FENWICK ELLIOTT BIM CONFERENCE MEP BIM IN UK [email protected] MEP BUILDING INFORMATION MODELLING PADDY CONAGHAN Chair CIBSE BIM Group Consultant: Hoare Lea [email protected]

Upload: vankhanh

Post on 27-Jul-2018

220 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

MEP BUILDING INFORMATION  MODELLING

PADDY CONAGHAN

Chair CIBSE BIM GroupConsultant: Hoare Lea

[email protected]

Page 2: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

CIBSE BIM GROUP  

Formed Spring 2011  

70 members representing (non‐exhaustively):•Government’s BIM Task Group •Consultants •MEP contractors•Main contractors •Manufacturers & trade associations•FM operators•BIM & modelling software vendors •Freelance BIM object builders•Buildingsmart•Institutions: e.g., CIBSE, BSRIA•Etc;  

Founding aim : •to create a specification for MEP BIM content  creation•To advance BIM in UK MEP Practice   

Page 3: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

BIM – THE CIBSE BIM GROUP ‘MIND MAP’

(18 MONTHS AGO )

THIS IS THE ABRIDGED VERSION!

CROWDED  LANDSCAPE

MANY PLAYERS

Page 4: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

Q2: 11 Q3: 11 Q4: 11 Q1: 12 Q2: 12 Q3: 12 Q4: 12

BIM – THE CIBSE BIM GROUP’S PROGRESS  TO DATE 

Align‘Show & Tell’

Build MEP Library

WINS   BLOBS   

Data  

Formats

Draft & Promote Product Templates 

CIBSE BIM Portal  

Respond to ISO, BSI , Gov/Buildingsmart, etc; Collaborate ( BSRIA BG6, CIC, etc); Interface with Vendors & 

Industry players,  Links to other institutions, & to International MEP BIM; etc; 

Roll Out?

‘Buy In?’

Industry Surveys   

Page 5: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

BIM – THE CHALLENGES  FOR THE MEP INDUSTRY

Consultants + Contractors (<75% of 

Respondants)

60% 

Informed 

BIM DATA UNAVAILABLE ON 

>80% OF UK MEP PRODUCTS

Page 6: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

All services modelled in 3D

Conceptual modelling

Dynamic modelling / compliance

Fabrication & off site manufacture

Virtual construction Operational data

Space planning in 3D Design model linked to schedules & calcs

C D E F G H J K LA B M

MEP BIM COLLABORATION  ‐

THE ‘VISION’

Asset dataBRIEF

5D – Cost  

Info

4D – Time  

Info

6D – Asset  

Info

Page 7: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

All services modelled in 3D

Conceptual modelling

Dynamic modelling / compliance

Fabrication & off site manufacture

Virtual construction Operational data

Space planning in 3D Design model linked to schedules & calcs

C D E F G H J K LA B M

Asset dataBRIEF

5D – Cost  

Info

4D – Time  

Info

6D – Asset  

Info

MEP BIM COLLABORATION  ‐

IN  PRACTICE 

C D E F1A B G H JF2

‘Generic’

design to Stage F1 (e.g. 

Revit

MEP) 

Fabrication Information 

(usually in CADmep+)‘Hand‐cranked’

FM 

information

Page 8: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

All services modelled in 3D

Conceptual modelling

Dynamic modelling / compliance

Fabrication & off site manufacture

Virtual construction Operational data

Space planning in 3D Design model linked to schedules & calcs

C D E F G H J K LA B M

MEP BIM COLLABORATION  ‐

IN  PRACTICE 

Asset dataBRIEF

5D – Cost  

Info

4D – Time  

Info

6D – Asset  

Info

C D E F1A B G H JF2

Parallel Model

Parallel Model

Page 9: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

MEP BIM PROCESS ‘DISCONNECTS’

SUMMARISED    Absence of  product BIM data 

• Designers data‐rich generic libraries  (usually Revit)

• Contractors’

products libraries (usually CAD mep+); 

geometrically exact – but lacking data. 

Split process does not  embed data in As Fixed Model

Autodesk owns Revit

& CADmep+ ; 

BIM Platform switch from design to installation stage

• Will both be continued and enabled to ‘talk’

to each other?

DISCONNECTS ARISE MAINLY WITH DATA – NOT GEOMETRY 

SO CAN DATA BE HANDLED ANOTHER WAY? 

• Manufacturers’

uncertainty

• Level 2 BIM aims confounded?

• Will one replace the other?

Page 10: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

BIM DATA CONTENT – REQUIREMENTS (COBie

UK 2012)

CONSTRUCTION OPERATIONS BUILDING INFORMATION EXCHANGE 

COBie

LOOKS  COMPLEX & SCARY!

BUT ALL OF THE INFORMATION EXISTS SOMEWHERE

THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT      

Page 11: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

CIBSE BIM GROUPS WORK ON DATA MANAGEMENT USA VETERANS ASSOCIATION MASTER MATRIX 

FULL PROJECT LIFE CYCLE 

LEVEL OF DETAIL  (DATA

 DRO

P INFO

SPECIFICATION DATA 

TO BE PROVIDED AT 

LOD 3

Page 12: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

GENERIC 

PROPRIETARY 

FM  

CIBSE BIM GROUPS WORK ON DATA MANAGEMENT 

PROJECT SPECIFIC  PRODUCT DATA

VA’S DATA FOR A PUMP 

Page 13: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

CIBSE BIM GROUPS WORK ON DATA MANAGEMENT 

GENERIC 

PROPRIETARY 

FM  

PROJECT SPECIFIC  PRODUCT DATA

VA’S DATA FOR A PUMP 

MOST PROJECT DATA FIELDS  (e.g. COBie) CAN BE POPULATED AUTOMATICALLY   

IF PRODUCT  INFORMATION  MIRRORS THAT FORMAT

EXTENDING THE COBie

DATA FIELDS ENABLES:

Product search , comparison, shortlisting

& selection

Dynamic Modelling Cost and time analysis

CIBSE ‘PRODUCT DATA TEMPLATES’

(PDTs)–

BEING TRIALLED   

PRODUCT DATA CAN BE SUPPLIED IN EXCEL  (TO MATCH COBie)Simple for ‘BIM‐shy’

manufacturers to provide.

BIM‐platform ‘agnostic’.

APPROX 200 PDTS NEEDED (TO COVER >95% OF MEP EQUIPMENT )     

& SERVES ALL  PLAYERS – NOT JUST FM OPERATORS 

Page 14: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

CIBSE’S PRODUCT DATA TEMPLATE – PUMP EXAMPLE  

Specifications Overall Width 325 mmSpecifications Overall Height 495 mmSpecifications Operating Weight 105.00 kg

Specifications Speed Type (fixed or variable) variableSpecifications Nominal Speed 2900 RPMSpecifications Minimal Speed 1450 RPMSpecifications Max Operating Pressure 15 barSpecifications Max Operating Temperature 121 degCSpecifications Max Inlet Pressure 12 kPaSpecifications Bearing Design Life L10 15 YearsSpecifications Efficiency Rating ME10 Text

Specifications Incoming Supply Electrical Voltage 415 VoltsSpecifications Incoming Supply Phase 3 NumberSpecifications Incoming Supply Electrical Frequency 50 HertzSpecifications Motor Enclosure Rating IP 56 TextSpecifications Motor kW TextSpecifications Full load current AmpsSpecifications Starting Current AmpsSpecifications Motor Type TEFC TextSpecifications Number of Poles 4 NumberSpecifications Motor Efficiency Class (CEMEP) IE3 TextSpecifications Starting Method DoL Text

Sustainable Material BREEAM etc Embodied Carbon kgCO2

Facilities/Asset Management Hourly TextFacilities/Asset Management Daily TextFacilities/Asset Management Weekly TextFacilities/Asset Management Monthly TextFacilities/Asset Management Quarterly TextFacilities/Asset Management 6 Monthly TextFacilities/Asset Management Annually TextFacilities/Asset Management Hours Run HoursFacilities/Asset Management Maintenance Required: 0-300hrs Nil TextFacilities/Asset Management Maintenance Required: 301-600hrs Nil TextFacilities/Asset Management Maintenance Required: 601-1000hrs Visual Check TextFacilities/Asset Management Maintenance Required: 1001-2000hrs Visual Check TextFacilities/Asset Management Maintenance Required: 2001-4000hrs Inspect TextFacilities/Asset Management Maintenance Required: 40001-8000hrs Lubricate Seals TextFacilities/Asset Management Maintance Required: 8001-12000hrs Replace Seals TextFacilities/Asset Management ExpectedLife 15 YearsFacilities/Asset Management WarrantyID 5 Text

Performance Data

Electrical Data

Sustainable Material, BREEAM, CSH etc

Maintenance Requirements

Template Category

Template Version

Category DescriptionL

Information Category Parameter Name Value Units

Specifications Manufacturer Armstrong TextSpecifications Internet Address URLSpecifications Product Model Name 4280 Starbloc TextSpecifications Product Model Number (Code) 50-150 TextSpecifications Special Features Text

Specifications Application LTHW TextSpecifications Pump Type Centrifugal TextSpecifications Configuration Close Coupled TextSpecifications Drive Type Direct TextSpecifications Casing Material Cast Iron TextSpecifications Impeller Material Bronze TextSpecifications Shaft Material Austentic S. Steel TextSpecifications Shaft Seal Type Silicon Carbide TextSpecifications Casing & Base Finish / Colour RAL 120 TextSpecifications Connection Type Flanged Text

Specifications Impeller Size (Ø) 114 - 157 mmSpecifications Number of Impellers 1 textSpecifications Suction Connection (Ø) 80 mmSpecifications Discharge Connection (Ø) 150 mmSpecifications Overall Length 520 mmSpecifications Overall Width 325 mmSpecifications Overall Height 495 mmSpecifications Operating Weight 105.00 kg

Specifications Speed Type (fixed or variable) variableSpecifications Nominal Speed 2900 RPMSpecifications Minimal Speed 1450 RPMSpecifications Max Operating Pressure 15 barSpecifications Max Operating Temperature 121 degCSpecifications Max Inlet Pressure 12 kPaSpecifications Bearing Design Life L10 15 YearsSpecifications Efficiency Rating ME10 Text

Specifications Incoming Supply Electrical Voltage 415 VoltsSpecifications Incoming Supply Phase 3 Number

Dimensional Data

Performance Data

Electrical Data

Pumps

Devices for moving fluid in a building services system.

1.0

Manufacturer Data

Construction Data

XYZ

123

Speed Type (fixed or variable) variableNominal Speed 2900 RPMMinimal Speed 1450 RPM

Page 15: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

Suction Discharge80 150 114 125 135 145 157

2.2 3 4 5.5 7.5 11Impeller

Pt1 Pt2 Pt3 Pt4 Pt5 Pt6 Pt7Head 12.5 12.5 12.35 11.5 8.3 4.7Flow 0 7 11.11 16.7 20.8 24.7Eff % 40 54 66 66Power 2.2 2.4 2.8 3 2.8Head 16 16 15.9 15 13 8Flow 0 7 11.11 16.7 20.8 26Eff% 40 55 68 70 66Power 2.8 3.1 3.7 3.9 3.8Head 19.2 19.2 19.1 18.7 17.3 15.3 10.2Flow 0 7 11.11 16.7 20.8 24.7 30Eff% 40 56 69 75 74 64Power 3.4 3.7 4.3 4.7 5.1 5Head 23 23 23 22.4 21.5 18.5 13Flow 0 7 11.11 16.7 20.8 27.7 34Eff% 40 56 70 76 76 66Power 4 4.7 5.2 6 6.5 6.7Head 29.5 29.5 29.5 29 28 25.5 17Flow 0 7 11.11 16.7 20.8 27.7 39Eff% 40 56 70 80 84 68Power 4.75 5.6 6.5 8.5 9.25 10

Head 2 2.2 2.5 3 4.5 7.1Flow 3 11.11 16.6 22.22 27.7 33.34

NPSHr

Impeller

Motor Power

114

125

135

145

157

0

5

10

15

20

25

30

35

0 10 20 30 40 50

Head (m

)

Flow Rate (l/s)

Flow/Head Performance Curves @ 2900rpm

114

125

135

145

157

NPSHr

35

55

75

95

0 10 20 30 40 50

Efficiency %

Flow Rate (l/s)

Flow/Efficiency Performance Curves @ 2900rpm

114

125

135

145

157

0

2

4

6

8

10

12

0 10 20 30 40 50

Power (kW)

Flow Rate (l/s)

Flow/Power Performance Curves

114

125

135

145

157

QUESTION : Find a pump with duty = 

22m head @ 16.5kg/s flow

ANSWER (1 of several): XYZ Product 123 :

145mm impeller @ 2900RPM 5.5kW motor @ 70% efficiency. 

Book Cost: £650.  Availability : 20 weeks   

CIBSE BIM GROUPS WORK ON DATA MANAGEMENT – PUMP EXAMPLE  

Page 16: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

MEP BIM PROCESS ‘DISCONNECTS’

SUMMARISED    Absence of  product BIM data 

• Designers data‐rich generic libraries  (usually Revit)

• Contractors’

vast  proprietary ‘object’

libraries (usually CAD 

mep+); geometrically exact – but lacking data. 

Split process does not  embed data in As Fixed Model

Autodesk owns Revit

& CADmep+ ; 

BIM Platform switch from design to installation stage

• Will both continue and enabled to ‘talk’

to each other?

• Manufacturers’

uncertainty

• Level 2 BIM aims confounded?

• Will one replace the other?

• Asset data can be embedded in model OR furnished direct .  

Page 17: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK

[email protected]

CIBSE PRODUCT DATA TEMPLATES

PRODUCT TYPE SPECIFIC  (Approx 200 needed for >95% MEP coverage) 

INTEGRATE  WITH COBie

/ IFC  DATA FIELDS AND CAN POPULATE THEM 

OPEN STANDARD FOR PRODUCT DATA PRESENTATION

REQUIRE NO BIM  COMPETENCE TO COMPLETE

REQUIRE MANUFACTURERS TO  ADOPT STANDARD DATA FORMATS

PRODUCT DATA  NEED ONLY TO BE PRESENTED ONCE TO BE USABLE BY ALL 

Designers & modellers

Procurers, Installers & Contractors

BIM Vendors & content ‐builders 

Clients & FM operators  

CAN BE PROVIDED ON MANUFACTURERS’

WEBSITES  OR IN HOSTED LIBRARIES 

SOFTWARE PLATFORM INDEPENDENT 

Page 18: MEP BUILDING INFORMATION MODELLING - Fenwick … · MEP BUILDING INFORMATION MODELLING. ... THE COMPLEXITY LIES IN DATA COLLECTION AND MANAGEMENT. ... Devices for moving fluid in

FENWICK ELLIOTT BIM CONFERENCE  ‐MEP BIM IN UK