FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
MEP BUILDING INFORMATION MODELLING
PADDY CONAGHAN
Chair CIBSE BIM GroupConsultant: Hoare Lea
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
CIBSE BIM GROUP
Formed Spring 2011
70 members representing (non‐exhaustively):•Government’s BIM Task Group •Consultants •MEP contractors•Main contractors •Manufacturers & trade associations•FM operators•BIM & modelling software vendors •Freelance BIM object builders•Buildingsmart•Institutions: e.g., CIBSE, BSRIA•Etc;
Founding aim : •to create a specification for MEP BIM content creation•To advance BIM in UK MEP Practice
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
BIM – THE CIBSE BIM GROUP ‘MIND MAP’
(18 MONTHS AGO )
THIS IS THE ABRIDGED VERSION!
CROWDED LANDSCAPE
MANY PLAYERS
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
Q2: 11 Q3: 11 Q4: 11 Q1: 12 Q2: 12 Q3: 12 Q4: 12
BIM – THE CIBSE BIM GROUP’S PROGRESS TO DATE
Align‘Show & Tell’
Build MEP Library
WINS BLOBS
Data
Formats
Draft & Promote Product Templates
CIBSE BIM Portal
Respond to ISO, BSI , Gov/Buildingsmart, etc; Collaborate ( BSRIA BG6, CIC, etc); Interface with Vendors &
Industry players, Links to other institutions, & to International MEP BIM; etc;
Roll Out?
‘Buy In?’
Industry Surveys
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
BIM – THE CHALLENGES FOR THE MEP INDUSTRY
Consultants + Contractors (<75% of
Respondants)
60%
Informed
BIM DATA UNAVAILABLE ON
>80% OF UK MEP PRODUCTS
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
All services modelled in 3D
Conceptual modelling
Dynamic modelling / compliance
Fabrication & off site manufacture
Virtual construction Operational data
Space planning in 3D Design model linked to schedules & calcs
C D E F G H J K LA B M
MEP BIM COLLABORATION ‐
THE ‘VISION’
Asset dataBRIEF
5D – Cost
Info
4D – Time
Info
6D – Asset
Info
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
All services modelled in 3D
Conceptual modelling
Dynamic modelling / compliance
Fabrication & off site manufacture
Virtual construction Operational data
Space planning in 3D Design model linked to schedules & calcs
C D E F G H J K LA B M
Asset dataBRIEF
5D – Cost
Info
4D – Time
Info
6D – Asset
Info
MEP BIM COLLABORATION ‐
IN PRACTICE
C D E F1A B G H JF2
‘Generic’
design to Stage F1 (e.g.
Revit
MEP)
Fabrication Information
(usually in CADmep+)‘Hand‐cranked’
FM
information
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
All services modelled in 3D
Conceptual modelling
Dynamic modelling / compliance
Fabrication & off site manufacture
Virtual construction Operational data
Space planning in 3D Design model linked to schedules & calcs
C D E F G H J K LA B M
MEP BIM COLLABORATION ‐
IN PRACTICE
Asset dataBRIEF
5D – Cost
Info
4D – Time
Info
6D – Asset
Info
C D E F1A B G H JF2
Parallel Model
Parallel Model
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
MEP BIM PROCESS ‘DISCONNECTS’
SUMMARISED Absence of product BIM data
• Designers data‐rich generic libraries (usually Revit)
• Contractors’
products libraries (usually CAD mep+);
geometrically exact – but lacking data.
Split process does not embed data in As Fixed Model
Autodesk owns Revit
& CADmep+ ;
BIM Platform switch from design to installation stage
• Will both be continued and enabled to ‘talk’
to each other?
DISCONNECTS ARISE MAINLY WITH DATA – NOT GEOMETRY
SO CAN DATA BE HANDLED ANOTHER WAY?
• Manufacturers’
uncertainty
• Level 2 BIM aims confounded?
• Will one replace the other?
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
BIM DATA CONTENT – REQUIREMENTS (COBie
UK 2012)
CONSTRUCTION OPERATIONS BUILDING INFORMATION EXCHANGE
COBie
LOOKS COMPLEX & SCARY!
BUT ALL OF THE INFORMATION EXISTS SOMEWHERE
THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
CIBSE BIM GROUPS WORK ON DATA MANAGEMENT USA VETERANS ASSOCIATION MASTER MATRIX
FULL PROJECT LIFE CYCLE
LEVEL OF DETAIL (DATA
DRO
P INFO
)
SPECIFICATION DATA
TO BE PROVIDED AT
LOD 3
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
GENERIC
PROPRIETARY
FM
CIBSE BIM GROUPS WORK ON DATA MANAGEMENT
PROJECT SPECIFIC PRODUCT DATA
VA’S DATA FOR A PUMP
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
CIBSE BIM GROUPS WORK ON DATA MANAGEMENT
GENERIC
PROPRIETARY
FM
PROJECT SPECIFIC PRODUCT DATA
VA’S DATA FOR A PUMP
MOST PROJECT DATA FIELDS (e.g. COBie) CAN BE POPULATED AUTOMATICALLY
IF PRODUCT INFORMATION MIRRORS THAT FORMAT
EXTENDING THE COBie
DATA FIELDS ENABLES:
Product search , comparison, shortlisting
& selection
Dynamic Modelling Cost and time analysis
CIBSE ‘PRODUCT DATA TEMPLATES’
(PDTs)–
BEING TRIALLED
PRODUCT DATA CAN BE SUPPLIED IN EXCEL (TO MATCH COBie)Simple for ‘BIM‐shy’
manufacturers to provide.
BIM‐platform ‘agnostic’.
APPROX 200 PDTS NEEDED (TO COVER >95% OF MEP EQUIPMENT )
& SERVES ALL PLAYERS – NOT JUST FM OPERATORS
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
CIBSE’S PRODUCT DATA TEMPLATE – PUMP EXAMPLE
Specifications Overall Width 325 mmSpecifications Overall Height 495 mmSpecifications Operating Weight 105.00 kg
Specifications Speed Type (fixed or variable) variableSpecifications Nominal Speed 2900 RPMSpecifications Minimal Speed 1450 RPMSpecifications Max Operating Pressure 15 barSpecifications Max Operating Temperature 121 degCSpecifications Max Inlet Pressure 12 kPaSpecifications Bearing Design Life L10 15 YearsSpecifications Efficiency Rating ME10 Text
Specifications Incoming Supply Electrical Voltage 415 VoltsSpecifications Incoming Supply Phase 3 NumberSpecifications Incoming Supply Electrical Frequency 50 HertzSpecifications Motor Enclosure Rating IP 56 TextSpecifications Motor kW TextSpecifications Full load current AmpsSpecifications Starting Current AmpsSpecifications Motor Type TEFC TextSpecifications Number of Poles 4 NumberSpecifications Motor Efficiency Class (CEMEP) IE3 TextSpecifications Starting Method DoL Text
Sustainable Material BREEAM etc Embodied Carbon kgCO2
Facilities/Asset Management Hourly TextFacilities/Asset Management Daily TextFacilities/Asset Management Weekly TextFacilities/Asset Management Monthly TextFacilities/Asset Management Quarterly TextFacilities/Asset Management 6 Monthly TextFacilities/Asset Management Annually TextFacilities/Asset Management Hours Run HoursFacilities/Asset Management Maintenance Required: 0-300hrs Nil TextFacilities/Asset Management Maintenance Required: 301-600hrs Nil TextFacilities/Asset Management Maintenance Required: 601-1000hrs Visual Check TextFacilities/Asset Management Maintenance Required: 1001-2000hrs Visual Check TextFacilities/Asset Management Maintenance Required: 2001-4000hrs Inspect TextFacilities/Asset Management Maintenance Required: 40001-8000hrs Lubricate Seals TextFacilities/Asset Management Maintance Required: 8001-12000hrs Replace Seals TextFacilities/Asset Management ExpectedLife 15 YearsFacilities/Asset Management WarrantyID 5 Text
Performance Data
Electrical Data
Sustainable Material, BREEAM, CSH etc
Maintenance Requirements
Template Category
Template Version
Category DescriptionL
Information Category Parameter Name Value Units
Specifications Manufacturer Armstrong TextSpecifications Internet Address URLSpecifications Product Model Name 4280 Starbloc TextSpecifications Product Model Number (Code) 50-150 TextSpecifications Special Features Text
Specifications Application LTHW TextSpecifications Pump Type Centrifugal TextSpecifications Configuration Close Coupled TextSpecifications Drive Type Direct TextSpecifications Casing Material Cast Iron TextSpecifications Impeller Material Bronze TextSpecifications Shaft Material Austentic S. Steel TextSpecifications Shaft Seal Type Silicon Carbide TextSpecifications Casing & Base Finish / Colour RAL 120 TextSpecifications Connection Type Flanged Text
Specifications Impeller Size (Ø) 114 - 157 mmSpecifications Number of Impellers 1 textSpecifications Suction Connection (Ø) 80 mmSpecifications Discharge Connection (Ø) 150 mmSpecifications Overall Length 520 mmSpecifications Overall Width 325 mmSpecifications Overall Height 495 mmSpecifications Operating Weight 105.00 kg
Specifications Speed Type (fixed or variable) variableSpecifications Nominal Speed 2900 RPMSpecifications Minimal Speed 1450 RPMSpecifications Max Operating Pressure 15 barSpecifications Max Operating Temperature 121 degCSpecifications Max Inlet Pressure 12 kPaSpecifications Bearing Design Life L10 15 YearsSpecifications Efficiency Rating ME10 Text
Specifications Incoming Supply Electrical Voltage 415 VoltsSpecifications Incoming Supply Phase 3 Number
Dimensional Data
Performance Data
Electrical Data
Pumps
Devices for moving fluid in a building services system.
1.0
Manufacturer Data
Construction Data
XYZ
123
Speed Type (fixed or variable) variableNominal Speed 2900 RPMMinimal Speed 1450 RPM
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
Suction Discharge80 150 114 125 135 145 157
2.2 3 4 5.5 7.5 11Impeller
Pt1 Pt2 Pt3 Pt4 Pt5 Pt6 Pt7Head 12.5 12.5 12.35 11.5 8.3 4.7Flow 0 7 11.11 16.7 20.8 24.7Eff % 40 54 66 66Power 2.2 2.4 2.8 3 2.8Head 16 16 15.9 15 13 8Flow 0 7 11.11 16.7 20.8 26Eff% 40 55 68 70 66Power 2.8 3.1 3.7 3.9 3.8Head 19.2 19.2 19.1 18.7 17.3 15.3 10.2Flow 0 7 11.11 16.7 20.8 24.7 30Eff% 40 56 69 75 74 64Power 3.4 3.7 4.3 4.7 5.1 5Head 23 23 23 22.4 21.5 18.5 13Flow 0 7 11.11 16.7 20.8 27.7 34Eff% 40 56 70 76 76 66Power 4 4.7 5.2 6 6.5 6.7Head 29.5 29.5 29.5 29 28 25.5 17Flow 0 7 11.11 16.7 20.8 27.7 39Eff% 40 56 70 80 84 68Power 4.75 5.6 6.5 8.5 9.25 10
Head 2 2.2 2.5 3 4.5 7.1Flow 3 11.11 16.6 22.22 27.7 33.34
NPSHr
Impeller
Motor Power
114
125
135
145
157
0
5
10
15
20
25
30
35
0 10 20 30 40 50
Head (m
)
Flow Rate (l/s)
Flow/Head Performance Curves @ 2900rpm
114
125
135
145
157
NPSHr
35
55
75
95
0 10 20 30 40 50
Efficiency %
Flow Rate (l/s)
Flow/Efficiency Performance Curves @ 2900rpm
114
125
135
145
157
0
2
4
6
8
10
12
0 10 20 30 40 50
Power (kW)
Flow Rate (l/s)
Flow/Power Performance Curves
114
125
135
145
157
QUESTION : Find a pump with duty =
22m head @ 16.5kg/s flow
ANSWER (1 of several): XYZ Product 123 :
145mm impeller @ 2900RPM 5.5kW motor @ 70% efficiency.
Book Cost: £650. Availability : 20 weeks
CIBSE BIM GROUPS WORK ON DATA MANAGEMENT – PUMP EXAMPLE
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
MEP BIM PROCESS ‘DISCONNECTS’
SUMMARISED Absence of product BIM data
• Designers data‐rich generic libraries (usually Revit)
• Contractors’
vast proprietary ‘object’
libraries (usually CAD
mep+); geometrically exact – but lacking data.
Split process does not embed data in As Fixed Model
Autodesk owns Revit
& CADmep+ ;
BIM Platform switch from design to installation stage
• Will both continue and enabled to ‘talk’
to each other?
• Manufacturers’
uncertainty
• Level 2 BIM aims confounded?
• Will one replace the other?
• Asset data can be embedded in model OR furnished direct .
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK
CIBSE PRODUCT DATA TEMPLATES
PRODUCT TYPE SPECIFIC (Approx 200 needed for >95% MEP coverage)
INTEGRATE WITH COBie
/ IFC DATA FIELDS AND CAN POPULATE THEM
OPEN STANDARD FOR PRODUCT DATA PRESENTATION
REQUIRE NO BIM COMPETENCE TO COMPLETE
REQUIRE MANUFACTURERS TO ADOPT STANDARD DATA FORMATS
PRODUCT DATA NEED ONLY TO BE PRESENTED ONCE TO BE USABLE BY ALL
Designers & modellers
Procurers, Installers & Contractors
BIM Vendors & content ‐builders
Clients & FM operators
CAN BE PROVIDED ON MANUFACTURERS’
WEBSITES OR IN HOSTED LIBRARIES
SOFTWARE PLATFORM INDEPENDENT
FENWICK ELLIOTT BIM CONFERENCE ‐MEP BIM IN UK