF BOARDS WITH LEENDS/GOODS WARNING BOARDSEARTHINGPROVISION OF LOCKSPAINTINGNON-INTERLOCKED SIGNALLING ARRANGEMENTINSTALLATION OF DATA-LOGGERRELEASING OF S&T GEARSTRANSPORTATION OF SERVICEABLE MATERIALSPROCUREMENT OF CEMENTWIRES TO BE USED IN S&T INSTALLATIONTESTING & COMMISSIONING INCLUDING ‘AS-MADE’DESIGNING OF CIRCUITPROCEDURE FOR INITIAL CHARGING OF SECONDARY CELLS

--ssSss--

Page 107: MEMU Master

Page 70 of 113

CHAPTER III

DETAILED TECHNICAL SPECIFICATIONS FOR CARRYING OUT

SIGNALLING WORKS

0.1 The detailed specification for the works which are to be carried out by the contractor are as stipulated hereunder:-

0.2 The work shall be carried out according to the drawings approved by the Railways and

shall conform to the provision in Signal Engineering Manual and Schedule of Dimensions. The contractor shall be solely responsible for the proper execution of the work as per specification.

1.0 CABLE LAYING:-

1.1.1 CABLE TRENCH:-

Excavation of cable trench shall be made in all kinds of soils including clearing roots of trees, rocks bushes etc., to a depth of 1.0M and a width of 0.3M/ 0.5M as required, for laying cables. Trenches shall be straight as far as possible and steep angles shall be avoided. Alignment of the main cable route as well as track/ road crossing will be given by Railways. While taking the trench, all the roots of trees, bushes, rocks, if any, should be cleared. The bottom of the trench shall be leveled and got rid of any sharp materials. Proper protection to cables to be given while crossing power cables, pipe lines etc., as required by Railways.

a. Signalling/power cables will be laid as close to the track as possible. The cable, track separation distance both within station limits and in the block section shall generally not exceed 6 Metres.

b. It is desirable that the excavation of trenches is not done in long lengths and does not remain uncovered overnight. It is preferable that trenches are dug, cables laid and refilling done on the same day.

c. The contractor who supervises the excavation work shall have the shoring materials ready on hand so that on banks where ashes or loose materials are encountered, shoring can be adopted.

d. During excavation, the earth of the trenches should not be thrown on the ballast. The earth should be thrown by the side of the trenches away from the track. Plastic sheets/gunny bangs may be used wherever necessary to cover the ballast.

1.1.2 In RE area the following clear distances shall be maintained between the signalling cables and the OHE mast or other structures likely to develop high potentials or switching stations earth.

Page 108: MEMU Master

Page 71 of 113

a) Minimum distance between the signalling cables and OHE masts or other structures likely to develop high potential or switching stations earth.

DEPTH OF CABLE (Metres)

DISTANCE (Metres) REMARKS

Upto 0.5 1.0 Provided cable is laid in concrete pipe for 3M on either side of the mast/structure

0.5More than 0.5 3.2

b) Minimum distances between signalling cables and OHE mast or switching station earth.

DESCRIPTION DISTANCE (Metres) REMARKSSwitching station viz., feeding posts, sectioning post or sub-sectioning post

5.0 Provided cable is laid in concrete pipes.1.0

Earth, OHE mast or sub-station earth

1.0

1.2 LAYING OF CABLES:-

1.2.1 Before the cables are laid, a visual inspection of cable shall be made and it shall be tested for insulation and continuity of the cores. The insulation resistance of a new cable shall not be below 500 M.Ohms per Km. at 20 deg C. The cable insulation should be measured using a 500V insulation Tester (Megger). If there is wide disparity between insulation of different conductors, the condition of the cable should be thoroughly checked before permitting its use. Bedding and armouring shall be inspected to see that there has been no damage during transit or in storage. In case where the wheels are not available or the area is not convenient for rolling the wheels, along the routes, the drum shall be mounted on the axle at one end of the trench and cable payed out. It should be carried out by adequate number of men, ensuring that the insulation of the cables is not damaged and no kink/twist is formed. In no case shall the drum be rolled on the road for laying of cables and the cable dragged on the ground for laying purposes. The cables shall be laid gently into the trench and not thrown out under any circumstances. Before laying of cable in the trench, a visual inspection shall be adequate for any damage or defect throughout its length. Normally cable laying should be commenced only after the relay room and apparatus cases, cable termination box on the route at the respective stations are ready and the cable should be duly brought inside at the relay room/apparatus cases immediately after the cables are laid, however, if for any reasons the cable is be laid in advance, special care should be taken to ensure that the coiled cable near the relay room/apparatus cases is fully protected before and during the construction of the relay room/apparatus cases and during final termination. The coiled cable shall be buried well in the ground such that the depth from the ground level to the top layer of the coil shall not be less than 1 M and shall be fully covered with a layer of bricks horizontally in its entire length and provided with adequate number of the cable markers. On no occasion, the ends of the cable should be left unsealed unless terminated properly.

Page 109: MEMU Master

Page 72 of 113

1.2.2 Cable laying shall commence after the depth and width of the cable trench, quality of bricks are jointly inspected by Railway Engineer's representative and contractor's representative and approved.

1.2.3 PLACING OF CABLES:-

When several cables of different types have to be laid down in the same trench, they shall be as far as possible in the following order starting from the track side.

i) Telecommunication cables.ii) Signalling cables.iii) Power cables.

1.2.4 Cable shall not be normally taken over the running track at the time of cable laying by the contractor as this is likely to cause accident to trains and damage to cables. If at any time the cable has to be taken across the track either in full drums or in spread out conditions it shall be done only in the presence of Railway's Supervisory staff and also after safety precautions have been taken to post flagmen on all the sides as may be required to stop any trains approaching the site of the fouled line.

1.2.5 At each end of the main cable/tail cable/power cable an extra coil length of 6 to 8 Metres should be kept.

1.2.6 At the time of commissioning of the cable, the insulation values of the cable should again be checked and the value obtained shall not be below 500 Meg.Ohms per Km at 20 deg.C. If there is wide disparity between insulation of different conductors, the condition of the cable should be thoroughly checked before permitting its use. The reading shall be recorded in a register based on Annexure `C' for all power cables, main and tail cables.

1.2.7 The contractor shall furnish the final as made cable plan and cable route plan and in R.P film with eight prints showing the distance of cables from the nearest track centre.

1.2.8 LAYING OF CABLE IN RCC DUCTS:

Excavation of cable trench to a depth of 0.85M and width of 0.85M and placing of the RCC cable supplied by Engineering Department. Also the inter-spacing between the ducts should be cement plastered. After laying of cables, the cable duct shall be filled up with river sand upto the edge of the pre-cast partition level and covered with RCC slabs as per the instructions of Railway Engineer at site. Any balance excavated earth shall be cleared well away from the existing tracks.

1.3 PLACING OF BRICKS :

1.3.1 One layer of country bricks of size of approximately 220mm x100mmx60mm shall be placed closely in breath-wise horizontally in the 1m X 0.3m trench over the cables. Two rows of country bricks of size of approximately 220mm x100mmx60mm shall be placed closely in breath-wise horizontally over the cables in the 1m X 0.5m trench.

1.3.2 SEPARATION OF POWER CABLES:-

Page 110: MEMU Master

Page 73 of 113

The signalling cable shall be separated from the power cable carrying 230V or above by a row of bricks placed vertically lengthwise between them wherever required.

1.4 RE-FILLING THE CABLE TRENCH:

After the bricks are placed over the cable without any gap between two bricks properly, the excavated earth shall be again put up in the trench. It shall be ensured that there are no stones or any sharp materials present. The refilled earth shall be consolidated and extra earth also shall be placed on the trench to compensate the sinkage and consolidation of earth.

1.5 TRACK/ROAD CROSSING/MECHANISED OR METALISED ROAD:

1.5.1 Wherever signalling/power cable has to cross the track/road it shall be ensured that:

I. The cable crosses the track/road at right angles.

II. The cables do not cross in between or inside points and crossings.

III. The track/road crossings to be carried out as per the instructions of Railway representative at site.

1.5.2 In case of track crossing, work includes removal of ballast, excavation of trench 1m/0.5m below the ground level and across the track at places indicated by the Railways and covering, resurfacing the trenches and ballast to the original condition after placing RCC pipe/pipes in position.

1.5.3 RCC Pipes 100mm I.D & 150mm O.D or DWC pipe, shall be provided for track/ road crossings as per Drg. No. SG/CN/02/1. For each track crossings two numbers of RCC pipes with collar each 2M long shall be provided. For each road crossing required number of RCC pipes each 2m long with collar shall be provided depending upon the width of the road.

1.5.4 In cases where more than one RCC pipe is used for track/road crossing, the bottom-most RCC pipe should be 1m below the ground level.

1.6 CABLE LAYING ON BRIDGES:-

On bridges, the cables are to be laid through GI Pipes 50mm dia- 3.65mm thick/100mm dia-4.5mm thick/DWC pipe with off-set both ends and with coupling wherever required as per Railway requirement. The pipes shall be suitably supported over the bridges/drainage/culverts with brick masonary works of size 300x300x300mm at an interval of 2M in box type bridges and suitable MS clamps at an interval of 1M in Girder bridges. The end of pipes will be closed with brick masonary abutments of size 0.5x0.5x0.5 Metre.

1.7 PROVISION OF RCC TROUGH :

Page 111: MEMU Master

Page 74 of 113

Excavation of trench 0.35M width and 0.8M depth, covering the cable laid with RCC trough (cable protector) as per Drg.No. SG/CN/02/2 and closing and leveling the trench.

1.8 CABLE LAYING ON PLATFORM :

The work includes removing/breaking of existing RCC slabs on the Passenger Plat form, trenching to a depth sufficient to accommodate the additional cables laid, covering the trench after the cables are laid, replacing the slabs removed or re-plastering with cement mortar and restoring to the original condition as per the instructions of Railway Representative at site.

1.9 MASONARY DUCT IN ROCKY AREA:

In Rocky area, Cable trenching and construction of masonary duct shall be carried out as per Drg. No. SG/CN/02/3 or 4.

1.10 Wherever the cable coil pits are required to be provided, the cable coil pit shall be excavated to a size of 1.0mx1.0m and a depth of 1.0m in rear of location boxes and to a size 2.0m X 2.0M and a depth of 1.5M in rear of Relay room and cable huts. After all the cables are drawn and coiled, over the coiled cable one layer of country bricks of size 220mmx100mmx60mm shall be placed throughout entire area of the bottom of the pit without any gap and then refilled with earth and consolidated.

1.11 CABLE MARKERS:-

Cable markers have to be supplied and concreted as per Drg.No.SG/CN/02/5. Cable markers have to be placed and concreted at an interval of 20M throughout the cable route, diversions and also on either side of track crossing along the cable route.

2.1.0 ERECTION OF APPARATUS CASES:-

2.1.1 The work consists of pit excavation, casting foundation with bolts of adequate size having cement concrete of ratio 1:3:6 as per:-

i) Drg.No. SG/CN/02/6 (Apparatus case full size)

ii) Drg.No. SG/CN/02/7 (Apparatus case Half/ Quarter size)

The position of apparatus case will be indicated by Railways.

2.1.2 Two `E’ types locks on the doors of full size apparatus case and one `E’ type lock on the front door for half size apparatus cases shall be firmly fixed and tested with `E’ type key . Locking and unlocking shall be smooth with least force. Suitable fixing arrangements for `E’ type lock on the door of apparatus case shall be fabricated by the contractor, if such arrangements does not exist. One hard wood shelf plank 37mm thick, planed and varnished shall be firmly fixed for all types apparatus cases/ battery boxes. Also latching arrangement for the back door shall be provided, if required.

Page 112: MEMU Master

Page 75 of 113

2.1.3 All the apparatus cases (Full/Half/Quarter) are to be painted with Aluminium on the outsides and the location numbers are to be painted in 'Bold' letters.

2.2 CABLE TERMINATION BOX FOR CABLE THROUGHING, POINT MACHINE AND LEVER LOCK:

2.2.1 Excavating earth and casting concreted foundation as per Drg.No. SG/CN/02/8 and C.T. boxes are to be erected on Rail vertically by using suitable size of bolts and nuts. The cables shall be taken through 2 Nos. of G.I. Pipes of size 32mm inner dia and 300mm length fixed at the bottom of the CTB with suitable fixing arrangements. It shall be ensured that there should be no break in the cable core during the process of taking the cables through pipes.

2.2.2 In case of CTB for Point machine and Lever lock, one no. of GI pipe 150mm long shall be fixed at the side of the CTB for drawal of jumper wires from point machines/lever locks with proper fixing arrangements. The CTB should be provided with EWS lock.

2.2.3 CT Box shall be painted with Aluminium paint and rails with black paint. The circuit particulars shall be painted neatly on the CT Box cover and the location number have to be painted in ‘BOLD’ letter.

2.3. SHIFTING OF APPARATUS CASES/ CT BOXES:

The work consists of excavation of pit around the existing apparatus cases full/ half size and CT boxes, shifting of the location box along with foundation clear of infringement from the track. The pit shall be excavated with maximum care to avoid any possibility of damage to the existing cables. The location box shall then be shifted carefully along with the foundation and cable termination, equipments etc., without disturbing the wiring. While shifting apparatus cases of full size, the brick wall covering the cables shall be broken before shifting the location box. After the location box is shifted, brick masonary walls shall be constructed on the front and back sides of the location box foundation. River sand shall be filled upto to the floor of the location and the bottom shall be sealed with sealing compound.

2.4. CABLE TERMINATION IN APPARATUS CASES/CTB’s:

2.4.1 At each apparatus case/CTB, the work consists of fixing all cables, fixing of laminated, termite proof particles board - exterior grade 25mm thick termination board along with terminal blocks and termination of cables/cores (conductors) using PVC/Nylon sleeves.

2.4.2 The underground signalling cable-main, tail and power shall be properly secured by wooden clamps of 50mm x 50mm teak wood inside apparatus case on 25mm x 100mm base plank. The cables shall be neatly skinned duly mending and taping of cable ends for termination bunched and terminated on the terminal board at the required place in order as per approved apparatus case circuit diagram. All the aluminium power cables of size 10 Sq.mm and above shall be provided with Aluminium lugs using crimping tool of appropriate size.

Page 113: MEMU Master

Page 76 of 113

2.4.3 Railway will indicate approximate total number of cable core, terminations to be made in the apparatus cases/cable termination boxes. The contractor shall fix Laminated, Termite Proof Particles Board - Exterior Grade termination board of not less than 25mm at each apparatus cases/C.T. box as required by Railway. Terminal blocks with links, fuse blocks with fuse shall be fixed on the terminal board pertaining to each apparatus case and cable termination box using proper size of wood screws. Two suitable holes shall be made on either side of terminal block and fuse block for bringing cable for termination. The contractor shall prepare cable termination and wiring details of apparatus cases and C.T. boxes and obtain the approval of the Railway Engineer before execution as per the approved cable plan. Termination of main cables, tail cables, power cables, core/cores shall be made at the proper terminal as per approved wiring diagram pertaining to each apparatus case and C.T. Boxes. Before final termination, each cable shall be tested for continuity, insulation etc. and readings recorded and jointly tested and signed.

2.4.4 As per site conditions, the termination of new cables may be required on the existing terminal blocks or by fixing new terminal/fuse blocks in old apparatus cases which shall be done as per approved circuit diagram wherever required. The terminal particulars are to be re-painted or corrected on the doors of apparatus cases as instructed by Railways. Suitable clamping arrangements have to be made for the new cables and also the bottom the opening of the apparatus cases shall be closed with masonary brick work and sealed with cable compound.

2.4.5 After fixing all the signalling cables inside the apparatus case, the side opening shall be closed with masonary work and plastered. The inner side is filled with Sand and finally the bottom is sealed with sealing compound.

2.4.6 All the underground cables shall be provided with punched name plates showing total no. of cores, cross section of each core, Aluminium or copper conductor and from and to details etc. and also painted inside each apparatus case.

2.4.7 The contractor shall submit final `As made' details for each apparatus case and C.T. box in R.P film duly signed. As made shall also show the position of various equipment fixed in each CT Box, apparatus case and battery box, cable details, from and to etc. PVC/NYLON sleeves shall be provided on each cable and cable core number and name of circuit shall be painted on them.

2.5 WIRING OF SIGNALS/LC GATE CONTROL/TRACK CIRCUIT/POINT CONTROL RELAYS IN LOCATIONS:

2.5.1 Relays, transformers, heavy duty contactors and other gadgets controlling the above functions shall be firmly fixed on suitable relay frames using MS Angles of size 25mmx25mmx6mm and MS Flats of size 25mmx6mm inside respective apparatus cases. The MS relay frame shall be painted before fixing. Laminated Termite Proof Particles board of 25mm thick of requisite size shall be fixed in side the apparatus case for fixing Resistance and Electrolytic condensers. In case of shelf type relays, the relays shall be mounted on shelf planks with suitable anti-tilting arrangement. If plug in type relays are used, 16/0.2mm flexible copper wire shall be used for wiring. For shelf type relay and point motor circuit, 3/0.75mm copper wire shall be used. There shall be no joint in the wire. For soldering the wire to relay clips of Plug-in-type relays in relay racks, best quality

Page 114: MEMU Master

Page 77 of 113

rosin core solder shall be used. The complete wiring shall be tested jointly and linked to tail cable.

2.5.2 The description of all relays, fixed in each apparatus case shall be painted inside apparatus case doors. PVC/Nylon sleeves shall be provided on each wire before termination on terminal block. The name of the circuit and wire where connected shall also painted on the sleeves.

2.5.3 Wire should be soldered to relay clips and suitable copper eyelets crimped with crimping tools shall be adopted before the termination. The wiring and termination shall be carried out as per the approved circuit diagram. The relays details shall be painted. PVC/Nylon sleeves shall be provided for each wire before termination and the details of circuit and where the wires connected etc., shall be painted on the sleeves. The complete wiring shall be tested.

2.6 ALTERATIONS TO PAINTING PARTICULARS AT LOCATION BOXES:

Consequent to introduction of new circuits or alterations to existing circuits in apparatus cases/CTB’s, new nomenclature should be painted on the cable sleeve. And also the new particulars should be painted on the inner side of the doors at apparatus cases/CTB’s.

2.7 FILLING OF EARTH AROUND LOCATIONS:

The work consists of filling of earth around the foundations of signals and apparatus cases for a width of 0.5m on all sides from 150mm below the foundation top to ground level. The earth shall be consolidated after filling.

3.0 MAIN SIGNALS :

3.1 CASTING OF COLOUR LIGHT SIGNAL FOUNDATION:

3.1.1 The work includes excavation of pit and casting of colour light signal foundations with M.S foundation bolts as per Drg.No. SG/CN/02/9. The position of signals will be indicated by Railways.

3.1.2 The foundations are to be plastered on all sides. Necessary earth work shall be made around the signal foundation and sufficient earth work shall be made upto the required level in the normal terrain and the cable entries shall be closed as per the instructions of Railway Representative at Site.

3.2 ERECTION AND WIRING OF SIGNALS:

3.2.1 Signal pole shall be securely fixed to surface base and erected on signal foundation and plumbed. The gap between the signal pole and surface base shall be filled with suitable putty to avoid tilting. Soon after installation, the pole shall be painted with two coats of Aluminium paint after a coat of primer and the signal unit shall be provided with two coats of black enamel paint.

Page 115: MEMU Master

Page 78 of 113

3.2.2 Multi unit colour light signals upto 4 aspects shall be properly mounted on the top of signal pole where there is no route indicator. If required, LED type signal aspect shall be fixed for signals. If there is route indicator a large off set bracket shall be fixed firmly with 2 nos. of `U' bolts 3/4" thick on the signal pole for mounting multi unit colour light signals. One 22mm through hole shall be drilled on signal pole just below the off set bracket and a 20mm through bolt shall be the provided to prevent offset bracket from sliding down.

3.2.3 Signal ladders with platform complete fittings, cast iron shoe and adequate number of support to suit signal pole 3.6/4.6m, shall be firmly fixed clear of infringement with suitable bolts and nuts and painted in black. The ladder shoes shall be concreted. This work also includes fixing of marker boards, enamelled number plates with suitable clamps at the required place. Speed board if any, shall be fixed on the pole with proper clamp clear of infringement as required by Railways.

3.2.4 Signal tail cable shall be taken through the signal pole without damaging insulation and armour, skinned and terminated on signal units. If the signal units are mounted on large offset brackets a vertical slotted hole of 50mmx50mm in size shall be made on signal pole for taking signal tail cable. Suitable protection shall be provided on the slotted hole to avoid damage to insulation of cable. Necessary lense guard shall be provided for CLS/ Route Indicator/ Calling-on signal.

3.2.5 This work includes fixing of filament switching units, Triple pole double filament lamp holders in each aspect of Colour Light Signal Unit and wiring lamp circuit between Signal Transformer and Signal Aspect as per the approved circuit diagram. The Signals shall be focussed for correct visibility after fixing the Signal lamps. The unwanted aspects shall be blanked using MS sheets of 3mm thick.

3.2.6 All the multi unit colour light signals shall be wired with 3/0.75mm copper wire and terminated. For each aspect 2 separate wires shall be used from the terminals and the wiring shall be tested jointly. The signal shall be focussed in day time and at bright light at 90% of rated voltage. The outside `V' cut prism section shall be correctly fixed to the respective track side for close up visibility to drivers.

3.2.7 BLANKING ARRANGEMENTS FOR SIGNALS:

In case of signals with a horizontal clearance between 2.21m and 2.36m (in B.G) from the nearest track center, blanking arrangement shall be provided. MS plate not less than 8mm thick, 30cm length shall be fixed on the ladder at a height of 6.3 feet from the rail level. The end portions of the plates should be folded and made smooth so that it will not harm the person climbing the ladder. This plate shall be painted with black.

3.2.8 The signals shall be properly earthed in RE area only.

3.2.9 Necessary wooden cross shall be fixed on the newly erected signals before being brought into use.

3.3 ROUTE INDICATORS:-

Page 116: MEMU Master

Page 79 of 113

All types of Route Indicators shall be mounted on the top of signal pole firmly. Necessary lens and guarding shall be provided as required by Railways. The tail cables for route indicators shall be taken through signal pole without any damage to the insulation and armour, skinned and terminated on route indicators. Route indicators shall be wired with Wire PVC 3/0.75mm copper as per the approved circuit diagram. Hoods shall be fixed properly and examined during day time and if required extension of hoods shall be made to have proper visibility. The route indicator lamps shall be fed at 90% of rated voltage and focussed in bright day light. The route indicators shall be painted as required by Railways.

3.4 CALLING - ON SIGNALS/’A’ MARKER LIGHTS:-

Calling on signals/’A’ marker shall be fitted on the signal posts at required height using off-set bracket. Suitable hole shall be drilled on the signal poles to bring the cable/jumper wires. The cable/jumper wires shall be taken to calling on signal/ ‘A’ marker through suitable steel hose pipes and wired by using 3/0.75mm copper wire. The calling on signals shall be provided with `C' marker and ‘A’ for ‘A’ marker. Number plates to be fixed and signals/’A’ marker, shall be energised at 90% of the rated voltage and focussed.

3.5 REPLACING THE TAIL CABLES IN SIGNALS:

Wherever necessary the existing tail cables shall be released from the existing signals and new tail cables shall be drawn to the aspects and terminated. The termination particulars shall be painted.

3.6 SHIFTING OF SIGNALS :

Wherever required the existing Colour Light Signals shall be shifted to clear any infringement from the tracks as instructed by Railway representative at site. The earth surrounding the foundation shall be excavated and the cable coils shall be loosened very carefully without causing any damage to the cables. The Signal shall be moved along with the foundation slowly to the new position and earthwork shall be done around the foundation. The loosened cables shall be buried at 1m depth.

3.7 REPLACEMENT OF SIGNAL UNITS:

The existing CLS units shall be removed from the signal post duly disconnecting the cables and new signal units (required as per signalling plan) shall be mounted on the existing signal pole. The tail cable is to be terminated and the signal aspect shall be wired by providing FSU, Lamps, etc. and focused. If there are any blank aspects, the same shall be covered with round MS plate. Lens guard should be provided to the new CLS unit and painted.

3.8 SCREENING ARRANGEMENTS:

For the Colour Light signals in RE area which are coming in the infringing zone, screening arrangement shall be provided as required by Railways. The screen made of MS wire-mesh will be fixed on MS angles of size 25x25x6mm with suitable fixing clamps, bolts and nuts and finally painted with black.

Page 117: MEMU Master

Page 80 of 113

4.0 SHUNT SIGNALS:

4.1 POSITION LIGHT GROUND TYPE SHUNT SIGNAL:

4.1.1 The work involves excavation of pits and casting of shunt signal foundations as per Drg.No. SG/CN/02/10. The position of shunt signals will be indicated by the Railways. Foundation for shunt signals shall be casted with cement concrete in the ratio 1:3:6 using stone jelly of size 20/25mm. The foundations are to be plastered on all sides. Necessary earthwork shall be made for each position light shunt signals as required by the Railways.

4.1.2 The position light shunt signal shall be properly mounted and plumbed.

4.1.3 The cables are to be taken through the unit, skinned and terminated. The post type/Ground type shunt signals shall be wired with 3/0.75mm copper wire and terminated and the wiring shall be tested jointly. The shunt signal shall be focussed in day time and at bright light at 90% of rated voltage.

4.1.4 This work includes fixing of lens guard and number plates. The post shall be painted with Aluminium while the signal unit and surface base with black enamel paint.

4.1.5 The CLS units, Route Indicators, Calling-on signals, position light shunt signals post type and ground type shall be provided with EWS locks.

4.2 POST TYPE SHUNT SIGNAL:

Small off-set bracket shall be firmly fixed with `U' bolts of suitable size on signal pole for mounting Post type shunt signals. One 22mm through hole shall be drilled on signal pole just below the off set bracket and a 20mm through bolt shall be the provided to prevent offset bracket from sliding down. A vertical slotted hole of 50x50mm in size shall be made on signal pole for taking the signal tail cable. Suitable protection shall be provided on the slotted hole to avoid damage to insulation of cable. The cables are to be taken through the unit, skinned and terminated. The post type/Ground type shunt signals shall be wired with 3/0.75mm copper wire and terminated and the wiring shall be tested jointly. The shunt signal shall be focussed in day time and at bright light at 90% of rated voltage. This work includes fixing of lens guard and number plates. The post and signal unit shall be painted with Aluminium and enamel black respectively. One EWS lock shall be provided for the signal.

5.0 TRACK CIRCUITS:

5.1 INSTALLATION:

5.1.1 The work includes drilling of holes, bonding of rail joints with 8 SWG GI soft solid wire, 7.2mm holes are to be drilled close to Fish Plates on the web of rail and the bond wires are to be fixed by driving channel bond pin tightly. Two bond wires are to be provided for each joint in parallel. One bond wire clip is to be provided for each joint to keep the bond wire intact. In point track circuit, parallel jumpers/ bond wires/cables shall be provided as required by the Railways with proper supporting arrangements.

Page 118: MEMU Master

Page 81 of 113

5.1.2 Four TLD boxes, two each at track feed end relay end shall be fixed clear of infringement and the respective track circuit tail cables 2 x 2.5 sq.mm PVC copper conductor from the apparatus case shall be terminated in these boxes. In Point zones additional TLD boxes shall be provided for parallel jumpers as per the instruction of Railway representative at site. The connection from the TLD boxes to the rail should be through 8 SWG GI soft solid wire which should be taken through PVC sleeve if required and fixed to the rail both at feed and relay ends. The GI Wire should be clipped on to the sleepers to prevent shorting with rails.

5.1.3 Wherever Glued joints are not provided, Rail Joint insulation RDSO type shall be provided with long bolts and nuts at places marked by Railways. In case of point zone track circuit, necessary insulation shall be provided for switch extension pieces/‘D’ brackets, throw bar lugs, gauge tie plates, crossing plates, stretcher bars, etc., as per site conditions and fixed by the contractor in the presence of Railway representative. Only non insulated gauge tie plate/crossing plate/stretcher bar for the above work, will be supplied by Railways. Contractor shall use proper 10mm thick MS flat, bolts and nuts for insulating them. All the insulation shall be tested jointly. Wherever the rodding crosses track circuit zone, it shall be provided with rod joint insulation and tested.

5.1.4 Polarity bonding in each point track circuits shall be provided using 8 SWG soft wire,

insulated and clipped on to sleeper. Parallel bonding shall be done wherever required. In RE area transverse bonding should be provided at both feed and relay ends by connecting 2GI 8SWG wire across the block joint as per the bonding plan.

5.1.5 Track circuit work includes fixing of track feed and track relay equipments in the apparatus cases as indicated by the Railway. The shelf type track relay shall be provided with suitable anti-tilting arrangement. Track relay details shall be painted on the inner side of the apparatus case door. Suitable flexible copper wire shall be used for wiring the track relay, track feed equipment, batteries, chokes, etc. and finally terminated at the terminal block. For each track circuit, secondary cell 80 AH shall be charged and installed in the apparatus case. The no. of cells and chokes to be used for each track circuit will be as per the following table:

APPLICABLE TO PLUG-IN-TYPE TRACK RELAYS:

LENGTH OF TRACK CIRCUIT

NO. OF CELLS (2.2V )

NO. OF CHOKES(IN RE AREA ONLY)

Upto 450M TWO ONE450M to 700M THREE TWOAbove 700 M FOUR TWO

5.1.6 The secondary cells shall be charged by the contractor through reputed agencies. The charging of secondary cells shall be done as indicated under Item No.43.

5.1.7 All the TLD boxes shall be painted and Track Circuit numbers along with feed end or relay end particulars shall be neatly painted as required by Railways.

Page 119: MEMU Master

Page 82 of 113

5.2 ALTERATIONS TO TRACK CIRCUIT:

5.2.1 Alterations to the existing track circuits involves by shifting the Feed end equipments/ Relay end equipments/block joints and installing them at a different locations and re-wiring them.

5.3 After completing the installation/alteration of track circuit, it shall be energised, tested, adjusted and readings recorded in track test record.

6.0 POINT MACHINES :

6.1 INSTALLATION OF POINT MACHINES ;

6.1.1 Electrically operated point machines shall be fitted in level to all facing points as per standard drawing on long sleepers on extended gauge tie plate, clear of infringement.

6.1.2 The point machine shall be installed after cleaning the machine (both inside and outside) and greasing/oiling all the moving parts. The point machines shall be hand operated, detection and motor controlling contact adjusted before taking to site. All unwanted openings shall be covered with MS Sheets.

6.1.3 The point machines shall be fixed with proper size of bolts and nuts and flat/spring washers with correct size of holes on special sleepers to avoid lateral play.

6.1.4 All point connecting rods shall be connected to point machines as per standard layout/drawings without any strain and with minimum offset. All connecting rods shall be in level and correct size of pins shall be used to avoid longitudinal play. Any changes in the connecting roddings during installation which necessitates welding and off sets shall be carried out by the contractor at site. The welding shall be by smithy process. Lengthy roddings shall be supported suitably.

6.1.5 All the wooden sleepers on which the point machine is installed shall be strapped on both side with 2"x3/4" MS strap. Necessary holes [22mm] be drilled on the strap and 20mm bolts and nuts shall be used for fixing to the sleepers.

6.1.6 Suitable eyelet shall be used for termination of power cables using crimpling tool. The jumper wires from the point machines to the CT boxes shall be taken through flexible conduit PVC pipes and securely fixed with suitable clips. The wiring inside the point machine for motor and detector circuit shall be tested for insulation and earth and the connections tightened. 7/1.4mm 3/0.75mm PVC copper wire shall be used for wiring point machines. PVC/Nylon sleeves shall be used for identification of cable cores/jumper wires and marked with paint. Necessary grooves/wards shall be cut on the point machine at the place of insertion of crank handle, for crank handle interlocking purpose.

6.2 ADJUSTMENT AND TESTING OF POINT MACHINES:

Page 120: MEMU Master

Page 83 of 113

6.2.1 The point machines shall be worked by hand crank and the housing of switch rail with the stock rail shall be checked. All the electrical wiring shall be carried out neatly.

6.2.2 The point machines shall be worked both ways with proper feed. It should work without undue friction and working current shall be recorded.

6.2.3 The point stretcher bar and lock connections should be adjusted in such a way that with a 5mm thick obstruction piece placed between the switch and stock rail at 150mm from the toe of switch,

a. The point does not get locked.b. The point detection circuit is not completed.c. The friction clutch disengages.d. The tripping current does not exceed 200% of normal working current.

6.2.4 The point machine shall be provided with EWS locks/pipe locks. A long necked lock shall be provided for commutator cover in the case of 5E only.

6.2.5 Necessary notches shall be cut on the pinion of point machine to suit crank handle configuration in the case of 5E only.

7.0 CABLE TERMINATION RACK [F.T.O.T ]:

7.1 CONCRETING & ERECTION OF CABLE TERMINATION RACK [F.T.O.T]:

7.1.1 Cable termination racks shall be erected on suitable teak wood base frame of size 50mm x 150mm in the relay room/ Cable Hut at the required location as directed by Railway with suitable foundation bolts and concreted. The cable termination racks shall be painted soon after installation before cable termination work is taken up. Suitable cable ducts wherever required shall be provided to bring all outside cables to the termination rack. All the cables are to be neatly skinned, fixed by wooden clamps, bunched individually and terminated in order. The cable armours and the rack shall be earthed. PVC/Nylon sleeves/indication sleeves shall be used for each cable and internal wiring termination and particulars written with paint on the PVC/Nylon sleeves.

7.1.2 The un-used space over the top of the cable termination rack meant for fixing NA transformer shall be blanked using Hylum sheet of 3mm thick and suitable bolts and nuts.

7.2 TERMINATION OF CABLES:

7.2.1 The PBT terminal and fuse blocks shall be fixed firmly on the cable termination racks and serially numbered with paint for easy identification. Tags shall be provided for each terminals and painted, giving description of the circuit. Suitable rubber gromite shall be provided on the holes of termination racks. Copper tape of width 20mm x 1.5mm shall be used for providing bus bars. Suitable holes shall be drilled in copper tape for this purpose.

7.2.2 All the cables shall be identified by a punched label, tied on to each cable. Painted cable termination index board using Plywood of thickness 12mm – TW/rough finish as per instructions of site incharge with Aluminium grooved Channel frame of overall size

Page 121: MEMU Master

Page 84 of 113

1200mmx1800mm –1no. shall be fixed in the relay room showing the terminal numbers circuit-wise. In case sufficient space is not available for fixing the board in one piece, it may be provided in parts retaining the overall size as per instructions of site incharge. `As made' terminal particulars shall be prepared in RP Film duly signed and handed over to the Railway at the time of commissioning.

7.3 For fixing indication transformers on cable termination racks / relay frames, suitable arrangements using Teak Wood planks - 25mm thick of requisite size shall be provided wherever required. Signal number, name of aspect shall be letter painted in each indication transformers wherever required. The indication transformers shall be tested for insulation and earth before fixing. The indication transformer will be wired using PVC 3/0.75mm copper wire as per approved circuit diagram. The wiring shall be neatly bunched and tested.

8.0 RELAY ROOM:

8.1 ERECTION OF RELAY RACK(PODANUR/SIEMENS):

8.1.1 Podanur type Relay racks shall be mounted on T.W base frame of size 50x150mm as required by Railways in the relay room with suitable foundation bolts and cement concrete.

8.1.2 Siemen’s relay rack, (to accommodate 56Nos. of ‘Q’ series relays) shall be anchored using ‘J’ type foundation bolts and nuts (12mmx100mm) with washers. In places where ‘J’ type bolts can not be used, special headed bullet type foundations shall be used. An insulator shall be provided for each foundation bolts and also to the ladders for carrying the cables. A MS wall angle of size 35x35x5mm shall be provided- one end grouted to wall and the other end fixed to the relay rack as tie.

8.1.3 The relay rack shall be painted soon after the installation before plugging of the Plug Board.

8.2 WIRING OF RELAYS(NEW/ADDITIONAL/ALTERATION):

8.2.1 Based on the circuit diagram, contact analysis chart shall be prepared by the contractor. The required number of 50 way terminal boards, plug boards and plug in type relays shall be fixed on the new/existing rack in the nominated places as instructed by Railway representative. The configuration of plug boards should be checked with the contact analysis chart. The nomenclature both on the rear and the front side of the plug board and on front side of the relays in the relay frame shall be painted.

8.2.2 Suitable arrangements shall be made in the relay rack for fixing condenser and resistance unit, required for slow to pick up or slow to release feature. Letter painting shall be made against each unit to identify the circuit for which it is used. Suitable wire supporting Tray made of PVC shall be provided for each row in relay rack to accommodate the complete bunch wherever the new wiring is carried out.

8.2.3 The wiring shall be carried out as per approved circuit diagram. The wiring shall be done on connectors and terminated on terminal clips by soldering process neatly, using high

Page 122: MEMU Master

Page 85 of 113

grade solder. PVC flexible wire 650V grade 16/0.20mm copper conductor shall be used. Potential free contacts of various relays required to be monitored by the Data logger should also be wired on the tag block of the data logger. In case of alteration to existing wiring, the wires and relays not required shall be removed. After completing the alteration work, the new wires have to be bunched neatly and brought to original condition. The relay rack wiring shall be tested initially by the contractor and then jointly with Railway Representative. Any addition/alteration to wiring in the course of testing shall be carried out free of cost by the contractor. Different colours of wire shall be used for identify the power supply circuit wiring. In case of alteration, a different colour of wire from the existing one shall be used for easy identification.

8.2.4 Before plugging, the relays shall be checked visually and defective ones noticed shall be replaced duly reporting the same to the railways.

8.2.5 The painted Relay Index board using plywood of thickness 12mm T.W/rough finish as per instructions of railway representative with Aluminium grooved channel of size 1200x1800mm – 2 Nos. shall be manufactured and fixed in the relay room giving the details of the relays and their position in the relay rack. In case of alteration/additional relay wiring, the relay particulars shall be incorporated in the existing relay index board available in the relay room. If sufficient space is not available for fixing the board in one piece, it may be provided in parts retaining the overall size as per instructions of site incharge.

8.2.6 Hardwood stand with decolum finish of size 500mmx700mm of 25mm thick shall be fixed on M.S angles grouted to wall at relay room for keeping ‘As made’ circuit diagram at suitable height as required by Railway Representative. In case of additional/alteration to existing relay wires, the latest ‘as made’ circuit diagram shall be kept in the relay room on the existing hardwood stand.

8.2.7 The new relay room shall be provided with Double Key Door Lock arrangement.

8.3 Rubber mat having sufficient width should be placed in front and rear of all the relay rack and FTOT. The mat should not be less than 6mm thick and it should withstand 650V AC.

8.4 FUSE BLOWN OUT INDICATION:

Fuse Blown out indication shall be provided using Hylum sheet 5mm thick and 50mm width and fixing of 5mm LEDs and resistance. The Hylum sheet shall be fixed by the side of the corresponding Fuse Blocks. Separate switch shall be provided for each circuits. This arrangement shall be made near FTOT inside the relay room.

9.0 ERECTION AND WIRING OF CONTROL PANEL:

9.1 ERECTION :

The control panel shall be erected on suitable teak wood base frame of size 50mmx150mm in the SM's room at suitable place on proper foundation bolts and cement concreted. Before erecting the control panel, suitable duct shall be made for bringing the jumper cable into the control panel from relay room/power room if

Page 123: MEMU Master

Page 86 of 113

necessary.The interspace of the cable duct after placing all the cables, shall be filled with river sand, before closing the duct with slabs.

9.1.1 The cables shall be clamped using TW 25mmx150mm base plank and 50mmx50mm TW clamp and the cable entries sealed using cable compound.

9.2 WIRING:

9.2.1 The control panel shall be wired including all thumb switches, Push buttons, indicators, counters, bell/buzzers and emergency push, etc. The wiring shall be done with flexible PVC copper wire 16/02mm or by switch board cable by soldering the wire to the terminal clips. High grade solder wire should be used. The wiring shall be done in such a manner that enough working space is available for replacement of knobs/buttons and attend to wiring. The wiring shall be neatly bunched.

9.2.2 Spare contacts in thumb switches and push buttons shall be paralleled. The contractor shall protect the control panel top plates while doing the wiring. The terminal particulars, power supply points, thumb switch/push button numbers, signals/track numbers shall be neatly painted on the inner side of the top plate. Before commencing wiring, all thumb switches, push buttons, indications shall be tested for proper contact and defectives shall be replaced in the initial stage itself. The indication lamp details shall be painted on the inner side of the top plate at respective places. Precautions shall be taken such that there is no break in the wires and damage to the insulation. There shall be no joint in the connecting wires. Each wire shall be identified properly.

9.2.3 One Voltmeter 0-300V AC for signal supply shall be mounted in panel/panel room.

9.2.4 The required number of buzzers operating on 24V DC as per approved circuit diagram for low voltage monitoring, signal blanking and approach warning, etc. shall be provided in the panel and wired.

9.2.5 One TW stand/tray shall be manufactured and kept at the Panel room for keeping different types of caps.

9.2.6 During the course of work, any modification to the panel/panel wiring shall be done by the contractor at site as required by the Railways at free of cost before final commissioning.

9.2.7 The work of alteration to control panel wiring includes drilling of holes on the Top plate wherever required and fixing of switches, push buttons, LEDs/ indication lamps with holder, termination of cables and carrying out alteration to the existing wiring as per approved circuits diagram, releasing of wires, and painting of particulars on the panel. If there are any small holes after releasing the switches or buttons, etc., the same may be plugged, covered with putty and painted neatly.

9.2.8 The cable termination and internal wiring terminal particulars of control panel shall be made on R.P Film duly signed by the contractor and handed over to the Railways.

9.2.9 The frames and the back doors shall be painted as required.

Page 124: MEMU Master

Page 87 of 113

9.3 INSTALLATION OF LOW VOLTAGE MONITORING DEVICE: The Low Voltage Monitoring Device Multimeter like external 1 & 2, internal, block, indication, etc., should be procured and installed inside Relay/Power Room as required by Railways. Necessary connections are to be made to various circuits and wired with 3/0.75mm wire. The description of the circuit shall be painted neatly.

10.0 INTERCONNECTIONS:

10.1 Interconnection arrangements between the cable termination rack, relay rack, control panel, power and battery room shall be carried out as follows:-

10.1.1 Interconnection between relay rack and FTOT, relay rack to control panel shall be carried out with cable having plain, annealed copper, multi core/single core conductor of 1/1.5 sq.mm PVC insulated, unarmoured, unsheathed 1100v grade cable.

10.1.2 Relay rack to relay rack wiring shall be done with 16/0.2mm PVC copper conductor by soldering process.

10.1.3 The inter-connection between the relay rack and power room, power room and FTOT, Block Instruments and FTOT shall be carried out with underground, armoured, sheathed, power/ signalling cables of adequate length. The termination shall be carried out using suitable size of copper eyelets/sockets. Inter-connection between power rack and battery room, shall be carried out by using suitable underground cables.

10.2 All the interconnecting wires shall be supported by means of Aluminium ladder. Ladder of suitable capacity shall be manufactured using Aluminium angles of size 50mmx50mmx6mm and Aluminium flats of size 25mmx6mm. The inter spacing between two rods of the ladder shall not be more than 125mm. The corners of the ladders as well as the inner path of the ladders shall be of curved shape and shall not damage the insulation of the inter-connection wire. The bends also shall not be steep. The bottom of the ladders shall be provided with hylum sheet of 3mm thickness. The ladder shall be fixed firmly with proper Aluminium flats.

10.3 The interconnection arrangement includes laying of signalling cables in ducts wherever necessary as indicated by Railways. Wherever cables are taken through cable ducts inside relay room/ battery room etc., the ducts shall be filled with river sand upto the floor level and covered with RCC slabs.

10.4 All connections/terminations shall be tested by the contractor and after satisfying himself jointly with Railway Representative. Any alterations required shall be carried out by the contractor free of cost.

10.5 Cable details, functions allotted to each core and terminal numbers shall be prepared in standard size RP film and handed over to Railways.

11.0 POWER SUPPLY ARRANGEMENT :

11.1 INSTALLATION IN POWER ROOM:

Page 125: MEMU Master

Page 88 of 113

Transformers, battery chargers, transformer rectifiers, voltage stabilizers, inverter, etc., as detailed in the schedule shall be installed and wired as per approved power diagram in power room. The list of materials to be supplied by Railways and contractor is given in Vol.I.

11.2 The contractor shall manufacture a power supply panel using 1200x1200mm hylum sheet not less than 10mm thick for mounting meters, switches/fuses, etc. as required by Railways. It shall be installed on a frame made of MS angles of size 25x25x6mm, MS flat of size 50x6mm and grouted to the wall after leaving sufficient space from the wall for testing and replacement. The cable shall be fixed on TW base plank of size 25x150mm using TW cable clamps of size 50x50mm and terminated on PBT Terminal blocks.

11.3 For mounting transformers, battery chargers, voltage stabilizers and other power supply equipments, a suitable stand made of MS angles of size 65mmx65mmx8mm and MS flats 50mmx6mm and with Hard Wood reapers of size 100mmx50mm shall be grouted to the wall and at floor. The power supply arrangements wiring shall be carried out using 7/1.4 mm PVC Copper wire as per the approved circuit diagram. The voltage stabilizer shall be installed at a suitable place as required by Railways and arrangements shall be made to isolate and put through the stabilizers if it becomes defective without disconnecting the leads.

11.4 Ammeter and Stabiliser by-pass arrangements shall be provided on the panel to prevent ammeter being always in the circuit. After wiring, the power rack shall be tested jointly. The power rack shall be energised to its rated capacity and kept in that condition for not less than a week before commencement and any defect notice shall be rectified by the contractor. The Guarantee Certificates and Technical Pamphlets for the power supply equipments shall be handed over to Railways. Any addition/alteration to power supply arrangement shall be carried out during Testing and Commissioning.

11.5 The power rack and power supply equipments shall be painted suitably and uniformly before installation as required by Railways. Schematic diagram of power supply arrangement and distribution details shall be painted on plywood 12mm thick-TW/rough finish as per instructions of site incharge with Aluminium grooved channel frame of size 1200x1800mm and fixed in the power room. As made power diagram shall be submitted in RP film duly indicating the power supply details and position of the equipments.

11.6 The power panel and power rack should be provided with separate earth.

11.7 The power room shall be provided with single door lock arrangement.

11.8 INTEGRATED POWER SUPPLY ARRANGEMENT:

This work involves supply and erection of integrated power supply units conforming to RDSO Specification No.RDSO/SPN/195/2000 with latest amendment as required by Railways and wired.

11.9 PROVISION OF POWER EQUIPMENTS AT LOCATIONS/LC GATE::

Page 126: MEMU Master

Page 89 of 113

The power equipments like Transformer Rectifier, Isolation Transformer, transformers, etc. as mentioned in the schedule should be procured by the contractor and the same shall be installed at the apparatus cases/LC gates as indicated by Railways. The equipments should be wired with 3/0.75mm copper wire. On 400V/230V side, the terminals should be protected suitably to avoid any shock. The particulars of equipments and the description of the circuit should be painted inside the Apparatus case as well as on inner doors. Sufficient HW planks (25mm thick) shall be provided for fixing equipments inside the apparatus case. In case of LC gates, one changeover switch shall be fixed on a hylum board and mounted on the wall inside the gate lodge using MS angles and suitably painted. As per the circuit, the required capacity of HRC Fuse should be provided and wired.

12.0 INSTALLATION OF SECONDARY CELLS AT BATTERY ROOM/ LOCATION:

12.1 This work includes manufacturing of battery stand, charging and installation of the cells as specified in the schedule. Secondary cells shall be initially charged by reputed firms only and shall undergo not less than 3 cycles of charges and discharges as detailed under Item No.41.

12.2 The various sets of charged secondary cells for different circuits shall be installed on battery stands in the Battery room/ Cable Hut of the station. The battery stand will be manufactured using MS angle 65x65x8mm, MS Flats 50x6mm and covered with 100x50mm Hardwood reaper. It shall be painted suitably with anti-corrosive black paint before installation of battery.

12.3 Battery links (copper/lead) with copper lugs crimped and suitable bolts and nuts shall be used for connecting cells. The charged Cells shall be fixed leaving sufficient working space for taking specific gravity reading and distilled water topping. Cells are to be connected with suitable copper lead links sufficient to carry the full load. Immediately after connection, petroleum jelly shall be applied on battery terminals.

12.4 In the Battery room/ Cable Hut wiring of the batteries shall be carried out by PVC 7/1.40mm copper wire with colour codes through PVC Pipes properly clamped and terminated in the T.W terminal box with locking facility in the battery room.

12.5 The details of batteries and the capacity, circuit, date of installation, etc., shall be painted on a board using water proof Plywood of thickness 12mm - TW finish with Aluminium grooved Channel frame of size 1200mmx 1800mm. The specific gravity and voltage reading shall be recorded for each cell in a separate register along with the Guarantee Certificate of the supplier and handed over to the Railway duly signed.

12.6 One Hydro Meter on suitable TW Stand and one battery tester shall be kept in the battery room.

12.7 In case of installation of secondary cells at location boxes, anticorrosive black paint to be coated inside the apparatus case. Additional ventilation arrangements shall be made. The date of installation, capacity serial No. and circuit particulars shall be painted on each cell and inner side of the door.

12.8 All connections/termination shall be tested by the contractor and after satisfying himself then to be tested jointly with Railway Representative. Any alterations shall be carried out by the contractor during testing and commissioning of installation.

Page 127: MEMU Master

Page 90 of 113

13.0 BLOCK INSTRUMENTS:

13.1 Double line block instruments, Neale’s Token instruments and Daido single line block instrument FM type shall be mounted on a block counter. All the outer sides and top of the counter shall be pasted with decolum sheets of required colour as indicated by railways.

13.2 Podanur type single line push button tokenless instrument shall be fixed on the ground as indicated by Railways.

13.3 Necessary Terminal Blocks and Fuse Blocks shall be fixed inside the Block Counter for termination of jumper wires and cables. Cable shall be fixed properly inside block counter and terminated. The Block relays shall be placed inside the Counter and shelf type relays shall be fixed firmly using anti-tilting arrangements. The relays shall be wired and properly identified.

13.4 In case of overhead alignment, the control and block lines shall be brought separately to the glass fronted test panel and terminated using wire PVC 3/0.75mm copper, through PVC tubes of 15/20mm, clamped to the wall. The test Panel shall be manufactured using T.W 25mm thick and separate doors shall be provided for block and controls. 4 Nos. of DPDT switches and required number of Lightning Discharger shall be fixed. The lead-in wires shall be soldered to the Block and Control Lines at the Wall Bracket.

13.4.1 From the termination box, block wires should be taken through PVC tube of suitable size suitably clamped in the wall and terminated inside the block counter.

13.4.2 The inter connection between the instrument and line battery (provided in the battery room) shall be done with underground cables.

13.5 In RE area block filters and block bell equipments should be installed and wired. The work involves installation of Block Filters and Block Bell equipments on a stand made with MS angles 50mmx50mmx6mm grouted to wall with T.W top plank of 25mm thick, termination of jumper wires in T.W Terminal box of size 300mmx450mmx100mm, wiring including interconnection between Terminal Box.

13.6 The block counter shall be provided with a suitable lock with 2 keys.

13.7 Separate block earth shall be provided for each section on either side.

13.8 INSTALLATION OF WAY STATION EQUIPMENTS :

The way station equipment such as selector, selector bell box shall be fixed at appropriate places and wired. The control telephone and battery shall be installed in suitable place and battery boxes manufactured out of TW. The wiring between the test panel/termination box and telephone cum battery box shall be carried out with PVC copper wire 3/0.75mm. The wiring from the equipment and telephone shall be carried out by using signalling cable.

14.0 INSTALLATION OF DISTILLED WATER PLANT:

Page 128: MEMU Master

Page 91 of 113

14.1 One set of Distilled water Plant capacity- 3.5 to 4.5 Litres/Hr., with two detachable heating elements of 1500W each to work on 230V AC, single phase, fitted with automatic cut-outs and removable connectors, with stainless steel boiling chambers, steel condenser pipe, toughened glass lid shall be installed at Distilled Water Plant Room on suitable stand.

14.2 For water supply, a fibre tank similar to ‘SINTEX’ make – 200 litres capacity shall be installed on cut rails, grouted to wall at suitable place indicated by Railway Representative.

14.3 The water supply connection from water tap towards fibre tank and Distilled Water tank shall be made using good quality of GI pipes, bends, taps and valves of 25mm dia wherever required.

14.4 The water pipe lines shall be clamped at required places using proper size of clamps. One separate power socket with fuse indication shall be provided and wired for distilled water plant.

14.5 The Distilled water plant shall be tested for its satisfactory working jointly with Railways.

15.0 INSTALLATION OF SM's SLIDE INSTRUMENT AT STATION/LC:-

15.1 AT STATIONS:

15.1.1 SM's Slide Instruments shall be installed at the Station on suitable block counters. T.W plank 25mm thick shall be fixed on the top of the Block counter over which the S.M's Slide control instrument shall be fixed. Sufficient working space shall be left for carrying out wiring. Wiring shall be done with 3/0.75mm copper wire. Care shall be taken to keep the wiring free from the slides. The spare contacts shall be paralleled.

15.1.2 Wiring leads brought out from SM's Control Instrument shall be terminated inside the counter. The signalling cables shall also be terminated inside the counters using PBT terminals fixed on laminated termite proof particles board - Exterior Grade - 25mm thick. The terminals particulars shall be neatly painted on the inner side of the doors. No wiring shall be exposed. Suitable colour decolum sheets shall be pasted on all outsides and top of the block counter.

15.2 At LCs the SM slide instrument shall be installed on a shelf made using hardwood plank of size 25mm thick. The plank shall be fixed on 2 MS angles 50x50x6mm of suitable length and grouted on the wall. The cable shall be taken through GI pipe from ground level. For termination of cables, a termination box of size 50cmx60cm made up of HW with decolum finish fitted with PBT terminals shall be fixed below the SM’s slide instrument. The SM’s control instrument shall be wired as per the approved circuit diagram. The particulars of the terminal shall be painted on the inside door of the termination box.

15.3 The SM's Slide Instrument shall be painted suitably as desired by Railways.

15.4 The SM's Control Instrument shall be earthed.

Page 129: MEMU Master

Page 92 of 113

16.0 SUPPLY AND INSTALLATION OF SOLAR PANEL:

16.1 The work consists of fabrication of MS frame of suitable size for the Solar Panels and its erection.

16.2 The frame shall be fabricated using MS angles of size 65mmx65mmx6mm and MS slotted angles of size 40mmx40mmx5mm, MS flats of size 40mmx10mm and MS plates of size 100mmx100mmx6mm.

16.3 The fabricated stand shall be erected and fixed on top of the Station building/LC gate rigid to withstand any adverse weather condition and the frame shall be fixed in slanting position.

16.4 The frame shall be painted before the Solar panels are fixed on the frames.

16.5 Suitable Number of Solar Panels (mono Crystalline Silicon, Solar Photo-Voltaic(SPV) Panels of required ratings shall be fixed in one frame using bolts and nuts.

16.6 The Solar Panels shall be connected in series/parallel as per the approved circuit diagram using wire PVC 3/0.75mm and 16/0.2mm copper.

16.7 The wiring from the Solar Panel to the cells shall be done by using cables taken through 50mm GI pipes fixed firmly using MS clamps.

17.0 ERECTION AND WIRING OF ILLUMINATED DIAGRAM:-

17.1 The Illuminated diagram shall be installed firmly above the S.M's slide instrument as indicated by the Railways on suitable supports. Before commencing wiring, the indication lamp details shall be painted in the inner side of the illuminated diagram. The illuminated diagram shall be wired with 16/0.2mm PVC flexible copper wire by soldering process using best quality of solder. The wires shall be taken through suitable PVC pipes from the Terminal box of the SM's slide control instrument to the illuminated diagram. Precautions shall be taken such that there is no break in the wire and damage to the insulation for the connecting wires. Each wire shall be identified properly. Sufficient spare wires shall be run and terminated duly identified.

17.2 The wiring shall be done in such a manner that enough working space is available for replacement of indication lamps and attend to wiring. The wiring shall be neatly bunched. The frames and board doors shall be painted as required.

18.0 INTERLOCKING OF LEVEL CROSSING GATES :

18.1 WITH LIFTING BARRIERS:

18.1.1 Excavation of pit, concreting foundation as per Drg.No.SG/CN/ 11 and erection of ground lever frame using suitable bolts and nuts. Casting of A type foundations for mounting the cranks is included in the scope of this work. All the foundations will be plastered on the top.

Page 130: MEMU Master

Page 93 of 113

18.1.2 Making rodding connection from the Ground lever frame to the boom locking mechanism through cranks, adjusting and testing the boom locking from ground lever frame. The rod run shall be at rail level and gap of not less than 40mm shall be maintained while crossing the track. All the joints of rod connecting cranks and levers shall be smithy welded. The rod run between the tracks shall be insulated while crossing the track circuited portion The Lengthy roddings shall be run on roller stands fixed on trestle located not more than 2.2 Metres between adjacent supports.

18.1.3 The gate interlocking arrangement shall be carried out as per the standard practice of S.Rly. as per the instructions of the Railway representative at site. Necessary interlocking shall be carried out in the locking tray of the ground frame wherever required by the railways. The locking tray is to be locked and sealed.

18.1.4 The lifting Barrier will be painted with two coats of enamel paint of approved quality as given below:

(A) Stands-Black(B) Boom with fringes: Black and Yellow stripe 300 mm wide alternatively

(C) Stop Disc on the boom: Red

18.1.5 Florescent paper strips should be pasted on both the lifting barrier boom.

18.2 WITH SWING GATES:

This work consists of fixing of gate locks on the each gate. The gate lock consists of 2 Nos. of `E' type locks. for each gate fixed on suitable MS flat min.10 mm thick as instructed by Railway representative at site. The arrangement shall be painted as per standard Railway practice.

18.3. INSTALLATION OF ELECTRONIC GATE WARNING EQUIPMENT:

The work includes fixing of Gate warning equipment on suitable fixtures as per Railway standard for LC gates - 2 Nos. one on each side of the track, fixing of amplifier at apparatus case and hooter at Road warning signal post, wiring as per approved circuit diagram and painting.

19.0 INSTALLATION OF ELECTRIC LEVER LOCK AND CIRCUIT CONTROLLER:-

19.1 This work includes excavation of pit, concreting of rail post vertically, fixing of electric lever lock and circuit controller on the rail, wiring, provision of MS Cover for EL&CC, provision of fabricated `FREE’ indication box, painting and concreting. The lever lock and circuit controller shall be connected to the lever through crank and 32mm/20mm MS rods/ joints through smithy welding. Free indication box shall be provided and all these equipment shall be wired with wire PVC 3/0.75mm as per the approved circuit diagram.

19.2 INSTALLATION OF LEVER LOCK CIRCUIT CONTROLLER INSIDE THE CABIN:

Page 131: MEMU Master

Page 94 of 113

The Electric Lever Lock and Circuit Controller should be fixed vertically on the rails inside the cabin below the concerned lever. The fixing rail is to be concreted. Also Counter motion crank is to be fixed on lever mounting channel and the same is to be connected with lever as well as lever lock circuit controller. The rods should be adjusted to correct length by smithy welding. Necessary notches are to be cut on the plunger of the lever lock and circuit controller as desired by Railways. The same should be wired with 3/0.75mm copper wire as per circuit diagram. The bands of the circuit controller are also to be cut as per the circuit diagram. The correct functioning of the lever lock and circuit controller is to be tested in presence of Railway representative. The lever lock and circuit controller, cranks and the connecting rods should be painted neatly.

20.0 INSTALLATION OF STAND-BY DIESEL GENERATOR SET:

20.1 The stand by diesel generator plant with control panel shall be installed in the generator room as per standard practice adopted by the Railways using anti-vibration packing to minimise the vibration. The exhaust pipe to be extended outside the room with minimum number of bends and the silencer is fixed towards the off side of the SM's Room. Required number of anti-vibration mounting (cushy foot) shall be provided by the contractor.

20.2 Necessary asbestos rope should be wrapped around the exhaust pipe. The control panel of the Diesel Generating set should be properly mounted. The wiring of generator and the control panel shall be carried out using PVC 7/1.40mm copper wire, through PVC Pipes, PVC bends and terminated. An Hour meter shall be provided as required by Railways. The changeover switch and phase selector switch shall be provided and connected for changing over, from normal power to stand by and vice-versa or from one phase to another on suitable fixtures as instructed by Railway representative at site.

20.3 The stand by generating plant and control panel shall be earthed.

20.4 Secondary cell of required capacity shall be installed and connected for self- starting facility, wherever required.

20.5 After installation, for initial commissioning, the procedure given in the firm's manual should be strictly followed. Each diesel generating set should be tested on full load continuously as per the rating of the generator, defects noticed if any, shall be rectified by the contractor.

20.6 The generator room shall be provided with a good quality of lock. The work involves supply, fixing and interconnecting phase selector switch and changeover switch for DG sets wherever required.

21.0 INSTALLATION OF DIAGNOSTIC PANEL:

21.1 The work includes manufacture, installation and wiring of Diagnostic Panel. The diagnostic panel will be fabricated from plywood 25mm thick of suitable size depending on yard layout and covered with white decolum sheet. The sides will be covered with Aluminium grooved channel. The yard lay out will be painted on the decolum sheet.

Page 132: MEMU Master

Page 95 of 113

21.2 The interconnections between independent relay contacts wired and terminated and 50 way terminal board on the diagnostic panel will be as per the approved circuit diagram using wire PVC 16/0.2mm copper. The interconnection wires shall be taken through ladders already available. The indications of points, signal, track, slots, LC gate if any, and important relays like LR, ASR, UCR, CHR, etc. shall be indicated in the panel by providing LED. The work also includes provision of (30 - 0 - 30) voltmeter for the internal supply and wiring the same. Test pin and sockets are to be provided and wired.

22.0 ELECTRIC KEY TRANSMITER AT STATION HOUSE:

22.1 Electric key transmitter with/without crank handle fixed to the key shall be installed firmly on suitable angle supports and teakwood boards in the place indicated by Railways, with economiser push switch and wired. The cables shall be terminated on a terminal box made using 25mm thick T.W. planks with decolumn finish and locking facilities. Required number of terminal blocks shall be fixed inside the terminal box for termination of cables and jumper wires. The wiring shall not be exposed. The cables shall be taken to the terminal box using HDPE pipes of 50mm dia. The crank handle shall be welded to the key in such a manner that there is no undue strain to the EKT contacts. The EKT should be painted and the circuit particulars and ward nos. are to be painted in bold letters.

22.2 INSTALLATION OF EMERGENCY KEY PROVING CONTACT:

22.2.1E' type lock having long plunger and key contact shall be assembled and shall be kept in a glass fronted decorated box and wired. The box shall have the locking and sealing facility using 6 levers NAVTAL LOCK with duplicate keys.

22.2.2The contacts shall be made when the key is `IN' and contacts shall break when the key is disturbed or taken `OUT' using a limit switch.

23.0 INTERLOCKING OF SIDING POINTS/TRAP POINTS:-

23.1 For siding points with succession key lock arrangements and trap points, hand plunger lock fitted with "E" type locks shall be provided on gauge tie plates with suitable bolts and nuts. This work includes fixing of switch extension pieces and split stretcher bars. Notches on split stretcher bars shall be cut at site.

23.2 It shall be ensured that, it is not possible to lock the points with an obstruction of 5mm test piece placed between switch and stock rail at 150mm from the toe of the switch.

23.3 `E' type lock shall be fitted to the hand plunger locks with proper bolts and nuts. After ensuring the free as well as the full movement of the plunger, marking shall be done and notches cut on the plunger.

23.4 Proper lubrication shall be done for the smooth operation of points, HP locks and `E' type

locks.

24.0 FIXING OF FACING POINT LOCK:

Page 133: MEMU Master

Page 96 of 113

24.1 For points single end and double end, the required Facing point locks should be fixed on the gauge tie plats. Necessary holes are to be drilled for fixing FPL. On split stretchers, necessary notches are to be cut for correct functioning. The FPL is to be connected to the Rod Transmission through cranks. Necessary smithy work, if required, should be carried out for achieving correct length of the rods. For facing point lock, the lock bar also is to be fixed. All the fittings like FPL, split stretchers are to be painted with black. A MS cover is to be provided for FPL.

24.2 PROTECTION BAR/LOCK BAR:

The protection bar/lock bar, if required, should be fixed close to the stock rail as per Signalling plan. The required lock bar clips (12 Nos.) and stops (4 Nos.) are to be fixed correctly. Necessary holes are to be drilled on the protection bar/lock bar for fixing lock bar clips and the lock bar driving arrangement should be riveted. The same is to be connected to the crank through 32m solid rods and solid joints. Necessary cranks are to be fitted on the sleeper and connected. The protection bar, clips, stops, etc. are to be painted with black paint. Finally, it should be tested for correct functioning.

24.3 FIXING OF POINT/TRAP INDICATORS:

Point indicators and Trap indicators shall be provided at places indicated in the Signalling plan. These indicators shall be firmly fitted on indicator stand on long sleepers/CI stands concreted firmly to the ground through suitable bolts and nuts complete with all ground connections, clear of infringements. Proper size of pins shall be used to avoid longitudinal play. All joints shall be smithy welded only. The indicators shall be adjusted properly and painted suitably.

25.0 FIXING OF ELECTRICAL DETECTOR:

25.1 The electrical detector shall be fixed on the extended gauge tie plate firmly. The switch extension piece shall be fixed on the switches and the point is to be connected with electrical detector by using ground connections. If any smithy work is involved, the same shall be carried out on the ground connection rods.

25.2 A TLD box shall be fixed near the electrical detector and the cable is terminated inside the TLD box. The electrical detector shall be wired with 3/0.75mm copper and the jumper wire shall be taken through hose pipe between electrical detector and TLD box.

25.3 The electrical detector shall be painted with Aluminium paint and the point ground connections, TLD box with black paint. The working of electrical detector shall be tested in presence of Railway representative to conform to obstruction test.

26.0 TELEPHONES:

26.1 PAGING AND TALK-BACK SYSTEM FOR HOME SIGNALS:

Paging and talk-back facility in lieu of Signal post telephone shall be supplied as per specification and installed including voice communication equipment with suitable switching arrangement at Home Signal post and at SM's room. This includes drawal of tail cable through GI pipe 25mm dia and 2mtrs long duly clamped to Signal post with bend

Page 134: MEMU Master

Page 97 of 113

as required at site, termination of tail cable at one end in the apparatus case and other end in the console. In the SM's room, console should be fixed on a table/wall. The wiring shall be done using wire PVC 16/0.2mm copper.

26.2 DESK TYPE TELEPHONES AT STATION HOUSE/APPARATUS CASES/LCs:-

Desk type magneto telephone shall be supplied and fixed at station house/ apparatus case/LCs. /apparatus cases near top points/siding points and securely fixed on shelf planks. It shall be ensured that no other gadgets is kept in that apparatus case and separate door lock arrangement made to protect the Telephone battery.

26.2.1 Nickel-Cadmium power pack 4V - 2.2AH, with battery charger 110V AC/4V DC shall be supplied and provided for telephone.

27 MASONARY PLATFORM FOR POST TYPE TELEPHONES:

Excavation of pit, construction of masonary platform as per Drg.No.SG/CN/02/12 with bricks of approx. size 220mmx100mmx60mm to operate signal Post Telephones near Home Signals and plastering as per the instructions of Railway representative at site.

28 INSTALLATION OF ANNUNCIATOR:

Fixing of Annunciator in the Station house on a suitable HW stand fixed to the table/wall by MS angles, wiring the same using wire PVC 16/0.2mm copper and painting. The hard wood plank shall be pasted with coloured Decolum sheets on all sides. The work also includes supply and wiring of magneto telephone - 1 No. and Ni-cad power pack 4V DC – 2.2AH with battery charger 110V AC/4V DC and painting of various circuit particulars on the Annunciator as instructed by Railway representative.

29 PROVISION OF TW KEY BOX &TOOL BOX:

29.1 PROVISION OF TW KEY BOX:

This work involves manufacture, supply and installation of Glass fronted Teakwood Key box of size 300mmx600mmx75mm with built in lock arrangement. Plastic tags duly engraved giving the particulars of various keys are to be provided along with the keys.

29.2 SUPPLY OF TW TOOL BOX:

A tool box of size 1000mm x750mm x100mm (inner dimensions) made of 25mm thick teak wood, perplex sheet fronted 6mm( Colourless) shall be manufactured and fixed on the wall at a convenient location as instructed by Railway representative at site. The box should have provision of padlock for locking arrangements and shall be equipped with the following tools:

Page 135: MEMU Master

Page 98 of 113

a Multimeter manufactured by Reputed firms similar to Model No.DM 352 of MOTWANE MAKE with suitable carrying case and test probes

1 No.

b Multimeter Model No.HM 102 BZ Hungchung with test probes with suitable carrying case.

1 No.

c Centre zero ammeter 30-0-30 Amps 1 No.d Screw drivers adjustable with common Handle for

different screw drivers (TAPARIA make)1 Set

e Spanner double ended 33mm (TAPARIA make) 1 No.f Spanners double ended 3/8x1/2" (TAPARIA make) 1 No.g Spanners double ended 5/8x3/4" (TAPARIA make) 1 No.h Spanners double ended 7/8x1" (TAPARIA make) 1 No.i Adjustable screw spanner 12" (TAPARIA make) 1 No.j Insulated cutting pliers (TAPARIA make) 1 No.k Insulated nose pliers (TAPARIA make) 1 No.l Hammer 1 1/2 lbs ball pane (GEODRE make) 1 No.m Hacksaw frame (GEODRE make) 1 No.n Electric soldering iron 230V 60W (Soldron/Philips

make)1 No.

o Megger 500V/ 500Mohms. with test probes 1 No.

30 ERECTION OF BOARDS WITH LEGENDS/ GOODS WARNING BOARDS:

30.1 Boards with Legends/Warning boards shall be fitted on to the Rails, erected and concreted to a size of 600mmx600mmx900mm at location indicated by Railway representative and as per approved signalling plan, clear of infringements.

30.2 Necessary legends such as "DRAW CLOSE IF SIGNAL IS AT ON" shall be letter painted as per standard practice of this Railway and as per Signal Engineering Manual.

30.3 For Goods Warning Board about 12 Nos. of Scotch light reflectors/strips shall be provided by the contractor.

30.4 Rail posts and other fittings shall be painted as required by Railways.

31. EARTHING: 31.1 All apparatus cases, battery boxes, CT boxes, armours of cables, battery chargers,

transformers, power panels, Control panel, Block Instruments/Control test panel/Cable Termination Rack/Relay Racks, etc., shall be earthed. If number of apparatus cases are grouped at a place, one earth shall be provided for all. Otherwise, separate earth is to be provided for each apparatus case. The earth resistance shall not be more than 10 Ohms.

31.2 This work includes excavation of pit at a given location as per Drg.No.SG/CN/02/13 on natural soil, supply and fixing earth pipe covering the same with the mixture of 2kgs. of charcoal, 2 kgs. of common salt and earth. A concrete enclosure has to be provided around the earth pipe as per drawing.

Page 136: MEMU Master

Page 99 of 113

32 PROVISION OF LOCKS:

Universal locks (EWS Locks)/GI locks/Navtal Locks shall be provided for CLS units, Route Indicators, point machines, apparatus cases, battery boxes and C.T. boxes wherever necessary.

33. PAINTING: 33.1 Block instruments, Block counters, control panel, EKT’s and all signalling gears installed

shall be painted in accordance with the standard practice of Southern Railway and as per Signal Engineering Manual.

33.2 While painting, initially one coat of primer and afterwards 2 coats of enamel paint shall be applied.

33.3 The details of paints to be used on the signaling gears are shown below.

S.No. Signalling Gadgets Colour to be painted (outside)

I Signal(Colour Light Signal) & Shunt Signal:

(i) Surface base(ii) Post(iii) Aspect unit complete

Black

Aluminium

Black

II All types of apparatus cases and cable termination box

Aluminium

III Track Lead Disconnection Box Black

IV SM’s Control Frame Instrument Green Enamel

V Point machines Black

VI Electrical Detectors Aluminium

VII Electrical Lever locks & Circuit Controller Black

VIII Key Transmitters Red or Black

IX (i)Double line SGE Block Instrument

(ii)Single Line Token Instrument

(iii)Single Line Tokenless Instrument

Green Enamel

Grey Enamel

Green Enamel

X (i)Interlocking frame supports, quadrants, lever below quadrants, locking trough, catch handle connection & Indication plates

(ii)Down rods between Lever tail and crank

(iii)All types of cranks, compensators, Facing point Locks, lock bars & Detectors.

Black

Black

Page 137: MEMU Master

Page 100 of 113

(iv)Roddings & Rod Rollers Black

Red Oxide Paint

XI (i)Point Lever

(ii)Lock Lever

(iii)LC Gate Control Lever

(iv)Spare Lever

(v)Signal Lever

Black

Blue

Chocolate

White

Red

XII Rails Black

34. NON-INTERLOCKED SIGNALLING ARRARNGEMENT:

34.1 Erection and wiring of temporary relay rack, SM's slide instrument, wiring alteration in the FTOT, apparatus cases, signals, Control panel etc., as per the instructions of Railway representative at site for operating signals and points during non-interlocked working.. The work also includes provision of Magneto Telephone communication between Top points /location goomties and SM's Room.

34.2 The SM’s control instrument shall be wired as required by Railways as per the temporary circuit diagram prepared in connection with N.I working. Necessary wooden crosses shall be fixed for the signals put out of use as indicated by railways. Special warning boards/stop/speed boards may be fixed temporarily as per the NI plan.

35. INSTALLATION OF DATA LOGGER:

35.1 The installation and commissioning of Data Logger includes wiring between Data logger equipment and relay rack/power equipment room. The potential free contacts of relays to be monitored will be made available on the tag block of the data logger.

36. RELEASING OF S & T GEARS:

36.1 An inventory of all the S&T gears to be released in the yard should be taken up jointly with Railway’s representative duly indicating as serviceable or unserviceable before NI working commences. The same should be submitted and approved by the Engineering in-charge.

36.2 The S&T gears as mentioned in the schedule should be released carefully without damage and stacked at a place indicated by the Railway representative.

36.3 All the concrete foundation of the released gears like signals, location boxes, ‘A’ type bases, etc. should be broken completely. The resultant pit shall be refilled with earth, rammed and re-surfaced. In case of releasing the stands grouted on the walls/floor should be restored to original condition and neatly plastered.

Page 138: MEMU Master

Page 101 of 113

36.4 All the unserviceable released materials shall be guarded by the contractor till they are auctioned.

37. TRANSPORTATION OF SERVICEABLE MATERIALS:-

The released serviceable materials shall be transported from the work spot to the Stores Depot as mentioned in Vol. I. Loading and Unloading of materials shall be done by the contractor. The released material shall be stacked neatly by the contractor in the Railway Stores.

38. PROCUREMENT OF CEMENT:

38.1 Cement for use in the works shall be procured by the contractor from the main producers/their authorised dealers/ authorised stock yards which shall conform to BIS Specifications.

38.2 Cement bags preferably in paper bag packing should bear the following information in legible marking:

(i) Manufacturer's name

(ii) Registered Trade Mark of manufacturer, if any

(iii) Type of cement

(iv) Weight of each bag in kgs. or No. of bags/tonne.

(v) Date of manufacturer, generally marked as week of the year/year of manufacturer, e.g., 30/93 which means of 30th week of 1993.

38.3 To ensure quality control, test certificates from the manufacturer should be produced by the contractors, which should confirm to the relevant specifications [latest may be incorporated].

38.4 Railways may also take samples during the course of the work and get the cement tested to ascertain their conformity to specifications.

38.5 When such sampling is done, it shall be as per IS Specifications.

38.6 Test on the cement as per IS:4301 shall be carried out in the field level. Some of the tests which may be carried out are:

(i) Compressive strength

(ii) Initial and final setting time

(iii) Consistency

(iv) Soundness

39. WIRES TO BE USED IN S&T INSTALLATION:

Page 139: MEMU Master

Page 102 of 113

The size of various wires/cables to be used for the wiring of signalling and telecommunication gadget is indicated below:

S.No. Size of wire Circuits/Equipments1 16/0.2 mm Copper Relay rack wiring

Panel wiring Plug-in type relay wiring at location

S.No. Type of wire Circuits/Equipments2 7/1.4mm Copper Power equipments

Point control wire(NW, RW & CW)3 3/0.75mm Copper Power equipments in locations

Relays other than plug-in typeBlock instrumentRotary key transmitterAll SignalsElectrical detectorSM’s control instrumentPoint machineLoop wire at locations

40. TESTING & COMMISSIONING INCLUDING AS MADE :

40.1 The entire installation shall be tested by the contractor and after satisfying himself, the railway shall jointly test along with the contractor. Any alteration during testing shall be carried out at free of cost as required by Railways before commissioning. All ‘As made’ documents have to be submitted before commissioning. Each installation shall be tested in the presence of the supervisory officials deputed by the Railways as soon as the particular installation/equipment is installed and unless the working of the equipment is actually ensured, it will not mean that the work has been completed to the satisfaction of the railway. This work involves testing and commissioning of the entire installation.

40.2 ‘AS MADE' DETAILS:

Before testing and commissioning of the entire installation, eight copies of final `as made' details as hereunder shall have to be supplied duly incorporating all particulars for the station. Circuit diagrams prepared in Autocad 2000 will be supplied by Railways in compact discs. All ‘As mades’ shall be prepared by the contractor in Autocad 2000 and submitted in compact discs in duplicate. All ` As made' documents/plans shall be made by the contractor in R.P Film to RAILWAY STANDARD only as laid down in the Special Condition of Contract and shall be handed over to the Railways, duly signed.

a) `As made' circuit diagramb) `As made' Cable Planc) `As made' Cable Route Plan/Red boundary pland) `As made' track bonding plans e) `As made' power supply layout diagramf) `As made' contact analysis chartg) `As made' relay disposition charth) `As made' Termination particulars of all locations & FTOT

Page 140: MEMU Master

Page 103 of 113

40.2.1 However, contractor shall hand over along with the negatives, 8 copies in each, duly making book-let neatly bound. Out of 8 sets, 2 sets of individual circuit and other plans shall be kept in thick plastic cover (2 sheets back to back in one plastic cover) duly filled in plastic folder and handed over to Railways. 2 copies of the above `as made' details before joint testing is taken up with Railways. Any correction made during testing shall be incorporated before submitting `FINAL' `As made' plan.

40.2.2 The contractor is required to supply the following bound registers 200 pages with good quality papers duly filled. (i) Cable meggering register,

(ii) Relay Register, (iii) Block Joint Register, (iv) Route Test Register, (v) Lamp Replacement Register, (vi) Relay Room Key Register, (vii) Battery Register, (viii)Route Cancellation Register and(ix) Earth resistance register.

41 DESIGNING OF CIRCUIT:

The Signalling Plan will be given by Railways to contractor. Based on the Signalling plan, the contractor should prepare Locking Table/Table of Control and submit to Railways within a week’s time for correctness. The railways will correct the same and hand over it to the contractor within a week’s time. After receiving the corrected Locking Table/Table of Control, the contractor shall prepare Circuit Diagram as per S.Rly practice and hand it over to Railways within two weeks for checking. The contractor can take a specimen copy of any approved circuit diagram to acquaint himself with the S.Rly interlocking practices. The Railways will check and make necessary corrections and hand it over to the contractor for final preparation of circuit diagram. About six copies shall be prepared and hand it over to Railways along with the negative within 15 days. The contractor should also give a hard disc duly copying all the circuits.

42 PROCEDURE FOR INITIAL CHARGING OF SECONDARY CELLS:

1 All the cells in the battery set shall be of the same type and capacity.

2 Electrolyte shall be prepared by mixing battery grade Sulphuric Acid and distilled water in the ratio 1:5 in a glass/Porcelain container by adding Acid to water and not vice-versa.

3 The new cells shall be cleaned with distilled water and filled with this electrolyte upto 12-15mm above the plates.

4 Allow the plates of cells to soak in the electrolyte for 12 hours.

5 Charge shall be applied at the rate of 4% of AH value of the cells to the correct terminals of the battery set duly interconnected.

6 Specific Gravity and voltage of each cell shall be measured and recorded once in 8 hours.

Page 141: MEMU Master

Page 104 of 113

7 Charging shall be stopped when specific gravity becomes 1210 +/ -5

8 If the specific gravity does not attain this value, little quantity of electrolyte shall be taken out and with electrolyte of higher value (1400 – obtained by adding acid and added water in the ratio 7:11) and charging shall be started afresh.

9 On charge, the cells shall be discharged with lamp load upto the limit when the specific gravity becomes 1190 and voltage 1.85 volts.

10 Charge and discharge cycle shall be repeated once again.

11 Final charge shall be given for putting the cells to use.

--ssSss--

Page 142: MEMU Master

Page 105 of 113

CHAPTER – IV

LIST OF DRAWINGS

1 SG/CN/O2/1 – TRACK AND ROAD CROSSING

2 SG/CN/O2/2 – CABLE PROTECTOR REINFORCED (‘V’ TROUGH)

3 SG/CN/O2/3 – CHASE CUTTING IN ROCKY AREA

4 SG/CN/O2/4 – CHASE CUTTING IN ROCKY AREA

5 SG/CN/O2/5 – CABLE MARKER AND CONCRETING

6 SG/CN/O2/6 – FOUNDATION FOR APP. CASE (FULL)

7 SG/CN/O2/7 – FOUNDATION FOR APP. CASE (HALF/QUARTER)

8 SG/CN/O2/8 – FOUNDATION FOR CABLE TERMINATION BOX

9 SG/CN/O2/9 – FOUNDATION FOR COLOUR LIGHT SIGNAL

10 SG/CN/O2/10– FOUNDATION FOR SHUNT SIGNAL

11 SG/CN/O2/11– FOUNDATION FOR GROUND LEVER FRAME

12 SG/CN/O2/12– MASONARY PLATFORM FOR SIGNAL POST TELEPHONE

13 SG/CN/O2/13– MASONARY WORK FOR EARTH ELECTRODE

Note: The above drawings may be obtained from the office of the Deputy Chief Signal & Telecommunication Engineer (Construction), Southern Railway, Ernakulam Junction.

--ssSss--

Page 143: MEMU Master

Page 106 of 113

CHAPTER –V

LIST OF SIGNALLING MATERIALS WITH THEIR SPECIFICATION/DRAWINGS

The Signalling & Telecom Materials to be supplied by the contractor will be to the following specifications/drawings with the latest amendments:

I. UNDERGROUND SIGNALLING AND POWER CABLES & WIRES:

1 PVC Insulated, armoured, unscreened Underground Signalling Cable ------- Core as per Specification No.IRS-S-63-89(Amendment-5). The core of the cable shall be given in Vol. I.

2 PVC Insulated, armoured, unscreened, Underground Power cable to Specification NO.IRS.63/89(Amendment-4) and IS.1554.

3 PVC Insulated, Railway signalling indoor Multi core/Single Core cable/wire to IRS Specification No.IRS-S-76/89(Amendment-1).

II. COLOUR LIGHT SIGNAL AND ACCESSORIES:

1 Signal Colour Light Multi Unit type 4/3/2 aspect without side light, signal transformers, lamps and lenses as per RDSO Drg.No.SA-23001 -23003A/M(Adv.) latest and IRS.S.26/64. The mounting socket should be provided for 140mm dia to RDSO Drg. No.SA-23005 A/M(Adv.) latest

2 Colour Light Signalling Tubular post 4.6/3.6 metres long conforming to IRS Spec. No.IRS/S-6-81, .

3 Route Indicator-Direction type, 5 unit Arm, 1 way - 6 way as per Drg.Nos.SA-23401-23406 and IRS.66/84 complete with fittings, mounting sockets 140mm dia to RDSO Drg.No.S.23005/M(adv)& IRS-S-66/84 without lamps, lens & signal transformer. (Suitable arrangement should be provided to fix the Arm as per Unit Combination ‘a’ and ‘b’ indicated on the drawing)

5 Ladder for colour light signal multi unit type 4.5 Metres as per RDSO Drg.No.SA-23153(Adv.)

6 Ladder for colour light signal multi unit type 3.5 Metres as per RDSO Drg.No.SA-23150(Adv.)

7 Signal Base for 140mm dia post as IRS(S) Drg.No.S-2011/M.8 Offset Signal bracket (large and small) with ‘U’ bolts and nuts for 140mm CLS post 9 ‘P’ /’’G’/’C’Marker (Non-illuminated) as per Drg.No.SA 23455-56/Adv/Alt110 Shunt Signal position Light type as per RDSO Drg.No.SA.23840(Adv.)11 Signal Colour Light Transformer as per IRS Specn. No.IRS-S-59&S-23 and RDSO

Drg.No.SA-23014/M latest, (IRS-59/77 with amendment -1)12 Lens optical outside step for long range colour light signal, 140mm dia 13mm focal

length ‘Red’ as per Specn. No.IRS-S-7/92 with latest amendments & IRS-S-10 and Drg.No.RDSO-S-23063/M (Adv.) latest.

Page 144: MEMU Master

Page 107 of 113

13 Lens Optical outside step for long range colour light signal, 140mm dia 13mm focal length ‘Yellow’ as per IRS-S-10 and drg.No.RDSO-S-23064/M(Adv.)

14 Lens Optical outside step for long range colour light signal, 140mm dia 13mm focal length ‘Green’ as per Specn. No.IRS-S-7/92 &IRS-S-10 and drg.No.RDSO-S-23065/M(Adv.) latest.

15 Lens Optical , inside step without Hot Strip for long range colour light signal, 213mm dia, 102mm focal length ‘clear’ as per Specn. No.IRS-S-7/92 &IRS-S-10 and Drg.No.RDSO-S-23060(Adv.) latest

16 Lens Optical , inside step with Hot Strip for long range colour light signal, 213mm dia, 102mm focal length ‘clear’ as per Specn. No.IRS-S-7/92 &IRS-S-10 and Drg.No.RDSO-S-23061/M latest

17 Lens Optical outside step 92mm dia, 16mm focal length ‘Lunar white’ as per Specn. No.IRS-S-7/92 &IRS-S-10 and Drg.No.RDSO-S-23422(Adv.) latest

18 Lens Optical inside step with moulded prism for close up indication 127mm dia 70mm focal length ‘Clear’ as per Specn. No.IRS-S-7/92 &IRS-S-10 and Drg.No.RDSO-S-23421(Adv.) latest.

19 Lens Optical inside stepped ‘Clear’ 101mm dia as per Specification No. IRS-S-7/92 & IRS-S-10 and drg.No.RDSO-S-2743/M.

20 Lamp Electric for Railway Signalling ‘Clear’ 12 Volts, 33 Watts 3 Pin double filament, double pole Sl.21 of Specification No.IRS-S-57/93 with Amendment-2.

21 Lamp Electric for Railway Signalling ‘Clear’ 12 Volts, 25 Watts/3 Pin double filament, double pole Sl.17 of Specification No.IRS-S-57/93 with amendment-2.

22 Lamp Electric for Railway Signalling ‘Clear’ 110 Volts, 25 Watts /3 Pin single filament, Sl.33 of Specification No.IRS-S-57/93 with amendment-2.

23 Lamp Electric Triple pole for Railway Signalling ‘Clear’ 12V, 24 Watt/3 pin double filament Sl.35 or 35-A of Specification No.IRS-S-57/93 with amendment-2.

24 LED signalling unit to Specn. No.RDSO/SPN/153/199825 Lenses Polycarbonate, Clear, Red & Green to Specn. No.IRS:S-7/92

(Amendment-3)& Drg.No.S-2484526 Electric Lamp Filament Switching unit to Specn. No.RDSO/SPN/158/2000

&Drg.No.SA2485127 Lamp Holder Unit for CLS lamps to Drg. No.SA-23030/M(ADV) & for Triple Pole

Lamps Drg. No.SA-24831.

III RELAYS AND ACCESSORIES:

1 Relays - `Q’ series ECRS Metal to Carbon to specn. No.BRS.941 & 942 & STS/E/RELAYS/DC LIT LED SIGNAL/03-2000, STS/E/RELAYS/AC LIT LED SIGNAL/03-2000 (ON, OFF, ROUTE, SHUNT & DCECR, ON, ROUTE & FOR LED SIGNAL)

2 Relays – ECRS (Metal-to-Metal Contact) – ON, OFF, ROUTE & SHUNT to Specn. No.IRS:S-46 Firms’ specification.

3 Relays—‘Q’ series Neutral line Relays to spcn. No.BRS:930A(Non-ACI) &BRS:931A(ACI)

4 Relays— Track--Plug-in type 9&4 ohm (ACI & Non-ACI) to specn. No.BRS:938A, 939A, 966 & Appendix F2

Page 145: MEMU Master

Page 108 of 113

5 Relays – special type to specn. No.BRS:930A, 932A, 935A, 937A, 943, 960 & RDSO/SPN/84/88, firm’s specification, etc.

6 Point Contactor unit to specn. No.IRS:S-46& Firm’s Specn.

IV TRACK CIRCUITS COMPONENTS & ACCESSORIES:

1 Track lead Junction Box as per RDSO Drg.No.SA-20101/M complete with 450mm long 25mm dia pipe, terminals and stump.

2 Choke Type ‘B’ having annealed enameled copper wire, as per IRS Specn.No.IRS-S-65/83.

3 ‘Disc’ Type Track Feed Resistance as per Drg.No.SA-20161-66/M4 Surge Discharger Type ‘A’ Non Restoration type as per IRS-S-52-76 with latest

amendments but without hard ware materials, i.e., bolts, nuts, washers, etc. and connection cables and Aluminium terminal lugs.

5 Track feed battery charger as per IRS Specn. No.IRS:S-89-93 with Amendment-16 Channel Pin single Groove 7mm dia (for 4mm dia) Bond wire as per IRS:S-17-757 Bond wire clip (52Kg.-90R Rails) as per RDSO Drg. No.S-22167(Adv.)8 Wire GI soft. 4mm (8 SWG) as per IS Specn. No.IS-2809 Audio frequency Track circuit equipments to RDSO Specn. No.146/2001

V INSULATIONS:

1 Insulated Rod Joint 32mm butt end as per RDSO Drg.No.SA-3637/M(Adv.)Alt.22 Insulation for Gauge tie plate (BG)complete with insulating bush and washer each

set comprising of:(a) Insulating plate for insulated tie plate BG as per RDSO Drg.No.T-10372- 1 No.(b) Insulating bushing for insulated stretcher bar BG as per RDSO Drg.No.T-10368 – 3 Nos.(c) Insulating Washer for insulated stretcher bar BG to IRS 40/84 as per RDSO drg.No.T-10371 – 6 Nos.

3 Insulation for altering stretcher bars(BG) each set comprising of (a) Insulating plate for altering insulated stretcher bars BG as per RDSO Drg.No.T-10384 – 2 Nos.(b) Insulating bushing for altering insulated stretcher bars for BG as per RDSO Drg.No.T-10535- 4 Nos.

4 Insulation for stretcher bars BG. Each set comprising of:(a) Insulating side plate for insulated stretcher bars BG as per RDSO Drg.No.T-10367 – 1 No.(b) Insulating bushing for insulated stretcher bars BG as per RDSO Drg.No..T-10368 – 2 Nos.(c)Insulating washer for insulated stretcher bars BG as per RDSO Drg.No.T-10371 – 4 Nos.

Page 146: MEMU Master

Page 109 of 113

5 Insulated Rail joint Nylon (Four channel type) 60 Kg. UTC complete as per RDSO Drg.No.SA-22181(Adv.) latest.

6 Insulated Rail joint Nylon (Four channel type) 52 kg. Complete as per RDSO Drg.No.SA-22101(Adv.) latest without iron & steel parts.

7 Insulated Rail joint Nylon (Four channel type) 90R complete as per RDSO Drg.No.SA-22191(Adv.) latest without iron and steel parts.

8 Insulated Rail joint Nylon (Four channel type) 60R complete as per RDSO Drg.No.SA-22131(Adv.) latest without iron & steel parts.

9 Insulated Rail joint Fish plate as per RDSO Drg.No.S-22101(Adv.)10 Rail joint Insulated backing plate 52kg. as per RDSO Drg.No.S-28107(Adv.)11 Rail joint Insulated backing plate ‘90R’ as per RDSO Drg.No.S-22117(Adv.)

12 Rail joint Insulated ferrule as per RDSO Drg.No.S-22108(Adv.)13 Throw bar lug insulation for 5 E point machine to Drg. No.SA-9001 and SA-9002

Driving lug insulation for IRS point machine – One set comprises of (a)Insulating plate to Drg.No.S-8804 - 1 No.(b)Insulating bush to Drg.No.S-8813 - 2 Nos.(c)Insulating washer to Drg.No.S-8640 - 2 Nos.

14 ‘D’ bracket insulation for IRS point machine - One set comprises of (a)Side plate LH to Drg.No.S-3266 - 1 No.(b) Side plate RH to Drg.No.S-3265 - 1 No.(c)Insulating bush to Drg.No.S-3199 - 4 Nos.(d) Insulating washer to Drg.No.S-8640 - 4 Nos.

VIPOWER SUPPLY EQUIPMENTS(The rating of these equipments will be indicated in Volume-I):

1 Transformer 230V AC/110V AC as per IRS Specn. No.IRS-S-72/88 with Amendment-1)

2 Transformer 230V AC/400V AC as per IRS Specn. No.IRS-S-72/88 except for the following modification:Para 1.1: This specification covers the requirement for 230/400V AC 50Hz single phase transformer used for power supply in colour Light Signal installationPara 3.2.3: The primary of the transformer 230/400V AC shall have min tappings at 0, 220, 220 & 230V. The secondary winding shall have min tappings at 0, 360, 380, 400 & 420V, being the nominal voltage at no load.Para 5.9 &5.10: These tests shall be carried out on the secondary winding side between terminals 0 V and 400V.

3 Transformer 400V AC/110V AC as per IRS Specn. No.IRS-S-72/88 except for the following modification:Para 1.1: This specification covers the requirement for 400/110V AC 50Hz single phase transformer used for power supply in Colour Light Signal installationPara 3.2.1: The rated input of the transformer shall be 400V AC.Para 3.2.3: The primary of the transformer 400/110V AC shall have min. tappings at 0, 360, 380, 400 & 420V. The secondary winding shall have tappings at 0, 100, 110 & 120V, being the nominal voltage at no load.Para 5.8: Open circuit test shall be carried out with 400V AC applied on the primary winding between terminals 0V and 400V.

Page 147: MEMU Master

Page 110 of 113

Para 5.12: Short circuit test shall be carried out with 400V applied to the primary winding at terminals 0V and 400V.

4 Indication Transformer for lamp proving as per IRS Specification No.IRS-S-62-92 5 Battery chargers for MFVR batteries to IRS.S-93/96B6 Battery chargers –SMPS based to RDSO/SPN/160/997 Battery chargers self regulating as per IRS Specn.No.IRS-S-86/2000 with

Amendment-18 Battery chargers Dual Bank as per IRS Specn.No.IRS-S-85/92 with Amendment-19 Voltage Stabilizer Ferro resonant type as per Specn.No.IRS-S-74/89 with

Amendment-6.10 Inverter for Railway Signalling installations for ‘On Line’ applications (with sine

wave output) as per IRS Specn.No.IRS-S-82/92 with Amendment-211 D.G set as per IRS:S-69/8612 Secondary cell-Low Maintenance to Specn. No.IRS-S-88/9313 Secondary cell- Maintenance Free to Specn. No.IRS-S-93/96A14 Solar photo voltaic module to Specn. No.IRS:S-84/9215 Transformer rectifier set to Specn. No.IRS:S-91/93 with Amendment-116 SMPS based IPS to Specn. No.RDSO/SPN:165/2000 with amendment 117 DC-DC converter to Specn.IRS:S-96/2000

18 Indication supply transformer(step down) for Railway S&T installations to IRS:S-83/92

19 Dual bank battery charger to Specn. No.IRS-S-85/9220 High voltage signal feed transformer to IRS:S-92/9321 Ni-CAD cells with charger to Specn. No.IS-10918

VII ACCESSORIES TO BLOCK INSTRUMENTS:

1 Block Bell Equipment to Block instrument as per Specn. IRS:TC-44/882 Filter Unit to Block instrument as per specn. No.IRS-S-68/89

VIII TERMINAL BLOCK, FUSE BLOCK &FUSE:

1 Terminal Block(M6-Terminals) (1 way-25mm) as per IRS Specification No.IRS-S-75-91 Amendment-2 and IRS Drg.No.SA-23741/A(Alt.4)

2 Terminal Block(M6-Terminals) (1 way 60mm) as per IRS Specification No.IRS-S-75-91(Latest) and IRS Drg.No.SA-23745/A(Alt.5)

3 Fuse Link cartridge cylindrical head(2A, 4A and so on) non-deteriorating type, non indication type as per IRS Specification No.IRS-S-78/92

4 Fuse Block as per IRS(S) Drg.No.SA-23748(Alt.4) IRS.75-91(Amendment 2)

Page 148: MEMU Master

Page 111 of 113

IX ELECTRO MECHANICAL ITEMS:

1 Electric Lever Lock and Circuit Controller combined 200mm stroke as per Drg.No.SA-22401(Adv.)

2 Electric point & lock Detector (with cross protection contacts) to IRS:S-49/74 (amendment-1) (For Single Pair of Point and Lock with In and Out movement), Drg.No.SA-23331(Adv.) (For Single Pair of Point and Lock with straight through movement), Drg.No.SA-23332(Adv) (For Double Slip Points), Drg.No.SA-23333(Adv)

3 Electric key transmitter to Specn. No.IRS:S-21/64(Amendment-1) & Drg.No.SA-22601.

X MECHANICAL ITEMS:

1 Lock Key ‘E’ type as per IRS Drg.No.SA-3376/M.2 Interlocking Frame Ground Type Single lever as per IRS:S-30/64

RDSO Drg.No.SA-922(Adv.)3 Lock facing point(H.P type) with key locks base as per IRS Drg.No.S-3152/M4 Lock facing point(H.P type) Split stretcher bar (BG) 52kg. Rail as per IRS

Drg.No.SA-3162/M5 Lock facing point(H.P type) Split stretcher bar 90R Rail as per

IRS Drg. No.SA-3163/M6 Indicator point on Trestle with short lamp base as per RDSO Drg.S-5777/2/M(Adv.)XI MISCELLANEOUS EQUIPMENTS:

1 Block Section/Shunting Limit Board as per RDSO Drg.No.SA-2373 (Adv) latest.2 RCC pipe 100mm inner dia 150mm outer dia 2 metre long with collars to IS

Specn.No.458/1971.3 Earth Leakage detector single channel/Multi-channel suitable to work on 110Voltage

50Hz single phase AC as per RDSO/SPN-256/77 complete with electro-magnetic counter.

4 Magneto Telephone Desk Type to IRS TC-36-855 Data Logger to Specn. No.IRS-S-99/20016 Paging and Talk Back System in lieu of Post Type Telephone as per details given

below:Specification:(a)System shall be capable of working on two wire only and no separate power supply to be provided at Home Signal. It should facilitate hand free listening(b)Audio and Visual indication using LEDs and Piezo Buzzer for power ON and Ringing(c)Easy removal of PCB for replacement in case of any failure(d)PCB connectors of different sizes to prevent wrong connections(e)Equipment should be housed in rugged weather proof metal console with a gauge of 1.6mm for field end and 1.0mm for office end

(f) (i)ASM’s Office equipment: Operating voltage : 12V DC

Page 149: MEMU Master

Page 112 of 113

Current consumption : <300mA Audio Power output : >500mW

(ii)Home Signal equipment: Audio Power output : >500mW Calling facility : Press button at the bottom of the unit Mounting : Double clamped on the signal post Housing : Rugged weather proof metal housing

(No separate Power Supply Arrangement)(g) Spares to be handed over for each set to Railway: (i) PCB : 1 No. (ii) Speakers : 2 Nos. (iii) Switches : 1 Set (iv) Fuses : 2 Nos.

Page 150: MEMU Master

Page 1 of 19

VOLUME - III

ATTENTION OF THE TENDERER IS DRAWN TO THE IMPORTANT MODIFICATIONS TO THE

FOLLOWING PARAS OF

REGULATIONS FOR TENDERS AND CONTRACTS AND INSTRUCTIONS TO TENDERERS

PARA 4.0 to 4.3 EARNEST MONEY DEPOSIT

(Vol .II)

PARA 4.4 to 4.4.3g SECURITY DEPOSIT

(Vol.II)

Para15.1 of Vol.II MOBILISATION ADVANCE

Para 16.7.1 to 16.7.8 VARIATION IN QUANTITIES (Vol.II)

New Clause INTRODUCTION OF NEW CLAUSE FOR

PERFORMANCE GUARANTEE

PARA 40 of MODIFICATIONS TO PROVISIONS OF

Vol.II GENERAL CONDITIONS OF CONTRACT

Para 41 of Vol.II MODIFICATIONS TO PROVISIONS OF GENERAL CONDITIONS OF CONTRACT

Page 151: MEMU Master

Page 2 of 19

40. GENERAL CONDITIONS OF CONTRACT WITH FOLLOWING MODIFICATIONS SHALL GOVERN IN THE TENDER.

Sl.No. GCC Item No. Existing Revised1 Earnest Money

Deposit(Clause 5.0)

The tenderer shall be required to deposit earnest money with the tender for the due performance of the stipulation to keep the offer open till such dates as specified in the tender, under Conditions of Tender, ANNEXURE-1. The earnest money will be as under:

The tenderer shall be required to deposit earnest money with the tender for the due performance with the stipulation to keep the offer open tll such date as specified in the tender,under the condition of tender.

i)For works estimated to cost upto Rs.1 Crore-2% of the estimated cost of the work.ii)For works estimated to cost more than Rs.1 Crore- -Rs.2 lakhs plus ½%(Half percent) of the excess of estimated cost of work beyond Rs.1 crore subject to maximum of Rs.1 crore.

Contract Value

i) for works up to Rs.5 lakh

ii) for works more than Rs.5 lakhs but upto Rs.20 lakhs

iii) for works above Rs.20 lakhs but up to Rs.50 lakhs

iv) for works above Rs.50 lakhs

Earnest money for due performance of stipulation to keep the offer open till the dater specified2½ % ad valorem subject to a maximum of Rs.10000/-

2% ad valorem subject to a maximum of Rs.20000/-

1% ad valorem subject to a maximum of Rs.35000/-

¾% ad valorem subject to a maximum of Rs.50000/-.

b) It shall be understood that the tender documents have been sold/issued to the tenderer and the

No Change.

Page 152: MEMU Master

Page 3 of 19

tenderer is permitted to tender in consideration of stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Engineer. Should the tenderer fail to observe or comply with the said stipulation, the aforesaid amount shall be liable to to be forfeited to the Railway.

c) If his tender is accepted this earnest money mentioned in sub clause (a) above will be retained as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of the General Conditions of Contract. The earnest money of other tenderers shall save as herein before provided, be returned to them, but the Railway shall not be responsible for any loss or depreciation that may happen thereto while in their possession, nor be liable to pay interest thereon

No Change.

d) The contractors approved for the works in various categories will have the option to deposit the Earnest Money for each individual works or furnish standing Earnest Money at the rates indicated below:

Contract Value: Amount of lumpsum Earnest Money

Upto Rs.5 lakhs Rs.10,000/-

Above Rs.5 lakhs Rs.20,000/-but up to Rs.20 lakhs

Above Rs.20 lakhs Rs.50,000/-but up to Rs.50 lakhs

Above Rs50 lakhs

The practice of allowing Standing EMD is dispensed forthwith for all tenders. Therefore, Sub-Clause (d) stands deleted.

Page 153: MEMU Master

Page 4 of 19

Rs1,00,000/-

2) No part of this fixed lumpsum deposit as Earnest Money can be accounted against the Security Deposit a contractor has to make on the acceptance of his tender and on execution of an agreement. It may, however, be noted by the contractors that this Earnest Money deposited by them is available for forfeiture to the extent specified, in cases where they tender but due to any circumstances fail to keep the offer open for the period specified in the tender documents. The earnest money should be in cash or in any of the following forms:

i) Deposit receipts, pay orders, demand drafts. These forms of earnest money could be either of the State Bank of India or of any of the Nationalized banks. No confirmatory advise from the Reserve Bank of India will be necessary.

ii) Deposit receipts executed by the Scheduled Banks (other than the State Bank of India and the Nationalized banks) approved by the Reserve Bank of India for this purpose. The Railways will not, however, accept deposit receipt without getting in writing the concurrence of the Reserve Bank of India

b) Standing or permanent earnest money may be accepted in the following forms:-

i) A deposit in cash,ii) Government securities

at 5% below the market value,

iii) Deposit receipts or demand drafts of the Nationalised banks,

iv) A deposit in the Post

The Earnest Money should be in cash or in any of the following forms:-

i)Deposit receipts, pay orders, demand drafts. These forms of earnest money could be either of the State Bank of India or of any of the Nationalized banks. No confirmatory advise from the Reserve Bank of India will be necessary.

ii) Deposit receipts executed by the Scheduled Banks (other than the State Bank of India and the Nationalized banks) approved by the Reserve Bank of India for this purpose. The Railways will not, however, accept deposit receipt without getting in writing the concurrence of the Reserve Bank of India

The phrase ``Standing or permanent” stands deleted.

Page 154: MEMU Master

Page 5 of 19

Office Savings Bank,v) National Savings

certificates,

vi) Twelve years National Defence certificates,

vii) Ten years Defence deposits,

viii) National Defence Bonds,

ix) National Savings Certificates,

x) Time Deposit account which came into force on 16.03.1970 and notified under Ministry of Finance, Notification No.F53(7) NS/70 dated 28.02.1970,

xi) IRFC Bonds.

Note: (vi) to (viii) These certificate / bonds may be accepted at their surrender value

2 16(1) Security Deposit

(1)The Earnest Money deposited by the Contractor with his tender will be retained by the Railways as part of security for the due and faithful fulfillment of the contract by the contractor. The balance to make up the security deposit, the rates for which are given below, may be deposited by the Contractor in cash or in the form of Government Securities or may be recovered by percentage deduction from the Contractor’s “on account” bills. Provided also that in case of defaulting contractor the Railway may retain any amount due for payment to the Contractor on the pending “ on account bills” so that the amounts so retained may not exceed 10% of the total value of the contract.

(2)Unless otherwise specified in

The sentence “in the form of Government Government Securities” stands deleted.

Unless otherwise specified in the special conditions, if any, the Security Deposit/rate of recovery/mode of recovery shall be as under:-

(a) Security Deposit for each work should be 5% of the contract value.

(b) The rate of recovery should be at the rate of 10% of the bill amount till the full security deposit is recovered.

© Security Deposits will be

Page 155: MEMU Master

Page 6 of 19

the special conditions, if any, the rates for deposit of security amount by contractors will be as under:-

(i)for contracts up to Rs.1 lakh -10% of the value of the contract.

(ii)for contracts more than Rs.1 lakh and up to Rs. 2 lakhs – 10% of the first Rs.1 lakh and 7-1/2% of the balance.

(iii)for contracts more than Rs.2 lakhs and up to Rs. 2 crore –10% of the first 1 lakh 7-1/2% of the next Rs.1 lakh and 5% of the balance subject to the maximum of Rs.10 lakhs. The amount over and above Rs.3 lakh to be recovered from the progressive bills of the contractors at the rate of 10% till it reaches the required value.

(iv)for contracts above Rs.2 crore – 5% of the contrct value. The amount over and above Rs.3 lakhs to be recovered from the progressive bills of the contractors at the rate of 10% till it reaches the required value

recovered only from the running bills of the contract and no other mode of collecting SD such as SD in the form of instruments like BG, FD etc. shall be accepted towards Security Deposit

Security Deposit shall be returned to the contractor after the physical completion of the work as certified by the Competent Authority. The Competent Authority shall normally be the authority who is competent to sign the contract. If this Competent Authority is of the rank lower than JA Grade, then a JA Grade Officer(concerned with the work) should issue the certificate. The certificate, inter alia, should mentioned that the work has been completed in all respects and that all the contractual obligations have been fulfilled by the contractors and that there is no due from the contractor to Railway’s against the contract concerned. Before releasing the SD, and unconditional and unequivocal no claim certificate from the contractor concerned should be obtained.

(3) No interest will be payable upon the Earnest Money and Security Deposit or amounts payable to the Contractor under the Contract, but Government Securities deposited in terms of Sub Clause(1)of this clause will be payable with interest accrued thereon.

No Change

3 Interest Rate for Advances extended by Railways

Mobilisation advance(for

TheTh The contractor may be granted a recoverable interest bearing mobilisation advance upto 10% of the Contract Value provided he specifically applies for it while Tendering. If the Tenderer fails to apply specifically for mobilization

The contractor may be granted a recoverable interest bearing mobilisation advance upto 10% of the Contract Value provided he specifically applies for it while Tendering. If the Tenderer fails to apply specifically for mobilization

Page 156: MEMU Master

Page 7 of 19

estimated value of work more than Rs.1 Crore)Clause 15.1 of SCC-Vol.II

advance while giving his offer in the tendering stage in cases where grant of mobilization advance is permissible, no subsequent requests from him for grant of this advance will be entertained. The rate of interest is 18% per annum.

advance while giving his offer in the tendering stage in cases where grant of mobilization advance is permissible, no subsequent requests from him for grant of this advance will be entertained. The rate of interest is 14% per annum

4 Variation in quantirties(item 16.7 of Special Conditions of Contract-Volume-II)

16.7.1 The drawings referred to in the list of plans, if any, are intended only to give a rough and general idea of the location and rough details of work to be done. No claim whatsoever will be admissible in respect of any alteration/addition /change in the type of works.

16.7.2 The quantities of various items given in the schedules for the works to be executed are only approximate and are only for the guidance of the contractor. As far as possible, they have been assessed correctly but are likely to vary during the execution of the work. The contractor’s attention is drawn to Clause 42 of the General Conditions of Contract dealing with variation in quantities.

16.7.5 For increase upto 25% of the quantities indicated in schedule, the contractor shall not be entitled for any compensation and will be paid for such increase in the quantities at the agreement rate.

16.7.6 In the event of reduction in the quantities to be

No change

No change

No change

Page 157: MEMU Master

Page 8 of 19

executed for any reason whatsoever, the contractor shall not be entitled for any compensation but shall be paid only for the actual quantity of work done, at the agreemental rates.-deleted

16.7.5 When the gross value of the work to be executed is likely to increase in excess of 25% of the original value of the agreement, the contractor should notify the Engineer in-charge atleast THIRTY DAYS before such necessity arises.-deleted

16.7.6 When the operation of the quantities results in the agreement value exceeding by 25% to 50%, for the first 15% increase, the payment will be reduced straightaway by 2% in the incremental value of the agreement and for the next 10% increase in the value the payment will be reduced straightaway by an additional reduction of 2% in the further incremental value of the agreement.-DELETED

16.7.9 Notwithstanding the above adhoc reduction, Railway reserves the right to refix the rates, by mutual consent, of those items in the schedule, where the quantities have exceeded by 25% of the agreemental quantities.

16.7.8 Execution of quantities beyond +50% of overall value

No change

No change

i)Individual NS items in contracts shall be operated with variation of plus or minus 25% and payment would be made as per the agreeement rate.For this no finance concurrence would be required.

ii) In case of increase in quantity of an individual item by more than 25% of the agreement quantity is considered as unavoidable, the same shall be got executed by floating a freh tender. If floating a fresh tender is considered not practicable, negotiations may be held with the existing contractor for arriving at reasonable rates for additional quantities in excess of 125% of agreement quantity.iii)The limit for varying quantities for minor value items shall be 100%( as aginst 25% prescribed for other items).A minor value item for this purpose is defined as an item whose original agreement value is less than 1% of the total original agreement value.

iv)No such quantity variation limit shall apply for foundation items

v)As far as SOR items are concerned, the limit of 25% would

Page 158: MEMU Master

Page 9 of 19

shall not be generally permitted. The rate for quantities in excess of 50% of the items shall be decided between the Railway and the contractor in advance of execution of the quantities involved, if in the opinion of the Railway, such quantities are also to be executed by the same contractor. In the event of mutually agreed rate not being arrived at, the Railway shall be entitled to execute the excess work by other means and the contractor shall have no claims on this account.-DELETED

apply to the value of SOR schedule as a whole and not on individual SOR items .However , in case of NS items, the limit of 25% would apply on the individual items irrespective of the manner of quoting the rate(single percentage rate or individual item rate)

vi) The aspect of vitation of tender with respect to variation in quantities should be checked and avoided

5 Introduction of Performance guarantee

NIL

The procedure for obtaining performance Guarantee is outlined below:-(a)The successful bidder shall submit a performance Guarantee(PG) amounting to 5% of the contract value. in any of the following forms:-

i) a deposit of cash

ii) Irrevocable Bank guarantee

iii) Government securities including State Loan bond at 5 percent below the market value

iv) Deposit receipts,Pay Orders,Demand Drafts and Gurantee Bonds. These forms of Performance Gurantee could either of the State Bank of India or any of the Nationalised Banks.

v) Guarantee Bond executed or Deposit receipts tendered by all scheduled Banks.

vi) A deposit in the Post Office savings account

vii) A Deposit in the

Page 159: MEMU Master

Page 10 of 19

.

Nil-

National Savings Certificate

viii) Twelve Years Natinal Defence Cerificates

ix) Ten years Defence Deposits

x) National Defence Bond: and

xi) Unit trust certificates at 5 percent below market value or at the face value which ever is less.

Also FDR in favour of FA&CAO/C(free from any encumbrance ) may be accepted.

b)A Performance Guarantee shall be submitted by the successful bidder after the letter of acceptance has been issued, but before signing of the agreement.The agreement should normally be signed within 15 days after the issue of LOA and the Performance guarantee shall also be submitted within this time limit. This guarantee shall be initially valid up to the stipilated date of completion plus 60 days beyond that,. In case the time for completion of work gets extended ,the contractor shall get the validity of Performance Guarantee extended to cover such extended time for completion of work plus 60 days

c)The Performance guarantee (PG) shall be released after the physical completion of thework based on the “Completion Certificate” issued by the competent authority stating that the contractor has completed the work in all respects satisfactorily. The security deposit ,however shall be released only after the

Page 160: MEMU Master

Page 11 of 19

expiry of the maintenance period and after passing the final bill based on “No Claims Certificate”

d) Whereever the contract is rescinded, the security deposit shall be forfeited and the Performance Guarantee shall be encashed and the balance work shall be got done independently without risk and cost of the failed contractor. Thefailed contractor shall be debarred from participating in the tender for executing the balance work. If the failed contractor is a JV or a partnership firm, then every member/partner of such a firm would be debarred from participating in the tender for the balance work either in his/her individual capacity or as a partner of any other JV/partnership firm.

e) The Engineer shall not make a claim under the Performance Guarantee except for amounts to which the President of India is entitled under the contract (not withstanding and/or without prejudice to any other provision in the contract agreement) in the event of:

i) Failure by the contractor to extend the validity of the Performance Guarantee as described herein above in which event the Engineer may claim the full amount of the Performance Guarantee.

ii) Failure by the contractor to pay President of India any amount due,either as agreed by the contractor or determined under any

Page 161: MEMU Master

Page 12 of 19

Clauses/Conditions of the agreement, within 30 days of the service of notice to this effect by Engineer.

The contract being determined or rescinded under provision of the GCC ,the performance Guarantee shall be forfeited in full and shall be absolutely at the disposal of the President of India.

6 62.Rescinding of contract-Risk & Cost Clause.(GCC)-Para 40 of Vol.II

Determination of contract owing to default of contractor –(1)if the contractor should

(i) Becomes bankrupt or insolvent, or

(ii) Make an arrangement with of assignment in favour of his creditors, or agree to carry out the contract under a Committee of Inspection of his creditors, or

(iii) Being a Company or Corporation, go into liquidation (other than a voluntary liquidation for the purpose of amalgamation or reconstruction), or

(iv)Have an execution levied on his goods or property on the works, or

(v) Assign the contract or any part thereof otherwise than as provided in Clause 7 of these conditions or

(vi)Abandon the contract, or(vii) Persistently disregard

the instructions of the Engineer, or contravene any provision of the contract, or

(viii) Fail to adhere to the agreed programme of

No change in sub-clauses (i) to (xiii)

No change in sub-clauses (i) to (xiii)

Page 162: MEMU Master

Page 13 of 19

work by a margin of 10% of the stipulated period, or

(ix) Fail to remove materials from the site or to pull down and replace work after receiving from the Engineer notice to the effect that the said materials or works have been condemned or rejected under Clause 25 and 27 of these conditions, or

(x) Fail to take steps to employ competent or additional staff and labour and required under Clause 26 of the conditions, or

(xi)Fail to afford the Engineer or Engineer’s representative proper facilities for inspecting the works or any part thereof as required under Clause(28)of the conditions, or

(xii) Promise, offer or give any bribe, commission, gift or advantage either himself or through his partner, agent or servant to any officer or employee of the Railway or to any person on his or on their behalf in relation to the execution of this or any other contract with this Railway.

(xiii) (A)At any time after the tender relating to the contract has been signed and submitted by the contractor, being a partnership firm admit as one of its partners or employee under it or

Page 163: MEMU Master

Page 14 of 19

being an incorporated company elect or nominate or allow to act as one of its directors or employ under it in any capacity whatsoever any retired engineer of the gazetted rank or any other retired gazetted officer working before his retirement, whether in the executive or administrative capacity, or whether holding any pensionable post or not, in the Engineering Department of the Railways for the time being owned and administered by the President of India before the expiry of two years from the date of retirement from the said service of such Engineer or Officer unless such Engineer or Officer has obtained permission from the President of India or any officer duly authorized by him in this behalf to, become a partner or a director or to take employment under the contractor, as the case may be or

(B) Fail to give at the time of submitting the said tender: (a) The correct information as

to the date of retirement of such retired engineer or retired officer from the said service, or as to whether any such retired engineer or retired officer was under the employment of the contractor at the time of submitting the said tender, or

No change in sub-clauses (B) (a) to (e)

Page 164: MEMU Master

Page 15 of 19

(b) The correct information as to such engineers or officers obtaining permission to take employment under the contractor, or

( c) Being a partnership firm, the correct information as to, whether any of its partners was such a retired engineer or a retired officer or,

(d) Being a partnership firm, the correct information as to, whether any of its directors was such a retired engineer or a retired officer, or

(e) Being such a retired engineer or retired officer suppress and not disclose at the time of submitting the said tender the fact of his being such a retired engineer or a retired officer or make at the time of submitting the said tender a wrong statement in relation to his obtaining permission to take the contract or if the contractor be a partnership firm or an incorporated company to be a partner or director of such firm or company as the case may be or to seek employment under the contractor, and after expiry of 48 hours notice, a final termination notice (Proforma as Annexure V) should be issued.

Then and in any of the said clause, the Engineer on behalf of the Railway may serve the Contractor with a notice (Proforma at Annexure –III) in writing to that effect and if the Contractor does not within seven days after the delivery to him of such notice proceed to make good his default in so far as the same is capable of being made good and carry on the

The sentence “and adopt either or both of the followingcourses read with provisions (x) & (y) stand deleted.

Page 165: MEMU Master

Page 16 of 19

work or comply with such directions as aforesaid to the entire satisfaction of the. Engineer, the Railway shall be entitled after giving 48 hours notice (Proforma at Annexure IV) in writing under the hand of the Engineer to rescind the contract as a whole or in part of parts(as may be specified in such notice) and adopt either or both of the following courses:-

(x) to carry out the whole or part of the work from which the contractor has been recovered by the employment of the required labour and materials, the costs of which shall include lead, lift, freight, supervision and all incidental charges,

(y) to measure up the whole or part of the work from which the contractor has been removed and to get it completed by another contractor, the manner and method in which such work is completed shall be in the entire discretion of the Engineer whose decision shall be final and in both the cases(x) and (y) mentioned above, the Railway shall be entitled(i) to forfeit the whole or such portion of the security deposit as it may consider fit and (ii) to recover from the Contractor the cost of carrying out the work in excess of the sum which would have been payable according to the certificate of engineer to the contractor if the works had been carried out by contractor. provided,

)))))))Deleted))))))))))))))))))))

Page 166: MEMU Master

Page 17 of 19

62(2)

however that such recovery can be made only when the cost incurred in excess is more than the security deposit proposed to be forfeited and shall be limited to the amount by which the cost incurred in excess exceeds the security deposit proposed to be forfeited. The amounts thus to be forfeited or recovered may be deducted from any moneys then due or which at any time thereafter may become due to contractor by the railway under this or may other contract or otherwise.

Provided always that in any case in which any of powers conferred upon the railway by sub clause (1) of clause 62 hereof shall have become exercisable and the same shall not be exercised, the non exercise shall not constitute a waiver of any of the conditions there of and such powers shall not withstanding be exercisable in the event of any future case of default by the contractor for which his liability for pasty and future shall remain unaffected.

(2)Right of Railway after rescission of contract owning to default of Contractor – In the event of any or several of the courses, referred to in sub-clause(1) of this clause, being adopted:-

(a)The Contractor shall have no claim to compensation for any loss sustained by him by reason of his having purchased or procured any materials or entered into any commitments or made any advances on account of or with a

))))))))))))))))))))))))

No Change

Page 167: MEMU Master

Page 18 of 19

view to the execution of the works or the performance of the contract and Contractor shall not be entitled to recover or be paid any sum for any work there to for actually performed under the contract unless and until the Engineer shall have certified the performance of such work and the value payable in respect thereof and the contractor shall only be entitled to be paid the value so certified.

(b)The Engineer or the Engineer’s Representative shall be entitled to take possession of any materials, tools, implements, machinery and buildings on the works or on the property on which these are being or out to have been executed, and to retain and employ the same in the further execution of the works of any part thereof until the completion of the works without the Contractor being entitled to any compensation for the use and employment thereof or for wear and tear or destruction thereof.

( c )The Engineer shall as soon as may be practicable after removal of the contractor fix and determined ex-parte or by or after reference to the parties or after such investigation or enquiries as he may consider fit to make or institute and shall certify what amount (if any) had at the time of rescission of the contract been reasonably earned by or would reasonably accrue to the contractor in respect of the work then actually done by him under the contract and what was the value of any unused, or partially used materials, any constructional plant and any temporary works upon the site.

(d)The Railway shall not be liable to the Contractor any moneys on

No Change

The following line is added at the end of sub clause (2) (c) :-The legitimate amount due to the contractor after making necessary deductions and certified by the Engineer should be released expeditiously.

Sub-clause 2(d) is deleted

Page 168: MEMU Master

Page 19 of 19

account of the contract until the expiration of the period of maintenance and thereafter until the costs of completion and maintenance, damages for delay in completion (if any) and all other expenses incurred by the Railway have been ascertained and the amount thereof certified by the Engineer. The Contractor shall then be entitled to receive only such sum or sums (if any) as the Engineer may certify would have been due to him upon due completion by him after deducting the said amount, but if such amount shall exceed the sum which would have been payable to the contractor, then the contractor shall upon demand pay to the Railway the amount of such excess and it shall be deemed a debit due by the Contractor to the Railway and shall be recoverable accordingly

Clause51(3) of GCC

The payment of Security Deposit Deleted.Since it is already covered under the revised Security Deposit Clause 16(1)

7 Clause 17(B) of GCC-Para 41.0 of Vol.II

Extension of time for delay due to contractor

The following may be read alonwith the existing clause.“The competent authority while granting extension to the currency of contract may also consider levy of token penalty as deemed fit based on the merit of the case”